222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
1
NATIONAL HIGHWAY AUTHORITY
Secretariat Section
CONFIRMED MINUTES
Subject:- 222nd Meeting of the NHA Executive Board Held on
October 16, 2012 at Islamabad
1. Introduction
1.1. The 222nd meeting of the Executive Board of the National
Highway Authority was held at 1130 hours on Oct 16, 2012 at the
NHA Head Office Auditorium, Islamabad. The Chairman NHA Mr
Muhammad Javaid Iqbal Awan presided.
1.2. All Members attended. List of participants is at Annex-A.
1.3. The meeting commenced with recitation of verses from the
Holy Quran and Urdu translation.
FORMAL BOARD PROCEEDINGS
2. Agenda Items
2.1. The Secretary NHA stated that 12 x working papers were
distributed in two volumes on Oct 10 & 12, 2012 respectively.
Subject-wise distribution is as follows:-
Item Noa. Minutes 1
b. Award of Works 3
c. Motorway (M-2) Overlay (BOT) 1
d. Contractual Matter 1
e. Consultancy Issues 3
f. NHA Budget 2012-13 1
g. NHF Matter (Withdrawn) 1
h. Modified PC-I 1
Total 12
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 2/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
2
2.2. The Secy NHA added that the Member (Planning) has
forwarded a working paper on “Award of Works (FERP): Construction
of Bridge Across Vadoor Nullah at km 96 - 97 (N-70) (NCB-S-12)” also
for consideration as a tabled agenda item stating that this matter is
of high importance as the road users are facing extremeinconvenience at this site as the traffic is moving through the Nullah
Bed on a temporary diversion for the past quite some time. Similarly,
the Chairman has directed placement of a working paper on
“Upgradation of Misc Posts in BS-1 to 16 of NHA Employees” as a
tabled agenda item, if permitted by the Board Members.
3. Agenda Item 1Confirmation of Minutes - 221st Meeting of the
Executive Board Held on Sep 25, 2012
3.1. The Secretary NHA solicited confirmation of minutes of
the 221st Executive Board meeting held on Sep 25, 2012 conveying
that the same were circulated on Oct 12, 2012 and that certain
written comments / observations have been received only from the
Chief (T&C), Planning Commission.
3.2. Minutes were confirmed with the suggested amendments.
Decision
3.3. The Executive Board confirmed minutes of 221st meeting
held on Sep 25, 2012 with following amendments:-
a. In Agenda Item 4 titled “Award of Works: FERP/
ADB/NCB Rehab of Mansehra- Naran- Jhalkhad-
Chillas (N-15, Pack-I): NCB-N-04 Basian-Balakot
(Km 34 - 38),” the ECNEC decision given under
Para 7.2(a) is replaced with the following:-
“The ECNEC considered the summary dated May 4,
2011 submitted by the Planning Commission titled
“Rehabilitation of National Highway Network
Damaged due to Unprecedented Monsoon Rains &
Flash Floods 2010” and approved the project, in
principle, and authorized Dy Chairman Planning
Commission/Chairman CDWP to approve the
reviewed scope and cost of project duly vetted by the high level Committee constituted by the CDWP.”
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 3/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
3
b. In Agenda Item 4 titled “Award of Works: FERP/
ADB/NCB Rehab of Mansehra- Naran- Jhalkhad-
Chillas (N-15, Pack-I): NCB-N-04 Basian-Balakot
(Km 34 - 38),” the last sentence in Para 7.16 isreplaced with the following:-
“However, he has now learnt that the cost has
increased from Rs 23 billion to Rs 32 billion,
therefore, owing to major increase in scope and cost,
the amended PC-I will again be considered by the
Planning Commission.”
c. In Agenda Item 4 titled “Award of Works: FERP/ADB/NCB Rehab of Mansehra- Naran- Jhalkhad-
Chillas (N-15, Pack-I): NCB-N-04 Basian-Balakot
(Km 34 - 38),” the following words are added at the
end of Para 7.22 under the head Decision:-
“subject to completion of codal formalities”
d. In Agenda Item 5 titled “FERP/ADB/NCB Rehab of
Mansehra - Naran - Jhalkhad - Chillas Road (N-15,
Pack-II): NCB-N-05 Mahandri - Naran (Km 89 to
119),” the ECNEC decision given under Para 8.2(a)
is replaced with the decision reproduced against “a”
above.
e. In Agenda Item 6 titled “Addendum 4 of M/s LRA
Group: Construction Supervision Consultants for
Gwadar - Turbat - Hoshab Road (M-8),” the existing
Para 9.14 is replaced as follows:-
“The Chief (T&C) remarked that while attending
meetings concerning review of the progress of
Balochistan projects with high level officials of
Government of Balochistan, an impression is
conveyed in such a manner that security issue is not
as such as it is portrayed.”
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 4/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
4
f. In Additional Agenda Item I titled “Addendum 3 of
M/s EA Consulting (Pvt) Ltd Construction
Supervision Consultants for Improvement of Inner
City Ring Road Project, Multan,” the following
sentence is added at the end of Para 18.9:-
“As such, the Board’s earlier decision needs to be
reviewed, before the instant proposal is considered.”
Action By : Secretary NHA
4. Agenda Item 2
Award of Work: Construction of Flood Protection
Bund Towards Garh Maharaja Side at Sultan BahooBridge Across River Chenab Linking Shorkot & Garh
Maharaja
4.1. Introduction of the Bridge Project.
a. NHA has undertaken the subject bridge under the
PM’s Directive to provide a road link across River
Chenab between Shorkot-Garh Maharaja. Presently,
traffic has to make long detours for crossing the river
either at Trimmu Headwork or at Muzaffargarh.
b. Bridge will facilitate traffic from Leiah, Bhakkar in
west and Jhang, TT Singh and Faisalabad in east. It
will reduce distance/ travel time and fulfil a genuine
and age old requirement and boost economic growth.
4.2. Current Status of Construction Packages.
I. Contract for Main Bridge was awarded to M/s Sh
Abdul Razzaq & Co- Mishal Sania (JV) for Rs 770.543
million in Jun-2010. Progress is 61.68%.
II. Contract for approach road (Garh Maharaja), drainage &
erosion works was awarded to M/s Hidayat Ullah
Khan & Co for Rs 570.118 million in Sep-2010.
Progress is 42.04%.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 5/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
5
III. Contract for 3.88 km approach road & drainage/
erosion works awarded to M/s FE & HNAC (JV) for
Rs 572.110 million in Sep-2011. Progress is 20.05%.
Note.Tendered cost of the packages is Rs 1912.771 M.
4.3. Hydraulic Study.
a. Due to above project, the need for flood protection
works emerged at the “Bridge” site and in vicinity.
b. Hydraulic study concluded that heading up of flood
water on Bridge upstream will create extra head of 6
feet above DWL (Design Water Level) which may overtopthe existing flood bund in Shorkot and badly damage
area on the right (Garh Maharaja) side where no flood
bund exists.
4.4. Protection Works. Following protection works were
decided to be carried out by selecting a new contractor through open
competitive bidding with shortest possible process time:-
a. Construction of protection bund Garh Maharaja side
(approx length 9.754 km).
b. Construction / raising of protection bund Shorkot
side (approx length 4.954 km).
4.5. Scope of Work. This working paper deals only with the
works at Para-4.4(a) above. Works include formation of embankment
for construction of flood protection bund from borrow excavation in
common material including clearing of site, compaction of natural
ground and levelling / dressing of protection bund.
4.6. Source of Funding / PC-I.
a. PC-I of Rs 1602.878 million for Sultan Bahoo Bridge
Project was approved by ECNEC on Jan 21, 2010.
b. Cost of protection works is being included in the
revised PC-I presently in process.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 6/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
6
c. PSDP allocation for FY 2012-13 for Sultan Bahoo
Bridge Project is Rs 150 million.
4.7. Engineer’s Estimate.
a. Rs 172,402,485/- (CSR-2009, District Jhang).
b. Rs 188,091,111/- (CSR-2009 + 9.1%, District Jhang).
4.8. Tendering Process.
a. Notice inviting bids on single stage two envelope
basis was published in press & uploaded on NHA &
PPRA websites on Apr 16, 2012. Pre-bid meeting was
held on Jun 21, 2012.
b. Seventeen firms (17) purchased bidding documents
and two downloaded the same from NHA website.
c. On the scheduled date viz Jun 29, 2012 twelve (12)
firms submitted Technical (Envelope-A) & Financial
(Envelope-B) bids within the given time:-
Messers’
i. NK & Company
ii. Saadullah Khan & Brothers (SKB)
iii. Ch Abdul Latif & Sons
iv. M Abrar Malik & Co
v. Hayat Ali & Co (Hayat)
vi. Sarwar & Co (Pvt) Ltd
vii. Astron Construction Co (Pvt) Ltd
viii. Sachal (JV) Techno Time Construction
(Sachal (JV) TTC)
ix. Chaudhry Construction Co
x. RMC Construction Company
xi. Abdullah Khan & Co
xii. AM Construction Company (AMCC)
d. Technical Proposals were opened and evaluated by
the Committee constituted in accordance with NHA
Code. Four bidders were recommended for opening
of Financial Bids.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 7/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
7
4.9. Financial Proposals Opened / Announced on Jul 2, 2012.
Messers’ Bid (Rs) Final Bid (Rs)a. Sachal (JV) TTC 146,576,435 146,576,435
b. SKB 151,581,484 151,581,484
c. Hayat 201,710,625 201,710,625
d. AMCC 257,502,621 239,477,436 *
* Rebate/premium Rs 18,025,183/=.
