testking.prince2foundation 150 · 4/8/2015  · prince2 prince2 foundation prince2 foundation...

62
TestKing.PRINCE2Foundation_150.QA Number : PRINCE2Foundation Passing Score : 800 Time Limit : 120 min File Version : 14.05 http://www.gratisexam.com/ PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All questions ok, many answers are well explained. This VCE alone will guarantee you a pass. Still valid.All questions are different than any vce.

Upload: others

Post on 21-Aug-2020

6 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

TestKing.PRINCE2Foundation_150.QA

Number: PRINCE2FoundationPassing Score: 800Time Limit: 120 minFile Version: 14.05

http://www.gratisexam.com/

PRINCE2 PRINCE2 FoundationPRINCE2 Foundation written Exam

100% valid, I didn't fail any question, all of them are in this VCE.

All questions ok, many answers are well explained.

This VCE alone will guarantee you a pass.

Still valid.All questions are different than any vce.

Page 2: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Exam A

QUESTION 1Which is a purpose of the Closing a Project process?

A. Authorize the final stage of the projectB. Confirm that all benefits defined in the Business Case have been achievedC. Recognize whether objectives set out in the original Project Initiation Documentation have been achievedD. Delegate day-to-day management of the end of the project to the Project Manager

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 2Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

A. Off-specificationsB. Follow-on action recommendationsC. Issue RegisterD. Risk Register

Correct Answer: BSection: (none)Explanation

Explanation/Reference:answer is verified.

QUESTION 3Which is an objective of the Closing a Project process?

A. Review and approve the plan for project closureB. Review the performance of the project against its baselineC. Perform any post-project reviews

Page 3: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

D. Create a Benefits Review Plan

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 4Which is a purpose of the Controlling a Stage process?

http://www.gratisexam.com/

A. Produce a Team Plan for the work to be assigned to a Team ManagerB. Select and implement actions that will resolve deviations from a plan within toleranceC. Obtain approvals for products delivered in a Work PackageD. Update a Project Plan to incorporate the actuals from a Stage Plan

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 5What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

A. Directing a ProjectB. Managing a Stage BoundaryC. Controlling a StageD. Starting up a Project

Page 4: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 6Which process is triggered towards the end of the final stage when all the assigned work has been completed?

A. Managing a Stage BoundaryB. Managing Product DeliveryC. Closing a ProjectD. Controlling a Stage

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 7Which is a purpose of the Controlling a Stage process?

A. Assign work to be done and take corrective action to ensure that the stage remains within toleranceB. Provide a fixed reference point at which acceptance for the project product is confirmedC. Enable the Project Board to be provided with sufficient information to authorize the next stageD. Enable the organization to understand the work that needs to be done to deliver the project's products

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 8

Page 5: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

A. Directing a ProjectB. Controlling a StageC. Managing a Stage BoundaryD. Managing Product Delivery

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 9In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

A. Product DescriptionB. Team PlanC. Work PackageD. Stage Plan

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 10Which is a purpose of the Directing a Project process?

http://www.gratisexam.com/

Page 6: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

A. Create and authorize the project mandateB. Ensure that work on products allocated to the team is authorized and agreedC. Control the day-to-day running of the projectD. Delegate day-to-day management of the project to the Project Manager

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 11Which is a purpose of the Directing a Project process?

A. Provide the information required to confirm if it is worthwhile to initiate a projectB. Enable overall control of a project to be exercised by the Project BoardC. Establish the level of control required by the Project Board after initiation.D. Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 12Which is an objective of the Directing a Project process?

A. Create and authorize the project mandateB. Provide management control and directionC. Control the day-to-day running of the projectD. Provide accurate progress information to the Project Manager

Correct Answer: BSection: (none)

Page 7: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Explanation

Explanation/Reference:

QUESTION 13In what process is the authorization to deliver the project's products given?

A. Starting up a ProjectB. Initiating a ProjectC. Managing a Stage BoundaryD. Directing a Project

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 14Who should act as the communication channel between a project and corporate or programme management?

