    SAP Planning & Scheduling Workshop

    Gus McIntosh

    Ben Mansi

  • Real Experience. Real Advantage.

    [

    2

    Learning Points

    Understand the capabilities of SAP and how you can use them to support an effective planning & scheduling process.

    Explore non standard SAP PM options for scheduling and how they can support your requirements.

    Better understanding of key tools and approaches that can be deployed to provide the basis for measuring planning and

    scheduling performance improvement.

  • Real Experience. Real Advantage.

    [ Agenda Planning in SAP

    Task Lists

    BOM

    Work Order Planning

    Scheduling

    Dates

    Capacities

    Capacity Evaluation

    Planning Board

    Project Systems

    MRS

    PMX

  • Real Experience. Real Advantage.

    [ Planning in SAP

    Task List Overview

    Task List Details

    Structures / functions

    Supporting Maintenance Plans / One Time Work

    Bill of Materials

    Work Order Planning

    Tools to Support Work Planning

    List Edit Reports

  • Real Experience. Real Advantage.

    [ Task List Overview Task Lists describe the sequence of individual maintenance activities to be

    performed, identify the required Resources (Labor, Materials, Services,

    Special tools) and related procedures.

    Predefined list of Work activities that contain Work Group, Skill, Work Description, Duration, Number of Workers and associated Material Items.

    Task Lists are building blocks of Maintenance Plans.

    Simplifies the Work Order Planning process

    Task List TL Types:

    General (can be used on multiple objects) (TL Type A)

    Functional Location (associated with FLocs) (TL Type T)

    Equipment (associated with specific Equipment item) (TL Type E)

    The type of Task List created will depend on the objective of the plan /and related Technical Object

    General TL can be configured

  • Real Experience. Real Advantage.

    [

    Contents

    Usage

    Work steps (operation)

    Long text (Std Text) instructions

    Maintenance work centers

    # Resources, Duration, Total Work

    Material components (Stock / non-stock w/BOM)

    Special Tools/drawings/equipment (PRTs)

    Craft / Specialists / Qualifications / Contractors

    Regular maintenance (PMs, PdMs, servicing & inspection)

    Major maintenance Activities (planned repairs, Overhauls)

    Why?

    To standardize work processes

    To plan maintenance orders more effectively

    To create maintenance plans more quickly

    Task List Overview

    Who?Maintenance and Service Planners

    Reliability Engineers

  • Real Experience. Real Advantage.

    [ Task List Overview

    Maintenance Item

    Maintenance Item

    Item dataPlanning dataTask List dataMaint. Plan dataLocation/accountassign

    Object ListObject List

    Lists of:Functional LocationEquipment

    MaintenanceStrategy

    Maintenance Plan& ScheduleWork

    Order

    Maintenance Task List

    Operation

    Operation

    OperationSub-Operation

    Maintenance Task List

    Operation

    Operation

    Operation

    Sub-Operation

    Long Text

    Standard Text

    Tools

    Services

    Components

    Labor

    Task List Overview

  • Real Experience. Real Advantage.

    [

    Equipment

    (Turbine 1000)

    Task List

    (Turbine 1000)

    Operation #1

    Operation #2

    Operation #3

    Operation #1

    Operation #2

    Leverage one or

    more Task Lists

    for planning work

    orders

    Task List Overview - Use in work order

  • Real Experience. Real Advantage.

    [ Task List

    Task List Header

    Operation

    Sub-operation

    Material

    Production Resources/Tools

    Maintenance Package

    Example of FL Task List

    Group and Group Counter numbers can be internally or externally maintained

    Header defines default Work Center

  • Real Experience. Real Advantage.

    [ Task List Use in Preventive Maintenance

    Task List Header

    Operation

    Sub-operation

    Material

    Production Resources/Tools

    Maintenance Package

    Standard / Long Text

    Classification

    Object Dependencies

    User Defined Fields

    Control Key (Internal, External, Services)

  • Real Experience. Real Advantage.

    [ Task List Profile

    General settings typically common

    across plants

    Internal processing settings typically

    common across plants

    External processing (operation

    Services) defaults can cause the need

    for multiple profiles by plant.

    Header data settings common across

    plants

    TL Profile Parameter ID PIN Sets default in IA01,2,3,5,6,7,13,14,15

  • Real Experience. Real Advantage.

    [ Task List StructureTask List Overview

    Header

    Operation Overview

    Operation details copied onto Work Order

    TL Group w/multiple

    Counters

    Alpha/numeric

    Work Center & System

    Condition are defaults

    for TL Operations

    Matl BOM populated

    on Gen TL makes items

    available

  • Real Experience. Real Advantage.

    [Only applicable if used in Strategy Plan

    Defines applicably frequency per Task / Operation

    Task List Structure Package Allocation Options

    This option has limited

    view of package text.

    This option has

    better view of

    package text but

    more screens

  • Real Experience. Real Advantage.

    [

    Internal Processing Detail

    Resources provided from internal Work Centers

    Work requirements define resource forecast when associated with Maintenance Plan

    Task List Structure Internal Processing

  • Real Experience. Real Advantage.

    [ Components Show Operation Assembly Options General Task Lists, Assembly (Material) BOMs can be used to display part

    requirements

    Assemblies are useful

    on work order

    operation assembly

    field for planning

    Parameter ID:

    PM_TREE_INACTIVE = X

    Non-stock assignment Only

    through a BOM

  • Real Experience. Real Advantage.

    [ Task List Structure - Components

    Component Overview

    From selected Operation Setting of 1 results in

    order setting:

    Use to

    activate on

    order

    Standard(S) BOM for freely assigned parts

  • Real Experience. Real Advantage.

    [

    Operation Relationship

    Finish to Finish

    Finish to Start

    Start to Finish

    Start to Start

    Task List Structure - Relationships

  • Real Experience. Real Advantage.

    [Standard FS relationship applies based on Operation #

    Relationships can be applied

    They are copied onto Work Order

    Network graphic is easiest way to maintain relations

    Task List Structure - Relationships

  • Real Experience. Real Advantage.

    [Relationship data copied from Task List onto Work Order

    Order scheduled with basic start of 01/31/2007

    Task List Structure - Relationships

  • Real Experience. Real Advantage.

    [With offset

    Task List Structure - Relationships

  • Real Experience. Real Advantage.

