2009/01/09- nrc staff prefiled initial statement of ... · “draft environment impact statement...
TRANSCRIPT
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION
BEFORE THE ATOMIC SAFETY AND LICENSING BOARD
In the Matter of ) ) SOUTHERN NUCLEAR OPERATING CO. ) Docket No. 52-011-ESP ) (Early Site Permit for Vogtle ESP Site) )
NRC STAFF INITIAL STATEMENT OF POSITION
ON JOINT INTERVENORS’ CONTENTIONS EC 1.2, EC 1.3, and EC 6
Patrick A. Moulding Jody C. Martin Sarah. W. Price Counsel for NRC Staff
January 9, 2009
TABLE OF CONTENTS
BACKGROUND ............................................................................................................................1 I. Environmental Contention 1.2...........................................................................................3 II. Environmental Contention 1.3...........................................................................................4 III. Environmental Contention 6.0...........................................................................................5
DISCUSSION................................................................................................................................5
I. Legal and Regulatory Requirements.................................................................................5 II. Witnesses..........................................................................................................................7
A. Staff Witnesses .............................................................................................................7 B. USACE Witnesses ......................................................................................................12
III. The Inadequacies Asserted by the Joint Intervenors’ Contentions Lack Merit. ..............14
A. Contention 1.2.............................................................................................................14
1. Available Information Was Appropriate to Enable Staff’s NEPA Analysis...............15 2. Staff Appropriately Assessed Impacts of Impingement and Entrainment. ..............16 3. Staff’s Analysis Accounts for a Reasonable Range of River Flows. .......................18 4. Staff Appropriately Evaluated Cumulative Impingement and Entrainment
Impacts from the Existing and Proposed Vogtle Units. ...........................................20 5. Staff Adequately Evaluated Thermal Impacts from the Existing and Proposed
Vogtle Units. ............................................................................................................22 6. Conclusion Regarding EC 1.2 .................................................................................26
B. Contention 1.3.............................................................................................................26
1. The Staff’s Analysis of the Dry-Cooling Alternative was Adequate. ........................27 2. The Proposed Design Will Have Only a Small Effect on Extremely Sensitive
Biological Resources...............................................................................................28 3. Conclusion Regarding EC 1.3 .................................................................................29
C. Contention 6................................................................................................................29
1. Potential Dredging of the Federal Navigation Channel is Not Necessary for the
NRC’s Federal Action and is Not a “Connected Action.”.........................................31
- - ii
2. The Staff’s Analysis Was Appropriate Given the Lack of a Formal Dredging
Proposal and the Absence of Project Details. .........................................................34 3. Staff Did Not Consider Upstream Releases For Navigation To Be Necessary or
Reasonably Foreseeable. .......................................................................................37 4. The Staff’s Analysis and Conclusion That Cumulative Impacts Could Be
MODERATE Is Reasonable. ...................................................................................38 5. Conclusion Regarding EC 6 ....................................................................................40
CONCLUSION ............................................................................................................................41
January 9, 2009
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION
BEFORE THE ATOMIC SAFETY AND LICENSING BOARD
In the Matter of ) ) SOUTHERN NUCLEAR OPERATING CO. ) Docket No. 52-011-ESP ) (Early Site Permit for Vogtle ESP Site) )
NRC STAFF INITIAL STATEMENT OF POSITION ON JOINT INTERVENORS’ CONTENTIONS EC 1.2, EC 1.3, and EC 6
Pursuant to 10 C.F.R. §§ 2.337(g)(2) and 2.1207(a)(1), and the Licensing Board’s
Memorandum and Order (Revised General Schedule) (November 13, 2008), the U.S. Nuclear
Regulatory Commission (“NRC”) staff (“Staff”) submits its initial written statement of position
with written testimony and supporting affidavits on the Joint Intervenors’ admitted contentions.1
For the reasons discussed below and in the testimony filed herewith, the Staff submits that the
contentions are without merit and that the Staff’s environmental review, as documented in
NUREG-1872, “Final Environmental Impact Statement for an Early Site Permit (ESP) at the
Vogtle Electric Generating Plant Site,” August 2008 (“FEIS”), complies with the requirements of
the National Environmental Policy Act (“NEPA”).
BACKGROUND
This proceeding concerns the application submitted to the NRC by Southern Nuclear
Operating Company (“Southern” or “Applicant”) for an early site permit (“ESP”). On August 14,
2006, the Applicant submitted an application pursuant to 10 C.F.R. Part 52, Subpart A, in which
1 Joint Intervenors include the Center for a Sustainable Coast, Savannah Riverkeeper, Southern Alliance for Clean Energy, Atlanta Women’s Action for New Directions, and Blue Ridge Environmental Defense League.
- - 2
it requested an ESP for a site within the existing Vogtle Electric Generating Plant (“VEGP”) site
near Waynesboro, Georgia (“Application”). On December 11, 2006, the Joint Intervenors filed a
joint petition for leave to intervene, which contained several contentions challenging the
Environmental Report (“ER”) filed as part of the Application.
On March 12, 2007, the Board ruled on the admissibility of the Joint Intervenors’
proffered contentions. See Southern Nuclear Operating Co. (Early Site Permit for Vogtle ESP
Site), LBP-07-3, 65 NRC 237 (2006). The Board admitted two contentions, EC 1.2 and EC 1.3.
EC 1.2, as admitted, was restated by the Board as follows:
The ER fails to identify and consider direct, indirect, and cumulative impingement/entrainment and chemical and thermal effluent discharge impacts of the proposed cooling system intake and discharge structures on aquatic resources.
Vogtle ESP, LBP-07-3, 65 NRC at 280. EC 1.3, as admitted, was restated by the Board as
follows:
The ER fails to satisfy 10 C.F.R. § 51.45(b)(3) because its analysis of the dry cooling alternative is inadequate to address the appropriateness of a dry cooling system given the presence of extremely sensitive biological resources.
Vogtle ESP, LBP-07-3, 65 NRC at 280.
On August 15, 2007, the Applicant revised its Application to include a request for a
limited work authorization.2 In September 2007, the NRC Staff published NUREG-1872, the
“Draft Environment Impact Statement for an Early Site Permit (ESP) at the Vogtle Electric
Generating Plant Site” (“DEIS”).3 On October 17, 2007, the Applicant filed two motions, seeking
summary disposition of Joint Intervenors’ Contention EC 1.2 and EC 1.3, respectively. On
2 Letter from J.A. “Buzz” Miller to U.S. NRC Document Control Desk, “Southern Nuclear Operating Company Vogtle Early Site Permit Application Supplement to Include Limited Work Authorization 2 Activities” August 15, 2007 (ML072330245).
3 The DEIS was made available to the Board and the parties to this proceeding on September 10, 2007. See Letter from J.M.Rund, NRC Staff Counsel, to Administrative Judges (September 10, 2007).
- - 3
January 15, 2008, the Licensing Board ruled on both motions, finding that summary disposition
was not warranted for either contention. See Southern Nuclear Operating Co. (Early Site Permit
for Vogtle ESP Site), LBP-08-2, 67 NRC 54 (2008); Southern Nuclear Operating Co. (Early Site
Permit for Vogtle ESP Site), LBP-08-3, 67 NRC 85 (2008). In August 2008, the Staff published
its FEIS.4 On September 12, 2008, the Staff notified the Board and Parties of the availability of
Errata to the FEIS. See Letter from Patrick Moulding, Counsel for NRC Staff, to the
Administrative Judges (September 12, 2008).
On September 22, 2008, the Joint Intervenors filed a Motion to Admit a New Contention.
The Staff and Applicant each filed an answer on October 6, 2008. On October 24, 2008, the
Board admitted the new contention as environmental contention 6 (“EC 6.0” or “EC 6”). EC 6.0,
as admitted, was restated by the Board as follows:
Because Army Corps of Engineers (Corps) dredging of the Savannah River Federal navigation channel has potentially significant impacts on the environment, the NRC staff’s conclusion, as set forth in the “Cumulative Impacts” chapter of the FEIS, that such impacts would be moderate is inadequately supported. Additionally, the FEIS fails to address adequately the impacts of the Corps’ upstream reservoir operations as they support navigation, an important aspect of the problem.
See Southern Nuclear Operating Co. (Early Site Permit for Vogtle ESP Site), Memorandum and
Order (Ruling on Motion to Admit New Contention), slip op. at Appendix A (Oct. 24, 2008) (“New
Contention Ruling”).
I. Environmental Contention 1.2
In admitting Contention 1.2 (“EC 1.2”), the Board noted that litigation of the merits of this
contention “may involve the question of the adequacy of the baseline information provided by
SNC relative to the portion of the Savannah River that encompasses the project area
4 The FEIS was made available to the parties and Board on August 14, 2008. See Letter from Patrick Moulding, Counsel for NRC Staff, to the Administrative Judges (August 14, 2008).
- - 4
associated with the intake/discharge structures for both the existing and proposed Vogtle
facilities.” LBP-07-3, 65 NRC at 259.
In ruling on the Applicant’s summary disposition motion, the Board held that with the
exception of the portion relating to chemical discharges, this contention is a contention of
inadequacy – not a contention of omission. LBP-08-2, 67 NRC at 65. The Board went on to
hold that there remained genuine material factual disputes regarding the adequacy of the
baseline aquatic information, the assessment of aquatic organism impingement and entrainment
including in regard to “worst case scenarios” regarding drought conditions, and potential thermal
impacts. Id. at 65-82. However, with regard to chemical discharges, the Board found that EC
1.2 was a contention of omission and that this portion of the contention was now moot. Id. at
82. Consequently, the Board revised Contention 1.2 to read as follows:
The ER fails to identify and adequately consider direct, indirect and cumulative impingement/entrainment and thermal effluent discharge impacts of the proposed cooling system intake and discharge structures on aquatic resources.
Id. at 83-84.
II. Environmental Contention 1.3
Joint Petitioners proffered two bases in support of Contention 1.3 (“EC 1.3”): that the
ER’s discussion of the no-action alternative does not provide an adequate discussion of
economic and environmental benefits, and that the ER discussion of the dry-cooling alternative
and aquatic impacts is insufficient because extremely sensitive biological resources are present.
The Board ruled that only the second basis was admissible. LBP-08-3, 67 NRC at 259-261. In
regard to the second basis, the Board held that the meaning of the term “extremely sensitive
biological resources” and “whether such resources are present are material factual and legal
disputes best resolved in merits litigation regarding this contention.” Id. at 261.
In ruling on the Applicant’s motion for summary disposition, the Board found that
Contention 1.3 was a contention of inadequacy, not a contention of omission. LBP-08-3,
- - 5
67 NRC 96. The Board found that there were still several issues of material fact outstanding;
however, the Board also held that the Joint Intervenors’ argument concerning hybrid cooling
technologies was outside the scope of this contention. Id. at 102-103. Thus, the “Joint
Intervenors will be free to present arguments and evidence regarding the merits of dry cooling
and the impact of a wet cooling system upon ‘extremely sensitive biological resources.’” Id. at
102.
III. Environmental Contention 6.0
In its ruling on the admissibility of Contention 6.0 (“EC 6.0”), the Board specifically
admitted it pursuant to three bases proffered by the Joint Intervenors: bases four, five and
seven. These bases challenge the Staff’s cumulative impacts analysis of dredging the Federal
navigation channel, and the relationship between United States Army Corps of Engineers
(“USACE” or “Corps”) flow regulation and the need for such dredging. New Contention Ruling
at 16-17. The Board found that it was not necessary to address several of the Joint Intervenors’
other proposed bases for EC 6.0 in its admissibility ruling, because the hearing process itself
would provide any requested remedy. Id. at 17. Consequently, the Board revised Contention 6
to read as follows:
Because Army Corps of Engineers (Corps) dredging of the Savannah River Federal navigation channel has potentially significant impacts on the environment, the NRC staff’s conclusion, as set forth in the “Cumulative Impacts” chapter of the FEIS, that such impacts would be moderate is inadequately supported. Additionally, the FEIS fails to address adequately the impacts of the Corps’ upstream reservoir operations as they support navigation, an important aspect of the problem.
Id. at 20.
DISCUSSION
I. Legal and Regulatory Requirements
The contentions at issue in this case all arise under the National Environmental Policy
Act (“NEPA”), and the NRC’s regulations that implement that statute. 42 USC §§ 4321 et seq;
- - 6
10 C.F.R. Part 51. NEPA requires that an agency prepare an Environmental Impact Statement
(EIS) before approving any major Federal action that will significantly affect the quality of the
human environment. 42 U.S.C. Sec. 4332(2)(C).
Under NEPA, the NRC is required to take a “hard look” at the environmental impacts of a
proposed action, as well as reasonable alternatives to that action. See Louisiana Energy
Servs., L.P. (Claiborne Enrichment Center), CLI-98-3, 47 NRC 77, 87-88 (1998). This “hard
look” is tempered by a “rule of reason” that requires agencies to address only impacts that are
reasonably foreseeable – not remote and speculative. See, e.g., Long Island Lighting Co.
(Shoreham Nuclear Power Station, Unit 1), ALAB-156, 6 AEC 831, 836 (1973). “NEPA does
not call for certainty or precision, but an estimate of anticipated (not unduly speculative)
impacts.” Louisiana Energy Servs. (National Enrichment Facility), CLI-05-20, 62 NRC 523, 536
(2005) (emphasis in original). Further, “NEPA gives agencies broad discretion to keep their
inquiries within appropriate and manageable boundaries.” Louisiana Energy Servs., L.P.,
CLI-98-3, 47 NRC at 103.
Generally, an Applicant has the burden of proof in a licensing proceeding. 10 C.F.R.
