SAP Planning & Scheduling Workshop
Gus McIntosh
Ben Mansi
-
Real Experience. Real Advantage.
[
2
Learning Points
Understand the capabilities of SAP and how you can use them to support an effective planning & scheduling process.
Explore non standard SAP PM options for scheduling and how they can support your requirements.
Better understanding of key tools and approaches that can be deployed to provide the basis for measuring planning and
scheduling performance improvement.
-
Real Experience. Real Advantage.
[ Agenda Planning in SAP
Task Lists
BOM
Work Order Planning
Scheduling
Dates
Capacities
Capacity Evaluation
Planning Board
Project Systems
MRS
PMX
-
Real Experience. Real Advantage.
[ Planning in SAP
Task List Overview
Task List Details
Structures / functions
Supporting Maintenance Plans / One Time Work
Bill of Materials
Work Order Planning
Tools to Support Work Planning
List Edit Reports
-
Real Experience. Real Advantage.
[ Task List Overview Task Lists describe the sequence of individual maintenance activities to be
performed, identify the required Resources (Labor, Materials, Services,
Special tools) and related procedures.
Predefined list of Work activities that contain Work Group, Skill, Work Description, Duration, Number of Workers and associated Material Items.
Task Lists are building blocks of Maintenance Plans.
Simplifies the Work Order Planning process
Task List TL Types:
General (can be used on multiple objects) (TL Type A)
Functional Location (associated with FLocs) (TL Type T)
Equipment (associated with specific Equipment item) (TL Type E)
The type of Task List created will depend on the objective of the plan /and related Technical Object
General TL can be configured
-
Real Experience. Real Advantage.
[
Contents
Usage
Work steps (operation)
Long text (Std Text) instructions
Maintenance work centers
# Resources, Duration, Total Work
Material components (Stock / non-stock w/BOM)
Special Tools/drawings/equipment (PRTs)
Craft / Specialists / Qualifications / Contractors
Regular maintenance (PMs, PdMs, servicing & inspection)
Major maintenance Activities (planned repairs, Overhauls)
Why?
To standardize work processes
To plan maintenance orders more effectively
To create maintenance plans more quickly
Task List Overview
Who?Maintenance and Service Planners
Reliability Engineers
-
Real Experience. Real Advantage.
[ Task List Overview
Maintenance Item
Maintenance Item
Item dataPlanning dataTask List dataMaint. Plan dataLocation/accountassign
Object ListObject List
Lists of:Functional LocationEquipment
MaintenanceStrategy
Maintenance Plan& ScheduleWork
Order
Maintenance Task List
Operation
Operation
OperationSub-Operation
Maintenance Task List
Operation
Operation
Operation
Sub-Operation
Long Text
Standard Text
Tools
Services
Components
Labor
Task List Overview
-
Real Experience. Real Advantage.
[
Equipment
(Turbine 1000)
Task List
(Turbine 1000)
Operation #1
Operation #2
Operation #3
Operation #1
Operation #2
Leverage one or
more Task Lists
for planning work
orders
Task List Overview - Use in work order
-
Real Experience. Real Advantage.
[ Task List
Task List Header
Operation
Sub-operation
Material
Production Resources/Tools
Maintenance Package
Example of FL Task List
Group and Group Counter numbers can be internally or externally maintained
Header defines default Work Center
-
Real Experience. Real Advantage.
[ Task List Use in Preventive Maintenance
Task List Header
Operation
Sub-operation
Material
Production Resources/Tools
Maintenance Package
Standard / Long Text
Classification
Object Dependencies
User Defined Fields
Control Key (Internal, External, Services)
-
Real Experience. Real Advantage.
[ Task List Profile
General settings typically common
across plants
Internal processing settings typically
common across plants
External processing (operation
Services) defaults can cause the need
for multiple profiles by plant.
Header data settings common across
plants
TL Profile Parameter ID PIN Sets default in IA01,2,3,5,6,7,13,14,15
-
Real Experience. Real Advantage.
[ Task List StructureTask List Overview
Header
Operation Overview
Operation details copied onto Work Order
TL Group w/multiple
Counters
Alpha/numeric
Work Center & System
Condition are defaults
for TL Operations
Matl BOM populated
on Gen TL makes items
available
-
Real Experience. Real Advantage.
[Only applicable if used in Strategy Plan
Defines applicably frequency per Task / Operation
Task List Structure Package Allocation Options
This option has limited
view of package text.
This option has
better view of
package text but
more screens
-
Real Experience. Real Advantage.
[
Internal Processing Detail
Resources provided from internal Work Centers
Work requirements define resource forecast when associated with Maintenance Plan
Task List Structure Internal Processing
-
Real Experience. Real Advantage.
[ Components Show Operation Assembly Options General Task Lists, Assembly (Material) BOMs can be used to display part
requirements
Assemblies are useful
on work order
operation assembly
field for planning
Parameter ID:
PM_TREE_INACTIVE = X
Non-stock assignment Only
through a BOM
-
Real Experience. Real Advantage.
[ Task List Structure - Components
Component Overview
From selected Operation Setting of 1 results in
order setting:
Use to
activate on
order
Standard(S) BOM for freely assigned parts
-
Real Experience. Real Advantage.
[
Operation Relationship
Finish to Finish
Finish to Start
Start to Finish
Start to Start
Task List Structure - Relationships
-
Real Experience. Real Advantage.
[Standard FS relationship applies based on Operation #
Relationships can be applied
They are copied onto Work Order
Network graphic is easiest way to maintain relations
Task List Structure - Relationships
-
Real Experience. Real Advantage.
[Relationship data copied from Task List onto Work Order
Order scheduled with basic start of 01/31/2007
Task List Structure - Relationships
-
Real Experience. Real Advantage.
[With offset
Task List Structure - Relationships
-
Real Experience. Real Advantage.