    [ Task List Structure - Relationships

  • Real Experience. Real Advantage.

    [ Task Lists - Supporting Maintenance Plans

    Strategy Plans must

    have same Strategy

    on Task List, Items

    and Plans

    Strategy plans

    MUST have a task

    list or will not

    schedule plan

    Error.

    Task Lists applied in same way to Strategy, Single

    Cycle or Multiple Counter Plans

  • Real Experience. Real Advantage.

    [ Task Lists - Supporting Reactive / One Time Work / OverhaulsUsing existing Task List to plan Work Order

    Choose all or specific Work Centers

    Choose all or specific Operations

  • Real Experience. Real Advantage.

    [Using Task List to plan Work Order Or setup as Manual call

    Task Lists - Supporting Reactive / One Time Work / Overhauls

  • Real Experience. Real Advantage.

    [Can use sub operations to plan multiple resources on same task list operation

    No component, PRT planning, External Services

    No date scheduling specific to sub operation

    No Relationships and Constraints

    Defined at superior Operation levelOn Work Order can adjust start and end times using offset

    Capacity requirement defined for sub operations

    Included within capacity loading

    Available within Planning Table for Dispatch

    Enter confirmations at sub operation level

    Operations & Sub operations

  • Real Experience. Real Advantage.

    [

    Apply Long text using standard text key

    Apply text directly to Operation

    Cut / Paste

    Upload

    Procedures and Long Text

  • Real Experience. Real Advantage.

    [ Planners and MRO Inventory and Purchasing

    Components:

    Stock material

    Non-stock Material

    Text Item

    Document

    Equipment(Pump)

    Coupling ImpellerBearing/Gasket

    Assembly

    Bearing Gasket Misc. Hardware

  • Real Experience. Real Advantage.

    [US01

    Aromatics

    ACU - East

    M1118 EXT. RDC COLUMN MIXER

    M6833 RDC MIXER

    P1677 RAFFINATE BOOSTER

    P4283 PARAFIN STRIPPER BOOT WATER

    P9614 TOLUENE COLUMN REFLUX PUMP

    Plant

    BPU

    Unit

    Equipment

    Service

    10003857 P-9614 PUMP

    BOM

    Equipment

    BILL OF MATERIALS FOR P-9614

    CHEMICAL SUPER PLANT

    AROMATICS

    AROMATICS CATALYTIC UNIT - EAST

    879444

    123456 Pump Shaft

    1.020 X .0075 Bearing

    BOM

    Bill of Materials

  • Real Experience. Real Advantage.

    [ Bill of MaterialsEquipment BOM Example

  • Real Experience. Real Advantage.

    [ Bill of MaterialsEquipmentBOM

    Equipment Equipment Equipment Equipment

    Mat 1

    Mat 2

    Mat 10

    Mat 11

    Mat 3

    Mat 6Mat 20

    Mat 7

    Construction typeBOM

    Construction

    type

  • Real Experience. Real Advantage.

    [

    Construction Type /

    Material BOM

    Equipment BOM

    BOM Items

    Bill of Materials Construction Type

  • Real Experience. Real Advantage.

    [

    Construction Type / Material BOM assigned to General Task List

    General Task List is made available as ref. object to related Equipment

    Bill of Materials Construction Type

  • Real Experience. Real Advantage.

    [ Work Order Planning

    Manual planning of Operations

    Similar structures / functions as for Task List

    Can establish default calculation method:

    Calculate Work

    Calculate Duration

    Calculate Manually

    All Internal Labor planned with reference to an Activity Type

    Holds Cost Rate

    Is used to calculate Plan and Actual labor cost

  • Real Experience. Real Advantage.

    [

    Select from BOM or add manually

    Work Order Planning

  • Real Experience. Real Advantage.

    [

    Material Requirement Date set by Operations Start

    Can adjust with Offset

    Work Order Planning

  • Real Experience. Real Advantage.

    [

    Unplanned Service Requirement

    Overall limit set

    Planned Service

    Need defined in terms of detailed Service Items referencing a Contract / Service Master

    Work Order Planning

  • Real Experience. Real Advantage.

    [ Codes To Support Work Planning Tools to help Planner manage the work

    Priority & Risk codes

    Equipment Criticality (ABC)

    Equipment Availability (System Condition, Revisions)

    User Status to support control, workflow and reporting

    In Planning or equivalent

    Review in field

    Waiting on Engineering, MOC.

    To further support Parts status

    Routinely a review of work orders should be made so that

    Priority work orders are being planned first

    Common Locations of multiple work orders can be reviewed

  • Real Experience. Real Advantage.

    [System Condition use to identify operational state for required intervention

    Revision code options for use

    Define turnarounds / outages / shutdowns

    Apply target basic dates

    Tagging / Grouping

    Basic Work Order scheduling

    Codes To Support Work Planning

  • Real Experience. Real Advantage.

    [ Consider different PM Priorities

    There needs to be a way to identify PMs

    that can be scheduled anytime. E.g. certain

    inspections. See Priority 0

    Assignment is across all plants by Order Types

  • Real Experience. Real Advantage.

    [ Operating Condition - Coordination with Production

    This field can be used to identify if the work can be performed while the equipment is in operation (like certain inspections, vibration analysis, testing) or if the equipment must be taken out of operation.

    It can be part of the ready to work criteria in selecting orders for scheduling.

    The Reservation by PM is part of the

    integration with Production Planning at the work center level.

  • Real Experience. Real Advantage.

    [ Operating Condition Where Used Order Header

  • Real Experience. Real Advantage.

    [ Operating Condition Where UsedOrder / Task List Operations

    The importance at the operation level is knowing in IW37N whether the equipment needs to be shutdown or in operation

    Maintenance Item (partial screen below)

    Setting the Operating Condition on the Maintenance Item will default to the work order header.

  • Real Experience. Real Advantage.

    [

    User Status to support process / workflow

    Control related single option

    Information multiple selection

    Codes To Support Work Planning

  • Real Experience. Real Advantage.

    [ User Statuses Informational for Process

    Informational User StatusesNo numbering, Multiple active, Can be automatically set, Transaction controls, Position controlled, Authorization controllable

    Used for process and backlog/fore log management, general information

  • Real Experience. Real Advantage.

