2011-12 fourth quarter council works program report · the 2011-12 council works program at the end...

23
Attachments: 1. Supporting Attachment 2. 2011-12 Council Works Program Fourth Quarter Report 3. Schedule of program adjustments 4. Recommended carry forward to 2012-2013 5. Listing of individual projects 6. Schedule of project variances, i.e. Projects >$200,000 variance to plan 2. FUTURE MELBOURNE (FINANCE AND GOVERNANCE) COMMITTEE REPORT Agenda Item 5.9 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT 14 August 2012 Presenter: Bob Rosen, Manager Capital Works Purpose and background 1. The purpose of this report is to inform the Future Melbourne Committee of the financial performance of the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments and the proposed carry forward funding to the 2012-13 financial year. Key issues 2. The value of work completed is $114.8 million compared to the annual budget of $130.5 million. After adjustments for abnormal expenditure and multi year projects, performance of 91.2 per cent of program has been achieved. A carry forward of $15.3 million into 2012-13 is required to complete the program. The Listing of Carry Forward Funding is at Attachment 4. 3. A number of significant milestones were achieved during the final quarter: 3.1. redevelopment of Swanston Street is proceeding rapidly with the tram stop between Bourke Street and Little Bourke Street now operational; 3.2. completion of the Boyd Community Hub in Southbank; 3.3. completion of the façade restoration and structural repairs to Kensington Town Hall; and 3.4. the execution of a Tripartite Agreement between the City of Melbourne, Lend Lease Development and Places Victoria in respect to the new Docklands Library and Community Centre. 4. Other major projects are maintaining steady progress despite site difficulties: 4.1. Carlton Baths and Family Resource Centre Redevelopment; and 4.2. Fitzroy Gardens Water Harvesting. 5. The recommended carry forward of project funding into the 2012-13 Council Works Program is $15.3 million compared to $19.7 million forecast at the end of the third quarter. 6. For a detailed report refer to Attachment 2 together with Attachments 3, 4, 5 and 6 appended to the report. Recommendation from management 7. That the Future Melbourne Committee recommend Council: 7.1. accept the 2011-12 Council Works Program Report; 7.2. note the proposed funding for carry forward projects totalling $15.3 million included in this report; and 7.3. approve the adjustments to the 2011-12 Council Works Program that are included in this report. Page 1 of 19

Upload: others

Post on 24-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

Attachments: 1. Supporting Attachment 2. 2011-12 Council Works Program Fourth Quarter Report 3. Schedule of program adjustments 4. Recommended carry forward to 2012-2013 5. Listing of individual projects 6. Schedule of project variances, i.e. Projects >$200,000 variance to plan

2.

F U T U R E M E L B O U R N E ( F I N A N C E A N D G O V E R N A N C E ) C O M M I T T E E R E P O R T

Agenda Item 5.9

2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT

14 August 2012

Presenter: Bob Rosen, Manager Capital Works

Purpose and background

1. The purpose of this report is to inform the Future Melbourne Committee of the financial performance of the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments and the proposed carry forward funding to the 2012-13 financial year.

Key issues

2. The value of work completed is $114.8 million compared to the annual budget of $130.5 million. After adjustments for abnormal expenditure and multi year projects, performance of 91.2 per cent of program has been achieved. A carry forward of $15.3 million into 2012-13 is required to complete the program. The Listing of Carry Forward Funding is at Attachment 4.

3. A number of significant milestones were achieved during the final quarter:

3.1. redevelopment of Swanston Street is proceeding rapidly with the tram stop between Bourke Street and Little Bourke Street now operational;

3.2. completion of the Boyd Community Hub in Southbank;

3.3. completion of the façade restoration and structural repairs to Kensington Town Hall; and

3.4. the execution of a Tripartite Agreement between the City of Melbourne, Lend Lease Development and Places Victoria in respect to the new Docklands Library and Community Centre.

4. Other major projects are maintaining steady progress despite site difficulties:

4.1. Carlton Baths and Family Resource Centre Redevelopment; and

4.2. Fitzroy Gardens Water Harvesting.

5. The recommended carry forward of project funding into the 2012-13 Council Works Program is $15.3 million compared to $19.7 million forecast at the end of the third quarter.

6. For a detailed report refer to Attachment 2 together with Attachments 3, 4, 5 and 6 appended to the report.

Recommendation from management

7. That the Future Melbourne Committee recommend Council:

7.1. accept the 2011-12 Council Works Program Report;

7.2. note the proposed funding for carry forward projects totalling $15.3 million included in this report; and

7.3. approve the adjustments to the 2011-12 Council Works Program that are included in this report.

Page 1 of 19

Page 2: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments
Page 3: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

1

SUPPORTING ATTACHMENT

Legal

1. There were no direct legal implications arising from the recommendations of this report. Legal advice has and will continue to be provided as required in respect to the various capital works projects. The finance implications are detailed throughout the body of the report and in attachments.

Finance

2. The 2011-12 budget included $130.5 million for Council Works Program (including carry forward funding). The financial value of works completed for the year totalled $114.8 million. A description on progress on projects has been included in the attachments.

Conflict of interest

3. No member of Council staff, or other person engaged under a contract, involved in advising on or preparing this report has declared a direct or indirect interest in relation to the matter of the report.

Stakeholder consultation

4. External stakeholder consultation and engagement is undertaken in relation to individual projects and programs. This occurs throughout the financial year.

Environmental sustainability

5. The Council Works Program directly supports the strategic objectives of reducing the ecological footprint of the city and the Council. Numerous projects are included to directly enhance opportunities for recycling, capturing and conserving water, planting trees and creating new public open space. In addition, the designs for all projects within the program build in measures to minimise the environmental impact and reduce operating costs.

Attachment 1Agenda Item5.9

Future Melbourne Committee14 August 2012

Page 2 of 19

Page 4: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments
Page 5: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

Attachment 2 Agenda Item 5.9

Future Melbourne Committee 14 August 2012

1

2011-12 COUNCIL WORKS PROGRAM FOURTH QUARTER REPORT

1. Overview

As forecast in the Third Quarter Report there has been considerable acceleration during the fourth quarter, which has delivered $48.3 million of work. The overall value of work completed in 2011-12 is $114.8 million compared to the annual plan of $130.5 million.

Significant milestones were achieved during the Fourth Quarter including the commencement of operations in Swanston Street between Bourke Street and Little Bourke Street, and the substantial completion of the tram stop between Collins Street and Flinders Lane. The final stage of the upgrade including the general upgrade of lighting, street furniture and planting, together with the accessible tram stop between A’Beckett Street and Franklin Street, is in train and is expected to be completed within the first quarter of 2012-13.

The completion of the restoration of the heritage Boyd High School building as a Community Hub was publicly acknowledged at the official opening on 7 July 2012. The Hub provides a unique mix of public library, maternal and child health, family services, playgroup, meeting rooms, artists’ studios and a café. This has been very well received well by the community.

Other significant projects are proceeding steadily, despite site difficulties. These include Fitzroy Gardens Water Harvesting project which is now proceeding strongly and is expected to be completed in November 2012, at which time construction of the new Depot and Visitors Centre can commence on site.

The Carlton Baths and Family Resource Centre Redevelopment has been delayed by sub-ground contamination which has been successfully removed. The project is now proceeding strongly.

