13.6 APPENDIX F - CONSTRUCTION SPECIFICATION
Environmental Engineering Consultants
Waste Management Specialists Tel: 0402 373 582 www.bowmanassociates.com.au PO Box 2059, ROSSMOYNE WA 6148
CONSTRUCTION SPECIFICATION VANCOUVER WASTE DISPOSAL
FACILITY
This document describes the standards, materials and engineering requirements for earthworks, geosynthetic liner and the associated Quality Assurance requirements, for the Vancouver Waste Disposal Facility.
April 24, 2018
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 2
TABLE OF CONTENTS 1 Specification Preliminaries ................................................................................................. 9
1.1 Introduction .................................................................................................................. 9
1.2 Construction Specification ............................................................................................. 9
1.3 Supporting Documents .................................................................................................. 9
1.4 Background ................................................................................................................... 9
1.4.1 Principal ............................................................................................................................................ 9
1.4.2 Landfill Users ..................................................................................................................................... 9
1.4.3 Superintendent ................................................................................................................................. 9
1.4.4 Designer .......................................................................................................................................... 10
1.4.5 Regulator ........................................................................................................................................ 10
1.4.6 Quality Assurance Engineer ............................................................................................................ 10
1.5 Definitions .................................................................................................................. 10
1.6 Site Location ............................................................................................................... 11
1.7 Site Access .................................................................................................................. 11
1.8 Works Area ................................................................................................................. 12
1.9 Current DWER Licence ................................................................................................. 12
1.10 Description of Works ................................................................................................... 12
1.11 Scope of Works ........................................................................................................... 12
1.12 Working Hours ............................................................................................................ 13
1.13 Contract Management ................................................................................................ 13
1.13.1 Project Scheduling ...................................................................................................................... 13
1.13.2 Progress Meetings ...................................................................................................................... 14
1.13.3 Progress Reporting ..................................................................................................................... 14
1.14 Hold Points ................................................................................................................. 14
1.15 Setting Out and Survey Control .................................................................................... 15
1.16 Errors in Setting Out .................................................................................................... 16
1.17 Site Survey, Area and Volume Calculations .................................................................. 16
1.18 As Constructed Drawings ............................................................................................. 17
1.19 Construction Quality Assurance Documentation .......................................................... 17
1.20 Environmental Performance ........................................................................................ 17
1.20.1 Equipment .................................................................................................................................. 17
1.20.2 Contamination of Site ................................................................................................................. 17
1.20.3 Stormwater Management and Water Discharge ....................................................................... 18
1.20.4 Fire Prevention ........................................................................................................................... 18
1.21 Environmental Obligations .......................................................................................... 18
1.21.1 Dust Control ............................................................................................................................... 18
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 3
1.21.2 Noise ........................................................................................................................................... 18
1.21.3 Licence Amendment Compliance ............................................................................................... 18
1.21.4 Soil Erosion ................................................................................................................................. 19
1.21.5 Dust, Dirt, Water and Fumes ...................................................................................................... 19
1.21.6 Waste Disposal ........................................................................................................................... 19
1.22 Shut Down Periods ...................................................................................................... 19
1.23 Project Supervision ..................................................................................................... 19
1.23.1 Project Supervisor ...................................................................................................................... 19
1.23.2 Communication .......................................................................................................................... 19
1.24 Wet Weather .............................................................................................................. 19
1.25 Occupational Health and Safety ................................................................................... 19
2 Site Services and Amenities .............................................................................................. 21
2.1 Contractors Site Office ................................................................................................. 21
2.2 Construction Water ..................................................................................................... 21
2.3 Power ......................................................................................................................... 21
2.4 Ablution Facilities ........................................................................................................ 21
2.5 Underground Services ................................................................................................. 21
2.6 Traffic Management .................................................................................................... 21
2.7 Plant Lay Down and Storage Area ................................................................................ 21
2.8 Standards .................................................................................................................... 22
3 Earthworks ........................................................................................................................ 25
3.1 General Requirements ................................................................................................. 25
3.2 Batter Construction ..................................................................................................... 25
3.3 Site Preparation .......................................................................................................... 25
3.3.1 Clearing ........................................................................................................................................... 25
3.3.2 Grubbing ......................................................................................................................................... 26
3.3.3 Spoil ................................................................................................................................................ 26
3.3.4 Material Stockpile Area .................................................................................................................. 26
3.4 Excavation .................................................................................................................. 26
3.4.1 Hard Rock ........................................................................................................................................ 26
3.4.2 Soft Ground ..................................................................................................................................... 27
3.4.3 Underground Springs and Seepage ................................................................................................ 27
3.5 Groundwater Management ......................................................................................... 27
3.6 Filling and Subgrade .................................................................................................... 27
3.6.1 Fill Placement .................................................................................................................................. 27
3.6.2 Landfill Access Road Preparation .................................................................................................... 28
3.6.3 Removal of Non-Conforming Materials .......................................................................................... 29
3.7 Frequency of Compliance Testing ................................................................................. 29
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 4
3.8 Proof Rolling ............................................................................................................... 30
3.9 Survey Verification ...................................................................................................... 30
4 Composite Lining System .................................................................................................. 31
4.1 Liner Construction Overview........................................................................................ 31
4.2 Confirmation of Materials Order .................................................................................. 31
4.3 Liner Quality Assurance Documentation ...................................................................... 31
4.4 Waste From Construction ............................................................................................ 32
5 Clay Liner .......................................................................................................................... 33
5.1 Clay Liner Characteristics ............................................................................................. 33
5.2 Verification of Clay Liner.............................................................................................. 33
6 High Density Polyethylene (HDPE) Geomembrane .......................................................... 34
6.1 Labelling ..................................................................................................................... 34
6.2 HDPE Material Properties ............................................................................................ 34
6.3 Quality Assurance ....................................................................................................... 35
6.4 Supply and Handling .................................................................................................... 35
6.5 Installation .................................................................................................................. 35
6.5.1 Planning .......................................................................................................................................... 35
6.5.2 Placement ....................................................................................................................................... 35
6.6 Welding Methods ........................................................................................................ 36
6.7 Seam Preparation........................................................................................................ 37
6.8 Welding of Geomembrane ........................................................................................... 37
6.8.1 Hot-wedge (Fusion) Welder ............................................................................................................ 37
6.8.2 Extrusion Welder ............................................................................................................................ 37
6.8.3 Fusion Welds ................................................................................................................................... 37
6.8.4 Extrusion Welds .............................................................................................................................. 37
6.9 Weld Testing ............................................................................................................... 37
6.9.1 Destructive Testing and Trial Welds ............................................................................................... 38
6.9.2 Production Seams ........................................................................................................................... 39
6.10 Non-destructive Testing .............................................................................................. 40
6.10.1 Patching and Extrusion Repairs .................................................................................................. 40
6.10.2 Reporting .................................................................................................................................... 40
6.11 Warranty .................................................................................................................... 41
7 Geotextile Cushion Layer .................................................................................................. 42
7.1 Labelling ..................................................................................................................... 42
7.2 Material Specification ................................................................................................. 42
7.3 Quality Assurance ....................................................................................................... 43
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 5
7.4 Storage and Handling .................................................................................................. 43
7.5 Installation .................................................................................................................. 43
7.6 Repair ......................................................................................................................... 44
8 Leachate Collection System .............................................................................................. 45
8.1 Leachate Collection Pipes ............................................................................................ 45
8.1.1 Installation ...................................................................................................................................... 45
8.1.2 Pipe Survey ..................................................................................................................................... 46
8.2 Leachate Sump ............................................................................................................ 46
8.3 Anchor Block ............................................................................................................... 46
8.4 Drainage Aggregate ..................................................................................................... 46
8.4.1 Aggregate Specification .................................................................................................................. 46
8.4.2 Quality Assurance ........................................................................................................................... 46
8.4.3 Placement and Compaction Methodology ..................................................................................... 46
9 Separation Geotextile ....................................................................................................... 48
9.1 Material Specification ................................................................................................. 48
9.2 Quality Assurance ....................................................................................................... 48
9.3 Storage and Handling .................................................................................................. 48
10 Access Road .................................................................................................................. 50
10.1 Subgrade Placement .................................................................................................... 50
10.2 Basecourse Material .................................................................................................... 50
10.3 Compaction Quality Assurance .................................................................................... 52
11 Fencing and Gates ......................................................................................................... 53
12 Construction Drawings .................................................................................................. 54
13 Designers Risk Assessment ........................................................................................... 55
14 Construction Quality Assurance Plan ............................................................................ 65
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 6
LIST OF TABLES
Table 1: Table of Standards................................................................................................................... 22
Table 2: Fill and Subgrade Compliance Testing Acceptance Criteria .................................................... 28
Table 3: Required Frequency of Field Density Testing .......................................................................... 29
Table 4: Fill and Subgrade Compliance Testing Acceptance Criteria .................................................... 33
Table 5: Selected Key Parameters for HDPE Geomembrane Liner - Manufacturer ............................. 34
Table 6: Minimum Test Values for a HDPE Weld Sample ..................................................................... 39
Table 7: Geotextile Cushion Layer Properties ....................................................................................... 42
Table 8: Drainage Aggregate Specification ........................................................................................... 46
Table 9: Separation Geotextile Properties ............................................................................................ 48
Table 10: Access Road Subgrade Compliance Testing Acceptance Criteria .......................................... 50
Table 14: Table of Construction Drawings for Cell 1, Cell 2 and Leachate Pond .................................. 54
Table 15: Qualitative Measures of Likelihood ...................................................................................... 55
Table 16: Qualitative Measures of Consequence/Impact .................................................................... 55
Table 17: Qualitative risk analysis matrix – Level of risk ...................................................................... 56
Table 18: Risk Assessment - Construction Activities ............................................................................. 57
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 7
ACRONYMS
AHD Australian Height Datum
AS Australian Standard
ASTM ASTM International (Formerly the American Society for Testing and Materials)
CBR Californian Bearing Ratio
DFES Department of Fire and Emergency Services
DWER Department of Water and Environmental Regulation
GRI Geosynthetic Research Institute
HDPE High Density Polyethylene
ISO International Organisation for Standardisation
NATA National Association of Testing Authorities
PE Polyethylene
UV Ultraviolet
WA Western Australia
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 8
UNITS OF MEASUREMENT
% Percent
cm3/2g Cubic Centimetre per Two Grams
oC Degrees Celsius
g/cc Grams per cubic centimetre
g/m2 Grams per Square Metre
kg Kilogram
kPa Kilopascal
km Kilometre
kN/m Kilonewtons per metre
m Metre
mm Millimetre
m2 Square Metre
m3 Cubic Metre
m/s Metres per Second
MPa Megapascal
Microns Micron (µm) = 1 x 10-6 metres
N Newton
N/m Newtons per Metre
psi Pounds per Square Inch
t tonne
wt% percentage by weight
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 9
1 SPECIFICATION PRELIMINARIES
1.1 INTRODUCTION
Vancouver Waste Services Pty Ltd is proposing to develop a putrescible landfill at Lot 102 Mindijup
Road, Palmdale in the City of Albany, the facility shall be known as the Vancouver Waste Disposal
Facility.
The location for the Vancouver Waste Disposal Facility, approximately 52 km north of Albany, is
already licenced by the DWER, Licence L7344/1998/10. The Licence includes Categories 63 – Inert
landfill and 67A – Compost Manufacturing Facility. Category 63 allows the disposal of clean fill and
tyres up to 500 tpa. Category 67A licences the site to compost up to 12,000 tpa of greenwaste,
forestry residue, straw and biosolids.
1.2 CONSTRUCTION SPECIFICATION
This document provides the Technical Specifications and the standard of construction to be followed
for the construction activities associated with Cell 1, Cell 2 and the leachate pond.
1.3 SUPPORTING DOCUMENTS
This Specification is intended to be read in conjunction with the following documents. Should any of
the listed information sources be in contradiction, the document listed first shall take precedence.
For technical queries, clarification may be sought from the Superintendent or the Designers
Representative.
Construction Specification (this document);
Construction Drawings;
CQA Plan;
Bill of Quantities; and
Landfill Licence Amendment.
1.4 BACKGROUND
1.4.1 PRINCIPAL
Vancouver Waste Services Pty Ltd, (ABN 16 135 344 357), is a private company owned by Martin
James Shuttleworth, and provides waste collection services within the region, disposal of tyres and
inert fill and operates a composting facility.
1.4.2 LANDFILL USERS
The Vancouver Waste Disposal Facility accepts waste from City of Albany and commercial waste
from the Principal’s waste transfer station in Albany.
1.4.3 SUPERINTENDENT
The Superintendent will act on behalf of the Principal to provide project management, monitoring,
inspections and quality assessment of the Works. The Superintendent will be responsible for
representing the Principal’s interest during the execution of the Works by the selected Contractor.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 10
1.4.4 DESIGNER
The landfill has been designed and specified by Bowman & Associates Pty Ltd. Any technical queries
regarding the Works shall be referred to the Superintendent or person otherwise nominated by the
Principal.
A designer’s risk assessment is provided in Section 13. The risk assessment relates to specific safety
and performance engineering design features considered during the design phase.
1.4.5 REGULATOR
The Department of Water and Environmental Regulation (DWER) will act on the proposal under Part
V of the EP Act and will assess the environmental risk of the development of Cell 1 and Cell 2 at the
Vancouver Waste Disposal Facility. Under the direction of the Principal the Contractor shall carry out
the landfill construction in compliance with the terms and conditions of the amended Licence issued
by the DWER. A copy of the licence can be provided to the Contractor upon request.
1.4.6 QUALITY ASSURANCE ENGINEER
A suitable Quality Assurance Engineer will be engaged by the Principal for the duration of the High
Density Polyethylene (HDPE) Geomembrane liner and Cushion Geotextile installation activities. The
Quality Assurance Engineer may also be the Superintendent. The Quality Assurance Engineer will be
responsible for verifying that the earthworks and geosynthetic liner placement occurs in accordance
with this specification.
All installation and Quality Assurance activities will be performed to the satisfaction of the Quality
Assurance Engineer and the Superintendent.
The Quality Assurance Engineer will independently review all manufacturers and as constructed
quality assurance documentation supplied by the Contractor to ensure the earthworks and lining
system meet the project document requirements.
1.5 DEFINITIONS
The following terminology shall apply in this Contract Specification:
Construction Drawings Series of drawings setting out the lines and dimensions of the
construction works.
Construction Specification Description of the requirements of the construction works. This
Document.
Contract Legally binding agreement between the Principal and the Contractor
for the provision of the Works.
Contractor Organisation or individual commissioned by the Principal to undertake
the construction works subject to this specification and associated
contract conditions as provided by the Principal.
Designer Bowman & Associates Pty Ltd.
Landfill Footprint The area within the site used for waste placement.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 11
Licence Amendment Conditions and approval issued by the Department of Water and
Environmental Regulation authorising the Principal to proceed with
the Works.
Lining Supervisor Contractor who is experienced in the installation of geosynthetic liners
nominated by the Contractor to install the geosynthetic liners.
Principal Vancouver Waste Services Pty Ltd.
Program of Works The schedule of tasks, milestones, dependencies and resource
allocations developed by the Contractor.
Practical Completion Completion of Works to the satisfaction of the Superintendent.
Project Manager Representative of the Contractor to manage the Contract.
Project Supervisor Person nominated by the Contractor to be onsite fulltime to manage
the Works.
Regulator Department of Water and Environmental Regulation (DWER).
Quality Assurance
Engineer
A suitable and experienced engineer or representative supplied by the
Principal who will observe and report on all lining operations.
Schedule of Rates Prices provided by the Contractor for quantities required for the
Works.
Site Vancouver Waste Disposal Facility, Lot 102 on Plan 22860 located off
Mindijup Road, Palmdale in the City of Albany.
Site Supervisor Representative of the Principal for the operation of the Vancouver
Waste Disposal Facility.
Superintendent The representative appointed by the Principal to manage the project.
Tenderer An individual or organisation that has or intends to submit an Offer to
for the Works.
Works All activities undertaken by the Contractor for the construction of
the landfill.
1.6 SITE LOCATION
The Vancouver Waste Disposal Facility is located approximately 52 km north east of Albany on Lot
102 on Plan 22860 located off Mindijup Road, Palmdale in the City of Albany (Drawing AL-WA-001).
Lot 102 covers an area totalling 584 hectares (ha) and has facilities for various types of waste
disposal. The site is owned by Martin James Shuttleworth.
1.7 SITE ACCESS
The main access to the site is from Lot 3 Mindijup Road, Palmdale. The Landfill is situated on Lot 102
located behind Lot 3.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 12
1.8 WORKS AREA
The area available for the construction of the landfill and the leachate pond is the parcel of land east
of the current site activities. The area is bordered on all sides by blue gum plantations and natural
bush. The footprint of the landfill is shown on Drawing AL-WA-002.
1.9 CURRENT DWER LICENCE
The Mindijup Rd Tyre Disposal Site operating Licence L7344/1998/10 was first issued in 1998.
The Licence has the following Categories:
Category 63: Inert landfill Class I accepting up to 500 tpa of used tyres; and
Category 67A: Compost manufacturing and soil blending with a licenced capacity of 12,000
tpa.