    [ User Statuses Sequentially Controlled

    Statuses can be:

    Sequentially numbered and activated/deactivated, Sequence controlSingle activationAuthorization controllable

    Used for process control and backlog/fore log management

  • Real Experience. Real Advantage.

    [ Status Transaction Controlled

    In this example, the status INP (In Process) is automatically set when a work order is printed or reprinted.

    The status INP is removed when the order is TECOd.

  • Real Experience. Real Advantage.

    [ User Status Assignments

    Assignment is at the order type and operation level

    Note: User statuses are available for notifications, orders, equipment, functional locations, serial numbers, IBase,

  • Real Experience. Real Advantage.

    [

    ABC Indicator for Criticality

    Codes To Support Work Planning

  • Real Experience. Real Advantage.

    [ ABC Indicator - Examples

    Used in List Edit displays to prioritize work

  • Real Experience. Real Advantage.

    [ Plant Sections

    Used in List Edit displays work locations.

    Augments functional location for some users.

  • Real Experience. Real Advantage.

    [ Planner GroupsPlanner Group Tables

    One table for flocs,

    equipment,

    notifications/orders

    One table for task

    lists

    Planner groups for orders is the number one means of

    denoting ownership of the order from a planning

    perspective. Work center is another common approach.

  • Real Experience. Real Advantage.

    [ Planner Group Use

    Planner group maintained on floc or equipment will default

    to notification or order unless user maintains personal

    defaults.

    Planner Grp On Notification

    Planner Grp On Order

  • Real Experience. Real Advantage.

    [ Planning Indicator Good KPI but bad locationThe Planning

    indicator provides nice out of the box

    reporting.

    The problem is the indicator is buried on the Control tab. GUIxT is a good solution.

  • Real Experience. Real Advantage.

    [ Planning indicator - Definition

    Planned: All preventive maintenance orders and other work orders that require planner intervention before the job is started.

    What if no parts and the operation is estimated/planned?

    Do KPIs exclude PMs?

    Unplanned: Work that is not immediate and handed to a craft to troubleshoot and plan themselves. No previous planner intervention.

    Immediate: Break in work that is not planned.

    Other solutions besides the planning indicator

    Important: Understood and agreed upon definition used consistently.

  • Real Experience. Real Advantage.

    [

    User Defined Fields

    Available within Planning Table

    Codes To Support Work Planning

  • Real Experience. Real Advantage.

    [ Default Settings on work order

  • Real Experience. Real Advantage.

    [ Default Settings on work order

  • Real Experience. Real Advantage.

    [

    By setting at Operation level to Immediately all Reservations or Requisitions associated available for further processing

    Setting can also be made at Component level

    Default value is configurable

    Early Release of Material Requirements puts in process without need to fully Release the Work Order for execution

    Generates Purchase Requisition and initiates Procurement process

    Stock Reservation established

    When and why would you release materials early?

    Where there is a long lead item and need exists to place purchase order

    Materials Planning Release

  • Real Experience. Real Advantage.

    [ List Edit Reports

  • Real Experience. Real Advantage.

    [

    Material Availability can be checked at any time from within the Work Order

    A Material Availability Report is also available that can provide status across multiple Work Orders

    Availability Report also includes for Non Stock items where planned Goods Receipt dates are compared to Operation Earliest Start dates

    Materials Availability

  • Real Experience. Real Advantage.

    [ Availability Checking Control

  • Real Experience. Real Advantage.

    [SAP List Edit function facilitates review of and adjustment of Work Orders

    IW38 Order Header

    IW37 Order Operations

    IW37N Order Header & Operations (Require 4.7 SP EA_APPL 200)

    Manage Planning Activities - List Edits

  • Real Experience. Real Advantage.

    [

    Column layouts can be adjusted and saved as user specific variant

    Can Sort on columns and filter data, e.g. by Status (System and User)

    Select single or multiple Work Orders and drill down to individual objects in Change mode

    Can carry out functions collectively e.g. Release Work Order

    Manage Planning Activities - List Edits

  • Real Experience. Real Advantage.

    [ Periodic Maintenance Schedule General industry acknowledgement of need for an effective scheduling

    process ensuring:

    Most important work is being executed

    It is being worked at the optimal time

    Execution is undertaken employing the most appropriate and available resources

    Cost of execution is reduced

    Most top performing Maintenance Organizations establish a Weekly Schedule and measure compliance against it.

    Schedule requires involvement and agreement from all involved departments particularly Production and Maintenance.

  • Real Experience. Real Advantage.

    [ Weekly Scheduling in SAP

    Objectives:

    Outline the use of standard SAP Capacity Leveling and Evaluation functions to support creation of Weekly Maintenance Schedule

    Identify options and approaches that work best

    Keeping it simple

    Consider shortfalls in functionality

    Touch on approaches without use of Capacity Leveling

  • Real Experience. Real Advantage.

    [ Prerequisites to Periodic Scheduling process

    An effective SAP planning process that defines and prioritizes work

    A maintenance backlog accurately represented in SAP in terms of:

    Work activity, labor resource estimates (number of people and man hours) and durations

    Material Requirements

    Criticality and Priority

    Work Categorization (e.g. Preventive, Corrective, Project, etc.)

    Resource group / Work Center capacity information maintained to reflect:

    Standard Working Times

    Weekly available capacity

  • Real Experience. Real Advantage.

    [ Scheduling in SAP SAP Date Scheduling

    Relationships & Constraints

    Revisions

    Manage Work Center Capacities

    Standard / Intervals / Versions

    Calculation from HR Employees / Work Center Hierarchies

    Capacity Evaluation

    Work Orders - Ready to Schedule?

    Scheduling Options:

    Capacity Leveling (Tabular Planning Table)

    Publish the Schedule

    Schedule Compliance Reporting

  • Real Experience. Real Advantage.

    [ Typical Scheduling Process

    Maintain Shifts &

    Availability

    Manage Work Center

    Capacity

    EvaluateRequirements

    v Capacity

    Define Weekly Schedule

    Hold PlanningMeetings

    FinalizeWeekly

    Schedule

    CommunicateWeekly

    Schedule

    Manage Work ready

    to be Scheduled

    Prepare to Schedule

    ManageEmployees &

    Schedules (HR)

    Work PlanningProcess

    ExecutionProcess

    ManageRemaining

    Work

    ManageDailyWork

    Assignment

    Preventive& Predictive

    Process

  • Real Experience. Real Advantage.