The structural repairs and fabric restoration at Kensington Town Hall have been completed.

Major assets renewal programs in respect to roads, footpaths, drains, parks and Council buildings have been delivered.

In summary, a large program of work has been successfully delivered during 2011-12.

2. Financial Performance Period: Jun-12

Council Works AreaBudget Actual Variance$'000s $'000s $'000s

Maintenance.Capital Grants 1,940 1,584 356Maintenance 8,361 8,768 (407)Minor Works 0 0 0Total Maintenance 10,301 10,352 (51)

Capital WorksNew Works/Upgrade 68,715 55,466 13,248Renewal / Refurbishment 51,524 48,947 2,577Total Capital Expenditure 120,239 104,413 15,826

Total Council Works Program 130,540 114,766 15,775

Full Year

Page 3 of 19

Page 6: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

2

3. Key Projects – Progress Report

Swanston Street Redevelopment $25.6 million As indicated in the overview, work on Swanston Street has been proceeding strongly despite encountering a number of unexpected latent conditions. Accessible tram stops are now operating between Latrobe Street and Little Lonsdale Street and between Bourke Street and Little Bourke Street. A further stop is approaching completion at the City Square. The whole project including the general upgrade of the street and four new accessible tram stops is expected to be completed in the first quarter of 2012-13. Boyd School Redevelopment $9.5 million The restoration of the heritage school building has now been completed including fitout as a community hub and is now operational. It was officially opened on 7 July 2012 and has added considerably to the Southbank community. A planning permit application has been submitted in respect to the residential and commercial development that will be constructed on another section of the site. Docklands Library, Community Centre and Boating Hub The various legal agreements underpinning this development have been executed and design work is advanced. Work is expected to commence on site in August 2012 with remediation of piles that will support the building and the adjacent promenade. The construction work will be carried out concurrently with a major public infrastructure upgrade in the precinct. Carlton Baths and Resource Centre Redevelopment $10.4 million Work has continued strongly on the Family Resource Centre and multi-purpose areas, whilst the health centre extension has been delayed by the discovery of contaminated ground, which has required removal and disposal by specialist firms. This has been completed but has impacted on the timing of the project and its ultimate cost. Work is now progressing on the Health Centre structure. Fitzroy Gardens Redevelopment $13.9 million The water harvesting project is now progressing steadily, following delays due to inclement weather and other site related difficulties. These have now been resolved and the structure is advancing quickly. It is expected to be completed in November 2012. The new Works Depot and Visitors Centre have been designed and will be tendered in early August 2012, to enable construction to start shortly after completion of the water harvesting work. Significant funds have been allocated in the 2012-13 Council Works Program for this work.

Holland Park Pavilion $2.5 million Progress on the refurbishment of the pavilion has ceased following the contractor being placed in administration. The contract has now been terminated and arrangements are being finalised to re-tender this work. Construction work is expected to recommence in October, with completion in May 2013. Kensington Town Hall Refurbishment $1.5 million Major repairs to the fabric and structure of the building, including removing lead paint, were completed during the fourth quarter. The follow up contract to provide an accessible entrance to the building, upgrade services and provide landscaping has been tendered and is expected to be let shortly. This work is expected to be completed in June 2013. Additional funding is being provided in the 2012-13 Council Works Program.

Page 4 of 19

Page 7: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

3

Water Conservation and Climate Adaptation $3.4 million The two principal elements of this work are the water harvesting projects to Birrarung Marr and Queen Victoria Gardens/Alexandra Gardens. The Birrarung Marr water harvesting project has been tendered and a contract is expected to be let in September 2012. It involves capturing stormwater run off from the main East Melbourne drain and storing it beneath the upper terrace. The water will be used for irrigating the grassed areas of Birrarung Marr. The work is expected to be completed early in the 2013-14 financial year.

The capturing of water in Queen Victoria Gardens and its storage in Alexandra Gardens has been designed and will be tendered shortly. Both these projects involve Federal Government Grant funding. This work is expected to be completed in early 2013-14.

Queen Victoria Market Improvements $1.4 million Construction contracts to improve the Victoria Street streetscape between Elizabeth Street and Peel Street have now been completed and the intersection of Queen Street and Victoria Street has now been enhanced. Improvements adjacent to the loading dock areas of the Meat Hall have been completed. Northbank Promenade $15.0 million These works are primarily funded by the State Government and the two current main projects include: a) Widening of the Northbank Promenade adjacent to the Spencer Street: This work is expected to

be completed in the first quarter of 2012-13. It is currently in an advanced stage.

b) An underpass for pedestrians and cyclists beneath the Charles Grimes Bridge providing a link from both Spencer Street and the Melbourne Convention Centre to Docklands. This work has been delayed pending additional funds, which have now been provided by the State Government. Works is expected to commence during the first quarter of 2012-13 and be completed in early 2013-14. The underpass is an innovative curved and cantilevered truss structure, which will complete the connection to Docklands on the Northbank.

4. Fourth Quarter Highlights

Streetscape Improvements

- Completion of Flinders Lane (Swanston Street to Queen Street) Streetscape improvement project including upgraded street lighting and street furniture, bluestone paving and accessibility compliance with a resheeted asphalt road surface

- Completion of Elizabeth Street (Flinders Street to Flinders Lane) verandah skylights and

lighting installation to improve lighting levels and community safety. Queens Bridge and Stock Bridge Structural Repairs

- Completion of Queens Bridge structural beams and web stiffener strengthening works to increase the load capacity of the bridge.

- Completion of the Angliss Stock Bridge repairs including the removal of existing lead based

paint and repainting to original colour scheme and minor repairs to the steel truss frames. Flood mitigation program Completion of drainage repair works to alleviate local flooding in Flinders Street between King Street and Spencer Street and the Flinders Street, Market Street intersection and commencement of drainage upgrade works in Wells Street, Southbank.

Page 5 of 19

Page 8: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

4

City Baths Chimney Banding The City Baths heritage chimney was showing significant signs of dilapidation due to age and building movement. Carbon fibre banding has been installed to secure the chimney, a first in Victoria on a heritage building. North Melbourne Library Upgrade This lighting upgrade program was completed during the quarter. Holland Park Completion of the upgrade to the car park adjacent to the child care centre Melbourne Town Hall and Administration Building Completion of the upgrade of the three passenger lifts. These upgrades were carried out progressively whilst maintaining access to the building.

5. Forecast

A number of key projects will be continuing into the 2012-13 financial year and a number of projects are due to commence construction relatively early in the financial year. In particular, the completion of water harvesting to Fitzroy Gardens and the commencement of the new Depot and Visitors Centre construction will occur over the next two quarters. The Docklands Library and Community Centre is expected to commence construction during the first quarter of 2012-13. Construction work will continue on the Carlton Baths and Family Resource Centre Redevelopment. New water harvesting projects are expected to commence during the first two quarters of 2012-13, at Birrarung Marr and at Queen Victoria Gardens. Design work will be progressing and tenders called in respect to the redevelopment of the Kathleen Syme Building in Carlton. It is also expected that works will commence in the first two quarters of 2012-13 in respect to the extension of the Northbank Promenade at the Charles Grimes Bridge, with the construction of the new underpass.

