Mihai Ioan STRATULAT - MsCE CONTACT Sos. Mihai Bravu 123-135, 1 st floor, ap. 4, sector 2, 021314 Bucharest, Romania E-mail: [email protected] Phone: +40 21 250 8088; Mobile: +40 724 643 222 DATE OF BIRTH 24 January 1951 EXECUTIVE SUMMARY Senior Construction / Contract Manager & Project Manager, with +40 years of experience, specialized in large scale projects related to water and hydraulics, mainly dams and hydropower, with proven track record of delivering projects within planned budget and deadlines. Specialized in overall project management, construction management and contracts management (Client's side). International experience, in Europe, Africa, Middle East, Ukraine. Fluent in English, French and Romanian with strong communication skills (both verbal and in writing). AREAS OF EXPERTISE Project Management, Contract Management & Project Controls – Water and waste Water treatment plant, water supply pipes and Distribution, Dams, HPP civil works and associated structures (Client's side) Design control of dams and associated works Planning of dams and associated works RELEVANT PROJECTS ( 1 ) Dams Hydro-power projects Special hydraulic works Bawanur Dam & HPP project (Kurdistan Region, Iraq) - Design Control & Contract management for infrastructure works Type of dam: embankment, with clay core H = 23.5 m L = 950 m V dam = 1.250.000 m 3 Spillway : RC controlled crest with 9 1 The detailed professional experience is listed below, in the body of the Resume Page 1 / 31

Upload: mihai-stratulat

Post on 13-Aug-2015

110 views

Category:

Documents


11 download

TRANSCRIPT

Page 1: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

CONTACT Sos. Mihai Bravu 123-135, 1st floor, ap. 4, sector 2, 021314 Bucharest, RomaniaE-mail: [email protected]: +40 21 250 8088;Mobile: +40 724 643 222

DATE OF BIRTH 24 January 1951

EXECUTIVE SUMMARY Senior Construction / Contract Manager & Project Manager, with +40 years of experience, specialized in large scale projects related to water and hydraulics, mainly dams and hydropower, with proven track record of delivering projects within planned budget and deadlines.

Specialized in overall project management, construction management and contracts management (Client's side).

International experience, in Europe, Africa, Middle East, Ukraine.

Fluent in English, French and Romanian with strong communication skills (both verbal and in writing).

AREAS OF EXPERTISE Project Management, Contract Management & Project Controls – Water and waste Water treatment plant, water supply pipes and Distribution, Dams, HPP civil works and associated structures (Client's side)

Design control of dams and associated works Planning of dams and associated works

RELEVANT PROJECTS (1) Dams Hydro-power projectsSpecial hydraulic works

Bawanur Dam & HPP project (Kurdistan Region, Iraq) - Design Control & Contract management for infrastructure works

Type of dam: embankment, with clay coreH = 23.5 mL = 950 mV dam = 1.250.000 m3

Spillway : RC controlled crest with 9 sections; L = 126 mBottom outlets = 10 x 3000 mmHPP = 4 x Kaplan turbines; 32 MW

Siriu Dam & Nehoiasu HPP (Romania) - Project Manager / Project Director

Type of dam: rockfill with clay corerockfill dam + HPPH = 123 mL = 510 mQ spillway = 1,720 m3/secHPP = 166 MWTunnels and galleries = 7,8 km

1 The detailed professional experience is listed below, in the body of the Resume

Page 1 / 24

Page 2: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

Ciresu - Surduc Dam & HPP (Phase 1) - Construction ManagerRockfill dam H = 65 m;HPP power = 55 MWTunnels and galleries (HPP headrace)= 16,5 km

Beni Haroun Dam - Water Transfer Facilities (Algeria) - Construction Supervision & Cost Control

(2) steps water intake (intake tower height = 30 m)underground pumping station (depth = 54 m)water conveying tunnel (level difference = 725 m)

EDUCATION 1969 - 1974Civil EngineeringTitle: Master ("Magna cum Laudae") Technical University of ConstructionFaculty of Hydro-technical Engineering - Bucharest, Romania

Majors:Dams and hydropower works

Minors:Hydraulic structuresCivil works

MEMBERSHIPS Member of the American Society of Civil Engineers (ASCE) Member of the Romanian Association of Civil Engineers

OTHER TRAINING Special training in organizing the activity on construction sites; Special training in programming and using personal computers in

design, engineering and planning activities;

LANGUAGES English - fluent French - fluent Romanian - native

KEY SKILLS Project management Contract management Organized and detail-

oriented Project reports expert Permit processing Risk management Results-oriented

Strong analytic skills Strong collaborative skills Contract

negotiation/review/drafting Computer pro-efficient Microsoft Office AutoCAD MSProject

ACCOMPLISHMENTS I have directed and coordinated several large scale public projects (with governmental & international financing), all of them delivered within the planned budget and deadlines, to the satisfaction of the Owners / Employers.

INTERNATIONAL EXPERIENCE

Iraq, Kurdistan, Algeria, Lebanon, Rwanda, Guinea, Ukraine, Bulgaria, Germany, Romania

RELEVANT PROJECTSA) Technical Assistance & Supervision (Design & Construction Control)

(2003 - 2015)

Page 2 / 24

Page 3: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

Client: Kurdistan Regional Government - Ministry of Municipalities

Location: Halabja and Sulaymania – Kurdistan, IraqProject: Halabja and Sulaymania Water supply and

treatment plant, water supply network and transmission lines

Type of Project: Underground water supply wells, transmission lines, water distribution pipes, water tanks, pumping stations, sewage networks, waste water pumping stations, automation and control (SCADA)Total value of works = 71,580,000 USD

Services: Team Leader / Chief Resident Engineer / Contract Manager - Works Supervision and Control / Khatib & Alami, Lebanon

design documents control - review the technical design and specifications issued by the designers team; review the technical solutions and methods proposed by contractor;coordination of the project controls activities on site; monitor the progress of works; monitor the compliance with the works quality conditions.

Client: République Libanaise - Ministère de l’Energie et de l’Eau

Location: Faraya province, LebanonProject: Boqaata DamType of Project: RCC dam

H = 71,5 mL = 222 mV = 180.000 m3 RCC and 50.000 RC.

