1mba3rd prtoject appraisal
TRANSCRIPT
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
1/116
PROJECT APPRAISALPROJECT APPRAISAL
SARITA THAKURSARITA THAKUR
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
2/116
Meaning and definitionMeaning and definition Assessment of a project in terms of its economic, social and financial viabilityAssessment of a project in terms of its economic, social and financial viability
A lending financial institution makes an independent and objectiveA lending financial institution makes an independent and objective
assessment of various aspects of an investment propositionassessment of various aspects of an investment proposition
It is defined as taking a second look critically and carefully at a project by aIt is defined as taking a second look critically and carefully at a project by a
person who is in no way involved or connected with its preparation. He isperson who is in no way involved or connected with its preparation. He is
able to take independent, dispassionate and objective view of the project inable to take independent, dispassionate and objective view of the project in
totality, along with its various componentstotality, along with its various components
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
3/116
UNIT - IIPROJECT APPRAISAL
INTRODUCTION PROJECT APPRAISAL:
1. Technique to analyse if the project is feasible or not.2. It helps in recognizing needs and problems, and their early
analysis3. A tool fordecision making4. Identifying input, output parameters and criteria for evaluating
systems.5. Evaluating feasibility in terms oftechnical, financial and
economic practicability.
6. Developing and implementation of system so designed interms of- Engg. Calculations
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
4/116
- Specification of finalization- Production, manufacturing
Installation and commissioning
SALIENT ASPECTS OF PROJECT APPRAISAL
a. Need - New or improvedb. Realisability - Cost/benefit termsc. Practicability - Technically, Financially economically viable.d. Optimality: Project to be best alternativee. Uncertainty : Probability of risk and cost of information to
achieve greater certaintyf. Controllability - Needs a feed back loop to review update and
keep system on rough track.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
5/116
Feasibility Study:
It involvedcreating, identifying, brain storming feasibility of
ideas and then selecting to prove further one or more feasiblesolutions.- Thenprilimary design, optimal design (best alternatives)- Detailed design (a complete description of projects for its
implimentation.- Lastly planning for production:
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
6/116
(ii) Environment (Business) Interest, Insurance,
Legal, Regulatory, Pollution.
b. Project Output(i) Desired(ii) Undesired
(i) Desired: Desired could involved physical quantities ofproducts how much, how many, could also involve valuejudgment status, comfort, Aesthetic Appeal (Keeping userin view undesired)
(ii) Undesired: Undesired Pollution, Waste material, WasteEnergy, Danger (Bhopal Gas Tragedy, Nuclear Explosion).
Discomfort to people living in vicinity.
c. Design Parameters: Like features attributes that wouldaffect behavior and performance. Most common ar
physical size, weight, etc.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
7/116
Feasibility Study has following sequence of events (Parts)
Need Analysis: Define objectives of the projects. New oimproves.
Project Identification: Quantifies input, output, designparameters.
a. Project Inputs:
(i) Purposeful Controllable- Uncontrollable
Controllable: Man hours, Capital Inflow,Activity Analysis:
Uncontrollable: Cost of Raw Material, Reliability of
Technology, Availability of Power, Govt.& Political Interference.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
8/116
d. Constraint Specification: on input, output, designparameters which could be essential to evaluate the alternativesolutions. Measure of the values indicate range of accepvalues.
e. Evaluation Criteria: Total revenue operating cost gross/ netprofit, ROI/ EOI etc.
3. Practicability Analysis: Idea to eliminate the concepts thatare not feasible. Are these operational financeableEconomical, Physically realizable, Politically acceptable ,
Physically Realizable which alternatives needs the
solutions within the specified parameters.
Financial Realizability: (i) Will the money requiredcome as per time frame.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
9/116
(ii) Sources of Capital Inflow who where from:4. Economic Practicality :
(i) Even a financially feasible may not beeconomically practical.
(ii) Economic Feasibility Study of alternativesolutions by constraints operating cost, Maintenancand Spare part expenditure.
(iii) Total revenue that would accrue over the operational
life of systems, (i.e. what is thebreak even point oroptimum point of economic operations of the project)
We will consider those alternative solutions to be
economically feasible that meet the specified rates ofreturn on investment.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
10/116
5. Social and Political Realizeability : The projectmay be physically, Financially, Economically feasible,but may encounter social at political obstacles.
Normally in case of large projects, there are additional
considerations ofhealth (Polio Campaign, Malaria, TB,CNG Buses) education (private and foreign universities)Welfare (METRO RAIL, Realignment over the rangearea, Civil Nuclear Technology).
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
11/116
Feasibility Study: A Schematic Diagram
Yes
Initial Screening
Is the Idea Prima Facie Promising ?
Plan Feasibility Analysis
Generation of Ideas
Conduct Market Analysis Conduct Technical AnalysisBasic and functional feasibliity
Terminate
Conduct Financial Analysis
Risk./ Return
PreliminaryPractica
lAnalysis
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
12/116
Yes NO
Is the Project Worthwhile?
Prepare Funding Proposal
Including optimality and controllability
Conduct Economic and Ecological Analysis
Social & Political Realisability
Terminate
St f j tSt f j t
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
13/116
Steps for projectSteps for project
appraisal/Aspects of projectappraisal/Aspects of project
appraisalappraisal Economic AspectsEconomic Aspects Technical AspectsTechnical Aspects
Organisational AspectsOrganisational Aspects Managerial AspectsManagerial Aspects
Financial AspectsFinancial Aspects
Market/Commercial AspectsMarket/Commercial Aspects
K i i P j A l i
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
14/116
Key issues in Project AnalysisPotential Market
Market AnalysisMarket Share
Technical ViabilityTechnical Analysis
Sensible ChoicesRisk
Financial Analysis
ReturnBenefits and Costs in Shadow Prices
Economic AnalysisOther Impacts
Environmental DamageEcological AnalysisRestoration Measure
T h i l A i l
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
15/116
Technical AppraisalBy technical appraisal of project, we mean an assessment of its basic technical and
functional feasibility of project (Road under/over bridge)Besides costs and schedules, the project performance depends on how well the project ismeeting the technical requirements of the end project (connect village to stadium)
- THREE STAGES OF TECH APPRAISAL
(i) Detailed technical Appraisal
Which include describing the details of the assignment
and the key property.
It l i l d d ibi th d fi i i f ti l
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
16/116
It also includes describing the deficiencies of particularacclamation.
The detailed technical appraisal method helps incommenting on the reviewers action, analysis and
conclusions.(ii) Exceptional Technical Appraisal appraisal reviews records only significant and exceptional
findings and action take by the reviewer. The exceptional review is often used forhigh level
reviews within an organization when the first level review isa narrative report.
(iii)Form Technical Appraisal In form review, further abbreviates the documentation
associated with reviewing an appraisal report. Forms are developed for specific institutional or agency
needs and the Standard Appraisal Review
R t f i b i id l t d b
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
17/116
Report from is becoming more widely accepted by manyusers.
Factors Effecting Technical Appraisal
(i) Layout:- Layout of the project includes description of theproject in terms of what they represent and when theyoccur,who has authorized it, number of people who willhandle. It also states where quality control will be exercised. A description and explanation of the methods of that
will be used to monitor progress e.g. bar chartscould be used.
For Example
Weekly progress meeting to exercise control over theproject.
(ii) L ti Th i k f t th t i fl l ti
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
18/116
(ii) Location:- The nine key factors that influence locationof a project are: (keep NANO Car Project In Mind)
- Costs- Infrastructure around the location
- Labour Characteristics- Wage rates- Motivation of workers- Telecommunication systems- Government stability and industrial relations laws
- Protection of patentsA availability of management resources and specific skills
and system and integration costs.These factors have an impact on management decisions
and governments policies.
