1.project management 19.03.09

Upload: padmaja-amala

Post on 08-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 1.Project Management 19.03.09

    1/151

    Project Management

    INTRODUCTION

    Sound Project Management from concept to commissioning is the key to

    success. When any project is taken up, each and every phase right from

    inception till the final completion must be thoroughly, effectively andtightly controlled so that each successive milestone achieved in timecontributes to building the blocks of ultimate success in fulfillment of

    desired objectives. Leading organizations in the world achieve success in

    Project management by controlling the following four factors through all

    phases of a project in order of priority.

    1. Safety,

    2. Quality,

    3. Time and

    4. Cost.

    Basics of a Project:

    1. Eco Friendly: Every project must incorporate requiredenvironment protection measures and meet the norms.

    2. Competitive: The project must be competitive when comparedagainst similar projects being done by others in the field.

    3. Project Cycle Time: With borrowed capital, reduction in projectcycle time goes a long way in reducing the project cost by way of

    reduction in interest during construction.4. Efficiency in Operations: Basic design of the project must aim at

    highest levels of efficiency in operations to fully justify time moneyand effort put in to build the project.

    5. Quality and Safety: Without the high standards of quality andsafety in execution, no project can be successful.

    6. Customer Expectations: Above all, ultimately, a project must beable to meet expectation of its Techno-economical viability.Projects must clearly establish this basic requirement.

    7. Reliable Technology: Use of proven and reliable technology isessential for any project, to be called successful.

    Trends, Issues and Critical Success Factors:

    Following factors contribute to success of projects.

    1. Clear Vision and Project Objectives: aims and objectives of theproject need to be clearly defined to set the right direction andtone to enable accurate assessment of benefits derived on projectcompletion.

    2. Strategic and Detailed Project Planning: Detailed work

    breakdown structure and integrated work plans need to be developed inthe beginning itself. Care is to be taken so that time estimation fordifferent activities remains as accurate as possible.

    Transmission Substation Manual 1

  • 8/6/2019 1.Project Management 19.03.09

    2/151

    Project Management

    3. Dynamic Leadership: Similar to importance of the role of a good

    captain in any game, role of dynamic leadership for a project isimportant. Positive, bold, timely and quality decisions taken by

    them to steer a project towards success are very important factors.

    4. Committed, Dedicated and Competent Team: Every projectrequires teamwork, close coordination and unidirectional efforts to

    create a synergy. Along with hard work, required level of technicaland managerial competence in team members is essential.

    5. Integrated Project Management Systems: Putting a sound

    project management system, which is capable of integratingmultifarious, and multi agency activities being done in parallel is

    required to ensure synchronism and converging of activitiestowards one common goal of project completion. This systemshould be able to organize, multi level planning and monitoring ofproject activities as per the requirement.

    6. Project Cost Control: Effective built in measures to ensure

    control of cost both in design and execution phases of a project areessential.

    7. Owner's Involvement: Deep involvement of owner at every step

    to see that above system functions to its full potential is must in

    any project management. Elaborate systems and procedures alone

    cannot guarantee any results unless they are effectively

    implemented and every step is followed till its logical conclusion.8. Handling of Emergencies and Surprises: Mid course

    corrections would be required to take care of any interim delays.

    Applying what if logic to anticipate project surprises, assessment

    of risks and putting in place a Risk Control and Mitigation

    Plan is necessary. Adequate safety and fire protection measures

    should also be a part of project execution.

    Clarity in Contract Management: Large projects require handling of

    major contracts. Following aspects are crucial to manage these

    contracts. Optimization of contract packages for effective and fasterimplement-tation. Here, scope of entire project is coveredunder mutually exclusive packages.

    Framing of qualification requirements to ensure competitionfrom competent agencies.

    Broad based specifications to generate competition.

    Clearly defined evaluation criteria and selection of agenciesbased on price and capability consideration.

    Tie up of work programme and quality plans withcommitment of matching resources as part of contract.

    Dispute resolution mechanism, introduction of incentives andpenalties.

    Transmission Substation Manual 2

  • 8/6/2019 1.Project Management 19.03.09

    3/151

    Project Management

    Mechanism for early closing of contracts after workcompletion.

    Sound Engineering Practices: Major projects require a very strong

    engineering support. Aspects related to engineering to be taken care

    include

    Up front engineering to maximum possible extent,

    Standardization of plants and layouts,

    Standardization of equipment,

    Design automation,

    Design simplification and reduction in number of components

    and

    High reliability of overall process, sub systems andcomponents.

    Quality Assurance:

    Control of quality from raw material stage.

    Control of quality during manufacturing stages for major and

    critical equipment with stage and final inspections at pre

    determined check-points.

    Quality assurance for field activities.

    Strong Infrastructure Base: Many projects have been delayed due to

    weak

    infrastructure. It needs to be ensured that basic infrastructure of roads;

    power, water, and tie up for raw material like steel and cement are made

    before start of main construction for large projects. Project team and

    team leader should be in position well in time. This will ensure

    expeditious completion of the project.

    Construction Technology: Choice of latest construction technology

    helps both in safe execution as well as results in substantial saving interms of time. It also helps in improving quality of construction and

    ultimately results in saving of costs. It is better if methodology to be

    adopted for construction and erection is worked out, discussed and

    decided in advance.

    Resources: Inadequate resources spell certain delay for any project

    execution. Adequate resources of men and material are essential in all

    the phase of project like engineering, procurement and construction.

    Manufacturing and Production: Detailed manufacturing plans,

    advance tie up for raw material, timely engineering inputs, adequate in-

    house facilities for manufacturing, outsourcing as per need are some of

    the important factors that control timely supplies. Following can further

    Transmission Substation Manual 3

  • 8/6/2019 1.Project Management 19.03.09

    4/151

    Project Management

    help in this stage of project.

    Timely procurement of bought out items,

    Improved productivity through technology up gradation,

    Dispatch of modular units in place of individual components,

    Improved packing to minimize transit damages and Faster transportation tie ups.

    Control and Monitoring: Close follow up and expediting at all levels

    based on exception is essential in all the phases of the project. Every

    team member must do it in his respective area with a sense of urgency

    and ownership. Increased use of Information technology in this

    area will help in faster work. Effective implementation of integrated

    project management systems is essential for the desired output. Regular

    audit and continuous improvement of these systems is essential for thedesired output and to keep pace with the changes.

    Fund Management: Interruption in flow of adequate funds will

    jeopardize the progress of any project. Performance linked budget

    projections and their regular monitoring helps in better management.

    Safety in Construction: During execution of any project, accidents of

    any type will lead to delays, Danger or loss of human lives is to be

    avoided at any cost. It can be checked with the following measures.

    Built in safety clauses in contracts.

    Adequacy of required skills in workers for that particular type

    of job.

    Availability of protective equipment.

    Proper working conditions.

    Adequate supervision.

    Owners insistence for importance of safety.

    Suitable incentives and penalties.

    Smooth Transition to Normal Operation: A project is complete only

    when it goes in normal operation phase and desired level of output in all

    parameters is achieved on a sustained basis. Hence, momentum of first

    start up of any project is required to be carried forward till this is

    achieved.

    Backward and Forward Integration: Completing a project in

    isolation may not deliver results if it is a part of chain of projects. In suchcases, backward and forward integration to march the schedules of other

    connected projects is essential to be constantly monitored.

    Transmission Substation Manual 4

  • 8/6/2019 1.Project Management 19.03.09

    5/151

  • 8/6/2019 1.Project Management 19.03.09

    6/151

    Project Management

    3. Nominated Tenders: For minor works at rate contract rates or

    approved schedule Rates from reputed firms.

    Important Terms and Conditions of Open Competitive Bids:

    Extracts of Instructions to Bidders (ITB), General Conditions of Contract, and

    General Conditions of Erection (GCE) are given in the Annexure-3. The projectmanagers shall go through the terms of contract and if any clarifications arerequired the same shall be obtained from the owner before tendering for thework. The terms of contract shall be considered while tendering and planningthe works for completion as per the targets given.

    Transmission Substation Manual 6

  • 8/6/2019 1.Project Management 19.03.09

    7/151

    Project Management

    PLANNING

    Activities involved in substation erection and the approximate

    duration required:

    Sl.No. Major Activity

    Year- 1

    Months1 to 12

    Year-2

    Months1 to 12

    Year-3

    Months1 to 12Pre-award Activities

    A Project Planning1. System studies 1-22. Land acquisition 1-33. Leveling and compacting 2-54. Finalize design and specifications 2-55. Award of contract 5-10Post-award Activities

    B Civil works6. Civil drawings 10-127. Site office and store 10-128. Marking layout 11-129. Roads 11-12 1-210. Fence and gate 11-1211. Foundations of buildings 11-12 1-212. Control room and other buildings 10-12 1-6

    13.Foundations for transformerand structures

    10-12

    14. Earth mat work 10-12 1-215. Cable trenches 1-416. Finishing and interface work 1-4

    C Supply of Materials17. Supply of structures 10-12 1-4

    18. Equipment manufacture and supply 10-12 1-819. Storage of materials received 10-12 1-820. Erection Activities21. Transformer erection 1-422. Main structure 10-12 1-623. Overhead shielding 6-824. Busbar stringing 6-10

    25. Equipment support structures 4-8

    26.

    Station auxiliariesi. Station transformerii. Diesel generatoriii. Communication facilities

    iv. Personal computer facilityv. Battery and chargervi. AC/DC distribution boardsvii. Illuminationviii. Fire fighting system etc.

