2012 construction general permit_paseo lineal phase i
DESCRIPTION
NPDES storm water discharge permitTRANSCRIPT
9/8/2015 2012 Construction General Permit
http://ofmpub.epa.gov/apex/aps/f?p=119:4:0::NO::P4_PERMIT_ID,P4_PERMIT_TYPE:21911,NOI 1/3
You are here: Permits Landing Page 2012 CGP 2012 CGP Details
Quick Jump to OtherPermits
2012 Construction General Permit eNOIDetail
Details for PRR12A796
General Information
Project / Site Name: PASEO PUERTA DE TIERRA FASE IICurrent Status: TerminatedTracking Number: PRR12A796Permit Type: NOI
Interview Page Answers
Is your project/site located in Indian Country Lands? NoAre you requesting coverage under this NOI as a 'federal operator' as definedin Appendix A?
No
Operator Information
Operator's Name: AUTORIDAD FINANCIAMIENTO INFRAESTRUCTURA AFIStreet: PO BOX 41207City: SAN JUANState: Puerto RicoZip Code: 00940Point of Contact Name: SALIM LAHAMPhone Number: 787 762-5757Operator Email: [email protected]: N/AIRS Employer Identification Number (EIN): 660480699
Project / Facility Information
Project / Site Name: PASEO PUERTA DE TIERRA FASE IIStreet: MUÑOZ RIVERA AVE.City: SAN JUANState: Puerto RicoZip Code: 00906Project / Facility on Indian Land? NoReservation Name: N/A
Additional Project Information
Is your project an 'emergency-related project' as defined in Appendix A? NoHave stormwater discharges from your project/site been covered previouslyunder an NPDES permit?
Yes
Estimated Project Start Date: 07/29/2014Estimated Project End Date 05/28/2015Have earth-disturbing activities commenced on your project/site? YesCounty or Similar government subdivision: San Juan
Feedback
9/8/2015 2012 Construction General Permit
http://ofmpub.epa.gov/apex/aps/f?p=119:4:0::NO::P4_PERMIT_ID,P4_PERMIT_TYPE:21911,NOI 2/3
Latitude and Longitude Information
Longitude: 66,05,15Longitude Unit: (degrees, minutes, seconds)Latitude: 18,27,49Latitude Unit: (degrees, minutes, seconds)Latitude / Longitude Data Source: GPSHorizontal Reference Datum NAD 83 or WGS 84Estimated Area to be Disturbed (to the nearest quarter acre): 3.41
Chemical Treatment Information
Will you use polymers, flocculants, or other treatment chemicals at yourconstruction site?
No
ESA
Under which criterion listed in Appendix D are you eligible for coverage underthis permit?
A. No federally-listed threatened or endangered species or theirdesignated critical habitat(s) are likely to occur in your site’s “actionarea” as defined in Appendix A of this permit
Provide the basis for criterion selection selected: Communications with government agencies1) Any federal listed species and/or designated habitat located in your area: N/A2) The distance between your site and the listed species or designated criticalhabitat (in miles):
N/A
SWPPP Point of Contact
Name: SALIM LAHAMOrganization Name: AFIPhone: 787 762-5757Fax: N/AEmail: [email protected]
Discharge Information
Does your project/site discharge stormwater into a Municipal Separate StormSewer System (MS4)?
Yes
Are there any surface waters within 50 feet of your project's earthdisturbances?
Yes
If a TMDL has been approved or established, identify the title or reference ofthe TMDL document:
N/A
Impaired Surface Waters to Which you Discharge
Surface water(s) to which you discharge Impaired Water Listed Water Pollutant(s) Tier 2, 2.5 or 3 Source TMDL Name and Pollutant
LAGUNA DEL CONDADO Yes OIL AND GREASE;TURBI NoEPA 2012 PRIMPAIREDWATERS LIST
Historic Preservation
Is your project/site located on a property of religious or cultural significance toan Indian tribe? Are you installing any stormwater controls as described inAppendix E that require? (Appendix E, Step 1):
Yes
If yes, have prior surveys or evaluations conducted on the site have alreadydetermined historic properties do not exist, or that prior disturbances haveprecluded the existence of historic properties? (Appendix E, Step 2):
Yes
If no, have you determined that your installation of subsurface earth-disturbing
9/8/2015 2012 Construction General Permit
http://ofmpub.epa.gov/apex/aps/f?p=119:4:0::NO::P4_PERMIT_ID,P4_PERMIT_TYPE:21911,NOI 3/3
stormwater controls will have no effect on historic properties? (Appendix E,Step 3):
N/A
If no, did the SHPO, THPO, or other tribal representative (whichever applies)respond to you within the 15 calendar days to indicate whether the subsurfaceearth disturbances caused by the installation of stormwater controls affecthistoric properties? (Appendix E, Step 4)
N/A
If yes, describe the nature of their response: N/A
Certifier Information
Name: SALIM LAHAMTitle: ENGINEEREmail: [email protected] Date: 04/14/2015
Preparer Information
Name: SALIM LAHAMPhone: (787) 763-5757Fax: N/AOrganization: AFIEmail: [email protected]
Corresponding DocumentsNo data found.
Back to Search Results
release 1.0