G t li i R l t b i l d
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
19/116
Government policies: Regulatory barriers may precludethe use of innovative technologies e.g. some reservation forSME Sector (Now only 3s items)
Types of equipment or processes: Equipments are
basically of two types temporary and permanentequipments. (Olympic stadium in China)
The availability and quality of equipments affect thetechnical appraisal.
Appropriateness of Local Conditions: The project should
be adaptable to local technical and environmentalconditions, such as voltage, dust, temperature, humidity, etc.
The appropriate supply of material and equipments forkeeping the project working should be available in
proximity.
I t f E i t Th t ti l i t f th
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
20/116
Impact of Environment: The potential impact of theproject on the human and physical environment is examinedto make sure that nay adverse effects can be controlled orminimized e.g. pollution.
Approach Followed: Procedures for obtainingengineering, architectural, or other professional services areexamined.
Risk Factor: It is necessary to identify the risks associatedwith the project and estimate the scale of risk. There should
also be contingency plans in place to minimize the risk ofproject failure or of a major gap between whats promisedand whats delivered.
Cost Estimated: Technical appraisal is a review of the cost
estimates of the engineering and maintaining the project.Cost estimates also determine whether technical appraisal isaccurate within an acceptable margin.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
21/116
Plant CapacityPlant Capacity
Product MixProduct Mix
Structure and civil WorksStructure and civil Works Schedule of project implementation.Schedule of project implementation.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
22/116
Technical AspectsTechnical Aspects
Site and Location: RM supply, proximity to markets, transportationSite and Location: RM supply, proximity to markets, transportation
facility, power supply, manpower, water, government policies,facility, power supply, manpower, water, government policies,
labour laws, climate, taxeslabour laws, climate, taxes
Size of plant/scale of operations: Technological capacity isSize of plant/scale of operations: Technological capacity is
standardised for achieving economies of scale, low demand or lessstandardised for achieving economies of scale, low demand or less
resource availability result in economies of scaleresource availability result in economies of scale
Technical feasibility: Technology selected, availability ofTechnical feasibility: Technology selected, availability ofinfrastructure, plant layout, project implementation schedules etcinfrastructure, plant layout, project implementation schedules etc
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
23/116
This can be viewed as whatever lies outside the project
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
24/116
This can be viewed as whatever lies outside the project,but that which can affect and be affected by the operationsof the project.
In project parlance the environment means much more
than just the weather.For example, for automobile environment, we can considerthe roads and highways; petrol pumps and servicingstations, etc. need to be included in our definition of theautomobile system.
When we say that something lies outside the project, andhence constitutes its environment, we mean that the projectcan do relatively little about its environmentscharacteristics or behaviour.
Identification of the environment depends on the answersto the following two questions.
1. Can I do anything about it?
2 Does it affect my situation or objectives?
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
25/116
2. Does it affect my situation or objectives ?If the answer to the first is No, and that do the second isYes, then it is the environment.
Characteristics of the Environment
The environment provide, given orfixed inputs to theproject.
It is also affected, directly or indirectly, by the outputsfrom the project;
Hence, it has a dynamic influence on the project or bythe project.
However, less attention is paid on environment because of
two reasons(a) Firstly : The environment is outside the project and
hence oflittle direct interest to us.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
26/116
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
27/116
Managerial AspectsManagerial Aspects
Organization structure, recruitment and training aspectsOrganization structure, recruitment and training aspects
are studiesare studies
Appraisal done to see if project is adequately staffed,Appraisal done to see if project is adequately staffed,initial recruitment is done. Managerial ability plays aninitial recruitment is done. Managerial ability plays an
important role in making an enterprise a success orimportant role in making an enterprise a success or
otherwise. In the absence of managerial competence ,otherwise. In the absence of managerial competence ,
the project which are otherwise feasible may fail.the project which are otherwise feasible may fail.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
28/116
It is strictly pointed out that if the project isIt is strictly pointed out that if the project is
weak, it can be improved upon, but if theweak, it can be improved upon, but if the
promoters are weak & lack in business, it ispromoters are weak & lack in business, it is
difficult to reverse the situation. So whiledifficult to reverse the situation. So while
doing the project appraisal , the managerialdoing the project appraisal , the managerial
competence or talent of the promoter shouldcompetence or talent of the promoter should
be taken into consideration.be taken into consideration.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
29/116
Managerial AspectsManagerial Aspects
Financial institutions check if promoters areFinancial institutions check if promoters are
competent and have business sensecompetent and have business sense
They can appoint nominee directors on boardThey can appoint nominee directors on board
The Companies Act and Industries ActThe Companies Act and Industries Act
empower government to exercise control overempower government to exercise control over
managementmanagement
They can also take over the management inThey can also take over the management in
case it is neededcase it is needed
Managerial Appraisal
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
30/116
Managerial Appraisal
One of the main preoccupations of management in anyorganization and in project organization is the allocation ofscarce resources.
These resources include manpower, materials, facilities,and financial resources.
For every project being planned, the project manager must
ask the following two questions:- Are the resources required for the given projectavailable ?- Is this the best use to which these resources caput ?
Most project are subjected to an evaluation before they aregiven the go-ahead.
An essential part of his evaluation is the financial
appraisal
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
31/116
appraisal.
Traditionally, this has been aimed at deciding whether ornot a project will be profitable and selecting the one
project out of several competing projects that appearsthe most profitable. The project manager shouldunderstand the processes so that he can benefit from them.(Difference between private public Social Benefitprojects).
It is with this intention that we present the varioustechniques ofmanagerial evaluation, which consist of thetechnical, economic, financial, social and political
appraisal and assessment of a project.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
32/116
FINDING A PROJECT MANAGERFINDING A PROJECT MANAGER 1.Project Department-1.Project Department---Growth oriented companies--Growth oriented companies
have a separate department called the projecthave a separate department called the projectdepartment.this deptt. Is responsible for:-department.this deptt. Is responsible for:-
Looking for new opportunities for growthLooking for new opportunities for growth
Formulate projectsFormulate projects
Responsibilty for implementation of the projectResponsibilty for implementation of the project
coordinating.,directing & controlling all aspects of thecoordinating.,directing & controlling all aspects of the
project.project.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
33/116
2.Recruitment from open marketA project
manager may also be appointed when the
company in venturing into new &innovtaive technology.The person to be
appointed must have considerable
experience in the new technology.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
34/116
TERM APPOINTMENTTERM APPOINTMENT IT ENGAGE A PROFESSIONAL PROJECTIT ENGAGE A PROFESSIONAL PROJECT
MANAGER ON TERM APPOINTMENT. In this case theMANAGER ON TERM APPOINTMENT. In this case the
terms of appointment have to be very lucrative to maketerms of appointment have to be very lucrative to make
the other person interested.the other person interested.
Service Companies:ItService Companies:It mean to borrow the staff frommean to borrow the staff from
project management service companis. A projectproject management service companis. A project
management compnies can offer many services includingmanagement compnies can offer many services including
loaning of staff who can bebased at the client office &loaning of staff who can bebased at the client office &
work for the client as if they were the clients regular staff.work for the client as if they were the clients regular staff.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
35/116
Problems & challenges of projectProblems & challenges of project
manager.manager. AuthorityAuthority
OrientationOrientation
MotivationMotivation Building effective groupsBuilding effective groups
Impartial approach.Impartial approach.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
36/116
Project Management SkillsProject Management Skills
Program area knowledge, standards, andProgram area knowledge, standards, and
regulationsregulations
Understand the project environmentUnderstand the project environment
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
37/116
Project Management SkillsProject Management Skills
Program area knowledge, standards, andProgram area knowledge, standards, and
regulationsregulations
Understand the project environmentUnderstand the project environment
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
38/116
Project Management SkillsProject Management Skills
General management skills (budgeting,General management skills (budgeting,
scheduling)scheduling)
Communication skillsCommunication skills
Interpersonal skillsInterpersonal skills
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
39/116
The project manager makes thingsThe project manager makes things
happen!happen!
