16.0 eia title tandra minerals exports_ep… · d v d ] v o ^ µ u u Ç v } v o µ ] } v í í r í...
TRANSCRIPT
TANDRA MINERALS SURVEY NO. 293/2, SIBILIPEDDAVALASA VILLAGE,
MAKKUVA MANDAL, VIZIANAGARAM DISTRICT, ANDHRA PRADESH
EXECUTIVE SUMMARY
SUBMITTED TO ANDHRA PRADESH POLLUTION CONTROL BOARD,
REGIONAL OFFICE, VIZIANAGARAM
Studies and Documentation By TEAM Labs and Consultants B-115 to 117 & 509, Annapurna Block, Aditya Enclave, Ameerpet, Hyderabad-500 038 Phone: 040-23748 555/616, Telefax: 040-23748666 Email: [email protected]
Submitted By M/s. Tandra Minerals Plot No. 585/A/1, Road No. 32. Jubilee Hills, Hyderabad – 500 045 Telangana State. Mobile No. +91 98492 45679
Tandra Minerals Summary and conclusion
11 - 1 Team Labs and Consultants
Chapter 11.0 SUMMARY AND CONCLUSION
11.1 Introduction
Tandra Minerals obtained mine lease to extract color granite and dispose the waste
material in an area of 9.132 ha using fully mechanized opencast mining at sy.no.
293/2, Sibilipeddavalasa village, Makkuva mandal, Vizianagaram district. Granite
has been extensively used as a dimension stone and as flooring tiles in public and
commercial buildings and monuments. Rough-cut and polished granite is used in
buildings, bridges, paving, monuments and many other exterior projects.
In principle of application of quarry lease notice was issued by Director of Mines
and Geology, Ibrahimpatnam, Govt. of Andhra Pradesh, vide notice No. 6248/R1-
2/2018, dt. 29.06.2018 for a period of 20 years. The mining plan was approved by the
joint and Deputy director of Mines and Geology, Visakhapatnam, Government of
Andhra Pradesh, vide Letter No. 2608/MP-VZM/CG/2018, dt. 08.10.2018. Capital
cost for the proposed mining project is Rs. 75 Lakhs.
The Ministry of Environment, Forest and Climate Change (MoEFCC), Government
of India (GOI) issued notifications vide SO 1533, dt. 14.9.2006, its amendments based
on the directions issued by National Green Tribunal (NGT), New Delhi vide O. A.
No. 16 of 2016, dt.13.09.2018 and vide E.A.NO 55/2018 of O. A. No. 520/2016, dt.
11.12.2018 on Moefcc notification S.O.2269 (E), dt.01.07.2016 and S.O.3977 (E), dt.
14.08.2018 and Office Memorandum dt.12.12.2018 issued in compliance with the
hon’ble NGT orders, New Delhi, which mandate prior environmental clearance for
all mining leases across the country. The project is considered as category B based
on the notification no S.O 2731 (€), dt. 09.09.2013. The notification and its
amendments based on NGT directions, classify mine lease areas of 5 - 25 ha as
category B2 at par with B1, and stipulate a three-stage process of scoping, public
consultation and appraisal by State Environmental Impact Assessment Authority
(SEIAA) to issue prior environmental clearance. Accordingly scoping for
preparation of environmental impact assessment (EIA) was done by the state expert
appraisal committee (SEAC), which issued terms of reference vide Letter No. SEIAA
/AP/VZN/MIN/12/2018/748 - 2012, dt.19.02.2019 for a production capacity of
Tandra Minerals Summary and conclusion
11 - 2 Team Labs and Consultants
150000 m3/annum (Colour granite - recovery @ 40% - 60000 m3/annum and waste @
60% - 90000 m3/annum) in an area of 9.132 ha. Accordingly, the present study
follows the prescribed ToR’s and draft EIA/EMP report for public consultation, to
facilitate informed view on the project by public/stakeholders for the lease area and
other mine leases with a total cluster area of 19.083 ha. The report presents
cumulative environmental impacts due to the mining cluster and the environmental
management plan to address the same in addition to the impact assessment and
environmental management for this project.