A. Project BoardB. Project AssuranceC. Project ManagerD. Project Support

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 15Which statement about the Directing a Project process is true?

A. Provides a mechanism for the Project Board to assure that there is continued business justification

Page 8: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

B. Covers the day-to-day activities of the Project ManagerC. Ensures there are regular progress meetingsD. Begins on completion of the Initiating a Project process

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 16Which of the following statements about the Project Initiation Documentation are true?

1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.

2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

http://www.gratisexam.com/

A. Only 1 is trueB. Only 2 is trueC. Both 1 and 2 are trueD. Neither 1 or 2 are true

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 17

Page 9: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Which is an objective of the Initiating a Project process?

A. Develop the corporate quality management system as part of the Project Initiation DocumentationB. Prepare the plans for the subsequent stagesC. Summarize how the organization's project management method will be tailored for the projectD. Request authority from corporate management to deliver the project

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 18Which is NOT a purpose of the Initiating a Project process?

A. Enable a Project Board decision about the commitment of resources to a projectB. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approvedC. Establish solid foundations for a projectD. Enable the Project Board to decide whether it is worthwhile to initiate a project

Correct Answer: DSection: (none)Explanation

Explanation/Reference:answer is modified.

QUESTION 19Which of the following statements about the Project Initiation Documentation are true?

1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.

2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

A. Only 1 is trueB. Only 2 is trueC. Both 1 and 2 are true

Page 10: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

D. Neither 1 or 2 are true

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 20Which plan provides the Business Case with costs during the Initiating a Project process?

A. Initiation Stage PlanB. Project PlanC. Stage PlanD. Team Plan

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 21Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

A. Project BriefB. Project Initiation DocumentationC. Project mandateD. Benefits Review Plan

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

Page 11: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

QUESTION 22Why is the Initiating a Project process used?

A. To decide which project approach is suitable for the projectB. To fully understand how the project objectives will be achieved before committing significant resourcesC. To produce the required Work PackagesD. To enable corporate or programme management to give authorization to deliver a project

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 23Which is a purpose of the Initiating a Project process?

A. Decide if it is worthwhile to initiate a projectB. Decide on the project approachC. Establish solid foundations for a projectD. Identify the number of Work Packages required

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 24Which is a purpose of the Managing Product Delivery process?

A. Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package

B. Provide a controlled link between the Project Manager and the Team Manager(s)C. Enable the Project Board to request updates to the current Team PlanD. Establish solid foundations for the project

Page 12: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 25From whom does a Team Manager obtain approval for a completed product?

A. Project ManagerB. Project SupportC. The authority defined in the Product DescriptionD. Senior Supplier

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 26Which is an objective of the Managing Product Delivery process?

A. Sign-off completed Work PackagesB. Ensure the Business Case is kept under reviewC. Report progress to the Project BoardD. Ensure that work on products is authorized and agreed with the team

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 27What process aims to ensure accurate progress information is provided to the Project Manager?

Page 13: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

A. Starting up a ProjectB. Managing a Stage BoundaryC. Managing Product DeliveryD. Directing a Project

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 28Which process covers the work done by external suppliers who may NOT be using PRINCE2?

A. Closing a ProjectB. Managing a Stage BoundaryC. Managing Product DeliveryD. Directing a Project

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 29Which two roles are linked by the Managing Product Delivery process?

A. Corporate or programme management and Project BoardB. Project Board and Project ManagerC. Project Manager and Team ManagerD. Team Manager and external supplier

Correct Answer: CSection: (none)

Page 14: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Explanation

Explanation/Reference:Explanation:

QUESTION 30What is the collective name for individuals or groups who may be affected by a project?

A. CustomersB. Project SupportC. StakeholdersD. Team members

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 31Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

A. Create a separate Project Board to manage the supplier elements of the projectB. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.C. Create user and supplier groupsD. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 32When should the Project Board refer to corporate or programme management for a decision?

A. The stage requires resources

Page 15: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

B. It is forecast that project level tolerance will be exceededC. The Senior Supplier or Senior User needs to be changedD. Any request for change needs to be approved

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 33Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of theEnd Stage Report to external interested parties.