Services: Deputy Contract Managerdesign documents control - review the technical design documents and specifications issued by the designers team; review the technical solutions and methods proposed by contractor;coordination of the project controls activities on site; monitor the progress of works; monitor the compliance with the works quality conditions; verify the compliance with the safety regulations

Client: ANBT (National Agency for Dams and Transfers)Location: Wilaya de Tipasa, AlgeriaProject: Kef Eddir DamType of Project: Earth Dam with clay core

H = 93 mL = 478 mStorage Capacity = 123 million m3

Services: Contract Manager technical support for remedial works at dam's body;

Page 3 / 24

Page 4: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

technical support for implementing a delays recovery scheme;design documents control - review the technical design and specifications issued by the designers team; review the technical solutions and methods proposed by contractor;coordination of the project controls activities on site; monitor the progress of works; monitor the compliance with the works quality conditions; liaison with the Employer

Client: Kurdistan Regional Government (Iraq) General Directorate for Dams & Reservoirs

Location: Kurdistan Region, IraqProject: Verification of the design documents for 40 (forty)

dams in the Region. Type of Project: Mixed types of dams (earthfill, rockfill, RCC, RC),

with complex functions (flood control, water storage, hydro-power, irrigation, water supply)

Services: Leading a multi-disciplinary team of verification engineers (geotechnical, hydraulics, structural)Review and verification of the design documents prepared for the regional dams implementation plan.

Client: Kurdistan Regional Government (Iraq) General Directorate for Dams & Reservoirs

Location: Kurdistan Region, IraqProject: Design Control of Basara DamType of Project: Mixed section (RCC + earthfill) and HPP

H = 54,7 mL = 345 mStorage Capacity = 59,7 million m3

HPP = 2x2,3 MWServices: Review and control of the project studies and

technical design of the projects;Project works planning;Technical assistance to Employer for the works tender;Technical support for mobilization and works start-up

Client: Kurdistan Regional Government (Iraq) General Directorate for Dams & Reservoirs

Location: Kurdistan Region, IraqProject: Three (3) medium and small dams:

Khornawazan dam Beduhe damJali dam

Type of Project: Rockfill / earthfill dams with clay core and riprap

Page 4 / 24

Page 5: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

protection and RC appurtenant structuresServices: Contract Manager and Works control of the

cofferdams, grouting works, watertight diaphragms, bottom discharge works, foundations preparation and other hidden works.

Client: ANBT (National Agency for Dams and Transfers)Location: AlgeriaProject: Beni Haroun Dam - Water Transfer FacilitiesType of Project: Water transfer scheme from Beni Haroun Dam

reservoir: (2) steps water intake / underground pumping station / water conveying tunnel / Total value of works = 482 million USD.

Intake tower height = 30 mPumping station in pit (depth = 54 m)Q = 504 million m3 / yearPumping height = 725 m

Services: Contract Management and design documents control - review the technical design and specifications issued by the designers team; review the technical solutions and methods proposed by contractor;coordination of the project controls activities on site; monitor the progress of works; monitor the compliance with the works quality conditions.

Client: ANBT (National Agency for Dams and Transfers)Location: Wilaya of Ghardaia, AlgeriaProject: Flood control works on M'Zab ValleyType of Project: Flood protection works for Ghardaia, El Atteuf and

Bounoura towns:Dams (earthfill)River banks protection and consolidationCollectors system

Services: Contract Manager design documents control - review the technical design and specifications issued by the designers team; review the technical solutions and methods proposed by contractor;coordination of the project controls activities on site; monitor the progress of works; monitor the compliance with the works quality conditions.

Client: Ministry of Agriculture and Rural Development / World Bank Programme - Romania

Location: Romania (several counties)Project: Rehabilitation of Irrigation Systems (World Bank

program) - Phase I + IIRomania

Type of Project: 4 (four) irrigation systems (Sadova-Corabia / Terasa

Page 5 / 24

Page 6: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

Covurlui / Terasa Brailei / Terasa Viziru ), including the main pumping station of Barbosi;Total area = 100,000 haTotal value of rehabilitation works = 102,980,000 USD

Services: Contract Manager / Team Leader - Works Supervision and Control

assistance for Client for the procurement of construction works and selection of main suppliers; design documents control - review the technical design and specifications issued by the designers team; review the technical solutions and methods proposed by contractor;coordination of the project controls activities on site; monitor the progress of works; monitor the compliance with the works quality conditions.

Client: Ministry of Regional Development - RomaniaLocation: Giurgiu county - RomaniaProject: Rehabilitation & Extension of Sewage & Water

Supply Networks (South East Region - Romania, Giurgiu County) - European Union Program

Type of Project: Underground water supply wells, water distribution pipes, water tanks, pumping stations, sewage networks, waste water pumping stations, automation and control (SCADA)Total value of works = 71,580,000 USD

Services: Contract Manager / Team Leader - Works Supervision and Control

design documents control - review the technical design and specifications issued by the designers team; review the technical solutions and methods proposed by contractor;coordination of the project controls activities on site; monitor the progress of works; monitor the compliance with the works quality conditions.

Client: Ministry of European Integration - RomaniaLocation: RomaniaProject: Large Scale Infrastructure Projects (PHARE

Program) - RomaniaType of Project: Municipal sewage system (Calafat town; Municipal

waste water treatment plant (WWTP) and pumping station (Calafat town); Industrial Park (Turnu Magurele town); A = 10,000 m2; Offices and industrial platform (Botosani); A = 12,000 m2; Logistic park (Suceava); A = 11,000 m2; Logistic and storage facilities for agricultural products (Cluj)Total value of works = 35,000,000 USD

Page 6 / 24

Page 7: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

Services: Contracts Manager / Team Leader - Works Supervision and Control

design documents control - review the technical design and specifications issued by the designers team; review the technical solutions and methods proposed by contractor;

coordination of the project controls activities on site; monitor the progress of works; monitor the compliance with the works quality conditions.

Client: Ministry of Municipalities - BulgariaLocation: Ruse city (Bulgaria)Project: Rehabilitation of the Municipal Water and Sewage

Scheme (EU Programme)Type of Project: Rehabilitation and extension of the city's sewage

system

Services: Contract Manager & Technical assistance for emergency and remedial works: review of the technical solutions for remedying the defective works; prepare and coordinate the implementation of the remedial works

B) Contract Management (1974 - 2003)

Client: National Water Company (CNAR) - RomaniaLocation: Buzau county, RomaniaProject: Siriu DamType of Project: rockfill dam + HPP

H = 123 mL = 510 mQ spillway = 1,720 m3/secHPP = 166 MWTunnels and galleries = 7,8 km

Services: Contract Manager: direct coordination of the works on site; purchasing and procurement (materials, equipment, subcontractors); organizing and planning of works; quality inspections of works; works commissioning.