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
40/116
Methods of Project AppraisalMethods ofProject Appraisal
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
41/116
Meaning of Project AppraisalMeaning of Project Appraisal: -: -
Project AppraisalProject Appraisal is the analysis of costs and benefits of a proposed project with ais the analysis of costs and benefits of a proposed project with a
goal of assuring a rational allocation of limited financial resources amongst alternategoal of assuring a rational allocation of limited financial resources amongst alternate
Investment opportunities with the objective of achieving specific goals.Investment opportunities with the objective of achieving specific goals.
Project AppraisalProject Appraisal is mainly the process of transmitting information accumulatedis mainly the process of transmitting information accumulatedthrough feasibility studies into a comprehensive form in order to enable thethrough feasibility studies into a comprehensive form in order to enable the
decision maker undertake a comprehensive appraisal of various projects anddecision maker undertake a comprehensive appraisal of various projects and
embark on a specific project or projects by allocating resources.embark on a specific project or projects by allocating resources.
The various Factors considered by Financial Institutions while appraising aThe various Factors considered by Financial Institutions while appraising aproject are: -project are: -
Technical, Financial, Economic, Commercial, Social andTechnical, Financial, Economic, Commercial, Social and
Managerial Factors.Managerial Factors.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
42/116
Objectives & ScopeObjectives & Scope: -: -
To extract relevant information for determining the success orTo extract relevant information for determining the success or
failure of a project.failure of a project.
To apply standard yardsticks for determining the rate of success orTo apply standard yardsticks for determining the rate of success or
failure of a project.failure of a project.
To determine the expected costs and benefits of the project.To determine the expected costs and benefits of the project.
To arrive at specific conclusions regarding the project.To arrive at specific conclusions regarding the project.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
43/116
SignificanceSignificance: -: -
It helps in arriving at specific and predicted results.It helps in arriving at specific and predicted results.
It evaluates the desirability of the project.It evaluates the desirability of the project.
It provides information to determine the success or failure of aIt provides information to determine the success or failure of aproject.project.
It employs existing norms to predict the rate of success or failureIt employs existing norms to predict the rate of success or failure
of the project.of the project.
It verifies the hypothesis framed for the project.It verifies the hypothesis framed for the project.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
44/116
Factors Considered while Appraising a ProjectFactors Considered while Appraising a Project: -: -
Technical FactorsTechnical Factors
Financial FactorsFinancial Factors
Economic FactorsEconomic Factors Social FactorsSocial Factors
Commercial FactorsCommercial Factors
Managerial FactorsManagerial Factors
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
45/116
Methods of Project AppraisalMethods ofProject Appraisal
METHODS O FPROJECT APPRAISAL
DISCOUNTING
CRITERIA
NON -DISCOUNTING
CRITERIA
NET
PRES ENT
VALUE
PROFIT-
ABILITY
INDEX
INTERNAL
RATE OF
RETURN
PAYBA CK
PERIODACCOUNTING
RATE OFRETURN
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
46/116
Pay-Back Period MethodPay-Back Period Method: -: -
TheThe Pay-Back PeriodPay-Back Period is the length of time required to recover the initial outlay onis the length of time required to recover the initial outlay on
the project Or It is the time required to recover the original investment throughthe project Or It is the time required to recover the original investment through
income generated from the project.income generated from the project.
Pay-Back PeriodPay-Back Period == Original Cost of Investment____Original Cost of Investment____
Annual Cash Inflows or SavingsAnnual Cash Inflows or Savings
ProsPros: -: - a) It is easy to operate and simple to understand.a) It is easy to operate and simple to understand.
b) It is best suited where the project has shorter gestation period andb) It is best suited where the project has shorter gestation period and
project cost is also less.project cost is also less.
c) It is best suited for high risk category projects. Which are prone to rapidc) It is best suited for high risk category projects. Which are prone to rapid
technological changes.technological changes.
d) It enables entrepreneur to select an investment which yields quick returnd) It enables entrepreneur to select an investment which yields quick return
of funds.of funds.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
47/116
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
48/116
Accounting Rate of Return MethodAccountingRate of Return Method: -: -
This method is considered better than pay-back period method because it considersThis method is considered better than pay-back period method because it considers
earnings of the project during its full economic life. This method is also knownearnings of the project during its full economic life. This method is also known
asas Return On InvestmentReturn On Investment (ROI). It is mainly expressed in terms of percentage.(ROI). It is mainly expressed in terms of percentage.
ARR or ROIARR or ROI == Average Annual Earnings After Tax_______Average Annual Earnings After Tax_______ * 100* 100
Average Book Investment After DepreciationAverage Book Investment After Depreciation
Here, Average Investment = (Initial Cost Salvage Value) * 1 / 2Here, Average Investment = (Initial Cost Salvage Value) * 1 / 2
Decision RuleDecision Rule: - In the ARR, A project is to be: - In the ARR, A project is to be ACCEPTEDACCEPTED when ( If Actual ARRwhen ( If Actual ARR
is higher or greater than the rate of return) otherwise it is Rejectedis higher or greater than the rate of return) otherwise it is Rejected
and In case of alternate projects, One with the highest ARR is toand In case of alternate projects, One with the highest ARR is to
be selected.be selected.
PP ) i i) I i i l l l d d d
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
49/116
ProsPros: -: - a) It is simple to calculate and easy to understand.a) It is simple to calculate and easy to understand.
b) It considers earning of the project during the entire operative life.b) It considers earning of the project during the entire operative life.
c) It helps in comparing the projects which differ widely.c) It helps in comparing the projects which differ widely.
d) This method considers net earnings after depreciation and taxes.d) This method considers net earnings after depreciation and taxes.
ConsCons: -: -a) It ignores time value of money.a) It ignores time value of money.b) It lays more emphasis on profit and less on cash flows.b) It lays more emphasis on profit and less on cash flows.c) It does not consider re-investment of profit over years.c) It does not consider re-investment of profit over years.
d) It does not differentiate between the size of investments required ford) It does not differentiate between the size of investments required for
different projects.different projects.
For ExampleFor Example: -: - Project AProject A Project BProject BInvestmentInvestment 25,00025,000 37,00037,000
Expected Life (In Yrs.)Expected Life (In Yrs.) 4 4
Net Earnings (After Dep. & Taxes)Net Earnings (After Dep. & Taxes)
YearsYears
11 25002500 37503750
22 18751875 3750375033 18751875 25002500
44 12501250 12501250
If the Desired rate of return is 12%, which project should be selected?If the Desired rate of return is 12%, which project should be selected?
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
50/116
NPV (Net Present Value) MethodNPV (Net Present Value) Method: -: -
This method mainly considers the time value of money. It is the sum of theThis method mainly considers the time value of money. It is the sum of the
aggregate present values of all the cash flows positive as well as negative thataggregate present values of all the cash flows positive as well as negative that
are expected to occur over the operating life of the project.are expected to occur over the operating life of the project.
