1.7g guide to the application - gov.uk · 2016. 5. 16. · app019 2.4 environmental features plans:...
TRANSCRIPT
-
Brechfa Forest ConnectionDevelopment Consent Order Application - Reference EN020016
Guide to the Application
March 2016
Gui
de to
the
App
licat
ion
1
.7G
-
Guide to the Application
This document provides a guide to Western Power Distribution’s Brechfa Forest Connection Project
Development Consent Order application. The original application was submitted to the Planning
Inspectorate on 29 May 2015, and accepted for examination by the Examining Authority on 26 June
2015.
Since the submission a number of the original application documents have been revised and new
documents produced. This guide charts the submission of these documents to the Planning
Inspectorate.
The following table identifies the documents we produced during the examination for which we
subsequently provided updates and/or revised documents. The left hand column of this table identifies
the initial submission with the remaining columns indicating when we submitted additional documents to
the Examining Authority.
For ease of navigation these documents are grouped by volumes as follows;
Volume This volume…
1. Application Information provides details of the specific application information required by the Planning Inspectorate
2. Plans, Drawings and Sections contains the plans which show where we propose to undertake the work
3. Draft Development Consent Order outlines the legal powers we are seeking from the Government to build the proposed connection
4. Compulsory Acquisition Information provides evidence of why we may require legal powers
5. Reports and Statements includes the Consultation Report and other reports and statements
6. Environmental Information shows how we assessed the potential impact on the environment
7. Other Media contains the 3D model of the proposed development and associated videos and images
8. Other Documents includes additional documents produced for the application submission
9. Examination Submissions Documents submitted to the Planning Inspectorate as part ofthe Examination
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
APP-0011.1 Covering Letter including Schedule of Documents
APP-0021.2 Application Form
APP-0031.3 Planning Inspectorate Electronic Application Index
APP-0041.4 Newspaper Notices
1.5 Red Line Boundary Shape Files1
APP-0051.6 Glossary and Abbreviations
APP-1351.7 Guide to the Application
REP1-0291.7A Guide to the Application
REP2-0251.7B Guide to the Application
REP3-0351.7C Guide to the Application
APP-0062.1 Works Plans: Overall Location Plan and Master Key to Sections Plan
APP-0072.1 Works Plans: Section A
APP-0082.1 Works Plans: Section B
APP-0092.1 Works Plans: Section C
APP-0102.2 Land Affected and Land Plans: Section A
APP-1362.2A Land Affected and Land Plans: Section A
APP-0112.2 Land Affected and Land Plans: Section B
APP-1372.2A Land Affected and Land Plans: Section B
APP-0122.2 Land Affected and Land Plans: Section C
APP-1382.2A Land Affected and Land Plans: Section C
APP-0132.2 Land Affected and Land Plans: Overall Location Plan and Master Key to Sections Plan
APP-1392.2A Land Affected and Land Plans: Overall Location Plan and Master Key to Sections Plan
APP0142.3 Access and Public Rights of Way Plans: Overall Location Plan and Master Key to Sections Plan
APP0152.3 Access and Public Rights of Way Plans: Section A
APP0162.3 Access and Public Rights of Way Plans: Section B
APP0172.3 Access and Public Rights of Way Plans: Section C
APP0182.4 Environmental Features Plans: Overall Location Plan and Master Key to Sections Plan
APP0192.4 Environmental Features Plans: Section A
