2. project 2: ventilation effectiveness advanced … … · c-331 11 doors closed, transfer grills...
TRANSCRIPT
![Page 1: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/1.jpg)
C-326
2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED SYSTEM RESEARCH
2.1 Executive Summary
Overview
Key Results
![Page 2: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/2.jpg)
C-327
Gate Status
1. Source Energy Savings and Whole Building Benefits (“must meet”)
2. Performance-Based Code Approval (“must meet”)
3. Prescriptive-Based Code Approval (“should meet”)
4. Cost Advantage (“should meet”)
5. Reliability Advantage (“should meet”)
6. Manufacturer/Supplier/Builder Commitment (“should meet”)
![Page 3: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/3.jpg)
C-328
7. Gaps Analysis (“should meet”)
Conclusions
![Page 4: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/4.jpg)
C-329
2.2 Sacramento Tracer Gas Testing
2.2.1. Description of House
Figure 2.1: Floor plan of the house tested
Figure 2.2: Front elevation of the house tested
![Page 5: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/5.jpg)
C-330
2.2.2. Description of Test Method
2.2.3. Test Performed
Table 2.1: List of tracer gas tests
Test Number Description
CFIS Tests With Mixing (All have AHU 20 min off/10 min on)
1 Doors Closed, Transfer Grills Open, 95% of the 62.2 Ventilation Rate*
2 Doors Closed, Transfer Grills Open, 60% of the 62.2 Ventilation Rate
3 Doors Closed, Transfer Grills Open, 33% of the 62.2 Ventilation Rate
4 Doors Closed, Transfer Grills Closed, 60% of the 62.2 Ventilation Rate
Laundry Exhaust Tests With Mixing (All at 100% of the 62.2 ventilation rate)
5 Doors Closed, Transfer Grills Open, AHU 20 min off/10 min on
6 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on
7 Doors Closed, Transfer Grills Closed, AHU 25 min off/5 min on
Laundry Exhaust Tests Without Mixing (All at 100% of the 62.2 ventilation rate)
8 Doors Open, Transfer Grills Open
9 Doors Closed, Transfer Grills Open
10 Doors Closed, Transfer Grills Closed
Master Bathroom Exhaust Tests With Mixing (All at 100% of the 62.2 ventilation rate)
![Page 6: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/6.jpg)
C-331
11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on
Master Bathroom Exhaust Tests Without Mixing (All at 100% of the 62.2 ventilation rate)
12 Doors Closed, Transfer Grills Open
13 Doors Closed, Transfer Grills Closed
Natural Infiltration Tests (No ventilation or AHU operation)
14 Doors Open, Transfer Grills Open
Air Handler Bump Tests (No ventilation, AHU on)
15 Doors Open, Transfer Grills Open
16 Doors Closed, Transfer Grills Open
17 Doors Closed, Transfer Grills Closed
*Test 1 was 95% instead of 100% of the 62.2 ventilation rate due to hardware limitations.
2.2.4. Results
Figure 2.3: Tracer gas measurement results for Test 1 (exhaust from laundry room)
![Page 7: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/7.jpg)
C-332
Figure 2.4: Tracer gas measurement results for Test 3 (CFIS)
2.2.5. Conclusions
2.3 Calibration of First Model
2.3.1. Introduction to CONTAM
2.3.2. Testing of Substitute House
![Page 8: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/8.jpg)
C-333
2.3.3. Calibration Procedure
![Page 9: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/9.jpg)
C-334
2.3.4. Calibration Results
Figure 2.5: Comparison of results for the laundry exhaust test without mixing (test 1)
![Page 10: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/10.jpg)
C-335
Figure 2.6: Comparison of measured results for the CFIS test (test 3)
Figure 2.7: Comparison of results for the laundry exhaust test with mixing (test 6)
![Page 11: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/11.jpg)
C-336
Figure 2.8: Comparison of results for the master bathroom exhaust test without mixing (test 15)
2.3.5. Use of Calibrated Model for Other Ventilation Systems
![Page 12: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/12.jpg)
C-337
Figure 2.10: Indoor and outdoor temperatures used in extension cases
Figure 2.11: Extension case—exhaust ventilation without central AHU
![Page 13: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/13.jpg)
C-338
Figure 2.12: Extension case—supply ventilation without central AHU
