2(169) tribal area project
TRANSCRIPT
-
8/9/2019 2(169) Tribal Area Project
1/22
Subject:- TRIBAL AREA DEVELOPMENT PROJECT PC-I
Today I have received PC-I of above project. Changes as desired by
Secretary, P&D have been incorporated in the document.
It is thus recommend that PD, DGK-RDP may be directed to submit 20copies of PC-I to Coordination Section for placing scheme before PDWP.
(Muhammad Aslam Ch.)
Chief (RP)27.02.2009
Secretary, P&D
-
8/9/2019 2(169) Tribal Area Project
2/22
Subject:- BRIEF FOR TRIBAL AREA DEVELOPMENT PROJECT D.G.
KHAN & RAJANPUR
Above stated information was desired by Secretary, P&D Department and
same is placed below at Flag A.
There is an allocation of Rs. 100.00 million during current financial year
and overall estimated cost is Rs. 3.033 billion at G.S.No. 1422 of MTDF.
In case clearance for above concept is awarded detailed PC-I may be
submitted by PD, D.G. Khan, Rural Development Project same concept paper is also
desired by DFID to explore possibilities for its financing.
Submitted please.
(MUHAMMAD ASLAM CH.)
CHIEF (RP)
13.09.2008
SECRETARY, P&D
-
8/9/2019 2(169) Tribal Area Project
3/22
Kindly refer to noting para.
It is submitted that the information regarding base line, vision of the project,
action plan and proposed interventions are to be worked out in detail. Some spade work
already done. However, Ex-Secretary, P&D Department desired to re-thrash all this
information and prepare a visionary paper after assessing the actual requirements of thearea in consultation with local leaders. Mr. Ikramullah Khan, PD, BRDP/MD, CDA who
had already worked as P.A. in the Tribal Areas was assigned to prepare fresh concept
paper and also to translate it into PC-I forms in consultation with the undersigned and staff
of D.G.K. RDP. The same was done and concept paper was submitted.
Now this paper is to be translated into PC-I and we also have to look into
other requirements of the area in view of the existing working of NB Deptts in TADP. To
asses the need and to know the exact requirements of NBD, this section has written a letter
to NBD, which includes EDOs of Agriculture, Works and Services, Health Departments,
SE, PHED, CE, I&P. Copies were also forwarded to DCO D.G.Khan & Rajanpur with the
request to provide the base line data, details of activities planned each department and
development schemes to be under taken with reference to objectives, cost lay out and
physical targets (F/A).
Letter was sent to all concerned on 20 th September 2008 but only one
department i.e. I&P (F/B). Responded Information from all remaining is still awaited and
we have again forwarded a reminder to do the needful before 12th October 2008 (F/C).
Mr. Aftab, DPD, DGK-RDP is working on the base line data and tailoring
same in the form of PC-I. This still needs a lot of work and skill to make it standard
documents acceptable to donors (as DFID has also indicated its willingness to explore its
financing in a tele-conference held in office Chamber of Secretary P&D Department.
Task is urgent. Work needs full time focus, concentration and skill at
appropriate level is also inevitable to accomplish this task. It is, therefore, requested
suggest as under:-
i). I may please be relived from the task of Chief (Ind.) & Chief (Env.) and
only works of regional Planning may be look after by me in addition to
working on PC-I of TADP & Punjab Poor Districts Development
Programme of DFID.
ii). Allow me to visit D.G. Khan for four days w.e.f. 13.10.2008 to 16.10.2008.
-
8/9/2019 2(169) Tribal Area Project
4/22
iii). Interim report may be submitted to Secretary P&D Department on 18th
October 2008.
iv). Remaining days i.e. 20th to 24th October 2008 may be utilized at P&D office
to look after the issue of R.P section only.
v). Meanwhile, Mr. Muhammad Awais, Assistant Chief (R.P), may co-opt mein the accomplishment of this task.
vi). Mr. Ikramullah Khan, and the undersigned may again visit to D.G. Khan
from 25th to 28th and PC-I may be submitted on 29th October 2008 in
accordance with the guidelines given by you.
vii). Second visit with Mr. Ikramullah Khan, may also provide an opportunity to
exchange views on proposed schemes with the leading person of Tribal
Area and District Administration of D.G. Khan and Rajanpur.
