1e. tsitrone pwi tf meeting, 4-6/11/2009, warsaw euratom 2010 wp for the pwi tf : tasks agreements...

25
1 E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Eurato m 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA : Timeline Meetings / Reporting (2008) WP2010 : selection criteria Work Programme 2010 : Main orientations Tasks agreements for 2010 TF and SEWG leadership Summary

Upload: destiny-hood

Post on 27-Mar-2015

218 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

Euratom2010 WP for the PWI TF :Tasks agreements and priority support

• The EU PWI TF under new EFDA :• Timeline • Meetings / Reporting (2008)• WP2010 : selection criteria

• Work Programme 2010 :• Main orientations• Tasks agreements for 2010• TF and SEWG leadership

• Summary

Page 2: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

2E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

Euratom

The PWI TF under new EFDA

Page 3: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

3E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

Euratom

Call for Participation for n+1 WP (summer)

Task agreements drafted for n+1 WP (nov)Implemented by end of the year

SEWGs meetings

Definition of the Work Program for the next year(s)

Annual PWI TF meeting, reporting on current WP

Timeline for the PWI TF

Next call : summer 2010 for WP2011

Presentation of the n+1 annual WPReporting on n-1 WP

to EFDA SC (main lines – ceiling) (feb-march)EFDA SC (Feb-March)

Answer to call (early sept)Call assessment by PWI TF (end sept)

Presentation to EFDA SC for approval (oct) EFDA SC (october)

Page 4: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

4E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

EuratomMeetings / Reporting

Meetings :• SEWG meetings : science oriented, large part for discussion, plans for collaborative work, joint SEWG meetings (fuel retention / fuel removal/ dust)

• Annual meeting : • SEWG reports : science oriented + table indicating degree of completion • EU/ International / ITER context (TG materials) • « free » session for topics not covered by SEWG• feedback from associations on organisation etc …• discussion of next year programme

Reporting :• Baseline support : • slides shown at annual meeting + template (degree of completion, highlights, publications)• Priority support : • reports to be sent by associations to SEWG leaders, justification of ppy + hardware, scientific highlights, publications …

Page 5: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

5E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

EuratomReporting 2008

Report to STAC 2009 on activities 2008:

The EU TF PWI has remained a leading contributor to the field of plasma wall interaction worldwide, focussing its work on priority PWI issues for ITER through the activities of its special expert working groups (SEWGs). A significant advantage in the EU PWI programme is the broad range of experiments, which allow the study of separate aspects of the problem and thus to address the most important ITER issues (choice of plasma facing components, fuel retention, ELMS and disruptions).

• 2008 WP successful (5 % delayed), TA2009 launched

• Scientific success demonstrated (>100 publications for 2008, strong participation in PSI and IAEA 08)

Page 6: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

6E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

EuratomCall 2009 for WP2010 : selection criteria

• Baseline support : ceiling (~ 90 ppy) but no strong reduction so far

• Priority support : ceiling for ppy (~ 21 ppy) and hardware (~ 400 kEuros) STRONG SELECTION (factor 2)

• Rejected : not in the scope of the PWI TF WP, JET related work

• Reduced ( shifted to BS) : • non collaborative work (unless priority like T/Be related work) + added value of the collaboration• no associated effort in BS• ceiling limit

• Justification / Recommendation under Ecom

• Ecom : new challenging tool ! Quality of task description ?

Page 7: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

7E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

Euratom

2010 WP for the PWI TF

Page 8: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

8E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

EuratomMain orientations for 2010-2011

• Strengthening of modelling for extrapolation to ITER and DEMO – Interpretative modelling for benchmarking tools used for ITER simulations

(SOLPS, ERO, DIVIMP …)– in close connection with ITM-TF (code development)

• 2 years WP : 1 call for 2010-2011 TA2010 and TA2011

• Integrated plasma operation : impact of impurity seeding – erosion, mixed material, fuel retention …

• Including recent ITER requests– W R&D – IC wall conditionning – divertor re-attachment heat loads – disruptions/runaways

• Bilateral collaborations :– mixed materials : PISCES (US) EFDA PWI TF – material damage : plasma guns (RF) F4E, but modelling + dust = PWI TF

