2013 Water and Wastewater Master Plan for the Lake-Based Systems Volume III - Water Master Plan Final Report P001-0005 March 31, 2014

Upload: others

Post on 14-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

2013 Water and WastewaterMaster Plan for the Lake-Based Systems

Volume III - Water Master PlanFinal Report

P001-0005

March 31, 2014

Page 2: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel

2013 Water and Wastewater Master Plan for the Lake Based Systems – Volume III

March 31, 2014

Page i

Table of Contents – Volume III – Water Master Plan

page

1 Introduction ................................................................................................................... 1 1.1 Background .................................................................................................................... 1 1.2 Master Plan Objectives ................................................................................................... 1 1.3 Master Plan Documentation Layout ................................................................................ 2 1.4 Master Plan Report Volume III ........................................................................................ 5

2 Water System Policy and Criteria ................................................................................. 6 2.1 Design Criteria................................................................................................................ 6

2.1.1 Water Treatment Plants ..................................................................................... 7 2.1.2 Transmission Mains ........................................................................................... 8 2.1.3 Water Pumping Stations ..................................................................................... 8 2.1.4 Water Storage Facilities ..................................................................................... 9

2.2 Service Levels ................................................................................................................ 9 2.3 Costing Methodology ...................................................................................................... 9

2.3.1 Unit Rates ........................................................................................................ 10 2.3.2 Operation and Maintenance Costs ................................................................... 11 2.3.3 Final Project Costs ........................................................................................... 11

3 Existing Water Transmission System ........................................................................ 12 3.1 Existing Infrastructure ................................................................................................... 12

3.1.1 Water Treatment Plants ................................................................................... 14 3.1.1.1 Lakeview Water Treatment Plant .................................................... 14 3.1.1.2 Lorne Park Water Treatment Plant .................................................. 14

3.1.2 Transmission Mains ......................................................................................... 15 3.1.2.1 West Trunk System ........................................................................ 15 3.1.2.2 Central Trunk System ..................................................................... 16 3.1.2.3 East Trunk System ......................................................................... 17

3.1.3 Water Pumping Stations and Reservoirs .......................................................... 17 3.2 Hydraulic Water Model ................................................................................................. 19 3.3 Water Servicing Flow Schematics ................................................................................. 20

4 Assessment of the Existing and Future Water Infrastructure .................................. 21 4.1 Opportunities and Constraints ....................................................................................... 21

4.1.1 Water Treatment Plants ................................................................................... 21 4.1.2 Transmission Mains ......................................................................................... 21 4.1.3 Pumping Stations and Storage Facilities .......................................................... 21 4.1.4 Growth Opportunities ....................................................................................... 22

4.2 Water Demand Requirements ....................................................................................... 22 4.3 Hydraulic Analysis ........................................................................................................ 22

4.3.1 Water Treatment Plants ................................................................................... 22 4.3.2 Transmission Mains ......................................................................................... 24 4.3.3 Water Pumping Stations ................................................................................... 24

Page 3: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel

2013 Water and Wastewater Master Plan for the Lake Based Systems – Volume III

March 31, 2014

Page ii

4.3.4 Water Storage .................................................................................................. 26 4.3.5 Intensification ................................................................................................... 26

5 Evaluation of Concepts and Strategies ..................................................................... 28 5.1 Objectives .................................................................................................................... 28 5.2 Description of the Evaluation Process ........................................................................... 28 5.3 Evaluation Criteria ........................................................................................................ 30 5.4 Servicing Concepts ....................................................................................................... 31 5.5 Servicing Strategies ...................................................................................................... 32 5.6 Alignments and Sites .................................................................................................... 34

6 Preferred Water Servicing Strategy............................................................................ 42 6.1 Preferred Servicing Strategy ......................................................................................... 42 6.2 Capital Program for the Preferred Water Servicing Strategy .......................................... 44

7 York Region Water Servicing Strategy ...................................................................... 54 7.1 York-Peel water servicing agreement ............................................................................ 54 7.2 Impact on Water Infrastructure ...................................................................................... 55

7.2.1 Water Treatment Plants ................................................................................... 55 7.2.2 Pumping Stations ............................................................................................. 55 7.2.3 Transmission Mains ......................................................................................... 55

8 Intensification and Post-2031 Growth ........................................................................ 56 8.1 2031 Intensification ....................................................................................................... 56

8.1.1 Mississauga City Centre ................................................................................... 56 8.1.2 Hurontario Corridor .......................................................................................... 56 8.1.3 Brampton Queen Street Corridor ...................................................................... 56 8.1.4 2031 Intensification Servicing ........................................................................... 57

8.2 Post-2031 Vision .......................................................................................................... 57 8.2.1 Post-2031 Intensification .................................................................................. 57 8.2.2 Post-2031 Greenfield ....................................................................................... 58

Page 4: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel

2013 Water and Wastewater Master Plan for the Lake Based Systems – Volume III

March 31, 2014

Page iii

List of Figures

Figure 3.1 Master Plan Document Layout .............................................................................................. 3 Figure 3.2 Existing Region of Peel Lake-Based Water Transmission System ....................................... 13 Figure 3.3 Projected Demands at the Lakeview Water Treatment Plant ............................................... 23 Figure 3.4 Projected Demands at the Lorne Park Water Treatment Plant ............................................. 23 Figure 3.5 Evaluation of 2031 storage deficiencies for planning Scenario B ......................................... 27 Figure 3.6 Process of identifying, evaluating and selecting a preferred servicing strategy ..................... 29 Figure 3.7 Alternative Water Servicing Strategy 1 ................................................................................ 35 Figure 3.8 Alternative Water Servicing Strategy 2 ................................................................................ 36 Figure 3.9 Alternative Water Servicing Strategy 3 ................................................................................ 37 Figure 3.10 Alternative Water Servicing Strategy 4 ................................................................................ 38 Figure 3.11 Alternative Water Servicing Strategy 5 ................................................................................ 39 Figure 3.12 Alternative Water Servicing Strategy 6 ................................................................................ 40 Figure 3.13 Alternative Water Servicing Strategy 7 ................................................................................ 41 Figure 3.14 Preferred water servicing strategy for the lake-based system .............................................. 43 Figure 3.15 Maximum day demands as per the York-Peel water servicing agreement ........................... 54 Figure 3.16 Post-2031 water servicing strategy ...................................................................................... 59 List of Tables

Table 3.1 Water design criteria for growth within the lake-based water system ...................................... 6 Table 3.2 Existing lake-based water transmission facilities.................................................................. 12 Table 3.3 Lake-based water reservoirs and pumping stations in the Region of Peel ............................ 17 Table 3.4 Forecasts of maximum day demands for the lake-based system (ML/d) .............................. 22 Table 3.5 Pumping station requirements for the lake-based system (ML/d) ......................................... 25 Table 3.6 Five-point evaluation criteria to assess strategies, alignments and sites .............................. 30 Appendices

Appendix 3A – Water Demand Projections Appendix 3B – Historical Water Flows Appendix 3C – Water Design Criteria and Starting Point Methodology Appendix 3D – Water Concept and Strategy Evaluation Tables Appendix 3E – Water System Schematics Appendix 3F – Unit Costs Appendix 3G – 2014 Water DC Map

Page 5: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014 Page 1

1 Introduction

1.1 Background

The Region of Peel encompasses the City of Mississauga, the City of Brampton and the Town of Caledon. The total 2011 population in the Region is approximately 1,340,000 residents and 686,000 employees1. The Region is responsible for water treatment, transmission and distribution mains, storage facilities and booster pumping stations, as well as wastewater treatment, sewers, force mains and sewage pumping stations. The Region employs the Ontario Clean Water Agency (OCWA) to operate, maintain and manage the major infrastructure of the lake-based water and wastewater systems, which are respectively referred to as the water transmission system and the wastewater trunk collection system. The Region of Peel is part of the Greater Golden Horseshoe (GGH) area situated around the western end of Lake Ontario that continues to be one of the fastest growing regions in North America. The Government of Ontario’s legislative growth plan, Places to Grow Act 2005, identifies substantial population and employment growth for the GGH to 2031. Readily available and accessible public infrastructure is essential to the viability of existing and growing communities. Infrastructure planning, land use planning and infrastructure investment require close integration to ensure efficient, safe and economically achievable solutions to provide the required water and wastewater infrastructure. To balance the needs of growth with the protection and preservation of natural, environmental and heritage resources, the Region of Peel initiated an update of its Water and Wastewater Master Plan. The 2013 Master Plan provides a review, evaluation and development of water and wastewater servicing strategies for all servicing within the lake-based systems. The lake-based systems service or will service all of Mississauga and Brampton and some areas of Caledon, including Bolton, Mayfield West and, for wastewater servicing, Caledon East. The study does not examine the groundwater-based systems or communal wastewater systems in Caledon. The 2013 Master Plan uses updated population and employment growth forecasts based on a 2031 planning horizon. The 2013 Master Plan builds on previous work undertaken as part of the 1999 Master Plan, the 2002 Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s planning for growth and will provide the framework and vision for the water and wastewater servicing needs for the lake-based service areas of the Region to 2031 and beyond.

1.2 Master Plan Objectives

The Water and Wastewater Master Plan comprehensively documents the development, evaluation and selection of the preferred water and wastewater servicing strategies to meet the servicing needs of existing and future development to 2031.

1 Region of Peel SGU GIS shapefile; ‘P2011’ and ‘E2011’ fields. Region of Peel, 2011.

Page 6: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014 Page 2

The 2013 Master Plan evaluates the ability of existing and planned water and wastewater infrastructure in the Region of Peel to efficiently and effectively service the Region’s existing and anticipated growth, and to evaluate and develop recommended servicing strategies. The key objectives of the 2013 Master Plan are as follows:

• Review planning forecasts to 2031 and determine the impacts on servicing needs for the Region’s lake-based water and wastewater infrastructure;

• Evaluate and incorporate proposed water and wastewater infrastructure needs to 2041 and 2051; • Review the Region’s current lake-based water and wastewater servicing strategies to support the

existing servicing agreements with York Region and the City of Toronto; • Undertake a comprehensive review and analysis for both water and wastewater servicing

requirements; • Address key servicing considerations as part of the development and evaluation of servicing

strategies including: o Level of service to existing users and approved growth o Operational flexibility o Security of supply o Mitigation of impacts to natural, social and economic environments o Opportunity to meet policy, policy statements, regulations and technical criteria o Opportunity to optimize existing infrastructure and service strategies o Ensuring the strategies are cost effective

• Consider and develop sustainable servicing solutions; • Utilize updated industry trends and more detailed information from relevant Region studies and

projects to provide better capital cost estimates; • Utilize recently completed and on-going projects to update infrastructure status, capacity and cost

estimates; • Utilize the updated water and wastewater hydraulic models for the analysis of servicing

alternatives; • Establish a complete and implementable water and wastewater capital program; and • Extensive consultation with the public and stakeholders.

1.3 Master Plan Documentation Layout

The 2013 Water and Wastewater Master Plan Report, including all supporting volumes, is the documentation placed on public record for the prescribed review period. The documentation, in its entirety, describes all required phases of the planning process and incorporates the procedure considered essential for compliance with the Environmental Assessment Act.

Page 7: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014 Page 3

The Master Plan Report is organized into five volumes as illustrated in Figure 3.1 and as described below:

Figure 3.1 Master Plan Document Layout

Volume I – Executive Summary Volume I provides a brief overview of the 2013 Master Plan, it summarizes the information contained in Volumes II, III, IV and V, including problem statement, purpose of the study, significant planning, environmental and technical considerations, description of the analysis performed and final solutions and recommendations. Volume II – Background and Planning Context Volume II details the master planning process including the Master Plan Class EA process, related studies, legislative and policy planning context, water and wastewater servicing principles and policies, population and employment growth forecasts, existing environmental and servicing conditions and future considerations. The appendices in this volume contain relevant baseline and planning information including:

• Appendix 2A – Water and Wastewater Servicing Principles and Policies Paper • Appendix 2B – Planning Data • Appendix 2C – Baseline Natural Heritage Studies Report

Volume III – Water Master Plan and Project File Volume III is the principle document summarizing the study objectives, approach, methodologies, technical analyses, evaluation and selection of the preferred water servicing strategy. The first section provides the context for the evaluation and decision-making processes undertaken to determine the preferred servicing strategy. The second section provides detailed project-specific evaluation and technical supporting documentation for the Water Capital Plan.

Page 8: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014 Page 4

Volume III – Water Master Plan Appendices Technical background information critical in the development of the Water Master Plan is included in the appendices of Volume III. The technical appendices contain relevant project, implementation and technical analysis information, including:

Volume IV – Wastewater Master Plan and Project File Volume IV is the principle document summarizing the study objectives, approach, methodologies, technical analyses, evaluation and selection of the preferred wastewater servicing strategy. The first section provides the context for the evaluation and decision-making processes undertaken to determine the preferred servicing strategy, while referring the reader to the second section for detailed project-specific evaluation and technical supporting documentation for the Wastewater Capital Plan. The second section, the Wastewater Project File, provides detailed project information for selected capital projects. Each file includes technical and financial documentation, including project tracking sheets, evaluation tables, maps and other technical supporting documentation to support the Schedule B projects satisfied under the Master Plan. The Master Plan provides systematic evaluation and documentation to support the Schedule B Class EA requirements as well as applicable review agency commitments prior to their respective implementation. Volume IV – Wastewater Master Plan Appendices Technical background information critical in the development of the Wastewater Master Plan is included in the appendices of Volume IV. The technical appendices contain relevant project, implementation and technical analysis information, including:

• Appendix 3A – Water Demand Projections • Appendix 3B – Historical Water Flows • Appendix 3C – Water Design Criteria and Starting Point Methodology • Appendix 3D – Water Concept and Strategy Evaluation Tables • Appendix 3E – Water System Schematics • Appendix 3F – Unit Costs • Appendix 3G – 2014 Water DC Map & Capital Plan Projects Map

• Appendix 4A – Wastewater Flow Projections • Appendix 4B – Historical Wastewater Flows • Appendix 4C – Wastewater Design Criteria and Starting Point Methodology • Appendix 4D – Wastewater Concept and Strategy Evaluation Tables • Appendix 4E – Unit Costs • Appendix 4F – Model Build and Calibration Report • Appendix 4G – Trunk Sewer and Pumping Station Schematics • Appendix 4H – Schedule B Projects • Appendix 4I – 2014 Wastewater DC Map & Capital Plan Projects Map

Page 9: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014 Page 5

Volume V – Public and Agency Consultation Volume V contains all relevant documentation of the public consultation process including notices, comments and responses, and distribution information. Presentation material from all Public Information Centres (PICs) held during the process is included. Other presentation material and discussion information from workshops held with relevant agencies, approval bodies and other stakeholders are also included.

1.4 Master Plan Report Volume III

The current volume, Volume III, provides the analysis and summary of the preferred 2031 water servicing strategy for the Region of Peel. It also provides the background support for satisfying the Class EA process. This volume has been organized in eight sections as described below: 1. Introduction 2. Water System Policy and Criteria 3. Existing Water Transmission System 4. Assessment of Existing and Future Water Infrastructure 5. Evaluation of Water Concepts and Strategies 6. Preferred Water Servicing Strategy 7. York Region Water Servicing Strategy 8. Intensification and Post-2031 Vision Volume III is one of five volumes that make up the compete Master Plan Class EA Study Report and should be read in conjunction with the other volumes.

Page 10: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014 Page 6

2 Water System Policy and Criteria

2.1 Design Criteria

The guiding principle for the design criteria is to ensure that demand projections are accurately predicted with an appropriate level of safety and risk management. This principle ensures that the infrastructure has sufficient capacity to meet the servicing requirements and that the timing of key infrastructure does not compromise operation of the facilities or impede approved and planned growth. The development of design criteria is an element that has been reviewed during each master plan update and, as a result, has evolved over the years. As such, an analysis of water design criteria was completed as part of the study to ensure that the projected water demands are accurate and reflect new trends to support decision making for the sizing and timing of future infrastructure. This analysis is included in Appendix 3C. Table 3.1 summarizes the current Region of Peel water design criteria used at a master planning level.

Table 3.1 Water design criteria for growth within the lake-based water system

Type of Development Average Day Demand Maximum Day Factor Peak Hour Factor

Residential 280 L/person/day 2.0 3.0

Employment 280 L/employee/day 1.4 3.0

Historical data demonstrate that average day flows equate to 280 L/cap/d for residential development. Based on the format of planning projections received from the Region of Peel, it is considered appropriate to utilize the employment (ICI) design criteria as a function of employees. Based on employment land criteria for lot coverage and employee density, it was determined that using an employment density of 48 employees/ha, the employment consumption rate equates to 280 L/emp/d. The rated capacity of a water treatment plant is defined as the maximum daily flow that the works is approved to treat. Water treatment capacity is based on meeting maximum day water demand requirements with an additional factor for in-facility uses such as filter backwashing. A review and sensitivity analysis of various methodologies for projecting future water demands was undertaken to determine the most appropriate methodology for the 2013 Master Plan. The approach moving forward is based on establishing a yearly starting point, calculated from historical flow data, and projecting growth demands from this starting point going forward. Projected water demands will be determined using the planning data for residential and non-residential users and applying the design criteria.

