    InterimClaimforanExtensionofTimeandresultantand

    overtimecosts

    SubmittedbyWesternConstructionCo.

    ContractNo:MK108007035-W-C02-001

    6th

    July2010

    A wholly owned subsidiary of

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    2/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page2of41

    TABLEofCONTENTS

    1 Introduction..................................................................................................................... 31.1 Thisdocument .......................................................................................................... 31.2 FormationofContract............................................................................................... 3

    2 ExecutiveSummary.......................................................................................................... 82.1 TheContract ............................................................................................................. 82.2 Delays ....................................................................................................................... 82.3 Quantum................................................................................................................... 8

    3 StatementofClaim .......................................................................................................... 93.1 Extensionoftime ...................................................................................................... 93.2 Delay,disruptionandresultantincreasedcosts .......................................................113.3 WaiverandEstoppel ................................................................................................123.4 FailuretoprovideaccesstotheWorksinatimescalenecessarytoachievePracticalCompletionofthePortionsortheWorksasawhole ........................................................143.5 FailuretoprovideconstructioninformationinatimescalenecessarytoachievePracticalCompletion.........................................................................................................15

    4 Time ...............................................................................................................................164.1 Programme..............................................................................................................16

    5 Overarchingcauseofdelay .............................................................................................185.1 MaladministrationbyTiwestRepresentative ...........................................................185.2 TiwestRepresentativeactsofpreventiongenerally .................................................20

    6 Eventsgivingrisetoentitlement.....................................................................................23 6.1 Introduction.............................................................................................................236.2 DelayEventandoractsofpreventionIssueofInformationforConstructionandaccesstoSite ....................................................................................................................236.3 Theseparationofevents..........................................................................................39

    7 TheQuantumofourClaim..............................................................................................40 8 ScheduleofAnnexureandExhibits .................................................................................41

    8.1

    Annexure .................................................................................................................41

    8.2 Exhibits ....................................................................................................................41

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    3/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page3of41

    1 INTRODUCTION1.1 Thisdocument1.1.1 ThepurposeofthisdocumentistodemonstratethattheWesternConstruction

    Co.(theContractor)isentitledtoanExtensionofTimeandresultantcosts.

    1.2 FormationofContract1.2.1 Tiwest,theownerandoperatoroftheplant,engagedProteusEPCMEngineers

    (TiwestsRepresentative)asitsagent.

    1.2.2 TiwestissuedtheProjectDocumenton16thMarch2009fortendertotheContractorforpricing.Thisdocumentwasinrespectofthesteelwork,

    mechanicalandpipingworksassociatedwiththeTiwestExpansionProject.For

    theavoidanceofdoubtthecivilconcrete,electricalandinstrumentationworks

    associatedwiththeexpansionprojectwereexcludedfromthescopeandwereto

    becarriedoutbyothers.

    1.2.3 On24thAugust2009theProjectDocumentwasIssuedforConstruction.1.2.4 ThePlant1.2.5 TheTiwestKPPisaTitaniumDioxide(TiO2)pigmentplantoperatingunderthe

    ChlorideRoute.Inthisprocess,theTitaniumbasedore(SyntheticRutile)is

    reactedwithChlorine(Cl2)gastomakeTitaniumTetrachloride(TiCl4)gas.Thisgas

    isseparatedfromtheothermetalchlorides,condensedandpurifiedbefore

    beingreactedwithpureOxygen(O2)toformTiO2.TheTiO2iscleaned,treatedand

    processed,beforebeingpackedinto25kgor1tonnebagsforsale.

    1.2.6 TheproposedexpansionoftheKPPwillincreaseproductionfrom116,000tonnesperannum(tpa)offinishedpigmentproductto153,000tpa.

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    4/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page4of41

    1.2.7 TheTiwestKPPisbroadlysegregatedintosix(6)geographicareascalledproductionunits.TheContractorisresponsibleforallSteelwork,Mechanicaland

    PipingWorksinalloftheseareas.Theseareasare:-

    a) Unit100-containsthereceivingandstoragefacilitiesfortherawingredients,SyntheticRutileandPETCoke

    b) Unit200-containsthechlorinationandTiCl4purificationequipmentc) Unit300-receivespureTiCl4andreactsitwithpureOxygento

    producecrudeTiO2pigment.Unit300alsocompressestheresulting

    ChlorinegasforrecyclingbacktoUnit200

    d) Unit400-receivesthecrudepigmentandmakesitintoapresentablebaggedproductforsale

    e) Unit500-encompassesallthechemicalstorageanddistribution,eitherofreactantsorproducts.Unit500alsocontainsalltheservices

    forthesite

    f) Unit600-processesthesiteprocesseffluentbeforedischargingtheneutralised,clearliquorintoCockburnSound

    1.2.8 TheContract1.2.9 Thenoticeofnoticeofaward,whichisdetailedbelow,providesthattheWorks

    shallbeinaccordancewiththefollowingdocuments:-

    a) Thetenderdocumentsb) TermsandconditionsofTiwestConstructionContractamendedas

    agreed

    c) TheContractorstendersubmissionreceivedbyTiwest4thMay2009

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    5/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page5of41

    d) Posttenderclarificationsandadjustmentsagreedpriortothenoticeofaward

    i) Includingrevisedconstructionschedule1.2.10 CommencementandCompletion1.2.11 TheContractorwastomobiliseon15thJuly2009.TheWorkscomprisedof

    SeparablePortionseachwithdifferentCompletionDates.Theseportionsareset

    outbelow:-

    a) Unit100i) Commencesitework17thAugust2009ii) Practicalcompletion30thJanuary2009

    b) Unit200i) Commencesitework5thAugust2009ii) Practicalcompletion18thFebruary2010

    c) Unit300i) Commencesitework21stAugust2009ii) Practicalcompletion10thFebruary2009

    d) Unit400i) Commencesitework27thAugust2009ii) Practicalcompletion30thMarch2010

    e) Unit500i) Commencesitework24thAugust2009ii) Practicalcompletion4

    th

    March2010

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    6/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page6of41

    f) Submitasbuilt31stMarch20101.2.12 TheresaclearerrorwithintheCommencementdateandPracticalCompletion

    dateofUnit100andUnit300asittheyduetobecompletedpriortoits

    commencement.Giventhisambiguitythedateswithintheapproved

    programmearetakenasagreed.

