PJ Deadline Date Requirement Amount Total C,R,orD through Deadline % Shortfall Current Status + Original Allocation Adjustments + HOME Deadline Compliance Status Report (sorted alphabetically by PJ) Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 Disbursements As of 05/31/2016 ++ CHDO-C C D Abilene TX 9/30/2014 9/30/2014 $11,279,009 $1,732,914 $9,728,655 $273,750 $11,387,183 $1,890,087 $11,239,292 100.00 16.36 100.00 deob complete 12/01/14 $0 $0 $0 $273,750 $0 $11,552,759 $11,552,759 $10,002,405 CHDO-R 9/30/2014 $1,732,914 $1,890,087 16.36 $0 $0 $11,552,759 CHDO-D $1,500,361 $1,890,087 18.90 $0 $0 $10,002,405 CHDO-C C D Adams County Consortium CO 9/30/2014 6/30/2014 $17,238,879 $2,560,016 $14,906,473 $79,191 $17,892,821 $2,774,767 $16,769,872 100.00 16.26 100.00 $0 $0 $0 $79,191 $0 $17,066,774 $17,318,070 $14,985,664 CHDO-R 9/30/2014 $2,560,016 $2,793,209 16.37 $0 $0 $17,066,774 CHDO-D $2,210,155 $2,723,209 18.48 $0 $0 $14,734,368 CHDO-C C D Aguadilla PR 7/31/2014 7/31/2014 $11,249,605 $1,687,441 $9,759,828 $0 $11,309,202 $2,405,847 $10,792,878 100.00 21.39 100.00 $0 $0 $0 $0 $0 $11,249,605 $11,249,605 $9,759,828 CHDO-R 7/31/2014 $1,687,441 $2,405,848 21.39 $0 $0 $11,249,605 CHDO-D $1,463,974 $2,258,995 23.15 $0 $0 $9,759,828 CHDO-C C D Akron OH 4/30/2014 6/30/2014 $41,214,832 $6,133,479 $36,337,410 $13,220 $41,228,387 $7,392,102 $39,799,660 100.00 18.08 100.00 $0 $0 $0 $13,220 $0 $40,889,860 $41,228,052 $36,350,630 CHDO-R 4/30/2014 $6,133,479 $7,179,158 17.56 $0 $0 $40,889,860 CHDO-D $5,401,866 $7,332,102 20.36 $0 $0 $36,012,438 Wednesday, June 01, 2016 Page 1 of 163 C-Commitments, R-CHDO Reservations, D-Disbursements PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date. PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date. + Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%. NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements. Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS) ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters. ++ * ** #

Upload: others

Post on 03-Feb-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Abilene

    TX

    9/30/2014

    9/30/2014

    $11,279,009

    $1,732,914

    $9,728,655

    $273,750 $11,387,183

    $1,890,087

    $11,239,292

    100.00

    16.36

    100.00

    deob complete 12/01/14$0

    $0

    $0$273,750

    $0$11,552,759

    $11,552,759

    $10,002,405

    CHDO-R 9/30/2014 $1,732,914 $1,890,087 16.36 $0$0$11,552,759

    CHDO-D $1,500,361 $1,890,087 18.90 $0$0$10,002,405

    CHDO-C

    C

    D

    Adams County Consortium

    CO

    9/30/2014

    6/30/2014

    $17,238,879

    $2,560,016

    $14,906,473

    $79,191 $17,892,821

    $2,774,767

    $16,769,872

    100.00

    16.26

    100.00

    $0

    $0

    $0$79,191

    $0$17,066,774

    $17,318,070

    $14,985,664

    CHDO-R 9/30/2014 $2,560,016 $2,793,209 16.37 $0$0$17,066,774

    CHDO-D $2,210,155 $2,723,209 18.48 $0$0$14,734,368

    CHDO-C

    C

    D

    Aguadilla

    PR

    7/31/2014

    7/31/2014

    $11,249,605

    $1,687,441

    $9,759,828

    $0 $11,309,202

    $2,405,847

    $10,792,878

    100.00

    21.39

    100.00

    $0

    $0

    $0$0

    $0$11,249,605

    $11,249,605

    $9,759,828

    CHDO-R 7/31/2014 $1,687,441 $2,405,848 21.39 $0$0$11,249,605

    CHDO-D $1,463,974 $2,258,995 23.15 $0$0$9,759,828

    CHDO-C

    C

    D

    Akron

    OH

    4/30/2014

    6/30/2014

    $41,214,832

    $6,133,479

    $36,337,410

    $13,220 $41,228,387

    $7,392,102

    $39,799,660

    100.00

    18.08

    100.00

    $0

    $0

    $0$13,220

    $0$40,889,860

    $41,228,052

    $36,350,630

    CHDO-R 4/30/2014 $6,133,479 $7,179,158 17.56 $0$0$40,889,860

    CHDO-D $5,401,866 $7,332,102 20.36 $0$0$36,012,438

    Wednesday, June 01, 2016 Page 1 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Alabama

    AL

    4/30/2014

    7/31/2014

    $311,525,305

    $41,282,882

    $271,360,516

    $199,023 $311,096,489

    $60,923,500

    $299,431,857

    99.86

    19.70

    100.00

    Requirement met 8/7/2014$428,816

    $0

    $0$199,023

    $5,106,790$309,264,484

    $311,724,328

    $271,559,539

    CHDO-R 4/30/2014 $41,282,882 $56,903,930 18.40 $0$5,106,790$309,264,484

    CHDO-D $35,258,164 $56,906,930 21.15 $0$5,106,790$269,099,695

    CHDO-C

    C

    D

    Alameda County Consortium

    CA

    7/31/2014

    8/31/2014

    $73,298,222

    $11,189,207

    $63,103,675

    $1,996,749 $73,795,060

    $15,826,884

    $69,549,638

    100.00

    21.22

    100.00

    $0

    $0

    $0$1,996,749

    $1$74,594,719

    $75,294,971

    $65,100,424

    CHDO-R 7/31/2014 $11,189,207 $15,176,424 20.35 $0$1$74,594,719

    CHDO-D $9,660,025 $15,455,557 24.00 $0$1$64,400,172

    CHDO-C

    C

    D

    Alaska

    AK

    7/31/2014

    7/31/2014

    $63,346,017

    $9,454,616

    $54,344,899

    $0 $65,624,989

    $16,429,736

    $59,196,508

    100.00

    26.07

    100.00

    $0

    $0

    $0$0

    $0$63,030,774

    $63,346,017

    $54,344,899

    CHDO-R 7/31/2014 $9,454,616 $16,186,399 25.68 $0$0$63,030,774

    CHDO-D $8,104,448 $16,429,736 30.41 $0$0$54,029,656

    CHDO-C

    C

    D

    Albany

    GA

    9/30/2014

    7/31/2014

    $13,649,430

    $1,939,833

    $12,049,831

    $126,566 $13,700,534

    $2,009,692

    $12,050,186

    100.00

    14.59

    100.00

    #

    $0

    $0

    $0$126,566

    $126,566$13,775,996

    $13,775,996

    $12,176,397

    CHDO-R 9/30/2014 $1,939,833 $2,009,692 14.59 # Shortfall notice 10/20/2014$0$126,566$13,775,996

    CHDO-D $1,699,894 $2,009,592 16.50 $0$126,566$12,176,397

    Wednesday, June 01, 2016 Page 2 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Albany

    NY

    7/31/2014

    7/31/2014

    $23,159,002

    $3,410,044

    $19,762,024

    $51,119 $23,204,715

    $3,789,957

    $22,511,837

    100.00

    16.42

    100.00

    $0

    $0

    $0$51,119

    $51,119$23,074,422

    $23,210,121

    $19,813,143

    CHDO-R 7/31/2014 $3,410,044 $3,785,328 16.40 $0$51,119$23,074,422

    CHDO-D $2,900,498 $3,789,957 19.26 $0$51,119$19,677,444

    CHDO-C

    C

    D

    Albuquerque

    NM

    4/30/2014

    6/30/2014

    $45,693,415

    $6,771,884

    $39,443,681

    $0 $45,741,655

    $10,245,571

    $39,654,185

    100.00

    22.69

    100.00

    $0

    $0

    $0$0

    $0$45,145,890

    $45,693,415

    $39,443,681

    CHDO-R 4/30/2014 $6,771,884 $6,999,738 15.50 $0$0$45,145,890

    CHDO-D $5,834,423 $8,355,319 21.48 $0$0$38,896,156

    CHDO-C

    C

    D

    Alexandria

    LA

    6/30/2014

    7/31/2014

    $8,826,424

    $1,062,471

    $7,769,023

    $245,870 $8,995,759

    $2,346,964

    $8,736,568

    100.00

    25.87

    100.00

    $0

    $0

    $0$245,870

    $298,374$9,072,294

    $9,072,294

    $8,014,893

    CHDO-R 6/30/2014 $1,062,471 $2,197,765 24.23 $0$298,374$9,072,294

    CHDO-D $903,860 $2,196,964 27.41 $0$298,374$8,014,893

    CHDO-C

    C

    D

    Alexandria

    VA

    7/31/2014

    7/31/2014

    $14,808,462

    $2,203,229

    $12,695,942

    $0 $14,783,054

    $3,269,376

    $13,716,483

    99.83

    22.26

    100.00

    Requirement met 9/23/2014$25,408

    $0

    $0$0

    $0$14,688,194

    $14,808,462

    $12,695,942

    CHDO-R 7/31/2014 $2,203,229 $3,269,376 22.26 $0$0$14,688,194

    CHDO-D $1,886,351 $3,269,376 26.00 $0$0$12,575,674

    Wednesday, June 01, 2016 Page 3 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Alhambra