Page 11: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014 Page 7

2.1.1 Water Treatment Plants

Under this approach, the design criteria will be applied to the residential and employment growth only and added to the starting point to project interval year flows. As such, the design criteria must estimate what could be consumed/generated and not necessarily what was consumed/generated. A baseline 2011 maximum day demand was calculated at each water treatment plant using historical demands as a basis for projecting future demands at the treatment plants. Equivalent per capita consumption was calculated for each year by dividing the year’s maximum day demand production by the year’s population (based on the planning data). An average per capita consumption was calculated for each plant over the last five and ten years (i.e., the 5-year and 10-year rolling averages). Going forward, the Region intends to update these rolling averages each year. The 2011 maximum day Starting Point is defined as the 2011 serviced population multiplied by the 5-year or 10-year rolling average. Residential and employment growth was then added to this baseline using the water design criteria presented in Table 3.1. The Region has historically applied the design criteria directly to the population and employment data to determine the water demand projections. The rolling average methodology will take into account yearly fluctuations between dry/warm years and wet years. Consumption will be higher in dry/warm years due to increased water usage. A sensitivity analysis was done on the projected demands to 2031 by comparing different methodologies and evaluating its impact on the 2031 demands. From the analysis it was concluded that on a Region-wide basis the 5- and 10-year averages using 275 L/cap/d and 280 L/cap/d are similar to those presently in use by the Region of Peel. This comparison confirms that the existing consumption criteria are representative of historical trends in the Region and supports validation of the criteria. As such, it is recommended that the Region continue to use the average day consumption design criteria of 280 L/cap/d for residential growth and 280 L/employee/d for employment growth, as per Table 3.1. Details of this analysis can be reviewed in Appendix 3C. The maximum day peaking factors that are currently being used by the Region are higher than those that have been observed in the last 10 years on a Region-wide basis. It was determined that the existing maximum day peaking factors, although higher than the observed trends, should be retained as they will allow for the effects of warmer-than-average summers. It is recommended that a 2011 starting point of 821.27 ML/d be used for the 2013 Master Plan, which corresponds to the 5-year rolling average methodology. A trigger point of 90 per cent of rated capacity has been used to determine when an expansion would be required. That is, an expansion is recommended when projected flows reach 90 per cent of plant capacity. If an expansion is recommended, further analysis should be conducted to confirm actual timing of the plant expansion project. The age and condition of the plant should be considered as well as the amount of storage in the system that can be used to supply maximum day demand.

Page 12: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014 Page 8

2.1.2 Transmission Mains

The transmission mains are required to convey the total pumping capacity requirements of the receiving pumping station and the upper zone reservoir. This capacity is based on the component of peak hour demand for the local zone and the maximum day demand requirements for each subsequent upper zone. Theoretical transmission main capacities are estimated using capacity calculations with a reasonable allowable head loss. For larger transmission mains, a factor of 1.5 m/km of head loss is typically used. The Region of Peel full pipe hydraulic model was utilized to assess the network and to further refine transmission main capacities. Four scenarios (minimum hour, maximum day, peak hour and maximum day plus fire) were evaluated to confirm transmission main requirements. Additional criteria developed from previous studies were carried over and utilized to establish existing and future transmission main capacities. These criteria are as follows:

• Transmission mains must be capable of transferring flow with an acceptable HGL and typically below 100 psi.

• Transmission mains are typically fed from the low-lift pumps, which also directly feed the local distribution system. As such, maximum flow is based on current pumping capacity, pressure head and the need to operate these pumps with an acceptable HGL.

• Velocities within transmission mains should be maintained below 2.0 m/s. Transmission main capacity expansions are based on service level (e.g., pressure, velocity, head loss). Oversizing was considered in areas where future potential growth and build out is expected to occur. Distribution feeder main sizing is based on flow demands and pressure requirements which include maintaining pressures in the distribution system between 40 and 100 psi. Distribution feeder mains require pressures higher than 40 psi to account for hydraulic losses in the local system. Water mains that are part of the local distribution system are sized for the greater of maximum day demand plus fire or peak hour demand.

2.1.3 Water Pumping Stations

Pumping stations are rated on their firm capacity, which is defined as the capacity of the pumping station with the largest pump out of service. For each pressure zone, the west, central and east pumping stations should be able to provide peak hour demands in the immediate serviced zone and have sufficient capacity to transfer maximum day demands to the upper serviced pressure zones. Capacity expansions are triggered once the pumping station’s firm capacity reaches the required maximum day demand or peak hour demand, depending on high-lift or low-lift requirement. System head curves were developed for each set of pumps to evaluate pumping capacity.

Page 13: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014 Page 9

2.1.4 Water Storage Facilities

Required storage is dictated by the ability to provide the required equalization storage, fire storage, and emergency supply to maintain a satisfactory level of service. Reservoir storage capacity at each pumping station is based on typical MOE criteria and Fire Underwriters Survey (FUS) criteria:

• Equalization storage at 25 per cent of the maximum day demand for the lower pressure zone at the reservoir’s HGL.

• Fire storage in accordance with the Standard of Municipal Fire Protection of the Canada Underwriters Association. Typically 360 L/s for 6 hours in each pressure zone based on each zone’s population.

• Emergency storage at 25 per cent of the equalization plus fire storage for the lower pressure zone at the reservoir’s HGL.

However, given that the existing Peel system typically operates under pumped supply, the reservoirs do not supply the pressure zone at the reservoir’s hydraulic grade line (HGL). Rather, they float the lower zone and control the operating pressure. As such, the typical storage capacity criteria is also cross-reference against storage volumes required for the pressure zones serviced by that pumping facility.

2.2 Service Levels

Although the focus of the Master Plan is on the water transmission system, service impacts to the local distribution system were also considered. As such, to ensure an adequate level of service, minimum water main sizes shall be as follows:

• 150-mm diameter water main for main lines in residential areas; 50-mm diameter water mains are allowed in cul-de-sacs and shall be looped back to the main line;

• 300-mm diameter water main for main lines servicing schools and high-density residential areas; and

• 300-mm diameter water main for main lines servicing industrial/ commercial/ institutional areas. As per the MOE Guidelines, the water system should be designed based on maximum day demand as well as recognize requirements for fire flows and peak hour demands. The maximum day demand is typically referenced as a maximum day factor above the average day demand. A minimum operating pressure of 40 psi (275 kPa) and a maximum operating pressure of 100 psi (690 kPa) shall be maintained within the distribution system under maximum day demand and a minimum operating pressure of 40 psi shall be maintained under peak hour demand. Under fire flow conditions, it is allowable for pressures to drop to a minimum of 20 psi (140 kPa).

2.3 Costing Methodology

Preliminary unit rates for linear and vertical infrastructure were discussed and agreed upon by the project team. These costs are based on 2013 dollars and take into consideration local prices of labour and local

Page 14: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014 Page 10

availability of materials wherever possible. Construction industry indices were referenced in the development of these unit costs. Estimates were favourably compared to costs of recent capital projects to support validation of the unit rates.

2.3.1 Unit Rates

The proposed unit rates will be used as a basis to develop estimates for each of the projects identified in the 2013 Master Plan. The rates were initially developed as part of the Quick Start program at the beginning of the master plan process.2 As the 2013 Master Plan focuses on trunk water and wastewater infrastructure, the emphasis of the peer review was on the unit rates for this size of infrastructure. A peer review of linear unit rates was conducted as part of the 2013 Master Plan. The unit rates used in the Quick Start program were provided to Estimating Services Incorporated (ESI) for review. The focus of the review was to determine whether the 2013 Master Plan unit rates provided a sound basis for project estimates. As part of the review, ESI developed their own unit rates for comparison based on consultation with suppliers as well as recent project experience. The ESI and Quick Start unit rates were compared to determine if the Quick Start values fell within a reasonable range of the ESI values. It is not expected that the rates should be identical, as ESI rates are based on May 2012 construction conditions and are not sufficiently conservative for a master planning study; whereas the Quick Start unit rates were developed to represent general unit rates in 2011 for master planning purposes. The results of the peer review were used to adjust the Quick Start unit rates for use in the 2013 Master Plan. The following adjustments were made: The pipe supply rates for force mains and water mains were increased by 20 per cent. Where appropriate, the 30 per cent factor was applied in the individual project costing sheets. A minimum installation cost of $40/metre was used to prevent unrealistically low installation costs. The formulae used to calculate excavation volume were adjusted. For the 5-metre deep wastewater pipe, a 5-metre deep trench box was assumed (i.e., the excavated volume was calculated as depth x width or 5 metre x width, per metre of pipe). Due to relatively negligible inflation between 2012 and 2013, an effective inflation rate of 0% was used to adjust the 2012 unit rates to 2013 dollars. Unit rates have changed significantly since the 2007 Master Plan. Factors that have contributed to the change in unit rates include inflation, the fact that pipe pricing is considerably higher now, excavation and granular costs have increased, and increasing fuel prices have had effects over several areas. The existing unit rates were revised based on the peer review process and are considered appropriate for master planning purposes. The unit rates are within the range of costs to be expected on competitively tendered jobs in the Region of Peel, accounting for add-ons that may be applied on a project specific basis (e.g., for urban areas, difficult construction conditions, and project-specific considerations). 2 Memorandum - Peel Quick Start. AECOM, August 2011.

Page 15: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014 Page 11

2.3.2 Operation and Maintenance Costs

Operation and maintenance (O&M) costs were considered qualitatively at every stage of the evaluation process. For example, where one strategy requires more pumping stations relative to other strategies, that strategy will score less favourable under the financial impact category due to higher maintenance and operating costs inherent with the new facilities.

2.3.3 Final Project Costs

Based on the linear and vertical unit rates, detailed costing sheets were developed to support the financial evaluation for each alternative alignment, storage facility, pumping station, and water or wastewater treatment project. This costing sheet considers base costs, including: construction, geo-technical, property requirements, permit and approval requirement, overhead and project contingencies.

Page 16: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014 Page 12

3 Existing Water Transmission System

3.1 Existing Infrastructure

The Region of Peel’s lake-based water transmission system services the City of Mississauga, much of the City of Brampton, and parts of the Town of Caledon. The system consists of two Lake Ontario-based water treatment plants (the Lakeview WTP and the Lorne Park WTP), transmission mains, pumping stations, reservoirs and elevated tanks that deliver water to customers through seven pressure zones separated by approximately 30-metre intervals of elevation. The lake-based water transmission system consists of three main trunk systems: west, central and east. The existing transmission facilities are summarized in Table 3.2. Separate from the water transmission system, the water distribution system conveys treated water from the water transmission facilities to the customers. With the exception of east-west sub-transmission, the water distribution system is not included in the 2013 Master Plan for the lake-based system. The Region of Peel also maintains four municipal groundwater systems servicing rural communities in the Town of Caledon. These municipal groundwater systems are not included in the 2013 Master Plan for the lake-based system.

Table 3.2 Existing lake-based water transmission facilities

West Trunk System Central Trunk System East Trunk System

Snelgrove Elevated Tank (WS6) West Brampton Reservoir (WS4) and Pumping Station (5LLP, 6HLP) Meadowvale North Reservoir (WS3) and Pumping Station (4LLP, 5HLP) Streetsville Reservoir (WS2) and Pumping Station (3LLP, 4HLP) Herridge Reservoir (WS1) and Pumping Station (2LLP, 3HLP) Lorne Park Water Treatment Plant and Pumping Station (1HLP, 2HLP)

Mayfield West Elevated Tank (CS7) North Brampton Reservoir (CS5) and Pumping Station (6LLP, 7HLP) East Brampton Reservoir (CS4) and Pumping Station (5LLP, 6HLP) Beckett Sproule Reservoir (CS3) and Pumping Station (4LLP, 5HLP) Hanlan Reservoir (CS2) and Pumping Station (3LLP, 4HLP) Silverthorn Reservoir (CS1) and Pumping Station (2LLP, 3HLP) Lakeview Water Treatment Plant and Pumping Station (1HLP, 2HLP)

Bolton Elevated Tank (BS6) Tullamore Reservoir (ES4) and Pumping Station (5LLP, 6HLP) Airport Road Reservoir (ES3) and Pumping Station (4LLP, 5HLP, York) Beckett Sproule Transfer Pumping Station

Note: W – West; C – Central; E – East; S – Storage; LLP – Low Lift Pump; HLP – High Lift Pump # - pressure zone serviced by the facility

Page 17: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014 Page 13

Figure 3.2 Existing Region of Peel Lake-Based Water Transmission System

Page 18: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 14

3.1.1 Water Treatment Plants

The Lorne Park WTP provides water supply for the west transmission system and the Lakeview WTP provides water supply for the central and east transmission systems. Although the water distribution system is interconnected throughout each pressure zone, the approximate service boundary between the west and central systems is McLaughlin Road and the approximate service boundary between the central and east systems is Airport Road.

3.1.1.1 Lakeview Water Treatment Plant

The Lakeview WTP is located in southeast Mississauga, east of Cawthra Road and south of Lakeshore Road East, at the south end of East Avenue. The Lakeview WTP is a conventional water treatment plant with an advanced treatment train consisting of ozone, biologically activated carbon (BAC) contactors and membrane filtration. The site area is approximately 27 hectares (67 acres), including water lots, of which approximately 14 hectares (35 acres) is presently being used for the water treatment plant. The potential ultimate site capacity is approximately 1150 ML/d under maximum day conditions and conventional technologies. The Lakeview WTP expansion schedule is primarily based on growth in east Peel and water demand for York Region. The Lakeview WTP raw water intake is a 2550-mm diameter pipe extending 2,000 metres into Lake Ontario. The pipe has two intake cribs that feed a common intake pipe. Overall, the intake has a net capacity of 1,150 ML/d.

3.1.1.2 Lorne Park Water Treatment Plant

The Lorne Park WTP is located in southwest Mississauga, east of Southdown Road and south of Lakeshore Road West within Jack Darling Memorial Park. The Lorne Park WTP is a conventional water treatment plant. The Lorne Park WTP is largely underground to minimize the visual impact on the park setting. The potential ultimate site capacity is approximately 500 ML/d under maximum day conditions and conventional technologies. The Lorne Park WTP expansion schedule is primarily required based on growth in west Peel. The 2002 Master Plan Addendum recommended expansion of the Lorne Park WTP capacity from 347 ML/d to 500 ML/d by 2013. Additional review under the 2007 Master Plan led to the concept of expanding the plant capacity through internal retrofitting. Following preliminary and detailed design, the following construction contracts were undertaken:

• Construction of a new pumping station and two sewage pumping stations within the same site (completed in 2011);

• Construction of a new pipe connection to the existing intake (completed in 2011); • Construction involving the new treatment processes, including the membrane and ultraviolet (UV)

disinfection processes (new building expansions and Milestone 1 for 210 ML/d membrane and UV disinfection completed in 2011 with the balance of the membranes completed in 2012).

Page 19: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 15

When completed, the Lorne Park WTP will have a treatment capacity of 500 ML/d, consisting of the 120 ML/d conventional treatment plant (Plant 1) and the 380 ML/d membrane filtration plant (Plant 2). The Lorne Park WTP raw water intake consists of a 1230-metre long horseshoe shaped tunnel 1800-mm in diameter and 355 metres of 2400-mm land-laid pipe. The Lorne Park WTP intake has a design capacity of 454 ML/d.

