2008-2009 hydrogen design contest: green buildings with ... contest submission 0… · adrienne...

41
2008-2009 Hydrogen Design Contest: Green Buildings with Hydrogen Mark Estill Student Centre University of Waterloo December 19, 2008 Faculty Advisor: Dr. Michael Fowler Team Members Rob Enouy Tim Pasche Andrea Murphy Chris Rea Adrienne Nelson Ankit Sharma Neal Tanaka

Upload: others

Post on 15-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

i

2008-2009 Hydrogen Design Contest: Green Buildings with Hydrogen

Mark Estill Student Centre

University of Waterloo

December 19, 2008

Faculty Advisor:

Dr. Michael Fowler

Team Members

Rob Enouy Tim Pasche

Andrea Murphy Chris Rea

Adrienne Nelson Ankit Sharma

Neal Tanaka

Page 2: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

ii

Executive Summary

The following design illustrates a fully implementable 76,000 ft2 Mark Estill student centre at

Farmingdale, N.Y. with an environmentally conscious building design with renewable

technology in order to mitigate dependence on carbon fuels. The renewable energy sources

consist of photovoltaic cells, wind turbines, biomass harvesting and reduced consumption

through energy efficient design. System design will allow excess energy from renewable

resources to produce hydrogen gas from an electrolyser. The hydrogen gas is used as a storage

medium, such that it may be converted back into usable electricity via a Proton Exchange

Membrane Fuel Cell (PEMFC), or used as transportation fuel for vehicles.

Hydrogen is generated via electrolysis at a rate of 5.2 kWh/Nm3. Produced hydrogen must be

pressurized in a storage vessel to be used at a later date. During peak hours when the renewable

resources cannot meet load demands, the stored hydrogen can be processed in a 130kW PEMFC

to produce a supplementary source of energy for the centre. This flexibility allows for grid draw

at peak hours to be completely eliminated, which reduces the overall costs of operations for the

student life centre.

Photovoltaic cells comprise the southward facing roof area of 23,548 ft2 to maximize solar gain

and are capable of generating 70kW at peak hours during the summer months. Wind turbines

will be erected around the outside of the building and are capable of generating 40 kW at peak

hours during the high wind months. The biomass system will collect food-waste throughout the

campus and return it to a process by which the biodegradable substances are passed through an

accelerated decomposition process to produce combustible gases that can be converted into 30

kW of electricity via a Stirling engine.

A geothermal system will be installed in conjunction with a small natural gas furnace in order to

meet the thermal demands of the building. The geothermal has the ability to produce 70% of the

building‟s max heat draw and can be powered by renewable resource energy production during

peak hours. The supplementary gas furnace is required for the months of November, December,

and January when the geothermal system is insufficient to meet heating demands.

Reinforced insulation in the exterior walls and roof will reduce the energy losses to surrounding

and thereby reduce the overall energy requirements of the building. North facing portions of the

roof will be lined with two layers of the most energy efficient windows available in order to

allow for indirect sunlight during the day without incurring a large energy loss. Also by using a

state of the art ventilation system, it is possible to maximize the return off of the heat energy

produced by the geothermal system.

The costs of the student life centre construction and materials were obtained from RS Means and

applied to this specific project. These costs can be considered accurate within 10% of actual

costs for the summer of 2009. The building designs are laid out in topographical, section,

elevation, and render plots via AutoCad.

The costs and benefits associated with renewable resources are laid out in detail and an

economic/business plan indicates the feasibility of implementing this project.

Page 3: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

iii

Table of Contents Executive Summary ...................................................................................................................................... ii

1. The Design ............................................................................................................................................ 1

1.1 Building Design ............................................................................................................................ 2

1.1.1 Plumbing Plan ....................................................................................................................... 6

1.1.2 Structural Design Description ............................................................................................... 6

1.1.3 Electrical Loading Details ..................................................................................................... 6

1.2 Solar Design .................................................................................................................................. 6

1.3 Geothermal Design ....................................................................................................................... 8

1.3.1 Calculations ........................................................................................................................... 8

1.4 Windmill Design ........................................................................................................................... 9

1.5 Biomass Design ............................................................................................................................ 9

1.5.1 Anaerobic Digestion ........................................................................................................... 10

1.5.2 Method ................................................................................................................................ 10

1.5.3 Calculations ......................................................................................................................... 11

1.6 Hydrogen Design ........................................................................................................................ 12

2. Safety Analysis ................................................................................................................................... 13

2.1 Geothermal Safety Analysis........................................................................................................ 13

2.2 Hydrogen Safety Analysis .......................................................................................................... 13

2.3 Solar Safety Analysis .................................................................................................................. 13

2.4 Wind Power Safety Analysis ...................................................................................................... 14

2.5 Biogas Safety Concerns .............................................................................................................. 14

2.6 Most Important Safety Concerns ................................................................................................ 15

2.6.1 Electrolyser ......................................................................................................................... 15

2.6.2 Hydrogen Storage Tank ...................................................................................................... 15

2.6.3 Biogas Delivery Lines ......................................................................................................... 15

2.6.4 Proton Exchange Membrane ............................................................................................... 15

3. Economic/Business Plan Analysis ...................................................................................................... 16

3.1 Capital Costs ............................................................................................................................... 16

3.1.1 Construction ........................................................................................................................ 16

3.1.2 Solar .................................................................................................................................... 17

3.1.3 Geothermal .......................................................................................................................... 17

3.1.4 Windmill ............................................................................................................................. 17

Page 4: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

iv

3.1.5 Biomass ............................................................................................................................... 17

3.2 Economic Justifications .............................................................................................................. 18

3.2.1 Insulation ............................................................................................................................. 18

3.2.2 Geothermal .......................................................................................................................... 18

3.2.3 Biomass ............................................................................................................................... 18

3.2.4 Wind & Solar ...................................................................................................................... 19

3.3 Operational Costs ........................................................................................................................ 19

3.4 Life Cycle Analysis ..................................................................................................................... 19

4. Environmental Analysis ...................................................................................................................... 20

4.1 Building Environmental Analysis ............................................................................................... 20

4.2 Geothermal Environmental Analysis .......................................................................................... 21

4.3 Hydrogen Environmental Analysis ............................................................................................. 21

4.4 Energy Efficiency ....................................................................................................................... 21

4.5 Carbon Dioxide Emissions.......................................................................................................... 22

5. Marketing and Education Plan ............................................................................................................ 24

5.1 Target Audience .......................................................................................................................... 24

5.2 Main Objectives .......................................................................................................................... 24

5.3 Key Messages ............................................................................................................................. 24

5.4 Implementation and Continued Education .................................................................................. 25

6.0 References ....................................................................................................................................... 27

Appendix A .................................................................................................................................................. A

Appendix B .................................................................................................................................................. B

Appendix C .................................................................................................................................................. C

Page 5: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

v

Table of Figures Figure 1: Integrated facility energy system overview .................................................................................. 1

Figure 2: Topographical building view ......................................................................................................... 2

Figure 3: Topographical building layout ...................................................................................................... 2

Figure 4: Basement and Second Floor Topographical Layout ...................................................................... 3

Figure 5: Sectional and elevation building layouts ....................................................................................... 3

Figure 6: Southwest Building View………………………………………….……………………………..4

Figure 7: North interior wall facing south into courtyard ............................................................................. 4

Figure 8: Balcony Overlooking the Courtyard ............................................................................................. 5

Figure 9: Southeast Bird‟s Eye View ............................................................................................................ 5

Figure 10: Biomass process flow diagram ................................................................................................. 10

Figure 11: Plumbing and geothermal documentation……………………………………………………...A

Figure 12: Structural calculations ............................................................................................................... B

Page 6: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

vi

List of Tables Table 1: Solar power generation New York, NY .......................................................................................... 7

Table 2: Wind power generation………………….………………………………………………………..9

Table 3: Capital costs ................................................................................................................................. 16

Table 4: Energy efficiency of generating systems ..................................................................................... 22

Table 5: Marketing costs…………………………………………………….…………………………….25

Table 6: Preliminary HAZOP analysis ....................................................................................................... C

Page 7: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

1

1. The Design

The design of the Mark Estill Student Life centre is composed of a ground level containing a

cafeteria, offices, lounges, and a courtyard; a second story containing a radio broadcasting area,

study rooms, offices, a patio, and a courtyard; and a basement level housing a bookstore, an art

gallery, as well as the mechanical systems of the building. The combined floor space is

calculated to be 76,000 ft2, with a footprint of 40,000 ft

2. The Java City building was demolished

in order to make adequate room for the Mark Estill Student Life centre.

Energy will be generated using a combination of solar, wind, and biomass renewable resources.

Geothermal systems will also being utilized to heat the building. An electrolyser will be used to

generate hydrogen from excess energy produced by the renewable energy systems. The stored

hydrogen will then be used to power the building when electricity generation cannot meet

demand and to fuel a campus hydrogen powered vehicle. Intelligent window placement in the

exterior walls and roof will allow for indirect lighting during daylight hours, which will likely

decrease the electrical load significantly during the day.

For an overview of the power systems see Figure 1 .

Figure 1: Integrated facility energy system overview

Page 8: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

2

1.1 Building Design

The layouts and floor plans for the building can be found in the following figures.

