(2104) removing miscellaneous structures - …€¦  · web viewe mail: [email protected]...

29
SP XXXX-XX Insert Date DIVISION SL DELETE WHEN DONE: Statements in red are guidelines or instructional in nature. Remove these notes before completing the spec. When appearing at the top left of a provision, it pertains to the paragraph immediately beneath the note, as well as any indented items following it. All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting. Table of Contents SL-1 (2104) REMOVING MISCELLANEOUS STRUCTURES..............................1 SL-1.1 DESCRIPTION............................................................ SL-1.2 MATERIALS.............................................................. SL-1.3 CONSTRUCTION REQUIREMENTS.............................................. SL-2 (2545) LIGHTING SYSTEMS...............................................4 SL-2.1 GENERAL................................................................ SL-2.2 MATERIALS.............................................................. SL-2.3 CONSTRUCTION REQUIREMENTS............................................. SL-1 (2104) REMOVING MISCELLANEOUS STRUCTURES SL-1.1 DESCRIPTION This Work consists of removing, and salvaging or disposing of the in place miscellaneous structures, equipment and materials from existing lighting systems, and backfilling trenches, holes, and depressions in accordance 2104 “Removing Pavement and Miscellaneous Structures” and as shown on the Plans. SL-1.2 MATERIALS None SL-1.3 CONSTRUCTION REQUIREMENTS A Remove Miscellaneous Structures Remove, and salvage or dispose of the existing lighting systems in place miscellaneous structures as shown on the Plans and in accordance with 2104 “Removing Pavement and Miscellaneous Structures”. Miscellaneous structures includes the following: (1) Foundations and Equipment Pads (2) Light Poles (3) Lighting Units (4) Service Cabinets (5) Conduit Systems Destroy removed miscellaneous structures being disposed of to the satisfaction of the Engineer. Except under roadway surfaces, remove and dispose of the existing lighting systems in place conduit systems as shown on the Plans, unless otherwise specified in Contract Documents or as directed by the Engineer. 1-SL

Upload: others

Post on 24-Nov-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

DIVISION SLDELETE WHEN DONE: Statements in red are guidelines or instructional in nature. Remove these notes before completing the spec. When appearing at the top left of a provision, it pertains to the paragraph immediately beneath the note, as well as any indented items following it.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

Table of ContentsSL-1 (2104) REMOVING MISCELLANEOUS STRUCTURES..................................................................................1

SL-1.1 DESCRIPTION..................................................................................................................................................SL-1.2 MATERIALS.....................................................................................................................................................SL-1.3 CONSTRUCTION REQUIREMENTS...................................................................................................................

SL-2 (2545) LIGHTING SYSTEMS..................................................................................................................... 4SL-2.1 GENERAL.........................................................................................................................................................SL-2.2 MATERIALS.....................................................................................................................................................SL-2.3 CONSTRUCTION REQUIREMENTS.................................................................................................................

SL-1 (2104) REMOVING MISCELLANEOUS STRUCTURES

SL-1.1 DESCRIPTIONThis Work consists of removing, and salvaging or disposing of the in place

miscellaneous structures, equipment and materials from existing lighting systems, and backfilling trenches, holes, and depressions in accordance 2104 “Removing Pavement and Miscellaneous Structures” and as shown on the Plans.

SL-1.2 MATERIALS

None

SL-1.3 CONSTRUCTION REQUIREMENTS

A Remove Miscellaneous StructuresRemove, and salvage or dispose of the existing lighting systems in place miscellaneous

structures as shown on the Plans and in accordance with 2104 “Removing Pavement and Miscellaneous Structures”. Miscellaneous structures includes the following:

(1) Foundations and Equipment Pads(2) Light Poles(3) Lighting Units(4) Service Cabinets(5) Conduit Systems

Destroy removed miscellaneous structures being disposed of to the satisfaction of the Engineer.

Except under roadway surfaces, remove and dispose of the existing lighting systems in place conduit systems as shown on the Plans, unless otherwise specified in Contract Documents or as directed by the Engineer.

Include the following section when it is known that lead based painted structures have been used on the existing traffic control signal system that is being removed. If unsure that lead base painted structures exist, it is the district traffic office’s responsibility to find out before including this section in the special provisions. This is to ensure contractors bid the project accordingly.

1-SL

Page 2: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

A.1 Structures Containing Lead Based PaintHandle, transport, and dispose of miscellaneous structures containing lead based paint

in accordance with Occupational Safety & Health Administration (OSHA) and the Minnesota Pollution Control Agency (MPCA) regulations and the following.

(1) Read, certify understanding, and agree to abide to the requirements in OSHA 29 CFR 1926.62 and Minnesota Rules Chapter 5206, 7025, 7035, 7045 relating to the removal and disposal of lead base painted miscellaneous structures as hazardous waste.

(2) Submit to the Engineer a completed “Contractor Certification of Disposal" form included in this section.

(3) Submit to the Engineer a copy of the “Tipping Receipt” from the scrap yard or recycler.

The following removal language should be included when lighting cable is to be removed. The plan must also have a removals page. Additionally this removal should always be listed as a separate pay item. Measurement and payment language shown in that section must also be included in the special provisions for this work as noted below.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

B Remove Direct Buried Lighting CableRemove in- place out- of- service (abandoned) cables. Removed cables are the

property of the Contractor.

“Abandoned” means underground cable no longer in service and physically disconnected to a system once the new system constructed under the Contract has been completed.

