**24//6-*/4*()5 - excelencia global · 2019-03-20 · indian institute of quantity surveyors 2015...
TRANSCRIPT
IIQS ANNUAL INSIGHT - 2015
Indian Institute of Quantity Surveyors-IIQS
Indian Institute of Quantity Surveyors 2015 IIQS
3 IIQS - 2015 | 3 IIQS - 2015 |
Indian Institute of Quantity Surveyors 2015 IIQS
www.iiqsglobal.org
Indian Institute of Quantity Surveyors Indian Institute of Quantity Surveyors (IIQS) is a professional body of Quantity Surveyors and its members include the profes-sionals working in the field of Quantity Surveying, Cost management, Commercial Management, Contract Management, Prop-erty Development, Engineering and other related field. This professional body was formed in December 1998. Ever since its inception, regular monthly Continuing Professional Development events, seminars are convened for its members. It helped the members to grow academically as well as professionally.
Vision
To establish and maintain a high standard of professional compe-tence and integrity by limiting membership to persons who have passed the examinations prescribed by, or acceptable to, the Institute and who have satisfied the requirements of training, practical knowledge, experience and integrity prescribed by the Institute.
Mission
The Mission of the Institute is to ensure professional advancement of Engineering and Quantity Surveying Professionals in the Property Development and Construction Industry, so that they can contribute more effectively in the ongoing development in the construction sector Worldwide and Particularly in India, as well as to share their knowledge and experience with the fellow professionals.
Memberships Available
Student
MIIQS
CIIQS
FIIQS
It’s hard to believe that I am writing the editorial for the second issue of
IIQS Annual Insight. Initially, when the concept was being perceived to
have an Annual Magazine for IIQS, I thought this project was too big for
the team. However, once IIQS Annual Insight first issue was published,
it gave enormous motivation and zeal to all to continue this on an annual
basis with the spirit of ‘together we can’ and that is the “Motto” of IIQS
Annual Insight 2015.
“Rain Falls, because the clouds can no longer handle its weight” Likewise,
IIQS Annual Insight 2015 is like a heavy rain filled with inspiration,
experience and human knowledge. We all need an escape from our stressful
lives sometimes and to do so, we listen to music, read a book, watch a film
or look at some art. I believe IIQS Annual Rain makes you relaxed and
contended.
Similar to IIQS annual Insight 2013, this issue also brings you an impressive
line-up of articles, CPD workshop memories, members’ achievements and
latest happenings and news from IIQS Home. The highlight of this issue
is the informative articles, which is definitely going to inspire you all and
help to enhance your knowledge. The aspect of exploring and discovering
is not only confined to readers but also to the authors as well. Authors also
enhance their learning when they write, it multiplies their knowledge when
they share. It is the IIQS’s “share and gain” approach that makes it stand-
out strong in the industry.
With lots of pride and modesty, we will be unveiling IIQS Annual Insight
2015 at a splendid function ‘IIQS International Conference’ on 1st August
2015 at Bangalore. It would be a great task for the team to make this event
a memorable and wonderful one and I want to say “thank you” for their
enormous efforts. I convey my special thanks to the editorial team who has
worked tirelessly and creatively throughout this journey.
If you ask me how I’d define success for IIQS magazine, I would say
that if this magazine helps even one person overcome adverse professional
circumstances, it would be the success beyond measure.
We truly hope that our readers would enjoy our humble effort. We will
be immensely interested to know your views on the magazine so that we
continually strive to improvise in our journey towards excellence.
Thank you,
Sinimol Noushad
Sinimol NoushadBTech, MBA, FRICS, MIS, MIIQS
IIQS Magazine Chief Editor & UAE Publications Lead
Rain falls, because the clouds can no longer handle its weight” Likewise, IIQS Annual Insight 2015 is like a heavy rain filled with inspiration, experience and human knowledge.
Editor’s noteEditor’s note
Indian Institute of Quantity Surveyors 2015 IIQS
5 IIQS - 2015 | 4 | IIQS - 2015 5 IIQS - 2015 |
Indian Institute of Quantity Surveyors 2015 IIQS
Dutco Tennant and BCL have over three decades of market presence, empowered with an experienced and aggressive management and sales team. The Company remains as a premier solutions provider by consistently maintaining its edge as a leading UAE, Middle East and Nor th Africa supplier to the prestige buildings, oil & gas sectors, infrastructure, water & electricity, por ts & civil engineering sectors. The Company has successfully implemented an extensive range of major supply contracts to various government depar tments and private clients in the UAE and Middle East markets.
Dutco Tennant/BCL is a premium professional company offering an unparalleled variety and quality of products and services throughout its market segments.
PO Box 233Dubai, U.A.E.Tel : +9714 2220186Fax : +9714 2236193Email : [email protected]
Public WorksWater & ElectricityCivil ContractorsM & E ContractorsBuildingsTelecommunicationIndustry & HospitalityPorts & AirportsLandscapingLaboratoriesOil & GasPolice & MilitaryEducationMaritime
Index
MESSAGES...........................................................................................................(07-11)
VISION / MISSION /MOTTO...........................................................................................(13)
HISTORY.....................................................................................................................(15)
IIQS GLOBAL BOARD OF DIRECTORS............................................................................(17)
IIQS UAE MEMBER COUNCILS......................................................................................(18)
IIQS MEMBER COUNCILS INDIA AND QATAR............................................................(19-21)
OUR VISION FOR NEXT 5 YEARS....................................................................................(23)
CONTINUING PROFESSIONAL DEVELOPMENT (CPD).................................................(25-37)
IIQS WORkSHOP EVENTS........................................................................................(39-41)
ARTICLES..............................................................................................................(45-97)
NETWORkING JOB OPPORTUNITIES............................................................................(100)
GLOBAL RECOGNITION INTERNATIONAL.....................................................................(101)
MEMBERS ACHIEVEMENTS ........................................................................................(101)
TESTIMONIALS FROM IIQS GLOBAL MEMBERS.......................................................(104-105)
MAGAZINE AND EVENT COMMITTEE...........................................................................(106)
Index
Indian Institute of Quantity Surveyors 2015 IIQS
6 | IIQS - 2015
Indian Institute of Quantity Surveyors 2015 IIQS
6 | IIQS - 2015
Mr. Varughese Mathew FRICS, FCIOB, MCIArb, IIQS Director & Global President
MessagesMessages
Greetings and welcome to IIQS International Magazine for Year 2015.
The publication of an International Magazine by IIQS fills us with great happiness. It is indeed
a timely, much needed effort from the executive team and a tribute to all our members. With the
recognition received by us for IIQS Magazine “Insight” published in Year 2013, this edition of
IIQS International Magazine 2015 reflects more dynamic approach to cover the Property and
Construction industry through various opulent articles written by industry experts.
Since the inception, IIQS focused on member’s development through regular CPD seminars,
workshops, group study, setting core values and code of conduct. Our successful CPDs are
measurements and milestones of our success as we continue our efforts to achieve overall excellence
of Indian Institute of Quantity Surveyors.
Currently we are conducting a 3 month Competency Enhancement Programs (CEP) in Qatar
and Dubai focusing professional membership for members, this program produced significant
positive impact on the CEP preparation, and that we owe their success to the volunteers of Dubai
and Qatar MC.
We are proud that our members have truly embraced the importance of learning as part of their
life and attained many accolades from some of the best universities and institution around the
World.We know that our members succeed in their mission as they diligently enhance their skills
in par with the best in the world and have high ethical conduct.I would also encourage all the
members to continue engage with the CPD team in relevant Member Council. We need your ideas,
your feedback and your help to build the Institute to a World Class level.
In addition, we are delighted to share that we have made necessary arrangement for an
international Conference to be held in Bangalore on 1st August 2015. This conference will bring
together expert from India and abroad to present and debate various best practices and topic of
interest for property and construction industry.
We extend our warm greetings and best wishes to all the well-wishers, the advertisers for their
great support and thankful to the editorial and publication team for the release of this magazine
on time. The effort and commitment throughout the publication stage of this magazine was evident
from the directors and leadership of each MC.
This magazine will certainly set a benchmark and will help in enhancing the knowledge of
its members. With the commendable experience and contributions from all the members of the
institute we hope to excel in every endeavors of the institute.We once again thank all the individuals
who have selflessly contributed their time and effort to make this publication possible.
It is with great pleasure we release IIQS International Magazine 2015 to the Property and
Construction industry around the Globe.
All the best,
Varughese Mathew
7 IIQS - 2015 | 7 IIQS - 2015 |
The publication of an International Magazine by IIQS fills us with great happiness.
1. Elixir Gardens Elixir Garden is a Beautifully landscaped and Architecturally designed Housing Complex located at the town centre of Vennikulam. Affordable size Villas as per the choice of the buyer for construction, selected few plots for sale and ready to occupy villas are also available. 2. Elixir Grande A Residential Tower at Manakachira, Thiruvalla an excellent location. 2 Bed room and 3 bed room apartments with fabulously designed amenities. Reasonable price and affordable payment term.
www.elixircorporates.com Email: [email protected]
Enquiries and Booking, please contact Jacob: 0091 944 7096 485 Varughese: 00971 50 5862496
With excellent reputation in Mumbai & Kerala, Proudly presents 2 distinctive projects in Kerala
Indian Institute of Quantity Surveyors 2015 IIQS
9 IIQS - 2015 | 8 | IIQS - 2015 9 IIQS - 2015 | 8 | IIQS - 2015
Indian Institute of Quantity Surveyors 2015 IIQS
Mr. Anurag BhushanConsul General of India
Mr.T.P SeetharamAmbassador
MessagesMessages MessagesMessages
The Indian Institute of Quantity Sureyors (IIQS) provides an important platfrom to show and develop knowledge.
Indian engineers and Quantity Surveyors have played an important role in UAE’s development. All major and Iconic projects in this Country have some imprints of their minds and hands.
Indian Institute of Quantity Surveyors 2015 IIQS
11 IIQS - 2015 | 10 | IIQS - 2015 11 IIQS - 2015 | 10 | IIQS - 2015
Indian Institute of Quantity Surveyors 2015 IIQS
Message from the Chartered Institution of Civil Engineering Surveyors - UAE Region
On behalf of the CICES UAE Region, it is with great pleasure that I am able to congratulate the
members of the Indian Institute of Quantity surveyors (IIQS) on their second IIQS publication,
‘IIQS Insight 2015’. The IIQS has enough reasons to publish such a journal duly documenting
the year’s achievements, due to the sustainability of the membership, the effective and efficient
continuing professional development programme and the record success of the massive number of
IIQS members who gained professional affiliations with internationally-recognized institutions.
I am sure that you will agree with me that professional institutions promoting best practice are
vital to both the industry and their members. It is our duty to the industry we are part of to en-
sure that we are in prime professional condition to undertake the responsibilities we are entrusted
with. We must always remember that challenges are natural and we have to face the situation
positively, expecting innovative changes in the near future, particularly with the advent of 2020.
In short, we must be ready to instigate change rather than be changed. As pivotal industry
professionals, through Continuing Professional Development programmes, we develop the com-
petencies necessary to conduct our duties in exemplary fashion. To accomplish this mission, the
CICES - UAE Region is proud to state that we have associated with professional institutions of
the industry. The IIQS is one of the dynamic players among them.
Furthermore, we would like to mention that many IIQS members, including the ICES UAE
Secretary, have added their invaluable contributions to the growth and success of the CICES
- UAE Region, since the inception of the Region.The mutual cooperation between the IIQS
Membership and CICES - UAE Region must extend beyond the UAE and progress to rest of
the GCC countries, which are closely coordinated by the CICES - UAE Region.
We look forward to a continued professional association with the IIQS as a leader among con-
struction professional Institutions in the Arabian Gulf region and once again we wish you every
success on the IIQS journey towards professional excellence.
Dhammika T. GamageNDT(Civil Eng.), I Eng., ICIOB, AIQSSL, PQS, MCIArb, FIIESL, FACostE, FAIQS, FRICS, FInstCESChairman - Chartered Institution of Civil Engineering Surveyors - UAE Region
Mr. Girish KumarPresidentEmbassy of India Cultural CentreDoha - State of Qatar
MessagesMessages MessagesMessages
The IIQS has enough reasons to publish such a journal duly documenting the year’s achievements, due to the sustainability of the membership.
The IIQS has done and continues to do pioneering work in the field of skill developent for Indian Engineers.
Indian Institute of Quantity Surveyors 2015 IIQS
13 IIQS - 2015 | 12 | IIQS - 2015 13 IIQS - 2015 |
VisionTo establish and maintain a
high standard of professional
competence and integrity by
limiting membership to persons
who have passed the examinations
prescribed by, or acceptable to,
the Institute and who have satisfied
the requirements of training,
practical knowledge, experience
and integrity prescribed by the
Institute.
MissionThe Mission of the Institute is to
ensure professional advancement
of Engineering and Quantity
Surveying Professionals in the
Property Development and
Construction Industry, so that they
can contribute more effectively
in the ongoing development in
the construction sector Worldwide
and particularly in India, as well
as to share their knowledge
and experience with the fellow
professionals.
MottoLighted to Learn & Live
C
M
Y
CM
MY
CY
CMY
K
A5 Advert portrait 148.5x210mm.pdf 1 10/28/13 3:54 AM
Indian Institute of Quantity Surveyors 2015 IIQS
15 IIQS - 2015 | 15 IIQS - 2015 |
ADs
HistoryIndian Institute of Quantity Surveyors (IIQS) is a professional body of Quantity Surveyors and its members include the professionals working in the field of Quantity Surveying, Cost management, Commercial Management, Contract Management, Property Development, Engineering and other related field. This professional body was formed in December 1998.It is worth noting that year 2007 to 2011 were truly remarkable years and I trust that the progress we made during this period will be written in the history of our Institute.
In 2007, IIQS took giant step by implementing high ethical principles, bylaws and logo. IIQS logo has a burning candle, which signifies giving light to the world. Our Motto is “Lighted to Learn and Live”. It is the collective aim and desire of IIQS to change its members to a self-motivated team that will pride itself in doing things rightly and taking decisions based on strong ethical valuesIndian Institute of Quantity Surveyors (IIQS), incorporated under Section 25 of the Companies Act 1956 (No. 1 of 1956) in India on 14 October 2011 Indian Institute of Quantity Surveyors (IIQS) is associated with National Institute of Construction Management and Research (NICMAR) Hyderabad since 2011 Indian Institute of Quantity Surveyors (IIQS) is an Affiliate Body of Indian Business and Professional Council (IBPC), Sharjah since January 2012.Indian Institute of Quantity Surveyors (IIQS) stands affiliated with the Embassy of India – Indian Cultural Centre Doha Qatar since June 2013.
A Cooperation Agreement between Australian Institute of Quantity Surveyors (AIQS) and Indian Institute of Quantity Surveyors (IIQS) was signed in April 2013. The Affiliation / Agreement Identifies synergies and a non-exhaustive between organizations, provide Continuing Professional Development to members, exchange relevant knowledge and research and to promote in a collaborative fashion their respective mission. In association with Federation of Indian Chambers and Commerce and Industry (FICCI), Indian Institute of Quantity Surveyors (IIQS) successfully convened a series of One Day Colloquium (ODC) in three major cities (Bangalore, Mumbai and New Delhi) in India during July 2013.
On 20 Dec 2014, Indian Institute of Quantity Surveyors (IIQS) entered in to an agreement with MCI Middle East in UAE for the management of its professional seminars. IIQS Set out values / high ethical conduct to IIQS members is to ensure that IIQS Members actions contribute to create a better society.
Members of IIQS shall:1.Maintain Professional Integrity;2.Maintain confidentiality and avoid conflict of interest.3. Maintain Process and procedures without favoritism.4. Maintain proficiency and competence truthfully;5. Maintain minimum 20 CPD hours every Year
شــركة عرعر يوتيليتي )ش ذ م م(ARAR UTILITY CO. LLC
P.O.BOX:231740, DUBAI, UNITED ARAB EMIRATES. TEL.:04-2556809, FAX: 04-2556202,
E-MAIL: [email protected]. WEBSITE: araruty.com
ELECTRICAL Supply, installation, testing and commissioning of all kinds of HV, MV, LV and FOC cables upto 132 kV cable erection work.Supply, install, test and commissioning of 11 kV& 33 kV substation work.Installation of 132kV substation work.Testing & commissioning of substation work upto 132 kV.Supply and installation of street lighting and public lighting.MEP works.
INFRASTRUCTUREWaterline pipe laying works and associated structural and shutdown works.Pumping station mechanical, electrical, instrumentation and pipe line works.Sewerage pipe laying and manhole works.Supply and installation of package substation.Shop drawing preparation and approval from various departments.N.O.C application procedures and follow ups and approval.Supply of skilled manpower.
A RELIABLE AND RESPONSIBLE
Indian Institute of Quantity Surveyors 2015 IIQS
17 IIQS - 2015 | 17 IIQS - 2015 |
ADs
IIQS GLOBALBOARD OF DIRECTORS
Varughese MathewLLM, FRICS, FCIOB, MCIArb
Director & President
Jacob JobyB.E (Civil), MBA, CCE
Director & Global Executive Director
Franklin JosephB.E.(Civil), MRICS, MIS, ICIOB
Director & Global General Secretary
KasiViswanathanB.E., LLM, MRICS, MIE, CCE, MIS Director & Global Governance
Committee Chair
Basavaraj BethB.E.(Civil), AIQS(Affil), CCE, ACIArb
Director & Global EventManagement Chair
Rama Rao KilariA.M.I.E(Civil), MRICS
Board Member & IT Administrator
Hirekar Director & Global Audit
Committee Vice Chair
E.V. Johnson NeilLLM, MRICS, MIS, FCIArbDirector & Vice President
Syed AslamB.E. (Civil), MinstCES
Director & Global AuditCommittee Chair
Paul BankalaB.E.(Civil), M.Sc., MRICS, ICIOB
Director & Global ProfessionalDevelopment Vice Chair
Sajeeth SidharthanB.E., MRICS, ACIArb, MSOE
Director & Global AwardingCommittee Chair
Naveen KumarDCE, CCE, MRICS, ACIArb
Director & Global MembershipCommittee Chair
Pavan Kumar MamidiB.E. Civil
Board Member & Treasurer
Ganesan GB.E.(Civil), M.Sc (QS), MRICS, MIS Director & Global Governance
Committee Vice Chair
ENGINEERING PROFESSIONALISED FOR SUSTAINABLE FUTURE
DRAINAGE SYSTEMS | ELECTROMECHANICAL | INFRASTRUCTURE GREEN ENERGY SYSTEMS | FACILITIES MANAGEMENT | MAINTENANCE SERVICES
P.O Box No - 36995,| Suite No - 2309 | SIT Tower, Dubai Silicon OasisDubai - UAE
T +971 4 392 5848 F +971 4 392 [email protected] www.amieton.com
ACCURATE SURVEYP.o. Box No. 47452, Sharjah Tel: +971 6 5341884 , Fax: +971 6 5428981Email: [email protected]
www.landmarksurveyuae.com
www.accuratesurvey.ae
LAND MARK SURVEYP.o. Box No. 91063, Abu Dhabi.Tel: +971 2 5548949, Fax: +971 2 5548954Email: [email protected]
LAND, ONSHORE, OFFSHORE AND OIL & GAS FIELD SURVEY
AN ISO 9001 : 2008 CERTIFIED COMPANY
For Complete Civil Engineering Survey Solutions
Dubai & Ajman Uited Arab Emirates
CALL US - +971 52 692 03 62
Fax No. +971 4 255 45 60Email Id: [email protected]
Indian Institute of Quantity Surveyors 2015 IIQS
19 IIQS - 2015 | 18 | IIQS - 2015 19 IIQS - 2015 | 18 | IIQS - 2015
RAKESH PERUMPILLYLLM,FRICS,FCIArb,FAIQS,MIIQS
CHAIRMAN
SOBHA RANIMRICS, MAIQS,ICIOB ,MIIQS
CHAIR PERSON
AVINASH GAIKWADB.E, PG Dip Surveying, MRICS,
MCIArb,MIIQS,Civil Commercial MediatorVICE CHAIRMAN
ASHOKVICE CHAIRMAN
PAUL BANKALAMSc, MRICS, ICIOB,MIIQS
IIQS DIRECTOR & DOHA MC REPRESENTATIVE
SYED ASLAMB.E. (Civil), MInstCES, MIIQS
IIQS DIRECTOR & BANGALORE MC REPRESENTATIVE
Dr. BINU VARGHESEPhD, MRICS, MIIQS
MC ADVISOR
JACOB JOBY B.E (Civil), MBA, CCE
IIQS DIRECTOR & BANGALORE MC REPRESENTATIVE
VIJAY LACHYAN M.E, FRICS, FCIArb,MIIQS
GENERAL SECRETARY
UMESH RAMAKRISNAN RAOGENERAL SECRETARY
KIRAN KUMAR P. B.E, MIIQS
TREASURER & MEMBERSHIP MANAGER
GANGADHAR HSTREASURER MANAGER
RAJANI RAJENDRANB.E, MRICS,MIIQSCPD EXECUTIVE
ULLAS KANAGALWORKSHOPS COMMUNCATION
MOHD.SHARIFB.E, MIIQS
FINANCIAL AUDITOR
MAHESH MVMEMBERSHIP DRIVE
MOHD.HANEEFA B.E, MIIQS
MEMBERSHIP SUPPORT
HARISH BNCOMMUNICATIONS - MEMBERSHIP
DRIVE
RISHI.P.S B.E, MIIQS
IT WEB LEAD
SREEROOP M.K.IT WEB LEAD
GURU.S.IYERB.E, MRICS,MIS, MIIQS,ACIArb
GOVERNANCE
IIQS - UAE MEMBER COUNCILORGANIZATION CHART (Year 2014-15)
IIQS - DOHA, QATAR MEMBER COUNCIL: ORGANIZATION CHART (Year 2014-15)
IIQS - BANGALORE MEMBER COUNCILORGANIZATION CHART (Year 2014-15)
SAJEETH SIDHARTHANB.E, MRICS, ACIArb, MSOE, MIIQS
CHAIRMAN
DHARMENDAR PARDASANIMSc (QS), FRICS, FAIQS, MCIArb, MCIOB, MIIQS
VICE CHAIRMAN
E V JOHNSON NEILLLM, MRICS, MIS, FCIArb, MIIQS
VICE CHAIRMAN
PAUL BANKALAMSc, MRICS, ICIOB,MIIQS
GENERAL SECRETARY
PAVAN KUMAR MAMIDIB.E, MIIQS
TREASURER
FRANKLIN G. JOSEPHB.E., MRICS, MIS, ICIOB, MIIQS
SPORTS & RECREATION
GANESH KUMAR G.B.E., MBA, M.Sc, L.L.M, FRICS,
FCIArb, FAIQS, MIIQS IIQS APC WORKSHOP
KALPESH SANGANIB.E., M.Sc., LLM,
FRICS, FCIArb, FAIQS, MIIQSIIQS APC WORKSHOP
GOVINDARAJU RATHODM.Tech., MRICS, MBA, MIIQS
SPORTS & RECREATION
VISWANATH C.B.Tech, MBA , MIIQS
SPORTS & RECREATION
AJITH PHILIPB.E., PG Dip. M.C.M., CCE, MIIQS
SPORTS & RECREATION
PARAG SUBHASH D.M.Sc. Q S, PGDQS, BE, MIIQS
SPORTS & RECREATION
Prasanna KumariBTech, MBA, MIIQS
IIQS APC WORKSHOP
PARIMELAZHAGANSPORTS & RECREATION
LALITHA JAYAKUMARSPORTS & RECREATION
SINIMOL NOUSHADB.Tech., MBA, FRICS, MIS, MIIQS
NEWS LETTERS / MAGAZINE
RITU SUBODH DASB.Tech Civil, PG Dip. Mgmt., MIIQS
NEWS LETTERS / MAGAZINE
BINU C. NINANNEWS LETTERS / MAGAZINE
ARULRAJ DEVARAJREGIONAL
REPRESENTATIVE (KSA)
MAHESH BUTANIMSc, MIIQS
REGIONAL REPRESENTATIVE (AUH)
MICHELLE GODHINOMEMBERSHIP / ACCOUNT
MANAGER
SACHITH SURESHMEMBERSHIP MANAGER
Member Council 2015Member Council For UAE, Qatar and India are developed and each member council is committed to develop the QS Profession and ensure that members attain professional standards of the global standards with the support of IIQS activities
Indian Institute of Quantity Surveyors 2015 IIQS
21 IIQS - 2015 | 20 | IIQS - 2015 21 IIQS - 2015 | 20 | IIQS - 2015
PROF. ER. BONNIGA RAVINDER B.E, M.TECH, MBA , M.PHIL, PGDQS, M.I.E, MIIQS
CHAIRMAN
TBACHAIRMAN
GOVINDARAJU RATHODM.TECH., MRICS, MBA, MIIQS
CHAIRMAN
M. KUMARESH MURTHYCHAIRMAN
MULLA JAVED HUSSAINBE, PGDQS, MBA, MIIQS
VICE CHAIRMAN
SANJEEV AGARWALVICE CHAIRMAN
SALEEM MERCHANT VICE CHAIRMAN
TBAVICE CHAIRMAN
PAUL BANKALAMSc, MRICS, ICIOB,MIIQS
IIQS DIRECTOR & HYDERABAD MC REPRESENTATIVE
NAVEEN GOELDCE, CCE, MRICS, ACIAR, MIIQSIIQS DIRECTOR & MUMBAI MC
REPRESENTATIVE
FRANKLIN G. JOSEPHB.E.(CIVIL), MRICS, MIS, ICIOB, MIIQS
IIQS DIRECTOR & MUMBAI MC REPRESENTATIVE
E V JOHNSON NEILLLM, MRICS, MIS, FCIArb, MIIQSIIQS DIRECTOR & CHENNAI MC
REPRESENTATIVE
KASI VISWANATHANB.E., LLM, MRICS, MIE, CCE,
MI, MIIQSIIQS DIRECTOR & CHENNAI
MC REPRESENTATIVE
RAMA RAO KILARIA.M.I.E(CIVIL), MRIC, MIIQS
IIQS DIRECTOR & HYDERABAD MC REPRESENTATIVE
P.V. SIVA PRASAD IOS DEGREE IN QS, DCE, MIIQS
GENERAL SECRETARY
M.S.GOMATHIGENERAL SECRETARY
VISHAL SHAHA CPD & MEMBERSHIP MANAGER
TBAGENERAL SECRETARY
V.V.S.RAMAKRISHNABE, M.TECH, MIIQS
TREASURER
UDAIYAR SANKARALINGAMTREASURER
MANOJEVENTS MANAGER
TBATREASURER
TBAMEMBERSHIP MANAGER
PRASANNA KUMARIBTECH, MBA, MIIQS
MEMBERSHIP MANAGER
RANJAN KUMARMEMBERSHIP MANAGER
IIQS - HYDERABAD MEMBER COUNCILORGANIZATION CHART (Year 2014-15)
IIQS - DELHI MEMBER COUNCILORGANIZATION CHART (Year 2014-15)
IIQS - MUMBAI MEMBER COUNCILORGANIZATION CHART (Year 2014-15)
IIQS - CHENNAI MEMBER COUNCILORGANIZATION CHART (Year 2014-15)
Indian Institute of Quantity Surveyors 2015 IIQS
23 IIQS - 2015 | 23 IIQS - 2015 |
With Best Wishes from Commercial Team of Parsons Overseas Limited
(Dubai Branch)
1. To increase our membership base substantially in India and other Gulf countries.
2. To enhance awareness of Quantity Surveying profession in India.
3. To create awareness in Engineering colleges in India that they need to start the
degree courses in Quantity Surveying.