Figure 2: Topographical building view

Figure 3: Topographical building layout

Page 9: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

3

Figure 4: Basement and Second Floor Topographical Layout

Figure 5: Sectional and elevation building layouts

Page 10: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

4

Figure 6: Southwest Building View

Figure 7: North interior wall facing south into courtyard

Page 11: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

5

Figure 8: Balcony Overlooking the Courtyard

Figure 9: Southeast Bird’s Eye View

Page 12: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

6

1.1.1 Plumbing Plan

The plumbing layout can be found in Appendix A. The Geothermal piping for space heating

throughout the facility appears within the plumbing layout. A value of $0.45 per square foot was

used to estimate the cost of the plumbing system (RSMeans, 2004). This resulted in an estimate

of $33,225.

1.1.2 Structural Design Description

The structural design for the facility is based primarily on the principle of redundancy through

repeated elements, which would be mass-produced and erected in series to speed construction

thus controlling both construction and maintenance costs. The structural system consists of

hollow structural steel (HSS) columns on concrete footings or concrete foundations, supporting

W-flange steel beams with open web steel joists. Slabs are corrugated steel deck with a

reinforced concrete topping. The roof structure is fabricated steel trusses with open web steel

joists supporting corrugated steel deck. On the north face of the sloped roofs, the trusses support

beams at the top and bottom of the pitch on which vertically oriented open web steel joists

support sloping glazing units. See Appendix for sizing calculations.

1.1.3 Electrical Loading Details

The electrical loading of the building was estimated using a figure of 10.4 kWh per square foot

per year (Energy Information Administration, 2003). This figure represents the total amount of

electricity consumed in a non-mall building and does not incorporate the electrical load of the

kitchen. The electrical loading is based on the assumption that the contract company responsible

for kitchen services will draw their electricity demand directly from the grid. Multiplying by the

area of the building, the overall electrical load was determined to be 900,000 kWh/year on

average. The electrical energy required to heat the building was determined to be 74,295

kWh/year. This was calculated by determining the heat required to maintain the building at a

specific temperature, followed by the equivalent amount of electricity required to produce 70%

of that heat from a geothermal source. Several case studies demonstrate that it is more

economical to use geothermal heat for approximately 70% of the heating requirement and

supplement the remaining 30% with a natural gas furnace (Cane, 2000, and Energy Services,

2008).

1.2 Solar Design

A solar cell array was chosen that uses a constant angle of elevation, which minimizes capital

and maintenance costs. The choice of elevation angle for solar cells is of the utmost importance

as this determines the angle at which the sun's radiation will strike the solar array at the peak

production time. The majority of solar radiation is collected at midday and so the elevation

should be selected so that throughout the duration of the year the average midday solar radiation

is perpendicular to the solar array. Due to the characteristics of the sun's path through the sky the

horizontal angle selected for the aforementioned criteria is equal to the latitude at which the solar

array will be located (Lasnier, 1990). In this circumstance this angle will be approximately

40.75 degrees, i.e., the latitude of Farmingdale, NY (Google Maps).

Solar power is generated through the collection of solar radiation and thus the amount of

electricity generated by the solar array will be equivalent to the amount of solar radiation

collected and the efficiency of the array. The amount of solar radiation that is received upon a

surface at 40.75 degrees is available in a table of solar insolation for New York, NY, the closest

Page 13: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

7

city. This data takes into consideration all mitigating effects such as weather. These can be

found in (Whitlock, 2000).

Owing to the fact that solar cells are never perfectly efficient in their conversion of solar energy

to electricity the concept of peak power must be implemented to simplify calculations. Peak

power is the amount of power generated by a square metre of solar cells exposed to 1000 Watts

per square metre of solar light (Solarbuzz, LLC, 2008). A conversion can be made between the

solar radiation and the electricity generated by the solar cells. This data is also presented in

Table 1.

Table 1: Solar power generation New York, NY

Month Solar Radiation

[kWh/sqm day]

Electricity Generation

[kWh/kWp day]

Power Generated

During Day[kW]

Sunlight per Day

[hour]

January 1.67 1.2533 37.17 7.41

February 2.37 1.7787 46.7 8.37

March 3.41 2.5592 58.21 9.67

April 3.93 2.9495 58.67 11.05

May 5.11 3.8351 68.89 12.24

June 5.48 4.1127 70.30 12.86

July 5.26 3.9476 68.78 12.62

August 5.01 3.7600 71.13 11.62

September 4.05 3.0395 64.96 10.29

October 2.85 2.1389 52.83 8.9

November 1.82 1.3659 38.87 7.73

December 1.4 1.0507 32.39 7.13

Peak power is a useful base point for the design of this system as it can account for the total area

taken up by solar modules on the roof space available and will also aid in the calculation of

costs. The calculation for total amount of roof space will be calculated for the solar cells. In this

application it is desired for all solar cell surfaces to be exposed to solar radiation at all high

points in the year. The lowest angle of elevation that the sun rises to is 15 degrees less than the

latitude (Komp, 1981), in this application that will be 25.75 degrees. In addition, the roof space

available for solar cells has an angle of elevation of 18 degrees. Now the total available area of

solar modules can be calculated from the available roof space and trigonometric calculations

using the above data. This results in the relationship:

Therefore, the total installed area of solar modules is 1649 square metres from the fact that 2187

square metres of roof space is available.

Page 14: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

8

The standard area per kilowatt peak is known to be 7 square metres of active photovoltaic area

(South Facing, 2006). In the calculations to consider the amount of roof space required the solar

modules will be considered to have a length of 1 metre in the direction of elevation, a typical

industrial size. With this knowledge is possible to calculate the total peak power installed on the

roof. This is found to be 219.8 kilowatts peak.

Knowing the total peak power installed it will be desired to know the amount of electricity

generated at various points in the year. Since the solar insolation tables are given in values

averages over an entire day, this will have to be recalculated into power during the productive

solar hours. The number of hours of sunlight in a particular day can be calculated with what is

referred to as the sunrise equation (Watts) and the twilight hours have been subtracted as they do

not provide direct sunlight to the solar modules. Using the data generated through the sunrise

equation, the solar insolation tables and the total peak power installed it is possible to calculate

the average power generated through solar radiation at various points of the year and the total

number of productive hours. This data can be found in .

1.3 Geothermal Design

Geothermal system is a flameless, combustion free method of providing the heating and cooling

energy required for a commercial building. The only energy input into the system is the electrical

energy required to run the heat pumps and ground loop fluid circulating pumps. This energy is

being produced by using on site renewable resources such as biomass, wind and solar energy.

Each unit of electrical energy into the system provides on average 3-4 times the conventional

equivalent heating/cooling energy to the building by using ground source heat pumps in

conjunction with the earth loop. The environmental impacts associated with the geothermal

technology are minimized due to the heat pump‟s high operating efficiency. According to the US

Environmental Protection Agency (EPA), geothermal systems are the most energy-efficient,

environmentally friendly as well as cost effective space conditioning systems available

(GeoExchange). Discuss merits of vertical closed loop geothermal piping.

1.3.1 Calculations

The calculations were based on the amount of energy required to either heat or cool the building.

All months of the year on average except June, July, and August were found to require heating.

The amount of electricity required to heat the building was calculated by converting the amount

of heat lost through the building exterior into an equivalent electrical load.

The geothermal system was sized to provide 70% of the maximum heat loss from the building,

which was calculated to be approximately 65,000 kWh/month. With a standard heat pump size

of 12,000 kWh/month (Cane, 2002), it was determined that five parallel heat pumps are required.

Based on a value of 100 meters per 2500 kWh/month (Cane, 2002), the length of pipe required

was determined to be 1800 meters. This length of pipe will require approximately 75 bore holes,

each containing 30 meters of vertical piping. An estimated 500 meters of extra piping was also

incorporated into the calculations to account for the piping throughout the building. Based on the

length of pipe and the coefficient of performance realized by the geothermal system, the amount

of energy required to operate the system per month was determined. Based on friction losses

through the piping system it was determined that a 15 horsepower pump would be sufficient and

would require an average of 50,000 kWh/year. The heat pump energy required was determined

to be an average of 20,000 kWh/year.

Page 15: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

9

1.4 Windmill Design

Wind power generated is proportional to the cube of the velocity of wind. Therefore, if the total

amount of power contributed by wind is to be calculated the data for the wind velocities in

Farmingdale, NY is required. This data is presented in Table 2 (City Data, 2008).

The wind turbine that will be employed in this application is not unidirectional, that is it swivels

in the direction of the wind, and therefore, the wind direction is not important in this application.

This windmill will be provided by Wind Turbine Industries (Sagrillo, 2007).

Wind generators will typically bring little power production when used in the small scale but

they provide a valuable source of power during the evening hours when solar generation will not

occur and will also provide educational demonstration. As such, a small number, ten, of wind

turbines were selected to be installed. These wind turbines will be installed outside the building

at a short distance to minimize the amount of wiring required to deliver the power to the

building.

Wind turbines will typically convert wind to power along a cubic function and thus a cubic

equation should be fit to the power production profile as given by the manufacturer (Sagrillo,

2007). After fitting this wind data to a curve the total amount of power generated can be

calculated on a monthly basis. This data can be found in Table 2.

Table 2: Wind power generation

Month Wind Velocity [mph] Power Produced [kW]

January 11.5 32.92

February 12.0 37.31

March 12.2 39.21

April 12.0 37.31

May 11.0 28.89

June 10.1 22.37

July 9.5 18.62

August 9.0 15.73

September 9.0 15.73

October 9.8 20.38

November 10.6 25.78

December 11.1 29.61

1.5 Biomass Design

Another method of energy production is the use of „biogas‟. To obtain biogas, food waste

produced on campus can be used as a feedstock for an anaerobic digester. The biogas produced

is composed mainly of methane and carbon dioxide gas (University of Adelaide, 2008). By

combusting the biogas for use inside an engine, the potential energy housed within the food

waste is converted to electrical energy for use within the student life centre; this provides

valuable electrical energy a peek demand periods or at night. See Figure 10 on next page for

visual.

