September 20, 2017 MPO Meeting
2020-2029 TIP Development
(NCDOT Prioritization 5.0)
Action Requested
• Approve the project lists of all modes for submission to NCDOT for scoring in Prioritization 5.0
o 2020-2029 TIP Development o Unanimous recommendation by the TCC during
the September 7 meeting.
P5.0 Adoption Public Involvement Process
• August 17 through August 31 • Media release to news outlets in Iredell,
Mecklenburg, and Union Counties • Social media promotion • Project lists and maps can be viewed on CRTPO
website • September 20 MPO meeting: Opportunity for
public comment on the projects proposed for P5.0 Submission.
P5.0 Project Submittal – Public Comment Summary
• 20 Total Public Comments Received – Highway Projects
o 19 submittals in opposition to the Waxhaw Parkway
alignment o Residents of Waxhaw Meadows Plantation o 1 Comment submitted in opposition to Express Lanes projects
along I-77, I-485 and U.S. 74
• No public comments received on CRTPO’s
proposed P5.0 non-highway projects
56 highway project submittals in P5.0
Project Types (10) Carryover*
(14) Holding Tank
(17) New Project (2035 H.Y. of MTP)
(15) New Project (2045 H.Y. of MTP)
STI Tiers (15) Statewide Mobility Projects
(18) Region E Projects
(3) Region F Projects
(15) Division 10 Projects
(5) Division 12 Projects
* Carryover projects do not count against CRTPO’s 46 submittal slots.
Proposed P5.0 Project Submittals
Statewide Mobility (1 of 2)
P5.0 Highway Project Location Estimated Cost to
NCDOT
I-77 Express Lane Project (SC State Line – Woodlawn Rd)
Charlotte $326
I-77 Express Lane Project (Woodlawn Rd – Belk Freeway)
Charlotte $98
I-77 & Brookshire Freeway Interchange Improvements
Charlotte $102
I-77 & Belk Freeway Interchange Improvements
Charlotte $129
I-77 Express Lane Project (Belk Freeway – Brookshire Freeway)
Charlotte $347
I-77 & Sunset Road Interchange Improvements
Charlotte $41
I-77 Widening Project (NC 150 to I-40)
Mooresville, Troutman, Statesville $355
P5.0 Highway Project Location Estimated Cost to
NCDOT
I-85 & Sugar Creek Road Interchange Improvements
Charlotte $20
I-85 Westbound Widening (Sam Wilson Rd – Gaston Co. Line)
Charlotte $13
I-85 & Brookshire Boulevard Interchange Improvements
Charlotte $20
I-85 & WT Harris Boulevard Interchange Improvements
Charlotte $25
I-85 & Mallard Creek Ch. Road Interchange Improvements
Charlotte $18
I-85 & I-77 Interchange Improvements
Charlotte $125
US 74 Express Lane (Belk Freeway – Albemarle Road)
Charlotte $82
I-85 & I-485 (NE of Charlotte) Interchange Improvements
Charlotte $35
Proposed P5.0 Project Submittals Statewide Mobility (2 of 2)
P5.0 Highway Project Location Estimated Cost to
NCDOT
US 601 Widening Project (Existing US 74 to Monroe Expressway)
Monroe $14
US 21/Statesville Rd Widening (Harris Boulevard to Gilead Road)
Charlotte Huntersville $58
US 21/Statesville Road Widening (Westmoreland Rd – Catawba Avenue)
Cornelius $16
NC 115/Old Statesville Rd Widening (NC 73 – Washam Potts Road)
Huntersville Cornelius $34
NC 115/Old Statesville Rd Widening (Washam Potts Rd – Potts Street)
Cornelius $18
Waxhaw Parkway – New Location (NC 16 to NC 75 East of Waxhaw)
Waxhaw $32
US 521 Widening Project (SC State Line – Ballantyne Commons Pkwy)
Charlotte TBD
NC 24/Harris Blvd Widening Project (Sugar Creek Rd – Research Drive)
Charlotte $22
NC 24/Harris Blvd Widening Project (N. Tryon Street – NC 49)
Charlotte $8
Proposed P5.0 Project Submittals Regional Impact (Region E) (1 of 2)
P5.0 Highway Project Location Estimated Cost to
NCDOT
NC 16/Brookshire Blvd Widening Project (I-85 to Belhaven Boulevard)
Charlotte $32
NC 49/S. Tryon St. Widening Project (I-485 to NC 160/Steele Creek Road)
Charlotte $56
NC 24/Harris Boulevard Widening (I-77 to Sugar Creek Road)
Charlotte $32
NC 24/Harris Boulevard Widening (Univ. City Blvd to The Plaza)
Charlotte $35
