2019 CAROLINAS AGC SUMMER CONFERENCE July 26, 2019 David Rogers, PE Assistant Construction Engineer

Upload: others

Post on 08-Jun-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

2019 CAROLINAS AGCSUMMER CONFERENCE

July 26, 2019David Rogers, PE

Assistant Construction Engineer

Page 2: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

• Carolinas AGC Members• Leslie Clark, Carolinas AGC (Staff Liaison)• Richard Nickel, Carolina Bridge Company (Joint)• Subcommittee Co-Chairs and committee members• E-Construction*

MANY THANKS!

Page 3: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Today’s Topics• SCDOT Staffing• Research Projects

– Upcoming research projects of interest• Specifications/Bridge Details

– Recent changes and future considerations• Project Funding and Upcoming Opportunities• Project of Interest• Recent Bridge Subcommittee Topics in SC

Page 4: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

HQ Construction Staff• Director of Construction

– Mr. Robbie Isgett, PE

• State Construction Engineer– Mr. Kevin Harrington, PE

• State Bridge Construction Engineer– Vacant

• Road and Bridge Construction Engineers

Page 5: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

3. Stephanie Jackson-Amell

Page 6: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

District Construction StaffDistrict 1• Allen Thompson (Acting DCE)• Derek Frick – ADCE 5/2019District 2• Mike Hannah – DCE• Drew McCaffrey – ADCEDistrict 3• Patrick McKenzie – DCE 7/2018• Ben Olson – ADCE 8/2018• David Hebert – D/B DCEDistrict 4• Melanie Mobley – DCE• Tom Gaines – ADCE 10/2018

District 5• David Johnson – DCE• Travis Patrick – ADCE• Jamie Poston – ADCEDistrict 6• Kevin Turner – Dist. Bridge Engineer• Daniel Burton – DCE 9/2018District 7• Brian Heape – DCE 6/2018• Lyle Davis – ADCE

Page 7: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Consulting Engineering & Inspection

• Active Projects– SCDOT Staff– On-call CE&I, SCDOT RCE – Nick Waites– Project-Specific CE&I – David Rogers

• Project-Specific CE&I– Typically Turn-Key– Most Design-Build Contracts– Large Design-Bid-Build Contracts– Bridge Packages

Page 8: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Consulting Engineering & Inspection

• Upcoming CE&I Project-Specific Contracts– I-85 over Rocky Creek (DB), Greenville– Berlin G. Myers Phase III, Dorchester– US 17 Speedway, Jasper County– I-26 Rehab MM 74 to 85, Newberry County

Professional Services Website:http://info2.scdot.org/professionalserv/Pages/Consultants-Professional-Services.aspx

Page 9: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

FY 19-20 Approved Research Projects

• Risk-Based Inspection Program• Evaluating the Construction Cost and Schedule

Impacts of SCDOT’s Traffic Control Restrictions• Impact of Utility Delays on Project Delivery• Investigation and Assessment of Effective

Patching Materials for Concrete Bridge Decks• Safe and Cost-Effective Reduction of Load

Postings for SC Bridges

Page 10: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

FY 19-20 Approved Research Projectshttps://www.scdot.scltap.org/

Page 11: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

New/Updated Specifications & Details

• Supplemental Specifications– Preformed Joint Filler (1/19)– High Strength Structural Bolts (1/19)– Preservative Treatment of Wood Products (1/19)– DBE Supplemental Specification (7/19)– Lane Closure Restrictions (7/19)

Page 12: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

New/Updated Specifications & Details

• Supplemental Specifications– Volumetric Concrete Mixers (7/19)– Fine & Coarse Aggregates for PCC (7/19)– Reinforcing Steel (7/19)– Sloped Edge Longitudinal Joints (7/19)

Follow the latest updates at:https://www.scdot.org/business/road-supplemental-specs.aspx