4. To ensure that we continue to organize CPD activities for our members
5. To expand IIQS chapters in more cities of India.
6. To maintain the recently developed website so that the members can access the
CPD notes of all previous seminars and other webinars etc, along with the full
directory of our members.
7. To certify our members with appropriate membership grades such as
MIIQS, CIIQS, FIIQS etc.
8. To ensure that our members follow the ethics of highest standards. This is being
ensured by including ethics as one of the mandatory competencies for achieving the
membership grade.
9. Most importantly, to give back to the society by engaging in some charity.
OUR VISION FOR NEXT 5 YEARS IS:
With Best Wishes from
Indian Institute of Quantity Surveyors 2015 IIQS
25 IIQS - 2015 | 25 IIQS - 2015 |
Continuing Professional Development (CPD)
IIQS CPD Programme IIQS CPD events are scheduled on monthly basis and it includes a wide range of activities such as talks and presentations on subjects of contract and commercial management, construction law, cost planning and management, business management, contract practice, contracts administration, procurement and tendering, risk management etc. IIQS encourages all members to maintain and develop their professional competence in the workplace and CPD is one of the recommended way of enhancing the professional competence through sharing knowledge with other industry professionals and networking.
Benifits of CPD • HelpsMemberstoenhancetheirknowledge• Networkingopportunities• Providingcompetitiveenvironmentformembers• Helpsmembersintheirday-to-daywork• Enhancespresentationskillsbyprovidingopportunities for presenting seminars and workshop
What is CPD?CPD stands for Continuing Professional Development’ and is the term that describes how professionals maintain their own competence in the workplace. CPD is about learning and development that enhances effectiveness in professional life.
Natural Stone Tr LLCDealers in Stone, Slates, Granite, Marbles, Cobbles, Pebbles etc
Te l : 97 1 65352252 Fax : 97 1 65352219
P .O .Box : 69 128 Shar jah , UAE
Duba i Of f ice - Te l : 97 142662840 Fax : 97 14266284 1
Ema i l : contactus@natura ls toneuae .comWebs i te : www.natura ls toneuae .com
Indian Institute of Quantity Surveyors 2015 IIQS
27 IIQS - 2015 | 26 | IIQS - 2015 27 IIQS - 2015 | 26 | IIQS - 2015
Indian Institute of Quantity Surveyors 2015 IIQS
S.NO. DATE TOPIC SPEAkER LOCATION
1 1/15/2013 UAE Construction - Contract Formation Mr. Gary J. Beamish. EngC CEng CEnv CWEM MICE MCIWEM MQSI Dubai
2 02/26/2013 Liquidated Damages - UAE Perspective Mr. Shah Nawaz. C.A. Regional Operations Director, Johnson Controls Dubai
3 03/25/2013 The Secret behind Construction Contract Pricing options - Understanding What’s on the menu
Mr. Sachin kerur. Head of Gulf Region, Pinsent Masons Dubai
4 04/15/2013 How to Manage projects and Deliver within Time and Budget Mr. Somnath Mukherjee. Chief Manager (Projects), Simplex Infrastructures Ltd. Dubai
5 05/28/2013 Art and Science of Decision Making Prof. Christopher Abraham. Sr.Vice President & Head of the Dubai campus, S P Jain School of Global Management Dubai
6 08/20/2013 Extension of Time - Various Delay Analysis Techniques Mr. Dharmendar Pardasani. MSc(QS), PG (Dip) (Const. Law & Arbitration), FRICS, FAIQS, MCIArb, MCIOB & Ms. Sukshma ShajeevBE(Civil), PG (Dip) (Const. Law & Arbitration), PMP, FCIArb
Abu Dhabi
7 09/28/2013 Review of UAE Civil Law in context of Construction Law Provisions Mr. Venkataraghavan Ramadurai. FCIArb, FCMA, LLM, B.Eng, C.Eng, PGDBA Commercial Manager, Voltas Limited, Abu Dhabi Sharjah
8 10/26/2013 Construction Claims - Effective Writing and Presentation Mr. ANDY HEWITT. FCInstCES, FQSi, ACIOB, ACIArb, MDB Practice Principal, Hewitt Construction Consultancy FZE Sharjah
9 11/23/2013 Construction Project Delivery – Program and Project Management Mr. Gary Beamish. EngC CEng CEnv CWEM MICE MCIWEM MQSI Sharjah
10 12/22/2013 Persuasion and Success in Business Mr. Venkata Raman Jagannathan. MCom, Grad CWA, ACS, PMP, PgMP, CSSGB, CSSBB, CSSMBB Dubai
S.NO DATE TOPIC SPEAkER LOCATION
1 02/21/2015 Creative: Thinking Outside Your Brains Mr. Abdulla Galadari. PhD in Civil Engineering (Faculty member at Masdar Institute and an adjunct faculty at the Higher Colleges of Technology.Registered mediator at the DIFC-LCIA)
Dubai
2 03/21/2015 Using FIDIC in the UAE Mr. Faisal Attia. LLB, LLMSenior Associate, Arbitration, Al Tamimi & Co. Dubai
3 04/21/2015 Forensic Analysis for Statements of Claim Mr. Gary J. Beamish. EngC CEng CEnv CWEM MICE MCIWEM MQSI Dubai
4 05/13/2015 Awaken the Creative Genius in YOU Mr. Christopher Abraham. Senior Vice President and Head of the Dubai campus, S P Jain School of Global Management Dubai
5 06/10/2015 Dozen Causes of Rates/ Prices Becoming Inapplicable Mr. Indrawansa Samaratunga. PhD, DSc FRICS, FAIQS, FIQSSL, FCI Arb, FCIOB, FCMI, FASI, FCABE Dubai
IIQS CPD EVENTS UAE - 2015
IIQS CPD EVENTS UAE - 2013
CPD EVENTS UAE
Indian Institute of Quantity Surveyors 2015 IIQS
29 IIQS - 2015 | 28 | IIQS - 2015 29 IIQS - 2015 | 28 | IIQS - 2015
CPD In UAEIIQS , has successfully organized 10 consecutive CPD events in UAE for year 2013 and 5 consecutive events in 2015 .CPD Sessions provide a great opportunity for our members to enhance their knowledge and skills. IIQS Structured CPD events are lead by experts indusrty speakers. IIQS takes this opportunity to thank all the speakers and guest for their valuable time and effort for IIQS CPD events.
IIQS & MCI Contract Signing.
DBB chief guests at CPD
Indian Institute of Quantity Surveyors 2015 IIQS
31 IIQS - 2015 | 30 | IIQS - 2015 31 IIQS - 2015 | 30 | IIQS - 2015
Indian Institute of Quantity Surveyors 2015 IIQS
S.NO DATE TOPIC SPEAkER LOCATION
1 1/20/2014 Effective writing skills and presentation of construction claims and responses Mr. Andy Hewitt DOHA
2 I2/16/2014 The True Cost of Sustainability and Well Being Ms. Holy Chant
Dr Ioannis Spanos DOHA
3 3/30/2014 Coping with Projects in Dynamic Environments Dr. Tahir Hanif DOHA
Dr. Gyoergy Miketa
4 4/27/2014 ‘Environmental Impact of TBM Construction DOHA
5 5/17/2014 Foundation of a Basic Claim’ Mr. Paul Bernard Sarpong DOHA
6 6/22/2014 Top Ten Tips for Successful Contracting in Qatar Mr. Paul Prescott
Mr. Gabriel Olufemi
7 8/27/2014 Insurances, Bonds, Guarantees and Warranties’ Sandesh Pangerkar DOHA
8 9/29/2014 Contractor or Subcontractor – Who wins under Bespoke Subcontract? Mr.Rajesh kumarMr. Rama S Sinnaswamy
DOHA
9 11/30/2014 Schedule Update Analysis - Retained Logic Vs Progress Override Mr. Dev Tamboli DOHA
IIQS CPD EVENTS QATAR - 20151 2/25/2015 Ground Conditions Risks in Qatar Mr. Paul Prescott DOHA
Mr. Gabriel Olufemi
2 4/8/2015 Time bar and Claims Mr. Paul Prescott DOHA
Mr. Gabriel Olufemi
3 5/6/2015 Earned Value Management of Construction Projects Mr. Rubesh Rajan DOHA
4 5/25/2015 Q - Construct Mr. Andrew Robertson DOHA
5 6/10/2015 Utilization of BIM in construction with special emphasis on Revit Mr. Amro khatib DOHA
CPD EVENTS QATAR
IIQS CPD EVENTS QATAR - 2014
Indian Institute of Quantity Surveyors 2015 IIQS
33 IIQS - 2015 | 32 | IIQS - 2015 33 IIQS - 2015 | 32 | IIQS - 2015
CPD In QatarThe Qatar Region provided a wonderful opportunity to deliver successful CPD seesions in Qatar. This was the important milestone for IIQS Qatar and it is planned in 2015 also. All IIQS Member Councils will continue to organize the CPD events and workshops for global members.
Mr. Narayan Murthy visit 25 April 2015
Inaguration day - lamp lighting
Indian Institute of Quantity Surveyors 2015 IIQS
35 IIQS - 2015 | 34 | IIQS - 2015 35 IIQS - 2015 | 34 | IIQS - 2015
Indian Institute of Quantity Surveyors 2015 IIQS
CPD NO. MONTH DESCRIPTION SPEAkER LOCATION
1 24.1.2014 Intricacies of Cost Management Mr. Sunjaay Athanki BArch, PGDCMID, CoA. MANAGING DIRECTOR – G&T India Bangalore
Role of a Quantity Surveyor in Construction Industry
2 28.2.2014 Risk Management in Construction Mrs.Reethaa G Natarajan (B.A. LL.B). Associate Director – Legal. Spacematrix Bangalore
3 25.04.2014 Project Management in the Indian Construction Industry Leadership for QS Career Success
Mr. Jeffrey. M. West, (Bsc Est. Man), MA-Design, FRICS Hi-PoinT Project Management Solutions. Pvt. Ltd.
Bangalore
4 30.05.2014 Post Contract - Change Management Mr. Prashanth Bk, Civil Engg, GradDip-QS from NICMAR Bangalore
5 27.06.2014 QS and Project in-charge : An over view in Building Construction & Real Estate Mr. D. Narasa Reddy, B Tech, NIT Warangal, President & COO – South, JMC projects (India) Ltd. Bangalore Bangalore
6 25-07-2014 Effective Cost and Time Management in Project Mr. Suresh. S, ME(Geotechnical), BE (Civil), MIE, MIGS Senior Executive Vice president (Projects) Prestige Estates and Projects Bangalore
7 26-09-2014 Vertical Transportation for Residential and Commercial Buildings in Construction Industry V. JAGADISH kUMAR BE (Mech), IGBC-AP, Director – L’Avenir Consultancy Pvt. Ltd, Bangalore Bangalore
8 28-11-2014 TAXATION (VAT & Service Tax) for Indian Construction Industry MADHUkAR N HIREGANGE. Senior Partner Hiregange & Associates, Chartered Accountants, Bangalore Bangalore
CPD NO. DATE DESCRIPTION SPEAkER LOCATION
1 30.01.2015 Introduction to the FIDIC Contracts Mr. Umesh R, BE (Civil), MRICS. Principal Consultant - Rohini Project Management Solutions, Bangalore Bangalore
CPD Events
S.NO DATE CPD TITLE SPEAkER LOCATION
1 Jan-14 “ Think big in QS profession and build a big picture for future Mr. S.Pochender. Director & CEO - Lanco Hills Technology Park, Hyderabad , India Hyderabad
2 Feb-14 Claims Management Mr. Vikramjeet Singh. Vice President-Contracts & Risk management, GkC Projects Limited, Hyderabad Hyderabad
3 Mar-14 Contracts Administration Mr. C. k. Moorthy - Consultant - Contracts Management. Hyderabad
4 Nov-14 Contracts Strategy Mr Anand Thiagarajan. Senior Project Manager L & T Hyderabad
5 Nov-14 Negotiations and Leadership Mr. Jacob Joby. Director Development, SP International Developers LLC, Dubai, U.A.E Hyderabad
IIQS CPD EVENTS BANGALORE - 2014
IIQS CPD EVENTS BANGALORE - 2015
IIQS CPD EVENTS HYDERABAD - 2015
CPD EVENTS INDIA
Indian Institute of Quantity Surveyors 2015 IIQS
37 IIQS - 2015 | 36 | IIQS - 2015 37 IIQS - 2015 | 36 | IIQS - 2015
CPD in Bangalore& HyderabadBangalore Member Council and Hyderabad Member Council have been very active in organizing CPD’s for it’s member. We thank both the Member Council’s for organizing wonderful CPD’s during 2014 - 2015.
CPD In Hyderabad
Indian Institute of Quantity Surveyors 2015 IIQS
39 IIQS - 2015 |
ADsVISION OF IIQS WORSHOP : To Create a professional environment among all QS community to share the knowledge and experience to enhance the professional competence as well as to be part of a large professional network. Workshop is a one of the IIQS structured training programs to provide a professional platform for Contracts & Commercial Management professionals, Quantity Surveyors & Construction Professionals to plan their professional development to become Chartered QS of RICS or attain any other professional membership. Since inception, substantial number of QS professionals have attained their Chartered status and have attained to management positions in Contracts and Commercial fields and are presently working in UAE, Doha, India and other countries.
IIQS WORKSHOPStructured Training Programme
WORSHOPAPC Workshops were designed to upgrade skills, learn new techniques and get informed on all the latest developments of the construction industry. These workshops are designed by very well experienced IIQS members and Directors to help enhancing professional knowledge and to obtain IIQS membership from Indian Institute of Quantity Surveyors (IIQS). The competencies are delivered by qualified and experienced professionals. These workshops provided in-depth analysis of the competencies and an excellent networking opportunity. As the workshops covers majority of QS competencies, it also helps in gaining memberships from various other international organizations like, RICS, ICES, CIOB, AIQS etc.
Indian Institute of Quantity Surveyors 2015 IIQS
41 IIQS - 2015 | 40 | IIQS - 2015 41 IIQS - 2015 | 40 | IIQS - 2015
Indian Institute of Quantity Surveyors 2015 IIQS
Matrix Events in 2013S.NO. DATE COMPETENCIES FOR CIIQS SPEAkER
1 10/April/15 Introduction of IIQS membership guidelines Mr. Aslam, B.E. (Civil), MinstCES
2 10/April/15 Introduction of RICS APC guidelines Mr. kalpesh Sangani, M.Sc, LLM, FRICS, FCIArb, FAIQS
3 10/April/15 Commercial Management in Construction Mr. kasiviswanath, B.E., LLM, MRICS, MIE, CCE, MIS
4 24/April/15 Quantification & Estimating Mr. kalpesh Sangani, M.Sc, LLM, FRICS, FCIArb, FAIQS
5 24/April/15 Cost Planning & Cost Control
6 8/May/15 Environment, Sustainability, Health and Safety Mr. Mohammed Shakeel Ansari, MSc,PgD(CLaw),MRICS,MCIArb, MIS
7 8/May/15 Construction Technology Mr. Ajith Philip, B.E (Civil), PG Dip (C.M)
8 22/May/15 Business Planning/Management, Team work-ing; Communication & Negotiation
Mr. Jacob Joby, B.E (Civil), MBA, CCE
9 5/Jun/15 Tendering and Procurement Mr. Ganesh kumar, M.Sc, L.L.M, FRICS, FCIArb, FAIQS
10 5/Jun/15 Design Economics Mr. kalpesh Sangani, M.Sc, LLM, FRICS, FCIArb, FAIQS
11 19/Jun/15 Contract Practice & Contract Administration Mr. Dharmendar Pardasani, M.Sc, LLM, FRICS, FAIQS,
12 19/Jun/15 Accounting Principles and procedures; Data Management
Mr. Naveen kumar, M.Sc, MRICS
13 3/July/15 Conflict avoidance, management and Dis-pute Resolution
Mr. Venkataraghavan, FCIArb, FCMA, MRICS
14 3/July/15 Conduct rules, Ethics and Professional Prac-tice; Client care
Mr. E.V. Johnson Neil, LLM, MRICS, MIS, FCIArb
15 24/July/15 Teamworking Mr. Jacob Joby, B.E (Civil), MBA, CCE
16 24/July/15 key Contractual terms - FAQ in APC interviews Mr. Ganesh kumar, M.Sc, L.L.M, FRICS, FCIArb, FAIQS
17 24/July/15 APC Interview Guidelines Mr. kalpesh Sangani, M.Sc, LLM, FRICS, FCIArb, FAIQS
18 28/Aug/15 Programming & Planning Mr. Varughese Mathew, LLM, FRICS, FCIOB, MCIArb.
IIQS APC Workshop Schedule UAE - 2015 IIQS APC Workshop Schedule Qatar - 2015
APC WORkSHOP
S.NO. DATE COMPETENCIES FOR CIIQS SPEAkER
1 5/Sep/15 Design Economics and Cost Planning Mr. kalpesh Sangani
2 5/Sep/15 Quantification and Costing of Construction works Mr. kalpesh Sangani
3 29/May/15 Procurement and Tendering Mr. Avinash Gaikwad
4 28/Aug/15 Contract Practice Mr. Dharmendar Pardasani
5 12/Jun/15 Commercial Management of Construction Mr. Varughese Mathew
6 25/Sep/15 Project Financial Control and Reporting Mr. Sandesh Pangerkar
7 14/Aug/15 Construction Technology Mr. Rakesh Perumpilly
8 14/Aug/15 Commercial Management of Construction Mr. Sandesh Pangerkar
9 5/Sep/15 Design Economics and Cost Planning Mr. kalpesh Sangani
10 28/Aug/15 Contract Administration Mr. Dharmendar Pardasani
11 5/Jun/15 Client Care Mr. Girish Hassan
12 5/Jun/15 Communication and Negotiation Mr. Girish Hassan
13 29/May/15 Conduct Rules, Ethics and Professional Practice Mr. Avinash Gaikwad
14 5/Jun/15 Health and Safety Mr. Mushtaq Naik
15 5/Jun/15 Team Working Mr. Vijay Lachyan
16 11/Sep/15 Accounting Principles and Procedures Mr. Mushtaq Naik
17 5/Jun/15 Business Planning Mr. Dev Raj
18 12/Jun/15 Conflict avoidance, Management and Dispute resolution Procedures Mr. Rakesh Perumpilly
19 29/May/15 Data Management Mr. Vijay Lachyan
20 12/Jun/15 Sustainability Mr. Avinash Gaikwad
Indian Institute of Quantity Surveyors 2015 IIQS
45 IIQS - 2015 |
S.No Decsription Author Name
1 Professional EthicsA Value That Makes You More Valuable
Mr. E V Johnson Neil
2 FIDIC 1999Bad News or Good News for QSs ?
Mr. Prof. Indrawansa Samaratunga DSc,
3 Adjudication:Riding High on Success in UK Construction Industry
Mr. Dharmendar Pardasani
4 Acceleration ClaimsConfusion Reigns Supreme!
Mr. N.M Raj
5 Defective Arbitration Clauses: An Overview
Mr. Badrinath Srinivasan
6 Programming and planningLifeline of a project
Mr. Varughese Mathew
7 Cost Planning Mr. Sampath Raman
8 Cost Management Mr. Nilesh kushe
9 Life Cycle Cost Analysis Mr. Jacob Joby
10 Do we need the Provisional Sums? Mr. Ajantha Premarathna
11 “Managing the Change” in Construction projects
Mr. Venkat Rakhavan
12 Is it possible to terminate due to non-payment and/or late payments?
Mr. Rajesh kumar
13 The ‘golden rules’ of bidding for projects in Qatar and the UAE
Mr. Paul Prescott / Mr. Gabriel Olufemi
14 Design and build projectgo for it, if you understand its challenges
Mr. Syed Aslam
15 The impact of cultural factors Mr. Akram Saad
16 Developing a contract procurements strategyfor mega infrastructures project
Mr. Sajeeth
17 BIM and The Qs Profession Mr. Sunil Sukumaran
18 Infrastructure conditionsof contract (ICC) with quantities form November 2014 edition
Mr. Paul Prescott / Gabriel Olufemi
19 Indian StandardMethods of measurement of building works – ISI 200
Mr. Umesh Ramakrishna Rao
20 Impact of boom and bust of housing market Market On Macroeconony
Mr. Naveen kumar
21 Happiness leads to success Mr. Christopher Abraham
ARTICLES
Indian Institute of Quantity Surveyors 2015 IIQS
IIQS
Qat
ar M
embe
rs a
nd
Mem
bers
Cou
ncil
Wit
h be
st c
ompl
imen
ts fr
om
47 IIQS - 2015 | 46 | IIQS - 2015
Dear Friend,
I am immensely pleased to write to you on the most important
requirement of our professional life, which is ‘Professional Ethics’.
As professionals in the construction sector, we operate in a
highly fragmented industry that includes many differing skills
and professions, where relationships and boundaries are not
always clear. In earlier times, the work of a Quantity Surveyor
was primarily based on measurement alone. But in recent
years, it has evolved rapidly into a more diverse, complex
and sophisticated profession, which demands a wide range
of specialist skills. In this changed scenario, because of
our regular involvement in financial transactions such as
procurement, contractual arrangements, payments and
valuations, we are obliged to act in a transparent and ethical
manner. As the sector is characterized being constructed on
‘personal relationships’, we must understand that these areas
are vulnerable to malpractice easily. Therefore, it is imperative
to understand the importance of Professional Ethics in a
crystallized way.
The Oxford English dictionary defines ‘ethics’ as moral
principles or rules of conduct. The rule of conduct provides a
set of moral principles according to which one should conduct
one’s affairs. It may be seen as being fair or not wronging or
harming others. Looking through a corporate eye, Professional
Ethics encompass the personal, organizational and corporate
standards of behavior expected of professionals. Those working
in acknowledged profession, exercise specialist knowledge
and skill. How the use of this knowledge should be governed
when providing a service to the public is termed as Professional
Ethics.
Murdoch and Hughes1 say that the primary aim of the
professional is to serve the public and if we are a true
professional, we will place the interest of the public before
any of our financial reward. The Royal Institution of Chartered
Surveyors2 (RICS) says: “behaving ethically is at the heart of what
it means to be a professional; it distinguishes professionals
from others in the marketplace”. The industry recognizes and
respects the professionals who practice highest level of ethics.
Seeley3 believes that upholding professional ethics underpins
the primary objectives of the professional codes of practice
and that is the key reason why people rely on professional
bodies. Therefore, international professional institutions such
as Royal Institution of Chartered Surveyors (RICS), Australian
Institute of Quantity Surveyors (AIQS), Institution of Surveyors (IOS),
Chartered Institute of Arbitrators (CIArb) etc. have produced
a simplified set of professional standards that requires their
members to understand and to be committed to maintain
such standards. The Indian Institution of Quantity Surveyors (IIQS)
also gives extreme importance to professional ethics.