1.10 DESCRIPTION OF WORKS
The Contract includes, but is not limited to, all equipment, labour, operations, management,
supervision, quality control and all other works required for the completion of the construction of
Cell 1, Cell 2 and the leachate pond at the Vancouver Waste Disposal Facility as described in this
Specification and in accordance with the Drawings provided. Cell 2 will not form part of the initial
Works, Cell 2 will be constructed once Cell 1 is partially filled with waste.
Any additional Works or variations from the Specification ordered by the Superintendent are to be
included as part of the Contract and will be subject to additional payment. All variations shall be
approved by the Superintendent and Principal prior to any Works being completed.
1.11 SCOPE OF WORKS
The Cell 1, Cell 2 and leachate pond base and side liner system will consist of the following elements
(from bottom to top):
Compacted, shaped and rolled subgrade consisting of insitu clay, the insitu clay will form the
secondary layer of the composite liner. The insitu clay will have a hydraulic conductivity of
less than 1 × 10-9 m/s and will help in limiting contaminant migration, water seepage and
landfill gas migration;
A 2.0 mm thick High Density Polyethylene (HDPE) geomembrane liner will be placed directly
above the insitu clay and will serve as the primary layer to limit contaminant migration and
to control landfill gas migration;
A non-woven geotextile cushion layer will be placed on top of the HDPE liner to serve as a
protective layer, minimising the risk of damage or puncture during installation of the
protection layer and operation of the landfill;
A 300 mm thick drainage layer of single sized crushed aggregate will be placed on top of the
cushion geotextile to serve as a leachate collection layer; and
Over the drainage layer will be a non-woven geotextile which will act as a separation
medium between the drainage aggregate and the waste.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 13
The scope of works for the construction of Cell 1, Cell 2 and leachate pond, this Specification and the
Drawings includes the following:
Survey and setting out for the construction area;
Mobilisation and demobilisation of plant and equipment;
Payment of Building and Construction Industry Training Fund Levy;
Supply of equipment, construction materials, labour and supervision;
Quality control and assurance;
Excavation as per the Drawings;
Construction of the perimeter bunds as per the Drawings;
Trimming and shaping of the Cell 1, Cell 2 and leachate pond subgrade as shown on the
Drawings;
Excavation of the perimeter anchor trench;
Preparation of the clay subgrade and conformance testing;
Installation of the ; HDPE Geomembrane and Cushion Geotextile as described in the
Specification and on the Drawings;
Backfilling of the perimeter anchor trench after liner installation;
Construction of the leachate collection system on the base of Cell 1 and Cell 2;
Construction of the concrete anchor block to support the leachate extraction pipes;
Construction of landfill access road;
Construction of stormwater channels; and
Installation of security fences and gates for landfill and leachate pond.
1.12 WORKING HOURS
The normal working hours and working days shall be no earlier than 6:00 am and no later than 5.00
pm Monday to Saturday, excluding public holidays. Work outside of these hours will be subject to
approval by the Principal. The Contractor shall be liable for any additional cost or any claims incurred
by the Principal as a result of working outside normal hours.
1.13 CONTRACT MANAGEMENT
1.13.1 PROJECT SCHEDULING
The Contractor shall submit a detailed program of works (in MS Project format or similar) based on
the outlined scope of works and Hold Points within two (2) weeks from the date of acceptance of the
tender or at least seven (7) days prior to the works commencing.
The program of works shall include a list of Subcontractors, resource allocation and time frames for
each task and Hold Points. This will be subjected to review by the Superintendent during progress
meetings and will be updated on a fortnightly basis showing the percentage of work completed to
form the approved project schedule and release of Hold Points.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 14
The Contractor shall provide the revised program of works to the Superintendent no less than two
(2) working days prior to each scheduled progress meeting.
1.13.2 PROGRESS MEETINGS
Progress meetings maybe held on site or at other agreed locations throughout the period of the
Works on a weekly basis or more frequent if required. The meetings will be attended by the
Contractor, Site Supervisor, Principal and the Superintendent.
1.13.3 PROGRESS REPORTING
The Contractor shall prepare and submit progress reports to the Superintendent based on the
previous progress meetings. The format of these reports shall be to the satisfaction of the
Superintendent and will include the following as a minimum:
Progress in Works, percentage of tasks completed, achievement of milestones;
Delay in achieving expected completion of tasks and valid comments stating the reason;
Updated and approved project schedule as per the previous project meeting;
Updated list of tasks and actions considered from the outcome of the previous meeting and
the anticipated dates of completion;
List of upcoming milestone events and the tasks required to complete them;
Completed Hold Points;
Details of work completed for invoicing; and
Updated proposed Practical Completion date.
1.14 HOLD POINTS
The following hold points are minimum requirements only, and additional inspections during the
construction phase may be required at the Superintendent’s discretion.
Hold points include but are not limited to the following:
Initial survey and setout of the Works;
Receipt and approval of construction Inspection and Test Plans (ITPs);
Receipt and approval of the Contractors work program, noise and dust plans, health and
safety plans and insurances (including sub-contractors);
When soft ground is encountered;
When hard ground is encountered;
Following preparation and proof rolling of all subgrade earthworks the Superintendent shall
inspect the finished surface for compliance with the requirements of the Specification;
Proof rolling of the subgrade surface for the access road;
Placement and as constructed survey of the basecourse layer for the access road;
As constructed survey of the prepared earthworks subgrade in the landfill cells and leachate
pond and the internal shoulder of the excavated anchor trench;
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 15
Prior to any concrete pours;
At hold points to be nominated by the Superintendent based on the Contractor’s proposed
construction plan for the installation of the HDPE geomembrane liner and cushion
geotextile;
Anchor trench excavation prior to HDPE deployment;
Prior to covering the HDPE geomembrane with the cushion geotextile, the Superintendent
shall inspect the geomembrane surface and cross reference the installers Quality
Assurance/Quality Control documentation that seams, panels, defects and repairs have been
accurately recorded and QA destructive and non-destructive testing has been completed;
and
All other hold points defined in the Specification or as directed by the Superintendent.
The Contractor is to provide the Superintendent with 48 hours written notice of an impending hold
point. If a Contractor proceeds to construct beyond the designated hold point without the
Superintendents inspection and/or without the Superintendents approval then the Superintendent
may direct the Contractor to uncover and remediate the Works to the hold point, at the Contractor’s
expense.
The Contractor shall be deemed to have allowed for all time delays and costs associated with the
hold points during the works.
1.15 SETTING OUT AND SURVEY CONTROL
The Contractor shall nominate its proposed surveying company or licensed surveyor within the
Tender Submission.
The Contractor shall be responsible for setting out the Works and for ongoing survey control,
including alignment of surface drains and construction of the liners to the grades, levels and
locations shown on the Drawings.
The term "survey mark" used in this clause means a survey peg, bench mark, reference mark, signal,
alignment, level mark or any other mark used or intended to be used for the purpose of setting out,
checking or measuring the work under the Contract.
Unless otherwise required by the Contract, the Contractor shall preserve and maintain in their true
positions the survey marks provided by the Principal or by the Superintendent in accordance with
the Contract.
Should any survey mark be disturbed or obliterated, the Contractor shall immediately notify the
Superintendent and shall, unless the Superintendent otherwise determines, rectify such disturbance
or obliteration to the satisfaction of the Superintendent. Unless the disturbance or obliteration has
been caused by the Principal, his employees or agents, the cost of rectification shall be borne by the
Contractor.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 16
1.16 ERRORS IN SETTING OUT
If at any time during the progress of the Works, any error is discovered in the position, level,
dimensions or alignment of any part of the works, the Contractor shall immediately notify the
Superintendent. The Contractor shall, unless the Superintendent otherwise directs, rectify the error.
Unless the error has been caused by incorrect data issued by the Principal, the cost of rectification
shall be borne by the Contractor.
The Superintendent may check the setting out of the work under the Contract by the Contractor but
the fact that the Superintendent may have carried out such checks shall not relieve the Contractor of
any responsibility for the correct setting out of the work.
1.17 SITE SURVEY, AREA AND VOLUME CALCULATIONS
The Contractor shall engage a licensed or qualified surveyor to carry out survey control during the
execution of the Works.
Site survey shall be conducted on a maximum 20 m grid over the cell area, at suitable points to
define earthworks volumes and areas including slopes to determine the location and levels of all
drainage infrastructures.
The survey shall also include:
Surface at time of setout;
Top of the prepared subgrade layer including drainage grades;
Top of compacted basecourse layer for the access road;
Survey of all test locations for the geotechnical quality control testing program;
Survey of anchor trenches for Cell 1, Cell 2 and leachate pond;
Panel layout for HDPE geomembrane and location of any repairs to the geomembrane;
Survey of the leachate drainage system installed;
Top of aggregate drainage layer; and
Survey of all, fences, culverts, roads and embankments constructed as part of the Works.
The results of the site surveys shall be supplied to the Superintendent as plan Drawings at a scale of
1:500 on paper and in 3D AutoCAD format with locations and levels to an accuracy of +/– 20 mm
horizontal and +/– 20 mm vertical and 0.2 m contour interval (or as determined by the
Superintendent), within five (5) working days of the survey being undertaken.
Where claims for payment are based on schedule of rates, quantities shall be calculated from the
survey for the items shown in the schedule of rates. Claims for payment must be substantiated by
relevant survey information and quantity calculations.
Should the survey data be deemed to be inaccurate or contain discrepancies, the Principal shall
appoint an alternative licensed surveyor to check the surveys or quantities. The Contractor will be
liable for all costs associated with any survey checks that indicate errors in the Contractor’s original
survey data.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 17
1.18 AS CONSTRUCTED DRAWINGS
The Contractor shall supply a set of ‘As Constructed’ Drawings in digital format. The As Constructed
Drawings will show the true position of the completed Works in Australian Height Datum (AHD) and
Horizontal Datum MGA 94 Zone 50. Any variations from the ‘Approved for Construction’ Drawings
will be clearly annotated on the As Constructed Drawings.
The Principal shall not issue a certificate of practical completion until As Constructed Drawings to an
accurate and acceptable standard have been supplied by the Contractor and approved by the
Superintendent.
1.19 CONSTRUCTION QUALITY ASSURANCE DOCUMENTATION
Prior to Practical Completion the Contractor must provide comprehensive Construction Quality
Assurance documentation setting out the following information:
Index;
List of all materials installed on site giving manufacturers details, agents details and a
materials list;
Earthworks soil and gravel test results;
All Construction Quality Assurance testing data for the geosynthetic liner system
materials including manufacture quality assurance test certificates for rolls delivered to
site;
Any Serial numbers;
Concrete delivery dockets;
Maintenance requirements for completed works; and
All survey data.
The documentation shall also be supplied in a digital format or be professionally bound and shall be
appropriately labelled.
1.20 ENVIRONMENTAL PERFORMANCE
1.20.1 EQUIPMENT
The equipment to be used on site shall have appropriate emission control devices and will be
maintained regularly to achieve optimum performance.
1.20.2 CONTAMINATION OF SITE
All refuelling of mobile plant will be undertaken in a designated area of the site. Any fuel tank(s)
stored onsite during construction shall be adequately contained and bunded in accordance with the
appropriate regulations to avoid spillage and contamination of soil. On occurrence of spillage events,
the contaminated soil shall be removed from the site for disposal at an appropriately licensed facility
at the Contractor’s sole expense.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 18
1.20.3 STORMWATER MANAGEMENT AND WATER DISCHARGE
Water management in the Works area will be the responsibility of the Contractor. Water in the
Works area that is generated by rain may be pumped and discharged as stormwater on another part
of the site, as directed by the Superintendent.
Water that is identified as leachate from the active landfill, or water that is suspected of
contamination with leachate must be retained and tested prior to discharge onto another part of the
site. The Contractor shall not discharge any water containing levels of salt, organic matter,
hydrocarbons or other contaminants which are incompatible with the receiving water body without
prior treatment and approval from the Superintendent. Each discharge request shall contain data on
levels of contamination for analysis by the Superintendent at least ten (10) days prior to discharge.
1.20.4 FIRE PREVENTION
The Contractor shall ensure that no fires are set alight at the Vancouver Waste Disposal Facility.
Flammable or explosive products will be stored onsite in accordance with the Explosives and
Dangerous Goods Act or any other relevant regulation. The Contractor shall obtain all the necessary
permits and licences to store and use such materials and pay all relevant fees and charges. The
Contractor shall provide and maintain adequate fire fighting equipment on site and observe the WA
Bushfires Act, Local Authority regulations, Department of Fire and Emergency Services (DFES)
requirements and any regulations in respect to fire prevention. To minimise the risk of fire, smoking
is only permitted in authorised areas. The Site Supervisor shall instruct the Contractor on the
locations where smoking is and is not permitted.
1.21 ENVIRONMENTAL OBLIGATIONS
1.21.1 DUST CONTROL
The Contractor shall implement all reasonable and practical measures to prevent or minimise the
generation of airborne particles during all tasks at all times of the Works. The Contractor shall be
bound to the Department of Environment’s publication, A Guideline for the Prevention of Dust and
Smoke Pollution from Land Development Sites in Western Australia (November 1996).
The Contractor shall provide a Dust Management Plan for the Works at least seven (7) days prior to
commencing the Works. This will be subjected to review and approval by the Superintendent prior
to the start of Works.
1.21.2 NOISE
The Contractor shall comply with the Environment Protection Authority, Environmental Protection
(Noise) Regulation 1997. The Contractor shall provide a Noise Management Plan for the Works at
least seven (7) days prior to commencing the Works. This will be subjected to review and approval
by the Superintendent prior to the start of the Works.
1.21.3 LICENCE AMENDMENT COMPLIANCE
The Contractor shall, during the period of the Works, comply with the terms and conditions specified
in the Licence Amendment/Amended Licence issued by the DWER. A copy of the Licence can be
provided to the Contractor upon request.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 19
1.21.4 SOIL EROSION
The Contractor shall take all proper precautions to prevent soil erosion from any land used or
occupied by the Contractor in the execution of the Works.
1.21.5 DUST, DIRT, WATER AND FUMES
The Contractor shall prevent any nuisance occurring through the discharge of dust dirt, water, fumes
and the like.
1.21.6 WASTE DISPOSAL
All waste from the Works (including foodstuffs) shall be handled and disposed of in accordance with
the requirements of relevant statutes to the satisfaction of the Superintendent.
1.22 SHUT DOWN PERIODS
The Contractor as part of their Tender Submission is to advise what period (if any) that the
Contractor intends to shut down the Works. The Contractor is to include the duration of any shut
down period over the Christmas, New Year or Easter period or winter months within the nominated
project period of time for practical completion.
1.23 PROJECT SUPERVISION
1.23.1 PROJECT SUPERVISOR
The Contractor shall nominate a person who will act as Project Supervisor. The Project Supervisor
shall be onsite at all times that work is being undertaken.
1.23.2 COMMUNICATION
The Contractor’s Project Manager and Project Supervisor shall be at all times contactable by mobile
phone and email. Mobile phone and email addresses shall be provided to the Superintendent at the
Award of Contract. All machine operators shall have UHF radios to allow communication throughout
the Works area and with third party users of the Vancouver Waste Disposal Facility. The UHF channel
nominated for communication purposes on the access road through Landfill site will be provided by
the Superintendent.
1.24 WET WEATHER
In the event of wet weather delaying work, any additional costs resulting from or associated with
wet weather, including but not limited to delayed work, mobilisation/de-mobilisation, will be borne
by the Contractor. If rain events over and above the expected values for the season do occur, the
Superintendent will consider extending the date of completion of the Contract. The Contractor will
not be entitled to compensation associated with any extension of the completion date.
1.25 OCCUPATIONAL HEALTH AND SAFETY
Site safety when undertaking the Works shall be the responsibility of the Contractor. The Contractor
shall determine appropriate safe working procedures and methodologies to construct the Works as
specified. Minimum Personal Protective Equipment (PPE) requirements for all visitors to the Site are
protective footwear, high visibility clothing (vest or jacket), long sleeved shirt and full length
trousers.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 20
There is no requirement placed on the Contractor by the City for Contractor’s employees to have
hepatitis shots prior to working on the Site. Should the Contractor wish to take the added precaution
of hepatitis shots for its staff working on the Site; then that will be the Contractor’s choice and will
be at the Contractor’s expense.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 21
2 SITE SERVICES AND AMENITIES
2.1 CONTRACTORS SITE OFFICE
The Contractor shall provide and maintain suitable site office as it deems necessary for the execution
of the Works and shall indicate the location of the proposed site office. The Contractor will obtain
any required building licenses at its own expense. The Contractor shall clean and maintain this office
during the Works.
Upon completion of the Works the Contractor shall remove the temporary site office and restore the
area to the same condition as before the commencement of Works.
2.2 CONSTRUCTION WATER
During construction water can be sourced from the existing infrastructure located on the Landfill
site. Supply of water will be from a designated source as determined by the Superintendent.
2.3 POWER
Supply of electricity during the Works will be the responsibility of the Contractor.
