23.anderson go - non-conventional
TRANSCRIPT
7/30/2019 23.Anderson GO - Non-Conventional
http://slidepdf.com/reader/full/23anderson-go-non-conventional 1/12
NON-CONVENTIONAL SUBSTATION AND DISTRIBUTION SYSTEM FOR
RURAL ELECTRIFICATION
G. O. Anderson and K. YanevElectrical Engineering Department, University of Botswana
ABSTRACT
In rural areas the concentration of users of electrical
energy is low, and costs related to the deployment of a
conventional substation are prohibitive. As a result, in
many cases, a power utility will not be able to generate
an adequate return on the investment necessary to
bring a conventional distribution substation on line.
On the other hand, rural users are typically satisfied
with a lower quality service and are willing to suffer
some power outages if this means having access to
electric power at a reasonable price. Additionally, highvoltage transmission lines on their path from power
source to major urban centres typically transverse
many rural areas to which they do not supply
electricity. In order to address the drawbacks
associated with prohibitive costs of a conventional
substation, a relatively small non-conventional
substation which can be located close to or underneath
extra high voltage transmission lines is investigated.
These non-conventional substations tap directly into
the overhead transmission lines using tapping through
high voltage connectors and do not interrupt the flow
of power along the transmission line. A combination of Non-conventional substation and a single wire earth
return (SWER) could provide a cheaper application to
rural electrification. The cost effective nature of the
combination for rural electrification is investigated
and analysed.
KEY WORDS Non-conventional Substation, Distribution System, RuralElectrification
1. INTRODUCTION
1.1 ALTERNATE SOURCES OF POWER SUPPLYFOR RURAL ELECTRIFICATION
The consumption of primary sources of energy by sourcein Botswana is similar to those of other third worldcountries. Alternate sources of power supply can becategorized as follows:
• Grid electricity (mains)
• Solar power
• Wind Power
• Diesel Generators
• Tapping from High Voltage Lines
• Single wire earth return
Bullets 1,5 and 6 are considered in this paper.
1.1.1 GRID ELECTRICITY SUPPLY
In rural areas the concentration of users is low and costsrelated to deploying a conventional substation are prohibitive. As a result, in many cases a power utility willnot be able to generate an adequate return on the largeinvestment necessary to bring a conventional distributionsubstation on line. On the other hand, rural users are
typically satisfied with a lower quality of service and arewilling to suffer some power outages if this means theywill have access to electrical power at a reasonable price
[2]. Additionally, high voltage transmission lines ontheir path from power source to major urban centrestypically traverse many rural areas to which they do not
supply electricity. Distribution networks are connected tothe transmission portion of the system via transmission
lines and substations [3].
1.1.2 Non Conventional Substation
In order to address the drawbacks associated with prohibitive costs of a conventional substation, a relativelysmall non conventional substation which can be locatedclose to or underneath extra high voltage transmissionlines is investigated. These non-conventional substationstap directly into the over head transmission lines using
tapping through high voltage connectors [4,6].
1.1.3 Single Wire Earth Return (SWER)
SWER can help reduce the amount of capital expenditure
required when compared to the usual three phase power supply of grid electricity. The application of SWER isdependent on the distance from source of power to pointof connection for application, because voltage drop alongthe wire depends on the distance.
The research focuses on non-conventional substation and
single wire earth return distribution system with respect torural electrification. Solar technology application anddiesel plant use are available in rural areas of Botswana.Wind power is not applicable, because the wind speed istoo low for power generation.
2. RURAL LOAD
To electrify a rural area, it is necessary to estimate the possible loads in the area. Loads in the rural areas areclassified into three categories: household load, small
business load and rural telecoms network loads for service providers.
• Household load is approximately506W• Business Load is approximately 1046W
• Base Transceiver Station (BTS) for Cellular 1346W
7/30/2019 23.Anderson GO - Non-Conventional
http://slidepdf.com/reader/full/23anderson-go-non-conventional 2/12
3. NON-CONVENTIONAL SUBSTATION
The connections of the non-conventional substation are asindicated in section 1.1.2, and [4,6]. Figures 3.1 and 3.2show how the non conventional substation taps power
from a high voltage transmission line.