Page 9: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

9E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

Euratom

0

1

2

3

4

5

6

Fuel r

eten

tion

Fuel r

emov

alDus

t

Mat

migr

ation

High Z

+ liq

uid

Mixe

d m

at

Disrup

tions

+ E

LMs

WP 2009TA 2009WP 2010TA2010

High Z

Disruptions

EFDA emerging techno + F4E

Total TA2009 : 22.6 ppy (+ 4 ppy for new associations)Total TA2010 : 24.5 ppy. No cut for PWI.

ppy

7 TAs for 2010

Page 10: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

10E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

EuratomTA 1 : Fuel retention(FOM, FZJ, IPP, CEA, MedC, MHST, TEKES, VR)

• Retention in C : TS (DITS project, CEA, VR, IPP, MHST), Textor (FZJ, MHST, VR), porosity of CFC (MedC)

• Retention in W : AUG (post mortem + particle balance, boron, IPP, Tekes), lab studies : dpa (IPP, FOM), transients (FOM)

• Retention in mixed materials : W/C (FOM, FZJ, PISCES), Be/W/C (IPP, MedC)

• Gaps : CEA, FZJ, post mortem + modelling

• Predictions for ITER T retention : ERO (FZJ), multi machine scaling (IPP)

PS : 3.1 ppy, hardware : 30 kEuros

Page 11: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

11E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

Euratom TA 2 : Fuel removal

(ERM, CEA, FZJ, IPP, IST, VR, SCK CEN, CIEMAT, MHST, IPPLM, VR, MedC, ENEA)

• ICWCTS, Textor, AUG (CEA, FZJ, IPP, IST, ERM) •Chemical cleaning : GDC, oxygen, nitrogen, ammonia : SCK CEN, CIEMAT, FZJ, VR, ENEA, MHST

• Photonic cleaning : Laser (break up products, in situ demo) : FZJ, IPPLM, VR, CEA, CIEMAT

• Removal in gaps : FZJ, IPP, MHST (chemical), MedC (torch), CEA (laser), modelling (IPP)

• Layers : MedC

PS : 3.5 ppy, hardware : 20 kEuros

Page 12: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

12E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

EuratomTA 3 : Dust

(IPP, VR, CEA, IPPLM, FZJ, FOM, ENEA)

• Multi machine dust collection and analysis : AUG, TS, Textor (FIB in IPP, VR)+ lab experiments (laser IPPLM)

• Dust during operation : Fast cameras AUG (IPP, CEA), Textor (FZJ, VR aerogel), FTU (ENEA), electrostatic dust detectors : CEA

• Dust generation and transport : FOM, CEA (modelling), FZJ (dust injection), UKAEA

PS : 1,65 ppy, hardware : 32 kEuros

Page 13: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

13E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

Euratom TA 4 : material migration

(CEA, CIEMAT, FZJ, Tekes, VR, FOM, IPP, ÖAW, DCU, IPPLM, IPP.CR, CY, MedC)

• Global material migration (first wall + divertor) : CEA (new Langmuir probes, modelling), FZJ, AUG (IPP, Tekes, IPPLM), FOM

• Tracer experiments (13C + W … ) : Textor (VR), AUG (modelling Tekes), CIEMAT

• Erosion / redeposition / re-erosion : FOM/MedC, FZJ, ÖAW, IPP.CR (impurity seeding), MHST, CY (chemical erosion modelling)

• Modelling : 3D start up (EMC3-Eirene, ERO) : IPP, FZJ, VTT (Textor, AUG)ERO benchmark (FZJ, VTT, FOM) : PISCES, Magnum, AUGGrid extension + benchmark (DIVIMP, B2E …) : IPPImpurity transport on MAST (DCU)Eirene ion : ÖAW, CEA, FZJ

PS : 3.8 ppy, hardware : 90 kEuros

Page 14: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

14E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

Euratom TA 5 : high-Z + liquid limiters

(SCK CEN, ENEA, FOM, FZJ, IPP, IPPLM, VR, FZK, MedC, IST, AEUL, CEA)

• Integrated scenario (impurity seeding, ramp up/down, RF …) : IPP, ENEA, FOM, W transport modelling (FZJ, IPP, CEA)