Page 16: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

10

Figure 10: Biomass process flow diagram

1.5.1 Anaerobic Digestion

Anaerobic digestion refers to the decomposition of organic matter by bacteria in the absence of

oxygen. It is widely used to treat wastewater and organic wastes. It is useful because the bacteria

reduce the volume and mass of the waste, while producing biogas at the same time (Monsal,

2008).

The actual process of anaerobic digestion is separated into three separate steps. The first is

hydrolysis. In this step, enzymes produced by hydrolytic bacteria break down and liquefy

insoluble organic polymers such as carbohydrates, cellulose, proteins and fats. The second step is

acetogenesis. This involves converting organic acids formed in the hydrolysis stage to acetic acid

by acetogenic micro-organisms. The final step is called methanogenesis, which involves the

conversion of the acetic acid to methane. This is facilitated by methanogenic bacteria (Residua,

2008).

1.5.2 Method

Food waste will be collected from the campus and taken to a storage area in the basement of the

student life centre. Having separate waste bins for food waste and proper advertisement will

ensure that a maximum amount of food waste collection will be achieved.

Before the waste can be digested, it needs to be processed. The first step is to shred the waste.

This is done for two reasons. The first is that it aids in the removal of objects like plastic bags.

The second reason is that it increases the available surface area for bacteria attachment. This

promotes the hydrolysis step of biodigestion (University of Southampton, Greenfinch Ltd, 2008).

In the next step, the waste is put through a drum screen that removes things like plastic bags.

This is done because some plastics, such as polyethylene, have been shown to reduce biogas

production (Muthuswamay, 1990). Once the waste has finished passing through the drum screen,

it goes through a magnetic separator to remove any ferric objects in the waste like bottle caps.

This is done because iron has been shown to inhibit biogas production (Jackson-Moss, 1990).

Page 17: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

11

The energy expended to prepare the waste is generally 5% of the work produced at the end of the

process (CADDET Centre for Renewable Energy, 1998). Once waste has been adequately

prepared, it is sent to a holding tank.

The prepared waste is then sent to the anaerobic digesters. The digesters are separated into two

different tanks. The first is the acetogenesis reactor, which is where both hydrolysis and

acetogenesis take place. A skimmer would also be present to remove lighter objects like

Styrofoam. The second tank is the methanogenesis tank. This is where methanogenesis takes

place. The reason a two-phase reactor setup was chosen is because it takes advantage of the

faster rate of production of the acetogenesis bacteria, which allows for a lower tank volume and

because it is a relatively fast rate process (Burke, 2001). The waste streams from the reactors are

sent to a dehydrator where the water is removed and the solids are sent to a composter where the

waste is converted to compost.

The biogas stream that results from the methanogenesis reactor is sent to a gas holding tank. The

biogas is then sent to the combustion chamber inside a 40kW Stirling engine. Inside the Stirling

engine, the biogas is combusted and produces heat. This heat creates a temperature differential

between two different piston chambers. The temperature differential and momentum drive the

two pistons inside the Stirling engine, producing work. The work is then converted to electrical

power (Haywood). The reason a Stirling engine was chosen is because of its high efficiency and

relatively low noise levels. Most importantly there is no requirement to „clean‟ or further dry the

biogas prior to combustion which is energy and maintenance intensive. A continuous combustion

process will also be used to supply heat; therefore, most types of emissions associated with a

non-continuous conventional combustion engine can be reduced (Lund Institute of Technology,

2004).

The process will take place in the basement of the building. A visual depiction of the space

allotted for the process can be found in the floor plan presented.

1.5.3 Calculations

Based on the amount of food waste produced per day, the amount of work produced from the

Stirling engine was calculated to be approximately 30 kilowatts. This was accomplished by

converting the food waste into an equivalent amount of biogas based on what real biodigestors

accomplish. The amount of food waste was estimated to be approximately 1000 lbs/day. This

was estimated by multiplying the amount of food waste generated per person as determined by

the US EPA by the population at SUNY, followed by a factor of 0.3 (EPA, 2008). The factor of

0.3 was used because to account for students who do not eat on campus. Based on these

numbers, the average student would be wasting approximately 330 grams or food each day. A

conversion rate for degradable waste to biogas of 73 % was used, based on results seen in

industry (CADDET Centre for Renewable Energy, 1998). Since biogas is generally considered to

contain approximately 55% methane, the amount of heat generated from burning it can be

calculated using the heat of combustion (U.S. Department of Energy, 2005). Thus, the amount of

heat provided was found to be 964,000 kWh/year. When multiplied by an engine efficiency of

30% (ACEEE, 2004), 33 kilowatts is the resultant electrical power. When the power used to

operate the equipment is subtracted, the final value is 263,000 kWh/year.

Page 18: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

12

1.6 Hydrogen Design

The design, see figure 1 for an overview of all the components, of the fuel cell includes a proton

exchange membrane based on the versatility and functionality in comparison to other types of

fuel cells, due to the range of operating temperature and feed fuels. Operation of such a system

would require feeds of hydrogen to complete the anodic reaction and a feed of air with the

oxygen present forming the cathodic reaction. The building load was determined to be 900,000

kWh/year (Energy Information Administration, 2003). The power production of the fuel cell was

sized at 130 kW or 115,000 kWh/year, meeting the building requirements with a 15% safety

factor.

Utilization of such a system can be deemed by having surplus power from building requirements

routed to the electrolyser for the generation of hydrogen gas. In the event of a power deficit,

power can be supplied by oxidizing hydrogen gas in a fuel cell to meet demands. Power response

from the systems may be slightly delayed as response times from power draw may exceed fuel

cell production. At these times it will be necessary to draw power from the grid in order to

facilitate an uninterrupted continuous operation. The operation of the fuel cell should match

production as the amount of draw increases. The energy produced from renewable sources in the

day achieves an excess over power requirements, allowing the conversion of H2O into hydrogen.

Power production at night is significantly lower from the renewable sources; however, the cost

associated with purchasing electricity at night time is also lower (Long Island Power Authority,

2008). Based on this lower cost of electricity at night, it was found to be more economical to

utilize hydrogen power during times of peak electricity demand in the grid, as opposed to using

the hydrogen supply as required.

The electrolyser, HyStat-60 sourced from Hydrogenics, is capable of producing peak production

of 60 Nm3/h with an available conversion rate of 5.2 kW/Nm

3 (Hydrogenics, 2008) at pressures

of up to 1000 kPag (10 barg). Oxygen produced in the formation of hydrogen gas can be utilized

for complete combustion of the biogas.

Compressed gas is the method of choice for the size of system due to the requirements of time

delivery, energy input for storage, and environmental friendly concerns. Once produced, the

compressed hydrogen gas will be routed to a storage vessel. Hydrogen storage within the vessel

will be available up to 5000 psi, which correlates to 53,500 moles of H2. Current calculations

have shown that a tank volume of 5 m3 will be sufficient for the best energy economic operating

scenario. Typically peak energy costs occur at the same frequency as peak production of

renewable sources; as such, hydrogen will be mainly consumed in winter months when solar

power production is lower. Hydrogen from the stored tank will also be available for the operation

of the hydrogen vehicle. When hydrogen provision to the operation of such a vehicle exceeds the

power production that is available, electricity at night could be utilized to provide hydrogen at

lower costs.

Page 19: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

13

2. Safety Analysis

2.1 Geothermal Safety Analysis

Safety for building and occupants is greatly improved by adapting to a geothermal system due to

the lack of flame heating (Collins, 2002). A safety concern associated with the geothermal

system is the possibility of a system leak. Since the ground piping will be connected to each

ground source heat pump (which will be located throughout the building), the possibility of a

leak through these pipes represents a safety concern. The heat transfer fluid in these pipes will be

a 50% ethylene glycol solution which can be harmful if it is in contact with the skin, swallowed,

or inhaled (Oxford University). In order to ensure that all piping is adequate to handle the

pressures applied, all piping and equipment will be pressure tested upon construction for one

hour at 100 psig (Collins, 2002).

2.2 Hydrogen Safety Analysis

Public safety concerns are utmost important for the growth, development and acceptance of a

hydrogen economy. Remediation of risks associated with the operations of hydrogen is

paramount to the sociable acceptance of such technology and infrastructure. Hydrogen itself

presents concerns of flammability, asphyxiation (Oxygen Deficient Environment), metal

embrittlement and compressed gases hazards.

Hydrogen flammability can occur with specific concentrations of hydrogen oxygen mixtures and

exposure to ignition source. Hydrogen has a lower ignition point then other carbon burning fuel

sources. Hydrogen rapidly diffusive into other gases making a flammable vapour ratio unable to

obtained in a well ventilated environment. Most occurrences of a hydrogen leak will cause a

flame velocity too high to be sustained, as such a leak fire is hard to maintain, but does present in

other hazards. Safety standards call for fuel cells installed indoors call upon many different

standards such as ASME, ANSI, IEEE, UL and NFPA. For example, NFPA 853 calls items such

as the fuel cell to be installed behind 1 hour fire resistant rating walls.