[ Task List Structure - Relationships
-
Real Experience. Real Advantage.
[ Task Lists - Supporting Maintenance Plans
Strategy Plans must
have same Strategy
on Task List, Items
and Plans
Strategy plans
MUST have a task
list or will not
schedule plan
Error.
Task Lists applied in same way to Strategy, Single
Cycle or Multiple Counter Plans
-
Real Experience. Real Advantage.
[ Task Lists - Supporting Reactive / One Time Work / OverhaulsUsing existing Task List to plan Work Order
Choose all or specific Work Centers
Choose all or specific Operations
-
Real Experience. Real Advantage.
[Using Task List to plan Work Order Or setup as Manual call
Task Lists - Supporting Reactive / One Time Work / Overhauls
-
Real Experience. Real Advantage.
[Can use sub operations to plan multiple resources on same task list operation
No component, PRT planning, External Services
No date scheduling specific to sub operation
No Relationships and Constraints
Defined at superior Operation levelOn Work Order can adjust start and end times using offset
Capacity requirement defined for sub operations
Included within capacity loading
Available within Planning Table for Dispatch
Enter confirmations at sub operation level
Operations & Sub operations
-
Real Experience. Real Advantage.
[
Apply Long text using standard text key
Apply text directly to Operation
Cut / Paste
Upload
Procedures and Long Text
-
Real Experience. Real Advantage.
[ Planners and MRO Inventory and Purchasing
Components:
Stock material
Non-stock Material
Text Item
Document
Equipment(Pump)
Coupling ImpellerBearing/Gasket
Assembly
Bearing Gasket Misc. Hardware
-
Real Experience. Real Advantage.
[US01
Aromatics
ACU - East
M1118 EXT. RDC COLUMN MIXER
M6833 RDC MIXER
P1677 RAFFINATE BOOSTER
P4283 PARAFIN STRIPPER BOOT WATER
P9614 TOLUENE COLUMN REFLUX PUMP
Plant
BPU
Unit
Equipment
Service
10003857 P-9614 PUMP
BOM
Equipment
BILL OF MATERIALS FOR P-9614
CHEMICAL SUPER PLANT
AROMATICS
AROMATICS CATALYTIC UNIT - EAST
879444
123456 Pump Shaft
1.020 X .0075 Bearing
BOM
Bill of Materials
-
Real Experience. Real Advantage.
[ Bill of MaterialsEquipment BOM Example
-
Real Experience. Real Advantage.
[ Bill of MaterialsEquipmentBOM
Equipment Equipment Equipment Equipment
Mat 1
Mat 2
Mat 10
Mat 11
Mat 3
Mat 6Mat 20
Mat 7
Construction typeBOM
Construction
type
-
Real Experience. Real Advantage.
[
Construction Type /
Material BOM
Equipment BOM
BOM Items
Bill of Materials Construction Type
-
Real Experience. Real Advantage.
[
Construction Type / Material BOM assigned to General Task List
General Task List is made available as ref. object to related Equipment
Bill of Materials Construction Type
-
Real Experience. Real Advantage.
[ Work Order Planning
Manual planning of Operations
Similar structures / functions as for Task List
Can establish default calculation method:
Calculate Work
Calculate Duration
Calculate Manually
All Internal Labor planned with reference to an Activity Type
Holds Cost Rate
Is used to calculate Plan and Actual labor cost
-
Real Experience. Real Advantage.
[
Select from BOM or add manually
Work Order Planning
-
Real Experience. Real Advantage.
[
Material Requirement Date set by Operations Start
Can adjust with Offset
Work Order Planning
-
Real Experience. Real Advantage.
[
Unplanned Service Requirement
Overall limit set
Planned Service
Need defined in terms of detailed Service Items referencing a Contract / Service Master
Work Order Planning
-
Real Experience. Real Advantage.
[ Codes To Support Work Planning Tools to help Planner manage the work
Priority & Risk codes
Equipment Criticality (ABC)
Equipment Availability (System Condition, Revisions)
User Status to support control, workflow and reporting
In Planning or equivalent
Review in field
Waiting on Engineering, MOC.
To further support Parts status
Routinely a review of work orders should be made so that
Priority work orders are being planned first
Common Locations of multiple work orders can be reviewed
-
Real Experience. Real Advantage.
[System Condition use to identify operational state for required intervention
Revision code options for use
Define turnarounds / outages / shutdowns
Apply target basic dates
Tagging / Grouping
Basic Work Order scheduling
Codes To Support Work Planning
-
Real Experience. Real Advantage.
[ Consider different PM Priorities
There needs to be a way to identify PMs
that can be scheduled anytime. E.g. certain
inspections. See Priority 0
Assignment is across all plants by Order Types
-
Real Experience. Real Advantage.
[ Operating Condition - Coordination with Production
This field can be used to identify if the work can be performed while the equipment is in operation (like certain inspections, vibration analysis, testing) or if the equipment must be taken out of operation.
It can be part of the ready to work criteria in selecting orders for scheduling.
The Reservation by PM is part of the
integration with Production Planning at the work center level.
-
Real Experience. Real Advantage.
[ Operating Condition Where Used Order Header
-
Real Experience. Real Advantage.
[ Operating Condition Where UsedOrder / Task List Operations
The importance at the operation level is knowing in IW37N whether the equipment needs to be shutdown or in operation
Maintenance Item (partial screen below)
Setting the Operating Condition on the Maintenance Item will default to the work order header.
-
Real Experience. Real Advantage.
[
User Status to support process / workflow
Control related single option
Information multiple selection
Codes To Support Work Planning
-
Real Experience. Real Advantage.
[ User Statuses Informational for Process
Informational User StatusesNo numbering, Multiple active, Can be automatically set, Transaction controls, Position controlled, Authorization controllable
Used for process and backlog/fore log management, general information
-
Real Experience. Real Advantage.