Page 13: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

New/Updated Specifications & Details

• Supplemental Technical Specifications– Earthquake Drains (1/19)– Vibrating Wire Data Collection Center (7/19)– Mixing Plants for Producing Asphalt Paving Mixes

(7/19)– Inspection and Qualification of Asphalt Mix Design

Labs (7/19)

Page 14: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

New/Updated Specifications & Details

• Supplemental Technical Specifications– Bi-directional Static Load Testing of Drilled Shafts

(7/19)– High Strain Dynamic Load Testing of Drilled Shafts

(7/19)– Rapid Load Testing of Drilled Shafts (7/19)– MSE Walls (1/19)

Follow the latest updates at:https://www.scdot.org/business/road-technical-specs.aspx

Page 15: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

New/Updated Specifications & Details

• “Blue Light” Special Provision– Use of Safety Improvement Team is preferred

method of coverage– Priority project list provided by the AGC– Contractor to coordinate with DCE or designee– 9 projects across 5 Districts in 2019 Lettings

include the pay item– $40 per hour for officers (non-SIT)

Page 16: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

UTILITIES BILL – A36,S401

• Signed in Law by Governor McMaster May 13, 2019• Financial assistance for public water and sewer relocations• Small Utility – 10,000 or fewer connections and serve

population of 30,000 or less. Utilities can’t opt out.• Cost Sharing

– Small Utility – Highway Project to bear all relocation costs– Large Utility – Up to 4% of the construction bid amount. Pro rata if

multiple large utilities.– Large & Small Utilities on same project – 100% of small utility’s cost

& up to 4.5% of original bid amount minus the small utility’s costs for large utility’s costs.

• Drawings and documents must be submitted 180 days prior to the letting date

Page 17: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Infrastructure Funding

• 2017 South Carolina Gas Tax Increase– Two cent per year for six years– Currently in Year Three– 22 cents as of July 1, 2019– Will cap at 28 cents

https://www.scdot.org/inside/new-gastax-trustfund.aspx

Page 18: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •
Page 19: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Millions

Page 20: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

SCDOT Awarded Contracts FY 2018-19

• Rural Routes Safety - $41M• Safety Total - $68M• Pavement Preservation - $76M• Pavement Rehab/Reconstruction - $501M• Pavement Total - $578M• Bridge Replacements - $85M• Bridge Maintenance - $16M• Bridge Total - $101M

Page 21: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

SCDOT Awarded Contracts FY 2018-19

• Interstate Widening - $316M• MPO/COG Projects - $54M• SCDOT Program Total - $1.2B• CTC/Other Administered by SCDOT - $82M

• Grand Total - $1.25B• Total Active - $3.68B

Page 22: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Bridge Projects

• August 2019 to July 2020 Lettings– 26 Bridge Replacements– 16 Bridges for Site-Specific Bridge Deck Repairs– 4 Bridge Rehabs– 2 Bridge Deck Replacements– 1 Bridge Jacking

Page 23: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Bridge Preservation

• Approximately $20 Million anticipated per year for bridge preservation and rehabilitation projects

• Site-Specific Deck Repairs– Replaces previous on-call partial and full-depth

deck patching contracts. Include joint repairs.– $7.5M in Deck Repairs Awarded Since April ‘19– August 2019 to July 2020 – 3 Projects, 16 Bridges

Page 24: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Design-Build Bridge Projects

• I-85 over Rocky Creek Bridge– January, 2020 Bid Opening

• US 1 over I-20 Interchange Improvement– March 2020 Bid Opening– Interchange Modification Report to be

completed by the DB Team

Page 25: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Design-Build Bridge Projects

• Closed and Load Restricted Bridges Replacement Package– September 2019 RFQ– 16 Structures in District 2

• Future Design-Build CLRB Packages– Annually over the next ten years– $10 to $20 Million each– Next up is District 4 – 10 Bridges for 2020

Page 26: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Design-Build Bridge Projects