One drawback of the above non-conventional substationsis that they do not provide any redundancy in the case of
failure of one of the components of the substation or overload. But this draw back is not a serious concern for people in the rural remote villages of Botswana. Nonconventional substations can be implemented where thereare high voltage lines passing through the village only or
where the HV line passes not more than 60 km away from
the village to avoid voltage drop problems.
Figure 3.1: Non conventional substation tapping power between two steel towers [52]
Figure 3.2: non conventional substation tapping power across a steel tower
7/30/2019 23.Anderson GO - Non-Conventional
http://slidepdf.com/reader/full/23anderson-go-non-conventional 3/12
3.1. NON CONVENTIONAL SUBSTATION
MODEL, DESIGN AND OPERATION
Non conventional substations use capacitive dividers totap power from high voltage lines for the purpose of meeting the electric power needs of rural and remote
areas. The principles of capacitive – couplingtransformers are not new, as they have long been used
both by manufacturers of the capacitor voltagetransformers required by electrical utilities and by someutilities for feeding small loads [5]. Figure 3.3 shows thecircuit model of a capacitive substation and figure 3.4shows the Thevenin equivalent circuit of the voltagedivider (C1 and C2) seen from the load side. The Thevenin
equivalent voltage divider thV is given by:
inth V C C
C V ×
+=
21
1 3.1
The impedance is given by capacitors in parallel as shown
in figure 3.3 i.e.21 C C C th += . The FSC block in figure
3.3 represents the Ferro resonance suppression (FSC)circuit.
This circuit is important since Ferro resonance and over voltage transients problems can occur in this substationduring different conditions. The FSC comprises a
capacitor 3C , an inductor 1 L connected in parallel and a
damping resistor R connected in series as shown on
figure 3.3. Values of capacitor 3C and inductance 1 L are
calculated so that
[ ] 12
2=
LC f π , where
f is frequency
of power signal [5]. The value of R is calculated so that
C L /3C
L R ⎟
⎠
⎞⎜⎝
⎛ <<
3
2, whereby dampening of
resonance is obtained [6].Tr is the fixed turn ratiodistribution transformer and is connected to the AC loadsvia the FSC.
Figure 3.3: Capacitive divider substation
Figure 3.4: Thevenin’s equivalent circuit of the voltage divider
The inductor L in figure 3.4 is added in series to thecapacitive voltage divider to provide reactance that
cancels the Thevenin reactance thC at 50 Hz. The
regulation is done by adjusting 1C , 2C and L so they
satisfy the equation below:
12 = LCw 3.2
Where 502π =w rad/seconds
Since the impedance is zero at 50 Hz, the output voltage
2V remains equal and in phase with ( thV ), which in turn
is proportional to and in phase with inV where the load
can be resistive, capacitive or inductive.
When the capacitive – coupling technique is used as asubstation feeding remote loads or for ruralelectrification, it normally includes distribution
transformers installed on the outgoing feeders [4]. Theother methods of capacitive divider which do not connect
directly to the HV line use the shield wire. The shieldwire runs horizontally to the phase conductors of a highvoltage transmission line and terminates to ground at agiven substation. In this particular application the shield
wire runs from the steel tower insulator to the substationwhere it terminates to ground. One of these methods wasfirst studied by Leigh Stubbs of South Africa and isreferred to as the Isolated shield wire – passive method. This technology is cost effective when compared withmore conventional electromagnetic coupling systems, e.g.
high voltage power transformers [7]. In Botswana nonconventional substations have never been tried. Thecapacitive voltage divider substation has never been used
by Botswana Power Corporation (BPC) for ruralelectrification.
3.2 SINGLE WIRE EARTH RETURN SYSTEM
Single Wire Earth Return (SWER) is a single-wiretransmission line for supplying single-phase electrical power to rural sparsely populated areas. SWER systemsare mainly used in rural electrification but can also beused in larger isolated loads such as water pumping.
3.2.1 SWER System Description
The system is as shown on figure 3.5
7/30/2019 23.Anderson GO - Non-Conventional
http://slidepdf.com/reader/full/23anderson-go-non-conventional 4/12
Figure 3.5: SWER system diagram
The SWER system has the following major components:
isolator transformer, distribution line, distributiontransformer and earth system. The villages which useSWER system must have soil resistivities that are suitablefor SWER system earthing. SWER technology has been
applied in many countries and all specifications areknown.