Where in- place out-of-service (abandoned) cables are not removed provide the following at no additional cost to the Department;

(1) Perform a megohm meter test of each cable run in accordance with 2545.3K.1,

(2) Repair damaged cable with a Direct Buried Underground Cable Splice in accordance with 2545.3G “Splices”

(3) Place a Department furnished locator ball on the direct buried underground cable splice before backfilling

(4) Collect and record GPS coordinates of the installed direct buried underground cable splice and submit to the Engineer

(5) Install new handholes in accordance with 2545.3D “Handhole Installation” at both ends of each cable run

(6) Expose and protect the conductors at both ends of each cable run to allow for future locating

(7) Identify the cable run at both ends with a tag durable to withstand wet locations and labeled “ABANDONED LIGHTING CABLE”

(8) Collect and record GPS coordinates of each cable run at 10 foot intervals and submit to the Engineer

(9) Submit an As Built of the approximate location and linear footage of each cable run to the Engineer

(10) Provide a one-time locate of each cable run using red paint and red locating flags with a capital “A” inside a circle to represent abandoned facilities before final acceptance of the project

Noncompliance of these provisions will result in suspending the Work in accordance with 1501.2 “Suspending Work.”

2-SL

Page 3: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

The requirements listed are necessary for the Department to maintain its abandoned facilities in accordance with Minnesota State Law 216D.04 Subdivision 3-Locating Underground Facility; Operator and Minnesota Rules 7560.0125 Abandoned and Out-Of-Service Facilities.

The Engineer will distribute copies of the As Builts and GPS coordinates to the project file, District Traffic Office, and MnDOT’s Locating Office.

(The following language is used for Non-Federally Funded Projects Only)

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

C Delivery of Salvaged Materials Load and deliver materials designated for salvage and storage in accordance with the

2104 “Removing Pavement and Miscellaneous Structures” and the following:

Disassemble salvaged materials as directed by the Engineer.

Deliver salvaged materials to the Department at the Electrical Services Section (ESS), 6000 Minnehaha Avenue, St. Paul, MN, 55111.

Notify ESS at least 3 Business Days in advance of the planned delivery time and date of the salvaged materials.

Notify the Engineer in advance of contacting ESS.

Repair and replace salvaged materials damaged from the hauling operation, at no additional cost to the Department.

Obtain a salvaged material receipt from MnDOT’s Central Electrical Inventory Center that shows the Department has received the salvaged materials.

Submit a copy of this receipt to the Engineer for the permanent project records.

(The following Section to be used for Federally Funded Lighting Projects Only)

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

D (2104) HAUL SALVAGED MATERIALLoad and haul materials designated for salvage and storage in accordance with the

2104 “Removing Pavement and Miscellaneous Structures” and the following:

Disassemble salvaged materials as directed by the Engineer.

Haul salvaged materials to the Department at the Electrical Services Section (ESS), 6000 Minnehaha Avenue, St. Paul, MN, 55111.

Notify ESS at least 3 Business Days in advance of the planned delivery time and date of the salvaged materials.

Notify the Engineer in advance of contacting ESS.

Repair and replace salvaged materials damaged from the hauling operation, at no additional cost to the Department.

Obtain a salvaged material receipt from MnDOT’s Central Electrical Inventory Center that shows the Department has received the salvaged materials.

Submit a copy of this receipt to the Engineer for the permanent project records.

3-SL

Page 4: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

Hauling of salvaged materials to the Department at the location specified is paid for under Item No. 2104.601 (HAUL SALVAGED MATERIAL) at the contract LUMP SUM price which is payment in full for costs relative to hauling the materials to, and depositing the materials, at the location specified elsewhere in these Special Provisions.

SL-2 (2545) LIGHTING SYSTEMSProvide and install materials and equipment for construction of lighting systems in

accordance with the National Electrical Code (NEC), as specified in the Contract, and the following.

SL-2.1 GENERAL

A 2545 DefinitionsDefinitions are in accordance with Standard Specifications for Construction

Section1103 and as follows:

Approved/Qualified Products List (APL)

2545 Abbreviations

Glossary of Acronyms and Abbreviations

Acronyms and abbreviation used in the Contract to represent full text in accordance with 1102 “Abbreviations and Measurement Units” and as shown in Table 2545-1:

B Temporary Lighting SystemInstall Department provided and other materials as specified in the Contract and as

directed by the Engineer. Provide and install additional materials and equipment needed for a complete and operating temporary lighting system.

These materials include:

(1) Risers (2) Weatherheads (3) Wood poles (4) Overhead quadruplex (5) Conduit and conduit fittings (6) Ground rod electrodes (7) Electrical cables and conductors (8) Bonding and grounding materials and connections (9) Galvanized steel strapping

Additional Contractor provided materials and Work is included in the Unit Prices of the Pay Items that are part of the Lighting System.

Pay power costs, including extension of power lines by the electric utility.

Maintain the temporary lighting system in good working order throughout the duration of the Project.

This includes knockdowns (poles and service cabinets), light pole damage, luminaire outages, cable and conductor damages (buried and above ground), foundation damage, and service cabinet component failures.

4-SL

Table 2545-1Acronyms and Abbreviations Used

Acronym orShort Form Full Name or MeaningAPL Approved/Qualified Products List

Page 5: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

Costs for maintaining the temporary lighting system are included in the Unit Prices of the Pay Items that are part of the Lighting System.

SL-2.2 MATERIALS

A Buy AmericaUse domestically manufactured products that are composed predominately of steel,

iron, or both for the permanent installation of MnDOT electrical systems in accordance with 23 CFR 635.410 Buy American requirements.