Client: National Water Company (CNAR) - RomaniaLocation: Buzau county, RomaniaProject: Ciresu - Surduc Dam and HPP (Phase I)Type of Project: Rockfill dam

H = 65 m;HPP power = 55 MWTunnels and galleries = 16,5 km

Services: Contract Manager: direct coordination of the works on site; purchasing and procurement (materials, equipment, subcontractors); organizing and

Page 7 / 24

Page 8: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

planning of works; quality inspections of works; works commissioning.

Client: SMIRRI BTP (Morocco)Location: GuineeaProject: Labe Dam Type of Project: Intake tower (H) = 75 meters

Tunnels and galleries = (610 + 680) metersHeadrace = 700 metersReservoir volume = 200,000,000 m3

Services: Contract Manager for infrastructure works: organizing and planning of works / direct coordination of the works on site.

Client: ARCIF S.A. (Romania)Location: Krivoirog, UkraineProject: Krivoirog Ore Processing FacilityType of Project: Infrastructure and slurry reservoir damServices: Contract Manager of infrastructure works:

organizing and planning of works / direct coordination of the works on site.

Client: Hunedoara and Oradea County Councils (Romania)Location: RomaniaProject: Development of water supply infrastructure Type of Project: Municipal water supply network, including water

treatment and water pumping stationsServices: Design coordination and control

Client: World Bank ProgrammeLocation: RwandaProject: Development of infrastructure works Type of Project: post-war roads and municipal utilities rehabilitation

in the region of Kigali capital cityServices: Contract Manager: direct coordination of the works

on site; purchasing and procurement (materials, equipment, subcontractors); organizing and planning of works; quality inspections of works.

Client: Ministry of Culture - RomaniaLocation: BucharestProject: National History Museum buildingServices: Construction manager: direct coordination of the

works on site; purchasing and procurement (materials, equipment, subcontractors); organizing and planning of works; quality inspections of works.

Client: ARCIF S.A.Location: IraqProject: Irrigation System Kirkuk - Iraq

Page 8 / 24

Page 9: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

Type of Project: Large scale irrigation systemArea served = 100,000 haMain canal (L) = 22 km; Secondary canals = 100 kmTertiary canals = 300 km; Bridges = 5 pcs.Art works and special works = 25 pcs.

Services: Contract Manager: direct coordination of the works on site; purchasing and procurement (materials, equipment, subcontractors); organizing and planning of works; quality inspections of works.

Client: ARCIF S.A.Location: IraqProject: Irrigation & Drainage System Hilla

Type of Project: Large scale irrigation and drainage systemArea served = 153,400 haCanals length & art works = 100,22 km

Services: Contract Manager: direct coordination of the works on site; purchasing and procurement (materials, equipment, subcontractors); organizing and planning of works; quality inspections of works

KEYPROFESSIONALEXPERIENCE(SUMMARY)

(October 2014 – March 2015)Deputy Contract Manager / Deputy Chief Resident Engineer for Supervision of the Works for an RCC Dam in LebanonBoqaata Dam, Lebanon

(August 2014 – October 2014)Team Leader, Chief Resident Engineer, Contract Manager with Khatib & Alami Lebanon Consulting EngineersProject financed by JICA

(August 2013 – August 2014)Contract Manager / Team Leader (Chef de Mission) for Technical Assistance to the client ANBT (National Agency for Dams and Transfer), AlgeriaKef Eddir dam, Wilaya de Tipasa, Algeria

(Jan 2013 – August 2013)Kurdistan Regional Government (Ministry of Agriculture and Water Reservoirs)Adviser - Supervision of infrastructure works (large scale projects)

(May 2012 - December 2012)Kurdistan Regional Government (Ministry of Agriculture and Water Reservoirs)Technical Expert (Team Leader) - Dams and Irrigation Projects (August 2010 - May 2012)Ministry of Agriculture and Rural Development (Romania) & World Bank

Page 9 / 24

Page 10: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

Contract Manager/ Team Leader - Construction Supervision Rehabilitation of Irrigation Schemes in Romania (Phase II)

(2008 - Dec 2009)TPF Utilities (Belgium) Contract Manager / Team Leader - Construction Supervision

Rehabilitation of Municipal Water Supply and Sewage Systems - Giurgiu County (Romania)

(2006 - 2008)Ministry of Agriculture and Rural Development (Romania) & World Bank RomaniaTeam Leader - Construction Supervision

Rehabilitation of Irrigation Schemes in Romania (Phase I)

(2004 - 2006) BG Ingenieurs Conseils SA (Switzerland)/ Team Leader - Construction Supervision

Flood Control Dams and Main Sewer - M'Zab Valley (Wilaya of Ghradaia, Algeria)

(2003 - 2004) Inocsa Ingenieria SL (Spain) & Ministry of European Integration (Romania)Deputy Team Leader - Construction Supervision

Large Scale Infrastructure Projects ( PHARE 2001 program)

(2002- 2003) Government fo Algeria (Ministry of Water Resources) & Sogreah (France) Contract Manager / Team Leader - Construction Supervision

Beni Haroun Dam - Water Transfer Unit (Algeria)

(2001 - 2002) Schleker GbmH (Germany)Construction manager - Civil Works

National Logistic Center

(1999 - 2001) SHDS International Engineers (Romania)Design Manager

Design of water and sewage infrastructure systems - Hunedoara amd Oradea Counties (Romania)

(Jan 1998 - Dec 1998) HDS Ingenieurs Conseils (Switzerland)Team Leader - Construction Supervision

Development of post-war infrastructure networks - Kigali region (Rwanda)

(1997 - 1998)

Page 10 / 24

Page 11: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

VIACONS (Romania)Executive Manager (Design Division)

Design of modernization works for national roads.

