1mba3rd prtoject appraisal

Upload: naresh-thakur

Post on 08-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    1/116

    PROJECT APPRAISALPROJECT APPRAISAL

    SARITA THAKURSARITA THAKUR

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    2/116

    Meaning and definitionMeaning and definition Assessment of a project in terms of its economic, social and financial viabilityAssessment of a project in terms of its economic, social and financial viability

    A lending financial institution makes an independent and objectiveA lending financial institution makes an independent and objective

    assessment of various aspects of an investment propositionassessment of various aspects of an investment proposition

    It is defined as taking a second look critically and carefully at a project by aIt is defined as taking a second look critically and carefully at a project by a

    person who is in no way involved or connected with its preparation. He isperson who is in no way involved or connected with its preparation. He is

    able to take independent, dispassionate and objective view of the project inable to take independent, dispassionate and objective view of the project in

    totality, along with its various componentstotality, along with its various components

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    3/116

    UNIT - IIPROJECT APPRAISAL

    INTRODUCTION PROJECT APPRAISAL:

    1. Technique to analyse if the project is feasible or not.2. It helps in recognizing needs and problems, and their early

    analysis3. A tool fordecision making4. Identifying input, output parameters and criteria for evaluating

    systems.5. Evaluating feasibility in terms oftechnical, financial and

    economic practicability.

    6. Developing and implementation of system so designed interms of- Engg. Calculations

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    4/116

    - Specification of finalization- Production, manufacturing

    Installation and commissioning

    SALIENT ASPECTS OF PROJECT APPRAISAL

    a. Need - New or improvedb. Realisability - Cost/benefit termsc. Practicability - Technically, Financially economically viable.d. Optimality: Project to be best alternativee. Uncertainty : Probability of risk and cost of information to

    achieve greater certaintyf. Controllability - Needs a feed back loop to review update and

    keep system on rough track.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    5/116

    Feasibility Study:

    It involvedcreating, identifying, brain storming feasibility of

    ideas and then selecting to prove further one or more feasiblesolutions.- Thenprilimary design, optimal design (best alternatives)- Detailed design (a complete description of projects for its

    implimentation.- Lastly planning for production:

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    6/116

    (ii) Environment (Business) Interest, Insurance,

    Legal, Regulatory, Pollution.

    b. Project Output(i) Desired(ii) Undesired

    (i) Desired: Desired could involved physical quantities ofproducts how much, how many, could also involve valuejudgment status, comfort, Aesthetic Appeal (Keeping userin view undesired)

    (ii) Undesired: Undesired Pollution, Waste material, WasteEnergy, Danger (Bhopal Gas Tragedy, Nuclear Explosion).

    Discomfort to people living in vicinity.

    c. Design Parameters: Like features attributes that wouldaffect behavior and performance. Most common ar

    physical size, weight, etc.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    7/116

    Feasibility Study has following sequence of events (Parts)

    Need Analysis: Define objectives of the projects. New oimproves.

    Project Identification: Quantifies input, output, designparameters.

    a. Project Inputs:

    (i) Purposeful Controllable- Uncontrollable

    Controllable: Man hours, Capital Inflow,Activity Analysis:

    Uncontrollable: Cost of Raw Material, Reliability of

    Technology, Availability of Power, Govt.& Political Interference.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    8/116

    d. Constraint Specification: on input, output, designparameters which could be essential to evaluate the alternativesolutions. Measure of the values indicate range of accepvalues.

    e. Evaluation Criteria: Total revenue operating cost gross/ netprofit, ROI/ EOI etc.

    3. Practicability Analysis: Idea to eliminate the concepts thatare not feasible. Are these operational financeableEconomical, Physically realizable, Politically acceptable ,

    Physically Realizable which alternatives needs the

    solutions within the specified parameters.

    Financial Realizability: (i) Will the money requiredcome as per time frame.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    9/116

    (ii) Sources of Capital Inflow who where from:4. Economic Practicality :

    (i) Even a financially feasible may not beeconomically practical.

    (ii) Economic Feasibility Study of alternativesolutions by constraints operating cost, Maintenancand Spare part expenditure.

    (iii) Total revenue that would accrue over the operational

    life of systems, (i.e. what is thebreak even point oroptimum point of economic operations of the project)

    We will consider those alternative solutions to be

    economically feasible that meet the specified rates ofreturn on investment.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    10/116

    5. Social and Political Realizeability : The projectmay be physically, Financially, Economically feasible,but may encounter social at political obstacles.

    Normally in case of large projects, there are additional

    considerations ofhealth (Polio Campaign, Malaria, TB,CNG Buses) education (private and foreign universities)Welfare (METRO RAIL, Realignment over the rangearea, Civil Nuclear Technology).

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    11/116

    Feasibility Study: A Schematic Diagram

    Yes

    Initial Screening

    Is the Idea Prima Facie Promising ?

    Plan Feasibility Analysis

    Generation of Ideas

    Conduct Market Analysis Conduct Technical AnalysisBasic and functional feasibliity

    Terminate

    Conduct Financial Analysis

    Risk./ Return

    PreliminaryPractica

    lAnalysis

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    12/116

    Yes NO

    Is the Project Worthwhile?

    Prepare Funding Proposal

    Including optimality and controllability

    Conduct Economic and Ecological Analysis

    Social & Political Realisability

    Terminate

    St f j tSt f j t

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    13/116

    Steps for projectSteps for project

    appraisal/Aspects of projectappraisal/Aspects of project

    appraisalappraisal Economic AspectsEconomic Aspects Technical AspectsTechnical Aspects

    Organisational AspectsOrganisational Aspects Managerial AspectsManagerial Aspects

    Financial AspectsFinancial Aspects

    Market/Commercial AspectsMarket/Commercial Aspects

    K i i P j A l i

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    14/116

    Key issues in Project AnalysisPotential Market

    Market AnalysisMarket Share

    Technical ViabilityTechnical Analysis

    Sensible ChoicesRisk

    Financial Analysis

    ReturnBenefits and Costs in Shadow Prices

    Economic AnalysisOther Impacts

    Environmental DamageEcological AnalysisRestoration Measure

    T h i l A i l

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    15/116

    Technical AppraisalBy technical appraisal of project, we mean an assessment of its basic technical and

    functional feasibility of project (Road under/over bridge)Besides costs and schedules, the project performance depends on how well the project ismeeting the technical requirements of the end project (connect village to stadium)

    - THREE STAGES OF TECH APPRAISAL

    (i) Detailed technical Appraisal

    Which include describing the details of the assignment

    and the key property.

    It l i l d d ibi th d fi i i f ti l

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    16/116

    It also includes describing the deficiencies of particularacclamation.

    The detailed technical appraisal method helps incommenting on the reviewers action, analysis and

    conclusions.(ii) Exceptional Technical Appraisal appraisal reviews records only significant and exceptional

    findings and action take by the reviewer. The exceptional review is often used forhigh level

    reviews within an organization when the first level review isa narrative report.

    (iii)Form Technical Appraisal In form review, further abbreviates the documentation

    associated with reviewing an appraisal report. Forms are developed for specific institutional or agency

    needs and the Standard Appraisal Review

    R t f i b i id l t d b

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    17/116

    Report from is becoming more widely accepted by manyusers.

    Factors Effecting Technical Appraisal

    (i) Layout:- Layout of the project includes description of theproject in terms of what they represent and when theyoccur,who has authorized it, number of people who willhandle. It also states where quality control will be exercised. A description and explanation of the methods of that

    will be used to monitor progress e.g. bar chartscould be used.

    For Example

    Weekly progress meeting to exercise control over theproject.

    (ii) L ti Th i k f t th t i fl l ti

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    18/116

    (ii) Location:- The nine key factors that influence locationof a project are: (keep NANO Car Project In Mind)

    - Costs- Infrastructure around the location

    - Labour Characteristics- Wage rates- Motivation of workers- Telecommunication systems- Government stability and industrial relations laws

    - Protection of patentsA availability of management resources and specific skills

    and system and integration costs.These factors have an impact on management decisions

    and governments policies.