6. Carry forward of funds to 2012-13

The proposed carry forward of funding to 2012-13 is $15.3 million compared to the forecast of $19.7 million, which was forecast in the third quarter report. Additional work was carried out and the carry forward has been reduced. The major elements within the carry forward are $2.9 million in respect to the Fitzroy Gardens Stormwater Harvesting and new Depot and $1.8 million for the Holland Park Sports Pavilion construction works. A full listing is at Attachment 4 to this report.

7. Other information

The following attachments are appended to this report: Attachment 3 – Schedule of program adjustments Attachment 4 –2011-12 Recommended carry forward to 2012-2013 Attachment 5 –2011-12 Listing of individual projects Attachment 6 –2011-12 Schedule of project variances, i.e. Projects >$200,000 variance to plan.

Page 6 of 19

Page 9: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

Council Works Program 2011-12 - 3rd Quarter Record of Program Adjustments (Cumulative) Attachment 3Agenda Item 5.9

Future Melbourne Committee14 August 2012

Project No. Project Name

Council Approved

Budget - Current Year

Carry Forward from Prior Year

Additional External Capital

Contribution

Transfers in / out from other

projects

Additional Funding

Approved by Council

Revised Total Notes

09PK002N Tan Track Stormwater Management Works $0 $0 $36,385 $0 $0 $36,385External funding received from Royal Botanic Gardensfor additional work undertaken

09PS046R Building Retrofits - Energy Performance Contract $0 $0 $0 $0 $1,264,568 $1,264,568

Contract in place with Honeywell as per Councilresolution in Oct-09. Cost of contract is recovered from operational budget savings arising from energy savings.

10CS003N Hotham Hub Children's Centre Landscaping $0 $0 $0 $15,810 $0 $15,810 Savings to be found from other projects

10PK027N Tan Track Timer Clock $0 $0 $78,559 $0 $0 $78,559External Contribution of $78,559 received that wasunbudgetted.

10RW007N Flemington/KensingtonBowling Club Synthetic Green $0 $0 $0 $0 $322,000 $322,000Funding of $310k provided as per FMC resolution fromAug-10 and Council meeting of 24 June 2011

11CD010N Drill Hall - CBD Health Service Fit-Out $180,000 $0 $0 $0 $195,000 $375,000

Increase in budget of $195k to enable the clinical fitoutand purchase and installation of computer and telephony hardware and infrastructure. Approved by Council at 30 August 2011 meeting.

11CD300M D - Hub Repair Works - Docklands $111,000 $0 $0 $0 $25,000 $136,000

Increase in budget of $25k to enable the preparation oa business case, including a concept plan and preliminary quantity surveyor's estimate for presentation to Council by June 2012. Approved by Council at 28 February 2012 meeting.

11DE003N Docklands Pedestrian Wayfinding Signage $0 $0 $0 $0 $150,000 $150,000Increase in budget by $150k was approved by Councilat 29 November 2011 meeting.

11CD013R Kensington Town Hall Refurbishment $1,000,000 $0 -$630,000 $0 $0 $370,000

This project is fully externally funded by State Govt. The contribution from State Govt. has recently been reduced by 8% reducing the budget amount to $920k. Of the $920k, $550k was received from the State Govtin June 2011 and was incorporated in the carry forward of project 10PS044R along with other Council funds.

11ES214R Streetscape Works in Bond Street $0 $0 $0 $0 $300,000 $300,000

Increase in budget of $300k to enable the streetscape works to be undertaken in Bond Street, Melbourne. Approved by Council at 27 September 2011 meeting.

11ES216N Bluestone Paving at the Arts Centre $0 $0 $0 $0 $450,000 $450,000

Increase of $450k for the Bluestone paving around theArts Centre. Approved by Council at 20 December 2012 meeting.

11ES310M Bluestone Paving at the Arts Centre $0 $0 $0 $0 $450,000 $450,000

Increase of $450k for the Bluestone paving around the Arts Centre. This money will be expended on land outside of the control of Council and therefore will take the form of a Grant to the Arts Centre. Approved by Council at 20 December 2012 meeting.

11PK007R Parks Renewal Program Works $7,005,000 $0 $113,093 $0 $0 $7,118,093External Contribution of $113,093 received that wasunbudgetted.

Page 1 of 3

Page 7 of 19

Page 10: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

Council Works Program 2011-12 - 3rd Quarter Record of Program Adjustments (Cumulative) Attachment 3Agenda Item 5.9

Future Melbourne Committee14 August 2012

11PK308M Playground at Savoy Site $400,000 $0 $0 -$380,000 $0 $20,000

17 April 2012Council decision to reallocate 2011-2012 Council Works Program funding as follows:Queensbridge Square — Landscaping and Tree Planting - $350,000in lieu of Southbank Police Pod; andHotham Hub Child Care Centre — Completion of Playground - $380,000in lieu of Playground at Savoy site

11CS004N Hotham Hub Childrens Playground Development $0 $0 $0 $380,000 $0 $380,000

FMC 5.9 17 April 2012Council reallocate 2011-2012 Council Works Program funding as follows:Li Queensbridge Square — Landscaping and Tree Planting - $350,000in lieu of Southbank Police Pod; and1.2 Hotham Hub Child Care Centre — Completion of Playground - $380,000in lieu of Playground at Savoy site

11BU004N New Organic Recycling Machine $0 $0 $0 $0 $12,000 $12,000

That the Future Melbourne Committee recommends Council;1.1. approve the purchase of the organic recycling machine for the Melbourne Town Hall at a cost of $24,000 (plus GST); and 1.2. invoice Epicure for 50 per cent of the purchase price.

11ES015N North & West Melb. Zebra Pedestrian Crossings $0 $0 $0 $0 $300,000 $300,000FMC2 CCP Nov 11 - 1.2 allocate up to $300,000 to the 2011-12 Council Works budget from reserves.

11PK013N Royal Park (RHC) Return to Parkland $0 $0 $100,000 $0 $0 $100,000

FMC Mar 2012. The cost for the community engagement is being met by the Department of Health, as part of the State Government’s commitment to the return of parkland

11PK014N Queensbridge Square Landscaping & Tree Planting $0 $0 $0 $350,000 $0 $350,000

FMC 5.9 17 April 2012Council reallocate 2011-2012 Council Works Program funding as follows:Li Queensbridge Square — Landscaping and Tree Planting - $350,000in lieu of Southbank Police Pod; and1.2 Hotham Hub Child Care Centre — Completion of Playground - $380,000in lieu of Playground at Savoy site

11SW000N Southbank - Police Pod $0 $0 $0 -$350,000 $0 -$350,000

FMC 5.9 17 April 2012Council reallocate 2011-2012 Council Works Program funding as follows:Li Queensbridge Square — Landscaping and Tree Planting - $350,000in lieu of Southbank Police Pod; and1.2 Hotham Hub Child Care Centre — Completion of Playground - $380,000in lieu of Playground at Savoy site

Page 2 of 3

Page 8 of 19

Page 11: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

Council Works Program 2011-12 - 3rd Quarter Record of Program Adjustments (Cumulative) Attachment 3Agenda Item 5.9

Future Melbourne Committee14 August 2012

$8,696,000 $0 -$301,963 $15,810 $3,468,568 $11,878,415

Total Program Budget $130,540,341Additional External Contributions -$301,963Transfer of Budget b/w Projects $15,810Additional Funding Approved by Counci $3,468,568Revised Program Funding $133,722,756

Recon of council works program - Column G $2,838,568 Additional Funding Approved by CounciRecon of council works program - Included in Column F $228,037 Additional External Contributions

Page 3 of 3

Page 9 of 19

Page 12: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments
Page 13: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

Proposed Carry- Justification for Carry-Forward and Other CommentsForward (GL)

Project Capital Projects

08CW002N Northbank Promenade Projects 1,2,5&6 705,090 Construction delayed due to requirement for additional funding from State Government.