A. Stage PlanB. Communication Management StrategyC. Follow-on action recommendationsD. Quality Management Strategy

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 34Which is NOT a purpose of the Organization theme?

A. Define a project management team structureB. Define the level of tolerance for each level of the project management teamC. Define the Project Board's responsibility for directing the projectD. Define which role is accountable for the project's success

Correct Answer: BSection: (none)Explanation

Page 16: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Explanation/Reference:answer is valid.

QUESTION 35Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

A. Those with a financial interest in the projectB. Those who will manage the project on a day-to-day basisC. Those who will specify the desired outputs of the projectD. Those who will create the project's outputs

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 36Which does the Executive need to ensure is in place before the project is initiated?

A. All Work Packages are authorizedB. An understanding of how the project will contribute to corporate objectivesC. The Project Plan has been approvedD. The Project Initiation Documentation is complete

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 37Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project iscomplete?

A. ExecutiveB. Senior User

Page 17: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

C. Senior SupplierD. Project Manager

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 38What product is used to maintain a record of those who have an interest in the project and their information requirements?

A. Project PlanB. Communication Management StrategyC. Project BriefD. Project Product Description

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 39Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

A. qualityB. supplierC. riskD. product

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

Page 18: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

QUESTION 40How many roles make up the Project Board?

A. OneB. TwoC. ThreeD. Four

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 41Which of the following statements about stakeholders are true?

1. Someone who thinks they will be affected by a project is a stakeholder on that project.

2. Stakeholders may be internal or external to the corporate organization.

A. Only 1 is trueB. Only 2 is trueC. Both 1 and 2 are trueD. Neither 1 or 2 are true

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 42Which is one of the six aspects of project performance that needs to be managed?

A. Progress

Page 19: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

B. ChangeC. RiskD. Security

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 43Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

http://www.gratisexam.com/

A. BenefitsB. QualityC. RiskD. Scope

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 44Which is NOT included in the PRINCE2 definition of a project?

A. A project is a temporary organizationB. A project's purpose is to deliver one or more business products

Page 20: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

C. A project is part of 'business as usual'D. A project is based on an agreed Business Case

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 45Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.

A. a corporateB. a temporaryC. an externalD. a technical

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 46Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managedusing PRINCE2 form the [ ? ] of the method.

A. PrinciplesB. ThemesC. ProcessesD. Techniques

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

Page 21: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Explanation:

QUESTION 47Which is NOT one of the PRINCE2 integrated elements?

A. Tailoring PRINCE2 to the project environmentB. The processesC. The productsD. The themes

Correct Answer: CSection: (none)Explanation

Explanation/Reference:answer is corrected.

QUESTION 48Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

A. Specify the desired resultB. Provide the resources and skills to deliver the desired resultC. Ensure the technical integrity of a projectD. Develop a project's products

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 49Which is a benefit of using PRINCE2?

A. Enables the management of projects as well as of 'business as usual' activitiesB. Can be tailored by leaving out elements of the method for some projectsC. Can be applied to any type of projectD. Avoids the need to involve corporate or programme management

Page 22: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 50Which is a benefit of using PRINCE2?

A. Is a method specifically designed for technical projectsB. Provides for the efficient and economic use of management timeC. Includes many of the proven planning techniques, such as critical path analysisD. Can be used to manage both projects and programmes

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 51Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

A. Specify the desired resultB. Provide the resources and skills to deliver the desired resultC. Pay for the projectD. Specify the benefits of the project

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 52

Page 23: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Which does NOT reflect the PRINCE2 principle of continued business justification?

A. There must be a justifiable reason for starting a projectB. The business justification drives decision makingC. If a project is no longer forecast to deliver a financial benefit, it should be stopped.D. If a project can no longer be justified, it should be stopped

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 53Which characteristic distinguishes a project from regular business operations?

A. Produces benefitsB. Introduces business changeC. Manages stakeholdersD. Incurs cost

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 54Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

A. ChangeB. Cross-functionalC. UniqueD. Risk

Correct Answer: B

Page 24: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Section: (none)Explanation

Explanation/Reference:answer is modified.