APP0202.4 Environmental Features Plans: Section B
Volu
me
1A
pplic
atio
n In
form
atio
nVo
lum
e 2
Plan
s, D
raw
ings
and
Sec
tions
1 Submitted electronically only. No PINS reference provided. 1
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
REP4-0231.7D Guide to the Application
REP5-0191.7E Guide to the Application
REP6-0121.7F Guide to the Application 1.7G Guide to the Application
REP5-0202.2B Land Affected and Land Plans: Section A
REP6-0132.2C Land Affected and Land Plans: Section A
REP5-0212.2B Land Affected and Land Plans: Section B
REP6-0142.2C Land Affected and Land Plans: Section B
REP5-0222.2B Land Affected and Land Plans: Section C
2
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
APP0212.4 Environmental Features Plans: Section C
APP0222.5 Heritage Designations Plans: Overall Location Plan and Master Key to Sections Plan
APP0232.5 Heritage Designations Plans: Section A
APP0242.5 Heritage Designations Plans: Section B
APP-0252.5 Heritage Designations Plans: Section C
APP-0262.6 Special Category Land Plans and Crown Land Plans: Overall Location Plan and Master Key to Sections Plan
APP-027 2.6 Special Category Land Plans and Crown Land Plans: Section B
APP-0282.6 Special Category Land Plans and Crown Land Plans: Section C
APP-0292.7 132kV Overhead Line Wood Pole Outline
APP-0302.7 132kV Overhead Line Work no.1 Profiles
APP-0312.7 132kV Overhead Line Work no.3 Profiles
APP-0322.7 132kV Underground Cable Work no.2 Design Drawings
APP-0332.7 Design Drawings Brechfa Forest Satellite Construction Compound
APP034 2.7 Key Plan for Detailed Design DrawingsAPP0352.8 Trees and Hedges with the Potential to be Affected Plans: Overall Location Plan and Master Key to Sections Plan
Volu
me
2 Pl
ans,
Dra
win
gs a
nd S
ectio
ns
3
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
4
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
APP0362.8 Trees and Hedges with the Potential to be Affected Plans: Section A
APP-0372.8 Trees and Hedges with the Potential to be Affected Plans: Section B
APP-0382.8 Trees and Hedges with the Potential to be Affected Plans: Section C
REP3-0362.9 Deviation Plans
APP-0393.1 Draft Development Consent Order
REP2-0273.1A Draft Development Consent Order
REP3-0483.1B Draft Development Consent Order
REP2-0263.1A Draft Development Consent Order (Tracked Change)
REP3-0493.1B Draft Development Consent Order (Tracked Change)
APP-0403.2 Draft Explanatory Memorandum
APP-0414.1 Statement of Reasons
APP-1394.1A Statement of Reasons
APP-140 4.1A Statement of Reasons (Tracked Change)
APP-0424.2 Funding Statement
APP-0434.3 Book of Reference
APP-1414.3A Book of Reference
REP2-0294.3B Book of Reference Part 1
APP-1424.3A Book of Reference (Tracked Change)
REP2-0284.3B Book of Reference (Tracked Change) Part 1
APP-0445.1 Consultation Report
APP-0455.1 Consultation Report Appendix 3.1 to 4.3
APP-0465.1 Consultation Report Appendix 5.1 to 6.2
APP-0475.1 Consultation Report Appendix 6.3 to 8.24
APP-0485.1 Consultation Report Appendix 9.1 to 14.7
APP-0495.1.1 Consultation Report Summary (Welsh)
APP-0505.1.1 Consultation Report Summary
Volu
me
2 Pl
ans,
Dra
win
gs a
nd S
ectio
nsVo
lum
e 4
Com
puls
ory
Acq
uisi
tion
Info
rmat
ion
Volu
me
5 R
epor
ts a
nd S
tate
men
tsVo
lum
e 3
Dra
ft D
evel
opm
ent C
onse
nt O
rder
5
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
REP3-0523.1C Draft Development Consent Order
REP4-0243.1D Draft Development Consent Order
REP5-0233.1E Draft Development Consent Order
REP3-0533.1C Draft Development Consent Order (Tracked Change)
REP4-0253.1D Draft Development Consent Order (Tracked Change)
REP5-0243.1E Draft Development Consent Order (Tracked Change)