§ 2.325. In cases involving NEPA contentions, however, the burden shifts to the NRC, because
the NRC, not the Applicant, has the burden of complying with NEPA. See, e.g., Duke Power
Co. (Catawba Nuclear Station, Units 1 & 2), CLI-83-19, 17 NRC 1041, 1049 (1983). However,
because “the Staff, as a practical matter, relies heavily upon the Applicant's ER in preparing the
EIS, should the Applicant become a proponent of a particular challenged position set forth in the
EIS, the Applicant, as such a proponent, also has the burden on that matter.” Louisiana Energy
Servs., L.P. (Claiborne Enrichment Center), LBP-96-25, 44 NRC 331, 338-39 (1996), rev’d on
other grounds by Louisiana Energy Servs., L.P. (Claiborne Enrichment Center) CLI-97-15,
46 NRC 294 (1997), citing Pub. Serv. Co. of New Hampshire (Seabrook Station, Units 1 and 2),
ALAB-471, 7 NRC 477, 489 n.8 (1978).
- - 7
However, in challenging the EIS, intervenors must identify, with some specificity, the
alleged deficiencies in the NRC’s NEPA analysis. See Hydro Res., Inc. (2929 Coors Road,
Suite 101, Albuquerque, NM 87120), CLI-99-22, 50 NRC 3, 13 (1999). While there may be
mistakes in the EIS, “in an NRC adjudication it is the Intervenors’ burden to show their
significance and materiality.” Exelon Generation Co. (Early Site Permit for Clinton ESP Site),
CLI-05-29, 62 NRC 801, 811 (2005). In order to advance a claim under NEPA, the intervenor
must allege with adequate support that the NRC Staff “has failed to take a ‘hard look’ at
significant environmental questions” – in other words, that the Staff has “unduly ignored or
minimized pertinent environmental effects of the proposed action.” Duke Energy Corp.
(McGuire Nuclear Station, Units 1 & 2; Catawba Nuclear Station, Units 1 & 2), CLI-03-17,
58 NRC 419, 431 (2003). As the Commission has stated, “[o]ur Boards do not sit to ‘flyspeck’
environmental documents or to add details or nuances. If the ER (or EIS) on its face ‘comes to
grips with all important considerations’ nothing more need be done.” Clinton ESP, CLI-05-29,
62 NRC at 811, quoting Systems Energy Resources, Inc. (Early Site Permit for Grand Gulf Site),
CLI-05-4, 61 NRC 10, 13 (2005).
II. Witnesses5
A. Staff Witnesses
The attached testimony presents the opinions of a panel of witnesses for each of the
three contentions. For Contention 1.2, the panel of witnesses is as follows: Jill S. Caverly,
Rebekah Harty Krieg, Anne “Nancy” Kuntzleman, Dr. Michael T. Masnik, Mark D. Notich, and
5 In its Order dated December 15, 2008, the Licensing Board instructed each party to identify whether there are any limitations on the availability of any of its witnesses during the March 16-19 hearing. The Staff has identified no limitations on the availability of any Staff witness during that time. With respect to witnesses from the USACE, the Staff has conferred with the Office of Counsel, Savannah District. The Office of Counsel has informed Staff counsel that there is no anticipated limitation on the availability of any of the USACE witnesses during that time.
- - 8
Lance W. Vail.6 For Contention 1.3, the panel of witnesses is as follows: Jill S. Caverly,
Rebekah Harty Krieg, Dr. Michael T. Masnik, Mark D. Notich, and Lance W. Vail.7
For Contention 6, the Staff has attached testimony presenting the opinions of two panels
of witnesses, one comprising witnesses from the Staff8 and one comprising witnesses from the
USACE.9 The Staff witnesses are Jill S. Caverly, Rebekah Harty Krieg, Anne “Nancy”
Kuntzleman, Mark D. Notich, and Lance W. Vail. The USACE witnesses are William G. Bailey,
Carol L. Bernstein, Lyle J. Maciejewski, and Stanley L. Simpson.
Also attached to this pleading as Attachment 1 is the testimony of Mark D. Notich that,
pursuant to 10 C.F.R. 2.337, sponsors the introduction of the Staff’s Final Environmental Impact
Statement into the record in this proceeding.10
Jill S. Caverly is a senior hydrologist in the hydrologic engineering branch, division of site
and environmental reviews in the NRC’s Office of New Reactors (“NRO”). See Statement of
Professional Qualifications for Jill S. Caverly (in Attachment 2). Ms. Caverly has worked at the
NRC since 1999, first as an engineer in the NRC’s office of Nuclear Material Safety and
Safeguards (“NMSS”) then as a senior project manager in the division of license renewal in the
6 See Attachment 2, “NRC Staff Testimony of Dr. Michael T. Masnik, Anne R. Kuntzleman, Rebekah H. Krieg, Jill S. Caverly, and Lance W. Vail Concerning Environmental Contention EC 1.2” (hereinafter “Staff EC 1.2”).
7 See Attachment 3, “NRC Staff Testimony of Dr. Michael T. Masnik, Rebekah H. Krieg, Jill S. Caverly, and Lance W. Vail Concerning Environmental Contention EC 1.3” (hereinafter “Staff EC 1.3”).
8 See Attachment 4, “NRC Staff Testimony of Mark D. Notich, Anne R. Kuntzleman, Rebekah H. Krieg, Jill S. Caverly, and Lance W. Vail Concerning Environmental Contention EC 6.0” (hereinafter “Staff EC 6”).
9 See Attachment 5, “U.S. Army Corps of Engineers Testimony of William G. Bailey, Carol L. Bernstein, Lyle J. Maciejewski, and Stanley L. Simpson Concerning Environmental Contention EC 6.0” (hereinafter “USACE EC 6 Testimony”).
10 See Attachment 1, “Prefiled Direct Testimony of Mark D. Notich Sponsoring NUREG-1872 Into Hearing Record.”
- - 9
office of Nuclear Reactor Regulation (“NRR”). Id. Prior to joining the NRC, Ms. Caverly worked
as a civil/hydraulic engineer for the U.S. Army Corps of Engineers, where she was responsible
for developing methodology for the evaluation and selection of environmental restoration
projects. Id. Ms. Caverly was assigned in June 2008 to oversee the work of Mr. Lance W. Vail
regarding the Vogtle ESP application.
Rebekah H. Krieg is employed as a senior research scientist in the Ecology Group,
Environmental Sustainability Division, Energy and Environment directorate of the U.S.
Department of Energy’s Pacific Northwest National Laboratory (PNNL). See Statement of
Professional Qualifications for Rebekah Harty Krieg (in Attachment 2). Ms. Krieg has worked at
PNNL from 1979-2002, and from 2005 until the present. Id. During this time she has been a
project manager of interdisciplinary teams that assisted the NRC Staff on the cleanup of Three
Mile Island, Unit 2, the Generic Environmental Impact Statement for decommissioning of
commercial nuclear power reactors, and the development of the Supplemental Environmental
Impact Statement for the restart of Watts Bar Nuclear Plant. Id. In addition, she acted as a
technical leader that provided support to the NRC on the review of several applications for
license renewal. Id. With regard to applications for new reactors, Ms. Krieg was the
pre-application team lead for four COL applications, and is the aquatic ecology reviewer for
another pre-application review. Id. Ms. Krieg is also the lead technical reviewer for the aquatic
ecology section of one COL application, in addition to being the lead aquatic ecology reviewer
for the Vogtle ESP application. Id.
Anne “Nancy” Kuntzleman is currently an aquatic biologist in the NRC’s NRO. See
Statement of Professional Qualifications for Anne “Nancy” Kuntzleman (in Attachment 2). Prior
to joining the NRC, Ms. Kuntzleman spent 11 years working for two environmental consulting
firms that provided numerous studies on terrestrial and aquatic biology for the Philadelphia
Electric Company, including performing fish estimates in the vicinity of the Limerick Generating
Station. Id. Later, Ms. Kuntzleman worked for 19 years as a senior biologist with the
- - 10
Department of the Navy, Engineering Field Activity Northeast (“EFANE”), where she served for
almost 18 years as the sole professional/technical authority for EFANE in the preparation and
coordination of all Department of the Army permit applications, Coast Guard permits, state
wetland permits, and water quality certificates for activities in waters of the United States (U.S.)
and navigable waters of the U.S. within the regulatory authority of Sections 401 and 404 of the
Clean Water Act (CWA), Sections 9 and 10 of the Rivers and Harbors Act of 1899, and Section
103 of the Marine Protection, Research, and Sanctuaries Act of 1972. Id. Since joining the
NRC in 2006, Ms. Kuntzleman has provided aquatic and terrestrial ecology reviews on several
COL applications and helped perform several pre-application reviews. Id. Ms. Kuntzleman has
provided technical oversight for the aquatic and terrestrial sections of the Vogtle ESP draft and
final EISs.
Dr. Michael T. Masnik is currently employed as a Senior Aquatic Ecologist in NRC’s
NRO. See Statement of Professional Qualifications for Michael T. Masnik (in Attachment 2).
Dr. Masnik joined the Atomic Energy Commission, the predecessor to the NRC, in 1974 as a
Fisheries Biologist performing and overseeing NEPA reviews for nuclear power reactor license
applications. Id. In the late 1970s and early 1980s Mr. Masnik participated in the initial
licensing reviews for more than 10 sites, participated in three alternative site reviews, and
investigated numerous environmental events involving aquatic resources occurring at operating
nuclear power stations. Id. In 1982, Dr. Masnik became a Technical Assistant to the Director of
the Three Mile Island cleanup effort, and for 13 years provided technical oversight of this
cleanup effort. Id. From 1997-2001, Dr. Masnik worked first as Acting, then Section Chief of
the Decommissioning section of NRC’s NRR. In this position, Dr. Masnik was responsible for
the project management of 19 permanently shut down reactors, and the development of the
Generic Environmental Impact Statement on the decommissioning of nuclear power reactors.
Id. From 2001-2007, Dr. Masnik worked as a project manager and aquatic and terrestrial
ecologist on numerous license renewals. Id. Starting in 2007, Dr. Masnik transferred to his
- - 11
current position in NRO, and he has provided oversight to several other ESP and combined
license applications. Id. In addition to his experience at the NRC, Dr. Masnik has authored or
co-authored 16 publications on such topics as thermal studies on fishes, recovery of damaged
aquatic ecosystems, and development of sampling methodology for fish and
macroinvertebrates, and he is a member of the American Fisheries Society. Id. As part of his
official duties, Dr. Masnik assisted in the development of the Biological Assessment for the
Vogtle ESP application, and acted as the lead technical reviewer for the NRC on aquatic
resources issues associated with the Application.
Mark D. Notich is a Senior Environmental Project Manager in the NRC’s NRO, and is the
project manager in charge of preparing the EIS for the Vogtle ESP application. See Statement
of Professional Qualifications for Mark D. Notich (in Attachment 1). Mr. Notich has thirty years
of experience providing environmental reviews and as a project manager for various projects.
Id. Since joining the NRC in 2005, Mr. Notich has provided support for the Clinton ESP and
Grand Gulf ESP, the Vermont Yankee license renewal, and pre-application reviews for the
North Anna Plant and the V.C. Summer Nuclear Power Station. Id.
Lance W. Vail is a Senior Research Engineer II, at PNNL. See Statement of
Professional Qualifications for Lance W. Vail (in Attachment 2). Since 1981, Mr. Vail has
gained extensive experience in projects covering a diverse set of water related issues. Id. In
addition, Mr. Vail has published numerous peer reviewed publications and is a member of the
American Geophysical Union, the American Society of Civil Engineers and the American Water
Resources Association. Id. With regard to work for the NRC, Mr. Vail has assessed the water
use, water quality, and hydrologic impacts of ten license renewal applications. Id. Mr. Vail has
also provided both safety and environmental reviews for three ESP applications. Id. Mr. Vail is
the lead hydrological technical reviewer for the Vogtle ESP and is responsible for the analysis
related to surface water and plant water systems.
- - 12
B. USACE Witnesses
William G. Bailey is employed as a Physical Scientist and serves as Chief of the
Savannah Planning Unit, Savannah-Mobile Regional Planning Center (Environmental
Resources, Plan Formulation, and Economics) with the USACE. See USACE EC 6 Testimony
at A1; Statement of Professional Qualifications for William G. Bailey (in Attachment 5). Mr.
Bailey holds degrees in Biology, Forestry and Civil Engineering. Id. Within the USACE, Mr.
Bailey has served as a civil engineer, a supervisor and team leader for the Impact Analysis
Team, the temporary Chief of the Environmental Resources Branch of Planning Division, team
leader within the Environmental Resources Branch of Planning Division, and supervisor within
the Impact Analysis Section of Planning Division's Environmental Resources Branch. Id. Since
2001, Mr. Bailey has served as the Savannah District Planning Unit’s technical expert on NEPA
and other environmental issues. Id. Mr. Bailey is responsible for the comprehensive water
resources development and management program of the Savannah District. In that capacity he
evaluates the environmental impacts of complex civil works and regulatory projects, providing
direction to and reviewing the work of environmental Staff, preparing environmental compliance
documents, including Environmental Assessments and Environmental Impact Statements,
coordinating projects and environmental documentation with Federal and state resource
agencies, and negotiating environmental compliance issues with Federal and state natural
resource agencies. Id. Mr. Bailey also manages the Savannah District Unit’s floodplain
management services and flood insurance studies. USACE EC 6 Testimony at A2(a).
Carol L. Bernstein is employed as a Supervisory Biologist and serves as Chief of the
Coastal Branch, Regulatory Division with the USACE, Savannah District. See Statement of
Professional Qualifications for Carol L. Bernstein (in Attachment 5). Ms. Bernstein holds
degrees in Renewable Natural Resources - Wildlife Ecology and Interdisciplinary Environmental
Sciences Studies. Id. Within the Army Corps of Engineers, Ms. Bernstein has served as Chief
of the Hazardous, Toxic, & Radioactive Waste (HTRW) Section and the Planning and
- - 13
Environmental Services Branch for the Baltimore District. Id. Ms. Bernstein has also served as
temporary Chief of the Planning Division in the Savannah District and as temporary Chief of the
Regulatory Division in the Mobile District. Id. Since 2001, Ms. Bernstein has served as Chief of
the Coastal Branch, Regulatory Division as a Supervisory Biologist. Id. Ms. Bernstein is
responsible for planning, programming, administering and enforcing the Regulatory Program,
including permit evaluation, enforcement, noncompliance, and mitigation under the Rivers and
Harbors Act and the Clean Water Act. USACE EC 6 Testimony at A2(b). Ms. Bernstein is also
responsible for developing policy and ensuring compliance with a variety of statutes, executive
orders, and environmental laws including the NEPA, the Endangered Species Act, and the
National Historic Preservation Act. Id. at A5(b).