4.10. Bid Securities. NHA Accounts Section has confirmed
acceptability of the bid security of all the bidders.
4.11. Summary. The summary of evaluation tabulated below
indicates comparative position vis-à-vis the estimated cost of Rs
188,091,111/- (CSR-2009+ 9.1%%, District Jhang):-
Lowest
RankingContractor (M/s)
Corrected
Bid (Rs)Variation
1st Sachal (JV) TTC 146,576,435 (-)22.07%
2nd SKB 151,581,484 (-)19.41%
3rd Hayat 201,710,625 +7.2%
4th AMCC 239,477,438 +27.3%
4.12. Recommendation. The Tender Acceptance Committee has
recommended award of works in question to the 1st lowest evaluated
bidder ie M/s Sachal (JV) TTC for Rs 146,576,435/- at (-)22.07% the
estimated cost.
Board’s Deliberations
4.13. The Member (Planning) presented details. The GM (P&CA)
& GM (Design-1) were also present.
4.14. The Board Members made the following observations:-
a. Since the cost of protection works was not included
in the approved PC-I, how can the works be awarded
without seeking approval of fresh PC-I? (Chief NTRC)
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 8/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
8
b. Original PC-I was approved as far back as in Jan-
2010, why NHA has not processed the revised PC-I
despite passage of considerable time? (Chief T&C)
c. It appears desirable to seek approval of revised PC-I
in the first instance. (JS-1 MoC)
d. Would it be possible for the contractor to deliver the
project of prescribed specifications at 22.07% below
the estimated cost? (Chief T&C)
e. What is the current financial progress of the three
ongoing packages and whether the expenditure so farincurred is within the 15% limit of the approved PC-I
cost as the three original packages were awarded at a
cost higher than the approved PC-I? (Chief T&C)
f. Why protection bund is proposed to be constructed
only on Garh Maharaja Side & why raising of bund
on Shorkot Side has not been proposed
simultaneously? Prudence demand execution of such
critical activity in totality. (Chief T&C)
g. Processing of PC-Is of major bridge projects and also
undertaking works without Hydraulic Model Study is
an undesirable proposition. Now that Hydraulic
Model Study for the subject bridge has been done it
may be seen whether the bridge parameters require
any revision. (Chief T&C)
h. Why following clause was included in the eligibility
criteria as it could give a clue to the prospective
bidders about the likely cost of the project and also it
needs to be clarified if this case is an exception or
incorporation of such a clause is a regular feature:-
“Completion certificate of at least one project of similar
nature with a value of minimum Rs 141 million during
the last five years.” (Chief T&C)
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 9/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
9
4.15. The following clarifications were rendered:-
a. Original PC-I was prepared without hydraulic model
study based on tentative design, therefore, cost of protection works was not included therein.
b. Original approved PC-I cost is Rs 1602.878 million
and expenditure so far incurred on 3 x ongoing
packages is Rs 829.657 million (Annex-B):-
Pack Project Rs in M
I. Main Bridge 475.271
II. Approach Road (Garh Maharaja) 239.678
III. Approach Road (Shorkot) 114.708
Total 829.657
c. Since the above amount is substantially less than
approved PC-I cost, the proposed river training works
may be allowed to be awarded. Revised PC-I based on
hydraulic model study and tendered cost is under
preparation and it will include all relevant costs.
d. Processing of revised PC-I got delayed because of
superfloods-2010 and time consumed in hydraulic
model study. It is assured that the revised PC-I will
be processed at priority within 60 days.
e. Careful rate analysis of the lowest evaluated bid was
carried out. The only major task is earthwork and
compaction level required is also less than 90% andthe contractor should be able to deliver protection
bund of the required specifications despite the bid
being substantially lower than the estimated cost.
f. Construction of flood protection bund towards Garh
Maharaja Side is of critical importance to save this
town from aggravated flooding caused due to bridge
construction. Time is of essence, as this task is
proposed to be completed within the next 5-6 monthsie before the next flood season.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 10/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
10
g. Flood protection bund on Shorkot Side already exists
and only its height is needed to be increased by
Punjab Irrigation Deptt (PID). Cost of raising of this
bund will be added to revised PC-I in consultationwith PID for expeditious completion of this task.
h. This project was entrusted to NHA as per a policy
decision of Inter-Provincial Coordination Committee
under which all road infrastructure development
projects funded through PSDP were to be executed
by NHA and simultaneously a suitable allocation was
also made in NHA’s PSDP 2009-10.
i. Because of political importance, commencement of
bridges is accorded priority by the government and
the related river training works, etc, are undertaken
after model study; which consumes considerable
time. Nevertheless, the observation regarding prior
model study has been noted for compliance in future.
j. The clause seeking completion certificate of at least
one project of similar nature with a value of around
80% of the estimated cost is included in the eligibility
criteria of every procurement proceedings and this
case was not an exception. This clause is also
present in the ADB eligibility criteria.
4.16. Matter was discussed and cleared by the Members.
Decision
4.17. The Executive Board approved award of work for
“Construction of Flood Protection Bund towards Garh Maharaja side
at Sultan Bahoo Bridge Across River Chenab Linking Shorkot & Garh
Maharaja” to the 1st lowest evaluated bidder ie M/s Sachal (JV) TTC
at the evaluated bid price of Rs 146,576,435/= (Rupees one hundred &
forty six million, five hundred & seventy six thousand, four hundred & thirty five)
only; which is (-)22.07% from updated estimate of Rs
188,091,111/=(CSR-2009+9.1 %, District Jhang).
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 11/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
11
4.18. The Board directed NHA to:-
a. Expedite processing of revised PC-I for Shorkot -
Garh Maharaja Bridge Project within 60 days.
b. Include cost of raising of Shorkot Side flood
protection bund in the revised PC-I.
c. Ensure that all major bridge construction projects
are undertaken after Hydraulic Model Study.
Action By : Member (Planning)
5. Agenda Item 3
Award of Works: Widening & Improvement of Bosan
Road, Multan Contract-2 (Package-II) Construction of
Right Turn Flyover at Chungi No 6
Introduction - Working Paper
5.1. Introduction. Bosan Road is one of the busiest roads of
Multan City. The GoP tasked NHA to widen & improve this road (7.5
km) from Chungi No 9 to BZU (Bahauddin Zakariya University) including
construction of 2-lane flyovers for right turns at Golbagh Chowk &
Chungi No 6 and a 2-lane flyover from Chungi No 6 to Northern
Bypass Chowk.
5.2. PC-I / Funding.
a. PC-I of this PSDP funded project of Rs 4,570.022
million was approved by ECNEC on Jan 21, 2010.
b. PSDP allocation (2012-13) is Rs 750 million.
5.3. Construction Packages.
IA. Road from Chungi No 9 to BZU (RD 00+000 to RD 03+450).
IB. Road from Chungi No 9 to BZU (RD 03+450 to RD 07+520).
II. 2-Lane Flyovers for Right Turns (Golbagh & Chungi No 6).
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 12/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
12
5.4. Package-wise Progress.
IA. Contract awarded to M/s Khalid Rauf & Co for Rs460.8168 million in Apr-2011. Progress is 49%.
IB. Contract awarded to FWO for Rs 530.6349 million
in Mar-2011. Progress is 49%.
II. Works are now proposed to be awarded.
5.5. Scope of Work (Pack-II).
a. Project entails construction of flyover bridge,
retaining walls, earth embankment, pavement
structure, drainage and protection works, traffic
control devices and electrification works.
b. Pavement structure at different locations comprises
asphaltic concrete wearing course, asphaltic base
course, aggregate base course and sub-base. The
thickness of each layer varies on different road
sections.
5.6. Engineer’s Estimate. Rs 179,329,439/= (CSR-2009+9.1%,
Multan).
5.7. Tendering Process.
a. Procurement process was initiated by advertising
“Invitation for Bids” on “Single-Stage-Two-Envelope”
basis in national newspapers and through display on
NHA & PPRA websites.
b. Firms registered with PEC in Category C-3 or above
with specialization in CE-01 & 02 were eligible for
issuance of bidding documents; purchased by
thirteen (13) firms:-
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 13/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
13
Messers’
i. Niaz Muhammad Khan & Brothers (Niaz)
ii. RMC Construction Company (RMCC)
iii. Al-Mehran Builders Pak (Pvt) Ltd
iv. Ch Abdul Latif & Sons (Pvt) Ltd
v. Chaudhry Construction Company
vi. Ghulam Rasool & Co
vii. Hakas (Pvt) Ltd
viii. Kundi Development Corporation
ix. M Ibrar Malik & Co (AMC)
x. Mishal Sania (Pvt Ltd
xi. Mohandisin-e-Masud
xii. Sh Iqbal Akhtar & Co (Pvt) Ltd
xiii. Wajid Iqbal & Co
c. Pre-bid meeting was held on May 30, 2012.
d. On the scheduled date viz Jun 6, 2012, only four
(04) firms listed at Sl “i to iv” above submitted
technical (envelope-A) and financial (envelope-B) bids
within the scheduled time.
e. Technical bids were opened by Bid Opening &
Evaluation (BO&E) Committee constituted in
accordance with NHA Code. After detailed evaluation,the firms at Sl “i & ii” above were recommended for
opening of financial bids.
5.8. Financial Evaluation. Financial proposals were opened on
Jun 26,2012.Following result was announced:-
Messers’ Quoted Bid (Rs) Final Bid (Rs)
a. RMCC 231,389,017 214,214,551*
b. Niaz 269,149,055 269,149,055
* 5% rebate on Bills No 1 to 6.