For an example, IIQS requires all its members to demonstrate
the following five professional and ethical standards.
• Maintain Professional Integrity
• Maintain confidentiality and avoid conflict of interest
• Maintain process and procedures without favouritism
• Maintain proficiency and competence truthfully
• Maintain minimum 20 CPD hours every year
Though the above standards appear easy to practice,
complying with these acts in day to day work environment
poses a challenge due to the pressing need of economic
survival and stiff competition. But, doing business ethically
and professionally will surely enhance your business results.
Cartlidge4 argues that professions can only survive if the public
retains confidence in them. He also claims that upholding
ethical standards has several benefits for firms and with such
a strong ethical culture may gain competitive advantages,
able to attract and retain competent and dedicated staff, be
more attractive to clients, gain greater company reputation. In
a nutshell, fair business is good business.
“Behaving ethically is at the heart of what it means to be a professional;it distinguishes professionals from others in the market place”
At this point, the question of conflict of interest indeed arises.
RICS defines conflict of interest, as anything that impedes or
might be perceived to impede an individual’s or firm’s ability
to act impartially and in the best interest of a client. A conflict
of interest can create a doubt on our integrity and can have
a harmful effect not only on our firm but also the profession as
a whole. In situations where a member perceives conflict of
interest; the client’s interest shall take precedence unless it is
contrary to the public interest.
To avoid potential conflicts of interest, we should always be open
and transparent in our dealings. We should disclose all interests,
relationships and matters likely to affect our independence or
impartiality or which might reasonably be perceived as likely to
do so. If we believe that we will be incapable of maintaining
the required degree of independence or impartiality, we
should promptly take necessary steps as may be required in
such circumstances.
Finally, upholding ethical standard is important and inevitable
for Quantity Surveyors. It has a clear connection with integrity
and professionalism and has characterized a professional as
trustworthy and competent. Warren Buffet suggests “In looking
for people to hire, you look for three qualities: integrity,
intelligence, and energy. And if they don›t have the first, the
other two will kill you.” Hence, those delivering construction
courses within the higher education system should do more to
promote ethics. Learning more about ethics should empower
students to actively question any dubious practice they might
see at work and thereby benefit the industry in the long term.
As CS Lewis said “education without values, as useful as it is,
seems rather to make man a cleverer devil.”
We cannot afford to be seen to be anything other than an
ethically responsible professional. Therefore, the process
of learning ethics should not stop at colleges/universities
but should continue throughout the professionals’ work-life.
Cultivating a habit of self-regulation and an awareness to
maintain high ethics, through lifelong learning is undoubtedly a
value that will make us more valuable amongst other industry
players.
Your Well-WisherE V Johnson Neil
1 John Murdoch & Will Hughes (2008) Construction Contracts Law and Management, Routledge, London
2 Royal Institution of Chartered Surveyors (http://www.rics.org/ae)
3 Seeley, I H (1997) Quantity Surveying Practice Hound mills Macmillan, Basingstoke
4 artlidge, D (2011) New Aspects of Quantity Surveying Practice, Spon Press, London
References
Royal Institution of Chartered Surveyors (http://www.rics.org/ae)
Indian Institute of Quantity Surveyors (http://www.iiqsglobal.org)
John Murdoch & Will Hughes (2008) Construction Contracts Law and Management, Routledge, London
Cartlidge, D (2011) New Aspects of Quantity Surveying Practice, Spon Press, London
Seeley, I H (1997) Quantity Surveying Practice Hound mills Macmillan, Basingstoke
Cunningham, T (2011) Professionalism and Ethics: A Quantity Surveying Perspective, Arrow, Dublin Institute of Technology
Johnson Neil is a Chartered Quantity Surveyor with 29 years of vast experience in the construction industry out of which 23 years have been gained in UAE.
Apart from his Civil Engineering and Quantity Surveying qualifications obtained from India and UK, he has a Master’s degree in Construction Law and Arbitration from the Robert Gordon University, UK.
He is a Member of the Royal Institution of Chartered Surveyors - UK (MRICS), Fellow of the Chartered Institution of Arbitrators - UK (FCIArb) and Member of the Institution of Surveyors - India (MIS).
He is currently running a Project Development and Cost & Contract Management Practice in Dubai, UAE focusing on his best competencies and interest that also includes claim management, dispute resolution, mentoring and training.
E V JOHNSON NEILLLM, MRICS, MIS, MIIQS, FCIArb,
Director, Eben Johnson Consultants, Dubai, UAE, Director and Global Vice President - IIQS
Professional EthicsA Value That Makes You More ValuableWritten as a letter to a friend
49 IIQS - 2015 | 48 | IIQS - 2015
Increasingly, Developers and Consultants in Dubai, have
commenced using FIDIC 19991 as the Form of Contract
for their current and forthcoming projects. For some time
now FIDIC 1999 has been in use in Abu Dhabi for most of their
projects. Therefore Quantity Surveyors in the UAE have no other
option but to master the complex administration aspects
under FIDIC 1999 as well, in addition to their current skills in
administrating contracts under FIDIC-4th Edition2.
What should not be forgotten is that, whilst FIDIC-4th is a tested3
Standard Form of Contract which has withstood the test of time
for over quarter a century, FIDIC 1999 is not so, and therefore
the industry is unaware as to how the Courts and Arbitrators
would decide on many unavoidable disputes that are likely to
arise due to serious concerns that exist in this latest FIDIC Form.
Some terminology found in FIDIC-4th still exists in FIDIC 1999 but
with different meanings/definitions and therefore the correct
usage needs to be adopted in order to avoid contention.
“Contract Price” for instance is not what it was under FIDIC-4th,
if used with reference to a FIDIC 1999 contract !
Lack of separate provisions to value variations, and the
combining of valuation of variations together with the
valuation of the original scope of work have produced a very
complex Sub-Clause 12.3, not easy to understand, and also
lacking adequate provisions to value some aspects of original
scope of work4 and varied work5. One unique feature in the
previous FIDIC versions (when compared to JCT, ICE, NEC and
other Forms of Contract), was Sub-Clause 52.3 which provided
for restoring an under-recovery of a Contractor ’s overheads,
which also provided for correcting an over-recovery in favour
of the Employer6. FIDIC has decided to do away with this
provision in the new Form, but Sub-Clause 12.4 could still
be construed as the mechanism to restore the Contractor ’s
under-recovery, but the correction of any over-recovery is not
available!
Opportunity for Contractors to claim varied rates/prices even
in re-measurement type of contracts, if the BOQ quantities do
not accurately represent the work shown in the Drawings and
described by the Specification, would make it very onerous for
QS Consultants to ensure the accuracy of quantities even in
the Bills of Estimated Quantities prepared for re-measurement
type of contracts. The new opportunity for Contractors to claim
Extension of Time and associated cost reimbursements due to
such quantity differences (without the instruction of a Variation)
is another area of concerns.
Termination for Employer ’s convenience is a new Clause which
did not exist in FIDIC-4th. Though drafted without provision for
a Contractor to claim loss of profit, nevertheless a Contractor
terminated pursuant to this Clause may succeed in receiving
compensation in law, judging from cases decided by the
highest court in the emirate, Dubai Court of Cassation.
Under FIDIC-4th it was not the contract that was terminated when
a party is in breach, but the employment of the Contractor under
the contract, and therefore there was no necessity to provide
for the survival of important provisions. In the only two instances7
where the contract is terminated, FIDIC-4th expressly provided
for the survival of Dispute Resolution by Arbitration, Entitlement
to damages for antecedent breaches, and the Method of
Calculation of the payments following a termination. Under FIDIC
1999, it is the contract that is terminated in all instances, but the
survival requirement of above important provisions is missing,
and therefore (unless the law applicable to the contract provides
otherwise), parties may end up in Courts to resolve their disputes,
which is thoroughly undesirable, and also a court appointed
expert may not want to adhere to the detailed method of
calculation of payments provided in the contract (such as “any
other cost or liability incurred by the Contractor in the expectation
of completing the whole of the Works” etc.), as such provisions
have not been made to survive the termination of the contract.
Increasingly, Developers and Consultants in Dubai, have commenced using FIDIC 19991 as the Form of Contract for their current and forthcoming projects.
FIDIC 1999Bad News or Good News for QSs ?
Lack of provision to extend time in “special circumstances”
(which provision existed in FIDIC-4th), would offer opportunities to
Contractors to plead for setting time at large, in order to escape
from Liquidated Damages thus leaving the Employers to prove
their losses in claiming damages for breach.
Notices have been made condition precedent which would
result in higher tender prices due to the tenderers either making
allowances for this risk or including the cost of a claims team
within the site overhead costs.
Lack of a provision such as Sub-Clause 52.2(a) of FIDIC-4th to
claim prolongation costs of a contractor when an instructed
Variation delays the project completion, leaves the Contractors
with the undesirable option of asserting that the Employer is in
breach of contract (in order to claim such costs as damages for
breach), every time a Variation is instructed !
Good news is that, the significantly increased cost management
and contract administration activities required for FIDIC 1999
contracts (when compared to those under FIDIC-4th) would
compel Contractors, Consultants and Developers to employ
more Quantity Surveyors for each project without whose
invaluable advice / services, the company interests cannot be
adequately protected.
Whilst FIDIC-4th relied on the presence of an impartial Engineer
to administrate the contract, the absence of the requirement of
Engineer’s impartiality under FIDIC 1999 has made it necessary
to refer any disputes to an independent Dispute Adjudication
Board (and not to the Engineer as in FIDIC-4th), for resolution
in the first instance, an area where Quantity Surveyors need
to enhance their current skill sets8. This is also an area where
Quantity Surveyors would have lucrative career opportunities.
At present Developers / Consultants delete the Dispute
Adjudication Board provisions in FIDIC 1999 contracts due to
the acute shortage of Adjudicators in this part of the world.
Quantity Surveyor, with his/her multi disciplinary education is
an ideally placed candidate to undertake further studies and
training in the field of dispute resolution to fill the thousands of
Adjudicator positions that would be created when FIDIC 1999
inevitably becomes the norm in the near future for almost all
projects in this part of the world, and the industry becomes
fully aware about the benefits of resolving the disputes by
referring to a Dispute Adjudication Board, which is less costly,
quicker and would not break down business relationships,
when compared to Litigation or Arbitration.
All the areas of concern in FIDIC 1999 cannot be highlighted
in a short article of this nature. FIDIC-4th needed some four
editions of improvements to reach its refined state. FIDIC 1999
is still in its 1st Edition and no doubt, FIDIC would address most
of the above concerns in its subsequent Editions, but until then
Quantity Surveyors have no other choice but to address them
through Particular Conditions before the tenders are invited
and also exercise care during the administration of the
contract.
1 Conditions of Contract for Construction for Building and Civil Engineering Works designed
by the Employer – First Edition 1999, published by Federation Internationale des Ingenieurs-
Conseils (FIDIC), Switzerland.2 Conditions of Contract for Works of Civil Engineering Construction – Fourth Edition 1987,
published by FIDIC.3 Though FIDIC-4th still has shortcomings (to the extent that the English literal meaning of a provi-
sion is exactly the opposite of what is intended !), authorities exist on how to interpret / construct
them.4 FIDIC 1999 does not have provisions to value an item of original scope of work which is
missing from the BOQ, in a re-measurement type contract (unless there is a rate or price for
a similar item existing elsewhere in the BOQ).5 FIDIC 1999 does not have provision to compensate the Contractor (or the Employer) with a
varied rate or price, when a variation affects cost of execution of an item of original scope
of work (unless its quantity also changes by more than 10%, as a result of the Variation,
whereas in FIDIC-4th this could be done under Sub-Clause 52.2.
6 Not the whole under-recovery or over-recovery but the net excess beyond 15% (or other
percentage agreed by the parties in the contract).7 Sub-Clause 65 – Special Risks (Force Majeure) and Sub-Clause 66 – Release from Perfor-
mance (Frustration).8 In the past, Lawyers were brought in to provide advice only when the parties entered into
the final tier of Arbitration in the multi-tiered dispute resolution process of FIDIC-4th. Until
then the Quantity Surveyor advised the company during the early tiers, especially in procuring
the Engineer’s Decision pursuant to Clause 67. But under FIDIC 1999, referring the disputes
to the Dispute Adjudication Board (“DAB”), arranging witness statements, preparing the
witnesses, dealing with matters of evidence and arguments, participating in hearings and
all other dealings with the DAB on jurisdictional, procedural and substantive issues, are now
matters that the Quantity Surveyors would have to undertake (and provide the companies
with correct advice), as lawyers are not engaged during this early tier. Companies which
would offer their QSs with training opportunities in these areas would have the company
interests protected.
Prof. Indrawansa Samaratunga DSc,FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FCABE
Chartered Surveyor, Chartered Manager, Chartered Construction Manager,Chartered Building Engineer, Chartered Quantity Surveyor
Arbitrator / Mediator - London Court of International ArbitrationArbitrator / Expert - Dubai International Arbitration Centre, UAE
Construction Law and Dispute Resolution Advisory Board member of the British University in Dubai
51 IIQS - 2015 | 50 | IIQS - 2015
United kingdom (Uk) was the first country to have
statutory framework for adjudication through
Housing Grants, Construction and Regeneration Act
(Construction Act 1996) which requires that all the construction
contracts in Uk need to have the adjudication as the
mandatory dispute resolution provision.
Since then, the adjudication has been adopted in some
other common law countries such as Australia, New Zealand,
Singapore and recently Malaysia.
The process of adjudication and the key differences that it
bears to arbitration are discussed hereunder.
Initiation of Adjudication
The adjudication process is initiated when the party referring
the dispute to adjudication gives written notice. This Notice
of Adjudication should include the nature of dispute and the
remedy being sought.
The Notice of Adjudication is considered the commencement
of the adjudication procedure.
Appointment of the adjudicator
Following issuance of the Notice of Adjudication by a party,
the next requirement is to appoint an adjudicator. The
appointment of an adjudicator must be achieved within seven
days from service of the Notice of Adjudication. The parties
can either agree on an individual to act as the adjudicator
or, if agreement cannot be reached, the party who referred
the dispute to adjudication may apply to an Adjudicator
Nominating Body (ANB). The ANB then notifies of its selection
to the party who referred the dispute to adjudication within
five days.
The referral notice
The referral notice must be served by the claimant within seven
days of service of the Notice of Adjudication. The referral
notice sets out in detail the case of the party who is referring
the dispute to adjudication and it should have the necessary
documentation in support of the claim together with expert
and factual witness statements (if any). A copy should be sent
to the other party at the same time.
Time Period / Adjudicator’s Decision
The responding party ’s response is required to be served within
seven days of the Referral Notice.
The adjudicator is required to reach his decision within 28 days
of service of the referral notice. This period can be extended
by a further 14 days if the party who referred the dispute in
the first place agrees, or can be further extended only if both
parties agree.
This tight time table is the essence of the adjudication process
which ensures to obtain quick and cost effective results
which are of a binding nature unless reversed by litigation or
arbitration.
The main difference between the adjudication and arbitration
lies in respect of adjudicator applying his own knowledge in
determining the fact and the law. An adjudicator is permitted to
rely on its knowledge and experience to initiate the determination
of the fact and the law, but at the same time his is required to
inform his findings to the parties in interest of the natural justice
and provide the parties the opportunity to respond. However, in
contrast, an arbitrator will only use his knowledge and experience
to better understand the evidence submitted by the parties, but
not to determine the fact and law. This is an important distinction
between the arbitration and adjudications.
The adjudicator’s decision is final and binding, providing it is not
challenged by subsequent arbitration or litigation. The parties are
obliged to comply with the decision of the adjudicator, even if
they intend to pursue court or arbitration proceedings. If a party
chooses to pursue subsequent proceedings in the arbitration or
Adjudication is a dispute resolution procedure for resolving disputes without resorting to lengthy and expensive arbitration or court procedures.
the courts, the dispute will be heard afresh, not as an ‹appeal› of
the adjudicator’s decision.
Adjudicator’s fees and expenses
The parties are jointly and severally liable to pay the adjudicator
the fee and expenses reasonably incurred by him.
Synopsis
The adjudication is a fast track dispute resolution process
wherein the adjudicator is permitted to use his expertise and
experience to initiate determination of facts and the law, which
is the main reason that the adjudicators can manage their
decision within the statutory 28 day period, instead of relying
only on the submissions of the parties. Also, the adjudicator has
full control on the procedural issues which also helps to define
the time period for each stage thereby helps in reaching the
decision within the tight time frame.
However, the down side being that the adjudication is
binding but temporarily final until the dispute is determined by
arbitration or litigation. Also, with the arbitration tribunals, one
can have a high level of confidence due to high credentials
required to become an arbitrator and the arbitration process
being conducted under strict statutory framework. In contrast,
the quality of adjudicators may be variable since there are
many short training courses available to be trained to work as
an adjudicator.
Notwithstanding very few drawbacks of adjudication, the main
reason that the adjudication has been very successful in Uk is
due to the reason that it has some very good features different
to arbitration, but at the same time retains some of the quasi-
judicial features of arbitration. The success of adjudication in
Uk can therefore be attributed to the following key reasons:
• It can be initiated any time during the course of the
contract; there is no requirement to wait until the end of
the project as in some of the arbitration provisions.
• The decision is quick (28 days extendable to 42 days with
consent of referring party), which provides a quick cash
flow relief to the claimant.
• It is binding and the enforcement can be obtained from
the court through a summary judgement.
• The case law on the challenge to adjudicator ’s decision
on the grounds of jurisdiction or the apparent bias
indicates that the courts have been unwilling to nullify
the adjudicator ’s decision unless there is a very strong
evidence of lack of jurisdiction or breach of natural justice.
• Most of the disputes in Uk construction industry that
were further referred by the losing parties to arbitraton
or litigation ended up in almost similar award as were
decided in the adjudication.
It is therefore high time that other countries also start initiating
the legal framework to have adjudication as a mandatory
dispute resolution mechanism in the construction contracts.
This shall protect the stability of the cash flow for the weaker
parties in the construction contracts namely contractors,
subcontractors, suppliers and the consultants and shall create
a healthy construction industry.
This tight time table is the essence of the adjudication process which ensures to obtain quick and cost effective results which are of a
binding nature unless reversed by litigation or arbitration.
Mr Dharmendar Pardasani is working as Director-Contracts with one of the largest Consultancy firm Parsons Overseas Limited in Dubai. He has a LLM (Construction Law & Arbitration) (UK), MSc in Quantity Survey (UK) and a Bachelor in
Civil Engineering (India). He has over 30 years of Experience in the Construction Industry.Mr. Pardasani a Fellow (FRICS) of Royal Institution of Chartered Surveyors (UK), Fellow (FCIArb) of Chartered Institute
of Arbitrators (UK), Fellow (FAIQS) of Australian Institute of Quantity Surveyors and Corporate Member (MCIOB) of Chartered Institute of Buildings. Also, he is Board Member of RICS MENEA Region Education Board.
Dharmendar PardasaniMSC(QS),FRICS,FAIQS,MCIOB,MCIArb
Director & Global Vice PresidentContracts Manager, Parsons UAE
Adjudication:Riding High on Success in Uk Construction Industry
53 IIQS - 2015 | 52 | IIQS - 2015
Recently, I was discussing various issues related to acceleration /disruption claims with Tony Bingham (renowned barrister) and Ian Robinson (Expert Delay Analyst for Walter Lilly – Walter Lilly v Mackay). Over the course of our conversations, we agreed that misconceptions still exist about how to properly identify, agree and quantify disruption /acceleration claims.
This article hopes to provide an overview of “acceleration” from a legal, contractual and practical perspective.
Acceleration ClaimsConfusion Reigns Supreme!
Legal / Contractual Aspect
In Ascon Contracting Ltd v. Alfred McAlpine Construction
(1999) Judge Hicks stated:
“…‘Acceleration’ tends to be bandied about as if it were
a term of art with a precise technical meaning, but I have
found nothing to persuade me that this is the case…”
With all due respect to the learned Judge, it is possible to
clearly define and quantify acceleration from a technical /
contractual angle. Over the years, I’ve submitted countless
acceleration claims and achieved a significant level of
success.
The Judge also stated:
“…what is plain is that there cannot be both an extension
of time to the full extent of the employer’s culpable delay,
with damages on that basis, and also damages in the form
of expense incurred by way of mitigation, unless it is alleged
and established that the attempt at mitigation, although
reasonable, was wholly ineffective…”
[Emphasis Added]
In this case, Ascon fell victim to the misconception I mentioned
earlier on about the quantification of acceleration claims. On
several occasions, I’ve had to deal with “Acceleration plus
Extension of Time” claims from Contractors; in most cases, the
two claim headings are mutually exclusive.
I place emphasis on the phrase “in most cases” because
it is possible to submit an acceleration and extension of
time claim in tandem. In the above extract, the Judge is
right and states something similar to what I told Contractors.
However, I underlined the words “wholly ineffective”; what if
the acceleration measures were not “wholly” but “partially”
ineffective”? Say, there was a 6 month delay caused by the
Employer and the Contractor managed to accelerate and
reduce the delay by 3 months. Is he not entitled to a 3 month
EOT plus an acceleration claim for reducing the delay? I would
say the Contractor is entitled to recovery for both claims.
1. Voluntary acceleration: Here, the Contractor accelerates
of his own volition in order to finish the works earlier than
the original contract completion date. It should be noted
that the FIDIC Red Book (1999 Edition) gives the Contractor
a contractual right to finish the Works before the Time for
Completion. Sub-Clause 8.2 states that “The Contractor shall
complete the whole of the Works, and each Section (if any),
within the Time for Completion…” [Emphasis Added]
However, the Contractor should be aware that the “The
Employer’s Personnel shall be entitled to rely upon the
programme when planning their activities.”,
Sub-Clause 8.3 refers. Furthermore, an unrealistic programme
with unachievable productivity levels may well prove to be the
Contractor ’s undoing during claims related scenarios.
Classification of Acceleration ClaimsAcceleration may broadly be categorised as follows:
2. Mutually agreed acceleration measures: In this situation, the
Contractor and the Employer mutually agree to acceleration
measures in order to recover delays which were not caused by
the Contractor. Alternatively, the parties may agree to a reduced
Time for Completion via the value engineering option pursuant
to Sub-Clause 13.2 of FIDIC (1999 Edition).
3. Instructed or Directed acceleration: In this scenario, the
Engineer instructs the Contractor to expedite progress of the
Works if there are any critical delays arising from events caused
by the Contractor, Sub-Clause 8.6 refers. It should be noted that
the Engineer is only entitled to invoke this Sub-Clause if delays
were caused by the Contractor.
4. Constructive acceleration: This occurs when the Contractor
accelerates the work even though he was not responsible for
delaying the works. Constructive acceleration is a complex /
risky measure and should only be undertaken after receiving
professional advice
Acceleration Does Not Automatically
Equate To Additional Costs
It is not always a foregone conclusion that acceleration results
in additional costs. Sometimes, a Contractor can actually
save money by accelerating the works!
For example, let’s assume that a Contractor is asked to
accelerate by renting an additional plant e.g. one more
excavator. Now, I’ve come across Contractors who would
submit this excavator ’s total cost as part of an acceleration
claim. This is incorrect because the excavator is executing
works and earning value /money. Notwithstanding additional
mobilization /demobilization costs, the Contractor could,
potentially, reduce his project duration and overall costs
(reduction to time-related prelims costs) if he is able to use the
excavator efficiently. A detailed cost analysis should be carried
out to in order to evaluate the validity of an acceleration
claim.
Conclusion
I hope this article will prove helpful while dealing with acceleration claims; it is a slightly complex topic and
one which should be handled with care. Presently, I’m discussing these type of claims with The Hon. Mr Justice
Akenhead (for a conference) and I hope to write about it in the future.
“…‘Acceleration’ tends to be bandied about as if it were a term of art with a precise technical meaning, but I have found nothing to
persuade me that this is the case…”
N.M.Raj, Managing Partner of Prime Consulting, is an internationally renowned and highly sought after claims / contracts specialist (FIDIC & other contracts). He is the creator of the internationally acclaimed
online Master Course in construction claims, Master Workshops and author of“Quick guide to construction claims” (with sales in over 65 countries).
Raj Has More Than 25 Years Of Commercial / Claims Management Experience On Iconic Projects Across the World.Raj holds dual qualifications in Engineering & Law; Raj has a degree in Civil Engineering and is a
Member (MCIArb) of The Chartered Institute of Arbitrators, FIDIC, SCL, DRBF & The AACE.Raj Has Also Held Memberships with the RICS, CIOB and APM.
N.M.Raj
55 IIQS - 2015 | 54 | IIQS - 2015
This short paper addresses an important aspect that a Quantity Surveyor may have to do in his career, which is to draft proper arbitration clause. Although the exercise of drafting arbitration seems straightforward, the history of arbitration has exposed the folly of humankind in failing to learn lessons from the past. Numerous cases are reported every year relating to defective arbitration clauses. This short paper provides a brief overview of defective clauses in arbitration.