    10-12 1-6

    Transmission Substation Manual 7

  • 8/6/2019 1.Project Management 19.03.09

    8/151

    Project Management

    27.Equipment erection in theswitch yard

    8-12 1-2

    28. Earth risers 10-12 1-3

    29.Equipment erection in thecontrol room

    8-12 1-4

    30. Jumpering to equipment 2-3

    31. Cable laying and terminations 8-12 1-432. Testing and commissioning 3-5

    33.Handing over for operation andmaintenance

    6

    PERT (Programme Evaluation and Review Techniques) and

    Critical Path Analysis:

    For construction of 220 /132 kV Substation with 2 Nos. 100 MVA Transformers, 2 In-coming and 2 Out-going 220 kV feeders, and 4Nos. 132 kV feeders. The project completion period given is 18 months.

    Analysis of Activities (AOA):

    Activity

    NameActivity Description

    Immediate

    Preceding Activity

    Activity

    Duration

    Months

    EarlyFinishTime

    Pre-award activities

    (1, 2) A Land Acquisition 3 2

    (2, 3) B. Infra Structure Facilities A (1, 2) 3 2

    (2, 4) C. Design and Engineering B (2, 3) 2 2

    (2, 5) D. Leveling C (2, 4) 3 2

    (4, 6) E. Tendering & Award ofcontracts

    for materials and erectionworks

    C (2, 4) 5 4

    Post -award activities

    (6, 7) F. Works on Control room andother buildings

    E (4, 6) 8 8

    (6, 8) G. Supply of structures(Towers ,

    Booms ,and Equipmentstructures) and earthing

    material

    E (4, 6) 6 6

    (6, 9)H. Foundations in Switch yard E (4, 6) 8 5

    (6, 10) I. Erection of Towers , Boomsand

    equipment structuresG (6, 8 ) 9 4

    (6, 11) J. Supply of out-door andin-door Equipment

    E (4, 6) 8 8

    (9, 12)K. Earth mat laying H (6,9) 2 2

    Transmission Substation Manual 8

  • 8/6/2019 1.Project Management 19.03.09

    9/151

    Project Management

    (10,13)

    L. Stringing and clipping I (6, 10) 2 2

    (14,15)

    M. Erection of Out-doorEquipment

    J (6, 11) 4 3

    (15,

    16)

    N. Jumpering L (14, 15) 2 1

    (7, 17)O. Erection of in-door Equipment J (6, 11) 5 3

    (17,18)

    P. Cable laying and terminations O (7, 17) 3 3

    (18,19)Q.Testing and commissioning P (17, 19) 2 2

    Analysis of Activities (AOA):

    Time Analysis: Forward Pass

    Time Analysis: Backward Pass

    Transmission Substation Manual 9

  • 8/6/2019 1.Project Management 19.03.09

    10/151

    Project Management

    Time Analysis: Critical path:

    Transmission Substation Manual 10

    PRE AWARD ACTIVITIES

  • 8/6/2019 1.Project Management 19.03.09

    11/151

    Project Management

    RESOURCES REQUIRED

    Men MoneyTools and

    PlantMaterials

    Engineers for

    1. Planning,

    2. Designing,

    3. Materialprocurement,

    4. Supervision ofWorks,

    5. Testing andcommissioning,

    6. Monitoring.

    Accountants for

    1. Arranging funds

    2. Billing

    3. Accounting

    Constructiongangs for

    1. Leveling.

    2. Excavation,foundations.

    3. Erection ofstructures.

    4. Stringing.

    5. Equipmenterection.

    6. Testing andcommissioning.

    Fundsrequired for

    1. Procurement of requiredtools andplant

    2. Procurement of requiredmaterials

    3. Salaries toregularemployees

    4. Regularflow offunds forpaymentstoconstructiongangs

    Tools andplantrequired for

    1. Leveling

    2. Excavation,foundations

    3. Erection ofStructures

    4. Erection ofEquipment

    5. Stringing

    6. Testingequipment

    Vehicles

    Trucks,Tractors withTrailers, Mobilecrane

    1. Cement,

    2. Coarse &fineaggregate,

    3. Reinforcement steel

    4. Foundation Bolts withnuts

    5. Structures

    6. Bolts & nuts7. Earth wire &

    accessories

    8. Conductor &accessories

    9. Insulators & hardware

    10.Earthing materials

    11.Transformers

    12.Circuit breakers

    13.Isolators

    14.CTs

    15.PTs

    16.CVTs

    17.LAs

    18.Control and Relaypanels

    19.AC /DC distributionboards

    20.Batteries and chargers21.Marshalling boxes22. Cables Lighting

    23. fixtures-In-door andout-door24.Fire fighting system

    Resource Analysis

    Transmission Substation Manual 11

    19

    28

  • 8/6/2019 1.Project Management 19.03.09

    12/151

    Project Management

    Personnel:

    Activity

    NameActivity Description

    Required number of

    Engineers

    SkilledWorke

    rs

    Gangswith 10Person

    sPre-award Activities

    (1, 2) A Land Acquisition 1 10

    (2, 3) B. Infra Structure Facilities 2 10 10

    (2, 4) C. Design and Engineering 3 - -

    ( 2, 5) D. Leveling 1 5 5

    ( 4, 6) E. Tendering & Award ofcontracts for materials and

    erection works

    3 - -

    Post -award Activities

    (6, 7) F. Works on Control room andother buildings

    2 10 10

    (6, 8) G. Supply of structures (Towers ,Booms, and Equipmentstructures) and earthingmaterial

    2 2 2

    (6, 9) H. Foundations in Switch yard

    2

    5 5

    (7, 10) I. Erection of Towers , Boomsand

    equipment structures3 3

    (11,12)

    J. Supply of Out-door andin-door Equipment

    1 2 2

    (9, 13)K. Earth mat laying

    3

    5 5

    (10,14)

    L. Stringing and clipping 4 4

    (15,16)

    L. Erection of Out-doorEquipment

    5 5

    (16,17)

    M. Jumpering 2 2

    (7, 18)O. Erection of In-door Equipment 2 4 4

    (17,19)

    P. Cable laying and terminations3

    5 5

    (19,20)Q.Testing and commissioning 10 3

    Cost Estimates:

    The cost estimates per bay of different bays in the EHV Substations are

    given in the Annexure-2 for reference. These may be updated as andwhen required. Based on the same the total cost of substation is worked

    out and funds requirement is analyzed.

    Transmission Substation Manual 12

  • 8/6/2019 1.Project Management 19.03.09

    13/151

    Project Management

    Cost Estimate (in Rs. Lakhs):

    Sl.N

    o.Details of Bay No. of Bays

    Cost per

    BayTotal Cost

    1. 220 kV Transformer

    bay 2 300 6002. 220 kV Feeder bay

    4 130 520

    3. 132 kV Feeder bay4 60 240

    4. Bus coupler bay andother substationequipment ,materialsetc.

    350 350

    5. Total estimated cost1710

    FUNDS REQUIRED

    Activity

    NameActivity Description

    Requirement pattern -

    months

    Fundsneeded

    (Rs. Lakhs)

    (1, 2) A Land Acquisition 1-2 40(2, 3) B. Infra Structure Facilities 2-3 40(2, 4) C. Design and Engineering 2-3 10(2, 5) D. Leveling 2-4 10(4, 6) E. Tendering & Award of

    contracts for materialsanderection works, approvalof manufacturing qualityplans.

    2-5 10

    (6, 7) F. Works on Control roomand other buildings 6-12 60

    (6, 8) G. Supply of structures(Tower Booms, andEquipment

    structures) and earthingmaterial

    6-14 100

    (6, 9) H. Foundations in Switchyard

    6-16 50

    (7, 10) I. Erection of Towers,

    Booms and equipmentstructures 9-18 50

    (11,12)

    J. Supply of out-door andin-door Equipment 8-20 1200

    Transmission Substation Manual 13

  • 8/6/2019 1.Project Management 19.03.09

    14/151

    Project Management

    (9, 13) K. Earth mat laying 9-16 20

    (10,14)

    L. Stringing and clipping18-21 20

    (15,16)

    L. Erection of Out-doorEquipment 20-24 30

    (16,17)

    M. Jumpering 21-22 10

    (7, 18) O. Erection of in-doorEquipment 18-24 20

    (17,19)

    P. Cable laying andterminations 24-26 20

    (19,20)

    Q.Testing andcommissioning

    26-28 20

    Funds Flow Analysis:

    Month

    FundsRequired(Rs.Lakh

    s)

    1. 15

    2. 50

    3. 20

    4. 20

    5. 20

    6. 207. 100

    8. 100

    9. 100

    10. 100

    11. 100

    12. 100

    13. 100

    14. 100

    15. 10016. 100

    17. 100

    18. 100

    19. 40

    20. 40

    21. 40

    22. 40

    23. 40

    24. 40

    25. 40

    26. 40

    Transmission Substation Manual 14

  • 8/6/2019 1.Project Management 19.03.09

    15/151

    Project Management

    27. 40

    28. 15

    Sources of Finance:

    Owners Support:

    1. Advance payment: The OWNER shall support the contractorby paying advance to cover contract front end expenditure suchas mobilization, early engineering work, and payments tosubcontractors, commission and insurances. Such advances willbe of the order of 10% to 20%.

    2. Progressive payments: Payments for the supplies made anderection works shall be made within stipulated time withoutdelays to enable the contractor achieve progress to meet thetargets. The measurements of work, passing of the bills shall notbe delayed by the OWNER in the interest of smooth progress of

    works.3. Retention amounts: The retention amounts kept by theOWNER from the progressive bills may be released to thecontractor as per the contractual terms without delay, as this willact as incentive for the contractor to finish the works.

    4. Redemption of Bank Guarantees: The contractor will befurnishing the Bank guarantee for 5 to 10% value of the contracttowards proper performance of the contract. The contractor shallbe cautious while signing the guarantee and avoid wordingswhich enable the OWNER to get the BG redeemed on firstdemand without referring the contractor.

    5. Documentation for payments: The documents to be

    presented for payment shall be as simplified as possible to

    avoid delays in release of payments due to misunderstanding.

