    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    1/67

    3.1 Measurement Method of Electrical System

    1. Code E-01 : Substation and Equipment

    1.1 Definition

    This work item is defined as the installation works of substation and equipment in

    accordance with the drawings, technical specifications and manufacturers instruction

    manual at the Site, including unloading of the Contractor supplied materials at the

    Contractor designated locations, site transportation, hauling, rigging, setting, assembling,

    bolting, terminating, welding if necessary, alignment, inspection, calibration, test, pre-

    commissioning and assistance for commissioning/start-up and operational test.

    This work item shall also include, but not limited, the following ;

    Installation of all parts /components/supports shipped separately for transportation

    Furnishing and installation of anchor bolt/bolt/nut/washer, if required

    Installation and connection of vendor cable/wire, including supply of terminal lug, ifrequired

    Furnishing and installation of warning tape and sign board

    Test and inspection as per the project specification and inspection procedure

    Furnishing and installation of field fabricated steel support material shall not be includedin this work item, but shall be included in Code E-25.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations

    Mechanical and electrical connections between shipping sections, including bus and

    ground joints

    Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,

    methodology, inspection/test plan and procedure, etc.)

    Removal of existing obstacles to installation work and restoration work uponcompletion thereof. Reinforcement or protection work for existing facilities, as required

    by the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary

    Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary

  • 8/12/2019 2.3.1 Measurement Method for Electical

    2/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    2/67

    The following works related to the installation of the work item on concretefoundation :

    Checking anchor bolts and foundation with respect to location, size, level, etc.

    Chipping concrete foundation Setting mortar pads and liner plates

    Adjusting anchor bolts

    Setting and grouting box-out anchor bolts

    Mortar grouting and curing

    Welding washers and/or liner plates, as required by technical specifications and/ordrawings

    Opening and re-closing manholes and/or handholes for cleaning and inspection

    Rust prevention during the construction work and timely removal of such rust andprevention materials, if any

    Cleaning equipment inside / outside as required Application of necessary anti-seizing solvent/compound/paste for bolts and nuts

    Application of specified compound/paste to gaskets

    Application of touch-up paint

    Preparation and submission of inspection/test record as per inspection/test plan

    All other work, as required by the drawings, technical specifications and manufacturers

    instruction manual

    Site cleaning the work place

    1.2 Measurement method and unit of quantities

    1.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,

    size, electrical rating, weight, type of equipment and elevation/location of working places,

    etc.

    1.2.2 Measurement method and unit of quantities

    The quantities shall be measured by number of complete set of equipment, where specified

    by SET, and by length of net installed cable excluding any waste or allowance, where

    specified by M.

    Any accessories, components and parts will not be separately measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    1.2.3 Progress Measurement method (to be decided later or refer to the Contractors PMS)

  • 8/12/2019 2.3.1 Measurement Method for Electical

    3/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    3/67

    The quantities measured as per 1.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

    Completion of installation and alignment : 80 %

    Submission of inspection and test record : 15 %

    Completion of Energization : 5 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    4/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    4/67

    2. Code E-02 : Transformer

    2.1 Definition

    This work item is defined as the installation works of transformers in accordance with the

    drawings, technical specifications and manufacturers instruction manual at the Site,

    including unloading of the Contractor supplied materials at the Contractor designated

    locations, site transportation, hauling, rigging, setting, assembling, bolting, terminating,

    welding if necessary, alignment, inspection, calibration, test, pre-commissioning and

    assistance for commissioning/start-up and operational test.

    This work item shall also include, but not limited, the following ;

    Installation of all parts /components/supports shipped separately for transportation Furnishing and installation of anchor bolt/bolt/nut/washer, if required

    Installation and connection of vendor cable/wire, including supply of terminal lug ifrequired

    Installation of transformer oil including purification and testing of the oil

    Furnishing and installation of warning tape and sign board

    Test and inspection as per the project specification and inspection procedure

    Furnishing and installation of field fabricated steel support material shall not be included

    in this work item, but shall be included in Code E-25.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, and

    installation locations

    Mechanical and electrical connections between shipping sections, including bus and

    ground joints

    Preparation of work plans and procedures and submission for the Contractors approval

    prior to starting the work (work procedure, construction method statement,methodology, inspection/test plan and procedure, etc.)

    Removal of existing obstacles to installation work and restoration work uponcompletion thereof. Reinforcement or protection work for existing facilities, as required

    by the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary

    Removal of reinforcing or protection materials used for the transportation or installation

    of equipment, as necessary

    The following works related to the installation of the work item on concrete

    foundation :

    Checking anchor bolts and foundation with respect to location, size, level, etc.

  • 8/12/2019 2.3.1 Measurement Method for Electical

    5/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    5/67

    Chipping concrete foundation

    Setting mortar pads and liner plates

    Adjusting anchor bolts

    Setting and grouting box-out anchor bolts Mortar grouting and curing

    Welding washers and/or liner plates, as required by technical specifications and/ordrawings

    Opening and re-closing manholes and/or handholes for cleaning and inspection

    Rust prevention during the construction work and timely removal of such rust andprevention materials, if any

    Cleaning equipment outside/inside as required

    Application of necessary anti-seizing solvent/compound/paste for bolts and nuts

    Application of specified compound/paste to gaskets

    Application of touch-up paint Preparation and submission of inspection/test record as per inspection/test plan

    All other work, as required by the drawings, technical specifications and manufacturersinstruction manual

    Site cleaning the work place

    2.2 Measurement method and unit of quantities

    2.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,size, electrical rating, weight, type of equipment and elevation/location of working places,

    etc.

    2.2.2 Measurement method and unit of quantities

    The quantities shall be measured by number of complete set of transformer.

    Any accessories, components and parts will not be separately measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    2.2.3 Progress Measurement method (to be decided later or refer to the Contractor s PMS)

    The quantities measured as per 2.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

    Completion of installation and alignment : 80 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    6/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    6/67

    Submission of inspection and test record : 15 %

    Completion of Energization : 5 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    7/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    7/67

    3. Code E-03 : Switchgear/MCC/Panel

    3.1 Definition

    This work item is defined as the installation works of switchgear, MCC and miscellaneous

    panels in accordance with the drawings, technical specifications and manufacturers

    instruction manual at the Site, including unloading of the Contractor supplied materials at

    the Contractor designated locations, site transportation, hauling, rigging, setting,

    assembling, bolting, welding if necessary, alignment, inspection, calibration, test, pre-

    commissioning and assistance for commissioning/start-up and operational test.

