23 - 1 nasa’s goddard space flight center lro integration and test joanne baker gsfc code 568...
TRANSCRIPT
23 - 1NASA’s Goddard Space Flight Center
LRO Integration and Test
Joanne Baker
GSFC Code 568
August 16-17, 2005
23 - 2NASA’s Goddard Space Flight Center
• LRO testing shall be in accordance with the “LRO Verification Plan”, 431-PLAN-000101.
• LRO integration and test shall be performed per the “LRO Integration and Test Plan”, 431-PLAN-000100.
• LRO launch site activities shall be performed in accordance with the “LRO Launch Site Support Plan”.
I&T Driving Documents
23 - 3NASA’s Goddard Space Flight Center
I&T Document Tree
RLEP Mission Assurance Requirements
430-RQMT-000006
LRO Mission Requirements Document 431-RQMT-00004
LRO Electrical Systems
Specification431-ICD-000008
Mechanical Systems
Specification431-RQMT-000012
Contamination Control Plan
431-PLAN-000110
Thermal Systems
Specification 431-SPEC-000091
GENERAL ENVIRONMENTAL
VERIFICATION STANDARD (GEVS)
SC Subsystem & Instr. ICDs / Specifications/
Requirements
Subsystem & Instr. Interface / Assembly
Drawings
Observatory Verification Plan & Matrix431-PLAN-000101
LRO Ground System ICD
431-ICD-000049
Rules for the Design, Development,
Validation, and OperationOf Flight SystemsGSFC-STD-1000
SC PAIP431-PLAN-000131
LRO Detailed Mission Requirements (DMR) for the LRO Ground System
431-RQMT-000048
LRO MissionVehicle Interface
Control Doc
LRO SystemSafety Plan
431-PLAN-000176
23 - 4NASA’s Goddard Space Flight Center
Integration and Test Plan431-PLAN-000100
Observatory Verification Plan & Matrix
431-PLAN-000101
Test Plans& Procedures
WOAs
LRO SystemSafety Plan
431-PLAN-000176
Mission ReadinessTest Plan
431-PLAN-000079
Handling & LiftProcedures
Simulations
Contamination Control Plan
431-PLAN-000110
I&T Document Tree – cont.
ITOS Procs
Test Results And Reports
Verification Matrix
SC PAIP431-PLAN-000131
GSE Requirements/Specification Docs
LRO Detailed Mission Requirements (DMR) for the LRO Ground System
431-RQMT-000048
InstrumentIntegration &
Test Plans
23 - 5NASA’s Goddard Space Flight Center
I&T Document Tree – cont.
Launch Site Support Plan
LRO MSPSP
Ground OperationsProcedures
Integration and Test Plan
431-PLAN-000100
LRO SystemSafety Plan
431-PLAN-000176
23 - 6NASA’s Goddard Space Flight Center
Orbiter Integration & Test Flow - 1
OB - Instrument Integration &
Alignment
Propulsion ModuleDelivery
Inst. Interface Check
Out W/ Flat Sat
Battery & PSEPlate Integration
Flat SatBuild Up and
Checkout
Flt. PowerSystemDelivery
Flt. C&DH SystemDelivery
C&DHPlate
Integration
Upper StructureIntegration
Reaction WheelIntegration
Optical BenchDelivery
ST & IRUIntegration &
Alignment
Battery & PSEOrbiter Integration
& Test
C&DH Integration & Test
PDEIntegration & Test
RF componentsIntegration & Test
Preliminary BusFunctional Testing
Optical BenchIntegration & Test
SA and HGAIntegration & Test
Bus MountedInstrument
Integration & Test
23 - 7NASA’s Goddard Space Flight Center
Orbiter Integration & Test Flow - 2
Time Offset/Drift
Test
CPT
ACS PolarityTest
AlignmentBaseline
Jitter Characterization
S/A and HGADeployment
Tests
LOLABoresightAlignment
InstrumentFunctional
Tests
LAMPEnd to End
Test
Comm SysEnd to
End Test
Day In theLife
RFCompatibility
Test
Mission Sims
23 - 8NASA’s Goddard Space Flight Center
Orbiter Integration & Test Flow - 3
Separation/ShockTest
Alignment Check
& FunctionalTest
EMCThermal
Vac & Balance
Pre-ShipActivities
AlignmentCheck
PostEnvironmental
CPT
Bus & Instrument
Special Tests
ShipTo KSC
Post-ShipActivities
Post-ShipFunctional or
CPT
Pad ReadinessActivities
PadInstallation
PadAliveness
Test
Fairing Installation
FinalClose Outs
LAUNCH
SpinBalance /
Mass Properties
Sine VibeW/ Aliveness
AcousticsW/ Aliveness
Pre-EnvironmentalReview
Fueling
23 - 9NASA’s Goddard Space Flight Center
I&T Verification Summary
• Interfaces – Mechanical Integration; Electrical Integration Procedures; Polarity test; Alignment; Spin
Balance; Mass Properties
• Functionality Hardware– Functional Test; Performance; Time verification; End to End Tests; Deployment Tests
• Functionality Software– Day in the Life; Separation timeline; Mission Sims
• Environments– Contamination; Jitter Characterization; Sine Vibe; Acoustics; Shock / Separation Test; EMC;
Thermal Vac / Balance
• Instrument Special Tests (unique configurations)– LOLA: Boresight alignment check; LAMP: End to End Test;
23 - 10NASA’s Goddard Space Flight Center
Ground Support Equipment – Orbiter Level
• Simulators: Instrument simulators, Spacecraft simulators; Flat Sat
• Mechanical GSE– Lift fixtures, handling dolly, turnover fixture, transportation fixture, thermal vac support structure.
• C&DH GSE– Front End Processors – S-band & Ka-band
– 1553 Bus Monitor
– Space Wire Test Rack
– Data Storage
– Workstations
• RF racks & antenna hats
• Time test rack
• Power GSE– Solar Array Simulator; Battery Simulator; Load Box
• ACS GSE– Dynamic Simulator; ACS component stimulators: Star Tracker, IRU
• Propulsion module simulator/GSE
• Instrument Unique Ground Support Equipment– CRaTER: CO60 source; non-ITOS workstation; Diviner: BCE; LAMP: Vac Ion, Pump, UV light source;
LEND: Californium source; LOLA: Laser Test Equipment (BCE), target; LROC: none identified
• Contamination– Instrument GN2 purges
23 - 11NASA’s Goddard Space Flight Center
I&T Summary
• Instrument requirements identified to date and understood.
• Most difficult area will be thermal vac test configuration.– Testing may be limited by configuration limitations.
• Other I&T requirements are not unique and can be realized.
• I&T plan will be in released draft form by mission PDR.
• Ready to proceed with preliminary design.