    [ SAP Date Scheduling Adopt a scheduling direction Forwards or Backwards

    Duration and Work Center standard work times drive Work Order schedule date calculation

    Time Window for Work

    4hrs 4hrs 6hrs 4hrs

    Basic Start

    Op. 010 Op. 020 Op. 030 Op. 040

    Work OrderBasic Start

    Date

    WO ScheduledDates

    Adjusted

    Times constrained by Work Center operating time

    Scheduling Direction

    010 020 030 040

    Start date 12/13/2007 12/13/2007 12/13/2007 12/14/2007

    Start time 7:00 11:00 15:00 12:00

    Finish date 12/13/2007 12/13/2007 12/14/2007 12/14/2007

    Finish time 11:00 15:00 12:00 16:00

    Duration (hours) 4 4 6 4

    People involved 2 1 2 2

    Work 8 4 12 8

    Work Order Operation

    Schedule Start

    Schedule Finish

  • Real Experience. Real Advantage.

    [ SAP Date Scheduling

  • Real Experience. Real Advantage.

    [ Scheduling Types

    Typically there are no reasons to change standard SAP Scheduling Type settings.

    The with Time indicator allows input of times against basic start and end dates as shown below.

  • Real Experience. Real Advantage.

    [ Scheduling Types

    The with Time indicator allows input of times against basic start and end dates as shown below.

  • Real Experience. Real Advantage.

    [ Scheduling Types

    3 Only Capacity Requirements

    All Operation Dates / Times set from Basic dates

  • Real Experience. Real Advantage.

    [ Scheduling Parameters

    Defined in configuration & control how dates are calculated

    Defined for Plant / Order Type

  • Real Experience. Real Advantage.

    [ Scheduling Parameters

    Options for Date Adjustment

    Do you want to adjust or retail Basic Dates?

    Are Material Requirement dates to be driven by Order Start or Operation Start?

    Automatic Scheduling: switch on to ensure dates are always re-calculated when Order processed / saved

    Scheduling with breaks: Consider excluding breaks from Work Center operating times. This ensures clean start and finish times without SAP calculations in fractions

    of hours.

    Shift Order: Switch on to exclude confirmed actual dates and times from re-calculation of schedule e.g. if work was not completed and need to adjust schedule

    dates to another time in future.

  • Real Experience. Real Advantage.

    [ Work Order Relationships & Constraints

  • Real Experience. Real Advantage.

    [ Work Order Relationships & Constraints

    Typically no need for complex relationships and constraints

    Adopt simple and standard approach to use of dates

    Operation start and stop dates / times are driven by WC Operating time

    You want to have a process where you adjust Order dates (start or finish) and let system calculate scheduled dates

  • Real Experience. Real Advantage.

    [ Revisions Transaction OIOB used to define Revisions

    Revisions can be used to define Maintenance Periods etc.

    Change Basic Start / End Dates

    Can adjust Revision dates and collectively re-apply

  • Real Experience. Real Advantage.

    [ Assign Revisions

    Can apply direct on Work Order Header or collectively through IW38 or IW37N

    Select Orders and assign Revision dates

  • Real Experience. Real Advantage.

    [ Can access & maintain from capacities from within both Evaluation &

    Leveling

    Changes to calculations are immediately reflected on Table / Reports

    If change from Planning Table will only become permanent when Save on exit

    Capacity values are not stored in SAP dynamically calculated

    Viewed in reference to a Factory Calendar

    SAP

    HR

    Work Center Capacity

    Capacity

    Planner Group

    Factory

    Calendar

    Employee HR

    Assignment

    Versions

    3 aspects can be taken into account:

    Standard Capacity

    Intervals & Shifts

    Versions

    Intervals of

    Available

    Capacity

    Standard

    Available

    Capacity

    Manage Work Center Capacities

  • Real Experience. Real Advantage.

    [ Factory Calendar Defines working days & Holidays

  • Real Experience. Real Advantage.

    [ Standard Work Center Capacity Defined on WC Capacity Header screen

    Can be used to group Work Centers in Capacity Planning

    Required if executing finite scheduling

    Required if assigning Shifts

  • Real Experience. Real Advantage.

    [ Standard Work Center Capacity

    For each Work Center you establish a standard available capacity and working times that reference a specific Factory Calendar

    Factory Calendar (defines working days / non working (including holidays) days.

    Breaks can be defined that are deducted from available operating time

    For typical routine maintenance scenarios it is recommended to exclude breaks and adjust start and finish dates to reflect normal available work time

    The standard capacity is applied to all the working days defined within Factory Calendar

    For non working days the capacity is set to zero.

    As previously notes the working times influence how schedule dates are calculated on the Work Order

    Work Center Capacity

    = Number of Ind. Capacities * Operating Time

    (Operating Time is adjusted by Utilization)

  • Real Experience. Real Advantage.

    [ Standard Work Center Capacity

    Calculation examples:

    (10 * 1.0) * 2 = 20

    (9 * 1.0) * 3 = 27

    (9 * 0.9) * 3 = 24.3

    (9 * 1.2) * 3 = 32.4

    Operating Time = Calculated Work Time * Utilization

    10 hrs, No Breaks = 10

    10 hrs, 1 hr Breaks = 9

    (10 * 1.0) * 2 = 20

    (9 * 1.0) * 3 = 27

    (9 * 0.9) * 3 = 24.3

    (9 * 1.2) * 3 = 32.4

    Operating Time = Calculated Work Time * Utilization

    10 hrs, No Breaks = 10

    10 hrs, 1 hr Breaks = 9

  • Real Experience. Real Advantage.

    [ Standard Work Center Capacity

    Calculation examples:Work Center factory calendar defined as 7 work days / week

    Non working holidays defined on 12/25 and 1/1

    Available capacity 45 hours per day

  • Real Experience. Real Advantage.

    [ Intervals & Shifts Standard capacity can be further refined by adding Intervals

    Different capacities can be set for individual days or periods of time

    In this example no intervals yet exist

    Indicates standard capacity

  • Real Experience. Real Advantage.

    [In this example interval added

    Note: Interval operating times also impact Order date scheduling.