2.4 ABLUTION FACILITIES
The Contractor will be responsible for providing temporary ablution facilities and potable water
during the Works.
2.5 UNDERGROUND SERVICES
The Contractor must determine the location of any services in the Works area by contacting ‘dial
before you dig’ prior to commencing Works and confirming with the landfill Site Supervisor and
Superintendent.
2.6 TRAFFIC MANAGEMENT
An appropriate site Traffic Management Plan will be determined between the Contractor and the
Principal. Where the Contractor’s plant and equipment is required to move through areas also used
by other Site users the Contractor and the Site Supervisor will prepare a Traffic Management Plan
for approval by the Superintendent.
The Contractor’s plant operators may coordinate plant movements using UHF radios. If the
Superintendent determines that provision of stop and go traffic controllers is appropriate for safe
and effective traffic management, controllers will be supplied at the Principal’s expense.
2.7 PLANT LAY DOWN AND STORAGE AREA
An area for the lay down of the Contractor’s plant and storage of construction materials will be
supplied by the Principal in close proximity to the Works area.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 22
2.8 STANDARDS
The standards below shall apply to all works undertaken by the Contractor.
Table 1: Table of Standards
Standard Description
Australian Standards
AS 1289.0 Methods of testing soils for engineering purposes
AS 1289.6.1.1 Methods of testing soils for engineering purposes – Soils strength and consolidation tests – Determination of the California Bearing Ratio of a soil
AS 2001.2.3.1 Methods of test for textiles - Physical tests - Determination of maximum force and elongation at maximum force using the strip method
AS 2033 Installation of Polyethylene Pipe Systems
AS 3500 National Plumbing and Drainage Code (As amended 2010)
AS 3705 Geotextiles - Identification, marking and general data
AS 3706.1 Geotextiles - Methods of Test
AS 3706.3 Geotextiles - Methods of test - Determination of tearing strength - Trapezoidal method
AS 3706.4 Geotextiles - Methods of test - Determination of burst strength - California bearing ratio (CBR) - Plunger Method
AS 3706.9 Geotextiles - Methods of test - Determination of permittivity, permeability and flow rate
AS 3706.11 Geotextiles - Methods of test - Determination of durability - Resistance to degradation by light, heat and moisture
AS 3798 Guidelines on earthworks for commercial and residential developments
ASTM International Standards
ASTM D1505 Standard Test Method for Density of Plastics by the Density Gradient Technique
ASTM D4218 Standard Test Method for Determination of Carbon Black Content in Polyethylene Compounds By the Muffle Furnace Technique
ASTM D4355 Standard Test Method for Deterioration of Geotextiles by Exposure to Light, Moisture and Heat in a Xenon Arc Type Apparatus
ASTM D5261 Standard Test Method for Measuring Mass per Unit Area of Geotextiles
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 23
Standard Description
ASTM D5321 Standard Test Method for Determining the Coefficient of Soil and Geosynthetic or Geosynthetic and Geosynthetic Friction by the Direct Shear Method
ASTM D792 Standard Test Methods for Density and Specific Gravity (Relative Density) of Plastics by Displacement
ASTM D1505 Standard Test Method for Density of Plastics by the Density-Gradient Technique
ASTM D1603 Standard Test Method for Carbon Black Content in Olefin Plastics
ASTM D3895 Standard Test Method for Oxidative-Induction Time of Polyolefins by Differential Scanning Calorimetry
ASTM D4833 Standard Test Method for Index Puncture Resistance of Geomembranes and Related Products
ASTM D5199 Standard Test Method for Measuring the Nominal Thickness of Geosynthetics
ASTM D5397 Standard Test Method for Evaluation of Stress Crack Resistance of Polyolefin Geomembranes Using Notched Constant Tensile Load Test
ASTM D5641 Standard Practice for Geomembrane Seam Evaluation by Vacuum Chamber
ASTM D5721 Standard Practice for Air-Oven Aging of Polyolefin Geomembranes
ASTM D5820 Standard Practice for Pressurised Air Channel Evaluation of Dual Seamed Geomembranes
ASTM D5885 Standard Test Method for Oxidative Induction Time of Polyolefin Geosynthetics by High-Pressure Differential Scanning Calorimetry
ASTM D5887 Test Method for Measurement of Index Flux Through Saturated Geosynthetic Clay Liner Specimens using a Flexible Wall Permeameter.
ASTM D5994 Standard Test Method for Measuring Core Thickness of Textured Geomembrane
ASTM D6365 Standard Practice for the Non-destructive Testing of Geomembrane Seams using the Spark Test
ASTM D6392 Standard Test Method for Determining the Integrity of Non-reinforced Geomembrane Seams Produced Using Thermo-Fusion Methods
ASTM D6693 Standard Test Method for Determining Tensile Properties of Non-reinforced Polyethylene and Non-reinforced Flexible Polypropylene Geomembranes
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 24
Standard Description
ISO Standards
ISO 11414 Plastics pipes and fittings -- Preparation of polyethylene (PE) pipe/pipe or pipe/fitting test piece assemblies by butt fusion
Geosynthetic Research Institute Standards
GRI-GT12a Test Methods and Properties for Nonwoven Geotextiles Used as Protection (or Cushioning) Materials
GRI-GM10 The Stress Crack Resistance of HDPE Geomembrane Sheet
GRI-GM13 Test Methods, Test Properties and Testing Frequency for High Density Polyethylene (HDPE) Smooth and Textured Geomembranes
GRI-GM19 Seam Strength and Related Properties of Thermally Bonded Polyolefin Geomembranes
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 25
3 EARTHWORKS
3.1 GENERAL REQUIREMENTS
The internal batters of the landfill and the leachate pond will be sloped at 1:3 gradients, the external
batters of the landfill at 1:5 gradient and the external batters of the leachate pond at 1:3 gradient.
The landfill base cross section is shown in the Drawing AL-WA-008. The external batters shall be
graded to ensure stormwater flows away from the landfill area as shown in Drawing AL-WA-006 and
Drawing AL-WA-017. The access road to the landfill shall be constructed in accordance with
Drawing AL-WA-005. The perimeter anchor trenches shall be situated at least 1.5 m back from the
landfill and leachate pond batter crest and be excavated to a minimum depth of 0.75 m and 0.6 m
wide as per the details provided on Drawing AL-WA-010 AND Drawing AL-WA-011. The liner
materials must be suitability secured in the anchor trenches and backfilled with 250 mm thick layers
of clayey fill placed and compacted in accordance with Section 3.6.1.
The earthwork structures shall be constructed using materials sourced from the approved stockpile
area. The in-situ materials are generally considered to be suitable fill materials (generally clayey sand
materials).
There is sufficient earthworks material from the site excavations and onsite material stockpiles to
complete the earthworks and filling required by the Drawings. All construction materials used by the
Contractor shall be free from grass, tree roots, stumps, waste, litter and debris.
The final surface for the filling works shall be constructed with an earthworks tolerance of -/+ 20 mm
of the design levels.
3.2 BATTER CONSTRUCTION
To ensure a stable, durable and safe internal batter during both construction and operation of the
landfill, the fill must be appropriately compacted, keyed into the natural material and finished with
an appropriate surface for the placement of landfill liner materials.
When using fill material to construct batters the following requirements must be adhered to:
Fill is to be keyed back into natural ground material by a minimum of 1.0 m;
The width of the working platform (and placed fill) is to be a minimum of 4.0 m up the entire
batter slope; and
The 1:3 internal batter surface for Cell 1, Cell 2 and leachate pond and 1:3 for external
batter surface.
The Drawings show the profile of the existing surface and the design surface.
3.3 SITE PREPARATION
3.3.1 CLEARING
It is the Contractor’s responsibility to clear all trees, stumps, brush, grass, roots and rubbish from
areas of the Works where earthworks will be carried out. Disposal of organic materials removed
from the area of the Works will be disposed at the Site’s greenwaste area following approval from
the Site Supervisor.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 26
3.3.2 GRUBBING
All stumps and roots in the area of the Works shall be grubbed out to a minimum depth of 500 mm
below the stripped areas, or otherwise to the satisfaction of the Superintendent. The Contractor
shall dispose of grubbed material at the Site’s greenwaste area following approval from the landfill
Site Supervisor.
3.3.3 SPOIL
The Contractor shall remove spoil from the Works area for landfill disposal or stockpiling, as directed
by the Site Supervisor or the Superintendent. Spoil includes debris resulting from clearing, stripping,
grubbing and excavated material unsuitable as fill unless otherwise specified or approved by the
Superintendent.
Clean topsoil complete with natural vegetation will be stockpiled separately for placement by the
Principal at a later date to aid rehabilitation.
3.3.4 MATERIAL STOCKPILE AREA
The Contractor shall stockpile the above materials in separate stockpiles, at least 10 m apart, for use
as fill and other construction purposes. Stockpiles shall be constructed to prevent segregation or
degradation of material. The stockpile area is situated immediately to the south east of the Works
area.
3.4 EXCAVATION
The Contractor shall carry out all earthworks for the Works as shown on the Drawings. The
Contractor shall perform excavation in every type of material encountered within the limits of the
Works to the lines, grades and elevations shown on the Drawings. Suitable excavated material will
be used as fill in the Works area. Excavated materials that are unsuitable for placement as fill, or not
required as fill, will be stockpiled separately in areas designated by Superintendent.
It is the responsibility of the Contractor to determine the appropriate equipment to undertake the
task after conducting assessment of the soil/rock type on the site. The foundation level cut to the
design level shall be brought to the attention of the Superintendent for inspection. Excavations not
classified as “Hard Rock” shall be classed as common excavation and the Contractor shall not be
entitled to any variation or extension of time due to failure to meet the approved project schedule.
3.4.1 HARD ROCK
Hard Rock refers to the excavation of in-situ material that cannot be ripped and excavated with a
track dozer in good condition with matching hydraulic single shank ripper of combined mass not less
than 52 tonnes (e.g. Caterpillar D10R or its equivalent) at a rate in excess of 90 m³ (solid) per hour.
The determination of what material is to be classed as Hard Rock will be determined by the
Superintendent.
Hard Rock encountered during excavation shall be removed by a methodology, and subject to
additional payment, as agreed upon by the Contractor and the Superintendent.
Payment for the removal of Hard Rock is not included in Schedule of Rates. Payment for the removal
of Hard Rock will be based on an agreed unit rate and the surveyed quantity as determined by the
Contractor’s licensed surveyor and agreed with the Superintendent.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 27
Due to the close proximity to the rail line blasting shall not be allowed.
3.4.2 SOFT GROUND
Soft ground shall be removed after gaining approval from the Superintendent and disposed of at a
location nominated by the Superintendent. The soft ground stockpile shall be protected from
erosion using appropriate slope. The subgrade is to be shaped by cutting into natural material or
engineered using locally sourced clayey material if soft ground is encountered.
3.4.3 UNDERGROUND SPRINGS AND SEEPAGE
Groundwater seepage and/or springs encountered during excavation shall be brought to the
attention of the Superintendent. The Superintendent shall instruct the Contractor should
groundwater relief drainage be required.
3.5 GROUNDWATER MANAGEMENT
The Contractor shall be aware of the anticipated groundwater or perched groundwater conditions
and excavations shall be dewatered as necessary. The dewatered materials shall provide stable
foundation for the fill materials in order to permit construction work to take place on a firm
subgrade.
3.6 FILLING AND SUBGRADE
All suitable excavated materials shall be used as fill material and backfill for anchor trenches.
Unsuitable materials are defined under AS 3798, Guidelines on earthworks for commercial and
residential developments. Fill material will be sourced from the Works or existing stockpiles at the
Site.
Suitable material from excavations shall be used immediately or stockpiled to allow future recovery
and reuse. Suitable material shall be separated during excavation and shall be placed in the
designated stockpile area outside the excavation areas as approved by the Superintendent. No
excavated material shall be hauled to spoil without the approval of the Superintendent
3.6.1 FILL PLACEMENT
The Contractor shall carry out the construction of the Works in accordance with the Drawings and
shall adhere to the slopes, levels, depths and heights shown thereon. Areas that have been over
excavated or removed as soft ground, require filling to meet design levels including anchor trenches
shall be filled using similar materials to those of the subgrade. The compacted material shall be
mixed and moisture conditioned prior to compaction. The mixing and moisture conditioning must
be carried out to achieve a uniform composition and moisture condition throughout each layer of
placed material.
The material shall be uniformly compacted using a 12 tonne pad foot roller or greater in near
horizontal layers not exceeding 250 mm thickness after compaction. Anchor trenches shall be
backfilled and compacted using a vibrating plate compactor in 250 mm thick layers after
compaction.
The characteristics of the fill material to be considered are:
Moisture content on placement to be between 3% dry and 2% wet of optimum moisture
content (using standard compaction);
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 28
A minimum standard compaction during placement of 95% for anchor trench; and
A minimum standard compaction during placement of 98% for landfill subgrade.
Table 2: Fill and Subgrade Compliance Testing Acceptance Criteria
Item Test Method Acceptance Criteria
Density (Anchor trench)
AS 1289 5.8.1
AS 1289 5.1.1
Minimum dry density ratio of 95% relative to Standard compaction
Density (Landfill subgrade)
AS 1289 5.8.1
AS 1289 5.1.1
Minimum dry density ratio of 98% relative to Standard compaction
Moisture variation AS 1289 5.4.1 -3.0% to +2.0% of the Standard Optimum Moisture Content (SOMC)
Permeability (Landfill subgrade)
AS 1289 5.1.1
AS 1289 6.7.2
Permeability less than 1 x 10-9 m/s
Testing shall be carried out to demonstrate the compliance of the layer with the moisture content,
density ratio and permeability requirements of this Specification as soon as practicable after
compaction. It is the responsibility of the Contractor to coordinate with the testing authority to
ensure that this requirement for the scope and time of testing is met at all times during the
construction of the Works.
An effective bond shall be created between successive layers. Prior to placement of each layer, the
surface of the previous layer shall be lightly scarified and moisture conditioned if necessary to bond
the layers and to prevent laminations at the layer interfaces. If laminations occur, either between or
within layers, the area shall be reworked at the Contractor’s expense to remove any laminations or
defects. Trafficked sections are to be ripped, moisture conditioned and re-compacted to the
specified requirements if, in the opinion of Superintendent, these areas have deteriorated.
The surface of compacted material shall be rolled and shaped to prevent ponding of water on the
surface of the layer. If the Contractor elects to create a smooth surface at the end of a shift using a
blade or smooth wheeled roller, then the smooth surface shall be roughened and moisture
conditioned prior to placement of the next layer.
Backfilled anchor trenches are to be finished with a smooth surface that slopes away from the
landfill to prevent stormwater from outside the landfill entering the landfill.
3.6.2 LANDFILL ACCESS ROAD PREPARATION
Prior to the construction of the access road to the landfill, the Contractor shall excavate and shape
the stripped ground surface to create a suitable working foundation. The entire foundation surface
shall be tyned to a loose depth of 150 mm, with all cobbles greater than 75 mm and roots removed.
The foundation shall then be compacted to not less than 95% of its standard maximum dry density,
as determined in accordance with AS 1289.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 29
Areas that are lower than specified in the Drawings shall be filled with material free from organic
matter and/or stones. Any excavated material that does not comply with fill material requirements
shall be disposed of as spoil.
Excavated final surfaces within the formation shall be compacted to not less than 95% of their
standard maximum dry density as determined in accordance with AS 1289. During compaction, the
moisture condition of placed material shall be at or near the material’s optimum moisture content
Any ruts, soft areas, loose areas or out of shape sections shall be reshaped and re-compacted.
3.6.3 REMOVAL OF NON-CONFORMING MATERIALS
Should inspection or testing of the material indicate that a layer is not in accordance with the
Specification, the Superintendent will direct the Contractor to rework the area at the Contractor’s
own expense. If the layer still does not conform to the requirements of the Specification after
reworking, the Contractor, at their own expense, shall remove the material to an approved
designated area to potentially be mixed and moisture re-conditioned.
3.7 FREQUENCY OF COMPLIANCE TESTING
Inspection and testing shall be carried out in accordance with relevant Standards and the
requirements of this Specification and in particular with AS 1289 Methods of Testing Soil for
Engineering Purposes. The Contractor’s program shall allow for testing to be carried out and
reporting. The Contractor’s program shall allow two (2) working days for completion of field density
and compaction testing.
The frequency of field density tests will comply with Table 8.1 of AS 3798, as summarised in Table 3
below. Table 3: Required Frequency of Field Density Testing
Type of Earthworks
Frequency of Tests
Type 1 Large-scale operations (greater
than 1500 m2)
Not less than:
1 test per layer per material type per 2,500 m2, or 1 test per 500 m3 distributed reasonably evenly throughout full depth and area, or 3 tests per Lot,
whichever requires the most tests
Type 2 Small scale operations (500 m2
to 1500 m2)
Not less than:
1 test per layer per 1,000 m2, or 1 test per 200 m3 distributed reasonably evenly throughout full depth and area, or 1 test per Lot per layer,
whichever requires the most tests
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 30
Type of Earthworks
Frequency of Tests
Type 3 Concentrated
operations (less than 500 m2)
Not less than:
1 test per 100 m3 distributed reasonably evenly throughout full depth and area, or 1 test per layer per 500 m2, or 3 tests per visit,
whichever requires the most tests
Type 4 Confined operations (trenches)
1 test per 2 layers per 50 m2
Note: A Lot is defined as an area of work that is essentially homogeneous in relation to material type, moisture
content and compaction effort.