QUESTION 55Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

A. Manage by stagesB. Manage by exceptionC. Continued business justificationD. Learn from experience

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 56Which role is responsible for creating Checkpoint Reports?

A. Senior SupplierB. Team ManagerC. Change AuthorityD. Project Support

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 57Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

Page 25: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

A. project cost toleranceB. stage cost toleranceC. Work Package cost toleranceD. product cost tolerance

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 58Which is a true statement about time-driven controls?

A. Time-driven controls are used for monitoring the progress of Work Packages and management stagesB. Time-driven controls take place when specific events happenC. Time-driven controls are produced at the end of a stageD. An Exception Report is a time-driven control

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 59Which of the following statements about lines of authority and reporting are true?

1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.

2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

A. Only 1 is trueB. Only 2 is trueC. Both 1 and 2 are trueD. Neither 1 or 2 are true

Page 26: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 60What theme provides all management levels within the project management team with mechanisms for monitoring and control?

A. ProgressB. ChangeC. OrganizationD. Quality

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 61Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

A. Corporate groupB. Project BoardC. Project AssuranceD. Executive

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 62Which is a FALSE statement about technical stages?

Page 27: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

A. Can overlap with other technical stagesB. Typified by the use a particular set of specialist skillsC. Include the Managing a Stage Boundary process activitiesD. Can span more than one management stage

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 63How should the Team Manager report that tolerances are forecast to be exceeded?

A. Create an Exception ReportB. Create a Highlight ReportC. Raise an issueD. Grant a concession

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 64Which statement about stages is true?

A. Management stages should be of the same durationB. The use of technical stages is mandatoryC. The use of management stages is mandatoryD. Management stages are driven by specialist teams

Correct Answer: CSection: (none)

Page 28: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Explanation

Explanation/Reference:Explanation:

QUESTION 65What product defines the reporting requirements between the Project Manager and Team Manager?

A. Project BriefB. Product DescriptionC. Team PlanD. Work Package

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 66Whose approval is needed to replace a Stage Plan with an Exception Plan?

A. Corporate or programme managementB. Project BoardC. Project ManagerD. Team Manager

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 67Which is a difference between management and technical stages?

A. Management stages require planning and technical stages do not

Page 29: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

B. Technical stages can overlap and management stages cannotC. Management stages deliver products and technical stages do notD. Technical stages require resources and management stages do not

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 68Which is a purpose of a Lessons Log?

A. Note any lessons that are raised in Checkpoint ReportsB. Record that corrective action is being takenC. Escalate lessons to the Project BoardD. Raise improvements with Project Assurance

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 69Which is a true statement about PRINCE2 event-driven controls?

A. Event-driven controls take place at predefined periodic intervalsB. Event-driven controls are produced at the frequency defined in a Work PackageC. Event-driven controls are used for decision makingD. Checkpoint Reports are event-driven controls

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

Page 30: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Explanation:

QUESTION 70Which is a purpose of an End Project Report?

A. Identify individuals or groups that need to be told that the project is coming to an endB. Review how well the project performed against the Project Initiation Documentation used to authorize itC. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closedD. Ensure that key project information is archived and made secure

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 71How many management stages should a PRINCE2 project consist of?

A. Start up stage, initiation stage and at least one other management stage to cover the remainder of the projectB. Start up stage, at least one other management stage to cover the remainder of the project and a closing stageC. Initiation stage and at least one other management stage to cover the remainder of the projectD. Start up stage, initiation stage and a closing stage

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 72What product would enable the Project Manager to review how a Work Package is performingagainst its cost tolerance?

Page 31: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

http://www.gratisexam.com/

A. Configuration Item RecordB. Quality RegisterC. Highlight ReportD. Checkpoint Report

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 73Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

A. Only corporate or programme managementB. Only the Project BoardC. Only the Project ManagerD. All levels of management

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 74Which is one of the three levels of plan in PRINCE2?

Page 32: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

A. Benefits Review PlanB. Programme PlanC. Team PlanD. Project Brief

Correct Answer: CSection: (none)Explanation

Explanation/Reference:answer is appropriate.