    This work item shall also include, but not limited, the following ;

    Installation of all parts /components shipped separately for transportation Furnishing and installation of anchor bolt/bolt/nut/washer, if required

    Installation and connection of vendor cable/wire, including supply of terminal lug ifrequired

    Furnishing and installation of warning tape and sign board

    Test and inspection as per the project specification and inspection procedure

    Furnishing and installation of field fabricated steel support material shall not be included

    in this work item, but shall be included in Code E-25.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations

    Mechanical and electrical connections between shipping sections, including bus andground joints

    Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,

    methodology, inspection/test plan and procedure, etc.) Removal of existing obstacles to installation work and restoration work upon

    completion thereof. Reinforcement or protection work for existing facilities, as required

    by the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary

    Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary

    The following works related to the installation of the work item on concretefoundation :

    Checking anchor bolts and foundation with respect to location, size, level, etc.

    Chipping concrete foundation

  • 8/12/2019 2.3.1 Measurement Method for Electical

    8/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    8/67

    Setting mortar pads and liner plates

    Adjusting anchor bolts

    Setting and grouting box-out anchor bolts

    Mortar grouting and curing Welding washers and/or liner plates, as required by technical specifications and/or

    drawings

    Opening and re-closing manholes and/or handholes for cleaning and inspection

    Rust prevention during the construction work and timely removal of such rust and

    prevention materials, if any

    Cleaning equipment inside/outside as required

    Application of necessary anti-seizing solvent/compound/paste for bolts and nuts

    Application of specified compound/paste to gaskets

    Application of touch-up paint

    Preparation and submission of inspection/test record as per inspection/test plan All other work, as required by the drawings, technical specifications and manufacturers

    instruction manual

    Site cleaning the work place

    3.2 Measurement method and unit of quantities

    3.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,

    size, electrical rating, weight, type of equipment and elevation/location of working places,etc.

    3.2.2 Measurement method and unit of quantities

    The quantities shall be measured by number of panel where specified by panel, and by

    number of complete set of equipment where specified by lot.

    Any accessories, components and parts will not be separately measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    3.2.3 Progress Measurement method (to be decided later or refer to the Contractor s PMS)

    The quantities measured as per 3.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

    Completion of installation and alignment : 80 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    9/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    9/67

    Submission of inspection and test record : 15 %

    Completion of Energization : 5 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    10/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    10/67

    4. Code E-04 : Bus Duct

    4.1 Definition

    This work item is defined as the installation works of bus duct in accordance with the

    drawings, technical specifications and manufacturers instruction manual at the Site,

    including unloading of the Contractor supplied materials at the Contractor designated

    locations, site transportation, hauling, rigging, setting, assembling, laying, bolting, welding

    if necessary, alignment, terminating, inspection, test, pre-commissioning and assistance for

    commissioning/start-up and operational test.

    This work item shall also include, but not limited, the following ;

    Installation of all parts /components/supports shipped separately for transportation Furnishing and installation of anchor bolt/bolt/nut/washer, if required

    Furnishing of welding rod and welding consumables, if required

    Test and inspection as per the project specification and inspection procedure

    Furnishing and installation of field fabricated steel support material shall not be included

    in this work item, but shall be included in Code E-25.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations

    Mechanical and electrical connections between shipping sections, including bus andground joints

    Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,

    methodology, inspection/test plan and procedure, etc.)

    Removal of existing obstacles to installation work and restoration work upon

    completion thereof. Reinforcement or protection work for existing facilities, as requiredby the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary

    Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary

    The following works related to the installation of the work item on concretefoundation :

    Checking anchor bolts and foundation with respect to location, size, level, etc.

    Chipping concrete foundation

    Setting mortar pads and liner plates

    Adjusting anchor bolts

  • 8/12/2019 2.3.1 Measurement Method for Electical

    11/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    11/67

    Setting and grouting box-out anchor bolts

    Mortar grouting and curing

    Welding washers and/or liner plates, as required by technical specifications and/or

    drawings Opening and re-closing manholes and/or handholes for cleaning and inspection

    Rust prevention during the construction work and timely removal of such rust andprevention materials, if any

    Cleaning equipment inside/outside as required

    Application of necessary anti-seizing solvent/compound/paste for bolts and nuts

    Application of specified compound/paste to gaskets

    Application of touch-up paint

    Preparation and submission of inspection/test record as per inspection/test plan

    All other work, as required by the drawings, technical specifications and manufacturers

    instruction manual Site cleaning the work place

    4.2 Measurement method and unit of quantities

    4.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,

    size, electrical rating, weight, type of equipment and elevation/location of working places,

    etc.

    4.2.2 Measurement method and unit of quantities

    The quantities shall be measured by length (linear meter) along the center line of bus duct

    from the construction drawing, or by number of complete set of equipment where specified

    by lot.

    Any accessories, components, fittings and support structure will not be separately

    measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    4.2.3 Progress Measurement method (to be decided later or refer to the Contractor s PMS)

    The quantities measured as per 4.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

    Completion of installation and alignment : 85 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    12/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    12/67

    Submission of inspection and test record : 15 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    13/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    13/67

    5. Code E-05 : Emergency Diesel Generator

    5.1 Definition

    This work item is defined as the installation works of emergency diesel generator in

    accordance with the drawings, technical specifications and manufacturers instruction

    manual at the Site, including unloading of the Contractor supplied materials at the

    Contractor designated locations, site transportation, hauling, rigging, setting, assembling,

    bolting, welding if necessary, alignment, terminating, calibration, inspection, test, pre-

    commissioning and assistance for commissioning/start-up and operational test.

    This work item shall also include, but not limited, the following ;

    Installation of all parts /components/supports shipped separately for transportation Furnishing and installation of anchor bolt/bolt/nut/washer, if required

    Installation and connection of vendor cable/wire, including supply of terminal lug ifrequired

    Test and inspection as per the project specification and inspection procedure

    Furnishing and installation of field fabricated steel support material shall not be included

    in this work item, but shall be included in Code E-25.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations

    Mechanical and electrical connections between shipping sections, including bus andground joints

    Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,

    methodology, inspection/test plan and procedure, etc.)