Above proposal is submitted as desired.
(MUHAMMAD ASLAM CH.)
Chief (R.P)
09.10.2008
SECRETARY, P&D
-
8/9/2019 2(169) Tribal Area Project
5/22
Subject:- PREPARATION OF PC-I/PROJECT FORMULATION FOR TRIBAL
AREA DEVELOPMENT PROJECT (TADP)
Programme Director, Punjab Devolved Social Services Programme (PDSSP)
was requested vide this office letter at page 251/C to approach Technical Assistance
Management Agency (TAMA) for the hiring of consultants for the preparation of PC-
I/Project Formulation for Tribal Area Development Project (TADP). Secretary, P&D
Department also had a telephonic discussion with D.G., ABAD for same assignment.
However, no response has been received from both sides so far.
If approved, we may send a reminder to P.D., PDSSP and a separate letter to
D.G., ABAD to process it further.
D.F.A-I & II is added please.
ASSISTANT CHIEF (RP)
26.11.2008
CHIEF (RP)
As per direction of Secretary P&D, I have discussed issue for formulation of
PC-I on Tribal Area Development Project with the DG, ABAD and subsequently with Chief,
ABAD. Chief, ABAD has stated that he has no funds for preparation of such documents and
Rs. 1.50 million are needed to do such work. He was of the view that in his budget there was
no provisions for POL, TA, Stationery etc. Chief, ABAD is perhaps not aware of the nature
of problem and its solution.
In these circumstances, it is proposed that staff of D.G. Khan, Rural
Development Project may be utilized under the supervision of Chief (RP). Chief (RP) may
be relieved from the assignment of Industries, TEVTA, Mines & Minerals, Environment and
Information Culture & Youth Affairs. In this way three or four days of each week are to be
devoted at D.G. Khan and remaining thee days at P&D headquarter. Mr. Khalid Basir
Sheikh, Assistant Chief (Industries) who has recently joined in P&D Department and
working as AC (Industries) may also co-opt as he has extensive experience in RP.
If above proposal agreed, PC-I on Tribal Area Development Project may be
prepared within 20 days.
Another modus operandi is to contact again PD, PDSSP and to remind him
for hiring a consultant at the earliest. DFA is placed below for that purpose.
(MUHAMMAD ASLAM CH.)
CHIEF (RP/ENV/IND)27.11.2008
SECRETARY, P&D
-
8/9/2019 2(169) Tribal Area Project
6/22
Subject:- OUTLINE FOR PREPARATION OF PC-I/FORMULATION FORTRIBAL AREA DEVELOPMENT PROJECT (TADP)
I have following submission on this issue:-
i. A lot of work is done and its updating, tabulation and analysis is required.
It can easily be done by utilizing the staff available in D.G. Khan Rural
Development Project Office (Flag A).
ii. Concept for proposed interventions for TADP is also prepared (Flag
B). These interventions, which are feasible after visit of project area,
may be incorporated in PC-I document.
iii. Lessons learned from implementation of BRDP, D.G. Khan Rural
Development Project and ABAD projects are also over asset which can be
looked into. However, all the inputs are scattered and to be presented inlogical sequence and in accordance with the requirement of the PC-I.
Implementation framework and criteria evolved for execution of physical
works and community development may be replicated after incorporating
some changes incurred due to evolving recent changes in administrative
setup.
iv. PC-I already prepared by D.G. Khan Rural Development Project
on this issue is also available (Flag C). These inputs can be used in PC-
I.
v. PC-I may be ready for presentation before you If above work plan
is adhered.