Instances of Defective Arbitration Clauses
While an arbitration clause may touch upon several aspects
such as pre-arbitral procedures (such as negotiations,
mediation, etc.), specific disputes to be referred to arbitration,
number of arbitrators, seat of arbitration, time limit within which
arbitrators should decide, finality of arbitral awards, procedure
to be followed by the arbitrator etc., there are certain
essentials that an arbitration clause should possess. These
essential contents will differ depending on the nature/ type
of arbitration. Defective arbitration clauses are those which
lack in one or some of the essential elements of an arbitration
clause.
Some of such common defects found in arbitration clauses
are briefly discussed below1:
• Reference to Non-Existent Arbitral Institutions: Here, the
parties agree in their arbitration clause to refer their disputes
to an arbitral institution which is non-existent. In a recent
case, for instance, the parties agreed to refer their disputes
to the Singapore Chamber of Commerce.2 The court found
that there was no institution administering arbitration under
such name.3
• Reference to Non-Existent Rules: In this scenario, parties
agree for arbitration under non-existent rules. In System for
International Agencies v. Rahul Coach Builders Pvt. Ltd.4, the
parties agreed to arbitration under the “by-laws of Indian
Company›s Act 1956” or “as per International Trade Laws”.
The rules under which the arbitration had to be conducted
did not exist.
• Reference to Arbitrators who are no more alive at the time of
dispute: An arbitration clause may provide for reference of a
dispute to an arbitrator but when disputes arise, the arbitrator
may not be alive. ACC Limited v. Global Cements Ltd.5 is
a case in point. Here, the arbitration clause provided for
arbitration by either of the two persons who were both dead
when disputes arose.6
• Unworkable Arbitration Clauses: In this type of defect, the
arbitration clause provides for arbitration under an arbitral
institution but mandates that the arbitration has to be
conducted under arbitration rules of some other arbitral
institution or arbitration rules inconsistent with the rules of
the arbitral institution. For instance, in Insigma Technology
Co. Ltd. v. Alstom Technology Ltd7, parties agreed
to refer disputes to arbitration before the Singapore
International Arbitration Centre but in accordance with
Rules of Arbitration of the International Chamber of
Commerce. This is the case where the ICC Rules, which
are the arbitration rules of the ICC’s International Court of
Arbitration, but the arbitration was to be conducted by
Singapore International Arbitration Centre, an institution
similar to ICC.
• Reference of Disputes to Arbitration as well as Courts: At
times, parties agree to refer disputes to arbitration under
valid clauses but also agree contradictorily that courts
of a certain country or city would have the exclusive
jurisdiction over disputes.8
Incomplete Arbitration Clauses: Courts generally look for an
unequivocal intent to arbitrate. From this perspective, the
arbitration clause must employ mandatory language (such
as “shall” or “will”) to convey parties intent to refer disputes to
arbitration. Failure to do so would make the arbitration clause
defective. In Wellington Associates Ltd. vs. kirit Mehta9, the
agreement contained an exclusive jurisdiction clause and also
provided that any dispute “may” be referred to arbitration. On
a combined reading of both clauses, the court concluded
that reference to arbitration was optional and parties had to
mutually agree to refer the dispute to arbitration.10
Consequences of Defective Arbitration Clauses
Although courts in many jurisdictions these days are in
favour of enforceability of arbitration clauses and adopt an
interpretation that is in favour of giving effect to arbitration
clauses, it is possible that courts may adopt a diametrically
opposite stand. In the latter situations, defective clauses could
potentially have serious adverse effects. The party which is at
the receiving end of the notice invoking arbitration often takes
advantage of these defects to defeat the salutary objectives
of arbitration i.e. efficiency and finality. In such cases, there is
considerable wastage of time and effort in litigating in courts
on whether the arbitration clause is valid or not in courts, often
up to the highest court in the relevant jurisdiction. Apart from
considerable wastage of time and effort, the invoking party
has to expend substantial expenses in litigating the matter in
court. It is also possible that the party at the receiving end of
the arbitration notice may initiate proceedings in a country
other than the one chosen by the parties in the agreement.
This may lead to multiple proceedings in different jurisdictions.
A corollary of this is that multiple proceedings on the subject
may lead to inconsistent decisions on the enforceability of the
arbitration clause.
Conclusion
The effectiveness of the arbitration clause may have implications
even on the enforceability of the claim itself. These adverse
consequences could be avoided or at least mitigated by parties
through due diligence in framing arbitration clauses.
Several measures to prevent pathological clauses exist. Some of
the common methods are the following:
• Arbitral institutions generally provide model arbitration
clauses along with their rules. It is prudent to use these
clauses considering their universal applicability world over.
• While choosing an arbitral institution, it is important for
the parties to be aware of the consequence of such
choice on the arbitration proceedings. For instance, the
applicable arbitral rules may provide for appointment of
three arbitrators in the absence of an agreement to the
contrary.1 Appointing three arbitrators in a small value
dispute may not be necessary and would only lead to
high costs and delays in concluding the proceedings.
• Before agreeing to an arbitration clause, the parties
must exercise due diligence in choosing an arbitral seat,
the arbitral institution, etc. The arbitral seat may contain
mandatory requirements which may be onerous to one
of the parties.
Contract law in general and arbitration law in particular should
be enacted such that it should enforce the fair and prudent
commercial expectations. In such an ideal scenario, there
would be no need to obtain legal counsel while negotiating
agreements. However, in practical world, it is prudent for the
parties to get a dispute resolution policy drafted and vetted
by legal counsel and apply the same while negotiating
agreements. These measures would go a long way in avoiding
defective arbitration clauses.
Defective Arbitration Clauses: An Overview
1Gary B Born, International Commercial Arbitration, Wolters Kluwer (2009), p. 675-694
2Pricol Ltd. v. Johnson Controls Enterprises Ltd. (2015) 4 SCC 177: MANU/SC/1165/2014
3Also see, Lucky-Goldstar International (HK) Ltd. v. Ng Moo Kee Engineering Ltd. [1993] 1 HKC 404 (Hong
Kong High Court); In Re: Arbitration between C.M. Karanji & Co. (India) v. Indo-China Trading Co., Ltd. CWN
763: MANU/ WB/0403/1951; In the Matter of the Arbitration between Laboratorios Grossman, S. A., Appel-
lant, and Forest Laboratories, Inc., 31 A.D.2d 628 (1968)
4MANU/SC/0145/2015
5AIR 2013 SC 3824: MANU/SC/0489/2012
6There are instances where parties have agreed to refer disputes to certain institutions which ceased exist
when disputes arose. See, Gary B Born, International Commercial Arbitration, Wolters Kluwer (2009), p. 683.
7[2009] 1 SLR 23: [2008] SGHC 134
8Also see, AEZ Infratech Pvt. Ltd. v. SNG Developers Ltd. 2014 (143) DRJ 616: MANU/DE/1383/2014 ; Paul
Smith Ltd. v. H & S International Holding Co. Inc., [1991] 2 Lloyd‘s L.Rep.,
127; P. T. Tri-M.G. Intra Asia Airlines v Norse Air Charter Limited, [2009] SGHC 13
9MANU/SC/0232/2000 : (2000) 4 SCC 272;
10Also see, Lobb Partnership Ltd. v. Aintree Racecourse Co. Ltd. [2000] BLR 65
11See, for instance, Article 12 of the Arbitration Rules of the Arbitration Institute of the Stockholm Chamber of Commerce, 2010; Article 7(1) of the UNCITRAL Arbitration Rules, 2010.
BA (Law) LLB (SDM Law College, Mangalore University, India) LL.M.(WB National University of Juridical Sciences, Kolkata), Associate of the Insurance Institute of India, Member,
Chartered Institute of Arbitrators, UK.Currently working as Senior Executive (Law), Bharat Heavy Electricals Limited, Ranipet, India.
Badrinath SrinivasanBA, LLB, LL.M.
57 IIQS - 2015 | 56 | IIQS - 2015
“Unless commitment is made, there are only promises and hopes; but no plans”. Peter Drucker.
Programming and planningLifeline Of A Project
This article will focus on the PROGRAMMING AND
PLANNING competency requirement for Contract &
Commercial / Quantity Surveying (QS) professionals
who are involved in property and construction industry.
Generally a program for a construction Contract is a
commitment and an obligation. Whether it is a Developer or a
Contractor, application of proper programming and planning
techniques right from the inception stage will help them to
identify the opportunities and risks to complete the project on
TIME and within the BUDGET.
The Developer ’s master program must be fully coordinated
with the chosen procurement route. The master program
must consider design, construction, defect liability period and
handing over etc. Once the selected Contractor enters into
a Contract agreement with the Developer, he is under the
obligation to prepare and submit a program in accordance
with the Contract provisions, e.g. FIDIC 87 clause 14 or FIDIC
99 clause 8.3. This program is known as the Contract program
and it is important that the Contractor incorporates his chosen
construction methodology in compliance with the Contract.
Inadequate planning and scheduling can cause major delays
to the project. Accordingly, all the potential risks and delay
events are assessed and addressed within the program as
the project progresses to minimize the program risks. Some of
the common delay events faced are, difficulties in obtaining
work permits from local authorities, changes in government
regulations and law, lack of both skilled and unskilled labour,
strikes, bad weather conditions, poor standard of safety
management, delay on materials to be supplied by developer.
Generally in Middle East, projects are planned, designed
and constructed within a very strict timeline. Due to the strict
program requirement, proper programming and planning
of works from the onset is implemented in all of the projects.
Time, Cost and Quality are considered equally important in
majority of the projects and therefore there is no compromise
on these aspects. Timely completion will help to avoid cost
escalation, budget increase, disputes, etc. Therefore it is
important that a project is planned, monitored and executed
within a strict timeline.
PROGRAM BACKGROUND
In the early 1900s Henry Gantt developed a type of bar chart
called Gantt chart, which illustrates a project schedule with
start and finish dates of the activities of a project. At that time,
this was widely welcomed as Gantt Chart was successfully
used to build the ships in record time.
In the 1950s, Program evaluation and review technique (PERT)
was developed by the U.S. Navy and a consulting firm of Booz
Allen and Hamilton to facilitate the Polaris missiles project.
PERT is a method to evaluate and estimate the time required
to complete a task within targets.
In the late 1950s, the critical path method (CPM), a project
modeling technique developed by Morgan R. Walker of
DuPont and James kelley of Remington Rand. A sequence
of activities is called a ‘path’, and the longest-path in the
diagram is the critical path. It is ‹critical› because all activities
on it must be completed within the assigned time to prevent
delay.
In 1983, software Primavera was launched by Primavera
Systems Inc. Primavera software includes project
management, collaboration and control capabilities and
integrates with other enterprise software such as Oracle or
ERP systems. Currently Primavera software is widely used to
manage project program.
Indian Institute of Quantity Surveyors membership criteria
includes Programming and Planning competency as
follows:
• Knowledge, interpretation and application of
programme and schedules being used in the projects
involved by the applicants.
The assessment includes questioning on project program; the
following guidelines will used to explore the knowledge of the
candidates.
From a Contractor ’s perspective, the pre-contract planning
may not have much significance. Whereas from a Developers
perspective pre-contract planning will have a major
significance and a detailed planning is required at various
stages such as Feasibility, Master planning, Concept design,
Schematic design, Detailed design, tender stage, etc.
The programming and planning updates are extremely
important throughout the construction duration as any delay to
the project need to be analyzed carefully in accordance with
the contractual delay analysis mechanism. The commonly
applied forensic delay analysis techniques are Impacted As-
Planned, Collapsed As-Built, As-Planned versus As-Built, Time
Impact Analysis.
Forecasting the right quantity, quality and source of material to
align with the requirement and availability within the program
is important to ensure that unexpected delay won’t occur due
to delay in delivery of material.
Forecasting of man-power in accordance with proven out-
put achieved for a similar works will help to identify the overall
resource requirement based on the programme schedule.
The forecasting of cash flow should include revenue and
expenses taking into consideration of advance payment,
retention and actual pay-in and pay-out to calculate the cash
flow projections.
• Knowledge and interpretation of other programming
techniques, pert diagram, network analysis / critical
path method.
This will include questioning on technical details of program
aspect including, PERT, CPM, float, explanation on early start
and late start, different type of the activity relationships, etc.
The following outline will be used to explore candidate’s
knowledge.
Program Evaluation and Review Technique (PERT) and
Critical Path Method (CPM) are tools widely used in project
scheduling. Perhaps, the greatest contribution of these
tools is the identification of critical activities that require the
closest monitoring.
One of the planning techniques used to forecast expenditure
of a project is to create a cost loaded program in primavera
and the same is used in many of the projects to update
the monthly progress for the interim progress payment.
Also, check would be required to ensure if the program is
levelled, so that the resource requirements are uniformly
spread during the construction, material deliveries are
properly planned, and execution methodology is carefully
analyzed and implemented.
As can be seen from the aforementioned, the Programming
and Planning competency is much wider than the knowledge
of planning software. Competent Contract & Commercial
professionals with PROGRAMMING and PLANNING skills will
help the project to be completed on TIME and within the
BUDGET.
Mr. Varughese Mathew has Master of Laws (LLM) in Construction Law and Arbitration and is a Fellow (FRICS) of Royal Institution of Chartered Surveyors, Fellow (FCIOB) of Chartered Institute of Buildings, Member (MCIArb) of
Chartered Institute of Arbitrators, Member (MIIQS) of Indian Institute of Quantity Surveyors.Varughese has extensive experience in construction and property development and been in senior positions with Skanska, Carillion, EC Harris, Al Faraa and currently with Tourism Development and Investment Co in Abu Dhabi.He headed Contracts, Commercial, Cost Control, Procurement, Planning and legal departments and successfully
managed several court cases and Arbitration related to property development and construction in UAE.
Varughese MathewLLM, FRICS, FCIOB, MCIArb, MIIQS
59 IIQS - 2015 | 58 | IIQS - 2015
Cost planning / estimating is a method of providing cost data assists the project team to make the appropriate design decisions. The client may have cost limit for the project and /or may have established a design brief which narrates the client’s needs. To ensure that the client obtains the best value for money, the design must be economical.
Cost Plan Stages
Typically cost planning is carried out at the completion each
of the following stages of the project pre-contract phase.
1. Feasibility stage
2. Concept Design stage
3. Schematic Design stage
4. Detail Design stage
The cost plan carried out at the feasibility stage is validated at
the end of the concept design stage. Typically in large projects
the cost plan that is approved by the client at the end of the
concept design stage is set as the budget for the project.
It may be noted that the cost plan produced at the end of
detail design stage is typically based on the Bill of Quantities.References and citations
College of Estate Management, Reading, Uk, cost planning module (1996)
New Rules of Measurement (NRM) by Royal Institution of Chartered Surveyors,2nd edition (2012)
Order of Cost Planning
The information provided in the cost plan must be in a form
that can be understood by all parties i.e. and hence it must
be presented in a proper elemental breakdown.
Lack of consistency in measurement and description makes it
extremely difficult for the client and project team to understand
what is included in the cost plan / estimate, cost limit or cost
target advised by the quantity surveyor; often resulting in
doubts about the cost advice provided. In order to overcome
this, the Royal Institution of Chartered Surveyors (RICS) have
produced a document called ‘New Rules of Measurement
(NRM) in 2009. This document provides guidance to quantity
surveyors so that a common and consistent basis is used to
measure areas and building works items for the purpose of
cost estimates and cost plans. It also provides guidance on
providing a structured approach for dealing with the other
constituents needed to calculate cost estimates, cost limits or
cost targets. The New Rules of Measurement (NRM), Volume 1
is for ‘Order of cost estimating and cost planning for capital
building works.
The appendices to the NRM, volume 1 contains the logic and
arrangement of levels 1 to 3 for elemental cost planning.
Basic Elements Required for a Cost Plan
The basic elements required for the preparation of a cost plan
are:
• Project Description
• Project Location
• Intended Building Use
• Client Brief / Design Information / Outline / Detailed
Specifications
• Historical Data
• Area Information
The following information shall also be included in the cost
plan to serve as an audit trail.
• Drawings and specifications used
• Any assumptions made
• Inclusions / exclusions
• Run date
• Source of data used
Conclusion
To conclude, it is an important role of quantity surveyor in a
project to provide cost plan produced in a systematic manner
at the conclusion of each stage of the design development.
A good cost plan is an essential ingredient for a good cost
management of a project.
Refer to sketch 1 below on project cycle
Cost Plan Process
The process chart shown below will assist the readers in the
understanding of the process involved. Note that ‘Value
Engineering; has a close relationship to the cost planning
process.
Sketch 2 - Cost Planning Process
Cost Plan Development
The relationship between the cost plan development and
the stages of the design development is shown in the sketch
below and will provide the reader an understanding in an
effective manner of the cost plan development.
Sketch 3 – Cost Plan Development
Cost planning
Sam is the Associate Director in Mace , Dubai and he is a qualified Civil Engineer and a Chartered Quantity Surveyor. Sam has over 25 years of experience and 15 years with British Consultancy organizations such as Bovis and Mace.
Sam provides training on cost management in Mace and has also conducted CPD events forCollege of Estate Management and Institute of Quantity Surveyors –Sri Lanka and he is the member of :
a. Member of Institution of Engineers (India)b. Member of Institution of Surveyors (India)c. Fellow member of Royal Institution of Chartered Surveyors, RICS (UK)
Sam Raman AMIE (India), B.Sc. (Hons.) (UK), MIS (India), FRICS (UK)
61 IIQS - 2015 | 60 | IIQS - 2015
The approach to cost management within a project is highly dependent upon the processes, policies and standards used in the host organisation. Cost management in a real estate project, will demand standard set of processes to map the cost at WBS level. All stakeholders might have different expectations from their project, but such expectations will create thrust to bring in processes and policies for effective cost management.
Cost Management
Is it tricky to manage costs in real estate projects? Are we
doing or managing something unusual? Answer is NO.
Still we normally observe cost is going up in projects. Someone
can enumerate reasons for such change but it ’s important to
bring it on table at the right time where Project Manager can
take corrective action to maintain project margins.
Right base accompanied with proper understanding on
scope and timelines is the key for any project. Most of the
time, controllers are not aware of the scope and timeline for
which project need to perform. Once the project is underway,
actual and forecast expenditures can be regularly monitored,
in fact it should happen that way. Use of standard cost report
is normally recommended where each elemental head will
get tracked in terms of its budget, commitment, anticipated
changes and actuals at pre-defined frequency. Frequency
of reporting and WBS are closely linked with the total value,
timeline of the project. Both these parameters can be
improved to bring out the desired results.
Let us see how such report will get evolved as project
progresses.
• WBS wise budget – provision available to complete the
desired scope within the desired time.
• Order value and agreed changes – actual value of
awarded work and changes agreed from time to time
with approval from project sponsor.
• Anticipated changes / unplaced order – provision kept
and weighed at frequency for the works not covered in
the scope awarded. Rigorous updates on this section is
important but often found un-attended and results into
uncontrolled cost report.
• Actuals also plays great role and gives idea on financial
completion of the project.
• The forecast cost is then sum of commitments, accruals,
actual expenditure and an estimate of the cost to
complete the balance works.
Graphically, a report showing S-curve for the original plan
along with updated S-curve of actual spend to date, can
quickly highlight financial status of the project. Such early
projections will help Project Manager to bring-back the project
on track and assures completion of project with minimum
variation of time as well as on cost front.
Table 1 – sample report at the start of the project (day ‘0’) - available data/budget has been captured under key
elemental heads.
Table 2 – sample report form after 3 months - excavation and shell and core works awarded.
Budget for shell and core has broken down further to reflect change in contracting strategy, separate heads to
capture purchase of concrete and steel as free issue material.
Table 3 – sample report form after 6 months - finishing and services works awarded (except lifts and DG works).
Such detailed monitoring and reporting on cost at predefined intervals will definitely help project management decision
making, increase accountability and responsiveness of the Project Manager. It will also help to bring in more control and to
provide consistent and reliable cost forecasts.
Reports/ elemental heads can be customized to meet unique requirements of any project /Project Manager. Review and open
discussion on such reports is important to maintain desired quality, accountability and ownership of cost. % completion
at the end of the report is typically financial completion of project and someone should not mix this with physical progress of
project.
General Manager - Contracts and C&B with Godrej Properties Ltd. Cost control engineer with 14+ years of professional work experience in Cost management, Feasibility studies, Formulation and roll-out of SOP’s, Planning of multiphase
projects & large townships and Audits of Real estate & Hospitality sectors in many parts of the India.
Nilesh Kushe MRICS, ME-Civil, CPM-OM
63 IIQS - 2015 |
Life Cycle Cost Analysis (LCC) advocates reducing the life cycle costs for buildings, equipments in wide areas within all sectors by showing why reliability and maintainability must be included in upfront decisions for strategic and tactical issues of achieving the lowest long term cost of ownership. LCC concepts are resurging presently within global organizations, responsible MNCs with Corporate Social Responsibility (CSR) in place, including worldwide Government efforts to minimize energy costs. A thorough Project Delivery Process (PDP) that addresses all aspects of planning, budgeting, design, and construction should be the basis of LCC.
Cost-effectiveness is a key component of
design for all projects, and initial project
costs are the focus of many activities in
the PDP. The long-term cost implications of building
projects, however, range far beyond initial design and
construction expenses. As the industry grows and ages,
the cumulative cost of operating and maintaining
facilities significantly impacts the overall institutional
budget. To improve the cost-effectiveness of its building
and renovation programs, we must invest in designs
and systems with improved long-term performance.
Why use LCC?
LCC helps change provincial perspectives for business issues
with emphasis on enhancing economic competitiveness by
working for the lowest long term cost of ownership which is not
an easy answer to obtain. Consider these typical problems
and conflicts observed in most companies: 1. Project Engineering wants to minimize capital costs
as the only criteria, 2. Maintenance Engineering wants to minimize repair
hours as the only criteria, 3. Production wants to maximize uptime hours as the
only criteria, 4. Reliability Engineering wants to avoid failures as the
only criteria, 5. Accounting wants to maximize project net present
value as the only criteria, and
6. Shareholders want to increase stockholder wealth as
the only criteria.
Management is responsible for harmonizing these
potential conflicts under the banner of operating for
the lowest long term cost of ownership. LCC can be
used as a management decision tool for harmonizing
the never ending conflicts by focusing on facts, money,
and time.
Engineering always want a simple, single value, criteria
for a project—the answer for LCC is called net present
value (NPV). NPV is the present value of proceeds
minus present value of outlays. Projects and processes
with the greatest NPV is usually the winner. Often for
incremental changes on a project or within a plant,
you lack enough details to arrive at a positive NPV. Thus
many improvement projects must be selected on the
least negative NPV values from many alternatives. So
once again, we can have the single number engineers
always want—it’s NPV but in this case, it ’s the least
negative NPV.
Designing for Minimum Life Cycle Costs
LCC is a method of evaluating the cost-effectiveness
of project design decisions. LCC is comprehensive
because it properly accounts for many project cost
Life Cycle Cost Analysis
65 IIQS - 2015 | 64 | IIQS - 2015
variables. These include a wide variety of project
costs (construction, operations, maintenance,
replacements, utilities, etc.). They also encompass
the time value of money, including a project-specific
discount rate, inflation, and cost escalations for a
variety of goods and services.
The LCC Process
Performing an LCC study involves (1) establishing
objectives for the analysis, (2) determining the criteria for
evaluating alternatives, (3) identifying and developing
design alternatives, (4) gathering cost information, and
(5) developing a life cycle cost for each alternative.
What goes into LCC?
LCC includes every cost that is appropriate and
appropriateness changes with each specific case
which is tailored to fit the situation. LCC follows a
process (Fabryck 1991- Appendix A) as shown in
Figure 1. The steps are:
Step 1-Identify what has to be analyzed and the time
period for the project life study along with the
appropriate financial criteria.
Step 2-Focus on the technical features by way of
the economic consequences to look for alternative
solutions.
Step 3-Develop the cost details by year considering
memory joggers for cost structures.
Step 4-Select the appropriate cost model, simple
discrete, simple with some variability for repairs and
replacements, complex with random variations, etc.
required by project complexity.
Step 5-Acquire the cost details.
Step 6-Assemble the yearly cost profiles.
Step 7-For key issues prepare breakeven charts to
simplify the details into time and money.
Step 8-Sort the big cost items into a Pareto distribution
to reconsider further study
Step 9-Test alternatives for high cost items such as what
happens if maintenance cost is ±10% than planned,
etc
Step 10-Study uncertainty/risk of errors or /alternatives
for high cost items as a sanity check and provide
feedback to the LCC studies in iterative fashion
Step 11-Select the preferred course of action and plan
to defend the decisions with graphics LCC combines
acquisition and sustaining costs. Acquisition and
sustaining costs are found by gathering the correct
inputs, building the input database, evaluating the
LCC and conducting sensitivity analysis to identify cost
drivers.
Summary Life-cycle costs include cradle to grave costs converted
to NPV economic models. When failure costs are
included, the quantity of maintenance manpower
required can be engineered which avoids the use
of antique rules of thumb about how maintenance
budgets are established. LCC is a method to correctly
consider long term business decisions which have
advantages for profitability. LCC is not easy, but it is
effective for building a sound business case for action. LCC is the “laser guided missile” attack on important
business problems for projects and processes—of course
it requires greater sophistication than attacking problems
with proverbial “hammers, tongs, and brute force”.