Lyle J. Maciejewski holds degrees in civil engineering and has worked as an engineer
within the U.S. Army Corps of Engineers since 1980. See Statement of Professional
Qualifications for Lyle Maciejewski (“Maciejewski SPQ”); USACE EC 6 Testimony at A2(c) and
A5(c) (in Attachment 5). Mr. Maciejewski has significant experience related to dredging
activities performed by the Corps. See Maciejewski SPQ. He has also led the hydrographic
survey operations for dredging work in the Mississippi River and adjacent ports, served as
project engineer coordinating administrative duties in the Hydropower Branch of the District and
as Contracting Officers Representative for District maintenance and construction dredging
contracts. Id. Since 1996, Mr. Maciejewski has served as the Operations and Maintenance
Project Manager for the Savannah Harbor and the Savannah River Below Augusta Project. Id.;
USACE EC 6 Testimony at A5(c). In that capacity he is responsible for scheduling and
developing harbor dredging contracts involving maintenance dredging of the harbor and river
basin and was detailed as head of the hydrographic survey section responsible for planning
conducting and producing the District hydrographic surveys including dredging payment
surveys. Id.
- - 14
Stanley L. Simpson holds a degree in civil engineering and has worked as an engineer
within the U.S. Army Corps of Engineers since 1983. See Statement of Professional
Qualifications for Stanley L. Simpson (in Attachment 5). Mr. Simpson began his employment
with the Corps as a hydraulic engineer and, since 1988, has served as the Savannah District
Water Control Manager, Engineering Division. Id. In his capacity as the Water Control
Manager, Mr. Simpson provides technical support to Engineering, Planning and Operations
Divisions and serves as the Systems Administrator for the CWMS and Water Control Data
System. USACE EC 6 Testimony at A2(d). As the South Atlantic Division technical expert on
water management and data dissemination, Mr. Simpson also provides project information, pool
projections, weather forecasts and river forecasts to private and municipal entities. Id. at A2(d),
A5(d).
III. The Inadequacies Asserted by the Joint Intervenors’ Contentions Lack Merit.
The Staff’s testimony presents its position that the inadequacies in the Staff’s FEIS
alleged by the Joint Intervenors lack merit. As explained in the Staff testimony and supported
by the Staff exhibits, the Staff has conducted its environmental review appropriately, in
compliance with the NRC’s regulations that implement NEPA and in accordance with applicable
Staff review guidance.
In reviewing the application, conducting its independent environmental analysis, and
reaching conclusions as to the associated impacts, the Staff has adequately considered and
evaluated the potential environmental impacts of the proposed action to aquatic resources in
the Savannah River. In doing so, the Staff has adequately evaluated the “dry cooling system”
alternative as well as the possible cumulative impacts associated with potential future dredging
of the Savannah River Federal navigation channel.
A. Contention 1.2
Contention 1.2 challenges the adequacy of the Staff’s analysis of the direct, indirect and
cumulative impacts of the proposed cooling system intake and discharge structures on aquatic
- - 15
resources. Specifically, it alleges that the Staff inadequately analyzes those impacts associated
with impingement and entrainment as well as with thermal effluent discharge.
However, the attached Staff testimony and exhibits demonstrate that the Staff’s analysis
in the FEIS with respect to each of these impact categories is both adequate and consistent
with applicable Staff review guidance. In doing so, the Staff also refutes the Joint Intervenors’
underlying assertion that inadequate “baseline information” concerning aquatic species has
been provided to appropriately evaluate important environmental impacts with respect to the
intake and discharge structures of both the proposed Units 3 and 4 and the existing Vogtle Units
1 and 2.
1. Available Information Was Appropriate to Enable Staff’s NEPA Analysis.
The data and level of detail presented in the FEIS concerning the presence and life
history of aquatic species comports with Staff guidance provided in Regulatory Guide 4.2,
Revision 2, Preparation of Environmental Reports for Nuclear Power Stations (NRC 1976); in
Regulatory Guide 4.7, and in applicable sections of NUREG-1555, Environmental Standard
Review Plan (NRC 2000 & 2007) (“ESRP”). See “NRC Staff Testimony of Dr. Michael T.
Masnik, Anne R. Kuntzleman, Rebekah H. Krieg, Jill S. Caverly, and Lance W. Vail Concerning
Environmental Contention EC 1.2” (hereinafter “Staff EC 1.2”) at A6-A7. The key sources of
information relied on by the Staff to characterize the Savannah River in the vicinity of the site
were both adequate and appropriately comprehensive to enable the Staff’s evaluation of
environmental impacts. Staff EC 1.2 at A5, A8-A9, A15.
Furthermore, the Staff’s focus on “important species” for the purpose of characterizing
the aquatic environment is consistent with the definitions and guidance in the ESRP and in
Regulatory Guide 4.2. Staff EC 1.2 at A10-A13. The Staff’s analysis also appropriately
recognizes the relationship between flows in the Savannah River and the availability of aquatic
habitat, noting the changes in river stage that occur at different flow levels but also the more
frequent (even daily) fluctuations that naturally occur and to which aquatic species are pre-
- - 16
adapted, even before the river flows were regulated by the use of impoundments. Staff EC 1.2
at A14.
2. Staff Appropriately Assessed Impacts of Impingement and Entrainment.
The Staff evaluated both impingement and entrainment impacts for the ESP with
particular consideration of the significant reductions in cooling water withdrawals and thermal
discharges associated with a closed-cycle cooling system compared to a once-through cooling
system. Staff EC 1.2 at A17. In accordance with guidance in the ESRP, the Staff evaluated
impacts from impingement and concluded that the impacts would be SMALL. Staff EC 1.2 at
A19-A21. This conclusion was based on a number of factors. These factors included the
applicant’s use of closed-cycle cooling, which reduced river water withdrawal substantially
compared to once-through cooling systems; the planned low through-screen intake velocity of
less than 0.5 feet per second at the minimum river water level of 78 feet; a calculated intake
canal flow velocity towards the intake screens of about 0.1 feet per second; and the Staff’s
evaluation of aquatic species inhabiting the middle Savannah River. Staff EC 1.2 at A19, A22.
The Staff also considered the past absence of significant impingement episodes at the existing
intake of Units 1 and 2 along with the preliminary results of the recent VEGP Units 1 and 2
impingement sampling program, as well as the results of a past impingement study at the
Savannah River Site. Staff EC 1.2 at A19. The Staff’s determinations regarding impingement
applied relevant ESRP guidance. Staff EC 1.2 at A20-A21.
Regarding impingement impacts, the Staff found that there would be daily and seasonal
variation in impingement and that the different life stages of organisms would experience
varying susceptibility to impingement. Staff EC 1.2 at A23. However, large numbers of
impinged fish are unusual at riverine intakes like that for the Vogtle site, and adult fish of any of
the “important species” that the Staff identified in the FEIS have a burst swim speed that would
enable them to avoid impingement. Staff EC 1.2 at A23-A24. Also, historic studies at the
Savannah River Site (“SRS”) indicated low impingement rates even at much higher withdrawal
- - 17
rates than those proposed for Units 3 and 4. Staff EC 1.2 at A23-A25. Therefore, the Staff
concluded that the losses due to impingement, including to any of the “important species”
identified, would not result in detectable changes to the Savannah River fishery. Staff EC 1.2 at
A23-25. Furthermore, preliminary sampling data obtained by Southern since the issuance of
the FEIS regarding both impingement and entrainment at the Units 1 and 2 intake structure
support this conclusion, as primarily young of the year and juveniles were impinged. Staff EC
1.2 at A23.
The Staff likewise followed ESRP guidance to evaluate impacts from entrainment. Staff
EC 1.2 at A27-A28. Based on several factors, the Staff concluded that impacts would be
SMALL. Because the amount of water withdrawn from the source waterbody greatly influences
the degree to which entrainment affects aquatic biota, key factors in the Staff conclusion
included the applicant’s use of a closed-cycle cooling system and the design and location of the
cooling intake canal and structure, including use of a weir wall and skimmer wall at the mouth of
the intake. Staff EC 1.2 at A26, A28-A30. The Staff also considered previous sampling data,
the high fecundity of most species inhabiting rivers, and the high natural mortality rates of eggs
and larvae. Staff EC 1.2 at A26. Furthermore, the Staff considered previous sampling related
to SRS operations, which indicates that historic operations of the SRS intake did not have a
discernable impact on fish species in the Savannah despite withdrawals much greater than
those anticipated for Units 3 and 4. Staff EC 1.2 at A28-A29.
In evaluating entrainment impacts, the Staff assumed both that entrainment is generally
proportional to withdrawals and also that eggs and larvae are uniformly distributed throughout
the water column. Staff EC 1.2 at A28, A30-A31. While the assumption of uniform distribution
is not necessarily realistic for some species that are demersal spawners (with eggs that sink
quickly and adhere), it is conservative for estimating entrainment at Vogtle even for those
species because the intake system design would result in water from the middle of the water
column preferentially entering the canal. Staff EC 1.2 at A30, A33. Uniform distribution is also
- - 18
consistent with the assumption previously used in the Final Environmental Statement for Units 1
and 2, and with the assumptions made by the Environmental Protection Agency in its Phase I
final regulations. Staff EC 1.2 at A30, A31. This assumption is also conservative because
times of year with higher ichthyoplankton densities correspond with periods of higher river flow,
resulting in a lower percentage being entrained. Staff EC 1.2 at A32-A33. Accordingly, the
uniform distribution assumption, in combination with the aforementioned intake design
considerations and sampling data, support the Staff’s conclusions in the FEIS. Furthermore,
additional information available since the FEIS was issued also confirms the Staff analysis,
including National Marine Fisheries Service concurrence with the Staff conclusions regarding
impacts to the shortnose sturgeon, as well as sampling data confirming that eggs and larvae are
several times more numerous in samples from the Savannah River than in samples from the
Units 1 and 2 intake canal. Staff EC 1.2 at A34.
3. Staff’s Analysis Accounts for a Reasonable Range of River Flows.
In evaluating impacts to aquatic resources, the Staff considered a range of flows,
including normal flows as well as low-flow conditions. In the FEIS, the Staff determined it was
conservative to base its low-flow analysis on “Drought Level 3” flows (3800 cfs) in the USACE’s
current Draft Drought Contingency Plan. Staff EC 1.2 at A35. However, in part because of
ongoing drought conditions as well as reservoir-release changes contemplated by the USACE,
the Staff also evaluated very-low flows of 3000 and 2000 cfs. Staff EC 1.2 at A35. These
values continue to bound recent seasonal release restrictions proposed by the USACE. Staff
EC 1.2 at A35. The Staff believes the FEIS analysis of these three low and very-low flow levels
remains appropriate; nevertheless, the Staff does not believe that current drought conditions
represent a new baseline condition for the Savannah River Basin or suggest the need to
reconsider long-term normal flows, particularly for a NEPA review of an ESP assuming the siting
of a plant with a 40-plus year operating life. Staff EC 1.2 at A36, A40.
- - 19
With respect to flow measurements, the Staff determined that it was appropriate to use
estimated releases from the Thurmond Dam as the basis of the Staff’s analysis of impacts at the
site. This is because primary discharges of groundwater and surface water to the Savannah
River between the Thurmond Dam and the site are likely to be approximately equivalent to
consumptive loss from other upstream users, even under lower-flow conditions. Staff EC 1.2 at
A37. Moreover, groundwater discharges would likely increase at extremely low stream flows,
while withdrawals would not. Staff EC 1.2 at A37. For these reasons, and given the reliability of
flow estimates at the Thurmond Dam, the Staff considered its use of the Thurmond Dam values
to be reasonable. Furthermore, since issuance of the FEIS, the Staff has considered additional
recent flow data from the USGS gauge at Waynesboro, Georgia, which supports the Staff’s view
that use of the Thurmond Dam releases represents a reasonable bounding assumption for
evaluating flows at the ESP site. Staff EC 1.2 at A37.
The Staff used these flow values to evaluate impacts to aquatic resources. Its analysis
of operational impacts in FEIS Chapter 5 is based on maximum withdrawal rates for Units 3 and
4, which the Staff considers to be an additional conservatism because withdrawals at this rate
would occur infrequently and only for short periods of time. Staff EC 1.2 at A38. Moreover, the
natural variation in flows at the VEGP site, even on a daily basis, is often greater than the
normal and maximum withdrawal rates for the proposed new Units, and variation in river flow
rates is considered normal and beneficial to riverine systems. Staff EC 1.2 at A38. Also, the
Staff relied on average-daily discharge flow and Drought Level 3 flows, even though flows are
generally higher in spring and early summer, when most fish spawning occurs. Staff EC 1.2 at
A38.
Using these flow values, the Staff determined the percentage of river flow that would be
withdrawn and consumptively used by the proposed new units. The Staff identified these
percentages not only for normal withdrawals and average river flows, but also for maximum
withdrawals and for river flows of 3800, 3000 and 2000 cfs. Staff EC 1.2 at A41-A42. While
- - 20
these percentages are relevant to the Staff’s conclusions regarding impacts from impingement
and entrainment, the Staff considered several other factors, as discussed earlier. These factors
(e.g., the type of cooling system and the intake structure design) have greater potential for
affecting impingement rates than do the kinds of flow variation expected in the Savannah River.
