2008 western regional gas conference
DESCRIPTION
2008 Western Regional Gas Conference. Update on the Progress of the Pipelines and Informed Planning Alliance (PIPA) Presented by Carl Weimer, Executive Director. Bellingham Tragedy. Pipeline was damaged by 3rd party Damage known but not fixed Valve installed wrong Valve malfunctioned - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/1.jpg)
2008 Western Regional Gas Conference
Update on the Progress of the Pipelines and Informed Planning Alliance (PIPA)
Presented byCarl Weimer, Executive Director
![Page 2: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/2.jpg)
Bellingham Tragedy• Pipeline was
damaged by 3rd party
• Damage known but not fixed
• Valve installed wrong• Valve malfunctioned• SCADA failure• Operator Error• Pipeline burst and
exploded killing 3 youngsters and an entire salmon stream
![Page 3: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/3.jpg)
Mission
The Pipeline Safety Trust promotes fuel transportation safety through education and advocacy, by increasing access to information, and by building partnerships with residents, safety advocates, government, and industry, that result in safer communities and a healthier environment.
![Page 4: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/4.jpg)
Major Initiatives of the Trust
• Working to strengthen rules and regulations• Provide easily accessible, credible information• Independent research and whitepapers• Responding to incidents & issues• Growing a core of involved citizens• Providing opportunities for collaboration
between citizens, pipeline operators, local government, and regulators
![Page 5: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/5.jpg)
The Goal of PIPA
To provide risk informed guidance to local government planners, property owners, developers, pipeline operators, and real estate agents to enhance safety both when new transmission pipelines are proposed for existing communities and when there is a change in land use adjacent to
existing transmission pipelines.
![Page 6: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/6.jpg)
Why is PIPA Important?
![Page 7: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/7.jpg)
![Page 8: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/8.jpg)
![Page 9: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/9.jpg)
![Page 10: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/10.jpg)
![Page 11: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/11.jpg)
![Page 12: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/12.jpg)
![Page 13: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/13.jpg)
How is PIPA Organized?
Steering Committee
Three Task Teams• Protecting Communities• Protecting Pipelines • Communications
Operates by Consensus A horse designed by consensus
![Page 14: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/14.jpg)
Who Is Involved?• 157 participants
![Page 15: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/15.jpg)
What Are the Expected Final Products?
• Report with Best Practices• Implementation Strategy
All Due by end of 2008
![Page 16: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/16.jpg)
Protecting Communities
1. Defining recommended characteristics of land use adjacent to transmission ROW.
2. Using enhanced building codes for structures adjacent to transmission ROW.
3. Simple, risk-informed guidance for 1 and 2 above.4. Model Ordinances, Planning Policies, Regulations,
or State Legislation
![Page 17: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/17.jpg)
Protecting Transmission Pipelines1. Determine if there is consensus on best practices for:
• Incorporating the ROW space in new developments• Defining acceptable land owner uses and activities on ROW.• Ensuring land owners working in the ROW notify operators prior to making changes in land use.• Guiding the specification, acquisition, development, and maintenance of transmission ROW.• Managing and recording land documents (easements, encroachment agreements, retention, recording practices).
2. Develop Guidance, Model Ordinances, Planning Policies, Regulations, or State Legislation for above
3. Review Common Ground Alliance (CGA) Best Practices and one-call system requirements for gaps
![Page 18: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/18.jpg)
Communications1. Determine best practices for fostering early communication
among stakeholders regarding risk-informed planning2. Determine best practices for communicating acceptable uses and
activities on pipeline ROW to land owners and other stakeholders. 3. Determine best practices for real estate disclosure of ROW.4. Determine barriers to effective communication and best practices
for engaging stakeholders.5. Describe benefits of pipeline transportation6. Describe best practices to effectively communicate risk of
pipelines and how risk is managed. 7. Examine possible tie-ins with Common Ground Alliance (CGA) Best
Practices8. Formulate PIPA risk communication plan and design format of
final PIPA work product for all Task Teams.
![Page 19: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/19.jpg)
What Are Some of the Sticky Issues?
![Page 20: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/20.jpg)
New Pipelines vs. Existing Pipelines
• It is nearly impossible to provide guidance about how new development near an existing pipeline ought to be done, without that same argument being used during new pipeline siting efforts.
![Page 21: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/21.jpg)
Setbacks
How close is too close?
Takings?
What about new pipelines?
![Page 22: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/22.jpg)
ConsultationZone
![Page 23: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/23.jpg)
How do we get local government to care?
Too BusyNo Authority
No Funding
No StaffNo Expertise
Not a Priority
![Page 24: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/24.jpg)
Good Communications
![Page 25: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/25.jpg)
Know Your Audience!
![Page 26: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/26.jpg)
Know Your Audience
![Page 27: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/27.jpg)
Know Your Audience
![Page 28: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/28.jpg)
How To Communicate Risk?Chance + Consequence
![Page 29: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/29.jpg)
Implementation vs. Shelfart
If all PIPA accomplishes is a good report providing guidance to local communities this entire effort will have been nearly a complete waste of time
![Page 30: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/30.jpg)
PIPA Demonstration Grants
• 3 grants of $25,000 to local communities to test some of PIPA’s ideas and strategies
![Page 31: 2008 Western Regional Gas Conference](https://reader035.vdocument.in/reader035/viewer/2022070410/56814668550346895db38bdc/html5/thumbnails/31.jpg)
Join Us In NovemberPipeline Safety – What More Needs To Be Done
A conference for all stakeholders
November 20 & 21, 2008Hotel Monteleone, New Orleans