Good alternatives for LCC require creative ideas. This
is the role of the Quantity Surveyor to suggest and
recommend cost effective alternatives. Much lower
LCC are obtained when creative efforts are employed
in the design area--making changes downstream in the
operating plants has smaller chances for improvements
because it ’s employed too late in the improvement
cycle. Design engineers are the most important link in
devising cost effective plants and naturally the burden
of LCC falls on their shoulders—but design engineers
can’t perform an effective analysis unless they have
reasonable data from operations.
LCC is simply a way-stop on the never ending journey for
reducing costs. LCC is clearly not a destination. LCC
provides the tools to engineer maintenance budgets,
ownership costs, and present decision making scenarios
in a financial perspective to achieve the lowest long
term cost of ownership.
Mr. Jacob Joby a Bachelor of Civil Engineering, a Certified Cost Engineer (CCE), Member (MIIQS) of Indian Institute of Quantity Surveyors and Masters in Business Administration in Real Estate.
Jacob is a mixed –use Development and Commercial Specialist with over 19 years of experience having worked in senior positions with Dubai World, Nakheel, Turner, Khansaheb and Strabag. Currently a Director Development with
Shapoorji Pallonji Group his management experience covers all aspects of the development lifecycle from business planning and strategy, to project visioning and feasibility, master planning and design, financing, construction, sales and
marketing and asset management related to property development and construction in UAE.
Jacob JobyCCE, MIIQS
Figure2:AcquisitionCostTree Figure3:SustainingCostTree
Acquisition costs have branches for the cost tree
shown in Figure 2 as a memory jogger.
Sustaining costs have branches for the tree as
shown in Figure 3 which is also a memory jogger.
Figure1:LifeCycleCostingProcess
67 IIQS - 2015 | 66 | IIQS - 2015
A provisional sum is the sum included in the contract and so is designated in the bill of quantities for the execution of work or the supply of goods, materials or services or for any contingency, (Rushbrooke n.d.).
Do we need the Provisional Sums?
P rovisional sums are introduced into the bills of
quantities during the preparation of the tender
document stage usually because:
(i). Some of the work could not be adequately decided and
detailed out by the Client before tendering;
(ii). Some of the work could not be designed by the design
team before the tender was sent out for the Contractors;
(iii). There was a need for specialist suppliers of materials or
Sub-Contractors who would be later nominated as the Sub-
Contractor or supplier by the Client to the Main Contractor;
(iv). There was a uncertainty whether some work was required
or not;
(v). Work required to be executed by the local authorities.
The advantage of this procedure is that the employer does not
have to enter into a series of separate contracts with various
parties in the same project, (Wainwright W.H., and Wood A.A
B 1983).
The definition for the provisional sums has been given in
many of the standard forms of contracts. In Sub-Clause 58.1
(Definition of “Provisional Sum”) of FIDIC fourth edition has
given the descriptive definition. Similarly, Sub-Clause 1.1.4.10
(Provisional Sum) under the definition of FIDIC 1999 edition has
given a brief definition:
“Provisional Sum” means a sum (if any) which is specified
in the Contracts as a provisional sum, for the execution of
any part of the Works or for the supply of Plant, Materials or
services under Sub-Clause 13.5 (Provisional Sums)”.
(In addition to the standard forms of contracts, the standard
method of measurements has also given some definitions
for the provisional sums. In the Principles of Measurements
(International) – June 1976 (POMI) under the clause GP6
(Work to be executed by a specialist nominated by the
employer), under clause GP7 (Goods, materials or services to
be provided by a merchant or tradesman nominated by the
employer), and GP8 (Work to be executed by a government
or public authority) has defined how to include a sum for the
work, services, and materials that is not comprehensively
identified at the time of tendering. In these three scenarios
it had generally been stated that “Unless otherwise required
by the conditions of the contract …. shall be given as a
sum; such sum shall be exclusive of profits…” meaning to the
provisional sums.
Civil Engineering Standard Method of Measurements-third
and fourth editions, CESMM-3 and 4, has also defined the
provisional sum under paragraph 5.17 and 5.18 respectively.
The definition given in the paragraph 5.18 of the CESSM-4 is
somewhat practical compared to CESSM-3 and POMI, thus:
“Provision of contingencies shall be made by giving Provisional
Sums in the Bill of Quantities and not by increasing the
quantities beyond those of the work expected to be required.”
The second sentence of the paragraph 5.18 has clearly
defined the provisional nature of the work, thus:
“Provisional Sums for Defined Work shall be included where
work is known to be required but the scope of the work cannot
be completely designed but the scope can be defined”.
Application of Provisional Sums
In most of the tenders, it is a standard practice to include
provisional sums for the mechanical and electrical engineering
services, vertical transportations, special finishing items,
swimming pools, boundary walls, landscaping and similar
work. The design team normally delay the design of these
elements of the project and include them as provisional sum
to the tender. Thereby, they save time to detail these elements
of the design and to some extent save their cost by transferring
the design scope to the specialist Sub-Contractors under the
provisional sums. The question is that would the Client get
the value of services for the fee he paid to the design team?
According to most of the consultancy agreement, the design
consultant shall design the whole project. However, by using
the provisional sum clause in the contract and with the option
of part of the permanent work designed by the contractor
(Sub-Clause 7.2 of FIDIC-1987 [Permanent Works Designed by
Contractor] and Sub-Clause 4.1 of FIDIC-1999 [Contractor ’s
General Obligation]), most of the consultants are pushing
these work elements to the provisional sums. This will transfer
the issues onerously to the Clients to make timely decision on
the procuring of nominated Sub-Contractors and suppliers to
comply with the contractors programme.
Further, during the post-contract stage, the design consultants
may develop the performance specifications with the input
of post-contract supervision staff and with expert contribution
from the Main Contractor. Thereby, the Client may not be
received the intended design input from the professional
consultant. Having provisional sums in the contract it would
lead to extension of the time claim situation due to the
procurement strategy to be followed by the Client and its
decision making process and procedures. Such extension
time to the contract would benefit both the contractor and
the consultant in commercial business points of view.
Effective Use of Provisional Sum Provision
The use of provisional sum clause in the contract shall be
beneficial to the Client and to the project. No provisional
sums shall be allowed to the tender unless it is really
required. The design team shall take all endeavors to
complete the design prior to tendering the project. Thereby,
the Client would be able to receive the cost certainty in
view of the completeness of the design. Further, the Client
would be able to avoid numbers of sub-contract tendering
packages, for which Clients have to invest more resources
over and above the main tender package. However, this is
practical only if the Client allows a sufficient design period
to the consultant to complete the design prior to the tender.
Selection and nomination of Sub-Contractor either by the
Client or through the Main Contractor is a time consuming
process. By avoiding provisional sums in the tender and
by including such items in the bills of quantities, the Client
would be able to get the cost certainty, less requirement
of coordination and less requirement of management of
procurement and nomination of Sub-Contractors, avoid
potential claims due to delay in instructing the use of
provisional sums (Sub-Clause 58.2 [Use of Provisional Sums]
of FIDIC -1987 or Sub-Clause 13.5 [Provisional Sums] of
FIDIC-1999).
Conclusion
It is a practice to use provisional sums in the tender
documents by the Clients largely due to influence of the
design consultant. This may be due to the failure to complete
the design completely prior to the project tendering. This
would occur due to two reasons; (i) lesser time allocation for
the design period, and (ii) the consultant ’s failure to meet
the design program. A third reason would be that Client
would want to accelerate the project tender program.
Parties shall extend their maximum effort to avoid the
inclusion of provisional sums within the tender so as to get
the price certainty at the time of signing of the contract
and avoid future disputes with the Main Contractor, as well
as to save the resources of the Client in the procurement
and nominating of Sub-Contractors and Suppliers.
References
Rushbrooke. n.d. Working with FIDIC, a practical approach to its use in the Middle East. Dubai: Middle East Construction, 16.
Wainwright W.H., and Wood A.A B. 1983. Variation and Final Account Procedure. London: Hutchinson.
Ajantha PremarathnaMSc. (PM), MBA (PIM-USJ), FRICS, FAIQS, FIQSSL, ACIArb,
AIQS and RICS APC Assessor and Chairman,Former member of MENEA World Regional Board of RICS,
UAE Country coordinator for AIQS and IQSSL,Director of Contracts and Procurement Department of Dubai Properties LLC
69 IIQS - 2015 | 68 | IIQS - 2015
As human beings, we view ‘change’ differently and our perception changes depending on the circumstances and what is the change we are hoping for. The truth is that whether the change brings good or bad, one thing is certain. Change is inevitable. As the famous French author François de La Rochefoucauld once quipped “The only thing constant in life is change”.
“Managing the Change” in Construction projects
“Change” defined
We all recognize that changes are inevitable in construction
projects and hence it has to be managed effectively to
minimize the impact. The change is viewed differently by
various stakeholders. The contractor perceives that a change
will bring in more revenue as a positive variation; whereas the
Consultant or Supervising Engineer view the change not as a
variation to the Works but only an explanation of the scope that
the contractor deemed to have priced for. Finally, despite the
desire to change or enhance the original design, the Client/
Employer1, may take a restrictive view and may hesitate to
adequately compensate for the changes.
Project changes are inevitable at every stage of design
and construction. Changes could be for two reasons. Firstly,
change in the Contract terms and Conditions itself, in which
case it amounts to amendment of the Contract and the
requirements of authorized signatories are to be complied
with. However such changes are rare in construction contracts.
More often the changes are in the scope of work or sometimes
on the method of working. Changes may arise due to poor
initial planning, design errors and gaps, technical innovation,
emerging of new products, changed circumstances However,
the reality is that Employer ’s change in requirement is the most
common reason for a variation in a construction contract.
Although the Contractor ’s first reaction is that additional work
means extra money, the underlying risk of a variation is the
consequences of delays and disruption and establishing
them aren’t easy and mostly likely to land in dispute.
Change management under FIDIC
Standard forms of Contract normally address the issues arising
due to changes, but it is important to understand how the
terms of the Contract allocate risks between parties and how
the change management procedure has been stipulated.
The change is normally described as variation under FIDIC
suite of contract. But a variation is not a claim. The loose
terminology often used goes like this “The Contractor is
claiming for variation or claiming for payment against interim
valuation”. For example, under FIDIC 992, the claims are to be
administered under Clause 20.1 and this is the overall clause
where the Contractor is instructed to bring any claims for
additional time and money and failing which the contractor
loses his entitlement. In short, it is the Contractor who will
notify and bring claims against the Employer. On the other
hand, variation is often instructed by the Engineer on behalf
of Employer and could be either addition or omission to the
original scope.
FIDIC empowers the Engineer to initiate variations either by
instruction (Sub Clause 3.3) or by a request for the Contractor
to submit a proposal (Sub-Clause 13.1). An instruction can be
issued at any time to the extent that it is necessary for the
execution of the Works (Sub-Clause 3.3).
In order to avoid instructing variations without the understanding
of its consequences, the Engineer will usually request a
proposal from the Contractor (Sub-Clause 13.3). The latter will
then respond in writing as soon as practicable, either by giving
reasons why he cannot comply or by submitting a detailed
proposal.
The Contractor is bound to execute each variation, unless
he promptly notifies the Engineer that undertaking the varied
work is not possible for the reasons beyond his control. The
Engineer is not permitted to omit work in order to have it done
by others. He is also not permitted to amend the conditions of
the contract. Thus variations must not differ radically from what
the Contractor has already promised to do. The Contractor is
also entitled to initiate variations on special grounds3. This kind
of variation has been named Value Engineering.
Need for robust change management procedure
It is important to have an established change control
procedure in place. In absence of this, quantity surveyors or
contract managers from both sides will end up having different
perception of scope and technical requirements which
could potentially result in dispute and delay. It is worthwhile
to establish a good change management procedure and
agree the changes in a fair and reasonable manner, More
often than not the variations are being evaluated only after
substantial completion of the work and both parties arguing
on the methodology and cost inputs. This practice puts the
Contractor in a difficult situation as the contractor need to
finance the varied scope of work upfront pending approval
of his costs.
A robust change control mechanism must capture change
estimation, impact analysis, post change analysis, statistics,
and more importantly, change traceability. An integrated
change management system requires technical supports
from different technologies, including collaborative workflow
and system integration.
Minimize changes, Contract with care!
This author is not against a change or variation incorporated in
a project. The emphasis is that a change must be always an
exception and must be justified. It is not just enough to have
a change control clause in the Contract. The design must be
complete and scope of work must be carefully and clearly
defined. The design team must understand the risks of design
errors and gaps and unless the team has satisfied with the
documentation the project should not even be tendered. The
Employer must understand the consequences of instructing
changes to a project during construction and the steep price
to pay for the associated delays and disruptions. Similarly the
contractor must ensure that the ambiguities in the scope and
technical requirements are carefully reviewed and clarified
during the tender process.
Changes may have considerable negative impacts on items
such as costs and schedule delays. A critical change may cause
consecutive delays in project schedule, re-estimation of work
statement, and extra demands for resources. Changes, if not
resolved through a formalized change management process,
can become the major source of contract disputes and can
contribute to project failure.
Effectively managing change orders in construction processes
is not trivial because change orders are a part of contract and
they need to be strictly traced in terms of contracts, documents,
approval process, payment claim, etc.
Proposed change control model (Ten Commandments)
1. No change of work without written instruction
2. Is the contractor is obligated to propose improvements or
value engineering?
3. Format and requirements of a change proposal and
approval protocols
4. Simplified procedure to agree minor changes (of smaller
value)
5. Who bears the cost of preparing change proposal? If the
proposal is declined, is the costs are reimbursed?
6. Procedure for agreeing time impact due to proposed
changes
7. What records to be kept by both parties? (Audit
requirements)
8. Notice requirements
9. A workable and swift dispute resolution mechanism (like
DAB)
10. Most importantly, training of all stakeholders of the
change management procedure
Finally, I will sign off this article with another famous quote
by Richard Hooker who said, “Change is not made without
inconvenience, even from worse to better.” So true in our
industry!
1 The terminology used in the article is based on FIDIC: Client is referred as Employer and Con-
tract administrator or supervising Engineer is referred as Engineer; Thankfully Contractor retains his title in all standard forms of Contract.
2 Conditions of Contract, FIDIC New Suite (1999) First edition
3 Sub-Clause 13.2 of FIDIC 1999
Venkat is an experienced trainer, author and distinguished speaker on various topics related to Contracts and Commercial management.. He has trained more than 600 professionals in the past two years and conducted several
workshops in the GCC region. His papers have been published in leading construction and arbitration journals.Venkat has over 30 years of experience in GCC and India in every aspect of construction and he has worked with
leading consultants and international contractors in the region.Venkat is one of the founding partners of ‘C Cubed Consultants’, a Contracts and claims management consultancy based in UAE. He advises Clients, Contractors on various aspects of contractual matters and helps them to resolve
their disputes in an amicable and practical way.
R Venkat Rakhavan, LLM, B.Eng., C.Eng., MRICS, FCIArb, FCMADirector, C Cubed Consultants Limited, UAE.
71 IIQS - 2015 | 70 | IIQS - 2015
When a party is obliged to make regular payments for a service under a contract, how many non-payments and/or late payments must occur before the victimised party can terminate? What amounts to a repudiatory breach in the context of an ‘innominate term’ to make regular payments? Valilas v Januzaj [2014] EWCA Civ 436 has laid down a marker for how the Court will treat non-payment.
V alilas (“Claimant”) is a dentist practising under oral
agreement since 2007 for the use of premises,
equipment and facilities and in return would pay
Januzaj (“Defendant”) 50 per cent of his receipts. Claimant
received most of his earnings under a contract with the
local health care centre where he received a fixed price per
unit. Payment was made by the local health care centre in
advance in equal monthly instalments (unit did not have to
be spread evenly through the year) but if Claimant did not
achieve the requisite number of units by the end of the year,
he had to refund the overpayment to the local health care
centre.
Claimant was prompt in his payment to the Defendant
from the commencement of Oral Agreement. However, at
a later point of time, the Defendant asked Claimant to sign
the associate agreement, following which the relationship
between them broke down. In addition, Claimant could
not achieve the target units on time. Claimant feared that
the Defendant would not refund his portion of the payment
received from the Cliamant, at the end of the financial year
(31 March 2011), in the event of a short fall in meeting the
required units. Fearing this, Claimant stopped making the
payments from August to September 2010 and later offered
to reconcile the payment at the year-end. However the offer
was rejected by Defendant and expelled the Claimant from
the premises on 11 Nov 2010.
The issue before the court are:
1. Whether Claimant› failure to pay Defendant for the use
of its premises, equipment and staff under an oral
agreement for three months constituted a repudiatory
breach/renunciation of the contract
2. Whether Defendant was deprived of substantially the whole
benefit of the agreement
3. Whether Payment obligation is a innominate / intermediate
term
4. Whether Claimant’ breach went to the root of the contract
5. Whether excluding Claimant from the premises was
wrongful
6. Is there any provision in the Contract to terminate for non-
payment
Decision
The Court of Appeal instantly turned down Defendant›s primary
case on the basis that in accordance with the Contract the
payment should be done on time by the claimant. Taking
into consideration, time of payment is not generally of the
essence1 of a commercial contract unless the parties have
agreed (either expressly or by necessary implication). It
rather continued on the basis that the applicable term was
‹innominate› or ‹intermediate› – other way around, whether
the actual or threatened breach repudiated the contract
based on the nature and effect of that breach.
The delayed payment did not cause any harm to the
Is it possible to Terminate due to Non payment and/or late payments?
defendant. The only likely loss to the Defendant was “the
loss of the use of money in the meantime”. The Breach is
considered Repudiatory only when the breach deprives the
innocent party substantially of the whole benefit2 that it was
supposed to have obtained as per the contract.
Whatever be the reasoning, a breach must go to the root3 of
the contract. In reality, at the offset, the consideration should
be given to the benefit gained by the injured party from the
execution of the Contract, and then one must consider the
effect4 of the breach on the injured party. Although a declared
intention by a party to execute a contract in a manner
substantially inconsistent with his obligations may amount to
a renunciation5 of it.
As per Lord Justice 3, the departure should be evaluated on
the basis that whether it goes to the root of the contract or not.
Though, Lord Justice 2 reads ‘going to the root of the contract’
as entailing “the failure must be compared with the whole of
the consideration of the contract and not just a part of it”, it
seems to be not consistent6.
Lord Justice 1, in a sound disagreement, judged that 3
non-payments, preceding to termination was a repudiatory
breach. His main argument was that Claimant had intentionally
decided to deviate from the contractual arrangement. In the
interim, defendant left the claimant to bear the running cost
of the Practice.
Lord Justice 2 & 3, by contrast, underscored their point that
Claimant’s delayed payment to the Defendant was not a
denial of payment but that it was purely a delayed payment.
The Appeal Court, by a majority of two to one, found that
failure to make payment is not a repudiatory breach. The
Court upheld the decision and dismissed the appeal.
When someone considers signing a contract for work in the
UAE or Qatar and the contract is to be governed by respective
law. Then one has to take notice of the local laws that apply
to this subject.
Remedies Under Civil Code
UAE Civil Code
The UAE Civil Code provides for the possibility of bringing a
contract to an end where its terms are silent on the right to
terminate. The UAE Civil Code does not mention suspension
expressly, but Article 247 does provide some limited comfort,
as it states that a party may refuse to continue its obligations
(i.e. carrying out of the works) if the other party is not performing
its obligations (i.e. payment).
The risk in relying exclusively on Article 247 in suspending work is
that following suspension the owner could look for terminating
the contract on the basis of the contractor ’s breach of
performance. Should a party want to terminate a contract
for breach (in the absence of express contractual terms as
to termination), ordinarily, that party shall file an application
with the local courts for an order granting that entitlement.
Provided the order is granted, a contractor may also be
entitled to damages for the owner ’s breach.
Qatar Civil Code
Multiple remedies exist under Qatar Civil Code for non-
payment. A party may submit an application to a Civil Court
to grant an order for payment of sums due after requesting
the other party to pay the due in not less than five days
73 IIQS - 2015 | 72 | IIQS - 2015
(Article 147 of Law No 13, 1990). If the other party fails to pay,
sums due for works already carried out under a Contract, the
party may Suspend the works unless it is otherwise agreed
between the parties (Article 191) or else, after notifying the
other party, request the Termination of the contract together
with compensation (Article 183(1)). The Court has options to
determine a grace period within which the other party shall
pay such sums (Article 183 (2)).
Author’s View
In reality, after Valilas, especially while assessing repudiation
for the late payment, the court shall draw distinction between
what has to be considered as non-payment and how to treat
the late payment. It is very difficult to show late payments
to be repudiatory in contrast to non-payments. One should
keep in mind that the test for repudiation is on par with
frustration of the contract. For a late payment to qualify as
being repudiatory, it should be severe7 enough to “demolish
the… confidence [of the claimant] in the defendants’ ability
to pay…”.
A failure to make a single progress payment does not
necessarily constitute a repudiatory conduct, although it
may seem so8. On the other hand, a repeated failure to
make payment when it is due may constitute a repudiation9.
Hence, it is critical to determine the reason for the non-
payment.
A small and inadvertent delay can be remedied by the
payment of interest. But where the reason for the non-
payment is either, i.e.:
• (a) wrongful refusal to pay an amount which is
properly due or
• (b) where there is substantial and seemingly
terminal financial incapability,
then the non-payment may be categorised as repudiatory.
In the above case, it was not an event of payments being
missed by mistake or as a result of some temporary or
unexpected shortage of funds. However, it is unfortunate
that the concurring judges paid less importance to the
fact that Claimant deliberately declared that he would
not comply with the Contract for an indefinite period, the
importance is Defendant would be paid eventually at the
end of the period and that there was no evidence that the
delay would cause serious damage. Hence assessment
of Lord Justice 2 & 3 should be treated as more rational.
There are opportunities and challenges for contractors bidding for projects in Qatar and the UAE. We have sought to identify some of the key risks typically found in Contracts in Qatar and the UAE by outlining the ‘Golden Rules’ of bidding to assist contractors in their Bid preparations.
The FIDIC suite of Contracts is used throughout the
world and these are the most commonly used forms
in Qatar and the UAE. In our Golden Rules we refer
to specific Clause numbering used in the FIDIC suite to help
identify the risks. If, however, FIDIC is not the form of Contract
to be used on a particular Bid, these principles would equally
apply.
RULE 1 – TENDER BONDS
1.1 This type of Bonds is of an ‹on demand› nature and is
typically 10% of the Tender Sum. Any Tender submitted
without a Tender Bond is likely to be excluded, leading to
a disqualified bid.
1.2 These Bonds will need to be in place for the tender period,
with a provision for extension upon mutual agreement,
until such time as the selected bidder has entered into
the Contract and provided the Performance Security to
the procuring entity.
1.3 The procuring entity will return the Tender Bonds to the
unsuccessful tenderers.
1.4 Contractors should carefully review the terms of the
Request for Proposal (RfP), as the RfP frequently states the
conditions for making a call on the Tender Bond, the form
of the Bond and the amount of the Bond.
1.5 Contractors should only submit the Bids if they are
comfortable to sign up to the Contract if they are chosen
as the selected Tenderer and Awarded the Contract, or
they face the risk of having the Tender Bond called by the
procuring entity.
RULE 2 – SITE RISKS / DATA
2.1 We frequently see responsibility for interpreting and
verifying the accuracy of the Site data being passed
to contractors. Clause 4.12 deals with the allocation of
physical and ground condition risk.
2.2 In Clause 4.12 of the FIDIC Red Book or Yellow Book, the
Contractor is entitled to an Extension of Time and recovery
of cost if it encounters adverse physical conditions that
were not reasonably foreseeable by an experienced
Contractor by the date of submission of the Tender.
2.3 In Clause 4.12 of the FIDIC Silver Book, a Contractor
accepts total responsibility for foreseeing all difficulties
and costs of successfully completing the Works. These
difficulties include all adverse physical or ground
conditions, whether foreseeable or not.
2.4 In Qatar and the UAE we frequently see the FIDIC Silver
Book approach being adopted by procuring entities in
their amended FIDIC Red Book and Yellow Book forms.
This approach is often perceived by contractors as an
unfair allocation of risk, particularly if the Employer made
insufficient data available about ground conditions
during the Tender stage, or if insufficient time was given
to the bidders to verify and carry out their own due
diligence.
2.5 Contractors will have to make a decision on whether
they can Price and Programme the ground condition
risk under such circumstance, if not they can seek any
amendments to the Conditions of Contract to deal with
such risk.
RULE 3 – PENALTIES / LIQUIDATED DAMAGES
3.1 The Qatar and the UAE Civil Codes do not distinguish
between Penalties and Liquidated Damages. Quite often
contracts refer to Penalties instead of Delay Damages or
Liquidated Damages for delay.
3.2 Liquidated Damages provisions should reflect the
anticipated loss likely to be suffered by the Party which
claims compensation. If the amount of Liquidated
Damages is exaggerated there is a risk the amount of
liquidated damages could be challenged in the Courts
and be held unenforceable.