    Export Credits:

    Export credit agencies are generally set up or sponsored by thegovernment with the primary function of encouraging the export ofmanufactured goods.

    The criteria to be satisfied for obtaining support from export creditagencies:

    Majority of equipment and services originate from theagency country,

    Financial soundness and reputation of contractingorganization,

    Financial soundness and reputation of OWNER organizationand

    The category status (based on the GNP per capita inflation,stability etc.) of the Owners country.

    Commercial Loans:

    Transmission Substation Manual 15

  • 8/6/2019 1.Project Management 19.03.09

    16/151

    Project Management

    These are often linked to export credits.

    Development Aid:

    In the case of developing countries Asian Development Bank, EuropeanDevelopment Bank, World Bank etc. provide Funding for the approved

    projects to the utilities with certain conditions. The Bank may paydirectly to the contractor against documents.

    It is important to see that the payments towards the supplies

    made and the erection works completed are received from theOWNER promptly for meeting the expenditure incurred so that

    the works will progress uninterrupted.

    Transmission Substation Manual 16

  • 8/6/2019 1.Project Management 19.03.09

    17/151

    Project Management

    CRASHING ANALYSIS

    Thus crashing involves crashing the critical activities.

    Crashing of the project time may be required when the Transmission

    Lines are ready to get benefits from the project early. It involvesadditional funds and men at appropriate time.

    Time estimate in the Critical Path Method does not take into accountthe uncertainties or probabilities. The time estimates are single timeestimates and no range of time duration is considered. Considering theuncertainties the expected time for an activity can be worked out asbelow.

    Expected Time (Te) = (T0+4 Tml+Tp) / 6

    Where T0=Optimistic time

    Tml=Most likely time

    Tp=Pessimistic time

    Transmission Substation Manual 17

  • 8/6/2019 1.Project Management 19.03.09

    18/151

    Project Management

    Standard deviation = (Tp- T0) /6

    Transmission Substation Manual 18

  • 8/6/2019 1.Project Management 19.03.09

    19/151

    Project Management

    PROJECT REVIEW

    The following schedules are also to be made for monitoring the works

    1. Schedule for finalizing sub-contracts,2. Cash inflow and cash outflow schedules,3. Billing schedules,

    4. Schedule of submission and approval by concerned

    i) Drawings

    ii) Field quality plansiii) Documents

    5. Schedule of receipt of equipment at site,

    6. Schedule for inputs from other sources,

    7. Communication facilities, Telephone, Telex, Wireless, Fax and

    8. Personal computer facility

    The process flow chart of various activities relating to the substation isat Annexure 4.

    Transmission Substation Manual 19

  • 8/6/2019 1.Project Management 19.03.09

    20/151

    Project Management

    The progress achieved against the programme shall be received andnoted on the Bar chart prepared for the specific project. The typical bar

    chart for a 220 kV substation is at Annexure - 1.

    Transmission Substation Manual 20

  • 8/6/2019 1.Project Management 19.03.09

    21/151

    Project Management

    ADMINISTRATIVE WORKS

    The project execution comprises the following important administrative works

    i Finalizing contractual terms and conditions,

    ii Arranging bank guarantees required,

    iii Sub-contracting, obtaining manufacturing quality plans from

    the suppliers and finalizing,

    iv Inspection of equipment during manufacture and witnessingtests before dispatch,

    v Getting test reports for the equipment and material, obtaining

    approvals from the customer and obtaining dispatch instructions from

    the customer,

    vi Documentation,

    vii Resource mobilization,

    viii Work supervision,

    ix Coordination with consultant, customer, sub-contractors, andproject managers at site and

    x Wages, housing and personnel matters.

    Transmission Substation Manual 21

  • 8/6/2019 1.Project Management 19.03.09

    22/151

    Project Management

    Documentation:

    The project management group shall look after the documentation work

    as it is the most important activity. Following are the importantdocuments.

    List of drawings of civil works

    List of tools and plant for erection

    List of material and equipment

    Substation single line drawing

    Detailed structural lay out drawing

    Plan showing the Cable trenches, earth mat, earth pits andFoundations for structures

    Drawings and bills of material for the main structures andequipment support structures

    Guaranteed technical particulars of equipment and materials

    Manuals for equipment erection and testing

    Field quality plans for civil and electrical works

    Standard specifications for all equipment, materials and works

    Transmission Substation Manual 22

  • 8/6/2019 1.Project Management 19.03.09

    23/151

    Project Management

    RECEIVING EQUIPMENT/MATERIALS AND STORAGE AT

    SITE

    The equipment and materials are generally transported to site by road

    by lorries and tractor trailers. Special precautions are to be taken in

    transporting heavy over dimensional consignments. Necessary prior

    permits are to be taken from the road transport authorities fortransporting the following heavy and over dimensioned equipment.

    Transformer tanks

    Reactor tanks

    Air- core reactors

    400 kV bushings

    Diesel generator set

    Tanks for oil storage

    Cooling equipment

    Large welded structures etc

    In case of galvanized steel structures, short simple members are

    resistant to transit damage. Large welded structures are likely to bebent during transit, unloading. These can be straightened easily at site.A 100% bolted design is more resistant to transport damage than

    welded designs or semi-bolted (ladder) designs.

    Transmission Substation Manual 23

  • 8/6/2019 1.Project Management 19.03.09

    24/151

    Project Management

    When transporting steel structures, these must be loaded in such away that white rust will not develop. This is best done by avoiding deck

    loading and by using spacers to allow air circulation between the layers.

    Unloading:

    The following equipment is required at site for unloading the equipment/materials from the truck or tractor trailer.

    Mobile crane

    Fork lifters

    Derrick crane

    Slings, pulley blocks

    The unloading and storage shall be supervised carefully to avoid damages.

    Inspection on Arrival at Site and Insurance Claims:

    The packing cases are inspected for transit damage. In case of anydamage, the matter is reported to the supplier and insurance company.

    The insurance claim is lodged. The surveyors of the insurance company

    conduct survey and assess the extent of the transit damage.

    Transport damages should be attended within one week of arrival atsite. It is advisable to decide in advance which insurance inspection

    authority one has to report to.

    Insurance policies are taken by Project Management Group from head

    quarters from experienced insurance company. For substation contractsAll Risk storage-cum-Erection Policy is preferred. It covers entire civil,

    erection, commissioning work up to handing over to customer. All the

    equipment, civil works are covered. Equipment insurance claims are

    identified as

    During Transport (Generally in separate transit policy)

    During Storage

    During Erection

    During Commissioning

    Damaged items should be segregated and kept for insurance survey.Packing case no., item no., date of arrival, transport truck no., details ofdamages should be noted and kept for surveyors. Photographs of

    damaged packages should be taken.

    Storage:

    Three categories of stores are necessary for substation equipment:

    Outdoor Fenced Store:

    The outdoor storage area should be above maximum flood level, and

    free from damp, mud etc. The approached road from the main road andto the substation should be firm and adequate. The necessary handlingequipment should be available.

    Transmission Substation Manual 24

  • 8/6/2019 1.Project Management 19.03.09

    25/151

    Project Management

    Indoor Closed Store:

    Indoor storage building should have sufficiently large storage area andsufficiently large doors on road side and substation side. It should bewell ventilated and well lighted. There should be proper watch andward. Transformer oil brought in tankers should be stored in specially

    built tanks. The oil drums should be stored as per recommendations ofthe supplier.

    Storage room for instruments and special equipment should also beplanned.

    Fire fighting arrangements must be adequate. Guidelines by insurance

    company shall be followed.

    INTERFACE BETWEEN CIVIL WORKS AND COORDINATIONBETWEEN VARIOUS ERECTION WORKS

    The following activities have a close interaction between civil works and

    erection works. Very close liaison between various groups is essential

    from design to handing-over stages.

    Foundation drawings

    Cable trench drawings

    Wall openings for air conditioning work

    Piping through wall

    Illumination work

    Sound absorption techniques used

    Vibration control

    Earthing system

    Piping for Fire Fighting System etc.

    There must be coordination between various works as mentioned belowso as to meet the target date of commissioning the substation.

    Transmission Substation Manual 25

  • 8/6/2019 1.Project Management 19.03.09

    26/151

    Project Management

    i) Foundations for main structures and equipment support structuresshall be completed in order to take up erection of structures.

    ii) The transformer plinth shall be completed before the transformertank arrives at site so as to keep the transformer on the plinth directly.

    iii) Temporary yard lighting must be done to facilitate erection worksduring nights if necessary

    iv) All the structural parts, bolts, nuts and washers for columns shallbe received before the other structural materials.

    v) By the time the columns are erected, the booms must be availablein complete shape at site for erection.

    vi) The ground wire, insulators, hardware, clamps & connectors,

    busbar conductor must be available by the time erection of main

    structures is completed.

    vii) The cable trenches and the marshalling boxes must be completedbefore laying the earth mat.

    viii) The equipment structures shall be erected after erection of main

    structures in order to erect the equipment on the structures.

    ix) After all the equipment is erected in a bay, jumpering shall be

    made from equipment to equipment and equipment to the cross bus

    /main bus/transfer bus.

    x) In the control room the cable trenches and cable racks shall beready for taking up the cable laying.

    xi) The battery and battery charger are to be erected and

    commissioned. The AC/DC distribution boards shall be erected andnecessary connections made from the incoming sources and to the

    various substation equipment.

    xii) The earth mat shall be ready by the time the equipment is erected

    so that risers are given to the equipment and structures.

    xiii) All the control and relay panels are to be erected for cabling. On

    completing the cable trenches the cables are to be laid andterminations made as per the approved drawings.

    xiv) Fire fighting equipment shall be available even before thematerials arrive at site and the fire fighting system for protectionof main substation equipment shall be installed beforecommissioning the switch yard.

    xv) Testing of equipment can be taken up after cable terminations tocontrol and relay panels and AC/DC panels.

