8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 1/22
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 2/22
Manufacturing Planning Solution Architecture
Planned Order Integration Challenges
Enhanced Planning and Scheduling Capabilities
Development and Deployment Strategy
Expected Takeaways
2
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 3/22
Who We ArePepsiCo Portfolio is Everywhere
3
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 4/22
Supply ChainPlanning and
Operations
ManufacturingPlanning
DemandPlanning
MaterialRequirementsPlanning
Distribution
RequirementsPlanning
ReplenishmentPlanning
TacticalCapacity
Planning
ManufacturingExecution Inventory
Policy
Integrated Supply Chain Planning and Operationsfor Quaker, Tropicana and Gatorade
Mixed planning technologysuite
Service contract expiringfor Manufacturing Planning
Seize the opportunity tosimplify architecture &Improve ROI
Take advantage of latestfeatures in SAP-SCM
4
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 5/22
We embarked on a journey to migrate toSAP-SCM for Manufacturing Planning
More than 100 manufacturing locations with diverseproduction planning needs
Fair share for inventory pre-build, safety stock and
demand cuts
Capability to turn off production lines for specificproducts and planner controlled production rates
Need for daily orders by downstream systems but displaymulti-day orders for production planners
5
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 6/22
SNPOptimization
DetailedScheduling
ECC Orders
MRP
SNP Optimization
Run on demand for 64 weeks rough cut capacity planningCost driven, constraints considered, with levelling of inventory,safety stock and demand cuts
Detailed Scheduling
Use SNP orders as inputs for 7 weeks of detailed scheduling
Planners can schedule orders using heuristics with sequencingper the sequence dependent setup
ECC Planned Orders
Real time synch between APO and ECCDaily orders for downstream systems and reports with enhanced
confirmation logic
Material Requirements Planning (MRP)
Continuous integration of Planned Orders between ECC and APO to drive MRP Requirements
Manufacturing Planning Solution Architecture
6
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 7/22
89% of over 110 businessrequirements met throughstandard / configuration
Solution enhancementsrequired in all impactedareas
Fit-Gap Analysis Unveiled 5 Areas of Impact
MasterData
SupplyNetworkPlanning
DetailedScheduling
Integrationwith
downstreamsystems
Reporting
7
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 8/22
Master Data: Production Line Run Strategy
Two SKUs can be produced on the same resourceProduction of SKU1 is blocked when production for SKU2 is turned onThis data feeds into Optimizer to turn on/off the PDS
Customization that allows date effective PDS availabilitywithout changing actual master data
8
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 9/22
Master Data: Time Effective Run Rate
9
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 10/22
Allows materials to prebuild evenly across all products at a location
Ensures that demand shortages are spread across all materials as evenly as
possible. Slow moving materials not penalized by a deeper cut.
Every product meets a tier before moving to the next
SNP: Cost Driven Leveling
Safety Stock Target 20%
30%
40%
60%
80%
10
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 11/22
Transition from SNP to PPDS
DS Scheduler responsible forConversion of SNP -> PPDS
• SNP Orders are uniquelyidentified with a Magenta Bar onthe DS Planning Board
• Interactive conversion throughDS Planning Board
• Schedulers Sequence in WeeklyIntervals/Periods to Match SNPSolve
• Setup Times are based on the
Sequence of Individual Ordersand may require manualintervention by the Scheduler
SNP Orders on the DS Planning BoardHighlighted in Magenta
11
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 12/22
Sequencing Production on the DS Planning Board
• Determine the initial sequenceof the Production Schedule
• Provide a Sort Criteria tocreate an ideal ProductionSequence
• Sequence Keys vary byprocess and businessrequirements
• Flexible in Nature (Size, Pack,Flavor) and align closely withSetup Matrix and Color Codes
GraphicalObjects onthe DSPlanningBoard bySequence
Key
Sequenced Orders on the DS PlanningBoard
12
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 13/22
Color Codes on the DS Planning Board
• User Defined color coding for
each material/location
• Allows the planners to viewgroups of products by colorand quickly identify scheduling
