MONDAY 8 OCTOBER, 2007Project Management - Setting the Standard
Australian Institute of Project Management National Conference 2007Hobart Tasmania October 7 ² 10, 2007
CS1.4.3Implementation of a Project
Management System:
Practical Lessons from aSuccessful Implementation
Graham Watt
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 2/24
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 3/24
OPWS Management System
Implementing a PM tool in a PM organization
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 4/24
What we wanted « a new PM System
OPWS needed a basic, integrated, reliable & easy-to-use system that assists PM¶s to makekey decisions on core disciplines such as time, cost, quality, risk & scope
PMS SAP- ERP
Business PlanningManagement Reporting
DW / BI
Internal / Collaborative Project Teams
Internal / External Mgt.
Works Mgt.
Contracts Mgt.
Methodology Mgt.
Knowledge Mgt.
Finances
HR
Internal Network / Internet
Common User Interface / Portal
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 5/24
Key Benefits for OPWS
Provide users a single (one) integrated system while dealing withmultiple data sources and processes
Provides OPWS Project Manager¶s with streamlined data processing,
ie. information entered in one process step is simultaneously
available for other relevant processes
Facilitates the standardisation of project creation and other business
processes
Improved resource and project planning
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 6/24
Program Schematic
Sept Oct Dec
S T AKE H OL DE
R
Y -I N
d G OV E RNAN
E
INFORMATION MGT STRATEGY
ERP STRATEGY d OPERATIONS
I NT E GRAT I ON
d
ON S I T E N
Y
RE V I E W
BUSINESS
DELIVER Y
PLANS
R
ol l o u t P l
i
g
- Fi ¡
ci¡
l /¢
£ ¤ ¥
l£
- Oper ¡
ti¤ ¡
l
- Consoli¦
¡
tion
§ OMMERCE ERP BACKBONE
FINANCIAL
-F inance - AP / AR
-Contr olling - Budget
-Pr ocur ement - A sset ̈ anagement
Nov
HUMAN RESOURCES
-HR - Payr oll
-Time and Attendance
-ESS
SMARTBU Y
- e-Pr ocur ement
SERVICE DELIVER Y ± BUS INESS UNITS
PROGRAM OFFICE
-Pr oject Office - Gover nance - Change ©
gmt
- P r actices - Funding - Risk © anagement
- OF T - CFO- O IR - CS&R- NSWP - ODG- OPWS-
W ± HAB -
W ± t
t fl t -
W ± CC U
- ERP Str
t
gy - Vendor
upport
- Ope r
tiona l Gover nance - Solution Manager
- Di
aster Recovery
- Pr oduction Support
2005Sept Oct DecSept Oct Dec
S T AKE H OL DE
RB UY -I N an d G OV E RNAN
C E
INFORMATION MGT STRATEGY
ERP STRATEGY and OPERATIONS
I NT E GRAT I ON
an d C ON S I T E N C Y
RE V I E W
BUSINESS
DELIVER Y
PLANS
R
ol l o u t P l anni n g
- Financial / People
- Oper ational
- Consolidation
COMMERCE ERP BACKBONE
FINANCIAL
-F inance - AP / AR
-Contr olling - Budget
-Pr ocur ement - A sset anagement
Nov
HUMAN RESOURCES
-HR - Payr oll
-Time and Attendance
-ESS
SMARTBU Y
- e-Pr ocur ement
SERVICE DELIVER Y ± BUS INESS UNITS
PROGRAM OFFICE
-Pr oject Office - Gover nance - Change
gmt
- P r actices - Funding - Risk anagement
- OF T - CFO- O IR - CS&R- NSWP - ODG- OPWS-
!
W " ± HAB " -
!
W " ± " t #
t $ fl $ $ t -
!