3.1.2 Transmission Mains

3.1.2.1 West Trunk System

WT1: Lorne Park WTP to the Herridge Reservoir (Pressure Zone 1)

There is an existing 1500-mm diameter Pressure Zone 1 transmission main from the Lorne Park WTP to the Herridge Reservoir. The theoretical capacity of this transmission main is approximately 271 ML/d; however, the actual capacity based on hydraulics and design criteria is estimated at 347 ML/d. WT2S: Lorne Park WTP to the discharge side of the Herridge Pumping Station (Pressure Zone 2)

The 2007 Master Plan recommended a new 2100-mm diameter Pressure Zone 2 transmission main from the Lorne Park WTP to the discharge side of the Herridge Pumping Station. The Herridge 2100 PZ2 Transmission Main from Lorne Park WTP to the Herridge Pumping Station was constructed over the past few years and is now in service. The theoretical capacity of this transmission main is approximately 378 ML/d; however, the actual capacity is estimated at 150 ML/d due to pumping constraints. WT2: Herridge Pumping Station to the Streetsville Reservoir (Pressure Zone 2)

There are two existing transmission mains from the Herridge Pumping Station to the Streetsville Reservoir: a 1050-mm diameter transmission main and a 1500-mm diameter transmission main. The total theoretical Pressure Zone 2 west transmission capacity is approximately 378 ML/d; however, the actual capacity is estimated at 286 ML/d. WT3: Streetsville Pumping Station to the Meadowvale North Reservoir (Pressure Zone 3)

There is an existing 900-mm diameter Pressure Zone 3 transmission main from the Streetsville Pumping Station to the Meadowvale North Reservoir. The 2007 Master Plan recommended twinning with a new 1200-mm diameter transmission main which was completed in 2013. With the new transmission main in service, the total theoretical Pressure Zone 3 west transmission capacity is approximately 222 ML/d; however, the actual capacity is estimated at 167 ML/d. WT4: Meadowvale North Pumping Station to the West Brampton Reservoir (Pressure Zone 4)

The 2007 Master Plan recommended a new 1500-mm transmission main from the Meadowvale North Pumping Station to the West Brampton Reservoir. This transmission main, with a theoretical capacity of approximately 271 ML/d, was commissioned in 2011; however, the actual capacity is estimated at 174 ML/d.

Page 20: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 16

3.1.2.2 Central Trunk System

CT1: Lakeview WTP to the Silverthorn Reservoir (Pressure Zone 1)

There are two existing Pressure Zone 1 transmission mains from the Lakeview WTP to the Silverthorn Reservoir: a 900-mm diameter transmission main and a 1500-mm diameter transmission main. The total theoretical Pressure Zone 1 transmission capacity is approximately 342 ML/d; however, the actual capacity is estimated at 228 ML/d. CT2H: Lakeview WTP to the Hanlan Reservoir (Pressure Zone 2)

There is an existing 2100-mm/1800-mm diameter Pressure Zone 2 transmission main from the Lakeview WTP to the Hanlan Reservoir. The transmission capacity of this main is approximately 438 ML/d. The 2007 Master Plan recommended a new transmission main to twin the existing Hanlan Transmission Main. Through the Class EA, a 2400-mm diameter Pressure Zone 2 transmission main was recommended. This transmission main is anticipated to be in service by 2017 with an approximate theoretical capacity of 934 ML/d. With this transmission main in service, the actual total transmission capacity will be approximately 1025 ML/d. CT2: Silverthorn Pumping Station to the Hanlan Reservoir (Pressure Zone 2)

There is an existing 1200-mm diameter Pressure Zone 2 transmission main from the Silverthorn Pumping Station to the Hanlan Reservoir. The theoretical transmission capacity of this main is approximately 151 ML/d; however, the actual capacity is estimated at 126 ML/d. CT3: Hanlan Pumping Station to the Beckett Sproule Reservoir (Pressure Zone 3)

There are two existing Pressure Zone 3 transmission mains from the Hanlan Pumping Station to the Beckett Sproule Reservoir: a 1200-mm diameter transmission main and a 1500-mm diameter transmission main. The total theoretical Pressure Zone 3 transmission capacity is approximately 422 ML/d. A new 2100-mm diameter transmission main, with a theoretical capacity of 657 ML/d, was recommended in the 2007 Master Plan and is currently under construction, with an anticipated in-service date of 2014. CT4: Beckett Sproule Pumping Station to the East Brampton Reservoir (Pressure Zone 4)

There is an existing 1050-mm diameter Pressure Zone 4 transmission main from the Beckett Sproule Pumping Station to the East Brampton Reservoir. The actual transmission capacity of this main is approximately 110 ML/d. A feasibility study and preliminary analysis for the 2013 Master Plan recommended a new 1500-mm diameter transmission main with a theoretical capacity of 271 ML/d. This project was identified as a Schedule C and a Class Environmental Assessment (EA) was undertaken. It is anticipated that the construction of this watermain will begin in 2016. CT5: East Brampton Pumping Station to the North Brampton Reservoir (Pressure Zone 5)

There is an existing 900-mm diameter Pressure Zone 5 transmission main from the East Brampton Pumping Station to the North Brampton Reservoir. The theoretical transmission capacity of this main is approximately 71 ML/d; however, the actual capacity is estimated at 55 ML/d.

Page 21: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 17

CT7: North Brampton Pumping Station to the Mayfield West Elevated Tank (Pressure Zone 7)

There is an existing 600-mm diameter Pressure Zone 7 transmission main from the North Brampton Pumping Station to the Mayfield West Elevated Tank. The theoretical transmission capacity of this main is approximately 24 ML/d.

3.1.2.3 East Trunk System

ET3A: Beckett Sproule Transfer Pumping Station to the Airport Road Reservoir (Airport Road Transfer)

There is an existing 2100-mm diameter transmission main from the Beckett Sproule Pumping Station to the Airport Road Reservoir to transfer water from the central to the east transmission system. The theoretical capacity of this transfer main is approximately 657 ML/d; however, the current actual transmission capacity is estimated at 340 ML/d due to pumping constraints. ET3Y: Airport Road Pumping Station to York Region (York Transfer)

There is an existing 1800-mm diameter transmission main from the Airport Road Pumping Station to the York-Peel boundary to supply water to York Region as per the York-Peel Water Supply Agreement. The theoretical capacity of this transmission main is 438 ML/d; however, the actual capacity is 401 ML/d. ET4: Airport Road Pumping Station to the Tullamore Reservoir (Pressure Zone 4)

The 2007 Master Plan recommended a new 1050-mm diameter Pressure Zone 4 transmission main from the Airport Road Pumping Station to the Tullamore Reservoir with a theoretical capacity of 106 ML/d. BT6: Tullamore Pumping Station to the Bolton Elevated Tank (Pressure Zone 6)

There is an existing 750-mm diameter Pressure Zone 6 transmission main on Mayfield Road from the Tullamore Pumping Station to the Bolton Elevated Tank. The theoretical transmission capacity of this main is 44 ML/d.

3.1.3 Water Pumping Stations and Reservoirs

There are currently 12 pumping stations and 10 reservoirs in the lake-based system. Table 3.3 summarizes the facilities and their capacities.

Table 3.3 Lake-based water reservoirs and pumping stations in the Region of Peel

Facility Serviced Pressure Zone

No. of Pumps

Installed Capacity (ML/d)

Firm Capacity (ML/d)

Actual Firm Capacity (ML/d)

Reservoir Capacity (ML)

Source of Installed Capacity

WEST TRANSMISSION SYSTEM

Lorne Park Water Treatment Plant

LL in Plant 10 1060 920 n/a n/a Region Records

1HLP 7 542 451 375 23.0

Page 22: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 18

Facility Serviced Pressure Zone

No. of Pumps

Installed Capacity (ML/d)

Firm Capacity (ML/d)

Actual Firm Capacity (ML/d)

Reservoir Capacity (ML)

Source of Installed Capacity

Lorne Park Pumping Station

2HLP 4 300 150 150 Region Records

Herridge Reservoir and Pumping Station

2LLP 12 408 340 328 45.0

OCWA Process Schematic 3HLP 4 99 67 36

Streetsville Reservoir and Pumping Station

3LLP 5 307 217 190 48.0

OCWA Process Schematic 4HLP 4 168 100 84

Meadowvale North Reservoir and Pumping Station

4LLP 6 346 275 215 55.0

OCWA Process Schematic 5HLP 6 144 116 74

West Brampton Reservoir and Pumping Station

5LLP 4 90 60 20 40.0

OCWA Process Schematic 6HLP 4 93 62 84

Snelgrove Elevated Tank

n/a n/a n/a n/a n/a 3.8 Region Records

CENTRAL TRANSMISSION SYSTEM

Lakeview Water Treatment Plant

LL in Plant 11 1,681 1,494 n/a n/a OCWA Process Schematic

Lakeview Pumping Station

1HLP 4 335 245 265 25.0

OCWA Process Schematic

2HLP 6 680 530 498

Silverthorn Reservoir and Pumping Station

2LLP 5 449 344 220 45.0

OCWA Process Schematic

3HLP 3 103 58 61

Hanlan Reservoir and Pumping Station

3LLP 9 1150 1004 630 77.0

OCWA Process Schematic

4HLP 4 160 103 89

Beckett Sproule Reservoir and Pumping Station

4LLP 6 370 279 193 95.0

OCWA Process Schematic

5HLP 6 257 197 154

East Brampton Reservoir and Pumping Station

5LLP 4 179 118 100 48.0

OCWA Process Schematic

6HLP 4 208 140 91

North Brampton Reservoir and Pumping Station

6LLP 4 127 91 65 52.8

OCWA Process Schematic

7HLP 4 35 25 25

Mayfield West Elevated Tank

n/a n/a n/a n/a n/a 9.2 Region Records

Page 23: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 19

Facility Serviced Pressure Zone

No. of Pumps

Installed Capacity (ML/d)

Firm Capacity (ML/d)

Actual Firm Capacity (ML/d)

Reservoir Capacity (ML)

Source of Installed Capacity

EAST TRANSMISSION SYSTEM

Airport Road Reservoir and Pumping Station

York 6 234 178

55.0 OCWA Process Schematic

4LLP 3 125 83 75

5HLP 3 120 80 94

Beckett Sproule Transfer Pumping Station

Transfer 4 369 277 340 n/a

Tullamore Reservoir and Pumping Station

5LLP 3 90 60 54 40.0

Region Records 6HLP 4 160 120 87

Bolton Elevated Tank

n/a n/a n/a n/a n/a 3.8 Region Records

North Bolton Elevated Tank

n/a n/a n/a n/a n/a 9.0 Region Records

3.2 Hydraulic Water Model

The Region maintains an InfoWater hydraulic model of its water distribution system. The water model used for the 2013 Master Plan was last updated based on the GIS data received on May 31, 2011. The model update process includes the following main steps:

1. GIS data review; 2. Model update; 3. Model QA/QC; and 4. Demand allocation.

Subsequent to the update of the hydraulic model, the model was calibrated to confirm the hydraulic model accuracy. Hydraulic model calibration is the process of testing and adjusting the model to ensure that model results bear reasonably close comparison to actual performance of the water distribution system over a range of operating conditions. Calibration is mandatory prior to use of the model for any capital works decision-making analysis, as well as further applications of the model such as water quality, operations or energy management modelling. The benefits of calibration include discovering and correcting discrepancies in the model data and, occasionally, identification of problems in the field.

Model calibration essentially encompasses all aspects of the model development and field data collection process. The process makes extensive use of the field program results as well as review of Region records and field confirmation. This calibrated model was used as part of the 2013 Master Plan analysis.

Page 24: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 20

3.3 Water Servicing Flow Schematics

To evaluate the water servicing requirements including immediate pressure zone demands as well as capacity required to service subsequent pressure zones, water servicing flow schematics were developed for each of the planning intervals, 2012, 2016, 2021, 2026, and 2031. Storage schematics for 2031 and 2051 were also developed to show storage surplus or deficit in each pressure zone. The water servicing flow schematics and storage schematics are included in Appendix 3E.

Page 25: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 21

4 Assessment of the Existing and Future Water Infrastructure

4.1 Opportunities and Constraints

As part of the Master Plan, it is important to perform an assessment of the factors that provide opportunities for developing and expanding the water system to meet growing demands as well as identifying existing constraints. In the Region of Peel the following opportunities and constraints for the water system were identified:

4.1.1 Water Treatment Plants

• The Lakeview Water Treatment Plant is currently being upgraded to a capacity of 1150 ML/d. Based on Places to Grow planning forecasts, this expansion is projected to provide sufficient capacity to service 2031 demands. The 2013 Master Plan will confirm long-term site capacity and future expansion requirements.

• The Lorne Park Water Treatment Plant is currently being upgraded to a capacity of 500 ML/d, which would be sufficient capacity to service 2031 demands, based on Places to Grow planning forecast. The 2013 Master Plan will confirm long-term site capacity and future expansion requirements.

• Additional capacity will be required to support additional demands in the Mississauga City Centre (MCC).

4.1.2 Transmission Mains

• There is an opportunity to optimize east-west transfers with distribution and pumping for improved level of service and security of supply.

• Additional transfer capacity is required from the Streetsville Pumping Station to the Meadowvale North Reservoir as well as from the Herridge Pumping Station to the Streetsville Reservoir.

4.1.3 Pumping Stations and Storage Facilities

• There is space for expansion of pumping capacity in the North Brampton Reservoir and Pumping Station facility, however there is no space to expand the reservoir.

• Additional storage capacity may be required north of Mayfield Road to service the upper pressure zones.

• Water is supplied to York Region through the Airport Road Pumping Station. • There is sufficient space at the West Brampton Reservoir and Pumping Station to expand both

pumping and storage capacity. • There is sufficient space at the Beckett Sproule Reservoir and Pumping Station to expand both

pumping and storage capacity. • There is sufficient space at the Silverthorn Reservoir and Pumping Station to expand the reservoir.

Page 26: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 22

4.1.4 Growth Opportunities

• The recent North Bolton Elevated Tank Class EA study in the Bolton Area should be incorporated into the updated Master Plan water servicing strategy.

• Significant additional growth could occur in the areas north of Mayfield Road post-2031. The 2013 Master Plan will determine the potential impact of this growth on infrastructure.

• A servicing strategy for population and employment growth potential in the Mayfield West development area will be incorporated into the 2013 Master Plan.

• Significant residential and employment growth is projected in northeast and northwest Brampton to 2031.

• The Hurontario Corridor is targeted for intensification. Results of the intensification analysis will be incorporated into the 2013 Master Plan.

4.2 Water Demand Requirements

Water demand requirements were developed for each system to identify existing and potential future supply deficiencies. Based on the planning projections, maximum day demand projections for the Region’s lake-based system, including York flows, are summarized in Table 3.4.

Table 3.4 Forecasts of maximum day demands for the lake-based system (ML/d)

Service Area 2011 2016 2021 2026 2031 West Transmission System 301.55 340.31 368.66 396.03 420.96 Central Transmission System 439.95 475.93 507.26 533.87 561.41

East Transmission System 61.60 76.62 91.28 100.04 106.77

Bolton 18.17 19.50 20.84 21.04 21.25 Peel Total 821.27 912.36 988.04 1,050.98 1,110.39 York Region (Agreement) 133.90 210.50 271.96 324.62 388.32 Peel Total including York 955.17 1,122.87 1,260.00 1,375.59 1,498.71

4.3 Hydraulic Analysis

4.3.1 Water Treatment Plants

The 2013 Master Plan analyzed the projected growth demand within each water treatment plant service area to ensure that the facility expansions and pressure zone shifting strategy were aligned adequately with growth. Figure 3.3 and Figure 3.4 show projected demands for each plant based on their pressure zone service area. The current plant capacities are also represented. There is sufficient total treatment capacity at each plant to service the Region’s needs to 2031. However, when considering the projections for each individual plant and their service area, 90 per cent of the Lakeview WTP capacity is reached before 2031, but it will not reach 100 per cent of its capacity until post-2031. The Lorne Park WTP will reach 84 per cent of its capacity by 2031.

Page 27: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 23

Figure 3.3 Projected demands at the Lakeview Water Treatment Plant

Figure 3.4 Projected demands at the Lorne Park Water Treatment Plant

Page 28: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 24

4.3.2 Transmission Mains

The InfoWater hydraulic model, in combination with the water system schematics were used to evaluate the water system’s transmission capacity. System head curves were developed for each pumping facility to evaluate the ability of the transmission mains to move water north through the system and assist in identifying constraints. Generally, existing transmission mains have sufficient capacity to move water to the next pumping station under maximum day conditions. The requirements identified under the 2007 Master Plan continue to be valid. The following transmission mains were identified as not being able to supply future demands. Herridge Pumping Station to the Streetsville Reservoir (WT2S) The existing Pressure Zone 2 transmission mains from the Herridge Pumping Station to the Streetsville Reservoir will reach their capacity by 2026. An extension of existing the 2100-mm transmission main from the Lorne Park WTP to the discharge side of the Herridge Pumping Station will be required to the Streetsville Reservoir. Streetsville Pumping Station to the Meadowvale North Reservoir (WT3) The existing Pressure Zone 3 transmission mains from the Streetsville Pumping Station to the Meadowvale North Reservoir will reach their capacity by 2021. Twinning of the existing transmission mains with a new 1200-mm transmission main will be required. Beckett Sproule Pumping Station to the East Brampton Reservoir (ET4) The existing Pressure Zone 4 transmission main from the Beckett Sproule Pumping Station to the East Brampton Reservoir will reach its capacity by 2021. Twinning of the existing transmission main with a new 1500-mm transmission main will be required.

