2015 bond projects 2… · victory middle school • estimated cost - $30 million • cm –beniton...
TRANSCRIPT
![Page 1: 2015 BOND PROJECTS 2… · VICTORY MIDDLE SCHOOL • Estimated cost - $30 million • CM –Beniton • Architect –LCA • Completion –August 22, 2016 • Status –Punch list](https://reader033.vdocument.in/reader033/viewer/2022042213/5eb6c27fd3a408204a3d50d7/html5/thumbnails/1.jpg)
2015 BOND PROJECTS WEST ADA SCHOOL DISTRICT
BOARD OF TRUSTEES UPDATE
JUNE 28, 2016
![Page 2: 2015 BOND PROJECTS 2… · VICTORY MIDDLE SCHOOL • Estimated cost - $30 million • CM –Beniton • Architect –LCA • Completion –August 22, 2016 • Status –Punch list](https://reader033.vdocument.in/reader033/viewer/2022042213/5eb6c27fd3a408204a3d50d7/html5/thumbnails/2.jpg)
VICTORY MIDDLE SCHOOL• Estimated cost - $30 million
• CM – Beniton
• Architect – LCA
• Completion – August 22, 2016
• Status – Punch list of classroom wings this week, expect to begin moving in furniture next week
• Projected cost – $27,327,836
• Prelim Architect Fees - $713,343 (Plant)
• Adjusted 2015 Bond cost - $26,614,493
• Remaining contingency - $728,131
![Page 3: 2015 BOND PROJECTS 2… · VICTORY MIDDLE SCHOOL • Estimated cost - $30 million • CM –Beniton • Architect –LCA • Completion –August 22, 2016 • Status –Punch list](https://reader033.vdocument.in/reader033/viewer/2022042213/5eb6c27fd3a408204a3d50d7/html5/thumbnails/3.jpg)
HILLSDALE ELEMENTARY• Estimated cost - $10 million
• CM – Russell
• Architect – Hummel
• Completion – August 22, 2016
• Status – Substantial completion July 30, begin moving furniture into building the first week in August
• Projected cost – $14,705,379
• Remaining contingency - $145,395
![Page 4: 2015 BOND PROJECTS 2… · VICTORY MIDDLE SCHOOL • Estimated cost - $30 million • CM –Beniton • Architect –LCA • Completion –August 22, 2016 • Status –Punch list](https://reader033.vdocument.in/reader033/viewer/2022042213/5eb6c27fd3a408204a3d50d7/html5/thumbnails/4.jpg)
MERIDIAN HIGH SCHOOL• Estimated cost - $24 million
• CM – CM Company
• Architect – Hummel
• Estimated completion – October 2017
• Status – Punch list of Phase 3B this week, Phase 5 completed March 2017, Phase 4 demo has begun, Phase 6 demo begins March 2017
• Projected cost - $20,637,382
• Remaining contingency - $1,269,339
![Page 5: 2015 BOND PROJECTS 2… · VICTORY MIDDLE SCHOOL • Estimated cost - $30 million • CM –Beniton • Architect –LCA • Completion –August 22, 2016 • Status –Punch list](https://reader033.vdocument.in/reader033/viewer/2022042213/5eb6c27fd3a408204a3d50d7/html5/thumbnails/5.jpg)
STAR MIDDLE SCHOOL• Estimated cost - $30 million
• CM – ESI
• Architect – LCA
• Estimated completion – November 2017
• Projected cost – $29,908,218
• Remaining contingency - $1,000,000
![Page 6: 2015 BOND PROJECTS 2… · VICTORY MIDDLE SCHOOL • Estimated cost - $30 million • CM –Beniton • Architect –LCA • Completion –August 22, 2016 • Status –Punch list](https://reader033.vdocument.in/reader033/viewer/2022042213/5eb6c27fd3a408204a3d50d7/html5/thumbnails/6.jpg)
FUTURE HIGH SCHOOL SITE ACQUISITION
• $2,000,000
• West of Ten Mile Road between Chinden and I-84
• 50-55 acres minimum
![Page 7: 2015 BOND PROJECTS 2… · VICTORY MIDDLE SCHOOL • Estimated cost - $30 million • CM –Beniton • Architect –LCA • Completion –August 22, 2016 • Status –Punch list](https://reader033.vdocument.in/reader033/viewer/2022042213/5eb6c27fd3a408204a3d50d7/html5/thumbnails/7.jpg)
2015 BOND SUMMARY
• 2015 Bond - $96,000,000
• Projected cost of all projects - $93,879,002
• Interest earned to date on 2015 bond - $435,000
• Unencumbered contingency - $3,142,865
• Unencumbered bond revenue - $5,698,863
• 96,000,000 – 93,879,002 = 2,120,998 + 435,000 + 3,142,865 = $5,698,863