    Removal of existing obstacles to installation work and restoration work uponcompletion thereof. Reinforcement or protection work for existing facilities, as required

    by the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary

    Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary

    The following works related to the installation of the work item on concretefoundation :

    Checking anchor bolts and foundation with respect to location, size, level, etc.

    Chipping concrete foundation

    Setting mortar pads and liner plates

  • 8/12/2019 2.3.1 Measurement Method for Electical

    14/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    14/67

    Adjusting anchor bolts

    Setting and grouting box-out anchor bolts

    Mortar grouting and curing

    Welding washers and/or liner plates, as required by technical specifications and/ordrawings

    Opening and re-closing manholes and/or handholes for cleaning and inspection

    Rust prevention during the construction work and timely removal of such rust andprevention materials, if any

    Cleaning equipment outside/inside as required

    Application of necessary anti-seizing solvent/compound/paste for bolts and nuts

    Application of specified compound/paste to gaskets

    Application of touch-up paint

    Preparation and submission of inspection/test record as per inspection/test plan

    All other work, as required by the drawings, technical specifications and manufacturersinstruction manual

    Site cleaning the work place

    5.2 Measurement method and unit of quantities

    5.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,

    size, electrical rating, weight, type of equipment and elevation/location of working places,

    etc.

    5.2.2 Measurement method and unit of quantities

    The quantities shall be measured by number of complete set of diesel engine generator.

    Any accessories, components, fittings and support structure will not be separately

    measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    5.2.3 Progress Measurement method(to be decided later or refer to the Contractor s PMS)

    The quantities measured as per 5.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

    Completion of installation and alignment : 85 %

    Submission of inspection and test record : 15 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    15/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    15/67

    6. Code E-06 : DC/AC and UPS System Equipment

    6.1 Definition

    This work item is defined as the installation works of DC/AC and UPS system equipment

    in accordance with the drawings, technical specifications and manufacturers instruction

    manual at the Site, including unloading of the Contractor supplied materials at the

    Contractor designated locations, site transportation, hauling, rigging, setting, assembling,

    bolting, welding if necessary, alignment, terminating, calibration, inspection, test,

    precommissioning and assistance for commissioning/start-up and operational test.

    This work item shall also include, but not limited, the following ;

    Installation of all parts /components/supports shipped separately for transportation Furnishing and installation of anchor bolt/bolt/nut/washer, if required

    Installation and connection of vendor cable/wire/bus bar

    Installation of battery rack

    Installation of battery electrolyte

    Test and inspection as per the project specification and inspection procedure

    Furnishing and installation of field fabricated steel support material shall not be included

    in this work item, but shall be included in Code E-25.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations

    Mechanical and electrical connections between shipping sections, including bus andground joints

    Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,

    methodology, inspection/test plan and procedure, etc.) Removal of existing obstacles to installation work and restoration work upon

    completion thereof. Reinforcement or protection work for existing facilities, as required

    by the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary

    Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary

    The following works related to the installation of the work item on concretefoundation :

    Checking anchor bolts and foundation with respect to location, size, level, etc.

    Chipping concrete foundation

  • 8/12/2019 2.3.1 Measurement Method for Electical

    16/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    16/67

    Setting mortar pads and liner plates

    Adjusting anchor bolts

    Setting and grouting box-out anchor bolts

    Mortar grouting and curing Welding washers and/or liner plates, as required by technical specifications and/or

    drawings

    Opening and re-closing manholes and/or handholes for cleaning and inspection

    Rust prevention during the construction work and timely removal of such rust and

    prevention materials, if any

    Cleaning equipment inside/outside as required

    Application of necessary anti-seizing solvent/compound/paste for bolts and nuts

    Application of specified compound/paste to gaskets

    Application of touch-up paint

    Preparation and submission of inspection/test record as per inspection/test plan All other work, as required by the drawings, technical specifications and manufacturers

    instruction manual

    Site cleaning the work place

    6.2 Measurement method and unit of quantities

    6.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,

    size, electrical rating, numbers of battery, weight, type of equipment and elevation/locationof working places, etc.

    6.2.2 Measurement method and unit of quantities

    The quantities shall be measured by number of complete set of DC/AC and UPS system.

    Any accessories, components, fittings and battery rack will not be separately measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    6.2.3 Progress Measurement method(to be decided later or refer to the Contractor s PMS)

    The quantities measured as per 6.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

    Completion of installation and alignment : 80 %

    Submission of inspection and test record : 15 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    17/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    17/67

    Completion of pre-commissioning : 5 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    18/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    18/67

    7. Code E-07 : Cable Tray/Rack/Duct with Accessories, Fittings and Covers

    7.1 Definition

    This work item is defined as the installation works of cable tray/rack/duct in accordance

    with the drawings, technical specifications and manufacturers instruction manual at the

    Site, including unloading of the Contractor supplied materials at the Contractor designated

    locations, site transportation, hauling, rigging, setting, assembling, laying, bolting, welding

    if necessary, alignment and inspection.

    This work item shall also include, but not limited, the following ;

    Installation of cable tray/rack/duct cover

    Installation of accessories and fittings including horizontal/vertical bend, tee, etc. Installation of grounding bonding jumper

    Furnishing and installation of sealing compound

    Furnishing and installation of cable tray rack/duct marker

    Furnishing and installation of anchor bolt/bolt/nut/washer, if required

    Test and inspection as per the project specification and inspection procedure

    Furnishing and installation of field fabricated steel support material shall not be included

    in this work item, but shall be included in Code E-25.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations

    Mechanical and electrical connections between shipping sections, including bus andground joints

    Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,

    methodology, inspection/test plan and procedure, etc.) Removal of existing obstacles to installation work and restoration work upon

    completion thereof. Reinforcement or protection work for existing facilities, as required

    by the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary

    Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary

    The following works related to the installation of the work item on concretefoundation :

    Checking anchor bolts and foundation with respect to location, size, level, etc.