NC 27/Mt. Holly Road Widening (Rhyne Road – Belmeade Blvd)
Charlotte $28
NC 16/Brookshire Blvd Widening (Gaston Co. Line – Belhaven Blvd)
Charlotte $51
NC 49/S. Tryon St. Widening Project (I-485 to Arrowood Road)
Charlotte $7
NC 115/Old Statesville Rd Widening (Hambright Rd – Mt. Holly-Huntersville Rd)
Huntersville $28
NC 200/Morgan Mill Road Widening (US 74 to Monroe Expressway)
Monroe $26
Proposed P5.0 Project Submittals Regional Impact (Region E) (2 of 2)
P5.0 Highway Project Location Estimated Cost to
NCDOT
NC 150 Widening Project (NC 115 to NC 801)
Mooresville $29
US 21/NC 115 Widening Project (Julian Place to Cedar Lane)
Troutman $46
NC 3 Widening Project (Cabarrus County Line – Rocky River Road)
Mooresville $38
Proposed P5.0 Project Submittals Regional Impact (Region F)
P5.0 Highway Project Location Estimated Cost to
NCDOT
Ballantyne Commons Parkway Widening (Annalexa Lane to Williams Pond Lane)
Charlotte $31
Bailey Road Extension & I-77 Overpass (US 21 to Future Northcross Drive Ext)
Cornelius $8
Monroe Northern Loop – New Location (US 74 to Walkup Avenue/Bivens Road)
Monroe $20
Ardrey Kell Road Widening (NC 16/Providence Road to Rea Road)
Charlotte TBD
Rocky River Road Widening (Old Charlotte Highway to US 74)
Monroe $11
Eastern Circumferential – New Location (Northeast Parkway to Sam Newell Road)
Charlotte Matthews
TBD
Old Monroe Road Widening (Wesley Chapel-Stouts Rd – Airport Road)
Monroe $27
Lawyers Road Widening (I-485 to Stevens Mill Road)
Mint Hill Stallings
$6
Lancaster Highway Widening (NC 51 to Ballantyne Commons Parkway)
Charlotte Pineville
TBD
Proposed P5.0 Project Submittals Division Needs (Division 10) (1 of 2)
P5.0 Highway Project Location Estimated Cost to
NCDOT
Eastern Circumferential – New Location (Rosemallow Road to Rocky River Road)
Charlotte $27
Carowinds Boulevard – New Location (NC 160/Steele Creek Rd to NC 49/S. Tryon St)
Charlotte $20
Westinghouse Boulevard Widening (NC 49/S. Tryon St to Nations Ford Road)
Charlotte $31
Park Road Widening (Johnston Road to NC 51)
Charlotte Pineville
$18
Eastern Circumferential – New Location (Rocky River Road to Plaza Road Extension)
Charlotte $28
Ardrey Kell Road Widening (Rea Road to US 521)
Charlotte TBD
Proposed P5.0 Project Submittals Division Needs (Division 10) (2 of 2)
Project Location Estimated Cost to
NCDOT
East-West Connector – New Location (Langtree Road to NC 115)
Mooresville $10
Southwest Bypass – New Location (US 21/NC 115 to Autumn Leaf Road)
Troutman $13
Connector Road Widening (NC 115 to US 21)
Mooresville $10
Langtree Road Widening (Alcove Road to East-West Connector)
Mooresville $9
Old Mountain Road Widening (US 21/NC 115 to Buffalo Shoals Road)
Troutman $43
Proposed P5.0 Project Submittals Division Needs (Division 12)
P5.0 Non-Highway Modes Proposed Project Inventory
• Bike/Ped: 22 projects • Transit: 9 Projects • Rail: 10 Projects • Aviation: 41 Projects Charlotte-Douglas: 14 Projects Charlotte-Monroe: 18 Projects Statesville Regional: 9 Projects
P5.0 Project Submittals – Bike/Ped
P5.0 Bicycle/Pedestrian Project Location/Agency Cost to NCDOT in
Millions of $ Local Match % of
total cost
Margaret Wallace Road Sidewalk
Charlotte $760k 20%
Providence Road Sidewalks Charlotte $1.1 25%
Irwin Creek Greenway East Mecklenburg Co
(Charlotte) $3.2 30%
Briar Creek Greenway Mecklenburg Co
(Charlotte) $4.9 25%
Briar Creek and Little Hope Creek Greenway
Mecklenburg Co (Charlotte) $2.1 25%
Walker Branch Greenway Mecklenburg Co
(Charlotte) $3.6 30%
Westmoreland Rd Underpass Cornelius $2.4 20%
Re-Submit P4.0 Projects that were unfunded in 2018-2027 TIP
*All P5.0 Bike/Ped Projects will be evaluated in the Division Needs Tier of STI
P5.0 Project Submittals – Bike/Ped
P5.0 Bicycle/Pedestrian Project
Location/Agency Cost to NCDOT in
Millions of $ Local Match % of
total cost