NPVNPV = PV of Net Cash Inflows Initial Outlay (Cash outflows)= PV of Net Cash Inflows Initial Outlay (Cash outflows)
Decision RuleDecision Rule: -: - If NPV is positive, ACCEPTIf NPV is positive, ACCEPT If NPV is negative, REJECTIf NPV is negative, REJECT If NPV is 0, then apply Payback Period MethodIf NPV is 0, then apply Payback Period Method
The standard NPV method is based on the assumption that the intermediateThe standard NPV method is based on the assumption that the intermediatecash flows are reinvested at a rate of return equal to the cost of capital. Whencash flows are reinvested at a rate of return equal to the cost of capital. Whenthis assumption is not valid, the investment rates applicable to the intermediatethis assumption is not valid, the investment rates applicable to the intermediatecash flows need to be defined for calculating the modified NPV.cash flows need to be defined for calculating the modified NPV.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
51/116
Pros and Cons of NPVPros and Cons ofNPV: -: -
ProsPros: -: -a) This method introduces the element of time value of money and as such is aa) This method introduces the element of time value of money and as such is a
scientific method of evaluating the project.scientific method of evaluating the project.
b) It covers the whole project from start to finish and gives more accurateb) It covers the whole project from start to finish and gives more accurate
figuresfigures
c) It Indicates all future flows in todays value. This makes possiblec) It Indicates all future flows in todays value. This makes possible
comparisons between two mutually exclusive projects.comparisons between two mutually exclusive projects.
d) It takes into account the objective of maximum profitabilityd) It takes into account the objective of maximum profitability
ConsCons: -: -a) It is difficult method to calculate and use.a) It is difficult method to calculate and use.
b) It is biased towards shot run projects.b) It is biased towards shot run projects.
c) In this method profitability is not linked to capital employed.c) In this method profitability is not linked to capital employed.
d) It does not consider Non-Financial data like the marketability of a product.d) It does not consider Non-Financial data like the marketability of a product.
For ExampleFor Examp
le: -: -
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
52/116
For ExampleFor Example: : Initial Investment 20,000Initial Investment 20,000
Estimated Life 5 years
Scrap Value 1000 XYZ Enterprises Capital Project
Year Cash flow Discount factor Present V@10%
1 5.000 0.909
2 10,000 0.826
3 10,000 0.751
4 3,000 0.683
5 2,000 0.621
5 1,000 0.621
PV of Net Cash Inflows = 24227
NPV = PV of Net Cash Inflows Cash Outflows
= 24227 20,000
NPV = 4227Here, NPV is Positive (+ ve) The Project is ACCEPTED.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
53/116
Profitability Index MethodProfitability Index Method: -: -
Profitability IndexProfitability Index is the ratio of present value of expected future cash inflowsis the ratio of present value of expected future cash inflows
andand
Initial cash outflows or cash outlay. It is also used for ranking the projects in orderInitial cash outflows or cash outlay. It is also used for ranking the projects in order
of their profitability. It is also helpful in selecting projects in a situation of capitalof their profitability. It is also helpful in selecting projects in a situation of capital
rationing. It is also know as Benefit / Cost Ratio (BCR).rationing. It is also know as Benefit / Cost Ratio (BCR).
PI =PI = Present value of Future cash InflowsPresent value of Future cash Inflows
Initial Cash OutlayInitial Cash Outlay
Decision RuleDecision Rule: - In Case of Independent Investments,: - In Case of Independent Investments, ACCEPTACCEPT a Project If a PI isa Project If a PI isgreater ( > 1 ) and Reject it otherwise.greater ( > 1 ) and Reject it otherwise.
In Case of Alternative Investments,In Case of Alternative Investments, ACCEPTACCEPT the project withthe project with
thethe
largest PI, provided it is greater than ( > 1 ) and Reject others.largest PI, provided it is greater than ( > 1 ) and Reject others.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
54/116
IRR (I l R f R ) M h dIRR (I
l R f R ) M h d
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
55/116
IRR (Internal Rate of Return) MethodIRR (Internal Rate of Return) Method: -: -
This method is known by various other names likeThis method is known by various other names like Yield on InvestmentYield on Investment ororRate ofRate of
Return MethodReturn Method. It is used when the cost of investment and the annual cash inflows. It is used when the cost of investment and the annual cash inflowsare known and rate of return is to be calculated. It takes into account time value ofare known and rate of return is to be calculated. It takes into account time value of
Money by discounting inflows and cash flows. This is the Most alternative to NPV.Money by discounting inflows and cash flows. This is the Most alternative to NPV.
It is the Discount rate that makes it NPV equal to zero.It is the Discount rate that makes it NPV equal to zero.
In this Method, the IRR can be ascertained by theIn this Method, the IRR can be ascertained by the Trial & Error Yield MethodTrial & Error Yield Method,,
Whose the objective is to find out the expected yield from the investment.Whose the objective is to find out the expected yield from the investment.
rate + NPV @ Smaller rateSum of the absolute values of the
NPV @ smaller and the bigger
Discount rates
Bigger
X discount discountrate
Decision Rule: - In the Case of an Independent Investment, ACCEPT the project if
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
56/116
p p j
Its IRR is greater than the required rate of return and if it is lower, ThenReject it. In Case of Mutually Exclusive Projects, ACCEPT the project with thelargest IRR, provided it is greater than the required rate of return &Reject others.
Pros: - a) It considers the profitability of the project for its entire economic life andhence enables evaluation of true profitability.
b) It recognizes the time value of money and considers cash flows overentire life of the project.
c) It provides for uniform ranking of various proposals due to thepercentage rate of return.
d) It has a psychological appeal to the user. Since values are expressed inpercentages.
Cons: - a) It is most difficult method of evaluation of investment proposals.b) It is based upon the assumption that the earnings are reinvested at the
Internal Rate of Return for the remaining life of the project.
c) It may result in Incorrect decisions in comparing the Mutually ExclusiveProjects.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
57/116
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
58/116
Assessment of NPV & IRR MethodAssessment of NPV & IRR Method
NPVNPV IRRIRRTheoretical ConsiderationsTheoretical Considerations: -: -
a) Does the method discount all casha) Does the method discount all cash YesYes YesYes
flows?flows?
b) Does the method discount cash flowsb) Does the method discount cash flows YesYes NoNo
at the opportunity cost of funds?at the opportunity cost of funds?
c) From a set of M.E. Projects, does thec) From a set of M.E. Projects, does the
method choose the project whichmethod choose the project which
maximizes shareholder wealth?maximizes shareholder wealth? YesYes NoNo
Practical ConsiderationsPractical Considerations: -: -
a) Is the Method Simple?a) Is the Method Simple? YesYes YesYes
b) Can the method be used with limitedb) Can the method be used with limited
information?information? NoNo NoNo
c) Does the method give a relative measure? Noc) Does the method give a relative measure? No NoNo
CASH FLOW ANALYSIS OFCASH FLOW ANALYSIS OF
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
59/116
CASH-FLOW ANALYSIS OFCASH-FLOW ANALYSIS OF
THE PROJECTTHE PROJECT PREPARE FINANCIAL PROJECTIONS:PREPARE FINANCIAL PROJECTIONS: FINANCIAL ADEQUACYFINANCIAL ADEQUACY FINANCIAL WORTHFINANCIAL WORTH RETURNS TO FINANCIALRETURNS TO FINANCIAL
STAKEHOLDERSSTAKEHOLDERS LIST THE ASSUMPTIONSLIST THE ASSUMPTIONS
SENSITIVITY ANALYSISSENSITIVITY ANALYSIS
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
60/116
SCHEDULES (CONTD.)SCHEDULES (CONTD.)
9. CASH-FLOW STATEMENT;9. CASH-FLOW STATEMENT;
10. RATE OF RETURN CALCULATION;10. RATE OF RETURN CALCULATION;
11. SENSITIVITY ANALYSIS.11. SENSITIVITY ANALYSIS.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
61/116
SELECTION CRITERIASELECTION CRITERIA
BENEFIT/COST RATIO;BENEFIT/COST RATIO;
NET PRESENT VALUE;NET PRESENT VALUE;
INTERNAL RATE OF RETURN:INTERNAL RATE OF RETURN: IRR;IRR;
ERR.ERR.