[ User Statuses Sequentially Controlled
Statuses can be:
Sequentially numbered and activated/deactivated, Sequence controlSingle activationAuthorization controllable
Used for process control and backlog/fore log management
-
Real Experience. Real Advantage.
[ Status Transaction Controlled
In this example, the status INP (In Process) is automatically set when a work order is printed or reprinted.
The status INP is removed when the order is TECOd.
-
Real Experience. Real Advantage.
[ User Status Assignments
Assignment is at the order type and operation level
Note: User statuses are available for notifications, orders, equipment, functional locations, serial numbers, IBase,
-
Real Experience. Real Advantage.
[
ABC Indicator for Criticality
Codes To Support Work Planning
-
Real Experience. Real Advantage.
[ ABC Indicator - Examples
Used in List Edit displays to prioritize work
-
Real Experience. Real Advantage.
[ Plant Sections
Used in List Edit displays work locations.
Augments functional location for some users.
-
Real Experience. Real Advantage.
[ Planner GroupsPlanner Group Tables
One table for flocs,
equipment,
notifications/orders
One table for task
lists
Planner groups for orders is the number one means of
denoting ownership of the order from a planning
perspective. Work center is another common approach.
-
Real Experience. Real Advantage.
[ Planner Group Use
Planner group maintained on floc or equipment will default
to notification or order unless user maintains personal
defaults.
Planner Grp On Notification
Planner Grp On Order
-
Real Experience. Real Advantage.
[ Planning Indicator Good KPI but bad locationThe Planning
indicator provides nice out of the box
reporting.
The problem is the indicator is buried on the Control tab. GUIxT is a good solution.
-
Real Experience. Real Advantage.
[ Planning indicator - Definition
Planned: All preventive maintenance orders and other work orders that require planner intervention before the job is started.
What if no parts and the operation is estimated/planned?
Do KPIs exclude PMs?
Unplanned: Work that is not immediate and handed to a craft to troubleshoot and plan themselves. No previous planner intervention.
Immediate: Break in work that is not planned.
Other solutions besides the planning indicator
Important: Understood and agreed upon definition used consistently.
-
Real Experience. Real Advantage.
[
User Defined Fields
Available within Planning Table
Codes To Support Work Planning
-
Real Experience. Real Advantage.
[ Default Settings on work order
-
Real Experience. Real Advantage.
[ Default Settings on work order
-
Real Experience. Real Advantage.
[
By setting at Operation level to Immediately all Reservations or Requisitions associated available for further processing
Setting can also be made at Component level
Default value is configurable
Early Release of Material Requirements puts in process without need to fully Release the Work Order for execution
Generates Purchase Requisition and initiates Procurement process
Stock Reservation established
When and why would you release materials early?
Where there is a long lead item and need exists to place purchase order
Materials Planning Release
-
Real Experience. Real Advantage.
[ List Edit Reports
-
Real Experience. Real Advantage.
[
Material Availability can be checked at any time from within the Work Order
A Material Availability Report is also available that can provide status across multiple Work Orders
Availability Report also includes for Non Stock items where planned Goods Receipt dates are compared to Operation Earliest Start dates
Materials Availability
-
Real Experience. Real Advantage.
[ Availability Checking Control
-
Real Experience. Real Advantage.
[SAP List Edit function facilitates review of and adjustment of Work Orders
IW38 Order Header
IW37 Order Operations
IW37N Order Header & Operations (Require 4.7 SP EA_APPL 200)
Manage Planning Activities - List Edits
-
Real Experience. Real Advantage.
[
Column layouts can be adjusted and saved as user specific variant
Can Sort on columns and filter data, e.g. by Status (System and User)
Select single or multiple Work Orders and drill down to individual objects in Change mode
Can carry out functions collectively e.g. Release Work Order
Manage Planning Activities - List Edits
-
Real Experience. Real Advantage.
[ Periodic Maintenance Schedule General industry acknowledgement of need for an effective scheduling
process ensuring:
Most important work is being executed
It is being worked at the optimal time
Execution is undertaken employing the most appropriate and available resources
Cost of execution is reduced
Most top performing Maintenance Organizations establish a Weekly Schedule and measure compliance against it.
Schedule requires involvement and agreement from all involved departments particularly Production and Maintenance.
-
Real Experience. Real Advantage.
[ Weekly Scheduling in SAP
Objectives:
Outline the use of standard SAP Capacity Leveling and Evaluation functions to support creation of Weekly Maintenance Schedule
Identify options and approaches that work best
Keeping it simple
Consider shortfalls in functionality
Touch on approaches without use of Capacity Leveling
-
Real Experience. Real Advantage.
[ Prerequisites to Periodic Scheduling process
An effective SAP planning process that defines and prioritizes work
A maintenance backlog accurately represented in SAP in terms of:
Work activity, labor resource estimates (number of people and man hours) and durations
Material Requirements
Criticality and Priority
Work Categorization (e.g. Preventive, Corrective, Project, etc.)
Resource group / Work Center capacity information maintained to reflect:
Standard Working Times
Weekly available capacity
-
Real Experience. Real Advantage.
[ Scheduling in SAP SAP Date Scheduling
Relationships & Constraints
Revisions
Manage Work Center Capacities
Standard / Intervals / Versions
Calculation from HR Employees / Work Center Hierarchies
Capacity Evaluation
Work Orders - Ready to Schedule?
Scheduling Options:
Capacity Leveling (Tabular Planning Table)
Publish the Schedule
Schedule Compliance Reporting
-
Real Experience. Real Advantage.
[ Typical Scheduling Process
Maintain Shifts &
Availability
Manage Work Center
Capacity
EvaluateRequirements
v Capacity
Define Weekly Schedule
Hold PlanningMeetings
FinalizeWeekly
Schedule
CommunicateWeekly
Schedule
Manage Work ready
to be Scheduled
Prepare to Schedule
ManageEmployees &
Schedules (HR)
Work PlanningProcess
ExecutionProcess
ManageRemaining
Work
ManageDailyWork
Assignment
Preventive& Predictive
Process
-
Real Experience. Real Advantage.