My personal vision on this issue is as under:-
INTERVENTIONS MAY BE CATEGORIZED INTO TWO PARTS
a. Interventions regarding development of physical
infrastructure
It includes:
i. Track roads,
ii. Rural roads,
iii. Link roadsiv. Water conservation and storage works
-
8/9/2019 2(169) Tribal Area Project
7/22
For this purpose two or three persons of BRDP and D.G. Khan Rural
Development Project having experience in preparation of road cost estimate may be
utilized to prepare rough cost estimate. Estimated cost may be Rs. 1.00 billion.
Engineering staff may also help to scrutinize scheme submi8tted by
Irrigation Department (page 209 to 222). Interventions regarding provision of water
development storage are also prime need of the area. This water may be utilized for
drinking purposes, livestock needs and in some cases for Irrigation. Estimates of about 10
prime spaces may be a part of PC-I. Cost may be Rs. 5 billion.
b. Development of small ponds
It is prime need of the area. With the involvement of community
development component in D.G. Khan Rural Development Project some estimation in
specific location may be prepared for pond development where desired.
PRODUCTION / INCOME GENERATING ACTIVITIES:-
To initiate such activities prime emphasis may be on skill generation. Skill
to be provided in accordance with the requirements and need of the area. For this
purpose, some training programs may be chalked out at least 4 to 5 prime location in each
union council and D.G. Khan Office may be directed to work out details.
PROVISION OF BASIC FACILITIES:-
For this purpose, EDO (Education) and EDO (Health) may be co-opted
and missing facilities in the institutions already available may be included in the PC-I.
DO (Planning) in D.G. Khan and Rajanpur may be consulted regarding activities to be
planned in that area.
Thus this visit may enable to propose framework of activities to be
initiated and tentative implementation plan of these activities. Brief resume on the work
performed during this visit may be presented to Secretary, P&D Department and detailed
implementation plan, phasing of these activities and implementation mechanism may
thus be tailored accordingly in the PC-I documents.
-
8/9/2019 2(169) Tribal Area Project
8/22
First visit to project area will be for four days, subsequently it will be
followed with another four days visit after week interval. After 20 days document will be
ready.
-
8/9/2019 2(169) Tribal Area Project
9/22
Subject:- TRIBAL AREA DEVELOPMENT PROJECT (TADP)
Reference noting para 27.
Working paper has been forwarded to Coordination Section. Pre-PDWP
meeting also convened with Project Director, D.G. Khan Rural Development Project
today. After comprehensive discussion on the observation of Working Paper, annotated
replies have been prepared (Flag A). This input may be used for PDWP and also got
included in approval version of PC-I, where amendments needed.
Submitted for perusal.
(MUHAMMAD ASLAM CH.)
CHIEF (RP)
18.03.2009
SECRETARY, P&D
-
8/9/2019 2(169) Tribal Area Project
10/22
Subject:- WORK PLAN FOR TADP (D.G. KHAN AND RAJANPURDISTRICTS) FOR FINANCIAL YEAR 2008-09
Project Director, D.G. Khan Rural Development Project vide PUC at page
145/C has submitted the Annual Work Plan for Tribal Areas Development Project
(TADP) for the year 2008-09. The work plan has following parts:-a. Para 3 of the work plan
Activities proposed for identification, survey, estimates, community
organizations, briefing and orientation of the line departments,
prioritization of the needs, preparation for training of unskilled personsand coordination with border military police check post for
implementation of the components of the project included in the approved
PC-I.
b. Para 4 of the work plan
Administrative, management and financial decisions including:-
i. Arrangement for posting of Project Director.
ii. Issuance of Administrative Approval.iii. Release of funds and use of assignment account of Project
Director DGK-RDP for this project.
iv. Advertise posting of staff and also to notify committee for
it Rules and qualifications for different posts in DGK-RDP may beapplied for this project too.
v. Notifications for different committees for execution,
approval and monitoring of project.vi. Shifting of assets of DGK-RDP to this project.
c. Para 5 of the work plan
Tentative schedule for final clearance of PC-I, issuance of administrative
approval, constitution of the different committees and opening /switchover of assignment account.