QUESTION 75What theme estimates the cost of delivering the project?

A. Business CaseB. ChangeC. PlansD. Progress

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 76Which is a task of product-based planning?

A. Identify activities and dependenciesB. Write the Project Product DescriptionC. Prepare the Work PackagesD. Produce Product Status Accounts

Correct Answer: BSection: (none)Explanation

Page 33: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Explanation/Reference:Explanation:

QUESTION 77Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of managementinvolved in a project.

A. Management strategiesB. PlanC. Stakeholder interestsD. Time-driven controls

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 78Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.

A. define a coding system to provide a unique identifier for the products withinB. summarize the results of the quality activities performed onC. provide a framework to design, develop and maintainD. define the project benefits to be achieved by each of

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 79What is the first task of product-based planning?

A. Produce the Initiation Stage Plan

Page 34: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

B. Write the Project Product DescriptionC. Identify dependenciesD. Create the product breakdown structure

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 80Which product identifies the management stages and timescales of a project?

A. Project BriefB. Project Product DescriptionC. Project PlanD. Initiation Stage Plan

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 81How many tasks does the product-based planning technique describe?

A. OneB. TwoC. ThreeD. Four

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

Page 35: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Explanation:

QUESTION 82Which is shown in a product breakdown structure?

A. Management stages, major products and control pointsB. In which order the products should be createdC. The major products that are to be developed in a planD. What resources are required to develop the products

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 83Which statement applies to Stage Plans?

A. Always have the same duration as the Project PlanB. Are produced at the same time as the Project Initiation DocumentationC. Assist the Project Manager in the day-to-day running and control of the projectD. Provide a baseline against which the Project Board monitor overall progress

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 84Which is a recommended quality review team role?

A. Project ManagerB. AssuranceC. Project SupportD. Administrator

Page 36: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 85Which is a recommended quality review team role?

A. Project ManagerB. AssuranceC. ChairD. Producer

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 86Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) theneeds of the business.

A. controlsB. productsC. project management teamD. stages

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

Page 37: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

QUESTION 87Which is a purpose of a Project Product Description?

http://www.gratisexam.com/

A. Records the costs and timescales for delivery of the project's final productB. Shows the dependencies between the project's products to aid planningC. Provides a list of all the products to be delivered by the projectD. Defines what the project must deliver in order to gain acceptance

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 88Which of the following statements about quality assurance and Project Assurance is true?

A. Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project BoardB. Project Assurance is independent of the Project; quality assurance is only independent of the Project ManagerC. Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project BoardD. Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 89

Page 38: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Who carries out audits that are independent of the project?

A. Quality assuranceB. Project AssuranceC. Project SupportD. Project Manager

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 90Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.

A. a solution should be designed forB. an issue should be created forC. the agreed actions should be recorded forD. the chair will approve the solution to

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 91Which statement about the quality review technique is FALSE?

A. It enables a check to be made on a product's fitness for purposeB. It defines the quality responsibilities of the project teamC. It supports the management of future changes by providing a baseline for a productD. It is used to gain wider acceptance of a product by involving key interested parties

Correct Answer: B

Page 39: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Section: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 92Which is part of quality control?

A. Undertake quality reviewsB. Write Product DescriptionsC. Provide assurance that the project is being conducted properlyD. Document the customer's quality expectations

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 93Which is part of quality control?

A. Document the project's acceptance criteria in the Project Product DescriptionB. Define the quality responsibilities of those involved in the production of the productsC. Produce quality records to show that the planned quality activities have been carried outD. Maintain the corporate organization's quality management system

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 94Which of the following statements about customer's quality expectations and acceptance criteria are true?

Page 40: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to keystakeholders.

2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.

A. Only 1 is trueB. Only 2 is trueC. Both 1 and 2 are trueD. Neither 1 or 2 are true

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 95Which is a true statement about acceptance criteria?

A. Acceptance criteria are used to produce the customer's quality expectationsB. Acceptance criteria are less specific and precise than customer's quality expectationsC. Once agreed, acceptance criteria CANNOT be changedD. Acceptance criteria should be agreed between the customer and the supplier

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 96Why is it crucial that the Project Product Description clearly defines acceptance methods?