[ SAP Date Scheduling Adopt a scheduling direction Forwards or Backwards
Duration and Work Center standard work times drive Work Order schedule date calculation
Time Window for Work
4hrs 4hrs 6hrs 4hrs
Basic Start
Op. 010 Op. 020 Op. 030 Op. 040
Work OrderBasic Start
Date
WO ScheduledDates
Adjusted
Times constrained by Work Center operating time
Scheduling Direction
010 020 030 040
Start date 12/13/2007 12/13/2007 12/13/2007 12/14/2007
Start time 7:00 11:00 15:00 12:00
Finish date 12/13/2007 12/13/2007 12/14/2007 12/14/2007
Finish time 11:00 15:00 12:00 16:00
Duration (hours) 4 4 6 4
People involved 2 1 2 2
Work 8 4 12 8
Work Order Operation
Schedule Start
Schedule Finish
-
Real Experience. Real Advantage.
[ SAP Date Scheduling
-
Real Experience. Real Advantage.
[ Scheduling Types
Typically there are no reasons to change standard SAP Scheduling Type settings.
The with Time indicator allows input of times against basic start and end dates as shown below.
-
Real Experience. Real Advantage.
[ Scheduling Types
The with Time indicator allows input of times against basic start and end dates as shown below.
-
Real Experience. Real Advantage.
[ Scheduling Types
3 Only Capacity Requirements
All Operation Dates / Times set from Basic dates
-
Real Experience. Real Advantage.
[ Scheduling Parameters
Defined in configuration & control how dates are calculated
Defined for Plant / Order Type
-
Real Experience. Real Advantage.
[ Scheduling Parameters
Options for Date Adjustment
Do you want to adjust or retail Basic Dates?
Are Material Requirement dates to be driven by Order Start or Operation Start?
Automatic Scheduling: switch on to ensure dates are always re-calculated when Order processed / saved
Scheduling with breaks: Consider excluding breaks from Work Center operating times. This ensures clean start and finish times without SAP calculations in fractions
of hours.
Shift Order: Switch on to exclude confirmed actual dates and times from re-calculation of schedule e.g. if work was not completed and need to adjust schedule
dates to another time in future.
-
Real Experience. Real Advantage.
[ Work Order Relationships & Constraints
-
Real Experience. Real Advantage.
[ Work Order Relationships & Constraints
Typically no need for complex relationships and constraints
Adopt simple and standard approach to use of dates
Operation start and stop dates / times are driven by WC Operating time
You want to have a process where you adjust Order dates (start or finish) and let system calculate scheduled dates
-
Real Experience. Real Advantage.
[ Revisions Transaction OIOB used to define Revisions
Revisions can be used to define Maintenance Periods etc.
Change Basic Start / End Dates
Can adjust Revision dates and collectively re-apply
-
Real Experience. Real Advantage.
[ Assign Revisions
Can apply direct on Work Order Header or collectively through IW38 or IW37N
Select Orders and assign Revision dates
-
Real Experience. Real Advantage.
[ Can access & maintain from capacities from within both Evaluation &
Leveling
Changes to calculations are immediately reflected on Table / Reports
If change from Planning Table will only become permanent when Save on exit
Capacity values are not stored in SAP dynamically calculated
Viewed in reference to a Factory Calendar
SAP
HR
Work Center Capacity
Capacity
Planner Group
Factory
Calendar
Employee HR
Assignment
Versions
3 aspects can be taken into account:
Standard Capacity
Intervals & Shifts
Versions
Intervals of
Available
Capacity
Standard
Available
Capacity
Manage Work Center Capacities
-
Real Experience. Real Advantage.
[ Factory Calendar Defines working days & Holidays
-
Real Experience. Real Advantage.
[ Standard Work Center Capacity Defined on WC Capacity Header screen
Can be used to group Work Centers in Capacity Planning
Required if executing finite scheduling
Required if assigning Shifts
-
Real Experience. Real Advantage.
[ Standard Work Center Capacity
For each Work Center you establish a standard available capacity and working times that reference a specific Factory Calendar
Factory Calendar (defines working days / non working (including holidays) days.
Breaks can be defined that are deducted from available operating time
For typical routine maintenance scenarios it is recommended to exclude breaks and adjust start and finish dates to reflect normal available work time
The standard capacity is applied to all the working days defined within Factory Calendar
For non working days the capacity is set to zero.
As previously notes the working times influence how schedule dates are calculated on the Work Order
Work Center Capacity
= Number of Ind. Capacities * Operating Time
(Operating Time is adjusted by Utilization)
-
Real Experience. Real Advantage.
[ Standard Work Center Capacity
Calculation examples:
(10 * 1.0) * 2 = 20
(9 * 1.0) * 3 = 27
(9 * 0.9) * 3 = 24.3
(9 * 1.2) * 3 = 32.4
Operating Time = Calculated Work Time * Utilization
10 hrs, No Breaks = 10
10 hrs, 1 hr Breaks = 9
(10 * 1.0) * 2 = 20
(9 * 1.0) * 3 = 27
(9 * 0.9) * 3 = 24.3
(9 * 1.2) * 3 = 32.4
Operating Time = Calculated Work Time * Utilization
10 hrs, No Breaks = 10
10 hrs, 1 hr Breaks = 9
-
Real Experience. Real Advantage.
[ Standard Work Center Capacity
Calculation examples:Work Center factory calendar defined as 7 work days / week
Non working holidays defined on 12/25 and 1/1
Available capacity 45 hours per day
-
Real Experience. Real Advantage.
[ Intervals & Shifts Standard capacity can be further refined by adding Intervals
Different capacities can be set for individual days or periods of time
In this example no intervals yet exist
Indicates standard capacity
-
Real Experience. Real Advantage.