4. CASE STUDY
The costs of using conventional and non conventionalsubstations for tapping power from high voltagetransmission lines was evaluated using the villages of Hatsalatladi and Boatlaname. The costs of Single Wire
Earth Return system versus three phase systems were alsoevaluated using the same rural villages.
The rural villages of Hatsalatladi and Boatlaname were
chosen because of the following reasons:• High Volltage transmission lines traverse
these villages
• The two villages are not electrified
Loadflow studies were carried out to determine the ability
of the system components to transfer energy fromgeneration sources to load without overloading the power components.
4.1 CASE STUDY: TAPPING POWER FROM HIGH
VOLTAGE TRANSMISSION LINES
Cost implications of building conventional and non – conventional 66/11 KV substations between the ruralvillages of Boatlaname and Hatsalatladi wereinvestigated. The villages of Boatlaname and Hatsalatladiare located in the Kweneng district and are approximately60 km apart. A line of 66 KV passes through these
villages but they are not electrified. These villages, eachhas a primary school, kgotla, clinic, bar, shop and someresidential houses. The substation proposed is located between the two villages with two 11 KV feeders, one for each village.
Case 1
4.1.1 Design of Non conventional substation atHatsalatladi and Boatlaname
The non conventional substation is relatively small in
terms of size and can be close to or underneath extra highvoltage transmission lines. A single line diagram of a nonconventional substation is shown on figures 4.1. Since thedistribution substation is used to distribute power to two
villages, a bus bar and tie bar shall be used with theassociated autoreclosers and knife links. Data for the
different system components was collected fromBotswana Power Corporation. All the prices for differentsystem components were collected from localmanufacturers and suppliers. At these villages the HV line
present is 66KV
Capacitors are chosen as follows C 1 = 0.98 µF, C 2 = 1.62µF, L =? Capacitors are chosen in such a way that C 1 is
smaller than C 2 by a factor that can give the desiredvoltage level at the output.
Therefore the Thevenin equivalent voltage divider Vth isgiven by:
inth V C C
C V ⎥
⎦
⎤⎢⎣
⎡
+=
21
1= kv66
62.198.0
98.0⎥⎦
⎤⎢⎣
⎡
+ 4.1
= 24.88kv ≈ 25kvAnd the series inductance L is given by:
2
1
Cw L = , where w = 2π50 rad/sec
C = C1 + C2
= 0.98 + 1.62= 2.6 µF
Therefore( )26 502106.2
1
π ××=
− L = 3.897 H
For designing the desired ferroresonance suppressioncircuit (FSC) the following points are considered:The capacitor C 3 is connected in parallel to the inductor
L1 and both are connected in series with a dampingresistor Rd
C f = C 1 + C 2= 0.98 +1.62 =2.6µF
And( )
f
f C f
L2
2
1
π
≤
Therefore, H L f 897.3≤ The damping resistor Rd should be in the range of thesystem rated load.
7/30/2019 23.Anderson GO - Non-Conventional
http://slidepdf.com/reader/full/23anderson-go-non-conventional 5/12
Figure 4.1: Non – Conventional 66 / 11 KV Substation single line diagram
Case 2
4.1.2 Design of Conventional substation at
Hatsalatladi and Boatlaname
The conventional substation is a fully flashed substationthat terminates the transmission line and as a result
maintains a high level of service. A single line diagram of the conventional substation is shown in figure 4.2.
The conventional substation has got back-up such that
when one component of the substation fails the customer still gets power via other system components. The cost breakdown covers planning, designing and installation.
Figure 4.2: 66 / 11 KV conventional substation single line diagram.