A. Enables Project Assurance to authorize quality activitiesB. Defines how all project products will be reviewed and approvedC. Defines how it will be proven that the completed project product meets the customer's expectationsD. Provides confirmation that all project products have met their quality criteria

Page 41: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 97Which is a purpose of the Quality theme?

A. Establish how the project will ensure that all products created meet their requirementsB. Establish quality assurance to maintain the quality management systemC. Identify all the products of the project to ensure the scope has been adequately definedD. Determine the communication needs of the organization's quality assurance function

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 98Which statement defines a risk?

A. A certain event occurring in the future that will have a negative impact on the project's objectivesB. An event that has already occurred that the Project Manager must deal with immediatelyC. An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectivesD. An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response

Correct Answer: CSection: (none)Explanation

Explanation/Reference:answer is modified.

QUESTION 99

Page 42: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Which risk response type is appropriate to respond to an opportunity?

A. AcceptB. FallbackC. ExploitD. Transfer

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 100Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity.

A. AvoidB. ReduceC. ShareD. Transfer

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 101Which is NOT considered when defining risk tolerance?

A. A Project Board's attitude towards risk takingB. The allocated risk budgetC. An organization's risk appetiteD. The amount of risk a Project Board considers acceptable

Correct Answer: B

Page 43: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Section: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 102Which is a responsibility of a risk owner?

A. Identify risks to the project that might occur in their department B. Own and authorize the use of the risk budget to fund risk responsesC. Manage, monitor and control all aspects of an assigned riskD. Determine project risk appetite

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 103Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.

A. Project AssuranceB. Project SupportC. the risk actioneeD. the risk owner

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 104Which is a purpose of the Risk theme?

Page 44: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

A. Establish a method for the implementation of continuous improvement during the projectB. Identify, assess and control problems that have occurredC. Provide the Project Board with a time-driven control to capture all project risksD. Establish a cost-effective procedure to identify, assess and control risks

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 105Which document should record the agreed amount of risk budget for a project?

A. Project BriefB. Project PlanC. Risk Management StrategyD. Risk Register

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 106Which statement describes the 'Implement' step within the recommended risk management procedure?

A. Take planned action to respond to a riskB. Implement the responsibilities for risks defined in the Risk Management StrategyC. Assess the proximity of a riskD. Identify the level of risks that can be tolerated by the project

Correct Answer: ASection: (none)Explanation

Page 45: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Explanation/Reference:Explanation:

QUESTION 107Which is a purpose of the Risk theme?

A. Establish a procedure to ensure every change is agreed by the relevant authority before it takes placeB. Establish a cost-effective procedure to identify, assess and control uncertaintyC. Establish mechanisms to control any unacceptable deviations from planD. Establish mechanisms to manage risks at the corporate or programme level of an organization

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 108Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses toa project's threats and opportunities.

A. change budgetB. project budgetC. project's cost toleranceD. project's risk tolerance

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 109Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

A. Risk category

Page 46: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

B. Risk descriptionC. Risk responseD. Risk status

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 110Which describes a risk effect?

A. The uncertainty expressed as a negative or favourable occurrenceB. The issue which is affecting the project and has resulted in a riskC. The impact(s) on the project objectives should the threat or opportunity occurD. The change in the status of a risk in response to actions taken to control it

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 111Which describes risk probability?

A. Level of risks which the project can tolerate before escalating to the Project Board B. Probable effect on the project delivering its objectivesC. Timeframe within which the risk may occurD. A measure of the likelihood of the risk occurring

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

Page 47: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Explanation:

QUESTION 112Which is a purpose of a Risk Register?

A. Capture risks that may occur during the projectB. Record how risk management activities will be undertaken on the projectC. Record the risk tolerance for the projectD. Capture issues which are impacting on the delivery of the project objectives

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 113Which describes a risk event?

http://www.gratisexam.com/

A. The area of uncertainty in terms of the threat or opportunityB. The derivation or sources of a potential risk to the projectC. The achievement of a milestone on the Project PlanD. The sequence of events and actions that will be put in place if a risk occurs

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

Page 48: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

QUESTION 114What is described as an organization's unique attitude towards risk taking

A. Risk appetiteB. Risk managementC. Risk evaluationD. Risk tolerance

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 115Which is a purpose of the Risk Register?