NC 115 Bicycle Lanes (Mt. Holly-Huntersville Rd – Hambright Rd)
Huntersville $2.6 20%
Stallings Elementary School Sidewalk Network
Stallings $294k 20%
Carolina Thread Trail Segment Q4
Troutman $1.7 26%
Lake Norman State Park Multi-Use Trail, Segment A
Troutman $631k 36%
Re-Submit P4.0 Projects that were unfunded in 2018-2027 TIP
*All P5.0 Bike/Ped Projects will be evaluated in the Division Needs Tier of STI
P5.0 Project Submittals – Bike/Ped
P5.0 Bicycle/Pedestrian Project
Location/Agency Cost to NCDOT in Millions of $
Local Match % of total cost
Marsh Road Sidewalk Charlotte $830k 21%
Ideal Way/Poindexter Drive Connection
Charlotte $1.3 24%
Jetton St Sidewalk Davidson $232k 20%
Potts Sloan Beatty Multi-Use Trail (Phase 1)
Davidson $934k 20%
Potts Sloan Beatty Multi-Use Trail (Phase 2)
Davidson $1.0 20%
Bike Improvements in Indian Trail
Indian Trail $350k 50%
New Projects Identified for P5.0 Submittal (1 of 2)
*All P5.0 Bike/Ped Projects will be evaluated in the Division Needs Tier of STI
P5.0 Project Submittals – Bike/Ped
P5.0 Bicycle/Pedestrian Project
Location/Agency Cost to NCDOT in Millions of $
Local Match % of total cost
Price Mill Creek Greenway Indian Trail $3.1 25%
Indian Trail Fairview Sidewalk Indian Trail $200k 25%
Matthews Township Parkway Multi-Use Path
Matthews $860k 20%
Pleasant Plains Rd Multi-Use Path
Matthews $1.5 20%
Marvin Greenway and Downtown Development Connections
Marvin $700k 50%
New Projects Identified for P5.0 Submittal (2 of 2)
*All P5.0 Bike/Ped Projects will be evaluated in the Division Needs Tier of STI
P5.0 Project Submittals – Transit
P5.0 Transit Project Location/
Agency Cost to NCDOT in
Millions of $ Local Match % of
total cost
Monroe Rd Corridor Shelter Project CATS $146k 80%
Freedom Drive Corridor Shelter Project
CATS $158k 80%
Hambright Road Park and Ride Lot CATS $2.4 70%
New Projects Identified for P5.0 Submittal
*All P5.0 Transit Projects will be evaluated in the Division Needs Tier of STI
P5.0 Project Submittals – Transit
P5.0 Transit Project Location/Agency Cost to NCDOT in
Millions of $ Local Match % of
total cost
ICATS Paratransit Fleet Expansion
ICATS $250k 90%
ICATS Fixed Route Fleet Expansion
ICATS $2.5 50%
ICATS Intercounty Express Bus Connector Expansion (Regional Impact Tier)
ICATS $1.0 60%
Mooresville Neighborhood Transit Transfer Center
ICATS $600k 70%
Statesville Neighborhood Transit Transfer Center
ICATS $600k 70%
Mecklenburg Transit Services Fleet Expansion
Mecklenburg Transit Services
$144k 10%
New Projects Identified for P5.0 Submittal
*All P5.0 Transit Projects will be evaluated in the Division Needs Tier of STI, unless specified otherwise
P5.0 Project Submittals – Rail
P5.0 Rail Project Location Cost to NCDOT in
Millions of $
Old Dowd Rd./Norfolk Southern Railroad Grade Separation
Charlotte $19.9
Clanton Rd./Norfolk Southern Railroad Grade Separation
Charlotte $19.5
AC&W Railroad Relocation/North Yard Lead
Charlotte $17.9
Re-Submit P4.0 Projects that were not committed in 2018-2027 TIP
*All P5.0 Rail Projects will be evaluated in the Statewide Mobility Tier of STI
P5.0 Project Submittals – Rail
P5.0 Rail Project Location Cost to NCDOT in
Millions of $
Hoskins Road Grade Separation (CSX) Charlotte $16.0
Hovis Road Grade Separation (CSX) Charlotte $12.0
CSX Monroe-Waxhaw and Waxhaw to Monroe Line Connector
Monroe $26.8
CSX SE Line - Richardson Creek Siding Monroe $15.6
CSX SG Line - Waxhaw Siding Waxhaw $23.5
CSX SG Line - Helms Road Grade Separation Waxhaw $20.0
CSX SF Line - Wesley Chapel Stouts Road Grade Separation Monroe $10.0
New Projects Identified for P5.0 Submittal
*All P5.0 Rail Projects will be evaluated in the Statewide Mobility Tier of STI
P5.0 Project Submittals – Aviation
P5.0 Aviation Project Cost to NCDOT
Center Airfield Lighting Vault Relocation $500,000
Concourse A Expansion Phase II $500,000
Concourse B Expansion $500,000
