Microsoft Project 2010

Tracking Progress on Tasks and Assignments

Soe Naing WinEmail: [email protected]

Page 2: 12   tracking progress on tasks and assignments

Update a previously saved baseline plan. Record actual work for tasks and assignments. Record actual work by time period. Interrupt work on a task and specify the date

on which the task should start again

In this chapter, you will learn how to:

Page 3: 12   tracking progress on tasks and assignments

Recall that a baseline is a collection of important values in a project plan, such as the planned start dates, finish dates, and costs of tasks, resources, and assignments. When you save (or set) a baseline, Project takes a “snapshot” of the existing values and saves it in the Project plan for future comparison.

Updating a Baseline

Page 4: 12   tracking progress on tasks and assignments

To keep an accurate baseline for later comparison, you have several options: • Update the baseline for the entire project. This simply

replaces the original baseline values with the currently scheduled values.

• Update the baseline for selected tasks. This does not affect the baseline values for other tasks or resource baseline values in the project plan.

• Save a second or subsequent baseline. You can save up to 11 baselines in a single plan. The first one is called Baseline, and the rest are Baseline 1 through Baseline 10.

Updating a Baseline

Page 5: 12   tracking progress on tasks and assignments

Exercise : compare the project plan as it is currently scheduled with the baseline plan and update the baseline for the project plan. • View > Task Views > Gantt Chart > Tracking Gantt

Updating a Baseline

Page 6: 12   tracking progress on tasks and assignments

Task Name > task 18, Original art review > Scroll to Task

View > Zoom > Timescale > Weeks

Updating a Baseline

Page 7: 12   tracking progress on tasks and assignments

To conclude this exercise, you will resave the baseline for the project plan. Doing so will update all baseline information for tasks, resources, and assignments prior to tracking progress.• Project > Schedule > Set Baseline > Set Baseline

Updating a Baseline

Make sure that the Set Baseline option is selected. In the For area, make sure that the Entire project option is selected

Page 8: 12   tracking progress on tasks and assignments

• Click OK to update the baseline.

• Project alerts you that you are about to overwrite the previously saved baseline values.

• Click Yes.

Project updates the baseline values for the project plan.

Updating a Baseline

Page 9: 12   tracking progress on tasks and assignments

Exercise, you record task-level and assignment-level actuals and see how the information is rolled up or down between tasks and assignments.• Change to Task Usage.

• Task Name > task 18, Original art review > Scroll to Task.

• View tab > Data > Tables > Work.

Tracking Actual and Remaining Values for Tasks and Assignments

Page 10: 12   tracking progress on tasks and assignments

For example,

• The work, total for task 18, 160 hours = the sum of Hany Morcos’ 80 hours of work on the task and Jane Dow’s 80 hours.

Tracking Actual and Remaining Values for Tasks and Assignments

Page 11: 12   tracking progress on tasks and assignments

Next, you’ll change the details shown on the timephased grid on the right side of the view.

• Format > Details > Actual Work.

Tracking Actual and Remaining Values for Tasks and Assignments

Page 12: 12   tracking progress on tasks and assignments

Next, you’ll enter task-level and assignment-level actual work values and see how they are reflected in the timephased details.

• Using the mouse, drag the vertical divider bar to the right until you can see all the columns in the Work table

Tracking Actual and Remaining Values for Tasks and Assignments

Page 13: 12   tracking progress on tasks and assignments

In the Actual column for task 18, Original art review, type or click 90h, and then press the Enter key

Tracking Actual and Remaining Values for Tasks and Assignments

Page 14: 12   tracking progress on tasks and assignments

Several important things occurred when you pressed Enter:

Tracking Actual and Remaining Values for Tasks and Assignments

Page 15: 12   tracking progress on tasks and assignments

Several important things occurred when you pressed Enter: • Project applied change highlighting to the updated values in the table.

• The amount of actual work you entered was subtracted from the Remaining column.

• The actual work was distributed to the two assignments on the task, resulting in 44.5 hours of actual work being recorded for one resource and 45.5 hours for the other resource. (The difference in assignments is due to Hany’s previously customized assignment values.) Likewise, the updated remaining work value was recalculated for each assignment.

• The updated actual and remaining work values were rolled up to the Acquisition summary task.

• The actual work values were also redistributed to the task and assignment timephased values.