5.9. Arithmetic Correction. The final bid amount of the lowest
bidder M/s RMCC emerged as Rs 220,115,707/= after application of
arithmetic checks in the light of IB (Instructions to bidders) Clauses 27 &
28. This amount was duly accepted by the BO&E Committee.
5.10. Summary. The summary of evaluation tabulated below
indicates comparative position vis-à-vis estimate of Rs 179,329,439(CSR-2009+ 9.1%, District Multan):-
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 14/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
14
LowestRanking
Contractor(M/s)
AnnouncedBid (Rs)
CorrectedBid (Rs)
Variation
1st RMCC 214,214,551 220,115,707 +22.74%
2nd Niaz 269,149,055 269,149,055 +50.09%
5.11. Recommendation. The Tender Acceptance Committee has
recommended award of works in question to the 1st lowest evaluated
bidder M/s RMCC at the corrected bid price of Rs 220,115,707/=.
Board’s Deliberations
5.12. The Member (Planning) presented details. The GM (P&CA)
& GM (Design-1) were also present.
5.13. On an observation by the Chief (NTRC), the GM (Design-1)confirmed that the works now proposed to be awarded are included in
the original package of Bosan Road Multan Project. However, the
Golbagh Flyover has been dropped.
5.14. The Chief (T&C) observed that the expenditure so far
incurred on Bosan Road Multan Project should have been indicated to
assess the need for PC-I revision. The GM (Design-1) clarified that this
project is located in urban area and the major cost component of the
PC-I was dedicated to land / RoW acquisition. Nevertheless, the up-to-date expenditure will be reflected in the minutes.
5.15. Note. An expenditure of Rs 2983 million has so far been
incurred on the Bosan Road Multan Project. It includes Rs 2397.876
million on land acquisition and utilities removal/relocation (Annex-C).
5.16. Matter was discussed and cleared by the Members.
Decision
5.17. The Executive Board approved award of works for
“Widening & Improvement of Bosan Road, Multan-Contract-2 (Pack-II)
- Construction of Right Turn Flyover at Chungi No 6” to the 1st lowest
evaluated bidder M/s RMC Construction Company at the corrected
bid price of Rs 220,115,707/- (Rupees two hundred and twenty million, one
hundred & fifteen thousand, seven hundred & seven) only; which is +22.74%
the Engineer’s Estimate of Rs 179,329,439/= (CSR-2009 + 9.1%).
Action By : Member (Planning)
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 15/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
15
6. Agenda Item 4
Award of Works Under Flood Emergency
Reconstruction Project (FERP) : NCB-N-06 Flood
Damaged of Chakdara - Kalam Road (N-95) Package-I:
Fatehpur to Madyan (Km 82+000 to 89+700)
Introduction - Working Paper
6.1. ADB Loan / Scope of Work.
a. Pakistan has received a loan (PAK 2742) from the
Asian Development Bank (ADB) towards the cost of
Flood Emergency Reconstruction Project (FERP).
b. Subject project ie NCB-N-06 Pack-I, Rehab of
Chakdara - Kalam Road (N-95): Fatehpur - Madyan
(km 82+000 to 89+700) is included in Phase-I of FERP.
NCB: National Competitive Bidding
6.2. Global PC-I.
a. Global PC-I of FERP based on DNA (Damage Need
Assessment) study conducted by NESPAK was
presented in ECNEC meeting held on May 26, 2011.
The ECNEC approved the PC-I, in principle, with the
following instructions:-
“The ECNEC considered the summary dated May 4, 2011
submitted by the Planning Commission titled “Rehabilitation of
National Highway Network Damaged due to Unprecedented
Monsoon Rains & Flash Floods 2010” and approved the project,
in principle, and authorized Dy Chairman Planning Commission/
Chairman CDWP to approve the reviewed scope and cost of
project duly vetted by the high level Committee constituted by the
CDWP.”
b. Revised PC-I is under preparation and included in
the deliverables of design consultants.
6.3. Engineer’s Estimate. Rs 806,795,292/= (CSR 2009+9.1%).
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 16/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
16
6.4. Tendering Process.
a. NHA and ADB agreed that the procurement of
subject works shall be made on Single-Stage-Two-Envelopes Basis for civil works in accordance with
ADB’s guidelines.
b. Escalation shall not be applicable on contracts of
12 months or less duration. Being 12 months
project, escalation is not applicable in this case.
c. Advertisement for Invitation of Bids (IFB) was
published in the press and displayed on NHA andPPRA websites on May 24, 2012. Bid documents
were procured by sixteen (16) eligible firms
individually or as JV.
d. Six (6) firms submitted technical and financial bids
on the due date viz Jun 13, 2012:-
Messers’ Legend
i. Zahir Khan & Brothers (JV) –Techno Time ZKB (JV) TT ii. Frontier Works Organization FWO
iii. Ch Abdul Latif & Sons (Pvt) Ltd CALSON
iv. Khattak Allied Construction Company Khattak
v. National Logistics Cell NLC
vi. Ghulam Muhammad Khan & Company GMK & Coy
6.5. Technical Evaluation.
a. Technical bids were opened on Jun 13, 2012 by the
Bid Opening & Evaluation (BO&E) Committee in thepresence of Reps of bidders. Price bids were kept
unopened and sealed in safe custody.
b. Technical bids were evaluated in accordance with
qualification criteria stipulated in bid documents.
Bids at sl “v” & “vi” were evaluated as “unqualified.”
c. Technical Bid Evaluation Report was approved by
ADB on Jun 27, 2012.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 17/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
17
6.6. Financial Bid Evaluation.
a. Financial bids were opened on Jul 2, 2012 in the
presence of BO&E Committee. Quoted/announcedbid prices were as summarized below :-
Bidder (M/s) Rupees
i. ZKB (JV) TT 912,455,000
ii. Khattak 1,089,135,000
iii. CALSON 1,266,433,000
iv. FWO 1,376,880,859
b. Bids were evaluated as per ADB’s standardprocedures. Only one typographic / arithmetic error
was found in the bid of M/s Khattak.
6.7. Summary. Summarized comparison vis-à-vis estimated
cost of Rs 806.795 million (CSR 2009 + 9.1%) is as under:-
6.8. ADB’s Concurrence. The Priced Bid Evaluation Report
was forwarded to ADB for review/concurrence. The ADB issued NOC
dated Aug 17, 2012 for award of works to M/s ZKB (JV) TT.
6.9. Recommendation. The Tender acceptance Committee has
recommended award of works is question to M/s ZKB (JV) TT at the
quoted / evaluated bid amount of Rs 912,455,000/=.
6.10. LoA. After seeking anticipatory approval of Chairman
NHA, LoA has been issued owing to emergency nature of work.
Board’s Deliberations
6.11. The Member (Planning) presented details. The GM (P&CA)
& GM (Design-1) were also present.
Rank Consultant (M/s) Submitted (Rs) Corrected (Rs) Variation
1st ZKB (JV) TT 912,455,000 912,455,000 +13.10%
2nd Khattak 1,089,135,000 1,096,100,000 +35.86%
3rd CALSON 1,266,433,000 1,266,433,000 +56.97%
4th FWO 1,376,880,859 1,376,880,859 +62.36%
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 18/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
18
6.12. On an observation by the VP-NESPAK, it was clarified that
the NLC was disqualified because of the instructions issued by the
MoC that “no work should be awarded to NLC on any NHA project tillthe inquiry on collapse of Shershah Bridge is finalized.” However, the
Executive Board (219th meeting of Jul 24, 2012) accorded its no objection
for pre-qualification of NLC for award of construction projects by NHA
and for works tendered subsequent to this decision NLC is free to
participate.
6.13. The VP-NESPAK further observed that this contract being
of 12 months duration escalation will not be applicable. However, past
experience reveals that most of the projects get delayed because of onereason or the other. Therefore, as pointed out by him during the last
Board meeting also, he would suggest that in case the project goes
beyond 12 months, and escalation is ultimately payable, it should be
ensured that escalation is not allowed on works completed within first
12 months and a clause to this effect may be added to the contract.
6.14. The Member (Planning) clarified that the subject contract
is an item based and not EPC (Engineering-Procurement-Construction)
contract and inclusion of the proposed clause in the agreement will
attract various complications and also ADB’s objection. Nevertheless,
the observation has been noted and will be complied with. Alongside,
inclusion of such a clause in future contracts would be analyzed.
6.15. The Chief (T&C) pointed out that NHA has yet to obtain
administrative approval for incurring expenditure on various schemes
included in FERP pending formal approval of the PC-I. To avoid any
subsequent hitch, NHA should immediately move a case for seeking
necessary admin approval.
6.16. The Chief (T&C) added that as was done in two other
contracts of FERP, in this case also NHA issued LoA to the lowest
evaluated bidder after seeking anticipatory approval of Chairman
NHA. He recalled his similar observation during the last Board
meeting and reiterated that formal SOPs should be developed for such
purposes with the approval of the Executive Board to avoid inherent
complications.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 19/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
19
6.17. The Member (Planning) clarified that the original PC-I of
FERP was based on DNA and that the revised PC-I is being finalized
on the basis of tendered cost. Nevertheless, a case for seeking adminapproval based on original PC-I would be moved, as suggested. The
observation regarding development of SOPs for issuing LoAs after
seeking anticipatory approval of Chairman NHA is already being
attended to.