[In this example interval added
Note: Interval operating times also impact Order date scheduling.
Intervals & Shifts
-
Real Experience. Real Advantage.
[
Monday 21st Holiday per Factory Calendar
----- 7 Day Cycle ---------
- 5 Day Interval--
Intervals & Shifts
-
Real Experience. Real Advantage.
[To add an interval
1 (default) or 7 days are applicable cycles
Intervals & Shifts
Although 7 day cycle only first 5 days applicable to Interval.
-
Real Experience. Real Advantage.
[
Monday 21st Holiday over ridden by Interval
----- 7 Day Cycle ---------
- 5 Day Interval--
Intervals & Shifts
-
Real Experience. Real Advantage.
[ Intervals & Shifts
-
Real Experience. Real Advantage.
[ Intervals & Shifts Can reference and apply shifts defined within HR
-
Real Experience. Real Advantage.
[ Intervals & Shifts Can apply shift sequence and define capacity by shift
-
Real Experience. Real Advantage.
[Can have multiple Versions of available capacity within Work Center
3 Standard delivered versions
Can add your own versions
Can change active Versions when evaluating capacity or leveling (scheduling)
Intervals are associated with specific versions
Capacity Versions
-
Real Experience. Real Advantage.
[Can apply different Versions of available capacity on Work Order Header
Schedule dates reflect defined versions.
Capacity Versions
-
Real Experience. Real Advantage.
[
HR assignment
Employee Assignment & Capacity Calculation
Within Capacity Leveling it is possible to calculate available capacity based on individual work schedules maintained within HR Master Records.
Configuration setting on Evaluation Profile
Not possible within Evaluation
Cumulate Capacity based on employees assigned to Work Center Capacity
-
Real Experience. Real Advantage.
[ Employee Assignment & Capacity Calculation
-
Real Experience. Real Advantage.
[Capacity leveling reflects HR Schedule of employees
Work Center Capacity is ignored
Employee Assignment and Capacity Calculation
-
Real Experience. Real Advantage.
[
Easy to configure reporting function to further support scheduling process
Capacity Evaluation
-
Real Experience. Real Advantage.
[
Standard Overview
Work Center Work Center
Change Work Order
Output to Printer
Export to Excel
Capacity Evaluation
-
Real Experience. Real Advantage.
[
Change Capacity
Work Center Work Center
Detailed Capacity List
Capacity Planning Table
Capacity & Work Order changes dynamically update reports
Change Work Order
Dispatch Work
Can branch to Capacity Planning Table & Dispatch work (Prepare Schedule) Changes update reports
Capacity Evaluation
-
Real Experience. Real Advantage.
[Select via overall profiles
Configured to meet specific reporting needs
Evaluation periods
Period Display
e.g. Day, week, Month
Data selection options
Filters
Exceptions
Can use Wildcard * in selection
Selection by status of Order
Capacity Evaluation
-
Real Experience. Real Advantage.
[The Standard Overview report
comparison of requirements compared to available capacity
Can adjust profile settings on the fly
Capacity Evaluation Standard Overview
-
Real Experience. Real Advantage.
[
Differing intervals to be evaluated
Time period definition
Applied Capacity Version
Can filter display based on loading
Capacity Evaluation Standard Overview
-
Real Experience. Real Advantage.
[
Graphic views available
Capacity Evaluation Standard Overview
-
Real Experience. Real Advantage.
[ Capacity Evaluation Standard Overview
-
Real Experience. Real Advantage.
[
Provides a breakdown of each requirement period in an Order Operation list form.
Layout can be configured to meet specific needs
Does not use ALV technology
Can download to Excel etc.
Capacity Evaluation Detailed List
-
Real Experience. Real Advantage.
[ Work Orders - Ready to Schedule?
-
Real Experience. Real Advantage.
[ List Edit - Used to manage backlog
Establish layouts to sort by Criticality, Priority, Order Type, Basic dates, etc.
System & User Status to select and identify readiness for scheduling
Drill down to adjust Work Order plan and status data
Use Revision functionality
Collective assignment & update of Basic Dates
Direct Access to Material Availability report for
selected Order / Operations
-
Real Experience. Real Advantage.
[ Order & Operations List Single screen combining Order
Header and Operation data.
Can define and save both selection parameters and layouts to meet
specific Scheduler processing
functions.
Manage Backlog
Manage dates / apply Revisions
Check Materials Availability
Publish Weekly Schedule
Monitor execution status
-
Real Experience. Real Advantage.
[ Order & Operation List Schedule Overview
Schedule Overview (Gantt)
-
Real Experience. Real Advantage.
[
Materials Availability Report
Order & Operation List Materials Availability
-
Real Experience. Real Advantage.
[ Materials Availability
-
Real Experience. Real Advantage.
[ Capacity Planning Table Using Planning Table to create the Weekly Schedule
Review work requirements against capacity
Manipulate capacity & requirements
Dispatch operations requirements to specific work days
Recommend use of CM25 Variable Capacity Planning Table
Dispatching work moves an operation onto a particular day and changes Operation system status (to DSPT).
This day may or may not be the same as how it was originally planned / scheduled in the work order.
Two dispatching options:
Manual
Finite (using a dispatch strategy).
-
Real Experience. Real Advantage.
[ Getting to Planning Table Can navigate between IW37N and
Planning Table using selection to
determine Orders to be included.
Call up Planning Board directly
Select by Work Center
Can refine selection further e.g. Revision
Recommend finalizing schedule using direct access to ensure all requirements accounted for
-
Real Experience. Real Advantage.
[ Getting to Planning Table Can change time settings
before execute.
Can further filter requirements data.
-
Real Experience. Real Advantage.
[ Time Profile Settings Backlog
Orders show
yesterday
Todays date = 1/24/2008
Backlog Orders show today
-
Real Experience. Real Advantage.