During the product quotation stage, inform the manufacturer that steel, and iron product must meet the Buy America requirements in accordance with 23 CFR 635.410 for either State funded or federal aid Projects. MnDOT electrical systems products required to meet Buy America include the following:

Anchor Rods, Anchor Rod Templates, and HardwareStainless Steel and Steel Light PolesTraffic Signal Mast Arm Poles and BasesSteel Screw-in Light FoundationsPVC Coated RSC and Steel FittingsPVC Coated Junction BoxesPVC Coated Cast Steel Expansion and Deflection Fittings (23 CFR 635 Notice of nationwide waiver of Buy America for Pig Iron)Pole Mounting AdapterNavigation Light Swing ArmSteel Vertical Mount Tenon Adapters Teflon Coated F436 Structural Washers Exceptions to the Buy America requirements are existing materials salvaged and

installed within the Project Site, and materials required for maintenance or temporary installations on the Project.

A.1 Verifying Compliance with Buy AmericaFor verifying compliance with Buy America requirements, obtain from the

manufacturer two out of the three following documents:

(1) Mill Test Report (MTR) issued and signed by the fabricator stating that the materials subject to Buy America were melted and manufactured in the United States; written certifications from factory

(2) Written certification on company letterhead and signed by an authorized representative from manufacturers providing additional treatment to the fabricated material (blasting, coating) stating the treatment process occurred in the United States

(3) Written certification on company letterhead and signed by an authorized manufacturer representative, declaring the supplied materials subject to Buy America requirements fully meet.

Submit documentation to the Engineer.

B Rodent Intrusion BarrierRodent intrusion barrier listed on MnDOT’s APL for Lighting may be used instead of

stainless steel woven wire for double-nut connection light pole bases with a 10 ¾ in diameter base plate opening.

C 10 Foot Long Ground Rod ElectrodesProvide ground rod electrodes in accordance with 3818 except 10 foot long instead of

15 foot long ground rod electrodes may be used for service cabinet equipment pads and light foundations.

5-SL

Page 6: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

D Arc-Flash Hazard Warning LabelsProvide 4 inch Height x 6 inch Width vinyl or polyester labels meeting the following:

(1) White background(2) Orange background behind the WARNING text(3) Black text(4) Self-adhesive(5) Machine printed letters and numbers(6) Water-resistant

Figure 1 is for information and reference only.

Include the following paragraph when the District requires rigid steel conduit (RSC) from a

pad-mounted transformer SOP to the service cabinet.

All red text must be removed from the Special Provisions prior to the Special Provisions being submitted for project letting.

E Source of Power RSCProvide RSC from the Source of Power (SOP) to the lighting service cabinet.

Use these Special Provisions when the District wants to allow the option for the Contractor to use steel screw in foundations instead of concrete foundations. Concrete light foundations are required instead of steel screw in foundations at locations where Design E and H foundations will be surrounded by bituminous or concrete. Ensure the Plans show concrete foundations at these locations. Ensure the companion paragraph for installation of steel screw in foundations posted in the Construction requirements section of these Special Provisions is included and the Installation Steel Screw In Foundation detail sheet found on MnDOT’s Cell Lighting Library or Traffic Engineering (OTST) website is included on the Plans.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

6-SL

Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1Figure 1: Arc-Flash Warning Label – Category 1

Page 7: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

F Light Foundation-Design P, E, and H Steel Screw In Light Foundations- Design _ Steel Screw In may be used instead of concrete light

foundations. Use foundation design type shown on the Plans. Provide Light Foundations- Design _ Steel Screw In listed on MnDOT’s APL for Lighting.

http://www.dot.state.mn.us/pro ducts/index.htm l

Installers of steel screw in foundations are required to be trained and certified every two years by the manufacturer or the manufacturer’s representative of an approved steel screw in foundation listed on MnDOT’s Approved/Qualified Products List. Before starting steel screw in foundation installation, submit a current certified installer card issued by the manufacturer for each employee directly performing the installation.

Ensure the soil class types and soil conditions on the Project are acceptable and suitable for proper support and long term stability of steel screw in light foundations.

Before placing an order for steel screw in foundations provide the following.

(1) Review the Soils Classification for Steel Screw In Foundation Installation table in the Construction Requirements section for acceptable and suitable soils for steel screw in foundations.

(2) Perform an onsite field review of the soils and general locations where light foundations will be installed on the project.

(3) Review the Plans for lighting unit foundations surrounded by concrete or bituminous (e.g., placed in sidewalk or a parking lot).

(4) Review the Construction Requirements section for Light Foundations-Design_ Steel Screw In.

Install concrete light foundations, design type as shown on the Plans, if the District Traffic Office determines the soil conditions or the placement of the staked locations are not suitable for steel screw in foundations.

Install concrete light foundations, design type as shown on the Plans, where Design E or H foundations will be surrounded by bituminous or concrete.

G Light Foundation- Design E Modified Provide and install Light Foundations- Design E Modified as shown on the Plans.

H Light Foundation, Design P ModifiedProvide and install Light Foundations, Design P Modified as shown on the Plans.

I Light Foundation, Design R-40When rock is encountered installing a light foundation contact Jihshya J. Lin (651 366

4490) in MnDOT’s Bridge Evaluation and Fabrication Methods Unit and Gary Person (651 366 5598) in MnDOT’s Foundations Unit for a foundation design that can be used instead of Light Foundation Design E Standard Plate 8127.

J Light Foundation, Design R-50When rock is encountered installing a light foundation contact Jihshya J. Lin (651 366

4490) in MnDOT’s Bridge Evaluation and Fabrication Methods Unit and Gary Person (651 366 5598) in MnDOT’s Foundations Unit for a foundation design that can be used instead of Light Foundation Design H Standard Plate 8128.

K Equipment Pad B ModifiedProvide and install a complete concrete pad in accordance with MnDOT Standard Plate

8106 and with the modifications shown on the Plans.

Construct the mounting bracket assembly for the required service equipment as shown on the Plans.