4.3.3 Water Pumping Stations

Assessment of pumping capacity was based on the ability to provide the firm capacity to meet the required demands in the system. The hydraulic analysis conducted in the 2013 Master Plan confirmed the need for pumping station expansions or new pumping stations that will be required within the 2031 timeframe as identified in the 2007 Master Plan. As part of the analysis, system head curves were developed for every pumping station to be able to identify constraints that limit the facility’s actual pumping capacity (these graphs are shown in Appendix 3E). Table 3.5 shows the lake-based pumping station requirements every five years to meet the projected demands.

Page 29: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 25

Table 3.5 Pumping station requirements for the lake-based system (ML/d)

The current capacities at some of the pumping stations may not be sufficient to meet 2031 water demand requirements. Water system schematics as well as hydraulic modeling to create system head curves were used to assess the water pumping station requirements. The calculated “starting point” along with growth layered onto each pressure zone and calculated pumping ratios generated the estimated yearly pumping requirements to 2031. Based on the analysis, the following pumping deficiencies were identified.

Facility Name Pressure Zone 2012 2016 2021 2026 2031 Actual

Capacity

Lorne Park WTP

LL in Plant 308.86 340.31 368.66 396.03 420.96 920.50 1HLP 318.38 200.53 229.37 257.85 258.91 451.20 2HLP 0.00 150.00 150.00 150.00 175.00 150.00

Herridge 2LLP 290.25 170.51 197.82 223.57 221.88 340.50 3HLP 20.23 20.80 21.37 22.07 22.77 67.00

Streetsville 3LLP 183.14 207.35 231.09 254.12 275.08 289.00 4HLP 123.58 136.08 143.57 149.00 153.76 236.00

Meadowvale North

4LLP 117.13 136.01 154.49 173.64 191.05 275.50 5HLP 48.14 58.38 67.01 71.83 76.09 116.20

West Brampton 5LLP 32.09 71.94 84.86 96.55 107.17 60.00 6HLP 78.17 46.81 55.95 67.54 78.30 62.00

Alloa 6LLP 0.00 46.81 55.95 67.54 78.30 84.00 7HLP 0.00 1.90 4.50 7.21 9.71 15.00

Lakeview WTP LL in Plant 676.34 782.56 891.34 979.56 1077.75 1494.00 1HLP 285.52 174.86 193.33 215.40 238.63 335.00 2HLP 403.03 620.45 711.70 781.27 859.67 800.00

Silverthorn 2LLP 241.73 137.10 151.82 164.77 178.89 343.90 3HLP 62.33 51.66 56.31 59.78 63.13 57.70

Hanlan 3LLP 540.20 660.77 767.56 848.27 938.81 1003.90 4HLP 82.00 85.64 87.31 88.13 89.17 102.90

Beckett Sproule

4LLP 201.33 199.15 212.34 218.91 225.39 279.20 5HLP 104.57 113.31 123.78 132.21 142.58 196.80

East Brampton 5LLP 90.00 87.48 97.20 102.37 108.05 118.30 6HLP 65.48 64.32 70.17 73.49 76.00 139.60

North Brampton

6LLP 46.50 29.36 31.82 33.24 34.30 91.00 7HLP 10.90 15.01 19.78 20.01 20.31 24.80

Airport Road York 149.22 210.50 271.96 324.62 388.32 400.50 4LLP 46.32 90.61 101.09 107.53 112.66 124.80 5HLP 51.87 40.79 53.59 59.31 63.65 120.00

Beckett Sproule

Transfer 213.82 306.63 384.08 445.70 516.34 276.90

Tullamore 5LLP 0.00 21.96 28.86 31.93 34.27 60.00 6HLP 0.00 23.62 26.81 29.78 32.19 120.00

Page 30: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 26

Lakeview Pumping Station Expansions to the Zone 1 and Zone 2 high-lift pumps, identified in the 2007 Master Plan, continue to be a requirement. Beckett Sproule Pumping Station There is sufficient Zone 4 and Zone 5 pumping capacity at this facility after the recent upgrades. Expansion of the Airport Transfer pumping was identified and planned based on the 2007 Master Plan and should be maintained. North Brampton Pumping Station Expansion of the Zone 6 pumping was identified in the 2007 Master Plan and continues to be a requirement. The firm capacity of this station will be exceeded by 2021 when the Victoria Reservoir is commissioned. There are currently two additional pump bays available. The Zone 7 pumping requires an additional 10 ML/d by 2031. It is recommended that a pump performance review be undertaken prior to moving forward with an expansion. Herridge Pumping Station There is sufficient Zone 2 pumping capacity at this facility to meet 2031 needs. There are three pump bays available for future capacity expansion. Streetsville Pumping Station Currently, there is a future Zone 3 72 ML/d pump being designed, and there are three pump bays available for future expansion. Upgrades to the Zone 4 pumps are currently underway, one pump is being decommissioned, two 68ML/d pumps are being designed and there are two additional pump bays available for future expansion. West Brampton Pumping Station Expansion of the Zone 5 pumping was identified in the 2007 Master Plan and continues to be a requirement. The station requires an additional 37 ML/d by 2031 to meet future demands. One additional pump bay is available for future expansion.

4.3.4 Water Storage

Water system schematics and Peel’s water hydraulic model was utilized to assess future storage requirements. Storage deficiencies were identified and can be seen in Figure 3.5.

4.3.5 Intensification

An analysis was completed to evaluate the impacts of meeting intensification targets in Mississauga and Brampton. Impacts to the transmission system were identified as part of the master plan process; however, impacts to the sub-transmission and distribution infrastructure were also analysed.

Page 31: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 27

Figure 3.5 Evaluation of 2031 storage deficiencies for planning Scenario B

Page 32: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 28

5 Evaluation of Concepts and Strategies

The identification and evaluation of servicing options is a critical component of the master planning process because it enables a comprehensive review of a reasonable range of alternatives while documenting the process in a transparent manner. The evaluation process that has been undertaken is described in the following sections.

5.1 Objectives

The Region intends the 2013 Master Plan to meet the Approach 2 requirements under the Municipal Engineers Association (MEA) Class EA process. Under Approach 2, a Master Plan Report is prepared at the conclusion of Phases 1 and 2 of the Class EA process. This approach allows for all Schedule A, A+ and select Schedule B projects identified in the Master Plan to move forward to implementation. To achieve this objective, systematic evaluation and documentation is required to support the Schedule B Class EA requirements along with any applicable review agency commitments prior to implementation. Any Schedule C projects identified will also require supporting information and decision making to proceed onto separate studies and continue to Phases 3 and 4 of the Class EA process. The proposed evaluation approach described herein has been designed to ensure a logical and transparent process that can document the evaluation and decision making that will ultimately develop a capital program that is defensible. Sustainability principles will also be considered in the development of the 2013 Master Plan, and will be integrated within the five-point evaluation, such as: 1. making best use of existing infrastructure; 2. minimizing the cost of new infrastructure; 3. considering operation and maintenance costs to ensure financial sustainability; 4. ensuring the long term reliability and security of the water and wastewater systems; and 5. performing financial evaluation including lifecycle costing.

5.2 Description of the Evaluation Process

Opportunities and constraints for each system were identified at the outset of the study and are used as a starting point for identifying conceptual servicing options. The evaluation process progresses from high-level concepts to more detailed servicing strategies and, where applicable, to detailed evaluation of individual alignments or sites. The progression from a high-level to an increasing level of detail allows for a more efficient process, as it screens out non-feasible and unfavourable servicing concepts before they are carried forward for detailed evaluation. The complete process of identifying, evaluating, and selecting a preferred servicing option is shown in Figure 3.6.

Page 33: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 29

Figure 3.6 Process of identifying, evaluating and selecting a preferred servicing strategy

Page 34: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 30

5.3 Evaluation Criteria

Detailed evaluation matrices supporting the evaluation of alternative servicing concepts, strategies, and alignments or sites are provided. Maps to accompany alternative servicing concepts, strategies, and alignments or sites are included in Appendix 3D. As described in Section 5.2, servicing strategies and appropriate alignments and sites are subject to a five-point evaluation, which includes five major areas of impact: environmental, technical, socio/cultural, financial, and legal/jurisdictional. The five-point evaluation criteria and their associated impacts are described in Table 3.6.

Table 3.6 Five-point evaluation criteria to assess strategies, alignments and sites

CRITERIA DESCRIPTION

Technical Impact

1. Describes any overall technical advantage/disadvantage to an option related to: • capacity requirements and level of service

• performance under power outage conditions

• alignments that can maximize a service area

• utilization of existing infrastructure

2. Describes difficulty of construction (construction in limited areas, crossings, protection of utilities, trees or structures)

3. Assesses whether existing infrastructure upgrades are required

4. Describes risk considerations:

• Level of security of water supply/transmission or wastewater treatment/conveyance

• Considers impact of deep sewers versus sewage pumping stations

5. Describes the ability for phasing:

• staged growth and maximizing the use of existing or planned infrastructure

• incremental extensions of infrastructure as growth progresses

• balanced infrastructure costs with staged level of growth (high-level comment)

6. Describes impact on the sizing of planned and existing infrastructure

7. Highlights trunk infrastructure that potentially should be oversized to benefit future growth

8. Comments on whether growth areas will need to be serviced by existing or new infrastructure

9. Compares relative sizing differences between alternatives

10. Describes the technical consideration required for construction:

• Highlights need for deep pipe construction, creek/highway/railway crossings, alignment changes, and potential challenges during construction

• Where applicable, comments on construction of projects that can be coordinated with road improvements or construction

Page 35: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 31

CRITERIA DESCRIPTION

11. Describes potential opportunities/constraints to servicing build out

12. Notes flexibility of servicing the mature state growth (post Places to Grow)

Environmental Impact

13. Describes the potential impacts of the option on the natural environment, proximity to existing natural features and designations including but not limited to Greenbelt, Niagara Escarpment, ESAs, ANSIs, conservation authority regulation limits, vegetation, woodlands, wildlife, aquatic resources and fisheries

14. Highlights requirements for major environmental crossings, deep sewers, development through environmental designated areas, and requirements for mitigative action

Financial Impact

15. Describes the capital cost relative to other options

16. Considers construction costs for new infrastructure and for upgrades to existing system

17. Highlights major projects that differ from other options that significantly contribute to the capital costs

18. Describes large up-front costs required for phasing of growth

19. Comments on post-construction impacts such as operation and maintenance costs and requirements, and compares to other options

Legal/Jurisdictional Impact

20. Notes any land requirement issues and agency concerns that may arise related to project alignments, land acquisition, planning permits, crossings etc.

21. Comments on compliance with Regional Guidelines and Policies

22. Describes the potential impacts related to opportunity or requirements for integrated planning, design, construction with other servicing such as bridge, road construction etc.

23. Notes if coordination with involved parties is required

Socio-Cultural Impact

24. Describes the potential impacts to residents, archaeological/heritage resources, and visual aesthetics

25. Describes any potential noise, dust, vibrations, traffic disruptions to residents and businesses during and following construction

5.4 Servicing Concepts

At a conceptual level, each system was considered in isolation with the list of opportunities, issues, and constraints in mind, both within the larger Regional context and at the localized service level. As shown in Figure 3.6, a list of servicing concepts to address existing and future servicing issues was considered

Page 36: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 32

at a high level, weighing the advantages and disadvantages of each concept. The initial, strategic concepts (red box) will be evaluated simplistically, with advantages and disadvantages listed. A score based on an overall rating of high, medium, or low was assigned to each concept based on this preliminary evaluation, where high is more favourable. Based on the scoring, concepts were either screened out or carried forward in combination for further evaluation. The concepts evaluated are listed as follows and the description and evaluation of these concepts can be found in Appendix 3D. 1. Do Nothing 2. Limit Community Growth 3. 2007 Master Plan 4. New Stream-Based or Groundwater-Based Water Treatment Plant 5. New Lake-Based Water Treatment Plant 6. Efficiency

5.5 Servicing Strategies

Combinations of the concepts carried forward formed various strategies (orange box in Figure 3.6) that are generally considered complete solutions. The descriptions of the strategies are relatively detailed and thus offer greater scope for more detailed evaluation. At this stage, each strategy is subjected to a five-point evaluation, which includes environmental, technical, socio/cultural, financial, and legal/jurisdictional impacts. Each strategy is scored based on the positive and negative aspects identified for each impact category using a rating system of high, medium and low, where high is more favourable. The strategy with the highest overall score was selected as preferred. Seven water servicing strategies were developed and evaluated with this process. The water servicing strategies are described as follows: Strategy 1 – Planned East-Central-West Boundaries:

• Build off planned 2031 infrastructure as per the 2007 Master Plan while maintaining the planned East-Central-West servicing boundary;

• Expand transmission, storage and pumping as outlined in the 2007 Master Plan;

• Add pumping and transmission capacity to match the planned East-Central-West boundary; and

• Continue to implement the Region’s water conservation program.

Strategy 2 – Hydraulic East-Central-West Boundaries:

• Build off planned 2031 infrastructure as per the 2007 Master Plan while shifting the planned East-Central-West servicing boundary to match system hydraulics;

• Expand transmission, storage and pumping as outlined in the 2007 Master Plan;

• Allow intra-zone boundaries to be defined by hydraulics within the system and adjust the planning boundaries accordingly; and

• Continue to implement the Region’s water conservation program.

Page 37: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 33

Strategy 3 – Planned/Hydraulic East-Central-West Boundaries:

• Build off planned 2031 infrastructure as per the 2007 Master Plan while shifting the planned East-Central-West servicing boundary to match system hydraulics in selected pressure zones;

• Allow servicing of some existing pressure zones to be dictated by existing hydraulics within the zone;

• Add pumping and transmission in selected pressure zones to shift the East-Central-West boundaries to closely match the planned boundary and maximize the use of existing infrastructure; and

• Continue to implement the Region’s water conservation program.

Strategy 4 – New Stream-Based Water Treatment Plant:

• Build off a modified version of the planned 2031 infrastructure as per the 2007 Master Plan and construct a new stream-based water treatment plant to service growth in the upper pressure zones;

• Provide supply to the northeast pressure zones from the new stream-based water treatment plant;

• Expand transmission, storage and pumping in the West Transmission System as per the 2007 Master Plan; and

• Potential opportunity to defer or reduce upgrades in the Central Transmission System.

Strategy 5 – New Groundwater-Based Water Treatment Plant:

• Build off a modified version of the planned 2031 infrastructure as per the 2007 Master Plan and construct a new groundwater-based water treatment plant to service growth in Brampton;

• Provide supply to the northeast pressure zones from the new groundwater-based water treatment plant;

• Expand transmission, storage and pumping in the West Transmission System as per the 2007 Master Plan; and

• Potential opportunity to defer or reduce upgrades in the Central Transmission System.

Strategy 6 – New Lake-Based Water Treatment Plant near the Shoreline:

• Build off a modified version of the planned 2031 infrastructure as per the 2007 Master Plan and construct a new lake-based water treatment plant near the Lake Ontario shoreline;

• Additional supply to the transmission and distribution system from a new lake-based water treatment plant; and

• Expand transmission, storage and pumping as per the 2007 Master Plan.

Page 38: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 34

Strategy 7 – New Lake-Based Water Treatment Plant within the Region of Peel:

• Build off a modified version of the planned 2031 infrastructure as per the 2007 Master Plan and construct a new lake-based water treatment plant within the Region of Peel;

• Additional supply to the transmission and distribution system from the new lake-based water treatment plant;

• Expand transmission, storage and pumping as outlined in the 2007 Master Plan; and

• New extended raw water intake required.

The seven strategies were evaluated using the five-point evaluation criteria and one was selected as the preferred water servicing strategy. The evaluation of water servicing strategies is shown in Appendix 3D.

5.6 Alignments and Sites

The preferred strategy was dissected into component parts, such as water mains, pumping stations and storage facilities. Where required, individual alignments and alternative facility sites were identified and, where appropriate under the Class EA process, subjected to a siting and alignment evaluation process (green box in Figure 3.6). This evaluation uses the same five-point evaluation criteria and rating system to score the alternative alignments and sites. The alignments and sites with the highest overall scores were selected as preferred.

Page 39: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 35

Figure 3.7 Alternative Water Servicing Strategy 1

Page 40: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 36

Figure 3.8 Alternative Water Servicing Strategy 2

Page 41: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 37

Figure 3.9 Alternative Water Servicing Strategy 3

Page 42: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 38

Figure 3.10 Alternative Water Servicing Strategy 4

Page 43: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 39

Figure 3.11 Alternative Water Servicing Strategy 5

Page 44: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 40

Figure 3.12 Alternative Water Servicing Strategy 6

Page 45: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 41

Figure 3.13 Alternative Water Servicing Strategy 7

Page 46: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 42

6 Preferred Water Servicing Strategy

This section summarizes the preferred Water Servicing Strategy for the Region of Peel to satisfy growth to 2031. In addition, this section includes capital costing and alignment and site evaluations for the preferred solution.