Oxygen deficient environments can lead to asphyxiation due to the low levels of oxygen

concentration in the air. Oxygen levels when starting to decrease can lead to headaches,

dizziness, fatigue and even death. Due to the hazards that these pose, proper ventilation is vital in

order to remediate these risks. Proper ventilation will also prevent the flammable air to hydrogen

gas mixture to be achieved.

Embrittlement of the metal may lead to effects causing rupture or pressure loss failure modes due

to the weakening of storage containment and delivery methods. Hydrogen embrittlement may be

avoided by the correct choice of materials. Piping and storage vessels should all follow

corresponding codes for the correct choice of materials to prevent structural failures.

Compressed gases pose a hazard due to the energy of release that it posses, hydrogen in an

uncontrolled release can harm people and damage property and render the building uses. Respect

to the transportation and storage of the hydrogen shall conform to standards such as those listed

before.

2.3 Solar Safety Analysis

A broken module will have consequences of broken glass being on the roof. No people will be

on the roof, excepting maintenance personnel, so this poses more an environmental risk to

Page 20: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

14

wildlife that may land on the roof. The likelihood of this event is relatively low and can be

mitigated by regular inspection of the solar modules by maintenance personnel.

Fraying electrical work will have the consequences of possible electrical shock to personnel on

the roof or, again, wildlife. Since the modules are not in motion the electrical fray would solely

be a result of weather conditions in the outdoors. Therefore, the electrical wiring that will run

from the solar module itself to the building's electrical system should be protected by conduits

which will prevent exposure of the insulation or wiring to the elements.

2.4 Wind Power Safety Analysis

There are few safety concerns associated with the operation of wind mills. The most pressing is

the possibility of strong bursts of wind accompanied with a malfunctioning braking system.

Excessive rotation could apply forces on the blades such that their structural integrity is

compromised and they break. This can result in scattered metallic debris. This can be offset by

regular inspection of the braking system by maintenance personnel. The windmills that are

being examined offer manufacturer warranties on the braking system for multiple years (Sagrillo,

2007), indicating that malfunctioning braking systems are a rarity. In addition the braking

system will be able to detect the forces on the blades and as such will prevent operation in a

circumstance such as a large amount of ice being frozen onto the blades.

A second concern with windmills is the actual noise and light flicker created by their rotation. In

typical applications the windmill will be elevated to such a level that at maximum rotation the

windmill will only produce ground level noise of approximately 50 decibels. This is well within

acceptable levels of exposure.

A final concern for the operation of the windmill is the fraying of the electrical work just as for

solar modules. Likewise, the electrical work after the turbine is only subject to environmental

stresses and should therefore be enclosed in conduit to protect the wiring from the elements. The

electrical components housed within the turbine itself are covered under warranty and can be

detected through poor energy production. Additionally, because the components are housed

within an enclosure, the effect of poor wiring within the turbine has been mitigated to a degree.

2.5 Biogas Safety Concerns

The shredder, drum separator, evaporator, Stirling engine, and magnetic separator are all pieces

of mechanical equipment with moving parts. As such, they need to be safeguarded so that an

operator will not accidentally injure themselves while working with or inspecting the equipment.

A lock out/tag out procedure will be implemented to ensure that the machines will not be running

while they are being serviced or cleaned.

The acetogenesis and methanogenesis tanks will be operating at atmospheric temperature;

therefore, the risks of explosion and buckling under pressure are minimized. To ensure that an

explosion or buckling does not occur in the event of a pressure build up or loss, pressure relief

valves will be installed and thick tank walls will be used. Since the off gas will be composed

mainly of methane, the gas will be sent to a tank instead of being vented to the atmosphere.

Alarm systems will trigger when the pressure relief system is activated and the process feed will

be halted. An operator will also perform regular pressure checks.

Page 21: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

15

2.6 Most Important Safety Concerns

In determining what the most pressing safety concerns were, an introductory hazard and

operability study was performed. This can be found in Appendix C.

2.6.1 Electrolyser

The possibility of a leak of hydrogen into the hydrogen room may lead to asphyxiation and

flammable environments. Inherent safety design can be approached by making sure that the

pressure of hydrogen supply and delivery is not at pressures in excess of operation of the fuel

cell. Active safety design consideration can be to make sure that there are minimal places that the

hydrogen can leak in delivery and supply lines. Installation of piping should conform to codes

with safety allowance for overpressure protection. Active controls can be implemented by

making sure that there is always adequate ventilation to the atmosphere preventing an

environment where either asphyxiation or a flammable environment may be achieved. The rapid

diffusion of hydrogen in air promotes such a system. Fire suppression systems should be

included. Gas detection should also be included as well as monitoring of pressure drops across

the system. Procedural controls can be implemented as well routine pressure checks of the

system would help determine if any leaks are present and checking gas monitoring and

ventilation systems so that they are always in correct working order.

2.6.2 Hydrogen Storage Tank

The hydrogen storage tank has been identified as a high public safety risk. Safety considerations

can be implemented in such a system in order to prevent unnecessary injury, loss of life or

property. Controls can be implemented such as pressure monitoring systems and procedural

pressure checks to confirm that no leaks are present. Hydrogen combustion presents with no

visible flame and as such if a leak from the hydrogen storage tank where to occur to visual

indication of such would not be present. In order to provide adequate safety considerations heat

sensors around the tank and gas analyzers could be operated to monitor the possibility of release

and combustion. Pressure relief systems should be in place in case such a system malfunctions

and over pressure occurs.

2.6.3 Biogas Delivery Lines

Based on the hazard and operability risk calculations, a leak in the biogas delivery lines poses a

major public safety concern. The reason for this is the release of biogas into the building.

Methane is listed as extremely flammable, explosive, and as an asphyxiant. The lower explosive

limit of 5% in air; therefore, extreme caution must be used in the event of a biogas leak (BOC

Gases, 1996). To mitigate this risk, we will install heat sensors and methane sensors to detect a

leak or a flame. A fire suppression system will also be installed. An automatic shutoff of the

process will occur if a leak or flame is detected. The enclosure room will also be fire proofed

according to NFPA standards. Frequent inspection of the pipe lines will also be done to ensure

that there are no leaks.

2.6.4 Proton Exchange Membrane

The operation and design of the fuel cell has been identified in the HAZOP to have a high public

safety concerns with the possibility of leaks around the flow of hydrogen. Safety design can be

implanted around the system as identified in the electrolyser systems. These mainly include

proper ventilation and air exchange systems, correct pressure rating of supply lines, procedural

pressure checks, and gas detection for a flammable environment or leaking. Additional controls

for such a system should be pressure relief in the case of overpressure.

Page 22: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

16

3. Economic/Business Plan Analysis

3.1 Capital Costs

Table 3: Capital costs

Categories Cost 2009 on Long Island Demolition $637,207.54

Basement $2,173,443.67

Ground Floor $3,742,271.80

Second Floor $1,459,787.14

Roof $1,212,305.85

Solar & Wind $2,293,413.69

Geothermal $1,632,249.22

Biomass $148,540.84

Hydrogen System $1,390,000.00

Insulation $3,311,757.42

Marketing $6,704.25

Landscaping $2,000,000.00

Total Project $20,007,681.41

Renewable Energy Operations $170,529.90

Building Maintenance $429,390.42

Yearly Cost Savings $48,646.16

3.1.1 Construction

The construction costs attributed to the Mark Estill Student life centre were determined using RS

Means costing data. RS Means collects data from major construction sites across the United

States and Canada to produce accurate costing information for any given year. Costs were

broken down into materials and labour costs for each building section and required demolition.

RS Means resources provide location indices across North America. Long Island is listed as

126.4, which means that to build on the island it requires a 26.4% cost increase as compared to

the average location across the continent. The inflation index is not provided by RS Means and

was conservatively estimated to be 4% per year. Taking a base year of 2004, the inflation

indices from 2004-2009 and 2007-2009 were calculated to be 116.99 and 108.16, respectively

(RSMeans, 2004). All cost data presented refers to the year 2009.

To properly construct the student life center for maximum benefit and to ensure a safe and timely

construction process, the location referred to Java City must be demolished. Demolition costs

were estimated with RS Means resources and include rubbish disposal, long haul, and

destruction of a two storey building. The overall demolition costs were determined to be

$637,207.

Costs associated with architecture fees and overhead & profit were approximated with a case

study of a similar two storey student union in the RS Means catalogue. The case study suggests

that architecture and overhead & profit comprise 7% and 25% (RSMeans, 2004) of overall

construction costs, respectively and were applied as such. The architecture fees and overhead &

profit costs associated were determined to be $520,779 and $1,859,928.

Page 23: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

17

By design, it is possible to reduce installation and labour costs by using materials that can be

easily assembled and pre-fabricated. Build-ability, as it is commonly referred to, is a modern

method of cost savings and can reduce installation and labour costs by an average of 7% (Smith,

2007). These savings were applied to the overall installation of materials and are responsible for

reducing costs by $120,313.

By applying the inflation and location indices to the overall construction costs, renewable

technologies, architecture fees and overhead & profit, the overall cost for construction and

implementation of this project was determined to be $20,007,681.

3.1.2 Solar

Solar modules are typically priced based on the peak power that is desired to be installed.

Complete installation costs are typically around $6,710 per kilowatt peak for an installation of

this size near this location (New Jersey Clean Energy, 2007). This cost is the final consumer

payment for the solar modules including all labour included in the installation. With knowledge

of the peak power installed as discussed in Section 1.0, the total cost of the solar modules will be

$1,475,410.