The work plan has been examined in RP Section and following
observations are made:-
i. No financial expenditure has been proposed during current financial year.
ii. The preparation activities proposed in para 3 of the plan for
implementation of components of physical infrastructure development,
community development, social infrastructure and livestock are found to
be according to the provisions of PC-I. The approval of the proposed work
plan is however required to be obtained from Project Steering Committee
which is yet to be constituted.
-
8/9/2019 2(169) Tribal Area Project
11/22
iii. Action regarding administrative arrangements requested vide para 4 (1, 2,
3, 4, 6) of the work plan may be initiated by Admn Wing of P&D
Department. The action on para 4 (2, 5) will be taken by RP Section.
iv. The project authority can however go ahead with incorporation of
amendments in the PC-I as per observations of PDWP, clearance of PC-I,clearance of posts and issuance of administrative approval.
It is proposed that Project Director, DGK-RDP may advised to initiate the
action regarding amendments of the PC-I, issuance of administrative approval and
clearance of posts. The project steering committee may also be notified as per
implementation arrangements provided in the PC-I and minutes of PDWP placed at Flag
A. The necessary draft notification for project steering committee is being prepared in
RP Section and will be submitted shortly.
(Dr. Mahmood Khalid Qamar)
CHIEF (RP)
16.04.2009
SECRETARY, P&D
-
8/9/2019 2(169) Tribal Area Project
12/22
Subject:- TRIBAL AREA DEVELOPMENT PROJECT D.G. KHAN &RAJANPUR
There is no proposal for inclusion of Tribal Area
Development Project in ADP 2009-10. The one approved by PDWP will
be considered under Southern Punjab Development Programme during
the currency of the next financial year.
CM Directive (98/C) is addressed to Secretary Local
Government Department. Further action on the issue will, therefore, be
taken after the receipt of reference from Local Government Department.
(Dr. Mahmood KhalidQamar)
Chief (Regional Planning)11.06.2009
SECRETARY, P&D
-
8/9/2019 2(169) Tribal Area Project
13/22
Subject:- PROVISION OF FUNDS FOR TRIBAL AREADEVELOPMENT PROJECT (TADP) D.G. KHAN &RAJANPUR IN THE ADP OF PUNJAB GOVERNMENTBUDGET FOR THE YEAR 2009-10
Project Director, D.G. Khan Rural Development Project has
informed that the scheme Tribal Area Development Project was approved
for the cost of Rs. 3380.840 million for implementation in D.G. Khan and
Rajanpur Districts. The scheme was proposed for inclusion in ADP 2009-
10 but was subsequently dropped from the programme with the
understanding that the identified schemes of Southern Punjab will be
funded out of Southern Punjab Development Project.
Currently 56 numbers of employees are working in DGK-RDP
which has been conceived to be continued in Tribal Area Development
Project as such initiation of Tribal Area Development Project from 1st July
2009 is very important for continuation of the staff already working as
D.G. Khan Rural Development Project which is scheduled to be closed on
30.06.2009.
Project Director, DGK-RDP has therefore requested for
allocation of Rs. 469.110 million to the scheme Tribal Area Development
Project in D.G. Khan and Rajanpur Districts during 2009-10. Allocation
may therefore be provided out of available allocations of Rs. 5,000.00
million in Southern Punjab Development Project appearing at Gen. Sr. No.
2287 of ADP 2009-10.
(Dr. Mahmood KhalidQamar)
Chief (Regional Planning)22.06.2009
SECRETARY, P&D
-
8/9/2019 2(169) Tribal Area Project
14/22
Subject:- PROVISION OF FUNDS FOR TRIBAL AREADEVELOPMENT PROJECT (TADP) D.G. KHAN &RAJANPUR IN THE ADP OF PUNJAB GOVERNMENTBUDGET FOR THE YEAR 2009-10
As desired I have discussed the case with Chief
(Coordination) and Project Director, D.G. Khan Rural Development
Project. The minimum requirement for the establishment of the project
and office building / POL charges for the period of 4 months are Rs. 7.108
million (Flag X). Out of this amount, Rs. 4.948 million is meant for
salaries.