08DE003N Cultural Precincts Program 240,828 Delays in construction of final lighting upgrade to Chinatown owing to delays in obtaining building owner approval to connect cables to their premises. Expected to commence shortly.

09PS006R MTH - Admin Building Air Conditioning Replacement 6,676 Part of MTH administration building refurbishment

09PS027R Admin Building - South Wall Render 59,620 Contract has been let and will be completed within the next 3 months

09PS046R Building Retrofits - Energy Performance Contract 73,181 Energy Performance contract. Council decision (refer project adjustments)

09PS049R MTH - Fire-Related Works 129,096 Carry forward to form part of the design funding for the MTH administration building refurbishment

10AC000N Public Art Program 24,052 Carry forward - funds committed to 1200 Buildings Public Art Commission to be resolved by December 2012

10CD007N D - New Library & Community Centre - Docklands 854,349

Approx $1.2m of design work has already been carried out by Lend Lease and their consultants but has not yet been invoiced by Lend Lease. Balance of funding is to be carried forward and will be supplemented by 12/13 funding

10PS001N Public Gallery Air Conditioning Upgrade 55,000 Carry forward to form part of the design funding for the MTH administration building refurbishment

10PS017R Council Buildings Insurance Compliance Works 84,000 Carry forward required to complete committed works on multiple Project Development Plans

10PS020R Nth Melb Library - Air Conditioning Replacement 150,000 Project is out tender.

10PS023R QVM - 153 Victoria Street Electricity Upgrade 234,800 Agreement between City Power and QVM still being negotiated

10PS036R Community Services Building Renewals 240,174 Funds committed

10PS042R Town Hall & Venue Renewal Works 85,395 Required for works to be completed late July/August within the MTH.

10PS062N East Melbourne Library Shading 8,109 Project delayed due to contractor not constructing according to approved shop drawings. Work required to be removed and started again.

11AC000N Art Play Backyard - Phase 1 41,000 Carry forward as project completion extended to 31 July 2012

11AC001N Public Art Program 190,966 Carry forward required to enable payment of committed work

11CD007N East Melbourne Library floor/environment upgrade 75,000 Project delayed due to required revision of technical requirements.

11CD013R Kensington Town Hall Refurbishment 661,894 Funds required for the next stage or works to be supplemented with 2012-2013 funding

11CR000R Town Hall Customer Service Point - design works 335,750 Part of ongoing MTH admin building refurb project

11CS004N Hotham Hub Childrens Playground Development 367,456 Carry forward. Funding transferred for project late in the financial year.

11CW004N Implementation of D2 Initiatives 252,712 Currently out to tender for sports court. All funds will be used for the project by Oct 2012. Months of negotiation of scope between Places Victoria and CoM, leading to a late start on the project

11CW005N Yarra Pedestrian Bridge - Western Gateway Linkage 46,926 Carry forward to complete signage.

11CW006N CH2 - Blackwater Treatment Plant upgrade 89,779 Ongoing resolution of technical problems that are preventing the black water plant from working satisfactorily

11DE003N Docklands Pedestrian Wayfinding Signage 114,571 New Council adopted project. C/f as ongoing project.

11ES011R Flood Mitigation 151,343 Refer to Briefing Note in DM#7263658

11ES016N Bicycle Improvements 607,129 To fund LaTrobe St bike project. Council decision

11ES031R Victorian Grants Commission - Local Roads Funding 225,973 12/13 Grant advance payment $225,973

11PK001N D - New Signage Installation - Docklands Waterways 67,622 C/f as ongoing project. PO will be raised for additional signs in 3 weeks

Recommended Carry-Forward of Capital Funds into 2012/13

Attachment 4Agenda Item 5.9

Future Melbourne Committee14 August 2012

Page: 1 of 2

Page 10 of 19

Page 14: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

Proposed Carry- Justification for Carry-Forward and Other CommentsForward (GL)

Project Capital Projects

Recommended Carry-Forward of Capital Funds into 2012/13

Attachment 4Agenda Item 5.9

Future Melbourne Committee14 August 2012

11PK005N Fitzroy Gardens-Stormwater Harvesting & New Depot 2,939,720 To complete the water harvesting project which has been delayed and partial contribution towards Depot & Visitor centre which will receive another $5.45m in 12/13

11PK006N Holland Park - Sports Pavilion Construction Works 1,810,000 Builder in Administration. Project to be re-tendered to complete works, extra funds may be required

11PK007R Parks Renewal Program Works 135,381 Balance of committed program

11PK010N North Melbourne Open Space Development 730,000 Errol Street project contract let late in the financial year

11PK014N Queensbridge Square Landscaping & Tree Planting 284,712 New Council adopted project ($350,000)

11PS002R QVM - 153 Victoria Street Electricity Upgrade Stg 3. 103,500 Agreement between City Power and QVM still being negotiated

11PS009N Office Precinct - Advance Design 195,000 Carry Forward, to be merged with 12PS024N. Associated with MTH future refurbishment

11PS015R Community Services Building Renewal Works 95,000 Carry forward to complete works

11PS019R Town Hall Buildings Renewal Works 70,325 Carry Forward required to complete segment of work

11PS023R Waste Trf Stn - Civil repair & upgrades 200,000 Delayed due to investigation requiring change in scope

11PS025R Insurance Works to Council Buildings - Stage 2 351,300 Required to complete insurance requirements. Scoping works for all sites completed for new sprinkler and protection system works (Major sites Town Hall and Libraries)

11PS026R Lift Upgrade works 174,000 Funding required to complete further lift works

11PS028R Melb City Baths Systems & Structure Renewal Works 251,000 Carry forward required for tiling scoped

11PS029R Newmarket & Kensington Renewal Works 30,000 Required to complete works

11PS030R Domain House AirCon Renewal Works 20,000 Required to complete works

11PS032R North Melb Recreation Centre Design Issues 33,297 Required to complete works

11PS033N Water Saving Works in Council Buildings 25,000 Required to complete works

11PS035N Art Play external shading and Sustainability works 68,960 Carry forward. Project completion extended to 31 July 2012

11RW000R Leased Recreation Facility Fence Renewals 26,390 Required to complete works

11RW001R Community Recreation Facility renewal works 52,911 Funds are being used on NMRC Refurbishment works, due to complete in Oct 2012

11RW012R North Melbourne Recreation Centre Refurbishment 103,928 Currently in construction, funds will be used for project by Oct 2012

11UL000N Climate Adaptation Projects 1,420,541 Carry forward required for completion of Birrarung Marr and QV Gardens/Alexandra Gardens water harvesting projects. To be supplemented with funding in 2012-13.