(1996 - 1997) SMIRRI BTP (Morocco)Contract Manager (Construction)

Labe Dam (Infrastructure) – Guinea. 7 cities Water supply schemes all over Guineea

(1994 - 1996) ARCIF S.A. (Romania)

Contract Manager Infrastructure and slurry reservoir dam - Ore Processing Facility,

Krivoirog (Ukraine)

(1988 - 1991) TRUSTUL CARPATI S.A.(Romania)Construction Manager

National History Museum - Bucharest, Romania(1986 - 1988) TCH Bucuresti S.A. (Romania)Technical Manager

Ciresu - Surduc Dam and HPP (Phase I)

(1982 - 1986) ARCIF S.A. (Romania)Contract Manager

Kirkuk and Al-Hilla Irrigation Systems (Iraq)

(1974- 1982) TCH Bucuresti S.A. (Romania)Construction Manager

Siriu Dam and Nehoias HPP

FULL PROFESSIONAL RECORD

October 2014 – March 2015 Deputy Contract Manager / Deputy Chief Resident Engineer for Supervision of the Works for an RCC Dam in LebanonBoqaata Dam, Lebanon

Review existing studies; Review existing technical design documentation; Prepare design review reports Inspect on-going works Prepare works inspection reports Coordinate the supervision team; Overall management of the construction supervision activities; Review the detailed design documents submitted by Contractor; Direct supervision of the contractor’s activities on site;

Page 11 / 24

Page 12: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

Organize the site and project meetings; Advise the Client with respect to any and all construction activities issues; Approve the sources of materials proposed to be used by the Contractor. Mitigate the construction risks (delays, quality, etc.) Follow up the contractor’s performance (time, cost, quality); approval of contractors' site installation; approval of equipment temporarily imported by contractors; approval of proposed sub-contractors with the prior agreement of the Employer; approval of contractor's proposal for traffic management and safety at work sites for his equipment; take the necessary measures to increase the rate of the works and advise the Employer accordingly in

case of slippage in the progress of the Works, with reference to the original or updated and approved work programme and if a postponement of the contractual Completion Date is foreseen the Consultant shall evaluate the implications for the contract and advise the Employer on the consequences of such postponement;

approval of work programme based on proposed resources, and the updated programme; Coordinate with third party designers for the implementation of technical solutions modifications; Assess the contractor’s claims and requests for change orders and variation orders; Review the design details submitted by contractors; Review contractor’s applications for payment; Issue the Payment certificates; Liaise with the Client’s main office (contract administration)

August 2013 – August 2014 Contract Manager / Team Leader (Chef de Mission) for Technical Assistance to the client ANBT (National Agency for Dams and Transfer), AlgeriaKef Eddir dam, Wilaya de Tipasa, Algeria

Advise the Employer on the construction supervision and project controls procedures for Kef Eddir dam in Wilaya de Tipasa, Algeria;

Advise the Employer on all the matters related to the execution of the works, the implementation of best construction supervision and project controls practices;

Review and advise upon the control methodologies proposed by the controlling company, TECSULT – AECOM Canada;

Technical support for the Employer in the implementation of the solution requested by the works contractor;

The dam is a 96 m high, embankment dam with clay core and upstream and downstream protection in rock fill. The main quantities of the Dam are:

Excavations : 2.360.000,00 cm; Local Material Backfilling: 5.000.000 cm; Concrete for the structures: 137.000 cm

August 2014 – October 2014 Kurdistan Regional Government – Halabja and Sulaymania Water supply and treatment plant, water supply network and transmission lines - Ministry of MunicipalitiesTeam Leader, Chief Resident Engineer, Contract Manager (Replacement) with Khatib & Alami Lebanon Consulting Engineers

Project financed by JICA Review existing technical design documentation;

Page 12 / 24

Page 13: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

Prepare design review reports Inspect on-going works Prepare works inspection reports Coordinate the supervision team; Overall management of the construction supervision activities; Review the detailed design documents submitted by Contractor; Direct supervision of the contractor’s activities on site; Organize the site and project meetings; Advise the Client with respect to any and all construction activities issues; Approve the sources of materials proposed to be used by the Contractor. Mitigate the construction risks (delays, quality, etc.) Follow up the contractor’s performance (time, cost, quality); approval of equipment temporarily imported by contractors; approval of proposed sub-contractors with the prior agreement of the Employer; approval of contractor's proposal for traffic management and safety at work sites for his equipment; take the necessary measures to increase the rate of the works and advise the Employer accordingly in case

of slippage in the progress of the Works, with reference to the original or updated and approved work programme and if a postponement of the contractual Completion Date is foreseen the Consultant shall evaluate the implications for the contract and advise the Employer on the consequences of such postponement;

approval of work programme based on proposed resources, and the updated programme; Coordinate with third party designers for the implementation of technical solutions modifications; Assess the contractor’s claims and requests for change orders and variation orders; Review the design details submitted by contractors; Review contractor’s applications for payment; Issue the Payment certificates; Liaise with the Client’s main office (contract administration)

Jan 2013 — August 2013 Kurdistan Regional Government – Ministry of Agriculture and Water ResourcesAdviser - Supervision of infrastructure works (large scale projects)

Advise the Employer on the construction supervision and project controls procedures for large dams and HPP works;

Advise the Employer on the implementation of best construction supervision and project controls practices for three recently tendered dams (Basara, Bastora, Bawanoor);

Review and advise upon the control methodologies proposed by the controlling company; Technical support for the Employer in the implementation of the three dams projects

May 2012 - Dec 2012 Kurdistan Regional Government – Ministry of Agriculture and Water Resources (General Directorate for Dams and Reservoirs)Team Leader - International Experts Panel

Assessment of technical documentations and contractors’ technical performance (irrigation and hydropower dams and reservoirs works). Forty (40) dams studies and design documentations (small / medium / large / major dams) examined and assessed. Review existing studies; Review existing technical design documentation; Prepare design review reports Inspect on-going works Prepare works inspection reports

Page 13 / 24

Page 14: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

Advise GDDR with respect to the corrective measures for design and construction works Close supervision of the contractors and the supervision team for three dams:

Khornawazan Dam in Sulaymanya District which consist of an embankment dam with the following characteristics: Approx. 800.000 cm of embankment, which was modified during the initial construction period

in rock fill dam with the proper calculation of the stability; dam height (downstream foot) : 23.5 m ; dam crest length : 195 m ; crest elevation : 390.50 m a.s.l. ; normal water level : 385 m a.s.l. ; useful storage capacity : 6.056.362 cm Maximum water level: 388 m a.s.l.

Beduhe Dam in the northern province of Duhok which consist of an dam body using compacted rock fill the following characteristics:

Around 100.000 cm of excavation; Approx. 500.000 cm of embankment, which was modified during the initial construction period

in rock fill dam with the proper calculation of the stability; 15.000 cm of concrete; 28.000 lm of grouting boreholes.