The scheme Tribal Area Development Project (TADP) was a
part of ADP 2008-09 and appeared at Gen. Sr. No. 1422 with an allocation
of Rs. 100.00 million but could not be included in ADP 2009-10.
It is, therefore, proposed that an amount of Rs. 7.108 million
may be provided to Tribal Area Development Project during 2007-08 out
of block allocation of Rs. 1,300.000 million meant for unfunded schemes
appearing at Gen. Sr. No. 4432.
(Dr. Mahmood KhalidQamar)
Chief (Regional Planning)23.06.2009
SECRETARY, P&D
-
8/9/2019 2(169) Tribal Area Project
15/22
Subject:- APPROVAL FOR PAY PACKAGE OF STAFF OF TRIBAL AREADEVELOPMENT PROJECT (TADP) FOR D.G. KHAN & RAJANPUR
DISTRICTS
Tribal Area Development Project (TADP) approved for the cost of Rs.3380.94
million is under implementation for the gestation period of five years. During 2009-10 anamount of Rs.20.00 million has been provided to the project for initiating surveys and
different activities for implementation of the project (Flag A at page 132/C).
While clearance of 124 posts (of contractual basis) envisaged for
implementation of the project, Finance Department has desired to seek the approval of pay
package of the posts from Chief Minister through a summary.
Project Director, TADP has accordingly submitted a draft summary for
approval of pay package of 120 posts in Administration Wing and Social Mobilization Wing
of the project. The pay package stands approved by PDWP in the form of PC-I.
Draft summary is placed below.
(Dr. Mahmood Khalid Qamar)
Chief (Regional Planning)
19.11.2009
SECRETARY, P&D
-
8/9/2019 2(169) Tribal Area Project
16/22
Subject:- MEETING OF CONTRACT APPOINTMENT REGULATIONSCOMMITTEE (CARC)
As desired, I have attended the meeting of Contract Appointment Regulations
Committee (CARC) held under the chairmanship of Secretary (Regulations) on 04.12.2009.
Necessary correction in the criteria for employment of Tribal Area Development Project Staff
has proposed by the Committee has been carried out and the revised version is placed below.
If approved the same may be submitted to Secretary (Regulations).
(Dr. Mahmood Khalid Qamar)
Chief (Regional Planning)05.12.2009
SECRETARY, P&D
-
8/9/2019 2(169) Tribal Area Project
17/22
Subject:- FIRST PROJECT STEERING COMMITTEE MEETING OF
TRIBAL AREA DEVELOPMENT PROJECT D.G. KHAN AND
RAJANPUR DISTRICTS
Tribal Area Development Project (TADP) approved for the cost of
Rs.3380.94 million is under implementation for the gestation period of five years. During
2009-10 an amount of Rs.20.00 million has been provided to the project for initiating
surveys and different activities for implementation of the project. As per provision of the
PC-I Steering Committee of the Project was constituted under the chairmanship of
Chairman, P&D Board (Flag X).
Project Director, TADP vide PUC has now requested for convening the
first meeting of the Project Steering Committee notified under the chairmanship of
Chairman, P&D Board to discuss the following agenda items:-Agenda item No.1
i. Introduction and objectives of the project
ii. Physical and financial phasing of project activities
iii. Work Plan for the year 2009-10 (both physical and financial)
Agenda item No.2 Implementation issues and options
i. Requirements of additional funds for the year 2009-10.
ii. Staffing of the project for TADP D.G. Khan & Rajanpur.
iii. Suggestion for changes in implementation methodology.
iv. Recommendations of the meeting held by the Minister, LocalGovernment and Community Development Department.
v. Socio Economic conditions of Tribal communities of District
Rajanpurwaving off, upfront contribution by poor communities.
vi. Filling of posts through transfer.
vii. Issues regarding identification of intervention by Line Departments.