    Chipping concrete foundation

  • 8/12/2019 2.3.1 Measurement Method for Electical

    19/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    19/67

    Setting mortar pads and liner plates

    Adjusting anchor bolts

    Setting and grouting box-out anchor bolts

    Mortar grouting and curing Welding washers and/or liner plates, as required by technical specifications and/or

    drawings

    Opening and re-closing manholes and/or handholes for cleaning and inspection

    Rust prevention during the construction work and timely removal of such rust and

    prevention materials, if any

    Cleaning equipment inside/outside as required

    Application of necessary anti-seizing solvent/compound/paste for bolts and nuts

    Application of specified compound/paste to gaskets

    Application of touch-up paint

    Preparation and submission of inspection/test record as per inspection/test plan All other work, as required by the drawings, technical specifications and manufacturers

    instruction manual

    Site cleaning the work place

    7.2 Measurement method and unit of quantities

    7.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,

    size, electrical rating, weight, type of equipment and elevation/location of working places,etc.

    7.2.2 Measurement method and unit of quantities

    The quantities shall be measured by length (linear meter) or piece along the center line of

    net installed cable tray/rack/duct excluding any waste or allowance from the construction

    drawings.

    Any accessories, fittings, elbow, cross, tee, reducer, etc. and covers will not be separately

    measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    7.2.3 Progress Measurement method(to be decided later or refer to the Contractor s PMS)

    The quantities measured as per 7.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

  • 8/12/2019 2.3.1 Measurement Method for Electical

    20/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    20/67

    Completion of installation and alignment : 85 %

    Completion of installation of cable tray cover: 15 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    21/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    21/67

    8. Code E-08 : Rigid Steel Conduit with Accessories, Fittings and Boxes

    8.1 Definition

    This work item is defined as the installation works of rigid steel conduit in accordance with

    the drawings, technical specifications and manufacturers instruction manual at the Site,

    including unloading of the Contractor supplied materials at the Contractor designated

    locations, site transportation, hauling, rigging, cutting, threading, reaming, bending, fitting,

    assembling, setting, laying, bolting, welding if necessary, alignment and inspection.

    This work item shall also include, but not limited, the following ;

    Installation of accessories and fittings

    Installation of condulets and boxes with cover plate Installation of steel conduit with fittings

    Furnishing and installation of sealing compound

    Furnishing and installation of conduit marker

    Furnishing and installation of anchor bolt/bolt/nut/washer, if required

    Test and inspection as per the project specification and inspection procedure

    Furnishing and installation of field fabricated steel support material shall not be included

    in this work item, but shall be included in Code E-25.

    Excavation, concrete work and backfilling shall not be included in this work item, but shall

    be included in Code E-24.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, and

    installation locations

    Preparation of work plans and procedures and submission for the Contractors approval

    prior to starting the work (work procedure, construction method statement,methodology, inspection/test plan and procedure, etc.)

    Removal of existing obstacles to installation work and restoration work uponcompletion thereof. Reinforcement or protection work for existing facilities, as required

    by the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary

    Removal of reinforcing or protection materials used for the transportation or installation

    of equipment, as necessary

    The following works related to the installation of the work item on concrete

    foundation :

    Checking anchor bolts and foundation with respect to location, size, level, etc.

  • 8/12/2019 2.3.1 Measurement Method for Electical

    22/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    22/67

    Chipping concrete foundation

    Setting mortar pads and liner plates

    Adjusting anchor bolts

    Setting and grouting box-out anchor bolts Mortar grouting and curing

    Welding washers and/or liner plates, as required by technical specifications and/ordrawings

    Opening and re-closing manholes and/or handholes for cleaning and inspection

    Rust prevention during the construction work and timely removal of such rust andprevention materials, if any

    Cleaning equipment inside/outside as required

    Application of necessary anti-seizing solvent/compound/paste for bolts and nuts

    Application of touch-up paint

    Preparation and submission of inspection/test record as per inspection/test plan All other work, as required by the drawings, technical specifications and manufacturers

    instruction manual

    Site cleaning the work place

    8.2 Measurement method and unit of quantities

    8.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,

    size, electrical rating, weight, type of equipment and elevation/location of working places,etc.

    8.2.2 Measurement method and unit of quantities

    The quantities shall be measured by length (linear meter) of net installed rigid steel conduit

    excluding any waste or allowance from the construction drawings.

    Any accessories, fittings, condulets and boxes will not be separately measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    8.2.3 Progress Measurement method(to be decided later or refer to the Contractor s PMS)

    The quantities measured as per 8.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

    Completion of installation and alignment : 85 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    23/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    23/67

    Submission of inspection record : 15 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    24/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    24/67

    9. Code E-09 : Flexible Conduit with Accessories, Fittings and Boxes

    9.1 Definition

    This work item is defined as the installation works of flexible conduit in accordance with

    the drawings, technical specifications and manufacturers instruction manual at the Site,

    including unloading of the Contractor supplied materials at the Contractor designated

    locations, site transportation, hauling, rigging, cutting, threading, reaming, bending, fitting,

    assembling, setting, laying, bolting, welding if necessary, alignment and inspection.

    This work item shall also include, but not limited, the following ;

    Installation of flexible conduit

    Installation of accessories and fittings Installation of condulets and boxes with cover plate

    Furnishing and installation of sealing compound

    Furnishing and installation of conduit marker, if required

    Furnishing and installation of anchor bolt/bolt/nut/washer, if required

    Installation and termination of grounding jumper

    Test and inspection as per the project specification and inspection procedure

    Furnishing and installation of field fabricated steel support material shall not be included

    in this work item, but shall be included in Code E-25.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, and

    installation locations

    Removal of existing obstacles to installation work and restoration work upon

    completion thereof. Reinforcement or protection work for existing facilities, as required

    by the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary Removal of reinforcing or protection materials used for the transportation or installation

    of equipment, as necessary

    Welding washers and/or liner plates, as required by technical specifications and/ordrawings

    Opening and re-closing manholes and/or handholes for cleaning and inspection

    Rust prevention during the construction work and timely removal of such rust andprevention materials, if any

    Cleaning equipment inside/outside as required

    Application of necessary anti-seizing solvent/compound/paste for bolts and nuts

    Application of touch-up paint

  • 8/12/2019 2.3.1 Measurement Method for Electical

    25/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    25/67

    Preparation and submission of inspection/test record as per inspection/test plan

    All other work, as required by the drawings, technical specifications and manufacturersinstruction manual

    Site cleaning the work place

    9.2 Measurement method and unit of quantities

    9.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,

    size, electrical rating, weight, insulation, type of equipment and elevation/location of

    working places, etc.