    1.2.13 NoticeofAwardandContractPrice1.2.14 Tiwestscorrespondencedated29thJune20091awardedtheContracttothe

    Contractorforthesumof$15,590,671.00.Thesumwasmadeupof:-

    ScheduleReference Description Price(AUD)

    A1.1 Contractorindirect $5,317,437.00

    A1.2 SteelWorks $2,769,012.00

    A1.3 MechanicalWorks $1,601,537.00

    A1.4 PipingWorks $5,386,734.00

    A1.5 PipingTieinWorks $581,951.00

    ContractPrice $15,656,671.00

    1TiwestPtyLtdletterdated29

    thJune2009

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    7/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page7of41

    1.2.15 TheContractoracknowledgedreceiptoftheaboveletterandadvisedthatitwouldworktothetermssetoutthereinon30

    thJune2009

    2.

    2WesternConstructionCo.letterdated30

    thJune2009

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    8/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page8of41

    2 EXECUTIVESUMMARY2.1 TheContract2.1.1 2.2 Delays2.2.1 2.3 Quantum2.3.1

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    9/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page9of41

    3 STATEMENTOFCLAIM3.1 Extensionoftime3.1.1 Clause7.3oftheContractprovides:-

    TheContractorisentitledtoanextensionoftimetotheDatefor

    PracticalCompletionif,andonlyif:

    (a) theContractor:

    (i) giveswrittennoticetoTiwest'sRepresentative,ofthe

    factoflikelihoodofdelaynotmorethan14daysafter

    thecommencementofthecauseofdelay;and

    (ii) provideswiththatnoticedetailsofthecauseofthe

    delayandhowPracticalCompletionislikelytobe

    delayed;

    (b) theContractorgivesTiwest'sRepresentative,within14days

    afterthecessationofthecauseofthedelay:

    (i) awrittenclaimforextensionoftimespecifyingthe

    numberofdaysclaimed;

    (ii) detailsofwhythecauseofthedelayactuallycausedthe

    delay,includingastatementofthefactsandthe

    provisionsofthisContractonwhichtheclaimisbased;

    (iii) detailedevidenceinsatisfactionoftherequirementsof

    clause7.3(c);and

    (iv) allotherinformationreasonablyrequiredbyTiwest's

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    10/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page10of41

    Representative;and

    (c) theContractorreasonablysatisfiesTiwest'sRepresentativein

    itsclaimunderclause7.3(b)that:

    (i) PracticalCompletionhasactuallybeendelayed:

    A. priortotheDateforPracticalCompletion,ina

    mannerwhichwillpreventtheContractorfrom

    achievingPracticalCompletionbytheDatefor

    PracticalCompletion,unlesstheDatefor

    PracticalCompletionisextended;or

    B. aftertheDateforPracticalCompletion,ina

    mannerwhichwilldelaytheContractorin

    achievingPracticalCompletion;

    3.1.2 MoreoverSpecialCondition3provides:-

    SC.3DelayandDisruption

    a) FurthertoClause7.2andforthepurposesofclarification,in

    theeventtheContractorisunabletoperformhisobligationsundertheContractduetoanydelay,interferenceordisruption

    (otherthanthatcausedbytheContractor)theContractoris

    entitledtobepaidstandbyratesinaccordancewithSchedule

    C1fortheaffectedlabour,plantandequipment.

    b) Intheeventthatthedelay,interferenceordisruptionaffects

    onlyoneareaoftheplantandlastsforaperiodnotexceeding

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    11/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page11of41

    onehour,Tiwestshallnotbechargedstandbyonthebasisthat

    theContractorsemployeecanbere-deployedtoanotherwork

    area.

    c) Ifthedelay,interferenceordisruptionaffectsmorethanone

    areaoftheplantorlastsforaperiodofmorethanonehour

    thentheContractorisentitledtochargestandbyratesfora

    minimumofonehourorthedurationofthedelay,interference

    ordisruptionwhicheverisgreater.

    3.1.3 TheContractorcontendsthatithasbeendelayedanddisruptedasaresultofTiwestRepresentativesfailuretoprovideConstructionInformationina

    timescaleconsistentwiththeapprovedprogramme.Further,theContractor

    contendsthatitisentitledtoanextensionoftimeasaresultofTiwest

    Representativesfailure.

    3.2 Delay,disruptionandresultantincreasedcosts3.2.1 Clause7.2(b)oftheContractDocumentprovides:-

    TheContractorisentitledtotheactual,directandunavoidableon-Site

    costsitcanestablishtothesatisfactionofTiwest'sRepresentativeit

    hasreasonablyincurredasaresultofthedelaycausedby:

    (i) abreachbyTiwestofthisContract;

    (ii) avariationtotheWorkundertheContractdirectedunder

    clause8.1;or

    (iii) thesuspensionoftheexecutionoftheWorkundertheContract

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    12/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page12of41

    pursuanttoawrittendirectiongivenunderclause7.8(a),unless

    thatdirectionwasgivenasaresultofabreachbythe

    ContractorofitsobligationsunderthisContract,

    forwhichtheContractorhasbeengrantedanextensionoftimetothe

    DateforPracticalCompletionunderthisContract.

    3.2.2 TheContractorcontendsthatasaresultofitsentitlementtoanextensionoftime,forwhichTiwestanditsRepresentativeareculpable,itisentitledto

    recoveractual,directandunavoidableon-Sitecosts.

    3.3 WaiverandEstoppel3.3.1 ThewidespreadinterpretationofWaiverandEstoppelreferstoconductwhich

    makesitunfairor,inequitableorunconscionableforthepromiseetoinsistona

    rightthatithas,bywayofitsconduct,leadtheotherpartytobelievewillno

    longerbeutilised.Thispositionhastoalterandbeunconscionableforitto

    apply;theutilisationofaconditionprecedent,orasitismorecommonlyknown

    atime-bar,whenithaspreviouslybeendisregardedamountstothis.

    3.3.2 Estoppel3.3.3

    Estoppelisaprinciplewhichprecludesanentityorpersonfromdenyingthetruthofastatementmadebyhimorfromallegingthatafactisotherwisethanit

    appearedtobefromthecircumstances.Thereareanumberoftypesof

    estoppelalthoughforthepurposeofthisdocumenttheinterestlayswiththatof

    estoppelbyrepresentationorconduct.