    G t li i R l t b i l d

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    19/116

    Government policies: Regulatory barriers may precludethe use of innovative technologies e.g. some reservation forSME Sector (Now only 3s items)

    Types of equipment or processes: Equipments are

    basically of two types temporary and permanentequipments. (Olympic stadium in China)

    The availability and quality of equipments affect thetechnical appraisal.

    Appropriateness of Local Conditions: The project should

    be adaptable to local technical and environmentalconditions, such as voltage, dust, temperature, humidity, etc.

    The appropriate supply of material and equipments forkeeping the project working should be available in

    proximity.

    I t f E i t Th t ti l i t f th

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    20/116

    Impact of Environment: The potential impact of theproject on the human and physical environment is examinedto make sure that nay adverse effects can be controlled orminimized e.g. pollution.

    Approach Followed: Procedures for obtainingengineering, architectural, or other professional services areexamined.

    Risk Factor: It is necessary to identify the risks associatedwith the project and estimate the scale of risk. There should

    also be contingency plans in place to minimize the risk ofproject failure or of a major gap between whats promisedand whats delivered.

    Cost Estimated: Technical appraisal is a review of the cost

    estimates of the engineering and maintaining the project.Cost estimates also determine whether technical appraisal isaccurate within an acceptable margin.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    21/116

    Plant CapacityPlant Capacity

    Product MixProduct Mix

    Structure and civil WorksStructure and civil Works Schedule of project implementation.Schedule of project implementation.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    22/116

    Technical AspectsTechnical Aspects

    Site and Location: RM supply, proximity to markets, transportationSite and Location: RM supply, proximity to markets, transportation

    facility, power supply, manpower, water, government policies,facility, power supply, manpower, water, government policies,

    labour laws, climate, taxeslabour laws, climate, taxes

    Size of plant/scale of operations: Technological capacity isSize of plant/scale of operations: Technological capacity is

    standardised for achieving economies of scale, low demand or lessstandardised for achieving economies of scale, low demand or less

    resource availability result in economies of scaleresource availability result in economies of scale

    Technical feasibility: Technology selected, availability ofTechnical feasibility: Technology selected, availability ofinfrastructure, plant layout, project implementation schedules etcinfrastructure, plant layout, project implementation schedules etc

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    23/116

    This can be viewed as whatever lies outside the project

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    24/116

    This can be viewed as whatever lies outside the project,but that which can affect and be affected by the operationsof the project.

    In project parlance the environment means much more

    than just the weather.For example, for automobile environment, we can considerthe roads and highways; petrol pumps and servicingstations, etc. need to be included in our definition of theautomobile system.

    When we say that something lies outside the project, andhence constitutes its environment, we mean that the projectcan do relatively little about its environmentscharacteristics or behaviour.

    Identification of the environment depends on the answersto the following two questions.

    1. Can I do anything about it?

    2 Does it affect my situation or objectives?

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    25/116

    2. Does it affect my situation or objectives ?If the answer to the first is No, and that do the second isYes, then it is the environment.

    Characteristics of the Environment

    The environment provide, given orfixed inputs to theproject.

    It is also affected, directly or indirectly, by the outputsfrom the project;

    Hence, it has a dynamic influence on the project or bythe project.

    However, less attention is paid on environment because of

    two reasons(a) Firstly : The environment is outside the project and

    hence oflittle direct interest to us.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    26/116

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    27/116

    Managerial AspectsManagerial Aspects

    Organization structure, recruitment and training aspectsOrganization structure, recruitment and training aspects

    are studiesare studies

    Appraisal done to see if project is adequately staffed,Appraisal done to see if project is adequately staffed,initial recruitment is done. Managerial ability plays aninitial recruitment is done. Managerial ability plays an

    important role in making an enterprise a success orimportant role in making an enterprise a success or

    otherwise. In the absence of managerial competence ,otherwise. In the absence of managerial competence ,

    the project which are otherwise feasible may fail.the project which are otherwise feasible may fail.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    28/116

    It is strictly pointed out that if the project isIt is strictly pointed out that if the project is

    weak, it can be improved upon, but if theweak, it can be improved upon, but if the

    promoters are weak & lack in business, it ispromoters are weak & lack in business, it is

    difficult to reverse the situation. So whiledifficult to reverse the situation. So while

    doing the project appraisal , the managerialdoing the project appraisal , the managerial

    competence or talent of the promoter shouldcompetence or talent of the promoter should

    be taken into consideration.be taken into consideration.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    29/116

    Managerial AspectsManagerial Aspects

    Financial institutions check if promoters areFinancial institutions check if promoters are

    competent and have business sensecompetent and have business sense

    They can appoint nominee directors on boardThey can appoint nominee directors on board

    The Companies Act and Industries ActThe Companies Act and Industries Act

    empower government to exercise control overempower government to exercise control over

    managementmanagement

    They can also take over the management inThey can also take over the management in

    case it is neededcase it is needed

    Managerial Appraisal

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    30/116

    Managerial Appraisal

    One of the main preoccupations of management in anyorganization and in project organization is the allocation ofscarce resources.

    These resources include manpower, materials, facilities,and financial resources.

    For every project being planned, the project manager must

    ask the following two questions:- Are the resources required for the given projectavailable ?- Is this the best use to which these resources caput ?

    Most project are subjected to an evaluation before they aregiven the go-ahead.

    An essential part of his evaluation is the financial

    appraisal

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    31/116

    appraisal.

    Traditionally, this has been aimed at deciding whether ornot a project will be profitable and selecting the one

    project out of several competing projects that appearsthe most profitable. The project manager shouldunderstand the processes so that he can benefit from them.(Difference between private public Social Benefitprojects).

    It is with this intention that we present the varioustechniques ofmanagerial evaluation, which consist of thetechnical, economic, financial, social and political

    appraisal and assessment of a project.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    32/116

    FINDING A PROJECT MANAGERFINDING A PROJECT MANAGER 1.Project Department-1.Project Department---Growth oriented companies--Growth oriented companies

    have a separate department called the projecthave a separate department called the projectdepartment.this deptt. Is responsible for:-department.this deptt. Is responsible for:-

    Looking for new opportunities for growthLooking for new opportunities for growth

    Formulate projectsFormulate projects

    Responsibilty for implementation of the projectResponsibilty for implementation of the project

    coordinating.,directing & controlling all aspects of thecoordinating.,directing & controlling all aspects of the

    project.project.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    33/116

    2.Recruitment from open marketA project

    manager may also be appointed when the

    company in venturing into new &innovtaive technology.The person to be

    appointed must have considerable

    experience in the new technology.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    34/116

    TERM APPOINTMENTTERM APPOINTMENT IT ENGAGE A PROFESSIONAL PROJECTIT ENGAGE A PROFESSIONAL PROJECT

    MANAGER ON TERM APPOINTMENT. In this case theMANAGER ON TERM APPOINTMENT. In this case the

    terms of appointment have to be very lucrative to maketerms of appointment have to be very lucrative to make

    the other person interested.the other person interested.

    Service Companies:ItService Companies:It mean to borrow the staff frommean to borrow the staff from

    project management service companis. A projectproject management service companis. A project

    management compnies can offer many services includingmanagement compnies can offer many services including

    loaning of staff who can bebased at the client office &loaning of staff who can bebased at the client office &

    work for the client as if they were the clients regular staff.work for the client as if they were the clients regular staff.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    35/116

    Problems & challenges of projectProblems & challenges of project

    manager.manager. AuthorityAuthority

    OrientationOrientation

    MotivationMotivation Building effective groupsBuilding effective groups

    Impartial approach.Impartial approach.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    36/116

    Project Management SkillsProject Management Skills

    Program area knowledge, standards, andProgram area knowledge, standards, and

    regulationsregulations

    Understand the project environmentUnderstand the project environment

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    37/116

    Project Management SkillsProject Management Skills

    Program area knowledge, standards, andProgram area knowledge, standards, and

    regulationsregulations

    Understand the project environmentUnderstand the project environment

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    38/116

    Project Management SkillsProject Management Skills

    General management skills (budgeting,General management skills (budgeting,

    scheduling)scheduling)

    Communication skillsCommunication skills

    Interpersonal skillsInterpersonal skills

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    39/116

    The project manager makes thingsThe project manager makes things

    happen!happen!