W " ± CC " U
- ERP Str ategy - Vendor support
- Ope r ationa l Gover nance - Solution Manager
- Disaster Recovery
- Pr oduction Support
2005
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 7/24
Overall Program
Pr oject ID Pr oject Name Pr oject Sponsor
ERP00 ERP Pr ogr am Elizabeth Zealand
ERP01 ERP Program Office Esta % lishment Eliza % eth Zealand
ERP02 ERP Integration and Consistency Revie&
Eliza % eth Zealand
ERP03 ERP Change'
anagement Program Eliza% eth Zealand
ERP04 ERP Training Program Eliza % eth Zealand
ERP05 ERP Integration Stream - Reporting, Testing, ' igration, Cutover Eliza % eth Zealand
ERP10 Finalise HR / Payroll Implementation Eliza % eth Zealand
ERP21 ERP Strategy Eliza % eth Zealand
ERP22 Operational Gover nance'
odel Eliza% eth Zealand
ERP23 ERP Production Support Plan Geoff Tye
ERP24 ERP Service Provider Selection Geoff TyeERP25 ERP Disaster Recover y Plan Geoff Tye
ERP26 SAP Solution ' anager Geoff Tye
OPWS Pro ject ' anagement System - P ' , GAO, SPS, SWS
OPWS ' I ' S to SAP ' igration - P ' , GAO, SPS, SWS
ERP32 NSW Procurement ' I ' S to SAP ' igration Paul Hopkins
ERP34 OPWS ' I ' S to SAP ' igration - Statefleet ' ichael Wright
ERP Backbone: Eliza % eth Zealand
Alastair Hunter
ERP Back % one - Scoping
ERP Back % one - Workflo&
/ Delegations
ERP Back % one - Finance / Asset ' anagement
ERP Back % one - Procurement
smart % uy® Integration (ERP50)
ERP Back % one - HR, Payroll, ESS, ' SS
ERP Back % one -Timesheets / Fle(
time / La % our Costing
ERP Back % one Roll-out - OFT ' ichael Silk
ERP Back % one Roll-out - OIR Don Jones
ERP Back % one Roll-out - Cor porate Eliza % eth Zealand
ERP78 SAP Technical Architecture and Infrastr ucture Geoff Tye
ERP79 SAP Upgrade Eliza % eth Zealand
ERP75
ERP70
Alan ' arshERP31
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 8/24
Program Governance
Pro ject Steerin ) Committees
Director - 0 eneral
ERP Pro ) ram Steerin ) Committee
Members 1 unctions Elizabeth
2
ealand (chair) Program direction Alan Marsh, Brian Baker Integrated schedule Paul Hopkins Change management integration OFT / OIR Representatives Program decisions
Alastair Hunter Program risks and issues Geoff Tye Funding approvals Internal Auditor Elaine Silver (Program Director)
Pro ject Steerin 3 Committees Pro ject Steerin
4
Committees Members 5
unctions Project Sponsor Business fit Business Owner Business benefits realization Process Owners Change management Project Manager Project risks & issues
ERP Program Director Scope, budget, schedule (as delegated)
Pro ject Steerin 6 Committees
Director - 7 eneral
ERP Pro 6 ram Steerin 6 Committee
8 unctions Program direction Integrated schedule Change management integration Program decisions Program risks and issues Funding approvals
Commerce
IM&T Boar 9
Pro ject Steerin @ Committees Pro ject Steerin
A
Committees Members B
unctions Project Sponsor Business fit Business Owner Business benefits realization Process Owners Change management Project Manager Project risks & issues
ERP Program Director Scope, budget, schedule (as delegated)
Divisional
IM&T Committees
CC an D e Mana D ement E orum
ElizabethF
ealand (chair) Penny Hume
Brian Baker Chantelle Adams Michael Silk Don Jones Brian Koks Bill Vanooi Kathleen Kenna Kirsten Watson Wicky Wigneswaran Michael Doherty Genevieve Auld Elaine Silver
Pro ject Steerin G Committees
Director - H eneral
ERP Pro G ram Steerin G Committee
I unctions Program direction Integrated schedule Change management integration Program decisions Program risks and issues Funding approvals
Pro ject Steerin P Committees Pro ject Steerin
Q
Committees Members R
unctions Project Sponsor Business fit Business Owner Business benefits realization Process Owners Change management Project Manager Project risks & issues
ERP Program Director Scope, budget, schedule (as delegated)
Pro ject Steerin S Committees
Director - T eneral