REP6-0153.2A Explanatory Memorandum
REP6-0163.2A Explanatory Memorandum (Tracked Change)
4.1B Statement of ReasonsOption A
4.1B Statement of Reasons Option A(Tracked Change)
REP5-0264.3C Book of Reference
REP6-0174.3D Book of Reference
REP5-0274.3C Book of Reference (Tracked Change)
REP6-0184.3D Book of Reference (Tracked Change)
6
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
APP-0515.1 Consultation Report Addendum
APP-0525.2 Flood Consequence Assessment
APP-0535.3 Statement of Statutory Nuisance
APP-0545.4 Habitat Regulations Assessment - No Significant Effects Report
REP3-0375.4A Habitat Regulations Assessment - No Significant Effects Report
APP-0546.1 Environmental Statement Non Technical Summary (Welsh)
APP-0556.1 Environmental Statement Non Technical Summary
APP-0566.2 Environmental Statement Chapter 1 - Introduction
APP-0576.2 Environmental Statement Chapter 2 - Project Description
APP-0586.2 Environmental Statement Chapter 3 - Project Alternatives
APP-0596.2 Environmental Statement Chapter 4 - Consultation
APP-0606.2 Environmental Statement Chapter 5 - Environmental Setting
APP-0616.2 Environmental Statement Chapter 6 - EIA Process
APP-0626.2 Environmental Statement Chapter 6 - EIA Process
APP-0636.2 Environmental Statement Chapter 8 - Land Use, Agriculture and Forestry
APP-0646.2 Environmental Statement Chapter 9 - Landscape and Visual Assessment
APP-0656.2 Environmental Statement Chapter 10 - Ecology
APP-0666.2 Environmental Statement Chapter 11 - Historic Environment
Volu
me
5 R
epor
ts a
nd S
tate
men
tsVo
lum
e 6
Envi
ronm
enta
l Inf
orm
atio
n
7
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
8
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
APP-0676.2 Environmental Statement Chapter 12 - Geology, Hydrogeology and Ground Conditions
APP-0686.2 Environmental Statement Chapter 13 - Hydrology, Drainage and Flood Risk
APP-0696.2 Environmental Statement Chapter 14 - Noise and Vibration
APP-0706.2 Environmental Statement Chapter 15 - Air Quality
APP-0716.2 Envirnmental Statement Chapter 16 - Traffic and Transport
APP-0726.2 Environmental Statement Chapter 17 - Socio-economics, Recreation and Tourism
APP-0736.2 Environmental Statement Chapter 18 - Electric and Magnetic Fields
APP-0746.2 Environmental Statement Chapter 19 - Cumulative Effects and Inter-relationships
APP-0756.2 Environmental Statement Chapter 20 - Environmental Management
APP-0766.3 Environmental Statement Figures 1.1 to 9.4
APP-0776.3 Environmental Statement Figure 9.5
APP-0786.3 Environmental Statement Figures 9.6 to 11.5
APP-0796.3 Environmental Statement Figures 12.1 to 17.1
APP-0806.3 Environmental Statement Figures 19.1 to 19.3
APP-0816.3 Environmental Statement Appendix 3.1 - WPD Schedule 9 Statement
Volu
me
6 En
viro
nmen
tal I
nfor
mat
ion
9
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
10
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
APP-0826.4 Environmental Statement Appendix 3.2 - Change Request Log
APP-0836.4 Environmental Statement Appendix 7.1 - Summary of LDP PoliciesAPP-0846.4 Environmental Statement Appendix 7.2 - Compliance with NPS EN1 and NPS EN5
APP-0856.4 Environmental Statement Appendix 7.3 - Climate Change Resilience Report
APP-0866.4 Environmental Statement Appendix 9.1 - Effects on Landscape Elements Part 1 of 2
APP-0876.4 Environmental Statement Appendix 9.1 - Effects on Landscape Elements Part 2 of 2
APP-0886.4 Environmental Statement Appendix 9.2 - Effects on Landscape Character
APP-0896.4 Environmental Statement Appendix 9.3 - Effects on Landscape Designations
APP-0906.4 Environmental Statement Appendix 9.4 - Effects on Representative Viewpoints