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    40/116

    Methods of Project AppraisalMethods ofProject Appraisal

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    41/116

    Meaning of Project AppraisalMeaning of Project Appraisal: -: -

    Project AppraisalProject Appraisal is the analysis of costs and benefits of a proposed project with ais the analysis of costs and benefits of a proposed project with a

    goal of assuring a rational allocation of limited financial resources amongst alternategoal of assuring a rational allocation of limited financial resources amongst alternate

    Investment opportunities with the objective of achieving specific goals.Investment opportunities with the objective of achieving specific goals.

    Project AppraisalProject Appraisal is mainly the process of transmitting information accumulatedis mainly the process of transmitting information accumulatedthrough feasibility studies into a comprehensive form in order to enable thethrough feasibility studies into a comprehensive form in order to enable the

    decision maker undertake a comprehensive appraisal of various projects anddecision maker undertake a comprehensive appraisal of various projects and

    embark on a specific project or projects by allocating resources.embark on a specific project or projects by allocating resources.

    The various Factors considered by Financial Institutions while appraising aThe various Factors considered by Financial Institutions while appraising aproject are: -project are: -

    Technical, Financial, Economic, Commercial, Social andTechnical, Financial, Economic, Commercial, Social and

    Managerial Factors.Managerial Factors.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    42/116

    Objectives & ScopeObjectives & Scope: -: -

    To extract relevant information for determining the success orTo extract relevant information for determining the success or

    failure of a project.failure of a project.

    To apply standard yardsticks for determining the rate of success orTo apply standard yardsticks for determining the rate of success or

    failure of a project.failure of a project.

    To determine the expected costs and benefits of the project.To determine the expected costs and benefits of the project.

    To arrive at specific conclusions regarding the project.To arrive at specific conclusions regarding the project.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    43/116

    SignificanceSignificance: -: -

    It helps in arriving at specific and predicted results.It helps in arriving at specific and predicted results.

    It evaluates the desirability of the project.It evaluates the desirability of the project.

    It provides information to determine the success or failure of aIt provides information to determine the success or failure of aproject.project.

    It employs existing norms to predict the rate of success or failureIt employs existing norms to predict the rate of success or failure

    of the project.of the project.

    It verifies the hypothesis framed for the project.It verifies the hypothesis framed for the project.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    44/116

    Factors Considered while Appraising a ProjectFactors Considered while Appraising a Project: -: -

    Technical FactorsTechnical Factors

    Financial FactorsFinancial Factors

    Economic FactorsEconomic Factors Social FactorsSocial Factors

    Commercial FactorsCommercial Factors

    Managerial FactorsManagerial Factors

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    45/116

    Methods of Project AppraisalMethods ofProject Appraisal

    METHODS O FPROJECT APPRAISAL

    DISCOUNTING

    CRITERIA

    NON -DISCOUNTING

    CRITERIA

    NET

    PRES ENT

    VALUE

    PROFIT-

    ABILITY

    INDEX

    INTERNAL

    RATE OF

    RETURN

    PAYBA CK

    PERIODACCOUNTING

    RATE OFRETURN

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    46/116

    Pay-Back Period MethodPay-Back Period Method: -: -

    TheThe Pay-Back PeriodPay-Back Period is the length of time required to recover the initial outlay onis the length of time required to recover the initial outlay on

    the project Or It is the time required to recover the original investment throughthe project Or It is the time required to recover the original investment through

    income generated from the project.income generated from the project.

    Pay-Back PeriodPay-Back Period == Original Cost of Investment____Original Cost of Investment____

    Annual Cash Inflows or SavingsAnnual Cash Inflows or Savings

    ProsPros: -: - a) It is easy to operate and simple to understand.a) It is easy to operate and simple to understand.

    b) It is best suited where the project has shorter gestation period andb) It is best suited where the project has shorter gestation period and

    project cost is also less.project cost is also less.

    c) It is best suited for high risk category projects. Which are prone to rapidc) It is best suited for high risk category projects. Which are prone to rapid

    technological changes.technological changes.

    d) It enables entrepreneur to select an investment which yields quick returnd) It enables entrepreneur to select an investment which yields quick return

    of funds.of funds.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    47/116

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    48/116

    Accounting Rate of Return MethodAccountingRate of Return Method: -: -

    This method is considered better than pay-back period method because it considersThis method is considered better than pay-back period method because it considers

    earnings of the project during its full economic life. This method is also knownearnings of the project during its full economic life. This method is also known

    asas Return On InvestmentReturn On Investment (ROI). It is mainly expressed in terms of percentage.(ROI). It is mainly expressed in terms of percentage.

    ARR or ROIARR or ROI == Average Annual Earnings After Tax_______Average Annual Earnings After Tax_______ * 100* 100

    Average Book Investment After DepreciationAverage Book Investment After Depreciation

    Here, Average Investment = (Initial Cost Salvage Value) * 1 / 2Here, Average Investment = (Initial Cost Salvage Value) * 1 / 2

    Decision RuleDecision Rule: - In the ARR, A project is to be: - In the ARR, A project is to be ACCEPTEDACCEPTED when ( If Actual ARRwhen ( If Actual ARR

    is higher or greater than the rate of return) otherwise it is Rejectedis higher or greater than the rate of return) otherwise it is Rejected

    and In case of alternate projects, One with the highest ARR is toand In case of alternate projects, One with the highest ARR is to

    be selected.be selected.

    PP ) i i) I i i l l l d d d

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    49/116

    ProsPros: -: - a) It is simple to calculate and easy to understand.a) It is simple to calculate and easy to understand.

    b) It considers earning of the project during the entire operative life.b) It considers earning of the project during the entire operative life.

    c) It helps in comparing the projects which differ widely.c) It helps in comparing the projects which differ widely.

    d) This method considers net earnings after depreciation and taxes.d) This method considers net earnings after depreciation and taxes.

    ConsCons: -: -a) It ignores time value of money.a) It ignores time value of money.b) It lays more emphasis on profit and less on cash flows.b) It lays more emphasis on profit and less on cash flows.c) It does not consider re-investment of profit over years.c) It does not consider re-investment of profit over years.

    d) It does not differentiate between the size of investments required ford) It does not differentiate between the size of investments required for

    different projects.different projects.

    For ExampleFor Example: -: - Project AProject A Project BProject BInvestmentInvestment 25,00025,000 37,00037,000

    Expected Life (In Yrs.)Expected Life (In Yrs.) 4 4

    Net Earnings (After Dep. & Taxes)Net Earnings (After Dep. & Taxes)

    YearsYears

    11 25002500 37503750

    22 18751875 3750375033 18751875 25002500

    44 12501250 12501250

    If the Desired rate of return is 12%, which project should be selected?If the Desired rate of return is 12%, which project should be selected?

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    50/116

    NPV (Net Present Value) MethodNPV (Net Present Value) Method: -: -

    This method mainly considers the time value of money. It is the sum of theThis method mainly considers the time value of money. It is the sum of the

    aggregate present values of all the cash flows positive as well as negative thataggregate present values of all the cash flows positive as well as negative that

    are expected to occur over the operating life of the project.are expected to occur over the operating life of the project.