ERP Pro S ram Steerin S Committee Members
U unctions ElizabethV
ealand (chair)
Gordon Hay Alan Marsh, Brian Baker Paul Hopkins, Chantelle Adams
Michael SilkDon Jones Alastair Hunter
Geoff TyeCharlie SherlockRichard Gibbs
JohnW
abou (ERP Manager)Greg Grebert (Secretariat)
Program direction Integrated schedule Change management integration Program decisions Program risks and issues Funding approvals
Commerce
IM&T Boar X
Pro ject Steerin Y Committees Pro ject Steerin
̀
Committees Members a
unctions Project Sponsor Business fit Business Owner Business benefits realization Process Owners Change management Project Manager Project risks & issues
ERP Program Director Scope, budget, schedule (as delegated)
Divisional
IM&T Committees
Cb an c e Mana c ement d orum
Elizabethe
ealand (chair) Penny Hume
Brian Baker Chantelle Adams Michael Silk Don Jones Brian Koks Bill Vanooi Kathleen Kenna Kirsten Watson Wicky Wigneswaran Michael DohertyGenevieve AuldGordon HayElaine Silver
ERP Cf an g eAh visor i
Boar h
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 9/24
Project Team
Business
Project
Manager
Vendor
Project
Manager
TrainingTeam p ead
Integration/
Test Manager
Functional /
Technical
Consu
ltants
Review
Business
Team
ERP ProjectManager
Business
Project
Manager
Vendor
Project
Manager/s
TechnicalTeam p ead
Integration/
Test Manager
Functional /
Technical
Consultants
Consultants
ProgramCoordinator
Business
Team
ChangeManager
Internal Auditor
BusinessProject
Manager
Business Test /Data Migration
p ead
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 10/24
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 11/24
Change Management Road Map
Pro ject activitq
Development
Deliver q
All projects/
Chg Mgt &
Training
Project
Mgrs
Project
Mgrs
All projects
B A¶s/ Functional
teams (Vendor &
Business)
Change Mgt
Change Mgt/
B A¶s
Change Mgt
Business Owner
Business & HR
Training
Training
Training &
Business (?)
Change Mgt
Change Mgt/ Chg
Network/Bus
Owners
Change Mgt/
Chg Network
Change Mgt &
Training
Change Mgt &
Training
Change Mgt,
Training & Chg
Network
B A¶s/ Functional
teams (Vendor &
Business)
Change Mgt
Change Mgt/
Chg Network/
Bus Owner
Bus Owner &
Chg Network
Business
Familiarity
&
Capability
DevProcess
Redesign
Communications
Org AlignmentStakeholder
Engagement
TrainingBusiness Impacts
Busine
ss
Readin
ess
Post
Go-
live
Suppo
rt
Benefi
ts
realisa
tion
Client Ref
Group
1
r
63
4
7
89 1
s
11
Business
Ownership
Change Program Monitoring
Continuous Feedback Readiness Survey #1 Readiness Survey #2 Deployment checklists
Change Mgt
2
Communication Activities
Process Awareness Breakpoint Sessions Day in thet
i fe of sessions Got
ive toolkit presentationProgram Awareness sessions
(J ob alignment Policy & Proc
Transition)
Deliverables
(C hg u
¶ment
C hg Network)
(H igh level & detailed
Impact u
ssessments)
(C omms Events,Process Wkshops,
Go-live toolkit)
(Bus Read Surveys,Deployment C hecklists)
Chg Mgt/
Business
Owner & Chg
Network
Bus Owners &
Chg Network
All proj/ Chg
Mgt &
Training
Client Ref
Group
Steering
Committee
Status Tracking
(C ommsstrategy,
integrated
plan & tools)
PIR Benefits Relµn
Monitoring
All
projects/Chg
Mgt &
Training
All
projects/Chg
Mgt &
Training
(Bus C aseProgram
Ex¶n Plan)
(Blueprint,Benefits
realisation)
( Training Strat, Training
Plan)
Support Plan
Change ManagementProgramERP Program
Ke
Change activity responsibilities
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 12/24
Provision of a copy of the training master for end users to practice post training.Training Delivery
Establishment of the training environment and the creation of data in the training clients to s upport hands-on practice using exercises.v ser Playpen Environment
Training in the Commerce Business Processes and training course delivery preparation for those identified to undertake training delivery external
to the core training team.