NON REVENUENON REVENUE
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
62/116
NON-REVENUE-NON-REVENUE-
GENERATING PROJECTSGENERATING PROJECTS WEAK FINANCES, SO WHY DO A FINANCIALWEAK FINANCES, SO WHY DO A FINANCIAL
ANALYSIS?ANALYSIS? NEED TO QUANTIFY THE ANNUAL DEFICITS;NEED TO QUANTIFY THE ANNUAL DEFICITS; NEED TO DEVELOP STRATEGIES TO SUSTAIN THENEED TO DEVELOP STRATEGIES TO SUSTAIN THE
PROJECT IMPACT;PROJECT IMPACT; POLICYPOLICY: SUBSIDISE ONLY THOSE WHO NEED IT,: SUBSIDISE ONLY THOSE WHO NEED IT,
BUT NOT FOREVER!BUT NOT FOREVER!
SELECTION CRITERIA:SELECTION CRITERIA:
LEAST-COST ANALYSIS:LEAST-COST ANALYSIS:LEAST-COST ANALYSIS.xlsLEAST-COST ANALYSIS.xls COST-EFFECTIVENESS ANALYSIS:COST-EFFECTIVENESS ANALYSIS:
COST-EFFECTIVENESS.xlsCOST-EFFECTIVENESS.xls
NON REVENUE GENERATINGNON REVENUE GENERATING
http://../My%20Documents/LEAST-COST%20ANALYSIS.xlshttp://../My%20Documents/LEAST-COST%20ANALYSIS.xlshttp://../My%20Documents/COST-EFFECTIVENESS.xlshttp://../My%20Documents/COST-EFFECTIVENESS.xlshttp://../My%20Documents/COST-EFFECTIVENESS.xlshttp://../My%20Documents/LEAST-COST%20ANALYSIS.xls -
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
63/116
NON-REVENUE GENERATINGNON-REVENUE GENERATING
PROJECTS (CONTD.)PROJECTS (CONTD.)
NEED FOR GRANT FUNDS;NEED FOR GRANT FUNDS;
GIFTS;GIFTS;
VERY SOFT LOANS;VERY SOFT LOANS;
SWEAT-EQUITY GET THE TARGETSWEAT-EQUITY GET THE TARGET
GROUP TO CONTRIBUTE WHATEVERGROUP TO CONTRIBUTE WHATEVER
THEY CAN, IN SUPPORT OF THETHEY CAN, IN SUPPORT OF THE
PROJECT.PROJECT.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
64/116
SENSITIVITY ANALYSISSENSITIVITY ANALYSIS
WHAT IF?WHAT IF? .SALES DECLINE BY 10%.SALES DECLINE BY 10% .CAPITAL COST INCREASE BY 10%.CAPITAL COST INCREASE BY 10% .OPERATING COST INCREASE BY 10%.OPERATING COST INCREASE BY 10% . THERE IS A 10% DELAY IN PROJECT. THERE IS A 10% DELAY IN PROJECT
IMPLEMENTATIONIMPLEMENTATION
WHICH HAS THE GREATEST IMPACT?WHICH HAS THE GREATEST IMPACT? IS THE PROJECT STILL VIABLE?IS THE PROJECT STILL VIABLE?
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
65/116
ECONOMIC ANALYSISECONOMIC ANALYSIS
WHY THIS ANALYSIS? :WHY THIS ANALYSIS? : MARKET FAILURE;MARKET FAILURE;
MONOPOLIES;MONOPOLIES; MERIT/DEMERIT GOODS;MERIT/DEMERIT GOODS;
GOVERNMENT FAILURE;GOVERNMENT FAILURE;
DIFFERENCE BETWEEN PRIVATE AND SOCIALDIFFERENCE BETWEEN PRIVATE AND SOCIAL
VALUATION OF COSTS AND BENEFITS;VALUATION OF COSTS AND BENEFITS;
IDENTIFY INTERNAL AND EXTERNAL COSTSIDENTIFY INTERNAL AND EXTERNAL COSTSAND BENEFITS:AND BENEFITS: ECONOMIC FOCUS.xlsECONOMIC FOCUS.xls
http://../My%20Documents/ECONOMIC%20FOCUS.xlshttp://../My%20Documents/ECONOMIC%20FOCUS.xlshttp://../My%20Documents/ECONOMIC%20FOCUS.xls -
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
66/116
ECONOMIC ANALYSIS (CONTD.)ECONOMIC ANALYSIS (CONTD.)
DOES THE PROJECT GENERATE NETDOES THE PROJECT GENERATE NET
BENEFITS FOR THE COUNTRY?BENEFITS FOR THE COUNTRY?
VALUING COSTS AND BENEFITS FROMVALUING COSTS AND BENEFITS FROM
THE NATIONAL PERSPECTIVE;THE NATIONAL PERSPECTIVE;
SHADOW-PRICING;SHADOW-PRICING;
RE-CALCULATING PROJECT WORTHRE-CALCULATING PROJECT WORTH
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
67/116
ECONOMIC ANALYSIS (CONTD.)ECONOMIC ANALYSIS (CONTD.)
THE NUMERAIRE USED IN MEASURINGTHE NUMERAIRE USED IN MEASURING
VALUE;VALUE;
CONVERSION FACTOR V/S THECONVERSION FACTOR V/S THE
SHADOW FOREIGN EXCHANGE RATESHADOW FOREIGN EXCHANGE RATE
APPROACH;APPROACH;
COMPARING THE RESULTS;COMPARING THE RESULTS;
RATIONALE FOR CHOOSING THERATIONALE FOR CHOOSING THE
CONVERSION FACTOR APPROACH.CONVERSION FACTOR APPROACH.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
68/116
SOCIAL PERSPECTIVESSOCIAL PERSPECTIVES
SO THE COUNTRY GAINS; BIG DEAL!SO THE COUNTRY GAINS; BIG DEAL! .WHO EXACTLY.WHO EXACTLY GAINS? .GAINS? . .THE POOREST OF THE POOR? ..THE POOREST OF THE POOR? . . OTHER DISADVANTAGED GROUPS?. OTHER DISADVANTAGED GROUPS?
WOMEN, YOUTHS, RURAL PEOPLE?WOMEN, YOUTHS, RURAL PEOPLE? ??
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
69/116
Project Appraisal- An OverviewProject Appraisal- An Overview
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
70/116
A dAgenda
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
71/116
AgendaAgenda
IntroductionIntroduction Aspects of Project FinanceAspects of Project Finance
Managerial AppraisalManagerial Appraisal
Technical AppraisalTechnical Appraisal
Commercial AppraisalCommercial Appraisal
Selected financial indicatorsSelected financial indicators
Case StudyCase Study
P j tP j t
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
72/116
ProjectProject
A non repetitive activityA non repetitive activity
Involves large capital expendituresInvolves large capital expenditures
Returns over a long period of timeReturns over a long period of time
Requires significant managerial bandwidthRequires significant managerial bandwidth
Varied risksVaried risks
Uncertainty of future business environmentUncertainty of future business environment
P j FiP j t Fi
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
73/116
Project FinanceProject Finance
Level of funding raised based purely on the meritsLevel of funding raised based purely on the meritsof the relevant projectof the relevant project
Lender is satisfied to look initially at the cashflowsLender is satisfied to look initially at the cashflows
and earnings of a economic unitand earnings of a economic unit
Debt would be repaid from the economic unitDebt would be repaid from the economic unit
The loan and equity returns are tied to the cashThe loan and equity returns are tied to the cash
flows and fortunes of the project rather than beingflows and fortunes of the project rather than being
dependant on the parent company/companies.dependant on the parent company/companies.