A. Describe the risk management techniques and standards to be applied to the projectB. Act as a central record of information relating to the identified risks for the projectC. Act as a repository for informal issuesD. List the responsibilities for achieving an effective risk management procedure

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 116Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

A. Controlling a StageB. Closing a ProjectC. Directing a ProjectD. Managing a Stage Boundary

Page 49: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 117Which is a purpose of the Managing a Stage Boundary process?

A. Provide the Project Board with sufficient information for approving the next stageB. Approve the next Stage PlanC. Review and close any risks and issues identified during the previous stageD. Control the link between the Project Manager and the Team Manager(s)

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 118During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

A. End Stage ReportB. Team PlanC. Work PackageD. Project Plan

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 119What plan is created, and submitted for approval, during the Managing a Stage Boundary process?

Page 50: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

A. Team PlanB. Stage PlanC. Benefits Review PlanD. Project Plan

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 120Which of the following is the Business Case used for during the Managing a Stage Boundary process?

A. Enable the Project Board to decide whether or not to authorize the projectB. Justify the continuing viability of the projectC. Enable the Project Board to decide whether or not to authorize project closureD. Justify the initiation of a project

Correct Answer: BSection: (none)Explanation

Explanation/Reference:answer is valid.

QUESTION 121Which activity takes place within the Managing a Stage Boundary process?

A. Produce Highlight ReportsB. Take corrective action within the limits of a stage's toleranceC. Produce an Exception PlanD. Authorize a Stage Plan for the next stage

Correct Answer: CSection: (none)

Page 51: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Explanation

Explanation/Reference:Explanation:

QUESTION 122Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?

A. Managing Product DeliveryB. Initiating a ProjectC. Managing a Stage BoundaryD. Starting up a Project

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 123Which is a purpose of a Project Brief?

A. Enable the assembly of the project mandateB. Describe the reporting requirements of the various layers of management involved with the projectC. Describe how changes to products will be controlledD. Provide a solid basis for the initiation of the project

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 124Which is an objective of the Starting up a Project process?

A. Identify who will be responsible for creating the Project Plan

Page 52: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

B. Agree how the project will be monitored and controlled after initiationC. Authorize the Project Manager to proceed with the initiation stageD. Agree how issues and changes will be identified, assessed and controlled

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 125Which is created during the Starting up a Project process?

A. Project mandateB. Project management team role descriptionsC. Communication Management StrategyD. Quality Register

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 126Which should be provided by corporate or programme management before the Starting up a Project process commences?

A. A Project BriefB. Sufficient information to identify the prospective ExecutiveC. The Project Initiation DocumentationD. Authority to initiate a project

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

Page 53: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

QUESTION 127Which should be provided by a project mandate?

http://www.gratisexam.com/

A. Terms of referenceB. Detailed Business CaseC. Stage tolerancesD. Initiation Stage Plan

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 128Why is a Project Brief produced?

A. To act as a trigger for the Starting up a Project processB. To record the strategies and management controls to be used by a projectC. To provide a full and firm foundation for the initiation of a projectD. To be used by the Project Board as a basis for reviewing the progress of a project

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

Page 54: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

QUESTION 129Which is a purpose of the Starting up a Project process?

A. Provide information so a decision can be made as to whether a project is viable and worthwhile to initiateB. Define the means of communication between the project and corporate or programme managementC. Define the project controlsD. Record any identified risks in the Risk Register

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 130Which product records any project outcomes perceived as negative by stakeholders?

A. Business CaseB. Project PlanC. Communication Management StrategyD. Project Product Description

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 131What is the definition of a project outcome?

A. A measurable improvement that is perceived as an advantage by one or more stakeholdersB. The reason for the projectC. The result of the change derived from using the project's outputsD. The project's specialist products.