    Transmission Substation Manual 26

  • 8/6/2019 1.Project Management 19.03.09

    27/151

    Project Management

    Transmission Substation Manual 27

  • 8/6/2019 1.Project Management 19.03.09

    28/151

    Project Management

    Bar chart showing Programme and Progress of 220 kV Substations

    Duration in QuartersSl.No

    .Task Name 1 2 3 4 5 6 7 8 9 10

    1. Land acquisition 2. Leveling 3. Infrastructure 4.

    Design andEngineering

    5. Tendering 6. Foundations 7.

    Supply ofstructures

    8.

    Erection ofstructures

    9. Earth mat 10.

    Stringing

    11.

    Supply ofEquipment

    1 Control room and

    Transmission Substation Manual 28

    ANNEXURE - 1

    BAR CHART

  • 8/6/2019 1.Project Management 19.03.09

    29/151

    PROGRAMMEPROGRESS

    Project Management

    other buildings

    13.

    Equipmenterection in out-door yard

    14.

    Jumpering

    15

    .

    Earth risers

    16.

    Erection of in-door equipment

    17.

    Cable laying andterminations

    18.

    Testing andCommissioning

    Transmission Substation Manual 29

  • 8/6/2019 1.Project Management 19.03.09

    30/151

    Project Management

    ANNEXURE - 2

    400 kV Substation Detailed Quantities and Cost Estimates

    Transmission Substation Manual 30

    Per Bay Quantities Per Bay Costs - Rs Lakhs

    ItemDescription of Work

    Rs LakhsRequi-

    redPerS/S

    400/220 kV

    TF Bay

    400kV

    LineBay

    400kV

    Reac-tor

    220 kVLineBay

  • 8/6/2019 1.Project Management 19.03.09

    31/151

    Project Management

    400 kV Substation Detailed Quantities and Cost Estimates

    Transmission Substation Manual 31

    Per Bay Quantities Per Bay Costs - Rs Lakhs

    Item Description of Work

    Rs Lakhs Requi-redPerS/S

    400/220 kV

    TF Bay

    400kV

    LineBay

    400kV

    -Reactor

    220kV

    LineBay

  • 8/6/2019 1.Project Management 19.03.09

    32/151

    Project Management

    400 kV Substation Detailed Quantities and Cost Estimates

    ItemDescription of

    Work

    Rs LakhsPer Bay Quantities Per Bay Costs - Rs Lakhs

    Requi-redPerS/S

    400/220 kV

    TF Bay

    400kV

    LineBay

    400kV

    Reac- tor

    220kV

    LineBay

  • 8/6/2019 1.Project Management 19.03.09

    33/151

    Project Management

    400 kV Substation Detailed Quantities and Cost Estimates

    Per Bay Quantities Per Bay Costs - Rs Lakhs

    ItemDescription of

    Work

    Rs LakhsRequiredPerS/S

    400/220 kV

    TF Bay

    400kV

    LineBay

    400kV

    Reactor

    220kV

    LineBay

  • 8/6/2019 1.Project Management 19.03.09

    34/151

    Project Management

    400 kV Substation Detailed Quantities and Cost Estimates

    Item Description of Work

    Rs Lakhs Per Bay Quantities PerBay Costs - Rs

    Lakhs

    RatePer

    RequiredPerS/S

    400/220 kV

    TF Bay

    400kV

    LineBay

    400kV

    Reactor

    220kV

    LineBay

  • 8/6/2019 1.Project Management 19.03.09

    35/151

    Project Management

    400 kV Substation Detailed Quantities and Cost Estimates

    Per Bay Quantities Per Bay Costs - Rs Lakhs

    Item Description of Work

    Rs Lakhs

    RequiredPerS/S

    400/220kV TFBay

    400kV

    LineBay

    400kV

    Reactor

    220kV

    LineBay

  • 8/6/2019 1.Project Management 19.03.09

    36/151

    Project Management

    400 kV Substation Detailed Quantities and Cost Estimates

    Transmission Substation Manual 36

    Per Bay Quantities Per Bay Costs - Rs Lakhs

    Item Description of Work

    Rs Lakhs RequiredPerS/S

    400/220 kV

    TF Bay

    400kV

    LineBay

    400kV

    Reactor

    220kV

    LineBay

  • 8/6/2019 1.Project Management 19.03.09

    37/151

    Project Management

    400 kV Substation Detailed Quantities and Cost Estimates

    Transmission Substation Manual 37

    Per Bay Quantities Per Bay Casts - Rs Lakhs

    Item Description of Work

    Rs Lakhs RequiredPerS/S

    400/220 kV

    TF Bay

    400kV

    LineBay

    400kV

    Reactor

    220kV

    LineBay

  • 8/6/2019 1.Project Management 19.03.09

    38/151

    Project Management

    400 kV Substation Detailed Quantities and Cost Estimates

    Per Bay Quantities Per Bay Costs - Rs Lakhs

    Item Description of WorkRs Lakhs Requi

    redS/S

    400/220 kV

    TF Bay

    400kV

    LineBay

    400kV

    Reactor

    220kV

    LineBay

  • 8/6/2019 1.Project Management 19.03.09

    39/151

    Project Management

    400 kV Substation Detailed Quantities and Cost Estimates

    ItemDescription of

    Work

    Per Bay Quantities Per Bay Costs - Rs Lakhs

    Rs Lakhs Required perS/S

    400/220 kV

    TF Bay

    400kV

    LineBay

    400kV

    Reactor

    220kV

    LineBay

  • 8/6/2019 1.Project Management 19.03.09

    40/151

    Project Management

    220 kV Substation Quantities and Detailed Costs Estimates

    Per Bay Quantities Per Bay Costs - Rs Lakhs

    Item Description of WorkRs Lakhs Required

    per S/S

    220/132kV TFBay

    220 kVLineBay

    132 kVLineBay

    Required PerS/S

    220/132kV TFBay

    220kV

    Line

    132kV Line

    BayRate Rat

    1 TF 100 MVA, 220/132 kV 150.00 Each 1 150

    Spares 3.00% 5

    CST 4.00% 6

    Transport and insurance 6.00% 9

    Erection charges 6.00% 9

    2Switchgear including cableconnections

    a Circuit breakers

    i) 220 kV 15.00 Each 1 1 1 15 15 15 0

    ii) 132 kV 8.60 Each 1 1 0 9 0 9

    b Current Transformers

    0 220 kV 3.00 Each 6 3 3 18 9 9 0

    ii) 132kV 1.30 Each 3 3 0 4 0 4

    c Capacitor Voltage -

    i) 220 kV 3.00 Each 6 3 18 0 9 0

    Transmission Substation Manual 40

  • 8/6/2019 1.Project Management 19.03.09

    41/151

    Project Management

    220 kV Substation Quantities and Detailed Costs Estimates

    220 kV Substation Quantities and Detailed Costs Estimates

    Transmission Substation Manual 41

    Per Bay Quantities Per Bay Costs - Rs Lakhs

    Item Description of Work

    Rs LakhsRequire

    d perS/S

    220/132kV TFBay

    220kV

    LineBay

    132 kVLineBay

    Required PerS/S

    220/132kV TFBay

    220kV

    LineBay

    132kV

    LineBay

    Rate

    Per

    ii) 132 kV 1.70 Each 3 0 0 0 5

    d Potential Transformers

    i) 220 kV 2.50 Each 6 15 0 0 0

    ii) 132 kV 1.00 Each 3 3 0 0 0

    e Isolators

    i a) 220 kV w/o E/S 3.00 Each 2 2 2 6 6 6 0

    i b) 220 kV c/w E/S 3.00 Each 2 1 6 0 3 0

    ii a) 132 kV w/o E/S 1.90 Each 1 1 0 2 0 2

    ii b) 132 kV c/w E/S 1.90 Each 1 1 2 0 0 2

    f Lightning Arresters

    i) 220 kV 1.00 Each 3 3 0 3 3 0

    ii) 132 kV 0.40 Each 3 3 0 1 0 1

    g Busbar earthing switch 4.00 Each 6 24 0 0 0

    h Control and relay panels

    220 kV side

    i) Line bay with D.R. & F.L. 12.0 Set 1 0 0 12 0

  • 8/6/2019 1.Project Management 19.03.09

    42/151

    Project Management

    Per Bay Quantities Per Bay Costs - Rs Lakhs

    Item Description of Work

    Rs Lakhs Required

    Per S/S

    220/132kV

    TF Bay

    220kV

    LineBay

    132 kVLineBay

    Required

    Per S/S

    220/132kV

    TF Bay

    220kV

    LineBay

    132kV

    LineBay

    Rate Per

    ii) Transformer 7.30 Set 1 0 7 0 0

    iii) Bus coupler bay 3.50 Set 1 4 0 0 0

    v) Busbar protection 8.80 Set 1 9 0 0 0

    132 kV side

    i) Line control relay panels 4.70 Set 1 0 0 0 5

    v) Event logger (500 points) 9.00 Set 0 0 0 0 0

    i Busbar, jumpers, isolators, earth

    connectors, clamps, connectors,

    i) 220 kV bays 4.00 Bay 1 1 1 4 4 4 0

    ii) 132 kV bays 3.00 Bay 1 0 0 0 3

    Spares 3.00 4 2 2 1

    CST 4,00 5 2 2 1

    Transport and insurance 6.00 7 4 4 2

    Erection charges 6.00 7 4 4 2

    3Scada & Telecom

    220 kV Substation Quantities and Detailed Costs Estimates

    Transmission Substation Manual 42

  • 8/6/2019 1.Project Management 19.03.09

    43/151

    Project Management

    Per Bay Quantities Per Bay Costs - Rs Lakhs

    Item Description of Work

    Rs LakhsRequire

    dPer S/S

    220/132kV TFBay

    220kV

    LineBay

    132 kVLineBay

    Required PerS/S

    220/132 kV

    TFBay

    220kV

    LineBay

    132kV

    LineBay

    Rate

    Per

    a)Optical Fibre terminalequipment

    33.00

    Bay 0 0 0 0 0

    b) 220 kV Bays: PLCC 20.0 Bay 1 0 0 20 0

    Spares 3.00 0 0 1 0

    CST 4.00 0 0 1 0

    Transport and insurance 6.00 0 0 1 0

    Erection charges 6.00 0 0 1 0

    4 Other Material

    a) Power and control cables

    i) 220 kV bays 2.00 Bay 1 1 1 2 2 2 0

    ii) 132 kV bays 1.50 Bay 1 0 0 0 2

    b) Steel structuresi) 220 kV bays (MT) 0.32 MT 86 43 43 28 14 14 0

    ii) 132 kV bays (MT) 0.32 MT 32 0 0 0 10

