PRECONSTRUCTION PROCESS OVERVIEW OVER-ARCHING CONCEPT FOR EACH PHASE: Build Team. Build Trust. Define Conceptual Systems & Materials. Develop all Systems, Material Selections & Details. Transfer Final Design Information into Construction & Permitting Documents. Obtain & Assemble Construction Costs. Build It. Continue Preconstruction Team Approach. No Surprises. Be Responsive. PROJECT START SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS BIDDING & GMP PHASE CONSTRUCTION CLOSE-OUT BEGIN WARRANTY PERIOD KEY MILESTONES FOR EACH PHASE: Establish vision and Partnering Approach Confirm precon schedule and milestones with Ankrom Moisan & Oppenheimer Development Corp. Establish conceptual construction schedule Conduct kick-off meeting Understand Oppenheimer Development Corp.’s functioning program Prepare precon fee matrix Establish lines of communication Establish project scope budgets Define building systems / structure Begin conceptual constructability reviews Integrate code requirements Define special details QA/QC reviews Establish estimate formats Identify commissioning Requirements Identify long lead and timeline Identify decision process Develop buyout plan Develop initial LEED goals Develop building systems Update code requirements Bi-weekly design coordination meetings Develop details Define bid packages Balance cost variances with budget Cost estimating and clarifications Update precon & construction schedules Constructability review Final buyout plan Early Contractor Involvement charrettes Check final detailing with estimate intents and assumptions Final building systems coordination working sessions Document commissioning functions Quality control / constructability reviews Market project to subcontractor community Prepare GMP qualification and assessment for construction ECI market validation Quality Assurance Plan Bid alternate packaging Solicit bidders Manage bid process Update detailed construction schedule Conduct Andersen internal PMP meeting Oppenheimer Development Corp. satisfaction survey Andersen pre-bid meeting Subcontracts and Purchase Agreements Trade partner and AHJ construction kick-off meeting 6-week look ahead schedules Standing weekly OAC meetings Update master CPM/last planner schedule Weekly Andersen staff meetings Open communication Quality control inspections LEED documentation and tracking Close as we go Pre-punch list by Andersen Punch list process Test / commission System training O&M Manuals Record Drawings CHECKLISTS FOR EACH PHASE: Precon Fee Worksheet Precon File Sharing & Setup Project Directory Template Project Permit Coordination Checklist Precon Team Assignment - Roles & Responsibilities Sustainability Checklist Constructability Review Forms M/E/P Solicitation & Final Form Quality Control Checklist Project Hazards Checklist Continue Constructability Reviews Confirm Sustainability Checklist Special Product Requirement Checklist Bid Package Strategy Outline Water-tight Integrity Analysis Subcontractor Risk Mitigation Plan Flow Chart Constructability Reviews Project Management Plan Site Specific Safety Plan Project Commissioning Plan PMP Meeting GMP Clarifications & Qualifications Letter Owner/Contractor Agreement Bid Spread Analysis & Mitigation Job Costing OAC Meeting Template Staff Meeting Template 6-Week Look Ahead Schedule Template Assign Project Closeout Responsibilities Monthly Owner Progress reports Pre-Punch/Punch Checklist Final Billing Checklist Unconditional Lien Releases Lessons Learned / Opportunities For Improvement Report GROW TRUST $ CD COST ESTIMATE $ DD COST ESTIMATE $ SD COST ESTIMATE $ ESTABLISH GMP & PRESENT TO TALON/LUP Pathway to Certainty for 12th & Main — MANAGING FOR PREDICTABLE OUTCOMES —

Upload: jamal-nelson

Post on 09-Apr-2017

17 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: 12th and Main - Pathway to Certainty - draft

PRECONSTRUCTION PROCESS OVERVIEWOVER-ARCHING CONCEPT FOR EACH PHASE:

Build Team. Build Trust.

Define Conceptual Systems & Materials.