    9.2.2 Measurement method and unit of quantities

    The quantities shall be measured by length (linear meter) of net installed flexible conduit

    excluding any waste or allowance from the construction drawings.

    Any accessories, fittings, condulets and boxes will not be separately measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    9.2.3 Progress Measurement method(to be decided later or refer to the Contractor s PMS)

    The quantities measured as per 9.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

    Completion of installation and alignment : 100 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    26/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    26/67

    10. Code E-10 : PVC Conduit with Accessories, Fittings and Boxes

    10.1 Definition

    This work item is defined as the installation works of PVC conduit in accordance with the

    drawings, technical specifications and manufacturers instruction manual at the Site,

    including unloading of the Contractor supplied materials at the Contractor designated

    locations, site transportation, hauling, rigging, cutting, reaming, bending, fitting,

    assembling, setting, laying, bolting, alignment and inspection.

    This work item shall also include, but not limited, the following ;

    Installation of PVC conduit

    Installation of accessories and fittings Furnishing and installation of sealing compound

    Furnishing and installation of conduit marker, if required

    Furnishing and installation of anchor bolt/bolt/nut/washer, if required

    Test and inspection as per the project specification and inspection procedure

    Furnishing and installation of field fabricated steel support material shall not be included

    in this work item, but shall be included in Code E-25.

    Excavation, concrete work and backfilling shall not be included in this work item, but shall

    be included in Code E-24.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations

    Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,

    methodology, inspection/test plan and procedure, etc.) Removal of existing obstacles to installation work and restoration work upon

    completion thereof. Reinforcement or protection work for existing facilities, as required

    by the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary

    Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary

    The following works related to the installation of the work item on concretefoundation :

    Checking anchor bolts and foundation with respect to location, size, level, etc.

    Chipping concrete foundation

  • 8/12/2019 2.3.1 Measurement Method for Electical

    27/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    27/67

    Setting mortar pads and liner plates

    Adjusting anchor bolts

    Setting and grouting box-out anchor bolts

    Mortar grouting and curing Welding washers and/or liner plates, as required by technical specifications and/or

    drawings

    Opening and re-closing manholes and/or handholes for cleaning and inspection

    Cleaning equipment inside/outside as required

    Application of necessary anti-seizing solvent/compound/paste for bolts and nuts

    Preparation and submission of inspection/test record as per inspection/test plan

    All other work, as required by the drawings, technical specifications and manufacturersinstruction manual

    Site cleaning the work place

    10.2 Measurement method and unit of quantities

    10.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,

    size, electrical rating, weight, depth of burial, type of equipment and elevation/location of

    working places, etc.

    10.2.2 Measurement method and unit of quantities

    The quantities shall be measured by length (linear meter) of net installed PVC conduit

    excluding any waste or allowance from the construction drawings.

    Any accessories, fittings and boxes will not be separately measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    10.2.3 Progress Measurement method(to be decided later or refer to the Contractor s PMS)

    The quantities measured as per 10.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

    Completion of installation and alignment : 90 %

    Submission of inspection record : 10 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    28/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    28/67

    11. Code E-11 : 3.6/6/11KV Cable

    11.1 Definition

    This work item is defined as the installation works of 3.6/6/11KV power cable in

    accordance with the drawings, technical specifications and manufacturers instruction

    manual at the Site, including unloading of the Contractor supplied materials at the

    Contractor designated locations, site transportation, hauling, rigging, pulling, laying,

    arrangement, cutting, inspection, test, pre-commissioning and assistance for

    commissioning/start-up and operational test.

    This work item shall also include, but not limited, the following ;

    Arrangement of cables Protection of installed cables from damage

    Furnishing and installation of cable marker

    Furnishing and application of cable pulling compound

    Furnishing and installation of electrical tapes

    Furnishing and installation of bolt/nut/washer, if required

    Test and inspection as per the project specification and inspection procedure

    Termination and splicing of 3.6/6/11KV cable shall not be included in this work item, but

    shall be included in Code E-12.

    Excavation, concrete work and backfilling shall not be included in this work item, but shall

    be included in Code E-24.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations

    Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,

    methodology, inspection/test plan and procedure, etc.)

    Removal of existing obstacles to installation work and restoration work uponcompletion thereof. Reinforcement or protection work for existing facilities, as required

    by the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary

    Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary

    The following works related to the installation of the work item on concrete

    foundation :

  • 8/12/2019 2.3.1 Measurement Method for Electical

    29/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    29/67

    Checking anchor bolts and foundation with respect to location, size, level, etc.

    Chipping concrete foundation

    Setting mortar pads and liner plates

    Adjusting anchor bolts Setting and grouting box-out anchor bolts

    Mortar grouting and curing

    Welding washers and/or liner plates, as required by technical specifications and/ordrawings

    Opening and re-closing manholes and/or handholes for cleaning and inspection

    Rust prevention during the construction work and timely removal of such rust andprevention materials, if any

    Cleaning equipment inside/outside as required

    Application of necessary anti-seizing solvent/compound/paste for bolts and nuts

    Preparation and submission of inspection/test record as per inspection/test plan All other work, as required by the drawings, technical specifications and manufacturers

    instruction manual

    Site cleaning the work place

    11.2 Measurement method and unit of quantities

    11.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,

    size, electrical rating, weight, depth of burial, type of insulation, type of equipment andelevation/location of working places, etc.

    11.2.2 Measurement method and unit of quantities

    The quantities shall be measured by length (linear meter) of net installed cable excluding

    any waste or allowance from the construction drawings.

    Any accessories and fittings will not be separately measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    11.2.3 Progress Measurement method(to be decided later or refer to the Contractors PMS)

    The quantities measured as per 11.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

    Completion of installation and alignment : 80 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    30/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    30/67

    Submission of inspection/test record : 10 %

    Completion of energization : 10 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    31/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    31/67

    12. Code E-12 : 3.6/6/8.7/15KV Cable Termination and Splicing Kit

    12.1 Definition

    This work item is defined as the installation works of termination and splicing kits for

    1.8/3/6/10KV power cable in accordance with the drawings, technical specifications and

    manufacturers instruction manual at the Site, including unloading of the Contractor

    supplied materials at the Contractor designated locations, site transportation, hauling,

    cutting, stripping, compressing, fitting, bolting, laying, arrangement, inspection, test, pre-

    commissioning and assistance for commissioning/start-up and operational test.