Page 55: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 132Which is NOT a purpose of a Benefits Review Plan?

A. Define the period over which the cost-benefit analysis will be basedB. Describe how to measure the performance of the project's products in operational useC. Define the scope, timing and ownership of the benefit reviews requiredD. Describe how to measure and confirm any benefits that are to be realised after the project is closed

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 133Which product documents the information needed to demonstrate continued business justification?

A. Business CaseB. Communication Management StrategyC. Project Product DescriptionD. Quality Management Strategy

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 134Which product documents the information needed to demonstrate continued business justification?

Page 56: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

A. Business CaseB. Communication Management StrategyC. Project Product DescriptionD. Quality Management Strategy

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 135Which is NOT a purpose of a Benefits Review Plan?

A. Define the period over which the cost-benefit analysis will be basedB. Describe how to measure the performance of the project's products in operational useC. Define the scope, timing and ownership of the benefit reviews requiredD. Describe how to measure and confirm any benefits that are to be realised after the project is closed

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 136What is an off-specification?

A. A new requirementB. A quality toleranceC. A type of issueD. A major risk

Correct Answer: CSection: (none)

Page 57: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Explanation

Explanation/Reference:Explanation:

QUESTION 137Which is a type of issue?

A. A lessonB. A request for changeC. An Exception ReportD. A risk with an estimated high impact

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 138Which is a typical core activity within configuration management?

A. Quality assuranceB. Risk managementC. Verification and auditD. Progress reporting

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 139Which is a typical core activity within configuration management?

A. Issue management

Page 58: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

B. Quality inspectionC. IdentificationD. Preparation

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 140What needs to be in place to ensure effective issue and change control?

A. Configuration management systemB. Manage by exceptionC. Quality planningD. Information needs for stakeholders

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 141Which should be funded by a change budget?

A. Increase in agreed scopeB. Initiation stageC. Change AuthorityD. Handover activities

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

Page 59: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Explanation:

QUESTION 142Which should be funded from a change budget?

A. The Starting up a Project processB. A fallback planC. An agreed change to the scope of a projectD. A change to a plan, within allocated tolerances, due to poor estimating

Correct Answer: CSection: (none)Explanation

Explanation/Reference:answer is perfected.

QUESTION 143Which is the Issue Register NOT used for?

A. Capture external events that are impacting a stageB. Record information about a deviation in stage toleranceC. Capture any threats or opportunities that might have an impact on a stageD. Record any problems identified when authorizing a Work Package

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 144If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

A. Checkpoint ReportB. Highlight ReportC. Issue ReportD. Product Status Account

Page 60: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 145Which is the purpose of the Change theme?

A. Prevent change to baselined productsB. Identify, assess and control any potential and approved changes to baselined productsC. Establish mechanisms to monitor and compare actual achievements against those plannedD. Assess and control uncertainty

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 146Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?

A. CaptureB. ExamineC. ProposeD. Decide

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 147

Page 61: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

A. Raise a request for changeB. Raise an off-specificationC. Write an Exception ReportD. Amend the Work Package

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 148Which of the following statements about the Closing a Project process are true?

1. The Closing a Project process provides a fixed point for the receipt of completed WorkPackages for the work performed in the final stage.

2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

A. Only 1 is trueB. Only 2 is trueC. Both 1 and 2 are trueD. Neither 1 or 2 are true

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 149What takes place during the Closing a Project process?

A. The post-project benefits reviews are performedB. Ownership of the project's products is transferred to the customer

Page 62: TestKing.PRINCE2Foundation 150 · 4/8/2015  · PRINCE2 PRINCE2 Foundation PRINCE2 Foundation written Exam 100% valid, I didn't fail any question, all of them are in this VCE. All

C. An End Stage Report is prepared for the final stageD. The project closure notification is reviewed and approved

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 150Which is an objective of the Closing a Project process?

A. Prepare the plan for the next stageB. Assess any benefits that have already been realizedC. Produce a Benefits Review Plan to identify what benefits are expectedD. Check that all benefits are realized before closing a project

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

http://www.gratisexam.com/