[ Tabular Planning Table Overview
View work requirements by period
Configure layout, selection rules, time periods of
table to meet specific company needs and
scheduling timeframes
Define weekly schedule by assigning
(Dispatching) work
Adjust dates within table to balance
resources with work requirements
Can Maintain Capacity and Order details
directly from table
Capacity details available / scheduled
Work List details
-
Real Experience. Real Advantage.
[For weekly schedule recommend daily view
Weekly or Monthly views can be used for longer term planning / scheduling
Week
Tabular Planning Table Views
Month
-
Real Experience. Real Advantage.
[ Tabular Planning Table Requirements Section of Planning Table
Field values and layout can be configured
Not ALV technology so somewhat limited
15 fields maximum
-
Real Experience. Real Advantage.
[
CapacityRequirements
from Work Order
Operations
Daily Capacityof
Work Center
Planning Table
MECH
12/11/07
24 Hrs
6 Hrs
18 Hrs
12/12/07
24 Hrs
12 Hrs
8 Hrs
12/13/07
24 Hrs
0 Hrs
4 Hrs
Avail.Cap
Dispatched
Pool/Rqmts
Total Reqts # P A OT S Start Time Order Op Op text FL
6 Hrs 1 PM03 0 01/22/2008 07:00 816542 0010 Op 1
12 Hrs
8 Hrs
4 Hrs
Period
1 PM03 0 01/22/2008 07:00 816542 0020 Op 2
1 PM03 0 01/22/2008 07:00 816542 0030 Op 3
1 PM03 0 01/22/2008 07:00 816542 0040 Op 4
Tabular Planning Table Pooled Requirements
A new operation first appears on
Capacity Planning
Table as a Pooled
Capacity
Requirement.
The scheduled date of the
operation is from
Order
Requirements are assigned independent of the remaining available capacity
Configure to calculate remaining available capacity as the difference between available resources and work already dispatched
-
Real Experience. Real Advantage.
[
Initial system distribution of hours based on Operation dates
45 Work Hours planned for 8/27
CapacityRequirements
from Work Order
Operations
Daily Capacityof
Work Center
Tabular Planning Table Pooled Requirements
Selected Work Requirements mapped to defined Work Center capacity based on Operation Dates
81
85
81
842
45
-
Real Experience. Real Advantage.
[
OperationStart & Finish
Dates
DispatchedOperation
Planning Table
MECH
12/11/07
24 Hrs
24 Hrs
0 Hrs
12/12/07
24 Hrs
20 Hrs
0 Hrs
12/13/07
24 Hrs
4 Hrs
0 Hrs
Avail.Cap
Dispatched
Pool/Rqmts
Total Reqts # P A OT S Start Time Order Op Op text FL
6 Hrs 1 PM03 0 01/22/2008 07:00 816542 0010 Op 1
12 Hrs
8 Hrs
4 Hrs
Period
1 PM03 0 01/22/2008 07:00 816542 0020 Op 2
1 PM03 0 01/22/2008 07:00 816542 0030 Op 3
1 PM03 0 01/22/2008 07:00 816542 0040 Op 4
DSPT
DSPT
DSPT
DSPT
Tabular Planning Table Schedule Process (Dispatch)
-
Real Experience. Real Advantage.
[ Tabular Planning Table Schedule Process (Dispatch)
Select Order Operations and click button
Status of DSPT applied
Pool requirements committed and become Scheduled.
-
Real Experience. Real Advantage.
[ Tabular Planning Table Schedule Process (Dispatch) Example of completed Weekly Schedule in Planning Board
-
Real Experience. Real Advantage.
[ Weekly Schedule Creation using IW37n & Planning Table If Work Order dates already defined within weekly period you can set the
Schedule in 5 simple steps:
1. Select required Order Operations (IW37N)
2. GoTo Planning Board
3. Select All Work Order Operations CM25)
4. Click Dispatch Button
5. Click Save Button
-
Real Experience. Real Advantage.
[ Assignment to Individuals
SAP Capacity Planning Table (Capacity Leveling) can be used to assign / dispatch to individual people
Work can be assigned to individual employees defined in HR module
Work times are driven by work schedule in HR
Process is called Split Assignment
Split Dispatched Operations to individual persons
Split Assignments are presented in CATS Work list for each individual
-
Real Experience. Real Advantage.
[ Assignment to Individuals
-
Real Experience. Real Advantage.
[ Assignment to Individuals
-
Real Experience. Real Advantage.
[ Assignment to Individuals
-
Real Experience. Real Advantage.
[ Assignment to Individuals
-
Real Experience. Real Advantage.
[ Assignment to Individuals
-
Real Experience. Real Advantage.
[Example of Weekly Schedule
Publish the Schedule
-
Real Experience. Real Advantage.
[
Example of Weekly Schedule (CM07 Report)
Publish the Schedule
-
Real Experience. Real Advantage.
[
After Dispatch refresh of IW37N updates status and dates ready for publishing
Selection variants and layouts defined to meet schedule publishing requirements
Variety of publishing methods
Publish the Schedule
-
Real Experience. Real Advantage.
[
Example of Weekly Schedule (IW37 Report)
Publish the Schedule
-
Real Experience. Real Advantage.
[ Some publish in Excel down load from List Edit
-
Real Experience. Real Advantage.
[ Schedule Compliance Report
Standard SAP does not readily support this reporting requirement
No history of schedule or date status at point of time
Required changes impact Work Order data
Straightforward report to develop in SAP (Abap) or in BI (preferred).
Advantages of BI:
Maintain compliance specific history over time
Technology readily support analysis within and across organizations
Use Dashboard to effective compare results and drive improved performance
Year Week Plant
Planner
Grp
Work
Center
# of
Scheduled
Orders
# of
Compliant
Orders
%
Compliant
2007 02 ABCD PG1 A 3 2 67%
2007 02 ABCD PG1 B 2 1 50%Sum
PG1 5 3 60%
-
Real Experience. Real Advantage.
