![Page 1: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/1.jpg)
Memorandum
CITY OF DALLAS DATE 22 August 2014
TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair), Lee Kleinman (Vice Chair), Deputy Mayor Pro Tern Monica Alonzo, Mayor Pro Tern Tennell Atkins, Sandy Greyson, and Sheffie Kadane
SUBJECT Cotton Belt Corridor
On Monday, 25 August 2014, you will be briefed on the Cotton Belt Corridor. The briefing materials are attached for your review.
Please feel free to contact me if you need additional information.
9l41~ Jill A. Jordan, P .E. Assistant City Manager
Attachment
c: A. C. Gonzalez, Cily Manager Warren M.S. Emsl, Cily AIIomey Craig D. Kinton, City Auditor Rosa A. Rios, City Secretary Daniel F. Solis, Administralive Judge Ryan S. Evans, First Assistant City Manager Forest E. Turner, Assistant City Manager
Joey Zapata, Assistant City Manager Charles M. Cato, (I) Assistant City Manager Theresa O'Donnell, (I) Assistant City Manager Jeanne Chipperfield, Chief Financial Officer Sana Syed, Public Information Officer Elsa Cantu, Assistant to the City Manager - Mayor & Council
"Dallas-Together. we do it better"
![Page 2: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/2.jpg)
Cotton Belt Corridor
Transportation and Trinity River Project Committee
25 August 2014
![Page 3: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/3.jpg)
Presentation Outline
2
Overview
Corridor Location
Ownership
TEX Rail Project
Project Development
Anticipated Private Sector Proposal
DART Alternatives Development
Next Steps
![Page 4: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/4.jpg)
Overview
Two independent projects
The FortWorthTransportation Authority [“TheT”]
Dallas Area RapidTransit [“DART”]
Serves a large part of the region
Located in Dallas, Collin and Tarrant counties
Thirteen (13) Cities
Two (2) Universities (University of Texas at Dallas and Texas A&M
Research & Ext Center)
Important transit connections
D/FW Airport and Orange Line Connection
DART Green Line and Red Line Connections
DART owns fifty-two (52) miles of Cotton Belt right-of-way
3
![Page 5: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/5.jpg)
Cotton Belt Corridor
4
![Page 6: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/6.jpg)
TEX Rail Project
5
![Page 7: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/7.jpg)
The T submitted New Starts application for TEX Rail in
October 2011
Seeking $405 million in federal funding
In August 2013, The T Board redefined project as
Minimum Operable Segment [“MOS”] from Downtown
Fort Worth to the D/FW Airport station
Revised environmental document under review by Federal
Transit Administration [“FTA”] and Federal Aviation
Administration [“FAA”]
Anticipated revenue service in 2018
TEX Rail Status
6
![Page 8: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/8.jpg)
Recent History
7
DART Public Private Partnership [“PPP’] meeting
May 2009
Cotton Belt Conceptual Engineering and Funding Study
(NCTCOG)
Completed April 2010
Cotton Belt Innovative Finance Initiative (NCTCOG)
Initiated July 2010 and Completed December 2011
DART Board
Authorized the President/Executive Director in May 2010 to enter into
an Memorandum of Understanding [“MOU”] with the Regional
Transportation Commission [“RTC”] to receive proposals to advance
Rail Service in the Corridor
No proposals were received; MOU no longer in effect
![Page 9: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/9.jpg)
8
![Page 10: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/10.jpg)
Potential Dallas Stations
Cypress Waters-North Lake
Knoll Trail-DNT area
Opportunity for significant redevelopment and
economic benefit to city
Preston Road
Neighborhood residents have voiced concerns
Coit Area
Texas A&M area redevelopment
University of Texas at Dallas
Transit Oriented Development
9
![Page 11: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/11.jpg)
Project Benefits
Provide passenger rail connections and service
between the DART, Denton County Transit
Authority [“DCTA”], and The T service areas
Provide for crosstown movement and
connections to D/FW Airport
Reduce congestion/travel delays along the
northern tier of the region
10
![Page 12: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/12.jpg)
Project Benefits (continued)
11
Provide reliable connections between existing and
proposed transit system
Promote development along the corridor through
Transit Oriented Development [“TOD”]
opportunities
Opportunity to incorporate Cotton Belt Hike
and Bike Trail within the Project
![Page 13: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/13.jpg)
DART Rail Service Coverage
12
Cotton Belt can help
fill a gap in rail transit
service for Far North
Dallas
Rail transit along LBJ
corridor could also
help address gap in
Far North Dallas
service
![Page 14: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/14.jpg)
Project Development
13
DART Initiated Preliminary Engineering Effort