Project AppraisalProject Appraisal
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
74/116
Project AppraisalProject Appraisal
The purpose of Project Appraisal is to ascertainThe purpose of Project Appraisal is to ascertainwhether the project is sound technically,whether the project is sound technically,economically, financially and managerially and iseconomically, financially and managerially and isultimately viable as a commercial proposition.ultimately viable as a commercial proposition.
Multifaceted activity; Requires skills ofMultifaceted activity; Requires skills of PsychologistPsychologist EngineerEngineer Financial AnalystFinancial Analyst
EconomistEconomist
P j t A i lProject Appraisal
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
75/116
Project AppraisalProject Appraisal
Each and every project is based upon assumptions, necessarilyEach and every project is based upon assumptions, necessarilyinvolve capital expenditure in the hope of a reasonable returninvolve capital expenditure in the hope of a reasonable returnon investment over a future period of time.on investment over a future period of time.
Project Appraisal necessarily involves validation of variousProject Appraisal necessarily involves validation of variousassumptionsassumptions
Appraisal ofAppraisal of Management/ Sponsor/ PromoterManagement/ Sponsor/ Promoter Technical aspectsTechnical aspects Market & Selling ArrangementsMarket & Selling Arrangements Financial viabilityFinancial viability
I iti l S i 1/ 3Initial Screening 1/ 3
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
76/116
Initial Screening 1/ 3Initial Screening 1/ 3
WHAT IS THE PRODUCT (General industry structure)WHAT IS THE PRODUCT (General industry structure) WHO IS SETTING UP THE PROJECT (Promoters andWHO IS SETTING UP THE PROJECT (Promoters and
their experience)their experience)
Our experience from similar unitsOur experience from similar units
Banks lending policiesBanks lending policies Government/ RBI RegulationsGovernment/ RBI Regulations
Past business financialsPast business financials
CollateralsCollaterals
I iti l S i 2/ 3Initial Screening 2/ 3
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
77/116
Initial Screening 2/ 3Initial Screening 2/ 3
Distance of unit from branchDistance of unit from branch RBI/ CIBIL/ AML ListsRBI/ CIBIL/ AML Lists
ECGC Specific Approval ListECGC Specific Approval List
Discussions with banksDiscussions with banks Independent Market EnquiryIndependent Market Enquiry
Initial Screening 3/ 3Initial Screening 3/ 3
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
78/116
Initial Screening 3/ 3Initial Screening 3/ 3
Prudential Exposure normsPrudential Exposure norms Individual & Group Exposure normsIndividual & Group Exposure norms
Industry Exposure normsIndustry Exposure norms
Scheme Eligibility Norms DER, PC, DSCR, AssetScheme Eligibility Norms DER, PC, DSCR, Asset
coveragecoverage Takeover norms, if applicableTakeover norms, if applicable
Profitability ProjectionsProfitability Projections
Credit Risk Rating normsCredit Risk Rating norms
M t A i l 1/ 5Management Appraisal 1/ 5
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
79/116
Management Appraisal 1/ 5Management Appraisal 1/ 5
Who are the promoters KYCWho are the promoters KYC Cohesiveness - relationshipCohesiveness - relationship
Competence - Age, QualificationsCompetence - Age, Qualifications
Experience general or similar lineExperience general or similar line
Net-worth of promotersNet-worth of promoters
IT/ Wealth tax statusIT/ Wealth tax status
Management Appraisal 2/ 5Management Appraisal 2/ 5
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
80/116
Management Appraisal 2/ 5Management Appraisal 2/ 5
Associate concerns in which interestedAssociate concerns in which interested Associate ConcernsAssociate Concerns
When establishedWhen established
Which industry; ProductsWhich industry; Products
Financial performanceFinancial performance
Visit to associate concernsVisit to associate concerns
Role of promoters in the associate concernsRole of promoters in the associate concerns
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
81/116
Management Appraisal 4/ 5Management Appraisal 4/ 5
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
82/116
Management Appraisal 4/ 5Management Appraisal 4/ 5
Shareholding patternShareholding pattern % stake of promoters; Majority shareholder% stake of promoters; Majority shareholder Stake held by investment companiesStake held by investment companies Stake by foreign funds/ FDI/ Overseas investorsStake by foreign funds/ FDI/ Overseas investors
Examine shareholders agreements; restrictiveExamine shareholders agreements; restrictivecovenantscovenants Partnership deed/ Society/ Trust deed to bePartnership deed/ Society/ Trust deed to be
examined for any restrictive clausesexamined for any restrictive clauses
Memorandum & AoA to be examined forMemorandum & AoA to be examined forobjectives, borrowing powers, security, nomineeobjectives, borrowing powers, security, nomineedirectors etc.directors etc.
Management Appraisal 5/ 5Management Appraisal 5/ 5
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
83/116
Management Appraisal 5/ 5Management Appraisal 5/ 5
Composition of BoardComposition of Board
Chief Executive; Organisational set upChief Executive; Organisational set up
In case promoters not qualified/ experienced,In case promoters not qualified/ experienced,
critically examine line managementcritically examine line management Adequacy of personnel for projectAdequacy of personnel for project
implementation and each of functional areasimplementation and each of functional areas
viz. finance, marketing, technology, production,viz. finance, marketing, technology, production,materials, HR etc.materials, HR etc.
KYCKYC
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
84/116
KYCKYC
Companies : Memorandum and articles of associationCompanies : Memorandum and articles of association object clause, borrowing powers, power to object clause, borrowing powers, power tomortgage, authorized share capital, directors andmortgage, authorized share capital, directors andboard of directors, nominee directors provision, Pvtboard of directors, nominee directors provision, Pvt
or public ltdor public ltd Partnership concerns Partnership deed Partnership concerns Partnership deed
(registration), no of partners, powers to borrow(registration), no of partners, powers to borrow Trusts, HUFs, Co-operatives necessary safeguardsTrusts, HUFs, Co-operatives necessary safeguards Address and Identity proof, Networth statements,Address and Identity proof, Networth statements,
ITRs, Signature attestation from bankers, PAN/SalesITRs, Signature attestation from bankers, PAN/Salestax/ EPF registrationtax/ EPF registration
Technical Aspects 1/3Technical Aspects 1/3
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
85/116
Technical Aspects 1/3Technical Aspects 1/3
Scope of projectScope of project Plant scale, product mixPlant scale, product mix CapacityCapacity Bottlenecks in upscalingBottlenecks in upscaling
LocationLocation Approach roadApproach road Infrastructure facilitiesInfrastructure facilities
Power distance from substationPower distance from substation Raw materialsRaw materials Availability of skilled/ unskilled labourAvailability of skilled/ unskilled labour
Technical Aspects 2/3Technical Aspects 2/3
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
86/116
Technical Aspects 2/3Technical Aspects 2/3
Mfg process - Selection of technologyMfg process - Selection of technology Technical consultants/ collaboratorsTechnical consultants/ collaborators Similar technology used by other unitsSimilar technology used by other units
Selection of machinery cost and qualitySelection of machinery cost and quality Performance guaranteePerformance guarantee Training personnelTraining personnel
Imported After sale serviceImported After sale service Second hand/ fabricatedSecond hand/ fabricated
Technical Aspects 3/3Technical Aspects 3/3
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
87/116
Technical Aspects 3/3Technical Aspects 3/3
Major Raw MaterialsMajor Raw Materials Availability (Quantity & Quality)Availability (Quantity & Quality) Price fluctuationsPrice fluctuations Imported or Indigenous - duty structureImported or Indigenous - duty structure
ProximityProximity Power, Water, FuelPower, Water, Fuel Effluent DisposalEffluent Disposal
Manpower availabilityManpower availability Implementation Schedule ????Implementation Schedule ????