3.1.3 Geothermal

Several case studies were analyzed in order to estimate the initial capital costs associated with

the entire installed HVAC geothermal system (heat pumps, circulating pumps, piping, fluid,

ground loop setup). To account for the affect of inflation, consumer price indexes for a variety of

years have been used (Bureau of Labor Statistics). These sites have been carefully chosen due to

their close resemblance to the climate data for Farmingdale, New York (Oregon Institute of

Technology). In the year 2007, there were approximately 2,890°F heating degree days (HDD)

and 442°F cooling degree days for Farmingdale using a base of 18°C. The initial capital cost for

the installed geothermal system will be estimated using the adjusted 2008 cost per square metre.

Using three case studies (The H.W. Wilson Company, 2005), (Chiasson, 2005), (Chiasson,

Murray High School: Geo-Heat Center, 2005) at a similar climate, the adjusted costs per square

metre were found to be $170.83, $182.18, and $188.99. The average of these was used to predict

a cost of $180.67 per square metre. The fixed capital investment of the geothermal system was

determined to be $1,632,249.

3.1.4 Windmill

Installed costs for the windmill that was selected were given by the manufacturer of the

windmill. The totaled installed cost of a windmill installation is $33,900 (Sagrillo, 2007).

Knowing the total number of windmills to be installed as discussed in Design, the total cost of

windmills installed will be $339,000.

3.1.5 Biomass

The cost of the biomass system excluding the Stirling engine was calculated using cost data from

industrial systems. The initial cost for a biomass plant using similar systems in Korea in 1997

was estimated to be below $125,000 per tonne/day for plants with a capacity of over 15

tonnes/day (CADDET Centre for Renewable Energy, 1998). The system used in the design of

the student life centre is estimated to be 0.5 tonnes/day. Since the larger systems incorporate

more technology, it was assumed that the $125,000 per tonne/day would be an appropriate rough

estimate and potentially take into account any costs that were neglected. The cost of the Stirling

Page 24: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

18

engine was estimated using a price of $1,000/kW (ACEEE, 2004). Therefore, for a 40 kW

Stirling engine, the cost is $40,000. By summing the costs and multiplying by the location factor

and inflation index ratios, the costs were determined to be approximately $160,424.

3.2 Economic Justifications

The student life centre design attempts to provide all electrical demand through harnessing

renewable resources, but the associated systems will require regular maintenance, repairs, and

monthly safety inspections. Based on the calculations of energy production, the building will

produce more electricity than it requires during the all months of the year with the exception of

January, November, and December. This excess production can be used to produce hydrogen,

which will be stored and used to generate electricity via fuel cell in the winter months. Most

energy stored in hydrogen will be drawn during peak hours of the winter months to completely

reduce grid power dependency during peak hours.

3.2.1 Insulation

The insulation was increased above the recommended R-values for insulation of a building in

New York State in order to reduce heat loss incurred. The exterior wall insulation was doubled

and polycarbonate 16 mm triple panes were installed for the ceiling and exterior wall windows.

Ceiling windows provide indirect lighting during sunlight hours to reduce electricity costs but

increase heat loss values, therefore windows in series were used in order to increase their overall

resistance to heat transfer. The overall cost of insulation including ceiling windows was

determined to be $3,311,757. As a result of the excess insulation, a cost of $1,888,339 was

realized (RSMeans, 2006). These additional expenses will reduce the equivalent emission from

5000 kg CO2/day for having to heat the less insulated building with a high efficiency gas

furnace. The insulation reduced the yearly heating flow to/from the environment from 740,000

kWh/year to 306,000 kWh/year.

3.2.2 Geothermal

The geothermal system provides an efficient and environmentally friendly method for heating a

building and draws its entire load from renewable resource power production. To determine the

cost and emission savings of a geothermal system it was compared to the cost and emissions

associated with using a high efficiency gas furnace for the heavily insulated student centre. A

geothermal system contributing 70% of max heat requirements will produce 306,000 kWh/year

with an electrical input of 75,000 kWh/year. The supplementary gas furnace will on average

produce 7 kg CO2/day and cost approximately $2000/year in natural gas. The equivalent cost

and emissions of a well insulated building heated 100% by an efficient gas furnace were

determined to be $14,000/year in natural gas costs (National Grid, 2008) and an average of 180

kg CO2/day, respectively.

3.2.3 Biomass

The biomass system collects biodegradable food waste and produces methane to be used in a

Stirling engine. The electricity produced by the biomass reactor and Stirling engine was

determined to be approximately 263,000kWh/year. The yearly operating costs of this system will

likely be 5% of the fixed capital investment and amounts to $7,427 (CADDET Centre for

Renewable Energy, 1998). Another economic benefit is the reduced waste transferred to a land-

fill site as they typically charge a tipping fee. Based on a landfill tipping fee of $70.53/ton (Repa,

2005), using biomass as a fuel would produce savings of approximately $12,000 a year.

Page 25: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

19

3.2.4 Wind & Solar

Based on local solar data, the solar cells will be responsible for approximately 220,000 kWh/year

renewable productions. Based on local wind data, the wind turbines are expected to produce

236,000 kWh/year.

3.3 Operational Costs

The electricity demand for the building was greatly reduced by the introduction of extra layers of

insulation. When supplemented with a geothermal system to heat the building, the overall

electricity draw was reduced to 940,000 kWh/year. In general, geothermal systems are designed

for 70% of max heating requirements of a building in order to reduce initial capital costs. In this

case, a high efficiency gas furnace will be used to supplement the heat draw during the cold

winter months. The natural gas required by this furnace will amount to $2,090/year (National

Grid, 2008) and produce 27 kg CO2/day during its three months of operation.

The kitchen area for resident and commuter dining will require an average of 300kW to seat

greater than 500 students for three meals a day (Webb, 2003). The renewable resources do not

have the ability to provide surplus power to the hydrogen system while sustaining the kitchen.

As such, the power required by the kitchen will be drawn directly from the grid. By locating an

electricity meter for the kitchen load, the electricity costs associated can be directly charged to

the contract company providing kitchen services.

Water consumption will comprise approximately 1,500m3/year for the biomass system and 9,000

m3/year (Rheem, 2007) for the kitchen services at a yearly cost of $11,990. The kitchen will also

require 4,000 m3/year of hot water. A tank-less gas-fire water heating system will be

implemented to ensure a constant supply of hot water that will produce approximately 140 kg

CO2 in emissions at a cost of $11,000/year. The natural gas water heaters are capable of using

bio-mass methane to reduce the net emissions of the building.

The building will require regular maintenance in the form of cleaning services, safety

inspections, general systems repairs, control systems maintenance, and maintenance salaries. A

general rule of thumb for large-scale commercial buildings is that operations and maintenance

costs will be 5% of its fixed capital investment (Chalmers University of Technology, 2001).

Based on this approximation the operations and maintenance costs for the building will be

$429,390. Other potential expenses may be incurred during unexpected breakdowns in the form

of specialty labour and replacement parts and lost energy production causing a draw from the

grid.

3.4 Life Cycle Analysis

The costs and benefits associated with renewable resource, geothermal, and the hydrogen storage

systems will not stray considerably with appropriate attention to maintenance and detail. The

PEM membranes have to be changes periodically, but otherwise the hydrogen system is fairly

robust. The solar cells may begin to lose solar conversion on the order of 1% per year after the

fifth year of operation. The wind turbines will require occasional maintenance and provide the

greatest possibility for a large investment due to an unexpected failure. The biomass system has

high operating and maintenance costs, and if standard industry techniques are realized it should

not differ greatly from its original state

Page 26: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

20

4. Environmental Analysis

4.1 Building Environmental Analysis

The student centre has been designed to respond directly to its site on the SUNY Farmingdale

campus in Long Island, New York. This simple first step of orientation has an environmental

impact upon the facility through solar heat gain and heat loss as well as daylight access to

interior spaces affecting lighting use. Using the given location, the building has been oriented to

face south in order to maximize the amount of solar access to roof-mounted photovoltaic arrays.

Each façade responds to its orientation in the quantity and size of glazing, for example, the east

and west facades are limited in their window quantities due to the uncontrollable nature of the

solar gain from the morning and afternoon sun resulting in over-heating or high-glare lighting

situations. The south facing concrete wall on the north boundary of the courtyard would be

ample thermal mass to collect and store solar heat to slowly give it off during the cooler hours,

working in both winter and summer conditions to temper the climate of the courtyard space.

The north-facing skylights, although they are a heat-loss outlet at night, create a great deal of

daylight throughout the public spaces of the facility, which in turn would require less electric

lighting during daylight hours. During the evening and night time hours of operation, all lighting

within the building would be designed to fall within the building perimeter to stop light

pollution, which is a potential problem with 24-hour facilities like a student facility.

Being beside the parking lot for commuters, and serving the commuting contingent of students,

the facility would try to encourage carpooling to reduce carbon emissions caused by automobile

use. In addition to encouraging carpooling, students and employees would be able to ride their

bikes to this facility, since there are ample bicycle racks at convenient locations around the

building.

The location of the building has been selected to mainly occupy what was an existing paved

parking lot surface, which means that the student life centre is not negatively affecting the

permeability of the ground surface on the site. Additionally, the vegetated ground cover to the

south east of the facility will allow for storm water runoff to safely percolate through the earth

and be absorbed into the soil instead of being whisked off site in a storm drain, carrying nutrients

and toxins alike with it.