Jali Dam in Erbil district which consist of an embankment dam with the following characteristics:

20 meter height; The upstream slope is covered with a hand placed riprap of 40 cm thickness The downstream slope is covered by coarse gravel and fine cobbles of 40cm thickness to

protect the slope from erosion. The dam consists of a seal core of clayey silt soil; Excavation volume is 40.000 cm; Back filling is 175.000 cm; The clay core is 35.000 cm; The filters are around 11.000 cm.

Aug 2010 — May 2012 Ministry of Agriculture and Rural Development (Romania) - World Bank (Romania)Contract Manager /Team Leader - Construction Supervision

World Bank funded program;All the supervision works were performed in conformity with the Red FIDIC rules. Rehabilitation of the Irrigation Schemes Terasa Brailei, Terasa Viziru, Campia CovurluiTotal Area included into the Rehabilitation and Reform Program = 100.000 ha;Total estimated cost = 102.980.000 USDArea (Phase Two) = 61.193 haThe main quantities performed by the works contractor was:

Around 400.000 cm of backfilling for the refurbishment of the damaged parts of the channles; Around 15.000 cm of concrete for concrete lining and structures; Hydro mechanical and electrical parts refurbishment.

Phase Two included also the rehabilitation of the Main Pumping Station of Barbosi, serving Campia Covurlui Irrigation System (Galati County).

Coordinate the supervision team; Overall management of the construction supervision activities; Review the detailed design documents submitted by Contractor; Direct supervision of the contractor’s activities on site; Organize the site and project meetings; Advise the Client with respect to any and all construction activities issues; Approve the sources of materials proposed to be used by the Contractor.

Page 14 / 24

Page 15: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

Mitigate the construction risks (delays, quality, etc.) Follow up the contractor’s performance (time, cost, quality); approval of contractors' site installation; approval of equipment temporarily imported by contractors; approval of proposed sub-contractors with the prior agreement of the Employer; approval of contractor's proposal for traffic management and safety at work sites for his equipment; take the necessary measures to increase the rate of the works and advise the Employer accordingly in case

of slippage in the progress of the Works, with reference to the original or updated and approved work programme and if a postponement of the contractual Completion Date is foreseen the Consultant shall evaluate the implications for the contract and advise the Employer on the consequences of such postponement;

approval of work programme based on proposed resources, and the updated programme; Coordinate with third party designers for the implementation of technical solutions modifications; Assess the contractor’s claims and requests for change orders and variation orders; Review the design details submitted by contractors; Review contractor’s applications for payment; Issue the Payment certificates; Liaise with the Client’s main office (contract administration) attend to the work inspections carried out by the State Inspectorate for Quality in accordance with the

Romanian Law; organize provisional and temporary taking – over of work and submit all supervision documents to the taking

– over committee according to the Applicable Law; issuing of Taking-Over Certificate; prepare final statement of accounts; recommend returns of guarantees and retention; Supervise, verify and correct, if necessary, the Contractor's "as-built" drawings Project reporting

Jan 2008 - Dec 2009 TPF Utilities (Belgium)

Contract Manager / Team Leader - Construction SupervisionMinistry of Environment – Romania (MMU Region 3 South Muntenia-Pitesti)County Council – Giurgiu, Romania(EU Funded Program – Sectorial Operational Projects “Environment” / POS Mediu – Axis 1)SC Apa Service S.A. – GiurgiuAll the supervision works were performed in conformity with the Red FIDIC rules.

Rehabilitation and new works for the treatment and distribution of potable water, as well as the treatment and collection of wastewater for three (3) settlements in Giurgiu County ( Slobozia, Bolintin Vale, Mihailesti).

Coordinate the supervision team; Overall management of the construction supervision activities; Direct supervision of the contractor’s activities on site; Organize the site and project meetings; Advise the Client with respect to any and all construction activities issues; Approve the sources of materials proposed to be used by the Contractor. Mitigate the construction risks (delays, quality, etc.) Follow up the contractor’s performance (time, cost, quality); Approval of contractors' site installation; Approval of equipment temporarily imported by contractors; Approval of proposed sub-contractors with the prior agreement of the Employer; Approval of contractor's proposal for traffic management and safety at work sites for his equipment; Take the necessary measures to increase the rate of the works and advise the Employer accordingly in case

of slippage in the progress of the Works, with reference to the original or updated and approved work programme and if a postponement of the contractual Completion Date is foreseen the Consultant shall

Page 15 / 24

Page 16: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

evaluate the implications for the contract and advise the Employer on the consequences of such postponement;

Approval of work programme based on proposed resources, and the updated programme; Coordinate with third party designers for the implementation of technical solutions modifications; Assess the contractor’s claims and requests for change orders and variation orders; Review the design details submitted by contractors; Review contractor’s applications for payment; Issue the Payment certificates; Liaise with the Client’s main office (contract administration) Attend to the work inspections carried out by the State Inspectorate for Quality in accordance with the

Romanian Law; Organize provisional and temporary taking – over of work and submit all supervision documents to the

taking – over committee according to the Applicable Law; issuing of Taking-Over Certificate; Prepare final statement of accounts; Recommend returns of guarantees and retention; Supervise, verify and correct, if necessary, the Contractor's "as-built" drawings. Project reporting

2006 - 2008 Ministry of Agriculture and Rural Development (Romania) – World Bank (Romania)Contract Manager /Team Leader - Construction Supervision

Rehabilitation of Irrigation Schemes – Romania ( Phase One )World Bank funded program; All the supervision works were performed in conformity with the Red FIDIC rules. Rehabilitation of the Irrigation Schemes Sadova – Corabia, Tecuci-NicorestiTotal Area included into the Rehabilitation and Reform Program = 100.000 ha;Total estimated cost = 102.900.000 USDArea (Phase One) = 50.000 ha ( Sadova Corabia = 40,000 ha, Tecuci – Nicoresti = 10,000 ha) The main quantities performed by the works contractor was:

Around 1.000.000 cm of backfilling for the refurbishment of the damaged parts of the channles; Around 23.000 cm of concrete for concrete lining and structures; Hydro mechanical and electrical parts refurbishment.