Staff EC 1.2 at A43. Likewise, with respect to entrainment impacts, the Staff’s evaluation
considered the percentage of water withdrawn from the Savannah River as one of several
factors; Units 3 and 4 withdrawals would meet the EPA regulations for withdrawals being no
greater than five percent of the source water body annual mean flow under normal surface
water consumption and normal annual mean flows. Staff EC 1.2 at A43. Thus the Staff
considered these percentages, as well as other factors and data, in determining that impacts
from impingement and entrainment on aquatic resources would be SMALL. Staff EC 1.2 at
A44. Although the Staff determined that entrainment impacts (and possibly impingement
impacts) could increase under very-low-flow conditions, the Staff determined that such losses
were unlikely to have any persistent long-term impacts on populations of aquatic organisms in
the River. Staff EC 1.2 at A45.
4. Staff Appropriately Evaluated Cumulative Impingement and Entrainment Impacts from the Existing and Proposed Vogtle Units.
The Staff also evaluated the cumulative impacts to aquatic resources from impingement
and entrainment associated with operation of all four Vogtle units. Staff EC 1.2 at A47. In that
evaluation, the Staff considered the percentage of water withdrawn and consumptively used
under normal withdrawal rates. Staff EC 1.2 at A46. Because maximum withdrawals are rare
and because closed-cycle wet cooling towers are able to operate at very stable flow rates, the
use of normal withdrawal rates for the four units is the approach most appropriate for the
evaluation of cumulative impacts. Staff EC 1.2 at A51. In its cumulative impacts analysis, the
Staff considered average river flows as well as low-flow and very-low-flow conditions. Staff EC
1.2 at A46.
- - 21
Although the Staff considered the percentages of the river flow withdrawn and
consumptively used by all four units, these percentages were not the only factor on which the
Staff’s conclusions regarding cumulative impacts from impingement and entrainment were
based. Staff EC 1.2 at A48-A50. With respect to cumulative impingement impacts for flows
down to Drought Level 3, the Staff considered the location, design, and planned operation of the
intake and cooling system, the life history characteristics of “important species,” EPA standards
for intake design, and the characteristics of the watercourse near the Vogtle site. Staff EC 1.2
at A48. The Staff found no indication that the additional small and undetectable impact from
Unit 3 and 4 impingement losses at these flows would destabilize the Savannah River fishery.
Staff EC 1.2 at A48.
The Staff’s analysis of cumulative entrainment losses at flows down to Drought Level 3
relied more heavily on consideration of percentage withdrawal values under combined
withdrawals by Units 1 through 4. Staff EC 1.2 at A48. However, entrainment impacts would be
minor even from these cumulative withdrawals. Staff EC 1.2 at A48. The Staff considered
several factors, including the use of closed-cycle cooling; the design, location, and planned
operation of the proposed intake; the characteristics of the watercourse in the vicinity of the
intake; the distribution, abundance and life history data of aquatic species near VEGP; and
previous impingement and entrainment studies at SRS. Staff EC 1.2 at A48. The Staff’s
conclusion is further supported by preliminary data from the sampling program at Units 1 and 2.
Staff EC 1.2 at A48.
Finally, the Staff evaluated cumulative impacts from impingement and entrainment from
all four Vogtle units under very-low-flow conditions. Staff EC 1.2 at A50. Water withdrawal
percentages would increase, but the Staff again relied on a range of factors in its analysis. Staff
EC 1.2 at A50. A small increase in impingement mortality might occur as a result of very-low-
flow conditions, and there would also be a proportional increase in entrainment rates. Staff EC
1.2 at A50. However, such very-low-flow conditions would be temporary, and State resource
- - 22
agencies could also require mitigating actions to reduce withdrawals under such conditions.
Staff EC 1.2 at A50. Many factors controlling impingement losses, such as fish behavior, would
be relatively unaffected by very-low-flow conditions. Staff EC 1.2 at A50. Moreover, historic
withdrawals from SRS were at percentages higher than those estimated for all 4 Vogtle units but
those entrainment losses did not result in observable adverse impacts to aquatic biota. Staff
EC 1.2 at A50.
5. Staff Adequately Evaluated Thermal Impacts from the Existing and Proposed Vogtle Units.
The Staff also evaluated the cumulative impact to aquatic resources from discharge of
heated cooling water associated with operation of Vogtle Units 3 and 4 following ESRP
guidance. Staff EC 1.2 at A52, A54. Pursuant to that guidance, the Staff’s review should
include “the analysis of alterations to the receiving water body resulting from plant
thermal…discharges in sufficient detail to predict and determine the nature and extent of
potential impacts on aquatic ecosystems.” ESRP at 5.3.2.2-1; Staff EC 1.2 at A54. The ESRP
also states that “the Staff’s analysis may be provided by referencing the aquatic biota
descriptions of ESRP 2.4.2 and describing in brief detail the effects on biota that are important
and susceptible to thermal … impact.” ESRP at 5.3.2.2-10; Staff EC 1.2 at A54. In the FEIS,
the Staff analyzed the interaction between the plume and the habitat and life history of important
species, the potential impacts from cold shock and heat shock, and the potential for an increase
in invasive or nuisance organisms due to increased ambient water temperatures. Staff EC 1.2
at A53, A54. In addition, a Biological Assessment describing the Staff’s findings was prepared
and sent to the National Oceanic and Atmospheric Administration for its review under Section 7
of the Endangered Species Act. Staff EC 1.2 at A54.
The Staff’s evaluation of thermal impacts to aquatic biota was predicated on use of the
CORMIX thermal plume code to estimate the size and shape of the thermal plume. Staff EC 1.2
at A53-A55, A57. The CORMIX code is supported by the U.S. EPA for use in environmental
- - 23
impact assessments of regulatory mixing zones resulting from continuous point source
discharges and is considered to be an industry standard for such assessments. Staff EC 1.2 at
A57. The CORMIX assessment as presented in Section 5.3.3.1 of the FEIS describes the areal
extent of the plume. Staff EC 1.2 at A56. In the FEIS, the Staff used the CORMIX assessment
to consider discharges to the Savannah River under a variety of flow conditions, river
temperatures, and discharge water temperatures and considering the design and location of the
discharge and the width of the river at the VEGP site. Staff EC 1.2 at A54, A55.
As a conservative measure, the Staff’s assessment considered the combined impact of
discharges of heated water from all four units. Staff EC 1.2 at A57. As further conservative
measures, the analyses assigned the total effluent discharge for all four units to a single outfall
pipe at maximum plant flows, maximum discharge temperatures and minimum ambient river
temperatures which the Staff considered would produce the maximum single thermal plume.
A57, A61. Further, in addition to the Drought Level 3 flows (3800 cfs), the Staff considered
thermal impacts under very-low-flows of 2,000 cfs and 3,000 cfs. Staff EC 1.2 at A57-A60.
These flow conditions resulted in the greatest plume size and the greatest impact and, although
the Staff expects that the occurrence of such low flows would be extremely rare and of
temporary duration, analysis of these flows was the Staff’s attempt to provide additional
conservative context for the analysis. Staff EC 1.2 at A58.
Utilizing the most conservative flow and discharge information, the maximum thermal
plume size was found to be approximately 15 feet wide by 97 feet long. Staff EC 1.2 at A54,
A59. As the Savannah River is 312 feet wide at the location of the Vogtle ESP site, the Staff
determined that the 5 degree Fahrenheit isotherm would occupy about 5% of the river cross
section. Staff EC 1.2 at A59.
In assessing the impact of the thermal plume on aquatic biota, the Staff in the FEIS
described the aquatic environment and biota, including the types, life stages, and relative
abundance of important biota in the vicinity of the VEGP. Staff EC 1.2 at A54. Because the
- - 24
thermal plume is expected to be small in comparison to the width of the river, the Staff
concluded that it would not impede up- or downstream migration of the important fish species of
concern known to occur in the vicinity of the Vogtle ESP site, including the robust redhorse and
the shortnose sturgeon, and that fish and other organisms would be able to avoid the elevated
temperatures associated with the plume. Staff EC 1.2 at A54. Because the Atlantic sturgeon
has the same spawning characteristics as the shortnose sturgeon (Staff EC 1.2 at A7), the Staff
concluded that the thermal plume would also create no barrier to its up- or downstream
migration (Staff EC 1.2 at A54). The Staff also concluded that impacts to the South Carolina
mussel species known to occur in the vicinity of the Vogtle ESP site would be minor. Staff EC
1.2 at A54.
Neither cold shock nor heat shock was found to be of concern at the Vogtle site. Staff
EC 1.2 at A53-A54. Cold shock occurs when organisms that have been acclimated to warm
water are exposed to a sudden temperature decrease. Staff EC 1.2 at A53. The potential for
cold shock is greater when heated water is discharged into a confined body of water, or when
all reactors are suddenly shut down, leading to a cessation of all thermal discharge to the
waterbody. At the Vogtle site, thermal discharges would be to a river where the volume of
discharge is small in comparison to the total river volume. Staff EC 1.2 at A53. Because fish
have to actively swim to maintain position in a plume the Staff believes it is unlikely that a fish
would become acclimated to the higher station discharge temperatures, thereby avoiding the
possibility of cold shock. Staff EC 1.2 at A59.
The Staff concluded that cold shock was less likely to occur at the Vogtle site due to the
presence of multiple reactor units which would be unlikely to shut down simultaneously leading
to a dramatic drop in the temperature of the receiving water in the river. Staff EC 1.2 at 54. As
all four units would be discharging to the river, the effect of the sudden cessation of discharge
related to shutdown of one unit is unlikely to have enough effect on the thermal plume to result
in cold shock. Staff EC 1.2 at A54.
- - 25
Heat shock occurs when organisms are confined to an area in which water temperatures
suddenly increase. Staff EC 1.2 at A53. The potential for heat shock is greater when heated
water is discharged into a confined body of water or when the thermal plume is sufficiently large
as to prevent organisms from avoiding its effects. Staff EC 1.2 at A53. Heat shock was
considered to be unlikely to occur at the site due to the small size of the thermal plume relative
to the river and the ability of aquatic biota to avoid the plume. EC 1.2 at A54.
The Staff also analyzed the potential impacts from the thermal plume with respect to
invasive or nuisance organisms which have been observed to increase in numbers in the vicinity
of thermal plumes. Staff EC 1.2 at A53. Based on the absence of an increase in invasive
nuisance organisms in the vicinity of the thermal plume for VEGP Units 1 and 2, no increase in
invasive or nuisance organisms is anticipated to occur due to the additional thermal impact for
the proposed units. Staff EC 1.2 at A53.
Based on its analysis of the interaction between the plume and the habitat and life
history of important species, the potential impacts from cold shock and heat shock, and the
potential increase in invasive or nuisance organisms due to increased ambient water
temperatures, the Staff concluded that impacts to aquatic organisms from thermal discharges
from the proposed VEGP units 3 and 4 would be minor. Staff EC 1.2 at A53.
Finally, the Staff’s analysis also reflects that, following publication of the DEIS, Southern
advised the Staff that flows related to cooling system operation would differ based on changes
between Revision 15 and Revision 16 of the AP1000 Design Control Document. Staff EC 1.2 at
A62. In order to determine how the impacts evaluated for Revision 15 would be affected, the
Staff identified the increase in fractional withdrawal of the Savannah River associated with the
change between Revision 15 and Revision 16 at the four flow rates considered – normal flows
of 8830 cfs, Drought Level 3 flows of 3800 cfs, and also the very-low flows of 3000 cfs and 2000
cfs. Id. The Staff determined the relevant percentages for normal and maximum withdrawals
and consumptive use by the proposed Units 3 and 4 as well as by all four Vogtle units. Id. As
- - 26
stated earlier, the range in flows at the VEGP site, even on a daily basis, is often greater than
the normal and maximum withdrawal rates for the proposed VEGP Units 3 and 4. Id. at A38,
A62. Accordingly, relative to the natural variability of the Savannah River, all of the percentage
increases in water use associated with the change between Revision 15 and Revision 16 are
exceedingly small. Id. at A62. There was no change in the blowdown flow rate associated with
the change between Revision 15 and Revision 16; therefore, there would be no change in the
thermal plume analysis or its impact under all flow conditions considered. The effects on
aquatic biota of the slight increase in normal and maximum withdrawal rates associated with
Revision 16 would be undetectable and not result in a change in the impact level associated
with impingement or entrainment. Id. The Staff believes that would be the case under average-
daily, Drought Level 3, or very-low flows when assessing both normal and cumulative impacts of
operation of VEGP Units 3 and 4. Id.
6. Conclusion Regarding EC 1.2
For the reasons stated above, the FEIS both identifies and adequately considers the
impacts of the proposed cooling system intake and discharge structures on aquatic resources
with respect to impingement, entrainment, and thermal effluent discharge. Furthermore, in
these respects the FEIS adequately considers the cumulative impacts of operations of all four
Vogtle units.
B. Contention 1.3
Contention 1.3 challenges the adequacy of the Staff’s analysis of the dry-cooling
alternative in the FEIS. Specifically, Joint Intervenors argue that “extremely sensitive biological
resources” are present – in particular, the robust redhorse and shortnose sturgeon – at the
Vogtle site and, thus, that the NRC is required to do a more in-depth review of the dry-cooling
alternative. The attached Staff testimony and exhibits demonstrate that the Staff’s analysis in
the FEIS with respect to dry-cooling technology is adequate and complies with applicable Staff
guidance.
- - 27
The Staff is required to analyze alternatives to the proposed action pursuant to section
51.45(b)(3). With regard to analyzing heat dissipation alternatives, the Staff follows the
guidance in section 9.4.1 of the ESRP. While the NRC must consider alternatives, “NEPA does
not guarantee that federally-approved projects will have no adverse impacts at all. Nor does it
require an agency to select the most environmentally benign alternative.” Hydro Resources Inc.
(P.O. Box 777, Crownpoint, NM 87313), CLI-06-29, 64 NRC 417, 429 (2006).