3.3 In the UAE, Courts can increase or decrease the rate of the
The ‘Golden Rules’Of Bidding For Projects In Qatar And The UAE
Mr. Rajeshkumar has Good experience on Major High Rise Buildings and Civil Engineering & Infrastructure
Projects. His experience spans from India to Dubai to Qatar, specialized in Quantity Surveying, Commercial and
Contract Management. He is Qualified with Civil Engineering from India and he has completed. MSc Construction
Law and Practice from Salford University, Uk. He is a Chartered Quantity Surveyor and holding membership from
various prestigious institute such as Chartered Institute of Arbitrators, Institution of Civil Engineering Surveyors,
Australian Institute of Quantity Surveyors, Incorporated Member of Chartered Institute of Building. Certified Cost
Professional too
Mr. Rajeshkumar
1
per Lord Justice Underhill at p. 29
2 per Diplock L.J. in Hongkong Fir Shipping v Kawasaki Kisen Kaisha Ltd [1962] 2 QB 26
3 per Lord Wilberforce in The Nanfri [1979] AC 757
4 Telford Homes v Ampurius Nu Homes [2013] EWCA Civ 577
5 Ross T. Smyth & Co. v Bailey, Son & Co [1940] 3 All E.R 60
6 White Knight Laundry & Cleaners Services Ltd v Sportscar Workshop
& Ors (1989 WL 1721062)
7 Decro-Wall, per Salmon L.J. at p. 369F
8 Tombs v Wilson Connolly [2005] 98 Con LR 44 at 62
9 Alan Auld Associates Ltd v Rick Pollard Associates [2008] BLR 419
75 IIQS - 2015 | 74 | IIQS - 2015
Liquidated Damages to reflect the actual loss suffered
by a party. Under Qatar law, the Qatar Courts can only
reduce the amount of Liquidated Damages, and not
increase it unless the party responsible for the Liquidated
Damages committed fraud or gross negligence. Any
term in the Contract which contravenes these principles
will be considered void under UAE and Qatar Law.
RULE 4 – DECENNIAL LIABILITY
4.1 The concept of Decennial Liability has its origins in the
French Civil Code. It provides a ten year strict liability
guarantee, which protects building owners if there is
total or partial collapse. As liability is strict, the building
owner does not have to prove breach of Contract or
negligence on the part of the Contractor in order to
succeed in its claim.
4.2 Under Qatar and UAE Law, Decennial Liability may apply
even if there has been no collapse of the building. A
defect which threatens the safety and the stability of a
building is enough to trigger this type of liability. A defect
might arise as a result of using defective materials,
wrong determination of the building base, or any other
error in the construction of the building or its design.
4.3 Whilst Decennial Liability benefits building owners, it
poses a risk to international contractors who have not
previously done business in Civil Code jurisdictions.
Professional Indemnity Insurance is unlikely to cover this
type of liability. Any term in the Contract which seeks
to exempt or limit a contractor›s liability is void and
enforceable.
RULE 5 – TIME RELATED CLAIMS
5.1 As there is no concept of the ‹prevention principle› or
‹time at large› under Qatar and UAE Law, contractors
should carefully check the grounds for making Extensions
of Time claims under their Contracts.
5.2 Clause 8.4 deals with the grounds for making an
Extension of Time and the causes of delay typically
found in Clause 8.4 are often heavily amended to
transfer the risk of certain events from the Employer to
the Contractor.
5.3 Clause 8.5 which deals with ‹Delays Caused by
Authorities› is also frequently amended so the risk of
any delay or disruption caused by Authorities is carried
by the Contractor. This may be a significant risk if the
Contractor is responsible for procuring all of the permits
and approvals from the Authorities before the works
proceed on site. A bidding Contractor should identify
which party is responsible for obtaining permits and
approvals for the works in order to assess this risk.
RULE 6 – COST RELATED CLAIMS
6.1 Contractors should also carefully check the grounds
for making claims for additional loss and expense and
profit under their contracts. We frequently see these
provisions deleted which makes it difficult for claims
to be made, especially where contractors have been
delayed for reasons beyond their control.
6.2 The ownership of ‹interface› and ‹integration› risk,
and which party is responsible for coordinating and
managing the interfaces between multiple contractors
working on the same site is a constant challenge for
contractors working in Qatar and the UAE.
6.3 Clause 4.6 which deals with ‹Co-operation› should be
carefully reviewed to see which party is responsible for
the additional cost if the Main Contractor is delayed
by other contractors engaged by the Employer on the
same Site, including any loss or damage to the Works by
other contractors engaged by the Employer.
RULE 7 – ChANGE IN LAW
7.1 In any developing country, the Laws are subject to
change. This is no different in Qatar and the UAE. The
Laws in Qatar and the UAE are published in Arabic and
there are no official English translations available.
7.2 Contractors should carefully check their Contracts to
understand if the risk for changes in legislation sits with
the Employer or is a risk which is to be carried by the
Contractor.
7.3 These Clauses are typically amended. Contractors are
advised to review the change in law clauses in their
Contracts to see if they can make a claim for additional
time and money for dealing with changes to the Laws
after the submission of their Tenders, or if there are any
constraints to making a claim if there is a change in law.
RULE 8 – TIME BAR CLAUSES
8.1 An underlying feature of the Qatar and UAE Civil
Codes is that contracting parties may not agree upon
a prescription period different from that prescribed by
Law. Denial of access to justice is also prohibited under
the general principles of Qatar and UAE Law.
8.2 It is arguable that the time bar period of 28 days in the
Clause 20.1 contravenes the mandatory provisions of
the Qatar and UAE Civil Codes. However, the alternative
argument which supports the upholding of the time
bar period is that by signing a Contract the parties are
waiving their underlying rights and not waiving their
entitlements to claim those rights.
8.3 The enforceability of a time bar clause will depend on
its own set of facts, together with the cause of the event
giving rise to the claim and when the notice was actually
served by the Contractor under the Contract.
8.4 However, we strongly recommend that contractors
comply with the strict notice periods under their contracts
as there is no certainty that arguments under the Civil
Code will succeed. The Courts or a Tribunal may uphold
a time bar clause if a Contractor has simply ignored the
notice periods under the Contract.
RULE 9 – LIMITATION OF LIABILITY
9.1 Under Qatari and UAE Law, a party cannot be discharged
from liability arising from fraud, wilful misconduct,
recklessness, gross negligence or decennial liability.
Damages for breach of Contract may often include claims
for loss of profit.
9.2 Legal principles which apply in a common law jurisdiction do
not necessarily apply in Qatar and the UAE. Qatar and UAE
are Civil Law jurisdictions. An example of this is the distinction
between direct and indirect losses which apply in English
Law. Under Qatar and UAE Law indirect and consequential
loss are not recoverable in any circumstances.
9.3 Despite this, Clause 17.6 (which deals with the limitation
of liability) is likely to include reference to indirect or
consequential loss. However, this should not cause major
concerns for contractors.
9.4 Contractors are advised to review Clause 17.6 to see if loss
of profit claims are excluded, and which exceptions fall
outside their cap on liability.
9.5 It is common in Qatar and the UAE for contractors to limit
their liability for delay damages to 10% of the Contract Price
with an overall cap on liability at 100% of the Contract Price,
subject to certain matters which cannot be excluded under
Qatar and UAE Law.
9.6 The statutory limitation of liability for commercial claims
is, typically, 10 years, and the parties cannot reduce this
liability period in the Contract. Contractors should carefully
review their contracts to ensure their liabilities in the event of
a breach of Contract are adequately capped to the extent
permitted under Qatar and UAE Law.
RULE 10 - DISPUTE RESOLUTION
10.1 The procedure for dispute resolution is always subject to
amendment, with frequent deletion of Dispute Adjudication
Board provisions, which are rarely used in Qatar and the UAE.
10.2 Certain government contracts select court proceedings
in place of arbitration. In those contracts which do
select arbitration, contractors should carefully review the
arbitration provisions to see if there are restrictions on when
the Contractor may commence proceedings.
10.3 We typically see provisions which state the Contractor
may not commence arbitration until the Works are taken
over by the employer. This may cause cash-flow issue for
contractors if they cannot bring a dispute at any time for
non-payment claims, especially if there is a dispute on the
value of a significant variation. This may also prevent the
Contractor commencing an arbitration if the dispute in
question relates to a failure by the Engineer to issue a Taking
Over Certificate for the Works or the rights of the Parties in
relation to a termination which took place prior to the Works
being taken over by the Employer.
10.4 The arbitration agreement in the Contract should always
identify the seat or legal place of the arbitration, the
governing law and the venue for hearings. This can cause
logistical difficulties and challenges if the venue is in a
different country to where the documents and witnesses
are located.
10.5 Contractors should review the terms of the arbitration
agreement to ensure the seat or legal place, the governing
law and the venue is identified in the arbitration agreement
to avoid any uncertainty. If these are unreasonable the
Contractor should consider raising this as an issue at Tender
stage.
10.6 Contractors should also carefully review their contracts
to see that the arbitral proceedings are to be conducted
in English, especially if the contracts and the technical
specifications are written in English. This is to avoid the
parties having to translate the Contract documents into a
different language as this is likely to prove costly and time
consuming and delay the final resolution of the dispute.
Gabriel OlufemiSolicitor
Paul PrescottLegal Director
77 IIQS - 2015 | 76 | IIQS - 2015
Design–build is a project delivery process used in the construction industry. It is a method to deliver a project in which the design and construction services are contracted to a single entity known as the design–builder or design–build contractor.
The traditional approach is the Employer (or client)
appoints an Engineer or Architect to design the
proposed project and then appoints a Contractor
for its construction, commonly known as “design–bid–build”
process. The design–build procurement route changes the
traditional approach. It provides a solution for the client›s desire
for a single point of responsibility in an attempt to reduce risks
and overall costs. It is now commonly used in many countries.
From the Client’s perspective, the design-build process
helps him to deal with one party and also it reduces the
overall project delivery period by overlapping the design
delivery process with that of construction. However, from
Contractor ’s perspective, it imposes increased contractual
obligations encompassing both design and construction
process. Therefore the contractor needs to identify a clear risk/
mitigation plan to meet those obligations.
As part of the invitation to tender for design-build contract,
the Employer will issue a document called the “Employer’s
Requirements”, which describes in reasonable details
the Employer ’s requirements with regards to the purpose,
design, scope, other technical criteria for the works and
other requirements that he consider necessary for design,
construction and maintenance of the works. The level of detail in
the employer›s requirements and the extent of design required
from the contractor is variable. Employer ’s requirements can
range from a very simple scope and specification to a fully
developed performance specification and concept design.
As an example, the employer ’s requirements may describe the
scope of works by stating “design and construct 200 number
bed space hospital with all modern facilities” or it may provide
further details such as size of the building, number of floors,
finishes including the conceptual structural and architectural
details.
As part of the tender submission, the contractor is required
to submit documents titled the “Contractor’s Proposal”. This
document sets out the framework for his proposals for designing
and constructing the works. For the sake of clarity and to avoid
any potential disputes, it is suggested that, the Contractor ’s
Proposal should properly clarify what has been considered/
allowed against the all key employer ’s requirements.
The format of Contractor’s proposal should be described
in the Employer›s requirement›s, but it might include:
concept drawings, Specifications, Schedules, Statements,
details of inconsistencies between the contractor›s proposals and
the Employer›s requirements, any proposed provisional
sums, proposed Sub-Contractors, details of insurances, an
initial construction phase plan, etc. Other documents such
as the tender price and its breakdown, tentative programme,
method statement and all other documents shall be submitted
as part of the overall tender submission.
Following points should be considered or implemented in order
to effectively deal with a Design and Build project.
1. Review the quality of the employer’s requirements and decide
one of the below suggested tender process:
a. A single-stage tender process – This is suitable where
the information presented in the requirements is
sufficiently well developed for the contractor to be
able to calculate a realistic price. This can be the case
where a concept design has already been prepared
by consultants working for the client, or if the proposed
work is very straight-forward. In such cases, much
of the design work might have been carried out by
the tenderer during the tender process and a firm price
can be submitted
a. A two-stage tender process – This is suitable where
the employer›s requirements are not sufficiently well
developed to calculate a realistic price. In this case,
include a fee for designing the building along with
a schedule of rates that can be used to establish the
construction price for the second-stage tender.
2. Seek clarification on any ambiguities within the Employer’
Requirements.
3. Caution must be exercised on the open-ended or
ambiguous requirements, such as a) design must be to the
best international standards b) specification of the materials
shall be to best of its kind c) some requirements referred
as paramount importance. These subjective requirements
could be matter of dispute unless properly clarified.
4. As far as possible, the breakdown of the tender price
should separately show cost of all major construction
works, equipment, and provision for maintenance of the
completed works, general items and provisional sums.
5. Specification and quality of the materials considered in
the tender must be properly described.
6. A compliance statement against all key employer’s
requirements must be included with clarity on non-
compliance (s), if any.
7. If the contractor does not have in-house capabilities for
the specialist works (including major sub-contract works), it is
recommended to enter into a pre-bid agreements with all
specialist contractors encompassing all relevant obligations
and risks.
8. In some instances, it is recommended to include
responsibility for preparation of the shop drawings within
the scope of the Main design engineer / architect.
9. Ensure synergy between the, Employer, contractor,
design team, and subcontractors. All members should be
experienced to think «outside the box.» Most importantly,
they must be capable of-coming up with «win-win’
solutions.
10.Ensure both technical and commercial team attends
the design review meeting in order to identify and to
eliminate unrecoverable costs as far as possible. Minimize
additional cost associated with design development.
11. Seek clarification on Fitness for purpose’ obligation
and avoid taking this obligation as far as possible.
12. Once the design and its associated documents
are accepted and approved by the Employer, identify
all changes initiated by the Employer. In order to
deal with this, maintain separate schedule for every
document through which the Employer or his agents
would have suggested the changes. These changes
must be notified as and when it occurs.
Whilst the design-build contract may have several
advantages, it does impose increased obligations
compared to the traditional design–bid–build” on to
the Contractor. However, Go for it, if you understand its
challenges.
“design and construct 200 number bed space hospital with all modern facilities”
Syed Aslam is a Quantity Surveyor having total 26 years’ experience in the construction and engineering sectors of which 23 years has been in the UAE with Dutco Balfour Beatty LLC as Commercial Manager for the Civil and Infrastructure division. His experience includes Tender Preparation, Contractual Claims,
Variation Accounts, all Measurements and Commercial administration on a variety of major projects encompassing Major Civil Construction Projects, Services Installations and Building Construction. As a
volunteer, to fulfill his corporate social responsibilities, Syed Aslam is an active member of Chartered Institution of Civil Engineering Surveyors (ICES) and Indian Institute of Quantity Surveyors (IIQS).
Syed Aslam B.E Civil, MIIQS, MinstCES
Design and Build ProjectGo for it, if you understand its challenges
79 IIQS - 2015 | 78 | IIQS - 2015
Culture in the construction industry is a shared understanding about what is expected to be done by all Parties. The Cultural practices that are prevalent and their objectives must be clearly understood in order to avoid disputes between the Parties involved in a Project. The understanding of cultural behavior, belief system and social order, which encompass the society and traditions, have a definite influence on the behavior of the Project’s stakeholders.
ThE IMPACT OF CULTURAL FACTORS
The growth of the construction industry has led to many
international Contracting Companies and Design Offices,
establishing their offices across various Geographic locations.
Some of such firms appoint a local Project Manager to
run the Project and some prefer to have their own Project
Managers that are familiar with the company rules, policies
and procedures. The foreign Project Manager and local
Project Manager do not have similar way of thinking but both
have the same target (which is handing-over the Project on
time). Since they don›t have the same background of cultural
factors, they have the differences in behavior, belief, attitude
and values, all of which are reflected in as to how they run their
Project. The Project Manager needs to be aware as to how he/
she should deal with individuals such as the Client, Consultant,
Contractor, Local Authorities and the rest of the Organization
as these members might be from the different cultures. He/
she should also understand and develop communication
skills, leadership skills, interpersonal skills, flexibility and the
technological skills in order to overcome all the problems.
Project Managers who are unable to deal effectively with the
society or environment, where they are working, should be
aware of the implications that arise due to cultural differences
as well as due to local legislation. They should be aware of
the essential aspects of management and execution skills to
avoid the Project’s progress delay.
Historically, many disputes and contractual problems remain
even after handing-over the Projects because of not having
considered the cultural factors in the design or execution,
which affects the progress of the Project. Therefore, it is very
important for each and every Engineer who is working in
private and government sector, as Client›s Representative,
Consultant or a Contractor, to concentrate and understand
the following key influences:
1. Law of the Country: it is essential to consider the religion
as an important criterion in Middle East, because the law
is predominantly based on religion (Shariat Law). In some
conflicts during the execution, the Project Manager and
team may not take action or may be limited due to the
religious factors as this can affect their career or future in
the Organization. Sometimes, conflicts may not manifest
as problem until raised to top management. These will be
discovered at a later stage affecting the handing-over of
the Project.
2. Mixing of Nationalities: The workforce employed on a
Project constitutes most probably of mixed nationalities.
This means a lot of traditions, rules, habits linked directly
to the religion such as regular holidays and festivals for
different traditions of other in the workforce. This cultural
mix will affect the duration and time of the execution of
the Project.
We have to note that once it comes to religious holidays
of multi-national people, the Project Manager cannot
force a group to work since the government rules respect
other religious traditions.
3. Procedures and Formalities: These depend on the rules
and regulations, which are derived from the Country›s Law
and these go through a systematic procedure. During the
design or execution, some points have to be rectified or
verified through the authorities for the proposed Project;
these points have to go through formalities which take a
lot of time because of the designated procedures. If the
procedures and formalities are not complied with or are
not clear, it has a negative time effect on the Project.
4. Awareness of the Local Language: The contract
language, most of the Clients, Consultants and Contractors
prefer to speak and write in their own language and they
don›t like to appoint or employ qualified interpreters which
affect directly the communication, progress and quality
of work. Using the Country›s language in the contract
documents is an important aspect and most construction
Organizations had not resolved this problem.
Many cultural factors have to be considered by the Project
Managers and team members. It is a big challenge but the
main challenge is to cooperate and understand the rules of the
environment and place of work to enable them to understand
as to how to effectively deal with the work force in a Project.
Meantime, understanding the reason behind each factor and
from where it originates as well as understanding the local
language will enable them to implement their contractual
obligations. It is very important to understand clearly the
history, topography, religion, language and tradition of the
Parties who are involved in the Project whether they are Client,
Consultant and Contractor. The culture in the construction
industry is a shared understanding about what is expected
to be done, by all Parties and the cultural objectives must be
very clear to avoid any disputes between the Parties involved.
The understanding of culture in this sense is the ideology, belief
system, norms or behaviors and social order which compose
the society and traditions which could be reflected on the
behavior of the Project›s stakeholders.
The Project Manager and team must clearly be prepared for
understanding the following points to avoid stress and tension
and to control the cultural aspects which can be ambiguous
during the design and construction of the Project:
- Learn local communication.
- Ensure judicious mix of locals and expats.
- Be creative and experimental within limits.
- Be culturally sensitive.
- Understand the complexities of the work force.
- Be more realistic in expectations.
- Be curious about the culture.
- Be friendly and avoid nervousness.
Akram SaadFIDIC, SCL, DRBF & The AACE.
RICS, CIOB and APM.
The Impact of Cultural Factors
Dr. Akram Saad is a Civil Engineer holding Doctorate in Construction and Project Management from Paramount California University, USA and various other professional qualifications. As a Chartered member of Cost
Professional’s, Arbitrator’s & Surveyor’s institutes and PMI, he is actively involved into construction related research. He has Over 30 years’ experience in Engineering, Project Management, Technical Presentations and
approved instructor by PMI Gulf Chapter for PMP Exam preparation courses and Proctor for AACEI. He is Board Member of “CASA”, Chinese American Scholar Association; Member of International who’s is Who Professional
81 IIQS - 2015 |
ADsOn any mega infrastructure project, developing a ‘contract procurement strategy’ plays a crucial role in the success of the project. The contract procurement strategy should reflect the project objective of the overall development as reflected in the client brief and these must be reflected in the Contract Documents.
Developing a Contract Procurements Strategy for Mega Infrastructure Projects
One of the main function of contracts administrators is
to achieve the client’s objective in most economical
terms providing best value for the development. In
order to achieve these, the following are the stages that form
part of the Contract Procurement Strategy.
1.0 Developing a Contract Plan
The Contract plan determines the number of contracts the
project will be divided into. The basic consideration should be
the effect of division of contract on the management effort that
is required to manage these contracts.
• Higher no of contracts will lead to interfacing issues between
Package Contractors and between Infra Contractors and
other Contractors working in the same area.
• Lower no of contracts will increase the Clients risk exposure
Hence the number of contracts the project is to be divided is
based on certain guiding principles namely:
a. Contract Size: The size of each contract shall be such
that these are manageable by Contractors in terms of
Time duration and availability resources (manpower and
equipments).
b. Time Duration: Time duration should allow for obtaining
construction permits, design review, mobilizing resources
/ Sub-Contractors and obtaining necessary approvals
from authorities. These should also take into account local
practices, holidays and summer break periods.
c. Type of Contract: Depending on the type of works, contract
can be separated Example: 132 kVA substation and
sewerage treatment plant can be contracted as Design and
Build as a separate contract. While the main infrastructure
package are normally tendered as re-measurable Contract.
d. Contract size should be within the capacity of sufficient
contractors to allow competitive tendering Example AED
400-500 Million or a monthly average billing of AED 20-25 M
is considered as manageable for large contractors.
e. Time constraints (132 kV substation or sewerage treatment
plant have longer gestation period) and capacity restrictions
required separation of the contracts.
2.0 Process of Tendering
Selecting the process of tendering depends on the level of
competition required and client’s policies existing regarding
procurement.
a. Open tendering: This form of tendering is highly risky
WITH BEST COMPLIMENTS from STERLING GENERATORS
OurStrength|LTPanels|HTPanels|SolarCss|DrawOurMCC&TTAPanels|Generators
TEL : +97142563980Email: [email protected]
www.civilmatrixco.com
We specialize in “Design & Build” of industrial building like warehouses, Logistics facilities,
factories, cold stores, etc
83 IIQS - 2015 | 82 | IIQS - 2015
for client on mega infrastructure projects as contract
will be awarded to the lowest tenderer, who may not
have the capacity or required expertise to carry out
the works.
b. Selective tendering: Selective tendering in one or two
stages with a limited number of organisation who are
already on vendor list or prequalified will reduce the
client’s risk even if awarded to lowest bidder.
c. Negotiated tendering: This form of tendering based
on Contractor ’s reputation or experience on previous
projects is not suitable for mega infrastructure projects.
This process is time consuming due to prolonged
negotiations and client may later realise that value
for money is not achieved due to lack of competition.
3.0 Tendering process is usually carried out in three key stages,
this helps to minimize the risks to the project.
3.1: Pre-qualification
Pre-qualification will eliminate any risks associated with suitably
of selected bidders. The following criteria is generally used for
pre-qualification.
a. Financial
• Evaluation of Financial Standing and records (Financial
statement Audited for last three years)
• Current Financial exposure
• History of Financial disputes
b. Technical
• Technical and management structure including
adequacy of
• Sub-Contractors to relate to specific project
• Current commitment of bidder
• Current capacity and ability to undertake the size of
project
• Ability to deliver the quality required for the project
• Performance on previous project
• Competence and resources to comply with statutory
health and safety requirements
• Approach to quality assurance system
c. Commercial
• Contracting strategy (in-house, sub-contract, JV, etc.)
• Risk management techniques
• Claims and variation track record
• Flexibility in commercial issues
• Dispute resolution track record
3.2: Tender Documentation
Tender documentation will comprise different volumes.
A detailed tender documentation will eliminate risks related
to missing information or incomplete information. Hence
sufficient time should be given for preparation of tenders.
Information proided should be sufficient enough to enable
the pricing of tenders. Suites of contracts and standard un-
amended forms of contract from recognized bodies should
preferably be used.
3.3: Bid Evaluation
A detailed bid evaluation will be carried out for the following
criteria considering the complexity of tender.
a. Technical Evaluation
• Method statement for execution the works
• Tender programme and its compliance with
project milestone, duration and logic used
• Proposed management team and their relevant
experience
• Proposed deployment of plant and resources
• Availability of resources (in-house or sub-
contracted) or through JV
• Material proposed and their Compliance with
specifications
• Proposed suppliers
• Percentage of local resources used for execution
of work
• Health and safety compliance
• Quality standards that will be adopted in project
delivery
• Compliance with manuals, training ,factory visits,
sample testing, etc.
• Warranties
b. Commercial
• Compliance with the invitation to tender
• Acceptance of tendering terms and conditions
• Compliance with contract period
• Compliance with payment terms
• Length of product validity and spares availability
c. Financial Evaluation
• Evaluation of priced rates
• Mathematical errors, carryover errors
• Review of rates against pre-tender estimates
• Identifying rates which are front loaded
• Rates if quoted in foreign currency should be adjusted
• Risk analysis and financial appraisal of innovative items
• Cost of variation / additions
• Cost of service, spares and maintenance cost
The detailed financial evaluation of the bids are carried out by
comparing the rates submitted by tenderers. Arithmetic check
carried out rate by rate will identify discrepancies in each bid
with Clients estimated rates.
4.0 Selecting the Contractors
Based on the above bid evaluation the most suitable
Contractor is selected giving due weightage to each of the
bid evaluation criteria.