    NPVNPV = PV of Net Cash Inflows Initial Outlay (Cash outflows)= PV of Net Cash Inflows Initial Outlay (Cash outflows)

    Decision RuleDecision Rule: -: - If NPV is positive, ACCEPTIf NPV is positive, ACCEPT If NPV is negative, REJECTIf NPV is negative, REJECT If NPV is 0, then apply Payback Period MethodIf NPV is 0, then apply Payback Period Method

    The standard NPV method is based on the assumption that the intermediateThe standard NPV method is based on the assumption that the intermediatecash flows are reinvested at a rate of return equal to the cost of capital. Whencash flows are reinvested at a rate of return equal to the cost of capital. Whenthis assumption is not valid, the investment rates applicable to the intermediatethis assumption is not valid, the investment rates applicable to the intermediatecash flows need to be defined for calculating the modified NPV.cash flows need to be defined for calculating the modified NPV.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    51/116

    Pros and Cons of NPVPros and Cons ofNPV: -: -

    ProsPros: -: -a) This method introduces the element of time value of money and as such is aa) This method introduces the element of time value of money and as such is a

    scientific method of evaluating the project.scientific method of evaluating the project.

    b) It covers the whole project from start to finish and gives more accurateb) It covers the whole project from start to finish and gives more accurate

    figuresfigures

    c) It Indicates all future flows in todays value. This makes possiblec) It Indicates all future flows in todays value. This makes possible

    comparisons between two mutually exclusive projects.comparisons between two mutually exclusive projects.

    d) It takes into account the objective of maximum profitabilityd) It takes into account the objective of maximum profitability

    ConsCons: -: -a) It is difficult method to calculate and use.a) It is difficult method to calculate and use.

    b) It is biased towards shot run projects.b) It is biased towards shot run projects.

    c) In this method profitability is not linked to capital employed.c) In this method profitability is not linked to capital employed.

    d) It does not consider Non-Financial data like the marketability of a product.d) It does not consider Non-Financial data like the marketability of a product.

    For ExampleFor Examp

    le: -: -

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    52/116

    For ExampleFor Example: : Initial Investment 20,000Initial Investment 20,000

    Estimated Life 5 years

    Scrap Value 1000 XYZ Enterprises Capital Project

    Year Cash flow Discount factor Present V@10%

    1 5.000 0.909

    2 10,000 0.826

    3 10,000 0.751

    4 3,000 0.683

    5 2,000 0.621

    5 1,000 0.621

    PV of Net Cash Inflows = 24227

    NPV = PV of Net Cash Inflows Cash Outflows

    = 24227 20,000

    NPV = 4227Here, NPV is Positive (+ ve) The Project is ACCEPTED.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    53/116

    Profitability Index MethodProfitability Index Method: -: -

    Profitability IndexProfitability Index is the ratio of present value of expected future cash inflowsis the ratio of present value of expected future cash inflows

    andand

    Initial cash outflows or cash outlay. It is also used for ranking the projects in orderInitial cash outflows or cash outlay. It is also used for ranking the projects in order

    of their profitability. It is also helpful in selecting projects in a situation of capitalof their profitability. It is also helpful in selecting projects in a situation of capital

    rationing. It is also know as Benefit / Cost Ratio (BCR).rationing. It is also know as Benefit / Cost Ratio (BCR).

    PI =PI = Present value of Future cash InflowsPresent value of Future cash Inflows

    Initial Cash OutlayInitial Cash Outlay

    Decision RuleDecision Rule: - In Case of Independent Investments,: - In Case of Independent Investments, ACCEPTACCEPT a Project If a PI isa Project If a PI isgreater ( > 1 ) and Reject it otherwise.greater ( > 1 ) and Reject it otherwise.

    In Case of Alternative Investments,In Case of Alternative Investments, ACCEPTACCEPT the project withthe project with

    thethe

    largest PI, provided it is greater than ( > 1 ) and Reject others.largest PI, provided it is greater than ( > 1 ) and Reject others.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    54/116

    IRR (I l R f R ) M h dIRR (I

    l R f R ) M h d

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    55/116

    IRR (Internal Rate of Return) MethodIRR (Internal Rate of Return) Method: -: -

    This method is known by various other names likeThis method is known by various other names like Yield on InvestmentYield on Investment ororRate ofRate of

    Return MethodReturn Method. It is used when the cost of investment and the annual cash inflows. It is used when the cost of investment and the annual cash inflowsare known and rate of return is to be calculated. It takes into account time value ofare known and rate of return is to be calculated. It takes into account time value of

    Money by discounting inflows and cash flows. This is the Most alternative to NPV.Money by discounting inflows and cash flows. This is the Most alternative to NPV.

    It is the Discount rate that makes it NPV equal to zero.It is the Discount rate that makes it NPV equal to zero.

    In this Method, the IRR can be ascertained by theIn this Method, the IRR can be ascertained by the Trial & Error Yield MethodTrial & Error Yield Method,,

    Whose the objective is to find out the expected yield from the investment.Whose the objective is to find out the expected yield from the investment.

    rate + NPV @ Smaller rateSum of the absolute values of the

    NPV @ smaller and the bigger

    Discount rates

    Bigger

    X discount discountrate

    Decision Rule: - In the Case of an Independent Investment, ACCEPT the project if

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    56/116

    p p j

    Its IRR is greater than the required rate of return and if it is lower, ThenReject it. In Case of Mutually Exclusive Projects, ACCEPT the project with thelargest IRR, provided it is greater than the required rate of return &Reject others.

    Pros: - a) It considers the profitability of the project for its entire economic life andhence enables evaluation of true profitability.

    b) It recognizes the time value of money and considers cash flows overentire life of the project.

    c) It provides for uniform ranking of various proposals due to thepercentage rate of return.

    d) It has a psychological appeal to the user. Since values are expressed inpercentages.

    Cons: - a) It is most difficult method of evaluation of investment proposals.b) It is based upon the assumption that the earnings are reinvested at the

    Internal Rate of Return for the remaining life of the project.

    c) It may result in Incorrect decisions in comparing the Mutually ExclusiveProjects.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    57/116

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    58/116

    Assessment of NPV & IRR MethodAssessment of NPV & IRR Method

    NPVNPV IRRIRRTheoretical ConsiderationsTheoretical Considerations: -: -

    a) Does the method discount all casha) Does the method discount all cash YesYes YesYes

    flows?flows?

    b) Does the method discount cash flowsb) Does the method discount cash flows YesYes NoNo

    at the opportunity cost of funds?at the opportunity cost of funds?

    c) From a set of M.E. Projects, does thec) From a set of M.E. Projects, does the

    method choose the project whichmethod choose the project which

    maximizes shareholder wealth?maximizes shareholder wealth? YesYes NoNo

    Practical ConsiderationsPractical Considerations: -: -

    a) Is the Method Simple?a) Is the Method Simple? YesYes YesYes

    b) Can the method be used with limitedb) Can the method be used with limited

    information?information? NoNo NoNo

    c) Does the method give a relative measure? Noc) Does the method give a relative measure? No NoNo

    CASH FLOW ANALYSIS OFCASH FLOW ANALYSIS OF

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    59/116

    CASH-FLOW ANALYSIS OFCASH-FLOW ANALYSIS OF

    THE PROJECTTHE PROJECT PREPARE FINANCIAL PROJECTIONS:PREPARE FINANCIAL PROJECTIONS: FINANCIAL ADEQUACYFINANCIAL ADEQUACY FINANCIAL WORTHFINANCIAL WORTH RETURNS TO FINANCIALRETURNS TO FINANCIAL

    STAKEHOLDERSSTAKEHOLDERS LIST THE ASSUMPTIONSLIST THE ASSUMPTIONS

    SENSITIVITY ANALYSISSENSITIVITY ANALYSIS

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    60/116

    SCHEDULES (CONTD.)SCHEDULES (CONTD.)

    9. CASH-FLOW STATEMENT;9. CASH-FLOW STATEMENT;

    10. RATE OF RETURN CALCULATION;10. RATE OF RETURN CALCULATION;

    11. SENSITIVITY ANALYSIS.11. SENSITIVITY ANALYSIS.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    61/116

    SELECTION CRITERIASELECTION CRITERIA

    BENEFIT/COST RATIO;BENEFIT/COST RATIO;

    NET PRESENT VALUE;NET PRESENT VALUE;

    INTERNAL RATE OF RETURN:INTERNAL RATE OF RETURN: IRR;IRR;

    ERR.ERR.

