2010 FIFA World Cup™Transport Action Plan for 2010
Department of
Transport
Creating a Positive Public Transport
Legacy from the 2010 FIFA World Cup™
Progress Report and Way Forward
Contents
A. Implications of Guarantees for the SectorB. Main objectivesC. Transport Action Plan for 2010D. Acceleration of National Transport ProgrammesE. PTIFF. Clarification of RolesG. Typical 2010 ScenariosH. Programme PhasesI. WC Operational Planning
Efficient and safe transport
Sufficient air & land transport operators
•Develop sector vision, goals and objectives
•Transport infrastructure, systems and operations improvements
•coordination
•Travel demand estimates
•X- operators
•Safe quality vehicles
•Accreditation
A1. Implications of Guarantees for the Sector
High quality transport for FIFA Family
Spectator transport
•Expected number
•High quality vehicles
•Cooperation with other sectors
•Sponsors involvement
•Expected numbers of international visitors
•Travel demand
•Accommodation- stadium links
•Tourism and Fan Fest transport requirements
•Quality vehicles
A2. Implications of Guarantees for the Sector
Zero probability of failure
Waiting time (5 minutes officials & players; 10 for accredited media people)
•Develop sector vision, goals and objectives
•Transport infrastructure, systems and operations improvements
•Travel demand estimates
•X- operators
•Safe quality vehicles
•Accreditation
A3. Implications of Guarantees for the Sector
B. Main Objectives
• Objective 1 - Support the success of the 2010 FIFA World Cup. The eyes of the world will be on South Africa. Transport must run so smoothly as to be invisible
• Objective 2 - The high profile of the events offers RSA a chance to accelerate the pace of implementation, and catalyse a lastingtransport legacy
G. Transport Plan for 2010 / Action Agenda
C. Transport Action Plan for 2010.Version Year 2006Action Agenda for ensuring Operational Success and Establishing a Legacy of Improvement from the Investment towards the 2010 FIFA World Cup
Initially a document to ensure EngagementArticulates Vision, Objectives & Principles for Successful World Cup Transport leaving a Legacy of Transport ImprovementSets out Planning and Implementation FrameworkReports on Status of PlanningProposes Implementation Plan Backed by PTIF Fund totalling R3.741bnCommunicates initial development programme to achieve World Cup readiness
Passenger rail transport integration [1st
phase (SARCC –Metrorail consolidation done)] 2nd phase (incorporation of long distance Shosholoza Meyl scheduled for mid 2007). Total rail investment 2006-09= R10,3bn. Expansion of bus services & metered taxis in host cities.Sections of the Gautrain that will have a direct bearing on the World Cup will be ready by 2010
D1. Opportunity to Accelerate Prioritised Transport Programmes
Taxi Recapitalisation- New taxi vehicles rollout & scrapping of old vehicles- Sept. 2006. Target -80% implementation by 2010
Public Transport Strategy by Jan. 07 Lekgotla
D2. Opportunity to Accelerate Prioritised Transport Programmes
•Aviation:
•ACSA revised their capital expenditure programme to address 2010 needs.
•Key projects have been brought forward to ensure adequate capacity at the following airports:
•New airport at the Dube Trade Port to be completed by 2010
•Upgrades:Johannesburg, Cape Town and Port Elizabeth Airports (among others)
Expansion of international and domestic air transport services (airlift strategy)
D3. Opportunity to Accelerate Prioritised Transport Programmes
E. Public Transport Infrastructure Fund (PTIF)
Established Mar. 2005. Public transport conditional grant.Focus on infrastructure investments to secure improved priority and better operations for public transport and NMT, supporting WC2010 needs.DOT will set KPIs and targets, and oversee expenditure2005/06 – R241,7m; 2006/07 – R700m; 2007/08 – R1800m; 2008/09 – 1000m, TOTAL = R3.74bnKey Issue: As we move closer to 2010. Does the fund need to change its focus / separate fund be established to ensure operational readiness ?
F. PTIF Projects
Request areas predominantly road and rail public transport and non-motorised transportProject types include planning, physical infrastructure and systemsPlanning includes transport planning, detailed project plans anddesignsInfrastructure and systems projects include:Public transport road infrastructure Public transport interchange facilities Rail upgrades Inter-modal facilities
ITS infrastructure and systemsNMT infrastructure Inner-city mobility systems Call centre systems
Key Requirements for PTIF Funding
• Projects to prioritise public transport• Projects to satisfy both long term mobility (legacy) and event
specific mobility requirements• Projects to have continuity from planning to execution• Projects to be executed in accordance with EPWP
requirements• Projects to be based on local IDPs and ITPs, addressing
community access and mobility needs• Projects to be practical and implementable ahead of 2010
Projects for 2005/06
Entity Project
Cape Town ITS system and public transport call centre
Ethekwini ITS system , Warwick junction upgrade and Reunion station upgrade
Tshwane Planning and preparations for construction of interchange
Johannesburg North/South public transport corridor (Phase 2: Soweto to Parktown)
Nelson Mandela
Khulani public transport corridor
Projects for 2005/06 (2)
Entity Project
Rustenburg Planning for taxi facilities and Non Motorised Transport
Polokwane Road upgrading for public transport and Non Motorised Transport Infrastructure
Mangaung Mangaung activity corridor and Elizabeth street pedestrianisation
Mbombela Planning support
Klerksdorp Planning support
Projects for 2006/07
Entity ProjectCape Town N2 Airport-City link, Klipfontein corridor, City wide NMT system, ITS
Ethekwini Public Transport Call Centre
Tshwane Inner City Distribution System, Pedestrian link (Loftus stadium to rail station)
Johannesburg SPTN network improvement, ITS, Stadium precinct improvements, Inner City Distribution system
Nelson Mandela
Coastal cycle & pedestrian ways, Uitenhage &Stanford corridors, completion og Khulani corridor, disabled facilities and ITS
Projects for 2006/07 (2)
Entity ProjectSARCC Station upgrades, pedestrian facilities, communication and safety
systemsPolokwane NMT infrastructure upgrading (Phase 1)
Mangaung Blooemfontein public transport interchange, selbourne Ave pedestrianisation
Ekurhuleni NMT facilities for Tembisa, Vosloorus, and intermodal facilities in metro
Mbombela Hazyview pedestrian bridge
F1. Clarification of Roles
• DOT– National Transport
Plan for 2010– Coordination & focal
point for info exchange– Technical support– Evaluate Priority
Statements– Manage PTIF
• Host Cities– Local Transport Plan
for 2010 (linked to the ITP)
– Prepare Priority Statements
– Deliver projects– Integrate local plan
with other sectors within the cities
F2. Clarification of Roles
• DOT– Remove critical
barriers– Monitor and evaluate– Interdepartmental
coordination– National operational
plan (framework.– Develop guidelines &
set standards
• Host Cities– Reporting (i.t.o. PTIF,
DORA, PFMA & MFMA)
– Local operational plan
Jointly (& with NT) develop an appropriate Funding Protocol
G. TYPICAL 2010 SCENARIONS
ARE WE READY FOR THE CHALLENGE?
Initial Travel Demand Estimates
64 MatchesAv. Capacity of 50 000 per match3.2 million tickets300 000 International visitors with tickets attending on av. 4-5 matches 200 000+ Long haul and cross border arrivals without tickets? Match scheduling agreements Regional and local movements? Plans for and estimates for Fan Fests
Low
Firm
Degree of Certainty
FACTORS AFFECTING ABILITY TO ACCOMMODATE TRAVEL DEMANDS
• Level of organised transport response to influence and manage travel patterns, mode selection etc
• Venue clustering, influencing match schedules
• Accelerating PT, transport management and NMT investment
• Reducing regular travel demands
Transport Factors Influence on WC Plans
• Tournament dates – must overlap with academic holidays (reduced demands, buses available, use student accommodation and campuses for WC)
• Match schedule – work within FIFA requirements to cluster venues to moderate transport demands within each market (air, land-distance, local)– vital.
• Venue city decisions on Fan Fests, other Public Viewing, and Training Venues must consider serving by transport as a critical factor.
Outline of Travel Demand Implication of Different World Cup Match Scheduling
Approaches 2010 WC Match Scheduling Scenario
Regional trips by ticket holders
1. Venue Clustering applied + overlap with academic holidays
Day 12-1580 000 to 100 000 trips
2. No Venue Clustering +20% on scenario 1 trips
3. Weeks 1 and 2 do not overlap with academic holidays
+20% on background travel demands
4. Scenario 1 and Each Group assigned to 3 venues for opening round
-25% on scenario 1 demands
MATCH SCHEDULING PRINCIPLES
• 10 venues submitted to FIFA • FIFA preferred tournament dates 31 days, 11 June to 11 July 2010(?)• Schedule where possible 2 free days between matches in same venue • Number of matches typically weighted to larger stadia and main cities• FIFA practice that each team plays no more than once in any venue
during 1st Round.• Each venue will play host to 2 matches featuring one of the top
seeded teams.• Match start times will be influenced by world broadcast peak audience.• Significant recognition of host country’s requirements &
constraints
OVERLAP OF ACADEMIC HOLIDAYS AND 2010 WORLD CUP
Move Move
Pressure on local transport
Pressure on inter-city land transport
Pressure on domestic airlines
TRANSPORT PRESSURES – NATIONAL PERSPECTIVESHOWING THE THREE PROPOSED INTER-VENUE
TRAVEL SYSTEMS
Venue ClusteringLimit to one match in each venue cluster each day, apart from days 12-15
This match schedule applies the principle of venue clustering to limit the demands on the three inter-venue transport travel systems
BUSIEST DAYS (DAY 15 – ALL MODES)
AIR PASSENGERS AT PEAK OF WORLD CUP
Domestic Airline Daily Capacity
Stretched to capacity on all World Cup days
Up to 80% above forecast capacity in 2010 for busiest days.
DAY 15, COACH & RAIL PASSENGERS
26, 800 pax. inter city trains
460, 50 seat coaches
THESE ARE GAPS. CURRENTCOACH FLEET WILL BE TAKEN UP BYSPECIAL TARGET GROUPS
VERY FEW AVAILABLE FOR INTER-CITY WORLD CUP SERVICES
Initial Estimate of number of vehicles required for local venue transport: All
venues
• 60 train-sets• 2400 buses for venue cities• 6000 minibus taxis• Full hire car fleet• Full tourism charter / shuttle fleet
} Vehicle and } system quality} issues
H. Programme Phases
PHASES OF WC TRANSPORT DEVELOPMENT
2004/5 2006 2007 2008 2009 2010
Alignment. Plans and approvals for accelerated Infrastructure Investment
Resourcing, Agreeing Operational Concepts, High Level Plans. Operations Funding, Procurement Detailing Operational Plans (inc. Finance plan), Systems Development and Initial TestingSystems on-line. Operations and Vehicles Delivery, Testing. Refinement and Running of Events
I. World Cup Operations Planning
Aviation
Distance PT (Road & Rail)Host Cities Integrated WC Ops Plans-Challenge Disparate capacities in host cities
X-Border Road
Road Safety & Road Traffic Man.
National Roads Infx & Sys. Man.
Freight TransportTransport Sectors
Focus International Regional Venue City
Other Sectors with key Transport Linkage
Security
Dept. Sport (LOC Stadiums, WC Ticketing, FIFA Family)
Home affairs / CustomsDEAT (Accommodation and Tourism)
Communications (WC Information & Info Systems)
THANK YOU