    This work item shall also include, but not limited, the following ;

    Termination and Splicing of cable installed Furnishing and installation of electrical tapes

    Furnishing and installation of bolt/nut/washer, if required

    Furnishing and installation of warning tape and sign board

    Test and inspection as per the project specification and inspection procedure

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations

    Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,

    methodology, inspection/test plan and procedure, etc.)

    Removal of existing obstacles to installation work and restoration work uponcompletion thereof. Reinforcement or protection work for existing facilities, as required

    by the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary

    Removal of reinforcing or protection materials used for the transportation or installation

    of equipment, as necessary The following works related to the installation of the work item on concrete

    foundation :

    Checking anchor bolts and foundation with respect to location, size, level, etc.

    Chipping concrete foundation

    Setting mortar pads and liner plates

    Adjusting anchor bolts

    Setting and grouting box-out anchor bolts

    Mortar grouting and curing

    Welding washers and/or liner plates, as required by technical specifications and/or

    drawings

  • 8/12/2019 2.3.1 Measurement Method for Electical

    32/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    32/67

    Opening and re-closing manholes and/or handholes for cleaning and inspection

    Cleaning equipment inside/outside as required

    Preparation and submission of inspection/test record as per inspection/test plan

    All other work, as required by the drawings, technical specifications and manufacturersinstruction manual

    Site cleaning the work place

    12.2 Measurement method and unit of quantities

    12.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,

    size, electrical rating, weight, depth of burial, type of insulation, type of equipment and

    elevation/location of working places, etc.

    12.2.2 Measurement method and unit of quantities

    The quantities shall be measured by number of complete set of termination kit from the

    construction drawings and by number of complete set of splicing kit physically done at Site

    due to cable drum limitation.

    Any accessories and fittings will not be separately measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    12.2.3 Progress Measurement method(to be decided later or refer to the Contractor s PMS)

    The quantities measured as per 12.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

    Completion of installation and alignment : 80 % Submission of inspection/test record : 20%

  • 8/12/2019 2.3.1 Measurement Method for Electical

    33/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    33/67

    13. Code E-13 : 600V/1KV Power/Control/Instrument/FO/miscellaneous Cable

    13.1 Definition

    This work item is defined as the installation works of 600V/1KV power cable, control

    cable, telephone cable, F/A cable, CCTV cable, Access Control cable, Public

    Address/paging cable and miscellaneous cable in accordance with the drawings, technical

    specifications and manufacturers instruction manual at the Site, including unloading of the

    Contractor supplied materials at the Contractor designated locations, site transportation,

    hauling, rigging, pulling, laying, arrangement, cutting, stripping, compressing, fitting,

    Splicing and terminating, bolting, inspection, test, pre-commissioning and assistance for

    commissioning/start-up and operational test.

    This work item shall also include, but not limited, the following ;

    Arrangement of cables

    Termination and Splicing of cable installed

    Furnishing and installation of termination material such as terminal lug, wire connector,etc.

    Protection of installed cables from damage

    Furnishing and installation of cable tie

    Furnishing and installation of cable marker

    Furnishing and application of cable pulling compound

    Furnishing and application of duct sealing compound

    Furnishing and installation of electrical tapes

    Furnishing and installation of bolt/nut/washer, if required

    Test and inspection as per the project specification and inspection procedure

    Excavation, concrete work and backfilling shall not be included in this work item, but shall

    be included in Code E-24.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials Material transportation from/to the Contractors warehouse and laydown areas, and

    installation locations

    Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,

    methodology, inspection/test plan and procedure, etc.)

    Removal of existing obstacles to installation work and restoration work upon

    completion thereof. Reinforcement or protection work for existing facilities, as required

    by the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary

  • 8/12/2019 2.3.1 Measurement Method for Electical

    34/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    34/67

    Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary

    The following works related to the installation of the work item on concrete

    foundation : Checking anchor bolts and foundation with respect to location, size, level, etc.

    Chipping concrete foundation

    Setting mortar pads and liner plates

    Adjusting anchor bolts

    Setting and grouting box-out anchor bolts

    Mortar grouting and curing

    Welding washers and/or liner plates, as required by technical specifications and/ordrawings

    Opening and re-closing manholes and/or handholes for cleaning and inspection

    Rust prevention during the construction work and timely removal of such rust andprevention materials, if any

    Cleaning equipment inside/outside as required

    Application of necessary anti-seizing solvent/compound/paste for bolts and nuts

    Preparation and submission of inspection/test record as per inspection/test plan

    All other work, as required by the drawings, technical specifications and manufacturersinstruction manual

    Site cleaning the work place

    13.2 Measurement method and unit of quantities

    13.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,

    size, electrical rating, weight, depth of burial, type of insulation, type of equipment and

    elevation/location of working places, etc.

    13.2.2 Measurement method and unit of quantities

    The quantities shall be measured by length (linear meter) of net installed cable excluding

    any waste or allowance from the construction drawings.

    Any accessories, terminal lugs and fittings will not be separately measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    13.2.3 Progress Measurement method(to be decided later or refer to the Contractors PMS)

  • 8/12/2019 2.3.1 Measurement Method for Electical

    35/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    35/67

    The quantities measured as per 13.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

    Completion of installation and alignment : 80 %

    Submission of inspection/test record : 10 %

    Completion of pre-commissioning : 10 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    36/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    36/67

    14. Code E-14 : Lighting Fixture

    14.1 Definition

    This work item is defined as the installation works of lighting fixture in accordance with

    the drawings, technical specifications and manufacturers instruction manual at the Site,

    including unloading of the Contractor supplied materials at the Contractor designated

    locations, site transportation, hauling, rigging, fitting, setting, assembling, bolting, welding

    if necessary, alignment, inspection, test, pre-commissioning and assistance for

    commissioning/start-up and operational test.

    This work item shall also include, but not limited, the following ;

    Installation of ballast, lamp, diffuser, louver and mounting accessories Replacement of lamps

    Installation of pole

    Furnishing and installation of anchor bolt/nut/washer, if required

    Test and inspection as per the project specification and inspection procedure

    Furnishing and installation of field fabricated steel support material shall not be included in

    this work item, but shall be included in Code E-25.