    NON REVENUENON REVENUE

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    62/116

    NON-REVENUE-NON-REVENUE-

    GENERATING PROJECTSGENERATING PROJECTS WEAK FINANCES, SO WHY DO A FINANCIALWEAK FINANCES, SO WHY DO A FINANCIAL

    ANALYSIS?ANALYSIS? NEED TO QUANTIFY THE ANNUAL DEFICITS;NEED TO QUANTIFY THE ANNUAL DEFICITS; NEED TO DEVELOP STRATEGIES TO SUSTAIN THENEED TO DEVELOP STRATEGIES TO SUSTAIN THE

    PROJECT IMPACT;PROJECT IMPACT; POLICYPOLICY: SUBSIDISE ONLY THOSE WHO NEED IT,: SUBSIDISE ONLY THOSE WHO NEED IT,

    BUT NOT FOREVER!BUT NOT FOREVER!

    SELECTION CRITERIA:SELECTION CRITERIA:

    LEAST-COST ANALYSIS:LEAST-COST ANALYSIS:LEAST-COST ANALYSIS.xlsLEAST-COST ANALYSIS.xls COST-EFFECTIVENESS ANALYSIS:COST-EFFECTIVENESS ANALYSIS:

    COST-EFFECTIVENESS.xlsCOST-EFFECTIVENESS.xls

    NON REVENUE GENERATINGNON REVENUE GENERATING

    http://../My%20Documents/LEAST-COST%20ANALYSIS.xlshttp://../My%20Documents/LEAST-COST%20ANALYSIS.xlshttp://../My%20Documents/COST-EFFECTIVENESS.xlshttp://../My%20Documents/COST-EFFECTIVENESS.xlshttp://../My%20Documents/COST-EFFECTIVENESS.xlshttp://../My%20Documents/LEAST-COST%20ANALYSIS.xls
  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    63/116

    NON-REVENUE GENERATINGNON-REVENUE GENERATING

    PROJECTS (CONTD.)PROJECTS (CONTD.)

    NEED FOR GRANT FUNDS;NEED FOR GRANT FUNDS;

    GIFTS;GIFTS;

    VERY SOFT LOANS;VERY SOFT LOANS;

    SWEAT-EQUITY GET THE TARGETSWEAT-EQUITY GET THE TARGET

    GROUP TO CONTRIBUTE WHATEVERGROUP TO CONTRIBUTE WHATEVER

    THEY CAN, IN SUPPORT OF THETHEY CAN, IN SUPPORT OF THE

    PROJECT.PROJECT.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    64/116

    SENSITIVITY ANALYSISSENSITIVITY ANALYSIS

    WHAT IF?WHAT IF? .SALES DECLINE BY 10%.SALES DECLINE BY 10% .CAPITAL COST INCREASE BY 10%.CAPITAL COST INCREASE BY 10% .OPERATING COST INCREASE BY 10%.OPERATING COST INCREASE BY 10% . THERE IS A 10% DELAY IN PROJECT. THERE IS A 10% DELAY IN PROJECT

    IMPLEMENTATIONIMPLEMENTATION

    WHICH HAS THE GREATEST IMPACT?WHICH HAS THE GREATEST IMPACT? IS THE PROJECT STILL VIABLE?IS THE PROJECT STILL VIABLE?

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    65/116

    ECONOMIC ANALYSISECONOMIC ANALYSIS

    WHY THIS ANALYSIS? :WHY THIS ANALYSIS? : MARKET FAILURE;MARKET FAILURE;

    MONOPOLIES;MONOPOLIES; MERIT/DEMERIT GOODS;MERIT/DEMERIT GOODS;

    GOVERNMENT FAILURE;GOVERNMENT FAILURE;

    DIFFERENCE BETWEEN PRIVATE AND SOCIALDIFFERENCE BETWEEN PRIVATE AND SOCIAL

    VALUATION OF COSTS AND BENEFITS;VALUATION OF COSTS AND BENEFITS;

    IDENTIFY INTERNAL AND EXTERNAL COSTSIDENTIFY INTERNAL AND EXTERNAL COSTSAND BENEFITS:AND BENEFITS: ECONOMIC FOCUS.xlsECONOMIC FOCUS.xls

    http://../My%20Documents/ECONOMIC%20FOCUS.xlshttp://../My%20Documents/ECONOMIC%20FOCUS.xlshttp://../My%20Documents/ECONOMIC%20FOCUS.xls
  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    66/116

    ECONOMIC ANALYSIS (CONTD.)ECONOMIC ANALYSIS (CONTD.)

    DOES THE PROJECT GENERATE NETDOES THE PROJECT GENERATE NET

    BENEFITS FOR THE COUNTRY?BENEFITS FOR THE COUNTRY?

    VALUING COSTS AND BENEFITS FROMVALUING COSTS AND BENEFITS FROM

    THE NATIONAL PERSPECTIVE;THE NATIONAL PERSPECTIVE;

    SHADOW-PRICING;SHADOW-PRICING;

    RE-CALCULATING PROJECT WORTHRE-CALCULATING PROJECT WORTH

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    67/116

    ECONOMIC ANALYSIS (CONTD.)ECONOMIC ANALYSIS (CONTD.)

    THE NUMERAIRE USED IN MEASURINGTHE NUMERAIRE USED IN MEASURING

    VALUE;VALUE;

    CONVERSION FACTOR V/S THECONVERSION FACTOR V/S THE

    SHADOW FOREIGN EXCHANGE RATESHADOW FOREIGN EXCHANGE RATE

    APPROACH;APPROACH;

    COMPARING THE RESULTS;COMPARING THE RESULTS;

    RATIONALE FOR CHOOSING THERATIONALE FOR CHOOSING THE

    CONVERSION FACTOR APPROACH.CONVERSION FACTOR APPROACH.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    68/116

    SOCIAL PERSPECTIVESSOCIAL PERSPECTIVES

    SO THE COUNTRY GAINS; BIG DEAL!SO THE COUNTRY GAINS; BIG DEAL! .WHO EXACTLY.WHO EXACTLY GAINS? .GAINS? . .THE POOREST OF THE POOR? ..THE POOREST OF THE POOR? . . OTHER DISADVANTAGED GROUPS?. OTHER DISADVANTAGED GROUPS?

    WOMEN, YOUTHS, RURAL PEOPLE?WOMEN, YOUTHS, RURAL PEOPLE? ??

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    69/116

    Project Appraisal- An OverviewProject Appraisal- An Overview

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    70/116

    A dAgenda

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    71/116

    AgendaAgenda

    IntroductionIntroduction Aspects of Project FinanceAspects of Project Finance

    Managerial AppraisalManagerial Appraisal

    Technical AppraisalTechnical Appraisal

    Commercial AppraisalCommercial Appraisal

    Selected financial indicatorsSelected financial indicators

    Case StudyCase Study

    P j tP j t

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    72/116

    ProjectProject

    A non repetitive activityA non repetitive activity

    Involves large capital expendituresInvolves large capital expenditures

    Returns over a long period of timeReturns over a long period of time

    Requires significant managerial bandwidthRequires significant managerial bandwidth

    Varied risksVaried risks

    Uncertainty of future business environmentUncertainty of future business environment

    P j FiP j t Fi

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    73/116

    Project FinanceProject Finance

    Level of funding raised based purely on the meritsLevel of funding raised based purely on the meritsof the relevant projectof the relevant project

    Lender is satisfied to look initially at the cashflowsLender is satisfied to look initially at the cashflows

    and earnings of a economic unitand earnings of a economic unit

    Debt would be repaid from the economic unitDebt would be repaid from the economic unit

    The loan and equity returns are tied to the cashThe loan and equity returns are tied to the cash

    flows and fortunes of the project rather than beingflows and fortunes of the project rather than being

    dependant on the parent company/companies.dependant on the parent company/companies.

