1_spreadfoundations

Upload: jimmy-villca-sainz

Post on 19-Feb-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/24/2019 1_spreadfoundations

    1/13

    1

    Foundation Systems 1,spread foundations

    Whats the point?

    The foundations primary purpose is:

    Distribute building loads to the soil

    Prevent frost uplift of the building (act asfrost barrier)

    Some foundation systems also providea level, controlled surface from whichthe buildings walls are raised.

    What types?

    Spread (aka strip) footings with stemwall foundations

    Pad footings with column foundations

    Pile footings with caps

    Caissons (aka drilled piers) with grade beams

    Mat (aka raft, slab) foundation with stemwalls

  • 7/24/2019 1_spreadfoundations

    2/13

    2

    Spread Footings

    Bottom of footing seton undisturbed earth orengineered fill andbelow frost line

    The rule of thumb forproportioning (alwaysuse a professionalengineer!) is the footingis twice as wide as thefoundation walltransferring load to it.

    Its thickness is at leastequal to the width ofthe foundation wall.

    W

    = 2W

    = W

    Characteristics

    Light loads

    Low rise

    Stable soils

    Common in residential and light commercial

    Also used as a frost barrier with heavier foundation

    systems

    A shallow foundation system (usually within 25 feet ofgrade)

  • 7/24/2019 1_spreadfoundations

    3/13

    3

    Strip footings

    Most common for low rise,low load conditions.

    A strip of reinforced concreteready to accept a wall ofsome kind on top.

    Dowels, Reinforcing barsprojecting from the top of thefooting connect to wallreinforcing to limit sideslip ofthe stemwall.

    outsideinside

    Strip footings

    An alternative to dowels is tomake a slight depression inthe top of the footing called akeyway.

    The keyway works when it isfilled with concrete from thewall pour above. Theconcrete acts as a shear keypreventing sideslip of thestemwall.

    outsideinside

  • 7/24/2019 1_spreadfoundations

    4/13

    4

    Spread footing process Layout strings from

    batter boards - markoutside of walls or

    outside of footing Project lines down to

    bottom of excavationwith plumb lines andmark with paint orlime

    Excavate for footing

    If rain is expected- (to within a fewinches of bottomelevation - handdig the rest afterthe rain)

    If no rain isexpected - dig tofinal elevation,

    Spread footing process2 Set formwork for

    footing,

    Set to square andlevel with transit

    double checkoutside walllocation tooutside of footing

    stake to grade tobrace

    Cross brace topof form

    Set reinforcing onchairs or bricks tokeep it up off thebottom of thefoundation -

    longitudinals firstthen transverse

    Spread footing process2 Pour the footing

    form full ofconcrete.

    Set reinforcing barsas dowels in thetop of the concreteto tie into the walls

    Estimating guidespriced this footingat approx. $24.00per linear foot in1998

    outsideinside

  • 7/24/2019 1_spreadfoundations

    5/13

    5

    Spread footing process3 With the forms

    stripped, thefoundation walls

    made of block orconcrete can beconstructed on the

    footing

    If concrete blockwalls are used,horizontal jointreinforcing isplaced betweenalternate coursesto provideadditional lateralstability.

    outsideinside

    Spread footing process4 Anchorage for sil l

    plates isaccomplished byfilling block coreswith concrete andJ shaped anchorbolts are inserted.

    Additional verticalreinforcing, ifrequired isaccomplished byplacing thereinforcing bar in avertical block coreand filling withconcrete.

    outsideinside

    Cast in Place stemwallfoundations

    Where high lateral forces,high hygroscopic pressuresor high masonry costs arefound, foundation walls areoften made of cast in placeconcrete

    Its a premium foundationwall - often most expensive

    Cost is high because webuild a wood wall (forms) fillit with a steel wall (rebar) andcover that with a concretewallthen throw the woodwall away!