M/s Team Labs and Consultants prepared Environmental Impact Assessment
Report for the proposed activity. The report is prepared using baseline data of
environmental status within 10 km radius of the mine lease area for major
environmental components; water, air, noise, soil, flora, fauna and socio-economic
environment for one season, and the proposed measures to be adopted for
mitigating and controlling pollution.
11.2 Mine Location
The Sailentfeatures of the mine lease location are presented in Table below. Sailentfeatures of the mine lease location
Description Remarks Name of the Project (s) M/s. Tandra Minerals
Location of the Project Survey No. 293/2, Sibilipeddavalasa Village, Makkuva Mandal, Vizianagaram District, Andhra Pradesh
Project / Activity 1(a) Category (A/B1/B2) B1 project type New project, Capital Cost, ₹ 75 lakhs Land Use Pattern (Forest, Agricultural, Grazing, Barren etc.)
Govt. Land Hill area – 9.132 ha
Survey of India sheet No E44L01 (65 N/1) Elevation above Mean Sea Level (AMSL), m 224 m Seismic zone Seismic Zone: II as per IS: 1893
Site surroundings
North : Agriculture Lands East : Hill area West : Open Lands South : Tandra Exports Quarry
Nearest Village Peddavalasa– 0.7 km – SW direction
Tandra Minerals Summary and conclusion
11 - 3 Team Labs and Consultants
Description Remarks Accessibility to site Site connecting – NW direction Road access Peddavalasa to Sibili road – 0.3 km – NW direction Nearest Town Vizianagaram – 64.5 km – SE direction District Head quarters Vizianagaram – 64.5 km – SE direction Nearest Railway station Parannavalasa station – 15 km – SE direction Nearest airport Vishakhapatnam Airport – 105 km – South direction Nearest Port Vishakhapatnam Port – 109 km – South direction Major Industries (Within 10 km radius) Nil
Water Bodies in buffer area Suvarnamukhi River - 4.3 km - SE direction Gomukhi Nadi - 3.8 km - SW direction
Presence of Water Bodies in Core Area Nil the Project / Activity attracts the provisions of CRZ Not Applicable
Reserve Forests
Nanda RF - 4.8 km - W direction Ansabadra RF - 6.7 km - NE direction Gunikonda RF - 6.4 km - SE direction Gaderukonda RF - 7.2 km - SE direction
Inter-state boundary and international boundary Andhra Pradesh - Odisha – 4.8 km - NW direction Protected Areas notified under the Wild Life (Protection) Act, 1972 Nil within 10 km Eco-sensitive areas as notified under section 3 of the E (P) Act, 1986 Nil within 10 km Critically polluted areas as identified by the CPCB from time to time, Nil within 10 km
The present mine lease forms a cluster of 2 mines with a total mine lease area of
19.083 ha.
11.3 Proposed Method of Mining
Fully mechanized opencast method by developing benches with a height of 6 m in 2
phases of 3m each is proposed, wherein wire saw cutting is adopted to cut the
granite, while blasting is proposed to construct the haulage road and remove over
burden. The separation of blocks from the mother rock will be carried out by
drilling, wedge cutting, blasting, excavation will be done by the machinery.
Transportation will be made by trucks to dispatching points.
Tandra Minerals Summary and conclusion
11 - 4 Team Labs and Consultants
11.3.1 Development and Production
It is proposed to initiate mining in the first year from the top most bench of 224
MRL, during second year mining is initiated from the top most bench of 214 MRL,
during third year mining is initiated from the top most bench of 210 MRL, during
fourth year mining is initiated from the top most bench of 205 MRL, during fifth year
mining is initiated from the top most bench of 200 MRL. Total excavation planned is
150000m3/year from which 60000 m3/year of colour granite is recovered. The waste
to be handled during this year is 90000 m3/ year.
