1400-1415 ddamulira sekitene grid connected solar pv p1 wed

Upload: lawrence-ddamulira

Post on 06-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    1/19

    MID YEAR PROJECT

    PRESENTATIONS

    Presentation by;

    1. Ddamulira Lawrence

    2. Sekitene Ronald

    Supervisors

    1. Mr. Rutalo Michael

    2. Prof. Lugujjo Eriabu

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    2/19

    PROJECT TITLE

    Installation of grid connected solar PV systems as a means

    of coping with load shedding.

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    3/19

    PROJECT BACKGROUND

    The Ugandan government continues to devise means

    of reducing the severity of Energy deficits.

    Only a small portion of the Hydro power potential

    estimated at over 2000MW has beentapped.(approximately 33%).

    Consumers need to find means of coping with the load

    shedding on an individual basis.

    Renewable energy sources are a major option.

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    4/19

    PROBLEM STATEMENT

    There is an energy deficit of at least 100MW and

    50MW during peak and off peak demand periods

    respectively according to UETCL.

    As a consequence of the energy deficits, the Utility

    Company Umeme is compelled to carry out scheduled

    load shedding .

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    5/19

    TYPICAL LOAD CURVE, UGANDA

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    6/19

    PROJECT JUSTIFICATION

    Ugandan power consumers need to come to terms with

    the existing state of affairs.

    Measures in place so far will not be able to alleviate

    the Energy deficit because increase in demand farexceeds growth in generation.

    The load growth is estimated at 10% per annum, with

    an approximate 17,000 new residential connections per

    annum as per 2010 according to Umeme

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    7/19

    PROJECT JUSTIFICATION

    Uganda is endowed with plenty of sunshine giving

    solar radiation of about 4-5 kWh/m2/day

    This level of insolation is quite favorable for all solar

    technology applicationsThe Ugandan government has a target of raising the

    renewable Energy usage to 61% by 2017.

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    8/19

    MAIN OBJECTIVE

    To optimize the design of grid connected solar P.V

    systems under Ugandan conditions.

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    9/19

    SPECIFIC OBJECTIVESTo establish the average power consumption of

    residential consumers for a given sample within a casestudy area.

    To size an appropriate grid connected solar P.V system

    basing on the average power consumption establishedfrom the case study area.

    To determine the overall initial capital investmentrequired for installation of the Grid connected solar

    P.V systems.To harmonize power being contributed by the solar P.V

    system with the grid in terms of frequency and voltage.

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    10/19

    METHODOLOGY

    Literature Survey

    Sizing the PV system suitable to supply the existing

    load

    Consultations with Ministry of Energy and Mineraldevelopment.

    Consultations with the department of meteorology for

    the up to date sunshine data

    Consultation with the main solar companies involvedin supply and installation of PV systems.

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    11/19

    EXPECTED RESULTSAn Optimum design of a grid connected solar P.V system.

    The initial capital investments required in the installation ofa particular size of grid connected solar P.V system for ahousehold.

    The possible reduction in the consumers monthly bill as aresult of the installation of the grid connected solar P.Vsystem.

    How the option of grid connected solar P.V systemcompares with other possible ways of coping with loadshedding in terms of cost, constraints and benefits.

    Recommendations as to best ways of realizing maximumefficiency of grid connected solar P.V systems underUgandan conditions.

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    12/19

    PROGRESS

    Covered most of the relevant literature

    Obtained a partnership with the Ministry of Energy

    and Mineral development to execute the project under

    supervision of Eng. Atwine Abdon.Established a case study residential area in Gayaza,

    Wakiso district.

    Established the average load demand from a sample of

    five homes in the case study area.

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    13/19

    TYPICAL SYSTEM DESIGNS

    1. Grid interactive only;

    y Mainly suitable in cases where utility outages are rare.

    2. Grid interactive with battery back up.

    y

    Can work well even for cases with common utilityblackouts, just like Uganda.

    y battery keeps critical load circuits in the house

    operating during a utility outage

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    14/19

    GRID INTERACTIVE ONLY

    BLOCK DIAGRAM

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    15/19

    SYSTEM WITH BATTERY BACKUP

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    16/19

    SIMPLE SYSTEM LAYOUT

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    17/19

    THE HOUSEHOLDS SAMPLED

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    18/19

    LOAD DEMANDHOME 1 HOME 2 HOME 3 HOME 4 HOME 5

    Lighting 277W 506W 714W 754W 205W

    Entertainment

    equipment

    602W 601W 574W 448W 2461W

    Heating

    equipment

    1695W 5500W 1790W 5545W 2100W

  • 8/2/2019 1400-1415 Ddamulira Sekitene Grid Connected Solar PV P1 Wed

    19/19

    TIMELINE