    Excavation, concrete work and backfilling shall not be included in this work item, but shall

    be included in Code E-24.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations

    Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,

    methodology, inspection/test plan and procedure, etc.) Removal of existing obstacles to installation work and restoration work upon

    completion thereof. Reinforcement or protection work for existing facilities, as required

    by the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary

    Removal of reinforcing or protection materials used for the transportation or installation

    of equipment, as necessary

    The following works related to the installation of the work item on concrete

    foundation :

    Checking anchor bolts and foundation with respect to location, size, level, etc.

    Chipping concrete foundation

  • 8/12/2019 2.3.1 Measurement Method for Electical

    37/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    37/67

    Setting mortar pads and liner plates

    Adjusting anchor bolts

    Setting and grouting box-out anchor bolts

    Mortar grouting and curing Welding washers and/or liner plates, as required by technical specifications and/or

    drawings

    Opening and re-closing manholes and/or handholes for cleaning and inspection

    Rust prevention during the construction work and timely removal of such rust and

    prevention materials, if any

    Cleaning equipment inside/outside as required

    Application of necessary anti-seizing solvent/compound/paste for bolts and nuts

    Application of touch-up paint

    Preparation and submission of inspection/test record as per inspection/test plan

    All other work, as required by the drawings, technical specifications and manufacturersinstruction manual

    Site cleaning the work place

    14.2 Measurement method and unit of quantities

    14.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,

    size, electrical rating, weight, depth of burial, type of insulation, type of equipment and

    elevation/location of working places, etc.

    14.2.2 Measurement method and unit of quantities

    The quantities shall be measured by number of complete set of lighting fixture from the

    construction drawings.

    Any mounting accessories, poles, ballast, louver, diffuser and lamps will not be separately

    measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    14.2.3 Progress Measurement method(to be decided later or refer to the Contractors PMS)

    The quantities measured as per 14.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

    Completion of installation and alignment : 80 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    38/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    38/67

    Submission of inspection/test record : 10 %

    Completion of energization : 10 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    39/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    39/67

    15. Code E-15 : Wiring Device

    15.1 Definition

    This work item is defined as the installation works of receptacle, switch, welding

    receptacle, terminal box, cable gland and local control station in accordance with the

    drawings, technical specifications and manufacturers instruction manual at the Site,

    including unloading of the Contractor supplied materials at the Contractor designated

    locations, site transportation, hauling, fitting, setting, assembling, bolting, welding if

    necessary, alignment, inspection, test, pre-commissioning and assistance for

    commissioning/start-up and operational test.

    This work item shall also include, but not limited, the following ;

    Installation of pull box, outlet box, cover plate and mounting accessories

    Furnishing and installation of anchor bolt/nut/washer, if required

    Test and inspection as per the project specification and inspection procedure

    Furnishing and installation of field fabricated steel support material shall not be included in

    this work item, but shall be included in Code E-25.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, and

    installation locations

    Preparation of work plans and procedures and submission for the Contractors approval

    prior to starting the work (work procedure, construction method statement,

    methodology, inspection/test plan and procedure, etc.)

    Removal of existing obstacles to installation work and restoration work upon

    completion thereof. Reinforcement or protection work for existing facilities, as required

    by the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary Removal of reinforcing or protection materials used for the transportation or installation

    of equipment, as necessary

    The following works related to the installation of the work item on concrete

    foundation :

    Checking anchor bolts and foundation with respect to location, size, level, etc.

    Chipping concrete foundation

    Setting mortar pads and liner plates

    Adjusting anchor bolts

    Setting and grouting box-out anchor bolts

    Mortar grouting and curing

  • 8/12/2019 2.3.1 Measurement Method for Electical

    40/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    40/67

    Welding washers and/or liner plates, as required by technical specifications and/ordrawings

    Opening and re-closing manholes and/or handholes for cleaning and inspection

    Rust prevention during the construction work and timely removal of such rust andprevention materials, if any

    Cleaning equipment inside/outside as required

    Application of necessary anti-seizing solvent/compound/paste for bolts and nuts

    Application of touch-up paint

    Preparation and submission of inspection/test record as per inspection/test plan

    All other work, as required by the drawings, technical specifications and manufacturers

    instruction manual

    Site cleaning the work place

    15.2 Measurement method and unit of quantities

    15.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,

    size, electrical rating, weight, depth of burial, type of insulation, type of equipment and

    elevation/location of working places, etc.

    15.2.2 Measurement method and unit of quantities

    The quantities shall be measured by number of complete set of wiring device from the

    construction drawings.

    Any mounting accessories and cover plates will not be separately measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    15.2.3 Progress Measurement method(to be decided later or refer to the Contractor s PMS)

    The quantities measured as per 15.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

    Completion of installation and alignment : 90 %

    Submission of inspection/test record : 10 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    41/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    41/67

    16. Code E-16 : CCTV/Access Control System Equipment

    16.1 Definition

    This work item is defined as the installation works of CCTV/Access Control system

    equipment in accordance with the drawings, technical specifications and manufacturers

    instruction manual at the Site, including unloading of the Contractor supplied materials at

    the Contractor designated locations, site transportation, hauling, rigging, fitting, setting,

    assembling, bolting, welding if necessary, alignment, inspection, calibration, test, pre-

    commissioning and assistance for commissioning/start-up and operational test.

    This work item shall also include, but not limited, the following ;

    Installation of parts/components/supports shipped separately for transportation Installation of mounting accessories, boxes and bracket, etc.

    Installation and connection of vendor cable/wire, including supply of terminal lug ifrequired

    Furnishing and installation of anchor bolt/nut/washer, if required

    Test and inspection as per the project specification and inspection procedure

    Furnishing and installation of field fabricated steel support material shall not be included in

    this work item, but shall be included in Code E-25.

    Excavation, concrete work and backfilling shall not be included in this work item, but shall

    be included in Code E-24.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, and

    installation locations

    Preparation of work plans and procedures and submission for the Contractors approval

    prior to starting the work (work procedure, construction method statement,methodology, inspection/test plan and procedure, etc.)

    Removal of existing obstacles to installation work and restoration work uponcompletion thereof. Reinforcement or protection work for existing facilities, as required

    by the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary

    Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary

    The following works related to the installation of the work item on concretefoundation :

    Checking anchor bolts and foundation with respect to location, size, level, etc.