6.18. Matter was discussed and cleared by the Members.
Decision
6.19. The Executive Board approved award of works for “Rehab
of Chakdara - Kalam Road (N-95), NCB-N-06 Pack-I: Fatehpur -
Madyan (km 82+000 to 89+700)” to M/s Zahir Khan & Brothers (JV)
Techno Time Construction Co at the quoted / evaluated bid amount of
Rs 912,455,000/= (Rupees nine hundred & twelve million, four hundred & fifty
five thousand) only; which is +13.10% the estimated cost (CSR-2009+9.1%)
subject to completion of codal formalities.
6.20. NHA is advised to:-
a. Analyze inclusion of a suitable clause in all future
projects / schemes in which escalation is not allowed
originally (normally upto 12 months duration) but is
allowed subsequently for delay in completion not
attributable to the construction contractor that
escalation will not be allowed on works completed
within the original completion period but permissible
only for balance works.
b. Develop SOPs for issuing LoAs for award of works in
urgent nature cases after seeking anticipatory
approval of Chairman NHA and place the same
before the Executive Board for approval.
Action By : Member (Planning)
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 20/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
20
7. Agenda Item 5
Overlay and Modernization of Lahore - Islamabad
Motorway (M-2) on Build-Operate-Transfer (BOT) Basis
Introduction - Working Paper
7.1. Introduction. The Lahore-Islamabad 6-lane divided access
controlled Motorway (357 km, M-2) was completed and opened to
traffic in Nov-1997. It has completed its designed life and is showing
deterioration and riding quality is fast going down beyond acceptable
limits. Virtually, it demands complete overlay.
7.2. Overlay and Modernization. NHA has initiated efforts to
save this precious asset and to keep it financially sustainable. If theoverlay / improvement program is delayed, M-2 will enter into
rehabilitation mode and require an investment level of 4 to 5 times
(over Rs 100 billion) higher than current requirement.
7.3. BOT Initiative. Keeping in view the financial constraint
faced by GoP/NHA, M-2 may become financially unsustainable. NHA
has, therefore, decided to undertake the project through Public-
Private-Partnership under Build-Operate-Transfer arrangement to:-
a. Improve existing M-2 to its as-built condition.
b. Modernize M-2 at par with international standards.
c. Gain guaranteed payments of about Rs 19 billion to
remove Salt Range bottleneck through realignment.
7.4. Scope of Work.
a. Overlay of M-2 to achieve improved ride quality to an
international motorway standard of IRI (International
Roughness Index) less than 1.5.
b. Modernization of motorway facilities including:-
i. Electronic toll collection (ETC).
ii. Road safety features and emergency assistance
system.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 21/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
21
iii. Centralized operation centre with closed circuit
TV.
iv. Traffic counting station/weigh-in-motion
systems.
v. Variable message signs (VMS).
vi. Electronic overloading / police fine collection
system (e-system) & automatic vehicle
classification (AVC).
vii. Landscaping.
viii. Propose business ideas to improve traffic
numbers without compromising safety and
violating motorway definition.
7.5. Advertisement. An advertisement was placed in the press
inviting Requests for Proposal (RFPs) on Oct 12, 2011. Following firms
/ JVs procured RFP documents:
Messers’
a. Frontier Works Organization (FWO).
b. VINCI, France.
c. Sultan Mahmood & Company.
d. Sh Abdur Razzaq & Co.
e. Maqbool Associates (Pvt) Ltd.
f. China State Construction Co.
7.6. BOT Proposal. Out of six (06) firms/JVs, who procured
RFPs, only M/s FWO, ZKB, SACHAL (JV) submitted the BOT proposal.
7.7. Technical Proposal. It was opened on Jul 6, 2012. M/s
FWO, ZKB, SACHAL (JV) secured eighty six (86) points out of 100 and
qualified for opening of financing proposal.
7.8. Financial Proposal. It was opened on Aug 8, 2012. The
IPDF (Infrastructure Project Development Facility) of the Finance Division
assisted NHA in detailed evaluation. The Evaluation Committeerecommended a Letter of Support (LoS) to be issued to the JV.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 22/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
22
7.9. Salient Features.
a. Project Cost. Rs 36,826 million.
b. Project Financing. Debt : 70% & Equity : 30%.
c. Base Toll Rate. Start of operation (expected year 2016)
for one passenger car unit (PCU) : Rs 1.58 pkm.
d. Other Features.
i. NHA/GoP Support : Nil
ii. Concession Period : Twenty (20) years
iii. Construction Period : Thirty six (36) months
e. Guaranteed Payments. Rs 19 billion will be paid by
the Concessionaire to NHA as follows:-
i. Upfront. Rs 9.50 billion upon achievement of Financial
Close
ii. Balance. Rs 9.50 billion during 4 to 8 year (five years) of
Concession Period @ Rs 1,900 million per year.
f. NHA’s Revenue Share. Rs 189.70 billion (Concession
Years 11 to 20).
7.10. Conclusion. The above is for information of the Board. A
detailed working paper, along with negotiated/ finalized Concession
Agreement, shall be submitted for approval, prior to signing.
Board’s Deliberations
7.11. The Member (Motorways/BOT) presented details.
7.12. The VP-NESPAK remarked that the BOT proposal is quite
encouraging but he has following observations:-
a. Entering into a concession of this size and for such a
long period (20 years) demands that NHA’s home-
work is of the highest quality. Previously, concession
agreements for Motorway (M-9) & Shahdara Flyover
(N-5) were approved by the Executive Board but the
projects got stuck up at the financial closure stage.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 23/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
23
b. NHA should ensure that the Executive Board is given
at least three weeks for study of the draft concessionagreement if & when finalized for detailed study of
various options.
c. NHA’s past experience with FWO for Operation &
Management (O&M) of the Motorways (M-1, M-2 &
M-3) is not very encouraging and this should be kept
in perspective. Therefore, as to how much say NHA
will have during the 20 years concession period may
also be elaborated.
d. FWO is a public sector entity with ultimate recourse
to federal funds; therefore, it is perhaps not a pure
"Public-Private-Partnership" rather a "Public-Public-
Partnership". Is it not like transferring M-2 from one
government entity to another? Opinion from the
Ministry of Law & Justice may be obtained.
e. If FWO can raise money for this project why can't
NHA do it by itself by raising loan against revenue
stream of M-2 for the next 10- 15 years?
f. NHA should carryout detailed (public sector comparative
or value for money) analysis to convince the Board that
it is in the interest of NHA and public to go for BOT
concession on this prestigious multi-billion dollar
asset. This would require precise assessment of
revenues and costs.
g. An analysis indicating Concessionaires Return on
Equity is extremely essential & should be presented
in the Board. Some road agencies fix an upper cap
on RoE to watch the interest of road user / public.
NHA should have a policy to ensure that private
operator does not make windfall profits at the cost of
road users.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 24/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
24
7.13. The AS (Finance) endorsed the above detailed analysis &
remarked as follows:-
a. Pre-concession negotiations/documentations should
be conducted / prepared in a very careful manner.
b. Motorway is an essential facility from the national
economic perspective; therefore, NHA should also
watch the interest of the road users who should not
be exploited by the BOT Concessionaire by imposing
very high toll rates.
c. Any legal implications on ongoing litigation with M/s
Daewoo for O&M of service areas be also studied.
d. The JV led by FWO is going to raise 30% equity for
the BOT concession and balance 70% is loan. Why
can’t NHA raise this much amount itself instead of
exposing NHA to FWO yet again.
7.14. The IG (NH&MP) remarked as follows:-
a. NHA should carryout a detailed survey of the current
traffic on the motorways and compare it with the toll
actually collected (reported) by FWO. According to his
estimation, at least 30% toll revenue is currently
being misappropriated.
b. Based on the detailed survey and through check on
revenue misappropriation / pilferage and keeping in
view the revised revenue stream, NHA should analyze
the possibility of carrying out overlay of M-2 through
own resources. Further, instead of undertaking this
task in totality, NHA can identify stretches in worst
condition for the overlay to be completed in parts.
7.15. The Chief (NTRC) made following remarks:-
a. It has been stated that M-2 has completed its
designed life but it should also be noted that during
the past 15 years the traffic volume on M-2 hasremained much less than the designed capacity.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 25/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
25
b. NHA should carryout detailed condition survey of
M-2 to identify stretches in critical condition and
determining the existing roughness index (IRI) for
phased overlay / rehabilitation.
7.16. The Chief (T&C) observed as follows:-
a. While approving PC-I of a project, the recurring cost
is mentioned and this may be provided.
b. Pavement design is prepared to sustain certain axle
load for a pre-determined period. Since heavy traffic
on M-2 could not achieve the anticipated volume due
to various reasons including Salt Range gradient, itmay be intimated as to how any axles have rolled
over M-2 since its opening.
c. Suggestion regarding condition survey is supported
to identify stretches in critical condition.
d. Exact detail/configuration of traffic be provided along
with detail of toll revenue and other income being
generated from M-2 to ascertain true picture of the
revenue stream.
7.17. The Member (MW/BOT) rendered following clarifications:-
a. The proposed BOT concession does not envisage
simple overlay of M-2 but also its restoration to as
built condition besides improvement/modernization
to international standards (details at Annex-D).
b. Through guaranteed revenue of Rs 19 billion removal
of Salt Range bottleneck by realignment is planned.