3.8 PROOF ROLLING
The subgrade prepared for the construction of the landfill liner system and the access road shall be
proof rolled prior the placement of the overlying layers in addition to field density testing of the final
surface.
Proof rolling will be carried out in the presence of the Superintendent and the following
methodology will be adhered to:
The surface of the subgrade is to be kept moist at all times to prevent desiccation cracking;
Subgrade is to be proof rolled using a smooth drum roller of 12 tonne capacity or greater
using a minimum of six (6) passes over the entire prepared surface; and
Subgrade to be inspected and approved by the Superintendent prior to placement of the
overlying layers.
The surface of the subgrade shall be clear of indentations from tyre tracks and desiccation cracks. In
the case of subgrade preparation for the installation of geosynthetic liners, the surface of the
subgrade will be free of stones greater than 20 mm and there will be no sudden change in grade of
greater than 20 mm over a distance of 5.0 m.
The Superintendent shall inspect and approve the prepared subgrade surface prior to the
construction of the overlying layers. The Contractor will be required to give 48 hours’ notice for
inspection of the prepared subgrade.
3.9 SURVEY VERIFICATION
The Contractor shall perform survey as part of its Quality Assurance Plan to demonstrate that the
compacted layer thickness, the completed fill thickness and surface grades comply with the
requirements of this Specification and the Drawings.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 31
4 COMPOSITE LINING SYSTEM
4.1 LINER CONSTRUCTION OVERVIEW
The liner construction is important as it protects the surrounding environment from the impacts of
leachate and landfill gas migration. The main engineering components of the proposed liner
configuration will include the following (as shown on the Drawings):
Compacted, shaped and rolled subgrade consisting of insitu clay, the insitu clay will form the
secondary layer of the composite liner. The insitu clay will have a hydraulic conductivity of
less than 1 × 10-9 m/s and will help in limiting contaminant migration, water seepage and
landfill gas migration;
A 2.0 mm thick High Density Polyethylene (HDPE) geomembrane liner will be placed directly
above the insitu clay and will serve as the primary layer to limit contaminant migration and
to control landfill gas migration;
A non-woven geotextile cushion layer will be placed on top of the HDPE liner to serve as a
protective layer, minimising the risk of damage or puncture during installation of the
protection layer and operation of the landfill;
A 300 mm thick drainage layer of single sized crushed aggregate will be placed on top of the
cushion geotextile to serve as a leachate collection layer; and
Over the drainage layer will be a non-woven geotextile which will act as a separation
medium between the drainage aggregate and the waste.
All geosynthetic layers will be secured to the top of the slope in anchor trenches as shown on the
Drawings.
4.2 CONFIRMATION OF MATERIALS ORDER
Within seven (7) days of award of Contract the Contractor must provide to the Superintendent
confirmation of the order to purchase all of the required geosynthetic liner materials and the
proposed delivery date of materials to site.
4.3 LINER QUALITY ASSURANCE DOCUMENTATION
The documents listed below must be supplied to the Superintendent by the Contactor before
placement of baseliner on the prepared subgrade surface will be authorised by the Superintendent.
Manufacturer’s laboratory test result sheets proving the Specification compliance of each
roll of HDPE geomembrane liner to be used in the Works;
Manufacturer’s laboratory test result sheets proving the Specification compliance of each
roll of welding rod to be used in the Works;
Manufacturer’s laboratory test result sheets proving the Specification compliance of each
roll of cushion geotextile to be used in the Works;
Proposed panel layout for the HDPE liner;
Work Method Statements for the deployment of all geosynthetic liners;
Daily subgrade surface acceptance by the lining installer;
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 32
Compaction test results for the prepared subgrade and basecourse layers; and
Survey of subgrade and anchor trenches.
These items are addressed in more detail in later sections of this Specification.
4.4 WASTE FROM CONSTRUCTION
All waste arising from the installation of composite liner and other Works will be removed from the
Works area by the Contractor and disposed at an appropriate location as approved by the
Superintendent.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 33
5 CLAY LINER
The insitu clay subgrade shall be used as the clay liner beneath the landfill and leachate pond. The
Contractor shall prepare the surface to the grades shown on the Drawings. Areas that have been
over excavated or removed as soft ground require filling to meet design levels shall be filled using
similar materials to those of the subgrade.
The surface of the clay subgrade shall be uniformly compacted using a 12 tonne pad foot roller or
greater.
5.1 CLAY LINER CHARACTERISTICS
The characteristics of the clay liner to be considered are:
Moisture content on placement to be between 3% dry and 2% wet of optimum moisture
content (using standard compaction);
A minimum standard compaction during placement of 98%; and
Permeability less than 1 x 10-9 m/s.
Table 4: Fill and Subgrade Compliance Testing Acceptance Criteria
Item Test Method Acceptance Criteria
Density AS 1289 5.8.1
AS 1289 5.1.1
Minimum dry density ratio of 98% relative to Standard compaction
Moisture variation AS 1289 5.4.1 -3.0% to +2.0% of the Standard Optimum Moisture Content (SOMC)
Permeability AS 1289 5.1.1
AS 1289 6.7.2
Permeability less than 1 x 10-9 m/s
Testing shall be carried out to demonstrate the compliance of the layer with the moisture content,
density ratio and permeability requirements of this Specification as soon as practicable after
compaction. It is the responsibility of the Contractor to coordinate with the testing authority to
ensure that this requirement for the scope and time of testing is met at all times during the
construction of the Works.
5.2 VERIFICATION OF CLAY LINER
The Contractor shall verify the integrity of the clay liner by carrying out testing in a NATA Registered
laboratory. The frequency of testing shall be in accordance with Table 3. The results of the testing
shall be provided to the Superintendent, and approved by the Superintendent, prior to the
placement of the HDPE geomembrane liner.
The Contractor shall be aware that permeability testing can take up to two weeks to complete. The
Contractor shall remain in contact with the NATA Registered testing laboratory throughout the
permeability testing period and should the criteria shown in Table 4 be achieved the Contractor
shall, through written notification from the NATA Registered laboratory, notify the Superintendent.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 34
6 HIGH DENSITY POLYETHYLENE (HDPE) GEOMEMBRANE
The High Density Polyethylene (HDPE) geomembrane liner shall be a new, top-quality product
designed specifically for use as landfill liner and have a thickness of not less than that specified
below. The geomembrane shall be uniform and free of pin-holes, blisters, undispersed raw materials
and contamination by foreign matter. The geomembrane liner shall be manufactured in rolls to a
seamless width of not less than 6.8 m.
6.1 LABELLING
Each roll of HDPE liner shipped from the place of manufacture shall be labelled with the following
information:
Product Identification;
Roll Number;
Roll Thickness;
Roll Dimensions;, and
Date of Manufacture.
6.2 HDPE MATERIAL PROPERTIES
One type of HDPE liner shall be used, with all rolls sourced from the same manufacturer and
produced from the same base resin formulation. Test results for the base resin and welding rod shall
be provided prior to delivery of the materials to site. The geomembrane shall be textured on one
side and installed with the textured surface facing down onto the underlying clay material.
The HDPE geomembrane shall be 2.0 mm nominal thickness and shall comply with all property
requirements and testing frequencies prescribed in Table 2(b) of the GRI-GM13 standards. The key
parameters of the GRI standards are presented in Table 5 for quick reference.
Table 5: Selected Key Parameters for HDPE Geomembrane Liner - Manufacturer
Property Unit Value Test method
Average Thickness mm > 1.9 ASTM D5994
Average Density g/cc > 0.94 ASTM D1505 / D792
Tensile Yield Strength kN/m > 29 ASTM D6693
Tensile Yield Elongation % > 12 ASTM D6693
Tensile Break Strength kN/m > 21 ASTM D6693
Carbon Black Content % 2.0 - 3.0 ASTM D4218
Note: This Table is included for convenient reference only of key parameters. For the complete list of parameters refer to the full Table in the GRI standard.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 35
6.3 QUALITY ASSURANCE
The following confirmation documents shall be provided to the Superintendent:
The Contractor shall provide the Superintendent with a quality assurance certificate from
the geomembrane manufacturer for each roll of geomembrane delivered; and
The quality assurance certificate shall contain properties mentioned in the above Table as a
minimum.
6.4 SUPPLY AND HANDLING
The HDPE geomembrane liner rolls are to be delivered to site bound with strapping and stored on a
hard, free-draining surface. The HDPE liner rolls are to be handled in accordance with the
manufacturer’s specification.
6.5 INSTALLATION
6.5.1 PLANNING
The planning phase shall address the following as a minimum:
The layout of the HDPE geomembrane in the area to be lined;
Points of overlaps and connections;
Arrangements for panel placements at any specific points to avoid any bends and minimise
the stress and overlaps on the HDPE;
Work method statement for deploying the HDPE including the equipment to be used shall be
prepared by the contractor and shall be approved by the Superintendent before
commencement of installation;
Work method for deploying HDPE over the clay subgrade;
The Contractor shall not allow any vehicles, cranes or any other mobile plant to traverse the
HDPE liner; and
The panel placement arrangement shall comply with the installation guidelines provided by
the manufacturer and any contradictions from the methodology proposed below shall be
brought to the attention of the Superintendent.
6.5.2 PLACEMENT
The placement methodology will comply with the following:
The HDPE membrane surface shall be inspected during unrolling and installation to ensure
no tears, punctures, abrasions, indentations, cracks, or other faults are present in the
material;
Any defects identified are to be marked with coloured marker, recorded and repaired;
The inspection of the surface of clay layer shall be conducted prior to placement of HDPE by
the Contractor and approved by the Superintendent;
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 36
The geomembrane shall installed with the textured surface facing down onto the underlying
clay material;
The HDPE panels shall be installed in such a way that continuous panels are used on the 1:3
grade slopes;
The placement shall be according to the pre-planned layout designed to minimise the
amount of panel welding required;
No material offcuts, sandbags, waste packaging or other foreign objects are to be left
between the clay subgrade and HDPE geomembrane;
Each panel shall be welded immediately after placement;
The adjacent panels will have an overlap of minimum 125 mm for fusion welding and
minimum 100 mm for extrusion welding;
The overlap shall be oriented down the slope and across the flat base in a tiled fashion to aid
drainage;
The connecting seam between the HDPE geomembranes on the slopes and the base shall be
located at a distance of 1.5 m from the slope toe on the flat area;
Sand bags shall be placed on free ends and on the seams at the end of each day to prevent
wind uplift;
Sand bags shall also be used during welding in windy conditions to prevent movement of the
HDPE panels;
HDPE unrolling and deployment methodology shall not score, scratch or crimp the HDPE
geomembrane;
Expansion and contraction of HDPE membranes while placing and seaming activities shall be
taken into consideration;
Care shall be taken during installation of the HDPE to ensure it is without substantial
buckling, wrinkling, or tensioning prior to placement of cover material;
HDPE geomembranes installed on the slopes shall be fixed in anchor trenches and anchorage
shall be carried out when the geomembranes are cool;
The trench shall be backfilled with low hydraulic conductivity soils and compacted as soon as
the cushion geotextile is laid; and
HDPE geomembranes shall not be installed during high wind, dusty or rainy conditions.
6.6 WELDING METHODS
A thermal methodology shall be used to join surfaces using applied heat. Hot-wedge welding shall be
used for welding all main joints between adjacent HDPE membranes, producing two parallel seams
with an air channel in between. Extrusion welding will be used primarily for detailed work and repair
work. Welding of any joints shall be carried out in one direction only.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 37
6.7 SEAM PREPARATION
The weld surfaces shall be cleaned prior to welding and shall be free from moisture, debris, and
foreign material. The grinding shall not be deeper than 10 per cent of the membrane thickness and
seams are to be aligned with the smallest possible number of wrinkles.
6.8 WELDING OF GEOMEMBRANE
6.8.1 HOT-WEDGE (FUSION) WELDER
The welding equipment to be used shall consist of fully automated devices comprised of heated
copper wedge, pressure rollers and electronic controls. The copper wedge shall be controlled and
constantly monitored by a programmable controller. The equipment shall have an audible
temperature alarm to measure the temperature at the point of contact and a variable speed drive
unit.
6.8.2 EXTRUSION WELDER
The surface extraction welder shall be semi-automatic, and have electronic controls monitoring the
pre-heat and extradite. The unit shall have preheating capabilities to preheat the casting of the
extradite.
6.8.3 FUSION WELDS
A minimum of 5 mm wide void will be created between at least 15 mm wide contact fusion areas
created over the parallel weld zones.
6.8.4 EXTRUSION WELDS
The extrusion process will be applied in approved areas that would be inaccessible to the dual track
fusion weld machine and for repair work. The minimum width of the surface extruded bead shall be
30 mm. The material of the extruded granular/rod to be used for surface extrusion welding shall be
the same type as used in the manufacture of the HDPE geomembrane. The manufacturer shall
provide certified test data for each batch of welding granule/rod and the Contractor shall make it
available for verification by the Superintendent. The sheet shall be pre-heated prior to casting of the
extradite over the upper and lower section of the weld zone. Patching HDPE geomembranes using
transverse joints on the slopes is not permitted.
Should an extrusion weld be performed in a corner or detailed area where a vacuum box would not
create an adequate seal for air testing, a copper wire shall be installed under the extrusion weld to
facilitate quality assurance by spark testing.
6.9 WELD TESTING
Weld testing will involve both destructive and non-destructive testing. Destructive testing will be
used to carry out spot checks of the welded seam and non-destructive testing will be used to test
the continuity and the completeness of the entire seam. Destructive testing shall also be used to
prequalify welding personnel, equipment and procedures for making seams. The destructive testing
will be carried out in compliance with the GRI-GM19 standards.
The Contractor shall record the date, time, technician and results of all testing to verify that every
seam and weld has been tested. Any failing tests will be appropriately repaired and recorded.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 38
6.9.1 DESTRUCTIVE TESTING AND TRIAL WELDS
The following measures will be followed for destructive testing and trial welds:
Trial weld (pre-qualifying test welds) testing will be performed:
o before the commencement of welding each day;
o if a stoppage occurs for more than 3 hours;
o if there is a change in weather conditions; or
o if 500 m of seam has been welded since the previous test;
The trial weld sample shall be a minimum of 1.5 m long;
Extrusion trial welds will be allowed to cool naturally, without immersion in water or similar;
Four 25 mm wide samples shall be cut from the weld sample;
Two samples shall be tested for shear strength;
Two samples shall be tested for peel strength, with both sides of a fusion wedge weld being
peeled;
In all tested welds, the failure shall be in the parent material and not the weld;
All four samples shall pass with the minimum properties as specified in Table 6 to approve
the welder and operator combination to commence work;
If a trial weld fails, the likely reason for the failure will be identified and recorded, the
welding technique adjusted and a further trial weld performed;
Trial welds qualify only the equipment and operator combination that performed the test
weld. Welding may not be performed by an alternative operator on the same equipment
without a passing trial weld;
Destructive seam tests shall be carried out at random locations as located by the
Superintendent or Quality Assurance Engineer, at a minimum frequency of one sample every
150 m of fusion welded seam;
Shear and peel testing shall be carried out in the presence of the Quality Assurance
Engineer;
A consistent squeeze out on the weld edge for extrusion welding shall be obtained; and
A 300 mm long weld sample from each trial weld and each destructive test sample will be
labelled, retained and submitted to the Superintendent for future reference or future
independent destructive seam testing.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 39
Table 6: Minimum Test Values for a HDPE Weld Sample
Test Minimum Force (N) Minimum Weight (Kg)
Shear 690 70.3
Peel 450 45.9
Note: These values are applicable only for a 25 mm wide sample of 2 mm thick HDPE.
6.9.2 PRODUCTION SEAMS
Destructive seam tests shall be carried out at random locations as identified by the Superintendent
or Quality Assurance Engineer as follows:
At a minimum frequency of one sample every 150 m of fusion welded seam;
A 1.5 m length section of seam shall be removed for testing;
Ten 25 mm-wide tokens shall be cut for destructive testing;
Five samples shall be tested for shear strength (at a maximum tensiometer rate of
50 mm/minute);
Five samples shall be tested for peel strength, with both sides of a fusion weld being tested;
A minimum of 4 out of 5 shear tests and a minimum of 4 out of 5 peel tests must pass for
the destructive test to pass;
Should less than 5 out of 5 samples pass, a retest of the seam in the vicinity of the test may
be required at the Superintendent’s discretion;
Should less than 4 out of 5 samples of either test pass, the integrity of the remainder of the
seam shall be determined by the following methodology:
o Destructive test samples will be taken 3 m either side of the failed test site;
o If these samples fail, samples will be taken a further 3 m along and so on until the
extent of the defective seam section is established;
o The entire length of the defective seam section will be capped using a HDPE strip,
overlapping the damaged area by a minimum of 100 mm in all directions; and
o The capped strip will be welded with a hot–wedge fusion welder where possible
and otherwise with an extrusion weld.