7-SL

Page 8: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

The following text is provided as the designer needs to determine the type of cabinet that needs to be used. Some electric utilities require cold sequence disconnects and others do not when 240/ 480 VAC systems are installed. The designers need to determine ahead of time the cold sequence disconnect requirements:

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

L Type L1 Service Cabinet (120/240 VAC)Provide and install MnDOT approved Type L1 Service Cabinets (120/240 VAC) listed on

MnDOT’s Approved/Qualified Products List for Lighting and as specified in the Contract for supplying power to 120 volt lighting systems.

The utility termination lugs are not required in the Xcel Energy service area.

M Type L1 Service Cabinet (240/480 VAC)With Cold Sequence Disconnect Before Meter Socket

Provide and install MnDOT approved Type L1 Service Cabinets (240/480 VAC) With Cold Sequence Disconnect Before Meter Socket listed on MnDOT’s Approved/Qualified Products List for Lighting and as specified in the Contract for supply power to 240 volt lighting systems.

Do not provide service cabinets with the cold sequence disconnect and utility termination lugs in the Xcel Energy service area unless required by the authority having jurisdiction.

N Type L2 Service Cabinet (120/240 VAC)Provide and install MnDOT approved Type L2 Service Cabinets (120/240 VAC) listed on

MnDOT’s Approved/Qualified Products List for Lighting and as specified in the Contract for supplying power to 120 volt lighting systems.

The utility termination lugs are not required in the Xcel Energy service area.

O Type L2 Service Cabinet (240/480 VAC)With Cold Sequence Disconnect Before Meter Socket

Provide and install MnDOT approved Type L2 Service Cabinets (240/480 VAC) With Cold Sequence Disconnect Before Meter Socket listed on MnDOT’s Approved/Qualified Products List for Lighting and as specified in the Contract for supply power to 240 volt lighting systems.

Do not provide service cabinets with the cold sequence disconnect and utility termination lugs in the Xcel Energy service area unless required by the authority having jurisdiction.

P Type B Service Cabinet (120/240 VAC)Service Cabinet Type B is only available in a 120/240 VAC.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

Provide and install MnDOT approved Type B Service Cabinets (120/240 VAC) listed on MnDOT’s Approved/Qualified Products List for Lighting and as specified in the Contract for supply power to 120 volt lighting systems.

Q Roadway Light Poles:Designers should consider if these light poles are going to be installed in close proximity to fences or sound walls. If this is the case change 180 degrees below to 90 degrees.0 degrees is under the davit on the road side of the pole base. 90 degrees clockwise would place the door on the downstream side of the pole.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

8-SL

Page 9: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

The Plan must indicate the following:Luminaire Type Local Smart Photocontrol (when specified)

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

(1) Breakaway Light Poles

Provide stainless steel or aluminum davit arm type breakaway light poles in accordance with 3811 “Light Poles”, as specified and shown on the Plans, and meeting the following:

(a) Pole height as specified and shown on the Plans(b) Davits type arms with lengths as specified and shown on the Plans(c) Single davit or twin (dual) arm type davits as specified and shown on

the Plans(d) High base or transformer base (T-Base) designed for 1 inch diameter

anchor rods on a(e) 15 inch bolt circle as shown on MnDOT Light Foundation Design E

Standard Plate 8127 for 30 foot and 40 foot poles(f) High base or transformer base (T-Base) designed for 1 ¼ inch

diameter anchor rods on a(g) 17 inch bolt circle as shown on MnDOT Light Foundation Design H

Standard Plate 8128 for 49 foot (50 foot) poles(h) Use Table SL-2.2 Materials-1 to help identify the pole type designation

for breakaway light poles required for the Project.

Table SL-2.2 MATERIALS-1Breakaway Pole Type Designation

Pole TypeDesignation*e.g.

Davit Arm Length (feet)6 ft., 9 ft., or 12 ft.(as specified on the Plans)

Twin Arm (Dual)**“D”= Twin Arm Davit

Pole Height (feet)30 ft., 40 ft. or 49 (50) ft. (as specified on the Plans)

9-40 9 — 406D-49 6 D 49* Pole Type Designation shown is an example only. See the Plan for required Pole Type Designation on the Project** — Blank denotes Single Arm Davit

Provide and install a complete lighting unit as specified in the Contract.

Provide MnDOT approved Luminaires as specified on the Plan. MnDOT approved luminaires are listed on MnDOT’s Approved/Qualified Products List for Lighting:

http://www.dot.state.mn.us/products/index.html

(2) Barrier Mounted Light Poles:

The Plan must include a detail showing the nominal mounting height of the luminaire when the light pole is installed on the bridge structure, barrier, or retaining wall.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

The Plan must indicate the following:Luminaire Type Local Smart Photocontrol (when specified)

All Red text must be removed from the special provisions prior to the special provisions being

9-SL

Page 10: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

submitted for project letting.

Provide and install galvanized steel davit arm type non breakaway light poles in accordance with 3811 Light Poles, as specified and shown on the Plans, and meeting the following:

(a) Galvanized (coated) steel (b) High base style (c) Double access openings at 0 degrees and 180 degrees to the mast

arms for twin arm (dual) davit poles on median barrier(d) Access opening at 0 degrees to the mast arm for single davit arm poles

unless otherwise noted on the Plans(e) High base designed for one inch anchor bolts in a six bolt cluster and a

base plate opening sized as shown on Standard Plate No. 8332 “Anchor Rod Assembly for Light Foundation-Barrier”

(f) Nominal luminaire mounting height as specified and shown on the Plans

Use Table SL-2.2 Materials-2 to help identify the pole type designation for barrier mount light poles required for the Project.