    Intervals & Shifts

  • Real Experience. Real Advantage.

    [

    Monday 21st Holiday per Factory Calendar

    ----- 7 Day Cycle ---------

    - 5 Day Interval--

    Intervals & Shifts

  • Real Experience. Real Advantage.

    [To add an interval

    1 (default) or 7 days are applicable cycles

    Intervals & Shifts

    Although 7 day cycle only first 5 days applicable to Interval.

  • Real Experience. Real Advantage.

    [

    Monday 21st Holiday over ridden by Interval

    ----- 7 Day Cycle ---------

    - 5 Day Interval--

    Intervals & Shifts

  • Real Experience. Real Advantage.

    [ Intervals & Shifts

  • Real Experience. Real Advantage.

    [ Intervals & Shifts Can reference and apply shifts defined within HR

  • Real Experience. Real Advantage.

    [ Intervals & Shifts Can apply shift sequence and define capacity by shift

  • Real Experience. Real Advantage.

    [Can have multiple Versions of available capacity within Work Center

    3 Standard delivered versions

    Can add your own versions

    Can change active Versions when evaluating capacity or leveling (scheduling)

    Intervals are associated with specific versions

    Capacity Versions

  • Real Experience. Real Advantage.

    [Can apply different Versions of available capacity on Work Order Header

    Schedule dates reflect defined versions.

    Capacity Versions

  • Real Experience. Real Advantage.

    [

    HR assignment

    Employee Assignment & Capacity Calculation

    Within Capacity Leveling it is possible to calculate available capacity based on individual work schedules maintained within HR Master Records.

    Configuration setting on Evaluation Profile

    Not possible within Evaluation

    Cumulate Capacity based on employees assigned to Work Center Capacity

  • Real Experience. Real Advantage.

    [ Employee Assignment & Capacity Calculation

  • Real Experience. Real Advantage.

    [Capacity leveling reflects HR Schedule of employees

    Work Center Capacity is ignored

    Employee Assignment and Capacity Calculation

  • Real Experience. Real Advantage.

    [

    Easy to configure reporting function to further support scheduling process

    Capacity Evaluation

  • Real Experience. Real Advantage.

    [

    Standard Overview

    Work Center Work Center

    Change Work Order

    Output to Printer

    Export to Excel

    Capacity Evaluation

  • Real Experience. Real Advantage.

    [

    Change Capacity

    Work Center Work Center

    Detailed Capacity List

    Capacity Planning Table

    Capacity & Work Order changes dynamically update reports

    Change Work Order

    Dispatch Work

    Can branch to Capacity Planning Table & Dispatch work (Prepare Schedule) Changes update reports

    Capacity Evaluation

  • Real Experience. Real Advantage.

    [Select via overall profiles

    Configured to meet specific reporting needs

    Evaluation periods

    Period Display

    e.g. Day, week, Month

    Data selection options

    Filters

    Exceptions

    Can use Wildcard * in selection

    Selection by status of Order

    Capacity Evaluation

  • Real Experience. Real Advantage.

    [The Standard Overview report

    comparison of requirements compared to available capacity

    Can adjust profile settings on the fly

    Capacity Evaluation Standard Overview

  • Real Experience. Real Advantage.

    [

    Differing intervals to be evaluated

    Time period definition

    Applied Capacity Version

    Can filter display based on loading

    Capacity Evaluation Standard Overview

  • Real Experience. Real Advantage.

    [

    Graphic views available

    Capacity Evaluation Standard Overview

  • Real Experience. Real Advantage.

    [ Capacity Evaluation Standard Overview

  • Real Experience. Real Advantage.

    [

    Provides a breakdown of each requirement period in an Order Operation list form.

    Layout can be configured to meet specific needs

    Does not use ALV technology

    Can download to Excel etc.

    Capacity Evaluation Detailed List

  • Real Experience. Real Advantage.

    [ Work Orders - Ready to Schedule?

  • Real Experience. Real Advantage.

    [ List Edit - Used to manage backlog

    Establish layouts to sort by Criticality, Priority, Order Type, Basic dates, etc.

    System & User Status to select and identify readiness for scheduling

    Drill down to adjust Work Order plan and status data

    Use Revision functionality

    Collective assignment & update of Basic Dates

    Direct Access to Material Availability report for

    selected Order / Operations

  • Real Experience. Real Advantage.

    [ Order & Operations List Single screen combining Order

    Header and Operation data.

    Can define and save both selection parameters and layouts to meet

    specific Scheduler processing

    functions.

    Manage Backlog

    Manage dates / apply Revisions

    Check Materials Availability

    Publish Weekly Schedule

    Monitor execution status

  • Real Experience. Real Advantage.

    [ Order & Operation List Schedule Overview

    Schedule Overview (Gantt)

  • Real Experience. Real Advantage.

    [

    Materials Availability Report

    Order & Operation List Materials Availability

  • Real Experience. Real Advantage.

    [ Materials Availability

  • Real Experience. Real Advantage.

    [ Capacity Planning Table Using Planning Table to create the Weekly Schedule

    Review work requirements against capacity

    Manipulate capacity & requirements

    Dispatch operations requirements to specific work days

    Recommend use of CM25 Variable Capacity Planning Table

    Dispatching work moves an operation onto a particular day and changes Operation system status (to DSPT).

    This day may or may not be the same as how it was originally planned / scheduled in the work order.

    Two dispatching options:

    Manual

    Finite (using a dispatch strategy).

  • Real Experience. Real Advantage.

    [ Getting to Planning Table Can navigate between IW37N and

    Planning Table using selection to

    determine Orders to be included.

    Call up Planning Board directly

    Select by Work Center

    Can refine selection further e.g. Revision

    Recommend finalizing schedule using direct access to ensure all requirements accounted for

  • Real Experience. Real Advantage.

    [ Getting to Planning Table Can change time settings

    before execute.

    Can further filter requirements data.

  • Real Experience. Real Advantage.

    [ Time Profile Settings Backlog

    Orders show

    yesterday

    Todays date = 1/24/2008

    Backlog Orders show today

  • Real Experience. Real Advantage.