The total length of fusion seams in the project will be calculated by the Contractor and confirmed by
a licensed surveyor.
At the request of the Superintendent, a selected number of site destructive seam samples maybe
tested by an independent NATA accredited laboratory in accordance with ASTM D6392. The
selection of samples and testing of the samples shall be arranged by the Superintendent based on
the site destructive seam test results. The rate of independent destructive seam testing shall be not
less than 10% of the total destructive samples or a minimum of 3 samples, or as determined by the
Superintendent.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 40
6.10 NON-DESTRUCTIVE TESTING
Non-destructive testing includes air pressure testing for dual track fusion welds and vacuum or spark
testing for extrusion welds.
The pressurised air equipment and testing shall comply with ASTM D5820 Standard Practice for
Pressurised Air Channel Evaluation of Dual Seamed Geomembranes. The seam should be pressurised
to minimum 30 psi/210 kPa (air pressure should be stabilised), then after a minimum of 2 minutes,
the air pressure should not decrease by more than 4 psi/15 kPa. After this the other end of the
seam should be cut to release the air pressure and confirm that the entire seam has been tested for
continuity and water tightness. Cut seams and air pressure needle holes shall be sealed using an
extrusion bead or as approved by the Superintendent.
The vacuum box equipment and testing shall comply with ASTM D5641 Standard Practice for
Geomembrane Seam Evaluation by Vacuum Chamber. A minimum vacuum pressure of minus 25 kPa
shall be used and be held for a minimum duration of 10 seconds. Adjoining areas shall be tested with
a minimum 75 mm overlap between test sections.
Spark Testing shall comply with ASTM D6365 Standard Practice for the Non-destructive Testing of
Geomembrane Seams using the Spark Test.
All seams, welds, patches and repairs will be tested and recorded as part of the Contractors Quality
Assurance documentation. Where detailed work prohibits the use of a vacuum testing box the spark
test shall be performed. The Contractor shall verify testing is complete by comparing testing records
to the As Constructed Drawings.
6.10.1 PATCHING AND EXTRUSION REPAIRS
The following measures will be employed for repairs and patching of the HDPE liner:
All fusion weld seam intersections will be protected with an extruded patch cover;
All repairs to the liner will be performed using a capping strip, overlapping the damaged area
by a minimum of 100 mm;
Extrusion repairs by placing a bead of extradite along a tear, over a hole or in any other
location where a minimum material overlap of 100 mm is not present shall not be
permitted; and
Care shall be taken when grinding the ends of fusion seams to extrude stopper plugs not to
grind through the second layer of HDPE geomembrane.
6.10.2 REPORTING
The Contractor shall record the roll number, location and installation date for each roll of HDPE
geomembrane to cross reference against the Quality Assurance documentation. These records shall
be made available to the Superintendent and the Quality Assurance Engineer.
Records shall also include:
All repairs made on the panel shall be recorded by the Contractor;
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 41
The Contractor shall record and prepare as-built to scale Drawings of the HDPE
geomembrane, with the layout of panels, roll numbers, location and detail of repairs and
patches and these records shall be made available to the Superintendent;
The Contractor shall provide to the Superintendent, progressive QA/QC documentation
during the lining works;
The Contractor shall provide all field final QA/QC documentation to the Superintendent
within 2 working days of the works being completed; and
Payments for the geosynthetic works will be subject to the completion of the works and
provision of the required QA documentation.
6.11 WARRANTY
The Contractor shall provide a warranty for the life of the HDPE geomembrane liner system prior to
completion of the Works. The Performance Warranty shall incorporate a minimum 5 year Product
(Manufacturer’s) Warranty and a 1 year Installation Warranty.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 42
7 GEOTEXTILE CUSHION LAYER
The cushion geotextile layer will act as the protection layer between the HDPE geomembrane and
waste layer. It shall be installed over the HDPE geomembrane layer.
7.1 LABELLING
Each roll of cushion geotextile shall comply with AS 3705-2003 Geotextile Identification, Marking and
General Data and shall be labelled to provide the following minimum:
Product name, grade and name of the manufacturer;
Date of manufacture, batch number, polymer type;
Manufacture quality control documentation from the manufacturer/supplier;
Roll number;
Roll dimensions; and
Roll weight.
Manufacture quality control documentation from the manufacturer/supplier shall be provided to
the Superintendent prior to the commencement of lining operations.
7.2 MATERIAL SPECIFICATION
The cushion geotextile layer will be a non-woven geotextile manufactured from polyamide,
polyolefines, polyester and/or polyvinyl materials. The cushion geotextile shall comply with the GRI-
GT12 (a) standards and testing frequencies and satisfy the following minimum properties:
Table 7: Geotextile Cushion Layer Properties
Property Unit Value
(minimum) Test
Mass Per Unit Area g/m2 500 ASTM D5261
Trapezoidal Tear Strength
(machine and cross machine direction) N 1,000 AS 3706.3
CBR Bust Strength N 6,800 AS 3706.4
Grab Tensile Strength
(machine and cross machine direction) N 2,800 AS 2001.2.3
UV Resistance % > 45 ASTM D4355 or
AS3706.11
UV resistance test results for the geotextile shall be based on manufacturer batch results and results
shall be less than 12 months old.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 43
7.3 QUALITY ASSURANCE
The following confirmation documents shall be provided to the Superintendent:
The Contractor shall provide the Superintendent with the quality assurance certificate from
the geotextile manufacturer for each roll of geotextile delivered;
The quality assurance certificate shall contain details mentioned in Table 7 as a minimum;
Geotextiles will be free from any flaws/needles, which may have an adverse effect on the
physical or mechanical properties of the product; and
Geotextiles shall be certified needle free by the manufacturer.
7.4 STORAGE AND HANDLING
All delivered geotextile cushion materials will be stored on level ground, free from any water logging
or drainage paths and not more than three (3) rolls high. Appropriate lifting methodology shall be
used to prevent any damage while handling.
7.5 INSTALLATION
Placement of the geotextile cushion layer shall be carried out in accordance with the manufacturer’s
recommendation, details of which shall be provided to the Superintendent for approval. The
following measures will be adopted during placement:
All testing of the HDPE geomembrane shall be completed prior to placement of geotextile
cushion layer;
A predetermined layout plan will be prepared to keep the overlap to a minimum;
The HDPE geomembrane surface shall be free from any sharp objects, stones, debris, water
or other potentially damaging objects;
Only geotextile cushion rolls inspected and approved by the Superintendent shall be
unrolled and used for placement;
The placement of geotextile shall be in accordance with the approved layout;
The geotextile sheets shall be continuous across the base;
Sheets will be anchored at the crest of the slope in the anchor trench and rolled down the
walls and slopes;
Geotextile sheets shall be deployed by hand to reduce the ground contact pressure on the
underlying HDPE geomembrane;
The adjacent geotextile cushioning sheets will have a minimum overlap of 300 mm;
Joining of sheets shall be conducted by stitching or heat-bonding with an approved hot-air
device;
No stapling of adjacent geotextile cushion sheets are allowed;
The joints shall be constructed parallel to the slope gradient;
Care shall be taken during heat bonding to prevent any damage to the underlying HDPE
geomembrane;
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 44
The geotextile cushion materials shall not have cross joints on slopes steeper than 1:5;
All deployed geotextile sheets shall be restrained with sand bags as soon as possible to
negate uplift and dislodgement from wind; and
The installation of geotextile shall be carried out by experienced and competent installers.
7.6 REPAIR
The repair shall be carried out in compliance with the methodology below:
Any repair on the damaged geotextile during installation shall be carried out by patching
with a new piece of geotextile made from the same material with a minimum 100 mm
overlap on all edges;
Repairs shall be conducted only after cleaning of the area subjected to repair; and
Any repair patches on a slope shall be double seamed into place.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 45
8 LEACHATE COLLECTION SYSTEM
The components of the leachate collection system associated within Cell 1 and Cell 2 construction
are the drainage layer, drainage pipes and leachate extraction pipes. The Contractor shall provide all
materials, supervision, labour and equipment for the placement of each component of the leachate
collection system in accordance with this Specification and the Drawings.
8.1 LEACHATE COLLECTION PIPES
The Contractor is to carry out the pipework installation as indicated on Drawing AL-WA-014. The
landfill will have two sizes of pipe, the first being DN160 PE110 PN20 black perforated pipes laid at
20.0 m centres as described in Drawing AL-WA-014. The primary collection pipe will be DN225
PE110 PN20 black perforated pipe feeding into the leachate sump. The leachate extraction pipes
running up the side slope of Cell 1 and Cell 2 will be DN450 PE100 PN16 and perforated within the
leachate sump.
8.1.1 INSTALLATION
The following measures and placement methodology will be adopted:
HDPE pipes shall be stored, handled and transported in accordance with AS 2033,
Installation of Polyethylene Pipe Systems;
Pipes will be handled carefully to avoid distortion, buckling or other damage;
The joining of pipes shall be by electro-fusion coupling or butt welding;
All joining procedures will be carried out according to the manufacturer’s specification;
Butt welding or electro-fusion welding will be carried out by a qualified technician and the
evidence of current certification from the Materials Institute of Western Australia to ISO
11414, Plastics Pipes and Fittings -- Preparation of Polyethylene (PE) Pipe/Pipe or Pipe/Fitting
Test Piece Assemblies by Butt Fusion or equivalent shall be provided to the Superintendent;
Drilling of HDPE pipes shall not be carried out on the lined cell area;
All swarf from drilling activity shall be removed prior to installation of pipes;
All cut edges and welded joints shall be neat and smooth;
The butt welds are to be de-burred on the inside of the pipes;
Pipes shall be clean internally and free from mud, dirt and other debris;
During placement of the pipe on the landfill liner, each pipe shall be lifted into position to
avoid any damage to the liner;
Each pipe shall be positioned accurately and placed directly on the cell liner;
Aggregate shall be placed around and on the leachate pipes and carefully compacted to
avoid any damage to the liner material or the HDPE pipe itself; and
Pipe extending into the leachate sump area shall be laid directly on the surface of the
leachate sump or otherwise supported on underlying drainage aggregate so that no bending
or deformation of the pipes occurs (Drawing AL-WA-015).
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 46
8.1.2 PIPE SURVEY
A detailed survey of the pipe network shall be carried out, detailing the pipe locations and invert
levels to verify compliance with the Drawings. The locations and invert levels of the pipes will be
reported to the Superintendent for approval.
8.2 LEACHATE SUMP
The leachate sump will be constructed as a depression within the landfill subgrade as detailed on
Drawing AL-WA-015.
8.3 ANCHOR BLOCK
At the top of the side slope a concrete anchor block will be constructed. The anchor block will be
reinforced N32 concrete, 20 mm, with reinforcing mesh and with 30 mm cover over reinforcement.
The anchor block will support the two extraction pipes running up the side slope and provide a
platform for managing the leachate extraction from the leachate sump, refer Drawing AL-WA-016.
8.4 DRAINAGE AGGREGATE
The drainage layer will be comprised of aggregates free from organic matter or fine grained material.
8.4.1 AGGREGATE SPECIFICATION
The drainage aggregates will be comprised of hard rock quarry product with a maximum particle size
of 50 mm and a minimum of 20 mm. Materials that are susceptible to degradation by leachate are
not acceptable; crushed concrete or limestone are not permitted. The aggregates shall comply with
the grading described in Table 8.
Table 8: Drainage Aggregate Specification
Sieve Size (mm) Percentage Passing (%)
37.5 100
26.5 70 - 100
13.2 0 - 5
2.36 0 -1
8.4.2 QUALITY ASSURANCE
The drainage aggregate layer shall have permeability greater than 1 x 10-3 m/s. The Contractor shall
supply a 20 kg sample of the proposed material, accompanied by a copy of particle size distribution
test results from a NATA registered laboratory at least 10 days prior to commencement of
construction. The particle size distribution test shall be conducted in accordance with AS 1289:3.6.
Soil classification tests.
8.4.3 PLACEMENT AND COMPACTION METHODOLOGY
The Contractor shall notify the Superintendent at least 48 hours prior to placement of aggregates.
Trafficking will only be permitted over the surface of the aggregate placed to the specified thickness,
using plant as approved by the Superintendent. The following measures will be adopted during
placement:
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 47
The leachate drainage material shall be placed and spread in a layer of 300 mm minimum
thickness;
Suitable equipment shall be used for spreading the aggregate, with a maximum allowable
ground contact pressure of 50 kPa, swamp dozer or Positrack machines only;
The equipment shall not be allowed to turn or screw on a tight radius over the emplaced
drainage aggregate;
The spread aggregate layer shall form a level surface;
Surcharge over the leachate pipes shall be in accordance with Drawing AL-WA-015;
The Contractor shall consider the temperature effects, bearing load from haulage and
spreading equipment, material placement techniques and geomembrane waves to reduce
the risk of damage to the previous works;
Any damage to the HDPE geomembrane due to the result of aggregate being pushed out
shall be repaired by the Contractor at no cost to the Principal;
The Contractor shall provide a Work Method Statement for approval by the Superintendent
prior to commencement of aggregate placement. The Work Method Statement shall outline
the measures implemented to prevent geomembrane waves/wrinkling, stress and damage;
and
The Work Method Statement shall also include the type and weight of the equipment to be
used, along with the methodology of placing the aggregate.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 48
9 SEPARATION GEOTEXTILE
A separation layer will be placed over the drainage aggregate layer and will serve as a separation
layer between the waste and the leachate drainage system. The separation layer shall be a non-
woven polyester or polypropylene geotextile.
9.1 MATERIAL SPECIFICATION
The separation geotextile will have the typical properties described in Table 9.
Table 9: Separation Geotextile Properties
Property Unit Value Test
Trapezoidal Tear Strength N > 390 AS 3706.3
CBR Bust Strength N > 2,650 AS 3706.4
Grab Tensile Strength N > 1,000 AS 2001.2.3
Pore Size Microns > 100 AS 3706.7
Permeability m/s > 3.3 x 10-3 AS 3706.9
UV Resistance % > 70 ASTM D4355
9.2 QUALITY ASSURANCE
The following confirmation documents shall be provided to the Superintendent:
The Contractor shall provide the Superintendent with a quality assurance certificate from
the geotextile manufacturer for each roll of geotextile delivered;
The quality assurance certificate shall contain properties mentioned in the above Table as a
minimum;
Geotextiles will be certified needle free and free from other flaws which may have an
adverse effect on the physical or mechanical properties of the product; and
The thread used for stitching shall be polymeric with chemical and UV light resistant
properties greater than the geotextile.
9.3 STORAGE AND HANDLING
All delivered geotextile separation materials will be stored on level ground, free from any water
logging or drain paths and not more than three (3) rolls high. Appropriate lifting methodology shall
be used to prevent any damage while handling.
Placement of geotextile separation layers shall be carried out in accordance with the manufacturer’s
recommendation, details of which shall be provided to the Superintendent for approval. The
following measures will be adopted during placement:
A predetermined layout plan will be prepared to keep the overlap and buckling to a
minimum;
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 49
Only geotextile separation rolls inspected and approved by the Superintendent shall be
unrolled and used for placement;
The geotextile sheets will overlap by a minimum of 500 mm;
Joining of sheets shall be performed by stitching or heat bonding with an approved hot-air
device, or by stapling to adjacent geotextile sheets;
The longitudinal joints between panels shall be parallel to the slope gradient;
The geotextile protection materials shall not have cross joints on slopes steeper than 1:5;
and
Sand bags shall be used to hold the separation layers to prevent wind uplift during adverse
weather conditions.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 50
10 ACCESS ROAD
An access road is required to be constructed from the entry to the Vancouver Waste Disposal Facility
and the landfill as shown on Drawing AL-WA-005.
The access road shall be constructed on the prepared subgrade surface and consist of a 260 mm
thick granular pavement layer. The Superintendent shall approve the materials and prequalification
test results prior to placement in the Works.
10.1 SUBGRADE PLACEMENT
The subgrade shall be uniformly compacted. The characteristics of the subgrade layer for the access
road to be considered are:
Moisture content on placement to be between 3% dry and 2% wet of optimum moisture
content (using standard compaction); and
A minimum standard compaction during placement of 95%.
Acceptance criteria test methods for road subgrade and basecourse layer are outlined in Table 10.
Table 10: Access Road Subgrade Compliance Testing Acceptance Criteria
Item Test Method Acceptance Criteria
Density AS 1289 5.8.1
AS 1289 5.1.1
Minimum dry density ratio of 95% relative to Standard compaction
Moisture variation AS 1289 5.4.1 -3.0% to +2.0% of the Standard Optimum Moisture Content (SOMC)
10.2 BASECOURSE MATERIAL
For construction of the pavement layer, the minimum completed thickness shall be 260 mm. The
Contractor shall perform survey as part of its Quality Assurance Plan shall demonstrate that the
compacted layer thickness comply with the requirements of this Specification.