• I-26 over US 1, SCLRR and SC 302– Lexington County– 2022 RFQ

• I-20 Over Wateree River and Swamp Bridge Package– Kershaw County– 2022/2023 RFQ

Page 27: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Major Design-Build Interstate Projects

• Carolina Crossroads– Phased approach under consideration– Will be announced Fall 2019

• I-526 Widening Low Country Corridor– I-526/I-26 Interchange– East and west segments

Page 28: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Upcoming Project of Interest

Page 29: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Berlin Myers Parkway, Phase III

• Dorchester County Tax Authority - Funded• Purpose – Create a new alignment route as an

alternate to US 17A• Last segment of the Berlin Myers Parkway (2.5

mi)• From E. Carolina Ave @ BMP (SC 165) to US

17A at Flood Heirs Road/W Fisher Rd

Page 30: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Berlin Myers Parkway, Phase III

• 4 lanes Divided with Curb & Gutter• Sawmill Branch Trail modifications• New grade separated interchange @ E Carolina

Ave• Intersection Improvements at Luden Rd,

Greenwave Blvd and Orangeburg Rd.• Preserve the Flood Control Channel Functions

Page 31: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •
Page 32: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •
Page 33: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •
Page 34: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •
Page 35: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •
Page 36: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •
Page 37: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Berlin Myers Parkway, Phase III

• Summer 2018 – Final Utility Coordination and ROW Acquisition

• January 2019 Final Construction Plans Completed

• Anticipated Letting in Early 2020

Page 38: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Berlin Myers Parkway, Phase III

• Seven Bridges– Bridge 1 over Sawmill Branch Floodplain

• 200x88 Continuous Flat Slab, 6 Spans, H-Pile Bents– Bridge 2 over Sawmill Branch Floodplain

• 120x79 Continuous Flat Slab, 3 Spans, H-Pile Bents– Bridge 3 over Sawmill Branch Floodplain

• 120x91 Continuous Flat Slab, 3 Spans, H-Pile Bents– Bridge over S-18-64 (East Carolina Ave.) G.S.I.

• 540x69, 3 Span, Steel Plate Girders, Piers on Drilled Shaft Footings, 240 ft Main Span

Page 39: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •
Page 40: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Berlin Myers Parkway, Phase III

• Seven Bridges (Cont.)– S-18-706 (Luden Drive) over Sawmill Branch

• 90x71 Continuous Flat Slab, 3 Spans, H-Pile Bents

– S-18-706 over Sawmill Branch Floodplain• 80x59 Continuous Flat Slab, 2 Spans, H-Pile Bents

– S-18-363 (Greenwave Blvd.) over Sawmill Branch Floodplain

• 320 ft variable width continuous flat slab (73 ft to 59 ft), 8 Spans, H-Pile Bents

Page 41: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •
Page 42: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Bridge Subcommittee Action Items

• Tentative Letting List• Bridge Rideability• Swiss Hammers• Template Requirements• Grooving Plans• Electronic Submittals• PDA Testing

• Issues with Payment– Stockpiled Materials– Reinforcing Steel– Concurrence with Weather

Conditions

• Sampling/Testing at Plants• OSOW Permits• Substantial Completion

Page 43: 2019 CAROLINAS AGC SUMMER CONFERENCE › cagcdocs › events › SCDOT... · • 90x71 Continuous Flat Slab, 3 Spans, H -Pile Bents – S-18-706 over Sawmill Branch Floodplain •

Upcoming Projects

• Tentative Letting Schedule:– https://www.scdot.org/business/constructionletting-tentative.aspx

• Design Build Projects:– https://www.scdot.org/business/design-build.aspx

• Other Resources:– Project Viewer– https://scdot.maps.arcgis.com/apps/MapSeries/index.html?appid=ca1

cd69fc88945f4bb465e16765d761c

– SCDOT Ten Year Plan– https://www.scdot.org/projects/ten-year-plan.aspx