Develop all Systems, Material Selections

& Details.

Transfer Final Design Information into Construction &

Permitting Documents.

Obtain & Assemble Construction Costs.

Build It. Continue Preconstruction Team Approach.

No Surprises.

Be Responsive.

PROJECT START

SCHEMATIC DESIGN

DESIGN DEVELOPMENT

CONSTRUCTION DOCUMENTS

BIDDING & GMP PHASE CONSTRUCTION CLOSE-OUT

BEGIN WARRANTY PERIOD

KEY MILESTONES FOR EACH PHASE:

� Establish vision and Partnering Approach

� Confirm precon schedule and milestones with Ankrom Moisan & Oppenheimer Development Corp.

� Establish conceptual construction schedule

� Conduct kick-off meeting � Understand Oppenheimer

Development Corp.’s functioning program

� Prepare precon fee matrix � Establish lines of communication

� Establish project scope budgets � Define building systems /

structure � Begin conceptual

constructability reviews � Integrate code requirements � Define special details � QA/QC reviews � Establish estimate formats � Identify commissioning

Requirements � Identify long lead and timeline � Identify decision process � Develop buyout plan � Develop initial LEED goals

� Develop building systems � Update code requirements � Bi-weekly design coordination

meetings � Develop details � Define bid packages � Balance cost variances with

budget � Cost estimating and

clarifications � Update precon & construction

schedules � Constructability review � Final buyout plan � Early Contractor Involvement

charrettes

� Check final detailing with estimate intents and assumptions

� Final building systems coordination working sessions

� Document commissioning functions

� Quality control / constructability reviews

� Market project to subcontractor community

� Prepare GMP qualification and assessment for construction

� ECI market validation � Quality Assurance Plan

� Bid alternate packaging � Solicit bidders � Manage bid process � Update detailed construction

schedule � Conduct Andersen internal PMP

meeting � Oppenheimer Development

Corp. satisfaction survey � Andersen pre-bid meeting

� Subcontracts and Purchase Agreements

� Trade partner and AHJ construction kick-off meeting

� 6-week look ahead schedules � Standing weekly OAC meetings � Update master CPM/last

planner schedule � Weekly Andersen staff

meetings � Open communication � Quality control inspections � LEED documentation and

tracking

� Close as we go � Pre-punch list by Andersen � Punch list process � Test / commission � System training � O&M Manuals � Record Drawings

CHECKLISTS FOR EACH PHASE:

� Precon Fee Worksheet � Precon File Sharing & Setup � Project Directory Template � Project Permit Coordination

Checklist � Precon Team Assignment -

Roles & Responsibilities

� Sustainability Checklist � Constructability Review Forms � M/E/P Solicitation & Final Form � Quality Control Checklist � Project Hazards Checklist

� Continue Constructability Reviews

� Confirm Sustainability Checklist � Special Product Requirement

Checklist � Bid Package Strategy Outline � Water-tight Integrity Analysis

� Subcontractor Risk Mitigation Plan Flow Chart

� Constructability Reviews � Project Management Plan � Site Specific Safety Plan � Project Commissioning Plan

� PMP Meeting � GMP Clarifications &

Qualifications Letter � Owner/Contractor Agreement � Bid Spread Analysis & Mitigation

� Job Costing � OAC Meeting Template � Staff Meeting Template � 6-Week Look Ahead Schedule

Template � Assign Project Closeout

Responsibilities � Monthly Owner Progress reports

� Pre-Punch/Punch Checklist � Final Billing Checklist � Unconditional Lien Releases � Lessons Learned / Opportunities

For Improvement Report

GROW TRUST$ CD COST ESTIMATE$ DD COST ESTIMATE$ SD COST ESTIMATE $ ESTABLISH GMP & PRESENT TO TALON/LUP

Pathway to Certainty for 12th & Main— MANAGING FOR PREDICTABLE OUTCOMES —