The basecourse material shall be mixed and moisture conditioned prior to compaction. The mixing
and moisture conditioning must be carried out to achieve a uniform composition and moisture
condition throughout each layer of placed material. The material shall be uniformly compacted using
a padfoot roller in near horizontal layers not exceeding 260 mm thickness after compaction.
Prior to any subsequent lifts of basecourse being placed the surface of the preceding lift shall be
tined to provide an interlocking bond between layers.
In accordance with the Main Roads Western Australia (MRWA) Specification 501 requirements for
basecourse materials, or as otherwise approved by the Principal, the characteristics and acceptance
criteria for the basecourse material are outlined below.
Acceptance criteria for the basecourse material particle size distribution in accordance with Table
501.08 of the MRWA Specification are outlined in Table 11.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 51
Table 11: Basecourse Material Particle Size Distribution Acceptance Criteria
Sieve Size
(mm)
% Passing by Mass
Target Grading
% Passing by Mass
Minimum and Maximum Limits
53 - 100
37.5 100 100
26.5 - 85 - 100
19.0 80 72 - 100
9.5 57 50 - 78
4.75 43 36 - 58
2.36 31 25 - 44
1.18 23 18 - 35
0.600 18 13 – 28
0.425 15 11 - 25
0.300 13 9 – 22
0.150 9 6 – 17
0.075 7 4 - 13
0.0135 4 2 - 9
Acceptance criteria for the basecourse material Atterberg limits in accordance with Table 501.09 of
the MRWA Specification are outlined in Table 12.
Acceptance of the proposed basecourse material or any variations from the material compliance
criteria, shall be reviewed and approved by the Superintendent.
Table 12: Basecourse Material Atterberg Limits Acceptance Criteria
Test Limits Test Method
Liquid limit Maximum 25% AS 1289
Linear Shrinkage Maximum 2.0% AS 1289
Compaction and moisture content acceptance criteria and test methods for road basecourse layer
are outlined in Table 13.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 52
Table 13: Basecourse Compaction and Moisture Content Compliance Testing Acceptance Criteria
Item Test Method Acceptance Criteria
Density AS 1289 5.8.1
AS 1289 5.1.1
Minimum dry density ratio of 98% relative to Standard compaction
Moisture variation AS 1289 5.4.1 -1.0% to +2.0% of the Standard Optimum Moisture Content (SOMC)
10.3 COMPACTION QUALITY ASSURANCE
The access road basecourse layer shall be compacted to a dry density of not less than 98% of
standard dry density as given in AS 1289 Methods for Testing Soils or by alternate method as
approved by the Superintendent. The Contractor shall conduct tests on compacted basecourse as
per the testing frequency specified.
The frequency of field density tests shall comply with Table 8.1 of AS 3798, as summarised in Table
3.
The final surface of the basecourse pavement layer shall be constructed with an tolerance of -0 mm
to +20 mm of the design levels.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 53
11 FENCING AND GATES
A 2.0 m high mesh and barbed wire security fence is to be installed around the landfill and leachate
pond perimeter as shown on Drawing AL-WA-020.
The fencing shall include vehicle and pedestrian access gates as shown on Drawing AL-WA-020.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 54
12 CONSTRUCTION DRAWINGS
Table 14: Table of Construction Drawings for Cell 1, Cell 2 and Leachate Pond
Drawing No Revision Description
AL-WA-001 A Cover Sheet, Drawing Schedule and Locality Plan
AL-WA-002 A Site Plan
AL-WA-003 A Overall Plan Layout
AL-WA-004 A Typical Road Cross Sections and Details
AL-WA-005 A Roadworks and Drainage Layout Plan
AL-WA-006 A Ultimate Landfill Earthworks Layout Plan
AL-WA-007 A Ultimate Landfill Top of Waste Surface Plan
AL-WA-008 A Ultimate Landfill Sections
AL-WA-009 A Landfill Cells 1 to 4 Earthworks Layout Plan
AL-WA-010 A Liner Details – Sheet 1 of 2
AL-WA-011 A Liner Details – Sheet 1 of 2
AL-WA-012 A Landfill Cell 1 Top of Waste Surface Plan
AL-WA-013 A Landfill Cell 2 Top of Waste Surface Plan
AL-WA-014 A Cells 1 and 2 Leachate Layout Plan
AL-WA-015 A Leachate Details – Sheet 1 of 2
AL-WA-016 A Leachate Details – Sheet 2 of 2
AL-WA-017 A Leachate Pond Layout Plan
AL-WA-018 A Leachate Pond Sections
AL-WA-019 A Access Road (MC01) Longitudinal Section
AL-WA-020 A Fence Layout Plan
AL-WA-021 A Groundwater Monitoring Bore Layout Plan
AL-WA-022 A Sediment and Erosion Control Layout Plan
AL-WA-023 A Sediment and Erosion Control Details
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 55
13 DESIGNERS RISK ASSESSMENT
Bowman & Associates has considered the construction practicalities and likely risks to be faced by
the contractor(s) executing the construction of the landfill and leachate pond at the Vancouver
Waste Disposal Facility.
The risk management approach outlined in this document is based on the framework in the
Australian Standard Risk Management (AS/NZS ISO 31000:2009) on which the Victorian EPA Licence
Assessment Guidelines (2010) have been based. We have also considered the Western Australian
Occupational Safety and Health Regulations (1996).
The below tables describe the risk ranking system used when assessing a particular activity for both
personnel and environmental risk using the Victorian EPA Assessments Guidelines structure.
Table 15: Qualitative Measures of Likelihood
Rating Indicator Description Frequency
5 Almost certain Multiple incidents have been recorded Is expected to occur almost all of the time
4 Likely Several incidents have been recorded Is expected to occur most of the time
3 Probable Some incidents have been recorded Might occur
2 Not likely Few recorded or known incidents Might occur but not expected to
1 Rare No recorded or known incidents Only expected to occur under atypical conditions
Table 16: Qualitative Measures of Consequence/Impact
Rating Indicator Description
5 Severe Human deaths, operations cause catastrophic off-site impacts, immense financial loss
4 Significant Extensive human injuries or illness, operations cause substantial off-site impacts, major financial loss
3 Medium Some health impacts to humans, operations cause some external impacts, large financial loss
2 Minor First aid treatment, operations cause minimal off-site impacts, small financial loss
1 Negligible Operations cause no injuries, negligible off-site impacts, and negligible financial loss
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 56
Table 17: Qualitative risk analysis matrix – Level of risk
Consequence
Likelihood
Almost
certain Likely Probable Not likely Rare
Severe V V V V H
Significant V V V H H
Medium V H H M M
Minor H H M L L
Negligible H M L L L
V = Very high risk; immediate action required
H = High risk; management required from senior staff
M = Medium risk; specify required management
L = Low risk; manage with standard operating procedure
Table 4 below describes some of the typical risks that have been identified during the design phase,
their impacts, assessed levels of risk and appropriate control measures that have been taken to
mitigate them to acceptable levels.
The risk assessment generally covers the following site construction and infrastructure works:
Earthworks (Excavation and Filling);
Construction of landfill access road;
Construction of swale drains and installation of stormwater culverts; and
Construction of the geosynthetic lining systems.
This list is by no means exhaustive, as many risks are a function of the construction methods and
techniques employed by the construction contractor(s), and as such cannot be clearly defined during
the design phase.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 57
Table 18: Risk Assessment - Construction Activities
Construction Element
Description of Risk Potential Impacts Likelihood /
Frequency Consequence
Severity Rating Level of risk Design Control Measures
General
General Travel of personnel to and from the site.
Extensive human injuries.
2 4 High Co-ordination between construction and site operations contractors.
Awareness of all site users, standard operation procedures and use of appropriate visibility gear.
General Contamination of site with hydrocarbons or polluted water.
Polluted water source.
2 2 Low The storage and handling of chemicals and fuels will be in accordance with the Dangerous Goods Safety (Storage and Handling of Non-explosives) Regulations 2007 and Australian Standard AS 1940 The storage and handling of flammable and combustible liquids.
Spill response established in Landfill Management Plan.
Water discharge procedure described in Landfill Management Plan.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 58
Construction Element
Description of Risk Potential Impacts Likelihood /
Frequency Consequence
Severity Rating Level of risk Design Control Measures
General Stormwater event - excessive rainfall
Erosion of partially completed construction works, wash out of road or temporary works.
3 2 Medium Design has considered storm events and has allowed adequate drainage along roads and hardstand areas.
Stormwater culverts have been designed for stormwater events.
Contractor(s) to employ temporary stormwater control during works as per the specification.
Clearing and Stripping
Stripping Personnel struck by machinery
Serious injury to human.
3 4 Very High Effective communication between onsite personnel and machine operators as per site procedures.
UHF radios to be carried by site personnel and in every machine onsite.
Onsite toolboxes to inform site personnel of current works onsite.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 59
Construction Element
Description of Risk Potential Impacts Likelihood /
Frequency Consequence
Severity Rating Level of risk Design Control Measures
Earthworks
Earthworks Injury due to buried services such as gas and power.
Unlikely if correct procedures are followed.
2 4 High Contractor required to ‘dial before you dig’ and locate services prior to commencement of works.
Initial works will be on previously developed land, underground services will be recorded as installed.
Earthworks Rollover of plant equipment.
Injury or death of Plant operator or bystander.
2 4 High Design batter slopes at maximum 1:2 grade.
Design calls for no deep excavation or steep grades.
Contractors are responsible for safe operation of vehicles.
Earthworks Personnel falling into excavated holes or trenches.
Injury from a fall or ledge collapse.
2 3 Medium No deep excavations or high ledges in the designed landform.
Contractor(s) expected to using bunting or flagging for temporary hazards in line with their own Occupational Health and Safety procedures.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 60
Construction Element
Description of Risk Potential Impacts Likelihood /
Frequency Consequence
Severity Rating Level of risk Design Control Measures
Earthworks Machinery falling into excavated holes, trenches or large excavations.
Machinery or personnel injury from fall.
2 3 Medium No deep excavations or high ledges in the designed landform.
Contractor(s) expected to using bunting or flagging for temporary hazards in line with their own Occupational Health and Safety procedures.
Earthworks Personnel struck by machinery
Serious injury to bystander.
3 4 Very High Effective communication between onsite personnel and machine operators as per site procedures.
UHF radios to be carried by site personnel and in every machine onsite.
Onsite toolboxes to inform site personnel of current works onsite.
Earthworks Radiation exposure from Nuclear Density Soil Gauge.
Low powered instrument, single dose no impact.
1 1 Low Contractor will employ an appropriately NATA accredited soil laboratory.
Site Infrastructure
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 61
Construction Element
Description of Risk Potential Impacts Likelihood /
Frequency Consequence
Severity Rating Level of risk Design Control Measures
Cranes
Truck Lifters
Manitou
Use of machinery to lift and place site facilities
(for example office blocks, water tanks, Generator, concrete culverts etc.)
Head trauma from falling objects.
4 4 Very High Materials to be lifted using correct lifting points and with suitability sized crane or lifting equipment.
No personnel to be positioned under lifting area or in front of moving lifting machinery.
Manual handling
Personnel injury when handling or lifting objects.
Injury/strains from incorrect lifting techniques.
4 2 High Current manual handling techniques.
Two or more person lifts where required.
Heavy items to be lifted or carried by appropriate lifting equipment.
Site traffic Vehicle / machinery being struck or collisions.
Vehicle or machinery collisions.
3 3 High Traffic management plan to be in place during construction works.
Designated parking areas for truck and light vehicles.
All contractors to be inducted.
Regular toolbox talks.
Entrance road and internal roads designed to suit construction and operational traffic, with good lines of sight and suitable road widths.
Landfill Cell 2 Construction
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 62
Construction Element
Description of Risk Potential Impacts Likelihood /
Frequency Consequence
Severity Rating Level of risk Design Control Measures
Lifting Geosynthetic rolls
Use of Manitou to lift and place geosynthetic rolls.
Head trauma from falling objects, hit by moving machinery.
3 4 Very High Materials/rolls to be lifted using correct lifting points and with suitability sized lifting equipment.
No personnel to be positioned under lifting area or in front of moving lifting machinery.
Liner Installation - HDPE
Personnel injury when deploying HDPE geomembrane liner.
Slips, trips and falls, or injury due to incorrect lifting technique.
3 2 Medium Installer must comply with manufacturers guidelines.
Installer must develop a work method statement for safe roll deployment.
Liner is not to be deployed in windy conditions.
Liner Installation - HDPE
Personnel injury when traversing HDPE liner on batters and in sump.
Minor sprains. 4 2 High HDPE liner is designed to be smooth textured facing up.
Rope ladders to be used on batters.
Liner Installation - HDPE
Personnel injury when welding HDPE liner.
Minor burns from extrusion equipment or cuts from knife use.
4 2 High Amount of welding required minimised by panel layout.
Main joins performed with automatic wedge welder, limiting extrusion welding requirement.
Test welds required to ensure operator proficiency.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 63
Construction Element
Description of Risk Potential Impacts Likelihood /
Frequency Consequence
Severity Rating Level of risk Design Control Measures
Liner Installation - Cushion Geotextile
Personnel injury when deploying the rolls of cushion geotextile material.
Slips, trips and falls, or injury due to incorrect lifting technique. Minor burns from heat bonding panels together.
4 2 High Design liner orientation (long seam down slope) reduces work required on sloping ground.
Preceding liners are maintained free of debris which may cause injury.
Leachate Collection System - HDPE pipes
Personnel injury when installing HDPE pipes.
Manual handling injuries.
Burns from welding HDPE.
2 2 High Pipes to be handled in accordance with Australian Standard AS2033 - Installation of polyethylene pipe systems.
Appropriately qualified pipe welding technician to perform welding activities.
Leachate collection system - HDPE pipes
Use of hand tools or power equipment for HDPE pipe drilling
Manual handling injuries and power tool injuries.
3 3 High Contractor will employ appropriately trained personnel to undertake these tasks.
Drilling equipment to be checked prior to use.
Leachate Collection System - Aggregate
Personnel injury when placing leachate drainage aggregate
Trip, slip and falls or being struck by machinery.
3 2 Medium Contractor will employ appropriately trained personnel to undertake these tasks.
Effective communication between onsite machinery placing aggregate and site contractors working within cell footprint.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 64
Construction Element
Description of Risk Potential Impacts Likelihood /
Frequency Consequence
Severity Rating Level of risk Design Control Measures
Separation Geotextile Installation
Personnel injury when deploying the rolls of separation material.
Slips, trips and falls, or injury due to incorrect lifting technique.
Minor burns from heat bonding panels together.
4 3 High Design liner orientation (long seam down slope) reduces work required on sloping ground.
The aggregate material is placed as a smooth working surface with surcharge over the pipes.
Construction Specification - Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 65
14 CONSTRUCTION QUALITY ASSURANCE PLAN
April 24, 2018
Environmental Engineering Consultants
Waste Management Specialists Tel: 0402 373 582 www.bowmanassociates.com.au PO Box 2059, ROSSMOYNE WA 6148
CONSTRUCTION QUALITY ASSURANCE PLAN – VANCOUVER WASTE DISPOSAL FACILITY
This document provides a guide to the Principal and Superintendent to manage the quality control
processes during construction of Cells 1 and 2 in accordance with the Specification, Design Drawings,
Landfill Licence and the Vic EPA BPEM guidelines.
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 1
Blank page
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 2
DOCUMENT CONTROL
Version Date Issued Prepared By Approved By Approved Signature
1 12.04.18 B Bowman B Bowman
DOCUMENT DISTRIBUTION
Version Type Format Issued to Organisation
1 Electronic .pdf Martin
Shuttleworth Vancouver Waste Services
FILE NAME
180412 BB Vancouver Landfill CQA Plan.docx
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 3
Blank page
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 4
TABLE OF CONTENTS
1 General ............................................................................................................................................ 6
1.1 Acronyms ................................................................................................................................ 6
2 Definitions ....................................................................................................................................... 7
3 Introduction .................................................................................................................................... 8
4 Preliminaries ................................................................................................................................... 8
4.1 Codes and Standards .............................................................................................................. 8
4.2 Landfill Location ...................................................................................................................... 9
4.3 Site Licence ............................................................................................................................. 9
4.4 Proposed Cell Design .............................................................................................................. 9
4.5 Purpose of the Plan ................................................................................................................. 9
4.6 Precedence of Documents .................................................................................................... 10
4.7 Process and Responsibilities ................................................................................................. 10
4.8 Hold Points ............................................................................................................................ 10
4.9 Set Out and Survey Control ................................................................................................... 11
4.10 Design Drawings .................................................................................................................... 13
5 Quality Assurance Parameters and Performance Indicators ........................................................ 14
5.1 Subgrade Preparation ........................................................................................................... 14
5.2 Insitu Clay Layer .................................................................................................................... 15
5.3 HDPE Geomembrane Liner ................................................................................................... 16
5.4 Cushion Geotextile ................................................................................................................ 19
5.5 Leachate Collection System .................................................................................................. 20
5.6 Separation Geotextile ........................................................................................................... 24
5.7 Access Road........................................................................................................................... 25
5.8 Water Management .............................................................................................................. 26
6 CQA Compliance Report ............................................................................................................... 27
7 References .................................................................................................................................... 28
8 Appendix A - Corrective Action Request Form ............................................................................. 29
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 5
TABLES
Table 1 - Table of Construction Drawings for Cell 1, Cell 2 and Leachate Pond ................................... 13
Table 2- Subgrade CQAP Parameters and Performance Indicators ...................................................... 14
Table 3 - Insitu Clay Liner CQAP Parameters and Performance Indicators .......................................... 15
Table 4 - HDPE Geomembrane – Proposed Conformance Testing of Site Materials ........................... 16
Table 5 - HDPE Liner CQAP Parameters and Performance Indicators .................................................. 17
Table 6 - Cushion Geotextile Layer CQAP Parameters and Performance Indicators ............................ 19
Table 7 - Leachate Collection System CQAP Parameters and Performance Indicators ........................ 22
Table 8 - Separation Geotextile Layer CQAP Parameters and Performance Indicators ....................... 25
Table 9: Access Road CQAP Parameters and Performance Indicators ................................................. 26
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 6
1 GENERAL
1.1 ACRONYMS
AHD Australian Height Datum
AS Australian Standard
ASTM American Standard Test Method
BPEM EPA Victoria Best Practice Environmental Management Guidelines
CQAP Construction Quality Assurance Plan
DWER Department of Water and Environmental Regulation
Ha Hectare
HDPE High Density Polyethylene
ITP Inspection and Test Plan
NATA National Association of Testing Authorities
QA/QC Quality Assurance/Quality Control
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 7
2 DEFINITIONS
For the purpose of this Construction Quality Assurance Plan (CQAP) the following terms are defined.