    CA

    7/31/2014

    7/31/2014

    $15,158,211

    $2,273,732

    $13,175,010

    $0 $15,314,970

    $4,050,601

    $14,843,509

    100.00

    26.72

    100.00

    $0

    $0

    $0$0

    $0$15,158,211

    $15,158,211

    $13,175,010

    CHDO-R 7/31/2014 $2,273,732 $4,050,601 26.72 $0$0$15,158,211

    CHDO-D $1,976,252 $4,050,601 30.74 $0$0$13,175,010

    CHDO-C

    C

    D

    Allegheny County Consortium

    PA

    4/30/2014

    6/30/2014

    $83,873,238

    $12,463,390

    $73,461,759

    $0 $84,398,131

    $15,690,739

    $79,090,098

    100.00

    18.88

    100.00

    $0

    $0

    $0$0

    $0$83,089,265

    $83,873,238

    $73,461,759

    CHDO-R 4/30/2014 $12,463,390 $15,347,192 18.47 $0$0$83,089,265

    CHDO-D $10,901,668 $14,959,912 20.58 $0$0$72,677,786

    CHDO-C

    C

    D

    Allentown

    PA

    7/31/2014

    7/31/2014

    $17,977,146

    $2,705,346

    $15,301,122

    $114,462 $18,101,408

    $2,815,347

    $17,215,753

    100.00

    15.61

    100.00

    $0

    $0

    $0$114,462

    $1$18,035,644

    $18,091,608

    $15,415,584

    CHDO-R 7/31/2014 $2,705,346 $2,728,956 15.13 $0$1$18,035,644

    CHDO-D $2,303,942 $2,605,412 16.96 $0$1$15,359,620

    CHDO-C

    C

    D

    Altoona

    PA

    7/31/2014

    7/31/2014

    $8,620,457

    $1,293,069

    $7,520,393

    $0 $8,776,972

    $2,395,853

    $8,582,701

    100.00

    27.79

    100.00

    $0

    $0

    $0$0

    $0$8,620,457

    $8,620,457

    $7,520,393

    CHDO-R 7/31/2014 $1,293,069 $2,359,511 27.37 $0$0$8,620,457

    CHDO-D $1,128,059 $2,395,853 31.86 $0$0$7,520,393

    Wednesday, June 01, 2016 Page 4 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Amarillo

    TX

    10/31/2014

    10/31/2014

    $18,512,283

    $2,753,186

    $16,043,620

    $282,791 $18,486,581

    $3,310,983

    $17,893,600

    99.86

    17.80

    100.00

    deob complete - 01/14/15$25,702

    $0

    $0$282,791

    $37,475$18,604,409

    $18,795,074

    $16,326,411

    CHDO-R 10/31/2014 $2,753,186 $3,155,994 16.96 $0$37,475$18,604,409

    CHDO-D $2,382,887 $3,265,497 20.24 $0$37,475$16,135,746

    CHDO-C

    C

    D

    American Samoa

    AS

    8/31/2014

    8/31/2014

    $5,807,811

    $0

    $4,980,642

    $6,562 $5,896,591

    $0

    $5,629,818

    100.00

    0.00

    100.00

    $0

    $0

    $0$6,562

    $0$5,814,373

    $5,814,373

    $4,987,204

    CHDO-R 8/31/2014 $0 $0 0.00 $0$0$5,814,373

    CHDO-D $0 $0 0.00 $0$0$4,987,204

    CHDO-C

    C

    D

    Amherst Consortium

    NY

    5/31/2014

    7/31/2014

    $20,554,850

    $3,049,004

    $17,616,068

    $0 $20,584,599

    $6,299,006

    $19,823,933

    100.00

    30.99

    100.00

    $0

    $0

    $0$0

    $0$20,326,691

    $20,554,850

    $17,616,068

    CHDO-R 5/31/2014 $3,049,004 $5,794,661 28.51 $0$0$20,326,691

    CHDO-D $2,608,186 $5,794,660 33.33 $0$0$17,387,909

    CHDO-C

    C

    D

    Anaheim

    CA

    7/31/2014

    7/31/2014

    $36,826,882

    $5,461,535

    $31,489,007

    $1 $37,289,509

    $7,534,282

    $33,691,077

    100.00

    20.69

    100.00

    $0

    $0

    $0$1

    $1$36,410,238

    $36,826,883

    $31,489,008

    CHDO-R 7/31/2014 $5,461,535 $5,905,185 16.22 $0$1$36,410,238

    CHDO-D $4,660,853 $7,534,282 24.25 $0$1$31,072,363

    Wednesday, June 01, 2016 Page 5 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Anchorage

    AK

    4/30/2014

    6/30/2014

    $19,984,466

    $2,853,831

    $17,340,882

    $180,912 $19,335,663

    $4,715,022

    $19,163,677

    96.75

    23.71

    100.00

    Requirement met 6/5/14$648,803

    $0

    $0$180,912

    $129,300$19,887,537

    $20,165,378

    $17,521,794

    CHDO-R 4/30/2014 $2,853,831 $3,466,784 17.43 $0$129,300$19,887,537

    CHDO-D $2,457,293 $3,441,264 19.96 $0$129,300$17,243,953

    CHDO-C

    C

    D

    Anderson

    IN

    4/30/2014

    6/30/2014

    $8,671,264

    $1,513,190

    $7,709,661

    ($250,000) $8,757,322

    $4,125,434

    $8,539,084

    100.00

    48.99

    100.00

    $0

    $0

    $0($250,000)

    ($250,000)$8,421,264

    $8,421,264

    $7,459,661

    CHDO-R 4/30/2014 $1,513,190 $3,897,975 46.29 $0($250,000)$8,421,264

    CHDO-D $1,368,949 $3,890,200 52.15 $0($250,000)$7,459,661

    CHDO-C

    C

    D

    Anderson County Consortium

    SC

    7/31/2014

    7/31/2014

    $3,400,290

    $415,181

    $1,818,864

    $125,983 $3,683,976

    $590,042

    $3,340,861

    100.00

    16.80

    100.00

    $0

    $0

    $0$125,983

    $111,603$3,511,893

    $3,526,273

    $1,944,847

    CHDO-R 7/31/2014 $415,181 $526,784 15.00 $0$111,603$3,511,893

    CHDO-D $177,967 $590,041 30.56 $0$111,603$1,930,467

    CHDO-C

    C

    D

    Ann Arbor

    MI

    $13,391,540

    $1,990,648

    $13,391,540

    $60 $13,391,540

    $9,453,747

    $13,391,540

    100.00

    71.24

    100.00

    $0

    $0

    $0$60

    $0$13,270,988

    $13,391,600

    $13,391,600

    CHDO-R $1,990,648 $9,453,747 71.24 $0$0$13,270,988

    CHDO-D $1,990,648 $9,453,747 71.24 $0$0$13,270,988

    Wednesday, June 01, 2016 Page 6 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Anne Arundel County

