    Generator Interconnection

    Business Practices ManualBPM-015-r6Effective date: TBD

    EM-1000 Public

    Manual No. 015

    Business Practices ManualGenerator Interconnection

  • 7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1

    2/14

    Generator Interconnection

    Business Practices ManualBPM-015-r6Effective date: TBD

    OPS-12 PublicPage i

    Disclaimer

    This document is prepared for informational purposes only to support the application of the

    provisions of the Open Access Transmission, Energy and Operating Reserve Markets Tariff

    (Tariff) of the Midwest ISO, Inc. (MISO) and the services provided under the Tariff. MISO may

    revise or terminate this document at any time at its discretion without notice. However, every

    effort will be made by MISO to update this document and inform its users of changes as soon as

    practicable. Nevertheless, it is the users responsibility to ensure you are using the most recent

    version posted on MISO website. In the event of a conflict between this document and the

    Tariff, the Tariff will control, and nothing in this document shall be interpreted to contradict,

    amend or supersede the Tariff.

    This Business Practices Manual (BPM) contains information to augment the filed and accepted

    Tariff of MISO. In all cases the Tariff is the governing document and not the BPM. Additionally, if

    not otherwise defined herein, all capitalized terms in this BPM have the meaning as defined in

    the Tariff.

    Time Zone

    In 2006, Central Indiana, where MISO offices are located, began observing Daylight Savings

    Time. However, MISO, its systems, and the Midwest Markets, will continue to do business in

    Eastern Standard Time year-round.

  • 7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1

    3/14

    Generator Interconnection

    Business Practices ManualBPM-015-r6Effective date: TBD

    OPS-12 PublicPage ii

    Revision History

    DocumentNumber

    Reason for Issue Revised by: Effective Date

    BPM-015-r6 Revised to reflect the November 1st,2011 filing of the modifications to theGenerator Interconnection Proceduresand Agreement.

    E. Laverty

    BPM-015-r5 MISO Rebranding Changes E. Nicholson MAR-21-2011

    BP-015-r5 Revised to reflect the sixth M2 milestoneoption and separate deliverabilityanalysis into its own subsection.

    E. Laverty MAR-21-2011

    BPM-015-r4 Revised to reflect July 15th

    filing forShared Network Upgrades

    E. Laverty JUL-16-2010

    BPM-015-r3 Revised to reflect numbering protocol E. Laverty JAN-01-2010

    TP-BPM-004-r2 Revised to reflect the Open AccessTransmission, Energy and OperatingReserve Markets Tariff for the MidwestISO, Inc. (Tariff) relating toimplementation of the Day-Ahead andReal-Time Energy and AncillaryServices Markets and to integrateproposed changes to the Balancing

    Authority Agreement.

    E. Laverty JAN-06-2009

    TP-BPM-004-r1 Revised to reflect the June 25th, 2008filing of the modifications to theGenerator Interconnection Proceduresand Agreement.

    J. Doner AUG-25-2008

  • 7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1

    4/14

    Generator Interconnection

    Business Practices ManualBPM-015-r6Effective date: TBD

    OPS-12 PublicPage iii

    TABLE OF CONTENTS

    1. Introduction ...........................................................................Error! Bookmark not defined.11.1 Purpose of the MISO Business Practices Manuals ....Error! Bookmark not defined.11.2 Purpose of this Business Practices Manual ...............Error! Bookmark not defined.11.3 References ................................................................Error! Bookmark not defined.1

    2. Generator Interconnection Process Overview .......... ..........Error! Bookmark not defined.33. Pre-Queue Phase ..................................................................Error! Bookmark not defined.4

    3.1 Resources Available ..................................................Error! Bookmark not defined.43.1.1 Contour Map.....................................Error! Bookmark not defined.43.1.1.1 Ongoing Efforts ................................Error! Bookmark not defined.6

    3.2 Regularly Scheduled Information Sessions .......... ......Error! Bookmark not defined.63.3 Ad Hoc Information Sessions ........... .......... ........... .....Error! Bookmark not defined.6

    4. Application Review Phase ....................................................Error! Bookmark not defined.84.1 Scoping Meeting ........................................................Error! Bookmark not defined.84.2 Initial Screening .........................................................Error! Bookmark not defined.9

    4.2.1 Application Milestones (M1) .......... ..Error! Bookmark not defined.104.2.2 Definitive Planning Phase Entry Milestones (M2)Error! Bookmark not defined.114.2.3 Letter of Credit Requirements .........Error! Bookmark not defined.134.2.4 Feasibility Study .............................Error! Bookmark not defined.134.2.5 Study Deposits and Refunds ..........Error! Bookmark not defined.15

