2012sep tdm phillips
TRANSCRIPT
-
8/11/2019 2012Sep TDM Phillips
1/26
-
8/11/2019 2012Sep TDM Phillips
2/26
Overview
Alder Substation Gas Insulated Switchgear (GIS) InstallationProject drivers and objectivesPublic outreach processProject & Ongoing ChallengesTriumphs & TribulationsLessons Learned & Continuous Improvements
Future PGE GIS ProjectsCurtis Substation Reconfigure 115 kV BusBell Substation Station Upgrades
210/18/2012
-
8/11/2019 2012Sep TDM Phillips
3/26
Alder Substation Project Drivers and Objectives
Multiple SE Portland distribution voltages4kV system was archaic and physically deterioratingSE Portland 13kV system load exceeds Planning GuidelinesS ecific contin encies would result in lon duration outa es for urban customers
Installation of a new transformer and feeder capacity at Aldersubstation address:
4kV conversionMitigation of overloaded feeders
Redundancy during maintenance & unplanned outages
310/18/2012
-
8/11/2019 2012Sep TDM Phillips
4/26
Alder Substation Site Januar , 2010
410/18/2012
-
8/11/2019 2012Sep TDM Phillips
5/26
Alder Substation Preliminar Desi n
510/18/2012
-
8/11/2019 2012Sep TDM Phillips
6/26
Public Outreach Process
Highly involved neighborhood associationMultiple meetings with the neighborhood association
June 2008PGE presents initial design to neighborhood association Land Use Team
August 2008Response less than enthusiastic
Neighborhood association proposed moving Alder or moving it undergroundOctober 2008
PGE presents AIS design
January 2009
Neighborhood association support secured
Project approved in February, 2009 utilizing GIS
610/18/2012
-
8/11/2019 2012Sep TDM Phillips
7/26
-
8/11/2019 2012Sep TDM Phillips
8/26
GIS Pro ect Challen es
DesignWe dont do this everyday
Specify & order GIS
Short design durationProject approval - February, 2009Foundation construction - March, 2010
Other project firstsons ruc onEquipment layout & small project site
Caused inefficient installation
GIS Voltage Transformer
810/18/2012
-
8/11/2019 2012Sep TDM Phillips
9/26
-
8/11/2019 2012Sep TDM Phillips
10/26
GIS On oin Challen es
TrainingLong maintenance interval
Aging workforceTravelling operatorsMeter/Relay techniciansWireman Disconnector Closed
Disconnector Opened
1010/18/2012
-
8/11/2019 2012Sep TDM Phillips
11/26
GIS Design What can be significantly influenced?
Indoor/Outdoor Foundation design
SizeCable trench
on u groun em e men sFeeder connections
Location
Local control cabinetsMounting
GIS mountedSeparately mounted
Design & components Breaker & Ground Embedments
1110/18/2012
-
8/11/2019 2012Sep TDM Phillips
12/26
GIS Foundation & Cable Trench
1210/18/2012
-
8/11/2019 2012Sep TDM Phillips
13/26
GIS Foundation Embedments
1310/18/2012
-
8/11/2019 2012Sep TDM Phillips
14/26
GIS Local Control Cabinets LCC
Considered LCC a breakermechanism cabinetConsidered motor-operateddisconnects a manually operatedswitchRequested two-door design
Added local I/O unitMinimized cable between GIS andcontrol enclosure
1410/18/2012
-
8/11/2019 2012Sep TDM Phillips
15/26
GIS Local Control Cabinets LCC
1510/18/2012
Front View Rear View
-
8/11/2019 2012Sep TDM Phillips
16/26
Alder Substation GIS Installation Trium hs
Met project objectivesProvided adequate spacebetween breakers
Specified 5 ft minimum
Cable trench pullouts
Minimized trip hazards
Local Control CabinetI/O units minimized field alarmwirin .Two door design (front/backaccess)
Self-performed construction
1610/18/2012
-
8/11/2019 2012Sep TDM Phillips
17/26
Alder Substation GIS Installation Tribulations
Construction cost and scheduleexceeded estimatesGIS foundation issuesTransmission line disconnects remainedHi-pot testing difficultiesVoltage transformers
Non-standard disconnecting means
Gas filling / gas cart inadequacy
1710/18/2012
-
8/11/2019 2012Sep TDM Phillips
18/26
Alder Substation - Before
1810/18/2012
-
8/11/2019 2012Sep TDM Phillips
19/26
-
8/11/2019 2012Sep TDM Phillips
20/26
Lessons Learned & Continuous Im rovements
Remove GIS line disconnector Separate Local Control CabinetsSeparate GIS and controlenclosure cablingnc u e vo age rans ormers or
each GIS feeder
Utilize composite bushings
open at LCCDesign flush breaker
Project after concrete pour Procure adequate gas cart
Alder LCCs
2010/18/2012
-
8/11/2019 2012Sep TDM Phillips
21/26
Curtis Fall, 2012 Ener ization
Existing Curtis SubstationCompliance Project Transmission Drop
Rebuild Curtis to a 4 position ringbus
Expandable to 5 th position2nd future transformer
Distribution is unchanged
2110/18/2012
-
8/11/2019 2012Sep TDM Phillips
22/26
Curtis Substation Outdoor Electrical Desi n
2210/18/2012
-
8/11/2019 2012Sep TDM Phillips
23/26
Curtis Substation Se tember, 2012
2310/18/2012
-
8/11/2019 2012Sep TDM Phillips
24/26
Bell Substation Fall, 2013 Ener ization
Customer Reliability Project Existing Bell SubstationRebuild Bell Substation to a 5position ring bus
Duplicate Curtis layoutStreamlined design to support
aggressive civil construction
2410/18/2012
-
8/11/2019 2012Sep TDM Phillips
25/26
Bell Substation Outdoor Electrical Desi n
2510/18/2012
-
8/11/2019 2012Sep TDM Phillips
26/26
2610/18/2012