    MD

    7/31/2014

    8/31/2014

    $17,668,069

    $2,616,505

    $15,324,826

    $0 $18,090,625

    $3,389,148

    $17,208,455

    100.00

    19.43

    100.00

    $0

    $0

    $0$0

    $0$17,443,367

    $17,668,069

    $15,324,826

    CHDO-R 7/31/2014 $2,616,505 $3,282,779 18.82 $0$0$17,443,367

    CHDO-D $2,265,019 $3,389,148 22.44 $0$0$15,100,124

    CHDO-C

    C

    D

    Anniston Consortium

    AL

    9/30/2014

    10/31/2014

    $2,103,453

    $315,518

    $750,000

    $0 $2,391,100

    $424,514

    $1,623,889

    100.00

    20.18

    100.00

    $0

    $0

    $0$0

    $0$2,103,453

    $2,103,453

    $750,000

    CHDO-R 9/30/2014 $315,518 $380,707 18.10 $0$0$2,103,453

    CHDO-D $112,500 $281,718 37.56 $0$0$750,000

    CHDO-C

    C

    D

    Apple Valley Consortium

    CA

    6/30/2014

    7/31/2014

    $5,838,616

    $875,943

    $4,028,233

    $14,909 $5,838,616

    $1,429,108

    $5,212,698

    100.00

    24.47

    100.00

    Deobligation complete 12/4/2014$0

    $0

    $0$14,909

    $0$5,839,621

    $5,853,525

    $4,043,142

    CHDO-R 6/30/2014 $875,943 $995,575 17.05 $0$0$5,839,621

    CHDO-D $604,386 $847,346 21.03 $0$0$4,029,238

    CHDO-C

    C

    D

    Arapahoe County Consortium

    CO

    4/30/2014

    6/30/2014

    $11,669,580

    $1,718,770

    $9,818,926

    ($64,871) $11,669,580

    $3,780,624

    $10,659,380

    100.00

    32.99

    100.00

    $0

    $0

    $0($64,871)

    $0$11,458,469

    $11,604,709

    $9,754,055

    CHDO-R 4/30/2014 $1,718,770 $3,829,256 33.42 $0$0$11,458,469

    CHDO-D $1,441,172 $3,780,623 39.35 $0$0$9,607,815

    Wednesday, June 01, 2016 Page 7 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Arecibo

    PR

    7/31/2014

    7/31/2014

    $11,806,955

    $786,963

    $10,016,452

    $1,559,777 $12,000,284

    $911,750

    $11,385,638

    100.00

    6.82

    100.00

    #

    $0

    $0

    $0$1,559,777

    $1,218,047$13,366,732

    $13,366,732

    $11,576,229

    CHDO-R 7/31/2014 $786,963 $882,677 6.60 # Deobligation complete 10/9/2014$0$1,218,047$13,366,732

    CHDO-D $518,388 $911,750 7.88 # $0$1,218,047$11,576,229

    CHDO-C

    C

    D

    Arizona

    AZ

    7/31/2014

    9/30/2014

    $140,272,367

    $20,905,368

    $119,119,669

    $0 $140,789,345

    $23,088,557

    $133,010,473

    100.00

    16.57

    100.00

    $0

    $0

    $0$0

    $0$139,369,121

    $140,272,367

    $119,119,669

    CHDO-R 7/31/2014 $20,905,368 $21,702,409 15.57 $0$0$139,369,121

    CHDO-D $17,732,463 $22,182,734 18.76 $0$0$118,216,423

    CHDO-C

    C

    D

    Arkansas

    AR

    7/31/2014

    7/31/2014

    $243,673,352

    $35,712,526

    $209,695,631

    $607,519 $245,336,468

    $36,965,260

    $228,988,836

    100.00

    15.27

    100.00

    $0

    $0

    $0$607,519

    $596,663$242,061,260

    $244,280,871

    $210,303,150

    CHDO-R 7/31/2014 $35,712,526 $36,847,016 15.22 $0$596,663$242,061,260

    CHDO-D $30,615,868 $35,725,528 17.17 $0$596,663$208,083,539

    CHDO-C

    C

    D

    Arlington

    TX

    7/31/2014

    7/31/2014

    $24,031,534

    $3,545,186

    $20,256,596

    $0 $24,487,672

    $4,646,556

    $23,607,507

    100.00

    19.66

    100.00

    $0

    $0

    $0$0

    $0$23,634,575

    $24,031,534

    $20,256,596

    CHDO-R 7/31/2014 $3,545,186 $4,356,863 18.43 $0$0$23,634,575

    CHDO-D $2,978,946 $4,416,663 22.24 $0$0$19,859,637

    Wednesday, June 01, 2016 Page 8 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Arlington County

    VA

    7/31/2014

    7/31/2014

    $21,777,710

    $3,230,098

    $18,874,967

    $1,000 $22,310,144

    $7,751,653

    $22,309,744

    100.00

    36.00

    100.00

    $0

    $0

    $0$1,000

    $0$21,533,985

    $21,778,710

    $18,875,967

    CHDO-R 7/31/2014 $3,230,098 $7,751,653 36.00 $0$0$21,533,985

    CHDO-D $2,794,686 $7,751,653 41.61 $0$0$18,631,242

    CHDO-C

    C

    D

    Asheville Consortium

    NC

    7/31/2014

    6/30/2014

    $24,831,191

    $3,683,921

    $21,152,051

    $0 $25,170,574

    $10,096,459

    $24,503,117

    100.00

    41.11

    100.00

    $0

    $0

    $0$0

    $0$24,559,471

    $24,831,191

    $21,152,051

    CHDO-R 7/31/2014 $3,683,921 $9,992,459 40.69 $0$0$24,559,471

    CHDO-D $3,132,050 $10,073,328 48.24 $0$0$20,880,331

    CHDO-C

    C

    D

    Athens-Clarke

    GA

    7/31/2014

    7/31/2014

    $15,979,391

    $2,383,787

    $13,684,991

    $31,866 $16,045,615

    $4,784,311

    $14,763,065

    100.00

    30.11

    100.00

    $0

    $0

    $0$31,866

    $0$15,891,913

    $16,011,257

    $13,716,857

    CHDO-R 7/31/2014 $2,383,787 $4,433,627 27.90 $0$0$15,891,913

    CHDO-D $2,039,627 $4,558,218 33.52 $0$0$13,597,513

    CHDO-C

    C

    D

    Atlanta

    GA

    4/30/2014

    6/30/2014

    $71,394,431

    $11,358,952

    $62,319,795

    $7,205,960 $72,131,449

    $13,253,486

    $66,017,798

    100.00

    17.04

    100.00

    $0

    $0

    $0$7,205,960

    $307,952$77,779,363

    $78,600,391

    $69,525,755

    CHDO-R 4/30/2014 $11,358,952 $13,117,945 16.87 $0$307,952$77,779,363

    CHDO-D $9,997,757 $11,558,561 16.82 $0$307,952$68,704,727

    Wednesday, June 01, 2016 Page 9 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Atlantic City

    NJ

    6/30/2014

    6/30/2014

    $10,253,154

    $1,560,928

    $8,960,180

    $153,030 $10,294,261

    $2,917,078

    $9,703,080

    100.00

    28.03

    100.00

    $0

    $0

    $0$153,030

    $0$10,406,184

    $10,406,184

    $9,113,210

    CHDO-R 6/30/2014 $1,560,928 $2,956,078 28.41 $0$0$10,406,184

    CHDO-D $1,366,982 $2,876,078 31.56 $0$0$9,113,210

    CHDO-C

    C

    D

    Atlantic County Consortium

    NJ

    9/30/2014

    9/30/2014

    $10,552,309

    $1,486,884

    $8,679,307

    $87,949 $10,734,684

    $1,548,736

    $10,453,358

    100.00

    14.75

    100.00

    #

    $0

    $0

    $0$87,949

    $87,949$10,498,886

    $10,640,258

    $8,767,256

    CHDO-R 9/30/2014 $1,486,884 $1,486,884 14.16 # Deobligation icomplete 2/27/2015$0$87,949$10,498,886

    CHDO-D $1,205,934 $1,436,297 16.65 $0$87,949$8,625,884

    CHDO-C

    C

    D

    Auburn Consortium

    ME

    9/30/2014

    7/31/2014

    $6,292,164

    $949,817

    $4,751,943

    $39,947 $6,292,164

    $1,506,007

    $6,040,090

    100.00

    23.78

    100.00

    Deobligation icomplete 3/31/2015$0

    $0

    $0$39,947

    $0$6,332,111

    $6,332,111

    $4,791,890

    CHDO-R 9/30/2014 $949,817 $1,448,142 22.87 $0$0$6,332,111

    CHDO-D $718,784 $1,506,007 31.43 $0$0$4,791,890

    CHDO-C

    C

    D

    Augusta

    GA

    4/30/2014

    6/30/2014

    $23,713,907

    $3,536,436

    $20,357,427

    $186,402 $23,848,496

    $5,589,290

    $21,920,996

    100.00

    23.64

    100.00

    $0

    $0

    $0$186,402

    $10,751$23,647,914

    $23,900,309

    $20,543,829

    CHDO-R 4/30/2014 $3,536,436 $5,316,058 22.48 $0$10,751$23,647,914

    CHDO-D $3,032,964 $5,313,132 26.18 $0$10,751$20,291,434

    Wednesday, June 01, 2016 Page 10 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Aurora