TOTAL CAPITAL PROJECTS 15,299,456

Page: 2 of 2

Page 11 of 19

Page 15: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

#PJ02 - 12-Jul-2012 08:09:30 LEADAV

Annual YTD VarianceProject Budget Actual Fav/(Unfav)

MAINTENANCE PROJECTSCapital Grant

11ES305M Traffic Signal Installations - Capital Grant 510,000 572,625 (62,625)11ES306M Street Lighting Improvements - Capital Grant 380,000 380,000 0 11PK308M Playground at Savoy Site 400,000 15,120 384,880 #11PS306M Drill Hall - Fitout Works 650,000 651,774 (1,774)

Project Costs to be allocated 0 (35,551) 35,551

Total Capital Grant 1,940,000 1,583,968 356,032

Maintenance11AC300M Arts House theatrical equipment maintenance 40,000 44,157 (4,157)11AC301M Art & Heritage Collection Maintenance 150,000 149,194 806 11AC302M Creative Spaces - Maintenance works 50,000 50,000 0 11AC303M Artplay - Annual Mtce of Theatre Equipment 40,000 41,156 (1,156)11AC304M Signal - Annual Mtce of Theatre Equipment 40,000 40,000 0 11CD300M D - Hub Repair Works - Docklands 111,000 66,672 44,328 *11CD301M Drill Hall Disabled toilet 35,000 36,822 (1,822)11CD302M Nth Melbourne/Kensington Community Hub - Advance Design 60,000 60,000 0 11CM300M Installation/Removal of Christmas Decorations City 250,000 255,491 (5,491)11CM301M D Install/Removal of Christmas Decorations Docklds 75,000 1,188 73,812 11CS300M Community Services Minor Works 250,000 401,336 (151,336)11CS316M Community Services Centres Signage 52,000 31,830 20,170 11DE300M Advance Streetscape Design 50,000 26,000 24,000 11DE301M D - Advance Industrial Design 50,000 65,754 (15,754)11DE302M Princes Park Bowls Club Improvements - Minor Works 50,000 50,000 0 11DE303M Advance Architectural Design 100,000 119,088 (19,088)11EM300M Banner Pole Maintenance 62,000 62,000 0 11ES300M Bridge Maintenance 230,000 230,000 0 11ES301M Street Lighting Maintenance 1,400,000 1,640,449 (240,449) #11ES302M Wharf and Marina Maintenance 150,000 150,000 0 11ES303M Street Trading / Skateboarding Asset Maintenance 30,000 30,000 0 11ES304M D - Public Lighting Maintenance - Docklands 250,000 181,807 68,193 11ES307M Feature and Decorative Lighting Maintenance 25,000 24,450 550 11ES308M Parking Guidance Signage Decommissioning 300,000 196,358 103,642 11ES309M Safe City Camera Maintenance 100,000 101,888 (1,888)11ES310M Arts Centre Bluestone Paving (Grant) 0 450,000 (450,000) *11IB300M Information Technology - Maintenance Works 900,000 860,000 40,000 11PK300M Playgrounds Audit Maintenance Works 100,000 106,564 (6,564)11PK301M Depot Yards - Plant & Infrastructure Maintenance 100,000 100,000 0 11PK302M Small Reserves - Maintenance Works 50,000 52,389 (2,389)11PK303M Parks Stormwater Drains - Maintenance Works 50,000 56,973 (6,973)11PK304M Tree Plot Maintenance Works 150,000 144,286 5,714 11PK305M Park Drought Works - Warm Season Grass Planting 100,000 161,589 (61,589)11PK306M Advance Park Design 150,000 165,760 (15,760)11PK307M Parks Buildings & Structures Maintenance Works 100,000 103,867 (3,867)11PS300M Accommodation Maintenance Works 50,000 12,462 37,538 11PS301M Accommodation Modifications 300,000 301,804 (1,804)11PS303M Annual Programmed Minor Works - PMS 1,526,175 1,749,429 (223,254) #11PS304M CH2 Western Shutter - Preventive Mtce 75,000 75,000 0 11PS305M Fawkner Park Tennis Crt Electrical Mtce 80,000 0 80,000 11PU300M Advance Urban Design 270,000 291,135 (21,135)11RW300M YMCA Recreation Facility Maintenance Works 200,000 129,555 70,445 11TM300M Melbourne Visitor Booth Maintenance 10,000 8,068 1,932

2011-12 Council Works Program Fourth Quarter Project Listing

* Denotes comment explaining adjustment is contained in Attachment 3# Denotes comment explaining variance is contained in Attachment 6

Attachment 5Agenda Item 5.9

Future Melbourne Committee14 August 2012

Page: 1 of 5

Page 12 of 19

Page 16: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

#PJ02 - 12-Jul-2012 08:09:30 LEADAV

Annual YTD VarianceProject Budget Actual Fav/(Unfav)

2011-12 Council Works Program Fourth Quarter Project Listing

* Denotes comment explaining adjustment is contained in Attachment 3# Denotes comment explaining variance is contained in Attachment 6

Attachment 5Agenda Item 5.9

Future Melbourne Committee14 August 2012

11TM302M Melbourne Visitor Centre Maintenance 50,000 20,509 29,491 11UL300M Tree Maintenance Works - Pest & Disease Management 150,000 150,000 0

Project costs to be allocated 0 (226,673) 226,673

Total Maintenance 8,361,175 8,768,357 (407,182)

TOTAL MAINTENANCE PROJECTS 10,301,175 10,352,325 (51,150)

CAPITAL PROJECTSNew Works

07DE005N North Melbourne (Errol St) Open Space Development 114,958 114,958 0 08CW002N World Trade Centre (Northbank Promenade 4,5 & 6) 9,091,597 2,050,000 7,041,597 #08DE003N Cultural Precincts Program 400,000 755,839 (355,839) #09CW004N Cultural Precincts Narration 41,000 41,000 0 09IB006N IT - Web & Customer Facing New Program 60,000 54,779 5,221 09IB008N IT - Pathway & AssetMaster New Program 180,000 (5,036) 185,036 09IB009N IT - Corporate Systems New Program 280,000 250,000 30,000 09PK002N Tan Track - New Stormwater Management Works 0 21,505 (21,505) *09PK004N Holland Park - Pathways, Lighting & Signage Works 0 80,706 (80,706) #09PS029N Comm Bank Building Upgrade - DDA Compliance 222,912 286,192 (63,280)10AC000N Public Art Program 188,975 164,923 24,052 10CD007N D - New Library & Community Centre - Docklands 2,740,000 1,145,000 1,595,000 #10CS001N Carlton Family, Childrens and Aged Services Design 70,340 66,057 4,283 10CS003N Hotham Hub Children's Centre Landscaping 0 39,016 (39,016) *10CW001N Yarra Pedestrian Bridge - Roadworks & Linkages 800,000 800,000 0 10CW002N Boyd School Redevelopment 7,380,952 7,441,785 (60,833)10CW003N Swanston Street Redevelopment Works 8,350,000 8,462,364 (112,364)10CW004N PL Swanson Street Redevelopment Works 6,350,000 8,797,922 (2,447,922) #10ES214N Streetscape Upgrade Elizabeth, Flinders Lane & King St 276,675 160,615 116,060 10IB000N IT New Corporate Systems 50,000 16,252 33,748 10IB002N IT New Pathway & Asset Master Applications 30,000 1,917 28,083 10IB004N IT New Web and Customer Facing Applications 136,000 80,500 55,500

