194 Avenue: World’s Tallest Causeway*
Presented to the esteemed attendees of the inauguralTransportation Connects Alberta Conference and Tradeshow
1 April 2019
Jack MasonDave Galić
*(probably)
2
Overview – InterimRed Deer 145km
Edmonton Airport ~150km
3
Overview – Interim
4
5
6
Future Interchange
• Access to North leg of Macleod Trail only• 30% Design is complete• Straightens out 194 Ave
7
Future Interchange
8
Profile
• Up to 15m of fill• 540,000m3 of imported dirt• World’s Tallest Causeway*
Terrestrial Wildlife9
10
Terrestrial Wildlife
11
Terrestrial Wildlife
12
13
14
15
Northern Leopard Frog – Heard, but not Seen
16
Cattle Grazing
17
Algae Bloom
18
Animal Remains Trigger Warning
19
20
21
22
23
24
Kevin – Sin City25
26
Wetland Regulatory27
• Desktop Precipitation and historical photograph analysis
• Field Assessment (ABWRET-A)
• Wetland Assessment and Impact Report (WAIR)
• Assessment of Permanence (Public Lands Act)
• Water Act Application• Public Notice• Compensation
28
Original Concept: Terrestrial / Aquatic Culvert
~50m long
29
Original Concept: Terrestrial / Aquatic Culvert
~70m long
Original Concept: Terrestrial / Aquatic Culvert
• Too long: 70m vs. 35m• Unfavourable openness ratio• Staging tricky• Geotechnical challenges
30
31
32
33
34
Separate Terrestrial and Aquatic Bridges
35
36
Terrestrial Wildlife Patterns
37 Diversion Poles
38
Construction Begins39
40
Savannah Sparrow Nest Protection
41
Red-Tailed Hawk Nest Protection
42
Turbidity Curtain
43
Fish Salvage
44
Rare Plant Transplant: False Western Gromwell
Rare Plant Transplant 45
46
Leafy Spurge
47
Riparian Topsoil Stockpile
48
• Slope Stability through the slough
• Large amount of settlement with a two year construction schedule• Wick Drains• Top-Down Construction
Geotechnical Challenges
49
Working Platform Construction
50
Working Platform Construction
51
Working Platform Construction
Why Vertical Wick Drains?52
Thurber estimated that to reach 1900mm of settlement, it would take:19 years without wick drains vs.300 days with wick drains
https://www.youtube.com/watch?v=gvPVka0tO4U
Wick Drain Animation53
54
Wick Drains
55
Wick Drain Challenges
56
Wick Drain Pre-Drilling Rig
57
Wick Drain Installation
58
Wick Drain Installation
~ 208,000 linear metres of wick drains were installed
59
Settlement
Preload
Quiz Time: Embankment Quantities in Candy60
Tallest fill height in gummy bears?
Number of skittles required to fill the causeway (from CPR to Macleod Trail)? 317,146,676,970~4.5 years’ worth of annual global production
boingboing.net
flickr.com
668
Settlement Requirements
62 Top Down Construction of the World’s Tallest Causeway*
Piling
63 Top Down Construction of the World’s Tallest Causeway*
Abutments
64 Top Down Construction of the World’s Tallest Causeway*
Girders
65 Top Down Construction of the World’s Tallest Causeway*
Preload Fill Removal
66 Top Down Construction of the World’s Tallest Causeway*
Preload Fill Removal
67 Top Down Construction of the World’s Tallest Causeway*
Shear Key Construction
68 Top Down Construction of the World’s Tallest Causeway*
MSE Wall Construction
69 Top Down Construction of the World’s Tallest Causeway*
Final Grouting
70
Planting Riparian Vegetation
71
Finishing TouchesGreen Side UpRiparian Vegetation
72
73