    CO

    4/30/2014

    6/30/2014

    $21,032,750

    $3,109,012

    $17,732,407

    $0 $21,068,398

    $4,497,202

    $20,254,805

    100.00

    21.70

    100.00

    $0

    $0

    $0$0

    $0$20,726,749

    $21,032,750

    $17,732,407

    CHDO-R 4/30/2014 $3,109,012 $3,957,202 19.09 $0$0$20,726,749

    CHDO-D $2,613,961 $3,769,609 21.63 $0$0$17,426,406

    CHDO-C

    C

    D

    Aurora

    IL

    4/30/2014 $1,558,528

    $233,779

    $0

    $0 $1,608,438

    $1,403,158

    $2,554,685

    100.00

    90.03

    0.00 **

    $0

    $0

    $0$0

    $0$1,558,528

    $1,558,528

    $0

    CHDO-R 4/30/2014 $233,779 $1,335,780 85.71 $0$0$1,558,528

    CHDO-D $0 $1,403,158 0.00 $0$0$0

    CHDO-C

    C

    D

    Austin

    TX

    10/31/2014

    10/31/2014

    $74,574,636

    $11,019,714

    $63,596,503

    $0 $77,470,432

    $14,140,220

    $71,783,340

    100.00

    19.25

    100.00

    $0

    $0

    $0$0

    $0$73,464,763

    $74,574,636

    $63,596,503

    CHDO-R 10/31/2014 $11,019,714 $14,140,220 19.25 $0$0$73,464,763

    CHDO-D $9,372,995 $14,140,220 22.63 $0$0$62,486,630

    CHDO-C

    C

    D

    Babylon

    NY

    4/30/2014

    7/31/2014

    $13,473,023

    $2,003,462

    $11,729,340

    $0 $13,514,054

    $3,292,465

    $12,320,469

    100.00

    24.65

    100.00

    $0

    $0

    $0$0

    $0$13,356,413

    $13,473,023

    $11,729,340

    CHDO-R 4/30/2014 $2,003,462 $2,814,849 21.07 $0$0$13,356,413

    CHDO-D $1,741,910 $2,304,878 19.85 $0$0$11,612,730

    Wednesday, June 01, 2016 Page 11 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Bakersfield

    CA

    6/30/2014

    7/31/2014

    $27,725,341

    $4,122,047

    $23,505,737

    $642 $28,453,325

    $4,560,406

    $24,941,980

    100.00

    16.60

    100.00

    $0

    $0

    $0$642

    $0$27,480,313

    $27,725,983

    $23,506,379

    CHDO-R 6/30/2014 $4,122,047 $4,260,406 15.50 $0$0$27,480,313

    CHDO-D $3,489,106 $4,260,406 18.32 $0$0$23,260,709

    CHDO-C

    C

    D

    Baldwin Park

    CA

    6/30/2014

    7/31/2014

    $7,101,482

    $859,435

    $5,821,165

    $1,344,035 $7,405,131

    $910,504

    $5,996,224

    100.00

    10.78

    100.00

    #

    Deobligation complete

    $0

    $0

    $0$1,344,035

    $407,392$8,445,517

    $8,445,517

    $7,165,200

    CHDO-R 6/30/2014 $859,435 $1,095,640 12.97 # $0$407,392$8,445,517

    CHDO-D $667,388 $910,504 12.71 # $0$407,392$7,165,200

    CHDO-C

    C

    D

    Baltimore

    MD

    7/31/2014

    7/31/2014

    $152,846,337

    $23,032,047

    $136,098,444

    $1,937,607 $154,500,944

    $29,361,726

    $148,577,997

    100.00

    19.12

    100.00

    $0

    $0

    $0$1,937,607

    $1$153,546,985

    $154,783,944

    $138,036,051

    CHDO-R 7/31/2014 $23,032,047 $29,407,312 19.15 $0$1$153,546,985

    CHDO-D $20,519,863 $29,361,726 21.46 $0$1$136,799,092

    CHDO-C

    C

    D

    Baltimore County

    MD

    7/31/2014

    8/31/2014

    $47,561,203

    $6,777,014

    $40,956,063

    $356,491 $48,527,005

    $7,134,919

    $46,251,859

    100.00

    15.11

    100.00

    $0

    $0

    $0$356,491

    $304,080$47,207,295

    $47,917,694

    $41,312,554

    CHDO-R 7/31/2014 $6,777,014 $7,018,062 14.87 # $0$304,080$47,207,295

    CHDO-D $5,786,243 $6,665,224 16.42 $0$304,080$40,602,155

    Wednesday, June 01, 2016 Page 12 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Barnstable County Consortium

    MA

    8/31/2014

    7/31/2014

    $13,248,903

    $1,963,281

    $11,455,271

    $0 $13,333,870

    $3,535,909

    $12,079,511

    100.00

    27.02

    100.00

    $0

    $0

    $0$0

    $0$13,088,543

    $13,248,903

    $11,455,271

    CHDO-R 8/31/2014 $1,963,281 $3,539,298 27.04 $0$0$13,088,543

    CHDO-D $1,694,237 $3,535,909 31.31 $0$0$11,294,911

    CHDO-C

    C

    D

    Baton Rouge

    LA

    10/31/2014

    10/31/2014

    $42,161,576

    $5,745,000

    $36,501,504

    $2,346,708 $42,811,819

    $6,735,251

    $38,094,341

    100.00

    15.30

    100.00

    $0

    $0

    $0$2,346,708

    $859,535$44,030,231

    $44,508,284

    $38,848,212

    CHDO-R 10/31/2014 $5,745,000 $6,186,486 14.05 # $0$859,535$44,030,231

    CHDO-D $4,895,989 $5,259,551 13.71 # $0$859,535$38,370,159

    CHDO-C

    C

    D

    Battle Creek

    MI

    6/30/2014

    7/31/2014

    $7,405,746

    $1,110,862

    $6,493,686

    $0 $7,536,205

    $3,219,671

    $7,429,324

    100.00

    43.48

    100.00

    $0

    $0

    $0$0

    $0$7,405,746

    $7,405,746

    $6,493,686

    CHDO-R 6/30/2014 $1,110,862 $3,253,304 43.93 $0$0$7,405,746

    CHDO-D $974,053 $3,219,671 49.58 $0$0$6,493,686

    CHDO-C

    C

    D

    Bay City

    MI

    6/30/2014

    7/31/2014

    $5,118,229

    $767,735

    $4,433,161

    $1 $5,137,408

    $1,920,862

    $5,126,184

    100.00

    37.53

    100.00

    $0

    $0

    $0$1

    $0$5,118,230

    $5,118,230

    $4,433,162

    CHDO-R 6/30/2014 $767,735 $1,728,615 33.77 $0$0$5,118,230

    CHDO-D $664,974 $1,841,510 41.54 $0$0$4,433,162

    Wednesday, June 01, 2016 Page 13 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Bayamon

    PR

    7/31/2014

    7/31/2014

    $29,564,141

    $3,876,569

    $25,474,923

    $761,306 $29,748,818

    $4,390,444

    $27,580,140

    100.00

    14.50

    100.00

    #

    $0

    $0

    $0$761,306

    $665,306$30,279,167

    $30,325,447

    $26,236,229

    CHDO-R 7/31/2014 $3,876,569 $3,876,569 12.80 # $0$665,306$30,279,167

    CHDO-D $3,263,186 $4,083,123 15.59 $0$665,306$26,189,949

    CHDO-C

    C

    D

    Beaufort County Consortium

    SC

    7/31/2014

    6/30/2014

    $4,799,119

    $715,484

    $2,913,009

    $0 $4,900,547

    $858,401

    $3,762,158

    100.00

    18.00

    100.00

    $0

    $0

    $0$0

    $0$4,769,895

    $4,799,119

    $2,913,009

    CHDO-R 7/31/2014 $715,484 $803,905 16.85 $0$0$4,769,895

    CHDO-D $432,568 $803,905 27.88 $0$0$2,883,785

    CHDO-C

    C

    D

    Beaumont

    TX

    7/31/2014

    7/31/2014

    $16,139,920

    $2,185,311

    $14,172,150

    $0 $16,377,797

    $8,644,134

    $15,786,440

    100.00

    53.56

    100.00

    $0

    $0

    $0$0

    $235,677$16,139,920

    $16,139,920

    $14,172,150

    CHDO-R 7/31/2014 $2,185,311 $8,351,269 51.74 $0$235,677$16,139,920

    CHDO-D $1,890,146 $8,644,134 60.99 $0$235,677$14,172,150

    CHDO-C

    C

    D

    Beaver County

    PA

    9/30/2014

    9/30/2014

    $19,669,369

    $2,928,258

    $17,611,397

    $0 $20,005,406

    $3,650,613

    $19,425,060

    100.00

    18.70

    100.00

    $0

    $0

    $0$0

    $0$19,521,719

    $19,669,369

    $17,611,397

    CHDO-R 9/30/2014 $2,928,258 $3,579,613 18.34 $0$0$19,521,719

    CHDO-D $2,619,562 $3,613,057 20.69 $0$0$17,463,747

    Wednesday, June 01, 2016 Page 14 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Bellflower