Figure 2.13: Extension case—exhaust ventilation with central AHU and standard thermostat
![Page 14: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/14.jpg)
C-339
Figure 2.14: Extension case—exhaust ventilation with central AHU and minimum run timer
Figure 2.15: Extension case—CFIS ventilation with minimum run timer
![Page 15: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/15.jpg)
C-340
Figure 2.16: Extension case—balanced ventilation system without AHU
Figure 2.17: Establishing the reference decay rate using the exhaust ventilation system without and AHU
![Page 16: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/16.jpg)
C-341
Figure 2.18: Comparison of reference decay rate with decay rates of house with balanced ventilation at 100% of the 62.2 rate
Figure 2.19: Comparison of reference decay rate with decay rates of house with balanced ventilation at 50% of the 62.2 rate
![Page 17: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/17.jpg)
C-342
2.4 ASHRAE Meeting—January 2007, Dallas
2.4.1. Building America Expert Meeting
2.4.2. SSPC 62.2 Meeting
![Page 18: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/18.jpg)
C-343
2.5 Preparation for First Round of Simulations
2.5.1. Weather Files
2.5.2. Schedule Files
2.5.3. AC Sizes
2.5.4. CONTAM Automation Tools
![Page 19: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/19.jpg)
C-344
2.5.5. Post-Processing Tools
2.6 First Round of Simulations
2.6.1. Model Description
![Page 20: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/20.jpg)
C-345
Figure 2.20: CONTAM layour during the first round of simulations
2.6.2. Parameters Varied
2.6.2.1. Presence and location of central system
2.6.2.2. Duct leakage
2.6.2.3. AHU operation
2.6.2.4. Enclosure leakage
2.6.2.5. Ventilation system
![Page 21: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/21.jpg)
C-346
2.6.2.6. Ventilation rate
2.6.2.7. Climate
2.6.3. Occupant Exposure as Metric Comparison
2.6.4. Post-Processing
2.6.5. Results
System Type Range Approximate Median
Fully ducted balanced ventilation system, with or without central duct system
1.0 1.0
Non-fully ducted balanced ventilation, with central duct system, and central air handler unit controlled to a minimum runtime of at least 10 minutes per hour
0.9 to 1.1 1.0
Supply ventilation, with central duct system, and central air handler unit controlled to a minimum runtime of at least 10 minutes per hour
1.1 to 1.7 1.25
![Page 22: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/22.jpg)
C-347
Exhaust ventilation, with central duct system, and central air handler unit controlled to a minimum runtime of at least 10 minutes per hour
1.1 to 1.9 1.25
Exhaust ventilation, with central duct system, and central air handler unit not controlled to a minimum runtime of at least 10 minutes per hour
1.0 to 1.8 1.5
Supply ventilation, without central duct system 1.4 to 1.9 1.75
Exhaust ventilation, without central duct system 1.3 to 2.6 2.0
2.7 ASHRAE Meeting—June 2007, Long Beach
2.7.1. Building America Expert Meeting
2.7.2. SSPC 62.2 Meeting
2.8 Second Round of Simulations
2.8.1. Changes from Previous Modeling
![Page 23: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/23.jpg)
C-348
2.8.2. Model Description
2.8.3. Parameters Varied
2.8.3.1. Presence of central system
2.8.3.2. Duct leakage
2.8.3.3. AHU operation
2.8.3.4. Enclosure leakage
2.8.3.5. Ventilation system
2.8.3.6. Ventilation rate
2.8.3.7. Climate
2.8.4. Exposure Calculation Method and Scenarios
![Page 24: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/24.jpg)
C-349
2.8.5. Post-Processing
2.8.6. Results
Table 2.2: Comparison of BSC and LBL results for Everybody Everywhere case
![Page 25: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/25.jpg)
C-350
Table 2.3: Comparison of BSC and LBL results for Volume Weighted Sources case
Table 2.4: Comparison of BSC and LBL results for Worst-Case Age-of-Air case
![Page 26: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/26.jpg)
C-351
Table 2.5: Comparison of BSC and LBL results for I Stink case
Figure 2.6: Comparison of BSC and LBL results for You Stink case
![Page 27: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/27.jpg)