11.4 Conceptual Plan
The mining operations will follow Fully mechanized open cast method. The entire
reserves estimated under proved, probable and possible categories are exploitable
except mineral blocked in 7.5 m buffer zone all along lease boundary as per statutory
requirement. The total reserves estimated are 2884090 m3 based on the mine scheme.
Therefore, the targeted capacity of 150000 m3/annum (Colour granite - recovery @
40% - 60000 m3/annum and waste @ 60% - 90000 m3/annum) and the anticipated life
of the mine is considered as 19 years for recovery of colour granite.
11.5 Employment Potential
The manpower requirement is 33 for various skilled, semi-skilled and unskilled jobs
headed by a mine’s manager.
11.6 Site Services
The Site services provided are temporary office, rest rooms, first aid room, blasting
shelters, water for drinking in the mine lease area. Temporary sheds with cement
plastered brick walls and G.I. sheet or grass roofing are constructed for site services.
The workers required shall be sourced from surrounding villages. Drinking water is
obtained from nearby villages through tankers to mining staff and workers. A
tractor mounted tanker is provided for sprinkling of water mainly on village roads
to suppress the dust generated due to vehicular movement. Fencing is also
provided around working area to avoid accidental slippage of men and animals,
while worked out areas are used as reservoir for storage of rain water.
Tandra Minerals Summary and conclusion
11 - 5 Team Labs and Consultants
11.7 Water Requirement and Effluent Generation
The total water requirement is 16.6 KLD. Water requirement for the proposed
activity is mainly for maintaining the green belt (3.6 KLD), for sprinkling on the haul
roads (2.3 KLD) to mitigate dust emissions, occasional wet drilling (9.2 KLD) and for
domestic purposes (1.5 KLD). Stagnated water in worked out area is used for
sprinkling, wet drilling and green belt development. The domestic water will be
drawn from Sibilipeddavalasa village. The generation of wastewater is from
domestic source only; it is expected to be approximately 1.2 KLD, which is sent to
septic tank followed by soak pit. The daily water requirement for the cluster of mine
operations would be approximately 27.2 KLD comprising of requirement for water
sprinkling on mine haulage roads etc. It is proposed 4.6 KLD of water is used for
water sprinkling for common Road.
11.8 Baseline Environmental Status
The baseline data for ambient air quality, surface and ground water quality, noise,
and soil quality was collected and analyzed for various parameters to determine the
existing quality and flora and fauna study of the impact area was conducted during
period of March – May 2019. The ambient air quality monitoring results shows that
the values are within the prescribed limits of national ambient air quality standards.
Ground water sample analysis results show that the values are above the limits for
total dissolved solids, total hardness, most of the locations compared to Indian
Standard Drinking Water Specification of IS: 10500-2012. Noise quality parameters in
the study area are within prescribed limits of Ambient Noise Standards. There are
no schedule I flora or fauna within the impact area.
11.8.1 Identification and Quantification of Impacts
The project activities that are likely to cause potential impacts on environment are
mining operations, transport and associated infrastructure. Mining operations
involve development of benches, haul roads, drilling, blasting, wire saw cutting,
excavation, handling and transportation of mineral and waste materials. The likely
effects of these activities are land degradation, fugitive dust generation, noise and
vibration levels, increased run-off during monsoon and human health risks. There
Tandra Minerals Summary and conclusion
11 - 6 Team Labs and Consultants
is one more mine adjacent to this lease area with an area of 9.951 ha. The cumulative
impacts due to the cluster are also assessed in addition to the impacts due to this
project.
ISCST3 model was used for air quality impact predictions. The predicted maximum
24 hourly GLC’s for the cluster were used to predict the ground level concentrations,
and the maximum predicted values of PM, PM10 and PM2.5 are 0.47, 0.03 and 0.02
g/m3 respectively and the maximum values are observed at center of mining area
for the cluster including Tandra exports. The cumulative values (baseline and
predicted) are found to be within the prescribed standards of national ambient air
quality.