    4.3 Determination of Project Linkages and Potential GroupingError! Bookmark not defined.184.4 Queue Position ........................................................Error! Bookmark not defined.19

    5. System Planning and Analysis Phase ...............................Error! Bookmark not defined.205.1 Regular Generator Interconnection System Impact StudyError! Bookmark not defined.235.2 Planning and Operating Horizon Studies .................Error! Bookmark not defined.235.2.1 Power Flow Analysis ................................................Error! Bookmark not defined.23

    5.2.1.1 Determine available injection capabilityError! Bookmark not defined.235.2.1.2 Determine upgrades for requested serviceError! Bookmark not defined.245.2.1.3 Base Case Assumptions ................Error! Bookmark not defined.24

    5.2.1.3.1 Load Levels and Generation DispatchError! Bookmark not defined.24

  • 7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1

    5/14

    Generator Interconnection

    Business Practices ManualBPM-015-r6Effective date: TBD

    OPS-12 PublicPage iv

    5.2.1.3.2 Generation to Include ....Error! Bookmark not defined.255.2.2 Criteria Used to Determine Constraints .......... .......... Error! Bookmark not defined.255.3 Custom Scope .........................................................Error! Bookmark not defined.255.3.1 Timeframe ...............................................................Error! Bookmark not defined.255.3.2 Transmission Modeled .............................................Error! Bookmark not defined.265.3.3 Generation modeled ................................................Error! Bookmark not defined.265.3.4 Study Scenarios and Analyses ................................Error! Bookmark not defined.27

    5.3.4.1 Injection (ERIS) evaluation ........... ..Error! Bookmark not defined.275.3.4.2 Deliverability (NRIS) evaluation ......Error! Bookmark not defined.275.3.4.3 Transmission Service Request (TSR) evaluationError! Bookmark not defined.275.3.4.4 Net Zero evaluation ........................Error! Bookmark not defined.28

    5.3.5 Study Generator Dynamic Model .............................Error! Bookmark not defined.285.3.6 Outages ...................................................................Error! Bookmark not defined.28

    5.3.6.1 System Intact ..................................Error! Bookmark not defined.285.3.6.2 Planned Outages (specify) .............Error! Bookmark not defined.28

    5.3.7 Deliverables .............................................................Error! Bookmark not defined.295.3.7.1 Required System Improvements & CostError! Bookmark not defined.295.3.7.2 Amount of Service Available without Additional UpgradesError! Bookmark not defined.295.3.7.3 Interconnection Facilities for Reactive CompensationError! Bookmark not defined.305.3.7.4 Availability of Transmission ServiceError! Bookmark not defined.30

    6. Definitive Planning Phase ..................................................Error! Bookmark not defined.326.1 Generator Interconnection System Impact Study .....Error! Bookmark not defined.326.1.1 Steady State Analysis ..............................................Error! Bookmark not defined.33

    6.1.1.1 Thermal analysis ............................Error! Bookmark not defined.336.1.1.1.1 Base Case AssumptionsError! Bookmark not defined.346.1.1.1.1.1. Load Levels and Generation DispatchError! Bookmark not defined.346.1.1.1.1.2. Generation to Include Error! Bookmark not defined.356.1.1.1.2

    Applicable Reliability CriteriaError! Bookmark not defined.35

    6.1.1.1.3 Cascading Outage ConditionsError! Bookmark not defined.366.1.1.1.4 Prior Outage Conditions Error! Bookmark not defined.366.1.1.1.5 Permissible Software ToolsError! Bookmark not defined.36

  • 7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1

    6/14

    Generator Interconnection

    Business Practices ManualBPM-015-r6Effective date: TBD

    OPS-12 PublicPage v

    6.1.1.1.6 Criteria Used to Determine ConstraintsError! Bookmark not defined.366.1.1.1.7 Deliverability Analysis....Error! Bookmark not defined.376.1.1.1.8 Network Upgrade Cost AllocationError! Bookmark not defined.386.1.1.1.9 Shared Network Upgrade Cost Allocation EligibilityError! Bookmark not defined.39

    6.1.1.2 Steady State Voltage Analysis ........Error! Bookmark not defined.426.1.1.3 Power Factor Requirement Analysis for Wind Turbine GeneratorError! Bookmark not defined.42

    6.1.2 Short Circuit and Stability Analysis .......... ........... ......Error! Bookmark not defined.426.1.2.1 Base Case Assumptions ................Error! Bookmark not defined.43