Market Analysis 1/ 2Market Analysis 1/ 2
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
88/116
Market Analysis 1/ 2Market Analysis 1/ 2
Target customersTarget customers Market prospects - Market SurveyMarket prospects - Market Survey
Demand Supply scenarioDemand Supply scenario
Price trendsPrice trends Competition - localCompetition - local
Competition foreign - duty structureCompetition foreign - duty structure
Firm tie ups (collaborator off take !!!)Firm tie ups (collaborator off take !!!)
Market Analysis 2/ 2Market Analysis 2/ 2
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
89/116
Market Analysis 2/ 2Market Analysis 2/ 2
Selling arrangementsSelling arrangements Industry practicesIndustry practices
Credit periodCredit period
Payment defaultsPayment defaults Advance paymentsAdvance payments
Ancillary units : Tripartite agreementsAncillary units : Tripartite agreements
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
90/116
Financial Appraisal - Cost of Project & Means of FinanceFinancial Appraisal - Cost of Project & Means of Finance
Project Cost Means of Finance
Land & site development Equity
Buildings (Main/ Auxiliary) Promoters Equity
Plant and Machinery Internal Accruals
Miscellaneous fixed assets Unsecured Loans
Pre. & pre-op exp. Subsidy
Contingency Term Loans
Margin Money for WC Others
Total Total
Capital Cost ValidationCapital Cost Validation
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
91/116
Capital Cost Validationp LandLand
Cost as per Sale / Lease deed, Registration costCost as per Sale / Lease deed, Registration cost
Cost of Land Development, as estimated by a CivilCost of Land Development, as estimated by a CivilEngineerEngineer Land use permissionLand use permission
Building & Civil worksBuilding & Civil works Approval of construction plan by Local AuthoritiesApproval of construction plan by Local Authorities Types of construction Estimates by a Civil EngineerTypes of construction Estimates by a Civil Engineer
Plant, Machinery & EquipmentsPlant, Machinery & Equipments Selection criteria i.e. Technical specifications, Capacity,Selection criteria i.e. Technical specifications, Capacity,
Quality, After sales service, Guarantee, DeliveryQuality, After sales service, Guarantee, Deliveryschedule, Cost, Terms of paymentschedule, Cost, Terms of payment
Quotations / Offer letters from manufacturersQuotations / Offer letters from manufacturers Excise Duty, Sales Tax, TransportationExcise Duty, Sales Tax, Transportation Foundation, Erection & CommissioningFoundation, Erection & Commissioning
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
92/116
Financial Viability 2/ 2Financial Viability 2/ 2
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
93/116
Financial Viability 2/ 2Financial Viability 2/ 2 DERDER
GPM and NPM comparison with peersGPM and NPM comparison with peers DSCRDSCR Project IRRProject IRR BEPBEP Cost of Capital (CoC)Cost of Capital (CoC) Return on Capital Employed (RoCE)Return on Capital Employed (RoCE) Sensitivity analysisSensitivity analysis
Variations in capacity utilisation, selling price, raw materialVariations in capacity utilisation, selling price, raw materialand other key costsand other key costs
Test the performance of key parametersTest the performance of key parameters Inter-firm comparisonInter-firm comparison Project Cost, Means of finance, Projections of income andProject Cost, Means of finance, Projections of income and
profitability and DSCRprofitability and DSCR
OthersOthers
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
94/116
Ot e s
Repayment schedule EMI/ BalooningRepayment schedule EMI/ Balooning
MoratoriumMoratorium
Capital/ interest subsidyCapital/ interest subsidy
Internal Risk RatingInternal Risk Rating
External ratingExternal rating
Primary and collateral securityPrimary and collateral security
Security Margin/ Asset CoverageSecurity Margin/ Asset Coverage
Pre-disbursement conditionsPre-disbursement conditions
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
95/116
Thank YouThank You
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
96/116
THE MAIN SCHEDULESTHE MAIN SCHEDULES
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
97/116
THE MAIN SCHEDULESTHE MAIN SCHEDULES
1. CAPITAL COST;1. CAPITAL COST; 2. DEPRECIATION SCHEDULE;2. DEPRECIATION SCHEDULE; 3. CAPITAL REPLACEMENT SCHEDULE;3. CAPITAL REPLACEMENT SCHEDULE;
4. CASH OPERATING EXPENSES;4. CASH OPERATING EXPENSES; 5. WORKING CAPITAL REQUIREMENTS;5. WORKING CAPITAL REQUIREMENTS; 6. LOAN REPAYMENT SCHEDULE;6. LOAN REPAYMENT SCHEDULE;
7. CASH REVENUE SCHEDULE;7. CASH REVENUE SCHEDULE; 8. INCOME STATEMENT;8. INCOME STATEMENT;
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
98/116
Presentation on
Appraisal of Project ReportBanks Perspective
Appraisal?Appraisal?
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
99/116
Appraisal?pp
A structured analytical tool to take a creditA structured analytical tool to take a credit
decision The basic premises of an appraisal aredecision The basic premises of an appraisal areto assess/ analyze:to assess/ analyze:
The Promoters.The Promoters. Viability of the business Macro & MicroViability of the business Macro & Micro
Environment of the Business.Environment of the Business. Business financialsBusiness financials Various Risk & its mitigation.Various Risk & its mitigation.
Permission & Approvals from RegulatoryPermission & Approvals from RegulatoryBodies.Bodies.
Promoter e al ationPromoter evaluation
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
100/116
Promoter evaluationPromoter evaluation
Track record of promotersTrack record of promoters
- Net worth/Availability of funds- Net worth/Availability of funds
ManagementManagement
- Experience of Management- Experience of Management- Ownership Pattern- Ownership Pattern
Check RBI Defaulters ListCheck RBI Defaulters List
Check CIBIL RecordsCheck CIBIL Records
Viability of the BusinessViability of the Business
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
101/116
Viability of the BusinessViability of the Business
SWOT AnalysisSWOT Analysis
Strengths & Weaknesses InternalStrengths & Weaknesses Internal
Opportunities & Threats - ExternalOpportunities & Threats - External
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
102/116
StrengthsStrengths
(Areas to Look for)(Areas to Look for)
Competent ManagementCompetent Management Distinctive competitive edgeDistinctive competitive edge
in terms of cost, productin terms of cost, productdifferentiation, R&D, skillsdifferentiation, R&D, skills
etcetc Good Brand Image StrongGood Brand Image Strong
& growing customer base.& growing customer base. Industrial relations lowIndustrial relations low
attrition rate.attrition rate. Sufficient FinancialSufficient Financial
Resources.Resources.
WeaknessesWeaknesses
(Areas to Look for)(Areas to Look for)
Lack of Management Depth/Lack of Management Depth/TalentTalent
Deteriorating competitiveDeteriorating competitivepositionposition
Newcomer with unprovenNewcomer with unproventrack record.track record.
Short on FinancialShort on FinancialResourcesResources
Technology Obsolescence.Technology Obsolescence.
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
103/116
OpportunitiesOpportunities
(Areas to Look for)(Areas to Look for)
Industrial ScenarioIndustrial Scenario
Faster market growthFaster market growth
Enter new market/Enter new market/customer segments.customer segments.
Expand product line/Expand product line/
Move up in the valueMove up in the value
chain to meet thechain to meet thegrowing aspirations ofgrowing aspirations of
customerscustomers
Vertical Integration.Vertical Integration.
ThreatsThreats
(Areas to Look for)(Areas to Look for)
Growing competitiveGrowing competitive
pressures.pressures.