Table SL-2.2 MATERIALS-2Barrier Pole Type Designation

Pole TypeDesignation*e.g.

Davit Arm Length (feet)6 ft., 9 ft., or 12 ft.(as specified on the Plans)

“B”DenotesBridge or Barrier Mount

Twin Arm (Dual)“D”= Twin Arm Davit

Nominal Pole Height (feet)40 ft. or 49 (50) ft. (as specified on the Plans)

6B-40 6 B ** 409BD-49 9 B D 49* Pole Type Designation shown is an example only. See the Plan for required Pole Type Designation on the Project** — Blank denotes Single Arm Davit

Maintain the nominal mounting height of the luminaire as shown on the Plans when the light pole is mounted on a foundation or structure designed above ground level or roadway surface.

Provide and install a complete lighting unit as specified in the Contract.

Provide MnDOT approved luminaires as specified on the Plan. MnDOT approved luminaires are listed on MnDOT’s Approved/Qualified Products List for Lighting:

http://www.dot.state.mn.us/products/index.html

Lighting Unit Options – Non-Breakaway Light PolesThe Plan must indicate the following:Luminaire TypeLocal Smart Photocontrol (if specified)

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

(3) Non-Breakaway Light Poles

Provide and install aluminum, galvanized steel, or stainless steel davit arm type non breakaway light poles in accordance with 3811 “Light Poles”, as specified and shown on the Plans, and meeting the following:

(a) Pole height as specified and shown on the Plans

10-SL

Page 11: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

(b) Davit type arms with lengths as specified and shown on the Plans(c) Single davit or twin (dual) arm type davits as specified and shown on

the Plans(d) High base or transformer base (T-Base)(e) 30 foot and 40 foot poles designed to be installed on MnDOT Light

Foundations-Design E Standard Plate No. 8127(f) 49 foot and 50 foot poles designed to be installed on MnDOT Light

Foundations-Design H Standard Plate No. 8128

Use Table SL-2.2 Materials-3 to help identify the pole type designation for non-breakaway light poles required for the Project.

Table SL-2.2 MATERIALS-3Non-Breakaway Pole Type Designation

Davit Arm Length (feet)6 ft., 9ft., or 12 ft.(as specified on the Plans)

Twin Arm (Dual)“D”= Twin Arm Davit

Pole Height (feet)30 ft., 40 ft. or 49 ft. (50 ft.) as specified and shown on the Plans

6-30 6 ** 30

9-40 9 — ** 40* Pole Type Designation shown is an example only. See the Plan for required Pole Type Designation on the Project** — Blank denotes Single Arm Davit

Maintain the nominal mounting height of the luminaire as shown on the Plan when the light pole is mounted on a foundation or structure designed above ground level, road or parking lot surface.

Provide MnDOT luminaires shown on the Plan and on MnDOT’s Approved/Qualified Products List for Lighting:

http://www.dot.state.mn.us/products/index.html

Provide and install a complete lighting unit as specified in the Contract.

(4) Rest Area Walkway Light Poles

Provide and install aluminum or stainless steel walkway poles as specified and shown on the Plans.

Provide a walkway light pole with a transformer base or high base of at least 1900 cubic inches designed to be installed on a Design P Foundation with four ¾ inch diameter anchor rods on an 11 inch bolt circle as shown on the Plans.

Provide MnDOT approved Walkway Luminaires as specified on the Plan. MnDOT approved Walkway Luminaires are listed on MnDOT’s Approved/Qualified Products List for Lighting:

http://www.dot.state.mn.us/products/index.html

Provide and install a complete lighting unit as specified in the Contract.

11-SL

Page 12: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

SL-2.3 CONSTRUCTION REQUIREMENTS

A Storing Materials Store and handle materials in accordance with 1606 “Storage of Materials”, 1607

“Handling Materials” and the manufacturer’s requirements. 

B Light Pole White “Neutral” Terminations Terminate the white neutral grounded conductor in light pole in accordance with

2545.3G “Splices” and as follows:

Provide and install split bolt connectors for splicing the white neutral grounded conductor. Do not use insulated wire splice connector blocks.

C Rodent Intrusion Barrier Rodent intrusion barrier listed on MnDOT’s Approved Products List may be installed

instead of stainless steel woven wire cloth, for double-nut connection light pole bases with a 10 ¾ inch diameter base plate opening. Install the barrier in accordance with manufacturer’s installation instructions.

Install the MnDOT’s APL barrier in accordance with manufacturer’s installation instructions. Fill gaps between the barrier and base plate, and between the barrier and the foundation with 100% clear silicone sealant.

D Arc-Flash Hazard Warning LabelingCalculate available fault current in accordance with 2545.3X and 2565.3 CC.

Establish available fault current and apply the appropriate label as follows.

Use the current edition of NFPA 70E “Standard for Electrical Safety in the Workplace” to determine the required PPE category and personal protective equipment.

If the available fault current is ≤ 25,000 amps then provide a label with the following information shown in Example 1.

12-SL

Example 1

Warning Arc Flash HazardAppropriate PPE RequiredArc Flash Boundary 19 inches Arc Flash PPE Category ____1____Working Distance 18 Inches Arc Flash Personal Protection Equipment (PPE)

List required clothing, Min Arc Rating of 4 cal/cm², and protective equipment in accordance with the PPE Table from the current edition of NFPA 70E Standard for Electrical Safety in the Workplace

Equipment ID

Page 13: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

If the available fault current is ˃ 25,000 amps, then determine PPE requirements in accordance with the current edition of NFPA 70E Standard for Electrical Safety in the

Workplace and provide a label with the following information shown in Example 2. Fill in the ___ (blank) with the required arc-flash PPE category and arc-flash boundary distance.