    6.1.2.1.1 Load Levels .......... .........Error! Bookmark not defined.436.1.2.1.2 Generation to Include ....Error! Bookmark not defined.43

    6.1.2.2 Applicable Reliability Criteria ......... .Error! Bookmark not defined.436.1.2.3 Permissible Software Tools .......... ..Error! Bookmark not defined.436.1.2.4 Criteria Used to Determine Stability and Short Circuit ConstraintsError! Bookmark not defined.436.1.2.5 Mitigation Used to Resolve Stability ConstraintsError! Bookmark not defined.44

    6.1.3 Mitigation Verification ...............................................Error! Bookmark not defined.446.1.4 Backfilling ................................................................Error! Bookmark not defined.446.1.5 Customer Funded Network Upgrade Optional StudyError! Bookmark not defined.45

    6.1.5.1 Background ....................................Error! Bookmark not defined.456.1.5.2 Network Upgrade Funding and Facilities Studies:Error! Bookmark not defined.466.1.5.3 MISO Sub Regional Planning MeetingsError! Bookmark not defined.466.1.5.4 Availability of ARRs ........... .......... ...Error! Bookmark not defined.466.1.5.5 Shared Network Upgrade Cost Allocation Treatment:Error! Bookmark not defined.46

    6.2 Facility Study ...........................................................Error! Bookmark not defined.466.2.1 Study Objectives ......................................................Error! Bookmark not defined.476.2.2 Scope of Upgrades ..................................................Error! Bookmark not defined.486.2.3 Cost of Upgrades .....................................................Error! Bookmark not defined.496.2.4 Contingencies ..........................................................Error! Bookmark not defined.506.2.5

    Facility Study Exhibits for the GIA ............................Error! Bookmark not defined.50

    6.2.6 Interconnection and Operating Guidelines ......... ......Error! Bookmark not defined.516.2.6.1 Interconnection Agreement Appendices PopulatedError! Bookmark not defined.51

    6.2.7 Submittal of IA for Appendix Review ........................Error! Bookmark not defined.52

  • 7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1

    7/14

    Generator Interconnection

    Business Practices ManualBPM-015-r6Effective date: TBD

    OPS-12 PublicPage vi

    6.2.8 Submittal of GIA/FCA for Execution / Filing UnexecutedError! Bookmark not defined.526.2.9 Provisional Generator Interconnection Agreement ...Error! Bookmark not defined.536.2.10 Use of Multi Party Facility Construction Agreement (MPFCA)Error! Bookmark not defined.54

    7. Post GIA Phase ...........................................................................................................8567.1 Providing Modeling Data .........................................................................................9577.2 Suspension .............................................................................................................9577.3 Construction ............................................................Error! Bookmark not defined.587.4 Testing .....................................................................Error! Bookmark not defined.587.5 Registration of Asset with MISO...............................Error! Bookmark not defined.587.6 Inclusion in Network Model ......................................Error! Bookmark not defined.597.7 Commercial Operation .............................................Error! Bookmark not defined.59

    Appendix A .................................................................................Error! Bookmark not defined.60Sample Contour Map .................................................................Error! Bookmark not defined.60Appendix B .................................................................................Error! Bookmark not defined.61Generator Interconnection Ad hoc Information Session Request FormError! Bookmark not defined.61Appendix C .................................................................................Error! Bookmark not defined.64General Study Process Diagrams .............................................Error! Bookmark not defined.64Appendix D ..........................................................................................................................1166Modeling data to be submitted by Interconnection Customer to MISO .......................... 1166Appendix E .................................................................................Error! Bookmark not defined.69Pre-Commercial Generation Test Notification Form ...............Error! Bookmark not defined.69

  • 7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1

    8/14

    Generator Interconnection

    Business Practices ManualBPM-015-r6Effective date: TBD

    OPS-12 PublicPage 7

  • 7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1

    9/14

    Generator Interconnection

    Business Practices ManualBPM-015-r6Effective date: TBD

    OPS-12 PublicPage 8

    7. Post GIA Phase

    The following sections describe various activities in project development after the Generator

    Interconnection Agreement is executed.

    Initial Payment

    The Interconnection Customer is required to pay the initial payment of either 1) 20% of the total

    cost of Network Upgrades, Transmission Owner Interconnection Facilities, Transmission

    Owners System Protection Facilities, Distribution Upgrades and/or Generator Upgrades

    identified in the GIA within 30 days of executing its GIA if the Generator In-service date is within

    5 years of executing the GIA; or 2) 10% if it is beyond 5 years; or 3) the total cost of Network

    Upgrades, Transmission Owner Interconnection Facilities, Transmission Owners System

    Protection Facilities, Distribution Upgrades and/or Generator Upgrades in the form of security.