6.1 Preferred Servicing Strategy

As described in Section 5, each strategy was evaluated using the five-point evaluation criteria, which include considerations for environmental, technical, socio-cultural, financial and legal-jurisdictional factors. The strategy with the highest overall score from the five-point short list evaluation matrix was Strategy 2. Key benefits of the preferred Water Servicing Strategy include: 1. Maximizing the use of existing water transmission mains and treatment infrastructure as it builds off

existing and planned transmission and distribution infrastructure; 2. Minimizes environmental crossings for west-to-east transfers as well as reduced transmission costs

with no west-to-east transfers; 3. Does not require the construction of a new water treatment plant within the 2031 horizon; and 4. Opportunity to leverage the existing water servicing strategy with optimization of system hydraulics.

Key projects within this strategy include: 1. Streetsville, Meadowvale North and East Brampton Transmission Main twinning; 2. Pumping station upgrades at Lakeview Zones 1 and 2, Herridge Zone 2, Streetsville Zones 3 and 4,

West Brampton Zones 5 and 6, North Brampton Zones 6 and 7 and the Beckett Sproule Transfer Station;

3. New North Bolton Elevated Tank; 4. Extension of the distribution system in northwest Brampton and northeast Brampton to service new

growth areas; and 5. Extension of the distribution system in Bolton. In addition to the key capital projects, several smaller upgrades are included within the strategy to address local capacity constraints within the system. The preferred Water Servicing Strategy can be seen in Figure 3.14. Each individual project is listed with its respective estimated capital cost in Table 3.7.

Page 47: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 43

Figure 3.14 Preferred water servicing strategy for the lake-based system

Page 48: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 44

6.2 Capital Program for the Preferred Water Servicing Strategy

The five-point evaluation process considered high-level analysis of the financial impacts of each strategy to provide perspective on the capital cost implications of the major capital works associated with each strategy. The strategies were compared against each other to determine the relative sub-score. Once the preferred strategy was selected, a detailed capital program was established, based on the methodology outlined in Section 5. For the purposes of the Master Plan, a project numbering system was created for both water and wastewater projects. Each Master Plan project number is comprised of three elements, separated by a hyphen “-“:

1. Water (“W”) or Wastewater (“WW”) Identifier

2. Project Type Code • “D” –Distribution Main • “ST” –Sub-Transmission Main • “T” –Transmission Main • “P” –Pumping Station • “S” – Storage Facility (Reservoir or Elevated Tank) • “TR” – Water Treatment Plant

3. Unique, 3-Digit Project Number (e.g., “021”)

For example, the Water Master Plan project number for the Beckett Sproule Pumping Station Expansion is “W-P-064”. Depending on the size and scope of a particular project, the Capital Program has separated project components into cost categories such as environmental assessment (EA), design and construction. The capital program for the preferred Water Servicing Strategy is shown in Table 3.7.

Page 49: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 45

Table 3.7 Capital program for the preferred water servicing strategy

Master Plan ID

Component Type Name Description Year in

Service Class EA Schedule

Class EA Schedule Coverage Size/ Capacity Length (m)

Total Component Estimated Cost

(2013$)

Pipes - Transmission

W-T-111 Design Streetsville Zone 4 Discharge 900mm Streetsville Zone 4 Discharge on Erin Mills Pkwy from Thomas Street to Britannia Road (Design) 2021 B Separate Study 900 mm 1,334 $2,890,372

W-T-111 Construction Streetsville Zone 4 Discharge 900mm Streetsville Zone 4 Discharge on Erin Mills Pkwy from Thomas Street to Britannia Road (Construction) 2021 B Separate Study 900 mm 1,334 $16,679,628

W-T-126 Construction Mississauga City Centre Transmission Main Transmission Main: 1500mm Z3 from Hanlan Res and PS to MCC (Construction) 2017 C-Completed Completed 1500 mm 5,961 $97,400,000

W-T-127 Design Streetsville Zone 4 Discharge 1050mm Streetsville Zone 4 Discharge. Streetsville PS to Thomas Street (Design) 2021 B Separate Study 1050 mm 952 $2,266,512

W-T-127 Construction Streetsville Zone 4 Discharge 1050mm Streetsville Zone 4 Discharge. Streetsville PS to Thomas Street (Construction) 2021 B Separate Study 1050 mm 952 $13,079,488

W-T-128 Design Burnhamthorpe Rd Transmission Main Transmission Main: Z3 1500mm on Burnhamthorpe Rd from Hurontario St to Confederation Pkwy (Design) 2016 A+/B 2013 MP 1500 mm 1,250 $1,893,289

W-T-128 Construction Burnhamthorpe Rd Transmission Main Transmission Main: Z3 1500mm on Burnhamthorpe Rd from Hurontario St to Confederation Pkwy (Construction) 2016 A+/B 2013 MP 1500 mm 1,250 $10,925,711

W-T-128 Design Burnhamthorpe Rd Transmission Main Transmission Main: Z3 1500mm on Burnhamthorpe Rd from Cawthra Rd to Hurontario St (Design) 2016 A+/B 2013 MP 1500 mm 2,150 $5,373,699

W-T-128 Construction Burnhamthorpe Rd Transmission Main Transmission Main: Z3 1500mm on Burnhamthorpe Rd from Cawthra Rd to Hurontario St (Construction) 2016 A+/B 2013 MP 1500 mm 2,150 $31,010,301

W-T-129 Construction Hanlan Transmission Main Transmission Main: Z2 2400mm from Lakeview WTP to Hanlan PS (Construction) 2016 C-Completed Completed 2400 mm 15,584 $369,000,000

W-T-130 Construction East Brampton Transmission Main East Brampton Transmission Main: Z4 1500mm Beckett Sproule PS to East Brampton PS (Construction) 2020 C-Underway Separate Study

Underway 1500 mm 6,138 $100,079,000

W-T-131 Design Streetsville Transmission Main Twinning Transmission Main: Z2 2100mm extension from Herridge Dr to Streetsville (Design) 2030 C Separate Study 2100 mm 6,614 $19,936,000

W-T-131 Construction Streetsville Transmission Main Twinning Transmission Main: Z2 2100mm extension from Herridge Dr to Streetsville (Construction) 2030 C Separate Study 2100 mm 6,614 $127,889,000

W-T-131 EA Streetsville Transmission Main Twinning Transmission Main: Z2 2100mm extension from Herridge Dr to Streetsville (EA) 2030 C Separate Study 2100 mm 6,614 $2,226,000

W-T-132 Construction Victoria Transmission Main Transmission Main: Z6 900mm from North Brampton PS to Victoria Reservoir (Construction) 2016 C-Completed Completed 900 mm 8,745 $29,773,000

W-T-133 Construction Victoria Transmission Main Transmission Main: Z6 1200mm from Victoria Reservoir back to Z6 Local (Construction) 2017 C-Completed Completed 1200 mm 8,472 $25,612,800

W-T-134 Construction Mayfield Rd Transmission Main Transmission Main: Z6 1050mm on Mayfield Rd from Alloa PS to Creditview Rd (Construction) 2014 A+ 2013 MP 1050 mm 674 $2,306,000

W-T-135 Design Meadowvale North Twinning Transmission Main: Z3 1050mm from Streetsville PS to Meadowvale North PS (Design) 2022 C Separate Study 1050 mm 8,000 $16,895,899

W-T-135 Construction Meadowvale North Twinning Transmission Main: Z3 1050mm from Streetsville PS to Meadowvale North PS (Construction) 2022 C Separate Study 1050 mm 8,000 $97,502,101

Pipes - Distribution

W-D-001 Construction Northwest Brampton Distribution Main Distribution Main: Z5 400mm on Future Rd from Winston Churchill Blvd to Heritage Rd (Construction) 2019 A+ 2013 MP 400 mm 1,437 $3,009,000

W-D-002 Design Dougall Ave Distribution Main Distribution Main: Z7 400 mm on Dougall Ave (Mayfield West) from Hurontario St to Kennedy Rd (Design) 2014 A+ 2013 MP 400 mm 1,425 $490,000

W-D-002 Construction Dougall Ave Distribution Main Distribution Main: Z7 400 mm on Dougall Ave (Mayfield West) from Hurontario St to Kennedy Rd (Construction) 2014 A+ 2013 MP 400 mm 1,425 $2,828,000

W-D-003 Design Bovaird Dr Distribution Main Distribution Main: Z6 400mm on Bovaird Dr, west of Heritage Rd (Design) 2023 A+ 2013 MP 400 mm 689 $218,000

W-D-003 Construction Bovaird Dr Distribution Main Distribution Main: Z6 400mm on Bovaird Dr, west of Heritage Rd (Contruction) 2023 A+ 2013 MP 400 mm 689 $1,258,000

W-D-004 Design Sandalwood Pkwy Distribution Main Distribution Main: Z6 400mm on Sandalwood Pkwy from Heritage Rd to Mississauga Rd (Design) 2021 A+ 2013 MP 400 mm 1,356 $431,000

Page 50: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 46

Master Plan ID

Component Type Name Description Year in

Service Class EA Schedule

Class EA Schedule Coverage Size/ Capacity Length (m)

Total Component Estimated Cost

(2013$)

W-D-004 Construction Sandalwood Pkwy Distribution Main Distribution Main: Z6 400mm on Sandalwood Pkwy from Heritage Rd to Mississauga Rd (Construction) 2022 A+ 2013 MP 400 mm 1,356 $2,487,000

W-D-005 Design Future Sandalwood Pkwy Distribution Main Distribution Main: Z6 400mm E-W Main on new road (North of Bovaird Dr, West of Heritage Rd) (Design) 2021 A+ 2013 MP 400 mm 730 $228,000

W-D-005 Construction Future Sandalwood Pkwy Distribution Main Distribution Main: Z6 400mm E-W Main on new road (North of Bovaird Dr, West of Heritage Rd) (Construction) 2022 A+ 2013 MP 400 mm 730 $1,313,000

W-D-006 Design Wanless Dr Distribution Main Distribution Main: Z6 400mm on Wanless Dr from Mississauga Rd to Creditview Rd (Design) 2013 A+ 2013 MP 400 mm 1,121 $298,000

W-D-006 Construction Wanless Dr Distribution Main Distribution Main: Z6 400mm on Wanless Dr from Mississauga Rd to Creditview Rd (Construction) 2013 A+ 2013 MP 400 mm 1,121 $1,716,000

W-D-007 Design Wanless Dr Distribution Main Distribution Main: Z6 400mm on Wanless Dr from Mississauga Rd to Heritage Rd (Design) 2025 A+ 2013 MP 400 mm 1,378 $400,000

W-D-007 Construction Wanless Dr Distribution Main Distribution Main: Z6 400mm on Wanless Dr from Mississauga Rd to Heritage Rd (Construction) 2025 A+ 2013 MP 400 mm 1,378 $2,310,000

W-D-008 Design Wanless Dr Distribution Main Distribution Main: Z6 400mm on Wanless Dr from Winston Churchill Blvd to Heritage Rd (Design) 2026 A+ 2013 MP 400 mm 1,475 $423,000

W-D-008 Construction Wanless Dr Distribution Main Distribution Main: Z6 400mm on Wanless Dr from Winston Churchill Blvd to Heritage Rd (Construction) 2026 A+ 2013 MP 400 mm 1,475 $2,441,000

W-D-009 Design Mayfield Rd Distribution Main Distribution Main: Z6 400mm on Mayfield Rd from Winston Churchill Blvd to Heritage Rd (Design) 2031 A+ 2013 MP 400 mm 1,436 $378,000

W-D-009 Construction Mayfield Rd Distribution Main Distribution Main: Z6 400mm on Mayfield Rd from Winston Churchill Blvd to Heritage Rd (Construction) 2031 A+ 2013 MP 400 mm 1,436 $2,182,000

W-D-010 Construction Countryside Dr Distribution Main Distribution Main: Z5 400mm on Countryside Dr from Clarkway Dr to Coleraine Dr (Construction) 2018 A+ 2013 MP 400 mm 1,383 $2,317,000

W-D-010 Design Countryside Dr Distribution Main Distribution Main: Z5 400mm on Countryside Dr from Clarkway Dr to Coleraine Dr (Design) 2018 A+ 2013 MP 400 mm 1,383 $401,000

W-D-011 Construction Clarkway Dr Distribution Main Distribution Main: Z5 400mm on Clarkway Dr from Countryside Dr to Mayfield Rd (Construction) 2030 A+ 2013 MP 400 mm 1,170 $1,782,000

W-D-011 Design Clarkway Dr Distribution Main Distribution Main: Z5 400mm on Clarkway Dr from Countryside Dr to Mayfield Rd (Design) 2030 A+ 2013 MP 400 mm 1,170 $309,000

W-D-012 Construction Northeast Brampton Distribution Main Distribution Main: Z5 400mm on future road from The Gore Rd to Clarkway Dr (Construction) 2020 A+ 2013 MP 400 mm 1,365 $2,499,000

W-D-013 Construction Northeast Brampton Distribution Main Distribution Main: Z5 400mm on Future Road from Clarkway Dr to Coleraine Dr (Construction) 2020 A+ 2013 MP 400 mm 1,452 $2,204,000

W-D-014 Construction Embleton Rd Distribution Main Distribution Main: Z5 400mm on Embleton Rd from Winston Churchill Blvd to Heritage Rd (Construction) 2021 A+ 2013 MP 400 mm 1,480 $2,448,000

W-D-015 Design Winston Churchill Blvd Distribution Main Distribution Main: 400mm on Winston Churchill Blvd from Embleton Rd to 1,700 m north (Design) 2025 A+ 2013 MP 400 mm 1,781 $501,000

W-D-015 Construction Winston Churchill Blvd Distribution Main Distribution Main: 400mm on Winston Churchill Blvd from Embleton Rd to 1,700 m north (Construction) 2025 A+ 2013 MP 400 mm 1,781 $2,894,000

W-D-016 Design Chinguacousy Rd Distribution Main Distribution Main: Z6 400mm on Chinguacousy Rd from Mayfield Rd to Wanless Dr (Design) 2015 A+ 2013 MP 400 mm 1,247 $327,000

W-D-016 Construction Chinguacousy Rd Distribution Main Distribution Main: Z6 400mm on Chinguacousy Rd from Mayfield Rd to Wanless Dr (Construction) 2015 A+ 2013 MP 400 mm 1,247 $1,886,000

W-D-017 Construction Torbram Rd Distribution Main Distribution Main: 400mm Z6 on Torbram Rd from Countryside Dr to Mayfield Rd (Construction) 2015 A+ 2013 MP 400 mm 1,266 $1,912,000

W-D-018 Construction Northwest Brampton Distribution Main Distribution Main: Z7 400mm on N-S Spine Road from Mayfield Rd to Wanless Dr (Construction) 2015 A+ 2013 MP 400 mm 916 $1,605,000

W-D-019 Construction Northwest Brampton Distribution Main Distribution Main: Z6 400mm on Future Road from Sandalwood Pkwy to James Potter Rd (Construction) 2012 A+ 2013 MP 400 mm 1,149 $1,960,000

W-D-020 Construction North Brampton Distribution Main Distribution Main: Z7 400mm on Future Road (North of Mayfield) from Heart Lake Rd to Dixie Rd v 2012 A+ 2013 MP 400 mm 1,392 $2,122,000

W-D-021 Construction Heart Lake Rd Distribution Main Distribution Main: Z7 400mm on Heart Lake Rd between Mayfield Rd and Old School Rd (Construction) 2015 A+ 2013 MP 400 mm 3,125 $5,885,000

W-D-022 Design Northwest Brampton Distribution Main Distribution Main: Z6 400mm on N-S Spine Road from Sandalwood Pkwy to Wanless Dr (Design) 2013 A+ 2013 MP 400 mm 1,175 $310,000

Page 51: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 47

Master Plan ID

Component Type Name Description Year in

Service Class EA Schedule

Class EA Schedule Coverage Size/ Capacity Length (m)

Total Component Estimated Cost

(2013$)

W-D-022 Construction Northwest Brampton Distribution Main Distribution Main: Z6 400mm on N-S Spine Road from Sandalwood Pkwy to Wanless Dr (Construction) 2013 A+ 2013 MP 400 mm 1,175 $1,789,000

W-D-023 Design Clarkway Dr Distribution Main Distribution Main: 400mm Z5 on Clarkway Dr from Castlemore Rd to Countryside Dr (Design) 2018 A+ 2013 MP 400 mm 3,118 $949,000

W-D-023 Construction Clarkway Dr Distribution Main Distribution Main: 400mm Z5 on Clarkway Dr from Castlemore Rd to Countryside Dr (Construction) 2022 A+ 2013 MP 400 mm 3,118 $5,480,000