Agenda item No.3 includeany other item with the permission of Chair.
Chairman, P&D Board may, therefore, be approached for indicating the
date and time of the Project Steering Committee.
(Dr. Mahmood Khalid Qamar)
Chief (Regional Planning)
05.01.2010
SECRETARY, P&D
-
8/9/2019 2(169) Tribal Area Project
18/22
Subject:- CONSTITUTION OF COMMITTEES
Project Director, TADP has informed that PC-I of Tribal Area
Development Project D.G. Khan provides for constitution of the following Committee:-
1. Senior recruitment committee for recruitment of officials of TADP
BS-16 and above.
2. Staff recruitment committee for recruitment of official in BS-1-15.
3. Special Purchase Committee for procurement of
equipment/vehicles.
He has, therefore, requested for notification of the above said Committee.
The case has been examined in RP Section and it is observed that the
constitution of Committees is in accordance with the objective and provisions of the PC-I.
Further necessary action regarding notification of the Committees as per drafts enclosed
with the PUC may kindly be taken by Admin Wing.
(Dr. Mahmood Khalid Qamar)
Chief (Regional Planning)
13.01.2010
SECRETARY, P&D
-
8/9/2019 2(169) Tribal Area Project
19/22
Subject:- TRIBAL AREA DEVELOPMENT PROJECT (TADP)
Observations of Sr. Advisor to Chief Minister Punjab regarding Tribal Area
Development Project (TADP) have been examined in Regional Planning Section in
consultation with Project Director, TADP (Flag X). The annotative comments of the
department on the observations are as under:-
Sr.
No.
Observations of Sr. Advisor to
Chief Minister Punjab
Comments of Project Director, TADP
1. My first and foremost concern is that
in the entire process of conception,
identification of schemes and
prioritization of the project, public
representatives of the area have not
been consulted. It is beyond my
understanding as to how can any
project of public welfare beimplemented, without the input of
public representatives. It is further
observed, that the identification of
initiatives in Education, Health and
Livestock are also to be identified by
the respective departments, and not
through public representatives.
The project is continuation of ADB funded
Bahawalpur Rural Development Project
which expired in 2007-08. The project was
rated as very good by Asian Development
Bank (ADB) and the interventions of the
D.G. Khan Rural Development Project have
been continued in the Tribal Area
Development Project. The project basicallyoffers the following interventions:-
Physical Infrastructure Development
(Jeepable tracks, metalled roads,
water resource development,
electrification, drinking water
supply) Cost Rs. 2,290 million.
Community Development (project is
open for the facilities to be identified
by Communities) Cost Rs. 600
million. Social Infrastructure (school council
support, health support, livestock,
skill generation, boarder military
police, institutional support and
consultancy) Cost Rs. 490.940
million.
As per implementation methodology
approved in the PC-I.
o Physical infrastructure
development projects will beidentified in consultation with
representatives of tribal area and
will be implemented by PMU,
Irrigation, Public Health, Local
Government Departments and
TEVTA.
o Community Development
Projects will be identified by the
communities and implemented
by themselves.
o Social Infrastructure Projects
will be identified by the
departments of education,
livestock, TEVTA and in
consultation with communities.
-
8/9/2019 2(169) Tribal Area Project
20/22
Sr.
No.
Observations of Sr. Advisor to
Chief Minister Punjab
Comments of Project Director, TADP
2. No full time Project Director is
available for the project. A part time
project director will have bearing on
the execution of the project.
Moreover, it is also proposed that
for the successful completion of the
project, office of the project director
should be located in Dera Ghazi
Khan.
Case for posting of full time Project Director
is under process. As per design of the
project the office of the project is
established in D.G. Khan.