APP-0916.4 Environmental Statement Appendix 9.5 - Visual Effects upon Residents
APP-0926.4 Environmental Statement Appendix 9.6 - Visual Effects upon Footpath Users
APP-0936.4 Environmental Statement Appendix 9.7 - Visual Effects upon Road Users
APP-0946.4 Environmental Statement Appendix 9.8 - Visual Effects upon other Recreational and Tourist Locations
APP-0956.4 Environmental Statement Appendix 10.1 - Bat Technical Report
Volu
me
6 En
viro
nmen
tal I
nfor
mat
ion
11
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
12
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
APP-0966.4 Environmental Statement Appendix 10.2 - Botany Technical Report
APP-0976.4 Environmental Statement Appendix 10.3 - Bird Technical Report
APP-0986.4 Environmental Statement Appendix 10.4 - Dormouse Technical Report
APP-0996.4 Environmental Statement Appendix 10.5 - Marsh Fritillary Technical Report
APP-1006.4 Environmental Statement Appendix 10.6 - Otter and Water Vole Technical Report
APP-1016.4 Environmental Statement Appendix 11.1 - Historic Environment Technical Report
APP-1026.4 Environmental Statement Appendix 11.2 - Historic Environment Planning Compliance
APP-1036.4 Environmental Statement Appendix 12.1 - Geo-Environmental Information Part 1 of 6
APP-1046.4 Environmental Statement Appendix 12.1 - Geo-Environmental Information Part 2 of 6
APP-1056.4 Environmental Statement Appendix 12.1 - Geo-Environmental Information Part 3 of 6
APP-1066.4 Environmental Statement Appendix 12.1 - Geo-Environmental Information Part 4 of 6
APP-1076.4 Environmental Statement Appendix 12.1 - Geo-Environmental Information Part 5 of 6
APP-1086.4 Environmental Statement Appendix 12.1 - Geo-Environmental Information Part 6 of 6
APP-1096.4 Environmental Statement Appendix 13.1 - Hydrology, Flood Risk and Drainage Data Table
APP-1106.4 Environmental Statement Appendix 14.1 - Noise Supporting Information
Volu
me
6 En
viro
nmen
tal I
nfor
mat
ion
13
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
14
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
APP-1116.4 Environmental Statement Appendix 15.1 - Air Quality Assessment
APP-1126.4 Environmental Statement Appendix 16.1 - Clarification of Traffic and Transport Scope
APP-1136.4 Environmental Statement Appendix 16.2 - Brechfa Forest Construction Programme
APP-1446.4 Environmental Statement Appendix 17.1 - Review of Socio-economic, Recreation and Tourism Assessments
APP-1146.4 Environmental Statement Appendix 18.1 - EMF Calculations
APP-1156.5 Environmental Statement Scoping Report
APP-1166.6 Environmental Statement Scoping Opinion
APP-1176.7 Environmental Statement Publicity Requirements
Volu
me
7 O
ther
Med
ia
APP-1187.1 3D Model Visualisation Document
APP-1198.1 Planning Statement
APP-1458.1 Planning Statement Appendix 1 - Details of Other Consents and Licenses
APP-1208.1 Summary Planning Statement
APP-1218.1 Summary Planning Statement (Welsh)
APP-1228.2 Strategic Optioneering Report
Volu
me
6 En
viro
nmen
tal I
nfor
mat
ion
Volu
me
8 O
ther
Doc
umen
ts
15
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
REP3-0548.1A Planning Statement Appendix 1 - Details of Other Consents and Licenses
16
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
APP-1238.3 Draft Section 106 Agreement
REP3-0388.3A Draft Section 106 Agreement
APP-1248.4 Lifetime Costs Report
APP-1258.5 Construction Management Strategy Part 1 of 2
APP-1268.5 Construction Management Strategy Part 2 of 2
APP-1278.6 Construction Environmental Management Plan
REP3-0398.6.1 Construction Environmental Management Plan - Habitat Management Plan
APP-1288.7 Construction Traffic Management Plan