    [ Tabular Planning Table Overview

    View work requirements by period

    Configure layout, selection rules, time periods of

    table to meet specific company needs and

    scheduling timeframes

    Define weekly schedule by assigning

    (Dispatching) work

    Adjust dates within table to balance

    resources with work requirements

    Can Maintain Capacity and Order details

    directly from table

    Capacity details available / scheduled

    Work List details

  • Real Experience. Real Advantage.

    [For weekly schedule recommend daily view

    Weekly or Monthly views can be used for longer term planning / scheduling

    Week

    Tabular Planning Table Views

    Month

  • Real Experience. Real Advantage.

    [ Tabular Planning Table Requirements Section of Planning Table

    Field values and layout can be configured

    Not ALV technology so somewhat limited

    15 fields maximum

  • Real Experience. Real Advantage.

    [

    CapacityRequirements

    from Work Order

    Operations

    Daily Capacityof

    Work Center

    Planning Table

    MECH

    12/11/07

    24 Hrs

    6 Hrs

    18 Hrs

    12/12/07

    24 Hrs

    12 Hrs

    8 Hrs

    12/13/07

    24 Hrs

    0 Hrs

    4 Hrs

    Avail.Cap

    Dispatched

    Pool/Rqmts

    Total Reqts # P A OT S Start Time Order Op Op text FL

    6 Hrs 1 PM03 0 01/22/2008 07:00 816542 0010 Op 1

    12 Hrs

    8 Hrs

    4 Hrs

    Period

    1 PM03 0 01/22/2008 07:00 816542 0020 Op 2

    1 PM03 0 01/22/2008 07:00 816542 0030 Op 3

    1 PM03 0 01/22/2008 07:00 816542 0040 Op 4

    Tabular Planning Table Pooled Requirements

    A new operation first appears on

    Capacity Planning

    Table as a Pooled

    Capacity

    Requirement.

    The scheduled date of the

    operation is from

    Order

    Requirements are assigned independent of the remaining available capacity

    Configure to calculate remaining available capacity as the difference between available resources and work already dispatched

  • Real Experience. Real Advantage.

    [

    Initial system distribution of hours based on Operation dates

    45 Work Hours planned for 8/27

    CapacityRequirements

    from Work Order

    Operations

    Daily Capacityof

    Work Center

    Tabular Planning Table Pooled Requirements

    Selected Work Requirements mapped to defined Work Center capacity based on Operation Dates

    81

    85

    81

    842

    45

  • Real Experience. Real Advantage.

    [

    OperationStart & Finish

    Dates

    DispatchedOperation

    Planning Table

    MECH

    12/11/07

    24 Hrs

    24 Hrs

    0 Hrs

    12/12/07

    24 Hrs

    20 Hrs

    0 Hrs

    12/13/07

    24 Hrs

    4 Hrs

    0 Hrs

    Avail.Cap

    Dispatched

    Pool/Rqmts

    Total Reqts # P A OT S Start Time Order Op Op text FL

    6 Hrs 1 PM03 0 01/22/2008 07:00 816542 0010 Op 1

    12 Hrs

    8 Hrs

    4 Hrs

    Period

    1 PM03 0 01/22/2008 07:00 816542 0020 Op 2

    1 PM03 0 01/22/2008 07:00 816542 0030 Op 3

    1 PM03 0 01/22/2008 07:00 816542 0040 Op 4

    DSPT

    DSPT

    DSPT

    DSPT

    Tabular Planning Table Schedule Process (Dispatch)

  • Real Experience. Real Advantage.

    [ Tabular Planning Table Schedule Process (Dispatch)

    Select Order Operations and click button

    Status of DSPT applied

    Pool requirements committed and become Scheduled.

  • Real Experience. Real Advantage.

    [ Tabular Planning Table Schedule Process (Dispatch) Example of completed Weekly Schedule in Planning Board

  • Real Experience. Real Advantage.

    [ Weekly Schedule Creation using IW37n & Planning Table If Work Order dates already defined within weekly period you can set the

    Schedule in 5 simple steps:

    1. Select required Order Operations (IW37N)

    2. GoTo Planning Board

    3. Select All Work Order Operations CM25)

    4. Click Dispatch Button

    5. Click Save Button

  • Real Experience. Real Advantage.

    [ Assignment to Individuals

    SAP Capacity Planning Table (Capacity Leveling) can be used to assign / dispatch to individual people

    Work can be assigned to individual employees defined in HR module

    Work times are driven by work schedule in HR

    Process is called Split Assignment

    Split Dispatched Operations to individual persons

    Split Assignments are presented in CATS Work list for each individual

  • Real Experience. Real Advantage.

    [ Assignment to Individuals

  • Real Experience. Real Advantage.

    [ Assignment to Individuals

  • Real Experience. Real Advantage.

    [ Assignment to Individuals

  • Real Experience. Real Advantage.

    [ Assignment to Individuals

  • Real Experience. Real Advantage.

    [ Assignment to Individuals

  • Real Experience. Real Advantage.

    [Example of Weekly Schedule

    Publish the Schedule

  • Real Experience. Real Advantage.

    [

    Example of Weekly Schedule (CM07 Report)

    Publish the Schedule

  • Real Experience. Real Advantage.

    [

    After Dispatch refresh of IW37N updates status and dates ready for publishing

    Selection variants and layouts defined to meet schedule publishing requirements

    Variety of publishing methods

    Publish the Schedule

  • Real Experience. Real Advantage.

    [

    Example of Weekly Schedule (IW37 Report)

    Publish the Schedule

  • Real Experience. Real Advantage.

    [ Some publish in Excel down load from List Edit

  • Real Experience. Real Advantage.

    [ Schedule Compliance Report

    Standard SAP does not readily support this reporting requirement

    No history of schedule or date status at point of time

    Required changes impact Work Order data

    Straightforward report to develop in SAP (Abap) or in BI (preferred).

    Advantages of BI:

    Maintain compliance specific history over time

    Technology readily support analysis within and across organizations

    Use Dashboard to effective compare results and drive improved performance

    Year Week Plant

    Planner

    Grp

    Work

    Center

    # of

    Scheduled

    Orders

    # of

    Compliant

    Orders

    %

    Compliant

    2007 02 ABCD PG1 A 3 2 67%

    2007 02 ABCD PG1 B 2 1 50%Sum

    PG1 5 3 60%

  • Real Experience. Real Advantage.