    Project AppraisalProject Appraisal

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    74/116

    Project AppraisalProject Appraisal

    The purpose of Project Appraisal is to ascertainThe purpose of Project Appraisal is to ascertainwhether the project is sound technically,whether the project is sound technically,economically, financially and managerially and iseconomically, financially and managerially and isultimately viable as a commercial proposition.ultimately viable as a commercial proposition.

    Multifaceted activity; Requires skills ofMultifaceted activity; Requires skills of PsychologistPsychologist EngineerEngineer Financial AnalystFinancial Analyst

    EconomistEconomist

    P j t A i lProject Appraisal

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    75/116

    Project AppraisalProject Appraisal

    Each and every project is based upon assumptions, necessarilyEach and every project is based upon assumptions, necessarilyinvolve capital expenditure in the hope of a reasonable returninvolve capital expenditure in the hope of a reasonable returnon investment over a future period of time.on investment over a future period of time.

    Project Appraisal necessarily involves validation of variousProject Appraisal necessarily involves validation of variousassumptionsassumptions

    Appraisal ofAppraisal of Management/ Sponsor/ PromoterManagement/ Sponsor/ Promoter Technical aspectsTechnical aspects Market & Selling ArrangementsMarket & Selling Arrangements Financial viabilityFinancial viability

    I iti l S i 1/ 3Initial Screening 1/ 3

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    76/116

    Initial Screening 1/ 3Initial Screening 1/ 3

    WHAT IS THE PRODUCT (General industry structure)WHAT IS THE PRODUCT (General industry structure) WHO IS SETTING UP THE PROJECT (Promoters andWHO IS SETTING UP THE PROJECT (Promoters and

    their experience)their experience)

    Our experience from similar unitsOur experience from similar units

    Banks lending policiesBanks lending policies Government/ RBI RegulationsGovernment/ RBI Regulations

    Past business financialsPast business financials

    CollateralsCollaterals

    I iti l S i 2/ 3Initial Screening 2/ 3

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    77/116

    Initial Screening 2/ 3Initial Screening 2/ 3

    Distance of unit from branchDistance of unit from branch RBI/ CIBIL/ AML ListsRBI/ CIBIL/ AML Lists

    ECGC Specific Approval ListECGC Specific Approval List

    Discussions with banksDiscussions with banks Independent Market EnquiryIndependent Market Enquiry

    Initial Screening 3/ 3Initial Screening 3/ 3

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    78/116

    Initial Screening 3/ 3Initial Screening 3/ 3

    Prudential Exposure normsPrudential Exposure norms Individual & Group Exposure normsIndividual & Group Exposure norms

    Industry Exposure normsIndustry Exposure norms

    Scheme Eligibility Norms DER, PC, DSCR, AssetScheme Eligibility Norms DER, PC, DSCR, Asset

    coveragecoverage Takeover norms, if applicableTakeover norms, if applicable

    Profitability ProjectionsProfitability Projections

    Credit Risk Rating normsCredit Risk Rating norms

    M t A i l 1/ 5Management Appraisal 1/ 5

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    79/116

    Management Appraisal 1/ 5Management Appraisal 1/ 5

    Who are the promoters KYCWho are the promoters KYC Cohesiveness - relationshipCohesiveness - relationship

    Competence - Age, QualificationsCompetence - Age, Qualifications

    Experience general or similar lineExperience general or similar line

    Net-worth of promotersNet-worth of promoters

    IT/ Wealth tax statusIT/ Wealth tax status

    Management Appraisal 2/ 5Management Appraisal 2/ 5

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    80/116

    Management Appraisal 2/ 5Management Appraisal 2/ 5

    Associate concerns in which interestedAssociate concerns in which interested Associate ConcernsAssociate Concerns

    When establishedWhen established

    Which industry; ProductsWhich industry; Products

    Financial performanceFinancial performance

    Visit to associate concernsVisit to associate concerns

    Role of promoters in the associate concernsRole of promoters in the associate concerns

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    81/116

    Management Appraisal 4/ 5Management Appraisal 4/ 5

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    82/116

    Management Appraisal 4/ 5Management Appraisal 4/ 5

    Shareholding patternShareholding pattern % stake of promoters; Majority shareholder% stake of promoters; Majority shareholder Stake held by investment companiesStake held by investment companies Stake by foreign funds/ FDI/ Overseas investorsStake by foreign funds/ FDI/ Overseas investors

    Examine shareholders agreements; restrictiveExamine shareholders agreements; restrictivecovenantscovenants Partnership deed/ Society/ Trust deed to bePartnership deed/ Society/ Trust deed to be

    examined for any restrictive clausesexamined for any restrictive clauses

    Memorandum & AoA to be examined forMemorandum & AoA to be examined forobjectives, borrowing powers, security, nomineeobjectives, borrowing powers, security, nomineedirectors etc.directors etc.

    Management Appraisal 5/ 5Management Appraisal 5/ 5

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    83/116

    Management Appraisal 5/ 5Management Appraisal 5/ 5

    Composition of BoardComposition of Board

    Chief Executive; Organisational set upChief Executive; Organisational set up

    In case promoters not qualified/ experienced,In case promoters not qualified/ experienced,

    critically examine line managementcritically examine line management Adequacy of personnel for projectAdequacy of personnel for project

    implementation and each of functional areasimplementation and each of functional areas

    viz. finance, marketing, technology, production,viz. finance, marketing, technology, production,materials, HR etc.materials, HR etc.

    KYCKYC

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    84/116

    KYCKYC

    Companies : Memorandum and articles of associationCompanies : Memorandum and articles of association object clause, borrowing powers, power to object clause, borrowing powers, power tomortgage, authorized share capital, directors andmortgage, authorized share capital, directors andboard of directors, nominee directors provision, Pvtboard of directors, nominee directors provision, Pvt

    or public ltdor public ltd Partnership concerns Partnership deed Partnership concerns Partnership deed

    (registration), no of partners, powers to borrow(registration), no of partners, powers to borrow Trusts, HUFs, Co-operatives necessary safeguardsTrusts, HUFs, Co-operatives necessary safeguards Address and Identity proof, Networth statements,Address and Identity proof, Networth statements,

    ITRs, Signature attestation from bankers, PAN/SalesITRs, Signature attestation from bankers, PAN/Salestax/ EPF registrationtax/ EPF registration

    Technical Aspects 1/3Technical Aspects 1/3

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    85/116

    Technical Aspects 1/3Technical Aspects 1/3

    Scope of projectScope of project Plant scale, product mixPlant scale, product mix CapacityCapacity Bottlenecks in upscalingBottlenecks in upscaling

    LocationLocation Approach roadApproach road Infrastructure facilitiesInfrastructure facilities

    Power distance from substationPower distance from substation Raw materialsRaw materials Availability of skilled/ unskilled labourAvailability of skilled/ unskilled labour

    Technical Aspects 2/3Technical Aspects 2/3

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    86/116

    Technical Aspects 2/3Technical Aspects 2/3

    Mfg process - Selection of technologyMfg process - Selection of technology Technical consultants/ collaboratorsTechnical consultants/ collaborators Similar technology used by other unitsSimilar technology used by other units

    Selection of machinery cost and qualitySelection of machinery cost and quality Performance guaranteePerformance guarantee Training personnelTraining personnel

    Imported After sale serviceImported After sale service Second hand/ fabricatedSecond hand/ fabricated

    Technical Aspects 3/3Technical Aspects 3/3

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    87/116

    Technical Aspects 3/3Technical Aspects 3/3

    Major Raw MaterialsMajor Raw Materials Availability (Quantity & Quality)Availability (Quantity & Quality) Price fluctuationsPrice fluctuations Imported or Indigenous - duty structureImported or Indigenous - duty structure

    ProximityProximity Power, Water, FuelPower, Water, Fuel Effluent DisposalEffluent Disposal

    Manpower availabilityManpower availability Implementation Schedule ????Implementation Schedule ????