1. The Staff’s Analysis of the Dry-Cooling Alternative was Adequate.
The Staff is required by section 51.45(b)(3) to analyze alternatives to the proposed
action. When reviewing alternatives to heat dissipation systems, the Staff follows the guidance
in section 9.4.1 of the ESRP. See “NRC Staff Testimony of Dr. Michael T. Masnik, Rebekah H.
Krieg, Jill S. Caverly, and Lance W. Vail Concerning Environmental Contention EC 1.3”
(hereinafter “Staff EC 1.3”) at A6. In this case, the proposed heat dissipation system is a
closed-cycle wet cooling system. Staff EC 1.3 at A5. As part of the Staff’s alternatives analysis,
it considered open-cycle once-through, and closed-cycle dry or wet/dry hybrid cooling system
design alternatives. Staff EC 1.3 at A7.
In analyzing the dry-cooling alternative, the Staff recognized that a dry-cooling system
would largely eliminate impacts on aquatic biota. Staff EC 1.3 at A10. However, the Staff also
found that a dry-cooling system would have some disadvantages with respect to land use, fuel
use, spent fuel transport, and spent fuel storage. Staff EC 1.3 at A11. Despite these
disadvantages, the Staff still might have considered dry-cooling the preferable alternative if the
proposed system would have had significant environmental impacts. Staff EC 1.3 at A12. But
the Staff concluded that proposed cooling system only produced small environmental impacts.
Staff EC 1.3 at A13.
Ultimately, the Staff’s review of heat dissipation alternatives was governed by section
9.4.1 of the ESRP. Staff EC 1.3 at A15. Consistent with that section, the depth of the Staff’s
analysis was governed by the nature and magnitude of the impacts of the proposed design.
- - 28
A16. Because the Staff found the impacts from the proposed wet cooling system design to be
small, it did not analyze other alternatives in greater depth. Staff EC 1.3 at A16. Further,
because of this small impact associated with the proposed design and the fact that several
disadvantages of the dry-cooling alternative were identified, the Staff concluded that the
dry-cooling alternative would not be environmentally preferable to the proposed design. Staff
EC 1.3 at A16. Pursuant to the ESRP, once a reviewer rejects an alternative, “that alternative
needs no further consideration other than the preparation of the reasons and justification for the
rejection.” Exhibit NRC-10 at 9.4.1-6.
2. The Proposed Design Will Have Only a Small Effect on Extremely Sensitive Biological Resources.
Contention 1.3 specifically challenges the analysis of dry cooling, given the presence of
“extremely sensitive biological resources” (ESBR) in the vicinity of the Vogtle site. Specifically,
Joint Intervenors pointed to the robust redhorse and shortnose sturgeon as examples of
ESBRs. The term ESBR comes from a 2001 rulemaking by the U.S. Environmental Protection
Agency. Staff EC 1.3 at A17; National Pollutant Discharge Elimination System; Regulations
Addressing Cooling Water Intake Structures for New Facilities, 66 Fed. Reg. 65,256, 65,282
(December 18, 2001). In pertinent part, this rulemaking states:
Although EPA has rejected dry cooling technology as a national minimum requirement, EPA does not intend to restrict the use of dry cooling or to dispute that dry cooling may be the appropriate cooling technology for some facilities. This could be the case in areas with limited water available for cooling or waterbodies with extremely sensitive biological resources (e.g., endangered species, specially protected areas).
Id. While the Staff did not use the term ESBR in the FEIS, it believes that the concept
“important species” used by the Staff would encompass all species that would be defined as
ESBRs. Staff EC 1.3 at A18-19. The Staff considered both the robust redhorse and the
shortnose sturgeon to be “important species” and it analyzed impacts to them both in the FEIS.
Staff EC 1.3 at A19.
- - 29
As discussed more fully in the Staff’s response to Contention 1.2, the Staff analyzed the
impacts from operation of the proposed Units 3 and 4 to important species, including the robust
redhorse and shortnose sturgeon. The Staff found that the impacts to important species from
the operation of the proposed wet cooling system design would be small. Staff EC 1.3 at A21-
A22. Consequently, the Staff found that the proposed cooling system design would not have a
significant adverse impact on any important species. Staff EC 1.3 at A23. Because the Staff
believes its consideration of “important species” encompasses any species that would be
defined as ESBRs, it is the Staff’s view that the proposed cooling system design would not have
a significant adverse impact on any ESBR. Staff EC 1.3 at A23.
3. Conclusion Regarding EC 1.3
The Staff found that impacts to all aquatic resources, which would include resources
likely to be considered ESBRs, from the operation of the proposed cooling system would be
small. Staff EC 1.3 at A25. Because the impacts from the proposed system are so minor, any
further reduction in mortality and morbidity due to the installation of a dry-cooling heat
dissipation system would be undetectable at the population level. Staff EC 1.3 at A25. Given
this small impact and the fact that there are several disadvantages to the dry-cooling alternative,
the Staff correctly determined that the dry-cooling alternative was not environmentally
preferable. Staff EC 1.3 at A26. Thus, consistent with section 9.4.1 of the ESRP, the Staff was
not required to analyze the dry-cooling alternative in greater depth, and its analysis in the FEIS
complied with NEPA requirements.
C. Contention 6
Contention 6 challenges the adequacy of the Staff’s analysis of the cumulative impacts
of dredging the Savannah River Federal navigation channel and possible water flow releases
from upstream reservoirs. New Contention Ruling at 18. Specifically, Joint Intervenors argue
that the Staff’s finding that impacts related to dredging of the Savannah River Federal
navigation channel could be MODERATE is inadequately supported and that the FEIS
- - 30
discussion of potential impacts associated with dredging “fails to address impacts of navigation
on the Corps’ upstream reservoir operations.” Joint Intervenors’ Motion to Admit New
Contention (September 23, 2008), at 2.
In its environmental analysis of the ESP application, which evaluates the impacts of the
construction and operation of two additional reactor units at the Vogtle Electric Generating
Plant, the Staff is required by NEPA to analyze cumulative impacts associated with that action
and other “connected” Federal actions. Based on the receipt of public comments on the DEIS
regarding the potential need for dredging of the Federal navigation channel to facilitate the
transport of components to the Vogtle site by barge, the Staff considered the potential impacts
of such dredging in its discussion of cumulative impacts and concluded that the cumulative
impacts could be MODERATE. “NRC Staff Testimony of Mark D. Notich, Anne R. Kuntzleman,
Rebekah H. Krieg, Jill S. Caverly, and Lance W. Vail Concerning Environmental Contention EC
6.0” (hereinafter “Staff EC 6”) at A29, A30. However, the Staff did not consider such a dredging
action to be necessary for the NRC’s action in granting an ESP, nor did the Staff assume that
such dredging was certain to occur. Moreover, at the time a formal plan is developed or an
application submitted for approval of such a project, that action would be reviewed by the Corps
pursuant to that agency’s regulatory guidelines. Accordingly, the Staff’s view is that the
potential dredging of the Savannah River Federal navigation channel is not a “connected action”
pursuant to NEPA and that analysis of the environmental impacts of a potential future dredging
action as a connected action in the ESP FEIS was not necessary.
Furthermore, the Staff denies the Joint Intervenors’ assertion that the Staff is responsible
for conducting a more detailed NEPA analysis in the FEIS regarding the potential dredging of
the Savannah River Federal navigation channel. The attached Staff testimony and exhibits
demonstrate that the Staff’s analysis in the FEIS with respect to potential dredging of the
Savannah River Federal navigation channel is both adequately supported and consistent with
NEPA requirements. The testimony also demonstrates why the Staff does not expect that
- - 31
environmental impacts on upstream reservoir operations would occur in connection with barge
transportation to the VEGP site.
1. Potential Dredging of the Federal Navigation Channel is Not Necessary for the NRC’s Federal Action and is Not a “Connected Action.”
NEPA requires that an agency include in an EIS the effects of other “connected actions”
to be performed. See 40 C.F.R. § 1508.25. “Actions are connected if they: (i) [a]utomatically
trigger other actions which may require environmental impact statements; (ii) [c]annot or will not
proceed unless other actions are taken previously or simultaneously; or (iii) [a]re interdependent
parts of a larger action and depend on the larger action for their justification.” Id. However, in
this proceeding, because the potential dredging of the Federal navigation channel is not
necessary for NRC approval of the ESP application and is not even certain to occur, it cannot
be said to be part of the NRC’s action in approving the ESP application. Moreover, that
dredging action, if it were to occur, would be subject to another Federal agency’s independent
decision-making authority. Therefore, potential dredging of the Savannah River Federal
navigation channel is not a part of the NRC action nor is it a “connected” action under NEPA.
In performing its FEIS analysis, the Staff assumed that heavy components would be
delivered to the Vogtle site by use of barges on the Savannah River. Staff EC 6 at A6. This
assumption was based, in part, on Southern’s plan to refurbish and dredge the barge slip. Staff
EC 6 at A6. NEPA may require actions to be treated as “connected” if it would be “irrational, or
at least unwise” to undertake one without the other. Save the Yaak Comm. v. Block, 840 F.2d
714, 720 (9th Cir. 1988). However, because rail and highway transportation are available
options, the Staff did not assume that barging was the only possible option for bringing
components to the Vogtle site. Staff EC 6 at A10. Thus there is no reason to conclude that
issuance of the ESP would be “irrational, or at least unwise” were dredging of the Federal
navigation channel not to occur. The Staff evaluated the impacts of barging because this was
the transportation option being contemplated by Southern in the ER. Staff EC 6 at A10.
- - 32
Furthermore, even if barging were the only means of transporting components to the
site, the Staff did not assume that dredging of the Federal navigation channel would be
necessary for barge transportation to the Vogtle site. Staff EC 6 at A10, A12. The Staff
assumed that large components could be barged during periods of naturally occurring high flow.
Staff EC 6 at A12 - A14. This assumption is consistent with the testimony of Corps witness
Stanley L. Simpson that “transportation of large industrial components upstream is not currently
possible due to the shallow river depths” but that “transportation of large components upstream
by barge has occurred several times in the last 10 years” and that “from previous experience
with nuclear waste shipments, it has required about 10,000 cfs discharge for more than one
week to get a barge to Jackson, SC and back from Savannah Harbor.” See “U.S. Army Corps
of Engineers Testimony of William G. Bailey, Carol L. Bernstein, Lyle J. Maciejewski, and
Stanley L. Simpson Concerning Environmental Contention EC 6.0” (hereinafter “USACE EC 6
Testimony”) at A7, A15.
For these reasons, the Staff did not consider issuance of the ESP to depend on the
potential dredging of the Federal navigation channel. Actions may need to be analyzed as
“connected” under NEPA if they are “inextricably intertwined.” Thomas v. Peterson, 753 F.2d
754, 759 (9th Cir 1985) (requiring analysis of both road and timber sales). However, as issuing
the ESP is not practically dependent on either the availability of barge transportation or on the
dredging of the Federal navigation channel, issuance of the ESP and dredging of the Savannah
River Federal navigation channel should not be considered “inextricably intertwined.”
In sum, while the Staff chose to analyze the impacts of potential dredging by the Corps
in its discussion of cumulative impacts, the Staff’s decision to do so does not mean that the
present (ESP) and potential (Corps) Federal actions are dependent on one another, nor does
NEPA require them to be evaluated as a single overarching action in the FEIS.
Furthermore, potential dredging of the Federal navigation channel is not part of the
NRC’s Federal action in issuing an ESP because the dredging action is outside the jurisdiction
- - 33
of the NRC and would be subject to an independent review by the Corps. NEPA does not
require the NRC to analyze as a “connected” action an undertaking (or potential undertaking)
that is under the jurisdiction of another Federal agency, where the other agency’s decision on
the action under its own jurisdiction would not determine, or be determined by, the NRC’s
Federal action. See Cal. Trout v. Schaefer, 58 F.3d 469, 473-474 (9th Cir. 1995); North
Carolina v. City of Virginia Beach, 951 F.2d 596 (4th Cir. 1991); cf. Wetlands Action Network v.
U.S. Army Corps of Eng’rs, 222 F.3d 1105, 1117-19 (9th Cir. 2000), cert. denied 534 U.S. 815
(2001) (upholding Corps decision to limit its NEPA review to portion of project under its control
and jurisdiction, where non-federal portion could proceed independently and each portion had
“independent utility”). As stated in the FEIS, maintenance of the Federal navigation channel is
the responsibility of the Corps, pursuant to its statutory mandate. See FEIS at 7-20; see also
Rivers and Harbors Act of 1899, 33 U.S.C.A. 403 (2008). The Corps, not the NRC, has the
authority to determine whether the Federal navigation channel will be dredged and the scope of
the dredging project.
Were the Corps to undertake dredging, it would prepare an environmental assessment
of the proposed action, and the Corps’ review process “would conclude with either an
Environmental Assessment (with a Finding of No Significant Impact) or an Environmental
Impact Statement (with a Record of Decision).” USACE EC 6 Testimony at A9. The Corps’
environmental review document would be coordinated with the public and natural resources
agencies, through which the Corps “would hope to obtain clearances under NEPA, the National
Historic Preservation Act, the Coastal Zone Management Act, the Magnuson Fishery
Conservation and Management Act, the Endangered Species Act, the Clean Water Act, and the
Clean Air Act.” Id. at A9. If instead Southern opted to perform the dredging work independent
of the USACE, Southern would be required to apply for a Corps permit. Id. at A10. That
application would be reviewed by the USACE’s Regulatory Division, which, pursuant to its
- - 34
review process would prepare an Environmental Assessment/Case document and render a
permit decision. Id. at A10.