    [

    Requirements of Report:

    Snapshot of scheduled work (DSPT) for week n+1 (day/time at end of week n)

    Snapshot of completion status (as defined) for week n+1 (day/time at start of week n+2)

    Comparison of schedule v completion

    Schedule Compliance Report

  • Real Experience. Real Advantage.

    [

    SAP Project System (PS)

  • Real Experience. Real Advantage.

    [ Use of SAP Project Systems

    Can enhance scheduling capability through use of PS Planning board

    Project environment - Shutdowns / Turnarounds

    SAP Project System (PS)

  • Real Experience. Real Advantage.

    [

    PROJECT

    WBS Structure

    Network Activity

    PS and PM Overview PS

    Project Definition

    PM Orders

    PM

  • Real Experience. Real Advantage.

    [

    PROJECT

    WBS Structure

    Network Activity

    PS and PM Overview PS

    Project Definition

  • Real Experience. Real Advantage.

    [ Project Coding Mask

    145

    Good practice to design / adopt coding mask(s) to ensure

    consistent numbering / identification of WBS Elements

    Level 1

    Level 2Level 3

    Capital or Expense Budget / Organizational Responsibility Phase, Stage, Event Major Resource Area

  • Real Experience. Real Advantage.

    [ Project Definition Example

    146

    Framework / defaults for

    all objects in project

    -Organizational

    -Overall Dates

    -Control settings

  • Real Experience. Real Advantage.

    [ Creating a project and associating WBS elements The first step is to

    create a project and

    create/assign WBS

    element values to the

    project.

    This transaction is of great use in creating

    both the Project and

    the WBS elements.

  • Real Experience. Real Advantage.

    [ Project WBS Structure Example

    148

  • Real Experience. Real Advantage.

    [

    149

    Project Copying

  • Real Experience. Real Advantage.

    [

    PROJECT

    WBS Structure

    Network Activity

    PM Orders

    Plan and Schedule Dates

    Plan Dates

    S F

    S

    F

    Plan Milestones

    S

    F

    PS

    PM

    Project Definition

  • Real Experience. Real Advantage.

    [ Networks / Activities The network /

    activity

    relationship is

    remarkably

    similar to the

    order

    operation

    relationship.

  • Real Experience. Real Advantage.

    [ Network finer points continued There are durations,

    relationships, intervals.

    If the network is linked to another, then its

    dates will move when

    the master network

    reschedules.

    Note: each activity within a network can be

    assigned a different WBS

    element if different from

    the parent.

  • Real Experience. Real Advantage.

    [ Network Activity Example

    153

    Activities within same Network can be linked to different WBS Multiple Network can be included within project

  • Real Experience. Real Advantage.

    [ Network Activity Relationships

    154

    Network

    Activity

    Network

    Order

  • Real Experience. Real Advantage.

    [ Project Date Planning & Scheduling

    155

    Top Down or Bottom Up

    Date Planning

    Scheduled / Calculated Dates

  • Real Experience. Real Advantage.

    [ Can Relate Across Network Orders and WBS

    156

    WBS Element

    WBS Element

  • Real Experience. Real Advantage.

    [ Gantt View of Plan

    157

    WBS Element

    Network Activity

  • Real Experience. Real Advantage.

    [ Rescheduling the project Have the option of

    rescheduling network only,

    networks and orders, or

    just orders.

    Pulls off the basic start date of the master network and

    then reassigns basic and

    scheduled start dates of all

    orders.

    Transaction gives warning messages for orders unable

    to schedule and why.

  • Real Experience. Real Advantage.

    [ PM Work Order to Project Assignment

    159

    Work Order to WBS

    Work Order to Network

    Activity

    Work Order Additional Data Tab

    WBS or Activity Dates

    applied to Work Order

  • Real Experience. Real Advantage.

    [ Linking maintenance orders to networks Once this link is made,

    the order schedule and

    basic dates will mirror

    the networks activity

    dates.

    Additionally, the order will begin showing up in

    PS networks as a

    network object as well.

    NOTE: Network assignment are made at

    the order level and not

    the operation level. It is

    imperative that the

    planning of the order

    operations is sound

    because moving individual

    operations is not

    possible.

  • Real Experience. Real Advantage.

    [ PM Work Order to Project Assignment

    161

  • Real Experience. Real Advantage.

    [

    162

    PM Work Order to Project Assignment

  • Real Experience. Real Advantage.

    [ Overview and reporting in PS Networks

  • Real Experience. Real Advantage.

    [

    164

    Project Date and Work Planning Reports

  • Real Experience. Real Advantage.

    [ More on Project Info Systems (CN41) Allows the user

    to set up which

    fields are

    displayed and

    how this may

    look in a graphical

    extract.

  • Real Experience. Real Advantage.

    [ More on Project Info Systems (CN41)

  • Real Experience. Real Advantage.

    [ More on Project Info Systems (CN41) -- Graphics Network Diagram

    These charts show durations,

    relationships, float

    and critical path

    (red) for the

    networks

  • Real Experience. Real Advantage.

    [ More on Project Info Systems (CN41) -- Graphics This is a

    Gantt view

    of the same

    network

    diagram.

  • Real Experience. Real Advantage.

    [

    169

    Example Report Work & Schedule Data

  • Real Experience. Real Advantage.

    [ Standard Exports MS Project

    170

  • Real Experience. Real Advantage.

    [

    SAP Multi Resource Scheduling (MRS)

  • Real Experience. Real Advantage.

    [ What is MRS? A Multi Resource Scheduling tool

    View the status of resource planning

    Assign suitable employees and tools to requirements (demands) from different areas

    Transfer data to and from systems which manage personnel resources and tools

  • Real Experience. Real Advantage.

    [ MRS Scenario Overview

    Planning and Scheduling

    Demands

    Plant Maintenance Order/

    Service Order

    Project System

    Network

    cProjects Request WebUItechnically based on PS

    Capacity Management

    Graphical Planning Board(SAP GUI based)

    Employee View(Web UI based)

    Manager View(Web UI based)

  • Real Experience. Real Advantage.

    [ Work Center / Resource Planning Structure (summary)

    MRS support RP structure to identify an organization hierarchy pertinent to Resource Planning, or the standard Org Management Structure can be used.

    Org Management transactions can link a MRS planner to parts of the structure and MRS transactions can be used to have the default work areas be identified in MRS.