    CA

    6/30/2014

    7/31/2014

    $9,416,418

    $1,412,463

    $7,960,302

    $0 $9,504,094

    $1,915,325

    $8,998,685

    100.00

    20.34

    100.00

    $0

    $0

    $0$0

    $0$9,416,418

    $9,416,418

    $7,960,302

    CHDO-R 6/30/2014 $1,412,463 $1,785,727 18.96 $0$0$9,416,418

    CHDO-D $1,194,045 $1,459,688 18.34 $0$0$7,960,302

    CHDO-C

    C

    D

    Bellingham

    WA

    4/30/2014

    6/30/2014

    $9,884,001

    $1,482,600

    $8,084,708

    $2 $10,110,479

    $2,407,696

    $9,475,288

    100.00

    24.36

    100.00

    $0

    $0

    $0$2

    $0$9,884,003

    $9,884,003

    $8,084,710

    CHDO-R 4/30/2014 $1,482,600 $1,994,681 20.18 $0$0$9,884,003

    CHDO-D $1,212,707 $2,120,746 26.23 $0$0$8,084,710

    CHDO-C

    C

    D

    Bergen County

    NJ

    8/31/2014

    7/31/2014

    $61,905,109

    $9,187,053

    $53,302,961

    $175 $62,459,767

    $17,366,561

    $60,230,050

    100.00

    28.35

    100.00

    $0

    $0

    $0$175

    $0$61,247,022

    $61,905,284

    $53,303,136

    CHDO-R 8/31/2014 $9,187,053 $16,499,965 26.94 $0$0$61,247,022

    CHDO-D $7,896,731 $17,236,037 32.74 $0$0$52,644,874

    CHDO-C

    C

    D

    Berkeley

    CA

    7/31/2014

    9/30/2014

    $23,756,645

    $3,564,676

    $20,597,621

    $131,646 $23,943,223

    $11,447,282

    $21,573,165

    100.00

    48.17

    100.00

    $0

    $0

    $0$131,646

    $0$23,764,506

    $23,888,291

    $20,729,267

    CHDO-R 7/31/2014 $3,564,676 $10,418,010 43.84 $0$0$23,764,506

    CHDO-D $3,090,822 $9,369,597 45.47 $0$0$20,605,482

    Wednesday, June 01, 2016 Page 15 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Berks County

    PA

    4/30/2014

    7/31/2014

    $12,872,063

    $1,916,163

    $11,024,757

    $49,900 $13,340,265

    $4,931,586

    $12,897,713

    100.00

    38.61

    100.00

    $0

    $0

    $0$49,900

    $0$12,774,423

    $12,921,963

    $11,074,657

    CHDO-R 4/30/2014 $1,916,163 $4,859,365 38.04 $0$0$12,774,423

    CHDO-D $1,639,068 $4,931,586 45.13 $0$0$10,927,117

    CHDO-C

    C

    D

    Bethlehem

    PA

    4/30/2014

    6/30/2014

    $9,724,382

    $1,261,062

    $8,297,459

    $364,806 $9,831,662

    $2,190,385

    $9,407,345

    100.00

    21.71

    100.00

    $0

    $0

    $0$364,806

    $252,316$10,089,188

    $10,089,188

    $8,662,265

    CHDO-R 4/30/2014 $1,261,062 $2,330,385 23.10 $0$252,316$10,089,188

    CHDO-D $1,047,023 $2,190,385 25.29 $0$252,316$8,662,265

    CHDO-C

    C

    D

    Bexar County

    TX

    9/30/2014

    10/31/2014

    $12,248,000

    $1,821,924

    $10,638,383

    $0 $12,257,132

    $2,477,515

    $11,815,897

    100.00

    20.40

    100.00

    $0

    $0

    $0$0

    $0$12,146,160

    $12,248,000

    $10,638,383

    CHDO-R 9/30/2014 $1,821,924 $2,319,712 19.10 $0$0$12,146,160

    CHDO-D $1,580,481 $2,402,747 22.80 $0$0$10,536,543

    CHDO-C

    C

    D

    Billings

    MT

    7/31/2014

    7/31/2014

    $8,913,069

    $1,210,200

    $7,586,231

    $149,130 $9,022,660

    $1,584,641

    $8,955,737

    100.00

    17.49

    100.00

    $0

    $0

    $0$149,130

    $149,130$9,062,199

    $9,062,199

    $7,735,361

    CHDO-R 7/31/2014 $1,210,200 $1,686,077 18.61 $0$149,130$9,062,199

    CHDO-D $1,011,174 $1,584,641 20.49 $0$149,130$7,735,361

    Wednesday, June 01, 2016 Page 16 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Binghamton

    NY

    9/30/2014

    10/31/2014

    $13,222,105

    $1,997,457

    $11,417,425

    $94,276 $13,296,210

    $2,131,865

    $12,940,172

    100.00

    16.01

    100.00

    $0

    $0

    $0$94,276

    $0$13,316,381

    $13,316,381

    $11,511,701

    CHDO-R 9/30/2014 $1,997,457 $2,062,910 15.49 $0$0$13,316,381

    CHDO-D $1,726,755 $2,116,002 18.38 $0$0$11,511,701

    CHDO-C

    C

    D

    Birmingham

    AL

    7/31/2014

    7/31/2014

    $46,187,872

    $6,210,575

    $40,747,297

    $0 $46,305,385

    $10,865,308

    $44,513,033

    100.00

    23.74

    100.00

    $0

    $0

    $0$0

    $655,155$45,771,531

    $46,187,872

    $40,747,297

    CHDO-R 7/31/2014 $6,210,575 $9,877,963 21.58 $0$655,155$45,771,531

    CHDO-D $5,394,489 $9,982,715 24.75 $0$655,155$40,330,956

    CHDO-C

    C

    D

    Blacksburg Consortium

    VA

    8/31/2014

    6/30/2014

    $5,096,466

    $764,470

    $2,662,205

    $0 $5,277,696

    $2,525,038

    $4,241,969

    100.00

    49.54

    100.00

    $0

    $0

    $0$0

    $0$5,096,466

    $5,096,466

    $2,662,205

    CHDO-R 8/31/2014 $764,470 $2,124,038 41.68 $0$0$5,096,466

    CHDO-D $399,331 $2,437,803 91.57 $0$0$2,662,205

    CHDO-C

    C

    D

    Bloomington

    IN

    6/30/2014

    6/30/2014

    $13,089,968

    $1,955,371

    $11,337,938

    $0 $13,279,787

    $2,657,114

    $12,921,814

    100.00

    20.38

    100.00

    $0

    $0

    $0$0

    $0$13,035,804

    $13,089,968

    $11,337,938

    CHDO-R 6/30/2014 $1,955,371 $2,657,114 20.38 $0$0$13,035,804

    CHDO-D $1,692,566 $2,656,971 23.55 $0$0$11,283,774

    Wednesday, June 01, 2016 Page 17 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Boise

    ID

    9/30/2014

    9/30/2014

    $14,518,241

    $2,148,013

    $12,342,895

    $0 $14,568,861

    $2,797,804

    $14,031,479

    100.00

    19.54

    100.00

    $0

    $0

    $0$0

    $0$14,320,088

    $14,518,241

    $12,342,895

    CHDO-R 9/30/2014 $2,148,013 $2,282,070 15.94 $0$0$14,320,088

    CHDO-D $1,821,711 $2,523,374 20.78 $0$0$12,144,742

    CHDO-C

    C

    D

    Boston

    MA

    8/31/2014

    8/31/2014

    $150,832,012

    $22,436,560

    $130,693,233

    $0 $155,278,742

    $38,005,670

    $149,845,762

    100.00

    25.41

    100.00

    $0

    $0

    $0$0

    $0$149,577,068

    $150,832,012

    $130,693,233

    CHDO-R 8/31/2014 $22,436,560 $39,479,985 26.39 $0$0$149,577,068

    CHDO-D $19,415,743 $37,796,730 29.20 $0$0$129,438,289

    CHDO-C

    C

    D

    Boulder Consortium

    CO

    4/30/2014

    6/30/2014

    $16,660,906

    $2,485,756

    $13,221,280

    $1 $17,072,479

    $2,969,926

    $16,261,340

    100.00

    17.92

    100.00

    $0

    $0

    $0$1

    $1$16,571,713

    $16,660,907

    $13,221,281

    CHDO-R 4/30/2014 $2,485,756 $2,933,126 17.70 $0$1$16,571,713

    CHDO-D $1,969,812 $2,918,126 22.22 $0$1$13,132,087

    CHDO-C

    C

    D

    Brazoria County

    TX

    9/30/2014

    10/31/2014

    $8,841,347

    $84,934

    $7,077,423

    $1,435,250 $9,137,455

    $143,165

    $8,977,348

    100.00

    1.41

    100.00

    #

    $0

    $0

    $0$1,435,250

    $1,434,528$10,129,749

    $10,276,597

    $8,512,673

    CHDO-R 9/30/2014 $84,934 $143,165 1.41 # Deob complete - 01/09/15$0$1,434,528$10,129,749