and master data issues
• Flexible in nature and alignsclosely integrated into theplanning process
• Master Data on the APOProduct Master
Color Codes for DS Planning Board
13
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 14/22
Inventory Review
• Sequence Keys provide a “BestCase” Production Schedule but donot address inventory or customerservice constraints
• Planners Review InventoryPositions in PPDS to identifymaterials with potential cuts
• Positive Inventory shown asGreen, Negative as Red andSafety Stock breach is shown inYellow
• Exceptions are monitored andcorrective actions are taken
Inventory Positions forEach Material
14
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 15/22
PPDS Optimization
• Used to do minimize cuts in theshort term
• Combination of Setup Costs andDelay Penalties
• Two Week Optimization Window
• Optimization results may result inadditional setup time, but loweroverall delays when days count
• No Order Creation, No Source ofSupply Determination and No
Alternate Modes
OptimizationResults
15
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 16/22
Detailed Scheduling Toolset
Reso urc e Netw ork s • Used to model physical constraints in the manufacturing process.• Resources grouped as networks and planned as a group.• Alerts created for orders that violate the resource network
Cam paign Planning • Used as a Planning Technique to group multiple orders and
schedule those orders as a group• Only used within DS Planning Board
Cont inuo us Inpu t /Outpu t Bot tom Up Schedu l ing
• Custom Scheduling Heuristic based on Bottom Up Heuristic• Aligns the start of the parent order to the start of the child order,
as they will physically run as a single process even though theyare two orders in the system.
16
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 17/22
MRP: Just In Time Requirements
FG Planned Order: 3, 000 CS SFG requirement:: 6, 000 LBOrder Time Stamp: 3/30 12:00 PM – 4/1 11:59 PM Total order duration: 60 hours
Mon 3/30 Tue 3/31 Wed 4/1
FG production duration 12 hours 24 hours 24 hours
FG production 600 CS 1,200 CS 1,200 CS
Standard Functionality
SFG Requirement 6, 000 LB
Configuration for Equal Distribution
SFG Requirement 2, 000 LB 2,000 LB 2,000 LB
Customization for Proportionate Distribution
SFG Requirement 1,200 LB 2,400 LB 2,400 LB
Custom logic to solve for just in time inventory of semi-finished goods and raw
materials : split dependent requirements in proportion to duration of theFinished Good / Semi-Finished Good production per day
17
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 18/22
Planned Order Consumption
Multi-day planned order: 3/30 12:00 PM – 4/3 10:00 AMConfirmations posted on 3/30, 3/31, 4/1, 4/2 and 4/3
Past and current finishdate
Past , current , +1 futurefinish date
Past , current , +4 futurefinish date
Past and current startdate ( Custom)
PO consumed only on4/3
PO consumed only on4/2 and 4/3
PO consumed every day.Over production on Thu / Fri canconsume next week’ s orders
PO consumedevery day
• Production confirmations posted by plant operators consume planned orders scheduled by
MP planners• Consumption of a planned order reduces dependent requirements• Tracked for Schedule adherence and attainment reporting• Standard functionality support backward consumption based on order finish date• Configuration for forward consumption based on order finish date is an additional feature• PepsiCo plants need backward consumption based on start date
18
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 19/22
Development and Deployment Strategy
Fit-Gap
Analysis
PhasedDevelop-ment
ProductionParallel
Deploy-
mentStrategy
Allowing the business to execute theMP solution in a production-likeenvironment is key• Quality of Solution Validation• Training and Change Management
19
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 20/22
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 21/22
STAY INFORMED
Follow the ASUGNews team:
Tom Wailgum: @twailgum
Chris Kanaracus: @chriskanaracus
Craig Powers: @Powers_ASUG
21
8/18/2019 2053 PepsiCos Manufacturing Planning Migration to Production Planning and Detailed Scheduling in SAP Advanced Planning and Optimization (1)
http://slidepdf.com/reader/full/2053-pepsicos-manufacturing-planning-migration-to-production-planning-and-detailed 22/22
THANK YOU FOR PARTICIPATING
Please provide feedback on this session by completinga short survey via the event mobile application.
SESSION CODE: ####
For ongoing education on this area of focus,visit www.ASUG.com
22