3. Construction of jeep able tracks (300
kms) needs to be undertaken
vigilantly, as there is a possibility of
misuse of funds.
Jeepable tracks will be approved by the
Steering Committee. Due vigilance will be
exercised while identification and
construction of jeepable tracks so as to
benefit maximum population/ area.
4. Electrification of remote areas
through alternate energy sourcerequires clarification. Any alternate
energy source introduced in the
tribal area should be having
minimum O&M cost.
As per information provided by Project
Director, TADP electrification throughalternate energy source is the most popular
demand of the area and so far applications
for 3,000 households have been received by
the project from the communities of the
project area cost of which is 5 times more
than the provision of the PC-I. While
procurement of solar panels the suppliers
will be made responsible for maintenance of
solar panels for 20 years, battery for two
years and other accessories for one year. As
such O&M expect of the alternate energysource will be taken care of.
5. Provision of a Mobile Dispensary is
a good initiative, but the vehicle
should be worthy of the tribal area
mountainous terrain.
During the proceedings of Steering
Committee meeting held under the
chairmanship of Secretary, P&D on
03.02.2010, the representative of Livestock
Department informed that the department is
providing 14 mobile dispensaries for
functioning in the project area. These mobile
dispensaries have been provided with 4x4
double cabin vehicles suitable formountainous terrain. Project authorities are
exploring with Livestock & Dairy
Development Department to support these
mobile dispensaries (already in pipeline)
through the missing requirements.
6. Skills training to tribal area
inhabitants has to be in line with the
local economic conditions and
needs. Identification of types ofskills, and medium of imparting
these skills, has not been explained
in the project documents.
The issue was discussed in the Steering
Committee meeting and programme based
on need assessment is being devised with
the help of TEVTA.
-
8/9/2019 2(169) Tribal Area Project
21/22
Sr.
No.
Observations of Sr. Advisor to
Chief Minister Punjab
Comments of Project Director, TADP
7. Eight numbers of Consultancies
are to be awarded for the project.
Details of these consultancies are
not known.
A provision of Rs. 48 million has been
provided for consultancies for baseline
survey, third party validation, ground water
studies, seismic surveys etc. The provision
will be utilized after approval by the
Steering Committee.
8. Keeping in view the economic
conditions of the tribal community
of both, Dera Ghazi Khan and
Rajanpur, reduction in their share in
community development projects
may be considered.
The issue of economic conditions of the
tribal community was discussed in the
Steering Committee meeting and it was
decided to contain their contribution in case
of community development project to 20%
which will be paid by them in shape of
labor, material, O&M etc.
9. It is observed that more than 50
posts in the PMU are under the
unskilled category. I would urge thatrecruitment against unskilled/ semi
skilled positions may be made from
local tribesmen. This proposal is
very much in line with one of the
objectives of the project i.e.,
employment generation. Moreover,
being part of the project, ownership
of the project by the tribesmen will
also be facilitated.
Out of 120 posts, 70 posts are vacant which
include 40 posts of clerical and 18 posts of
support staff. While recruiting the un-skilledand semi-skilled positions local tribesmen
will be given the first preference.
If approved the above remarks may be conveyed to Sirdar Zulfiqar Ali Khan Khosa, Sr.
Advisor to Chief Minister Punjab in response to his note for Chairman, P&D Board.
(Dr. Mahmood Khalid Qamar)
Chief (Regional Planning)
04.02.2010
SECRETARY, P&D
-
8/9/2019 2(169) Tribal Area Project
22/22
Subject:- MINUTES OF FIRST STEERING COMMITTEE MEETING OF
TRIBAL AREA DEVELOPMENT PROJECT (TADP)
Minutes of the First Steering Committee meeting for Tribal Area
Development Project (TADP) held on 03.02.2010 under the chairmanship of Secretary,
P&D are placed below for approval.
(Dr. Mahmood Khalid Qamar)
Chief (Regional Planning)
08.02.2010
SECRETARY, P&D