Notice of Intent issued in July 2010
Advanced Engineering and Environmental Analysis
Preliminary Engineering Effort to Support and
Provide Starting Point for Private-Sector
Proposal
No Proposal Received
Completed Documentation of Environmental
Conditions and 5% Engineering Report
April 2014
Spent Approximately $8 million
![Page 15: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/15.jpg)
Design Alternatives
14
![Page 16: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/16.jpg)
Range of Alignment Options Evaluated
Base Line project options
Double track rail
Lowest cost rail
Bus Rapid Transit [“BRT”]
Alignment alternatives
Cypress Waters
Interface with Red Line east of Central Expressway
Profile options in North Dallas
At-grade
Tunnel
15
![Page 17: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/17.jpg)
16
![Page 18: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/18.jpg)
Operable Segments
17
![Page 19: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/19.jpg)
Regional Rail Vehicle
18
![Page 20: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/20.jpg)
Major Assumptions – Double Track Rail
19
2020 revenue service start
TEX Rail to D/FW Airport and the DCTA extension to
Downtown Carrollton are completed before 2020
Assumption of a federal grant for 20% of the capital cost,
the remainder of the capital costs to be funded with debt
DART will contribute no money to construction or
operations until 2035 at the earliest
![Page 21: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/21.jpg)
Major Assumptions – Double Track Rail
20
New Diesel Multiple Unit [“DMU”] vehicles
Full double-tracking along the whole corridor
20-minute peak headways, 60-minute off-peak and
weekend service
![Page 22: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/22.jpg)
Major Assumptions – Lowest Cost Rail
21
2020 revenue service start
TEX Rail to D/FW Airport and the DCTA extension to
Downtown Carrollton are completed before 2020
Assumption of no federal grant / All capital costs to be
funded with debt
DART will contribute no money to construction or
operations until 2035 at the earliest
![Page 23: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/23.jpg)
Major Assumptions – Lowest Cost Rail
22
New Diesel Multiple Unit [“DMU”] vehicles
30-minute peak headways, 60-minute off-peak and weekend service
No extra work done at Downtown Carrollton to prepare for full double-tracking, no operating facility
Rail service stops at D/FW North Station and TEX Rail and/or a bus shuttle takes passengers into D/FW Airport
Single-track rail service, sidings where necessary
![Page 24: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/24.jpg)
BRT Technology
Valley Rapid, San Jose, CA
23
![Page 25: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/25.jpg)
BRT Examples
24
LA Orange Line
Sample BRT Video
![Page 26: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/26.jpg)
Major Assumptions - BRT
25
2020 revenue service start
Assumption of no federal grant / All capital costs to be
funded with debt
DART will contribute no money to construction or
operations until 2035 at the earliest
![Page 27: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/27.jpg)
Major Assumptions - BRT
26
TEX Rail to D/FW Airport and the DCTA extension to
Downtown Carrollton are completed before 2020
Service delivered with articulated buses
10-20 minutes peak headways, 30-minute off-peak and
weekend service
The BRT corridor ends at D/FW North Station but the
bus continues into D/FW Airport
![Page 28: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/28.jpg)
Cross Section
BRT split by direction
(railroad track does not
need to be moved)
Shown herein as BRT 1
27
BRT confined to one side
(railroad track may need to
be moved to make room for
busway)
Shown herein as BRT 2
![Page 29: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/29.jpg)
Current Status
Currently in DART Financial Plan for beyond 2035
Strong region-wide support to develop early
No other funding source is currently available
DART has developed a range of options for
consideration
28
![Page 30: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/30.jpg)
Summary Table: Gross Capital Cost
29
![Page 31: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/31.jpg)
Summary Table: Funding through 2034
30
![Page 32: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/32.jpg)
Addressing the Funding Gap
31
![Page 33: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/33.jpg)
Next Steps
32
Which mode to pursue
Project phasing
Identifying funding sources
Position the project for grant application
Implementing alternative funding possibilities
![Page 34: Memorandum · 2015-01-20 · Memorandum CITY OF DALLAS DATE 22 August 2014 TD The Honorable Members of the Transportation and Trinity River Project Committee: Vonciel Jones Hill (Chair),](https://reader033.vdocument.in/reader033/viewer/2022060502/5f1c187559c7c22675717a11/html5/thumbnails/34.jpg)
Discussion
33