Cell Fill area within a stage which is operational for a period of time.
Construction Quality Assurance Plan
Description of the requirements for the Works. This Document.
Construction Quality Assurance Engineer/Consultant
The representative appointed by the Principal to manage the quality assurance of the construction works.
Contract Legally binding agreement between the Principal and the Contractor for the provision of the Works.
Contractor Organisation or individual commissioned by the Principal to undertake the Works subject to the Specification and associated contract conditions as provided by the Principal.
Designer Bowman & Associates Pty Ltd.
Drawings Series of drawings setting out the lines and dimensions of the Works.
Hold Point Mandatory verification point beyond which the Works cannot proceed without approval by the Superintendent.
Landfill Footprint The area within the site used for waste placement.
Licence Amendment Conditions and approval issued by the Department of Water and Environmental Regulation authorising the Principal to proceed with the construction works.
Principal Vancouver Waste Services Pty Ltd (Vancouver)
Program of Works The schedule of tasks, milestones, dependencies and resource allocations developed by the Contractor.
Regulator Department of Water and Environmental Regulation (DWER).
Roof Tile Alignment A systematic design of overlapping materials in one direction.
Schedule of Rates Prices provided by the Contractor for quantities required for the Works.
Site Lot 102 on Plan 22860 located off Mindijup Road, Palmdale in the City of Albany.
Site Supervisor Representative of the Principal for the operation of the facility.
Specification A document that specifies in a complete, precise, verifiable manner, the requirements, design, behaviour, or other characteristics of a system, component, product, result or service.
Superintendent The representative appointed by the Principal to manage the project.
Works All activities undertaken by the Contractor for the execution of this Contract.
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 8
3 INTRODUCTION
Vancouver Waste Services Pty Ltd (Vancouver) is proposing to develop a putrescible landfill at Lot
102 Mindijup Road, Palmdale in the City of Albany, the facility shall be known as the Vancouver
Waste Disposal Facility.
4 PRELIMINARIES
The development and implementation of a Construction Quality Assurance Plan (CQAP) provides
assurance that the facility is to be constructed in accordance with the approved Licence for the
facility. The summary report which will be compiled after construction will provide a means of
demonstrating to the public and regulating authorities that the constructed liner meets its design
requirements.
The CQAP is to be used to verify:
Materials used comply with Specifications;
Quality Assurance procedures and testing results; and
Method of construction/installation is appropriate and, as a result, design requirements
have been met.
The CQAP provides a summary of the material/construction specifications, testing methods, testing
frequency, corrective action and provides for appropriate documentation procedures.
This CQAP shall be submitted to the DWER as part of the approvals process for the construction of
Cell 1 and Cell 2 at the Vancouver Waste Disposal Facility.
This CQAP has been prepared in general accordance with the EPA Victoria Best Practice
Environmental Management guidelines titled Siting, design, operation and rehabilitation of landfills
(August 2015) hereby referred to as the BPEM and the amended Landfill Licence conditions.
4.1 CODES AND STANDARDS
All work shall comply with the Codes, Standards and Regulations applicable in Western Australia. As
a minimum all work shall conform to the standards nominated in the Specification. In the case of a
dispute between codes, the Western Australian regulations take precedence.
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 9
4.2 LANDFILL LOCATION
The Vancouver Waste Disposal Facility is located approximately 52 km north east of Albany on Lot
102 on Plan 22860 located off Mindijup Road, Palmdale in the City of Albany. Lot 102 covers an area
totalling 584 hectares (ha) and has facilities for various types of waste disposal. The site is owned by
Martin James Shuttleworth.
4.3 SITE LICENCE
The Mindijup Rd Tyre Disposal Site operating Licence L7344/1998/10 was first issued in 1998 and
applies to the adjacent Lot 3 owned by Martin Shuttleworth.
The Licence has the following Categories:
Category 63: Inert landfill Class I accepting up to 500 tpa of used tyres; and
Category 67A: Compost manufacturing and soil blending with a licenced capacity of 12,000
tpa.
4.4 PROPOSED CELL DESIGN
The detailed design aspects of the landfill and leachate pond lining system include:
Compacted and proof rolled subgrade for baseliner;
Compacted and proof rolled subgrade and basecourse layer for access road;
Construction of embankments for the anchor trench and stormwater control;
Low permeability insitu clay layer; as a secondary containment system;
2.0 mm smooth/textured HDPE liner; as the primary containment system;
Cushion geotextile; to protect the HDPE from puncturing; and
Leachate collection system.
The design details for the landfill and leachate pond liner and construction details have been
provided in the Specification and Drawings.
4.5 PURPOSE OF THE PLAN
The purpose of this CQAP is to detail the testing methods and frequencies and quality assurance
(QA) procedures to construct the following landfill lining system and associates access road Works:
Subgrade Preparation (Section 5.1);
Insitu Clay Liner (Section 5.2);
High Density Polyethylene (HDPE) geomembrane liner (Section 5.3);
Cushion Geotextile (Section 5.4);
Leachate Collection System (Section 5.5);
Separation Geotextile (Section 5.6);
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 10
Access Road Construction (Section 5.7); and
Water Management (Section 5.8).
4.6 PRECEDENCE OF DOCUMENTS
This CQAP shall be used in conjunction with any Specification and Drawings for the Works and shall
be primarily used to assist the Contractor and the Superintendent with the construction verification
process during construction. Should there be any discrepancy between this CQAP and Specification
or Drawings, the Specification shall take precedence, followed by the Drawings.
4.7 PROCESS AND RESPONSIBILITIES
The Principal will be responsible for the day to day monitoring and construction management during
the project construction phase.
A suitably qualified Superintendent will be appointed to act on behalf of the Principal to provide
project management and quality assessment of the Works. The Superintendent will represent the
Principal (Vancouver) in all dealings with the Contractor and will be responsible for monitoring and
inspecting the Works. The Superintendent will also be responsible for ensuring that field and
laboratory testing is in accordance with this CQAP.
The Superintendent will inspect the Works at hold points identified within this CQAP. Typically these
hold points include the preparation of the subgrade, which form the insitu clay layer, and during the
placement of the HDPE liner. Where hold points are nominated, approval to recommence Works will
need to be provided by the Superintendent before any subsequent Works may be undertaken.
The nominated responsibilities listed in the CQAP may be undertaken and additional site inspection
completed by the Superintendent at their discretion. Where required by the Superintendent the
Corrective Action Requests (Appendix A) may be used to formally track the progress of non-
conformances and the rectification of such during construction.
When Works are completed to the satisfaction of the Superintendent, a Verification Report will be
submitted to the Superintendent by the Contractor.
The Superintendent or CQA Engineer will prepare a CQA validation report (Completion Report)
based on the completed Works and in association with any Specification and Drawings and the
Licence Amendment requirements. This report shall be provided to the DWER within one month of
the completion of the construction Works for Cell 1 to satisfy DWER requirements.
4.8 HOLD POINTS
This CQAP details milestones and hold points. The hold points have been marked in the construction
quality assurance parameter Tables provided below. Superintendent site inspections and/or
document review and subsequent approval for each hold point will be required prior to commencing
with the next stage of construction. The following hold points are minimum requirements only, and
additional inspections during the construction phase may be required at the Superintendent’s
discretion.
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 11
Hold points include but are not limited to the following:
Initial survey and setout of the Works;
Receipt and approval of construction Inspection and Test Plans (ITPs);
Receipt and approval of the Contractors work program, noise and dust plans, health and
safety plans and insurances (including sub-contractors);
When soft ground is encountered;
When hard ground is encountered;
Following preparation and proof rolling of all subgrade earthworks the Superintendent
shall inspect the finished surface for compliance with the requirements of the
Specification;
Proof rolling of the subgrade surface for the access road;
Placement and as constructed survey of the basecourse layer for the access road;
As constructed survey of the prepared earthworks subgrade in the landfill cells and
leachate pond and the internal shoulder of the excavated anchor trench;
Prior to any concrete pours;
At hold points to be nominated by the Superintendent based on the Contractor’s
proposed construction plan for the installation of the HDPE geomembrane liner and
cushion geotextile;
Anchor trench excavation prior to HDPE deployment;
Prior to covering the HDPE geomembrane with the cushion geotextile, the
Superintendent shall inspect the geomembrane surface and cross reference the
installers Quality Assurance/Quality Control documentation that seams, panels, defects
and repairs have been accurately recorded and QA destructive and non-destructive
testing has been completed; and
All other hold points defined in the Specification or as directed by the Superintendent.
The Contractor is to provide the Superintendent with 48 hours’ notice of an impending hold point. If
a Contractor proceeds to construct beyond the designated hold point without the Superintendent’s
inspection and/or without the Superintendent’s approval then the Superintendent may direct the
Contractor to uncover and remediate the Works to the hold point, at the Contractor’s expense.
4.9 SET OUT AND SURVEY CONTROL
The Contractor shall be responsible for setting out the Works and for ongoing survey control,
including construction of the liners to the grades, levels and locations shown on the Drawings.
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 12
The term "survey mark" used in this clause means a survey peg, bench mark, reference mark, signal,
alignment, level mark or any other mark used or intended to be used for the purpose of setting out,
checking or measuring the work under the Contract.
Unless otherwise required by the Contract, the Contractor shall preserve and maintain in their true
positions the survey marks provided by the Principal or by the Superintendent in accordance with
the Contract.
Should any survey mark be disturbed or obliterated, the Contractor shall immediately notify the
Superintendent and shall, unless the Superintendent otherwise determines, rectify such disturbance
or obliteration to the satisfaction of the Superintendent. Unless the disturbance or obliteration has
been caused by the Principal, his employees or agents, the cost of rectification shall be borne by the
Contractor.
4.9.1 ERRORS IN SETTING OUT
If at any time during the progress of the work under the Contract, any error is discovered in the
position, level, dimensions or alignment of any part thereof, the Contractor shall immediately on his
discovery of the error notify the Superintendent and shall, unless the Superintendent otherwise
directs, rectify the error. Unless the error has been caused by incorrect data issued by the
Superintendent, the cost of rectification shall be borne by the Contractor.
The Superintendent may check the setting out of the work under the Contract by the Contractor but
the fact that the Superintendent may have carried out such checks shall not relieve the Contractor of
any responsibility for the correct setting out of the work.
4.9.2 SITE SURVEY, AREA AND VOLUME CALCULATIONS
The Contractor shall engage a licensed surveyor to carry out survey control during the execution of
the Works.
Site survey shall be conducted on a maximum 20 m grid over the cell area suitable to define
earthworks volumes and areas including slopes to determine the location and levels.
The survey shall also include:
Surface at time of setout;
Top of the prepared subgrade layer including drainage grades;
Top of compacted basecourse layer for the access road;
Survey of all test locations for the geotechnical quality control testing program;
Survey of anchor trenches for Cell 1, Cell 2 and leachate pond;
Panel layout for HDPE geomembrane and location of any repairs to the geomembrane;
Survey of the leachate drainage system installed;
Top of aggregate drainage layer; and
Survey of all, fences, culverts, roads and embankments constructed as part of the Works.
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 13
The results of the site surveys shall be supplied to the Superintendent as plan Drawings at a scale of
1:500 on paper and in 3D AutoCAD format with locations and levels to an accuracy of + or – 20 mm
horizontal and + or – 20 mm vertical and 0.2 m contour interval (or as determined by the
Superintendent), within five (5) working days of the survey being undertaken.
Quantities shall also be calculated from the survey for the items shown in the Schedule of Rates.
Claims for payment must be substantiated by relevant survey information and quantity calculations.
Should the survey data be deemed to be inaccurate or contain discrepancies, the Principal shall
appoint an alternative licensed surveyor to check the surveys or quantities. The Contractor will be
liable for all costs associated with the survey checks that indicate errors in the Contractor’s original
survey data.
4.10 DESIGN DRAWINGS
The following Drawings of the Vancouver Waste Disposal Facility form part of the construction
documents and are referred to as the ‘Drawings’.
The Drawings include reference to the elevation benchmark and system, Australian Height Datum
(AHD), the layout plan, base elevation, grades and geosynthetic liners.
Table 1 - Table of Construction Drawings for Cell 1, Cell 2 and Leachate Pond
Drawing No Revision Description
AL-WA-001 A Cover Sheet, Drawing Schedule and Locality Plan
AL-WA-002 A Site Plan
AL-WA-003 A Overall Plan Layout
AL-WA-004 A Typical Road Cross Sections and Details
AL-WA-005 A Roadworks and Drainage Layout Plan
AL-WA-006 A Ultimate Landfill Earthworks Layout Plan
AL-WA-007 A Ultimate Landfill Top of Waste Surface Plan
AL-WA-008 A Ultimate Landfill Sections
AL-WA-009 A Landfill Cells 1 to 4 Earthworks Layout Plan
AL-WA-010 A Liner Details – Sheet 1 of 2
AL-WA-011 A Liner Details – Sheet 1 of 2
AL-WA-012 A Landfill Cell 1 Top of Waste Surface Plan
AL-WA-013 A Landfill Cell 2 Top of Waste Surface Plan
AL-WA-014 A Cells 1 and 2 Leachate Layout Plan
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 14
Drawing No Revision Description
AL-WA-015 A Leachate Details – Sheet 1 of 2
AL-WA-016 A Leachate Details – Sheet 2 of 2
AL-WA-017 A Leachate Pond Layout Plan
AL-WA-018 A Leachate Pond Sections
AL-WA-019 A Access Road (MC01) Longitudinal Section
AL-WA-020 A Fence Layout Plan
AL-WA-021 A Groundwater Monitoring Bore Layout Plan
AL-WA-022 A Sediment and Erosion Control Layout Plan
AL-WA-023 A Sediment and Erosion Control Details
5 QUALITY ASSURANCE PARAMETERS AND PERFORMANCE INDICATORS
5.1 SUBGRADE PREPARATION
The subgrade for liner construction shall be excavated, filled and compacted to the required levels as
defined in the Specification and on the drawings, over the entire earthworks footprint to form a firm
base for placement of the HDPE. The subgrade beneath the landfill and leachate pond will form the
insitu clay liner.
The following parameters and performance indicators shall be checked and used as a guide, to
ensure and confirm that the landfill and leachate pond subgrade has been constructed and achieves
the requirements of the Specification and Drawings.
Table 2- Subgrade CQAP Parameters and Performance Indicators
Item Parameter Frequency Responsibility Performance
Indicator
1 Inspection of subgrade surface for soft spots and for shape and grading of surface
Prior to placement of HDPE
Superintendent Firm surface with no significant rutting or heaving. Grade over the surface is typically consistent (Hold Point)
2 Review of test results for subgrade
Completion of subgrade construction
Superintendent Test results met specification requirements
3 Survey of top of subgrade by licenced surveyor
Prior to placement of HDPE
Contractor Excavation and depths as specified
(Hold Point)
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 15
Item Parameter Frequency Responsibility Performance
Indicator
4 Review of survey information
Prior to placement of HDPE
Superintendent
Survey of an appropriate density of reading and adequate coverage
(Hold Point)
5.2 INSITU CLAY LAYER
The insitu clay subgrade shall be used as the clay liner beneath the landfill and leachate pond. The
Contractor shall prepare the surface to the grades shown on the Drawings. Areas that have been
over excavated or removed as soft ground require filling to meet design levels shall be filled using
similar materials to those of the subgrade.
The surface of the clay subgrade shall be uniformly compacted using a 12 tonne pad foot roller or
greater.