    3.3.4 Tiwesthas,byitsconduct,establishedthattheDateforSubstantialCompletionhas,orwastobe,revisedandthatthecostsassociatedwithsuchextension

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    13/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page13of41

    wouldbedealtwithatalaterdate.Ithasdonethisby:-

    a) IssuingConstructionInformationaftertheDateforSubstantialCompletion

    b) IssuingVariationsaftertheDateforSubstantialCompletionc) Waivingitsrighttoenforcethetimebarassetoutunderthe

    Contract

    3.3.5 Waiver3.3.6 Waiveristherelinquishmentofarightorremedywhichmaybebyexpress

    writtenstatement,impliedand,orbyinactioninenforcingaright.Therefore,in

    theeventthattheContractorfailstoenforceatimebarduringtheperiodfor

    completionitmaynotseektoestablishadefenceonthatbasisatornearingits

    conclusion.

    3.3.7 HudsonsBuildingandEngineeringContractsisconsideredanauthorityonsuchmatters.Thereinitstatesthat:-

    ...thecourtshavenotbeenslowtoapplyprinciplesofwaiveror

    estoppels,orimpliedpromiseorunjustenrichment,soastopreventan

    ownerinappropriatecircumstancesfromsettingupadefenceofnon-

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    14/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page14of41

    compliancewithcontractualrequirementsofformforvariedwork.3

    3.3.8 TheconductoftheContractorhasbeenthatishaswaiveditsrightstoenforcethetimebarinrespectof:-

    a) Noticeofdelayb) Theextensionoftimeprovisionsc) Noticeofdelayanddisruptioncosts

    3.3.9 TheContractorcontendsthatTiwesthasbywayofitsconductandotherwise:-a) WaiveditsrighttoenforceanytimebarwithintheContract

    3.3.10 TheContractorfurthercontendsthatanyenforcementofsuchclauseswouldbeanunjustenrichmentonthepartoftheTiwest.

    3.4 Failure to provide access to the Works in a timescalenecessary toachieve Practical CompletionofthePortions

    ortheWorksasawhole

    3.4.1 TiwestanditsRepresentativefailedtoprovideaccesstotheWorksinaccordancewiththeagreedprogrammeorinatimescaleconsistentwiththe

    DateforSubstantialCompletion.Moreover,itshouldbenotedthatfailureto

    provideaccessconstitutesanactofpreventiononthepartofTiwest.Thecourt

    3 Wallace: I.N. Duncan, (1994) Hudsons Building and Engineering Contracts, Eleventh Edition, London ,

    Sweet&Maxwell,Section7.042atp.903

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    15/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page15of41

    casesbelowprovidethatTiwestoritsRepresentativemaynotenforcethetime

    barinrespectofprovidingnoticeintheeventofadelayoranactofprevention:-

    a) GaymarkInvestmentsPropertyLtdvWalterConstructionGroup(1999)16BCL449

    b) AbigroupContractorsPtyLtdvPeninsulaBalmainPtyLtd[2001]NSWSC752

    c) BeckhausvBrewarrinaNo.2[2004]NSWSC11603.4.2 Therefore,theContractorcontendsthatithassuffereddamageasaresultofthe

    actsofpreventionandthatthetimebarisnotapplicable.

    3.5 Failure toprovideconstruction information ina timescalenecessarytoachievePracticalCompletion

    3.5.1

    TiwestRepresentativehasissuedConstructionInformationinatimescaleinconsistentwiththeDateforPracticalCompletionfortheSeparablePortions,or

    necessarytoachievetheDateforPracticalCompletion.Moreover,ithasissued

    ConstructionInformationaftertheDateforSubstantialCompletionpreventing

    theContractorfromachievingthisDate.

    3.5.2 TheContractorcontendsthatithasincurreddamageasaresultoftheTiwestRepresentativefailingtoissueConstructionInformationinatimescalenecessary

    toachieveSubstantialCompletion.AsaresultofthisfailuretheContractorhas

    beenpreventedfromcompletingitsWorksonorbeforetheDateforSubstantial

    Completion,fortheSeparablePortionsorasawhole,andhasincurreddamage.

    TheContractorfurthercontendsthatTiwestRepresentativeisprecludedfrom

    utilisingtheconditionprecedent,ortimebar,asadefenceasaresultofthe

    abovecaselawandthatanyattempttodosowouldbeunconscionable.

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    16/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page16of41

    4 TIME4.1 Programme4.1.1 Clause2.2.1.3oftheScopeofWorksprovides:-

    Thebulkoftheworkshalltakeplacewhiletheexistingplantisfully

    operational.ThereforetheContractorshallberequiredtocarefullyplan

    theworkandliaisewithTiwestonadailybasistoplanworkaheadto

    avoidpotentialriskstopersonnel,equipmentandproductionandto

    minimisedelaysingainingaccesstoworkareas.

    Whenpreparingforplannedshutdowns,theContractorshallliaise

    continuouslywithTiwestonsitetoensuretheworkissafelycoordinated

    andintegratedwithothershutdownactivities

    TheContractorsWorkScheduleshallbeakeycomponentofthe

    managementplans[Emphasisadded].TheContractorshallprepareand

    maintainaWorkScheduleinGanttChartformusingPrimaveraVersion5

    (orabove)software.

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    17/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page17of41

    4.1.2 Itisevidentfromthetextabovethattheworkscheduleisoffundamentalimportanceandhadtobestrictlyadheredto.Moreover,on9

    thJuly2009,Tiwest

    RepresentativeissuedtheContractoralistofkeydatesforthecompilationof

    thebaselineprogramme4.

    4.1.3 TheContractorsprogrammedated20thAugust2009wassubmittedandapprovedasthebaselineprogrammeon25

    thAugust2009

    5.

    4.1.4 ActivityWCC1020identifiesthedatefortheissueofconstructioninformation.Anextractofthissectionoftheprogrammeisshownbelow:-

    4.1.5 ItisthereforeevidenttoTiwestRepresentativethattheinformationwasrequiredtobeissuedonorbythe29

    thJune2009andanyfailuretoadhereto

    thisdatewouldresultindelaytotheproject.

    4ProteusECPMEngineersletterdated9th

    July2009

    5WesternConstructionCo.letterdated10

    thNovember2009

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    18/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page18of41

    5 OVERARCHINGCAUSEOFDELAY5.1 MaladministrationbyTiwestRepresentative5.1.1 ItshouldbenotedthattheContractormustdispatchtheburdenofproofuponit

    toestablishanextensionoftime.Further,thislevelofproofisonthebalanceof

    probabilityandnotbeyondallreasonabledoubt.Itisacommonmisconception

    thatthelatterisapplicablealthoughthisisreservedforcriminalmatters.

