15-1scheduling operations scheduling chapter 8. 15-2scheduling the hierarchy of production decisions...

77
15-1 Scheduling Operations Scheduling Chapter 8

Upload: marjory-stafford

Post on 30-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-1 Scheduling

Operations SchedulingChapter 8

Page 2: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-2 Scheduling

The Hierarchy of Production The Hierarchy of Production DecisionsDecisions

The logical sequence of operations in factory planning corresponds to the sequencing of chapters in a production management text book.

All planning starts with the demand forecast. Demand forecasts are the basis for the top level (aggregate)

planning. The Master Production Schedule (MPS) is the result of

disaggregating aggregate plans down to the individual item level. Based on the MPS, MRP is used to determine the size and timing

of component and subassembly production. Detailed shop floor schedules are required to meet production

plans resulting from the MRP.

Page 3: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-3 SchedulingHierarchy of Hierarchy of

Production DecisionsProduction Decisions

Page 4: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-4 Scheduling

Scheduling: Establishes the timing of the use of equipment, facilities and human activities in an organization

Effective scheduling can yield

Cost savings

Increases in productivity

Improved customer satisfaction

Scheduling Scheduling

Page 5: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-5 Scheduling

SchedulingScheduling Techniques Techniques

Scheduling techniques are designed to disaggregate the master production schedule into time-phased daily or hourly activities.

A detailed production schedule must include when and where each activity must take place in order to meet the master schedule.

Page 6: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-6 Scheduling

Scheduling ActivitiesScheduling Activities Scheduling involves the following major activities:1. Routing (determining where the work is going to be done).2. Short-run capacity planning.3. Short-run machine, manpower and production scheduling.4. Determining the sequence of activities (determining when the

work is to be done).5. Dispatching (issuing the order to begin work).6. Controlling the progress of orders and monitoring the process to

determine that operations are running according to plan.7. Revising the schedule based on changes in order status of jobs,

material and/or capacity availability and various other reasons.8. Expediting (speeding the progress of the work order) late, critical

jobs.

Page 7: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-7 Scheduling

Elements of SchedulingElements of SchedulingElements of Scheduling Problems:1.Job arrival patterns (static vs. dynamic). Dynamic arrival pattern

means that more jobs will arrive in the system during the time those currently in the system are being processed. In a static system, all jobs that will ever enter the system are known. Most job shops are dynamic.

2.Ratio of workers to machines (machine limited vs. labor limited environment).

3.Priority rules for scheduling.4.Flow patterns of jobs through the plant.

a. Flow shop: All jobs follow the same pattern of flow through the system. In a flow shop, routing is not typically a problem.b. Job shop: Each job follows its own specified pattern. Job shop is more difficult to analyze than the flow shop.

Page 8: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-8 Scheduling

Goals of Production SchedulingGoals of Production Scheduling

High Customer Service: on-time delivery

Low Inventory Levels: WIP and FGI

High Utilization: of machines and labor

Page 9: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-9 Scheduling

Meeting Due Dates – MeasuresMeeting Due Dates – Measures Service Level:

Used typically in make to order systems.

Fraction of orders which are filled on before their due dates.

Fill Rate: Used typically in make

to stock systems. Fraction of demands met

from stock.

Lateness: Used in shop floor control. Difference between order due date and

completion date. Average lateness has little meaning. Better measure is lateness variance.

Tardiness: Used in shop floor control. Is equal to the lateness of a job if it is

late and zero, otherwise. Average tardiness is meaningful but

unintuitive.

Page 10: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-10 Scheduling

Basic DefinitionsBasic Definitions Throughput (TH): for a line, throughput is the average quantity of good (non-

defective) parts produced per unit time. Work in Process (WIP): inventory between the start and endpoints of a product

routing. Raw Material Inventory (RMI): material stocked at beginning of routing. Finished Goods Inventory (FGI): material held in inventory prior to shipping to

the customer. Cycle Time (CT): time between release of the job at the beginning of the routing

until it reaches an inventory point at the end of the routing.

Makespan: The total amount of time to process a fixed number of jobs.

Little’s Law: TH = WIP/CT WIP=TH*CT (L=λw) where λ=TH and w=CT

Page 11: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-11 Scheduling

Reducing WIP and Cycle TimeReducing WIP and Cycle Time

Less WIP Equals Shorter Cycle Times (Little’s Law)

Shorter cycle time means:

Less WIP

Better responsiveness

All of which reduce costs and improve sales revenue

Page 12: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-12 Scheduling

Classic Scheduling – Assumptions Classic Scheduling – Assumptions

MRP/ERP: Benefits – Simple paradigm, hierarchical

approach.