[
Requirements of Report:
Snapshot of scheduled work (DSPT) for week n+1 (day/time at end of week n)
Snapshot of completion status (as defined) for week n+1 (day/time at start of week n+2)
Comparison of schedule v completion
Schedule Compliance Report
-
Real Experience. Real Advantage.
[
SAP Project System (PS)
-
Real Experience. Real Advantage.
[ Use of SAP Project Systems
Can enhance scheduling capability through use of PS Planning board
Project environment - Shutdowns / Turnarounds
SAP Project System (PS)
-
Real Experience. Real Advantage.
[
PROJECT
WBS Structure
Network Activity
PS and PM Overview PS
Project Definition
PM Orders
PM
-
Real Experience. Real Advantage.
[
PROJECT
WBS Structure
Network Activity
PS and PM Overview PS
Project Definition
-
Real Experience. Real Advantage.
[ Project Coding Mask
145
Good practice to design / adopt coding mask(s) to ensure
consistent numbering / identification of WBS Elements
Level 1
Level 2Level 3
Capital or Expense Budget / Organizational Responsibility Phase, Stage, Event Major Resource Area
-
Real Experience. Real Advantage.
[ Project Definition Example
146
Framework / defaults for
all objects in project
-Organizational
-Overall Dates
-Control settings
-
Real Experience. Real Advantage.
[ Creating a project and associating WBS elements The first step is to
create a project and
create/assign WBS
element values to the
project.
This transaction is of great use in creating
both the Project and
the WBS elements.
-
Real Experience. Real Advantage.
[ Project WBS Structure Example
148
-
Real Experience. Real Advantage.
[
149
Project Copying
-
Real Experience. Real Advantage.
[
PROJECT
WBS Structure
Network Activity
PM Orders
Plan and Schedule Dates
Plan Dates
S F
S
F
Plan Milestones
S
F
PS
PM
Project Definition
-
Real Experience. Real Advantage.
[ Networks / Activities The network /
activity
relationship is
remarkably
similar to the
order
operation
relationship.
-
Real Experience. Real Advantage.
[ Network finer points continued There are durations,
relationships, intervals.
If the network is linked to another, then its
dates will move when
the master network
reschedules.
Note: each activity within a network can be
assigned a different WBS
element if different from
the parent.
-
Real Experience. Real Advantage.
[ Network Activity Example
153
Activities within same Network can be linked to different WBS Multiple Network can be included within project
-
Real Experience. Real Advantage.
[ Network Activity Relationships
154
Network
Activity
Network
Order
-
Real Experience. Real Advantage.
[ Project Date Planning & Scheduling
155
Top Down or Bottom Up
Date Planning
Scheduled / Calculated Dates
-
Real Experience. Real Advantage.
[ Can Relate Across Network Orders and WBS
156
WBS Element
WBS Element
-
Real Experience. Real Advantage.
[ Gantt View of Plan
157
WBS Element
Network Activity
-
Real Experience. Real Advantage.
[ Rescheduling the project Have the option of
rescheduling network only,
networks and orders, or
just orders.
Pulls off the basic start date of the master network and
then reassigns basic and
scheduled start dates of all
orders.
Transaction gives warning messages for orders unable
to schedule and why.
-
Real Experience. Real Advantage.
[ PM Work Order to Project Assignment
159
Work Order to WBS
Work Order to Network
Activity
Work Order Additional Data Tab
WBS or Activity Dates
applied to Work Order
-
Real Experience. Real Advantage.
[ Linking maintenance orders to networks Once this link is made,
the order schedule and
basic dates will mirror
the networks activity
dates.
Additionally, the order will begin showing up in
PS networks as a
network object as well.
NOTE: Network assignment are made at
the order level and not
the operation level. It is
imperative that the
planning of the order
operations is sound
because moving individual
operations is not
possible.
-
Real Experience. Real Advantage.
[ PM Work Order to Project Assignment
161
-
Real Experience. Real Advantage.
[
162
PM Work Order to Project Assignment
-
Real Experience. Real Advantage.
[ Overview and reporting in PS Networks
-
Real Experience. Real Advantage.
[
164
Project Date and Work Planning Reports
-
Real Experience. Real Advantage.
[ More on Project Info Systems (CN41) Allows the user
to set up which
fields are
displayed and
how this may
look in a graphical
extract.
-
Real Experience. Real Advantage.
[ More on Project Info Systems (CN41)
-
Real Experience. Real Advantage.
[ More on Project Info Systems (CN41) -- Graphics Network Diagram
These charts show durations,
relationships, float
and critical path
(red) for the
networks
-
Real Experience. Real Advantage.
[ More on Project Info Systems (CN41) -- Graphics This is a
Gantt view
of the same
network
diagram.
-
Real Experience. Real Advantage.
[
169
Example Report Work & Schedule Data
-
Real Experience. Real Advantage.
[ Standard Exports MS Project
170
-
Real Experience. Real Advantage.
[
SAP Multi Resource Scheduling (MRS)
-
Real Experience. Real Advantage.
[ What is MRS? A Multi Resource Scheduling tool
View the status of resource planning
Assign suitable employees and tools to requirements (demands) from different areas
Transfer data to and from systems which manage personnel resources and tools
-
Real Experience. Real Advantage.
[ MRS Scenario Overview
Planning and Scheduling
Demands
Plant Maintenance Order/
Service Order
Project System
Network
cProjects Request WebUItechnically based on PS
Capacity Management
Graphical Planning Board(SAP GUI based)
Employee View(Web UI based)
Manager View(Web UI based)
-
Real Experience. Real Advantage.
[ Work Center / Resource Planning Structure (summary)
MRS support RP structure to identify an organization hierarchy pertinent to Resource Planning, or the standard Org Management Structure can be used.