C-352
Figure 2.21: Difference between 1X and 2X Manual J sizing
![Page 28: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/28.jpg)
C-353
Figure 2.22: Effect of climate on yearly average exposure
Figure 2.23: Effect of central system on yearly average exposure
![Page 29: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/29.jpg)
C-354
Figure 2.24: Effect of duct location and leakage level on yearly average exposure
![Page 30: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/30.jpg)
C-355
Figure 2.25: Effect of minimum runtime on yearly average exposure
Figure 2.26: Effect of envelope leakage rate on yearly average exposure
2.9 ASHRAE Meeting – January 2008 – New York City
2.9.1. Building America Expert Meeting
2.9.2. SSPC 62.2 Meeting
![Page 31: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/31.jpg)
C-356
2.10 Third Round of Simulations
2.10.1. Model Description
![Page 32: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/32.jpg)
C-357
Figure 2.27: CONTAM model layout with added zones
2.10.2. Parameters Varied
2.10.2.1. Presence of central system
2.10.2.2. AHU operation
2.10.2.3. Enclosure leakage
2.10.2.4. Ventilation system
2.10.2.5. Ventilation rate
![Page 33: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/33.jpg)
C-358
2.10.2.6. Climate
2.10.3. Exposure Scenarios
2.10.4. Post Processing
![Page 34: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/34.jpg)
C-359
2.10.5. Results
Figure 2.28: System coefficients for 3.5 ach50 enclosure, exposure scenario 1
Figure 2.29: System coefficients for 3.5 ach50 enclosure, exposure scenario 2
![Page 35: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/35.jpg)
C-360
Figure 2.30: System coefficients for 3.5 ach50 enclosure, exposure scenario 3
Figure 2.31: System coefficients for 3.5 ach50 enclosure, exposure scenario 3
![Page 36: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/36.jpg)
C-361
![Page 37: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/37.jpg)
C-362
Table 2.7: System coefficients for 3.5 ach50 enclosure, exposure scenario 1
With AHU Ventilation type
Ventilation ducting
With Min Turnover
Without Min Turnover
Without AHU
fully ducted 1.35 1.65 1.65 Supply
not fully ducted 1.35 1.65 1.65
fully ducted 1.65 2 2 Exhaust
not fully ducted 1.65 2 2
fully ducted 1 1 1 Balanced
not fully ducted 1 1.35 1.35
Table 2.8: System coefficients for 3.5 ach50 enclosure, exposure scenario 3
With AHU Ventilation
type Ventilation ducting With Min
Turnover Without Min
Turnover
Without AHU
fully ducted 1.65 2 2 Supply
not fully ducted 2 2 2
fully ducted 1.35 1.65 1.65 Exhaust
not fully ducted 2 2 2
fully ducted 1.35 1.35 1.35
fully ducted + exhaust in wet rooms 1 1 1
Balanced
not fully ducted 1.35 1.65 2
2.11 ASHRAE Meeting – June 2008 – Salt Lake City
2.11.1. SSPC 62.2 Committee Meeting
2.12 Fourth Round of Simulations
![Page 38: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/38.jpg)
C-363
2.12.1. Model Description
2.12.2. Parameters Varied
2.12.3. Exposure Scenarios
![Page 39: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/39.jpg)
C-364
2.12.4. Post Processing
2.12.5. Results
Figure 2.32: System coefficients for 3.5 ach50 enclosure, exposure scenario 5
![Page 40: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/40.jpg)
C-365
Figure 2.33: System coefficients for 3.5 ach50 enclosure, exposure scenario 6
Table 2.9: System coefficients for 3.5 ach50 enclosure, exposure scenario 5
With AHU Ventilation type Ventilation ducting
With Min Turnover Without Min
Turnover
Without AHU
fully ducted 1 1 1 Supply
not fully ducted 1 1.35 1.65
fully ducted 1 1.65 2 Exhaust
not fully ducted 1 2 2
fully ducted 1 1 1.35 Balanced
not fully ducted 1 2 2
Table 2.10: System coefficients for 3.5 ach50 enclosure, exposure scenario 6
With AHU Ventilation type Ventilation ducting
With Min Turnover Without Min
Turnover
Without AHU
fully ducted 1 1.35 1.35 Supply
not fully ducted 1 1.35 1.65
fully ducted 1.35 2 2 Exhaust
not fully ducted 1.35 2 2
fully ducted 1 1 1.35 Balanced
not fully ducted 1 1.65 2
![Page 41: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/41.jpg)
C-366
2.12.6. Sensitivity Analysis
Table 2.11: Pollutant source cases for sensitivity study
Scenario 1 3 5 6 7 8 9 10 11 12