In short, regardless of whether the Corps undertakes such a dredging project or
Southern applies for a Corps permit to do so itself, the Corps would conduct an environmental
review of that activity under NEPA, the Clean Water Act, and other relevant environmental
statutes. Id. at A10. The NRC does not control the USACE review process or the USACE’s
ultimate decision on whether to conduct or permit such dredging. Accordingly, NEPA does not
require that impacts associated with the potential Corps channel-dredging action be analyzed
as direct impacts of the NRC’s proposed licensing action. See, e.g., City of Shoreacres v.
Waterworth, 420 F.3d 440, 449-50, 451-54 (5th Cir. 2005) (discussing why Corps approval of
dredge-and-fill permit for port construction likely would not require including NEPA consideration
of potential future deepening of ship navigation channel; such activity would be the result of
action by another Federal entity over which the Corps had no control).
2. The Staff’s Analysis Was Appropriate Given the Lack of a Formal Dredging Proposal and the Absence of Project Details.
Both the Staff’s decision to discuss the potential dredging impacts and the level of detail
in the Staff’s analysis comply with NEPA. First, the Staff has neither reviewed nor become
aware of any formal proposal to dredge the Federal navigation channel. Staff EC 6 at A13, A16,
A18, A22, A27, A31. Likewise, the USACE has not developed a plan or received a formal
request or authorization for dredging of the Savannah River Federal navigation channel in the
near future to facilitate barge traffic as far north as the Vogtle Electric Generating Plant. USACE
EC 6 Testimony at A8. Accordingly, a plan for future potential dredging of the Federal
navigation channel is neither pending at this time nor is such dredging certain to occur. It thus
is not required to be analyzed as a direct impact of the proposed action in the ESP FEIS.
Nevertheless, the Staff discussed the potential impacts of dredging in Chapter 7 of the FEIS, in
- - 35
response to public comments and in the interest of disclosing potential cumulative impacts from
other activities, even if those activities are not certain to occur.
NEPA does not require an agency to consider the environmental effects that speculative
or hypothetical projects might have on a proposed project. See Northcoast Envtl. Ctr. v.
Glickman, 136 F.3d 660, 668 (9th Cir. 1998), citing Kleppe v. Sierra Club, 427 U.S. 390 (1976);
see also Sierra Club v. Marsh, 976 F.2d 763, 767-68 (1st Cir. 1992). In interpreting Kleppe, the
Commission has determined that for a NEPA analysis to be necessary, a future action “must at
least constitute a ‘proposal’ pending before the agency” and “must be in some way interrelated
with the action that the agency is actively considering[.]” See Duke Energy Corp. (McGuire
Nuclear Station, Units 1 and 2; Catawba Nuclear Station, Units 1 and 2), CLI-02-14,
55 NRC 278, 295 (2002).
The DEIS did not include an analysis of the impacts of dredging the Federal navigation
channel because, based on the Staff’s informal discussions with members of the Corps, it was
not expected to occur. Staff EC 6 at A9. Based on these informal discussions, it was the Staff’s
understanding that Southern had submitted no formal request for dredging to be performed
either by the Corps or by Southern (see Staff EC 6 at A13, A16, A18, A22, A27, A31) and that
the Corps had developed no plan and received no authorization for dredging of the Savannah
River Federal navigation channel. Staff EC 6 at A16, A18, A31.
Therefore, at the time the FEIS was issued, the Staff considered it unlikely that dredging
of the Federal navigation channel would occur, particularly within any short-term time frame.
Staff EC 6 at A13. The Staff had neither reviewed nor become aware of any formal Corps plan
for dredging of the Federal navigation channel. Staff EC 6 at A13, A16, A18, A22, A27, A31.
Likewise, while it is possible that dredging of the Federal navigation channel could be
conducted by Southern pursuant to a permit issued by the Corps, the Staff had not (and still has
not) reviewed or become aware of any such permit application pending before the Corps. Staff
EC 6 at A16, A18, A22, A27. This view is consistent with testimony from Corps witnesses,
- - 36
confirming that Southern has not indicated that channel dredging would be included in any
permit application to the Corps. USACE EC 6 Testimony at A8, A10. Accordingly, the Staff’s
decision that it was appropriate to consider the impacts of dredging the navigation channel as a
potential future Federal action was the result of public comments received on the DEIS, not
because the Staff believed such an action was certain to occur.
In the absence of a formal plan or request for permit to conduct dredging, the Staff at the
time of the FEIS (and now) had no specific information regarding the scope of any potential
dredging project, the amount of dredge material to be removed, the locations which will be
utilized for disposal of dredge materials, and the mitigative measures which may be required by
the Corps should dredging occur. Staff EC 6 at A28. As such, the Staff had (and still has) no
formal request or permit application upon which to base a quantitative NEPA review of the
environmental impacts that could result from a future dredging action. Staff EC 6 at A27, A28.
To require the Staff to have quantitatively analyzed the environmental impacts of potential
dredging in the FEIS would require them to “do the impractical.” Wetlands Action Network,
222 F.3d at 1119 (the Corps was not required to complete NEPA analysis of all phases of a
construction project within a single EA or EIS when details and planning decisions of all phases
had not been completed).
The U.S. Court of Appeals for the Sixth Circuit considered a similar situation in which the
merger of rail and barge companies was expected to result in development of capital
improvements projects, the construction of which was proposed to begin following approval of
the merger. See Crounse Corp. v. I.C.C., 781 F.2d 1176 (6th Cir. 1986). In determining
whether the NEPA analysis surrounding the merger was sufficient in light of the anticipated
future construction of three transfer structures, the Sixth Circuit found: “[w]e do not believe that,
in assessing the environmental impact of the merger, the [I.C.C.] was obligated to assess the
impact of contemplated projects which the Commission has no power to approve, which are not
an inherent component of the proposed merger, and which will be subject to environmental
- - 37
review should they ever reach the actual proposal stage.” Id. at 1194-1195. Likewise, the NRC
has no power to approve a future action to dredge the Savannah River Federal navigation
channel, the action is not necessary to the NRC’s licensing action, and it will be subject to
environmental review by the USACE if a detailed plan or permit application is submitted. Thus,
the Staff’s qualitative analysis of potential dredging of the Savannah River Federal navigation
channel pursuant to public comments was reasonable in light of the limited information available
for review.
3. Staff Did Not Consider Upstream Releases For Navigation To Be Necessary or Reasonably Foreseeable.
The Joint Intervenors have also suggested that the Staff’s analysis should have included
consideration of the environmental impact of releases of water from upstream reservoirs. In the
FEIS analysis, however, the Staff considered that any releases of water from upstream
reservoirs would occur only in response to the need for flood control as determined by the
Corps pursuant to the flood control rule curve, and would not alter the conservation pools. Staff
EC 6 at A7, A14. The Staff assumed that these reservoir operations would not be altered
solely for the purpose of navigation. Id. at A7. Based on informal discussions with members of
the Corps, the Staff assumed that navigation of the Savannah River would be feasible during
periods of naturally high flows without dredging of the Federal navigation channel, id. at A7, and
without the need for additional releases of water from upstream reservoirs. Id. at A14.
Moreover, at the time of preparation of the FEIS, the Staff was not aware of and had not
reviewed any formal Corps plan for the intentional release of water from upstream dams in order
to support barging to the Vogtle site. Staff EC 6 at A14, A17, A18. Again, the Staff assumed
that any releases from these upstream reservoirs would be pursuant to Corps implementation of
the flood control rule curve and not specifically to allow navigation. Id. at A7. The Staff
assumed that upstream releases for navigation would not occur under drought conditions, id. at
A8, and would not alter the conservation pools as alleged by the Joint Intervenors. Id. at A7.
- - 38
Consequently, the Staff did not consider it reasonably foreseeable that there would be impacts
to the upstream reservoirs associated with releases for navigation. Id. at A7, A14, A17. The
Staff believes these views are confirmed by the testimony provided by Stanley L. Simpson of
the Corps, which states that “[t]he USACE has made no study of minimum river flow needed to
eliminate the need for dredging of the Savannah River Federal navigation channel or whether
releases from upstream reservoirs could enable barge traffic to reach as far upstream as the
Vogtle Electric Generating Plant. The region is presently experiencing a drought and excess
water is not available in the lakes for such purposes.” USACE EC 6 Testimony at A15. Thus,
water releases from upstream reservoirs for navigation and associated impacts are not
“reasonably foreseeable” for purposes of NEPA.
4. The Staff’s Analysis and Conclusion That Cumulative Impacts Could Be MODERATE Is Reasonable.
Although the Staff did not consider that dredging of the Savannah River Federal
navigation channel was in fact likely to occur, the Staff included the potential impacts of such
dredging in its discussion of cumulative impacts. Staff EC 6 at A19-A22. The Staff added its
analysis of the potential impacts of such dredging in Chapter 7 (Cumulative Impacts) of the
FEIS. Staff EC 6 at A6, A9, A19, A22. Because no specific plan for dredging of the Federal
navigation channel was submitted to the NRC or to the Corps and no such plan has been
prepared by the Corps (see USACE EC 6 Testimony at A8), the Staff was able to perform only a
qualitative analysis of the expected impacts. Staff EC 6 at A27, A28. The Staff’s analysis was
appropriate because the dredging project is incompletely defined, the amount of material that
would be removed is unknown, and the locations of the dredged material disposal areas have
not been identified. Staff EC 6 at A28; see also USACE EC 6 Testimony at A17. In spite of
these limitations, the Staff in the FEIS identified the general types of impacts to aquatic biota
that might result from any such dredging. Staff EC 6 at A24. The Staff concluded that dredging
of the Federal navigation channel downstream of the VEGP site would likely have an effect on
- - 39
aquatic organisms, impacts which could include temporary loss of benthic habitat, disruption of
spawning migrations, and resuspension of sediments that might be contaminated. Staff EC 6 at
A24. The Staff also noted that dredging would require the disposal of dredged materials. Staff
EC 6 at A24. As a result of the analysis, the Staff determined that the cumulative impacts to
aquatic organisms from construction and dredging of the Federal navigation channel could be
MODERATE, depending on the type of mitigation. Staff EC 6 at A29.
The Staff’s conclusion is based in part on its understanding that the Corps would
conduct its own NEPA review of any dredging action which might be undertaken in order to
maintain the Savannah Federal navigation channel. Staff EC 6 at A30. The Staff’s conclusion
was informed by the Staff reviewer’s past professional experience with preparation and
coordination of Department of the Army permit applications, state wetland permit applications,
and water quality certificate applications. Staff EC 6 at A25. In the FEIS, the Staff emphasized
that any dredging of the Savannah River Federal navigation channel would require a separate
NEPA process with a separate environmental review performed by the Corps, the agency with
the appropriate authority or jurisdiction. Staff EC 6 at A28. The Staff anticipated that this review
would be conducted at the time an actual dredging project is formally requested or a permit
application is submitted. Staff EC 6 at A28.
Such a review would be conducted in accordance with applicable statutes and regulatory
guidelines, including Corps guidance, and would reflect any additional permitting requirements
resulting from coordination with other state and Federal agencies. USACE EC 6 Testimony at
A9-A12. The Staff anticipated that the Corps and other Federal and state regulatory and
resource agencies responsible for reviewing the dredging project would require project-specific
mitigation measures to ensure that the cumulative impacts to aquatic organisms in the region
would not be LARGE, defined as clearly noticeable environmental effects that would be
sufficient to destabilize important attributes of the resource. Staff EC 6 at A30, A33.
- - 40
5. Conclusion Regarding EC 6
In summary, the potential dredging of the Savannah River Federal navigation channel
does not constitute a connected action under NEPA; therefore, the Staff was justified in
evaluating the potential environmental impacts associated with such a future action as
cumulative impacts rather than as impacts of the NRC’s action. The Staff considered that
releases of water from upstream reservoirs would occur only in response to the Corps’
implementation of the flood control rule curve, and would not occur during drought conditions
simply to enable navigation. Accordingly, the Staff does not consider impacts to upstream
reservoirs to be reasonably foreseeable.
However, in response to public comments, the Staff did include a qualitative discussion
of environmental impacts expected to be associated with dredging of the Federal navigation
channel in the FEIS. The Staff found that cumulative impacts to aquatic resources from the
construction of the proposed reactor units and dredging of the Federal navigation channel could
be MODERATE. This analysis and determination were based on the professional experience
and judgment of the Staff, and it appropriately reflected the limited information available given
the absence of a formal dredging plan or proposal and uncertainty as to the scope of the
dredging if it were eventually to be undertaken. Furthermore, any dredging of the Federal
navigation channel would be an action independent of the proposed ESP, it would need to be
authorized under the jurisdiction of the Corps, and the Corps would be required to perform an
independent NEPA review of the environmental impacts of that project. Thus, the Staff’s
analysis discloses impacts of such a project to the extent reasonably possible at this time. For
these reasons, the Staff’s analysis was consistent with the requirements of NEPA and with the
NRC’s regulations.
- - 41
CONCLUSION
For the reasons discussed above, the Staff submits that the Joint Intervenors’
contentions are without merit and that the Staff’s environmental review, as documented in the
FEIS, complies with the requirements of NEPA. Accordingly, Joint Intervenors’ Contentions EC
1.2, EC 1.3, and EC 6 should be resolved in favor of the Staff.
Respectfully submitted,
/signed (electronically) by/ Patrick A. Moulding Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O-15 D21 Washington, DC 20555-0001 (301) 415-2549 [email protected]
Executed in Accord with 10 CFR § 2.304(d) Jody C. Martin Counsel for the NRC Staff
U.S. Nuclear Regulatory Commission Mail Stop O-15 D21 Washington, DC 20555-0001 (301) 415-1569 [email protected]
Executed in Accord with 10 CFR § 2.304(d) Sarah W. Price
Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O-15 D21 Washington, DC 20555-0001 (301) 415-2047 [email protected] Dated at Rockville, Maryland This 9th day of January, 2009
S
ubm
itted
: Jan
uary
9, 2
009
So
uthe
rn N
ucle
ar O
pera
ting
Co.