10MC001N New Christmas Decorations 40,000 (18,687) 58,687 10PK003N Fawkner Park Northern Entry New Interface Works 57,880 69,442 (11,562)10PK012N Princes Park Depot New Park Reinstatement Works 59,620 86,820 (27,200)10PK013N Royal Park Entries to The Avenue & Southgate St 64,696 28,581 36,115 10PK014N Southbank Promenade Infrastructure & Landscaping 80,000 71,712 8,288 10PK019N Water Conservation & Climate Adaption Projects 1,500,000 1,537,770 (37,770)10PK024N D Docklands Waterways Working Berth Upgrade Works 40,000 4,946 35,054 10PK026N Princes Park New Depot & Relocation Works 0 145,182 (145,182) #10PK027N Tan Track Timer Clock 0 78,469 (78,469) *10PS001N Public Gallery Air Conditioning Upgrade 55,000 0 55,000 10PS005N Princes Park - Depot Development 49,280 51,316 (2,036)10PS006N Water Saving Works in Council Buildings 90,000 90,000 0 10PS024N QVM - F Shed Cover - Design 40,000 32,791 7,209 10PS062N East Melbourne Library Shading 28,000 20,000 8,000 10PS063N North Melbourne Community Centre CS - Desk Upgrade 30,000 23,754 6,246 10PS065R Kensington Community Rec Centre - Pool UV System 60,000 59,779 221 10PS067N North Melb Pool - Design of Refurbishment Works 23,065 41,135 (18,070)10PU003N Urban Forest Strategy - Eades Place Greening 284,400 661,750 (377,350) #10PU005N Moonee Ponds Creek Landscaping 90,909 109,636 (18,727)10RW005N Carlton Baths Rec Centre - Upgrade Works - Design 200,000 200,420 (420)10RW006N Docklands Social and Recreation Hub Design 50,000 6,400 43,600 10RW007N Flemington/Kensington Bowling Club Synthetic Green Install 0 352,210 (352,210) *

Page: 2 of 5

Page 13 of 19

Page 17: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

#PJ02 - 12-Jul-2012 08:09:30 LEADAV

Annual YTD VarianceProject Budget Actual Fav/(Unfav)

2011-12 Council Works Program Fourth Quarter Project Listing

* Denotes comment explaining adjustment is contained in Attachment 3# Denotes comment explaining variance is contained in Attachment 6

Attachment 5Agenda Item 5.9

Future Melbourne Committee14 August 2012

11AC000N Art Play Backyard - Phase 1 70,000 29,000 41,000 11AC001N Public Art Program 450,000 259,034 190,966 11BU004N New Organic Recycling Machine 0 24,000 (24,000) *11CD004N North Melbourne Library Upgrade 40,000 55,523 (15,523)11CD007N East Melbourne Library floor/environment upgrade 100,000 25,000 75,000 11CD008N Multicultural Hub Access to Drill Hall 175,000 192,810 (17,810)11CD010N Drill Hall - CBD Health Service Fit-Out 180,000 352,014 (172,014) *11CM001N New Christmas Decorations 1,000,000 993,670 6,330 11CS004N Hotham Hub Childrens Playground Development 0 12,544 (12,544)11CS041N Nth Melb Community Centre redevelopment works 336,600 346,564 (9,964)11CS042N Nth Melb MCH New Consulting Room 54,000 42,918 11,082 11CW002N QVM - Capital Improvements 750,000 600,000 150,000 11CW004N Implementation of D2 Initiatives 500,000 247,288 252,712 #11CW005N Yarra Pedestrian Bridge - Western Gateway Linkage 522,000 475,074 46,926 11DE003N Docklands Pedestrian Wayfinding Signage 0 35,429 (35,429) *11ES005N Safe City Taxi ranks 620,000 305,260 314,740 #11ES013N Major Streetscape Improvements - KSA 1,000,000 1,000,000 0 11ES015N North & West Melb. Zebra Pedestrian Crossings 0 300,000 (300,000) *11ES016N Bicycle Improvements 1,200,000 592,871 607,129 #11ES017N Minor Streetscape Improvements 210,000 196,882 13,118 11ES018N New Drainage Infrastructure 300,000 300,000 0 11ES023N Construction of Bin Enclosures 100,000 100,000 0 11ES032N Road Safety Improvements 400,000 402,180 (2,180)11ES216N Arts Centre Bluestone Paving 0 450,000 (450,000) *11IB000N Information Technology - New Works Program 1,570,000 1,371,000 199,000 11PK001N D - New Signage Installation - Docklands Waterways 100,000 32,378 67,622 11PK003N Holland Park - Childcare Centre Carpark Works 190,000 201,742 (11,742)11PK004N Royal Park - Native Gardens New Public Toilet 200,000 249,704 (49,704)11PK005N Fitzroy Gardens-Stormwater Harvesting & New Depot 6,450,000 2,962,230 3,487,770 #11PK006N Holland Park - Sports Pavilion Construction Works 2,250,000 440,000 1,810,000 #11PK008N Fawkner Park - Western Boundary Stage 3 Works 100,000 110,176 (10,176)11PK010N North Melbourne Open Space Development 800,000 70,000 730,000 #11PK013N Royal Park (RHC) Return to Parkland 0 82,747 (82,747) *11PK014N Queensbridge Square Landscaping & Tree Planting 0 65,288 (65,288) *11PS001N QVM - Upgrade of Fire Services - Stage 2 300,000 300,000 0 11PS005N Furniture Equipment & Whitegoods Acquisitions 40,000 40,000 0 11PS009N Office Precinct - Advance Design 250,000 55,000 195,000 11PS033N Water Saving Works in Council Buildings 100,000 75,000 25,000 11PS035N Art Play external shading and Sustainability works 188,960 120,000 68,960 11RW006N Carlton Baths Community Centre Upgrade 5,900,000 6,184,999 (284,999) #11RW008N Royal Park North Cricket Practice Nets 170,000 218,638 (48,638)11RW009N North Melbourne Pool - Solar Heating 75,000 75,360 (360)11RW013N Kensington Comm Rec Centre personal training area 50,000 75,254 (25,254)11RW014N Pool Backwash Water Treatment System 75,000 71,953 3,047 11SW000N Southbank - Police Pod 350,000 0 350,000 #11UL000N Climate Adaptation Projects 1,942,000 919,689 1,022,311 #

Project costs to be re-allocated 0 (72,457) 72,457

Total New Works 68,714,819 55,466,482 13,248,337

Renewal / Refurbishment09PS005R Town Hall & Venue Renewal Works 30,910 32,227 (1,317)09PS006R MTH - Admin Building Air Conditioning Replacement 124,550 117,874 6,676 09PS024R Leased Commercial Properties - Renewal Works 195,005 176,805 18,200 09PS027R Admin Building - South Wall Render 115,620 56,000 59,620

Page: 3 of 5

Page 14 of 19

Page 18: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

#PJ02 - 12-Jul-2012 08:09:30 LEADAV

Annual YTD VarianceProject Budget Actual Fav/(Unfav)

2011-12 Council Works Program Fourth Quarter Project Listing

* Denotes comment explaining adjustment is contained in Attachment 3# Denotes comment explaining variance is contained in Attachment 6