Problems – MRP assumes that lead times are an attribute

of the part, independent of the status of the shop.

MRP uses pessimistic lead time estimates.

Page 13: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-13 SchedulingClassic Scheduling – Assumptions Classic Scheduling – Assumptions (cont.)(cont.)

Classic Scheduling: (only classic in academia) Benefits – “Optimal” schedules

Problems – Bad assumptions. All jobs available at the start of the problem. Deterministic processing times. No setups. No machine breakdowns. No preemption. No cancellation.

Page 14: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-14 Scheduling

Objectives in Job Shop SchedulingObjectives in Job Shop Scheduling

Meet due dates Minimize work-in-process (WIP) inventory Minimize average flow time Maximize machine/worker utilization Reduce set-up times for changeovers Minimize direct production and labor costs

(note: that these objectives can be conflicting)

Page 15: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-15 SchedulingMeasures to Evaluate Performance of a Measures to Evaluate Performance of a

Scheduling MethodScheduling Method Service Level: Fraction of orders filled on before their due

dates (used in make-to-order systems) Fill Rate: Fraction of demand that are met from inventory

without backorder (used in make-to-stock systems) Job Flow Time: Time elapsed from the release of a job

until it is completed. Lateness: Difference between completion time and due

date of a job (may be negative). Tardiness: The positive difference between the

completion time and the due date of a job. Makespan: Flow time of the job completed last.

Page 16: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-16 SchedulingMeasures to Evaluate Performance of a Measures to Evaluate Performance of a

Scheduling MethodScheduling Method Production Rate Utilization

Keep in mind that high utilization means high return on investment. This is good provided that the equipment is utilized to increase revenue. Otherwise, high utilization only helps to increase inventory, not profits.

Page 17: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-17 Scheduling

TerminologyTerminology

Flow shop: n jobs processed through m machines in the same sequence

Job shop: the sequencing of jobs through machines may be different, and there may be multiple operations on some machines.

Parallel processing vs. sequential processing: parallel processing means that the machines are identical, any job can be processed on any machine.

Page 18: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-18 Scheduling

Common Sequencing RulesCommon Sequencing Rules

FCFS. First Come First Served. Jobs processed in the order they come to the shop.

SPT. Shortest Processing Time. Jobs with the shortest processing time are scheduled first.

EDD. Earliest Due Date. Jobs are sequenced according to their due dates.

CR. Critical Ratio. Compute the ratio of processing time of the job and remaining time until the due date. Schedule the job with the largest CR value next.

Page 19: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-19 SchedulingSSchedulingcheduling S Service ervice OOperations perations Vs Vs

Manufacturing OperationsManufacturing Operations Scheduling service systems presents certain

problems not generally encountered in manufacturing systems. This is primarily due to:

1. The inability to store services

2. The random nature of customer requests

To avoid problems such as long delays, unsatisfied customers, service systems rely on appoinment systems and reservation systems.

Page 20: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-20 Scheduling

High-Volume SystemsHigh-Volume Systems

Flow system: High-volume system with Standardized equipment and activities

Flow-shop scheduling: Scheduling for high-volume flow system

Work Center #1 Work Center #2 Output

Page 21: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-21 Scheduling

High-Volume SystemsHigh-Volume Systems

Examples of high-volume products include autos, personal computers, televisons.

In process industries, examples include petroleum refining, sugar refining.

A major issue in design of high-volume (flow) systems is line balancing.

Page 22: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-22 SchedulingSuccess FactorsSuccess Factors in in High-Volume High-Volume SystemsSystems

Process and product design

Preventive maintenance

Rapid repair when breakdown occurs

Minimization of quality problems

Reliability and timing of supplies

Page 23: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-23 Scheduling

Intermediate-Volume SystemsIntermediate-Volume Systems

Outputs are between standardized high-volume systems and made-to-order job shops

The volume of output is not large enough to justify continuous production.

Examples include canned foods, paint and cosmetics.