    5.1.2 TiwestRepresentativehasfailedto:-a) Issueconstructioninformationinatimescaleconsistentwiththe

    baselineprogram

    b) Providefreeissuematerialinatimescaleconsistentwiththebaselineprogram

    c) EvaluatetheContractorsclaimsforanextensionoftimeinafairandreasonablemanner

    d) AwardanextensionoftimetoeachSeparablePortionratherthantheDateforPracticalCompletion

    5.1.3 Further,TiwestRepresentativehasinstructedtheContractortoprovideadditionallabourtositeasaresultofslowprogressatthesametimeithasfailed

    toprovidetheContractorinformationthatwouldallowittoprogressworkfronts.

    5.1.4 TheresultofTiwestRepresentativesactionswheretoincreasetheworkforce,andincurassociatedadditionalcost,atatimewhentherewerefewareasthat

    theContractorcouldactuallyprogresstheWorksasaresultofthelackof

    ConstructionInformation.ThisismaladministrationbyTiwestRepresentative.

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    19/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page19of41

    5.1.5 Commencementonsite5.1.6 TheContractorsletterof29thJuly20096recordsthatithadbeenprevented

    fromcommencingtheWorksonsitebyTiwestRepresentativesduetothe

    programmenotbeingapproved.Asidentifiedabovetheprojectwasclearlyfast

    trackandanydelayincommencementwouldhaveasignificanteffectonthe

    overallprogramme.Moreover,itshouldbenotedthatthiswasthesamedate

    thattheConstructionInformationwastobeissuedeitheronorby.Withinthe

    samecorrespondencetheContractorrecordedthat:-

    a) Itwasoutstandingmarkingplandrawingsforthemajorityofthestructuralwork

    b) Ofthe715linesonthelinelistithadonlyreceived128linesinisometricform

    c) Thatitwouldtakeupto4weekstomobilisegiventhatitwasntgivenaccess

    5.1.7 NotwithstandingTiwestRepresentativesfailuretoissuetheConstructionInformationinatimescaleconsistentwiththebaselineprogrammeithas

    directedtheContractortoincreaseitslabourresources7.MoreoverTiwest

    Representativenotesthattheadditionalmanpowerhasnotincreased

    productivity.Whilstitisinsomewhyattemptingtoinferthatthereissomekind

    6WesternConstructionCo.letterdated29th

    July2009

    7ProteusECPMEngineersletterdated13

    thJanuary2010

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    20/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page20of41

    ofmanagementissueitisapparentthattheincreaseinresourcesissimply

    addingtotheexistingproblemofthelackofConstructionInformationandlack

    ofworkfrontsasaresultofthisinformationnotbeingissued.

    5.2 TiwestRepresentativeactsofpreventiongenerally5.2.1 PursuanttothetermsoftheContractTiwsestanditsRepresentativeare

    responsibleforissuingthenecessaryConstructionInformationinatimescale

    consistentwiththeDate/sforPracticalCompletion.Moreover,theapprovalof

    thebaselineprogramme,whichsetoutthedateforreleaseofallConstruction

    Informationas29th

    June2009,providesthattheTiwestRepresentativehas

    agreedthedatesthatitwouldissuethisinformation.

    5.2.2 OnreviewofthedocumentregisterissuedbyTiwestRepresentativeitisapparentthatthemajorityoftheConstructionInformationwasissuedafterthe

    abovedate.AcopyoftheregisterissuedcrossreferencedagainsttheSeparable

    PortionDateforPracticalCompletionandthedateforissueofallConstruction

    IssueinformationiscontainedatAppendixA.

    5.2.3 Unit1005.2.4 AlloftheinformationlistedwithintheregisterthatisidentifiedasbeingforUnit

    100hasallbeenissuedafterthedateforreleaseofConstructionInformationset

    outinthebaselineprogramme.Further,informationhasbeenissuedafterthe

    DateforPracticalCompletion.

    5.2.5 InrespectofinformationissuedaftertheDateforSubstantialCompletionforthisSeparablePortionitrangesfrom4daysto285daysaftertheprogrammed

    date.

    5.2.6 TheConstructionInformationinrespectofthisSeparablePortionwasissuedonaverage100daysafterthebaselineprogrammedate.

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    21/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page21of41

    5.2.7 Unit2005.2.8 TiwestRepresentativefailedtoissueanyoftheConstructionInformation

    identifiedontheregistertothisSeparablePortionpriorto,oron,theapproved

    programmedate.Further,largeamountsoftheinformationwasissuedafterthe

    SeparablePortionDateforPracticalCompletion.

    5.2.9 TheConstructionInformationinrespectofthisSeparablePortionwasissuedonaverage165daysafterthebaselineprogrammedate.

    5.2.10 Unit3005.2.11 AsisthesamewiththeprecedingUnitsTiwestRepresentativefailedtoissueany

    oftheConstructionInformation,identifiedfromitsownregister,priortooron

    thedatesetoutinthebaselineprogramme.ConstructionInformationhasbeen

    issuedfrom7daysto344daysaftertheprogrammeddate.

    5.2.12 TheConstructionInformationinrespectofthisSeparablePortionwasissuedonaverage435daysafterthebaselineprogrammedate.

    5.2.13 Unit4005.2.14 Again,andasliketheUnitsabove,TiwestRepresentativehasfailedtoissueany

    oftheConstructionInformation,thatisidentifiabletothisSeparablePortion,

    priortoorontheprogrammeddate.Moreover,largequantitiesofthis

    informationwasissuedaftertheSeparablePortionDateforPractical

    Completion.

    5.2.15 ThedelayinissuingtheinformationbyTiwestRepresentativerangesfrom4daysand336daysaftertheprogrammeddatefortheissueofConstruction

    Information.

    5.2.16

    TheConstructionInformationinrespectofthisSeparablePortionwasissuedon

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    22/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page22of41

    average130daysafterthebaselineprogrammedate.

    5.2.17 Unit5005.2.18 Again,andasliketheUnitsabove,TiwestRepresentativehasfailedtoissueany

    oftheConstructionInformation,thatisidentifiabletothisSeparablePortion,

    priortoorontheprogrammeddate.Further,informationhasbeenissuedafter

    theDateforPracticalCompletionforthisSeparablePortion.