• W diags : IPP, CEA (IR), FZJ (spectroscopy), MedC (W coatings)

• W exposure to ITER like conditions (retention, damage, neutron) : SCK CEN (Vision), FOM (transients + impurity seeding), FZJ/VR, IPP/IPPLM (surface morphology), FZK (damage modelling)

• W coatings : ENEA, IPP

PS : 5,65 ppy, hardware : 143 kEuros

• Operation with liquid metals PFCs (retention, power loads, plasma

performance …) : ENEA, IST, AEUL, FZK (modelling)

Page 15: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

15E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

EuratomTA 6 : mixed materials

(SCK CEN, FZJ, IPP, MedC, VR, FOM, Tekes, ÖAW, ENEA, CRPP)

• Mixed layers analysis (composition, fuel retention …) : ÖAW, ENEA (properties deposited layers),FZJ / VR, CEA, CRPP (W/C, gaps), IPP (tokamak deposits)FOM / FZJ (D + He),IPP (ternary with Be, nitrogen), TEKESMedC (Be/C, Be/W, Be/C/W layers)

• Modelling : FZJ (ERO for PISCES), TEKES (MD + ERO upgrade on material mixing models), CEA (MD on Be/W, SOLPS), IPP, ÖAW

PS : 2.25 ppy, hardware : 45 kEuros

Page 16: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

16E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

EuratomTA 7 : Transients(CEA, FZJ, IPP, FOM, ÖAW, UKAEA, IST, FZK)

• Power loads during disruptions (including runaways) : CEA, IPP, FOM, UKAEA, IST

• Massive gas injection : CEA, FZJ, UKAEA, IST, IPP (modelling), FZK (runaway modelling)

PS : 2.8 ppy, hardware : 70 kEuros

• Heat flux during ELMs : UKAEA, IPP, FZJ (fast ions), ÖAW (turbulent transport)

• ELM mitigation : FZJ (3D modelling for RMP), IPP

• Heat flux inter ELMs : CEA, IPP, ÖAW (turbulent transport)

Page 17: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

17E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

EuratomPWI TF leadership

• TF leadership (2009-2011) : leader E. Tsitrone (CEA), deputy R. Neu (IPP)

• SEWGs (2010) : • Material migration : S. Brezinsek (FZJ)• High Z : G. Maddaluno (ENEA)• Mixed materials : K. Krieger (IPP)• Fuel retention : vacant

deadline for application : November 13• Fuel removal : P. Coad (UKAEA)• Dust : M. Rubel (VR)• Transients : M. Lehnen (FZJ)

• TF leadership (leader + deputy) (0.5 ppy) : EFDA SC on proposal by EFDA leader, 3 years term 2009-2011• SEWG leadership (0.25 ppy) : EFDA on proposal from PWI TF leadership, term = duration of the call (1 year)

Page 18: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

18E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

EuratomSummary

• WP2010 : 7 TAs to be implemented soon• Successful WP2008 no cut for 2010 (~ 21 ppy and ~ 400 kEuros)• Strong selection on PS (ECOM quality of task description )• Interpretative modelling, impurity seeding• Effort needed on disruptions/runaways

• PSI 2010 : acknowledgement EU PWI TF (see PWI webpage)

• Preparation for 2011 WP : starts … now ! list of priorities SEWGs (new ones ? merging ?) TAs ? estimate of ppy/hardware

• Your feedback is important :• call / TAs / reporting / ECOM• channel through contact persons

Page 19: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

19E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

Euratom

Annex

Page 20: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

20E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

Euratom7 TAs for 2010

Fuel retention : TA-1: Fuel retention as a function of wall materials foreseen for ITER

• Fuel removal : TA-2: Fuel removal compatible with retention in different and mixed first wall materials

• Dust : TA-3: Dust generation and characterization in different devices

• Material migration : TA-4: Erosion, transport and deposition of first wall impurities

• High Z : •TA-5: Development of the PWI basis in support of integrated high-Z scenarios for ITER. Liquid plasma-facing components

• Mixed materials : TA-6: Expected alloys and compounds and their influence on PWI processes

