![Page 1: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/1.jpg)
OrganizationDateAWV Stakeholder GroupJan. 12, 2016
![Page 2: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/2.jpg)
• North and south portal construction
• Update on tunneling machine• Schedule and next steps• Upcoming closures
Alaskan Way Viaduct Replacement Program Update
![Page 3: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/3.jpg)
Envisioning the
NORTH PORTAL
![Page 4: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/4.jpg)
Building the
NORTH PORTAL
North Portal December 29, 2015
![Page 5: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/5.jpg)
North operations building
December 4, 2015
NORTH OPERATIONSBuilding
![Page 6: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/6.jpg)
Building the
NORTH PORTAL
North portal January 6, 2016
![Page 7: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/7.jpg)
Building the northbound lanes coming out of the
SR 99 tunnelJanuary 6, 2016
Building the
NORTH PORTAL
![Page 8: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/8.jpg)
Envisioning the
SOUTH PORTAL
![Page 9: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/9.jpg)
The south portal work zone in December 2015
Building the
SOUTH PORTAL
![Page 10: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/10.jpg)
Rendering of the south portal operations building
Building the
SOUTH PORTAL
![Page 11: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/11.jpg)
Building the
SOUTH PORTAL
The tunnel operations buildingJanuary 6, 2016
![Page 12: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/12.jpg)
Filling the
ACCESS PIT
![Page 13: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/13.jpg)
Repairing
BERTHA
Getting ready to resume tunneling
December 15, 2015
![Page 14: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/14.jpg)
Repairing
BERTHA
Recent activities• Access pit backfilling• Performing load tests• Building tunnel rings• Removing tunnel soil with a
barge• Tunneling through the
access pit wallBackfilling access pit
Building rings
![Page 15: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/15.jpg)
Repairing
BERTHA
![Page 16: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/16.jpg)
STP’s next steps• Late January 2016: Reach planned maintenance site (Safe
Haven 3)
• March 2016: Tunnel under viaduct
• January 2017: Complete tunneling
• June 2017: Final concrete pour
• April 2018: Complete testing and commissioning
• April 2018: Tunnel ready for traffic
Repairing
BERTHA
![Page 17: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/17.jpg)
2016 lane closures on
Aurora Avenue North
![Page 18: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/18.jpg)
2016 lane closures on
Aurora Avenue North
![Page 19: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/19.jpg)
How to REACH US
Website: www.AlaskanWayViaduct.org
Twitter: @BerthaDigsSR99
Email:[email protected]
Hotline:1-888-AWV-LINE
Our information center, Milepost 31, is located at 211 First Ave. S. in Seattle’s Pioneer Square neighborhood.
![Page 20: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/20.jpg)
OFFICE OF THE WATERFRONTJanuary 12, 2016
ALASKAN WAY VIADUCT REPLACEMENT PROGRAM STAKEHOLDER GROUP
![Page 21: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/21.jpg)
2015 WORK PLAN:KEY ACCOMPLISHMENTS• Completed MarketFront (PC‐1 North) Development Agreement (May)
• Completed Draft Environmental Impact Statement (EIS) for Alaskan Way, Promenade and Overlook Walk (June)
• Aquarium Master Plan approved by Council (August)
• Maintenance Report completed (November)
• Design progress on critical utilities, including telecommunications, Seattle City Light and Seattle Public Utilities and Puget Sound Energy coordination (30% designs completed, continues in 2016)
• Continued stakeholder engagement (ongoing)
![Page 22: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/22.jpg)
NEXT STEPS IN 2016
• Supplement Draft EIS for Alaskan Way, Promenade and Overlook Walk (spring)
• Develop MOU with Aquarium regarding next steps for expansion (summer)
• Complete updated 60% design of Main Corridor (summer)
• Final EIS for Alaskan Way, Promenade and Overlook Walk (fall)
• Cost Estimate and Validation Process (CEVP) workshop with WSDOT (fall)
• Complete City/WSDOT funding agreement (end of year)
![Page 23: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/23.jpg)
SUPPLEMENTAL DRAFT EIS• OW will complete a Supplemental Draft EIS in spring 2016
• Final EIS is anticipated in fall 2016
• In addition to the action and no action alternatives evaluated in the Draft EIS, the Supplemental Draft EIS will evaluate two new alternatives:
A narrower Alaskan Way that does not include dedicated bus lanes between Yesler and King streets (transit would operate in the general purpose lanes)
A revised Overlook Walk to accommodate a potential Aquarium expansion project in that location
![Page 24: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/24.jpg)
SCHEDULE
![Page 25: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/25.jpg)
QUESTIONS?
![Page 26: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/26.jpg)
26
ELLIOTT BAY SEAWALL PROJECT
Alaskan Way Viaduct Stakeholder Group
January 12, 2016
![Page 27: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/27.jpg)
27
WINTER 2016: CONSTRUCTION CONTINUES
– Work continues between University street and Yesler Way.
– Work begins between Pine and Pike streets
– Business will be open and accessible
– Some businesses will not have access for certain construction activities and for a limited duration
– Access to Colman Dock remains the same
![Page 28: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/28.jpg)
28
CONSTRUCTION CONTINUESUNIVERSITY STREET TO YESLER WAY
![Page 29: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/29.jpg)
29
RECENT CONSTRUCTION HIGHLIGHTS
![Page 30: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/30.jpg)
30
THE WATERFRONT IS OPEN!
![Page 31: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/31.jpg)
31
JANUARY 2016 CONSTRUCTION STARTSPINE TO PIKE STREETS
![Page 32: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/32.jpg)
32
QUESTIONS?
Email: [email protected]
Website: waterfrontseattle.org/seawall
24‐hour hotline: 206‐618‐8584
![Page 33: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/33.jpg)
Stakeholder Group Feedback
![Page 34: 2016 0112 AWV Stakeholder Group DRAFT...SUPPLEMENTAL DRAFT EIS • OW will complete a Supplemental Draft EIS in spring 2016 • Final EIS is anticipated in fall 2016 • In addition](https://reader034.vdocument.in/reader034/viewer/2022042803/5f4b6c55ba50cb2c4919ccf7/html5/thumbnails/34.jpg)
How to REACH US
Website: www.AlaskanWayViaduct.org
Twitter: @BerthaDigsSR99
Email:[email protected]
Hotline:1-888-AWV-LINE
Our information center, Milepost 31, is located at 211 First Ave. S. in Seattle’s Pioneer Square neighborhood.