    CHDO-D ($179,654) $143,165 1.71 # $0$1,434,528$8,365,825

    Wednesday, June 01, 2016 Page 18 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Brevard County Consortium

    FL

    9/30/2014

    10/31/2014

    $28,515,411

    $4,122,683

    $24,636,583

    $371,137 $28,545,010

    $4,506,945

    $27,053,070

    100.00

    15.80

    100.00

    $0

    $0

    $0$371,137

    $156,000$28,524,556

    $28,886,548

    $25,007,720

    CHDO-R 9/30/2014 $4,122,683 $4,288,662 15.03 $0$156,000$28,524,556

    CHDO-D $3,540,859 $4,377,913 17.76 $0$156,000$24,645,728

    CHDO-C

    C

    D

    Bridgeport

    CT

    7/31/2014

    7/31/2014

    $31,073,395

    $4,781,529

    $27,323,461

    $960,276 $30,757,968

    $6,671,006

    $28,973,070

    98.98

    20.93

    100.00

    Requirement met$315,427

    $0

    $0$960,276

    $0$31,876,857

    $32,033,671

    $28,283,737

    CHDO-R 7/31/2014 $4,781,529 $6,185,889 19.41 $0$0$31,876,857

    CHDO-D $4,219,038 $6,441,890 22.90 $0$0$28,126,923

    CHDO-C

    C

    D

    Bristol Consortium

    TN

    6/30/2014

    7/31/2014

    $12,285,074

    $1,819,900

    $8,821,462

    $0 $12,694,167

    $2,132,534

    $12,408,881

    100.00

    17.58

    100.00

    $0

    $0

    $0$0

    $0$12,132,668

    $12,285,074

    $8,821,462

    CHDO-R 6/30/2014 $1,819,900 $1,820,921 15.01 $0$0$12,132,668

    CHDO-D $1,300,358 $1,937,226 22.35 $0$0$8,669,056

    CHDO-C

    C

    D

    Brockton

    MA

    8/31/2014

    7/31/2014

    $16,332,083

    $2,383,597

    $14,347,554

    $77,900 $16,445,071

    $6,579,724

    $16,226,980

    100.00

    40.10

    100.00

    $0

    $0

    $0$77,900

    $77,900$16,409,983

    $16,409,983

    $14,425,454

    CHDO-R 8/31/2014 $2,383,597 $6,701,724 40.84 $0$77,900$16,409,983

    CHDO-D $2,085,918 $6,579,724 45.61 $0$77,900$14,425,454

    Wednesday, June 01, 2016 Page 19 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Broward County Consortium

    FL

    9/30/2014

    10/31/2014

    $63,443,848

    $8,956,714

    $52,046,680

    $694,715 $64,705,660

    $11,295,652

    $59,961,209

    100.00

    17.85

    100.00

    $0

    $0

    $0$694,715

    $533,469$63,267,888

    $64,138,563

    $52,741,395

    CHDO-R 9/30/2014 $8,956,714 $11,066,635 17.49 $0$533,469$63,267,888

    CHDO-D $7,247,139 $11,031,794 21.27 $0$533,469$51,870,720

    CHDO-C

    C

    D

    Brownsville

    TX

    8/31/2016

    10/31/2014

    $21,682,799

    $3,608,548

    $18,388,181

    $2,429,080 $22,319,146

    $5,490,637

    $18,414,208

    100.00

    22.82

    100.00

    $0

    $0

    $0$2,429,080

    $0$24,056,987

    $24,111,879

    $20,817,261

    CHDO-R 8/31/2016 $3,608,548 $5,490,637 22.82 $0$0$24,056,987

    CHDO-D $3,114,355 $5,351,446 25.77 $0$0$20,762,369

    CHDO-C

    C

    D

    Bryan

    TX

    9/30/2014

    10/31/2014

    $7,362,829

    $1,104,424

    $6,165,986

    $0 $7,605,357

    $1,149,614

    $7,025,461

    100.00

    15.61

    100.00

    $0

    $0

    $0$0

    $0$7,362,829

    $7,362,829

    $6,165,986

    CHDO-R 9/30/2014 $1,104,424 $1,149,614 15.61 $0$0$7,362,829

    CHDO-D $924,898 $1,149,614 18.64 $0$0$6,165,986

    CHDO-C

    C

    D

    Bucks County Consortium

    PA

    4/30/2014

    6/30/2014

    $24,448,554

    $3,597,173

    $21,164,174

    $32,528 $23,829,359

    $4,497,293

    $23,329,563

    97.47

    18.59

    100.00

    Requirement met 7/16/2014$619,194

    $0

    $0$32,528

    $32,528$24,198,008

    $24,481,082

    $21,196,702

    CHDO-R 4/30/2014 $3,597,173 $5,021,650 20.75 $0$32,528$24,198,008

    CHDO-D $3,104,516 $4,497,293 21.50 $0$32,528$20,913,628

    Wednesday, June 01, 2016 Page 20 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Buffalo

    NY

    1/31/2015

    9/30/2014

    $101,390,678

    $15,487,369

    $89,068,133

    $2,520,416 $101,895,941

    $27,236,534

    $89,846,697

    100.00

    26.38

    100.00

    $0

    $0

    $0$2,520,416

    $0$103,249,124

    $103,911,094

    $91,588,549

    CHDO-R 1/31/2015 $15,487,369 $29,800,296 28.86 $0$0$103,249,124

    CHDO-D $13,638,987 $24,560,349 27.01 $0$0$90,926,579

    CHDO-C

    C

    D

    Burbank

    CA

    6/30/2014

    7/31/2014

    $14,491,194

    $1,966,407

    $12,514,259

    $243,850 $14,757,788

    $9,188,643

    $14,463,428

    100.00

    62.36

    100.00

    $0

    $0

    $0$243,850

    $243,850$14,735,044

    $14,735,044

    $12,758,109

    CHDO-R 6/30/2014 $1,966,407 $8,880,365 60.27 $0$243,850$14,735,044

    CHDO-D $1,669,866 $9,145,789 71.69 $0$243,850$12,758,109

    CHDO-C

    C

    D

    Burlington

    VT

    8/31/2014

    7/31/2014

    $5,271,819

    $945,878

    $3,906,565

    ($182,477) $5,572,759

    $1,538,908

    $5,318,388

    100.00

    30.24

    100.00

    $0

    $0

    $0($182,477)

    ($182,477)$5,089,342

    $5,089,342

    $3,724,088

    CHDO-R 8/31/2014 $945,878 $1,597,322 31.39 $0($182,477)$5,089,342

    CHDO-D $741,090 $1,538,908 41.32 $0($182,477)$3,724,088

    CHDO-C

    C

    D

    Burlington County Consortium

    NJ

    8/31/2014

    7/31/2014

    $17,643,710

    $2,621,048

    $15,007,255

    $9,124 $18,181,172

    $4,999,808

    $17,023,445

    100.00

    28.61

    100.00

    $0

    $0

    $0$9,124

    $0$17,473,651

    $17,652,834

    $15,016,379

    CHDO-R 8/31/2014 $2,621,048 $4,820,764 27.59 $0$0$17,473,651

    CHDO-D $2,225,579 $4,979,176 33.56 $0$0$14,837,196

    Wednesday, June 01, 2016 Page 21 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Butler County Consortium