Tracking Actual and Remaining Values for Tasks and Assignments

Page 16: 12   tracking progress on tasks and assignments

To conclude this exercise, you will enter actual work values at the assignment level and see the effect on the task.• In the Actual column for Hany Morcos’s assignment to task 18, type or click

60h, and then press Enter.

Tracking Actual and Remaining Values for Tasks and Assignments

Page 17: 12   tracking progress on tasks and assignments

Drag the vertical divider bar back to the left to see more of the updated timephased values for the task.

Tracking Actual and Remaining Values for Tasks and Assignments

Page 18: 12   tracking progress on tasks and assignments

Exercise C: you enter some actuals for tasks for specific time periods.Click the minus sign next to task 15, Acquisition, to collapse this phase of the project plan.

• Task Name column > click the name of task 22, Organize manuscript for copyedit > Scroll to Task.

Project scrolls the timephased grid to display the first scheduled work values of the Editorial phase.

Tracking Timephased Actual Work for Tasks and Assignments

Page 19: 12   tracking progress on tasks and assignments

The first timephased actual work values that you will enter are at the task level and not for specific assignments.• In the timephased grid, click the cell at the intersection of the Wednesday,

May 23 column and the task 22 actual work row. The actual work row is directly below the work row, which contains the value 12h.

Tracking Timephased Actual Work for Tasks and Assignments

Page 20: 12   tracking progress on tasks and assignments

• Type 9h, and then press the Tab key.

Tracking Timephased Actual Work for Tasks and Assignments

Page 21: 12   tracking progress on tasks and assignments

• In the Thursday, May 24 actual work cell, type 15h, and then press Tab.

Tracking Timephased Actual Work for Tasks and Assignments

Page 22: 12   tracking progress on tasks and assignments

• For task 22, enter the following actual work values for the dates listed.

Date Actual Hours

Friday, May 25 12

Monday, May 28 12

Tuesday, May 29 15

Tracking Timephased Actual Work for Tasks and Assignments

Page 23: 12   tracking progress on tasks and assignments

For task 23, Copyedit, you have weekly actual work values from the assigned resource. The copyeditors have completed the task. For this task, you’ll adjust the timescale to record weekly actual values.• View tab > Zoom group > Timescale box > Weeks.

Enter the following actual work values into the timephased grid for the Copyeditors’ assignment to task 23, Copyedit

Date (Week of) Actual Hours

May 27 60

June 3 80

June 10 48

Tracking Timephased Actual Work for Tasks and Assignments

Page 24: 12   tracking progress on tasks and assignments

The resource’s actual work values were rolled up to the task’s actual work values. The original work values were saved in the baseline should you ever need to refer to them later.

Tracking Timephased Actual Work for Tasks and Assignments

Page 25: 12   tracking progress on tasks and assignments

Here is how Project handles tasks in relation to the rescheduled date: • If the task does not have any actual work recorded for it prior

to the rescheduled date and does not have a constraint applied, the entire task is rescheduled to begin after that date.

• If the task has some actual work recorded prior to but none after the rescheduled date, the task is split so that all remaining work starts after the rescheduled date. The actual work is not affected.

• If the task has some actual work recorded for it prior to as well as after the rescheduled date, the task is not affected

Rescheduling Incomplete Work

Page 26: 12   tracking progress on tasks and assignments

Exercise D: you reschedule uncompleted work• View tab > Gantt Chart. • In the Task Name column, click the name of task 31, Proofread

and index > Scroll to Task

Rescheduling Incomplete Work

Page 27: 12   tracking progress on tasks and assignments

You have learned that over the weekend of July 28, a water pipe burst in the proofreaders’ office. None of the project’s equipment or material was damaged, but the cleanup will delay work until Wednesday, August 1. This effectively stops work on the proofreading task for a few days. Next, you will reschedule incomplete work so that the project can begin again on Wednesday.

• Project > Status > Update Project.

Rescheduling Incomplete Work

Page 28: 12   tracking progress on tasks and assignments

• Select the Reschedule uncompleted work to start after option, and in the text box, type or select 7/31/12.

Rescheduling Incomplete Work

Page 29: 12   tracking progress on tasks and assignments

• Project splits task 31 so that the incomplete portion of the task is delayed until Wednesday

Rescheduling Incomplete Work