Phase One included also the rehabilitation of the Main Pumping Station of Sadova (on Danube River), serving Sadova – Corabia Irrigation System (Dolj County)Total cost of rehabilitation works – Phase One = 60,90 mil. USD

Coordinate the supervision team; Overall management of the construction supervision activities; Direct supervision of the contractor’s activities on site; Organize the site and project meetings; Advise the Client with respect to any and all construction activities issues; Approve the sources of materials proposed to be used by the Contractor. Mitigate the construction risks (delays, quality, etc.) Follow up the contractor’s performance (time, cost, quality); approval of contractors' site installation; approval of equipment temporarily imported by contractors; approval of proposed sub-contractors with the prior agreement of the Employer; approval of contractor's proposal for traffic management and safety at work sites for his equipment; take the necessary measures to increase the rate of the works and advise the Employer accordingly in case

Page 16 / 24

Page 17: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

of slippage in the progress of the Works, with reference to the original or updated and approved work programme and if a postponement of the contractual Completion Date is foreseen the Consultant shall evaluate the implications for the contract and advise the Employer on the consequences of such postponement;

approval of work programme based on proposed resources, and the updated programme; Coordinate with third party designers for the implementation of technical solutions modifications; Assess the contractor’s claims and requests for change orders and variation orders; Review the design details submitted by contractors; Review contractor’s applications for payment; Issue the Payment certificates; Liaise with the Client’s main office (contract administration) attend to the work inspections carried out by the State Inspectorate for Quality in accordance with the

Romanian Law; Organize provisional and temporary taking – over of work and submit all supervision documents to the

taking – over committee according to the Applicable Law; issuing of Taking-Over Certificate; prepare final statement of accounts; recommend returns of guarantees and retention; Supervise, verify and correct, if necessary, the Contractor's "as-built" drawings. Project reporting

2004 - 2006 Government Of Algeria – Hydraulic Dept. Of The Wilaya Of Ghardaia BG Ingenieurs Conseils S.A. (Switzerland)Contract Manager / Team Leader - Supervision of construction works

Flood Control Dams & Main Sewer ; Ghardaia, M’zab ValleyM’Zab Valley Flood Control and Protection:- Flood retaining dam, located at El Abiodh, on the upstream sector of the oued basin;- Storage capacity = 1.500.000 m3- Dam type = embankment dam- Height = 15 meters ;- Length = 1100 meters ;- Embankments volume = 653.000 m3 of backfills, including the backfilling for the damaged and new parts of the Oued, in view of the realization of the protection for the banks ;

Waste water collecting system (for the Ghardaia and Bounoura towns):- main sewer collector;- upstream sector - circular pipe of D = 1000 mm, with a length of 3,5 km- downstream sector – ovoid collector with a length of 1,7 km;- bank protection wall – with an an average height of 4 meters, with a length of 2 km;

financial management of the civil work contracts. prepare monthly disbursement tables continuous follow-up of the contractors’ work programs and monitoring cash-flow in relation to the planned

schedules; approval of contractors' site installation; approval of equipment temporarily imported by contractors; approval of proposed sub-contractors with the prior agreement of the Employer; approval of contractor's proposal for traffic management and safety at work sites for his equipment; approval of work programme based on proposed resources, and the updated programme;

Page 17 / 24

Page 18: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

approval of quantities and calculations established by contractors; approval of corrections/modifications of geometric survey, if required; approval of earthmoving scheme for earthworks; approval of procedures for construction of drainage works; approval of procedures for plant rehabilitation works; approval of proposed sources of materials; approval of construction techniques for structures; approval of setting-out of the works; inspect the works to check whether performance complies with specifications and drawings; order and approve tests of materials and of completed works, and order the removal of improper or

substandard work; control materials incorporated into the works; examine and attend the measurement of any work that is about to be covered or put out of view before

permanent work is placed thereon; record work site daily events and quantities to pay (subject to geometric and quality tests); take the necessary measures to increase the rate of the works and advise the Employer accordingly in case

of slippage in the progress of the Works, with reference to the original or updated and approved work programme and if a postponement of the contractual Completion Date is foreseen the Consultant shall evaluate the implications for the contract and advise the Employer on the consequences of such postponement;

establish content and formats of a system of weekly reports by the Contractor to the Engineer and the Employer;

Organize provisional and temporary taking – over of work and submit all supervision documents to the taking – over committee according to the Applicable Law;

calculate liquidated damages, if necessary; supervise the Contractor in all matters concerning safety and care of works; issuing of Taking-Over Certificate; prepare final statement of accounts; project reporting

2003 - 2004 Ministry of European Integration (Romania) - Inocsa Ingenieria (AECOM)Deputy Contract Manager / Deputy Team Leader - Construction Supervision

Large Scale Infrastructure Projects – PHARE 2001 Program - RomaniaPHARE 2001 funded projects – development of local infrastructure:

Turnu MagureleIndustrial park ( Area = 10,000 m2 ) Calafatmunicipal sewage systemmunicipal waste water treatment plant and pumping station Botosanioffices and industrial area ( approx. 12,000 m2 ) Suceavalogistic and small industry park ( approx. 11,000 m2) Clujwhole sale market and storage facilities for agricultural products

All the supervision works were performed in conformity with the Red FIDIC rules.

Page 18 / 24

Page 19: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

The estimated total value of the construction works = 35,000,000 USD carry out the duties of the Engineer, as described in the civil works contract documents; manage the Consultant's team; elaborate the programme of activities of his team; take care of his team's logistics; check that the services are carried out in accordance with the Terms of Reference; verify and certify the interim and final statements of work; produce the periodic reports; produce the final reports produce any other reports as required by the Employer inspect the works during the Defects Liability Period and issue the related reports; advise the Client on any issue likely to affect the financial resources, e.g., variation orders, or the scope of

work; co-ordinate daily the supporting staff assigned under his direct control, ensuring a constant supervision and

quality control of the works in progress. Follow-up the works in order to advise the Resident Project Manager about any event which might create

disturbance or disorders on site. Analyze any claims for extensions of time and additional and unexpected cost and generate reports

complete with recommendations for the Employer. draw up variation orders and value all varied work in accordance with the Contract. carry out effective financial management of the works contract by checking and confirming contractors’ cash

flow projections, making projections of costs to completion, maintaining a data-base of payments to the contractor, and maintaining all records necessary for auditing purposes and the defense of claims.

keep weekly records of all quantities approved for payment; prepare, in close co-ordination with the Project Director all documentation regarding the Monthly Statement and the Interim Payment Certificate (IPC), and particularly the Supporting Documents to the IPC's.

verify constantly, in co-ordination with the Project Director and the Senior Quality Engineer, that the payable quantities refer only to works which already passed the Quality Control.

act as the reference person, on behalf of the Project Director, for answering to all queries and clarifications from PMU, concerning the Interim Payment Certificates and the Monthly Statements.