, Doc
ket N
o. 5
2-01
1-ES
P
Mar
ch 2
009
Man
dato
ry H
earin
g on
Unc
onte
sted
Issu
es
H
earin
g Ex
hibi
ts
Part
y
Exh.
#
Witn
ess/
Pa
nel
D
escr
iptio
n
NR
C
0000
01
All
NU
REG
-187
2, F
inal
Env
ironm
enta
l Im
pact
Sta
tem
ent f
or a
n ea
rly S
ite P
erm
it (E
SP) a
t the
Vog
tle
Elec
tric
Gen
erat
ing
Plan
t Site
, Vol
umes
1 &
2 (A
ugus
t, 20
08) c
ombi
ned
with
cor
rect
ed A
ppen
dix
F an
d th
e Se
ptem
ber 3
, 200
8 Er
rata
. Vol
ume
1 (M
L082
2401
45);
Vol
ume
2 (M
L082
2401
65);
App
endi
x F
(ML0
8226
0203
); Er
rata
(ML0
8255
0040
)
NR
C
0000
02
E.C
. 1.2
A
cade
my
of N
atur
al S
cien
ces o
f Phi
lade
lphi
a (A
NSP
). 20
01. 2
000
Sava
nnah
Riv
er B
iolo
gica
l Su
rvey
s for
Wes
tingh
ouse
Sav
anna
h R
iver
Com
pany
. Rep
ort N
o. 0
1-16
F. P
atric
k C
ente
r for
En
viro
nmen
tal R
esea
rch,
Phi
lade
lphi
a, P
enns
ylva
nia.
(ML0
7131
0366
).
NR
C
0000
03
E.C
. 1.2
A
cade
my
of N
atur
al S
cien
ces o
f Phi
lade
lphi
a (A
NSP
). 20
03. 2
001
Sava
nnah
Riv
er B
iolo
gica
l Su
rvey
s for
Wes
tingh
ouse
Sav
anna
h R
iver
Com
pany
. Rep
ort N
o. 0
3-08
F, P
atric
k C
ente
r for
En
viro
nmen
tal R
esea
rch,
Phi
lade
lphi
a, P
enns
ylva
nia.
(ML0
7131
0328
).
NR
C
0000
04
E.C
. 1.2
A
cade
my
of N
atur
al S
cien
ces o
f Phi
lade
lphi
a (A
NSP
). 20
05. 2
003
Sava
nnah
Riv
er B
iolo
gica
l Su
rvey
s for
Wes
tingh
ouse
Sav
anna
h R
iver
Com
pany
. Rep
ort N
o. F
04-0
6, P
atric
k C
ente
r for
En
viro
nmen
tal R
esea
rch,
Phi
lade
lphi
a, P
enns
ylva
nia.
(ML0
7131
0324
).
NR
C
0000
05
E.C
. 1.2
Th
e C
aten
a G
roup
. 200
7. F
resh
wat
er M
usse
l Sur
veys
, The
Sav
anna
h R
iver
from
Aug
usta
to
Sava
nnah
: Sou
th C
arol
ina
& G
eorg
ia. T
he C
aten
a G
roup
, Hill
sbor
ough
, Nor
th C
arol
ina.
(M
L081
4300
80).
Part
y
Exh.
#
Witn
ess/
Pa
nel
D
escr
iptio
n
NR
C
0000
06
E.C
. 1.2
Ex
cerp
ts fr
om: M
arcy
Jr. B
.C.,
D.E
. Fle
tche
r, F.
D. M
artin
, M. P
alle
r, an
d M
.J.M
. Rei
cher
t. 20
05.
Fish
es o
f the
Mid
dle
Sava
nnah
Riv
er B
asin
. The
Uni
vers
ity o
f Geo
rgia
Pre
ss, A
then
s, G
eorg
ia. (
no
ML
#).
NR
C
0000
07
E.C
. 1.2
Ex
cerp
ts fr
om: R
egul
ator
y G
uide
4.2
Rev
. 2, P
repa
ratio
n of
Env
ironm
enta
l Rep
orts
for N
ucle
ar
Pow
er S
tatio
ns (1
976)
. Ent
ire d
ocum
ent a
t: (M
L003
7395
19).
NR
C
0000
08
E.C
. 1.2
R
egul
ator
y G
uide
4.7
, Rev
. 2, G
ener
al S
ite S
uita
bilit
y C
riter
ia fo
r Nuc
lear
Pow
er S
tatio
ns (1
998)
. (M
L003
7398
94).
NR
C
0000
09
E.C
. 1.2
& 1
.3
NU
REG
-155
5 St
anda
rd R
evie
w P
lans
for E
nviro
nmen
tal R
evie
ws f
or N
ucle
ar P
ower
Pla
nts
(“ES
RP”
) (20
00) S
ectio
ns: 2
.4.1
; 2.4
.2; 5
.3.1
.2; 5
.3.2
.2; 9
.4.1
.
NR
C
0000
10
E.C
. 1.2
& 1
.3
NU
REG
-155
5 St
anda
rd R
evie
w P
lans
for E
nviro
nmen
tal R
evie
ws f
or N
ucle
ar P
ower
Pla
nts
(“ES
RP”
) Dra
ft R
ev. 1
(200
7) S
ectio
ns: 4
.7; 5
.3.1
.2; 9
.4.1
.
NR
C
0000
11
E.C
. 1.2
Ex
cerp
ts fr
om: S
pech
t 198
7, C
ompr
ehen
sive
Coo
ling
Wat
er S
tudy
, Fin
al R
epor
t, V
olum
e V
, A
quat
ic E
colo
gy, S
avan
nah
Riv
er P
lant
, DP-
1739
-5. E
ntire
doc
umen
t at:
(ML0
7079
0356
).
NR
C
0000
12
E.C
. 1.2
Pa
ller M
.H.,
B.M
. Sau
l, an
d D
.V. O
stee
n. 1
986.
Dis
tribu
tion
and
Abu
ndan
ce o
f lch
thyo
plan
kton
in
the
Mid
-Rea
ches
of t
he S
avan
nah
Riv
er a
nd S
elec
ted
Trib
utar
ies.
Prim
ary
Rep
ort N
o. D
PST-
86-
798,
Env
ironm
enta
l and
Che
mic
al S
cien
ces,
Inc.
, Aik
en, S
outh
Car
olin
a. (M
L071
7100
43).
NR
C
0000
13
E.C
. 1.2
Ex
cerp
ts fr
om: B
enne
tt D
.H. a
nd R
.W. M
cFar
lane
. 198
3. T
he F
ishe
s of t
he S
avan
nah
Riv
er P
lant
: N
atio
nal E
nviro
nmen
tal R
esea
rch
Park
. SR
O-N
ERP-
12. S
avan
nah
Riv
er E
colo
gy L
abor
ator
y, U
.S.
Dep
artm
ent o
f Ene
rgy,
Was
hing
ton,
D.C
. Ent
ire d
ocum
ent a
t: (M
L071
3103
21).
NR
C
0000
14
E.C
. 1.2
Ex
cerp
ts fr
om: N
UR
EG -1
087
Fina
l Env
ironm
enta
l Sta
tem
ent R
elat
ed to
the
Ope
ratio
n of
Vog
tle
Elec
tric
Gen
erat
ing
Plan
t, U
nits
I an
d 2.
Doc
ket N
os. 5
0-42
4 an
d 50
-425
(198
5). E
ntire
Doc
umen
t at
: (M
L062
2105
06).
Part
y
Exh.
#
Witn
ess/
Pa
nel
D
escr
iptio
n
NR
C
0000
15
E.C
. 1.2
H
endr
icks
A.S
. 200
2. T
he C
onse
rvat
ion
and
Res
tora
tion
of th
e R
obus
t Red
hors
e, M
oxos
tom
a ro
bust
um. V
ol. 3
. Geo
rgia
Pow
er C
ompa
ny E
nviro
nmen
tal L
abor
ator
y, S
myr
na, G
eorg
ia.
(ML0
9007
0613
)
NR
C
0000
16
E.C
. 1.2
N
icho
ls M
. 200
3. C
onse
rvat
ion
Stra
tegy
for R
obus
t Red
hors
e (M
oxos
tom
a ro
bust
um)
Envi
ronm
enta
l Lab
orat
ory
Geo
rgia
Pow
er C
ompa
ny fo
r Rob
ust R
edho
rse
Con
serv
atio
n C
omm
ittee
, A
tlant
a, G
eorg
ia. (
ML0
9006
0104
).
NR
C
0000
17
E.C
. 1.2
& 1
.3
Exce
rpts
from
: Gra
bow
ski T
.B. a
nd J.
J. Is
ely.
200
6. "
Seas
onal
and
Die
l Mov
emen
ts a
nd H
abita
t U
se o
f Rob
ust R
edho
rses
in th
e Lo
wer
Sav
anna
h R
iver
, Geo
rgia
, and
Sou
th C
arol
ina.
" Tr
ansa
ctio
ns
of th
e A
mer
ican
Fis
herie
s Soc
iety
135
(5):1
145-
1155
. (N
o M
L#).
NR
C
0000
18
E.C
. 1.2
Le
tter f
rom
Uni
ted
Stat
es D
epar
tmen
t of C
omm
erce
, Nat
iona
l Oce
anic
and
Atm
osph
eric
A
dmin
istra
tion,
Nat
iona
l Mar
ine
Fish
erie
s Ser
vice
from
Wal
t Wils
on, F
ishe
ries B
iolo
gist
, Pro
tect
ed
Res
ourc
es D
ivis
ion
to N
RC
Sta
ff, O
ctob
er 2
4, 2
006,
“En
dang
ered
and
Thr
eate
ned
Spec
ies a
nd
Crit
ical
Hab
itats
und
er th
e Ju
risdi
ctio
n of
the
NO
AA
Fis
herie
s Ser
vice
.” (M
L063
2001
27).
NR
C
0000
19
E.C
. 1.2
G
eorg
ia D
epar
tmen
t of N
atur
al R
esou
rces
(GD
NR
). 20
08. L
ocat
ions
of S
peci
al C
once
rn A
nim
als,
Plan
ts a
nd N
atur
al C
omm
uniti
es in
Bur
ke C
ount
y, G
eorg
ia. (
ML0
9006
0090
).
NR
C
0000
20
E.C
. 1.2
E-
Mai
l fro
m Je
nnife
r Pric
e, S
outh
Car
olin
a D
epar
tmen
t of N
atur
al R
esou
rces
, to
Reb
ekah
Krie
g,
Paci
fic N
orth
wes
t Nat
iona
l Lab
orat
orie
s, Ju
ly 2
6, 2
007,
“Fe
dera
l Thr
eate
ned
and
Enda
nger
ed
Spec
ies i
n th
e V
icin
ity o
f Vog
tle E
lect
ric G
ener
atin
g Pl
ant.”
(ML0
7214
0872
).
NR
C
0000
21
E.C
. 1.2
So
uth
Car
olin
a, R
are,
Thr
eate
ned
,and
End
ange
red
Spec
ies I
nven
tory
; Spe
cies
Fou
nd in
Bar
nwel
l C
ount
y. (M
L090
0601
26).
NR
C
0000
22
E.C
. 1.2
& 1
.3
Exce
rpts
from
: Col
lins M
.R. a
nd T
.I.J.
Smith
. 199
7. "
Dis
tribu
tions
of S
hortn
ose
and
Atla
ntic
St
urge
on in
Sou
th C
arol
ina.
" Nor
th A
mer
ican
Jour
nal o
f Fis
herie
s Man
agem
ent,
17:9
95-1
000.
(No
ML#
).
Part
y
Exh.
#
Witn
ess/
Pa
nel
D
escr
iptio
n
NR
C
0000
23
E.C
. 1.2
Ex
cerp
ts fr
om: H
alve
rson
et a
l. 19
97, S
avan
nah
Riv
er S
ite E
colo
gy E
nviro
nmen
tal I
nfor
mat
ion
Doc
umen
t. W
SRC
-TR
-97-
0223
, Wes
tingh
ouse
Sav
anna
h R
iver
Com
pany
, Was
hing
ton,
D.C
. (N
o M
L#).
NR
C
0000
24
E.C
. 1.2
C
ollin
s M.R
. and
T.I.
J. Sm
ith. 1
993.
"C
hara
cter
istic
s of t
he A
dult
Segm
ent o
f the
Sav
anna
h R
iver
Po
pula
tion
of S
hortn
ose
Stur
geon
." P
roce
edin
gs o
f the
Ann
ual C
onfe
renc
e of
Sou
thea
ster
n A
ssoc
iatio
n of
Fis
h an
d W
ildlif
e A
genc
ies 4
7:48
5-49
1. (M
L073
2407
26).
NR
C
0000
25
E.C
. 1.2
& 1
.3
Stat
us R
evie
w o
f Atla
ntic
Stu
rgeo
n (A
cipe
nser
oxy
rinch
us):
Prep
ared
by
the
Atla
ntic
Stu
rgeo
n St
atus
Rev
iew
Tea
m fo
r the
Nat
iona
l Mar
ine
Fish
erie
s Ser
vice
Nat
iona
l Oce
anic
and
Atm
osph
eric
A
dmin
istra
tion
Febr
uary
23,
200
7. U
pdat
ed w
ith c
orre
ctio
ns o
n Ju
ly 2
7, 2
007.
(ML0
8296
0581
).
NR
C
0000
26
E.C
. 1.2
G
raph
Sho
win
g W
ayne
sbor
o-Th
urm
ond
Dis
char
ge, D
ate
(1.2
2.05
- 10
.27.
08).
(ML0
8323
0089
) (B
lack
and
Whi
te C
opy.
No
ML#
for c
olor
cop
y).
NR
C
0000
27
E.C
. 1.2
Ex
cerp
ts fr
om: F
reem
an, F
.C. a
nd P
. Mar
cine
k, 2
006.
"Fi
sh A
ssem
blag
e R
espo
nses
to W
ater
W
ithdr
awls
and
Wat
er S
uppl
y R
eser
voirs
in P
iedm
ont S
tream
s" E
nvi.
