    Overview

    Alder Substation Gas Insulated Switchgear (GIS) InstallationProject drivers and objectivesPublic outreach processProject & Ongoing ChallengesTriumphs & TribulationsLessons Learned & Continuous Improvements

    Future PGE GIS ProjectsCurtis Substation Reconfigure 115 kV BusBell Substation Station Upgrades

    210/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    3/26

    Alder Substation Project Drivers and Objectives

    Multiple SE Portland distribution voltages4kV system was archaic and physically deterioratingSE Portland 13kV system load exceeds Planning GuidelinesS ecific contin encies would result in lon duration outa es for urban customers

    Installation of a new transformer and feeder capacity at Aldersubstation address:

    4kV conversionMitigation of overloaded feeders

    Redundancy during maintenance & unplanned outages

    310/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    4/26

    Alder Substation Site Januar , 2010

    410/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    5/26

    Alder Substation Preliminar Desi n

    510/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    6/26

    Public Outreach Process

    Highly involved neighborhood associationMultiple meetings with the neighborhood association

    June 2008PGE presents initial design to neighborhood association Land Use Team

    August 2008Response less than enthusiastic

    Neighborhood association proposed moving Alder or moving it undergroundOctober 2008

    PGE presents AIS design

    January 2009

    Neighborhood association support secured

    Project approved in February, 2009 utilizing GIS

    610/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    7/26

  • 8/11/2019 2012Sep TDM Phillips

    8/26

    GIS Pro ect Challen es

    DesignWe dont do this everyday

    Specify & order GIS

    Short design durationProject approval - February, 2009Foundation construction - March, 2010

    Other project firstsons ruc onEquipment layout & small project site

    Caused inefficient installation

    GIS Voltage Transformer

    810/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    9/26

  • 8/11/2019 2012Sep TDM Phillips

    10/26

    GIS On oin Challen es

    TrainingLong maintenance interval

    Aging workforceTravelling operatorsMeter/Relay techniciansWireman Disconnector Closed

    Disconnector Opened

    1010/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    11/26

    GIS Design What can be significantly influenced?

    Indoor/Outdoor Foundation design

    SizeCable trench

    on u groun em e men sFeeder connections

    Location

    Local control cabinetsMounting

    GIS mountedSeparately mounted

    Design & components Breaker & Ground Embedments

    1110/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    12/26

    GIS Foundation & Cable Trench

    1210/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    13/26

    GIS Foundation Embedments

    1310/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    14/26

    GIS Local Control Cabinets LCC

    Considered LCC a breakermechanism cabinetConsidered motor-operateddisconnects a manually operatedswitchRequested two-door design

    Added local I/O unitMinimized cable between GIS andcontrol enclosure

    1410/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    15/26

    GIS Local Control Cabinets LCC

    1510/18/2012

    Front View Rear View

  • 8/11/2019 2012Sep TDM Phillips

    16/26

    Alder Substation GIS Installation Trium hs

    Met project objectivesProvided adequate spacebetween breakers

    Specified 5 ft minimum

    Cable trench pullouts

    Minimized trip hazards

    Local Control CabinetI/O units minimized field alarmwirin .Two door design (front/backaccess)

    Self-performed construction

    1610/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    17/26

    Alder Substation GIS Installation Tribulations

    Construction cost and scheduleexceeded estimatesGIS foundation issuesTransmission line disconnects remainedHi-pot testing difficultiesVoltage transformers

    Non-standard disconnecting means

    Gas filling / gas cart inadequacy

    1710/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    18/26

    Alder Substation - Before

    1810/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    19/26

  • 8/11/2019 2012Sep TDM Phillips

    20/26

    Lessons Learned & Continuous Im rovements

    Remove GIS line disconnector Separate Local Control CabinetsSeparate GIS and controlenclosure cablingnc u e vo age rans ormers or

    each GIS feeder

    Utilize composite bushings

    open at LCCDesign flush breaker

    Project after concrete pour Procure adequate gas cart

    Alder LCCs

    2010/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    21/26

    Curtis Fall, 2012 Ener ization

    Existing Curtis SubstationCompliance Project Transmission Drop

    Rebuild Curtis to a 4 position ringbus

    Expandable to 5 th position2nd future transformer

    Distribution is unchanged

    2110/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    22/26

    Curtis Substation Outdoor Electrical Desi n

    2210/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    23/26

    Curtis Substation Se tember, 2012

    2310/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    24/26

    Bell Substation Fall, 2013 Ener ization

    Customer Reliability Project Existing Bell SubstationRebuild Bell Substation to a 5position ring bus

    Duplicate Curtis layoutStreamlined design to support

    aggressive civil construction

    2410/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    25/26

    Bell Substation Outdoor Electrical Desi n

    2510/18/2012

  • 8/11/2019 2012Sep TDM Phillips

    26/26

    2610/18/2012