The Contractor shall verify the integrity of the clay liner by carrying out testing in a NATA Registered
laboratory. The frequency of testing shall be in accordance with the Specification. The results of the
testing shall be provided to the Superintendent, and approved by the Superintendent, prior to the
placement of the HDPE geomembrane liner.
The following parameters and performance indicators shall be checked and used as a guide to
confirm that the insitu clay layer has been constructed to the requirements of the Specification and
Drawings.
Table 3 - Insitu Clay Liner CQAP Parameters and Performance Indicators
Item Parameter Frequency Responsibility Performance
Indicator
1 Inspection of the subgrade/insitu clay layer during the trimming and compaction process
Prior to CQA testing
Superintendent Visual inspection of surface of subgrade/insitu clay layer
2 Inspection of CQA test data from the NATA Registered laboratory
Prior to survey of the surface of the insitu clay layer
Superintendent Confirmation that insitu clay layer meets specification
3 Inspection of insitu clay layer surface for imperfections
Prior to and during HDPE installation, entire subgrade surface to be inspected
Superintendent Visual inspection to confirm surface is smooth and firm, without irregularities, hollows or shrinkage cracks and free of loose stones and other unsuitable materials
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 16
Item Parameter Frequency Responsibility Performance
Indicator
4 Inspection of Insitu clay liner surface for defects and surface irregularities
During HDPE installation
Superintendent Visual inspection during HDPE installation
5.3 HDPE GEOMEMBRANE LINER
The HDPE geomembrane liner is installed over the insitu clay layer and under a layer of protective
cushion geotextile. The contactor shall use a qualified experienced geomembrane installation
specialist (Installer) to construct the geomembrane liner. The Installer shall perform all works
described in the Specification and provide all necessary QA/QC documentation. The Contractor is
responsible for all aspects of the Installer’s work.
The Contractor shall be responsible for all QA/QC of the transportation and installation of the
geomembrane. This shall include all preparations for the undertaking of inspections. Inspected
processes shall include delivery, handling and storage, placement, joining and repairs. The
geomembrane should generally be installed and tested under the recommended QA/QC guidelines
provided by the geomembrane manufacturer.
The visual inspection of the material shall be undertaken during the lining works by the CQA
engineer or the Superintendent.
Table 4 - HDPE Geomembrane – Proposed Conformance Testing of Site Materials
Item Property Standard Frequency Minimum Value
Start-up test weld Welding Equipment
Start of works daily and whenever the welding equipment is shut-off for more than 3 hours. Also after significant changes in weather conditions.
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 17
Item Property Standard Frequency Minimum Value
Weld Conditions
Test weld strips will be required whenever personnel or equipment are changed and/or wide temperature fluctuations are experienced. Minimum 1.5m continuous seam.
Destructive weld testing
Onsite, hand tensiometer in peel and shear
ASTM D6392 1 test per 150 m of weld (minimum)
Peel: 450 N/25mm
Shear; 690 N/25mm
Non-Destructive Weld Testing
Air pressure test
ASTM D5820 All seams over full length
Observed, validated and recorded by the consultant
Vacuum box test
ASTM 5641 Presence/absence of bubbles
Visual Inspection Tear, punctures, abrasions, cracks, indentations and thin spots
Every roll N/A
The following parameters and performance indicators shall be checked and used as a guide, to
confirm the geomembrane liner has been constructed to the requirements of the Specification and
Drawings.
Table 5 - HDPE Liner CQAP Parameters and Performance Indicators
Item Parameter Frequency Responsibility Performance Indicator
1 Submission of the manufacturers QA/QC documentation and independent compliance test results
Prior to lining works commencing and per Specification
Installer/Contractor Review all data to confirm compliance with all items listed in the Specification
(Hold Point)
2 Inspection and recording of condition of materials when unloaded at the site
Upon arrival of materials
Contractor Visual inspection of incoming material and recording of condition when unloaded at the site, e.g. whether rolls are wrapped
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 18
Item Parameter Frequency Responsibility Performance Indicator
3 Documenting how materials are stored and when used
Prior to and during the installation process
Contractor Documentation kept up to date after inspection
4 Inspection of finished insitu clay layer surface to be lined
Prior to installing works commencing
Superintendent Surface free of stones, rocks and other loose material that may damage the HDPE liner
5 Inspection of geomembrane material surface for defects or damage
During and after installation, entire placed surface to be inspected
Superintendent Visual inspection to confirm no tears, punctures, abrasions, indentations, cracks, thin spots or other faults in the material
6 Recording of panel number, size, location, type and date of installation in log book and on as built drawing during installation
All panels Installer To be marked on each panel and recorded in a log book or other method prior to covering
7 Inspection of panel overlap to meet the specified requirements. Panels to be generally in a roof tile alignment
All panels Superintendent Specified overlap achieved and panels are overlapped
8 Test welds conducted by each welder prior to welding works
Prior to each new working period and every 5 hours thereafter
Installer Results of the test welds must meet the requirements of the Specification prior to welding
9 Panels shall be welded to adjacent panels, and seam number, date and time, welder’s name, welding apparatus number and temperature shall be recorded
All welds Installer Visual inspection and welds to be marked near each seam and recorded in a log book or other method prior to covering
10 All defects and damage to the liner shall be repaired. Each repair number and details as per panels and seams shall be recorded
All defects/damage Installer Any defects/damage shall be marked for repair or patched immediately. Patch numbers will be marked on or near the patch and recorded in a log book or other method prior to covering
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 19
Item Parameter Frequency Responsibility Performance Indicator
11 Non destructive testing of primary and secondary welds to be verified and recorded
All welds Installer Testing shall be undertaken until it is verified that the welds conform with the specified requirements. All results shall be marked near the weld and recorded in a log book prior to covering
12 Destructive testing to be undertaken on primary welds to be verified, recorded and independently tested
One sample per 150 m of primary weld completed
Installer
Testing results shall confirm compliance with the specified requirements. Each test to be individually marked and recorded
13 The liner material shall be secured in anchor trenches
In all areas indicated on the Drawings
Superintendent Liner material extends into the trench and along the base
5.4 CUSHION GEOTEXTILE
The Contractor shall be responsible for all QA/QC of the transportation and installation of the
cushion geotextile. This shall include all preparations for the undertaking of inspections. Inspected
processes shall include delivery, handling and storage, placement, joining and repairs.
The geotextile will be used; as a protection cushion layer placed over the installed geomembrane
liner.
The following parameters and performance indicators shall be checked and used as a guide to
confirm that the geotextile layer has been constructed to the requirements of the Specification and
Drawings.
Table 6 - Cushion Geotextile Layer CQAP Parameters and Performance Indicators
Item Parameter Frequency Responsibility Performance Indicator
1 Submission of the manufacturer’s QA/QC documentation
Prior to lining Works commencing and as per Specification
Contractor Review all data to confirm compliance with all items listed in the Specification
(Hold Point)
2 Inspection and recording of condition of materials when unloaded at the site
Upon arrival of materials
Contractor Visual inspection of incoming material and recording of condition when unloaded at the site, e.g. whether rolls are wrapped
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 20
Item Parameter Frequency Responsibility Performance Indicator
3 Documenting how materials are stored and when used
Prior to and during the installation process
Contractor Documentation kept up to date after inspection
4 Inspection of geotextile material surface for defects or damage
During and after installation
Superintendent Visual inspection to confirm no tears, punctures, holes or other faults in the material
5 Inspection of finished HDPE surface to be lined
Prior to installing works commencing
Superintendent Surface free of stones, rocks and other loose material that may damage the geomembrane liner
6 Inspection of panel overlap to meet the specified requirements
All overlaps Superintendent Specified overlap achieved and panels are overlapped in the direction of flow
7 All defects and damage to the geotextile shall be repaired as per the specified requirements
All defects Contractor Visual inspection confirming patching or panel replacement as per the specified requirements
8 All panels joined to adjacent panels using approved method in accordance with the specified requirements
All panels/joins Contractor All joins have been established
9 Geotextile shall be secured in anchor trenches
In all areas indicated on the Drawing
Contractor Material extends into the trench and across the base of the trench, or as otherwise requested in the Specification
10 Inspection of geotextile anchoring before and after backfilling has occurred using approved material
In all constructed trenches
Superintendent Trenches are filled and compacted as described in the Specification
(Hold Point)
5.5 LEACHATE COLLECTION SYSTEM
The leachate collection system is comprised of a series of elements, these include:-
Leachate Sump and Leachate Extraction Pipes;
Concrete Anchor Block;
Leachate Collection Pipework;
Leachate Drainage Aggregate; and
Separation Geotextile.
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 21
The leachate collection systems pipework consisting of perforated leachate pipes shall be installed
over the placed cushion geotextile layer as per the Drawings. The aggregate shall be placed on the
floor and in the leachate sump and mounded over the pipework as per the Drawings.
Pipe dimensions and specifications are detailed in the Drawings and Specifications.
The following parameters and performance indicators shall be checked and used as a guide, to
confirm the landfill leachate collection system has been constructed to the requirements of the
Specification and Drawings.
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 22
Table 7 - Leachate Collection System CQAP Parameters and Performance Indicators
Item Parameter Frequency Responsibility Performance Indicator
Leachate Sump and Anchor Block
1 Submission of documentation for concrete anchor block and leachate sump pipework
Prior commencement of Works
Contractor Compliance with Specification
2 Inspection of liner surface
Prior to installation of Reinforcement
Superintendent Compliance with Specification
(Hold Point)
3 Inspection prior to pouring concrete
Prior to concrete placement
Superintendent Compliance with Specification
(Hold Point)
4 Survey of the concrete anchor block by licensed surveyor
Prior to completion of Works
Contractor Size and thickness in accordance with the Drawings
(Hold Point)
5 Inspection of leachate sump including perforation size
Prior to placement Superintendent Compliance with Specification and Drawings
6 Inspection of placed leachate pipework in sump
After placement Superintendent Compliance with Specification and Drawings
Leachate Collection Pipework
1 Submission of QA/QC documentation for proposed leachate collection pipe system including manufacturer and pipe properties
Prior to commencement of Works
Contractor Compliance with Specification and Drawings
(Hold Point)
2 Inspection of pipe type and size
All pipes Superintendent Compliance with Specification and Drawings
3 Inspection of the inside of perforated pipes to confirm drilling swarf has been removed
All perforated pipes Superintendent Pipes are free of dirt, debris and drilling swarf prior to installation
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 23
Item Parameter Frequency Responsibility Performance Indicator
4 Inspection of leachate collection pipe and header leachate collection pipe alignment and spacing
During installation and prior to connecting
Superintendent All leachate pipes to be HDPE pipe in accordance with the sizes and positioning described in the Specification and Drawings
5 Inspection of leachate collection and header leachate collection drilling pattern
All pipes Superintendent Pipes have been drilled in accordance with the drawings and are clean, free of drill swarf, dirt and debris
6 Inspection of pipe welding and jointing
All welds Superintendent Pipes to be connected via extrusion welding, butt welding or electrofusion to the specified requirements
7 QA certification of all welds
During installation Contractor Each weld carried out in compliance with manufacturers recommendations
8 Survey of leachate pipe alignment by licensed surveyor
Prior to aggregate installation
Contractor Pipes positioned in accordance with the Drawings and verification recorded as invert levels of pipes
9 Inspection to ensure that pipes are placed on even bed
All pipes sufficiently supported prior to placement of aggregate
Superintendent All pipe work adequately supported
(Hold Point)
Leachate Drainage Aggregate
1 Review of prequalification test results for aggregate material
Prior to delivery and/or prior to placement over the pipes
Superintendent Test results met Specification requirements
(Hold Point)
2 Inspection of leachate drainage aggregate
Upon delivery, during placement and following survey
Superintendent Compliance with Specification and Drawings
(Hold Point)
3 Survey of leachate drainage aggregate
At completion of placement
Contractor Review of survey information shows aggregate placement as per the Specification and Drawings including thickening of the aggregate over and around the leachate collection pipes
(Hold Point)
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 24
5.6 SEPARATION GEOTEXTILE
The Contractor shall be responsible for all QA/QC of the transportation and installation of the
separation geotextile. This shall include all preparations for the undertaking of inspections.
Inspected processes shall include delivery, handling and storage, placement, joining and repairs.
The geotextile will be used as a separation layer for the leachate drainage system, which includes
the pipework and aggregate and as a separation layer over the perforations on the concrete
leachate sump well.
The following parameters and performance indicators shall be checked and used as a guide to
confirm that the geotextile layer has been constructed to the requirements of the Specification and
Drawings.
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 25
Table 8 - Separation Geotextile Layer CQAP Parameters and Performance Indicators
Item Parameter Frequency Responsibility Performance Indicator
1 Submission of the manufacturer’s QA/QC documentation
Prior to lining Works commencing and as per Specification
Contractor Review all data to confirm compliance with all items listed in the Specification
(Hold Point)
2 Inspection and recording of condition of materials when unloaded at the site
Upon arrival of materials
Contractor Visual inspection of incoming material and recording of condition when unloaded at the site, e.g. whether rolls are wrapped
3 Documenting how materials are stored and when used
Prior to and during the installation process
Contractor Documentation kept up to date after inspection
4 Inspection of separation geotextile material surface for defects or damage
During and after installation
Superintendent Visual inspection to confirm no tears, punctures, holes or other faults in the material
5 Inspection of finished aggregate layer
Prior to installing Superintendent Aggregate free from organic matter, lumps of clay or fine-grained material
6 Inspection of panel overlap to meet the specified requirements
All overlaps Superintendent Specified overlap achieved and panels are overlapped in the direction of flow
7 All defects and damage to the separation geotextile shall be repaired as per the specified requirements
All defects Contractor Visual inspection confirming patching or panel replacement as per the specified requirements
8 All panels joined to adjacent panels using approved method in accordance with the specified requirements
All panels/joins Contractor All joins have been established
9 Geotextile shall be secured
In all areas indicated on the Drawings
Contractor Compliance with Specification and Drawings
5.7 ACCESS ROAD
The subgrade for the access road construction shall be excavated, filled and compacted over the
entire footprint to form a firm base for construction of the pavement layer. The pavement shall be
constructed on the prepared subgrade surface and consist of a 260 mm thick granular pavement
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 26
layer with gravel materials sourced by the Contractor. To provide a suitable granular material for the
access road construction, the material from the Works will need to be mixed thoroughly and tested
for conformance prior to placement. The Superintendent shall approve the materials and test results
prior to placement in the Works.
The following parameters and performance indicators shall be checked and used as a guide, to
ensure and confirm that the access road subgrade and pavement basecourse has been constructed
and achieves the requirements of the Specification and Drawings.
Table 9: Access Road CQAP Parameters and Performance Indicators
Item Parameter Frequency Responsibility Performance Indicator
1 Inspection of subgrade surface for soft spots and for shape and grading of surface
Prior to placement of basecourse layer
Superintendent Firm surface with no significant rutting or heaving. Grade over the surface is typically consistent
2 Survey of top of subgrade by licensed surveyor
Prior to placement of basecourse layer
Superintendent Excavation and depths as specified
3 Testing for particle size distribution and Atterberg Limits for gravel material
Prior to compaction of basecourse layer
Superintendent Compliance with the Specification
4 Compaction and moisture content testing for pavement layer
After placement and compaction of basecourse material
Superintendent Compliance with the Specification
5 Review of survey information
At completion of placement
Superintendent
Survey of an appropriate density of reading and adequate coverage
5.8 WATER MANAGEMENT
Any standing water shall be collected, diverted, drained or pumped away before works can
commence, to the satisfaction of the Superintendent. During construction, the Contractor shall
ensure that the site is free of all standing water and drains and bunds are to be constructed to
manage runoff.
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 27
6 CQA COMPLIANCE REPORT
Once the Superintendent is satisfied that the Cell 1 and leachate pond liner system and access road
for the landfill has been constructed appropriately, the Superintendent or CQA Engineer will prepare
a Construction Quality Assurance Validation Report to verify that the Works have been undertaken
in accordance with the DWER Licence, CQA Plan, Specification and Drawings.
The report shall include the results of surveys, inspections, material conformance test results, as-
constructed Drawings, monitoring records, soil testing and include justification for any deviations
from the project documents.
The Principal will provide the DWER with the Construction Quality Assurance Validation Report for
the Works within one month of the completion of the landfill works, to outline that landfill
construction was undertaken in accordance with the Licence and project requirements.
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 28
7 REFERENCES
EPA Victoria (2015) Best Practice Environmental Management guidelines: Siting, design, operation
and rehabilitation of landfills – BPEM (Publication 788.3, August 2015)
Construction Quality Assurance Plan – Vancouver Waste Disposal Facility
Prepared by Bowman & Associates Pty Ltd Page 29
8 APPENDIX A - CORRECTIVE ACTION REQUEST FORM
VANCOUVER WASTE SERVICES - VANCOUVER WASTE DISPOSAL FACILITY
LANDFILL CONSTRUCTION WORKS
CORRECTIVE ACTION REQUEST
No. ……………………….
Date of Issue
Description of Issue Specific Problem Identified Remedial Measure Proposed Remedial Measure
Performance Confirmation of Success of
Remedial Measure
Requested By
Issued To Date Completed Completed By Received By (Superintendent)
Approved By (Project Manager)