APP-1298.7 Construction Traffic Management Plan Figures 1.1 to 4.2
APP-1308.7 Construction Traffic Management Plan Appendix 1 PRoW Management Strategy
APP-1318.7 Construction Traffic Management Plan Appendix 2 Access Pro Formas
APP-1328.8 Transport Assessment
APP-1338.9 Outline Archaeological Written Scheme of Investigation
APP-1348.9 Outline Archaeological Written Scheme of Investigation Figure 1.1
APP-1358.10 DCO Documents Errata
APP-1478.10 Volume 6.4 - Appendix 14.1 Noise Supporting Information Errata
APP-1488.11 Sections 56 and 59 and Regulation 13 Compliance Certificates and Notice of Recipients Not Included in the Revised Book of Reference
Volu
me
8 O
ther
Doc
umen
ts
17
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
8.3B Draft Section 106 Agreement(unsigned)
REP4-0268.6A Construction Environmental Management Plan
18
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
APP-1498.12 Response to ExA Procedural Decision dated 6 July 2015 and Planning Inspectorate Section 55 Application Checklist
REP1-0299.1 Response to the Examining Authority's First Written Questions
REP1-0309.2.1 CA01 Appendix 1 Change Requests
REP1-0319.2.2 CA12 Appendix 1 Justification for Land
REP1-0329.2.3 CA13 Appendix 1 Organogram
REP1-0339.2.4 CA14 Appendix 1 Annual Report and Financial Statement
REP1-0349.2.5 CA18 Appendix 1 Land Owner Engagements
REP1-0359.2.6.1 DLV02 Appendix 1 Figure 1 Appendix 9.5 Residential Receptors
REP1-0369.2.6.2 DLV02 Appendix 2 Figure 1 Appendix 9.6 Footpaths
REP1-0379.2.6.3 DLV02 Appendix 3 Figure 1 Appendix 9.7 Classified Roads
REP1-0389.2.6.4 DLV02 Appendix 4 Figure 1 Appendix 9.8 Other Receptors
REP1-0399.2.7 DLV03 Appendix 1 Viewpoints
REP1-0409.2.8.1 DLV06 Appendix 1 Phillip Black - CV
REP1-0419.2.8.2 DLV06 Appendix 2 Ellie Davies - CV
REP1-0429.2.8.3 DLV06 Appendix 3 John Meehan - CVREP1-0439.2.9 DLV13 Appendix 1 Modified Table 9.1
REP1-0449.2.10 DLV15 Appendix 1 Table of Receptors
REP1-0459.2.11 DLV19 Appendix 1 Options Comparison
Volu
me
9 Ex
amin
atio
n Su
bmis
sion
s
19
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
20
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
REP1-0469.2.12 DLV20 Appendix 1 Report into Underground Cables
REP1-0479.2.13.1 DLV22 Appendix 1 Route Alignment Selection Report
REP1-0489.2.13.2 DLV22 Appendix 2 Route Alignment Selection Report Figures
REP1-0499.2.13.3 DLV22 Appendix 3 Route Alignment Selection Report Appendix 1.1
REP1-0509.2.13.4.1 DLV22 Appendix 4 Route Alignment Selection Report Appendix 1.2 Part 1
REP1-0519.2.13.4.2 DLV22 Appendix 4 Route Alignment Selection Report Appendix 1.2 Part 2
REP1-0589.2.13.4.3 DLV22 Appendix 4 Route Alignment Selection Report Appendix 1.2 Part 3
REP1-0599.2.13.4.4 DLV22 Appendix 4 Route Alignment Selection Report Appendix 1.2 Part 4
REP1-0529.2.13.5 DLV22 Appendix 5 Route Alignment Selection Report Appendix 2.1
REP1-0539.2.14.1 DLV24 Appendix 1 National Grid - Our Approach to Design and Routeing 2012
REP1-0549.2.14.2 DLV24 Appendix 2 National Grid - Approach to Options Appraisal 2012
REP1-0559.2.14.3 DLV24 Appendix 3 NG UG Policy New Connections
REP1-0569.2.14.4.1 DLV24 Appendix 4 CIGRE Guidelines Part 1
REP1-0579.2.14.4.2 DLV24 Appendix 4 CIGRE Guidelines Part 2
REP1-0609.2.15 DCO03 Appendix 1 Mitigation Table
REP1-0619.2.16 DCO24 Appendix 1 Brechfa Forest West Wind Farm Approved layout
REP1-0629.2.17 DCO33 Appendix 1 Email from Openreach
REP1-0639.2.18.1 DCO34 Appendix 1 S37 Consent Burry Port
Volu
me
9 Ex
amin
atio
n Su
bmis
sion
s
21
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
REP4-0469.2.15A DCO03 Appendix 1 Mitigation Table
REP5-0299.2.15B DCO03 Appendix 1 Mitigation Table
22
