TT-01 WD = 39.2 m MSLT-03 WD = 45.5 m MSL
G1201
Installation scope of Work (G1201) - Final Fabricated weights w/o
rigging
Lift for T-03 Jacket (532 Te)
Lift for T-03 Boat Landing (36 Te, excluding stabbing guides on jacket)
T-03 Topsides lift (198 Te)
T-03 Skirted Piles driving and Grouting (145 Te ea, 113m long, 54" dia)
Single lift for TT-01 Jacket (517 Te)
Lift for TT-01 Boat Landing (36 Te, excluding stabbing guides on jacket)
TT-01 Topsides lift (197 Te)
TT-01 Skirted Piles driving and Grouting (133 Te ea, 105 m long)
Revision 5: 25-Feb-2015
Client Dubai Petroleum Establishment (DPE)
Job Type
Lumpsum EPCI for 2 unmanned WHP: T-03 & TT-01
Qualified weight with DPE
Topsides work on unit rates - no equipment installed
Job Award Amendment to Rashid C Contract signed May 14th, 2015
Job Status
Design 1, Build 2' Concept
Fast track project
3 Leg, skirted piles Jacket
Vertical Offshore transportation
Both Platforms installed in 10 days
Mechnical Completion 20 February 2016
Synopsis Owner Stephanie Gambier
StructureContractual
weights (Te)
Net final
weight
(Te)
T-03 Jacket 342 533
TT-01 Jacket 302 518
T-03 Deck 235 198
TT-01 Deck 235 197
T-03 Piles 290 435
TT-1 Piles 275 400
T-03 Boat Landing 18 36
TT-01 Boat Landing 18 36
Jan
Feb
Mar
Apr
May Jun
Jul
Aug
Sep Oct
Nov
Dec Jan
Feb
Design engineering (Plan)
Actual - Design engineering
Issue MTO 90% (Plan) P
Actual - Issue MTO 90% (30 Jun- 24 Aug)
Issue AFC dwgs for Jacket (Plan: 15 - July) P
Actual - Issue AFC dwgs for Jacket (15 Jul - 20 Jul) A
Receive soil report (Plan: 31-May) x
Actual - Receive soil report (26 Aug) x
Issue last remaining AFC dwgs (Plan: 15-Aug) x
Actual - Issue last remaining AFC dwgs (14 Oct) x
Fabrication Jackets & Decks (Plan)
Actual - Fab Jackets & Decks (27 Aug - 17 Jan)
Fabrication Skirts & Mudmat (Plan) P
Actual - Fab Skirts & Mudmat (25 Sep- 07 Dec)
Load out of 2 platforms decks and jackets (Plan) P
Actual - Load out of 2 platforms decks and jackets A
Installation by G1201 (Plan) P
Actual - Installation by G1201 (05 Feb-20Feb) A
AS BUILT SCHEDULE OF EXECUTION2015 2016
Actual
Actual
Plan
Actual
Actual
Plan
Amendment signature with DPE 14-May-15
KOM with DPE 21-May-15
DPE to provide soil data 31-May-15
Primary steel MTO 30-Jun-15
Jacket Main legs AFC drawings 30-Jun-15
Completion of Jacket AFC drawings 19-Aug-15
completion of Deck AFC drawings 19-Aug-15
Platforms ready for load-out at DWDD 15-Jan-16
Mechanical Completion 15-Feb-16
Actual with DPE
14-May-15
21-May-15
26-Aug-15
18-Jul-15
23-Jul-15
14-Oct-15 (mudmat &
pile skirts)
12-Oct-15 (grating,
handrails)
24-Jan-16