    Market Analysis 1/ 2Market Analysis 1/ 2

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    88/116

    Market Analysis 1/ 2Market Analysis 1/ 2

    Target customersTarget customers Market prospects - Market SurveyMarket prospects - Market Survey

    Demand Supply scenarioDemand Supply scenario

    Price trendsPrice trends Competition - localCompetition - local

    Competition foreign - duty structureCompetition foreign - duty structure

    Firm tie ups (collaborator off take !!!)Firm tie ups (collaborator off take !!!)

    Market Analysis 2/ 2Market Analysis 2/ 2

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    89/116

    Market Analysis 2/ 2Market Analysis 2/ 2

    Selling arrangementsSelling arrangements Industry practicesIndustry practices

    Credit periodCredit period

    Payment defaultsPayment defaults Advance paymentsAdvance payments

    Ancillary units : Tripartite agreementsAncillary units : Tripartite agreements

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    90/116

    Financial Appraisal - Cost of Project & Means of FinanceFinancial Appraisal - Cost of Project & Means of Finance

    Project Cost Means of Finance

    Land & site development Equity

    Buildings (Main/ Auxiliary) Promoters Equity

    Plant and Machinery Internal Accruals

    Miscellaneous fixed assets Unsecured Loans

    Pre. & pre-op exp. Subsidy

    Contingency Term Loans

    Margin Money for WC Others

    Total Total

    Capital Cost ValidationCapital Cost Validation

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    91/116

    Capital Cost Validationp LandLand

    Cost as per Sale / Lease deed, Registration costCost as per Sale / Lease deed, Registration cost

    Cost of Land Development, as estimated by a CivilCost of Land Development, as estimated by a CivilEngineerEngineer Land use permissionLand use permission

    Building & Civil worksBuilding & Civil works Approval of construction plan by Local AuthoritiesApproval of construction plan by Local Authorities Types of construction Estimates by a Civil EngineerTypes of construction Estimates by a Civil Engineer

    Plant, Machinery & EquipmentsPlant, Machinery & Equipments Selection criteria i.e. Technical specifications, Capacity,Selection criteria i.e. Technical specifications, Capacity,

    Quality, After sales service, Guarantee, DeliveryQuality, After sales service, Guarantee, Deliveryschedule, Cost, Terms of paymentschedule, Cost, Terms of payment

    Quotations / Offer letters from manufacturersQuotations / Offer letters from manufacturers Excise Duty, Sales Tax, TransportationExcise Duty, Sales Tax, Transportation Foundation, Erection & CommissioningFoundation, Erection & Commissioning

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    92/116

    Financial Viability 2/ 2Financial Viability 2/ 2

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    93/116

    Financial Viability 2/ 2Financial Viability 2/ 2 DERDER

    GPM and NPM comparison with peersGPM and NPM comparison with peers DSCRDSCR Project IRRProject IRR BEPBEP Cost of Capital (CoC)Cost of Capital (CoC) Return on Capital Employed (RoCE)Return on Capital Employed (RoCE) Sensitivity analysisSensitivity analysis

    Variations in capacity utilisation, selling price, raw materialVariations in capacity utilisation, selling price, raw materialand other key costsand other key costs

    Test the performance of key parametersTest the performance of key parameters Inter-firm comparisonInter-firm comparison Project Cost, Means of finance, Projections of income andProject Cost, Means of finance, Projections of income and

    profitability and DSCRprofitability and DSCR

    OthersOthers

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    94/116

    Ot e s

    Repayment schedule EMI/ BalooningRepayment schedule EMI/ Balooning

    MoratoriumMoratorium

    Capital/ interest subsidyCapital/ interest subsidy

    Internal Risk RatingInternal Risk Rating

    External ratingExternal rating

    Primary and collateral securityPrimary and collateral security

    Security Margin/ Asset CoverageSecurity Margin/ Asset Coverage

    Pre-disbursement conditionsPre-disbursement conditions

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    95/116

    Thank YouThank You

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    96/116

    THE MAIN SCHEDULESTHE MAIN SCHEDULES

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    97/116

    THE MAIN SCHEDULESTHE MAIN SCHEDULES

    1. CAPITAL COST;1. CAPITAL COST; 2. DEPRECIATION SCHEDULE;2. DEPRECIATION SCHEDULE; 3. CAPITAL REPLACEMENT SCHEDULE;3. CAPITAL REPLACEMENT SCHEDULE;

    4. CASH OPERATING EXPENSES;4. CASH OPERATING EXPENSES; 5. WORKING CAPITAL REQUIREMENTS;5. WORKING CAPITAL REQUIREMENTS; 6. LOAN REPAYMENT SCHEDULE;6. LOAN REPAYMENT SCHEDULE;

    7. CASH REVENUE SCHEDULE;7. CASH REVENUE SCHEDULE; 8. INCOME STATEMENT;8. INCOME STATEMENT;

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    98/116

    Presentation on

    Appraisal of Project ReportBanks Perspective

    Appraisal?Appraisal?

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    99/116

    Appraisal?pp

    A structured analytical tool to take a creditA structured analytical tool to take a credit

    decision The basic premises of an appraisal aredecision The basic premises of an appraisal areto assess/ analyze:to assess/ analyze:

    The Promoters.The Promoters. Viability of the business Macro & MicroViability of the business Macro & Micro

    Environment of the Business.Environment of the Business. Business financialsBusiness financials Various Risk & its mitigation.Various Risk & its mitigation.

    Permission & Approvals from RegulatoryPermission & Approvals from RegulatoryBodies.Bodies.

    Promoter e al ationPromoter evaluation

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    100/116

    Promoter evaluationPromoter evaluation

    Track record of promotersTrack record of promoters

    - Net worth/Availability of funds- Net worth/Availability of funds

    ManagementManagement

    - Experience of Management- Experience of Management- Ownership Pattern- Ownership Pattern

    Check RBI Defaulters ListCheck RBI Defaulters List

    Check CIBIL RecordsCheck CIBIL Records

    Viability of the BusinessViability of the Business

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    101/116

    Viability of the BusinessViability of the Business

    SWOT AnalysisSWOT Analysis

    Strengths & Weaknesses InternalStrengths & Weaknesses Internal

    Opportunities & Threats - ExternalOpportunities & Threats - External

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    102/116

    StrengthsStrengths

    (Areas to Look for)(Areas to Look for)

    Competent ManagementCompetent Management Distinctive competitive edgeDistinctive competitive edge

    in terms of cost, productin terms of cost, productdifferentiation, R&D, skillsdifferentiation, R&D, skills

    etcetc Good Brand Image StrongGood Brand Image Strong

    & growing customer base.& growing customer base. Industrial relations lowIndustrial relations low

    attrition rate.attrition rate. Sufficient FinancialSufficient Financial

    Resources.Resources.

    WeaknessesWeaknesses

    (Areas to Look for)(Areas to Look for)

    Lack of Management Depth/Lack of Management Depth/TalentTalent

    Deteriorating competitiveDeteriorating competitivepositionposition

    Newcomer with unprovenNewcomer with unproventrack record.track record.

    Short on FinancialShort on FinancialResourcesResources

    Technology Obsolescence.Technology Obsolescence.

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    103/116

    OpportunitiesOpportunities

    (Areas to Look for)(Areas to Look for)

    Industrial ScenarioIndustrial Scenario

    Faster market growthFaster market growth

    Enter new market/Enter new market/customer segments.customer segments.

    Expand product line/Expand product line/

    Move up in the valueMove up in the value

    chain to meet thechain to meet thegrowing aspirations ofgrowing aspirations of

    customerscustomers

    Vertical Integration.Vertical Integration.

    ThreatsThreats

    (Areas to Look for)(Areas to Look for)

    Growing competitiveGrowing competitive

    pressures.pressures.