    Limited Operation

    If any of the Transmission Owners Interconnection Facilities, Network Upgrades, or

    Transmission Owners System Protection Facilities, Distribution Upgrades or Generator

    Upgrades are not reasonably expected to be completed prior to the Commercial Operation Date

    of the Generating Facility, Transmission Provider shall, upon the request and at the expense of

    Interconnection Customer, perform operating studies on a timely basis to determine the extentto which the Generating Facility and the Interconnection Customers Interconnection Facilities

    may operate prior to the completion of the Transmission Owners Interconnection Facilities,

    Network Upgrades, Transmission Owners System Protection Facilities, Distribution Upgrades

    or Generator Upgrades consistent with Applicable Laws and Regulations, Applicable Reliability

    Standards, Good Utility Practice, and the GIA. The maximum permissible output of the

    Generating Facility will be updated on a quarterly basis if the Network Upgrades necessary for

    the interconnection of the Generating Facility pursuant to the GIA are not in service within six (6)

    months following the Commercial Operation Date of the Generating Facility as specified in

    Appendix B of the GIA. These quarterly studies will be performed using the same methodology

    set forth Section 6.2.9 of this BPM for Provisional Generation Interconnection Agreements.

    These quarterly updates will end when all Network Upgrades necessary for the interconnection

    of the Generating Facility pursuant to this GIA are in service.

  • 7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1

    10/14

    Generator Interconnection

    Business Practices ManualBPM-015-r6Effective date: TBD

    OPS-12 PublicPage 9

    7.1 Providing Modeling Data

    Within thirty (30) Calendar Days after the Generation Interconnection Agreement has been

    signed, the Interconnection Customer is required to provide a model for the Generating Facility

    to MISO.

    The Interconnection Customer shall provide power flow modeling data for the generator and

    associated interconnection facilities as applicable by submitting a project into Model on Demand

    (MOD). The Interconnection Customer shall provide a working stability model for the Generating

    Facility that is compatible with MISO standard models (typically PSS/e models). Refer to

    Appendix D for the specific requirements to be provided. These models are intended to be used

    in MISO Planning Studies. The Interconnection Customer will be required to update the

    submitted models throughout the development of the Generating Facility as needed.

    Submittal of modeling data for corresponding Network Upgrades shall be coordinated between

    the Interconnection Customer and the Transmission Owner.

    7.2 Suspension

    After the execution of the Interconnection Agreement, the Interconnection Customer is expected

    to meet the milestones and construction schedule as established in the Interconnection

    Agreement. In certain conditions, Interconnection Customer has the option to suspend the

    construction of the Network Upgrades and Interconnection Facilities based on narrowly defined

    criteria. The following rules and conditions will govern the suspension of a project in the post-IAphase.

    Permitted only for Force Majeure reasons: Any act of God, labor disturbance, act of

    the public enemy, war, insurrection, riot, fire, storm or flood, explosion, breakage or

    accident to machinery or equipment, any order, regulation or restriction imposed by

    governmental, military or lawfully established civilian authorities, or any other cause

    beyond a Partys control. A Force Majeure event does not include an act of

    negligence or intentional wrongdoing by the Party claiming Force Majeure.

    When coming out of suspension with only partial construction resulting in reduced

    project capacity, recovery eligibility is reduced on a pro-rata basis relative to the new

    size of the project

    Will require an up-front payment equivalent to greater of Network Upgrade costs or

    $5 million

    Formatted: Space After: 12 pt

  • 7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1

    11/14

    Generator Interconnection

    Business Practices ManualBPM-015-r6Effective date: TBD

    OPS-12 PublicPage 10

    Suspended IRs may be revisited periodically to ensure Interconnection Customer is

    working toward coming out of suspension

  • 7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1

    12/14

    Generator Interconnection

    Business Practices ManualBPM-015-r6Effective date: TBD

    Page 11OPS-12

    Public

    Appendix D

    Modeling data to be submitted by Interconnection Customer to MISO

    Powerflow Modeling data into Model on Demand (MOD)

    Interconnection Customer to submit project in MOD to model their Generating Facility, as notedahead:

    Submit MOD projects to model generators with a project type Generator in MOD. Set the

    project status as per the following:o For generator with a signed Generation Interconnection Agreement (GIA) that is not in

    service, set the status as Planned.

    o For changes to existing generators as per representation in the MOD base case, submit

    project with a status of In-Service

    Choose an effective date of MOD project as per best available information of the expected

    in-service date.