Volume Weighted 100 0 0 50 40 30 50 50 33 20
Kitchens & Baths Only 0 100 0 0 10 20 10 20 33 20
Occupants Only 0 0 100 50 50 50 40 30 33 60
![Page 42: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/42.jpg)
C-367
Table 2.12: System coefficients for 3.5 ach50 enclosure, exposure scenario 7
With AHU Ventilation type Ventilation ducting
With Min Turnover Without Min
Turnover
Without AHU
fully ducted 1 1.35 1.35 Supply
not fully ducted 1 1.35 1.65
fully ducted 1.35 1.65 2 Exhaust
not fully ducted 1.35 2 2
fully ducted 1 1 1.35 Balanced
not fully ducted 1 1.65 2
Table 2.13: System coefficients for 3.5 ach50 enclosure, exposure scenario 8
With AHU Ventilation type Ventilation ducting
With Min Turnover Without Min
Turnover
Without AHU
fully ducted 1 1.35 1.35 Supply
not fully ducted 1 1.35 1.65
fully ducted 1 1.65 2 Exhaust
not fully ducted 1.35 2 2
fully ducted 1 1 1.35 Balanced
not fully ducted 1 1.65 2
Table 2.14: System coefficients for 3.5 ach50 enclosure, exposure scenario 9
With AHU Ventilation type Ventilation ducting
With Min Turnover Without Min
Turnover
Without AHU
fully ducted 1 1.35 1.35 Supply
not fully ducted 1 1.35 1.65
fully ducted 1.35 1.65 2 Exhaust
not fully ducted 1.35 2 2
fully ducted 1 1 1.35 Balanced
not fully ducted 1 1.65 2
Table 2.15: System coefficients for 3.5 ach50 enclosure, exposure scenario 10
With AHU Ventilation type Ventilation ducting
With Min Turnover Without Min
Turnover
Without AHU
fully ducted 1 1.35 1.35 Supply
not fully ducted 1.35 1.65 1.65
fully ducted 1.35 1.65 2 Exhaust
not fully ducted 1.35 2 2
fully ducted 1 1 1 Balanced
not fully ducted 1 1.65 2
![Page 43: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/43.jpg)
C-368
Table 2.16: System coefficients for 3.5 ach50 enclosure, exposure scenario 11
With AHU Ventilation type Ventilation ducting
With Min Turnover Without Min
Turnover
Without AHU
fully ducted 1 1.35 1.35 Supply
not fully ducted 1.35 1.65 1.65
fully ducted 1.35 1.65 2 Exhaust
not fully ducted 1.35 2 2
fully ducted 1 1 1 Balanced
not fully ducted 1 1.65 2
Table 2.17: System coefficients for 3.5 ach50 enclosure, exposure scenario 12
With AHU Ventilation type Ventilation ducting
With Min Turnover Without Min
Turnover
Without AHU
fully ducted 1 1 1.35 Supply
not fully ducted 1 1.35 1.65
fully ducted 1 2 2 Exhaust
not fully ducted 1 2 2
fully ducted 1 1 1.35 Balanced
not fully ducted 1 2 2
2.13 ASHRAE Meeting – January 2009 – Chicago
2.13.1. Building America Expert Meeting
2.13.2. SSPC 62.2 Committee Meeting
2.14 Post January 2009 meeting
2.14.1. Rescaling Coefficient Range
![Page 44: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/44.jpg)
C-369
Figure 2.34: Example illustration of the process of rescaling the coefficients
2.14.2. Average Exposures Instead of Highest Occupant Exposures
Figure 2.35: Results of average exposure analysis for volume-weighted source scenarios
![Page 45: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/45.jpg)
C-370
Figure 2.36: Results of average exposure analysis for kitchen & bathrooms source scenarios
Figure 2.37: Results of average exposure analysis for occupant-generated source scenario
2.15 ASHRAE Meeting – June 2009 – Louisville
2.15.1. SSPC 62.2 Committee Meeting
![Page 46: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/46.jpg)
C-371
2.15.2. Presentation of Technical Papers
2.16 Post June 2009 Meeting
2.16.1. Progress and current status of change proposal
2.17 References
![Page 47: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/47.jpg)
C-372
![Page 48: 2. PROJECT 2: VENTILATION EFFECTIVENESS ADVANCED … … · C-331 11 Doors Closed, Transfer Grills Open, AHU 25 min off/5 min on Master Bathroom Exhaust Tests Without Mixing (All](https://reader034.vdocument.in/reader034/viewer/2022043017/5f39d5b7588e7f04e4747de6/html5/thumbnails/48.jpg)
C-373
2.18 APPENDICES
2.18.1. Substitute House Testing Trip Report
2.18.2. January 2007 Expert Meeting Summary Report
2.18.3. June 2007 Expert Meeting Summary Report
2.18.4. January 2008 Expert Meeting Summary Report
2.18.5. January 2009 Expert Meeting Summary Report
2.18.6. 2009 ASHRAE Transactions 11, Paper #1 Presentation
2.18.7. 2009 ASHRAE Transactions 12, Paper #2 Presentation