    Growing bargainingGrowing bargaining

    power of customers/power of customers/supplierssuppliers

    Changing buyersChanging buyers

    needs/ tastes Risingneeds/ tastes Rising

    sale of substitutesale of substituteproductsproducts

    Adverse Govt Policies.Adverse Govt Policies.

    Vulnerability toVulnerability to

    recession/ businessrecession/ business

    Business FinancialsBusiness Financials

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    104/116

    Manufacturing efficiencyManufacturing efficiency Operating efficiencyOperating efficiency Is the unit turning over the assets efficiently.Is the unit turning over the assets efficiently. Cash Flow pattern.Cash Flow pattern. Liquidity to meet day to day operationsLiquidity to meet day to day operations What is the quality of current assetsWhat is the quality of current assets

    Can the unit sustain in difficult timesCan the unit sustain in difficult times Can it service our interest and repaymentsCan it service our interest and repayments

    What are we looking at?What are we looking at?

    Key Financial RatiosKey Financial Ratios

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    105/116

    Key Financial RatiosKey Financial Ratios

    Growth in sales - It shows prosperityGrowth in sales - It shows prosperity RM Content in sales It indicates cost efficacyRM Content in sales It indicates cost efficacy Gross profit/sales It indicates mfg. efficacyGross profit/sales It indicates mfg. efficacy

    PBDIT/sales It indicates operPBDIT/sales It indicates oper Cash accruals/Sales Ultimate earningsCash accruals/Sales Ultimate earnings Current ratio Will it meet comCurrent ratio Will it meet com TOL/TNW Resilience inTOL/TNW Resilience in Sales/TTA Asset turn arSales/TTA Asset turn aro ROCE ROCE

    Assessment of Right Quantum &Assessment of Rig

    ht Quantum &

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    106/116

    Type of DebtType of Debt

    Broadly Debt is required by the Corporates for Broadly Debt is required by the Corporates for

    Capital Investment (Project Finance)Capital Investment (Project Finance)

    Working CapitalWorking Capital

    F f AdF f Ad

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    107/116

    Forms of AdvancesForms of Advances

    Fund Based FacilitiesFund Based Facilities

    Term LoansTerm Loans

    Cash CreditCash Credit

    Bills Discounted/ PurchasedBills Discounted/ PurchasedDemand Loans, Overdraft etcDemand Loans, Overdraft etc

    Non Fund Based FacilitiesNon Fund Based Facilities

    Letter of Credit (Domestic/ Foreign)Letter of Credit (Domestic/ Foreign)

    GuaranteeGuarantee

    Deferred Payment Guarantee/ Co-Deferred Payment Guarantee/ Co-Acceptance of BillsAcceptance of Bills

    Project FinancingProject Financing

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    108/116

    Project FinancingProject Financing

    A funding structure that relies on future cash flowsA funding structure that relies on future cash flowsfrom a specific development as the primary sourcefrom a specific development as the primary sourceof repayment with that developments assets, rightsof repayment with that developments assets, rightsand interests legally held as collateral security. Theand interests legally held as collateral security. The

    Key Areas are -Key Areas are -Management AnalysisManagement AnalysisMarket & Demand AnalysisMarket & Demand Analysis

    Technical AnalysisTechnical AnalysisFinancial AnalysisFinancial Analysis

    Project FinancialsProject Financials

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    109/116

    jFocus AreasFocus Areas

    Capital StructureCapital Structure

    a) Desired Debt/Equity Ratio < 2:1a) Desired Debt/Equity Ratio < 2:1

    b) Min. Promoter Contribution at 20-25%b) Min. Promoter Contribution at 20-25%

    Fixed Asset Coverage RatioFixed Asset Coverage Ratio

    (Fixed Assets (WDV)/Term Liabilities)(Fixed Assets (WDV)/Term Liabilities)Fixed Asset Coverage >1.25 is preferred.Fixed Asset Coverage >1.25 is preferred.

    Debt Service Coverage Ratio (DSCR)Debt Service Coverage Ratio (DSCR)

    EBIDA/(Interest + Principal Amount)EBIDA/(Interest + Principal Amount)

    Desired DSCR is >1.50Desired DSCR is >1.50

    Project FinancialsProject Financials

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    110/116

    jFocus AreasFocus Areas

    Break Even PointBreak Even PointLower the level, the better it is for the project.Lower the level, the better it is for the project.

    Sensitivity AnalysisSensitivity Analysis

    Impact study on the cash flows due to adverseImpact study on the cash flows due to adversechanges in the Cost or the Sales side.changes in the Cost or the Sales side.

    Repayment PeriodRepayment PeriodNormally repayment term of 7 years is preferred.Normally repayment term of 7 years is preferred.

    WorkingWorkingCapital FinancingCapital Financing

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    111/116

    What we look for?What we look for?

    Focus onFocus on Volumes/ Sales growthVolumes/ Sales growth

    Operating efficiencyOperating efficiency

    LiquidityLiquidity

    GearingGearing

    Quality of current assets.Quality of current assets. Efficiency in asset turn over.Efficiency in asset turn over.

    Methods of WC AssessmentMethods of WC Assessment

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    112/116

    Methods of WC AssessmentMethods of WC Assessment

    As per Nayak committee (TurnoverAs per Nayak committee (Turnover

    Method)Method)

    Working Capital Gap MethodWorking Capital Gap Method Cash flow methodCash flow method

    Turnover MethodTurnover Method

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    113/116

    Turnover MethodTurnover Method

    For Working Capital Limits up to Rs. 5.00 CroreFor Working Capital Limits up to Rs. 5.00 Crore

    1.1. Annual turnover as projected by borrower.Annual turnover as projected by borrower.

    2.2. Turnover as accepted by Bank.Turnover as accepted by Bank.

    3.3. Working Capital requirements [25% of sales i.e.Working Capital requirements [25% of sales i.e.item 2].item 2].

    4.4. Minimum margin required [5% of sales i.e. item 2].Minimum margin required [5% of sales i.e. item 2].

    5.5. Actual margin available (Net Working Capital).Actual margin available (Net Working Capital).6.6. Maximum permissible Bank Finance is lower of theMaximum permissible Bank Finance is lower of the

    (item 3 item 4) and (item 3 item 5).(item 3 item 4) and (item 3 item 5).

    Working Capital Gap MethodWorking Capital Gap Method

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    114/116

    11stst

    Method ofMethod ofLendingLending 22ndnd

    Method ofMethod ofLending (MPBF)Lending (MPBF)

    CACA 10001000 10001000

    CL excl BankCL excl Bank 400400 400400

    WC GapWC Gap 600600 600600

    Min. StipulatedMin. Stipulated

    NWCNWC

    150150

    (25% of WC Gap)(25% of WC Gap)

    250250

    (25% of CA)(25% of CA)

    Bank FinanceBank Finance 450450 350350

    Working Capital Gap Methodg p p

    Cash-flow MethodCash-flow Method

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    115/116

    Cash-flow MethodCash flow Method

    Prepare a cash flow statement for the next 12 monthsPrepare a cash flow statement for the next 12 months Arrive at the maximum requirement.Arrive at the maximum requirement.

    Obtain documents for the max. amount.Obtain documents for the max. amount.

    Operation based on monthly requirements.Operation based on monthly requirements. Monitoring at periodical intervals.Monitoring at periodical intervals.

    Challenges Faced by Risk and Providers ofChallenges Faced by Risk and Providers of

    CapitalCapital

  • 8/7/2019 1MBA3RD PRTOJECT APPRAISAL

    116/116

    CapitalCapitalRisk Head Description

    Promoter Risk Capability to implement projects

    Ability to Infuse Capital

    Market Risk Demand Risk Tariff Risk

    Financing Risk Financial Closure Risk

    Equity Infusion Risk

    Construction Risk Capability to construct

    Technology Used, Equipment Quality

    Land Acquisition Risk, Environmental Risks

    Fuel Supply Risk Availability of Requisite quantity and Quality of Fuel at

    Budgeted Cost

    Regulatory Risk Risk of not getting approvals