The usage of water within the facility and on the site is of prime importance to the environmental

sustainability of the student life centre. The landscaping on the site would be designed to require

no watering since it will be primarily indigenous species which are hearty enough to survive in

the climate without irrigation. As much as possible within the facility, there would be water-

efficient equipment and fixtures. Between pressurized dishwashing equipment in the kitchens

and dual-flush toilets and efficient faucets in the washrooms, there would be a substantial

savings of potable water use compared to a building of similar occupancy of similar scale.

The environmental impact of a building can include both the facility, as well as the programs that

it encourages. For this reason, in the student life centre, there will be a comprehensive recycling

program which will include collection for metals, glass, paper, and plastics to be recycled at a

local facility, as well as organic waste which will be used in the biomass plant. Recycling will

also be manifested through the use of building materials with a percentage of recycled material

within it, such as the fabricated steel trusses, and the cement fibre board cladding. For materials

Page 27: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

21

that are unable to be made of recycled content, the use of rapidly renewable resources would be

substituted. Examples include numerous fibre-based products supplied by the agricultural

industry and some wood products. Wherever possible, the building materials would be sourced

from local manufacturers or transported by environmentally responsible methods of transit (i.e.

by ship or train as opposed to by truck) to reduce the carbon emissions of bringing the materials

to site.

The quality of a building is largely dependent on the comfort of the interior environment. By

creating a healthy interior environment for the occupants of the student life centre through air

quality and system controls, the facility will have a smaller impact on the greater environment.

The air quality within new facilities is commonly compromised by the volatile organic

compounds (VOCs) within materials that off-gas into the rooms, creating that signature “new”

smell. By using only non-VOC-emitting paints, carpets, and sealants, the student life centre

would help to limit the existence of toxic chemicals in the atmosphere. Other toxins in the air

within the building would be emitted by the biomass plant in the basement. This is a concern

when it comes to the livability of the adjacent rooms, and so there would be airtight seals on all

of the doors and openings into the biomass plant, as well as special attention paid to the partition

walls to ensure their air tightness.

4.2 Geothermal Environmental Analysis

Large scale geothermal power plants have environmental issues such as noise and air pollution,

water quality, land use and impact on wildlife and vegetation although they still operate at higher

efficiencies than conventional power plants. However, the geothermal system being designed for

this project has no direct emissions or noise concerns. The only area of concern is the particular

type of refrigerant used in the ground source heat pumps to transfer energy. Refrigerants have

commonly been known to have an adverse affect on the environment because they deplete the

ozone layer. Over the years older refrigerants, such as R-22, have begun to be phased out and

newer more environmentally friendly refrigerants, such as R-410a, have become widely

available. R-410a is a chlorine-free hydro fluorocarbon (HFC) refrigerant that does not harm the

earth‟s ozone layer.

4.3 Hydrogen Environmental Analysis

The presence of hydrogen release into the atmosphere poses little impact, hydrogen is found in

the atmosphere at low concentrations. The physical characteristics of hydrogen allow for rapid

dispersion making it decrease in concentration rapidly eliminating many impacts. Combustion of

hydrocarbon fuels results in the production of green house gas emissions. The combustion of

hydrogen produces water vapour a clean natural substance.

4.4 Energy Efficiency

The total amount of energy fed to the solar cell and the amount of power generated were both

calculated in Design. From this information the efficiency of the solar modules can be

calculated. This data is presented in Table 4. The loss of energy can be accounted for by

reflection of sunlight off of the module and by some absorption of heat.

The total amount of energy fed to a windmill can be calculated by considering the kinetic energy

delivered to the windmill. The rotor diameter is known to be 9.5 metres (Sagrillo, 2007) and the

density of air is assumed to be 1.2 kilograms per metre cubed. Knowing the velocity of wind and

the power generated, as shown in Table 2, the efficiency of the windmills can be calculated.

Page 28: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

22

This data is presented in Table 4. The loss of energy can be accounted for by the fact that the

wind still has kinetic energy after passing the windmill, the frictional forces within the windmill

and the efficiency of the turbine.

The total amount of energy fed to the biogas system can be calculated by considering the

potential amount of methane fed to the system. Knowing the amount of electricity generated and

the amount of waste fed to the system, the efficiency of the biogas system can be calculated.

This data is presented in Table 4. The loss of energy can be accounted for by the fact that not all

of the waste fed to the system is converted into methane and that the Stirling engine cannot

perfectly convert heat into electricity.

The hydrogen system designed was found to have an efficiency of 45.56% considering the

amount of power supplied to the electrolyser and the amount of electricity generated as the two

points of attention. The tabulated results can be found in Table 4. The loss of energy can be

explained by imperfect losses during the electrolyzing of water and the use of the fuel cell. So

losses will always occur in both of these systems due to heat generation and in the case of the

fuel cell there are losses due to incomplete combustion of hydrogen.

The inverter selected for this operation was found to have an efficiency of 90%. This is shown

in Table 4. The cause for this is due to the loss of heat by the inverter as well as the

fundamentals upon which the inverter changes DC current into AC current to be used in the

building.

Table 4: Energy efficiency of generating systems

Source Energy Input (kW) Electricity Generated

(kW)

Efficiency (%)

Solar/m2 0.147 0.01472 10.01

Wind (per windmill) 4.58665 2.61337841 57

Biogas (overall) 150.68 30 19.9

Hydrogen (per kW in) 1 0.4556 45.56

Inverter (per kW in) 1 0.9 90

4.5 Carbon Dioxide Emissions

One of the systems in the student life centre that will emit carbon dioxide is the biomass system.

When biogas undergoes complete combustion, it produces carbon dioxide and water. In the

absence of complete combustion carbon monoxide is also formed. Other constituents of the

biogas result in minute amounts of sulphur dioxide; however, food waste tends to be low in

sulphur content and therefore sulphur dioxide emissions were taken as negligible (Australian

Institute of Energy, 2004). As a worst case scenario for carbon dioxide emissions, the case of

complete combustion of methane was considered. This assumption is justified by the non-

fluctuating operating conditions of the Stirling engine, as the emissions associated with a

fluctuating fuel intake are minimized (Lund Institute of Technology, 2004). Assuming that the

biogas contains a maximum of 45% carbon dioxide along with the minimum 55% methane

(U.S. Department of Energy, 2005), the calculated amount of carbon dioxide released to the

atmosphere in a day of operation is approximately 480,000 grams. Biomass is generally

considered to be carbon neutral because the carbon dioxide that is released when the biogas is

burned would have been absorbed from the atmosphere during the cycle of growth and harvest of

the organic matter. While this is not necessarily true in all cases due to the energy that goes into

Page 29: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

23

harvesting and transporting the food products, it still results in a decrease in carbon emissions

when compared to conventional fossil fuels (Energy System Research Unit, 2002).

In addition to the biomass system, carbon dioxide will also be emitted due to natural gas use in

the furnace and water heating systems. These will be responsible for an average daily release of

146,859 grams of carbon dioxide.

Therefore, the net daily carbon dioxide emissions will average 626,859 grams of carbon dioxide,

146,859 grams of carbon dioxide if we neglect the biomass emissions as discussed above. If the

building were to have not used geo-thermal and had instead used a furnace of efficiency 90% the

daily emissions would 800,408 grams of carbon dioxide. If the building were to use typical

insulation in addition to the previous change the average daily emissions of carbon dioxide

would be 1,053,492 grams. The difference between these figures and the current emissions do

not account for the additional reductions in carbon dioxide emissions due to use of renewables

instead of grid power.

Page 30: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

24

5. Marketing and Education Plan

In order to ease fears and apprehensions that the general public has towards new technologies, it

is the job of those who are properly education and know the facts to educate on the advantages of

the new technologies and re-assure them of their efficiency, safety and ability to reliably replace

existing systems. An important part of creating acceptance for hydrogen power as well as other

non-commercial or relatively new forms of power production is the way in which you reach the

public and the specific message that you relay. The following is a description of our target

audience, the specific messages we want to portray and how we will go about getting that

message out.

5.1 Target Audience

The marketing and education plan will be two-fold, designed to penetrate two distinct segments

of the population based on their relationship with the project. The first group consists of those

who will be in continuous contact with the student centre, mainly the students and staff of

Farmingdale Campus. The second group consists of the general population, specifically those in

the community of Farmingdale New York. Both groups will need to be assured of the safety and

reliability of the new technologies being employed in the student centre for both Hydrogen as

well as the other renewable energy sources. Information sessions and public consultation will be

held for staff, students and the general community to indicate how their daily routines will be

changed with new technology.

5.2 Main Objectives

The most important objective to address with this marketing campaign is to increase acceptance

of hydrogen fuel technologies on the campus and in the community at large. To effectively

increase acceptance among people it will be a priority to ensure that they feel safe with the

technology. This will require reference to the safety features included in the hydrogen system on

site in any detailed literature dispersed. In addition to increasing acceptance, knowledge of

hydrogen systems should be advanced in the community. People will only be truly excited about

new programs if they understand what they are all about and therefore any small increase in

technical knowledge will increase the individual's understanding of the importance of advancing

hydrogen and renewable energy technologies.

The next objective with the marketing campaign will be to ensure that the campus community is

aware of the composting program that will be part of the biogas system. In order to properly

power the building to design specifications most campus compost must be collected. This can

only be properly done if the students, staff and faculty are aware of the program and have

accepted it as important. Therefore, this portion of the campaign must include technical

education to convince people and a description of the compost program so that they can become

involved.

