This training was prepared by the U.S. Department of Agriculture (USDA) team of Otto Gonzalez-USDA Foreign Agricultural Service (Team Leader), Jon Fripp (Civil Engineer) and Chris Hoag (Wetland Plant Ecologist)-USDA Natural Resources Conservation Service (Civil Engineers). Fripp and Hoag were the primary authors of this material. The U.S. AID provided funding support for the USDA team.
8
Introduction to Check Dams
![Page 2: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/2.jpg)
Check Dams•Usually Used in Collection Zone•Can Also be used in Transport Zone
![Page 3: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/3.jpg)
These are structures
• Use caution
• Understand the processes at work in the system
• Know the components of a check dam
!
![Page 4: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/4.jpg)
What happens in if all the vegetation is removed from a watershed?
Understand the processes at work in the system
Answer:More erosion of surface
![Page 5: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/5.jpg)
So what happens if you have more water running down the watershed collection zone?
Answer: Erosion. Gullies will form and grow. The channel will get hungry and eat its boundary.
![Page 6: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/6.jpg)
The stream or gulley will start by attacking the bottom of the channel first.
![Page 7: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/7.jpg)
The channel will get deeper
Section
![Page 8: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/8.jpg)
![Page 9: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/9.jpg)
The channel will keep getting deeper until the sides start to fall in
Section
![Page 10: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/10.jpg)
Then it starts to get wider
Now it is really starting to get bad
![Page 11: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/11.jpg)
This is process is called the channel stages
Stage 1
Section
Stage 3
Stage 2
Assessment Tool: Channel StagesGood for collection and transport zone
![Page 12: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/12.jpg)
STAGE 1
Test Time
![Page 13: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/13.jpg)
Headcut
STAGE 2
Channel downcutting creates straighter, steeper gully.
![Page 14: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/14.jpg)
wideningSTAGE 3
Channel widening, cut banks on both sides.
![Page 15: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/15.jpg)
It is best to stop this process early in Stage 2
![Page 16: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/16.jpg)
To stop it: use a check dam
Profile
Stage 2
![Page 17: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/17.jpg)
Profile
A check dam will keep the channel from getting too deep
![Page 18: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/18.jpg)
Check DamsLots of different types
Lots of different materials
![Page 19: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/19.jpg)
A Check Dam must• Have a Control Section
• Have a Energy Dissipation Section
• Be Keyed into Channel Bottom
• Be Keyed into Channel Bank
• Be appropriately spaced
Components of a check dam
This introduction is going to cover the basicsYou may want to get more detailed training
![Page 20: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/20.jpg)
Control Section: Keeps the water in the channel
Bank Key: Keeps water from eroding around check dam
![Page 21: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/21.jpg)
•Control Section should have the same area as a stable section of the stream or gully.
![Page 22: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/22.jpg)
Energy dissipation section should be two times the structure height
Maximum height should be less than 1.5 m
H
2H
![Page 23: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/23.jpg)
Key into channel bottom for a minimum of 60 cm
Key into channel bank for a minimum of 1 m
Top of check dam should be at least 30 cm below top of channel
section
1 m
60 cm
![Page 24: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/24.jpg)
Energy Dissipation Section: Absorbs energy as water flows over top.
Key into Channel Bottom: Keeps water from eroding under check dam
May need a filter with log check dams
Profile
Same rules for all types of check dams
![Page 25: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/25.jpg)
Profile
The check dams work as a team
Downstream erosion might undermine the upstream check dam
![Page 26: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/26.jpg)
Space so that the slope can be level between the check dams and the upstream one will not be undermined.
Profile
![Page 27: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/27.jpg)
Test Time
Question: What is wrong with this check dam
Answer: bank key and adjacent protection
![Page 28: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/28.jpg)
Question: What is wrong with this check dam?
Answer: no control section. Made worse by bad bank key
![Page 29: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/29.jpg)
Question: What is wrong with this check dam?
Answer: bank key in
![Page 30: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/30.jpg)
Answer: everything, bad spacing, no control section, no bed or bank key in, no energy dissipation
Question: What is wrong with this check dam?
![Page 31: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/31.jpg)
Question: What is wrong with this check dam? Answer: nothing major
![Page 32: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/32.jpg)
Question: What is wrong with this check dam?
Answer: nothing major
![Page 33: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/33.jpg)
Question: What is wrong with these check dams?
Answer: nothing major
![Page 34: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/34.jpg)
You need an engineer to help with the design if:
• The river has high velocities
• The river is large
• The erosion is significant
• The river system is unstable
• There is something very important on the bank
• The project will cost a lot of money
• Laws state you must have an engineer
![Page 35: 13 Check Dams 2006](https://reader033.vdocument.in/reader033/viewer/2022042422/563db8bd550346aa9a968316/html5/thumbnails/35.jpg)
The End