Primavera P6 Settings
Presented by
Karen Reynolds, PartnerConstruction Science, LLC
Primavera P6 Settings
Presented by
Karen Reynolds, PartnerConstruction Science, LLC
SETUPSETUP“Scope of Work”
©2012 Construction Science, LLC 2
ToolbarsToolbars
Turn Toolbars On Project Assign Edit Layout Enterprise Action Bottom Layout Dictionaries Display Find Standard Top Layout
Turn Toolbars Off Print Administrator Publish Reports Tools Move
©2012 Construction Science, LLC 3
©2012 Construction Science, LLC
4
ToolbarsToolbars
Turn on buttons in each menu area
Click “More Buttons”
NewOpenClose All
ProjectsEPSOBS
ActivitiesWBS
AddDelete
DissolveLink Activities
UndoFill Down
Activity CodesPredecessors
Successors
TableGantt Chart
Activity NetworkRelationship Lines
DetailsTrace Logic
No Bottom Layout
Filter ByGroup & Sort By
Zoom InZoom OutHint HelpContent
Activity CodesCalendars
ImportExport
Customize Project ColumnsCustomize Project Columns
©2012 Construction Science, LLC 5
Project ID, Project Name, Start, Finish, Must Finish By, Total Float, Data Date
Customize Project Details BoxCustomize Project Details Box
To customize tabs in the Details box
Right-click anywhere in the Details box Select Customize Project Details
©2012 Construction Science, LLC 6
Show on BottomDetails
General, Notebook, Dates Defaults
©2012 Construction Science, LLC 7
Customize Activity ColumnsCustomize Activity Columns
Choose from over 250 columns
Activity ID, Activity Name, Original Duration, Start, Finish, Total Float, Activity Type, Duration Type, Calendar
Customize Activity Details BoxCustomize Activity Details Box
©2012 Construction Science, LLC 8
Right-click in grey area
General, Status, Predecessor, Successor, Codes
©2012 Construction Science, LLC 9
The Predecessor TabThe Predecessor Tab
Critical: determined by P6 based on user definition in Tools -> Schedule -> Options
Driving: determined by P6, if activity is affecting the schedule of its successor
©2012 Construction Science, LLC 10
The Successor TabThe Successor Tab
Customize the columns as shown (right-click in the grey).
Critical: determined by P6 based on user definition (float or longest path) on Settings tab of Project Details Box.
Critical: determined by P6 based on user definition in Tools -> Schedule -> Options
Late Start: Helps you understand schedule flexibility
Driving: determined by P6, if activity is affecting the schedule of its successor
©2012 Construction Science, LLC11
Calendar RecommendationCalendar Recommendation
Use the Global Calendar list ONLY as a library of calendars to copy when creating Project Calendars.
Since the Default Calendar controls the days which are shaded grey on the Gantt Chart, design a basic 5 workday/week calendar so the weekends will be shaded grey on the Gantt Chart.
With extreme caution, you can use Global Calendars to set Holidays for Project Calendars
Project Calendar OverrideProject Calendar Override
©2012 Construction Science, LLC 12
The settings at Admin > Admin Preferences > Time Periods
will override the calendar assigned to the project unless the box is checked to allow the
calendar to drive.
Baseline SetupBaseline Setup
When creating baselines from projects which already have progress (actuals), you must use the correct Admin settings or the Gantt Chart bars will not appear correctly
©2012 Construction Science, LLC 13
Admin -> Preferences -> Earned ValueUnder Earned Value Calculation,
When calculating earned value from a baseline use:Select “Budgeted Values with Current Dates”,
NOT “Budgeted Values with Planned Dates”
The Impact of TimeThe Impact of Time
P6 schedules by the hour regardless of the time unit you choose to display
To View Time• Go to Edit -> User Preferences -> Dates• Check “12 Hour”• Check “Show Minutes”
The default time of 12:00 AM impacts• Data Date – day after last update• Must Finish By – must finish before