2. phase: 2. phase: plan the project what? how? work breakdown structure estimation of resources ...
TRANSCRIPT
2. 2. PhasePhase: : PLAN THE PROJECT
What? How?
Work Breakdown Structure Estimation of resources Definition of dependencies between
project activities Development of PERT diagram Assignment of responsibilities
Work Breakdown Structure (WBS)Work Breakdown Structure (WBS)
Project - Hierarchical system (tree): Goal
• Objectives• Workpackages
• ...• Tasks
Decomposition „upside- down“
W BS
T ask1.1.1
T ask1.1.2
T ask1.1.3
W P1.1
T ask1.2.1
T ask1.2.2
W P1.2
T ask1.3.1
T ask1.3.2
T ask1.3.3
W P1.3
O bjec tive 1
TaskTask
S.M.A.R.T. Criterion: Specific Measurable (costs, work, time) Assignable (responsibility) Realistic Time-related
TASK DESCRIPTIONTASK DESCRIPTION
Task ID, title, description Input (outcomes of other tasks) Title, type, description of a
deliverable Start and end time Effort (e.g. in person-months) Costs Responsibility
ExampleExample: : CConferenceonference planning planning
1. Conference programme1.1 Define programme of conference 1.2 Obtain speakers1.3 Prepare conference materials
1.3.1 Obtain presentations from speakers
1.3.2 Prepare and print conference materials
ExampleExample: : CConferenceonference planning planning (2)(2)
2. Set the conference site & date2.1 Set the conference date2.2 Select & commit conference site 2.3 Confirm arrangements
ExampleExample: : CConferenceonference planning planning (3) (3)
3. Develop marketing plan3.1 Develop and print conference
brochure3.2 Obtain Label Sets for Direct
mailing3.3 Mail brochures3.4 Receive & acknowledge
registrations
Duration of a Task Duration of a Task
Task duration = Effort / No of persons
• Random characterAverage time of activity duration:
TA = (O + 4.M + P) / 6 O - optimistic completion time P - pesimistic M – most likely completion time
COSTS CATEGORIESCOSTS CATEGORIES
• Personnel costs• Equipment• Travel and subsistence• Consumables• Other direct costs• Subcontracting • Indirect Costs (overheads)
SEQUENCING THE PROJECT SEQUENCING THE PROJECT ACTIVITIESACTIVITIES
• Logical / time dependencies• Types of dependencies:
• Finish Start („Immediate predecessor“)
• Finish Finish• Start Start • Start Finish
Activity Title Imm. Pred.
A (2.1) Date -
B (1.1) Programme -
C (2.2) Site A
D (1.2) Speakers B
E (3.1) Conf.broch. C, D
F (3.2) Database C, D
Example: Conference planning
Activity Place Imm.Pred.
G (3.3) Mailing E, F
H (1.3.1) Obtain D
I (3.4) Process G
J (2.3) Finish H, I
K (1.3.2) Print J
ExampleExample: Conference planning: Conference planning (2)(2)
PERT DIAGRAMPERT DIAGRAM(Project Evaluation & Review Technique)(Project Evaluation & Review Technique)
NODE: ID - activity identifier ES - earliest possible start EF - earliest possible finish LS - latest possible start LF - latest possible finish AD - activity duration TS - time slack
USE OF PERTUSE OF PERT
Locating the Critical Path (CP) Earliest possible time of finishing
the project Determination of paralelly
executable tasks View from „bird perspective”
CRITICAL PATHCRITICAL PATH
Critical path: The longest path in PERT
Delay of activity delay on critical path prolongation of the project duration
CALCULATION OF THE CALCULATION OF THE CRITICAL PATHCRITICAL PATH
ESk = max {EFi , i all imm. predecessors of the node k}
EFk = ESk + ADk LFk = min {LSi , i all nodes for which the
node k is a predecessor}LSk = LFk - ADk
Activities on CP have zero Time slack
ExampleExample: Conference Planning: Conference Planning
0 2A 24 6
2 7C 56 11
11 20E 911 20
11 16F 515 20
20 22G 220 22
22 28I 622 28
11 15H 424 28
5 11D 65 11
0 5B 50 5
29 31K 229 31
28 29J 128 29
startend
4 4
4
13
APPLICATION OF PERTAPPLICATION OF PERT
• Planning – activity scheduling, assigment team members to tasks
• Implementation – realocation of resources
• Control – Comparision of plan and current status quo
Project ProposalProject Proposal
Problem definition, Aim of the project, approach taken, expected benefits
Detailed description of project activities (Workplan) - dates, resources, deliverables, ...
Budget, management structure, ... Depends on the type of the project
PURPOSE OF THE PROJECT PURPOSE OF THE PROJECT PROPOSALPROPOSAL
• Detailed project description (Request for Grant)
• Dynamic tool for project manager for decision making
• Reference document for project control
• Becoming familiar with the project
TEAM ASSIGNMENT 2TEAM ASSIGNMENT 2
Develop a Project Proposal for the „ACRU Continuind Education“ Project addressing the following items:
• WBS with brief description of each activity
• PERT diagram• Budget