Org Management transactions can link a MRS planner to parts of the structure and MRS transactions can be used to have the default work areas be identified in MRS.
MRS requires a linkage of a Work Center to one node in the RP structure via the HRMS linkage.
MRS planning board uses the PM Work Order Operations Work Center to identify what resource should be shown.
Capacity Data of work center is only used when scheduling on work center level is done (Scheduling in PM/CS and PS, and in the MRS Demand View). It is not taken into
account when scheduling is done on individual level. (MRS Resource View)
MRS can enforce a 1-to-1 relationship between the MRS assignments and the PM Order operations. Thus if multiple assignments are created for an operation, new operations will
be created during Back Integration.
-
Real Experience. Real Advantage.
[ Master Data for Qualifications: Overview
Qualification Matrices
Employee Profile
Requirements Profile
Qualification
Catalogues
Employee
Demand
Skill Level
-
Real Experience. Real Advantage.
[ Functional Overview
Work Center
Capacity
Alert Monitor
Demand Gantt
Work Center
Gantt
-
Real Experience. Real Advantage.
[ Functions in Demand Gantt chart
Flexible selection of relevant orders and networks in entry screen
E.g. usage of Order List (IW38)
Simultaneous planning of PM/CS orders and PS networks
Display of relationships between order operations (also across orders)
Graphical shifting of operation dates via Drag&Drop
Re-Scheduling of orders Simulation possible (only after pressing Save the data is written to
the data base)
Undo / Redo function
Dispatching of orders to Work Center Gantt chart
-
Real Experience. Real Advantage.
[ Details about work center dispatching
In the work center view a possibility is provided to drill down from
work center level to resource level. For this purpose the resources of
the work centers can be displayed with their assignments and
availabilities.
Via drag and drop the operations can be planned from work center
level to resource level.
-
Real Experience. Real Advantage.
[ Details about absolute Capacity Utilization
-
Real Experience. Real Advantage.
[ Scheduler Workplace
-
Real Experience. Real Advantage.
[ Terms
Demands
Resources
Organizational unit
Resource node
Position
Person
Resource planner
Capacitive scheduling
-
Real Experience. Real Advantage.
[ Demand
Order
Operation
Operation
Operation
Demand
Demand
Demand
MRS
-
Real Experience. Real Advantage.
[ Organizational Units with Positions
Plant
Machine Shop
Technical
Services
MillwrightsPipe Fitters
Note: Organizational Unit = Resource Node
Organization Unit
-
Real Experience. Real Advantage.
[
Pipefitter Millwright Machinist
Organization Unit
Position
Plant
Note: A Person is assigned to a Position
Machine Shop
Technical
Services
MillwrightsPipe Fitters
Organizational Units with Positions
-
Real Experience. Real Advantage.
[ Master Data
Resource planning structure: Human Resources (HR or BP record)
Resource availability data
Organizational unit/Work center
Resource planner
Qualifications, scales, qualification catalogs, and qualification matrixes
Employee and requirements profiles
Tools (as equipment or material)
-
Real Experience. Real Advantage.
[ HR to ERP Relationship
Organizational Unit
Organizational Unit
Organizational Unit
HR record/person
HR record/person
HR Work Center
HR Work Center
Work Center
(0005)
Work center of technician
Work Center
(ZMRS)
Work Center
(ZMRS)
HR Logistics
LinkA 061
LA
LinkA 008
P
Position
Resource Planner
Work center with resource planning
node
HRMS Link
LinkA 008
P
LinkA 061
LA
PPOME
PO10
PO10
PO10
PO13
PA30
PO01
IR02
IR01
Daily batch job
Daily batch job
-
Real Experience. Real Advantage.
[
Plant
Technical
Services
Organization Unit
Position
Maintenance Work Center
Person
John Wayne
4343
Mark Scott
4555
Technician Work Center
John Wayne
WC_4343
Mark Scott
WC_4555
Used when work
initially planned in
operation.
Written back to
operation when
Resource is
scheduled.
Technical
Services
Piperfitter
PiperfitterPIPE
Pipefitter1223
1223
Seen as
Resources
Kahn Ellis
Resource Planner
Another view of the relationships
-
Real Experience. Real Advantage.
[ Schedule to Work Center
-
Real Experience. Real Advantage.
[ Schedule to Resource
-
Real Experience. Real Advantage.
[ Demand layout
-
Real Experience. Real Advantage.
[ Resource layout
-
Real Experience. Real Advantage.
[ 1:1 assignment relationship versus no relationship
1:1 relationship:
Cause additional operation to be created per resource assigned
Assign technician work center representing resource to operation
No relationship:
Assign resource(s) to operation in Requirements Assignment tab
Cannot display assignments in List Edit
-
Real Experience. Real Advantage.
[
Vesta Plant Maintenance Excel Integration (PMX)
-
Real Experience. Real Advantage.
[ Standard product functionality
Data Flow:
Work order data
Updated Dates
Updated EmployeeAssignments
Sheet filled with Activities
Detailed Dispatching
-
Real Experience. Real Advantage.
[ IT Overview
The Vesta Integration is developed as a Microsoft Excel Add-In
It uses standard SAP BAPIs to interface with SAP
The add-on honors all SAP and Microsoft security mechanisms
MS ExcelV
esta
Inte
gra
tion
Ad
d-
on
SAPB
AP
Is
an
d R
FC
s
-
Real Experience. Real Advantage.
[
210
Key Learnings
Understand core SAP planning functions and tools
How to develop and manage a maintenance schedule in SAP
Use of and impact of dates
Codes to support the process
How to define and manage capacities
Assess, manage and prioritize work
Awareness of non core SAP PM options that can further enhance & support scheduling
Understanding of how PS can expand scheduling capability
-
Real Experience. Real Advantage.
[
] Thank you for participating.