    5.2.19 ThedelayinissuingtheinformationbyTiwestRepresentativerangesfrom4daysand317daysaftertheprogrammeddatefortheissueofConstruction

    Information.

    5.2.20 TheConstructionInformationinrespectofthisSeparablePortionwasissuedonaverage122daysafterthebaselineprogrammedate.

    5.2.21 Releaseofinformationgenerally5.2.22 PursuanttothetermsoftheContracttheContractorwasrequiredtosubmitas-

    builtdrawingsonorby31stMarch2010.Itisclearfromtheinformation

    containedatAppendixAthatsubstantialinformationwasissuedafterthisdate.

    Therefore,itisevidentthatTiwestRepresentativehaspreventedtheContractor

    from:-

    a) CompletingtheSeparablePortionsinatimescaleconsistentwiththeContractandortheapprovedprogramme

    b) CompletingtheWorksinatimescaleconsistentwiththeContractandortheapprovedprogramme

    5.2.23 FortheavoidanceofdoubttheinformationcontainedatAppendixAwasprovidedtotheContractbyTiwestRepresentativeandisthereforethedates

    thereinaretakenasagreed.

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    23/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page23of41

    6 EVENTSGIVINGRISETOENTITLEMENT6.1 Introduction6.1.1 Thissectionofthedocumentidentifiesandillustratestheeventsthathave

    delayedandpreventedtheContractorfromcompletingtheWorksinatimescale

    consistentwiththebaselineprogramme.Asaresultofthesedelaysthe

    ContractorhasbeeninstructedbyTiwestRepresentativetomobiliseadditionalresourcesinanefforttoreducethedelay.

    6.1.2 AsstatedabovetheConstructionIssueinformationshouldhavebeenissuedinasingletrancheonorbefore29

    thJune2009.Inrealitytheinformation,andaccess

    toareasofthesite,wassuppliedoveraprolongedperiodoftime.Duetothe

    numberofdrawingissues,andgiventheirrationalordertheywereissuedin,

    plustheaccessissues,itisimpossibletoseparatethedelayevents.

    Notwithstandingthatitisclear,assetoutbelow,thatTiwestandits

    Representativeareculpableforthosedelaysandtheresultantcost.

    6.2 Delay Event and or acts of prevention Issue ofInformationforConstructionandaccesstoSite

    6.2.1 CauseofDelay6.2.2 ActivityWCC1020ISSUEIFCISOMETRICSofthebaselineprogrammehasa

    startandfinishdateof29th

    June2009.ThereforeTiwestRepresentativewas

    requiredtoissueallConstructionInformationonorbeforethisdate.

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    24/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page24of41

    6.2.3 TheContractorscorrespondenceof7thAugust20098recordsthatithadbeenrequestedtoinstalltheChlorAlkaliprioritypipeworkbythe17

    thAugust2009

    andthatishasbeenunabletodosoasaresultofTiwestRepresentativefailing

    toissuethegeneralarrangementdrawings.Further,asiteinspectionconducted

    onoraroundthattimeindicatedthatnopipetrayshadbeeninstalledand

    therefore,evenifthedrawingshadbeenissued,thepipecouldstillnothave

    beeninstalled.

    6.2.4 TheContractorservednoticeon30thOctober20099thatitintendedtosubmitanextensionoftimeandresultantcostsasaresultoflateaccesstoareasofthe

    site.

    6.2.5 TiwestRepresentativeacknowledgedreceiptoftheContractorsnoticeon13thNovember2009

    10andadvisedthatitshouldberesubmittedinaccordancewith

    thetermsoftheContract.Notwithstandingtheproceduralerrorsitisevident

    thatTiwestRepresentativeisawareofthedelays.Moreover,therewasnothing

    precludingTiwesttoreviewthesituationandissueanappropriateextensionof

    time.

    6.2.6 On3rdDecember200911theContractornotifiedTiwestRepresentativethatit

    8WesternConstructionCo.letterdated7

    thAugust2009

    9WesternConstructionCo.letterdated30

    thOctober2009

    10ProteusECPMEngineersletterdated13th

    November2009referenced07035-L-518

    11WesternConstructionCo.letterdated3

    rdDecember2009

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    25/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page25of41

    hadbeendelayedasaresultof:-

    a) Rainb) Additionalworksc) Excavationofpiperacksduetoemissionsd) Evacuationduetogase) Demobilisingfromoneofthebuildingsasaresultofadirectionfrom

    TiwestRepresentative

    6.2.7 TheContractorcontinuedtosufferdelayanddisruptionasaresultofchemicalreleasesintotheworkareaandon22ndDecember200912advisedthatitsought

    torecovercostsfortheconstructionofascaffoldthatwouldallowsafeegressin

    theeventoffutureevacuationsduetogasleaks.

    6.2.8 On23rdDecember200913theContractoradvisedthatithadincurredadditionalcostsinrespectofthedelaysatsiteandintendedtoseekpaymentforthese

    costs.OnthesamedatetheContractoradvisedthatitestimatedthatthe

    currentassessmentofman-hourstocompletetheprojectwouldbecirca88,000

    whereastheContractallowancewasover30,000less.Further,the

    correspondenceadvisedthathisequatedtoalmost7weeksofconstructiontime

    andthat,asaresultofthedelays,theDateforPracticalCompletionwouldhave

    12WesternConstructionCo.letterdated22nd

    December2009

    13WesternConstructionCo.letterdated23

    rdDecember2009

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    26/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page26of41

    tobeextendedto1st

    May201014

    .

    6.2.9 NotwithstandingtheongoingdelayanddisruptioninrespectoftheConstructionInformationTiwestadvisedtheContractorthatitwasconductingamajor

    shutdownoftheplantstarting15thMarch2010for6days15.Thisclearlyhadan

    impactontheprojectastheContractorwasforcedtodemobiliseandremobilise

    beforeandaftertheperiodofsuspension.