  • 8/12/2019 2.3.1 Measurement Method for Electical

    42/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    42/67

    Chipping concrete foundation

    Setting mortar pads and liner plates

    Adjusting anchor bolts

    Setting and grouting box-out anchor bolts Mortar grouting and curing

    Welding washers and/or liner plates, as required by technical specifications and/ordrawings

    Opening and re-closing manholes and/or handholes for cleaning and inspection

    Rust prevention during the construction work and timely removal of such rust andprevention materials, if any

    Cleaning equipment inside/outside as required

    Application of necessary anti-seizing solvent/compound/paste for bolts and nuts

    Application of touch-up paint

    Preparation and submission of inspection/test record as per inspection/test plan All other work, as required by the drawings, technical specifications and manufacturers

    instruction manual

    Site cleaning the work place

    16.2 Measurement method and unit of quantities

    16.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,

    size, electrical rating, weight, depth of burial, type of insulation, type of equipment andelevation/location of working places, etc.

    16.2.2 Measurement method and unit of quantities

    The quantities shall be measured by number of complete set of CCTV/Access Control

    system equipment from the construction drawings.

    Any boxes, mounting accessories and brackets will not be separately measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    16.2.3 Progress Measurement method(to be decided later or refer to the Contractors PMS)

    The quantities measured as per 16.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

    Completion of installation and alignment : 80 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    43/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    43/67

    Submission of inspection/test record : 10 %

    Completion of pre-commissioning : 10 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    44/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    44/67

    17. Code E-17 : Communication System Equipment

    17.1 Definition

    This work item is defined as the installation works of Public Address/ Paging/

    Telephone/Multi-Function/Radio system equipment in accordance with the drawings,

    technical specifications and manufacturers instruction manual at the Site, including

    unloading of the Contractor supplied materials at the Contractor designated locations, site

    transportation, hauling, rigging, fitting, setting, assembling, bolting, welding if necessary,

    alignment, inspection, calibration, test, pre-commissioning and assistance for

    commissioning/start-up and operational test.

    This work item shall also include, but not limited, the following ;

    Installation of parts/components/supports shipped separately for transportation

    Installation of mounting accessories, boxes and bracket, etc.

    Installation and connection of vendor cable/wire, including supply of terminal lug ifrequired

    Furnishing and installation of anchor bolt/nut/washer, if required

    Test and inspection as per the project specification and inspection procedure

    Furnishing and installation of field fabricated steel support material shall not be included in

    this work item, but shall be included in Code E-25.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations

    Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,

    methodology, inspection/test plan and procedure, etc.)

    Removal of existing obstacles to installation work and restoration work uponcompletion thereof. Reinforcement or protection work for existing facilities, as required

    by the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary

    Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary

    The following works related to the installation of the work item on concretefoundation :

    Checking anchor bolts and foundation with respect to location, size, level, etc.

    Chipping concrete foundation

    Setting mortar pads and liner plates

  • 8/12/2019 2.3.1 Measurement Method for Electical

    45/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    45/67

    Adjusting anchor bolts

    Setting and grouting box-out anchor bolts

    Mortar grouting and curing

    Welding washers and/or liner plates, as required by technical specifications and/ordrawings

    Opening and re-closing manholes and/or handholes for cleaning and inspection

    Rust prevention during the construction work and timely removal of such rust andprevention materials, if any

    Cleaning equipment inside/outside as required

    Application of necessary anti-seizing solvent/compound/paste for bolts and nuts

    Application of touch-up paint

    Preparation and submission of inspection/test record as per inspection/test plan

    All other work, as required by the drawings, technical specifications and manufacturers

    instruction manual Site cleaning the work place

    17.2 Measurement method and unit of quantities

    17.2.1 General

    The Subcontractor Prices shall not be adjusted for the differences in installation method,

    size, electrical rating, weight, depth of burial, type of insulation, type of equipment and

    elevation/location of working places, etc.

    17.2.2 Measurement method and unit of quantities

    The quantities shall be measured by number of complete set of Public

    Address/paging/Telephone/Multi Function/Radio system equipment from the construction

    drawings.

    Any boxes, mounting accessories and brackets will not be separately measured.

    Furnishing and installation of Scaffolding should not be measured separately, but deemed

    measured and included in the unit price of this work.

    No measurement shall be made for any rework.

    17.2.3 Progress Measurement method(to be decided later or refer to the Contractors PMS)

    The quantities measured as per 17.2.2 above shall be broken down into the following

    activities with the relevant factor for progress measurement and to calculate monthly

    progress payment thereof.

    Completion of installation and alignment : 80 %

    Submission of inspection/test record : 10 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    46/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    46/67

    Completion of pre-commissioning : 10 %

  • 8/12/2019 2.3.1 Measurement Method for Electical

    47/67

    Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument

    47/67

    18. Code E-18 : TEL/LAN System Equipment

    18.1 Definition

    This work item is defined as the installation works of TEL/LAN system equipment in

    accordance with the drawings, technical specifications and manufacturers instruction

    manual at the Site, including unloading of the Contractor supplied materials at the

    Contractor designated locations, site transportation, hauling, rigging, fitting, setting,

    assembling, bolting, welding if necessary, alignment, inspection, calibration, test, pre-

    commissioning and assistance for commissioning/start-up and operational test.

    This work item shall also include, but not limited, the following ;

    Installation of parts/components/supports shipped separately for transportation Installation of mounting accessories, boxes and bracket, etc.

    Installation and connection of vendor cable/wire, including supply of terminal lug ifrequired

    Furnishing and installation of anchor bolt/nut/washer, if required

    Test and inspection as per the project specification and inspection procedure

    Furnishing and installation of field fabricated steel support material shall not be included in

    this work item, but shall be included in Code E-25.

    Further details of this work item are listed below. But all other associated activities

    required until issuance of Provisional Turnover Certificate shall also be included in the

    scope of this work item.

    Receiving, storing and maintaining the Contractor supplied materials

    Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations

    Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,

    methodology, inspection/test plan and procedure, etc.)

    Removal of existing obstacles to installation work and restoration work upon

    completion thereof. Reinforcement or protection work for existing facilities, as requiredby the Contractor

    Preassembling work prior to the commencement of the installation work, as necessary

    Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary

    The following works related to the installation of the work item on concretefoundation :

    Checking anchor bolts and foundation with respect to location, size, level, etc.

    Chipping concrete foundation

    Setting mortar pads and liner