    c) Grounding and earthing

    220 kV Substation Quantities and Detailed Costs Estimates

    Transmission Substation Manual 43

  • 8/6/2019 1.Project Management 19.03.09

    44/151

    Project Management

    Per Bay Quantities Per Bay Costs - Rs Lakhs

    Item Description of Work

    Rs Lakhs Required

    Per S/S

    220/132kV TFBay

    220kV

    LineBay

    132 kVLineBay

    Required PerS/S

    220/132kV TFBay

    220kV

    LineBay

    132kV

    LineBay

    Rate

    Per

    220 kV bays 1.20 Bay 1 1 1 1 1 1 0

    132 kV bays 0.90 Bay 1 0 0 0 1

    d) Battery & charger 2.50 Set 1 3 0 0 0

    Spares 3.00 1 1 1 0

    CST 4.00 1 1 1 1

    Transport and insurance 6.00 2 I 1 1

    Erection charges 6.00%

    2 1 1 1

    5 Miscellaneous items

    a)*

    Fire fighting equipment 8.00 - LS 3

    b) Electricity system 2.50 - LS 3

    c) Transformer rail track 4.00 - LS 4

    d) Lighting 1.50 - LS 2

    e) Diesel set 9.00 - LS 9

    f) Mobile crane 15.00

    - 0 0

    220 kV Substation Quantities and Detailed Costs Estimates

    Transmission Substation Manual 44

  • 8/6/2019 1.Project Management 19.03.09

    45/151

    Project Management

    Per Bay Quantities Per Bay Costs - Rs Lakhs

    Item Description of Work

    Rs Lakhs Required

    Per S/S

    220/132kV TFBay

    220kV

    LineBay

    132 kVLineBay

    RequiredPer S/S

    220/132 kVTF Bay

    220kV

    LineBay

    132kV

    LineBay

    Rate

    Per

    g) A/C plant 3.00 - LS 3

    Transmission Substation Manual 45

  • 8/6/2019 1.Project Management 19.03.09

    46/151

    Project Management

    h) Fencing 0.30 - LS 0

    i) Concrete for foundations

    i) 220 kV bays 0.90 Bay 1 I 1 1 1 1 0

    ii) 132 kV bays 0.70 Bay 1 0 0 0 1

    j) Synchronizing (.roily 0.75 0 0 0 0 0

    k) Station transformers 1.40 1 1 0 0 0

    Items (j)

    &

    Spares 3.00 0 0 0 0

    CST 4.00 0 0 0 0

    Transport and insurance 6.00 0 0 0 0

    Erection charges 6.00 0 0 0 0

    6Land and rights, levelling ofsite

    20.00

    - LS 20

    220 kV Substation Quantities and Detailed Costs Estimates

    Per Bay Quantities Per Bay Costs - Rs Lakhs

    Item Description of Work Rs Lakhs

    RequiredPer S/S

    220/132kV TFBay

    220kV

    LineBay

    132 kVLineBay

    Required

    Per S/S

    220/132kV TFBay

    220kV

    LineBay

    132 kVLineBay

    Rate

    Per

    Transmission Substation Manual 46

  • 8/6/2019 1.Project Management 19.03.09

    47/151

    Project Management

    7aBuildings (Control house, stores,etc.)

    20.00

    - LS 20

    b

    Miscellaneous civil works(enclosures & siding, roads,foundation for structures, cablelaying system, sanitary system,oil system, etc..)

    21.50

    LS 22

    c Colony (staff quarters)34.3

    0- LS 34

    Sub-Total

    313 271 117 52

    Engineering and Management 7.8% 24 21 9 4

    Contingencies 3.0% 9 8 4 2

    Total 346 300 130 58

    Transmission Substation Manual 47

  • 8/6/2019 1.Project Management 19.03.09

    48/151

    Project Management

    ANNEXURE - 3

    BID DOCUMENTS

    INSTRUCTIONS TO BIDDERS (ITB)

    1.0 Source of Funds

    2..0 Scope of the Bid: The scope of the contract shall be on the basis of

    single bidders( Lead partner) responsibility completely covering all

    the equipment, material, and services specified under the

    accompanying technical specification.

    Scope of the bid covers Supply, civil & construction, erection,

    testing and commissioning, Design, engineering, manufacture,

    testing, supply on FOR destination site basis, including transportation

    & insurance, storage, erection, testing and commissioning of the

    equipments/items, complete in all respects.

    (a) Circuit breakers, isolators, current transformers, capacitorvoltage transformers and surge arresters.

    (b) Fire protection, Detection and Alarm system.

    (c) Illumination, wherever required.

    (d) Substation Monitoring System, Remote Transfer Unit (RTU)

    (e) Complete Relay and protection system including Control andRelay panels.

    (f) Power & Control cables along with complete accessoriesincluding cabling between marshalling box, auto transformersand bay kiosk/control room. Laying of co-axial cable fromyard to control room, laying of cables in HDPE pipes, supplyand laying of control cable from relay panel to carrier roomfor protection signaling, supply and laying of copper cablefrom 48V DCDB to PLCC, OFC panels.

    (g) Aluminum tubes, insulator hardware, spacers for conductors,bus post insulators, clamps & connectors, bay marshallingboxes, construction of cable trenches/ cable trays for control

    room, trench covers, cabling accessories, junction boxes etc.,grounding mat M.S. Rod and earth pipes etc. as specified inthe Bidding documents.

    (h) All works relating to supply, preparation of fabricationdrawings for all main structures including lightning mastsand equipment support structures, fabrication,galvanization, transportation to and storage at site anderection of these structures as detailed in SectionStructures.

    Drawings for the main structures and theirfoundations shall be provided by the Purchaser.Wherever the drawings and designs are provided by theOWNER, the suitability of these design and drawings shall beverified by the bidder for design requirements as per

    Transmission Substation Manual 48

  • 8/6/2019 1.Project Management 19.03.09

    49/151

    Project Management

    standards, site and soil conditions based on the soilinvestigation and furnish the detailed design verificationcalculations before execution if sought by the OWNER.

    Support structures for circuit breakers shall be as per CBmanufacturer's design.

    (i) Bus Post Insulators (including requirement for wave traps),

    insulator strings and hardware, clamps & connectors,

    (including terminal connectors for Employer supplied Autotransformers), Aluminum tubes, Bus bar and earthing

    materials, Bay marshalling box, spacers, cabletrenches/Cable trays & covers, Cabling accessories, junction

    boxes, buried cable trenches, grounding mat, M.S. rod andearth pipes etc. as specified in the Biding documents.

    (j)The Bidder shall take delivery of equipment at substation sitesupplied by him directly from his transporter and store them

    in his safe custody. However if any of the

    equipment/material is diverted from OWNER' stores,

    transportation charges from stores to site will be

    paid as per SSR rates prevailing on the date of

    transport.

    (k)Any other equipment/material required to complete the specifiedscope.

    2.1 Design, engineering, manufacture, testing, supply on FADS (Free AtDestination Site) including transportation & insurance, storage at

    site of mandatory spares.

    2.2 Civil works - The scope of work shall include but shall not be limited

    to civil works for the following

    (a) Soil investigation including soil resistivity measurement ifrequired.

    (b) Leveling of site, if required.

    (c) Foundation of 315 MVA Auto transformers (owner supplied),and associated SA along with jacking pad and pylon supports,rail track and fire resistant wall between transformers.

    (d) Foundation for Lattice & pipe structures and all equipments.

    (e) Foundation for lighting poles, Bay marshalling box,panels and control cubicles of equipments.

    (f) Cable trenches along with covers and sump pits.

    (g) Cable trench crossings, rail tracks, culverts etc.

    (h) Metal spreading and anti weed treatment as per siterequirement.

    (i) Drainage system in the substation, if required.

    Transmission Substation Manual 49

  • 8/6/2019 1.Project Management 19.03.09

    50/151

    Project Management

    (j) Laying of ground mat conductors and connection to theequipment support structures, lighting masts etc. and thenform a complete earthing system.

    (k) Provision of base channels in control house flooring for C&RPanels, if required.

    (l) Final grading and metalling after completing of thefoundations.

    2.3 The contract is on TURN KEY basis and hence any otheritems not specifically mentioned in the specification but

    which are

    required for erection, testing and commissioning and

    satisfactory operation of the substation are deemed to be

    included in the scope of the specification unless

    specifically excluded. Quantities wherever indicated in the

    Bidding documents are tentative only for the scope of the worksand will be considered only for the evaluation of Bids. Actualquantity will be as per the approved design and drawings for the

    complete scope of the works based on system requirement.