7.18. The Member (Planning) remarked as follows:-
a. The GoP because of overall financial constraints is
unable to meet the requirement of ongoing / planned
projects and the yearly PSDP allocation of NHA isnormally 30-40% less than the demanded funds.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 26/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
26
b. NHA has not yet cleared substantial payments for
land acquired for M-2 about two decades back and is
also facing difficulty in making payments for the landpresently being acquired for Motorway (M-4).
c. NHA has not asked any funds from PSDP for overlay
of M-2. If this is delayed any further, the requirement
may transform in to rehab and even reconstruction,
the cost of which would be phenomenal.
d. NHA is following the GoP instructions regarding
maximization of off-budget financing.
e. FWO has provided a certificate that it operates as a
commercial company.
f. Bid is close to parameters pre-defined by the IPDF.
g. NHA will ensure that all observations made by the
honorable Board Members are kept in perspective
while processing / negotiating concession agreement.
7.19. The Chairman remarked that services of a financial
analyst be hired for detailed scrutiny of the concession agreement.
Decision
7.20. The Executive Board reviewed the working paper
regarding “Overlay and Modernization of Lahore-Islamabad Motorway
(M-2) on Build-Operate-Transfer (BOT) Basis” and advised NHA to
keep all the observations discussed above before finalizing concession
agreement with the JV comprising M/s FWO, ZKB & Sachal.
Note. Since the Finance Division has issued Dollar denominated Sukuk in
international capital market & Rupee denominated Sukuk in local capital
market, against Motorway (M-2), NHA on Oct 22, 2012 referred the matter to
MoC with the request to approach Finance Division to seek clearance for NHA
to proceed ahead with the subject BOT process.
Action By : Member (Motorways/BOT)
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 27/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
27
8. Agenda Item 6
Construction of Hiran Minar Interchange on Lahore -
Islamabad Motorway (M-2) at Km 51+886 : Request
for Invoking Clause 70.1 (Price Adjustment)
Introduction - Working Paper
8.1. Background / Introduction.
a. NHA has taken up the subject project on a directive
notified by the Prime Minister’s Sectt on Dec 1, 2006
for development of tourism industry by providing a
comfortable access to Hiran Minar via Lahore -Islamabad Motorway (M-2).
b. Construction of an intersection at km 51+886 on M-2
provides the shortest link to Hiran Minar and this
constitutes second such facility near Sheikhupura in
addition to an interchange on Sheikhupura -
Gujranwala Road.
8.2. Scope of Work.
a. Interchange is being constructed by incorporating
existing bridge across M-2 on Hafizabad -
Sheikhupura Road.
b. Project includes two separate ramps for 2-way traffic
connecting M-2 with this road both to the north &
south forming a T-junction on either end of the
ramps.
c. Project also includes Toll Plaza and Admin Building
including sanitary, water supply and electric works.
8.3. PC-I. PC-I of Rs 183 million was cleared by CDWP on Sep
17, 2009 with the directions that project cost be updated based on
NHA’s CSR-2009 with permissible premiums & got cleared by
Chairman CDWP. Cost was updated to Rs 260.319 million.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 28/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
28
8.4. Contract. Contract for construction of Hiran Minar
Interchange was awarded with a completion period of 6 months:-
a. Contractor : M/s Luqman Brothers
b. Design Consultant : M/s REC (Pvt) Ltdc. Supervisory Consultant : -do-
d. Commencement : Jul 7, 2010
e. Completion : Jan 2, 2011
f. Progress : 65%
8.5. Delay. The Sub-Clause 70.1 (Price Adjustment) was deleted
as the project duration was less than six months. However, the project
has been considerably delayed due to following reasons:-
a. Agreement for hiring of M/s REC as supervisory
consultant was signed on Jun 18, 2010. M/s REC
was to review the original design (prepared in 1999) as
per current conditions within one month of the
signing of the contract agreement.
b. M/s REC took 3 months for design review and it was
got approved from NHA on Sep 6, 2010. This delayed
the project for almost 3 months. Further 3 months
were consumed for latest soil investigations.
c. Payment to WAPDA on part of the Employer was
delayed for a considerable period of time.
d. Payments to contractor were delayed for almost 6
months due to which EoT up to Jun 29, 2012 was
necessitated.
8.6. Incorporation of Escalation Clause.
a. Project has got delayed by almost one year due to no
fault of the contractor. Therefore, as recommended
by PD and Senior Procurement & Contract Specialist,
the contractor cannot be penalized for the delay.
b. It is proposed that Clause 70.1 (Price Adjustment) may
be invoked through an amendment in the contractagreement in accordance with PEC guidelines.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 29/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
29
8.7. Proposal. Executive Board’s approval is requested.
Board’s Deliberations
8.8. The Member (Construction) presented details. The GM(Construction-N) was also present.
8.9. The Chief (T&C) had forwarded some written observations,
which were responded as follows:-
a. Whether provision for escalation was made in the
approved PC-I. If, not then without approval of
revised PC-I, the proposal cannot be supported.
It is confirmed that the approved PC-I has provision
of escalation. Since, original completion period was 6
months escalation clause was not incorporated.
b. M/s REC signed agreement with the client on Jun
18, 2010 based on design carried out in 1999
without latest soil investigation. Why NHA did not
look into this matter and now the proposal for
inclusion of "Price Adjustment" clause in contract
agreement is being made with 65% progress?
Project was designed in 1999 for link road, therefore,
for ramps in ponding areas slush was replaced with
sand. Without proper design road would have failed,
as such, soil investigation / testing was conducted
by the University of Engineering & Technology,
Lahore prior to commencement of work.
c. Whether the issue has the in-house consensus
including the Finance Wing.
It is confirmed that NHA Finance Wing has accorded
concurrence.
d. At this stage. if the proposal is accepted, then actual
cost of escalation will be more than Rs 42 million atthe time of completion of project.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 30/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
30
Overall increase including escalation cost is within
15% of the original PC-I cost, therefore, revision of
the PC-I would not be required.
e. It should be clarified whether escalation has beenworked out as per actual expenditure.
It is confirmed that the escalation has been
calculated as per actual payment.
f. There is no allocation for the project in PSDP 2012-
13. How the funding will be arranged?
Expeditious completion of the interchange is inNHA’s interest as expected toll collection is Rs 50
million plus annually.
g. What is the status of revised PC-I.
As explained against “d” above.
8.10. The Chief (NTRC) observed that the project was advertised
as a fixed price contract, as such, it may be explained whether
inclusion of escalation clause at this stage is legally tenable.
8.11. The AS (Finance) observed that post tender amendments
to contract conditions does not appear to be fair to other bidders.
Matter needs to be certified by PPRA or PEC.
8.12. The Member (Construction) clarified that this proposal
has been brought before the Executive Board as per the policy
decision taken by the Board in 2008.
8.13. Note. The Executive Board in its 160th meeting held on
Sep 24, 2008 took the following decisions:-
a. “The Executive Board approved incorporation of escalation Clause 70.1 in the Conditions-of-Contract (Part-II) in all ongoing maintenance / development contracts awarded during or subsequent to July 2007
of more than six months duration.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 31/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
31
b. The Board further decided that specific project, if any,of less than six months duration requiring suitable remedial action because of non inclusion of escalation clause would be identified and brought before the Board for decision on merit with detailed justification
/ cost effect.
c. Real escalation (positive or negative) will be paid on a monthly basis against actual work done and actual consumption of materials after its detailed assessment on a case-to-case basis.”
8.14. The Chief (T&C) pointed out that it has been stated in the
working paper that the price adjustment clause is proposed to be
invoked in accordance with PEC guidelines. A copy of these guidelines
be placed before the Board.
8.15. Matter was discussed and it was decided that a copy of
the PEC guidelines be placed before the Board.
Decision
8.16. The Executive Board considered the working paper
seeking approval for inclusion of Clause 70.1 (Price Adjustment) clause in
the contract agreement for “construction of Hiran Minar Interchangeon Lahore - Islamabad Motorway (M-2) at Km 51+886” and decided
that the matter would be reconsidered when a copy of the relevant
provisions of PEC guidelines is placed before the Board.
Action By : Member (Construction)
9. Agenda Item 7Addendum-3 of M/s Indus Associated Consultants forConstruction Supervision of Ratodero - Naudero
Project (15 Km)
Introduction - Working Paper
9.1. Introduction.
a. The GoP has entrusted to NHA the responsibility for
construction & development of a number of roads
under the President of Pakistan’s Sindh Development
Package including Ratodero - Naudero Road.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 32/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
32
b. Project consists of rehab/up-gradation of Ratodero -
Naudero Road (14.785 km) including 2 km internal
roads. It caters for existing/future intercity traffic to
help develop the area besides improved connectivity
with Ratodero - Khuzdar - Gwadar Road (M-8).
c. Overall objective is to facilitate travel between
Larkana & Indus Highway (N-55) through reduction
in transport travel time / vehicle operating cost at an
economical & financially sustainable level.
d. This road already stands federalized as National
Highway (N-55).
9.2. Construction Contract.
a. Contract for construction of Ratodero-Naudero Road
Project was awarded to M/s Sachal Engg Works at a
cost of Rs 790 million.
b. Commencement was fixed as Sep 6, 2009 and
completion Nov 30, 2010 (15 months). However, the
Contractor was granted Extension of Time (EoT) and
revised completion date was fixed as Feb 23, 2011.
Project has been substantially completed.
9.3. Design & Supervision Consultancy.
a. M/s Indus Associated Consultants was assigned the
design & supervisory consultancy at a cost of Rs
13,151,500/- but for 6 months only.
b. Addendum-1 of Rs 3,557,767/- was approved for
additional cost of Naudero Bypass.
c. Addendum-2 of Rs 19,161,120/- was approved for:-
i. Grant of EoT for supervision till Nov 30, 2010.
ii. Inclusion of additional staff appointed directly by NHA to meet own staff requirements.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 33/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
33
9.4. Delay. Completion of the project got delayed for various
reasons including delay in payment of certified payments of the
Contractor by NHA, disruption of work by land claimants and
relocation of utilities.