    OH

    7/31/2014

    6/30/2014

    $10,985,689

    $1,617,247

    $8,786,309

    $0 $11,292,396

    $3,485,264

    $10,986,470

    100.00

    32.33

    100.00

    $0

    $0

    $0$0

    $0$10,781,649

    $10,985,689

    $8,786,309

    CHDO-R 7/31/2014 $1,617,247 $3,188,359 29.57 $0$0$10,781,649

    CHDO-D $1,287,340 $3,437,039 40.05 $0$0$8,582,269

    CHDO-C

    C

    D

    Caguas

    PR

    7/31/2014

    7/31/2014

    $18,829,073

    $2,789,388

    $16,276,726

    $41,145 $18,902,832

    $3,098,598

    $17,840,707

    100.00

    16.42

    100.00

    $0

    $0

    $0$41,145

    $41,145$18,870,218

    $18,870,218

    $16,317,871

    CHDO-R 7/31/2014 $2,789,388 $3,061,471 16.22 $0$41,145$18,870,218

    CHDO-D $2,406,536 $3,090,558 18.94 $0$41,145$16,317,871

    CHDO-C

    C

    D

    California

    CA

    7/31/2014

    8/31/2014

    $1,053,849,299

    $156,647,344

    $902,633,787

    ($50,636) $1,056,098,411

    $186,316,597

    $993,992,452

    100.00

    17.85

    100.00

    $0

    $0

    $0($50,636)

    ($50,636)$1,043,978,050

    $1,053,798,663

    $902,583,151

    CHDO-R 7/31/2014 $156,647,344 $184,123,539 17.64 $0($50,636)$1,043,978,050

    CHDO-D $133,965,017 $179,611,099 20.12 $0($50,636)$892,762,538

    CHDO-C

    C

    D

    Cambridge

    MA

    9/30/2014

    9/30/2014

    $20,193,801

    $3,012,345

    $17,319,075

    $0 $20,915,803

    $11,327,247

    $19,492,093

    100.00

    56.40

    100.00

    $0

    $0

    $0$0

    $0$20,082,297

    $20,193,801

    $17,319,075

    CHDO-R 9/30/2014 $3,012,345 $11,333,997 56.44 $0$0$20,082,297

    CHDO-D $2,581,136 $11,299,960 65.67 $0$0$17,207,571

    Wednesday, June 01, 2016 Page 22 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Camden

    NJ

    8/31/2014

    7/31/2014

    $25,944,721

    $3,896,852

    $22,933,226

    $34,290 $26,258,072

    $6,955,038

    $23,938,977

    100.00

    26.77

    100.00

    $0

    $0

    $0$34,290

    $0$25,979,011

    $25,979,011

    $22,967,516

    CHDO-R 8/31/2014 $3,896,852 $7,245,056 27.89 $0$0$25,979,011

    CHDO-D $3,445,127 $6,079,385 26.47 $0$0$22,967,516

    CHDO-C

    C

    D

    Camden County Consortium

    NJ

    7/31/2014

    7/31/2014

    $24,237,337

    $3,588,385

    $20,920,844

    $0 $24,353,589

    $7,492,403

    $23,341,020

    100.00

    31.32

    100.00

    $0

    $0

    $0$0

    $0$23,922,565

    $24,237,337

    $20,920,844

    CHDO-R 7/31/2014 $3,588,385 $7,848,257 32.81 $0$0$23,922,565

    CHDO-D $3,090,911 $7,492,403 36.36 $0$0$20,606,072

    CHDO-C

    C

    D

    Canton

    OH

    4/30/2014

    6/30/2014

    $15,793,741

    $2,653,821

    $13,863,801

    $231,731 $16,124,962

    $5,062,182

    $15,338,788

    100.00

    31.59

    100.00

    $0

    $0

    $0$231,731

    ($250,000)$16,025,472

    $16,025,472

    $14,095,532

    CHDO-R 4/30/2014 $2,653,821 $5,006,612 31.24 $0($250,000)$16,025,472

    CHDO-D $2,364,330 $5,062,182 35.91 $0($250,000)$14,095,532

    CHDO-C

    C

    D

    Carolina

    PR

    7/31/2014

    7/31/2014

    $25,604,269

    $2,624,334

    $21,909,349

    $1,544,175 $25,786,008

    $2,624,334

    $23,210,894

    100.00

    9.68

    100.00

    #

    $0

    $0

    $0$1,544,175

    $1,442,285$27,110,790

    $27,148,444

    $23,453,524

    CHDO-R 7/31/2014 $2,624,334 $2,624,334 9.68 # Deobligation complete 10/9/2014$0$1,442,285$27,110,790

    CHDO-D $2,070,096 $2,624,334 11.21 # $0$1,442,285$23,415,870

    Wednesday, June 01, 2016 Page 23 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Cedar Rapids

    IA

    7/31/2014

    7/31/2014

    $10,295,222

    $1,544,283

    $8,961,371

    $0 $10,497,814

    $4,594,243

    $10,387,314

    100.00

    44.63

    100.00

    $0

    $0

    $0$0

    $0$10,295,222

    $10,295,222

    $8,961,371

    CHDO-R 7/31/2014 $1,544,283 $4,294,243 41.71 $0$0$10,295,222

    CHDO-D $1,344,206 $4,435,697 49.50 $0$0$8,961,371

    CHDO-C

    C

    D

    Charleston

    SC

    6/30/2014

    6/30/2014

    $15,702,047

    $2,357,653

    $13,526,117

    $65,855 $15,662,047

    $2,624,794

    $15,238,789

    99.75

    16.70

    100.00

    Deobligation complete 9/11/2014$40,000

    $0

    $0$65,855

    $0$15,717,685

    $15,767,902

    $13,591,972

    CHDO-R 6/30/2014 $2,357,653 $2,502,780 15.92 $0$0$15,717,685

    CHDO-D $2,031,263 $2,549,216 18.82 $0$0$13,541,755

    CHDO-C

    C

    D

    Charleston Consortium

    WV

    8/31/2014

    7/31/2014

    $18,063,925

    $2,681,339

    $15,372,455

    $0 $18,210,053

    $4,506,362

    $17,501,929

    100.00

    25.21

    100.00

    $0

    $0

    $0$0

    $0$17,875,594

    $18,063,925

    $15,372,455

    CHDO-R 8/31/2014 $2,681,339 $4,339,979 24.28 $0$0$17,875,594

    CHDO-D $2,277,619 $4,222,794 27.81 $0$0$15,184,124

    CHDO-C

    C

    D

    Charleston County

    SC

    7/31/2014

    7/31/2014

    $15,294,699

    $2,264,131

    $12,696,912

    $0 $15,534,800

    $2,539,573

    $13,921,134

    100.00

    16.82

    100.00

    $0

    $0

    $0$0

    $0$15,094,207

    $15,294,699

    $12,696,912

    CHDO-R 7/31/2014 $2,264,131 $2,293,871 15.20 $0$0$15,094,207

    CHDO-D $1,874,463 $2,355,473 18.85 $0$0$12,496,420

    Wednesday, June 01, 2016 Page 24 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Charlotte Consortium

    NC

    7/31/2014

    6/30/2014

    $48,637,880

    $7,192,811

    $41,311,567

    $0 $49,063,401

    $8,302,610

    $44,211,322

    100.00

    17.31

    100.00

    $0

    $0

    $0$0

    $0$47,952,075

    $48,637,880

    $41,311,567

    CHDO-R 7/31/2014 $7,192,811 $8,054,726 16.80 $0$0$47,952,075

    CHDO-D $6,093,864 $7,556,750 18.60 $0$0$40,625,762

    CHDO-C

    C

    D

    Charlottesville Consortium

    VA

    6/30/2014

    7/31/2014

    $16,703,602

    $2,474,926

    $14,215,586

    $0 $16,778,574

    $5,711,498

    $16,536,263

    100.00

    34.62

    100.00

    $0

    $0

    $0$0

    $0$16,499,508

    $16,703,602

    $14,215,586

    CHDO-R 6/30/2014 $2,474,926 $5,310,712 32.19 $0$0$16,499,508

    CHDO-D $2,101,724 $5,711,498 40.76 $0$0$14,011,492

    CHDO-C

    C

    D

    Chattanooga

    TN

    7/31/2014

    6/30/2014

    $24,273,613

    $3,606,997

    $21,290,034

    $7,473 $24,355,831

    $6,634,465

    $23,628,500

    100.00

    27.59

    100.00

    $0

    $0

    $0$7,473

    $0$24,046,644

    $24,281,086

    $21,297,507

    CHDO-R 7/31/2014 $3,606,997 $6,425,229 26.72 $0$0$24,046,644

    CHDO-D $3,159,460 $6,626,650 31.46 $0$0$21,063,065

    CHDO-C

    C

    D

    Chesapeake

    VA

    7/31/2014

    6/30/2014

    $12,182,960

    $1,851,126

    $10,477,977

    $283,020 $12,182,960

    $2,112,635

    $11,768,819

    100.00

    17.12

    100.00

    Deobligation complete 10/1/2014$0

    $0

    $0$283,020

    $0$12,340,839

    $12,465,980

    $10,760,997

    CHDO-R 7/31/2014 $1,851,126 $2,061,051 16.70 $0$0$12,340,839

    CHDO-D $1,595,378 $2,037,972 19.16 $0$0$10,635,856

    Wednesday, June 01, 2016 Page 25 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Chester