Page 24: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-24 Scheduling

Intermediate-Volume SystemsIntermediate-Volume SystemsThe three basic issues in these systems are:

1.Run size, 2.Timing, and 3.Sequence of jobs

Economic run size:

2

'

kQ

h

h’ is defined as h’= h(1- λ/P)

Page 25: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-25 Scheduling

Scheduling Low-Volume SystemsScheduling Low-Volume Systems

Loading - assignment of jobs to process centers

Sequencing - determining the order in which jobs will be processed

Job-shop scheduling Scheduling for low-volume

systems with many variations in requirements

Page 26: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-26 Scheduling

Gantt Load ChartGantt Load Chart

Gantt chart - used as a visual aid for loading and scheduling

WorkCenter

Mon. Tues. Wed. Thurs. Fri.

1 Job 3 Job 42 Job 3 Job 73 Job 1 Job 6 Job 74 Job 10

Figure 15.2

Page 27: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-27 Scheduling

Infinite loading: Assigning jobs to work centers without considering the capacity of work center.

Finite loading: Takes into acccount the capacity of work center.

• Forward scheduling: Scheduling ahead from some point in time.

Backward scheduling. Scheduling backwards from due dates.

LoadingLoading

Page 28: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-28 Scheduling

28

LoadingLoading

Page 29: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-29 Scheduling

LOADING (LOADING (The Assignment ProblemThe Assignment Problem))

In many business situations, management needs to assign - personnel to jobs, - jobs to machines, - machines to job locations, or - salespersons to territories.

Consider the situation of assigning n jobs to n machines.

When a job i (=1,2,....,n) is assigned to machine j (=1,2, .....n) that incurs a cost Cij.

The objective is to assign the jobs to machines at the least possible total cost.

Page 30: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-30 Scheduling

The Assignment ProblemThe Assignment Problem

This situation is a special case of the Transportation Model and it is known as the assignment problem.

Here, jobs represent “sources” and machines represent “destinations.”

The supply available at each source is 1 unit And demand at each destination is 1 unit.

Page 31: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-31 Scheduling

The Assignment ProblemThe Assignment Problem

The assignment model can be expressed mathematically as follows:Xij= 0, if the job j is not assigned to machine i

1, if the job j is assigned to machine i

Page 32: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-32 Scheduling

The Assignment ProblemThe Assignment Problem

Page 33: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-33 Scheduling

The Assignment Problem Example The Assignment Problem Example Ballston Electronics manufactures small electrical

devices. Products are manufactured on five different assembly

lines (1,2,3,4,5). When manufacturing is finished, products are transported

from the assembly lines to one of the five different inspection areas (A,B,C,D,E).

Transporting products from five assembly lines to five inspection areas requires different times (in minutes)

Page 34: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-34 Scheduling

The Assignment Problem Example The Assignment Problem Example Ballston Electronics manufactures small electrical

devices. Products are manufactured on five different assembly

lines (1,2,3,4,5). When manufacturing is finished, products are transported

from the assembly lines to one of the five different inspection areas (A,B,C,D,E).

Transporting products from five assembly lines to five inspection areas requires different times (in minutes)

Page 35: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-35 Scheduling

The Assignment Problem ExampleThe Assignment Problem Example

Under current arrangement, assignment of inspection areas to the assembly lines are 1 to A, 2 to B, 3 to C, 4 to D, and 5 to E.This arrangement requires 10+7+12+17+19 = 65 man minutes.

Page 36: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-36 Scheduling

The Assignment Problem ExampleThe Assignment Problem Example Management would like to determine whether

some other assignment of production lines to inspection areas may result in less cost.

This is a typical assignment problem. n = 5 And each assembly line is assigned to each inspection area.

It would be easy to solve such a problem when n is 5, but when n is large all possible alternative solutions are n!, this becomes a hard problem.

Page 37: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-37 Scheduling

The Assignment Problem ExampleThe Assignment Problem Example Assignment problem can be either formulated as a

linear programming model, or it can be formulated as a transportation model.

However, An algorithm known as Hungarian Method has proven to be a quick and efficient way to solve such problems.

This technique is programmed into many computer modules such as the one in WINQSB.

Page 38: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-38 Scheduling

The Assignment Problem ExampleThe Assignment Problem Example

WINQSB solution for this problem is as follows:

Page 39: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-39 Scheduling

Hungarian Method ExampleHungarian Method Example

Step 1: Select the smallest value in each row.Subtract this value from each value in that row

Step 2: Do the same for the columns that do not have any zero value.

Page 40: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-40 Scheduling

Hungarian Method ExampleHungarian Method Example

If not finished, continue with other columns.

Page 41: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-41 Scheduling

Hungarian Method ExampleHungarian Method Example

Step 3: Assignments are made at zero values. Therefore, we assign job 1 to machine 1; job 2 to

machine 3, and job 3 to machine 2. Total cost is 5+12+13 = 30. It is not always possible to obtain a feasible

assignment as in here.

Page 42: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-42 Scheduling

Hungarian Method Example 2 Hungarian Method Example 2

Page 43: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-43 Scheduling

Hungarian Method Example 2Hungarian Method Example 2

A feasible assignment is not possible at this moment.

In such a case, The procedure is to draw a minimum number of lines through some of the rows and columns, Such that all zero values are crossed out.

Page 44: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-44 Scheduling

Hungarian Method Example 2Hungarian Method Example 2

The next step is to select the smallest uncrossed out element. This element is subtracted from every uncrossed out

element and added to every element at the intersection of two lines.

Page 45: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-45 Scheduling

Hungarian Method Example 2Hungarian Method Example 2

We can now easily assign to the zero values. Solution is to assign (1 to 1), (2 to 3), (3 to 2) and (4 to 4).

If drawing lines do not provide an easy solution, then we should perform the task of drawing lines one more time.

Actually, we should continue drawing lines until a feasible assignment is possible.

Page 46: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-46 Scheduling

SequencingSequencing

Sequencing: Determine the order in which jobs at a work center will be processed.

Workstation: An area where one person works, usually with special equipment, on a specialized job.

Page 47: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-47 Scheduling

SequencingSequencing n jobs on a Single Machine n jobs on a Single Machine

Priority rules:

Simple heuristics such as FCFS, SPT, DD, CR are used to select the order in which jobs will be processed.

CR= (Due Date – Current Time)/ Processing Time

Job time: Time needed for setup and processing of a job.

Page 48: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-48 Scheduling

Example: Sequencing RulesExample: Sequencing Rules

Use the FCFS, SPT, and Critical Ratio rules to sequence the five jobs below. Evaluate the rules on the bases of average flow time, average number of jobs in the system, and average job lateness.

(Due Date)

Job Processing Time Time to Promised Completion

A 6 hours 10 hours

B 12 16

C 9 8

D 14 14

E 8 7

Page 49: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-49 Scheduling

Example: Sequencing RulesExample: Sequencing Rules

FCFS Rule A > B > C > D > E

Processing Due Flow

Job Time Date Time Lateness

A 6 10 6 0

B 12 16 18 2

C 9 8 27 19

D 14 14 41 27

E 8 7 49 42

49 141 90

Page 50: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-50 Scheduling

Example: Sequencing RulesExample: Sequencing Rules

FCFS Rule Performance

Average flow time:

141/5 = 28.2 hours Average number of jobs in the system:

141/49 = 2.88 jobs Average job lateness:

90/5 = 18.0 hours

Page 51: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-51 Scheduling

Example: Sequencing RulesExample: Sequencing Rules

SPT Rule A > E > C > B > D

Processing Due Flow

Job Time Date Time Lateness

A 6 10 6 0

E 8 7 14 7

C 9 8 23 15

B 12 16 35 19

D 14 14 49 35

49 127 76

Page 52: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-52 Scheduling

Example: Sequencing RulesExample: Sequencing Rules

SPT Rule Performance

Average flow time:

127/5 = 25.4 hours Average number of jobs in the system:

127/49 = 2.59 jobs Average job lateness:

76/5 = 15.2 hours

Page 53: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-53 Scheduling

Example: Sequencing RulesExample: Sequencing Rules

Critical Ratio Rule E > C > D > B > A

Processing Promised Flow

Job Time Completion Time Lateness

E (.875) 8 7 8 1

C (.889) 9 8 17 9

D (1.00) 14 14 31 17

B (1.33) 12 16 43 27

A (1.67) 6 10 49 39

49 148 93

Page 54: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-54 Scheduling

Example: Sequencing RulesExample: Sequencing Rules

Critical Ratio Rule Performance

Average flow time:

148/5 = 29.6 hours Average number of jobs in the system:

148/49 = 3.02 jobs Average job lateness:

93/5 = 18.6 hours

Page 55: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-55 Scheduling

Example: Sequencing RulesExample: Sequencing Rules

Comparison of Rule Performance

Average Average Average

Flow Number of Jobs Job

Rule Time in System Lateness

FCFS 28.2 2.88 18.0

SPT 25.4 2.59 15.2

CR 29.6 3.02 18.6

SPT rule was superior for all 3 performance criteria.

Page 56: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-56 Scheduling

SequencingSequencing n jobs on two machines n jobs on two machines

Johnson’s Rule: technique for minimizing completion time for a group of n jobs to be processed on two machines or at two work centers.

Minimizes total idle time

Johnson’s Rule requires satisfying the following conditions:

Page 57: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-57 Scheduling

Johnson’s Rule ConditionsJohnson’s Rule Conditions

Job time must be known and constant

Job times must be independent of sequence

Jobs must follow same two-step sequence

Job priorities cannot be used

All units must be completed at the first work center before moving to second

Page 58: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-58 Scheduling

Johnson’s Rule Optimum SequenceJohnson’s Rule Optimum Sequence

1. List the jobs and their times at each work center

2. Find the smallest processing time. If it belongs to the first operation of a job schedule that job next, otherwise schedule that job last.

3. Eliminate the job from further consideration

4. Repeat steps 2 and 3 until all jobs have been scheduled

Page 59: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-59 Scheduling

Johnson’s Algorithm ExampleJohnson’s Algorithm Example

Data:

Iteration 1: min time is 4 (job 1 on M1); place this job first and remove from lists:

Job Time on M1 Time on M21 4 92 7 103 6 5

List 1 List 24 (1) 5 (3)6 (3) 9 (1)7 (2) 10 (2)

Page 60: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-60 Scheduling

Johnson’s Algorithm Example (cont.)Johnson’s Algorithm Example (cont.)

Iteration 2: min time is 5 (job 3 on M2); place this job last and remove from lists:

Iteration 3: only job left is job 2; place in remaining position (middle).

Final Sequence: 1-2-3

Makespan: 28

List 1 List 26 (3) 5 (3)7 (2) 10 (2)

Page 61: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-61 SchedulingGantt Chart for Johnson’s Algorithm Gantt Chart for Johnson’s Algorithm ExampleExample

Machine 1

Machine 2

Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

3

1 2 3

1 2

Short task on M1 to“load up” quickly.

Short task on M2 to“clear out” quickly.

Page 62: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-62 Scheduling

http://www.baskent.edu.tr/~kilter62

ExampleExampleA group of six jobs is to be processed through a two-machine flow shop. The first operation

involves cleaning and the second involves painting. Determine a sequence that will minimize the total completion time for this group of jobs. Processing times are as follows:

Page 63: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-63 Scheduling

http://www.baskent.edu.tr/~kilter63

Select the job with the shortest processing time. It is job D, with a time of two hours.

Since the time is at the first center, schedule job D first. Eliminate job D from further consideration.

Job B has the next shortest time. Since it is at the second work center, schedule it last and eliminate job B from further consideration. We now have

The remaining jobs and their times are

Page 64: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-64 Scheduling

http://www.baskent.edu.tr/~kilter64

The shortest remaining time is six hours for job E at work center 1. Thus, schedule that job toward the beginning of the sequence (after job D). Thus,

Job C has the shortest time of the remaining two jobs. Since it is for the first work center, place it third in the sequence. Finally, assign the remaining job (F) to the fourth position and the result is

Page 65: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-65 Scheduling

http://www.baskent.edu.tr/~kilter65

Sequencing Jobs When Setup Times Sequencing Jobs When Setup Times Are Sequence-DependentAre Sequence-Dependent

Page 66: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-66 Scheduling

Scheduling DifficultiesScheduling Difficulties

Randomness in job arrival times Variability in

Setup times Processing times Interruptions Changes in the set of jobs

No method for identifying optimal schedule Scheduling is not an exact science Ongoing task for a manager

Page 67: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-67 Scheduling

Classic Dispatching ResultsClassic Dispatching Results Optimal Schedules: Impossible to find for most real problems. Dispatching: sorts jobs as they arrive at a machine. Dispatching rules:

FIFO – simplest, seems “fair”. SPT – Actually works quite well with tight due dates. EDD – Works well when jobs are mostly the same size. Many (100?) others.

Problems with Dispatching: Cannot be optimal (can be bad). Tends to be myopic.

Page 68: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-68 Scheduling

The Difficulty of Scheduling ProblemsThe Difficulty of Scheduling Problems

Dilemma: Too hard for optimal solutions. Need something anyway.

Classifying “Hardness”: Class P: has a polynomial solution. Class NP: has no polynomial solution.