Training Database
All training course material including user acceptance test and participant guides, self paced learning tools and quick reference materials.Train the Trainer
Design documents that describe, for each course to be developed, the course str ucture, business processes supported, system transactions,
specific demonstrations, walkthroughs and exercises, including relevant timings.Training Materials
Design documents that describe, for each course to be developed, the course objectives, business processes supported, the intended audience,and delivery approach ± Instr uctor led, self -paced.
Course Outlines
Required number of courses scheduled (identified by audience analysis) by location.Training Course Schedule
Identification of the end user audience mapped to training course curriculum. Audience Analysis
Training course materials templates that demonstrate the look and feel of final course materials.Training Material Templates
Document that outlines the approach the Training Team will adopt to develop and deliver a quality training solution.End v ser Training and Documentation Strategy
DescriptionDeliverable
Training Deliverables
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 13/24
System andscapeERP, OMS, ERP Portal«how it all fits together«
Commerce ERP Portal
Business Warehouse Reports ± Commerce/OPWS Reports
cProjects
ERP
Human Resources, Finance, Materials Management, Project Systems
Employee
Self Service
Managers
Self Service
HR
Supplier
RelationshipManagement
(SRM)
Purchasing
Contracts
Projects, Knowledge, &Document Mgt
Pay details, leave,T&A, HDA, personnel
information
Managementreporting
Purchasing ±requisitioning and
approvalContract management
Access to thesystem for all staff
µBackend¶ accessto the system for
some Finance andHR staff
Knowledge Management
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 14/24
System Overview
Project Planning
Resourcing
Scheduling
Mast er at a
cProject s Gantt chart WBS Element s/ Cost Collect ors
MIMS
Sales rder
Project at es
Purchasing, Cont ract s
Project Plan
Roadmap
Regist ers(Risk, Scope
Change, Lesson Learned)
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 15/24
Lessons Learned
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 16/24
What we did well
Planning
Program/Project Governance
Roles and responsibilities
Delivered to time and budget
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 17/24
What we could have done better
Procurement Option
Better trained the business team
Co-located the business and vendor teams
Better planned for the ³post go-live´ period
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 18/24
ORIGINAL
REVISED
Requirements &Design
Build & Test
Change Management
Formal Training
Re-training & ser Assistance
Awareness &Business Process Review
Training
Change Management
Requirements &Design
Build & TestGo-Live
Change in Focus
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 19/24
Some Specific Lessons - Technical
nderstanding the hardware requirements.
Impacts on L AN WAN traffic of an ERP
nderstanding your software version.
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 20/24
Some Specific Lessons ± Project team
The importance of communication.
Provide a dedicated project team.
nderstand and resource for testing
Project Management processes.
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 21/24
Some Specific Lessons ± in the business
Provide adequate Change Management and Training
Plan for training well beyond Go-Live
nderstand the essential business practices in sufficient detail todetermine fit with software
Detailed assessment of the extent of development required
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 22/24
Questions
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 23/24
Question & Discussion Time
MONDAY 8 OCTOBER, 2007Project Management - Setting the Standard
Australian Institute of Project Management National Conference 2007
Hobart Tasmania October 7 ² 10, 2007
8/8/2019 1215 Graham Watt
http://slidepdf.com/reader/full/1215-graham-watt 24/24
LUNCHIn the Trade Exhibition Area
Please reconvene at 14:00for Concurrent Session 2
MONDAY 8 OCTOBER, 2007Project Management - Setting the Standard
Australian Institute of Project Management National Conference 2007
Hobart Tasmania October 7 ² 10, 2007