W-D-024 Construction N-S Spine Rd Distribution Main Distribution Main: Z7 400mm on N-S Spine Road from Mayfield Rd to Wanless Dr (Construction) 2015 A+ 2013 MP 400 mm 1,034 $1,558,000

W-D-025 Construction North Brampton Distribution Main Distribution Main: Z5 400mm on Future Street - West of Bramalea Rd (Countryside Villages) (Construction) 2015 A+ 2013 MP 400 mm 652 $1,415,000

W-D-026 Construction North Brampton Distribution Main Distribution Main: Z5 400mm on Future Street - Bramalea Rd to Torbram Rd (Countryside Villages) (Construction) 2017 A+ 2013 MP 400 mm 864 $1,329,000

W-D-027 Design Highway 50 Distribution Main Distribution Main: Z5 400mm on Highway 50 from Castlemore Rd to Coleraine Dr (Design) 2018 A+ 2013 MP 400 mm 1,990 $558,000

W-D-027 Construction Highway 50 Distribution Main Distribution Main: Z5 400mm on Highway 50 from Castlemore Rd to Coleraine Dr (Construction) 2018 A+ 2013 MP 400 mm 1,990 $3,217,000

W-D-028 Design Queen Street East Distribution Main Distribution Main: Z5 400mm on Queen Street East from Kennedy Rd to Hwy 410 2023 A+ 2013 MP 400 mm 1,216 $448,000

W-D-028 Construction Queen Street East Distribution Main Distribution Main: Z5 400mm on Queen Street East from Kennedy Rd to Hwy 410 2023 A+ 2013 MP 400 mm 1,216 $2,583,000

W-D-029 Design Derry Rd Distribution Main Distribution Main: Z5 400mm on Derry Road West from Ninth Line to Tenth Line (Design) 2023 A+ 2013 MP 400 mm 1,370 $542,000

W-D-029 Construction Derry Rd Distribution Main Distribution Main: Z5 400mm on Derry Road West from Ninth Line to Tenth Line (Construction) 2023 A+ 2013 MP 400 mm 1,370 $3,130,000

W-D-030 Design Ninth Line Distribution Main Distribution Main: Z5 400mm on Ninth Line from Derry Rd to Terragar Blvd (Design) 2023 A+ 2013 MP 400 mm 881 $406,000

W-D-030 Construction Ninth Line Distribution Main Distribution Main: Z5 400mm on Ninth Line from Derry Rd to Terragar Blvd (Construction) 2023 A+ 2013 MP 400 mm 881 $2,341,000

W-D-031 Design Eastern Ave Distribution Main Distribution Main: Z5 400mm on Eastern Ave from Hansen Rd to Rutherford Rd (Clark Extension) (Design) 2025 A+ 2013 MP 400 mm 431 $115,000

W-D-031 Construction Eastern Ave Distribution Main Distribution Main: Z5 400mm on Eastern Ave from Hansen Rd to Rutherford Rd (Clark Extension) (Construction) 2025 A+ 2013 MP 400 mm 431 $664,000

W-D-032 Design Hurontario St Distribution Main Distribution Main: Z7 400mm on Hurontario St from Valleywood Blvd to Dougall Ave (Design) 2016 A+ 2013 MP 400 mm 1,203 $352,000

W-D-032 Construction Hurontario St Distribution Main Distribution Main: Z7 400mm on Hurontario St from Valleywood Blvd to Dougall Ave (Construction) 2016 A+ 2013 MP 400 mm 1,203 $2,033,000

W-D-033 Design Hurontario St Distribution Main Distribution Main: Z7 400mm on Hurontario St from Mayfield Rd to Valleywood Blvd (Design) 2019 A+ 2013 MP 400 mm 999 $262,000

W-D-033 Construction Hurontario St Distribution Main Distribution Main: Z7 400mm on Hurontario St from Mayfield Rd to Valleywood Blvd (Construction) 2019 A+ 2013 MP 400 mm 999 $1,511,000

W-D-034 Construction Northwest Brampton Distribution Main Distribution Main: Z7 400mm on Road (North of Mayfield) from Hurontario St to McLaughlin Rd (Mayfield West Phase 2) (Construction) 2023 A+ 2013 MP 400 mm 1,427 $2,624,000

W-D-035 Construction Northwest Brampton Distribution Main Distribution Main: Z7 400mm on Road (North of Mayfield) from Chinguacousy Rd to McLaughlin Rd (Mayfield West Phase 2) (Construction) 2025 A+ 2013 MP 400 mm 1,358 $2,077,000

W-D-036 Design Chinguacousy Rd Distribution Main Distribution Main: Z7 400mm on Chinguacousy Rd, North of Mayfield Rd (Design) 2025 A+ 2013 MP 400 mm 951 $250,000

W-D-036 Construction Chinguacousy Rd Distribution Main Distribution Main: Z7 400mm on Chinguacousy Rd, North of Mayfield Rd (Construction) 2025 A+ 2013 MP 400 mm 951 $1,446,000

W-D-037 Design McVean Distribution Main Distribution Main: 400mm Z5 on McVean Dr from Countryside Dr to Mayfield Rd (Design) 2016 A+ 2013 MP 400 mm 1,235 $325,000

W-D-037 Construction McVean Distribution Main Distribution Main: 400mm Z5 on McVean Dr from Countryside Dr to Mayfield Rd (Construction) 2016 A+ 2013 MP 400 mm 1,235 $1,870,000

W-D-038 Design Coleraine Dr Distribution Main Distribution Main: 400mm Z5 on Coleraine Dr from Albion Vaughan Rd to Countryside Dr (Design) 2031 A+ 2013 MP 400 mm 1,829 $477,000

W-D-038 Construction Coleraine Dr Distribution Main Distribution Main: 400mm Z5 on Coleraine Dr from Albion Vaughan Rd to Countryside Dr (Construction) 2031 A+ 2013 MP 400 mm 1,829 $2,753,000

Page 52: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 48

Master Plan ID

Component Type Name Description Year in

Service Class EA Schedule

Class EA Schedule Coverage Size/ Capacity Length (m)

Total Component Estimated Cost

(2013$)

W-D-039 Design Coleraine Dr Distribution Main Distribution Main: 400mm Z5 on Coleraine Dr from Countryside Dr to Mayfield Rd (Design) 2031 A+ 2013 MP 400 mm 1,245 $327,000

W-D-039 Construction Coleraine Dr Distribution Main Distribution Main: 400mm Z5 on Coleraine Dr from Countryside Dr to Mayfield Rd (Construction) 2031 A+ 2013 MP 400 mm 1,245 $1,883,000

W-D-040 Design Winston Churchill Blvd Distribution Main Distribution Main: Z6 400mm on Winston Churchill Blvd from Wanless Dr to Mayfield Rd (Design) 2031 A+ 2013 MP 400 mm 1,204 $317,000

W-D-040 Construction Winston Churchill Blvd Distribution Main Distribution Main: Z6 400mm on Winston Churchill Blvd from Wanless Dr to Mayfield Rd (Construction) 2031 A+ 2013 MP 400 mm 1,204 $1,828,000

W-D-041 Design Northwest Brampton Distribution Main Distribution Main: Z6 400mm on Future Road North of Bovaird Dr and West of Heritage Rd (Design) 2031 A+ 2013 MP 400 mm 1,303 $376,000

W-D-041 Construction Northwest Brampton Distribution Main Distribution Main: Z6 400mm on Future Road North of Bovaird Dr and West of Heritage Rd (Construction) 2031 A+ 2013 MP 400 mm 1,303 $2,168,000

W-D-141 Design Hurontario St Twinning Distribution Main: Z4 400mm Twinning on Hurontario St from Bristol Rd to Eglinton Ave (Design) 2021 A+ 2013 MP 400 mm 1,224 $608,000

W-D-141 Construction Hurontario St Twinning Distribution Main: Z4 400mm Twinning on Hurontario St from Bristol Rd to Eglinton Ave (Construction) 2021 A+ 2013 MP 400 mm 1,224 $3,506,000

W-D-043 Design Eglinton Ave Distribution Main Distribution Main: Z4 400mm on Eglinton Ave from Glen Erin Dr to Winston Churchill Blvd (Design) 2015 A+ 2013 MP 400 mm 675 $337,000

W-D-043 Construction Eglinton Ave Distribution Main Distribution Main: Z4 400mm on Eglinton Ave from Glen Erin Dr to Winston Churchill Blvd (Construction) 2015 A+ 2013 MP 400 mm 675 $1,944,000

W-D-044 Design Webb Dr Distribution Main Distribution Main: Z4 400mm on Webb Dr from City Centre Dr to Duke of York Blvd (Design) 2017 A+ 2013 MP 400 mm 739 $367,000

W-D-044 Construction Webb Dr Distribution Main Distribution Main: Z4 400mm on Webb Dr from City Centre Dr to Duke of York Blvd (Construction) 2017 A+ 2013 MP 400 mm 739 $2,116,000

W-D-045 Design Webb Dr Distribution Main Distribution Main: Z4 400mm on Webb Dr from Duke of York Blvd to Grand Park Dr (Design) 2017 A+ 2013 MP 400 mm 949 $472,000

W-D-045 Construction Webb Dr Distribution Main Distribution Main: Z4 400mm on Webb Dr from Duke of York Blvd to Grand Park Dr (Construction) 2017 A+ 2013 MP 400 mm 949 $2,724,000

W-D-046 Design Grand Park Dr Distribution Main Distribution Main: Z4 400mm on Grand Park Dr from Burnhamthorpe Rd to Webb Dr (Design) 2017 A+ 2013 MP 400 mm 194 $105,000

W-D-046 Construction Grand Park Dr Distribution Main Distribution Main: Z4 400mm on Grand Park Dr from Burnhamthorpe Rd to Webb Dr (Construction) 2017 A+ 2013 MP 400 mm 194 $605,000

W-D-047 Design Burnhamthorpe Rd Distribution Main Distribution Main: Z4 400mm on Burnhamthorpe Rd from Confederation Pkwy to Grand Park Dr (Design) 2017 A+ 2013 MP 400 mm 506 $258,000

W-D-047 Construction Burnhamthorpe Rd Distribution Main Distribution Main: Z4 400mm on Burnhamthorpe Rd from Confederation Pkwy to Grand Park Dr (Design) 2017 A+ 2013 MP 400 mm 506 $1,488,000

W-D-048 Design Hurontario St Twinning Distribution Main: Z4 400mm Twinning on Hurontario St from Britannia Rd to Matheson Blvd (Design) 2021 A+ 2013 MP 400 mm 1,110 $555,000

W-D-048 Construction Hurontario St Twinning Distribution Main: Z4 400mm Twinning on Hurontario St from Britannia Rd to Matheson Blvd (Construction) 2021 A+ 2013 MP 400 mm 1,110 $3,199,000

W-D-049 Design Mayfield Rd Distribution Main Distribution Main: Z7 400mm on Mississauga Rd between Wanless Dr and Mayfield Rd (Design) 2014 A+ 2013 MP 400 mm 755 $205,000

W-D-049 Construction Mayfield Rd Distribution Main Distribution Main: Z7 400mm on Mississauga Rd between Wanless Dr and Mayfield Rd (Construction) 2014 A+ 2013 MP 400 mm 755 $1,182,000

W-D-050 Design E-W Spine Rd Distribution Main Distribution Main: Z7 400mm on E-W Spine Road between N-S Spine Roads (North of Wanless Dr) (Design) 2015 A+ 2013 MP 400 mm 859 $265,000

W-D-050 Construction E-W Spine Rd Distribution Main Distribution Main: Z7 400mm on E-W Spine Road between N-S Spine Roads (North of Wanless Dr) (Construction) 2015 A+ 2013 MP 400 mm 859 $1,528,000

W-D-051 Design Mayfield Rd Distribution Main Distribution Main: Z7 400mm on Mayfield Rd from Winston Churchill Blvd to Heritage Rd (Design) 2016 A+ 2013 MP 400 mm 1,458 $553,705

W-D-051 Construction Mayfield Rd Distribution Main Distribution Main: Z7 400mm on Mayfield Rd from Winston Churchill Blvd to Heritage Rd (Construction) 2016 A+ 2013 MP 400 mm 1,458 $3,195,295

W-D-052 Design Mayfield Rd Distribution Main Distribution Main: Z7 400mm on Mayfield Rd from Heritage Rd to Mississauga Rd (Design) 2026 A+ 2013 MP 600 mm 1,383 $712,919

W-D-052 Construction Mayfield Rd Distribution Main Distribution Main: Z7 400mm on Mayfield Rd from Heritage Rd to Mississauga Rd (Construction) 2026 A+ 2013 MP 600 mm 1,383 $4,114,081

Page 53: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 49

Master Plan ID

Component Type Name Description Year in

Service Class EA Schedule

Class EA Schedule Coverage Size/ Capacity Length (m)

Total Component Estimated Cost

(2013$)

W-D-060 Design Intensification Upgrades Additional Intensification Upgrades. Local/Sub-trunk watermain replacements/upgrades (Design) 2016 A+ 2013 MP - $15,665,000

W-ST-116 Design Mayfield Rd Sub-Transmission Main Sub-Transmission Main: Z6 750mm on Mayfield Rd from Chinguacousy Rd to Van Kirk Dr (Design) 2013 A+ 2013 MP 750 mm 1,760 $730,000

W-ST-116 Construction Mayfield Rd Sub-Transmission Main Sub-Transmission Main: Z6 750mm on Mayfield Rd from Chinguacousy Rd to Van Kirk Dr (Construction) 2013 A+ 2013 MP 750 mm 1,760 $4,213,000

W-ST-074 Design Creditview Sub-Transmission Main Sub-Transmission Main: Z6 750mm on Creditview Rd from Wanless Dr to Mayfield Rd (Design) 2013 A+ 2013 MP 750 mm 926 $398,000

W-ST-074 Construction Creditview Sub-Transmission Main Sub-Transmission Main: Z6 750mm on Creditview Rd from Wanless Dr to Mayfield Rd (Construction) 2013 A+ 2013 MP 750 mm 926 $2,297,000

W-ST-075 Design Bovaird Dr Sub-Transmission Main Sub-Transmission Main: Z6 750mm on Bovaird Dr from Mississauga Rd to Heritage Rd (Design) 2019 A+ 2013 MP 750 mm 1,396 $704,000

W-ST-075 Construction Bovaird Dr Sub-Transmission Main Sub-Transmission Main: Z6 750mm on Bovaird Dr from Mississauga Rd to Heritage Rd (Construction) 2019 A+ 2013 MP 750 mm 1,396 $4,061,000

W-ST-076 Design Future Extension of Sandalwood Pkwy Sub-Transmission

Sub-Transmission: Z6 600mm on Future Extension of Sandalwood Parkway from Creditview Rd to Mississauga Rd (Design) 2023 A+ 2013 MP 600 mm 1,357 $478,000

W-ST-076 Construction Future Extension of Sandalwood Pkwy Sub-Transmission

Sub-Transmission: Z6 600mm on Future Extension of Sandalwood Parkway from Creditview Rd to Mississauga Rd (Construction) 2023 A+ 2013 MP 600 mm 1,357 $2,758,000

W-ST-077 Design Heritage Rd Sub-Transmission Main Sub-Transmission Main: Z6 600mm on Heritage Rd North of Bovaird Dr (Design) 2021 A+ 2013 MP 600 mm 1,300 $459,000

W-ST-077 Construction Heritage Rd Sub-Transmission Main Sub-Transmission Main: Z6 600mm on Heritage Rd North of Bovaird Dr (Construction) 2021 A+ 2013 MP 600 mm 1,300 $2,650,000

W-ST-078 Design Heritage Rd Sub-Transmission Main Sub-Transmission Main: Z6 600mm on Heritage Rd from Sandalwood Pkwy to Wanless Dr (Design) 2024 A+ 2013 MP 600 mm 1,138 $457,000

W-ST-078 Construction Heritage Rd Sub-Transmission Main Sub-Transmission Main: Z6 600mm on Heritage Rd from Sandalwood Pkwy to Wanless Dr (Construction) 2024 A+ 2013 MP 600 mm 1,138 $2,635,000

W-ST-079 Construction Mayfield Rd Sub-Transmission Main Sub-Transmission Main: Z6 900mm on Mayfield Rd from Alloa PS to Mississauga Rd (Construction) 2014 A+ 2013 MP 900 mm 1,051 $3,016,000

W-ST-080 Design Mayfield Rd Sub-Transmission Main Sub-Transmission Main: Z6 750mm on Mayfield Rd from Heritage Rd to Mississauga Rd (Design) 2026 A+ 2013 MP 750 mm 1,368 $566,000

W-ST-080 Construction Mayfield Rd Sub-Transmission Main Sub-Transmission Main: Z6 750mm on Mayfield Rd from Heritage Rd to Mississauga Rd (Construction) 2026 A+ 2013 MP 750 mm 1,368 $3,265,000