Summary
When developing a contract procurement strategy, its
important that the client’s objectives are communicated
appropriately via the tender documents or through the post
tender negotiation meetings and reflected in the Contract
documents.
The terms of contracts shall be selected logically depending
on the nature of work, its certainty, urgency and requirement
of all parties. If the projects risks, project objectives are not
covered, then clients spend enormous amount of time, money
and resources to create value. Hence it can be concluded
that an appropriate contract procurement strategy will help in
creating value for the project.
Mr. Sajeeth Sidharthan is a Member (MRICS) of Royal Institution of Chartered Surveyors, Associate Member (MCIArb) of Chartered Institute of Arbitrators, Member of Society of Engineers(MSOE)
and an Alumni of Manchester Business School and MSRIT BangaloreSajeeth has extensive experience in construction, consultancy and cost management of Large Scale
development and been in senior positions with both Contracting and Consulting Firms. Currently running his own Consultancy Firm advises leading Consultants/Clients on projects with Meydan, Musanada, RTA and TECOM Investments. He currently advises clients on selection of Contracts, Commercial
Negotiation, Cost Control, Procurement Planning and Claim Avoidance strategy in UAE.
Sajeeth SidharthanMRICS, MCIArb, MSOE
85 IIQS - 2015 | 84 | IIQS - 2015
Building Information Modelling (BIM) is a recent technological advancement that has attracted considerable amount of attention in the construction industry worldwide. The UK government has recognised this and has mandated that all public sector projects to have BIM ready by 2016 (level 2). The EU made BIM a mandate in January 2014 and BIM is mandatory for projects with a gross floor area of more than 5000sq.m in Singapore. The aforementioned is just to name a few, alternatively named BIM technology, Virtual Design and Construction is in use in India and USA.
BIM AND The Qs Profession
In line with the global movement of BIM, in November
2013, the Dubai Municipality decided to make BIM
mandatory from 1st January 2014 for projects that fall
into the following criteria:
• All buildings delivered by/through an international
consultant.
• For architectural and M&E works for all buildings 40
stories or higher.
• All hospitals, universities and other similarly specialised
buildings.
• Facilities/buildings that are 28,000 sq. m or larger.
The Middle East is currently lagging behind in the adoption
of BIM technology in comparison with Europe, USA etc.
Presently in Dubai the focus is on the design and build phase
of the project, therefore, currently the primary use of BIM is to
coordinate design and communication between the various
parties involved in the process.
BIM has three different levels of sophistication wherein the
concepts of 4D, 5D and 6D are used to indicate the elements
and benefits of increasingly complex BIM models which in
brief as follows:
Level 0 - Unmanaged CAD, in 2D, with paper data exchange.
Level 1 - Managed CAD in 2D or 3D format. Data structure
and formats are standardised. There is no integration
of commercial data at this stage.
Level 2 - Managed 3D with data attached by the different
disciplines. However commercial data is managed
by ERP software and integration is achieved
by third party software. At this stage 3D has the
ability for model walkthroughs, clash detection,
project visualisation, virtual mock up models and
prefabrication information.
Level 3 - This level of BIM will utilise 4D construction sequencing
(construction planning and management and
schedule visualisation), 5D cost information (quantity
take off and real time cost estimating) and 6D project
lifecycle management information.
Due to the lag in the implementation of BIM in Dubai
in comparison to Uk, USA etc., the professions in the
construction industry and contractors are also lagging behind.
Unfortunately, quantity surveyors have been found to be slow
in the acceptance of BIM as a potential tool for project cost
management partly because of the lack of awareness of
the BIM’s potential in the QS profession. However, this is not
surprising when the primary drive with BIM is related to the
architectural profession.
Whilst in some quarters of the QS profession there is a thought
that BIM is a threat to the QS profession, this has been proven
not to be the case in the report ‘How can BIM support the
New Rules of Measurement’ published by the RICS on 31st
January 2014 in conjunction with the University of Salford.
The report requires the QS to gain a greater understanding of
BIM thereby using BIM to significantly improve the efficiency
and accuracy of quantity surveying functions. Whilst there
are provisions to automate certain QS functions, BIM by all
means does not give you cost estimates at the press of a
button.
In the paper titled ‘The Relationship of Building Information
Modeling (BIM) Capability in Quantity Surveying Practice and
Project Performance’ by P. F. Wong, H Salleh and F. A. Rahim
published in 2014, BIM capabilities in quantity surveying
practices is defined as follows:
1.Cost appraisal can be prepared quickly at the feasibility
stage.
2.Preliminary cost plan can be prepared by extracting
quantities directly from the model.
3.Easily update cost plans with more detail as design is
developed.
4.Easily generate accurate cost estimates for various design
alternatives.
5.Design changes reflected consistently in all drawing views.
6.Cost implication of design changes can be generated
easily without manually re-measurement.
7.lash detection reduces design errors and cost estimate
revisions.
8.Cost checking performs quickly to ensure all items are
captured.
9.Improved visualization for better understanding of designs.
10.Automatically quantify for BOQ preparation.
11.Intelligent information management system allows data to
be stored in a central coordinated model.
It is evident that BIM still requires a lot of collaborative work
between the QS and Architect to ensure that the correct
coding, zoning etc., is used. Considering that the majority of
time of the QS function is based around quantification, there
is no doubt that BIM technology offers a solution to simplify
the traditional methods of quantity take off which is inefficient,
time-consuming, and subject to errors. Numerous software
solutions are available for QS’s to speed up the extraction of
quantities from a BIM model and use the same for developing
the BOQ or a detailed cost plan. This is on the assumption
that all the information the QS requires is available directly
from the BIM. This is unlikely and a certain amount of work will
have to be done manually. It is still necessary to check that
all components are captured and measured in accordance
with the standard method of measurement. The final cost
estimate will require the input of a good QS to ensure that
the estimate is robust and up to date with the current market
trends.
BIM will assist in making QS functions much more efficient and
streamlined which is much needed considering that the pre
contract functions of a QS is at the tail end of each stage (e.g.
concept design stage, schematic design stage etc.). When
delays occur to the design, the period allowed for the QS to
complete his works is reduced in order to recover the project
programme. The consequences of the aforementioned
sometimes results in a decrease in the quality of the work
produced and subsequently causes dissatisfaction with
Lead Consultants and Clients. BIM has the potential to bring
in greater efficiency in the work undertaken by the QS and
improve the overall quality of cost estimates.
Level 3 BIM is some years away from full implementation in the
Uk (who are currently at the forefront of the technology drive)
and even further away in Dubai. However this should not stop
the QS profession from adapting to the new technology, gain
a greater understanding of the potential benefits of BIM to the
QS functions thereby taking on board BIM to the level of the
other professions in the construction industry.
Sunil Sukumaran is the Managing Director of Hepher Quantity Surveying who has 30 years of practical experience in Pre & Post Contract Works working with Contractors and Consultants and has been
working in the UAE for the past 18 years. He is a Chartered QS and PM and an Associate of the CIArb.
Sunil Sukumaran
87 IIQS - 2015 | 86 | IIQS - 2015
It is worth reminding ourselves that the Infrastructure Conditions of Contract (ICC) have recently been updated with the issue of the With Quantities Form November 2014 Edition. It is likely the other contracts in the ICC suite will be updated shortly.
Infrastructure Conditions Of Contract (ICC) With Quantities Form November 2014 Edition
This news may be of particular interest to governmental
procurers and private developers operating in the
international construction market, who frequently use
the FIDIC Conditions of Contract for Construction for Building
and Engineering Works Designed by the Employer (commonly
known as the Red FIDIC Book).
We highlight below some of the key features from the recent
ICC form which may make it an attractive alternative form for
international infrastructure projects.
1. International Application
First, the ICC form has been tailored to the international
market as the parties are free to decide the governing law
and the contract language that will apply to the contract. This
information may be agreed between the parties and included
in the appendix to the contract. The ICC form allows the
parties to refer any dispute to arbitration which is the method
of dispute resolution frequently used in the international
construction market.
2. Payment
The ICC form uses the Bill of Quantities as the pricing document.
The parties may choose if the works are to be undertaken on
a fixed lump sum basis or alternatively, the works may be
remeasured.
The parties are also free to choose the method of measurement
to apply by identifying the method of measurement in the
appendix to the contract. If they do not include a method of
measurement in the appendix, CESMM (4th Edition) will apply
by default as stated under Clause 11.1.
3. Design
Although the ICC form lends itself to the traditional method of
procurement, where the employer is responsible for designing
the whole of the permanent works, the ICC form may also be
used if the contractor is designing any part of the permanent
works.
The ICC form anticipates that for some projects the parties
may wish for the contractor to have some design responsibility
for part of the permanent works. Drafting is included at Clauses
4.8, 6.3 and 6.4 to allow for this. Employers, however, may wish
to review these clauses to ensure that they adequately reflect
their requirements.
4. Building Information Modelling
The ICC form makes specific reference to Building Information
Modelling (BIM) and allows the parties to agree on the BIM
Protocol that will apply.
If the parties wish to use BIM on their project, the parties are to
select and state in the appendix to the contract the protocol
that will apply and any supporting requirements. This will
include any IT software and associated systems which need
to be included in the Information Protocol for the parties to
exchange the updated BIM models.
However, the parties may wish to supplement the existing
copyright clause at Clause 4.11 by including drafting to allow
the parties to licence to each other the BIM models. The
current drafting at Clause 4.11 is limited to copying and using
the data which may be viewed as too narrow for the purposes
of using BIM on a project.
5. Risks
The ICC form is innovative regarding the allocation and
apportionment of risk. The ICC form divides risks into three
categories being the ‘Excepted Risks’, the ‘Employer ’s Risks’
and the ‘Shared Risks’. These are covered under Clause 8 of
the ICC form.
The Excepted Risks are dealt with under Clauses 8.2, 8.3 and
8.4 and are similar to how Employer ’s Risks are dealt with
under Clauses 17.2, 17.3 and 17.4 of the Red FIDIC Book for
the rectification of loss or damage to the Permanent Works.
Contractors may wish to review the list of Excepted Risks to
see if this list adequately covers all of the project risks which
may occur and cause loss or damage to the works while the
works are in their care.
The Employer ’s Risks are listed in limbs (a) to (j) of Clause 8.5
and are a comprehensive set of project risks frequently seen
in the Red FIDIC Book. If any of the Employer ’s Risks occur, the
contractor is entitled to claim additional time and money in
accordance with the provisions of the ICC form.
The Shared Risks under Clause 8.7 are risks which only entitle
the contractor to claim additional time but do give rise to
any financial compensation unless otherwise stated in the
contract.
A noticeable risk which is missing, is the general ‘catch all’
clause typically found at Clause 8.4(e) of the Red FIDIC Book
giving the contractor an extension of time if there has been
delay, impediment or prevention caused by or attributable
to the Employer. This typical extension of time ground is not
included as one of the Shared Risks referred to in Clause
8.7, nor referred to in Clause 9.4 which deals with extensions
of time. It is strongly recommended this catch all clause is
included as one of the Shared Risks to avoid any arguments that
an extension of time cannot be granted as a result of ‘acts of
prevention’ by the Employer.
Contractors are reminded that if a risk does not fall under any of
the Excepted Risks, the Employer’s Risks or the Shared Risks, then
such risk will be carried by them in accordance with Clause 8.1.
Therefore contractors should carry out a careful analysis of the
risks in the ICC form to fully understand the project specific risks
which they will carry on a particular project.
The ICC approach in setting out the project risks under one
clause is helpful and in theory should assist the parties to quickly
identify and agree the allocation and responsibility for risks on
any given project.
6. Force Majeure
As with most international standard forms of contract, the ICC
conditions of contract provide relief as a result of exceptional
events or circumstances which prevent a party from performing
its obligations.
Contractors with experience of international construction
projects will be familiar with the wording in Clause 19.1 of the
Red FIDIC Book which defines when an event will be treated as
force majeure.
89 IIQS - 2015 | 88 | IIQS - 2015
Force majeure is an exceptional event or circumstance
which is: (a) beyond a party ’s control; (b) which such
party could not reasonably have provided against before
entering into it; (c) which, having arisen, such party could
not reasonably have avoided or overcome; and (d) which is
not substantially attributable to the other party.
Therefore a party must have been prevented from
performing its obligations under the contract and overcome
5 hurdles to succeed in its claim for force majeure.
FIDIC also provides a non-exhaustive list of exceptional
events or circumstances which may qualify as force majeure
provided the conditions (a) to (d) of Clause 19.1 are satisfied.
These events may include war, hostilities rebellion, terrorism,
riot, commotion.
Additional relief may also be found at Clause 19.7 of FIDIC
(Release from Performance under the Law) if an obligation
is impossible or unlawful to perform. Clause 19.7 entitles the
affected party to be released from further performance
of the contract if the event or circumstance is outside
the control of the parties, making it impossible or unlawful
for either or both parties to fulfil its or their contractual
obligations.
Therefore, an event which is exceptional in nature may be
treated as force majeure under Clause 19.1 of the Red FIDIC
Book if it affects performance of a party›s obligations under
the contract. However, this same event may not make that
party›s obligation impossible to perform for the purposes
of satisfying the test under Clause 19.7. FIDIC must clearly
have intended there to be a distinction, depending on the
severity of the event in question, in terms of relief that may
be sought under Clause 19.1 and Clause 19.7.
For an event to qualify as a force majeure event in the ICC
form, the event must make it impossible or unlawful for either
or both parties to fulfil their contractual obligations. This is
a higher threshold when compared to that typically found
under Clause 19.1 of the Red Book. The threshold for force
majeure in the ICC form is similar to the strict test found
under Clause 19.7 (Release from Performance under the
Law) of the Red Book. This distinction is arguably unhelpful.
Contractors may therefore wish to make amendments to
the ICC form to bring it in line with the Red FIDIC Book. This
is to give contractors relief for events which they could not
reasonably have avoided and which will prevent them
performing their obligations.
7. Collaboration and Early Warning
Many parties and stakeholders are adopting pro-active risk
management tools in their contracts as a way to identify
and manage risks during the currency of the project. The
inclusion of early warning notices and risk reduction meeting
provisions focus the parties› minds on project delivery.
In the ICC form the contractor, the employer, and the
engineer shall each in the performance of the contract,
collaborate in a spirit of trust and mutual support in the
interests of the timely, economic, and successful completion
of the works.
The ICC form, however, seems to have taken this
collaboration principle a step further as it allows the parties
to agree actions and measures and the associated matters
of payment and additional time. This may be seen by some
as taking the collaboration principle a step too far. Time will
only tell if the parties are keen to follow the ICC approach.
8. Conclusion
Overall, the ICC form is to be welcomed and may be seen
as a useful alternative approach to FIDIC in the international
construction market.
The standard methods of measurement for building works - IS 1200 , has been well established for over 55 years on the standard for preparation of bill of quantities in civil engineering works.Measurements occupy a very important role in planning and execution of any civil engineering work from the time of preparation of preliminary estimates to final completion and settlement of payments for a project.
Indian Standard of Measurement of Building Works - IS 1200
Gabriel OlufemiSolicitor
Paul PrescottLegal Director
The standard method of measurements - IS1200, is used
in preparation of bills of quantities. It also documents
the measured quantities of the items of work identified
by drawings and specification in tender documents. Bills of
quantities are issued to tenderers, for them to prepare a price
for carrying on works based on this standard. It is found that
the methods followed for measurement are not uniform and
considerable differences exist between practices followed by
various construction agencies, government departments etc.
Hence,to eliminate ambiguities in measurements, standards
method of measurements - IS1200 has been developed
and adapted by Bureau of Indian Standards. A snapshot of
the latest parts have been presented in this paper which is
beneficial to a large community of Quantity Surveyors, Project
Managers, Contract Managers and others in the field of Civil
Engineering trades.
Methods of measurement of Building Works It is important to establish a considerable degree of
standardization in the method of preparing the bill of
quantities and the units used in them. To achieve this a
standard method of measurement is used, the purpose of
which can be summarized as under:
a) To facilitate pricing by standardization
of bill of quantities
b) To provide a systematic structure of bill
of items leading to uniform items and description
c) To provide a rational system of billing
d) To simply the measurement of
work and administration of contracts
e) To provide a uniform basis for measurement
of works so as to avoid misunderstanding of works
f) To assist in financial control of work
Indian Standards on method of measurement of building
and civil engineering works have, therefore, been formulated
which have been covered in various parts of IS 1200 based
on different trades. These have been amended and revised
from time to time so as to keep the same based on the latest
practices being followed by various construction agencies
and government departments. The following is the list of IS:
1200 parts with latest reaffirmed / amended dates:
91 IIQS - 2015 | 90 | IIQS - 2015
For the purpose of deciding whether a particular requirement
of these standards are complied with, the final value, observed
or calculated, expressing the results of measurement, shall be
rounded off in accordance with IS:2-1960 – Rules for rounding
off numerical values (revised). The number of significant
places retained in the rounded off value should be the same
as that of the specified value in these standards.
After a contract is entered into, the engineer for the contract
is responsible for discharging the measurement function and
he may delegate his authority to the engineer ’s reprenstatives
to carry out measurement work with assistance of quantity
surveyors and the site staff. Emphasis is made to ensure
consistent and systematic approach throughout the pre and
post contract stages. This provides a structured framework
to implement an independent checking system for the
measurement works.
Conclusion
Measurement is used by various stakeholders and construction
professionals throughout the development process to calculate
the quantity of work to be done. A project manager may
require details of areas of a proposed office block to establish
a budget at the initial stages of a contract. A quantity surveyor
may calculate the approximate quantities of work during the
design development stage to produce a cost plan to check
the adequacy of the building budget. A quantity surveyor may
take off quantities from detailed drawings to produce a bill
of quantities for tendering purposes. On smaller projects
an estimator may need to measure the quantities from
the tender drawings and specifications as part of a tender
submission. A contractor will present measured variations as
part of a final account settlement. The purpose of measuring
any building work is to establish the correct amount of work
to be done. This involves producing accurate quantities in
a way which is comprehensive, technically accurate and
clear in its approach and presentation. Measurement has
two basic essential activities; description and quantification.
Description usually involves ‘ translating’ information
contained on drawings, specifications and technical
reports and communicating that information accurately
and concisely so that another person will completely
understand the writer ’s intentions. The measurer must be
able to describe concisely what the designer has drawn or
the builder has built. In practical terms this means that the
description must be clear enough to enable an estimator
to visualize the detail without having to refer to the drawing.
Designers and quantity surveyors must be aware that others
will rely on their descriptions when pricing building works.
Descriptions must therefore be accurate, clear, concise
and unambiguous. Hence IS 1200 with various parts plays a
very important and key role in providing the standardization
in the method of measurement required by the Quantity
Surveying community.
Umesh Ramakrishna Rao
BE (Civil), MRICS, MIIQS Fellow,Institution of Engineers (India) and Institution of Valuers (India)
Principal ConsultantRohini Project Management Solutions
Project Management & Cost Management Consultants, Bangalore
SlNo
IS Number Title Reaffirm date No of.amd
1 IS 1200 (Part 1):1992
Methods of measurement of building and civil engineering works : Part 1 Earthwork(fourth revision)
Sept 2012 1
2 IS 1200 (Part 2):1974
Methods of measurement of building and civil engineering works : Part 2 Concreteworks ( third revision)
Sept 2012 2
3 IS 1200 (Part 3):1976
Methods of measurement of building and civil engineering works : Part 3 Brickwork(third revision)
Sept 2012
4 IS 1200 (Part 4):1976
Methods of measurement of building and civil engineering works : Part 4 Stonemasonry (third revision)
Sept 2012
5 IS 1200 (Part 5):2013
Methods of measurement of building and civil engineering works : Part 5 Form work(fourth revision)
6 IS 1200 ( Part 6):1974
Methods of measurement of building and civil engineering works : Part 6 refractorywork (second revision)
Sept 2012 2
7 IS 1200 (Part 7):2013
Methods of measurement of building and civil engineering works : Part 7 Hardware(third revision)
8 IS 1200(Part 8):1993
Methods of measurement of building and civil engineering works : Part 8 steel workand iron work (fourth revision)
Sept 2012 1
9 IS 1200(Part 9):1973
Methods of measurement of building and civil engineering works : Part 9 roof cover-ing ( including cladding) (second revision)
Sept 2012 1
10 IS 1200(Part 10):2013
Methods of measurement of building and civil engineering works : Part 10 ceilingand linings (third revision)
11 IS 1200 (Part 11):2013
Methods of measurement of building and civil engineering works : Part 11 paving ,floor finishes , dado and skirting (fourth revision)
12 IS 1200(Part 12):1976
Methods of measurement of building and civil engineering works : Part 12 Plasteringand pointing(third revision)
Sept 2012
13 IS 1200 (Part 13):1994
Methods of measurement of building and civil engineering works : Part 13Whitewashing , colour washing, distempering and painting of building surfaces(fifth revision)
Sept 2012 2
14 IS 1200(Part 14):1984
Methods of measurement of building and civil engineering works : Part 14 Glazing(third revision)
Sept 2012 1
15 IS 1200(Part 15):1987
Methods of measurement of building and civil engineering works : Part 15 Painting ,polishing, varnishing etc. (fourth revision)
Sept 2012
16 IS 1200(Part 16):1979
Methods of measurement of building and civil engineering works : Part 16 Laying ofwater and sewer lines including appurtenant items (third revision)
Sept 2012
17 IS 1200(Part 18):1974
Methods of measurement of building and civil engineering works : Part 18 Demoli-tion and dismantling (third revision)
Sept 2012
18 IS 1200(Part 19):1981
Methods of measurement of building and civil engineering works : Part 19 watersupply , plumbing and drains (third revision)
Sept 2012
19 IS 1200(Part 20):1981
Methods of measurement of building and civil engineering works : Part 20 laying ofgas and oil pipeline (third revision)
Sept 2012
20 IS 1200(Part 21):1973
Methods of measurement of building and civil engineering works : Part 21Wood- work and joinery (second revision)
Sept 2012 1
21 IS 1200(Part 22):1982
Methods of measurement of building and civil engineering works : Part 22 Materials Sept 2012
22 IS 1200(Part 23):1983
Methods of measurement of building and civil engineering works : Part 23 Piling(fourth revision)
Sept 2012
23 IS 1200(Part 24):1983
Methods of measurement of building and civil engineering works : Part 24 Wellfoundation (third revision)
Sept 2012 1
24 IS 1200(Part 25):1971
Methods of measurement of building and civil engineering works : Part 25 Tunneling( Second revision)
Sept 2012 4
25 IS 1200(Part 26):1987
Methods of measurement of building and civil engineering works : Part 26Acid test lining
Sept 2012
26 IS 1200(Part 27):2013
Methods of measurement of building and civil engineering works : Part 27Earth work done by mechanical appliances (first revision)
27 IS 1200(Part 28):1992
Methods of measurement of building and civil engineering works : Part 28sound insulation work
Sept 2012
28 IS 3861:2002 Method of measurement of plinth , carpet and rentable arears of buildings(second revision)
Sept 2012
29 SP 27: 1987 Hand book on method of measurement of buildings works (first revision) Oct 2013
93 IIQS - 2015 | 92 | IIQS - 2015
Presently, world is recovering from Global Financial Crisis of 2008, worst financial crisis since 1930. The Great Depression of 1930 was caused due to fall of stock market, while the global financial crisis of 2007 was caused due to housing market bubble in US and overvaluing mortgages by subprime housing market. Housing Market plays a vital role in countries economy and life of citizens, but due to the cyclic nature of housing market, it also affects the economy of country. To save the world from such financial crisis in future, it is important to understand cyclic behaviour of housing market or minimize the impact of boom and burst of housing market on economies.
Impact Of Boom & BustOf Housing Market Market on Macroeconomy
hOW hOUSING MARKET AFFECTS MACROECONOMY
GDP (Gross domestic Product) can be decomposed in four
categories: investment, consumption, government spending
and net export (difference between export and import).
Investment spending typically requires financing and is
normally depended on interest rates. Higher interest rate may
lead to weak housing sales, rising inventories of home sale,
and falling housing prices. These, in turn make building houses
less profitable, and so the builders are likely to construct new
houses, which creates reduction in investments. New housing
construction is included in the investment category of total
economy spending i.e. included in GDP.
Housing market also affects GDP via consumption spending.
It is important to remember that houses that individual or
family own are a biggest asset on their balance sheet. It has
been noted that change in housing prices are correlated with
change in consumption. The change in housing prices affects
consumption either via wealth effect (when house prices
rise/fall household may feel more/less wealthy and react by
increase/decrease their consumption) or via collateral effect
(an increase in value of a house might allow the owner access
to more credit and opposite might occur when values falls).
Employment has direct relation with household consumption.
Household consumption increases, when more people are
employed. The increased consumption causes increased
demand and subsequently business/economic growth.
This creates an accelerated effect, as business grows
further; more people get employment, which reduces the
government unemployment expenditures, increases tax
revenues. This creates additional funds to the government for
spending or to reduce budget deficits or budget surplus. The
consequential affect is increased government spending i.e.
more employment or reduction in budget deficit, increased
country credit rating, which helps to get cheaper finance.
Employment is key to business and country ’s economic
growth.