    MRS requires a linkage of a Work Center to one node in the RP structure via the HRMS linkage.

    MRS planning board uses the PM Work Order Operations Work Center to identify what resource should be shown.

    Capacity Data of work center is only used when scheduling on work center level is done (Scheduling in PM/CS and PS, and in the MRS Demand View). It is not taken into

    account when scheduling is done on individual level. (MRS Resource View)

    MRS can enforce a 1-to-1 relationship between the MRS assignments and the PM Order operations. Thus if multiple assignments are created for an operation, new operations will

    be created during Back Integration.

  • Real Experience. Real Advantage.

    [ Master Data for Qualifications: Overview

    Qualification Matrices

    Employee Profile

    Requirements Profile

    Qualification

    Catalogues

    Employee

    Demand

    Skill Level

  • Real Experience. Real Advantage.

    [ Functional Overview

    Work Center

    Capacity

    Alert Monitor

    Demand Gantt

    Work Center

    Gantt

  • Real Experience. Real Advantage.

    [ Functions in Demand Gantt chart

    Flexible selection of relevant orders and networks in entry screen

    E.g. usage of Order List (IW38)

    Simultaneous planning of PM/CS orders and PS networks

    Display of relationships between order operations (also across orders)

    Graphical shifting of operation dates via Drag&Drop

    Re-Scheduling of orders Simulation possible (only after pressing Save the data is written to

    the data base)

    Undo / Redo function

    Dispatching of orders to Work Center Gantt chart

  • Real Experience. Real Advantage.

    [ Details about work center dispatching

    In the work center view a possibility is provided to drill down from

    work center level to resource level. For this purpose the resources of

    the work centers can be displayed with their assignments and

    availabilities.

    Via drag and drop the operations can be planned from work center

    level to resource level.

  • Real Experience. Real Advantage.

    [ Details about absolute Capacity Utilization

  • Real Experience. Real Advantage.

    [ Scheduler Workplace

  • Real Experience. Real Advantage.

    [ Terms

    Demands

    Resources

    Organizational unit

    Resource node

    Position

    Person

    Resource planner

    Capacitive scheduling

  • Real Experience. Real Advantage.

    [ Demand

    Order

    Operation

    Operation

    Operation

    Demand

    Demand

    Demand

    MRS

  • Real Experience. Real Advantage.

    [ Organizational Units with Positions

    Plant

    Machine Shop

    Technical

    Services

    MillwrightsPipe Fitters

    Note: Organizational Unit = Resource Node

    Organization Unit

  • Real Experience. Real Advantage.

    [

    Pipefitter Millwright Machinist

    Organization Unit

    Position

    Plant

    Note: A Person is assigned to a Position

    Machine Shop

    Technical

    Services

    MillwrightsPipe Fitters

    Organizational Units with Positions

  • Real Experience. Real Advantage.

    [ Master Data

    Resource planning structure: Human Resources (HR or BP record)

    Resource availability data

    Organizational unit/Work center

    Resource planner

    Qualifications, scales, qualification catalogs, and qualification matrixes

    Employee and requirements profiles

    Tools (as equipment or material)

  • Real Experience. Real Advantage.

    [ HR to ERP Relationship

    Organizational Unit

    Organizational Unit

    Organizational Unit

    HR record/person

    HR record/person

    HR Work Center

    HR Work Center

    Work Center

    (0005)

    Work center of technician

    Work Center

    (ZMRS)

    Work Center

    (ZMRS)

    HR Logistics

    LinkA 061

    LA

    LinkA 008

    P

    Position

    Resource Planner

    Work center with resource planning

    node

    HRMS Link

    LinkA 008

    P

    LinkA 061

    LA

    PPOME

    PO10

    PO10

    PO10

    PO13

    PA30

    PO01

    IR02

    IR01

    Daily batch job

    Daily batch job

  • Real Experience. Real Advantage.

    [

    Plant

    Technical

    Services

    Organization Unit

    Position

    Maintenance Work Center

    Person

    John Wayne

    4343

    Mark Scott

    4555

    Technician Work Center

    John Wayne

    WC_4343

    Mark Scott

    WC_4555

    Used when work

    initially planned in

    operation.

    Written back to

    operation when

    Resource is

    scheduled.

    Technical

    Services

    Piperfitter

    PiperfitterPIPE

    Pipefitter1223

    1223

    Seen as

    Resources

    Kahn Ellis

    Resource Planner

    Another view of the relationships

  • Real Experience. Real Advantage.

    [ Schedule to Work Center

  • Real Experience. Real Advantage.

    [ Schedule to Resource

  • Real Experience. Real Advantage.

    [ Demand layout

  • Real Experience. Real Advantage.

    [ Resource layout

  • Real Experience. Real Advantage.

    [ 1:1 assignment relationship versus no relationship

    1:1 relationship:

    Cause additional operation to be created per resource assigned

    Assign technician work center representing resource to operation

    No relationship:

    Assign resource(s) to operation in Requirements Assignment tab

    Cannot display assignments in List Edit

  • Real Experience. Real Advantage.

    [

    Vesta Plant Maintenance Excel Integration (PMX)

  • Real Experience. Real Advantage.

    [ Standard product functionality

    Data Flow:

    Work order data

    Updated Dates

    Updated EmployeeAssignments

    Sheet filled with Activities

    Detailed Dispatching

  • Real Experience. Real Advantage.

    [ IT Overview

    The Vesta Integration is developed as a Microsoft Excel Add-In

    It uses standard SAP BAPIs to interface with SAP

    The add-on honors all SAP and Microsoft security mechanisms

    MS ExcelV

    esta

    Inte

    gra

    tion

    Ad

    d-

    on

    SAPB

    AP

    Is

    an

    d R

    FC

    s

  • Real Experience. Real Advantage.

    [

    210

    Key Learnings

    Understand core SAP planning functions and tools

    How to develop and manage a maintenance schedule in SAP

    Use of and impact of dates

    Codes to support the process

    How to define and manage capacities

    Assess, manage and prioritize work

    Awareness of non core SAP PM options that can further enhance & support scheduling

    Understanding of how PS can expand scheduling capability

  • Real Experience. Real Advantage.

    [

    ] Thank you for participating.

    SESSION CODE: 36245