  • 7/24/2019 1_spreadfoundations

    6/13

    6

    Begin withForms

    Formwork is usually builtfrom the outside - in.

    The exterior form(plywood) is constructedon a layer of vertical studs(to brace the plywood)these vertical studs arethen braced with horizontalstuds (walers) to make theform stiffer

    Then the reinforcing isinstalled, wired together ateach vert/horiz intersection

    Begin withForms

    Formwork is usually builtfrom the outside - in.

    The exterior form(plywood) is constructedon a layer of vertical studs(to brace the plywood)these vertical studs arethen braced with horizontalstuds (wales) to make theform stiffer

    Then the reinforcing isinstalled, wired together ateach vert/horiz intersection

    Ties thatbindand separate!

    To keep the forms theproper distance apart,wire ties with plasticcones are insertedbetween forms. Thecones keep the inside andoutside form boards apart.

    The loops in the ends ofthe forms allow the ties tobe tensioned so the formsdont spread apart.

    They push and pull at thesame time

  • 7/24/2019 1_spreadfoundations

    7/13

    7

    The wet concrete mix is prettyheavy, the forms have to bebraced both horizontally andvertically to resist the hydraulicload imposed by the mix

    Horizontal 2x4s (wales) areattached to the back of theplywood formwork to be thefirst bracing layer

    Then vertical 2xs areclamped to the horizontalsto become the secondbracing layer

    Finally, diagonal braces areadded and staked to theground, now the formbracing is complete

    Forming apour joint

    The pour joint begins withcontinuity of the reinforcing

    Sometimes an additional dowelis placed to insure the joint willresist lateral displacement

    To stop the pour, a plywood capis made by drilling holes in apiece of plywood, and attaching itto the plywood forms on eachside of the wall, making sure therebar passes through the holes

    A 2x4 is often nailed to the insideof this plywood cap to displaceconcrete and form a shear key

    Often, the foundationcannot be poured all atonce. To stop a pour, wedetail a pour jointthatwill let the reinforcingpass through and becontinuous (so the twopours structurallybehave like one pour )

    The combination ofcontinuity of reinforcingand a vertical shear keyprevents lateralmovement of the secondpour relative to the first.

  • 7/24/2019 1_spreadfoundations

    8/13

    8

    Keep it drydampproofing Keeping the foundation wall dry is

    accomplished in degrees.

    The lowest level of protection is termeddampproofing

    Dampproofing coatings are applied to theoutside face of the foundation.

    Usually dampproof coatings do not have theability to bridge across cracks which developin the foundation

    Dampproof coatings are carried down thefoundation wall and over the top of thefooting to minimize leakage through thefoundation/footing joint.

    Dampproof coatings are usually brushapplied and can be cementitious (thoro seal)

    or asphaltic

    outsideinside

    Keep it drywater resistantcoatings Water resistant coatings are

    the next step up in keeping thefoundation dry.

    These coatings usually havethe ability to span cracks to amodest degree.

    Water resistant coatings areusually applied with a trowel

    and are often asphaltic orbituminous materials (blacksticky stuff)

    Asphaltic and bituminouscoatings are UV sensitive,they need to be backfilled orprotected from the sun in lessthan 30 days or they begin tobecome brittle. (crack easily)

    outsideinside

  • 7/24/2019 1_spreadfoundations

    9/13

    9

    Keep it drywaterproofcoatings Waterproof coatings offer the

    highest level of water protectionfor the foundation wall.

    Waterproofing systems fall intothree categories

    Applied sheet membranes

    Spray applied membranes

    Attached board membranes

    All offer superior waterproofingqualities when correctly applied.

    All are fragile! When backfillingthey should be protected fromscuffing, scraping, bashing, orsimilar injury.

    If the membrane is puncturedduring backfilling operations, thedamage wont be known until that

    first rain.

    outsideinside

    Keep it drywaterproofcoatings

    Some popular membranes

    Bituthene - a roll of heavypolyethylene backed with athick layer of sticky masticprotected by paper. With thepaper removed it sticks to thefoundation wall and spanscracks to keep water out.