Install labels on the front of the dead front door of the electric service cabinet at eye level.

The following Section should only be included in projects when the contractor is going to be required to do excavation work. It should not be included when you are doing a luminaire replacement project.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

E Maintain Roadway Lighting Maintain and keep in operation new and existing lighting systems in accordance with

2545.3C “Existing Lighting Systems” and as follows:

This Work is included in the Unit Prices of the Pay Items that are part of the Lighting System.

Transfer of locating responsibility for underground lighting facilities to the Contractor begins on the project start date as shown on the proposal. Locate underground lighting facilities in accordance with Minnesota State Statute 216D.

MnDOT’s locating group will provide an initial locate of the underground lighting facilities within the project limits at the request of the Contractor at the start of the project. Submit request for initial locate to MnDOT’s Locating Office at least four Working Days before the Project start date.

Locate requests that are within the construction project limits will continue to be received by MnDOT’s locating office. These locate tickets will be forwarded to the Contractor’s representative responsible for coordinating locate requests within the projects limits. The locate tickets will be forwarded via email or fax.

Contact MnDOT’s Locating Office to confirm the locate tickets have been received within two hours of MnDOT’s Locating Office sending out.

Repair damage as the result of improperly located or unmarked underground lighting facilities within the project limits.

13-SL

Example 2

Warning Arc Flash HazardAppropriate PPE RequiredArc Flash Boundary ____Feet Arc Flash PPE Category ________Working Distance 18 Inches Arc Flash Personal Protection Equipment (PPE)

List required clothing, Min Arc Rating of ___ cal/cm², and protective equipment in accordance with the PPE Table from the current edition of NFPA 70E Standard for Electrical Safety in the Workplace

Equipment ID

Page 14: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

Repair damaged underground lighting facilities in accordance with 2545.3B “Construction Requirements, General” and in accordance with RTMC design and construction requirements.

Notify MnDOT’s Locating Office to provide contact information and confirm responsibility for locating MnDOT’s underground lighting facilities on the Project.

Fill out the locating responsibility form below and submit to the Engineer at the pre-construction meeting, a copy of the completed form should be sent to the following:

Electrical Services Dispatch Phone: (651)366-5750Fax: (651)366-5742E mail: [email protected] Minnehaha Ave. St. Paul, MN 55111-4014AndLocating Supervisor Phone: (651)755-9061Fax: (651)366-5742E mail: [email protected] Minnehaha Ave. St. Paul, MN 55111-4014

(The following Section should be filled out by the specification writer to direct the contractor and project engineer to the correct person in the District.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

MnDOT District Lighting Operations Name:Phone:Fax:E mail:Address:Maintain and repair damage that in the opinion of the Engineer has occurred by

someone other than the Contractor. The Department will pay for this Work in accordance with 1402.5 “Extra Work”.

Responsible for maintenance of the existing, temporary, and newly constructed lighting systems during periods of authorized Work suspension.

Submit to the Department contact information with the names and telephone numbers for 24 hours a day, 7 days a week maintenance as defined above.

The following Section should be left on its own page so the contractor can remove it and use the blank page

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

14-SL

Page 15: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

The verbiage below needs to be included when steel screw in foundations are going to be allowed by the District on construction projects. The specification writer needs to place the foundation design type in the blank line below. If there will be more than one design type foundation used, duplicate the verbiage below and have separate paragraphs for each design type of foundation. Make sure the companion paragraph for each foundation type located in the materials section of these special provisions is included.Plan designers and special provision writers must ensure the Steel Screw In Light Foundation Installation detail sheet which can be found in MnDOT’s cell library for Micro

15-SL

Locating Responsibility FormJob S.P. Number __________________________________

Job Type __________________________________

Start Date __________________________________

End Date __________________________________

T.H. __________________________________

Location __________________________________

Lighting/ Signal Inspector __________________________________

Contractor __________________________________

Contractor (24 Hour Contact) __________________________________

Project Manager __________________________________

Phone Number __________________________________

Fax Number __________________________________

Email __________________________________

Electrician __________________________________

Phone Number __________________________________

Locator Area __________________________________

Project Engineer __________________________________

Phone Number __________________________________

Chief Inspector __________________________________

Phone Number __________________________________

Weekly Meeting __________________________________

Page 16: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

station or on the Traffic Engineering (OTE) Lighting-Home web site page under Detail Sheets is included in the plan set prior to plan turn in.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

F Anchor Rod Tightening (Lighting)

The sixth paragraph of 2545.3H.1 “Anchor Rod Connections” is deleted and replaced with the following.

Install poles and tighten anchor rods in accordance with the MnDOT Anchor Rod Tightening Handbook- New Installation Procedures and the MnDOT Anchor Rod Tightening Form.

Complete a MnDOT Anchor Rod Tightening Form at a rate of one form per every 15 light poles with a minimum of one completed form per Project. Submit the completed forms to the Engineer.

For light poles use torque wrenches to tighten the top nuts to the required torque values.

Obtain Engineer’s approval of the wrench and provide proof of calibration performed within the last 12 months from an accredited calibration service before installing light poles.

If there are concerns with equipment downtime and completing the entire pole installation process in accordance with 2454.3H “Pole Installation”, then provide one crew for installing the pole and another crew for anchor rod tightening.

16-SL

Page 17: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

17-SL

Page 18: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

G Light Foundations-Design__ Steel Screw In (E, H, and P)Install Light Foundations Design__ Steel Screw In listed on MnDOT’s Approved/Qualified

Products List under “Roadway lighting” in accordance with the manufacturers recommended installation instructions, details on the Plans, 2545.3E “Light Foundations and Equipment Pad Installation”, 2451 “Structures Excavations and Backfills”, and the following:

Install foundations using a hydraulic drive head with a gear motor torque rating in accordance with Table 2545-2.