7/30/2019 23.Anderson GO - Non-Conventional
http://slidepdf.com/reader/full/23anderson-go-non-conventional 6/12
4.1.3 Design of a Power Distribution System at
Hatsalatladi and Boatlaname
A case study was conducted at the rural villages of
Hatsalatladi and Boatlaname to determine the percentagesaving when using SWER system. A potential load wasestimated and the system was modelled using DigSilentsoftware to determine the system’s capability to transfer energy from the source to the load without overloading
transmission lines and other power system components.The life cycle cost of a SWER and a three phase systemwere evaluated. The following circuit components weremodelled using DigSilent power factory software. Figure4.3 represents a three phase system while figure 4.4
represents a SWER system for the villages of Hatsalatladi
and Boatlaname.
Figure 4.3 Design of a single-line diagram of a three-phase system for the villages of Hatsalatladi and Boatlaname.
Figure 4.4: Single line diagram for SWER system.
7/30/2019 23.Anderson GO - Non-Conventional
http://slidepdf.com/reader/full/23anderson-go-non-conventional 7/12
4.1.4 Design of a three phase system for Boatlaname
and Hatsalatladi
The single wire earth return (SWER) uses the 66/19.1 KVtransformer. And when power is reticulated in the villagessingle phase pole mounted transformers are used to step
down the voltage from 19.1 KV to 240 V.
4.2 LIFE CYCLE COSTING OF ENERGY
SYSTEMS
Doing a life-cycle cost analysis (LCC) gives the total costof the power system - including all expenses incurredover the life of the system. There are two reasons for carrying out a LCC analysis: 1) to compare different power options and 2) to determine the most cost-effective
system designs. The LCC analysis consists of finding the present worth of any expense expected to occur over thereasonable life of the system [11]. To be included in theLCC analysis, any item must be assigned a cost, eventhough there are considerations to which a monetary valueis not easily attached. A meaningful LCC comparison can
only be made if each system can perform the same work with the same reliability.
4.3 LCC CALCULATION
The life-cycle cost of a project can be calculated using theformula:
LCC = C + Mpw + E pw + R pw - S pw.[98] 4.7
Where the pw subscript indicates the present worth of each factor.
The capital cost (C) of a project includes the initial capitalexpense for equipment, the system design, engineering,and installation. This cost is always considered as a single
payment occurring in the initial year of the project,regardless of how the project is financed.
Maintenance (M) is the sum of all yearly scheduledoperation and maintenance (O&M) costs. O&M costsinclude such items as an operator's salary, inspections,insurance, property tax, and all scheduled maintenance.
The energy cost (E) of a system is the sum of the yearlyfuel cost if applicable. Energy cost is calculatedseparately from operation and maintenance costs, so thatdifferential fuel inflation rates may be used.
Replacement cost (R) is the sum of all repair andequipment replacement cost anticipated over the life of
the system. Normally, these costs occur in specific yearsand the entire cost is included in those years.
The salvage value (S) of a system is its net worth in thefinal year of the life-cycle period. It is common practiceto assign a salvage value of 20 percent of original cost for mechanical equipment that can be moved. This rate can
be modified depending on other factors such asobsolescence and condition of equipment.
Future sums of money must also be discounted because of the inherent risk of future events not occurring as planned. Several factors should be considered when the
period for an LCC analysis is chosen Comparison canonly be made if each system can perform the same work
with the same reliability.
5. RESULTS AND ANALYSIS OF GRID POWER
SOURCES
The villages of Hatsalatladi and Boatlaname were used asa case study. The life cycle costs of conventional and nonconventional methods of tapping power from high voltage
transmission lines and electrical power distribution usingthree phase and SWER systems are presented. The results
also cover DigSilent simulation for power distribution
using SWER and three phase systems. Load flow analysiswas carried out on a conventional substation, SWER andthree phase systems. Simulation results for conventionalsubstation are also presented.
5.1 RESULTS FOR CONVENTIONAL AND NON
CONVENTIONAL SUBSTATIONS
Load flow results of a conventional substation are shownin fig 5.1. Project life cycle costs for a conventionalsubstation are shown table 5.1. Load flow studies arecarried out to determine the active and reactive flows inthe lines, the voltage profiles at the buses and systemlosses. Lifecycle costs for non conventional substation are
shown on table 5.2.
The power system components are based on the proposeddesign from figure 4.2. The prices for differentcomponents were obtained from local manufacturers andsuppliers.