5.3 Key Messages

As mentioned above, the most important message will be the safety of hydrogen technologies.

This will not only address the student centre itself but should also hydrogen technologies as a

whole. Only when safety assurance can be supplied will people be convinced of the importance

of the remainder of the program.

The second key message will be the environmental progressiveness of the building itself. This

will require education in each subsystem of the student centre, especially with regards to how

Page 31: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

25

much each subsystem will reduce carbon emissions. Further addressing the reduction of carbon

emissions will be demonstration that these technologies are sustainable long term. That is, after

marketing the public should be convinced that these technologies will be able to provide

adequate power for years to come.

5.4 Implementation and Continued Education

The initial marketing blitz announcing the Student Centre, trying to help educate the public and

get them on board with the idea of alternative energies will begin during the construction phase

of the building. People will be curious as to what the new student centre will be like and the

marketing and education should begin to help ease people into the idea of Hydrogen and other

alternative energy sources. The first wave of advertising will occur as construction commences

and is to include full page advertisements in the school, local and regional newspapers as well as

posters throughout the Farmingdale campus and information brochures. The second wave of

marketing will happen one week prior to the building opening and include the Compost Cards.

Advertisements will be constructed and published in the school as well as in the community

newspaper. Posters will also be put up around the SUNY campus including the Farmingdale

campus. A brochure will also be made that outlines the advantages of using renewable energies

to reduce dependence on fossil fuels. Each new technology will be outlined briefly and short

descriptions of benefits as well as safety and reliability will be included. The brochure will be

aimed at educating people with a bit more of the details and facts behind renewable energy

technologies and their use in our design.

Table 5: Marketing costs

Dimensions Numbers Cost ($)

Posters 58” X 40” 20 1,293.80

20” X 14” 50 858.50

Brochures 5.5” X 8.5” 100,000 1,937.22

Compost Cards 4” X 6” 100,000 2,066.11

6” X 11” 100 48.62

Ad Space Varying 3 newspapers 500.00

TOTAL: 6,704.25

In order for the biomass reactor to be used most efficiently on campus, we are proposing a

campus-wide compost system. The system will be used to separate usable organic compound

(i.e. food waste and paper/cardboard) from that which cannot be digested in the bioreactor

(mostly plastics, Styrofoam, metals and other synthetics). The compost cards will be sent out to

all students and staff at the university informing them of the new system. The cards, in slightly

larger form, will also be located in key areas (restaurants, cafeterias, coffee shops, etc.) where

most of the organic waste can be collected. There will also be signs on the garbage cans

outlining what CAN and CANNOT be placed in the Biomass waste bins.

Page 32: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

26

Page 33: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

27

6.0 References

ACEEE. (2004). Emerging Technologies & Practices. Washington, DC: ACEEE.

Australian Institute of Energy. (2004). Fact Sheet 8: Biomass. Retrieved December 7, 2008, from

Australian Institute of Energy: http://www.aie.org.au/national/factsheet/FS8_BIOMASS.pdf

BOC Gases. (1996). Methane: Material Safety Data Sheet. Murray Hill, NJ: BOC Gases.

Bungie Studios. (n.d.). Posthumous Mark Estill Artwork. Retrieved December 14, 2008, from

Posthumous Mark Estill Artwork: http://Mark Estill.bungie.org/artwork.html

Bureau de Normalisation du Québec. (2006). Hydrogen Installation Code. Sainte-Foy, QC:

Bureau de Normalisation du Québec.

Bureau of Labor Statistics. (n.d.). U.S. Department of Labor. Retrieved December 12, 2008,

from Consumer Price Index History Table: http://www.bls.gov/cpi

Burgess, W. E. (2004). Ventilation for Control of the Work Environment. Hoboken, NJ: John

Wiley & Sons, Inc.

Burke, D. (2001). Dairy Waste Anaerobic Digestion Handbook. Olympia, WA: Environmental

Energy Company.

CADDET Centre for Renewable Energy. (1998). Food Waste Disposal Using Anaerobic

Digestion. Oxfordshire, UK: CADDET Centre for Renewable Energy.

Cadwallader, L. H. (1999). Safety Issues with Hydrogen as a Vehicle Fuel. Washington, DC:

Department of Energy.

Cane, D. G. (2000). Learning from experiences with Commercial/Institutional Heat Pump

Systems in Cold Climates. Sittard, NL: CADDET.

Casillo, J. (2008, March 4). Long Island Water Corporation. Retrieved December 1, 2008, from

Long Island Water Corporation Rates and Charges:

http://www.amwater.com/files/2008%20Tariff%20for%20Water.pdf

Chalmers University of Technology. (2001). Construction Economics and Organization.

Gothenburg, SW: Chalmers University of Technology.

Chiasson, A. (2005). Canyon View High School: Geo-Heat Center. Cedar City, UT: GHC

Bulletin.

Chiasson, A. (2005). Murray High School: Geo-Heat Center. Salt Lake City, UT: GHC Bulletin.

City Data. (2008). City Data. Retrieved October 10, 2008, from Farmingdale, NY:

http://www.city-data.com/city/Farmingdale-New-York.html

Collins, P. O. (2002). Geothermal Heat Pump Manual. New York, NY, U.S.: New York City

Department of Design and Construction.

Department of Energy. (2001). Standards Committee Activity Updates. Fuel Cell Summit .

Page 34: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

28

Digital Room. (n.d.). Digital Room. Retrieved December 14, 2008, from Digital Poster Printing:

http://www.digitalroom.com

Energy Information Administration. (2003). 2003 CBECS Detailed Tables. Retrieved September

18, 2008, from Commercial Buildings Energy Consumption Survey:

http://www.eia.doe.gov/emeu/cbecs/cbecs2003/detailed_tables_2003/detailed_tables_2003.html#

consumexpen03

Energy Services. (2008). Geothermal Heat Pumps. Lakewood, CO: Western Area Power

Administration.

Energy System Research Unit. (2002). Biomass - Using Anaerobic Digestion. Retrieved

November 14, 2008, from University of Strathclyde:

http://www.esru.strath.ac.uk/EandE/Web_sites/03-04/biomass//background%20info.html

EPA. (2008, November). Municipal Solid Waste Generation, Recycling,and Disposal in the

United States: Facts and Figures for 2007. Retrieved October 26, 2008, from U.S.

Environmental Protection Agency: http://www.epa.gov/osw/nonhaz/municipal/pubs/msw07-

fs.pdf

Fowler, M. (2008, December 4). RE: Fuel Cell and Electrolyzer Costs. (C. Rea, Interviewer)

GeoExchange. (n.d.). GeoExchange. Retrieved December 5, 2008, from GeoExchange Heating

and Cooling Systems: Fascinating Facts:

http://www.geoexchange.org/geothermal/publications/doc_download/17-geoexchange-

fascinating-facts.html

Google Maps. (n.d.). Google Maps. Retrieved October 22, 2008, from SUNY Farmingdale NY:

http://maps.google.ca/maps?f=q&hl=en&geocode=&q=SUNY+Farmingdale+NY&sll=49.89123

5,-97.15369&sspn=42.780056,78.75&ie=UTF8&ll=40.750492,-

73.431029&spn=0.011818,0.019226&z=16&g=SUNY+Farmingdale+NY

Haywood, D. An Introduction to Stirling-Cycle Machines. Canterbury, NZ: University of

Canterbury.

Hou, Y. Z. (2007). The analysis for the efficiency properties of the fuel cell engine. Renewable

Energy , 1175-1186.

Hydrogenics. (2008). HySTAT-60 Hydrogen Generation System. Mississauga, ON: Hydrogenics.

Jackson-Moss, C. D. (1990). The Effect of Iron on Anaerobic Digestion. Biotechnology Letters ,

149-154.

Komp, R. (1981). Practical Photovoltaics. Ann Arbor, MI: Aatec.

Lasnier, F. A. (1990). Photovoltaic Engineering Handbook. New York, NY: Adam Hilger.

Long Island Power Authority. (2008, January 1). Long Island Power Authority. Retrieved

November 25, 2008, from LIPA‟s Common Non-Residential Power Rates:

http://www.lipower.org/pdfs/account/rates_comm.pdf

Page 35: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

29

Lund Institute of Technology. (2004, January 23). Stirling Engine Research. Retrieved

December 2, 2008, from Department of Energy Sciences:

http://www.vok.lth.se/~ce/Research/stirling/stirling_en.htm

Miller, K. (2001). NHA Hydrogen Safety Codes and Standards Activities. 2001 DOE Hydrogen

Program Review. Washington, DC: Department of Energy.

Monsal. (2008, May 1). Monsal Advanced Digestion Technology. Retrieved November 24, 2008,

from Plant and Technology for Anaerobic Digestion:

http://www.monsal.com/pages.asp?ContentID=1

Muthuswamay, S. N. (1990). Effects of Plastics in Anaerobic Digestion of Urban Solid Wastes.

Waste Management and Research , 375-378.