Attachment 5Agenda Item 5.9

Future Melbourne Committee14 August 2012

09PS046R Building Retrofits - Energy Performance Contract 0 1,191,387 (1,191,387) *09PS048R MTH - LIft Upgrade & Related Works 436,600 436,600 0 09PS049R MTH - Fire-Related Works 129,096 0 129,096 09PS050R BIS Server Room 50,000 94,073 (44,073)10CW005N Upgrade of Queen Street at QVM 650,000 650,000 (0)10ES006R Corporate Fleet Replacement 27,850 26,828 1,022 10ES012R Drains Renewal 129,773 129,773 0 10ES014R Parking Meter Renewal 264,491 264,383 108 10IB001R IT Renewal of Corporate Systems 100,000 99,361 639 10IB003R IT Renewal of Pathway & Asset Master Applications 185,000 125,000 60,000 10IB005R IT Renewal of Web and Customer Facing Appns 180,000 94,294 85,706 10IB007R IT Renewal of Technological Infrastructure 1,130,000 1,159,847 (29,847)

10MC000R Refurbishment of Christmas Tree 108,940 123,154 (14,214)10MC002R Refurbishment of Christmas Decorations City 72,750 24,428 48,322 10PK020R Parks Renewal Program Works 148,647 141,908 6,739 10PS002R Safe Access Works 35,000 22,650 12,351 10PS009R Sinclair's Cottage Stables Renewal Works 51,010 73,684 (22,674)10PS010R DDA Physical Access 185,008 185,008 0 10PS015R City Square Carpark Sewer Pump Works 45,000 45,000 (0)10PS017R Council Buildings Insurance Compliance Works 194,000 110,000 84,000 10PS020R Nth Melb Library - AirConditioning Replacement 150,000 0 150,000 10PS023R QVM - 153 Victoria Street Electricity Upgrade 300,000 65,200 234,800 #10PS036R Community Services Building Renewals 483,174 243,000 240,174 #10PS042R Town Hall & Venue Renewal Works 115,395 30,000 85,395 10PS044R MV Site - Kensington Town Hall Upgrade 1,188,000 954,106 233,894 #10PS047R Public Toilets - Renewal Works 116,084 90,000 26,084 10PS048R CBD Lifts - Renewal Works 55,000 55,000 0 10PS049R Administration Building - Renewal Works 50,000 76,000 (26,000)10PS050R Stores & Archives Building - Renewal Works 314,153 264 313,889 #10PS052R Leased Commercial Properties - Renewal Works 247,765 270,870 (23,105)10PS060R Newmarket Saleyards Fencing & Paving 100,000 100,000 0 10RW002R Leased Recreation Facility - Fence Renewals 8,836 10,049 (1,213)11AC002R Arts House energy efficient LED theatrical lights 20,000 19,500 500 11BU003R Replacement of Major Catering Equipment 128,500 128,500 0 11CD001R Library Services Plant and Equipment Replacement 80,000 76,510 3,490 11CD002R Library collections 865,000 888,198 (23,198)11CD003R Library infrastructure renewal - City Library 100,000 131,736 (31,736)11CD013R Kensington Town Hall Refurbishment 1,000,000 220,000 780,000 *11CM000R Refurbishment of the Christmas Tree 150,000 152,522 (2,522)11CM002R Refurbishment of Christmas Decorations - City 150,000 45,814 104,186 11CM003R D - Refurbishment of Christmas Decorations - Docklands 70,000 42,276 27,724 11CR000R Town Hall Customer Service Point - design works 350,000 14,250 335,750 #11CS052R Lady Huntingfield Children's Centre Ovens 30,000 28,138 1,862 11ES006R Corporate Fleet Replacement 1,030,000 1,024,183 5,817 11ES008R DDA Compliance - Infrastructure 350,000 350,000 (0)11ES010R Queens Bridge & Stock Bridge Structural Repairs 1,550,000 1,550,000 (0)11ES011R Flood Mitigation 1,000,000 848,657 151,343 11ES012R Drains Renewal 1,000,000 1,000,000 (0)11ES014R Parking Meter Renewal 800,000 800,000 (0)11ES026R Kerb and Channel Renewal 1,200,000 1,200,000 0 11ES027R Street Furniture Installation 400,000 400,000 (0)11ES030R Roads to Recovery Program 347,450 347,450 0 11ES031R Victorian Grants Commission - Local Roads Funding 550,000 550,000 0 11ES132R Roadways Renewal 5,000,000 5,000,000 1 11ES213R Footpaths Renewal 4,500,000 4,500,000 (0)

Page: 4 of 5

Page 15 of 19

Page 19: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

#PJ02 - 12-Jul-2012 08:09:30 LEADAV

Annual YTD VarianceProject Budget Actual Fav/(Unfav)

2011-12 Council Works Program Fourth Quarter Project Listing

* Denotes comment explaining adjustment is contained in Attachment 3# Denotes comment explaining variance is contained in Attachment 6

Attachment 5Agenda Item 5.9

Future Melbourne Committee14 August 2012

11ES214R Streetscape Works in Bond Street 0 300,000 (300,000) *11IB001R Information Technology - Renewal Works Program 7,360,000 8,757,306 (1,397,306) #11PK007R Parks Renewal Program Works 7,005,000 6,982,711 22,289 *11PK011R Parks Buildings & Structures Renewal Works 400,000 400,000 0 11PS000R QVM - Repl. of Franklin St Asbestos Rooves - Stg 3 104,500 101,836 2,664 11PS002R QVM - 153 Victoria Street Electricity Upgrade Stg 3. 104,500 1,000 103,500 11PS003R QVM - Dairy Hall Works 292,600 299,812 (7,212)11PS004R QVM - Window & Gutter Restoration Works Vic. St. 137,940 117,245 20,695 11PS010R Off-street Car Parks Security Systems Renewal Work 125,000 125,000 0 11PS013R Admin Buildings Renewal Works 971,400 940,579 30,821 11PS014R Baths Renewal Works 223,400 276,216 (52,816)11PS015R Community Services Building Renewal Works 715,350 629,552 85,798 11PS016R Leased Commercial Properties Renewal Works 847,725 803,494 44,231 11PS017R Leased Recreational Properties Renewal Works 13,400 13,400 0 11PS018R Public Conveniences Renewal Works 23,300 21,342 1,958 11PS019R Town Hall Buildings Renewal Works 149,325 79,000 70,325 11PS020R DDA Compliance Works - Buildings 500,000 465,000 35,000 11PS021R Melb Town Hall and MTH-Admin Electrical safety wrk 120,000 117,525 2,475 11PS023R Waste Trf Stn - Civil repair & upgrades 250,000 50,000 200,000 #11PS024R QVM - Solar Array panel and sys. monitoring upgrade 85,000 85,000 0 11PS025R Insurance Works to Council Buildings - Stage 2 401,300 50,000 351,300 #11PS026R Lift Upgrade works 978,000 204,000 774,000 #11PS027R CH2 - Lighting Renewal Works 150,000 150,000 0 11PS028R Melb City Baths Systems & Structure Renewal Works 531,000 227,000 304,000 #11PS029R Newmarket & Kensington Renewal Works 250,000 220,000 30,000 11PS030R Domain House AirCon Renewal Works 90,000 70,000 20,000 11PS031R Carlton Gardens Tennis Club Pavilion Renewal Works 200,000 156,535 43,465 11PS032R North Melb Recreation Centre Design Issues 150,000 116,703 33,297 11PS034R Pools Electrical RCD circuitry Renewal Wrks 60,000 60,000 (0)11PS036R QVM - Minor Capital Renewal Works 180,000 180,000 0 11RW000R Leased Recreation Facility Fence Renewals 200,000 173,610 26,390 11RW001R Community Recreation Facility renewal works 100,000 47,089 52,911 11RW002R Annual Fitness Centre Equipment Renewal 100,000 96,013 3,987 11RW012R North Melbourne Recreation Centre Refurbishment 317,000 213,072 103,928