W-ST-081 Construction Mississauga Rd Sub-Transmission Main Sub-Transmission Main: Z6 600mm on Mississauga Rd from Sandalwood Pkwy to Wanless Dr (Construction) 2013 A+ 2013 MP 600 mm 1,170 $2,405,000

W-ST-082 Construction Mississauga Rd Sub-Transmission Main Sub-Transmission Main: Z6 600mm on Mississauga Rd from Wanless Dr to Mayfield Rd (Construction) 2013 A+ 2013 MP 600 mm 1,245 $2,547,000

W-ST-083 Design Heritage Rd Sub-Transmission Main Sub-Transmission Main: Z6 750mm on Heritage Rd from Wanless Dr to Mayfield Rd (Design) 2025 A+ 2013 MP 750 mm 1,224 $511,000

W-ST-083 Construction Heritage Rd Sub-Transmission Main Sub-Transmission Main: Z6 750mm on Heritage Rd from Wanless Dr to Mayfield Rd (Construction) 2025 A+ 2013 MP 750 mm 1,224 $2,949,000

W-ST-084 Construction Mayfield Rd Sub-Transmission Main Sub-Transmission Main: 600mm Z5 on Mayfield Rd from Goreway Dr to McVean Dr (Construction) 2017 A+ 2013 MP 600 mm 1,399 $3,417,000

W-ST-085 Construction Mayfield Rd Sub-Transmission Main Sub-Transmission Main: 600mm Z5 on Mayfield Rd from McVean Dr to The Gore Rd (Construction) 2017 A+ 2013 MP 600 mm 1,363 $2,769,000

W-ST-086 Construction Mayfield Rd Sub-Transmission Main Sub-Transmission Main: 600mm Z5 on Mayfield Rd from The Gore Rd to Clarkway Dr (Construction) 2020 A+ 2013 MP 600 mm 1,420 $4,499,000

W-ST-086 Design Mayfield Rd Sub-Transmission Main Sub-Transmission Main: 600mm Z5 on Mayfield Rd from The Gore Rd to Clarkway Dr (Design) 2020 A+ 2013 MP 600 mm 1,420 $779,000

W-ST-087 Construction Mayfield Rd Sub-Transmission Main Sub-Transmission Main: 600mm Z5 on Mayfield Rd from Clarkway Dr to Coleraine Dr (Construction) 2020 A+ 2013 MP 600 mm 1,395 $3,120,000

W-ST-087 Design Mayfield Rd Sub-Transmission Main Sub-Transmission Main: 600mm Z5 on Mayfield Rd from Clarkway Dr to Coleraine Dr (Design) 2020 A+ 2013 MP 600 mm 1,395 $540,000

W-ST-088 Construction Williams Pkwy Sub-Transmission Main Sub-Transmission Main: Z5 600mm on Williams Parkway from Heritage Rd to Mississauga Rd (Construction) 2020 A+ 2013 MP 600 mm 1,140 $2,638,000

W-ST-089 Design Heritage Rd Sub-Transmission Main Sub-Transmission Main: Z5 600mm on Heritage Rd from Embleton Rd to Williams Parkway (Design) 2020 A+ 2013 MP 600 mm 2,276 $1,033,000

Page 54: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 50

Master Plan ID

Component Type Name Description Year in

Service Class EA Schedule

Class EA Schedule Coverage Size/ Capacity Length (m)

Total Component Estimated Cost

(2013$)

W-ST-089 Construction Heritage Rd Sub-Transmission Main Sub-Transmission Main: Z5 600mm on Heritage Rd from Embleton Rd to Williams Parkway (Construction) 2020 A+ 2013 MP 600 mm 2,276 $5,956,000

W-ST-124 Design Coleraine Dr Sub-Transmission Main Sub-Transmission Main: Z6 600mm on Coleraine Dr from Bolton Elevated tank to Mayfield Rd (Design) 2019 A+ 2013 MP 600 mm 4,482 $1,557,000

W-ST-124 Construction Coleraine Dr Sub-Transmission Main Sub-Transmission Main: Z6 600mm on Coleraine Dr from Bolton Elevated tank to Mayfield Rd (Construction) 2019 A+ 2013 MP 600 mm 4,482 $8,986,000

W-ST-090 Construction Heritage Rd Sub-Transmission Main Sub-Transmission Main: Z6 600mm on Heritage Rd South of Sandalwood Pkwy (Construction) 2021 A+ 2013 MP 600 mm 685 $2,324,000

W-ST-090 Design Heritage Rd Sub-Transmission Main Sub-Transmission Main: Z6 600mm on Heritage Rd South of Sandalwood Pkwy (Design) 2021 A+ 2013 MP 600 mm 685 $402,000

W-ST-117 Construction Mayfield Rd Sub-Transmission Main Sub-Transmission Main: Z6 750mm on Mayfield Rd from Creditview Rd to Chinguacousy Rd (Construction) 2013 A+ 2013 MP 750 mm 1,386 $3,304,000

W-ST-091 Design Countryside Dr Sub-Transmission Main Sub-Transmission Main: 750mm Z5 on Countryside Dr from Goreway Dr to McVean Dr (Design) 2013 A+ 2013 MP 750 mm 1,411 $773,000

W-ST-091 Construction Countryside Dr Sub-Transmission Main Sub-Transmission Main: 750mm Z5 on Countryside Dr from Goreway Dr to McVean Dr (Construction) 2013 A+ 2013 MP 750 mm 1,411 $4,461,000

W-ST-092 Design Countryside Dr Sub-Transmission Main Sub-Transmission Main: 750mm Z5 on Countryside Dr from McVean Dr to The Gore Rd (Design) 2013 A+ 2013 MP 750 mm 1,349 $622,000

W-ST-092 Construction Countryside Dr Sub-Transmission Main Sub-Transmission Main: 750mm Z5 on Countryside Dr from McVean Dr to The Gore Rd (Construction) 2013 A+ 2013 MP 750 mm 1,349 $3,590,000

W-ST-093 EA Countryside Dr Sub-Transmission Main Sub-Transmission Main: 750mm Z5 on Countryside Dr from The Gore Rd to Clarkway Dr (EA) 2018 A+ 2013 MP 750 mm 1,389 $70,000

W-ST-093 Design Countryside Dr Sub-Transmission Main Sub-Transmission Main: 750mm Z5 on Countryside Dr from The Gore Rd to Clarkway Dr (Design) 2018 A+ 2013 MP 750 mm 1,389 $631,000

W-ST-093 Construction Countryside Dr Sub-Transmission Main Sub-Transmission Main: 750mm Z5 on Countryside Dr from The Gore Rd to Clarkway Dr (Construction) 2018 A+ 2013 MP 750 mm 1,389 $4,045,000

W-ST-102 Design Lakeshore Rd Sub-Transmission Main Sub-Transmission Main: Z1 on Lakeshore Rd from existing 400mm wm on Wesley Ave to existing 600mm wm at Enola Ave (Design) 2021 A+ 2013 MP 600 mm 2,465 $2,828,000

W-ST-102 Construction Lakeshore Rd Sub-Transmission Main Sub-Transmission Main: Z1 on Lakeshore Rd from existing 400mm wm on Wesley Ave to existing 600mm wm at Enola Ave (Construction) 2021 A+ 2013 MP 600 mm 2,465 $16,317,000

W-ST-118 Construction Williams Pkwy Sub-Transmission Main Sub-Transmission Main: 900mm Z5 on WIlliams Parkway: Section B: McLaughlin Rd to Kennedy Rd (Construction) 2017 C-Underway Separate Study

Underway 900 mm 2,796 $14,653,000

W-ST-118 Design Williams Pkwy Sub-Transmission Main Sub-Transmission Main: 900mm Z5 on WIlliams Parkway: Section B: McLaughlin Rd to Kennedy Rd (Design) 2017 C-Underway Separate Study

Underway 900 mm 2,796 $2,539,000

W-ST-119 Construction Williams Pkwy Sub-Transmission Main Sub-Transmission Main: 900mm Z5 on WIlliams Parkway: Section C: Kennedy Rd to E-B PS (Construction) 2019 C-Underway Separate Study

Underway 900 mm 3,180 $11,876,000

W-ST-119 Design Williams Pkwy Sub-Transmission Main Sub-Transmission Main: 900mm Z5 on WIlliams Parkway: Section C: Kennedy Rd to E-B PS (Design) 2019 C-Underway Separate Study

Underway 900 mm 3,180 $2,058,000

W-ST-120 Construction Heart Lake Rd Sub-Transmission Main Sub-Transmission Main: 750mm Z5 on Heart Lake Rd, Clark Blvd and Dixie Rd from Beckett Sproule PS to E-B PS (Construction) 2019 C-Underway Separate Study

Underway 750 mm 6,071 $16,233,000

W-ST-120 Design Heart Lake Rd Sub-Transmission Main Sub-Transmission Main: 750mm Z5 on Heart Lake Rd, Clark Blvd and Dixie Rd from Beckett Sproule PS to E-B PS (Design) 2019 C-Underway Separate Study

Underway 750 mm 6,071 $2,814,000

W-ST-121 Construction Williams Pkwy Sub-Transmission Main Sub-Transmission Main: 750mm Z5 on WIlliams Parkway: Section A: West Brampton PS to McLaughlin Rd (Construction) 2024 C-Underway Separate Study

Underway 900 mm 5,000 $19,374,000

W-ST-121 Design Williams Pkwy Sub-Transmission Main Sub-Transmission Main: 750mm Z5 on WIlliams Parkway: Section A: West Brampton PS to McLaughlin Rd (Design) 2024 C-Underway Separate Study

Underway 900 mm 5,000 $3,357,000

W-ST-094 Design Main Street Sub-Transmission Main Sub-Transmission Main: Z5 600mm on Main Street from Wellington St to Williams Parkway 2024 A+ 2013 MP 600 mm 2,201 $1,497,000

W-ST-094 Construction Main Street Sub-Transmission Main Sub-Transmission Main: Z5 600mm on Main Street from Wellington St to Williams Parkway 2024 A+ 2013 MP 600 mm 2,201 $8,640,000

W-ST-095 Design Thomas Street Sub-Transmission Main Sub-Transmission Main: Z4 600mm on Thomas Street from Winston Churchill Blvd to Ninth Line (Design) 2022 A+ 2013 MP 600 mm 2,093 $1,038,000

W-ST-095 Construction Thomas Street Sub-Transmission Main Sub-Transmission Main: Z4 600mm on Thomas Street from Winston Churchill Blvd to Ninth Line (Construction) 2022 A+ 2013 MP 600 mm 2,093 $5,993,000

W-ST-096 Design Queen St Sub-Transmission Main Sub-Transmission Main: Z4 600mm on Queen St from Goreway Dr to McVean Dr (Design) 2024 A+ 2013 MP 600 mm 1,354 $1,013,000

Page 55: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 51

Master Plan ID

Component Type Name Description Year in

Service Class EA Schedule

Class EA Schedule Coverage Size/ Capacity Length (m)

Total Component Estimated Cost

(2013$)

W-ST-096 Construction Queen St Sub-Transmission Main Sub-Transmission Main: Z4 600mm on Queen St from Goreway Dr to McVean Dr (Construction) 2024 A+ 2013 MP 600 mm 1,354 $5,847,000

W-ST-115 Design Clark Blvd Sub-Transmission Main Sub-Transmission Main: Z5 600mm on Clark Boulevard crossing Hwy 410 (Design) 2020 A+ 2013 MP 600 mm 664 $568,000

W-ST-115 Construction Clark Blvd Sub-Transmission Main Sub-Transmission Main: Z5 600mm on Clark Boulevard crossing Hwy 410 (Construction) 2020 A+ 2013 MP 600 mm 664 $3,281,000

W-ST-097 Design Mayfield Rd Sub-Transmission Main Sub-Transmission Main: 600mm Z7 on Mayfield Rd from McLaughlin Rd to Hurontario St (Design) 2013 A+ 2013 MP 600 mm 1,366 $587,000

W-ST-097 Construction Mayfield Rd Sub-Transmission Main Sub-Transmission Main: 600mm Z7 on Mayfield Rd from McLaughlin Rd to Hurontario St (Construction) 2013 A+ 2013 MP 600 mm 1,366 $3,386,000

W-ST-122 Design Mayfield Rd Sub-Transmission Main Sub-Transmission Main: 600mm Z7 on Mayfield Rd from Chinguacousy Rd to McLaughlin Rd (Design) 2013 A+ 2013 MP 600 mm 1,389 $488,000

W-ST-122 Construction Mayfield Rd Sub-Transmission Main Sub-Transmission Main: 600mm Z7 on Mayfield Rd from Chinguacousy Rd to McLaughlin Rd (Construction) 2013 A+ 2013 MP 600 mm 1,389 $2,819,000

W-ST-123 Design Mayfield Rd Sub-Transmission Main Sub-Transmission Main: 600mm Z7 on Mayfield Rd from Alloa PS to Chinguacousy Rd (Design) 2013 A+ 2013 MP 600 mm 2,057 $718,000

W-ST-123 Construction Mayfield Rd Sub-Transmission Main Sub-Transmission Main: 600mm Z7 on Mayfield Rd from Alloa PS to Chinguacousy Rd (Construction) 2013 A+ 2013 MP 600 mm 2,057 $4,145,000

W-ST-098 Design Heritage Rd Sub-Transmission Main Sub-Transmission Main: Z4 600mm on Heritage Rd from Meadowvale N PS to Steeles Ave (Design and Construction) 2016 A+ 2013 MP 600 mm 1,367 $705,000

W-ST-098 Construction Heritage Rd Sub-Transmission Main Sub-Transmission Main: Z4 600mm on Heritage Rd from Meadowvale N PS to Steeles Ave (Design and Construction) 2016 A+ 2013 MP 600 mm 1,367 $4,068,000

W-ST-099 Design Silverthorn Sub-Transmission Main Queensway 900mm Z2 Extension on Cawthra Rd from Queensway and Cawthra Rd towards the Silverthorn PS Discharge (Design) 2024 B Separate Study 900 mm 2,374 $2,509,000

W-ST-099 Construction Silverthorn Sub-Transmission Main Queensway 900mm Z2 Extension on Cawthra Rd from Queensway and Cawthra Rd towards the Silverthorn PS Discharge (Construction) 2024 B Separate Study 900 mm 2,374 $14,476,000

W-ST-100 Design Eglinton Ave Sub-Transmission Main Sub-Transmission Main: Z4 600mm on Eglinton Ave from Erin Mills Pkwy to Glen Erin Dr (Design) 2015 A+ 2013 MP 600 mm 720 $258,000

W-ST-100 Construction Eglinton Ave Sub-Transmission Main Sub-Transmission Main: Z4 600mm on Eglinton Ave from Erin Mills Pkwy to Glen Erin Dr (Construction) 2015 A+ 2013 MP 600 mm 720 $1,490,000

W-ST-101 Design Duke of York Sub-Transmission Main Sub-Transmission Main: Z4 600mm on Duke of York Blvd from City Centre Dr to Webb Dr (Design) 2017 A+ 2013 MP 600 mm 308 $225,000

W-ST-101 Construction Duke of York Sub-Transmission Main Sub-Transmission Main: Z4 600mm on Duke of York Blvd from City Centre Dr to Webb Dr (Construction) 2017 A+ 2013 MP 600 mm 308 $1,293,000

W-ST-102 Design Lakeshore Rd Sub-Transmission Main Sub-Transmission Main: Z1 600mm on on Lakeshore Rd from the Lakview WTP to the existing 600 mm watermain at Enola Ave (Design) 2021 A+ 2013 MP 600 mm 1,320 $1,517,000

W-ST-102 Construction Lakeshore Rd Sub-Transmission Main Sub-Transmission Main: Z1 600mm on on Lakeshore Rd from the Lakview WTP to the existing 600 mm watermain at Enola Ave (Construction) 2021 A+ 2013 MP 600 mm 1,320 $8,758,000

W-ST-103 Design Bloor St Main Sub-Transmission Main Sub-Transmission Main: Z2 1050mm on Bloor Street form Silverthorn PS to Cawthra Rd (Design and Construction) 2022 A+ 2013 MP 1050 mm 573 $940,663

W-ST-103 Construction Bloor St Main Sub-Transmission Main Sub-Transmission Main: Z2 1050mm on Bloor Street form Silverthorn PS to Cawthra Rd (Design and Construction) 2022 A+ 2013 MP 1050 mm 573 $5,428,337

W-ST-104 Construction West Brampton Sub-Transmission Main Sub-Transmission Main: 900mm Z6 from West Brampton PS to Heritage Rd/Bovaird Dr (Construction) 2020 A+ 2013 MP 900 mm 1,719 $6,473,000