2002 - 2003 Government of Algeria, Ministry of Water Resources &Sogreah (France)Supervision Engineer - Construction

The transfer system of Beni Haroun is the main system supplying the Constantine and Aures areas. It provides the transfer of 504 million m3 / year from the dams of Beni Haroun and Bou Sabia towards six (6) Communities (Wilayas): Batna, Kenchela, Mila, Oum El Bouaghi, Constantine and Jijel.The pumping station of Beni Haroun, located on the left bank of the reservoir of Beni Haroun, at 30 km. North-West of Constantine, is the most powerful pumping station of the system. This station is the head of the transfer system.The transfer station has an installed power of 180 MW and is capable of pump an annual volume of 504 million m3 over a level maximum difference of 680 meters, to the expansion basin of d’Atn Tinn, which is the highest point of the sector leading to the intermediary reservoir of Oued Athmania.The works also included:A water intake with two steps and retaining threshold;An intake tunnel of 100 meter length;A double discharge pressure pipes lines of 1400 mm diameter and 130 meters length until the water-hammer protection station;

Page 19 / 24

Page 20: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

A service & operation building;An administrative building;A connection station for two 220 KV lines for the electric power supply of the station.

The mission of the Consultant included : assistance for the evaluation of the offers submitted by the Contractors, the control of design prepared by

Alstom-Dragados, technical assistance during construction and supervision of the execution of the works through a team of

resident engineers. carry out the duties of the Engineer, as described in the civil works contract documents; manage the Consultant's team; elaborate the programme of activities of his team; take care of his team's logistics; check that the services are carried out in accordance with the Terms of Reference; verify and certify the interim and final statements of work; produce the periodic reports; produce the final reports produce any other reports as required by the Employer advise the Client on any issue likely to affect the financial resources, e.g., variation orders, or the scope of

work; supervise execution of works and check the finished works before taking-over; timely inform Client about probable Variation Orders and unexpected increases in costs, resulting from the

Site Instruction issued to the Contractor; co-ordinate daily the supporting staff assigned under his direct control, ensuring a constant supervision and

quality control of the works in progress. Follow-up the works in order to advise the Client about any event which might create disturbance or

disorders on site. co-ordinate the activities of the Quantity Surveyors, for the daily measurements of the approved works. analyse any claims for extensions of time and additional and unexpected cost and generate reports complete

with recommendations for the Employer. draw up variation orders and value all varied work in accordance with the Contract. prepare contract addenda. carry out effective financial management of the works contract by checking and confirming contractors’ cash

flow projections, making projections of costs to completion, maintaining a data-base of payments to the contractor, and maintaining all records necessary for auditing purposes and the defence of claims.

keep weekly records of all quantities approved for payment; prepare, in close co-ordination with the Project Director all documentation regarding the Monthly Statement and the Interim Payment Certificate (IPC), and particularly the Supporting Documents to the IPCs.

verify constantly, in co-ordination with the Project Director that the payable quantities refer only to works which already passed the Quality Control.

act as the reference person, on behalf of the Project Director, for answering to all queries and clarifications from PMU, concerning the Interim Payment Certificates and the Monthly Statements.

2001 - 2002 Schlecker GbmH (Germany)

Construction managerNational logistic centerResponsible for the organization, planning and supervision of the subcontractors.In charge with the overall execution of the construction works for the project.

Page 20 / 24

Page 21: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

1999 - 2001 SHDS International Engineers (Romania)Design manager – infrastructure networks

Development of water supply & sewage in local communities ( Hunedoara County, Oradea County)Design coordination of municipal water supply and waste water networks

Jan 1998 - Dec 1998 HDA Ingenieurs Conseils – SwitzerlandContract Manager / Team Leader - Construction Supervision

World Bank Relief Programs (post-war)Rehabilitation of existing roads and utilities networks damaged during the civil war;Implementation of new rural roads and utilities networks in the surrounding areas of Kigali capital city.All the supervision works were performed in conformity with the Red FIDIC rules.

Acting as Team Leader for the entire supervision team (Resident Engineers, Site Inspectors). Responsible for the relation with the Client, the local authorities, the Contractors. In charge with the planning and organization of the supervision activities. Checking and validating the Contractors’ design documents, quality control program, works statements Coordinating and chairing the Project Meetings (design and construction progress). Evaluation of Contractor’s and/or Client’s requests for changes and/or variations within the project In charge with the Project Status Reporting and with the control and validation of the payment documents

issued by the Contractors.

1997 - 1998 VIACONS (Romania)Executive Manager (Design Division)

Development / modernization of national roads network (Romania)Extension / rehabilitation of national and local roads sectors coordination of the activity of all design teams within the company. tenders and design contracts administration.

1996 - 1997 SMIRRI BTP – MoroccoContract Manager / Executive manager (Construction)

Labe Dam (infrastructure) – Guinea as the part of water supply scheme for 6 cities in Guineea. Earth fill body with an approximate quantity of local material earthworks of 375.000 cm; Plastic sheet upstream protection ;

Tower intake; tunneled head race Responsible for the organization, planning and supervision of the infrastructure works and temporary

setting. Responsible for the relations with the local authorities and the main contractors.

1994 - 1996 ARCIF S.A (Romania)Contract Manager (civil works)

Infrastructure and slurry reservoir dam - Ore Processing Facility, Krivoirog (Ukraine)

1992 - 1994 Independent EngineerConstruction manager (civil works)

Housing project (Koln)

Page 21 / 24

Page 22: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

1988 - 1991 TRUSTUL CARPATI S.A. (Romania)Construction Manager (civil works)

National History Museum – Bucharest (Romania)

Responsible for the overall organization and planning of the construction activities for structural works on site.

In charge with the supervision, coordination and control of the materials and workforce on site. In charge with the works status reporting and construction documents

1986 - 1988 TCH Bucharest S.A. (Romania)Technical Manager

Ciresu - Surduc dam and HPP (Phase I ) – RomaniaIt was designed as a rock fill dam with clay core, 90 m high and around 300 m length at the upper part.Due to the political changes in Romania, the construction of the dam was stopped at the phase of excavation for the foundation and the deviation gallery.