9.5. Addendum-3 of M/s Indus Associated Consultants.
a. Needed for construction supervision till project
completion as fixed by NHA against recommendation
of Resident Engineer and “the Engineer” that the
agreement may be extended in line with the
completion date fixed for Contractor with full
strength of supervision staff upto Aug 31, 2011 andwith reduced staff till Oct 31, 2011 for settlement of
issues/finalization of accounts.
b. NHA Finance Wing has accorded concurrence.
9.6. Fiscal Summary/Variation.
Cost Rupees Variation
a. Original 13,151,500 ---
b. Addendum-1 3,557,767 + 27.05%
c. Addendum-2 19,161,120 + 145.70%
d. Revised (a+b+c) 35,870,387 + 172.75%
e. Addendum-3 13,024,000 +99.03
Total Revised (d+e) 48,894,387 +271.78%
9.7. Project PC-I.
a. PC-I of Rs 623 million was approved by ECNEC onNov 6, 2008. Revised PC-I has been prepared and is
under scrutiny by NHA Planning Wing.
b. Provision for consultancy in the original PC-I is Rs
16.05 million, however, an amount of Rs 50 million
has been provided in the revised PC-I.
9.8. Recommendation. The Executive Board is requested to
approve Addendum-3 of M/s Indus Associated Consultants costingRs 13,024,000/=.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 34/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
34
Board’s Deliberations
9.9. The Member (Construction) presented details.
9.10. The AS (Finance) observed that increase in consultancy cost by +271.78% is on very high side and needs detailed justification.
He also wished to know if the construction cost has also increased.
9.11. Further detailed discussion in this case could not be held
because of paucity of time and it was decided that a fresh working
paper may be processed for the next Board meeting.
Decision
9.12. The Executive Board considered the working paper
seeking approval of “Addendum-3 of M/s Indus Associated
Consultants for construction supervision of Ratodero - Naudero Road
costing Rs 13,024,000/=” and directed that a fresh working paper
may be processed for the next Board meeting.
Action By : Member (Construction)
10. Agenda Item 8Addendum-1 of M/s Techno Consult International
(Pvt) Ltd for Construction Supervision: Hyderabad -
Badin to Mir Wah Sanjar Chang Road
Introduction - Working Paper
10.1. Project Road.
a. Subject project has been assigned to NHA on thedirections of the President of Pakistan as deposit
work. It connects many cities of Districts Badin and
Tando Allahyar.
b. Project road starts at km 50 of Hyderabad - Badin
Road and terminates at Mirwah - Sanjar Chang
Road. It will constitute a significant link in road
network of Hyderabad Division and facilitate the flow
of traffic commuting through Tando MohammadKhan, Badin and Tando Allahyar Districts.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 35/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
35
c. The existing stretches of the road measuring 20.547
km (km 0+000 to 1+125, km 20+225 to 27+835, km 35+100 to
44+700 and km 46+225 to 48+337) had deterioratedextensively. Moreover, within project route
alignment, the road is discontinued and does not
exist in many stretches totaling 27.790 km.
10.2. Scope of the Project.
a. Scheme envisages provision of 48+337 km long, 6.1
m wide (two lanes of 3.05 m each) road link between
Hyderabad - Badin Road and Mir Wah - SanjarChang Road through reconstruction of existing
stretches totaling 20.547 km and construction of a
new road over the remaining stretches measuring
27.790 km.
b. Project scope also includes construction of new
structures viz 4 bridges & 222 culverts & setting up
of necessary road furniture.
10.3. Project Packages for Construction Work.
I. Construction / improvement of 24.40 km (km
0+000 to 24+400) road from Jagsi Goth to Haji
Sawan Road.
II. Construction / improvement of 23.937 km (km
24+400 to 48+337) road from Haji Sawan Road to
Mirwah Sanjar Chang Road.
10.4. Project PC-I.
a. PC-I of Rs 880.110 million based on estimated
quantities was processed in Oct-2009 and cleared by
CDWP on Nov 19, 2009 subject to revision of
scope/cost rationalization.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 36/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
36
b. Cost was later rationalized to Rs 835.226 million on
CSR Jan-2009 with no premium. However, bid cost
of only Pack-I was Rs 719.517 million and Pack-II Rs
664.499 million making a total of Rs 1384.016
million necessitating revision of the PC-I.
10.5. Contacts. Following construction contracts are being
supervised by M/s Techno Consult International (Pvt) Ltd:-
Pack Contractor (M/s) Rs in M Start Progress Completion
I.Maqbool
Associates801.70
Feb-
201097% Aug-2012
II. SARCO 664.50Oct-
201055% Nov-2012
10.6. Addendum-1. Necessitated due to grant of EoTs to
construction contractors to complete the work as under:-
Pack Contractor (M/s) EoT
I. Maqbool Associates Feb 25, 2012
II. SARCO Jun 30, 2012
10.7. Fiscal Summary/Variation.
Cost Rupees Variation
a. Original 38,409,000 ---
b. Addendum-1 22,219,622 + 57.85 %
c. Total (a +b) 60,628,622 + 57.85 %
10.8. Proposal. Approval of Addendum-1 of M/s Techno
costing Rs 22,219,622/= entailing EoT from Jun 10, 2011 to Jun 30,
2012 (387 days).
Board’s Deliberations
10.9. The Member (Construction) presented details.
10.10. On an observation if further addendum of M/s Techno
would also be processed, the Member (Construction) responded in
affirmative stating that Pack-I has been substantially completed but
progress on Pack-II is yet 55%.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 37/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
37
10.11. Matter was discussed and cleared by the Members.
Decision
10.12. The Executive Board approved Addendum-1 of M/s
Techno Consult International (Pvt) Ltd, for “Construction Supervision
for Road from Hyderabad Badin to Mirwah Sanjar Chang Road”
costing Rs 22,219,622/= (Rupees twenty two million, two hundred & nineteen
thousand, six hundred & twenty two) only having net cost effect of
+57.85% vis-à-vis original contract cost 60,628,622/= entailing EoT
from Jun 10, 2011 to Jun 30, 2012 (387 days).
Action By : Member (Construction)
11. Agenda Item 9
Addendum-3 of M/s NESPAK for Updation of LARP of
M-4: Gojra-Shorkot, Section-II and Shorkot-Khanewal
Section-III, Alongwith Interchanges
Introduction - Working Paper
11.1. Introduction (M-4).
a. The Faisalabad- Khanewal Motorway (M-4, 184 km)
begins at the end point of Pindi Bhattian -
Faisalabad Motorway (M-3) at Sargodha Road
Interchange in northern outskirts of Faisalabad City.
b. M-4 alignment originally terminated near Khanewal
on N-5 traversing Gojra, Toba Tek Singh and
Shorkot. In 2008, the Prime Minister, announced a
Special Development Package for Southern Punjab. It
included extension of M-4 from Khanewal to Multan.
c. The Faisalabad-Khanewal Section is being
constructed through Asian Development Bank’s
financing and Khanewal - Multan Section through
Islamic Development Bank’s financing.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 38/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
38
11.2. Project PC-I Status (M-4).
a. PC-I of Rs 28,566.74 million was approved by
ECNEC on Jun 2, 2008 for Faisalabad - Khanewal.
b. PC-I of Rs 3.957 billion for land acquisition and
allied facilities was approved by ECNEC on Sep 19,
2007 for Faisalabad - Khanewal.
c. Revised PC-I of Rs 14.4949 billion was approved by
ECNEC on Dec 9, 2010 for Khanewal - Multan
(Extension).
11.3. Construction Packages (Faisalabad-Khanewal).
Section Km
I. Faisalabad-Gojra 58
II. Gojra-Shorkot 62
III. Shorkot-Khanewal 64
Total 184
11.4. Land Acquisition & Resettlement Plan (LARP).
a. LARP has been approved by ADB for main
carriageway and land acquisition of Section-I
(Faisalabad - Gojra, 58.2 km) done accordingly. LARP for
interchanges of Section-I is under process.
b. Land acquisition for 35 km of Section-II (Gojra -
Shorkot) has been completed and remaining 27 km is
under process. LARP is being prepared by NESPAKwho submitted the draft on Aug 31, 2012.
c. Land acquisition of Section-III (Shorkot - Khanewal) is
also under process. LARP is being prepared by
NESPAK & draft will be submitted by Oct 15, 2012.
d. Land acquisition and EIA (Environmental Impact
Assessment) for M-4 Extension (Khanewal - Multan) was
also prepared by NESPAK. Awards for landannounced and construction work is ongoing.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 39/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
39
11.5. Agreement with NESPAK.
a. Agreement with NESPAK was concluded in Jan-2007
for Rs 4,691,952/=. Original scope of workcomprised preparation of EIA and LARP of
Faisalabad-Khanewal.
b. NESPAK prepared and submitted to NHA necessary
reports; which were approved by ADB.
11.6. Addendum-1.
a. It was agreed by ADB in Jun-2008 that LARP indifferent sections would be prepared separately (one
for each section total three LARPs) after conducting
extensive socio-economic survey of M-4 (Faisalabad-
Khanewal).
b. Due to this additional scope of work, Addendum-1
was approved in Jul-2008 with revised cost of Rs
6,488,952/= viz +38.3% variation.
c. LARP for RoW of main carriageway of Section-I
(Faisalabad – Gojra) was prepared as per ADB’s
Safeguard Policy and submitted to ADB. It was
approved and construction activity allowed by ADB.
11.7. Addendum-2.
a. The GoP approved Khanewal - Multan Extension (57
km) in 2009. Additional field activities to prepare
independent LARP and EIA were required for this
section and this task was assigned to NESPAK, being
already mobilized on M-4, under Addendum-2.
b. Revised cost after Addendum-2 was Rs 8,160,952/=
viz +73.94 % cumulative variation. This addendum
was approved in Mar-2009 and formalities were
completed in Aug-2012.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 40/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
40
11.8. Addendum-3.
a. ADB again reviewed its Safeguard Policy in 2009 and
approved Revised LARF (Land Acquisition & Resettlement
Framework) in 2010. To comply with the requirementof this new policy, NHA has to update LARP for
Sections-II & III entailing additional scope of work.
b. Scope/cost of Addendum-3:-
Rupees
i. Verification of land ownership (already done
in Mar-2007, but approval not accorded by
ADB)
2,987,923
ii. Verification & updating of LARP as per
latest ADB Policy and LARF 2010
4,512,077
Total 7,500,000
c. Revised cost after Addendum-3 is Rs 15,660,952/=
viz +233.78 % cumulative variation.
11.9. Cost Effect/Fiscal Summary/Variation.
Cost Rupees Variation
a. Original 4,691,952 ---
b. Addendum-1 1,797,000 +38.30%
c. Addendum-2 1,672,000 +35.64%
d. Revised (a+b+c) 8,160,952 +73.94%
e. Addendum-3 7,500,000 +159.84%
Total (d+e) 15,660,952 +233.78%
11.10. NHA Code. The NHA Executive Board is the competent
authority to approve Addendum-3 as per NHA Code 2005.
11.11. Proposal. Approval of Addendum 3 of NESPAK.
Board’s Deliberations
11.12. The GM (M-4) presented details.
11.13. Matter was discussed and cleared by the Members.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 41/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
41
Decision
11.14. The Executive Board approved Addendum 3 of M/sNESPAK for preparation of LARP for M-4 Sections-II & III as per ADB’s
New Safeguard Policy-2009 and Revised LARF-2010 costing Rs 7.5
million (Rupees seven million and five hundred thousand) only.
11.15. Revised agreement cost will be Rs 15,660,952/= having
total +233.78 % variation vis-à-vis original cost.
Action By : Member (Aided Projects)
12. Agenda Item 10
Revised Estimates 2011-12 & Budget Estimates
2012-13
12.1. Discussion on this working paper could not be held
because of paucity of time. This matter will, therefore, be taken up in
the next Board meeting.
12.2. The Chief (T&C), however, desired that while presenting
fresh working paper, copies of supporting documents / data may also
be added. He also suggested that the next year’s PSDP allocation
proposed by NHA should also be discussed in the Board before
presentation to the Planning Commission.
Action By : Member (Finance) & Member (Planning)
13. Agenda Item 11
Financing Arrangement for NHF and Welfare
Measures for NHA Employees & Their Families:
Transfer of 50% of NHA's Police Fine Share to NHF
13.1. The Secretary NHA apprised the Board that the subject
working paper has been withdrawn.
Action By : Member (Operation)
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 42/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
42
14. Agenda Item 12
Modified PC-I for Amri - Qazi Ahmed Bridge Across
River Indus (Between Hyderabad Bypass and Dadu -
Moro Bridge) Connecting N-5 with N-55
Introduction - Working Paper
14.1. Original & Revised PC-I.
a. PC-I for construction of Amri - Qazi Ahmed Bridge
across River Indus (between Hyderabad Bypass and Dadu -
Mora Bridge) connecting N-5 with N-55 was approved
by ECNEC at a rationalized cost of Rs 3,683 million
on Jan 21, 2010.
b. Scope of work envisaged construction of a 2-lane,
1,241 m main Bridge with 15.431 km approach
roads, 2-flyovers (each at an interchange at N-5 and N-55),
guide banks and other allied structures.
c. PC-I was revised due to enhancement of the Bridge
from 2-lane to 4-lane in view of verbal instructions
of the President of Pakistan to the Chairman NHA.
d. Revised PC-I, prepared at pre-award status, was
discussed on Jul 24, 2012 (219th Board meeting) at a
cost of Rs 5,290.41 million and recommended for
approval by CDWP/ECNEC.
14.2. Modification. Scope of work has been further modified due
to inclusion of additional river training works (Spur and Dike).
14.3. Revision in the Scope of Work from Time-to-Time.
a. Original PC-I (Rs 3,683 million; Jan-2010).
i. Construction of a 2-lane, 1,241 m long main bridge.
ii. Construction of 15.431 km approach roads.
iii. Construction of 2-flyovers.
iv. Construction of guide banks and other allied structures
(cost estimated without Model Study).v. PC-I was based on NHA’s CSR 2009 (Dadu, Sindh).
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 43/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
43
b. Revised PC-I (Rs 5,290 million; Jul-2012).
i. Conversion of 2-lane bridge into 4-lane.
ii. Cost estimation based on actual tendered rates.
c. Modified Revised PC-I (Rs 6,892 million; Oct-2012) -
After Hydraulic Model Study.
i. Increase in length of bridge from 1,241m to
1,320 m; addition of three (03) spans.
ii. Addition of river training works (Spur and Dike) as
emerged after the Model Study and consultation
with Sindh Irrigation Department.
iii. Increase in length of approaches from 15.4 km to
19.3 km.
iv. Cost is based on tendered rates for awarded
works, CSR-2009 + 9.1% for guide banks and
tendered rates for conversion of 2-lane bridge
into 4-lane.
14.4. Project Cost. Original and revised costs of the project
compare as under. Detailed comparison is at Annex-E:-
Cost Rs in Million
a. Original 3,683.000
b. Revised 5,290.418
c. Modified Revised 6,892.109
14.5. Funds. Rs 500 million allocated in PSDP 2012-13.
14.6. Implementation. Project scheduled for construction in 5
years after start in FY 2011-12 depending upon availability of funds.
14.7. Economic Analysis.
a. Benefit Cost Ratio : 3.741:1
b. Internal Rate of Return : 29.81 %c. Net Present Value : Rs 11,185.01 M
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 44/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
44
14.8. Proposal. Recommendation of the modified PC-I costing
Rs 6,892.11 million to the CDWP/ECNEC for approval.
Board’s Deliberations
14.9. The Member (Planning) introduced the proposal and the
GM (Planning) presented details. The Member (Construction) and GM
(Design-1) were also present.
14.10. The Chief (T&C) pointed out that it has been stated in the
working paper that the raising of bunds due to revised requirement of
Federal Flood Commission (minimum 7 ft) shall be done by Sindh
Irrigation Department for which cost is not indicated in the PC-I. The
modified PC-I should have been prepared in totality and the cost of Sindh Government’s component also included after consulting all
stakeholders.
14.11. The GM (Design-1) clarified that after approval of the
original PC-I, which was prepared without model study, the river flow
pattern was changed by the Superfloods-2010. The peak flood left a
free board of only 6 inches on the flood protection bund. Subsequent
to construction of the new bridge additional flux would be created
compelling raising of the bund, which is Sindh Government’s domain.
14.12. The Sindh Irrigation Deptt has not been rendering
unstinted cooperation while NHA is under instructions of the GoP
higher-ups to complete this project at priority. Resultantly, indulgence
of WAPDA was sought and it was on the intervention at the level of
Member (Power) WAPDA (now Chairman) that certain technical issues
were resolved. Any further consultations with the provincial
authorities would delay processing of the modified PC-I.
14.13. The Chief (T&C) agreed that raising of the protection bund
is beyond NHA’s purview but reiterated that NHA may obtain relevant
input / cost estimates from the provincial authorities concerned and
add the same to the modified PC-I cost and leave further decision in
the matter to the CDWP.
14.14. The AS (Finance) endorsed the above remarks stating that
the project cost should be holistic but NHA can highlight as to whichcomponents of the PC-I pertained to the provincial government.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 45/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
45
14.15. On another observation by the Chief (T&C) it was clarified
that the cost of land acquisition and length of approaches has
increased due to addition of loops to the interchanges.
14.16. Matter was discussed and cleared. However, it was finally
decided that to save on time NHA would include Rs 400 million in the
project cost for raising of protection bund and submit the PC-I to the
Planning Commission where this cost will be rationalized after detailed
scrutiny.
14.17. The Chairman NHA remarked that the revised PC-I before
submission to the Planning Commission will be scrutinized by theprescribed Technical Working Party.
Decision
14.18. The Executive Board recommended the modified PC-I for
“construction of Amri-Qazi Ahmed Bridge across River Indus (between
Hyderabad Bypass and Dadu - Mora Bridge) connecting N-5 with N-55” at a
cost of Rs 7292.11 million to the CDWP/ECNEC for approval.
Action By : Member (Planning) & Member (Construction)
15. Additional Agenda Item I
Award of Works Under Flood Emergency Re-
construction Project (FERP) : NCB-S-12 Construction
of Bridge Across Vadoor Nullah at Km 96-97 (N-70)
Introduction - Working Paper
15.1. ADB Loan/ Scope of Work.
a. Pakistan has received a loan (PAK 2742) from the
Asian Development Bank (ADB) towards the cost of
Flood Emergency Reconstruction Project (FERP).
b. Subject project ie NCB-S-12 Construction of Bridge
over Vadoor Nullah at km 96-97 (N-70) is included in
Phase-I of FERP.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 46/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
46
15.2. Global PC-I.
a. Global PC-I of FERP based on DNA (Damage Need
Assessment) study conducted by NESPAK waspresented in ECNEC meeting held on May 26, 2011.