Table 2545-2Hydraulic Drive Head with Gear Motor Minimum Torque Rating

Foundation Design Minimum Torque in ft lbf E and P 10,000H 15,000

Ensure sufficient clockwise torque and downward pressure when installing foundations into the ground. A two speed drive head is recommended.

To prevent possible damage to the foundation do not exceed a torque capacity of 20,000 foot pounds for a Light Foundation Design E and P, and 30,000 foot pounds for a Light Foundation Design H.

The Department may require a torque measuring device to measure the installation torque to ensure maximum torque values are not exceeded.

Install foundations into undisturbed ground unless predrilling has been approved.

Install foundations in soil classifications in accordance with Table 2545-3.

Table 2545-3Soil Classification for Steel Screw In Foundation Installation

Class

Common Soil-Type Description

Geological Soil Classification

Typical Blow Count “N” per ASTM –D1586

Installation Requirements

0 Sound hard rock, unweathered

Granite, Basalt, Massive Limestone

N.A.Do not install, not acceptable or suitable for steel screw-in foundations

1 Very dense and/or cemented sands; coarse gravel and cobbles

Nitrate-bearing gravel/rock 60-100+ Acceptable for

steel screw-in foundations.*Pre-drill likely required in Class 1, 2, and 3 soils before installing steel screw in foundations

2 Dense fine sands; very hard silts and clays (may be preloaded)

Basal till; boulder clay; weathered laminated rock

45-60

3 Dense sands and gravels; hard silts and clays

Glacial till; weathered shales, schist, gneiss and siltstone

35-50

4 Medium dense sands and gravels; very stiff to hard silts and clays

Glacial till; hardpan; marls 24-40 Class 4, 5, 6, and

7 soils are suitable for installing steel screw-in foundations*Class 4 may require predrill

5 Medium dense course sands and sandy gravels; stiff to very stiff silts and clays

Saprolites, residual soils. 14-25

6 Loose to medium dense fine to coarse sands to stiff clays and silts

Dense hydraulic fill; compacted fill; residual soils

7-14

18-SL

Page 19: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

before installing steel screw in foundations

7 Loose fine sands; alluvium; loess; medium-stiff and varied clays; fill

Flood plain soils; lake clays; fill 4-8

8 Peat, organic silts; inundated silts, fly ash, very loose sands, very soft to soft clays

Miscellaneous fill, swamp marsh

0-5Do not install, not acceptable or suitable for steel screw in foundations

* Pre-drill may be allowed in Class 1, 2, 3 and 4 soils.

Pre-drill in certain soil types as specified in the Soil Classification for Steel Screw In Foundation Installation table in this section may be allowed when soils are difficult. Obtain Engineer’s approval before predrilling.

When pre-drilling provide the following.

(1) 6 inch hole for a Light Foundation Design E and P(2) 8 inch hole for a Light Foundation Design H(3) Drill no deeper than the length of the foundation(4) Before installing steel screw in foundations place the soil back in holes

to the level of the surrounding ground surface. Do not compact soil(5) Do not install steel screw in foundations in pre-excavated holes or

drilled shafts.(6) Do not install steel screw in foundations in frozen soils

Original staked locations for foundations may be moved no more than 10 feet in either direction parallel to the roadway to secure a more desirable location when soil conditions are questionable, or very dense or difficult. Obtain approval from the District Traffic Office before moving staked locations.

When rock or other conflicts are encountered during the installation process that prevents the foundation from being installed in accordance with contract documents, relocate the foundation 5 feet to 10 feet in either direction parallel to the roadway from the originally staked location.

Backfill unused holes made during steel screw in foundation installation attempts.

Install a concrete light foundation, design type as specified in the Plan, if the District Traffic Office determines the soil condition or the placement of the staked location is not suitable for a steel screw in foundation.

Install concrete light foundations, design type as specified on the Plan, where Design E and H foundations will be surrounded by bituminous or concrete.

Install preformed joint filler between concrete and the steel screw in foundation, where a Design P foundation will be surrounded by concrete.

Turn the foundations so poles mast arms and davits are perpendicular to the centerline of the roadway unless specified elsewhere in Contract Documents.

Turn the foundation shaft cableways parallel with the roadway unless specified elsewhere in Contract Documents or when directed by the Engineer. Use the notched cableway indicators located on the top of the foundation base plate to achieve the required placement of shaft cableways.

As the foundations are screwed into the ground ensure the shaft alignment is within a tolerance of 1/4 inch per 5 feet of depth. Install foundations plumb. Ensure the foundation base plate is level from side to side and front to back and the top of the foundation is flush with the ground line when the installation is complete.

19-SL

Page 20: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

Backfill and compact the cable or conduit trench.

H Electrical ServiceCoordinate the installation of Electrical Service, provide power to the service cabinets,

and verify the actual Work to be done and associated costs.

Proposed source of power addresses are shown on the Plans.

Responsible for “Application for Electrical Service” fees and payment to the Electric Utility for providing the electrical service connections.

Secure approval from the Engineer for any changes to the Electrical Service as reflected in the Plan.

No measurement is made of the various items that constitute Electrical Service, however this Work is included as part of the project (the electrical service costs will not be paid for as part of the pay item). Provide the Engineer a copy of the invoice from the electric utility. Payment is the electric utility company invoice cost plus 10%. The payment is compensation in full for costs, including, but not limited to, providing power to service cabinets, electric utility fees, Electric Utility Coordination, notifying MnDOT of ownership details, and all materials and labor necessary to construct the Electrical Service.