Rock fill body, central spillway, diversion channel, head race tunnel, stilling basin, underground HPPTechnical coordination and overall control of civil works

1982 - 1986 Ministry of Agriculture – Iraq / General Directorate for Irrigation and Drainage WorksARCIF S.A. (Romania)Contract Manager

Construction of irrigation systems Kirkuk and Al-Hilla (Iraq)

KIPA-KIRKUK project is a part of grand-scale irrigation project. Building of the main canal, three pumping stations SSI, SSIII, SSX with complete delivery and installation of electrical and electromechanical equipment. Manufacture and assembly of the pipeline in the length 33 km, with the pipes of pre-stressed concrete diameter from 1,200 to 1,800 mm., including the drainage pipeline which fitted in the irrigation system KIPA.

Technical Data:Kirkuk area:

1. 22 km of main canal for irrigation; 100 km of secondary canals2. 300 km of tertiary branches; 5 bridges; 30 km of paved and bitumen roads; 25 different art

works and ancillary structuresAL-HIILA project:

1. MC1 canal, 17,800 hectares, left side of Shatt Al-Diwaniya, 1 pumping station 2. MC3 canal, 48,600 hectares, left side of Shatt Al-Diwaniya, 1 pumping station 3. MC2 canal, 87,000 hectares, left side of Shatt Al-Diwaniya, 1 pumping station.

For both contracts the main quantities was: Around 2.000.000 cm of clay substitution for Kirkuk area and around 1.500.000 cm for Hilla Kifl area, Lining concrete around 25.000 cm; Concrete for structure around 9.000 cm; Hydro technical and mechanical equipment for different intakes.

Responsible for planning and managing design development; and handling construction co-ordination issues between related parties of the project;

Ensure the smooth progress and completion of projects within cost, time and quality standards Oversee construction aspect of site

Page 22 / 24

Page 23: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

Prepare detailed plans for project execution and resource allocation Review deliveries with Project Managers and Site Agents Liaise with the Client and Sub Contractors Supervise and coordinate all aspects of the construction process including Architect and Engineer related

activities and site layout requirements; Coordinate activities and requirements of all other Company disciplines related to site construction during

the construction process; Schedule and coordinate pre-bidding activities with Company designated Contractors/General Contractors

and hold a pre-construction meeting with the nominated General Contractor and all other parties as directed by the Company;

Conduct site visits following the commencement of site construction (not including pre-construction site walks) to verify contractor compliance with permits, drawings and Company specifications;

Monitor Construction for compliance with plans and applicable building codes; Perform work in accordance with Company’s standards, policies and procedures and at the direction of the

Project Director or his\her designee; Provide written weekly status reports in Company database on all projects assigned in a format acceptable

to the Company; Attend Status meetings and report on the status of all assigned projects. Track daily manpower for projects against approved budgets; Review and project manpower needs Use of project controls tools (i.e. estimate, cost report, schedule) in daily work execution and reinforce

expectation of Supplemental Labor contractor to same criteria; Project Completion in time and within the budget. Maintain productive relationship with the external stakeholders at site. Ensure motivation, retention and development of team. Continuously improve work practices, resources productivity, and efficiency. Manage the Accounts and Quality Assurance. Plan, organize and coordinate the entire team for the Project Completion in time and within the budget Study the drawings / site. Plan the activities, schedule bar charts jointly with planning manager. Identify resource requirement Machinery, Manpower, Material etc jointly with Planning Manager. Indent for construction material and give requirement of other resources as per the schedule. Mobilize the site as per contract requirements. Day to day monitoring of the site as per the schedule and priorities. Ensure proper allocation of manpower, materials and machinery. Monitoring the utilization of resources and reduce cost wastage. Conduct progress reviews daily and weekly. Take necessary corrective actions. Providing timely data to billing and planning engineers regarding extra items, joint measurements, holds,

additions and alterations etc. Timely communicating items debatable to sub agencies to the concerned HODs; Identifying and attend the snag points and handing over; Maintain productive relationship with the external stakeholders at site. Proactive communication with client representative on day to day progress and issues. Understand client priorities and respond appropriately. Ensuring timely preparation and submission of bills of sub agencies. Ensuring that only authorized sub agencies having valid work orders are engaged on site. Facilitate attention towards welfare of sub agencies and their workforce. Proper co-ordination with other agencies engaged by the client. Ensure compliance to ISO procedures, Quality requirements and safety standards.

Page 23 / 24

Page 24: 2015 05 21_CV_M_Stratulat_WSTP

Mihai Ioan STRATULAT - MsCE

Ensure quality work as per contract specifications and client satisfaction. Ensure adherence to safety manual in all respects. Close NCs pertaining to site and keep control on defect occurrences. Improve work practices, resource productivity, efficiency, Take necessary steps to avoid recurrence of similar problems. Identify and implement improved methods and procedures.

1974 - 1982 TCH Bucharest (Romania)Construction Manager

Siriu Dam and HPP (Romania) - Hydropower and flood control dam;Rock fill body, central spillway, diversion channel, hydromechanical equipment, roads and viaducts, head race tunnel, stilling basin, underground HPP, transforming station.

Managing the construction works for the heavy civil structures of the dam In charge with the works status reporting and construction documents. In charge with the subcontracting and purchasing Checking and validating the design documents, quality control program, works statements. Coordinating and chairing the Project Meetings (design and construction progress). Evaluation of the requests for changes and/or variations within the project. In charge with the Project Status Reporting and with the control and validation of the payment documents

REFERENCES

Akram A. Rasul - General Director - Kurdistan Regional Government (General Directorate for Dams and Reservoirs)tel: 00964 7701521418 / 00964 7504468548; email: [email protected]; [email protected]

Peshraw Omer Assaad - Technical Director - Kurdistan Regional Government (General Directorate for Dams and Reservoirs); tel: 00964 7504558451 / 00964 7701576211; email: [email protected]; [email protected]

Gabriel Ionita - Senior Agriculture Specialist / Task Team Leader - World Bank (Romania); tel: +40 21 201 03 11; email: [email protected]

Youssef Tazi - President "Groupe CCGT" (former Smirri BTP) - tel: + 212 0537 630512; email: [email protected]