Example: Sequencing problems grow as n!. Compare en/10000 and 10000n10.

At n = 40, en/10000 = 2.4 1013, 10000n10 = 1.0 1020

At n = 80, en/10000 = 5.5 1030, 10000n10 = 1.1 1023

3! = 6, 4! = 24, 5! = 120, 6! = 720, … 10! =3,628,800, while

13! = 6,227,020,800

25!= 15,511,210,043,330,985,984,000,000

0

1E+22

2E+22

3E+22

4E+22

5E+22

6E+22

7E+22

8E+22

9E+22

56 57 58 59 60 61 62 63

en/10000

10000n10

Page 69: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-69 Scheduling

The Difficulty of Scheduling ProblemsThe Difficulty of Scheduling Problems

NP stands for non polynomial, meaning that the time required to solve such problems is an exponential function of the number of jobs rather than a polynomial function.

The problems for which total enumeration is hopeless are known in mathematics as NP hard.

Page 70: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-70 Scheduling

Computation TimesComputation Times

Current situation: computer can examine 1,000,000 sequences per second and we wish to build a scheduling system that has response time of no longer than one minute. How many jobs can we sequence optimally?

Number of Jobs Computer Time

5 0.12 millisec6 0.72 millisec7 5.04 millisec8 40.32 millisec9 0.36 sec10 3.63 sec11 39.92 sec12 7.98 min13 1.73 hr14 24.22 hr15 15.14 day

20 77,147 years

Page 71: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-71 Scheduling

Effect of Faster ComputersEffect of Faster Computers

Future Situation: New computer is 1,000 times faster, i.e. it can do 1 billion comparisons per second. How many jobs can we sequence optimally now?

Number of Jobs Computer Time

5 0.12 microsec6 0.72 microsec7 5.04 microsec8 40.32 microsec9 362.88 microsec10 3.63 millisec11 39.92 millisec12 479.00 millisec13 6.23 sec14 87.18 sec15 21.79 min

20 77,147 years

Page 72: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-72 Scheduling

Implications for Real ProblemsImplications for Real Problems

Computation: NP algorithms are slow to use.

No Technology Fix: Faster computers don’t help on NP algorithm.

Scheduling is Hard: Real scheduling problems tend to be NP Hard.

Scheduling is Big: Real scheduling problems also tend to be quite large; impossible to solve optimally.

Page 73: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-73 Scheduling

Implications for Real Problems (cont.)Implications for Real Problems (cont.)

Robustness? NP hard problems have many solutions, and presumably many “good” ones. Our task is to find one of these.

Role of Heuristics: Polynomial algorithms can be used to obtain “good” solutions. Example heuristics include: Simulated Annealing Tabu Search Genetic Algorithms

Page 74: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-74 Scheduling

The Bad NewsThe Bad News

Violation of Assumptions: Most “real-world” scheduling problems violate the assumptions made in the classic literature: There are always more than two machines. Process times are not deterministic. All jobs are not ready at the beginning of the problem. Process time are sequence dependent.

Problem Difficulty: Most “real-world” production scheduling problems are NP-hard. We cannot hope to find optimal solutions of

realistic sized scheduling problems. Polynomial approaches, like dispatching, may

not work well.

Page 75: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-75 Scheduling

The Good NewsThe Good News

Due Dates: We can set the due dates.

Job Splitting: We can get smaller jobs by splitting larger ones. Single machine SPT results imply small jobs “clear out”

more quickly than larger jobs. Mechanics of Johnson’s algorithm implies we should

start with a small job and end with a small job. Small jobs make for small “move” batches and can be

combined to form larger “process” batches.

Page 76: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-76 Scheduling

The Good News (cont.)The Good News (cont.)

Feasible Schedules: We do not need to find an optimal schedule, only a good feasible one.

Focus on Bottleneck: We can often concentrate on scheduling the bottleneck process, which simplifies problem closer to single machine case.

Capacity: Capacity can be adjusted dynamically (overtime, floating workers, use of vendors, etc.) to adapt facility (somewhat) to schedule.

Page 77: 15-1Scheduling Operations Scheduling Chapter 8. 15-2Scheduling The Hierarchy of Production Decisions The logical sequence of operations in factory planning

15-77 Scheduling

Minimizing Scheduling DifficultiesMinimizing Scheduling Difficulties

Set realistic due dates

Focus on bottleneck operations

Consider lot splitting of large jobs