    6.2.10 TheContractorsletterof18thJanuary2010setsoutthat:-

    Themainreasonforthelowproductivityistheproportionoflabour

    spentonadditionalpipeworkorpipereworkThecontinualreworkis

    affectingourworkflowbecauseourcrewscontinuallyneedtostop

    workonpipelinesduetoclasheswithexistingsteel.Thestopping,

    redesigningandthenreworkingofapipelineismuchslowerthan

    puttinginprefabricatedspools16

    6.2.11 ItisevidentthatasaresultofTiwestRepresentativesfailuretoissuecogentConstructionInformation,oratall,theContractorwasincurringdifficulty

    14WesternConstructionCo.letterdated23

    rdDecember2009

    15TiwestPtyLtdletterdated13th

    January2010

    16WesternConstructionCo.letterdated18

    thJanuary2010

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    27/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page27of41

    installingandorprogressingtheWorks.Ultimatelythiswasdelayingand

    disruptingtheContractor.

    6.2.12 TheContractorsubmittedarevisedscheduleonoraround1stFebruary2010thatrevisedtheDateforPracticalCompletionto20thApril2010.

    6.2.13 ThisprogrammewasacceptedbyTiwestRepresentativeon5thFebruary201017;thereforetherevisedPracticalCompletionDatewasalsoaccepted.

    6.2.14 TheContractorissuedadelayregistertoTiwestRepresentativeon10thFebruary2010

    18.Thisdocumentsetsoutanumberofthedelaystotheprojectforwhich

    Tiwestareculpable.TiwestRepresentativerespondedtothissubmissionon11th

    February2010andstatedthattheContractorhadfailedtoisolateeventsfor

    whichtheitwasculpable.Giventhattheindividualeventshavebeenidentified

    andthereasonwhyTiwestRepresentativehasfailedinitsobligationto

    determineanextensionoftimeinafairorreasonablemannerandthereforeits

    conductisunconscionable.

    6.2.15 TheContactorscorrespondenceof15thFebruary2010recordsthatameetingtookplacebetweenitandTiwestRepresentativeinrespectofanextensionof

    timeandresultantcosts.TheletterrecordsthatTiwestRepresentativestated

    thatindirectcostsmayonlyberecoveredthroughthere-measureformula;thisis

    clearlyincorrectasclauses7.2and7.3apply.Again,thisreiteratesthatTiwest

    17WesternConstructionCo.letterdated8th

    February2010

    18WesternConstructionCo.letterdated10

    thFebruary2010

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    28/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page28of41

    Representativesconductisunconscionableasitisfailingtotakeconsideration

    ofthetermsoftheContractwhenconsideringthematters.

    6.2.16 TiwestRepresentativesletterof15thFebruary201019awardsa6.5workingdayextensionoftimeandrevisedtheDateforPracticalCompletionto17thMarch

    2010.TiwestRepresentativehasfailedtotakeconsiderationofthefactthatthe

    ContractcontainsSeparablePortionsandthateachoftheseportionsshould

    havebeenextendedindividually.

    6.2.17 On16thFebruary201020theContractorwrotetoTiwestRepresentativetorecordthatameetinghadtakenplacethedaypriorandthat:-

    a) ItwasagreedbetweentheContractorandTiwestRepresentativethatthatthefinalnumberofmanhoursusedtocompletetheproject

    wouldbereconciledattheDateforPracticalCompletion

    b) TheContractorwilladdadditionalresourcestotheprojectandthattheseadditionalresourceswouldbereimbursedthrough:-

    i) Re-measurecostsii) Prolongationcostsduetotheincreasedscopeofworkiii) Siteinstructionsincludingallequipmentandindirectcosts

    6.2.18 TiwestRepresentativeacknowledgedreceiptofthiscorrespondenceon18th

    19ProteusECPMEngineersletterdated15th

    February2010referenced07035-L-655

    20WesternConstructionCo.letterdated16

    thFebruary2010

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    29/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page29of41

    February201021

    andnotedtheContractorscommitmentand,moreimportantly,

    thatitwaswaivingthenotificationperiodwithinclause7.3oftheContractuntil

    23rd

    February2010.ItisevidentthatTiwestRepresentativeisawareofthe

    delays,haswaivedthetimebarwithintheContract,thatEstoppelwouldapply

    andthatanyattempttore-applysuchclausewouldbeunconscionable.

    6.2.19 On23rdFebruary201022theContractorwrotetoTiwsetRepresentativesettingoutthatithadbeendelayedasaresultof:-

    a) Thelackofaccessb) SlippingofequipmentdeliverydateswhichTiwestweretosupplyc) Raindelaysd) Evacuationsfromsitee)

    Additionalsiteinstructions

    6.2.20 Further,theContractorrequestedthattheDateorPracticalCompletionbeextendedto21

    stApril2010andthat,whilstthetendermanninglevelpeakedat

    65menonsite,theContractorwasincreasingitsworkforceto100men.Ascan

    beeseenfromtheConstructionInformationregisters,thatareanalysedabove

    andappended,theContractorhadreceivedasubstantialamountofinformation

    inandaroundthistime.Essentiallytheincreaseintheworkforcewasanextra-

    21ProteusECPMEngineersletterdated18th

    February2010referenced07035-L-657

    22WesternConstructionCo.letterdated23

    rdFebruary2010

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    30/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page30of41

    ordinarymeasuretakenbytheContractortoreducethedelayforwhichitis

    entitledtobecompensated.

    6.2.21 TiwestwrotetotheContractoron2ndMarch201023advisingthatascheduledshutdownoftheplanthadbeenmovedto19thApril2010andthataccesstothe

    sitewouldberestrictedforaperiodof13days.

    6.2.22 TiwestRepresentativewrotetotheContractoron3rdMarch201024and,interalia,setoutthatitbelievedthatSpecialConditionstookprecedenceoverthe

    GeneralConditionsofContract.OnreviewoftheContractthereisambiguityas

    clause1.2states:-

    Ingivingadirectionunderthisclause,Tiwest'sRepresentativewill

    construethedocumentscomprisingtheContractintheorderof

    precedenceinwhichtheyarelistedinthedefinitionoftheContractin

    clause1.1.

    6.2.23 Onreferencetoclause1.1theordersetoutisasfollows:-a) ThisConstructionContractb) TheContractSpecifics

    23TiwestPtyLtdletterdated2nd

    March2010

    24ProteusECPMEngineersletterdated3

    rdMarch2010referenced07035-L-679

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    31/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page31of41

    c) TheScopeofWork,includingreferencedDrawingsandDocumentation

    d) Theotherschedules,exhibitsandannexurese) Theotherdocuments(ifany)referredtoinItem2

    6.2.24 ItisclearfromthisthattheContracttakesprecedenceoverallotherdocumentationandthatthereisnoreferencetoSpecialConditions.