Project adjustments to be allocated 0 (175,595) 175,595

Total Renewal / Refurbishment 51,524,347 48,946,951 2,577,396

TOTAL CAPITAL PROJECTS 120,239,166 104,413,433 15,825,733

TOTAL MAINTENANCE AND CAPITAL PROJECTS 130,540,341 114,765,758 15,774,583

Page: 5 of 5

Page 16 of 19

Page 20: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments
Page 21: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

Page 1 of 3

Attachment 6 Agenda Item 5.9

Future Melbourne Committee 14 August 2011

2011-12 Council Works Program Schedule of Projects Variances Projects >$200,000 variance to plan

Project $Annual Budget

Actual Expend. Variance

08DE003N Cultural Precincts Program 400,000 755,839 (355,839)

The structure of the Cultural Precincts Program is based on the State Government contribution being in arrears, hence work is carried out before the State Government can be invoiced. The proposed State Government contribution was not included in the original budget.

10PS023R QVM – 153 Victoria Street Electricity Upgrade 300,000 65,200 234,800

Negotiation between QVM management and Citipower being finalized in respect to the requirements for upgrading power at QVM. Work is expected to commence in August 2012.

10PS036R Community Services Building Renewals 483,174 243,000 240,174

Extensive program finalized scoping late in financial year and could not be fully achieved. Work is progressing to complete the delivery.

10PS044R Kensington Town Hall Upgrade 2,188,000 1,174,106 1.013,894 11CD013R Two separate contracts are required to deliver the heritage repairs

and the requirements for services upgrades and a compliant accessible entrance. Insufficient funds for both hence repairs and removal of hazardous materials carried out prior to the services upgrade, which will receive additional funding in 2012-13.

10PS050R Stores & Archives Building – Renewal Works 314,153 264,000 313,889

Major rendering repairs were planned but scaled back pending the Council’s decision on the future of the building. The remaining funding has been declared surplus.

10PU003N Urban Forest Strategy – Eades Place Greening 284,400 661,750 (377,350)

Following commencement of the project additional scope and cost was required to address electrical power matters and other latent conditions.

10CD007N Community Infrastructure Docklands Library 2,500,000 510,000 1,990,000

This project is the multi year project to develop a library and community centre in Docklands. Developer arrangements have been finalised and construction will commence in the first quarter of 2012-13.

10ES006R Corporate Fleet Replacement 1,325,000 1,057,437 267,563

Lower expenditure due to planned number of new executive vehicles being purchased not being achieved due to several executives electing not to take up vehicles as part of their salary package. The excess funds are surplus.

10CW004N PL Swanston Street Redevelopment Works 6,350,000 8,797,922 (2,447,922)

Additional work was carried out to meet the various timeframes resulting in over expenditure in 2011-12, which will be offset by savings in the 2012-13 Council Works Program. The overall project budget is unchanged at $25.6 million.

Page 17 of 19

Page 22: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

Page 2 of 3

Project $Annual Budget

Actual Expend. Variance

11CR000R Town Hall Customer Service Point – design works 350,000 14,250 335,750

The funding for this project is to be carried forward in conjunction with other projects and amalgamated to form the design funding for the refurbishment of the town hall administration building.

11CW004N Implementation of D2 initiatives 500,000 247,288 252,712

The shortfall of expenditure relates to the delays in the joint agreement between Places Victoria and City of Melbourne in respect to the siting and scope of the multi purpose sporting courts.

11ES005N Safety City taxi ranks 620,000 305,260 314,740

Council agreement to not proceed with additional safe city taxi ranks in Collins Street, whilst concentrating on the Queen Street mega taxi rank site: This has led to an under expenditure.

11ES016N Bicycle Improvements 1,200,000 592,811 607,129

Funding required for Latrobe Street improvements, which was agreed by April 2012 Council meeting to be deferred due to requirement for community engagement to seek the most appropriate solution.

11IB001R Information Technology – Renewal Works Program 7,360,000 8,757,306 (1,397,306)

Council agreed to accelerate the IT replacement program in order to address some irregularities, resulting in pre-commitment of some 2012-13 program funds.

11PK005N Fitzroy Gardens – Stormwater Harvesting & New Depot 6,450,000 2,962,230 3,487,770

The stormwater harvesting project has been delayed by inclement weather and an earlier collapse of batters. This has resulted in consequent delays to the tendering and construction of the depot and visitors centre.

11ES301M Street Lighting Maintenance 1,400,000 1,640,449 (240,449)

The over expenditure is due to CitiPower increasing the 2011 operational maintenance and repair costs by 32 per cent to maintain Council’s unmetered street lighting network. This decision occurred in mid year.

11PS303M Annual Programmed Minor Works - PMS 1,526,175 1,749,429 (223,254)

Additional works found to be required compared to the original scheduled scope.

11PK006N Holland Park – Sports Pavilion Construction works 2,250,000 440,000 1,810,000

Progress on the construction was slow due to financial difficulties of the contractor who subsequently has gone into administration. The contract has been terminated and tenders are being recalled for the balance of the work.

11PK010N North Melbourne Open space Development 800,000 70,000 730,000

This project is the creation of new public space at Errol Street North Melbourne. The contract has been executed following a protracted period involving referrals to VCAT, however the start was considerably delayed.

11PS025R Insurance Works to Council Buildings – Stage 2 401,300 50,000 351,300

Works delayed due to the late appointment of a project manager by the managing contractor.

Page 18 of 19

Page 23: 2011-12 FOURTH QUARTER COUNCIL WORKS PROGRAM REPORT · the 2011-12 Council Works Program at the end of the fourth quarter of the 2011-12 financial year and of the works program adjustments

Page 3 of 3

Project $Annual Budget

Actual Expend. Variance

11PS026R Lift Upgrade works 978,000 240,000 774,000

The full amount of funding was not fully required and $600,000 has been declared surplus. $174,000 is to be carried forward to address current requirements.

11PS028R Melb City Baths Systems & Structure Renewal Works 531,000 227,000 304,000

Planning of the works required significant preliminary investigations, scoping, design and sourcing appropriate materials. The work will be carried out in 2012-13.

11RW006N Carlton Baths Community Centre Upgrade 5,900,000 6,184,999 (284,999)

Considerable additional work has been required to deal with site contamination, whilst building works continued on site. This has led to additional expenditure being required.

11UL000N Climate Adaptation Projects 1,942,000 919,689 1,022,311

This involves the Birrarung Marr and Queen Vic. Gardens Water Harvesting projects. Both projects have had significant design changes following further detailed investigation. This has delayed both of the projects which will be proceeding during 2012-13, where further funding is provided.

Page 19 of 19