National Grid. (2008, December 1). National Grid. Retrieved December 5, 2008, from Gas Rates

- Eastern NY:

http://rates.nationalgridus.com/servicerate/ny_gasrateEastview.cfm?region=EAST&zipcode=117

72&sdate=01/Dec/2008&edate=31/Dec/2008&serviceclass=SAL_167&leftMenuHighlight=New

York&CFID=932424&CFTOKEN=81571183

New Jersey Clean Energy. (2007). New Jersey Clean Energy. Retrieved October 12, 2008, from

Paid Projects: http://www.njcleanenergy.com/files/file/CORE_Paid_Projects_010408.xls

Oregon Institute of Technology. (n.d.). Geo-Heat Center. Retrieved November 26, 2008, from

Geothermal Direct-Use Case Studies: http://geoheat.oit.edu

Oxford University. (n.d.). Safety Data for Ethylene Glycol. Retrieved December 6, 2008, from

Physical Chemistry at Oxford University: http://msds.chem.ox.ac.uk/ET/ethylene_glycol.html

Repa, E.W. (2005, March). NSWMA‟s 2005 Tip Fee Survey. Retrieved December 14, 2008, from

ISProductions:

http://wastec.isproductions.net/webmodules/webarticles/articlefiles/463-

Tipping%20Fee%20Bulletin%202005.pdf

Residua. (2008). Anaerobic Digestion. Retrieved December 1, 2008, from WASTE:

http://www.waste.nl/content/download/472/3779/file/WB89-

InfoSheet(Anaerobic%20Digestion).pdf

RSMeans. (2006). Building Construction Cost Data. Kingston, MA: RSMeans.

RSMeans. (2004). Square Foot Costs. Kingston, MA: RSMeans.

Sagrillo, M. W. (2007, June). Home Power. Retrieved September 20, 2008, from Wind Turbine

Buyer's Guide: http://www.homepower.com

Smith, J. J. (2007). Building Cost Planning for the Design Team. Liverpool, UK: Elsevier.

Solarbuzz, LLC. (2008). Glossary of Solar Terms S-Z. Retrieved October 22, 2008, from

Solarbuzz: http://www.solarbuzz.com/consumer/Glossary3.htm#W

Page 36: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

30

South Facing. (2006). South Facing Solar Electricity. Retrieved October 30, 2008, from Solar

Electricity Pricing Guide: http://www.south-facing.co.uk/solar-electricity-prices.aspx

The H.W. Wilson Company. (2005). Pipeline Partnership. PublicWorks.

Turner, J. S. (2008). Renewable Hydrogen Production. International Journal of Energy Research

, 379-407.

U.S. Department of Energy. (2005, September 12). How Anaerobic Digestion (Methane

Recovery) Works. Retrieved November 18, 2008, from Energy Efficiency and Renewable

Energy:

http://apps1.eere.energy.gov/consumer/your_workplace/farms_ranches/index.cfm/mytopic=3000

3

University of Adelaide. (2008). University of Adelaide. Retrieved November 15, 2008, from

Beginner's Guide to Biogas: http://www.adelaide.edu.au/biogas/safety/

University of Southampton, Greenfinch Ltd. (2008). Biodigestion of Kitchen Waste. Retrieved

November 13, 2008, from University of Southampton:

http://www.soton.ac.uk/~sunrise/Biodigestion%20final%20report.pdf

Watts, T. (n.d.). Rutgers Physics: Terence Watts. Retrieved November 25, 2008, from Equation

for Time of Sunrise and Simple Evaluation:

http://www.physics.rutgers.edu/~twatts/sunrise/node5.html

Whitlock, C. (2000). Release 3 NASA Sufrace Meteorology and Solar Energy Data Set for

Renewable Energy Industry Use. Rise & Shine 2000, the 26th Annual Conference of the Solar

Energy Society of Canada Inc. and Solar. Halifax, NS.

Page 37: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

A

Appendix A

Figure 11: Plumbing and geothermal documentation

Page 38: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

B

Appendix B

Figure 12: Structural calculations

Page 39: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

C

Appendix C

Table 6: Preliminary HAZOP analysis

Equipment Process

Variable

Mode of

Failure Cause of Failure Effect of Failure

Frequency

of

Occurrence

(1-10)

Severity

(1-10) Risk

Design Remediation

Method

Electrolyser Pressure Low

Leak from pipe,

valve, flange or

tubing

flammability,

asphyxiation 4 9 36

Regular maintenance,

increased ventilation, fire

supression

Hydrogen Storage

Tank Pressure Low

Leak from pipe,

valve, flange or

tubing

flammability,

asphyxiation, low

power production

4 8 32

Increase renewable energy

supply for better energy

production

Biogas Line Flow No/Low

Flow Leak in line release of biogas 3 10 30 Methane sensor, inspection

Biogas Line Pressure Too Low Leak in pipe release of biogas 3 10 30 Methane sensor, inspection

Proton Exchange

Membrane Flow High

Incorrect pressure

regulator setting,

valve setting

explosion, leaking,

excess power

production

3 8 24 Pressure relief, gas

detection, flow monitors,

Proton Exchange

Membrane Pressure Too High

Leak, explosion,

fire, asphyxiation,

incorrect valve

setting, incorrect

pressure regulator

setting

leak, explosion,

high power

production

3 8 24

Hydrogen gas dection, fire

suppression, ventilation,

pressure relief,

maintenance schedule,

operating procedures

Proton Exchange

Membrane Flow

No/Low

Flow

No stored hydrogen,

blockage, valve

setting

low energy

production 3 7 21 Draw power from grid,

Acetogenesis Tank Pressure Too Low Blockage up stream tank buckling 2 10 20 Pressure relief, thick walls

Methanogenesis

Tank Pressure Too Low Blockage up stream tank buckling 2 10 20 Pressure relief, thick walls

Biogas Line Flow Too High High pressure in

tank

pipe rupture,release

of biogas 2 10 20 Pressure relief

Biogas Line Pressure Too High High pressure in

tank

pipe rupture,release

of biogas 2 10 20 Pressure relief

Page 40: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

D

Equipment Process

Variable

Mode of

Failure Cause of Failure Effect of Failure

Frequency

of

Occurrence

(1-10)

Severity

(1-10) Risk

Design Remediation

Method

Acetogenesis Tank Pressure Too High Blockage tank explosion 2 10 20 Pressure relief, thick walls

Proton Exchange

Membrane Pressure Too Low

No stored hydrogen,

blockage, valve

setting

insufficient power, 6 3 18 Grid utilization

Acetogenesis Tank Flow No/Low

Flow

Leak or blockage in

piping

pipe rupture, spill

of waste/acidic

products

3 4 12 Frequent pipe inspection,

use acid resistant material

Methanogenesis

Tank Flow

No/Low

Flow

Leak or blockage in

piping

pipe rupture, spill

of waste/acidic

products

3 4 12 Frequent pipe inspection,

use acid resistant material

Methanogenesis

Tank Pressure Too High Blockage tank explosion 2 6 12 Pressure relief, thick walls

Dehydrator Pressure Too Low Leak release of bacteria 3 4 12 Flow censor, pipe

inspection

Hydrogen Storage

Tank Flow

No/Low

Flow Blockage, leak

loss of hydrogen,

explosion, fire 1 10 10

Flow meter, regular

maintenance schedule, fire

supression, ventilated area

Hydrogen Storage

Tank Flow High Blockage

back flow of

pressure 1 10 10

Check valve, automatic

shut down on electrolyzer

Hydrogen Storage

Tank Pressure Too High

High energy

production tank explosion 1 10 10

Automatic shutdown on

electrolyzer

Solar Module

Wiring Integrity

Frayed

wires Constant abrasion electrocution 2 5 10

Protective conduit on

wiring and periodic wiring

inspection

Wind Mill Wiring Integrity Frayed

wires Constant abrasion electrocution 2 5 10

Protective conduit on

wiring and periodic wiring

inspection

Geothermal

Internal Piping Flow

No/Low

Flow

Leak or blockage in

piping

pipe rupture,

release of hot

water/ethylene

glycol solution

2 5 10 Flow censor, automatic

stop

Page 41: 2008-2009 Hydrogen Design Contest: Green Buildings with ... Contest Submission 0… · Adrienne Nelson Ankit Sharma Neal Tanaka . ii Executive Summary The following design illustrates

E

Equipment Process

Variable

Mode of

Failure Cause of Failure Effect of Failure

Frequency

of

Occurrence

(1-10)

Severity

(1-10) Risk

Design Remediation

Method

Geothermal

Internal Piping Flow High Blockage

pipe rupture,

release of hot

water/ethylene

glycol solution

2 5 10 Pressure relief valve

Electrolyser Pressure Too High Blockage explosion, rupture, 1 9 9

Pressure relief, flow

meters, regular

maintenance schedule

Dehydrator Flow No/Low

Flow Blockage

pipe rupture,

release of bacteria 2 4 8

Flow censor, automatic

stop

Dehydrator Pressure Too High Blockage pipe rupture,

release of bacteria 2 4 8

Pressure gauge, pressure

relief

Electrolyser Flow No/Low

Flow Low energy input low production 8 1 8 None, Inherent

Wind Mill Braking Integrity Malfunction Broken component

excessive blade

speed possibly

destroying blades

1 6 6 Perform regular inspection

on the braking component

Wind Mill Blades Integrity Imbalance Uneven erosion of

blades

destruction of blade

effecting shrapnel 1 6 6

Perform regular inspection

on wind mill blades

Electrolyser Flow High High energy input high production 1 5 5 Increase electrolyser

Solar Cells Integrity Broken

modules

Impact from foreign

object

possible cuts or

other injuries 4 1 4

Periodic inspection of

rooftop

Drum Separator Flow No/Low

Flow

Blockage in

conveyor

possible spill of

waste 1 2 2

Automatic stop when

blocked

Magnetic

Separator Flow

No/Low

Flow

Blockage in

conveyor

possible spill of

waste 1 2 2

Automatic stop when

blocked