11.9 Environment Management Plan
The management plan is drawn in consultation with the project proponent, mining
engineer and geologist after evaluating various methods for mitigation and control
of pollution. The environment management plan is drawn to address the impacts
monitored, identified and predicted for the present project and the cluster in which
the present project falls in. The environment management plan addresses the
impacts identified.
11.9.1 Dust Emissions
Dust will be generated during mining, drilling and also during handling and
transportation of the material. Haulage of minerals within lease area will lead to
emissions of fugitive dust in the mining area. It is proposed to provide water
sprinkling in haul roads to reduce the fugitive dust emissions. Tractor mounted
sprinkler will be deployed. Dust generated during occasional drilling and blasting
will be suppressed by covering the drill rods by wet gunny cloth.
11.9.2 Noise Pollution Control
Major noise sources during operation are mine machineries, equipment, occasional
drilling and blasting and vehicular movement. The following measures will be
adopted to reduce noise levels; improved silencers, mufflers and closed noise
generating parts, regular and periodic maintenance of noise generating machinery
Tandra Minerals Summary and conclusion
11 - 7 Team Labs and Consultants
including transport vehicles, location of site office and other infrastructures away
from the noise sources. Personal protective equipment like earmuffs, earplugs.
Canal caps will be provided to workers involved in work closer to noise generating
sources. The exposure to noise levels is also mitigated by adopting employee
rotation.
11.9.3 Water Resources and Waste Water Generation
The daily water requirement for the mine operations would be approximately 16.6
KLD comprising of requirement for water sprinkling on mine haulage roads etc.
The other major impact anticipated from mining activity is erosion and
sedimentation, as large area of land is exposed to erosion. The area exposed due to
mining shall be 9.132 ha in this project. It is proposed to provide garland drains
with rip rap at the discharge point to avoid sediment joining streams outside the ML
area. The daily water requirement for the cluster of mine operations would be
approximately 33.2 KLD comprising of requirement for water sprinkling on mine
haulage roads etc. it is proposed to use 4.6 KLD of water for water sprinkling for
common road.
11.9.4 Land Management
Land degradation is one of the major adverse impacts of opencast mining in the
form of excavated voids and also in the form of waste dump of 1.3 ha. During plan
period about 6.872 ha area will be occupied by pit, and plantation will cover 0.075 ha
and roads cover an area of 0.03 ha. Other temporary constructions are dismantled
after completion of mine workings.
11.9.6 Socio-Economic Environment
There are no settlements in the ML area. Hence no rehabilitation and resettlement
(R&R) is required. The mining activity will improve the economic status of the
people surrounding the mine lease area. The proposed project generates
employment to 33 people, and all the semiskilled and unskilled jobs will be provided
to the local villagers. Apart from employment, the state government and village
panchayath will get royalty due to mining.
Tandra Minerals Summary and conclusion
11 - 8 Team Labs and Consultants
11.9.7 Green Belt
Greenbelt is proposed as an additional mitigation measure for dust control in
addition to water sprinkling. It is proposed to have dense green belt in and around
the mine site, loading and unloading facilities, and in abandoned mine area during
reclamation process. About 0.075 ha (115 trees) area will be planted during lease
grant year and 600 tress along connecting road. Precautionary measures like regular
watering, providing manure and fencing will be taken up to achieve 90% of survival
rate of plantation.
11.9.8 Transportation
The required truck trips for transporting the mineral from this mine lease shall be in
the order of 50/day. The surrounding area is forming a cluster of mines producing
granite and total number of truck trips generated due to the cluster is 100/day.
Currently the Mine lease area is connected to Duggeru – Makkuva by a cart truck
road. The Duggeru – Makkuva road is a 2-lane road and hence, the dispatch of
trucks shall be staggered in consultation with neighboring mine lease proponents to
avoid traffic congestion.