•Transients : •TA-7: Mitigation of disruption loads for ITER. Heat load in ITER relevant ELM scenarios

Page 21: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

21E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

EuratomITER high priority research needs :strongly PWI related

[D. Campbell, ITPA CC meeting june 2008]

1. Disruption/ Runaway Mitigation1. Disruption/ Runaway Mitigation

2. ELM Control/ Mitigation2. ELM Control/ Mitigation

3. Plasma Facing Materials3. Plasma Facing MaterialsPhysics basis for ITER reference scenarios with W/ Be PFCs ; C removal

4. Scenario Development4. Scenario Development

5. Diagnostics5. DiagnosticsDust / Hot dust ; divertor erosion ; mirrors ; H/D/T inventory

Beryllium

Tungsten

Carbon

Heat loads, runaway electrons: reduction > 1 order of magnitude

reduction > 1 order of magnitude

Page 22: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

22E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

Euratom

1. Disruption/ Runaway Mitigation1. Disruption/ Runaway Mitigation

2. ELM Control/ Mitigation2. ELM Control/ Mitigation

3. Plasma Facing Materials3. Plasma Facing MaterialsPhysics basis for ITER reference scenarios with W/ Be PFCs ; C removal

5. Diagnostics5. DiagnosticsDust / Hot dust ; divertor erosion ; mirrors ; H/D/T inventory

Heat loads, runaway electrons: reduction > 1 order of magnitude

Fuel retention

Fuel retention Fuel Removal

Transient heat loads

ELMs and disruptions

Material erosion and transport in tokamaks

Materials

Material migration

High-Z Materials

ITER-like Material Mix

Dust in fusion devices

Dust

EU-PWI TF : targeted at ITER through 7 SEWGs

Material Erosion W R&D

Fuel retention

Dust

Heat loads

ITPA Div SOL : 5 topics

Page 23: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

23E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

Euratom

1. Disruption/ Runaway Mitigation1. Disruption/ Runaway Mitigation

2. ELM Control/ Mitigation2. ELM Control/ Mitigation

3. Plasma Facing Materials3. Plasma Facing MaterialsPhysics basis for ITER reference scenarios with W/ Be PFCs ; C removal

5. Diagnostics5. DiagnosticsDust / Hot dust ; divertor erosion ; mirrors ; H/D/T inventory

Heat loads, runaway electrons: reduction > 1 order of magnitude

Fuel retention

Fuel retention Fuel Removal

Transient heat loads

ELMs and disruptions

Material erosion and transport in tokamaks

Material migration

Material migration

High-Z Materials

ITER-like Material Mix

Dust in fusion devices

Dust

Towards increased coordination …

F4E

F4E

EFDA Emerging Techno

Diag TG

MHD TG, ITM TF

H & CD TG

US : PISCES

US : PISCES

RF : plasma guns

RF : plasma guns

Page 24: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

24E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

Euratom

Task Force Plasma-Wall InteractionMain orientations at

Annual General MeetingContact Persons from 23 associations+ JET TF E and FT, EFDA, F4E, ITER IO

ITPA divertor and SOL (co-chair)

Special Expert Working GroupsAnnual specialised meeting of SEWG members

Joint meetings (mat migration + retention + removal)

EU PWI TF: mature organisation

Associations Baseline work programme

Priority support

EFDA

ITM-TFTG MHDTG H&CD (ICWC)TG diags (LIBS)TG MaterialsTG Transport

Emerging techno(Dust & T)

(Disrup.)

Page 25: 1E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw Euratom 2010 WP for the PWI TF : Tasks agreements and priority support The EU PWI TF under new EFDA :

25E. Tsitrone PWI TF meeting, 4-6/11/2009, Warsaw

EuratomHighlights of 2008

Strong participation in PSI and IAEA 2008 > 20 oral papers (2 PSI review) [see talk] , > 100 publications

ITER fuel retention ITPA DivSOL • MIT meeting + IAEA + final report

Joint meeting (ITM / MHD / PWI) on disruptions

Preparation of WP2009 in new EFDA frame• Call for interest launched in Summer 08• Task agreements finalised early 09

Annual meeting Frascati Oct. 2008• reporting : WP2008 95% executed (5% delayed)