7/30/2019 23.Anderson GO - Non-Conventional
http://slidepdf.com/reader/full/23anderson-go-non-conventional 8/12
Table 5.1: Life cycle costs for a fully flashed conventional substation with redundancy
Item Item description QTY Unit cost
(BWP)
Total cost (
BWP )
Percent
Total
1 CAPITAL COSTS ( C )
66 kv disconnector switch - motorised 3 30,000 90,000
66 kv breaker 3 125,000 375,000
66 kv busbar 1 160,000 160,000
11 kv autorecloser 3 164,000 492,000
On load 11 kv isolators 3 22,500 67,500
Knife-links 2 5,800 11,600
11 KV busbar 1 10,000 10,000
11 kv tiebar 1 10,000 10,000
Civil works 1 400,000 400,000
earthing 1 175,000 175,000
66/11 kv, 5 MVA Transformer 2 4900,000 9,800,000
A) SUBTOTAL 11,591,100 80
2 OPERATION & MAINTENANCE ( Mpw )
Servicing of Transformer and switchgear 2 1,500,000 3,000,000
B) SUBTOTAL 3,000,000 21
3 REPLACEMENT (Rpw) (YEAR)
On load 11kv isolators ( 20 ) 3 22,500 67,500
66 KV breaker ( 20 ) 3 125,000 375,000
C) SUBTOTAL 442,500 3
4 SALVAGE (Spw) ( YEAR )
20% of original (20)
D) SUBTOTAL 695,466 4.8
TOTAL LIFE – CYCLE COSTS (C+Mpw+Rpw-Spw) 14,338,134 100
Table 5.2: Life cycle cost for a non conventional substation (capacitor divider substation)Item Item Description Qty Unit cost
(BWP)
Total cost (
BWP )
Percent
Total
1 CAPITAL COSTS ( C )
66 kv disconnector switch - motorised 1 30,000 30,000
66 kv breaker 1 125,000 125,000
11 KV busbar 1 10,000 10,000
11 kv autorecloser 3 164,000 492,000
On load 11 kv isolators 1 22,500 22,500
Knife-links 2 5,800 11,600
11 kv tiebar 1 10,000 10,000
Civil works 1 400,000 400,000
earthing 1 175,000 175,000
25/11 kv, 250 KVA Transformer 1 2900,000 2,900,000Capacitors C1 and C2 1 15,000 15,000
Inductor L 1 8,000 8,000
FSC 1 12,500 12,500
SUBTOTAL 4,176,100 75
2 OPERATION AND MAINTENANCE (Mpw)
Servicing of Transformer and switchgear
1 1,500,000 1,500,000
SUBTOTAL 1,500,000 27
3 REPLACEMENT (Rpw) (YEAR)
On load 11kv isolators ( 20 ) 1 22,500 22,500
66 KV breaker ( 20 ) 1 125,000 125,000
C) SUBTOTAL 147,500 2.6
4 SALVAGE (Spw) ( YEAR )
20% of original (20)
D) SUBTOTAL 250,566 4.5TOTAL LIFE – CYCLE COSTS ( C+Mpw+Rpw-Spw) 5,573,034 100
7/30/2019 23.Anderson GO - Non-Conventional
http://slidepdf.com/reader/full/23anderson-go-non-conventional 9/12
Figure 5.1: load flow results for three phase system for Boatlaname and Hatsalatladi
5.1.1 Discussion
It is noticed that when a non conventional substation isused the cost of construction is substantially reduced. Thisis attributed to the absence of back up in the nonconventional substation and only one transformer is
required for a non conventional substation. The absenceof 66 KV bus bar interconnecting the two transformersalso reduce the cost significantly.
Therefore non conventional substations can be used to provide robust power source in the rural areas of
Botswana and enhance rural telecommunications as theyare cost effective. The cost savings from the above casestudy is (14,338,134 – 5,573,034 = BWP 8,765,100). These substations are only applicable where there areextra HV or HV power lines traversing rural villages.
5.1.2 Results for Three Phase and SWER Systems.
Figure 5.1 shows load flow results for three phase systemwhile figure 5.2 shows load flow results for SWER
system. Life cycle costs for three phase system and
SWER system are shown on tables 5.3 and 5.4respectively.