    Volclay panels - sheets ofcardboard filled with bentoniteclay mechanically fastened

    (nail, screws) to thefoundation. In the presence ofwater, the clay expands to 15times dry volume forming animpervious clay layer outsidethe wall.

    Spray applied modified bitumen- a spray on membrane,depending on thickness todevelop the ability to span.

    outsideinside

  • 7/24/2019 1_spreadfoundations

    10/13

    10

    Keep it warminsulation Heat loss through the

    foundation has been found tobe a significant source ofenergy consumption inresidential and smallcommercial buildings.

    Rigid foam boards are themost common means ofinsulating the foundation wall.

    Often the insulation is placedon the outside of thefoundation wall to keep themass warm

    This also keeps the rocks,logs, disco boots, brokenbottles which may be part of

    the backfill from poking a holein the waterproofing!

    outsideinside

    Insulation flavors plain vanilla

    Expanded polystyrene(beadboard or EPS) -available in

    white

    light grey

    Open cells - Holds water(which reduces R value)

    R value approx 3.5 per inch

    Lowest price range

  • 7/24/2019 1_spreadfoundations

    11/13

    11

    Rainbow flavors

    Extruded polystyrene(styrofoam) - available in

    blue (dow)

    Pink (Owens Corning)

    Green (Amoco)

    Yellow (Certainteed)

    Closed cells - Wont holdwater

    R value approx 5 per inch

    Middle price range

    Dirty yellow

    Polyisocyanurate (polyiso) -available in

    yellow

    Closed cells - Wont holdwater

    R value approx 10 per inch

    highest price range

    Keep it warminsulation Rigid board insulation comes in three

    commonly used types

    Expanded polystyrene R=3.5 per 1thickness (usually white, akabeadboard) holds water inside theboard between the beads, decreasingthermal effectiveness. Least expensive($ .61/sf)

    Extruded polystyrene R= 5 per 1

    thickness (usually blue, yellow, pink, limegreen) doesnt hold water inside,moderately expensive ($ .75/sf)

    Polyisocyanurate R=7.5 per 1 thickness(usually a dirty yellow to orange color)can hold water, most expensive. ($.78/sf)

    outsideinside

  • 7/24/2019 1_spreadfoundations

    12/13

    12

    The belt and suspendersdrainboard Additional insurance in the form of dry

    foundation walls can be added byinstalling an air gap between the backfill

    and the foundation wall assembly.

    Making dirt conform to an air gap isdifficult, but a component called adrainboard makes it simple.

    The drainboard is a plastic (often arecycled plastic) sheet which is vacuumformed into a surface of dimples andvalleys.

    Attached to the top of the dimple is ageotextile fabric, also called a filterfabric. This fabric keeps large soilparticles from clogging the spacesbetween the dimples.

    outsideinside

    Dropping waterdrainboard

    A primary moisture moving mechanismin soil is capillary action. Water at ahigher vapor pressure moves betweensoil particles.

    The drainboard allows the water throughthe filter, but then, unable to get acrossthe air gap, the water drops to thebottom of the drainboardand into awaiting drain tile.

    DimplesGeotextile filter fabric

    Getting rid of waterperimeter drain The drainboard is draped over another

    recycled plastic product, the perimeteror footing drain.

    outsideinside

  • 7/24/2019 1_spreadfoundations

    13/13

    13

    Getting rid of watersump pumps

    This continuous flexible pipeis either sloped to run out ofthe excavation (run todaylight)

    or is piped to a plastic bucket(sump)

    which has a pump in it (sumppump)

    connected to a pipe (ejectorpipe)

    that either dumps the water inthe storm sewer or outside ongrade

    .as long as the power is on,

    the pump doesnt burn out,and the ejector pipe doesntfreeze up...