The ECNEC approved the PC-I, in principle, with the
following instructions:-
“The ECNEC considered the summary dated May 4, 2011
submitted by the Planning Commission titled “Rehabilitation of
National Highway Network Damaged due to Unprecedented
Monsoon Rains & Flash Floods 2010” and approved the project,
in principle, and authorized Dy Chairman Planning Commission/
Chairman CDWP to approve the reviewed scope and cost of project duly vetted by the high level Committee constituted by the
CDWP.”
b. Revised PC-I is under preparation and included in
the deliverables of design consultants.
15.3. Engineer’s Estimate. Rs 99,145,096/= (CSR 2009+9.1%).
15.4. Tendering.
a. Procurement of subject works was undertaken on
Single-Stage-Two-Envelopes basis for civil works in
accordance with ADB’s guidelines.
b. Escalation shall not be applicable on contracts
having 12 months or less duration. Being 9 months
project, escalation is not applicable in this case.
c. Advertisement for Invitation of Bids (IFB) was
published in the press and displayed on NHA and
PPRA websites on Apr 27, 2012. Bid documents were
procured by eleven (11) eligible firms individually or
as JV.
d. Five (5) firms submitted technical and financial bids
on the due date viz May 14, 2012:-
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 47/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
47
Messers’ Legend
i. Techno Time Construction Company Techno Time
ii. Mohandisin-e-Masud Builders, Engineers Mohandisin
iii. Sh Abdur Razzaq & Company (Pvt) Ltd SARCO
iv. Haji Noor Muhammad & Sons HNMS v. Sachal Engineering Works (Pvt) Ltd Sachal
15.5. Technical Evaluation.
a. Technical bids were opened on May 14, 2012 by the
Bid Opening & Evaluation (BO&E) Committee in the
presence of Reps of the bidders. Price bids were kept
unopened and sealed in safe custody.
b. Technical bids were evaluated in accordance with
qualification criteria stipulated in bid documents. As
a result, bid of M/s Haji Noor Muhammad & Sons
was evaluated as “unqualified.”
c. Technical Bid Evaluation Report was approved by
ADB on Jun 20, 2012.
15.6. Financial Bid Evaluation.
a. Financial bids were opened on Jun 21, 2012 in the
presence of BO&E Committee. Quoted/announced
bid prices were as summarized below:-
Bidder (M/s) Rupees
i. Techno Time 127,302,427
ii. Mohandisin 138,500,000
iii. SARCO 142,333,667
iv. Sachal 148,422,770
b. Bids were evaluated in accordance with ADB’s
standard procedures. However, there were certain
typographic and arithmetic errors in the bids of M/s
Techno Time, M/s Mohandisin and M/s Sachal.
15.7. Summary. Summarized comparison vis-à-vis estimated
cost of Rs 99,145,096/= (CSR 2009 + 9.1%) is as under-
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 48/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
48
Rank Consultant (M/s) Submitted (Rs) Corrected (Rs) Variation
1st Techno Time 127,302,427 127,302,466 +28.40%
2nd Mohandisin 138,500,000 131,381,382 +32.51%
3rd SARCO 142,333,667 142,333,666 +43.56%
4th Sachal 148,422,770 148,454,069 +49.73%
15.8. ADB’s Concurrence. The Priced Bid Evaluation Report
was forwarded to ADB for review/concurrence on Jun 27, 2012. The
ADB issued NOC dated Jul 2, 2012 for award of works to M/s Techno
Time Construction Company at Rs 127,302,466/-.
15.9. Recommendation. The Tender Acceptance Committee has
recommended acceptance of the bid of Rs 127,302,466/= of M/s
Techno Time Construction Company.
Board’s Deliberations
15.10. The Member (Planning) presented details. The Member
(Operation), GM (P&CA) & GM (Design-1) were also present.
15.11. The VP-NESPAK observed that the lowest bid at +28.40%
the estimated cost is on higher side particularly if compared with the
bids generally received in the recent past. Moreover, the project is also
not located in a hard or security prone area. The Board may consider
fixing a limit for acceptance of bids higher than the estimated cost as
even competitive bidding can be manipulated. He also enquired if a
bid with such a high variation was accepted in the past.
15.12. It was clarified that NHA is engaging contractors for anumber of schemes under FERP & the bids are generally competitive
barring that under debate. Bids for other development projects invited
on single stage two envelope basis during the past around 12 - 15
months were also quite competitive. However, during 2009 and 2010
bids of even more than 30% the estimated cost were accepted. Re-
tendering is an option but it will take more than 3 months, whereas,
NHA has to finalize the bidding process under FERP at priority as per
the understanding reached with ADB.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 49/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
49
15.13. On the suggestion regarding fixing an upper limit, it was
submitted that the single stage two envelop system has proved quitebeneficial in attracting competitive bids and the ADB guidelines for
technical evaluation are also reasonably stringent. Therefore, the
existing system may continue.
15.14. On another observation, it was clarified that the estimated
cost was based on CSR-2009 + 9.1% premium and if the bid is
compared with the recently approved CSR-2011, it is almost at par as
the difference between CSR-2009+9.1% premium and current rates is
in the range of 30%.
15.15. The Member (Operation) conveyed that Vadoor Nullah
receives water only in case of heavy rains and a culvert originally
existed at this site but was washed away in the Superfloods-2010. For
the past two years, traffic is passing through a temporary diversion
and the road users are facing extreme difficulty at this bottleneck. It is
essential that the bridge is completed before next monsoon season.
15.16. Matter was discussed and cleared by the Members.
15.17. The Chief (T&C) remarked that his observations regarding
administrative approval for incurring expenditure on FERP pending
formal approval of global PC-I hold good in this case too (Para-6.15).
Decision
15.18. The Executive Board approved award of works for “NCB-
S-12 Construction of Bridge Across Vadoor Nullah at Km 96 - 97
(N-70)” to M/s Techno Time Construction Company at the quoted /
corrected bid amount of Rs 127,302,466/= (Rupees one hundred & twenty
seven million, three hundred & two thousand, four hundred and sixty six) only;
which is +28.40% the estimated cost (CSR-2009+9.1%) subject to
completion of codal formalities.
Action By : Member (Planning)
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 50/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
50
16. Additional Agenda Item II
Upgradation of Misc Posts in BS-1 to 16 of NHA
Employees
16.1. The Secretary NHA solicited permission of the Executive
Board for tabling working paper on the subject matter, as directed by
the Chairman NHA. However, due to paucity of time, it was decided
that this matter will be considered in the next Board.
Action By : Member (Admin)
17. Status Report on Revised PC-Is and Scrutiny of Revised PC-Is by the Technical Working Party
17.1. The Chairman during the course of discussion on award
of works remarked that in most of the cases expenditure on various
projects exceed the permissible 15% limit of the approved PC-I. He has
already directed all concerned Members of NHA to expedite processing
of revised PC-Is of completed / near completion projects and would
like that a special Board meeting be convened for review of all such
PC-Is in Dec-2012.
17.2. The AS (Finance) remarked that this is a much needed
exercise not only for identifying the cost impact because of delay in
completion of projects and due to variation orders issued from time-
to-time but also to critically analyze the lessons learnt for corrective
actions. He suggested that a comprehensive briefing on each mega
project entailing time / cost overrun be arranged for the Board.
17.3. The Member (Planning) stated that revised PC-Is of a large
number of projects are required to be processed and this might not be
possible by Dec-2012, however, effort would be made to expedite as
many revised PC-Is as possible within the next 2-3 months.
17.4. The Chairman further remarked that all fresh and also
revised PC-Is should be processed through the prescribed Technical
Working Party (TWP) before submission to the Executive Board.
8/9/2019 222 Executive Borad Meeting of NHA
http://slidepdf.com/reader/full/222-executive-borad-meeting-of-nha 51/52
222nd Meeting, October 16, 2012, Islamabad
NHA Executive Board’s Confirmed Minutes
51
17.5. The above suggestions were appreciated and endorsed by
the Members.
17.6. Note. For scrutiny of revised PC-Is of development projects
/schemes by the TWP, no clause exists in NHA Code 2005. In view of the above decision, the relevant contents of NHA Code (Sections 50 & 51,
Chapter-2 -- Planning Process) will be suitably modified.
Action By : Member (Planning), Member (Construction),
Member (Aided Projects) and Secretary NHA
18. Tribute to Mr Muhammad Ali Gardezi, FormerChairman NHA
18.1. Mr Muhammad Ali Gardezi, a BS-21 officer of Pakistan
Administrative Service, served as the Chairman NHA on deputation
from Jul 6, 2011 to Oct 2, 2012. During his 15 months tenure Mr
Gardezi throughout endeavored and worked untiringly to improve the
working system of NHA. When he joined, NHA was in poor financial
health and the situation warranted special steps / measures. When
Mr Gardezi left in Oct-2012, the general situation of NHA projects and
the reputation of NHA improved substantially in the eyes of general
public, stakeholders and decision makers.
18.2. The Executive Board unanimously resolved to pay glowing
tributes to Mr Muhammad Ali Gardezi for the services rendered and
the quality leadership provided by him as the Chairman NHA. His
contribution and untiring efforts would be long remembered. The
Board wished him best of luck and success in his future career and
the times ahead.
19. Conclusion
19.1. The Chairman wrapped up the meeting by thanking the
Members for their active participation and useful input in this first
Board meeting chaired by him. He expressed the hope that with the
cooperation and assistance by the Board Members, the working
system and output of NHA would be further improved and this would
be of immense benefit to entire Pakistan, the national highways being
the economic lifeline of the country.
------------------