19 March 2012 Muon Week - Operations 1
Muon WeekMuon Operations Session
Introduction• Status and LHC Schedule• Detector Readiness + Preparation for Physics Running
– CSC, MDT, RPC, TGC
• Dedicated Runs, Weekly Operation, Planning etc.
March 19th 2012A. Polini
![Page 2: 19 March 2012Muon Week - Operations1 Muon Week Muon Operations Session Introduction Status and LHC Schedule Detector Readiness + Preparation for Physics](https://reader035.vdocument.in/reader035/viewer/2022072008/56649d8a5503460f94a70f37/html5/thumbnails/2.jpg)
19 March 2012 Muon Week - Operations 22
Status
• 3 months shutdown just over• Running since 2 weeks with 24/7 shifts• Many activities performed on Detector,
Infrastructure, HW + SW – MDT EE side C fully installed– RPC power, HV, gas, etc.– TGC chamber replacement + conditioning– MDT gas leaks and general overhaul– CSC Rod Firmware
– … and many more detailed reports afterwards
Priority:• Readiness for Highest Luminosity Running• Good and Stable Data Taking Conditions
![Page 3: 19 March 2012Muon Week - Operations1 Muon Week Muon Operations Session Introduction Status and LHC Schedule Detector Readiness + Preparation for Physics](https://reader035.vdocument.in/reader035/viewer/2022072008/56649d8a5503460f94a70f37/html5/thumbnails/3.jpg)
19 March 2012 Muon Week - Operations 3
LHC Schedule
Day LHC Tentative Planning:
1 injection & closed orbit
3 : ramp & squeeze probe
5 : injection of nominal bunch at ref orbit (flat).
7 start collimation setup at 450 GeV.
8 aperture at 450 GeV.
12 : setup first collisions
14 ramp & squeeze with nominal bunch.
16 : start collimation setup at 4 TeV
20 : multi-bunch injection
23 first stable beams 3x3.
![Page 4: 19 March 2012Muon Week - Operations1 Muon Week Muon Operations Session Introduction Status and LHC Schedule Detector Readiness + Preparation for Physics](https://reader035.vdocument.in/reader035/viewer/2022072008/56649d8a5503460f94a70f37/html5/thumbnails/4.jpg)
19 March 2012 Muon Week - Operations 44
Agenda
![Page 5: 19 March 2012Muon Week - Operations1 Muon Week Muon Operations Session Introduction Status and LHC Schedule Detector Readiness + Preparation for Physics](https://reader035.vdocument.in/reader035/viewer/2022072008/56649d8a5503460f94a70f37/html5/thumbnails/5.jpg)
19 March 2012 Muon Week - Operations 55
Cosmic Run (Solenoid ON Toroid OFF)• Conditions:
– Solenoid ON, Toroid OFF– MDT/CSC Ready (HV/LV OK), RPC Ready (but ~80% of HV channels ON), TGC Off
• Trigger:– RPC lower Sectors (10-16) Mu_4 mu_11, Calibration Stream on
• Minimum participating components: Muon ID (SCT+TRT) • List of Runs:
198923 Mon Mar 12 2012 02:04:06 − 09:43:57 Solenoid ramping down from 2:30 am
198920 Sun Mar 11 2012 22:54:35 − Mon Mar 12, 01:29:07Physics_Cosmic_Muon Stream ON
198906 Sun Mar 11 2012 10:34:53 − 22:28:25 198902 Sun Mar 11 2012 01:51:58 − 09:18:17
NO CAL + NO PIX198900 Sun Mar 11 2012 00:34:37 − 01:33:45198898 Sat Mar 10 2012 22:58:18 − Sun Mar 11, 00:24:14
No Calorimeter198896 Sat Mar 10 2012 19:33:50 − 22:02:16
PIX standby198892 Sat Mar 10 2012 11:54:32 − 19:14:34
HLT passthrough 198890 Sat Mar 10 2012 08:52:03 − 11:31:18
Run Restarted198886 Fri Mar 09 2012 20:40:53 − Sat Mar 10, 08:31:11
LVL1 Prescales OK198807 Fri Mar 09 2012 10:53:19 − 11:50:44
1st run ON (CAL + PIX included)
All events available on the tier0 Many Thanks to Data Preparation
![Page 6: 19 March 2012Muon Week - Operations1 Muon Week Muon Operations Session Introduction Status and LHC Schedule Detector Readiness + Preparation for Physics](https://reader035.vdocument.in/reader035/viewer/2022072008/56649d8a5503460f94a70f37/html5/thumbnails/6.jpg)
19 March 2012 Muon Week - Operations 66
Beam Splashes
• Beam 1 @ 23:37, March 14th
– run 199193, lb 200, event 12287 BCID 0 (1)– trigger 1 BC earlier
• Beam 2 @ 00:15 March 15th
– LB 238 ev 14656 BCID 202 (200) – “Too many hits in events” for many SSW at
BCID = 200 for TGC – Occupancy peak in all the MDT crates @ BCID
= 200 – Larg – triggering 1 or 2 BC earlier
• Data available for Analysis• EE status?
Improvements for next official ones?
MDT Occupancy
RPC DCS (peaks)
![Page 7: 19 March 2012Muon Week - Operations1 Muon Week Muon Operations Session Introduction Status and LHC Schedule Detector Readiness + Preparation for Physics](https://reader035.vdocument.in/reader035/viewer/2022072008/56649d8a5503460f94a70f37/html5/thumbnails/7.jpg)
19 March 2012 Muon Week - Operations 7
Last Week Operation and Planning
• No Muon planning Meeting tomorrow March 20th
• Friday afternoon (Solenoid + Toroid slow dump)– DSS TGC, CSC, MDT – Magnets up again from Sunday ~14:00– TGC restart took longer (excluded)
• Access Requests:– RPC: Gas system (adjust exhaust bubblers) + HV checks– TGC: Investigate ROD A12 problem
• Open Issues from Atlas Run Meeting:– TGC:
• Problems with recovery/removal timeout• Problems at initialization• TTC partition restart
– RPC:• synchronization and killed trigger sectors
– CSC: • DQ Agent/Gnam Crash