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
REP1-0649.2.18.2 DCO34 Appendix 2 Existing Assets Table
REP1-0659.2.18.3 DCO34 Appendix 3 Proposed Works to Existing Assets Plans
REP1-0669.2.19.1 EIA09 Appendix 1 Notes of NRW ecology meetings
REP1-0679.2.19.2 EIA09 Appendix 2 Follow up Email with NRW
REP1-0689.2.19.3 EIA09 Appendix 3 CCC Scoping Opinion to PINS
REP1-0699.2.19.4 EIA09 Appendix 4 CCC Response on Draft ES
REP1-0709.2.20.1 EIA13 Appendix 1 BFWWF Habitat Management Plan
REP1-0719.2.20.2 EIA13 Appendix 2 BFWWF Completed Unilateral Undertaking
REP1-0729.2.21 EIA17 Appendix 1 Stage 3 Consultation - NRW
REP1-0739.2.22 EIA20 Appendix 1 Conceptual Site Model
REP1-0749.2.23.1 EIA22 Appendix 1 Relevant Watercourses Part 1
REP1-0759.2.23.2 EIA22 Appendix 2 Relevant WatercoursesPart 2
REP1-0769.2.24 EIA26 Appendix 1 Outline Frac-out Contingency Plan
REP1-0779.2.25 EIA29 Appendix 1 SIA Guidelines
REP1-0789.2.26 EIA30 App1 Tables 20.1 & 20.2
REP1-0799.2.27 HA11 Appendix 1 HRA Figure 2 Otter Figures
REP1-0809.2.28 OM02 Appendix 1 Guide to the Application
REP1-0829.3.1 Statements of Common Ground - Carmarthenshire County Council
REP1-0839.3.2 Statements of Common Ground - Historic Environment - Dyfed Archaeological Trust and Cadw
Volu
me
9 Ex
amin
atio
n Su
bmis
sion
s
23
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
REP5-0309.2.18.2A DCO34 Appendix 2 Existing Assets Table
REP4-0479.2.18.3A DCO34 Appendix 3 Proposed Works to Existing Assets Plans
24
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
REP2-0369.3.3 Statements of Common Ground - Natural Resources Wales
REP2-0379.3.4 Statements of Common Ground - Landscape and Visual - Carmarthenshire County Council
REP2-0389.3.5 Statements of Common Ground - Historic Environment - Carmarthenshire County Council
REP2-0399.3.6 Statements of Common Ground - Landscape and Visual - Natural Resources Wales
REP3-0479.3.7 Statements of Common Ground - Development Consent Order - Carmarthenshire County Council
REP1-0279.4 Applicant’s Responses to Relevant Representations
REP1-0849.5 Position with regard to Statements of Common Ground
REP2-0309.6.1 Applicant’s Comments on Written Representations from Carmarthenshire County Council
REP2-0319.6.2 Applicant’s Comments on Written Representations from Other Parties
REP2-0329.7 Applicant’s Comments on Carmarthenshire County Council's Local Impact Report
REP2-0359.7A Applicant’s Comments on Carmarthenshire County Council's Local Impact Report
REP2-0339.8 Applicant’s Comments on Responses to Examining Authority’s First Written Questions
REP2-0349.9 Commentary of Changes to Draft Development Consent Order 3.1
REP3-0409.10 Commentary of Changes to Draft Development Consent Order 3.1A
REP3-0419.11 Applicant's Response to Open Floor Hearings
Volu
me
9 Ex
amin
atio
n Su
bmis
sion
s
25
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
26
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
REP3-0429.12 Applicant's Response to Compulsory Acquisition Hearing
REP3-0439.13 Applicant's Response to Issue Specific Hearing on Environmental Matters
REP3-0449.14 Applicant's Response to Issue Specific Hearing on the DCO
REP3-0459.15 Responses to Examining Authority Questions asked at Hearings
REP3-0469.16 Existing and Wire Line View Transparencies
Volu
me
9 Ex
amin
atio
n Su
bmis
sion
s
27
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
REP4-0279.17 Applicant’s Responses to Examining Authority’s Second Round of Written QuestionsREP4-0289.18.1 Updated Land Owner Engagement Table
REP5-0319.18.1A Updated Land Owner Engagement Table
REP6-0209.18.1B Updated Land Owner Engagement Table
9.18.1C Updated Land Owner Engagement Table
REP4-0379.18.2 Table of Plots with Unknown Ownership
REP4-0389.18.3 Copy of Metropolitan Board of Works v McCarthy (1874)
REP4-0399.18.4 Copy of Wildtree Hotels Limited v Harrow London Borough Council (2000)REP4-0409.18.5 Copy of Secretary of State's Decision and Examining Authority's Recommendation in Hinkley Point C Connection REP4-0419.18.6 Copy of Section 37 Recommendation and Secretary of State Decision for Legacy Substation to Oswestry Substation 132kV Connection
REP4-0429.18.7 List of Documents to be Certified by the Secretary of State
REP4-0439.18.8 Protective Provisions Table
REP4-0449.18.9 Letter from Mainline Pipelines agreeing to Protective Provisions
28
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
Volu
me
9 Ex
amin
atio
n Su
bmis
sion
s
29
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
REP4-0299.18.10 Plan Showing Location of Temporary Bridge
REP5-0329.18.10A Plan Showing Location of Temporary Bridge
REP4-0309.18.11 WPD Adaptation to Climate Change Reports (from June 2011 and May 2015)
REP4-0319.18.12 Due Diligence LetterREP4-0329.18.13 Consultation responses from the Ministry of DefenceREP4-0339.18.14 Consultation responses from the Civil Aviation AuthorityREP4-0349.18.15 WPD Company Directive on Pollution Prevention
REP4-0359.18.16 Special Report - The State of Environmental Impact Assessment Practice in the UK - IEMA (2011)
REP4-0369.18.17 The Energy Networks Association – Engineering Technical Report 136 (June 2007)
REP4-0459.19 Table of Proposed Amendments to Book of Reference
REP4-0489.20 Applicant’s Comments on Submissions made by Interested Parties at Deadline 3REP4-0499.21 Commentary of Changes to Draft Development Consent Order 3.1C
REP5-0339.22 Applicant’s Written Submissions following the Compulsory Acquisition Hearing held on Wednesday 10 February 2016
REP5-0359.22.1 Applicant’s Written Submissions following the Compulsory Acquisition Hearing held on Wednesday 10 February 2016 - Appendices
REP5-0349.23 Applicant's Written Submissions following the Issue Specific Hearing on the DCO held on Thursday 11 February 2016
REP5-0369.23.1 Applicant's Written Submissions following the Issue Specific Hearing on the DCO held on Thursday 11 February 2016 - Appendices
REP5-0259.24 Commentary of Changes to Draft Development Consent Order 3.1D
REP5-0379.25 HRA NSER Addendum: Location within DCO where mitigation is secured
30
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
Volu
me
9 Ex
amin
atio
n Su
bmis
sion
s
31
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
REP5-0389.26.1 Outline Tree Inventory Showing Trees Potentially Affected, Maps 1-9
REP5-0399.26.2 Outline Tree Inventory Showing Trees Potentially Affected, Maps 10-18REP5-0409.26.3 Outline Tree Inventory Showing Trees Potentially Affected, Maps 19-27REP5-0419.26.4 Outline Tree Inventory Showing Trees Potentially Affected, Maps 28-36REP5-0429.26.5 Outline Tree Inventory Showing Trees Potentially Affected, Maps 37-45REP5-0439.26.6 Outline Tree Inventory Showing Trees Potentially Affected, Maps 46-55
REP5-0289.27 Book of Reference Change Commentary 4.3B to 4.3C
CR-0029.28 Statement of Applicant Alternative Undergrounding Option in the Towy Valley
CR-0039.29 Addendum to the Environmental Statement - Potential undergrounding of an additional part of the Brechfa Connection
CR-0049.29.1 Addendum to the Environmental Statement FiguresPart 1: Figure 2.1 to 9.4CR-0059.29.2 Addendum to the Environmental Statement FiguresPart 2: Figure 9.5 VP09 to VP15CR-0069.29.3 Addendum to the Environmental Statement FiguresPart 3: Figure 9.5 AVP1CR-0079.29.4 Addendum to the Environmental Statement FiguresPart 4: Figure 9.5 AVP2CR-0089.29.5 Addendum to the Environmental Statement FiguresPart 5: Figure 9.5 AVP3CR-0099.29.6 Addendum to the Environmental Statement FiguresPart 6: Figure 9.5 AVP4CR-0109.30 HRA NSER Screening of Alternative Undergrounding Option in the Towy ValleyCR-0119.31 Draft Development Consent OrderCR-0129.31 Draft Development Consent Order (Tracked Change)
32
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
Volu
me
9 Ex
amin
atio
n Su
bmis
sion
s
33
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
CR-0139.32 Draft Explanatory Memorandum
REP6-0219.32A Draft Explanatory Memorandum REP6-0229.32A Draft Explanatory Memorandum (Tracked Change)
CR-0149.33 Statement of Reasons 9.33A Statement of Reasons
CR-0159.33 Statement of Reasons (Tracked Change)
9.33A Statement of Reasons (Tracked Change)
CR-0169.34 Alternative Undergrounding Option in the Towy Valley Works Plans - Section A
CR-0179.34 Alternative Undergrounding Option in the Towy Valley Works Plans - Section B
CR-0189.35 Diagram Illustrating Change OHL to UCG
CR-019Construction Traffic Management Plan Appendix 1
CR-0209.37 132kV OHL Work No 1 Profiles - Alternative Terminal Option
CR-0219.38 Consultation Statement
CR-0229.39 Trees and Hedges with the Potential to be Affected Plans Section ACR-0239.39 Trees and Hedges with the Potential to be Affected Plans Section BCR-0249.40 Master Landowner Communication TableCR-0259.41 Copies of Redacted Correspondence between BJP and Bruton KnowlesCR-0269.42 Commentary of changes to DCO Vol 03.1E
REP6-0239.43.1 Communication between the Applicant and Affected Persons who have not yet agreed Heads of Terms (Part 1 of 4)
REP6-0249.43.2 Communication between the Applicant and Affected Persons who have not yet agreed Heads of Terms (Part 2 of 4)
REP6-0259.43.3 Communication between the Applicant and Affected Persons who have not yet agreed Heads of Terms (Part 3 of 4)
34
-
Guide to the Application
Volume Main Submission 29 May 2015Documents Submitted21 August 2015
Documents Submitted25 September 2015
Documents Submittedfor Deadline 19 November 2015
Documents Submitted for Deadline 224 November 2015
Documents Accepted as late submissions to Deadline 2
Documents Submitted for Deadline 317 December 2015
Volu
me
9 Ex
amin
atio
n Su
bmis
sion
s
35
-
Guide to the Application
Documents Accepted as late submissions to Deadline 3
Documents Submitted for Deadline 41 February 2016
Documents Submitted for Deadline 518 February 2016
Documents Accepted as late submissions to Deadline 5
Documents Submitted24 February 2016
Documents Submitted for Deadline 617 March 2016
Documents Submitted for Deadline 731 March 2016
REP6-0269.43.4 Communication between the Applicant and Affected Persons who have not yet agreed Heads of Terms (Part 4 of 4)
REP6-0279.44 Applicant’s response to ExA’s questions regarding changes to the Book of Reference
REP6-0289.45 Applicant’s response to the ExA’s procedural decision letter of 1 March 2016
REP6-0299.46 Agreed notes from landowner meeting on Friday, 4 March 2016 to discuss alternative alignment and access options
REP6-0199.47 Book of Reference Change Commentary 4.3C to 4.3D
REP6-0309.48.1 Copies of correspondence with Affected Parties regarding unknown plots (Part 1 of 2)
REP6-0319.48.2 Copies of correspondence with Affected Parties regarding unknown plots (Part 2 of 2)
REP6-0329.49 Applicant response to RIES
REP6-0339.50 Response to Procedural Decision 27 February, Mr and Mrs Shaw
9.51 Heads of Terms(Tracked change)
9.52 Review of proposals to realign a section of OHL on land at Penwaun and Llwyn Newydd
9.53 Bruton Knowles correspondence direct with landowners
36