DETERMINANTS OF hOUSING MARKET
Housing market depends on various different factors, which
jointly or individually affect the prices. Most of the factors are
interlinked and affects each other. The determinants, which
mainly affect housing market, are –
(1) Business Cycle (GDP), (2) Unemployment Rate, (3)
Disposable Income, (4) Credit Availability, (5) Interest Rate,
(6) Supply of New dwellings, (7) Rental Income, (8) Foreign
Exchange Rate
hISTORY OF hOUSING MARKETS
The US, Uk, & Japan housing markets directly affect the
global economy; hence it is important to study the historical
behaviour of these markets to create more reliable economy.
1. JAPAN
By 1991, Japanese, commercial land prices rose 302.9%
compared to 1985, while residential land and industrial land
price jumped 180.5% and 162.0%, respectively, compared
to 1985. Nationwide, statistics showed that commercial land,
residential land and industrial site land prices were up by
80.9%, 51.1%, and 51.7%, respectively. In early 90’s, Japan’s
property prices fell by 75% and could not able to recover in
last 2 decades, which is also called as Lost Decade. The entire
asset prices crisis was far worse, especially in large business
districts of Tokyo. By 2004, prime “A” property in Tokyo’s financial
districts had slumped to less than 1% of its peak, and Tokyo’s
residential homes were less than a tenth of their peak. Over
the period of 1995 to 2007, Japanese GDP fell from $5.33 to
$4.36 trillion (in nominal terms), while the country experienced
a stagnant price level (no inflation) and interest rates were
close to “ZERO” or negative.
2. UNITED kINGDOM
Between, 1980 to 1986 house prices in Uk were rising with a
slow rate, but increased sharply from 1987 to 1989 before a
sharp fall in 1991. The prices remained low from 1991 to 1996
and started increasing from 1998 and continued till global
financial crisis of 2007. Due to the global financial crisis, the
housing prices declined 20% in 2007-2008, but recovered
10% in year 2010. The Uk government supported the housing
market by reducing the interest rates close to 0.5% and by
providing government funding for first time new house buyers.
Between, 2010 - 2012 prices were stable but further rose by
10% in 2013 and have been continuously rising and already
expected to be a bubble, which may burst as soon as interest
rates are increased (possibly towards end of 2015).
3. UNITED STATES
U.S. subprime mortgage crisis was a nationwide banking
emergency that coincided with the U.S. recession of
December 2007 – June 2009. It was triggered by a large
decline in home prices, leading to mortgage delinquencies
and foreclosures and the devaluation of housing-related
securities. Decline in residential investment preceded the
recession and were followed by reductions in household
spending and then business investment. Spending reductions
were more significant in areas with a combination of high
household debt and larger housing price declines.
U.S. home prices declined steeply after peaking in mid-2006,
it became more difficult for borrowers to refinance their
loans. As adjustable-rate mortgages began to reset at higher
interest rates (causing higher monthly payments), mortgage
delinquencies soared. Securities backed with mortgages,
including subprime mortgages, widely held by financial
firms globally, lost most of their value. Global investors also
drastically reduced purchases of mortgage-backed debt
and other securities as part of a decline in the capacity and
willingness of the private financial system to support lending.
Concerns about the soundness of U.S. credit and financial
markets led to tightening credit around the world and slowing
economic growth in the U.S. and Europe.
The crisis had severe, long-lasting consequences for the U.S.
and European economies. The U.S. entered a deep recession,
with nearly 9 million jobs lost during 2008 and 2009, roughly
6% of the workforce. One estimate of lost output from the crisis
comes to “at least 40% of 2007 gross domestic product”.
U.S. housing prices fell nearly 30% on average and the U.S.
stock market fell approximately 50% by early 2009. As of
early 2013, the U.S. stock market had recovered to its pre-
crisis peak but housing prices remained near their low point
and unemployment remained elevated. Economic growth
remained below pre-crisis levels. Europe also continued
to struggle with its own economic crisis, with elevated
unemployment and severe banking impairments estimated
at €940 billion between 2008 and 2012.
US housing market gained significantly after the recession, but
still at the risk since federal government is keeping interest rate
close to 0.5% from last 6-7 years to support the economy,
which is over due to be raised and planned to increase
towards end of 2015. Once interest rates are increased it will
be difficult to sustain the growth.
BUSSINESS CYCLE AND hOUSING CYCLE
94 | IIQS - 2015
Due to the cyclic nature of housing market, after the sharp
increase of 4 to 5 years, it declines sharply; it is evident from
1991 and 2008 falls. Housing market cycle follows business
cycle, 4 to 5 years of shorter cycle and 15 to 20 years longer
cycle.
To rescue the economy from recession, Governments takes
various actions, such as, increase government spending,
reduce taxes and interest rates etc., which starts economic
upturn. The economic upturn starts creating positive
confidence to the business and financial institutions and
subsequently investments and credit expansion starts. This
creates a demand of new properties, but due to short supply,
it leads to increased rents. The delivery of new properties takes
long time, which causes booming demand and creates a
bubble. The speculators inflate bubble more, which makes
properties unviable.
To control booming market, government starts increasing
taxes and interest rates. This slows down the market and start
downturn. But it is not possible to deflate bubble without
popping, which cause sharp decline in property market and
slow down the business and investments.
Japan, US and Uk tried to slow down the market but speculated
bubble busted and caused sudden crash.
CONCLUSION
Delay in start of new projects (due to effect of last cycle) and
over leverage of companies and individuals are two major
factors that creates bubble in property market. To prevent
the property market from sudden crash, it is important for
governments to regulate the financing policies to control
demand and supply on a regular basis rather than leaving for
market for its own correction.
Naveen Kumar is a professional Quantity Surveying with an experience of 25 years in India and Abroad. Presently working with M/s Al Faraa General Contracting as Commercial Manager and has pre and post commercial and contract management experience in high rise buildings. He is Director in IIQS, Member of Royal Institution of Chartered Surveyors (MRICS), Certified Cost Engineer by AACEI andAssociate Member of Chartered Institute of Arbitration.
Naveen Kumar Director IIQS, MIIQS, MRICS, CCE, ACI (Arb), DCE
Members Best Compliments
Ramarao KilariDirector IIQS
Ramarao
Paul Mathew, Commercial Manager,
TDIC, Abu Dhabi
Paul BankalaContracts Administrator,
Dubai Aviation Engineering Projects
Basavaraj k BethB.E.(Civil), AIQS(Affil),
CCE, ACIArbDirector & Global Event
Management Chair
George John, Senior Cost Manager,
TDIC, Abu Dhabi
Biju Thomas PuthenPurackal
Senior QS, Link International Property LLC, Abu Dhabi
Prasanna KumariContracts Engineer
ARCO Gen. Contracting LLC, Dubai
TEL. NO.: 04-3958771, FAX NO.: 04-3958775, P.O. BOX 119070, DUBAI, UNITED ARAB EMIRATES
Email: [email protected], Web: www.alavoncontractingsllc.com
TEL. NO.: 04-3958771, FAX NO.: 04-3958775, P.O. BOX 119070, DUBAI, UNITED ARAB EMIRATES
Email: [email protected], Web: www.alavoncontractingsllc.com
TEL. NO.: 04-3958771, FAX NO.: 04-3958775, P.O. BOX 119070, DUBAI, UNITED ARAB EMIRATES
Email: [email protected], Web: www.alavoncontractingsllc.com
TEL. NO.: 04-3958771, FAX NO.: 04-3958775, P.O. BOX 119070, DUBAI, UNITED ARAB EMIRATES
Email: [email protected], Web: www.alavoncontractingsllc.com
97 IIQS - 2015 | 96 | IIQS - 2015
married or divorced, etc. If, with a magic wand, we could put
a group of people into the same set of circumstances (same
house, same spouse, same place of birth, same face, and
same aches and pains), the differences in their happiness
levels would be reducedby a measly 10 per cent.”
Prof. Lyubomirsky notes in her book The How of Happiness
that this finding runs contrary to many of our efforts to
obtain happiness: “One of the great ironies of our quest to
become happier is that so many of us focus on changing
the circumstances of our lives in the misguided hope that
those changes will deliver happiness… An impressive body
of research now shows that trying to be happy by changing
our life situations ultimately will not work. Although we may
achieve temporary boosts in well-being by moving to
new parts of the country or the world, securing raises, or
changing our appearances, such boosts are unlikely to be
long-lasting.”
Most experts agree that human beings immediately adapt
to positive circumstantial changes in the hope of bringing
about happiness in their lives. Although the circumstances
change, it may not be a source of long-term happiness, as
they will eventually be taken for granted.
Happiness strategies
The remaining 40 per cent of our happiness is determined
by our behavior—intentional activities referred to as
“happiness strategies.”
This is the core of the research of leading professionals in this
field which advocates increasing and sustaining happiness
through intentional activities.
Genuinely happy people make things happen, and don’t
just sit around being content. They learn more, achieve
more and control their thoughts and feelings. If an
unhappy person wants to experience interest, enthusiasm,
contentment, peace and joy, he or she can make it happen
by learning the habits of a happy person.
Scientific research supports the use of strategies such as
expressing gratitude, acts of kindness, nurturing relationships,
committing to goals, among others. Researchers describe
precisely what these somewhat generic terms mean in
this context and provide a rationale for why they work and
explore what they might look like in practice. They do not
say that these are the only meaningful happiness strategies,
but separately they meet standards for being “evidenced-
based,” and together they constitute a list sufficiently broad
“so that every individual could find a set right for him or her.”
The science of happiness is here to stay with the single
focus of making the world a better place.
Prof. Christopher Abraham explores the science of happiness, and how it relates to professional and personal success. Psychological studies have primarily concentrated on human failing and pathology. In fact, the idea of psychotherapy, a concept realized by Sigmund Freud, is based on the fact that human beings are distressed and need to be calm.
The practitioners that followed Freud developed a model
that seemed to portray humans as mechanical and
passive, being shaped by situations surrounding them.
However, this view was soon altered when eminent psychologist
Martin Seligman, in 1998, urged psychology professionals to
set about the healing process with understanding and building
strong qualities. Seligman is credited with sowing the seeds of
happiness studies and positive psychology. He went on to be
the world’s leading scholar on optimism.
Seligman’s idea quickly caught on, with the Gallup
organization founding the Gallup Positive Psychology Institute
to fund research on the subject. This provided the foundation
of the Gallup Positive Psychology Summit, which was globally
recognized within two years of it being held.
So what really makes us happy? How can we become
happier? And is happiness sustainable? Current cutting edge
research on studying happiness indicates that our individual
level of happiness springs from three primary sources:
Our genetic set point
• Fifty per cent of our happiness derives from a genetically
determined set point, contend leading researchers such
as Professor Sonja Lyubomirsky from the University of
California.
• The set point for happiness is similar to the set point for
weight. Some people are blessed with skinny dispositions:
even when they’re not trying, they easily maintain their
weight. By contrast, others have to work hard to keep their
weight at optimum levels, and the moment they relax
their dietary and exercise regime, they gain back all the
weight.
• So those of us with low happiness set points will have to
work harder to achieve and maintain happiness, while
those of us with high set points will find it easier to be
happy under similar conditions.
Our life circumstances
“Life circumstances” determine a scant 10 per cent of our
happiness, Prof. Lyubomirsky continues: “Only about 10 per
cent of the variance in our happiness levels is explained by
differences in life circumstances or situations-that is, whether
we are rich or poor, healthy or unhealthy, beautiful or plain,
Happiness Leads To Success
Prof. Christopher Abraham holds three Post Graduate qualifications in Business Administration (Marketing), Human Resources Management, and Labor and Administrative Law.
He is a PhD Scholar in Positive Psychology and the Science of Happiness. He has twenty-eight years of professional experience in management consulting, marketing, executive development and management education.
Currently he is the Sr.Vice President and Head of the Dubai campus at S P Jain School of Global Management, one of the World’s Top 20 ranked Business Schools with campuses in Dubai, Singapore and Sydney.
Christopher Abraham
Indian Institute of Quantity Surveyors 2015 IIQS
CPD Events SnapshotMatrix Events in 2013Matrix Events in 2013
WATER MANAGEMENT
BUILDING CONSTRUCTION
EARTHWORKS & INFRASTRUCTURE
IRRIGATION & LANDSCAPING
M.E.P WORKS
ARCO General Contracting LLC (Al Ryum
Group of Companies),now a highly successful
ISO certified entity, has built a solid reputation
for market excellence, drawing on a rich history
and a strong heritage of Quality, Stability and
Innovative leadership in the marketplace. We take
pride in our successful accomplishment and in
satisfaction of our clients and we regard our clients as
our most valuable asset.
Your Vision, Our Commitment
Our Esteemed Clients
ARCO General Contracting Co. LLCP.O. Box No. 212842, Dubai, UAET: +971 4 4510066Email: [email protected]
Indian Institute of Quantity Surveyors 2015 IIQS
101 IIQS - 2015 | 100 | IIQS - 2015
Global RecognitionInternational
IIQS members have achieved various International
awards from the reputable organizations for their
commitment and their outstanding contribution
towards the society and Quantity Surveying Profession.
IIQS is proud to share our pleasure and congratulating
all the members, who have devoted so much of their
personal and professional time towards the success
of IIQS.
Qatar National Environment Aword
IIQS provides a great platform for networking opportunities during the CPD events as well
as during the social events. Any relevant information required for effectively carrying out
the day to day works and also for upgrading professional qualifications is shared among
the members. Any job opportunities also shared which is of immense help to members
who have lost their jobs or are looking for new opportunities
AIQS Infinite Value AwardMs. Sinimol Noushad, FRICS & Ms. Asha Balachandaran,MRICS, have been honored as Finalist and Winner for“SGA Property Consultancy Women in Construction Award” Sydney, Australia.
Members Achievements
Networking And Job opportunities
During the CPD events, IIQS recognizes the dedication and the hard work of members who upgrade their professional qualifications or achieve membership of prestigious global bodies
Indian Institute of Quantity Surveyors 2015 IIQS
102 | IIQS - 2015
CALGARY PROJECT CONSULTANTS (CPC)
- Established in the U.A.E. since 2008.
- CPC is also a RICS Regulated company.
SERVICES OFFERED
- Quantity Surveying - Cost Management
- Contract Administration - Value Engineering
- Claims Assistance - Project Management
CURRENT & RECENTLY COMPLETED MAJOR PROJECTS
Al Habtoor City – 1660 key hotel complex for Starwood Hotels & Resorts,
Dubai
Waldorf Astoria – 320 key hotel, Palm Jumeirah, Dubai
Metropolitan Hotel and Villa Complex for Al Habtoor Group, Dubai
Town houses and New Retail Center at Jumeirah Island for Nakheel, Dubai
Dubai Herbal & Treatment Center Extension for Roya Project
Management, Dubai
H Hotel Refurbishment for H Hotel, Dubai
Shangri-La Hotel Refurbishment for Roya Project Management, Dubai
Contact Details Tel : +9714 2664163 Fax : +9714 2664184
Email : [email protected]
CALGARY PROJECT CONSULTANTS (CPC)
- Established in the U.A.E. since 2008.
- CPC is also a RICS Regulated company.
SERVICES OFFERED
- Quantity Surveying - Cost Management
- Contract Administration - Value Engineering
- Claims Assistance - Project Management
CURRENT & RECENTLY COMPLETED MAJOR PROJECTS
Al Habtoor City – 1660 key hotel complex for Starwood Hotels & Resorts,
Dubai
Waldorf Astoria – 320 key hotel, Palm Jumeirah, Dubai
Metropolitan Hotel and Villa Complex for Al Habtoor Group, Dubai
Town houses and New Retail Center at Jumeirah Island for Nakheel, Dubai
Dubai Herbal & Treatment Center Extension for Roya Project
Management, Dubai
H Hotel Refurbishment for H Hotel, Dubai
Shangri-La Hotel Refurbishment for Roya Project Management, Dubai
Contact Details Tel : +9714 2664163 Fax : +9714 2664184
Email : [email protected]
CALGARYPROJECTCONSULTANTS(CPC)
CALGARY PROJECT CONSULTANTS (CPC)
- Established in the U.A.E. since 2008.
- CPC is also a RICS Regulated company.
SERVICES OFFERED
- Quantity Surveying - Cost Management
- Contract Administration - Value Engineering
- Claims Assistance - Project Management
CURRENT & RECENTLY COMPLETED MAJOR PROJECTS
Al Habtoor City – 1660 key hotel complex for Starwood Hotels & Resorts,
Dubai
Waldorf Astoria – 320 key hotel, Palm Jumeirah, Dubai
Metropolitan Hotel and Villa Complex for Al Habtoor Group, Dubai
Town houses and New Retail Center at Jumeirah Island for Nakheel, Dubai
Dubai Herbal & Treatment Center Extension for Roya Project
Management, Dubai
H Hotel Refurbishment for H Hotel, Dubai
Shangri-La Hotel Refurbishment for Roya Project Management, Dubai
Contact Details Tel : +9714 2664163 Fax : +9714 2664184
Email : [email protected]
Indian Institute of Quantity Surveyors 2015 IIQS
105 IIQS - 2015 | 104 | IIQS - 2015
About 10 years back when i was new to UAE it was the CPDs at IIQS that got me acquainted to the QS practises in UAE. With all its limitations IIQS did its best to have excellent speakers for the various CPDs whereby our knowledge was enhanced. In addition, it also gave me a platform to be a speaker on more than one occasion.
Other than the above, IIQS have also initiated various other activities amongst which are conducting internal cricket tournaments / participating in other tournaments, organising Family Get together and the like, through which our families are also given its share of fun and enjoyment.
I wish IIQS all the very best for all its future endeavours.
Ajith PhilipContract Manager
Nakheel, Dubai
IIQS star ted its journey with a vision of establishing and maintaining high standards of professional competence and integrity. During the very first CPD I attended, I was very impressed with the work IIQS does. My wish was fulfilled when I joined the IIQS committee and was surprised to see the mix of experience and youth in the committee. I must say that IIQS is really doing a great service to the Construction Industry and truly live to their motto- ‘Lightened to Learn & Live’. My hear tiest congratulations to IIQS and all the best for their future.
Parag Quantity Surveyor
Parsons Overseas Ltd., Dubai
I highly appreciate IIQS’ dedicated and untiring approach in nurturing the professional standards of Indian Quantity Surveyors fraternity. IIQS is providing the required platform to Indian Quantity Surveyors and mentoring them to convert the professional threats into opportunities by attaining various professional memberships from international professional institutes, thereby to compete on an international level and excel in their career. I feel privileged to be associated with IIQS.
I wish Good luck to IIQS in achieving the Chartered status and I look forward to see it’s recognition worldwide in the near future.”
Quraishi B.E, MIE, C.Eng.(I),
MIRC,MIIQSDoha, Qatar
The IIQS, has enabled me to update and develop professionally in my field. I have attended almost all the CPD’s delivered by IIQS, Qatar with great professionalism and standards. IIQS gave me an immense oppor tunity for networking with various kinds of professional people on various capacities working with different organizations. It helped me to develop my communication skills and to gather knowledge on new things which I didn’t know. It has shown me a path towards attaining the additional professional qualifications and guiding the procedure to achieve it.
Venkat N MIIQS
Quantity Surveyor, CCC, Qatar
Quantity Surveying is a humble profession and it is required from inception to completion of any construction. In this competitive world, every professional needs to sharpen their knowledge to sustain in their respective field. Such sharpening happens only when you have the zeal of continuous professional development attitude. IIQS started to take up this challenge and continuous to give such a platform (knowledge hub) to all Indian Quantity Surveyors. IIQS started with a small drop of water and has become an oasis of knowledge sharing hub in the Gulf desert and slowly spreading to other parts of the World. It is also having healthy relations with all other nationalities over here in QS field. Great courage, discipline, voluntary spirit, strong mottos, good ethics, strong relationship and incessant thrust for improvement are the leading contributors to thrive the IIQS in this region. We are all contributing to develop IIQS to give dividends to us in our future endeavors and to our upcoming disciples of QS. It’s my pride and strength to be a part of IIQS. “Learning never ends, Knowledge never be stolen, improvement never stops”
Chamarty B. Tech, MBA
Senior Quantity SurveyorDUTCO BALFOUR BEATTY
LLC,
Being par t of IIQS is one of the most positive professional experience I have had in my 14 years as a QS and Contracts Engineer. I highly recommend IIQS CPDs and APC workshops to any individual interested in expanding their professional membership training needs. I appreciate how the lectures were kept engaged by the speakers who are very experienced and knowledgeable about the subject being dealt with. The information shared is exceptionally lot more than what was expected.Once again many thanks to IIQS for its incredible help and suppor t in my career.
Prasanna Contracts Engineer
ARCO Gen. Contracting LLC, Dubai
“After my association with IIQS in year 2014, I realise the positive changes come in my professional life day by day. I strongly believe that IIQS provides a platform to share the knowledge, grow in the profession to move next level and
serve for the society.
The success behind the IIQS where it stands now is only because of strong leaders,many of talented professionals and their effor ts.
The Days are not too far that IIQS achieving the higher limits in future.I wish all the very best to IIQS and I am proud to be a member.”
Sebastin MIIQS,
Doha, Qatar
Being a new IIQS member since June 2015, I am for tunate to be par t of IIQS. I attended first IIQS CPD Event in April 2015; I take this oppor tunity to thank IIQS team for creating such an event in a very professional manner in Qatar. There is still long way to go but I still feel I am late to join IIQS and thankful to IIQS Doha MC team for their hard work as they
are putting high effor t to make it a great success.
WASHIM MIIQS
Doha, Qatar
It gives me immense pleasure to be par t of this souvenir. I take this oppor tunity to mention here that I had been associating with IIQS since I was in Dubai. In Qatar from inception I am par ticipating in all activities conducted by IIQS Qatar Chair. The association with IIQS really supplied me the nourishment to my carrier through well organized CPDs
and structured training program. I could see young Indian Quantity Surveyors are developing their professional skill to compete with the industry requirements in the Middle East which is a great achievement by IIQS. I am sure by this pace
and motivation we will achieve the status of ‘Char tered’.
TharamalCCP, MIS, ACIArb,
MIIQS
I have been associated with IIQS for the past 10 years and actively par ticipating in the affairs of Qatar chapter of IIQS. I have attended all the CPD’s conducted by IIQS and it helped me a lot in carrying out my day to day activities in my role. I also joined APC workshop conducted by IIQS which helped me to improve the QS competencies. IIQS Qatar chapter conducting CPD’s on current trends in market. IIQS gave me access to meet highly qualified
professionals in the Industry. IIQS is immensely helping all QS professionals in improving their professional exper tise along with guiding through job oppor tunities. I would like to thank all the members of IIQS Team who are behind the success of IIQS and wish
them all the best.
kiran MIIQS
Doha, Qatar
IIQS offers the best available seminars in the region. I have enjoyed all the seminars and workshops conducted by IIQS which has helped me in my day to day works. Hats off to IIQS founders and all who are presently running the show to
offer the best professional guidance and suppor t to APC candidates and aspirants.
Siji MIIQS
Doha, Qatar
IIQS TESTIMONIALS
106 | IIQS - 2015106 | IIQS - 2015
Offshore Wind Projects
Dredging
Offshore Oil & GasIn just two words, marine ingenuity,
we express that we are passionate
dredging and marine contractors
with a worldwide innovative
approach to meet your challenges.
Our people - who manage a
versatile fleet - specialise in
dredging, marine engineering
and offshore projects (oil, gas
and wind).
www.vanoord.com
Dredging and Marine Contractors
Marineingenuity
Magazine Editor Editorial Team
Editorial Team Wow! the magazine editorial team has
finally made it! A nostalgic memory of the team working their way forward to ensure that the magazine
‘IIQS Annual Insight 2015’ is unveiled on 1st August 2015 at
IIQS International Conference, Bangalore
Dharmendar Pardasani | E.V. Johnson Neil | Syed Aslam | Govindaraju Rathod | Mr. Varughese Mathew | Paul BankalaSinimol Noushad
Dutco Balfour Beatty LLC
Dutco Balfour Beatty LLC (DBB). started in the UAE in 1976 and has evolved to become one of the leading and preferred multi disciplinary Construction Company based out of Dubai and operating throughout the United Arab Emirates. DBB has been involved in many developments that have become significant landmarks in the United Arab Emirates.
DBB is regarded as one of the largest and most diversified Civil Engineering, Building and Marine contractors in the United Arab Emirates with an umbrella of capabilities comprising of independently managed Construction, Mechanical and Electrical divisions.To know more about our capabilities make an enquiry on [email protected]
FLEXIBLESAFETY
CLIENTSSYNERGY
STANDARDSSUCCESS
EMPLOYEESGROWTH
COMMUNITIESQUALITY
INTERIORS & FITOUT
|
| ||
||
ROADS & INFRASTRUCTURE MARINE PLANT & TRANSPORT
SCAFFOLDING PILING & GROUND ENGINEERINGSPECIAL PROJECTSBUILDING
Roads & Infrastructure
Special Projects - Dubai mall
Marine & Civil
Civil & InfrastructureInteriors & Joinery
A Dutco Balfour Beatty Company
Tel: 971 4 8801010+ Email: [email protected]| | | | www.dutcobalfourbeatty.comP.O.Box 8944 Dubai, UAEFax: 9714 8801515+