    Include the following information in the project name as per the naming convention below:

    o MISO generator interconnection project number

    o Interconnecting Transmission Owner (ITO)

    o State where project is interconnecting

    o Fuel Type

    o Example: G000-XEL-MN-Wind.prj

    Include the following power-flow data in the MOD project:o Bus number(s) corresponding to POI approved by ITO

    o For the Generator Step-up transformer, provide:

    Voltage ratings (kV)

    Normal and emergency rating (MVA)

    Impedance

    Load tap changer/phase shifter information

    o As applicable, for Generating Facility with collector systems:

    Pad-mount transformer data (voltage levels, ratings, impedance parameters)

    Collector system equivalent (voltage level, MVA rating, impedance)

    Interconnection radial line parameters (voltage level, MVA rating, impedance

    parameters)

    Additional equipment as needed

    o Net maximum and minimum real power (MW) output (Pmax and Pmin)o Net maximum and minimum reactive (MVArs) output (Qmax and Qmin) ( if a wind

    machine, please note below)

    Formatted: Font: 14 pt, No underlin

    Formatted: Heading 1

    Formatted: Font: 14 pt, Not Bold, N

  • 7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1

    13/14

    Generator Interconnection

    Business Practices ManualBPM-015-r6Effective date: TBD

    Page 12OPS-12

    Public

    o Remote bus number for which the voltage is to be regulated by the generator, as

    applicable

    o External Reactive Compensation, as applicable

    o Power Factor and reactive power limits:

    Type of wind machine WMOD1 WPF Notes

    Not a wind machine 0 Do not populateReactive limits will be asspecified by Qmax and Qmin

    Wind machine with arange of reactive poweroutput with unequal,leading and laggingpower factor limits

    1 Do not populate

    Reactive limits will be as

    specified by Qmax and Qmin.This would be most applicablefor wind machines that have adifferent range for lagging andleading power factor.

    Wind machine with theequal leading andlagging power factorcapability

    2Specify rated powerfactor value

    Reactive limits will change as afunction of active power outputand power factor specified here.This will replace the maximumand minimum reactive limitsspecified under Qmax andQmin.

    Wind machine with afixed leading OR laggingreactive power capability

    3

    Specify rated power

    factor value (specifypositive WPF forlagging power factoroperation and viceversa)

    Reactive power output willchange to a fixed value as a

    function of the active poweroutput and power factor. Thiswill replace the maximum andminimum reactive limitsspecified under Qmax andQmin.

    1For more details, refer to the PSS/e Program Operation Manual for the specifics on generator data records.

    Formatted: Left

    Formatted Table

    Formatted: Left, Indent: Left: 0", Abetween paragraphs of the same style

    Formatted: Left, Indent: Left: 0", Abetween paragraphs of the same style

    Formatted: Left, Indent: Left: 0", Abetween paragraphs of the same style

    Formatted: Left, Indent: Left: 0", Abetween paragraphs of the same style

  • 7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1

    14/14

    Generator Interconnection

    Business Practices ManualBPM-015-r6Effective date: TBD

    Page 13OPS-12

    Public

    Dynamic Modeling

    Interconnection Customer to submit working dynamic model for Generating Facilitycompatible with MISO standard models (typically PSS/E models) that include:

    General parameters for various generator types:

    o Time constants

    o Sub-transient, transient, and synchronous impedances:

    Saturated

    Unsaturated

    o Mechanical parameters:

    Inertia Damping

    For Steam or Hydro Units:

    o Generator Data

    o Exciter Data

    o Governor Data

    o Power System Stabilizer Data (if installed)

    o Min/Max exciter limiter Data (optional)

    o Turbine Load Controller Data (optional)

    For Wind Units:

    o Wind Turbine Generator Type (i.e. 1, 2, 3, or 4)

    o Generator Data

    o Control mode

    o Mechanical (Turbine) Datao Electrical (Exciter/Converter) Data

    o Pitch Control Data (optional)

    o Aerodynamic Data (optional)

    For PV Units:

    o Electrical (Converter) Data

    o Control Data

    Dynamic models for reactive compensation devices used, if applicable

    Maximum and minimum generator terminal voltage limits for normal and emergency

    conditions (including LVRT capabilities)

    Protection information including voltage and frequency protection as applicable

    Single line diagram (including breaker configuration)

    Formatted: ParaText, Line spacing: