Introductions
4/7/20152
City
Mayor
City Council
Department Heads
Staff
Carollo Engineers
Design Team
Hoffman Construction
GC/CM Contractor
City Council Workshop
Agenda
4/7/20153
Introductions
Project Goals
Project History / Milestones
Facilities Plan to 30% (Concept to Reality)
Why GC/CM?
Cost / Funding / Rates Relationship
Key Decisions / Next Steps
Other Topics
City Council Workshop
Agenda
4/7/20154
Presentation will address
Project Cost
Cost Saving Measures
Schedule
RV Park
Permits
Please be patient as we lead you though the presentation
There will be opportunity to ask questions at the end of
each section and at the end of the presentation
City Council Workshop
Project Goals
4/7/20155
“Recognizing that the City of Oak Harbor is connected to
the pristine waters of Puget Sound, specifically Oak Harbor
and Crescent Harbor Bay, the City’s goal is to obtain the
highest of water quality practical while recognizing the
limitations of the rate payers of the City to fund the
improvements.”
City Council Workshop
Project Goals
4/7/20156
Provide reliable wastewater treatment services;
Meet high water quality standards;
Allow phased expansion to meet future demands; and
Deliver construction and operation of a new facility by 2017 in
a cost-effective manner
City Council Workshop
Agenda
4/7/20157
Introductions
Project Goals
Project History / Milestones
Facilities Plan to 30% (Concept to Reality)
Why GC/CM?
Cost / Funding / Rates Relationship
Key Decisions / Next Steps
Other Topics
City Council Workshop
Existing
Lagoons
Existing
Force Main
Existing
Rotating Biological
Contactor (RBC) Plant
Oak Harbor
Outfall
Collapsed
Crescent Harbor
Outfall
(in need of repair)
Project History
4/7/20159
Existing Rotating Biological Contactor(RBC) Plant
Located next to Windjammer Park
RBC process largely disabled (Available for emergencies)
Aging facility that is difficult/expensive to maintain
Currently used to
screen coarse material
and send influent to
the Lagoons
City Council Workshop
4/7/201510
Force Main Failure in 2005 caused emergency repair
With Oak Harbor outfall failed, the impact of another
failure could be
extreme
City Council Workshop
Project History
Seaplane Base Lagoon
Draft FEMA documents potential flooding in 100 year storm
event
11
Existing
Seaplane Base
Lagoon
Project History
Previous storm events have put the lagoons at risk
12
Dike Protecting
Treatment Plant
Flooded
Access Road
Dike Protecting
Lagoons
Debris
Right up to
Fence
Project History
Milestones
4/7/201514
December 2010 – Started Facilities Plan
April 2011 – Narrowed to 5 potential sites (Resolution 11-07)
January 2012 – Added 6th site - Crescent Harbor North (Resolution 12-05)
City Council Workshop
Milestones
4/7/201515
April 2012 – Narrowed Selection to Windjammer Vicinity
& Crescent Harbor North (Resolution 12-10)
August 2012 – Selected Windjammer Vicinity
(Resolution 12-17)
Oak
Harbor
Outfall
Milestones
4/7/201516
Why Windjammer Vicinity instead of Crescent Harbor
North????
Capital Cost of two options was similar
Crescent Harbor North would have included
Pump Station near existing RBC Plant
+/- 2 miles of piping to and from Crescent Harbor North
Ongoing annual O&M cost and risk associated with pumping
wastewater to Crescent Harbor North and effluent back to Oak
Harbor ($170,000/yr)
Risk of impacting cultural resources at sites & along alignment
City Council Workshop
Agenda
4/7/201517
Introduction and Project Goals
Project History / Milestones
Facilities Plan to 30% (Concept to Reality)
Why GC/CM?
Cost / Funding / Rates Relationship
Key Decisions / Next Steps
Other Topics
City Council Workshop
Facilities Plan to 30%From Concept to Reality
4/7/201518
We will cover the following items in this section
Milestones from the Facilities Plan to 30% (Concept to Reality)
30% Design Review
30% Cost Estimate(s)
City Council Workshop
Facilities Plan to 30%Milestones
4/7/201519
November 2013 – Facilities Plan Adopted (Resolution 13-31)
November 2013 – Completed 15% Value Engineering
December 2013 – Authorized to pursue GC/CM (Resolution 13-32)
January 2014 – Navy non-committal (Resolution 14-05)
City Council Workshop
Facilities Plan to 30%Milestones
4/7/201520
March 2014 – Purchased Whidbey Island Bank property
Why the Whidbey Island Bank Property?
No net loss of park space
Willing seller vs. Condemnation
Minimized impact on potential cultural resources
Minimized displacement of businesses to avoid relocation
requirements
City Council Workshop
Facilities Plan to 30%Milestones
4/7/201521
March 2014 – State Capital Project Advisory Review
Board (CPARB) – Project Review Committee (PRC)
approval to use General Contractor / Construction
Manager (GC/CM)
March 2014 – Started selection process for GC/CM
City Council Workshop
Facilities Plan to 30%Milestones
4/7/201522
April 2014 – City
Council Workshop
City Council Workshop
Facilities Plan to 30%Milestones
4/7/201523
July 2014 – Selected Hoffman as GC/CM
City Council Workshop
Facilities Plan to 30%Milestones
24
August 2014 – Authorized site layout on former
Whidbey Island Bank Property (Resolution 14-28)
Treatment Plant
Project
Limits
Facilities Plan to 30%Milestones
4/7/201525
January 2015 – Defined Work Area (Resolution 14-43)
City Council Workshop
Facilities Plan to 30%
30% Design - Conceptual Rendering
4/7/201528
Solids
Handling
Headworks
Primary
TreatmentElectrical /
Controls
Secondary
(MBR)
Admin /
Maintenance
Training Facility
Existing Whidbey
Island Bank
Building
City Council Workshop
Facilities Plan to 30%30% Cost Estimate - “Project Limits”
4/7/201536
Treatment Plant
City Council Workshop
Facilities Plan to 30% 30% Cost Estimate
Components consistent with Facilities Plan
4/7/201537
Cost Component Description
Soft CostEngineering, Legal,Administration, GC/CM
services prior to construction, Overhead, etc.
Land AcquisitionPurchase price of land/structures for purpose
of building new facilities
Treatment Plant (WWTP)
Construction
Total Construction Cost of new treatment
plant and associated improvements
City Council Workshop
4/7/201538
$78.9
*
$116.5
WWTP Construction is
> 75% of Total Project Cost
*Cost at construction mid-point
City Council Workshop
Facilities Plan to 30%30% Cost Estimate – Carollo’s Estimated
Total Project Cost at Facilities Plan Level
Facilities Plan to 30%30% Cost Estimate
Refinements since Facility Plan Approval
4/7/201539
Project ComponentPlan Assumption
(Scenario 2, Phase 1)
30% Design
Assumption
Electrical,
Instrumentation and
Control
Assumed as a % of
construction on low end of
typical range
Assumed as a % of
construction on high end of
typical range
Site Layout Between 3 to 4 acres
Approx. 2.5 acres to
minimize impact on
Windjammer Park
Solids ProcessHaul Class B biosolids
to Eastern WA
Reuse Class A biosolids
on Whidbey Island
City Beach St.
Improvementsn/a (no site selected)
Re-grade along eastern
WWTP frontage
Future Bayshore
Extensionn/a (no site selected)
Full section extended along
southern frontage
Training Facility n/a (not included) 200-seat capacity
City Council Workshop
Facilities Plan to 30% 30% Cost Estimate –
The current project scope is very
similar to “Scenario 2, Phase 1” per
Facilities Plan, and reflects VE and
Community input.
4/7/201540
Project ComponentPlan Assumption
(Scenario 2, Phase 1)
30% Design
Assumption
WWTP Capacity 2.6 mgd (Yr. 2021) 2.6 mgd (Yr. 2021)
Treatment Process MBR/UV MBR/UV
Effluent OutfallNew Outfall into
Oak Harbor
New Outfall into
Oak Harbor
City Council Workshop
Facilities Plan to 30% 30% Cost Estimate –
Carollo’s Estimated Total Project Cost
4/7/201541
$78.9
$116.5*
$38.1
*Cost at construction mid-point
City Council Workshop
Facilities Plan to 30%30% Cost Estimate – Where have the estimated $38.1M occurred?
39%
30%
21%
10%
Estimating Methods
Scope Modifications
Added Technical Detail
"Other"
Four Categories of Construction Cost Increase
4/7/201542
Focus Area: Electrical,
Instrumentation and Control
Focus Area: Ground Improvements
(Geotechnical)
Focus Area: Solids Handling
City Council Workshop
Facilities Plan to 30%30% Cost Estimate - How do the
Carollo and Hoffman cost estimates
compare at this stage of design?
4/7/201543
Currently reconciled to within 15% of one another
Within estimating accuracy at this level of detail
Have confirmed scope, quantities and approach to work
for major cost components
Continue to review/refine cost differences as detail is
added through 60% design
Concrete (~30% difference due to unit pricing)
Process/Mechanical (~15% difference due to scope
assumptions)
City Council Workshop
4/7/201544
Costs shown are for
construction only and
do not reflect overhead,
soft costs or outfall
construction.
City Council Workshop
Facilities Plan to 30% 30% Cost Estimate – Construction Costs
Range from $98 M to $113 M
Agenda
4/7/201545
Introduction and Project Goals
Project History / Milestones
Facilities Plan to 30%
Why GC/CM?
Cost / Funding / Rates Relationship
Key Decisions / Next Steps
Other Topics
City Council Workshop
Why GC/CM?
4/7/201546
November 19, 2013 – Project Delivery Presentation
Project Delivery Options
Design – Bid – Build
Design – Build
General Contractor / Construction Manager
City Council Workshop
Why GC/CM?
4/7/2015City Council Workshop47
Advantages
Greatest project value
High level design control
Cost certainty earlier in project
Incorporate contractor feedback in design
Disadvantages
Requires PRC approval
Unfamiliar delivery method
Not lowest cost initially
Why GC/CM?
4/7/201548
Construction can overlap Design on elements that are
well defined.2015 2016 2017
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2014 2018
30%
60%
90%
Site Prep
WWTP Construction
WWTP Design
WWTP Construction
Site Restoration
April 7, 2015
December 31, 2017
City Council Workshop
Why GC/CM?GMP Development Process30% Budget
Estimate
Development*
Value
Engineering &
Program
Refinement
Design
Progression
to 60% Detail
60% Estimate
Development/
Reconciliation
Design Scope
Containment and
Cost Testing***
90% Design
Estimate
Development
Bidding of
Major
Subcontract
Packages
Establish MACC
& Obtain
Council
Approval**
Commit Major
Subcontracts,
Complete
Subcontract
Bidding,
Construction
Maximum Construction
Cost Guaranteed Here
Confirm
Estimate
Assumptions &
Basis *
Where we are today
Independent 3rd Party Cost
Verification Here
Why GC/CM? - Process Provides Better
Cost Control and Earlier Cost Certainty
4/7/201550 City Council Workshop
Agenda
4/7/201551
Introduction and Project Goals
Project History / Milestones
Facilities Plan to 30%
Why GC/CM?
Cost / Funding / Rates Relationship
Key Decisions / Next Steps
Other Topics
City Council Workshop
Cost / Funding / Rate Relationship
4/7/201552
Customer rates are a blending of:
RATES
Schedule
Funding
Cost
City Council Workshop
Cost / Funding / Rates RelationshipWhat are we doing about the increased
cost?
4/7/201553
RATES
Schedule
Funding
Cost
City Council Workshop
Cost / Funding / Rates RelationshipWhere have the estimated $38.1M occurred?
39%
30%
21%
10%
Estimating Methods
Scope Modifications
Added Technical Detail
"Other"
Four Categories of Construction Cost Increase
4/7/201554
Focus Area: Electrical,
Instrumentation and Control
Focus Area: Ground Improvements
(Geotechnical)
Focus Area: Solids Handling
City Council Workshop
Cost / Funding / Rates RelationshipEstimating Methods ~ 39% of Increase(Transition from planning estimate to definitive
estimate)
4/7/201555
Line ItemApproximate
Increase
Cost Saving
ApproachRange of Potential Savings
Electrical,
Instrumentation &
Control (EI&C)
$14 M
Internal VE to
reduce EI&C
allowance %
$1.0 M $3.0 M
Contingency --Reduce
Contingency %$1.0 M $3.0 M
Escalation to Mid-point
of Construction$600 K
Maintain Planning-
level Mid-point
(5/16)
-- $600 K
Total Potential Cost Savings $2.0 M $6.6 M
City Council Workshop
Cost / Funding / Rates Relationship Scope Modifications ~ 30% of Increase(Elements added between planning and 30% design)
4/7/201556
Line ItemApproximate
Increase
Cost Saving
ApproachRange of Potential Savings
Class A Solids Handing
Technology$9.0 M
Phase-in Class A
Technology$7.0 M $10.0 M
200-Seat Training
Facility$1.6 M
Outside Funding
for Training Facility-- $1.6 M
Lab/Admin/Maint.
Facility Programming$600 K
Reduce Size of
Non-process
Facilities
-- $600 K
Extend Bayshore 350
LF Along Southern
Frontage
$225 K
Outside Funding
for Bayshore
Extension
-- $225 K
Total Potential Cost Savings $7.0 M $12.4 M
City Council Workshop
Cost / Funding / Rates RelationshipSite-specific Technical Detail ~ 20% of Increase (Elements revised due to additional design information)
4/7/201557
Line ItemApproximate
Increase
Cost Saving
ApproachRange of Potential Savings
Sitework $6.0 M
Optimize Ground
Improvements,
Shoring,
Earthwork
$1.6 M $3.1 M
Archaeology $550 K n/a -- --
700 LF City Beach
Street Re-grade$340 K n/a -- --
Premium Architecture
Treatments$950 K n/a -- --
Total Potential Cost Savings $1.6 M $3.1 M
City Council Workshop
Cost / Funding / Rates Relationship Specific Actions Already Completed to
Reduce Cost
4/7/201558
Formal Value Engineering (VE) to:
Screen, grit modifications in headworks ($1 M)
Aeration basin design criteria and volume reduction ($1.1 M)
Develop early site contract ($225 k)
Architectural design selected to minimize construction
materials, cost and schedule while achieving look based
on community input
City Council Workshop
Cost / Funding / Rates Relationship Specific Ongoing Actions to
Reduce Cost
4/7/201559
Internal Value Engineering (VE) to:
Reduce EI&C cost and estimating conservatism
Reduce cost and conservatism for ground improvements
Optimize non-process facility footprint for cost
Optimize process facilities for cost
Phasing discussions for solids handling
Reduce the number of unknowns (ie - early procurement)
Other funding sources for select project elements
200-seat training facility
Bayshore extension
City Council Workshop
Cost / Funding / Rates Relationship Improved Level of Detail Helps to Further
Reconcile and Confirm Costs
Typical 30% Design Typical 90% Design
4/7/201560
±150 Drawing Sheets
Very Limited
Specifications
> 600 Drawing Sheets
> 2,000 Pages of
Specifications
ADD TYPICAL 30% MECH PLAN ADD TYPICAL 90% MECH PLAN
City Council Workshop
Cost / Funding / Rate Relationship
4/7/201561
What sources of funding are being pursued?
RATES
Schedule
Funding
Cost
City Council Workshop
Cost / Funding / Rate Relationship
4/7/201562
RATES
Schedule
Funding
Cost
The optimal funding package includes those
sources which balance:
1. The lowest effective interest rate.
2. The maximization of long-term savings
3. The ability to pay.
City Council Workshop
4/7/201563
Imagine financing a new car for $10,000
Loan criteria:
1) Lowest interest rate.
2) Finance over a period of years that:
i. Keeps payment amount affordable
ii. Reduces lifetime interest expense
City Council Workshop
Cost / Funding / Rate Relationship
Cost / Funding / Rate Relationship
4/7/201564
RATES
Schedule
Funding
Cost
Sources of funding being pursued:
1) Grants/FP Loans No interest rate
2) SRF Funds 1.7% to 2.7%
3) Revenue Bonds 4.5%
•The ultimate goal is to develop a package which
incorporates the lowest weighted average interest rate.
lower interest rate = lower payment rate = lower utility rate
City Council Workshop
Cost / Funding / Rate Relationship
4/7/201565
Sources of obtained so far:
Type Amount % Rate Years Annual Payments Lifetime Cost
2015 SRF Loan Package $11.4 million 2.70% 20 $745,163.90 $14,903,278.08
2016 SRF Loan Package $15.0 million 1.70% 20 $891,007.83 $17,820,156.57
Centennial Grant Award $4.6 million 0% 0 $0.00 $0.00
FP Loan $0.4 million 0% 0 $0.00 $0.00
$31.4 million 1.79% 20 $1,636,171.73 $32,723,434.65
Revenue Bonds $31.4 million 4.50% 30 $1,927,694.45 $57,830,833.42
Savings from effort: ($291,522.71) ($25,107,398.77)
Annual payment is smaller even when shortening length of financing to 20 years!!
Will continue to pursue additional packages/grants
City Council Workshop
4/7/201566
RATES
Schedule
Funding
Cost
Revenue Bond Funding
• Portions of project not financed via previous
sources will be financed with Revenue Bonds.
•Timing of bond issue(s) is dependent upon
construction schedule, bond market, and timing
of the receipt of other funding sources.
•Total package to be structured to “level” rate
requirement.
City Council Workshop
Cost / Funding / Rate Relationship
4/7/201567
RATES
Schedule
Funding
Cost
2015 SRF Loan Package $11.4 million
2016 SRF Loan Package 15.0 million
2017 SRF Loan Package 15.0 million
Centennial Grant Award 4.6 million
FP Loan 0.4 million
Cash Reserves 15.0 million
Revenue Bonds 36.7 million
Total $98.1 million
City Council Workshop
Cost / Funding / Rate Relationship
Cost / Funding / Rate Relationship
4/7/201569
RATES
Schedule
Funding
Cost
Other sources: Non-sewer component funding:
Some components of the project are not sewer
related and will not be funded by rates
Sub-project
Bayshore Drive
Splash Park
200-seat Public Facility
MVFT-Arterial, Grants, REET
General Fund, Grants
General Fund (cost benefit analysis)
Potential Sources of Funding
Sub-projects are subject to these funding sources
City Council Workshop
Cost / Funding / Rate Relationship
4/7/201570
Scheduling Impacts
Rates
Schedule
Funding
Cost
City Council Workshop
Cost / Funding / Rate Relationship
Site Preparation Start –vs- Overall Completion
4/7/2015City Council Workshop71
2015 2016 2017Activity M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Permitting
30% Design
Site Prep
60% Design
90% Design
100% Design
30% Design
Approval / Procure
Site Prep
Plant Construction
60% Design
Approval / Procure
Site Prep
Plant Construction
90% Design
Approval / Procure
Site Prep
Plant Construction
Base Assumption Overall Schedule with Site Prep Release with 5/5/15 City Council ApprovalOption 2 Overall Schedule with Site Prep Release Utilizing 60% Design Documents and Reconciled EstimateOption 3 Overall Schedule with Site Prep Release Utilizing 90% GMP Documents
2014
City of Oak Harbor - Construction Schedule Study7-Apr-15
2018
April 7, 2015
December 31, 2017
Base Assumption
Option 2
Option 3
Cost / Funding / Rates Relationship How do we move forward and
simultaneously control cost?
4/7/201572
Early work is planned to speed schedule (avoid
escalation) & Mitigate risk (associated cost)
Ongoing Budget management during design
Specific VE between CE, HCI, COH
Scope modifications by COH
Alternate sources of funding for certain projects components
(bayside, training facility, etc.)
Early work construction will not commence before the
reconciled budget is shown to match City’s budget
City Council Workshop
Cost / Funding / Rates RelationshipRate Impacts
4/7/201574
The goal of the WWTP funding plan has been to
accumulate$15 million in cash to effectively provide:
Initial Cash Reserves to strengthen utility for credit purposes
A form of down payment to lessen interest expense
Cash reserves to bridge the receipt of loan proceeds.
Ordinance No. 1587 passed October 5, 2010:
Increased wastewater rates systematically over time (Moodys).
Provides accumulation of cash reserves
Avoids dramatic rate changes in any one year.
Rates from $40.00 to 64.75 over 5-year period.
Cost / Funding / Rates Relationship Rate Impacts
4/7/201575
The level of significance of the drivers of rate impact
are as follows:
1) Cost – Cost is by far has the greatest impact on rates.
2) Schedule – can be the least, or the most, significant
based on potential delays and the resulting escalation.
3) Funding Source – While important, funding source has
the lesser level of significance to overall rate impact.
Agenda
4/7/201576
Introduction and Project Goals
Project History / Milestones
Facilities Plan to 30%
Why GC/CM?
Cost / Funding / Rates Relationship
Key Decisions / Next Steps
Other Topics
City Council Workshop
Key Council Decisions
4/7/201577
TOPIC DATE
1. Training Facility & How To Fund APR 21
2. Authorize Outfall Award APR 21
3. What To Do w/Bank Building? MAY/JUN
4. Decision on Aesthetics MAY/JUN
5. Utility Relocation and Initial Site Preparation JUN
6. Bond Sales JUN
7. Phase-in Solids Dryer? AUG
8. Bayshore Extension & How To Fund? AUG
9. Authorize Deep Excavation Award AUG
City Council Workshop
Agenda
4/7/201578
Introduction and Project Goals
Project History / Milestones
Facilities Plan to 30%
Why GC/CM?
Cost / Funding / Rates Relationship
Key Decisions / Next Steps
Other Topics
City Council Workshop
RV ParkConstruction Impacts to
Staysail RV Park
4/7/201580
Need location to store equipment/materials
Need access to site from Beeksma Drive
Will impact 13 full hook-up and 23 overflow sites
Need location to stockpile approx. 54,000 cy of soil
Near construction site:
Reduces trucking costs
Minimizes traffic impacts
Reduces damage to roadways
City Council Resolution 14-43 authorized closing of
Staysail RV Park and utilizing site for stockpile/laydown
City Council Workshop
RV ParkConcerns About Closure
of Staysail RV Park
4/7/201581
Loss of revenue to General Fund
Sewer Fund could pay General Fund for loss of revenue as
mitigation
Loss of customers to local businesses
Options that have been suggested to reduce impact
Lease private property on west side of Beeksma Drive for soil
stockpile – keep existing Staysail RV Park open
Lease private property on Bayshore Drive for use as a
temporary RV Park
Create partial hook-up RV sites at Marina
City Council Workshop
RV ParkOPTION 1 –Lease Private Property West of Beeksma
Drive for Material Storage
4/7/201582
Considerations:
Haul road still required
Loss of 25+ hook-up and 23 (tent) overflow sites
Revenue from RV site rentals to General Fund
Cost of lease of private property
Increase traffic impacts on Beeksma Drive
Archeology concerns
Delay in DAHP permit for WWTP?
Permits
SEPA
Grading
RV Park patrons near active haul road and construction site
City Council Workshop
RV ParkOPTION 2 – Lease Private Property on
Bayshore Drive for RV Park
4/7/201584
Considerations:
Revenue from RV site rentals to General Fund
Cost of lease
Zoning
Archeology
Permits
SEPA
Grading
No hook-ups
No park amenities
No restrooms
No showers
New location for staff to monitor
City Council Workshop
RV ParkOPTION 3 –Create RV Sites at
Oak Harbor Marina
4/7/201585
Considerations Revenue from RV site rentals to Marina Fund
Possible to create approx. 30 partial hook-up sites
Possible to install power and water
Cost
Archeology concerns
Shoreline permit
Not feasible to install sewer hook-ups
Staysail dump station will be open
Marina has portable pump out
Near Park
Other available amenities
Restrooms/Showers
Laundry
Bicycles
Food vendor(s)
Marina staff on-site
City Council Workshop
RV Park
4/7/201586
Potential site • Approximately
45 by 380 foot
area
• Water & power
available to
extend to site
Potential Site
City Council Workshop
RV Park - Amenities
Amenities Include:
• Park
• Picnic area
• Playground
• WiFi available
• Bicycles available
• Ample parking
• Showers
• Laundry
• Staff on-site
4/7/201587 City Council Workshop
RV PARKNext Steps
4/7/201588
Current RV Park open through May 26, 2015
Can extend based on construction schedule
April 22, 2015 City Council workshop
May 5, 2015 City Council meeting
City Council Workshop
Permits
4/7/201590
City is both project owner and approving authority
Typical City permits required in addition to Federal and State
City permits include:
SEPA
Shoreline Substantial Development permit
Site plan
Including design review/design guideline conformance
Civil plans (aka utility plans)
Grading
Building
Including mechanical and plumbing
Landscape
City Council Workshop
Permits
4/7/201591
City code requires certain permit approvals before
others
Example: site plan must be approved before grading plan
This process works for typical project sequencing
Does not work for GC/CM delivery method
Phased nature of design
Phased nature of construction
Staff proposes to amend code to recognize GC/CM
Allows different sequencing of permits
Appropriate permits still required & standards still met
Schedule: PC in April/May; CC in May/June
City Council Workshop
Memorandum of Agreement
4/7/201593
Section 106 – NHPA
Requires that we talk with interested parties regarding
cultural resources
Nearing completion of MOA which includes an
Archaeological Work Plan
City Council Workshop
Key Council Decisions
4/7/201594
TOPIC DATE
1. Training Facility & How To Fund APR 21
2. Authorize Outfall Award APR 21
3. What To Do w/Bank Building? MAY/JUN
4. Decision on Aesthetics MAY/JUN
5. Utility Relocation and Initial Site Preparation JUN
6. Bond Sales JUN
7. Phase-in Solids Dryer? AUG
8. Bayshore Extension & How To Fund? AUG
9. Authorize Deep Excavation Award AUG