Man
agem
ent v
ol. 3
8, n
o. 3
pp
. 435
-450
. Ent
ire d
ocum
ent a
t: (M
L083
3803
92).
NR
C
0000
28
E.C
. 1.2
H
isto
ric S
avan
nah
Stre
amflo
w G
raph
from
USG
S ga
ge #
021
9700
0 at
Aug
usta
, GA
(~19
04-2
007)
. (M
L082
9706
93).
NR
C
0000
29
E.C
. 1.2
& 1
.3
Lette
r fro
m U
nite
d St
ates
Dep
artm
ent o
f Com
mer
ce, N
atio
nal O
cean
ic a
nd A
tmos
pher
ic
Adm
inis
tratio
n, N
atio
nal M
arin
e Fi
sher
ies S
ervi
ce fr
om R
oy E
. Cra
btre
e, P
h.D
., R
egio
nal
Adm
inis
trato
r to
Will
iam
Bur
ton,
dat
ed A
ugus
t 11,
200
8, “
A B
iolo
gica
l Ass
essm
ent f
or th
e Sh
ortn
ose
Stur
geon
for t
he V
ogtle
Ele
ctric
Gen
erat
ing
Plan
t Ear
ly S
ite P
erm
it A
pplic
atio
n.”
(M
L082
4804
50).
NR
C
0000
30
E.C
. 1.2
& 1
.3
Sout
hern
Nuc
lear
Ope
ratin
g C
ompa
ny, D
raft
Inte
rim R
epor
t of F
ish
Impi
ngem
ent a
nd E
ntra
inm
ent
Ass
essm
ent a
t the
Pla
nt V
ogtle
Ele
ctric
Gen
erat
ing
Plan
t, Se
ptem
ber 2
008.
(ML0
8283
0945
).
Part
y
Exh.
#
Witn
ess/
Pa
nel
D
escr
iptio
n
NR
C
0000
31
E.C
. 1.2
Le
tter f
rom
J. A
. "B
uzz"
Mill
er, S
enio
r Vic
e Pr
esid
ent,
Nuc
lear
Dev
elop
men
t, So
uthe
rn N
ucle
ar
Ope
ratin
g C
ompa
ny, I
nc. t
o N
RC
Sta
ff d
ated
May
27,
200
8 w
ith a
ttach
ed Im
ping
emen
t and
En
train
men
t Mon
itorin
g U
pdat
e at
Pla
nt V
ogtle
. (M
L081
5100
22).
NR
C
0000
32
E.C
. 1.2
N
ote-
to-F
ile: T
rip re
port
of M
arch
7-9
, 200
7, to
ur o
f VEG
P U
nits
1 a
nd 2
. (M
L070
7400
99).
NR
C
0000
33
E.C
. 1.2
N
ote-
to-f
ile:
Trip
repo
rt of
Oct
ober
14,
200
8. (M
L082
6201
84).
NR
C
0000
34
E.C
. 1.2
Pa
ller M
.H. 1
992.
The
Influ
ence
of S
avan
nah
Riv
er D
isch
arge
and
Cha
ngin
g Sa
vann
ah R
iver
Site
(S
RS)
Coo
ling
Wat
er R
equi
rem
ents
on
the
Pote
ntia
l Ent
rain
men
t of I
chth
yopl
ankt
on a
t the
SR
S Sa
vann
ah R
iver
Inta
kes.
WSR
C-R
P-92
-100
1, W
estin
ghou
se S
avan
nah
Riv
er C
o., A
iken
, Sou
th
Car
olin
a. (M
L071
2001
82).
NR
C
0000
35
E.C
. 1.2
& 1
.3
Exce
rpts
from
: U.S
. Env
ironm
enta
l Pro
tect
ion
Age
ncy
"Nat
iona
l Pol
luta
nt D
isch
arge
Elim
inat
ion
Syst
em: R
egul
atio
ns A
ddre
ssin
g C
oolin
g W
ater
Inta
ke S
truct
ures
for N
ew F
acili
ties,"
66
Fed.
Reg
. 65
,256
. (D
ecem
ber 1
8, 2
001)
. (no
ML
#).
NR
C
0000
36
E.C
. 1.2
M
cFar
lane
R.W
., R
.F. F
riets
che
and
R.D
. Mira
cle.
197
8. Im
ping
emen
t and
Ent
rain
men
t of F
ishe
s at
the
Sava
nnah
Riv
er P
lant
. An
NPD
ES 3
16b
Dem
onst
ratio
n. D
P-14
94, E
.I. D
u Po
nt D
E N
emou
rs
and
Com
pany
, Sav
anna
h R
iver
Lab
orat
ory,
Aik
en, S
outh
Car
olin
a. (
ML0
7079
0211
).
NR
C
0000
37
E.C
. 1.2
Ex
cerp
ts fr
om: N
UR
EG-1
437
Vol
. 1 &
2 G
ener
ic E
nviro
nmen
tal I
mpa
ct S
tate
men
t for
Lic
ense
R
enew
al o
f Nuc
lear
Pla
nts,
Mai
n R
epor
t, Fi
nal R
epor
t. (1
996)
. Ent
ire D
ocum
ent:
(Vol
. 1
ML0
4069
0705
; Vol
. 2 M
L040
6907
38).
NR
C
0000
38
E.C
. 1.2
U
.S. A
rmy
Cor
ps o
f Eng
inee
rs (U
SAC
E). 2
006.
Dro
ught
Con
tinge
ncy
Plan
Upd
ate:
Sav
anna
h R
iver
Bas
in. D
raft
Envi
ronm
enta
l Ass
essm
ent a
nd F
indi
ng o
f No
Sign
ifica
nt Im
pact
. M
obile
/Sav
anna
h Pl
anni
ng C
ente
r, Sa
vann
ah D
istri
ct, U
.S. A
rmy
Cor
ps o
f Eng
inee
rs.
(ML0
8323
0104
).
Part
y
Exh.
#
Witn
ess/
Pa
nel
D
escr
iptio
n
NR
C
0000
39
E.C
. 1.2
U
S A
rmy
Cor
ps o
f Eng
inee
rs, S
avan
nah
Dis
trict
, Dra
ft En
viro
nmen
tal A
sses
smen
t and
Fin
ding
of
No
Sign
ifica
nt Im
pact
, Tem
pora
ry D
evia
tion
Dro
ught
Con
tinge
ncy
Plan
, Sav
anna
h R
iver
Bas
in,
Oct
ober
200
8. (M
L082
9605
88).
NR
C
0000
40
E.C
. 1.2
A
ucot
t, W
.R.,
S.R
.S. M
eado
ws,
and
G.G
. Pat
ters
on. 1
987.
Reg
iona
l Gro
und-
Wat
er D
isch
arge
to
Larg
e St
ream
s in
the
Upp
er C
oast
al P
lain
of S
outh
Car
olin
a an
d Pa
rts o
f Nor
th C
arol
ina
and
Geo
rgia
. Wat
er-R
esou
rces
Inve
stig
atio
ns R
epor
t 86-
4332
, U.S
. Geo
logi
cal S
urve
y, C
olum
bia,
So
uth
Car
olin
a. (M
L090
0607
59).
NR
C
0000
41
E.C
. 1.2
Fl
ow D
ata
from
Thu
rmon
d D
am D
isch
arge
and
USG
S G
auge
#02
1973
269
Nea
r Way
nesb
oro,
GA
. (M
L083
2403
62).
NR
C
0000
42
E.C
. 1.2
Ex
cerp
t fro
m: C
lark
e, J.
S. a
nd C
.T. W
est,
USG
S, G
roun
d-W
ater
Lev
els,
Pred
evel
opm
ent G
roun
d-W
ater
Flo
w, A
nd S
tream
-Aqu
ifer R
elat
ions
In T
he V
icin
ity O
f The
Sav
anna
h R
iver
Site
, Geo
rgia
A
nd S
outh
Car
olin
a. 1
997.
Ent
ire d
ocum
ent a
t: (M
L073
3309
61).
NR
C
0000
43
E.C
. 1.2
Ex
cerp
t fro
m: U
S G
loba
l Cha
nge
Res
earc
h Pr
ogra
m: T
he P
oten
tial C
onse
quen
ces o
f Clim
ate
Var
iabi
lity
and
Cha
nge
(200
0). (
ML0
9006
0226
).
NR
C
0000
44
E.C
. 1.2
Ex
cerp
t fro
m: I
nter
gove
rnm
enta
l Pan
el o
n C
limat
e C
hang
e: C
limat
e C
hang
e 20
07, S
ynth
esis
R
epor
t. (M
L090
0602
19).
NR
C
0000
45
E.C
. 1.2
Ex
cerp
ts fr
om: N
UR
EG 1
437,
Sup
plem
ent 3
4-G
ener
al E
nviro
nmen
tal I
mpa
ct S
tate
men
t for
Li
cens
es R
enew
al o
f Nuc
lear
Pla
nts,
Supp
lem
ent 3
4, R
egar
ding
Vog
tle E
lect
ric G
ener
atin
g Pl
ant,
Uni
ts I
and
2. D
raft
Rep
ort f
or C
omm
ent.
Entir
e do
cum
ent a
t: (M
L083
3803
25).
NR
C
0000
46
E.C
. 1.3
Ex
cerp
ts fr
om: R
ichm
ond,
A.M
. and
B. K
ynar
d. 1
995.
"O
ntog
enet
ic B
ehav
ior o
f Sho
rtnos
e St
urge
on, A
cipe
nser
bre
viro
stru
m."
Cop
eia
1995
(1 ):
72-1
82. (
No
ML#
).
NR
C
0000
47
E.C
. 1.3
Ex
cerp
ts fr
om: H
all J
.W.,
T.I.J
. Sm
ith, a
nd S
.D. L
ampr
echt
. 199
1. "
Mov
emen
ts a
nd H
abita
ts o
f Sh
ortn
ose
Stur
geon
, Aci
pens
er b
revi
rost
rum
, in
the
Sava
nnah
Riv
er."
Cop
eia
1991
(3):6
95-7
0. (
No
ML#
).
Part
y
Exh.
#
Witn
ess/
Pa
nel
D
escr
iptio
n
NR
C
0000
48
E.C
. 6.0
Ex
cerp
ts fr
om: U
S A
rmy
Cor
ps o
f Eng
inee
rs, E
R-1
105-
2-10
0, P
lann
ing
Gui
danc
e N
oteb
ook
(200
0). E
ntire
doc
umen
t at:
(ML0
8352
0607
).
NR
C
0000
49
E.C
. 6.0
U
S A
rmy
Cor
ps o
f Eng
inee
rs, E
R-2
00-2
-2, P
roce
dure
s For
Impl
emen
ting
NEP
A (1
988)
. (M
L083
5108
21).
NR
C
0000
50
E.C
. 1.2
A
P100
0 D
CD
Rev
isio
ns 1
5 an
d 16
Val
ues:
Sum
mar
y of
Coo
ling
Syst
em F
low
Rat
e C
hang
es.
(ML0
9006
0290
).
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION
BEFORE THE ATOMIC SAFETY AND LICENSING BOARD
In the Matter of ) ) SOUTHERN NUCLEAR OPERATING CO. ) Docket No. 52-011-ESP ) (Early Site Permit for Vogtle ESP Site) )
CERTIFICATE OF SERVICE I hereby certify that copies of “NRC Staff Initial Statement Of Position On Joint Intervenors’ Contentions EC 1.2, EC 1.3, and EC 6” together with Exhibit List, Attachments, and Exhibits NRC000001 through NRC000050 have been served upon the following persons by Electronic Information Exchange this 9th day of January, 2009: Administrative Judge G. Paul Bollwerk, III, Chair Atomic Safety and Licensing Board Panel Mail Stop T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 (E-mail: [email protected])
Administrative Judge Nicholas G. Trikouros Atomic Safety and Licensing Board Panel Mail Stop T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 (E-mail: [email protected])
Administrative Judge James Jackson Atomic Safety and Licensing Board Panel Mail Stop T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 (E-mail: [email protected])
Office of Commission Appellate Adjudication U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 (E-mail: [email protected])
Emily Krause Law Clerk Atomic Safety and Licensing Board Panel Mail Stop T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 (E-mail: [email protected])
Office of the Secretary ATTN: Docketing and Service Mail Stop 0-16C1 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 (E-mail: [email protected])
- - - 2 -
Diane Curran, Esq. Harmon, Curran, Spielberg & Eisenberg, LLP 1726 M Street, NW Suite 600 Washington, DC 20036 (E-mail: [email protected])
Lawrence D. Sanders, Esq. Turner Environmental Law Clinic Emory University School of Law 1301 Clifton Road Atlanta, GA 30322 (E-mail: [email protected])
M. Stanford Blanton, Esq. Peter D. LeJeune, Esq. C. Grady Moore, III, Esq. Kenneth C. Hairston, Esq. Balch & Bingham LLP 1710 Sixth Avenue North Birmingham, AL 35203-2014 (E-mail: [email protected]; [email protected]; [email protected]; [email protected])
Moanica Caston, Esq. Southern Nuclear Operating Co., Inc. 40 Inverness Center Parkway P.O. Box 1295, Bin B-022 Birmingham, AL 35201-1295 (E-mail: [email protected]) Copy provided by e-mail only
Steven P. Frantz, Esq. Kathryn M. Sutton, Esq. Paul M. Bessette, Esq. Mary Freeze Morgan, Lewis & Bockius LLP 1111 Pennsylvania Avenue, NW Washington, DC 20004 (E-mail: [email protected]; [email protected]; [email protected]; [email protected])
Jeffrey Stair, Esq. Georgia Public Service Commission 244 Washington Street Atlanta, GA 30334 (E-mail: [email protected]) Copy provided by e-mail only
/signed (electronically) by/ Patrick A. Moulding Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O-15 D21 Washington, DC 20555-0001 (301) 415-2549 [email protected]