2015 - dpe t03&tt01 synopsis (rev5)

1
TT-01 WD = 39.2 m MSL T-03 WD = 45.5 m MSL G1201 Installation scope of Work (G1201) - Final Fabricated weights w/o rigging Lift for T-03 Jacket (532 Te) Lift for T-03 Boat Landing (36 Te, excluding stabbing guides on jacket) T-03 Topsides lift (198 Te) T-03 Skirted Piles driving and Grouting (145 Te ea, 113m long, 54" dia) Single lift for TT-01 Jacket (517 Te) Lift for TT-01 Boat Landing (36 Te, excluding stabbing guides on jacket) TT-01 Topsides lift (197 Te) TT-01 Skirted Piles driving and Grouting (133 Te ea, 105 m long) Revision 5: 25-Feb-2015 Client Dubai Petroleum Establishment (DPE) Job Type Lumpsum EPCI for 2 unmanned WHP: T-03 & TT-01 Qualified weight with DPE Topsides work on unit rates - no equipment installed Job Award Amendment to Rashid C Contract signed May 14th, 2015 Job Status Design 1, Build 2' Concept Fast track project 3 Leg, skirted piles Jacket Vertical Offshore transportation Both Platforms installed in 10 days Mechnical Completion 20 February 2016 Synopsis Owner Stephanie Gambier Structure Contractual weights (Te) Net final weight (Te) T-03 Jacket 342 533 TT-01 Jacket 302 518 T-03 Deck 235 198 TT-01 Deck 235 197 T-03 Piles 290 435 TT-1 Piles 275 400 T-03 Boat Landing 18 36 TT-01 Boat Landing 18 36 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Design engineering (Plan) Actual - Design engineering Issue MTO 90% (Plan) P Actual - Issue MTO 90% (30 Jun- 24 Aug) Issue AFC dwgs for Jacket (Plan: 15 - July) P Actual - Issue AFC dwgs for Jacket (15 Jul - 20 Jul) A Receive soil report (Plan: 31-May) x Actual - Receive soil report (26 Aug) x Issue last remaining AFC dwgs (Plan: 15-Aug) x Actual - Issue last remaining AFC dwgs (14 Oct) x Fabrication Jackets & Decks (Plan) Actual - Fab Jackets & Decks (27 Aug - 17 Jan) Fabrication Skirts & Mudmat (Plan) P Actual - Fab Skirts & Mudmat (25 Sep- 07 Dec) Load out of 2 platforms decks and jackets (Plan) P Actual - Load out of 2 platforms decks and jackets A Installation by G1201 (Plan) P Actual - Installation by G1201 (05 Feb-20Feb) A AS BUILT SCHEDULE OF EXECUTION 2015 2016 Actual Actual Plan Actual Actual Plan Amendment signature with DPE 14-May-15 KOM with DPE 21-May-15 DPE to provide soil data 31-May-15 Primary steel MTO 30-Jun-15 Jacket Main legs AFC drawings 30-Jun-15 Completion of Jacket AFC drawings 19-Aug-15 completion of Deck AFC drawings 19-Aug-15 Platforms ready for load-out at DWDD 15-Jan-16 Mechanical Completion 15-Feb-16 Actual with DPE 14-May-15 21-May-15 26-Aug-15 18-Jul-15 23-Jul-15 14-Oct-15 (mudmat & pile skirts) 12-Oct-15 (grating, handrails) 24-Jan-16 20-Feb-16 Key Dates

Upload: richard-richards

Post on 12-Apr-2017

14 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2015 - DPE T03&TT01 Synopsis (rev5)

TT-01 WD = 39.2 m MSLT-03 WD = 45.5 m MSL

G1201

Installation scope of Work (G1201) - Final Fabricated weights w/o

rigging

Lift for T-03 Jacket (532 Te)

Lift for T-03 Boat Landing (36 Te, excluding stabbing guides on jacket)

T-03 Topsides lift (198 Te)

T-03 Skirted Piles driving and Grouting (145 Te ea, 113m long, 54" dia)

Single lift for TT-01 Jacket (517 Te)

Lift for TT-01 Boat Landing (36 Te, excluding stabbing guides on jacket)

TT-01 Topsides lift (197 Te)

TT-01 Skirted Piles driving and Grouting (133 Te ea, 105 m long)

Revision 5: 25-Feb-2015

Client Dubai Petroleum Establishment (DPE)

Job Type

Lumpsum EPCI for 2 unmanned WHP: T-03 & TT-01

Qualified weight with DPE

Topsides work on unit rates - no equipment installed

Job Award Amendment to Rashid C Contract signed May 14th, 2015

Job Status

Design 1, Build 2' Concept

Fast track project

3 Leg, skirted piles Jacket

Vertical Offshore transportation

Both Platforms installed in 10 days

Mechnical Completion 20 February 2016

Synopsis Owner Stephanie Gambier

StructureContractual

weights (Te)

Net final

weight

(Te)

T-03 Jacket 342 533

TT-01 Jacket 302 518

T-03 Deck 235 198

TT-01 Deck 235 197

T-03 Piles 290 435

TT-1 Piles 275 400

T-03 Boat Landing 18 36

TT-01 Boat Landing 18 36

Jan

Feb

Mar

Apr

May Jun

Jul

Aug

Sep Oct

Nov

Dec Jan

Feb

Design engineering (Plan)

Actual - Design engineering

Issue MTO 90% (Plan) P

Actual - Issue MTO 90% (30 Jun- 24 Aug)

Issue AFC dwgs for Jacket (Plan: 15 - July) P

Actual - Issue AFC dwgs for Jacket (15 Jul - 20 Jul) A

Receive soil report (Plan: 31-May) x

Actual - Receive soil report (26 Aug) x

Issue last remaining AFC dwgs (Plan: 15-Aug) x

Actual - Issue last remaining AFC dwgs (14 Oct) x

Fabrication Jackets & Decks (Plan)

Actual - Fab Jackets & Decks (27 Aug - 17 Jan)

Fabrication Skirts & Mudmat (Plan) P

Actual - Fab Skirts & Mudmat (25 Sep- 07 Dec)

Load out of 2 platforms decks and jackets (Plan) P

Actual - Load out of 2 platforms decks and jackets A

Installation by G1201 (Plan) P

Actual - Installation by G1201 (05 Feb-20Feb) A

AS BUILT SCHEDULE OF EXECUTION2015 2016

Actual

Actual

Plan

Actual

Actual

Plan

Amendment signature with DPE 14-May-15

KOM with DPE 21-May-15

DPE to provide soil data 31-May-15

Primary steel MTO 30-Jun-15

Jacket Main legs AFC drawings 30-Jun-15

Completion of Jacket AFC drawings 19-Aug-15

completion of Deck AFC drawings 19-Aug-15

Platforms ready for load-out at DWDD 15-Jan-16

Mechanical Completion 15-Feb-16

Actual with DPE

14-May-15

21-May-15

26-Aug-15

18-Jul-15

23-Jul-15

14-Oct-15 (mudmat &

pile skirts)

12-Oct-15 (grating,

handrails)

24-Jan-16

20-Feb-16

Key Dates