I Compliance with NEC Article 110. 24Provide fault current calculations in accordance with 2565.3CC “Available Fault Current

Calculations” and as follows:

Fill out the following Electric Service Information Form for Lighting Systems.

Submit to the Engineer, four copies of the Electric Service Information Form for Lighting Systems, before final acceptance of the project. The Engineer will distribute copies to the following:

(1) MnDOT Electrical Services Section(2) MnDOT Traffic Electrical Systems Engineer(3) MnDOT District Traffic Engineer(4) City of __________ or County of ________

Provide an "Electrical Service Information Form for Lighting Systems". This form is considered incidental work.

(The following form should be left on its own page so it can be removed from the special provisions and used by the contractor) See the next page of this document

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

20-SL

Page 21: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

21-SL

Page 22: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

J Salvage and Reinstall Lighting UnitSalvage and reinstall the complete lighting unit (pole, mast arm, luminaire, lamp,

transformer base and foundation), salvaged from the project, at the location shown on the Plans or as designated by the Engineer.

Install components of the lighting unit to the satisfaction of the Engineer and include miscellaneous hardware required for complete lighting unit relocation.

Restore the area of the removed foundations in accordance with 2105 “Excavation and Embankment”.

K Install Salvaged Lighting Service CabinetInstall the lighting service cabinet salvaged from the project, on Equipment Pad B and

at the location shown on the Plans or as designated by the Engineer. Coordinate with the electric utility to reconnect power to the service cabinet.

Install components of the service cabinet to the satisfaction of the Engineer and include miscellaneous hardware required for a complete service cabinet installation.

L AS BUILT DRAWINGS BASIS OFPAYMENTEnsure Division S Special Provisions “As-Builts” are included in the Division S Special Provisions.This would include the pay item 2011.601.

2011.601/01000 AS BUILT AS BUILT LS LUMP SUM 2018

After the July 2015 Project letting date the As-Builts verbiage should automatically be included in Division S Special Provisions by MnDOT’s Project Management & Technical Support Office.The District needs to include the verbiage below to trigger installation of Divisions S Special Provisions.Add the pay item as shown above to your pay item list.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

M As Built Drawings and GPS CoordinatesAs Built drawings and GPS coordinates in accordance with Division S Special Provisions

“AS-Builts” including Pay Item No. 2011.601 (AS BUILT).

The following removal language should be included when lighting cable is to be removed. The plan must also have a removals page. Additionally this removal should always be listed as a separate pay item. Be sure to include the removals language in that section of this specification above.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

N Remove Direct Buried Lighting CableRemove direct buried lighting cable as shown on the Plans is measured by the linear

foot. Direct buried lighting cable is paid for under pay Item No. 2104.503 (REMOVE DIRECT BURIED LIGHTING CABLE) at the Contract price per LINEAR FOOT, which price is compensation in full.

O Salvage Lighting UnitSalvage lighting unit (includes pole, mast arm, luminaire, transformer base, and

foundation) as specified herein, at the location shown on the Plans is measured as an integral unit complete and is paid for under pay Item No. 2104.502 (SALVAGE LIGHTING UNIT) at the Contract price per EACH, which price is compensation in full.

22-SL

Page 23: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

P Salvage Light FoundationSalvage light foundation as specified herein, at the location shown on the Plans is

measured as an integral unit complete and is paid for under pay Item No. 2104.502 (SALVAGE LIGHT FOUNDATION) at the Contract price per EACH, which price is compensation in full.

Q Install Salvaged Lighting UnitInstall salvaged lighting unit (includes pole, mast arm, luminaire, transformer base,

and foundation) as specified herein, at the location shown on the Plans is measured as an integral unit complete in place and is paid for under pay Item No. 2545.602 (INSTALL LIGHTING UNIT) at the Contract price per EACH, which price is compensation in full.

This item includes installing salvaged lighting units as specified including the following:

(1) Foundation(2) Luminaire(3) Pole base(4) Pole and bracket(5) Breakaway fuse holder(6) Wiring between pole base and luminaires(7) Numbering of the light pole(8) Miscellaneous items required for a complete installation(9) Bonding and grounding materials and connections(10) Traffic Control

The section below is provided for the very rare instance you have painted structures containing lead based paint. MnDOT discontinued using lead based paint in 1984.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

R Structures Containing Lead Based PaintHandle, transport, and dispose of miscellaneous structures containing lead based paint

in accordance with Occupational Safety & Health Administration (OSHA) and the Minnesota Pollution Control Agency (MPCA) regulations and the following.

(1) Read, certify understanding, and agree to abide to the requirements in OSHA 29 CFR 1926.62 and Minnesota Rules Chapter 5206, 7025, 7035, 7045 relating to the removal and disposal of lead base painted miscellaneous structures as hazardous waste.

(2) Submit to the Engineer a completed “Contractor Certification of Disposal" form included in this section.

(3) Submit to the Engineer a copy of the “Tipping Receipt” from the scrap yard or recycler.

The form below is provided as an example. The actual form must be downloaded by the contractor. Keep the form on the next two pages in the document.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

23-SL

Page 24: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

24-SL

Page 25: (2104) REMOVING MISCELLANEOUS STRUCTURES - …€¦  · Web viewE mail: bruce.camitsch@state.mn.us 6000 Minnehaha Ave. St. Paul, MN 55111-4014 (The following Section should be filled

SP XXXX-XXInsert Date

The Office of Environmental Stewardship sets the policy and procedures for regulated materials management.

The contractor must follow the links below to obtain the current work order form and the list of approved waste contractors.

http://www.dot.state.mn.us/environment/regulatedmaterials/wastemgmt.html

Hazardous Waste Work Order Form (Word) MnDOT approved list of waste contractors (Word)  

25-SL