Concourse C Expansion $500,000
Fourth Parallel Runway Design $500,000
Fourth Parallel Runway Construction $500,000
Fuel Farm Pumping Station Expansion $375,000
Taxiway A Rehabilitation $500,000
New Projects, Charlotte-Douglas Airport (1 of 2)
Note: Charlotte-Douglas Airport projects would be scored in the STATEWIDE MOBILITY tier
P5.0 Project Submittals – Aviation
P5.0 Aviation Project Cost to NCDOT
Taxiway M Rehabilitation $500,000
Terminal Lobby Expansion Construction $500,000
Third Aircraft Rescue and Firefighting Station $500,000
West Ramp Expansion Phase I $500,000
West Ramp Expansion Phase II $500,000
West Ramp Lavatory and Fuel Station $500,000
New Projects, Charlotte-Douglas Airport (2 of 2)
Note: Charlotte-Douglas Airport projects would be scored in the STATEWIDE MOBILITY tier
P5.0 Project Submittals – Aviation
P5.0 Aviation Project Cost to NCDOT in
Millions of $
East Partial Parallel Taxiway (AV-5824) $2.8
Land acquisition - East Area $500k
Land acquisition & design for auto parking expansion $980k
New air traffic control tower and access road $4.3
North hangar area improvements - Phase ia $1.3
North hangar area improvements - Phase ii (AV-5825) $530k
North hangar area improvements - phase iii $692k
North hangar area improvements - phase iv $755k
Strengthen taxiways to 95,000 dual wheel, fillet (AV-5814) $1.2
Terminal building expansion $1.7
Re-Submit P4.0 Projects, Charlotte-Monroe Exec. Airport (1 of 2)
Note: Charlotte-Monroe Airport projects would be scored in the Division Needs tier
P5.0 Project Submittals – Aviation
P5.0 Aviation Project Cost to NCDOT in
Millions of $
Airfield lighting rehabilitation $821k
Airport layout plan update and air traffic control tower study $279k
Corporate hangar site development $791k
Land acquisition - Runway 23 protection $449k
Land acquisition - west hangar area $475k
Strengthen Taxiways to 95,000 Dual Wheel, Fillet Widening- Phase 1-B
$2.0
North Hangar area improvements (phase 2) $1.3
North Hangar area improvements (phase 3) $1.3
North Hangar area improvements (phase 4) $1.3
New Projects, Charlotte-Monroe Exec. Airport (2 of 2)
Note: Charlotte-Monroe Airport projects would be scored in the Division Needs tier
P5.0 Project Submittals – Aviation
P5.0 Aviation Project Sub-Project Scope
Cost to NCDOT (in Millions of
$)
Runway Extension to 8,000 Feet (Phase 1) Environmental
Permitting and Land Acquisition
$9.6
Runway Extension to 8,000 Feet (Phase 2) Aviation Dr. Relocation & Utility Relocation
$5.1
Runway Extension to 8,000 Feet (Phase 3) Site Preparation (Phase A)
$10.3
Runway Extension to 8,000 Feet (Phase 4) Site Preparation (Phase B)
$10.3
Runway Extension to 8,000 Feet (Phase 5) Paving and Lighting $3.3
Statesville Regional Airport P5.0 Projects (1 of 2)
Note: Statesville Airport projects would be scored in the Division Needs tier
P5.0 Project Submittals – Aviation
P5.0 Aviation Project Project Status
Cost to NCDOT in Millions of
$
South Parallel Taxiway (West Side) Resubmit P4.0 project $10.4
Runway 10 Safety Area Improvements New Project $5.8
Terminal Renovation New Project $1.4
West Aviation Development Area New Project $34.4
Note: Statesville Airport projects would be scored in the Division Needs tier
Statesville Regional Airport P5.0 Projects (2 of 2)
September 20, 2017 MPO Meeting
2020-2029 TIP Development
(NCDOT Prioritization 5.0)
P5.0 Highway Project Status
Carryover: Must meet at least one of the following: • In years 6-10 of the DRAFT TIP • A sibling to a project in the DRAFT TIP • Partially complete or completed NEPA document
Holding Tank: Projects that have not met one of the carryover criteria.
• Removed from the P5.0 database by NCDOT-SPOT office. • CRTPO can use a submittal slot to add project back in.
New Projects: From the 2045 MTP fiscally constrained project list
• 2035 and 2045 horizon years