W-ST-104 Design West Brampton Sub-Transmission Main Sub-Transmission Main: 900mm Z6 from West Brampton PS to Heritage Rd/Bovaird Dr (Design) 2020 A+ 2013 MP 900 mm 1,719 $1,122,000

W-ST-105 Design Kennedy Rd Sub-Transmission Main Sub-Transmission Main: 600mm Z6 on Kennedy Rd from McFadden Dr to Somerset Dr (Design) 2021 A+ 2013 MP 600 mm 337 $132,000

W-ST-105 Construction Kennedy Rd Sub-Transmission Main Sub-Transmission Main: 600mm Z6 on Kennedy Rd from McFadden Dr to Somerset Dr (Construction) 2021 A+ 2013 MP 600 mm 337 $766,000

W-ST-106 Design Mayfield Rd Sub-Transmission Main Sub-Transmission Main: Z7 600mm on Mayfield Rd from Alloa PS to Mississauga Rd (Design) 2015 A+ 2013 MP 600 mm 1,022 $536,000

W-ST-106 Construction Mayfield Rd Sub-Transmission Main Sub-Transmission Main: Z7 600mm on Mayfield Rd from Alloa PS to Mississauga Rd (Construction) 2015 A+ 2013 MP 600 mm 1,022 $3,091,000

W-ST-107 Design Mayfield Rd Sub-Transmission Main Sub-Transmission Main: 750mm Z6 on Mayfield Rd from Kennedy Rd to Stonegate Dr (Design) 2016 A+ 2013 MP 750 mm 523 $329,000

Page 56: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 52

Master Plan ID

Component Type Name Description Year in

Service Class EA Schedule

Class EA Schedule Coverage Size/ Capacity Length (m)

Total Component Estimated Cost

(2013$)

W-ST-107 Construction Mayfield Rd Sub-Transmission Main Sub-Transmission Main: 750mm Z6 on Mayfield Rd from Kennedy Rd to Stonegate Dr (Construction) 2016 A+ 2013 MP 750 mm 523 $1,897,000

W-ST-108 Design Bolton ET Connection Bolton Z6 750mm Elevated Tank connection (Design) 2017 A+ 2013 MP 750 mm 249 $110,000

W-ST-108 Construction Bolton ET Connection Bolton Z6 750mm Elevated Tank connection (Construction) 2017 A+ 2013 MP 750 mm 249 $635,000

W-ST-109 Design Coleraine Dr Sub-Transmission Main Sub-Transmission Main: Z6 600mm from Holland Dr to Bolton ET on Coleraine Dr (Design) 2016 A+ 2013 MP 600 mm 221 $120,000

W-ST-109 Construction Coleraine Dr Sub-Transmission Main Sub-Transmission Main: Z6 600mm from Holland Dr to Bolton ET on Coleraine Dr (Construction) 2016 A+ 2013 MP 600 mm 221 $691,000

W-ST-110 Design Goreway Dr Sub-Transmission Main Sub-Transmission Main: Z5 750mm on Goreway Dr from Castlemore Rd to Countryside Dr (Design) 2019 A+ 2013 MP 750 mm 3,150 $1,288,000

W-ST-110 Construction Goreway Dr Sub-Transmission Main Sub-Transmission Main: Z5 750mm on Goreway Dr from Castlemore Rd to Countryside Dr (Construction) 2019 A+ 2013 MP 750 mm 3,150 $7,435,000

W-ST-112 Design Confederation Pkwy Sub-Transmission Main Sub-Transmission Main: Z3 900mm on Confederation Pkwy from Burnhamthorpe Rd to Eglinton Ave (Design) 2032 B Separate Study 900 mm 1,999 $3,220,468

W-ST-112 Construction Confederation Pkwy Sub-Transmission Main Sub-Transmission Main: Z3 900mm on Confederation Pkwy from Burnhamthorpe Rd to Eglinton Ave (Construction) 2032 B Separate Study 900 mm 1,999 $18,584,532

W-ST-113 Design Mayfield Rd Sub-Transmission Main Sub-Transmission Main: Z5 900mm on Mayfield Rd from Goreway Dr to North Brampton PS (Design) 2016 B Separate Study 900 mm 6,637 $4,384,592

W-ST-113 Construction Mayfield Rd Sub-Transmission Main Sub-Transmission Main: Z5 900mm on Mayfield Rd from Goreway Dr to North Brampton PS (Construction) 2016 B Separate Study 900 mm 6,637 $25,302,408

W-P-061 Construction West Brampton Pumping Station Expansion West Brampton Z5 Pumping Station Expansion (Construction) 2 pumps at 30 ML/d each 2020 A 2013 MP 60 ML/d $1,242,000

W-P-063 Design Streetville PS Pump adition Streetsville PS Z3 Low Lift Pump addition. One pump at 90 MLD (Design) 2021 A 2013 MP 90 ML/d - $161,000

W-P-063 Construction Streetville PS Pump adition Streetsville PS Z3 Low Lift Pump addition. One pump at 90 MLD (Construction) 2021 A 2013 MP 90 ML/d - $932,000

W-P-064 Design Beckett Sproule PS Pump adition Beckett Sproule PS transfer pump addition. 1 pump at 92 MLD (Design) 2020 A 2013 MP 92 ML/d - $165,000

W-P-064 Construction Beckett Sproule PS Pump adition Beckett Sproule PS transfer pump addition. 1 pump at 92 MLD (Construction) 2020 A 2013 MP 92 ML/d - $953,000

W-P-065 Design Beckett Sproule PS Pump adition Beckett Sproule PS transfer pump addition. 1 pump at 92 MLD (Design) 2026 A 2013 MP 92 ML/d - $165,000

W-P-065 Construction Beckett Sproule PS Pump adition Beckett Sproule PS transfer pump addition. 1 pump at 92 MLD (Construction) 2026 A 2013 MP 92 ML/d - $953,000

W-P-066 Design Beckett Sproule PS Pump adition Beckett Sproule PS transfer pump addition. 1 pump at 92 MLD (Design) 2029 A 2013 MP 92 ML/d - $165,000

W-P-066 Construction Beckett Sproule PS Pump adition Beckett Sproule PS transfer pump addition. 1 pump at 92 MLD (Construction) 2029 A 2013 MP 92 ML/d - $953,000

W-P-068 Design Streetville PS Pump Addition Streetsville PS Z3 Low Lift Pump addition. One pump at 72 MLD (Design) 2014 A+ 2013 MP 72 ML/d - $138,000

W-P-068 Construction Streetville PS Pump Addition Streetsville PS Z3 Low Lift Pump addition. One pump at 72 MLD (Construction) 2014 A+ 2013 MP 72 ML/d - $795,000

W-P-069 Design Alloa PS Z7 Pump Addition Alloa PS Z7 High Lift Pump addition. One pump at 12 MLD (Design) 2019 A+ 2013 MP 12 ML/d - $58,000

W-P-069 Construction Alloa PS Z7 Pump Addition Alloa PS Z7 High Lift Pump addition. One pump at 12 MLD (Construction) 2019 A+ 2013 MP 12 ML/d - $331,000

W-P-141 Construction Alloa Pumping Station (Construction) Alloa Pumping Station (Construction) C Completed 60 ML/d $17,167,910

W-P-061 Design West Brampton Reservoir and PS Expansion

West Brampton Z4 Reservoir and Z5 Pumping Station Expansion 20 ML and 60 MLD (Design) 2020 A 2013 MP 20 ML / 60 MLD $2,946,000

W-P-061 EA West Brampton Reservoir and PS Expansion

West Brampton Z4 Reservoir and Z5 Pumping Station Expansion 20 ML and 60 MLD - (EA/Feasibility Study) 2020 A 2013 MP 20 ML / 60 MLD $329,000

Pumping Stations / Reservoirs

Page 57: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 53

Master Plan ID

Component Type Name Description Year in

Service Class EA Schedule

Class EA Schedule Coverage Size/ Capacity Length (m)

Total Component Estimated Cost

(2013$)

W-S-062 Construction West Brampton Reservoir Expansion West Brampton Z4 Reservoir Expansion 20 ML (Construction 2020 A 2013 MP 20.0 ML $17,653,000

W-S-072 Construction North Bolton Elevated Tank North Bolton Elevated Tank (Construction) 2014 C-Completed Completed 9.0 ML $11,500,000

W-S-073 Construction Victoria Reservoir Victoria Reservoir (Zone 6) (Construction) 2016 C-Completed Completed 40.0 ML $55,050,000

W-S-142 Construction Alloa Reservoir 25 ML (Construction) Alloa Reservoir 25 ML (Construction) C Completed 25.0 ML $17,712,923

Treatment

W-TR-136 Construction Lakeview WTP Expansion - Standby Power - Generators Lakeview WTP Expansion - Standby Power - Generators (Construction) 2014 A 2013 MP $13,650,000

W-TR-137 Construction Lakeview WTP Expansion - Standby Power - Building Lakeview WTP Expansion - Standby Power - Building (Construction) 2015 A 2013 MP $19,950,000

$1,627,057,632

Page 58: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 54

7 York Region Water Servicing Strategy

The York water requirements were supplied from York Region and defined as Schedule C of the York-Peel Water Servicing Agreement. They are a key component of the long-term water supply and servicing requirements for the Region of Peel. They are generally reflected in the water supply requirements for the Central and East Transmission Systems. The 2031 water supply requirement for York Region is 388 ML/d.

7.1 York-Peel water servicing agreement

The maximum day demands as per the York-Peel Servicing Agreement are shown in Figure 3.15.

Figure 3.15 Maximum day demands as per the York-Peel water servicing agreement

Water supplied to York Region is treated at the Lakeview Water Treatment Plant and pumped north through the Central Transmission System. It is then transferred to the East Transmission System through the Beckett Sproule Transfer Pumping Station and then pumped to York Region from the Airport Road Pumping Station. Currently, this station has two installed pumps at a capacity of 277 ML/d and has a planned expansion to take the capacity to meet York’s demand requirement as per the Agreement.

Page 59: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 55

7.2 Impact on Water Infrastructure

7.2.1 Water Treatment Plants

The York water demand requirement is supplied by the Lakeview WTP. This facility has sufficient capacity to service the required maximum day water demands to 2031, including York demands as per the Agreement. Beyond 2031, expansion of one or both of the water treatment plants could be required.

7.2.2 Pumping Stations

The 2007 Master Plan identified upgrades at the Beckett Sproule and Airport Road Reservoirs and Pumping Stations to meet York’s demand requirements. Some of these upgrades have been implemented while others continue to be valid and are included in the capital program.

7.2.3 Transmission Mains

York demands are supplied by the Central and East Transmission Systems. A major required upgrade is the Hanlan Transmission Main which is currently under construction. This transmission main will service growth in Peel as well as York water demand requirements.

Page 60: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 56

8 Intensification and Post-2031 Growth

8.1 2031 Intensification

Intensification is currently underway in many parts of the Region of Peel. Future intensification is reflected in the Region’s detailed growth projections within the 2031 planning horizon. The focus of this intensification is within three corridors: the Mississauga City Centre (MCC), the Hurontario Corridor and the Queen Street Corridor in Brampton.

8.1.1 Mississauga City Centre

The Mississauga City Centre (MCC) is bounded by Central Parkway to the south, Highway 403 to the north, the Cooksville Creek to the east and Grand Park Drive to the west. The area occupies approximately 26 hectares. Current water servicing to this area is through several trunk water mains from the Silverthorn Pumping Station and the Hanlan Pumping Station. The majority of the MCC is located within Pressure Zone 3C, with a small area southeast of Hurontario Street.and Burnhamthorpe Road located within Pressure Zone 2C. The local service area is serviced by a looped system of 300-mm and 400-mm water mains that generally follow the road alignments. Growth within the MCC from 2013 to 2031 is estimated to be approximately 16,497 people and 8,583 jobs.

8.1.2 Hurontario Corridor

The Hurontario Corridor runs along Hurontario Street from south of Lakeshore Road in Mississauga to Queen Street in Brampton and is anticipated to be the focus of intensification within the Region of Peel. The area occupies approximately 568 hectares. The Hurontario Corridor is serviced from the Lakeview Water Treatment Plant through the Central Transmission System covering Pressure Zones 1C though 5C. Growth within the Hurontario Corridor from 2013 to 2031 is estimated to be approximately 27,674 people and 19,990 jobs.

8.1.3 Brampton Queen Street Corridor

The Brampton Queen Street Corridor runs along Queen Street in Brampton from McLaughlin Road to Highway 50. The Queen Street Corridor occupies a large area spread from east to west and is mostly contained within Pressure Zone 5C, with some eastern extents crossing into Pressure Zones 5E and 4E. The corridor is predominantly serviced from the Beckett Sproule Pumping Station and the East Brampton Pumping Station. The area is directly serviced through several distribution mains ranging from 300-mm to 600-mm.

Page 61: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 57

Growth within the Queen Street Corridor from 2013 to 2031 is estimated to be approximately 32,630 people and 22,240 jobs.

8.1.4 2031 Intensification Servicing

In addition to the projects that make up the preferred Water Servicing Strategy outlined in Section 6, the 2013 Master Plan recommends several specific projects to service growth within the intensification areas. Upgrades to the Beckett Sproule, East Brampton, Hanlan and Silverthorn Pumping Stations, several smaller water main upgrades downstream of the MCC and wastewater treatment upgrades all service 2031 intensification growth and will make up part of the longer term strategy for intensification growth within these areas. There are a few storage expansions that may also be required. The Lakeview Water Treatment Plant will require upgrades to the intake as well as Pressure Zone 2C pumping. These projects, coupled with the 2031 Water Servicing Strategy, give the Region the ability to service the 2031 growth, but also support long term servicing in these areas.

8.2 Post-2031 Vision

The 2013 Master Plan puts forward a comprehensive trunk-level water and wastewater plan to service growth within the Region of Peel to the approved Places to Grow 2031 forecast. While the approved urban boundary and growth targets are to 2031, the Master Plan also considered implications of potential post-2031 growth on the system. The preferred Water Servicing Strategy addresses the growth needs to 2031 and also establishes flexibility within the system to implement a post-2031 strategy, once the long-term targets are confirmed and approved. Post-2031 growth is anticipated at two levels: intensification and greenfield growth. It is expected that greenfield growth will most likely occur in new pressure zones and will require new pumping and storage facilities.

8.2.1 Post-2031 Intensification

While intensification is presently occurring within Peel and will continue to 2031, potential post-2031 intensification growth was investigated within the major intensification areas outlined in the previous sections. Since the post-2031 growth projections are not finalized at this time, only a high level servicing investigation of intensification growth was completed. Detailed analysis of water infrastructure capacity and constraints has not yet been undertaken for the intensification areas. However, the 2031 Water Servicing Strategy establishes flexibility within the water distribution system and will support a longer-term post-2031 strategy within the intensification areas.

Page 62: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 58

Post-2031 intensification growth within the MCC, Hurontario Corridor and the Brampton Queen Street Corridor will require a strategy that focuses not only on local upgrades but also on the transmission, pumping and storage capacities as well as upgrades to the existing water treatment plants or investigate other water source options. Depending on location, timing and scale and the significance of post-2031 growth, the east-central-west zone boundary strategy will need to be revisited and analyzed in greater detail. It is understood that there are limitations to pumping, transmission and storage capacity, treatment capacity and treatment facility site capacity as well as several constructability issues within the existing water system. All of these factors must be considered when developing a post-2031 water servicing strategy.

8.2.2 Post-2031 Greenfield

The majority of both residential and employment development within Peel throughout the past several years has taken place within greenfield growth areas. The built boundaries of Mississauga and Brampton have continued to extend to the north forcing both the water and wastewater infrastructure to extend along with them. This has necessitated the construction of sewer extensions through the growth areas as well as increasing capacity (twining in some cases) in the downstream sections of sanitary trunk sewers. Throughout this growth, the Region of Peel has implemented strategic oversizing of trunk infrastructure to support development outside of past planning horizons. Though 2031 is the planning horizon for the 2013 Master Plan, there is an expectation that there could be significant post-2031 growth extending further into greenfield areas outside of the current urban boundary. In the development of the Water Servicing Strategy and recommendation of specific projects, the 2013 Master Plan considered the long-term greenfield growth scenario that could occur and ensured that flexibility is built into the program. However, similar to the servicing requirements to accommodate post-2031 intensification, the magnitude and location of growth will have a significant impact on the transmission and pumping upgrades, as well as plant upgrade requirements.

Page 63: 2013 Water and Wastewater - Master Plan for the Lake-Based ... · Master Plan Addendum and the 2007 Master Plan Update. The 2013 Master Plan is a critical component in the Region’s

Regional Municipality of Peel 2013 Water and Wastewater Master Plan

for the Lake Based Systems – Volume III

March 31, 2014

Page 59

Figure 3.16 Post-2031 water servicing strategy