    2.4 The list of approved makes of main equipment/ material isenclosed in the specification and the equipment offered shall befrom the manufacturers given in the list only. The Bought-outitems required for main equipment/ material offered from the sub-vendors should have been supplied to State TRANSCOs,PGCIL and

    have proven performance. The bidder should own/lease/procurethe minimum tools & plants required for the execution of works intime as per the contract. The required T & P shall be indicatedtogether with quantity.

    2.5 Before proceeding with the construction work of the substation,the Contractor shall fully familiarize himself with the siteconditions and general arrangements & scheme etc. Though theEmployer shall endeavor to provide the information, it shall not bebinding for the Employer to provide the same. The bidders areadvised to visit the substation sites and acquaint themselves with

    the topography, infrastructure and also the design philosophy.The bidder shall be fully responsible for providing all equipment,materials, system and services specified or otherwise which arerequired to complete the supply, construction and successfulcommissioning, operation & maintenance of the substation in allrespects. All materials including cement & steel required for theCivil and construction/installation work shall be supplied by theContractor.

    2.6 The complete design (unless specified otherwise in specification

    elsewhere) and detailed engineering shall be done by theContractor.

    2.7 The Contractor shall also be responsible for the overall co-ordination with internal/external agencies, project management,

    Transmission Substation Manual 50

  • 8/6/2019 1.Project Management 19.03.09

    51/151

    Project Management

    training of Employer's manpower, loading, unloading, handling,moving to final destination including Employer supplied materialif any for successful erection, testing and commissioning of thesubstation/switchyard.

    2.8 Design of bay extension works and its associated works including

    preparation of single line diagram, electrical layouts, erectionkey diagrams, and electrical and physical clearance diagrams,design calculations for Earth mat, Direct Stroke LightingProtection (DSLP), if required as per the site conditions. Controland protection schematics, wiring and termination schedules,and other relevant drawings & documents required forengineering of all facilities within the fencing to be providedunder this contract, are covered under the scope of theContractor.

    2.10 Specific exclusions:

    The following items of work are specifically excluded from the

    scope of the specifications for all substations:

    (i) Transmission line side insulator string for line termination andtension clamp for earth wire termination.

    (ii) Supply, erection, testing and commissioning of 315MVA Auto Transformers.

    (iii) Drawings for all the structures (booms and columns)

    and Lightening masts as required will be furnished to the

    contractor by the purchaser.

    However, if any modification in design of a particular

    structure is required as per site conditions, the

    successful bidder has to do it at no additional cost to

    the OWNER.

    3.0 Submission of Bids:

    3.1Procedure for bid submission: The bidders who are desirous of

    participating in e- procurement shall submit their Technical bids,

    Price bids etc., in the standard formats prescribed in Tenderdocuments, displayed at e- market place. The bidders shouldinvariably upload the scanned copies in support of their bids. Bidder

    should take care that the scanned copies are clear & visible. The

    bidders shall sign on all the statements, documents, certificates,

    being uploaded by them, owning responsibility for their correctness /authenticity. The Department will not hold any risk and

    responsibility for the loss in transit during uploading of the scanneddocument, for the invisibility of the scanned document online, and

    any other problem(s) encountered by the bidders while submittinghis bids online.

    The following certificates, documents etc., are to be scanned anduploaded on to the e- procurement platform at

    Transmission Substation Manual 51

  • 8/6/2019 1.Project Management 19.03.09

    52/151

  • 8/6/2019 1.Project Management 19.03.09

    53/151

    Project Management

    Address of the OWNER:

    iii) And the third big size envelope for covering the above two

    envelopes which shall be super scribed as follows.

    I. Specification No.

    II. Name of the bidder:

    III. Name of the Work:

    IV * Full Bid Security enclosed in the form of Demand DraftNo.

    _____ Date_____

    (OR)

    Bank Guarantee No. ________ Dt. __________

    For Rs.________/- valid up to ______________* Strike-off whichever is not applicable.

    V. Bid is valid for 90 days from the date of opening ofthe pre-qualification / technical bids as mentioned inNIT.

    (If the validity of the bid is not as per specification it isliable to be returned unopened at the discretion of theOWNER.)

    VI. OWNERs terms of payment are accepted.

    VII. The bids shall be addressed to

    Address of the OWNER:

    (All the above envelopes shall be duly sealed

    individually.)

    iv) On all the three envelopes the Bidder shall clearly indicate thenames of the works for which they intend to participate. Thename of works as indicated on top of each envelope shouldtally with the Bid security amount and Bank Guarantee for

    these works deposited/furnished by the Bidder. In case the Bidsecurity amount deposited by the Bidder is found short theoffer shall be liable to rejected / ignored.

    v) All Bids and accompanying documents shall be in duplicateand shall be addressed to the

    Address of the OWNER:

    vi) The bids shall be submitted in duplicate complete with allparticulars called for in the schedules enclosed to specification.There shall not be any deviation from the contents of the

    schedule

    3.5 The dates stipulated in the tender notice are firm and under anycircumstances they will not be relaxed unless officially extended.

    Transmission Substation Manual 53

  • 8/6/2019 1.Project Management 19.03.09

    54/151

    Project Management

    The bidder has to keep track of any changes by viewing theaddendum / corrigendums issued by the Tender inviting Authorityon time-to-time basis in the e-procurement platform. TheDepartment calling for tenders shall not be responsible for anyclaims/ problems arising out of this.

    3.6 The bidder should upload scanned copies as specified in checklistand all enclosures required for the schedules and Appendices andproduce copies (Bid security, & Transaction Fee) one day beforethe date of opening of Pre-qualification bid.

    Contractor should produce the originals of all documents forverification if asked for by the Competent Authority within 3(Three) days.

    3.7 The Tender opening Authority will not consider any tenderreceived after expiry of date and time fixed (As specified in

    NIT) for receipt of tenders.3.8 Transaction fee and Bid Security: The Transaction fee at

    0.03% on ECV

    (Estimate Contract value) of work with a cap of Rs 10000/-

    (Rupees ten thousands only) for all tenders with ECV up to Rs. 50

    Crores plus service charges @12.36%,and Rs.25000/- (RupeesTwenty Five thousand only) plus service charges @ 12.36% for

    tenders with Estimated Contract Value (FECV) above Rs.50.00crores in favour of --------. All the tenderers have to pay the above

    non-refundable service charge through Online Payment Gatewaywith any MASTER/VISA credit card issued by any bank and through

    Net Banking facility with ICICI or HDFC Banks.Bid Security should

    be scanned and uploaded on line and the originals handed over to

    the ----------

    Bid Security shall be paid as indicated in the NIT. Bid

    Security must be in form of DD or BG from any scheduled Bank (as

    per approved list)/ Nationalized Bank. The Bidder is requested to

    submit the DD or BG from the scheduled Banks approved by the

    OWNER (List is enclosed). Demand Drafts shall be valid for aperiod of 6 months from the date of tender notice. Bid Securityshall be valid 30 days over and above the bid validity of 90 days.

    Bid Security will be forfeited:

    a) If the bidder withdraws the tender during Tender validity

    period.

    b) In case of successful bidder if he fails to sign the agreement for

    whatever so reason.

    c) If he fails to furnish the required performance security.

    Transmission Substation Manual 54

  • 8/6/2019 1.Project Management 19.03.09

    55/151

    Project Management

    The Bid Security of the unsuccessful bidder will be returned tothem either after finalization of the tenders or after the tender

    validity period which ever is later.

    The BID SECURITY deposited by the bidders will not carry any

    interest and it will be dealt with as provided in the conditionsstipulated in the tenders.

    3.9 Successful bidder shall pay the Corpus fund to APTS @ 0.03% onECV in the form of DD payable at Hyderabad and drawn in favour

    of ----- to sustain e procurement initiatives, research anddevelopment of software application for automation for process in

    user departments.

    3.10 The successful bidder is expected to complete the work within thetime period specified in the NIT.

    4.0 Bidders Eligible to Tender:

    The Bidders / Firms who

    i) Possess the valid registration as mentioned in the NIT andsatisfies all the conditions therein.

    ii) Are not blacklisted or debarred or suspended by theGovernment for what ever the reason, prohibiting them not tocontinue in the contracting business

    iii) Have complied with the eligibility criteria specified in the NIT

    are the eligible bidders/Firms.5.0 Bidders Ineligible to Tender:

    (i) A retired officer of the Govt. of AP or Govt. of India executing

    works is disqualified from tendering for a period of two yearsfrom the date of retirement without the prior permission of the

    Government.

    (ii)The Bidder who has employed any retired officer as mentioned

    above shall be considered as an ineligible Bidder.

    (iii) The Bidder himself or any of his employee is found to beGazetted Officer who retired from Government Service and hadnot obtained permission from the Government for accepting

    the Bidders employ-ment within a period of 2 years from thedate of his retirement.

    (iv) The Bidder or any of his employees is found at any time afteraward of contract, to be such a person who had not obtained

    the permission of the Government as aforesaid beforesubmission of the tender or engagement in the Bidders

    service.6.0 Last date / time for Submission of the Tenders.

    Transmission Substation Manual 55

  • 8/6/2019 1.Project Management 19.03.09

    56/151

    Project Management

    1. Tenders must be submitted online not later than the dateand time specified in NIT.

    2. The tender inviting authority may extend the dates for issueand receipt of Tenders by issuing an amendment in whichcase all rights and obligations of the tender inviting authority

    and the bidders will remain same as previously.

    3. If for any reason the last date of submission of tenders offlineis declared a holiday, the next working day will be treated asthe last date for submission of tenders.

    7.0 Late Tenders:

    Tenders will not be received after the last date / time prescribed inNIT.

    8.0 Modification to the Tender:

    Bidders can modify their Tender percentage online before the lastdate/time prescribed in NIT.

    No Tender shall be modified after the last date /time of

    submission of Tenders.

    The successful bidder is expected to complete the work withinthe time period specified in the NIT.