The results from figure 5.2.show that voltage magnitudes,voltage phase angles and equipment setting are operating
within their limit for a given load profile.
7/30/2019 23.Anderson GO - Non-Conventional
http://slidepdf.com/reader/full/23anderson-go-non-conventional 10/12
Table 5.3: Life cycle cost for three phase system (prices obtained from local suppliers)
Item Item Description Qty Unt Cost (BWP) Total Cost
(BWP)
Percent
Total
1 CAPITAL COST (C)
Three Phase Power lines + Neutral line (80km) 4x80 8,000 2,560,000
66 kV disconnector switch - motorised 1 30,000 30,000
66 kV breaker 11 kV busbar
11
125,00010,000
125,00010,000
11kV autorecloser 3 164,000 492,000
On-load 11 kV isolator 1 22,500 22,500
Knife –links
11 kV tiebar
2
1
5,800
10,000
11,600
10,000
Civil works 1 400,000 400,000
Earthing 1 175,000 175,000
66/11kV, 400 kVA Transformer 1 2,900,000 2,900,000
A) SUBTOTAL 6,736,100 82.8
2 OPERATION AND MAINTENANCE (Mpw)
Servicing of Transformer and Switchgear 1 1,500,000 1,500,000
B) SUBTOTAL 1,500,000 18.4
3 REPLACEMENT (Rpw) (YEAR)
On load 11 kV isolators (20) 1 22,500 22,500
66 kV breaker (20) 1 125,000 125,000
C) SUBTOTAL 147,500 1.8
4 SALVAGE (Spw) (YEAR)
20% of original (20)
(D) SUBTOTAL 250,566 3.1
TOTAL LIFE CYCLE COSTS (C + Mpw + Rpw –Spw) 8,133,034 100
Figure 5.2: load flow results for SWER system
7/30/2019 23.Anderson GO - Non-Conventional
http://slidepdf.com/reader/full/23anderson-go-non-conventional 11/12
Table 5.4: Life cycle costs for SWER system (prices obtained from local suppliers)Item Item Description Qty Unit cost
(BWP)
Total cost (
BWP )
Percent
Total
1 CAPITAL COSTS ( C )
SWER line (long span using Magpie Conductor) 80km 12,000 960,000
Isolating Transformer:
Fuse links
400KVA transformer Earthing
Reclosers
Sectionalisers
Distribution transformers:10KVA transformers
Earthing
2
11
1
5
104
104
14,000
85,00014,000
28,000
8,000
7,500
4,000
28,000
85,000
14,00028,000
40,000
780,000
416,000
A) SUBTOTAL 2,351,000 82
2 OPERATION AND MAINTENANCE (Mpw)
Servicing of Transformer and switchgear
1 500,000 500,000
B) SUBTOTAL 500,000 17.5
3 REPLACEMENT (Rpw) (YEAR)
Fuse links ( 20 ) 1 14,000 14,000
Sectionalisers ( 20 ) 8 8,000 64,000
C) SUBTOTAL 147,500 5
4 SALVAGE (Spw) ( YEAR )20% of original (20)
D) SUBTOTAL 141,060 4.9
TOTAL LIFE – CYCLE COSTS ( C+Mpw+Rpw-Spw ) 2,857,440 100
5.1.3 Discussion
From figures 5.1 and 5.2 it can be seen that all the buses
are operating within their voltage limit. And also the phase angles are within tolerance for all the buses utilised
in this load flow analysis. The use of SWER system as arobust power source is viable in the rural areas of Botswana. The simulations show that SWER system can
provide enough power to the rural areas as three phasesystem. But the life cycle costs suggest that by using aSWER system power utilities and corporations can save
cost by almost 50% as can be seen in table 5.4.
6. CONCLUSION
In most of the rural areas of Botswana power sources arenot always available and this scenario has led to rural
dwellers in these areas being unable to accesstelecommunication and other electrical services. Thisresearch investigated different power sources for application in the rural areas of Botswana taking into
consideration the life cycle costs and the technologyefficiency of each power source.