Growing bargainingGrowing bargaining
power of customers/power of customers/supplierssuppliers
Changing buyersChanging buyers
needs/ tastes Risingneeds/ tastes Rising
sale of substitutesale of substituteproductsproducts
Adverse Govt Policies.Adverse Govt Policies.
Vulnerability toVulnerability to
recession/ businessrecession/ business
Business FinancialsBusiness Financials
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
104/116
Manufacturing efficiencyManufacturing efficiency Operating efficiencyOperating efficiency Is the unit turning over the assets efficiently.Is the unit turning over the assets efficiently. Cash Flow pattern.Cash Flow pattern. Liquidity to meet day to day operationsLiquidity to meet day to day operations What is the quality of current assetsWhat is the quality of current assets
Can the unit sustain in difficult timesCan the unit sustain in difficult times Can it service our interest and repaymentsCan it service our interest and repayments
What are we looking at?What are we looking at?
Key Financial RatiosKey Financial Ratios
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
105/116
Key Financial RatiosKey Financial Ratios
Growth in sales - It shows prosperityGrowth in sales - It shows prosperity RM Content in sales It indicates cost efficacyRM Content in sales It indicates cost efficacy Gross profit/sales It indicates mfg. efficacyGross profit/sales It indicates mfg. efficacy
PBDIT/sales It indicates operPBDIT/sales It indicates oper Cash accruals/Sales Ultimate earningsCash accruals/Sales Ultimate earnings Current ratio Will it meet comCurrent ratio Will it meet com TOL/TNW Resilience inTOL/TNW Resilience in Sales/TTA Asset turn arSales/TTA Asset turn aro ROCE ROCE
Assessment of Right Quantum &Assessment of Rig
ht Quantum &
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
106/116
Type of DebtType of Debt
Broadly Debt is required by the Corporates for Broadly Debt is required by the Corporates for
Capital Investment (Project Finance)Capital Investment (Project Finance)
Working CapitalWorking Capital
F f AdF f Ad
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
107/116
Forms of AdvancesForms of Advances
Fund Based FacilitiesFund Based Facilities
Term LoansTerm Loans
Cash CreditCash Credit
Bills Discounted/ PurchasedBills Discounted/ PurchasedDemand Loans, Overdraft etcDemand Loans, Overdraft etc
Non Fund Based FacilitiesNon Fund Based Facilities
Letter of Credit (Domestic/ Foreign)Letter of Credit (Domestic/ Foreign)
GuaranteeGuarantee
Deferred Payment Guarantee/ Co-Deferred Payment Guarantee/ Co-Acceptance of BillsAcceptance of Bills
Project FinancingProject Financing
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
108/116
Project FinancingProject Financing
A funding structure that relies on future cash flowsA funding structure that relies on future cash flowsfrom a specific development as the primary sourcefrom a specific development as the primary sourceof repayment with that developments assets, rightsof repayment with that developments assets, rightsand interests legally held as collateral security. Theand interests legally held as collateral security. The
Key Areas are -Key Areas are -Management AnalysisManagement AnalysisMarket & Demand AnalysisMarket & Demand Analysis
Technical AnalysisTechnical AnalysisFinancial AnalysisFinancial Analysis
Project FinancialsProject Financials
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
109/116
jFocus AreasFocus Areas
Capital StructureCapital Structure
a) Desired Debt/Equity Ratio < 2:1a) Desired Debt/Equity Ratio < 2:1
b) Min. Promoter Contribution at 20-25%b) Min. Promoter Contribution at 20-25%
Fixed Asset Coverage RatioFixed Asset Coverage Ratio
(Fixed Assets (WDV)/Term Liabilities)(Fixed Assets (WDV)/Term Liabilities)Fixed Asset Coverage >1.25 is preferred.Fixed Asset Coverage >1.25 is preferred.
Debt Service Coverage Ratio (DSCR)Debt Service Coverage Ratio (DSCR)
EBIDA/(Interest + Principal Amount)EBIDA/(Interest + Principal Amount)
Desired DSCR is >1.50Desired DSCR is >1.50
Project FinancialsProject Financials
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
110/116
jFocus AreasFocus Areas
Break Even PointBreak Even PointLower the level, the better it is for the project.Lower the level, the better it is for the project.
Sensitivity AnalysisSensitivity Analysis
Impact study on the cash flows due to adverseImpact study on the cash flows due to adversechanges in the Cost or the Sales side.changes in the Cost or the Sales side.
Repayment PeriodRepayment PeriodNormally repayment term of 7 years is preferred.Normally repayment term of 7 years is preferred.
WorkingWorkingCapital FinancingCapital Financing
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
111/116
What we look for?What we look for?
Focus onFocus on Volumes/ Sales growthVolumes/ Sales growth
Operating efficiencyOperating efficiency
LiquidityLiquidity
GearingGearing
Quality of current assets.Quality of current assets. Efficiency in asset turn over.Efficiency in asset turn over.
Methods of WC AssessmentMethods of WC Assessment
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
112/116
Methods of WC AssessmentMethods of WC Assessment
As per Nayak committee (TurnoverAs per Nayak committee (Turnover
Method)Method)
Working Capital Gap MethodWorking Capital Gap Method Cash flow methodCash flow method
Turnover MethodTurnover Method
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
113/116
Turnover MethodTurnover Method
For Working Capital Limits up to Rs. 5.00 CroreFor Working Capital Limits up to Rs. 5.00 Crore
1.1. Annual turnover as projected by borrower.Annual turnover as projected by borrower.
2.2. Turnover as accepted by Bank.Turnover as accepted by Bank.
3.3. Working Capital requirements [25% of sales i.e.Working Capital requirements [25% of sales i.e.item 2].item 2].
4.4. Minimum margin required [5% of sales i.e. item 2].Minimum margin required [5% of sales i.e. item 2].
5.5. Actual margin available (Net Working Capital).Actual margin available (Net Working Capital).6.6. Maximum permissible Bank Finance is lower of theMaximum permissible Bank Finance is lower of the
(item 3 item 4) and (item 3 item 5).(item 3 item 4) and (item 3 item 5).
Working Capital Gap MethodWorking Capital Gap Method
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
114/116
11stst
Method ofMethod ofLendingLending 22ndnd
Method ofMethod ofLending (MPBF)Lending (MPBF)
CACA 10001000 10001000
CL excl BankCL excl Bank 400400 400400
WC GapWC Gap 600600 600600
Min. StipulatedMin. Stipulated
NWCNWC
150150
(25% of WC Gap)(25% of WC Gap)
250250
(25% of CA)(25% of CA)
Bank FinanceBank Finance 450450 350350
Working Capital Gap Methodg p p
Cash-flow MethodCash-flow Method
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
115/116
Cash-flow MethodCash flow Method
Prepare a cash flow statement for the next 12 monthsPrepare a cash flow statement for the next 12 months Arrive at the maximum requirement.Arrive at the maximum requirement.
Obtain documents for the max. amount.Obtain documents for the max. amount.
Operation based on monthly requirements.Operation based on monthly requirements. Monitoring at periodical intervals.Monitoring at periodical intervals.
Challenges Faced by Risk and Providers ofChallenges Faced by Risk and Providers of
CapitalCapital
-
8/7/2019 1MBA3RD PRTOJECT APPRAISAL
116/116
CapitalCapitalRisk Head Description
Promoter Risk Capability to implement projects
Ability to Infuse Capital
Market Risk Demand Risk Tariff Risk
Financing Risk Financial Closure Risk
Equity Infusion Risk
Construction Risk Capability to construct
Technology Used, Equipment Quality
Land Acquisition Risk, Environmental Risks
Fuel Supply Risk Availability of Requisite quantity and Quality of Fuel at
Budgeted Cost
Regulatory Risk Risk of not getting approvals