    9.0 Qualification Requirements of the Bidders:

    9.1 The Bidder shall furnish the following particulars in the formats

    provided online and supported documentary evidence shall beuploaded.

    Attested copies of documents relating to the Registration of thefirm, Commercial Tax Registration, Latest Income Tax Clearancecertificate /latest IT return and PAN number from IT Departmentetc.

    Availability of key personnel for administration /site managementand execution viz., technical personnel required for the work.

    9.2 Qualification criteria for opening of the price bid: Bidders qualified

    in the Technical / Pre qualification Bid are eligible.9.3 Even though the bidders meet the above qualification

    requirements, they are liable to be disqualified / debarred /suspended / blacklisted if they have Furnished false / fabricatedparticulars in the forms, statements and /Annexures submitted inproof of the qualification requirements and/or Not turned up forentering into agreement, when called upon within the timespecified in the letter of acceptance.

    9.6 Record of poor progress such as abandoning the work, not

    properly completing the contract, inordinate delays in completion,litigation history or financial failures etc. and/or Participated in the

    previous bidding for the same work and had quoted unreasonably

    high tender percentage.

    Transmission Substation Manual 56

  • 8/6/2019 1.Project Management 19.03.09

    57/151

    Project Management

    9.8A history of criminal record in which the bidder is involved if any.

    9.9 Even while execution of the work, if found that the work was

    awarded to the bidder based on false /fake certificates ofexperience, the bidder will be blacklisted and work will be

    taken over invoking clause 61 of PS to APSS.

    9.10 History of litigation with Govt. during the last 5 years in which the

    bidder is involved.

    10.0 Eligibility of the Bidder

    Eligibility of a bidder will be based on meeting the minimum criteriaspecified in Part-A below regarding the Bidders technical experience and

    financial position. The bidder shall also be required to furnish theinformation specified in Part-B below in their Bid. Technical experience

    and financial resources of any proposed subcontractor shall not be taken

    into account in determining the Bidders compliance with the qualifyingcriteria.

    The bid can be submitted by an individual firm or a Joint Venture

    of not exceeding three firms (Specific requirements for Joint Venturesare given under Para 10.1.3 below).

    The OWNER reserves the right to waive minor deviations if they do notmaterially affect the capability of the Bidder to perform the contract.

    The Purchaser may assess the capacity and capability of the bidder, to

    successfully execute the scope of work covered under the packagewithin stipulated completion period. This assessment shall inter-aliasinclude

    i. Document verification;

    ii. Bidders

    work/manufacturing facilities, manufacturing capacity, details of

    works executed, works in hand, anticipated in future & the

    balance capacity available for the present scope of work;

    iii. Details of plant and

    machinery, manufacturing and testing facilities, manpower and

    financial resources;

    Details of quality systems in place;

    Past experience and performance;

    Customer feedback;

    (viii) Bankers feedback etc.

    Part-A

    Technical Experience:

    Transmission Substation Manual 57

  • 8/6/2019 1.Project Management 19.03.09

    58/151

    Project Management

    The bidder must have successfully executed one sub-station orswitchyard of 220/132 kV class or above having atleast 2(two) circuitbreaker bays during last 10 years as on the date of bid opening andwhich must be in satisfactory operation for atleast 2 (two) years as onthe date of bid opening, provided.

    i. the 400 kV class Circuit breaker being offered are frommanufacturer(s) who have designed, manufactured, type testedand supplied the Circuit Breaker of 400 kV or above class whichmust be in satisfactory operation for atleast 2 (two) years as onthe date of bid opening.

    (OR)

    ii. the 400kV class Circuit breaker being offered are from

    manufacturer(s) who have established production line in India forthese equipments, based on technological support of a parent

    company or collaborator for the Circuit Breaker (s) can also beconsidered provided

    iii. Such manufacturer (s) has designed, manufactured; type testedand supplied the 220 kV or above class Circuit Breaker.

    iv. The parent company (Principals) or collaborator meets qualifyingrequirements stipulated above; and

    v. The 400 kV class Circuit breaker manufacturer(s) furnishes Alegally enforceable undertaking (jointly with the parent companyor collaborator) to guarantee quality, timely supply, performance

    and warranty obligations as specified for the equipment(s); andvi. A confirmation letter from the parent company or collaborator

    along with the bid stating that parent company or collaboratorshall furnish performance guarantee for an amount of 10 % of thecost of such equipment(s). This performance guarantee shall bein addition to Contract Performance Guarantee to be submittedby the Bidder.

    (OR)

    The bidder shall have satisfactorily completed as a prime contractor or

    as a sub-contractor or as a member in a Joint Venture 345/400kV orhigher voltage class transmission line(s)within the last ten (10) years as

    on date of bid opening. The bidder should have erected and strung with

    tension stringing equipments, not less than 50 km cumulative route

    length of transmission line of 345/400kV or higher voltage class,

    provided he associates a substation contractor who must have

    successfully executed one sub-station or switchyard of 110/132kV class

    or above having atleast 2(two) circuit breaker bays during last 10 years

    as on the date of bid opening and which must be in satisfactory

    operation for atleast 2 (two) years as on the date of bid opening. In sucha case, the bidder shall furnish Joint Deed of Undertaking (Format

    enclosed) with the substation contractor. Further, circuit breakers being

    offered should meet the requirement.

    Transmission Substation Manual 58

  • 8/6/2019 1.Project Management 19.03.09

    59/151

    Project Management

    For the purpose of qualifying requirement, one no. of circuit breaker bayshall be considered as a bay used for controlling a line or a transformer

    or a reactor or a bus section or a bus coupler and comprising of at leastone circuit breaker, two disconnectors and three nos. of single phase CTs

    / Bushing CTs.

    Financial Position:

    The bidder should have achieved an Annual Financial Turnover (AFT) ofat least Rs.11.00 crores- in any one year during the last five financialyears. The Bidder shall have Liquid Assets (L.A.) or / and evidence ofaccess to or availability of credit facilities of Rs 5.5 Crores.

    In case bidder is a holding company, AFT & LA referred to in clause

    above shall be that of holding company only (i.e. excluding itssubsidiary / group companies). In case bidder is a subsidiary of a holding

    company, AFT & LA referred to in clause above shall be that of subsidiary

    company only (i.e. excluding its holding company).

    Joint Venture Firms:

    The figures for each of the partners of the joint venture shall be addedtogether to determine the bidders compliance with the minimumqualifying criteria set out in para above; however, in order for a jointventure to qualify, the partner(s) of joint venture must meet thefollowing minimum criteria:

    a. The lead partner shall meet, not less than 50% of the

    minimum criteria given at Para (Financial position) and 100% ofcriteria (Technical experience) above.

    b. Each of the other partner(s) shall meet,

    Further, each of the other partner(s) must have successfully executed, atleast one feeder bay and one transformer bay (132/110kV class or

    above) including all civil works in the last 10 years which must be insatisfactory operation for a minimum of 2 years as on the date of bid

    opening.

    a) One of the partners shall be nominated as Lead Partner, and the LeadPartner shall be authorized to incur liabilities and receive instructionsfor and on behalf of any and all partners of the Joint Venture, and the

    entire execution of the Contract shall be done with the Lead Partnerand payment under the contract shall be received by the Lead Partner

    on behalf of the Joint Venture as per power conferred to him in the

    Power of Attorney. The authorization shall be evidenced by submitting

    a Power of Attorney signed by legally authorized signatory of all thepartners. The payment under the Contract can also be received by

    other partner(s) based on authorization of Lead Partner.

    b) All partners of the Joint Venture shall be liable jointly and separately

    for the execution of the Contract in accordance with the Contract

    Transmission Substation Manual 59

  • 8/6/2019 1.Project Management 19.03.09

    60/151

    Project Management

    terms and a copy of the agreement entered into by the joint venturepartners having such a provision shall be submitted with the bid.

    A statement to this effect shall be included in the authorizationmentioned under (a) above as well as in the Bid Form and in the ContractForm (in case of a successful bid).

    PART-B :

    The Bidder shall also furnish following documents/details with its bid:

    A certificate from banker (as per format) indicating various fund

    based/non fund based limits sanctioned to the bidder and the extent of

    utilization as on date. Such certificate should have been issued not

    earlier than three months prior to the date of bid opening. Wherever

    necessary OWNER may make queries with the Bidders bankers.

    The complete annual reports together with Audited statement ofaccounts of the company for last five years of its own (separate)

    immediately preceding the date of submission of bid.

    Note :

    I. In the event the bidder is not able to furnish the information of its own

    (i.e separate), being a subsidiary company and its accounts are being

    consolidated with its group/holding/parent company, the bidder

    should submit the audited balance sheets, income statements, other

    information pertaining to it only (not of its group/Holding/ParentCompany) duly certified by any one of the authority [ (i) Statutory

    Auditor of the bidder /(ii) Company Secretary of the bidder or (iii) A

    certified Public Accountant] certifying that such information/

    documents are based on the audited accounts as the case may be.

    II. Similarly, if the bidder happens to be a Group/Holding/Parent

    Company, the bidder should submit the above documents/information

    of its own (i.e. exclusive of its subsidiaries) duly certified by any one

    of the authority mentioned in Note-I above certifying that these

    information/documents are based on the audited accounts, as thecase may be.

    III.Bidder shall have adequate sub-station / transmission line design

    infrastructure and erection facilities and capacity and procedures

    including quality control.

    IV.The bidder should own / lease / procure the minimum tools & plants

    required for the execution of the works in time as per the contractperiod. The required T & P shall be indicated together with quantity.

    V. The bidder should indicate number of technical persons along withtheir qualifications available with him for execution of the works as

    follows.

    Transmission Substation Manual 60

  • 8/6/2019 1.Project Management 19.03.09

    61/151

    Project Management

    Project Manager 1 No. Graduate Engineer.