High Voltage tapping is an emerging technology usingnon conventional methods e.g. (capacitor divider substation) for rural electrification. A capacitive voltagedivider substation was designed to service the ruralvillages of Hatsalatladi and Boatlaname. Another substation was designed using conventional methods for
the same villages and the life cycle costs of the twosubstations show that capacitive voltage divider substation is cheaper as indicated in table 6.1.
The life cycle costs conducted on the designed systemsshow that SWER system is more cost effective as
indicated in table 6.1. Therefore SWER system is a good
option for electrification of rural settlements, becauseonce implemented, it can cater for everyone in the villageincluding service providers and customers alike. The
price for individual connections will also be affordable asits life cycle costs are low when compared with three
phase system.
The life cycle costs for different power source alternatives
investigated are shown in table 6.1.
Table 6.1: life cycle cost for different preferred power sourcesPower source Type of technology Life cycle cost
(BWP)
Grid
Capacitor divider
substation
5,573,034
HV tapping
Conventional
substation
14,338,134
SWER 2,857,440Power distribution
Three phase
distribution
8,133,034
Where HV transmission lines traverse rural villages or
pass nearby, non conventional substations (Capacitor voltage divider substation) should be used to tap power
and a SWER system can be used to reticulate power insuch villages. Where there is no grid, PV systems could be considered as a reliable load alternate power source.
7. REFERENCES:
[1] Sarah E.A. Kabaija, sources of energy used in householdsin Botswana
[2] Anthony J. Pansini.: Guide to Electrical Power
Distribution Systems. Marcel Dekker/CRC Press, BocaRaton, FL, 6th edition, 2005
[3] Transmission & Distribution World, April 2001
7/30/2019 23.Anderson GO - Non-Conventional
http://slidepdf.com/reader/full/23anderson-go-non-conventional 12/12
[4] Ferracci, P.: Ferroresonance, Groupe Schneider: Cahier technique no. 190:www.schneiderelectric.com/en/pdf//ect190.pdf , pp. 1-28,
March 1998.
[5] Gish, W.B., Feero, W.E., and Greuel, S.,:Ferroresonance
and loading relationships for DSG installations, IEEE
Trans. On Power Delivery, Vol. 6, No.2, pp. 736-743,April 1991.
[6] Bolduc, L., Bouchard, b., and beaulieu, G.: Capacitor
divider substation, IEEE Trans. Power Delivery, Vol. 12 No. 3, pp. 1202-1209, July 1997.
[7] CSA Standard CAN3-C13.1-M79, Capacitor Voltage
Transformers, March 1979.
[8] DIgSILENT Power Factory Software: Software for the
simulation of power system dynamics, DigSilent GmbH:
http://www.digsilent.de/software/
[9] P. Wolfs, S. Senini, D Seyoun and A, Loveday: AProposal to Investigate the Problems of Three-Phase
Distribution Feeders Suppling Power to SWER Systems,AUPEC 2004 Proceedings, September 2004.
[10] R. Billinton and R.N. Allan: Reliability evaluation of SWER
power systems, Plenum Press, New York,1996.
[11] Environmental and Ecological Life Cycle Inventories.
ECLIPSE public results.http://www.eclipse-eu.org/pubres_guide.html .
Principal Author: Professor George O. Anderson is theFounding Dean of the
Faculty of Engineeringand Technology of the
University of Botswana,Immediate-Past Head of the Department of Electrical Engineering,Associate Editor of theInternational Journal of
Power and Energy Systems, Interim Chairman of theBotswana Section of the IEEE and Resource Person for evaluation of Research Projects in Power and EnergySystems for funding by the South African NationalResearch Foundation (NRF). Professor Anderson has
written two books and has to his credit more than hundred publications in international journals and internationalconference proceedings. Prof. Anderson's researchinterests are in the areas of Power System Stability, Power Systems Economics Power Quality and RenewableEnergy.
Co-Author: Kamen M. Yanev holds a M.Sc. degree inElectrical and Control Engineeringfrom the HIMEE, Sofia. He has been a University Lecturer since1974, teaching in different
Commonwealth Universities around
the world. At present he is a Senior Lecturer in Control andInstrumentation Engineering at theUniversity of Botswana. He hasmore than 75 publications in the
area of Control Engineering,Electronics and Instrumentation.
Presenter: Professor George O. Anderson