11.9.9 Occupational Health and Safety Measures
Protective equipment will be provided to the employees such as safety shoes,
helmets and dust masks. Dust masks would be provided for the safety of workers at
site, engaged at dust generation points like drills, loading and unloading points, etc.
Dust masks would prevent inhalation of particulate matter thereby reducing the risk
of lung diseases and other respiratory disorders. Regular health monitoring of
workers will be carried out. The health impact due to dust shall be addressed by
rotation of employees from dust generating jobs after periodic health monitoring.
11.10 Environmental Monitoring Program
The monitoring program consists of collection and analysis of air, soil, noise and
surface and ground water samples. Environmental monitoring shall be conducted
on quarterly basis to assess the pollution level in the ML area and in the surrounding
areas as well. An Environment Management cell shall be established to look after
Tandra Minerals Summary and conclusion
11 - 9 Team Labs and Consultants
all the environment related activities. This cell will be headed by the Mines Manger.
The cell is responsible for all the environmental management activities including
environmental monitoring, greenbelt development and to ensure statutory
compliance with the regulatory authorities. The total capital expenditure envisaged
for environmental monitoring is Rs.1.59 lakhs. The total capital expenditure
envisaged for cluster environmental monitoring is Rs.7.44 lakhs.
11.11 Environment management Plan
The management measures mentioned in the previous paragraphs with respect to
air, noise and vibration, water, solid waste, occupational health and greenbelt are
generically, applicable to both the mine leases in the cluster. Additionally, the
following measures shall be adopted to mitigate the cumulative impacts;
Strengthening of common haulage roads, mining activity during day time to reduce
noise and vibration impact, blasting activity to be conducted at designated times
decided on mutual consultation, mineral dispatch on mutual consultation to avoid
traffic congestion, pooling of CER fund to avoid duplication of CER activity,
adoption of water conservation measures and water harvesting measures in
common properties of the surrounding villages after mutual consultation to
compensate the water usage from common properties, plantation along connecting
roads, drainage management and planning to avoid the sediment load and to avoid
over flow of storm water into the connecting drains, mutual support in case of any
emergency. The total capital expenditure envisaged for environmental management
is Rs.8.78 lakhs with annual recurring expenditure of 5.18 lakhs. The total capital
expenditure envisaged for cluster environmental management is Rs.7.44 lakhs with
annual recurring expenditure of 14.62 lakhs.
11.12 Corporate Environment Responsibility (CER)
It is proposed to spend Rs. 1.5 Lakhs in seven years for CER activities like provision
of drinking water facility, solar street lamps, trees plantation. The management will
provide training and awareness on job facilities to unemployed graduates and post
graduates, embroidery and tailoring training to backward and weaker section
women and training to local sports persons.
Tandra Minerals Summary and conclusion
11 - 10 Team Labs and Consultants
11.13 Mine Closure Plan
The disturbed land including area disturbed due to excavation, dumping,
construction of haul roads, ramps, structures would be reclaimed before finally
abandoning the mine. Thus, the area shall be fully reclaimed during last five years
of life of the mine. During post mining period all the disturbed areas will be
reclaimed before decommissioning / abandoning the mine. The closure involves
the; back filling the over and side burden, fencing around the pit and greenery
development. The top bench shall be afforested with local grass and plants.
11.14 Conclusion
The environmental impact study identified various mining activities that may result
in change in baseline status, and accordingly the proposed mitigation measures
mentioned in mine plan and the environment management plan were observed to be
sufficient to ensure least impact on the surrounding areas. The residual impact due
to mining is mainly loss of habitat which has to be compensated, loss of biodiversity
which can be offset, and worked out mine pit which has to be reclaimed. The
management assures to adopt extensive plantation in surrounding areas to
compensate habitat and biodiversity loss, thereby reducing the impact to the
maximum extent, while taking responsibility for implementing an effective mine
closure plan.