    Site Incharge 2 Nos. Graduate Engineers (1 No Electrical and 1 No.

    Civil) with Five Years of experience in similar project.

    Technical persons 3 Nos. each Electrical & Civil Diploma holders OR

    3 Nos. each ITI holders Electrical & Civil with experience of five years insimilar project.

    Any of the joint ventures contractors in one bid shall not associate with

    any other bidders as Joint venture for the same tender.

    Litigation History:

    The bidder should provide detailed information on any litigation or

    arbitration arising out of contracts completed or under execution by it

    over the last five years. A consistent history of awards involving

    litigation against the Bidder or any partner of JV may result in rejection ofBid.

    One Tender per Bidder: Each Bidder shall submit only one Tender for

    the work. A Bidder who submits more than one Tender will cause

    disqualification of all the Tenders submitted by the Bidder.

    Language of the Bidding Documents:

    Bids shall be submitted in English language only.

    Cost of Tendering:

    The Bidder shall bear all costs associated with the preparation and

    submission of his Tender and the tender inviting authority will in no case

    be responsible and liable for those costs.

    Cumulative Financial Capability:

    If the bidder is bidding for more than one contract, the aggregate

    requirement of turnover and credit facility will be counted for awarding

    more than one contract. Bidder shall furnish the certified profit & loss

    account statements for the last five years.

    Site Visit:

    The Bidder, at the Bidders own responsibility and risk is advised to visit

    and examine the Site of Work and its surroundings and obtain all

    information that may be necessary for preparing the Tender for entering

    into a contract, for construction of the work. The costs of visiting the

    site shall be at the Bidders own expense.

    Clarification on Bidding Documents:

    A prospective Bidder requiring any clarification on the Bidding

    Documents may notify the tender inviting authority in writing or by fax

    at the tender inviting authoritys mailing address indicated in the

    Invitation for Bids. The clarifications sought by the bidders received 15

    Transmission Substation Manual 61

  • 8/6/2019 1.Project Management 19.03.09

    62/151

    Project Management

    days earlier to the date of opening of the pre-qualification bid will be

    clarified provided these clarifications as found necessary only in case of

    any ambiguity in the bidding documents brought out by the bidder. In all

    other cases the specification provisions in the bidding documents

    prevail.

    Amendment of Bidding Documents:

    At any time before the deadline for submission of bids, the purchaser

    may, for any reason, whether at its own initiative or in response to a

    clarification requested by a prospective bidder, modify the bidding

    documents by amendment.

    PRICES:

    The bidder is entirely responsible for quoting prices with correct taxesand duties, other local taxes or levies if any, license fee etc. that theyhave to incur until completion of project. Evaluation will be done onprices inclusive of all taxes, duties and other levies if any, license feeetc., he has to incur till completion of the contract. The Bidder isrequested to quote prices as indicated in Price schedule A forevaluation along with break up of all taxes and duties for the purpose ofpayment. Percentage of taxes and duties as applicable is to be indicatedclearly in Schedule A supplementary without which the bid is liable forrejection. It is noted that the entry tax on goods entering into local areaof Andhra Pradesh is NIL as on the date as per the recent

    pronouncement of A.P High Court.Bids received for individual items with lump sum price showing

    all taxes and duties as inclusive without giving break up of each

    tax component are liable for rejection.

    Bidders must submit the bid for the full quantity required as per

    bidding documents for all the items mentioned in the price

    schedules.

    (a) For Equipment & Materials:

    The Bidder has to quote his prices for equipment and material inSchedule-A & Schedule A supplementary. The quoted rates forthe items of Equipment & Materials i.e., Circuit Breakers, Instrumenttransformers, Lighting arresters, Isolators, substation lattice and pipestructures, Moose ACSR conductor and Power and Control cables areVARIABLE. The Price variation clause applicable is mentionedbelow.

    Prices of all other equipment /material shall be firm on all accounts suchas increase in quantity of Equipment / Materials over that provided inthe contract, execution of contract beyond the scheduled completionperiod for whatever reasons, increase in the rates of material and labourboth during and beyond the completion period etc.

    (b) For Works:

    The Bidder has to quote in Schedule-C, the percentage Excess/on par/Transmission Substation Manual 62

  • 8/6/2019 1.Project Management 19.03.09

    63/151

    Project Management

    Less over the estimated value of the works given in the Schedule-B. Therates duly loaded with quoted tender percentage for all the items of

    works covered in Schedules B, except for the items cement,reinforcement steel & earth flat/ rod shall be firm on all accounts such

    as (i) increase in quantum of work upto 25% over that provided in the

    contract, (ii) execution of contract beyond the scheduled completionperiod for whatever reasons, (iii) increase in the rates of material andlabour both during and beyond the completion period etc. These prices

    shall include all the taxes and duties wherever applicable. Price variationis applicable for items cement, reinforcement steel & earth flat/ rod

    which are as perPrice Variation clause mentioned below.

    The prices quoted shall be inclusive of all taxes, duties and levies

    including Works Contract Tax, Service Tax, Educational cess, Exciseduty, CST/GST, VAT, Octroi, Modvat etc., packing, forwarding, loading,

    unloading, transportation to site/stores/storage and insurance to covertransport, storage, erection, testing & commissioning etc. till the works

    are taken over by OWNER.

    All the information required in the various prices and other schedules

    must be complete, otherwise the bids are likely to be rejected. Underno circumstances shall a bidder alter his price during the validity period

    after bids are opened. Any bidder who does so resulting in recalling of

    bids by the OWNER or additional expenditure to the OWNER shall not

    only lose his bid security but also run the risk of being blacklisted by

    the OWNER which reserves the right under the law to recover damagesresulting there from.

    PRICE VARIATION (PV) Clause:

    The Price Variation applicable in respect of the items substationstructures, cement, reinforcement steel & earth flat is subject to the

    following conditions:

    a) Price variation shall be applicable for both upward and downward

    variation in prices of respective items within the originalcompletion period.

    b) The indices adopted for calculation of price variation shall be (i)Wholesale Price Index, released from Ministry of Commerce &

    Industry, Govt. of India for the items cement, reinforcement steel& earth flat, and (ii) All India average Consumer price Index

    number for industrial workers as published by the Labour Bureau,Ministry of Labour, Govt. of India in respect of the items

    transmission line towers, substation structures.

    c) Upto 5% variation of indices, the agreement rates of the

    respective items hold good. Price variation shall be applied onlywhen the variation in respective items price indices is above 5%

    or below 5%. Difference above or below 5% will only be

    considered.

    Transmission Substation Manual 63

  • 8/6/2019 1.Project Management 19.03.09

    64/151

    Project Management

    d) The completion schedule enclosed to the specification in the formof bar chart shall be the basis for timing of the each activity forcalculating the Price Variation during a month. If the schedule isnot complied by the contractor as per the above programme dueto the reasons like right-of-way, the particular activity or task can

    be rescheduled by moving upward or downward on the time axisof the bar chart within the agreement period, as agreed by theConcerned Executive Engineer (field officer), as per the actual siteconditions. In such cases, the concerned Executive Engineer willrecord the reasons for re-scheduling / delay of the work.

    e) Price adjustment shall be calculated separately for Reinforcementsteel & Cement components in proportion to the cost of work doneinvolving the above materials during the billing period as given inthe formula given below. The percentage of Reinforcement steel &Cement components is based on estimated rate only. The Price

    Variation amount so obtained will be added to the cost of workdone calculated on quoted rate, put up for billing.

    f) The concerned Field Executive Engineer will calculate the PriceVariation for the billing period, preferably monthly. For thispurpose the contractor shall submit invoice supported bycalculations as per formula specified along with documentaryevidence for different indices applicable for Price Adjustment,

    g) Price variation will be limited to the amount arrived based onschedule date of completion or actual date of completion which

    ever is earlier. Lower of the two indices values will be considered.h) In specific cases like substation site being not handed over to the

    contractor in time by the OWNER due to delay in land acquisition,natural calamities, right-of-way problems, for which the contractoris not responsible, extension of the agreement period may begiven duly rescheduling the programme of completion with theapproval of competent authority. In all such cases, OWNER willconsider application of price variation clause case to case.

    i) Applicable formula for calculating Price Variation for

    Reinforcement steel, Cement & MS Flat/Rod (in Earthing):

    billingforup(putdoneworkofcostWPI

    WPWPI

    100

    PCorPs0.85PV

    0

    01

    = W

    here,

    PV = increase / decrease in the cost of work done during

    the period under consideration due to variation in the rate of Steel/ Cement.

    Ps or PC = Percentage of steel or cement component in the total

    value of item of work under consideration. For thispurpose estimate rate, exclusive of taxes & duties, isto be considered.

    Transmission Substation Manual 64

  • 8/6/2019 1.Project Management 19.03.09

    65/151

    Project Management

    WPIO = The base price index of Steel or Cement during tenderquoting month.

    WPI1 = The Wholesale Price Index for Steel or Cement of thefirst week of calendar month programmed i.e. to be

    completed as per the agreed period of schedule oractual period of completion, whichever is lower.

    Ps or PC = (Quantity of Steel or Cement in PO quantity x Rate ofSteel or

    100 Cement as per estimate)/ (Total estimate value ofitem of work under consideration) / 100

    j) Applicable formula for calculating Price Variation for Substation

    structures of 400 kV SS:

    ++++=

    0000

    0

    W

    W11

    ZN

    ZN16

    LA

    LA40

    HA

    HA1815

    100

    PP

    Where,

    Po = Ex-works price quoted / confirmed.

    HA = Price of heavier angles. (This price is applicable on thefirst working day of the month, two months prior to thedate of delivery). For this purpose bidders need toproduce delivery challans of the material supplied.

    HAo = Price of heavier angles. (This price is applicable on thefirst working day of the month, one month prior to thedate of tendering).

    LA = Price o