2018 Work Program
PAGE
TSX-V: EAS
EASTASIAMINERALS.COM
Timeline for 2018 Sangihe Work Program
2
•! Completed Geotechnical Test work for IFS •! Completed Final pit design, calculated Ore
Reserves •! Obtained approval from Ministry of
Environment the KA for IFS and AMDAL study submitted for Indonesian Government approval
•! Completed Construction Phase •! Commenced and completed mining of Oxide Ore •! Initiated Leaching operations •! Completed Reserve Development Drilling (26
holes) to expand defined Ore Reserves •! Commenced Gold and Silver Production in
Sangihe Process Plant •! Completed 1st month of Gold & Silver Production
•! Completed full quarter of gold and silver production
•! Completed full quarter of revenue •! Completed End of Year Reserves
and Resources Statement •! Completed RKAB 2019 Work Plan
and Budget
•! Submitted Sangihe Mine Construction Licence for Indonesian Government approval
•! Submitted Revised Work Plan and Budget •! Commenced Construction Stage •! Application for Sangihe Mine Production
Licence submitted for Indonesian Government approval
Q4 Q2 Q3 Q1
.