    PA

    7/31/2014

    7/31/2014

    $7,255,515

    $1,088,327

    $6,079,304

    $0 $7,337,310

    $1,443,914

    $6,844,150

    100.00

    19.90

    100.00

    $0

    $0

    $0$0

    $0$7,255,515

    $7,255,515

    $6,079,304

    CHDO-R 7/31/2014 $1,088,327 $1,367,920 18.85 $0$0$7,255,515

    CHDO-D $911,896 $1,426,700 23.47 $0$0$6,079,304

    CHDO-C

    C

    D

    Chester County

    PA

    4/30/2014

    6/30/2014

    $21,284,271

    $3,158,449

    $18,326,555

    $0 $21,580,656

    $3,785,126

    $21,580,363

    100.00

    17.98

    100.00

    $0

    $0

    $0$0

    $0$21,056,324

    $21,284,271

    $18,326,555

    CHDO-R 4/30/2014 $3,158,449 $3,280,250 15.58 $0$0$21,056,324

    CHDO-D $2,714,791 $3,735,126 20.64 $0$0$18,098,608

    CHDO-C

    C

    D

    Chesterfield County

    VA

    7/31/2014

    9/30/2014

    $8,315,988

    $1,229,009

    $6,936,508

    $0 $8,460,846

    $1,923,116

    $7,973,908

    100.00

    23.47

    100.00

    $0

    $0

    $0$0

    $0$8,193,396

    $8,315,988

    $6,936,508

    CHDO-R 7/31/2014 $1,229,009 $1,952,450 23.83 $0$0$8,193,396

    CHDO-D $1,022,087 $1,923,116 28.22 $0$0$6,813,916

    CHDO-C

    C

    D

    Chicago

    IL

    4/30/2014

    6/30/2014

    $653,482,616

    $97,275,907

    $575,667,514

    $10 $658,892,755

    $137,015,525

    $619,087,025

    100.00

    21.13

    100.00

    $0

    $0

    $0$10

    $0$648,506,050

    $653,482,626

    $575,667,524

    CHDO-R 4/30/2014 $97,275,907 $135,639,097 20.92 $0$0$648,506,050

    CHDO-D $85,603,642 $135,126,887 23.68 $0$0$570,690,948

    Wednesday, June 01, 2016 Page 26 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Chico

    CA

    7/31/2014

    9/30/2014

    $11,237,666

    $1,546,048

    $9,211,036

    $164,237 $11,377,890

    $2,672,744

    $11,215,673

    100.00

    23.44

    100.00

    $0

    $0

    $0$164,237

    $164,237$11,401,903

    $11,401,903

    $9,375,273

    CHDO-R 7/31/2014 $1,546,048 $2,672,744 23.44 $0$164,237$11,401,903

    CHDO-D $1,242,054 $2,672,744 28.51 $0$164,237$9,375,273

    CHDO-C

    C

    D

    Chula Vista

    CA

    6/30/2014

    7/31/2014

    $17,969,740

    $2,666,937

    $15,504,702

    $1 $18,568,466

    $4,848,312

    $17,700,085

    100.00

    27.27

    100.00

    $0

    $0

    $0$1

    $1$17,779,588

    $17,969,741

    $15,504,703

    CHDO-R 6/30/2014 $2,666,937 $4,848,312 27.27 $0$1$17,779,588

    CHDO-D $2,297,182 $4,848,312 31.66 $0$1$15,314,550

    CHDO-C

    C

    D

    Cincinnati

    OH

    4/30/2014

    6/30/2014

    $87,648,884

    $12,820,939

    $77,506,633

    $1,606,610 $87,657,300

    $14,750,270

    $82,668,480

    100.00

    16.68

    100.00

    $0

    $0

    $0$1,606,610

    $441,899$88,418,924

    $89,255,494

    $79,113,243

    CHDO-R 4/30/2014 $12,820,939 $13,521,314 15.29 $0$441,899$88,418,924

    CHDO-D $11,299,602 $14,529,272 18.56 $0$441,899$78,276,673

    CHDO-C

    C

    D

    Clackamas County

    OR

    8/31/2014

    7/31/2014

    $19,802,989

    $2,930,949

    $16,967,937

    $0 $19,834,915

    $7,006,024

    $18,796,434

    100.00

    35.86

    100.00

    $0

    $0

    $0$0

    $0$19,539,658

    $19,802,989

    $16,967,937

    CHDO-R 8/31/2014 $2,930,949 $7,138,473 36.53 $0$0$19,539,658

    CHDO-D $2,505,691 $6,588,473 39.44 $0$0$16,704,606

    Wednesday, June 01, 2016 Page 27 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfall Current Status

    +Original Allocation

    Adjustments+

    HOME Deadline Compliance Status Report

    (sorted alphabetically by PJ)

    Requirement Years: 2012 Commitments, 2012 CHDO Reservations, and 2009 DisbursementsAs of 05/31/2016

    ++

    CHDO-C

    C

    D

    Clark County

    WA

    8/31/2014

    7/31/2014

    $21,989,663

    $3,253,891

    $20,521,870

    $18,792 $21,831,843

    $5,077,312

    $21,288,979

    99.28

    23.41

    100.00

    Requirment met 9/19/2014$157,820

    $0

    $0$18,792

    $0$21,692,606

    $22,008,455

    $20,540,662

    CHDO-R 8/31/2014 $3,253,891 $4,850,380 22.36 $0$0$21,692,606

    CHDO-D $3,033,722 $4,790,573 23.69 $0$0$20,224,813

    CHDO-C

    C

    D

    Clark County Consortium

    NV

    7/31/2014

    9/30/2014

    $77,266,257

    $11,411,127

    $67,755,833

    $0 $78,765,391

    $18,421,189

    $73,257,261

    100.00

    24.21

    100.00

    $0

    $0

    $0$0

    $0$76,074,180

    $77,266,257

    $67,755,833

    CHDO-R 7/31/2014 $11,411,127 $17,355,567 22.81 $0$0$76,074,180

    CHDO-D $9,984,563 $18,000,150 27.04 $0$0$66,563,756

    CHDO-C

    C

    D

    Clarksville

    TN

    6/30/2014

    6/30/2014

    $7,228,139

    $1,020,471

    $6,021,593

    $75,000 $7,423,276

    $1,232,734

    $7,232,408

    100.00

    16.88

    100.00

    $0

    $0

    $0$75,000

    $75,000$7,303,139

    $7,303,139

    $6,096,593

    CHDO-R 6/30/2014 $1,020,471 $1,179,783 16.15 $0$75,000$7,303,139

    CHDO-D $839,489 $1,232,734 20.22 $0$75,000$6,096,593

    CHDO-C

    C

    D

    Clayton County

    GA

    7/31/2014

    7/31/2014

    $11,877,963

    $1,745,703

    $9,284,248

    $0 $12,089,123

    $1,847,120

    $11,744,967

    100.00

    15.87

    100.00

    $0

    $0

    $0$0

    $0$11,638,020

    $11,877,963

    $9,284,248

    CHDO-R 7/31/2014 $1,745,703 $1,745,703 15.00 $0$0$11,638,020

    CHDO-D $1,356,646 $1,721,264 19.03 $0$0$9,044,305

    Wednesday, June 01, 2016 Page 28 of 163

    C-Commitments, R-CHDO Reservations, D-Disbursements

    PJ did not receive an allocation until after 2012. Therefore, it has no amount subject to the FY 2014 commitment or CHDO reservation deadline date.

    PJ did not receive an allocation until after 2009. Therefore, it has no amount subject to the FY 2014 disbursement deadline date.

    +

    Due to CHDO deobligation or waiver, PJ could have met its cumulative CHDO reservation requirement with a percentage less than 15%.

    NOTE: Any ADDI allocations received through FY2007 are reflected in the Original Allocation and respective Requirements.

    Source: Data entered by HOME Participating Jurisdictions into HUD’s Integrated Disbursement and Information System (IDIS)

    ++Adjustments could include grant reductions, deobligations, recapture of expired funds, or waivers of deadline requirements due to Presidentially-declared disasters.++

    *

    **#

  • PJDeadline

    DateRequirement

    Amount

    Total C,R,orD through Deadline % Shortfal