    NotwithstandingthisSpecialConditionshavebeeninsertedatAnnexure5,which

    fortheavoidanceofdoubtisitemdandbeneaththeContract,whereatit

    states:-

    Thefollowingmodificationwilltakeprecedenceoverthewordinginthe

    standardtermsandconditionscontainedwithinthisContract.

    6.2.25 ClearlytherearetwoordersofprecedenceandanambiguitywithintheContract.WhereastheContractallowsforTiwestRepresentativetomakeits

    ownrectificationoftheContractthelawprovidesthatthesetermsberead

    contraproferentem.Thismeansthatthetermisconstruedagainsttheparty

    thatdraftedit;thereforeTiwestisnotentitledtoderiveabenefitfromitsown

    error.

    6.2.26 NotwithstandingtheaboveprincipleTiwestRepresentativehasindicatedthattheContractorisnotentitledtorecoveranycostsotherthanstandbycostsin

    respectoftheinclementweatheranddelayanddisruptionclaims.WhilstSC.2c

    providestheContractorisentitledtorecoverstandbyratesalthoughitdoesnot

    precludeitfromrecoveringanyothercosts.Therefore,theContractwouldbe

    supplementbyimpliedterms.GiventhattheContractorhassuffereddelay,and

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    32/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page32of41

    damage,asaresultofeventsforwhichTiwestareculpableitwouldbeentitled

    torestitutionandwouldbeabletorecovercostsresultantfromthedelay.

    6.2.27 WithinthesamecorrespondenceTiwestRepresentativehasstatedthatthere-measurementclauseonlyappliesintheeventthatthetotalContractpriceis

    exceedby20%.Onreviewofclauseitstatesthat:-

    RemeasureofquantitiesshallbecarriedoutbytheTiwest

    representativeinaccordancewiththelatestrevisionofIssuedfor

    Constructiondrawingsandspecifications.TheTiwestrepresentative

    shallarrangefortheremeasureoftheactualquantitiestobe

    undertakenandupdatedaspartofthemonthlyprogressclaim

    process.Thecontractorisentitledtoreviewandifapplicablenotify

    Tiwestofanyquantitiesindispute,andprovidesuchsubstantiationas

    necessarytoreachanagreementonthequantities.Anyotherclaim

    whichmayresultinanadjustmenttothecontractpriceshallbein

    accordancewithclause8and16.

    6.2.28 ThestatementmadebyTiwestRepresentativeisclearlyincorrect.Further,theContractprovidesthatTiwestRepresentativeistovaluetheWorksonamonthly

    basis;itclearlyhasnotdonethiscarriedoutthisoutandasaresultisinbreach

    oftheContractasaresultofitattemptingtosetthenotionalvalueof20%

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    33/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page33of41

    increase.

    6.2.29 On5thMarch201025theContractoradvisedthattheworkforceatsitehadincreasedto152operativesandthatithadincreasedtheworkingweekto60

    hours.MoreovertheContractorisstillactivelyseekingtorecruitadditional

    operatives.

    6.2.30 On11thMarch201026TiwestRepresentativesinformedtheContractorthatitwasconcernedaboutthelackofprogressandthatdirectedthat:-

    ThereisnotenoughmanpowercurrentlyonthisjobsothatWCCocan

    finishontimeandthemanpowershouldincreaseby4timessothat

    thedeadlinecanbeachieved.

    6.2.31 FromtheinformationreleaseschedulebelowitisevidentthattheContractorwasstilloutstandingaconsiderableamountofConstructionInformationaround

    thistime.Therefore,TiwestRepresentativehasinstructedtheContractorto

    quadruplethelabourforceatatimewhenitstillhadnotprovidedallthe

    ConstructionInformationandtheContractordidnothaveuninterruptedaccess

    tothesite.Thisinstructionclearlyillustratesmaladministrationoftheprojectby

    25WesternConstructionCo.letterdated5th

    March2010

    26ProteusECPMEngineersletterdated11

    thMarch2010referenced07035-L-687

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    34/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page34of41

    TiwestRepresentative.

    6.2.32 Furthermore,onthe15thMarch201027TiwestRepresentativerecordedthatameetingtookplaceon8

    thMarch2010.Thecorrespondencenotesthata

    proposalwasacceptedthattheContractor:-

    a) Wouldemployanother30operativesandseektoincreasethisto40b) Wouldemployanother3supervisors

    6.2.33 Again,TiwestRepresentativehasdirectedtheContractortoincreaseresourcesatatimewhenitdoesnothavethenecessary,orcomplete,Construction

    Informationoruninterruptedaccesstothesite.

    6.2.34 TheContractorraisedtheissueofuninterruptedaccess,ordisruptedaccess,againon18

    thMarch2010

    28.TheContractorscorrespondencenotedthat:-

    OnTuesdaythe16thMarch20105ofouremployeeswereovercome

    byfumes.WesternConstructionCo.carriedoutaninvestigationand

    forwardedthereportastherootcauseswerenotclarifiedandcould

    onlybeidentifiedbybothPorteusandTiWest.Todatewehavehad

    noformalresponseintermsof;

    DocumentedevidenceofaccidentinvestigationbyProteusorTiWest

    27ProteusECPMEngineersletterdated15th

    March2010referenced07035-L-688

    28WesternConstructionCo.letterdated18

    thMarch2010

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    35/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page35of41

    detailingthecauseoftheaccidentandtherootcausesofthefailure,

    Northeactionsthathavebeentakento

    Rectifythesituation Theplansandproceduresthatareadoptedtopreventre-

    occurrence.

    Thepersonorpersonsresponsibleforimplementingtheactions

    6.2.35 ItisevidentthattheContractorwasstillincurringsignificantproblemswiththeworkingconditionsthat,inturn,werecausingdelaytotheproject.Moreoveron

    thesamedatetheContractornotifiedTiwestRepresentativethat:-

    theprioritypipelinesinsubarea4Ecannotbecompletedbeforethe

    Aprilshutdownduetothelackofsupportingsteelwork.29

    6.2.36 FortheavoidanceofdoubtTiwestwereresponsibleforthefreeissueofthismaterial.

    29WesternConstructionCo.letterdated18

    thMarch2010

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    36/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page36of41

    6.2.37 On31stMarch201030theContractoradvisedthatcomplexityofthe5KOpiperackstiffeninghadincreasedfromtheagreedScopeofWorkandasaresultithad

    takenadditionaltimetoinstallandincurredadditionalcost.Onthesamedate

    theContractorconfirmedthattheinsulationwasnotincludedwithinitstender

    astheinformationwasissuedafteritssubmissiondate31

    .Notwithstandingthis

    TiwestRepresentativehadissueddrawingsthatincludedthiswork,whichthe

    Contractorhadcarriedout,andasaresulttheContractorhadincurredadditionalcostandtimeasaresultoftheinstallation.

    6.2.38 TheContractorscorrespondenceof15thApril201032requestedanextensionoftimeuntilthe13

    thJune2010asaresultofthe13and10dayshutdownsplus

    TiwestRepresentativerequestingarevisedprogrammeconcentratingonpriority

    lines.

    6.2.39 TheContractorscorrespondenceof25thMay201033notifiedTiwestRepresentativeofitsintentiontomakeaclaiminrespectoftheengineeringand

    procurementattheproject.Therefore,thePartieswereawarethatthesituation

    hadprogressedtoapointwherebytheContractorwouldseekrecompensefor

    TiwestRepresentativesmaladministrationoftheproject.

    30WesternConstructionCo.letterdated18

    thMarch2010

    31WesternConstructionCo.letterdated18

    thMarch2010

    32WesternConstructionCo.letterdated18th

    March2010

    33WesternConstructionCo.letterdated25

    thMarch2010

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    37/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page37of41

    6.2.40 TiwestRepresentativeissuedaresponseon27thMay201034statingthattheforegoingnoticewasnotinaccordancewiththeContractandassuchwas

    rejected.TheContractorrespondedon28th

    May201035

    clarifyingthattheclaim

    wasgoingtobesubmittedasaresultof:-

    a) Theseverityandfrequencyofdelaysb) DelayanddisruptioncausedbyConstructionInfromationbeing

    issuedlate

    c) Tiwestissuinglateandincompletefreeissuematerial6.2.41 Almost2monthsaftertheContractorsnoticeinrespectoftheinsulationnot

    beingincludedwithintheScopeofWorksTiwestRepresentativerepliedon31st

    May201036

    statingthattheContractdidnotincludeaclauseforsuchomissions.

    ClearlyTiwestRepresentativewaseithernotfamiliarwiththeContract,orwas

    simplychoosingtoignoreit,asitcontainsavariationclausethatallowsforthese

    workstobeinstructed.TiwestRepresentativehadissuedawritteninstructionin

    theformofthedrawinganditstransmittal;thereforetheContractorhadbeen

    instructedtocarryouttheseworks.Moreover,thelawallowsforthe

    rectificationofacontractintheeventthereisanerrorbyeitherorboththe

    parties.TiwestRepresentativeclearlychosetoignoretheseoptionsinaneffort

    34ProteusECPMEngineersletterdated27

    thMay2010referenced07035-L-795A

    35WesternConstructionCo.letterdated28th

    May2010

    36ProteusECPMEngineersletterdated31

    stMay2010referenced07035-L-794A

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    38/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page38of41

    toderiveabenefitfromthesituation;itsconductwasunconscionable.

    6.2.42 On10thJune2010theContractoradvisedthatasaresultof:-a) Tiwestnotprovidingaccessinatimescaleconsistentwiththe

    baselineprogramme

    b) Tiwestnotprovidingfreeissuematerialinatimescaleconsistentwiththebaselineprogramme

    c) TiwestnotsupplyingConstructionInformationinatimescaleconsistentwiththebaselineprogramme

    d) Inclementweathere) TiwestsuspendingtheWorksf) Gasleakswithintheplant

    6.2.43 Ithadincurreddelayanddisruptionandthatitintendedtosubmitanextensionoftimeupto21

    stJune2010

    37andresultantcostsof$4,013,538.31.

    6.2.44 Summary6.2.45 ItisevidentfromtheeventssetoutabovethattheContractorwas:-

    a) PreventedfromcommencingtheWorksb) PreventedfromcompletingtheSeparablePortionsinatimescale

    37WesternConstructionCo.letterdated28

    thMay2010

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    39/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page39of41

    consistentwiththeDate/sforPracticalCompletionorthebaseline

    programme

    c) InstructedtocarryoutovertimeworkingasaresultofthedelayssetouthereinandTiwestRepresentativesmaladministrationofthe

    project

    6.2.46 TheContractorisentitledtorecovertheresultantcostsoftheaboveevents.6.3 Theseparationofevents6.3.1 GiventhenumberandfrequencyoftheeventscausedbyTiwestRepresentative

    issuingConstructionInformationinanuncontrolledandad-hocmanneritis

    impossibletoseparatetheeffectofeachoftheseevents.TiwestRepresentative

    isculpableforthemaladministrationoftheprojectandanyattemptfromitto

    deriveabenefitfromthecomplexsituationithascreatedwouldbe

    unconscionable.WhilstthismaynotbecompliantwiththeContractitis

    acceptedatLaw.

    6.3.2 Itshouldbenotedthattheevaluationofanyclaimistobecarriedoutonthebalanceofprobability.TheinformationsetoutinAnnexureAprovidesthat

    TiwestRepresentativefailedtocomplywiththeContract,ortheprogrammeit

    approved,beyondallreasonabledoubt.Thislevelofproofcarriesafargreater

    weightthanthebalanceofprobability.

    6.3.3 TiwestRepresentativehasfailedtoacknowledgethedamagecausedtotheprojectasaresultofitsactions.FurtherithassoughttouseContractclauses

    whichithaseitherpreviouslywaived,orarestruckoutasaresultofitsactsof

    prevention,tomakeadefence.

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    40/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    Status:Draft

    Revision:0001

    IssueDate:6th

    July2010Page40of41

    7 THEQUANTUMOFOURCLAIM7.1.1

  • 8/9/2019 2010_07_06 Rev 003 - Issue to Client

    41/41

    TiwestExpansionProject

    Steelwork,MechanicalandPiping(SMP)Works

    8 SCHEDULEOFANNEXUREANDEXHIBITS8.1 Annexure8.1.1 AnnexureAInformationreleaseschedule8.2 Exhibits8.2.1 ExhibitACorrespondencereferredtowithinthisdocument