26467sahiwal_1st_010

180
Sr No. Chapter 01. Carriage ..….……………………………………………………………………………………………… 01 to 22 02. Loading, Unloading & Stacking ……………………………………………………………………… 23 to 25 03. Earthwork ( Excavation & Embankment) ……….…………………………………………………. 26 to 33 04. Dismentling (Demolition) ………………………..……………………………………………………. 34 to 38 05. Mortar ………………………………………….…………………………………………………………. 39 to 40 06. Concrete ………………………………………….…………….……….………………………………. 41 to 51 07. Brickwork ……………………………………...………………………………………………………… 52 to 58 08. Stone Masonary ………………………………………………………………………………………… 59 to 61 09. Roofing ……………………………………………………...…………………………………………… 62 to 67 10. Flooring ………………………………………………………………………………………………….. 68 to 73 11. Surface Rendering …………………………………...………………………………………………… 74 to 78 12. Wood Work ………………………………….…………………………………………………………… 79 to 89 13. Painting & Varnishing ………………………..……………………………………………………….. 90 to 96 14. Lining of Canals ……………………..…………………………………………………………………. 97 to 98 15. Sheet Piling ……………………………………………………………………………………………… 99 to 100 16. Protection & Diversion Work ………………..……………………………………………………….. 101 to 111 17. Outlets …………………………………………….……………………………………………………… 112 to 114 18. Road & Road Structure ………………………………………..……………………………………… 115 to 119 19. Plumbing, Sanitary Installation & Gas Fittings ………………….………………………………… 120 to 126 20. Surface Drainage …………………………………………………..………………………………….. 127 to 128 21. Sewerage ………………………………………………………………………………………………… 129 to 133 22. Sinking of Wells ………………………………………………………………………………………… 134 to 137 23. Tubewell & Water Supply …………………………..………………………………………………… 138 to 151 24. Electric Installation …………………………………………………………………………………….. 152 to 166 25. Iron Work ………………………………………………………………………………………………… 167 to 173 26. Miscellaneous ……………………………………………………...…………………………………… 174 to 177 TABLE OF CONTENTS Page Nos

Upload: amna-rafique

Post on 28-Mar-2015

43 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: 26467Sahiwal_1st_010

Sr No. Chapter

01. Carriage ..….……………………………………………………………………………………………… 01 to 2202. Loading, Unloading & Stacking ……………………………………………………………………… 23 to 2503. Earthwork ( Excavation & Embankment) ……….…………………………………………………. 26 to 3304. Dismentling (Demolition) ………………………..……………………………………………………. 34 to 3805. Mortar ………………………………………….…………………………………………………………. 39 to 4006. Concrete ………………………………………….…………….……….………………………………. 41 to 5107. Brickwork ……………………………………...………………………………………………………… 52 to 5808. Stone Masonary ………………………………………………………………………………………… 59 to 6109. Roofing ……………………………………………………...…………………………………………… 62 to 6710. Flooring ………………………………………………………………………………………………….. 68 to 7311. Surface Rendering …………………………………...………………………………………………… 74 to 7812. Wood Work ………………………………….…………………………………………………………… 79 to 8913. Painting & Varnishing ………………………..……………………………………………………….. 90 to 9614. Lining of Canals ……………………..…………………………………………………………………. 97 to 9815. Sheet Piling ……………………………………………………………………………………………… 99 to 10016. Protection & Diversion Work ………………..……………………………………………………….. 101 to 11117. Outlets …………………………………………….……………………………………………………… 112 to 11418. Road & Road Structure ………………………………………..……………………………………… 115 to 11919. Plumbing, Sanitary Installation & Gas Fittings ………………….………………………………… 120 to 12620. Surface Drainage …………………………………………………..………………………………….. 127 to 12821. Sewerage ………………………………………………………………………………………………… 129 to 13322. Sinking of Wells ………………………………………………………………………………………… 134 to 13723. Tubewell & Water Supply …………………………..………………………………………………… 138 to 15124. Electric Installation …………………………………………………………………………………….. 152 to 16625. Iron Work ………………………………………………………………………………………………… 167 to 17326. Miscellaneous ……………………………………………………...…………………………………… 174 to 177

TABLE OF CONTENTS

Page Nos

Page 2: 26467Sahiwal_1st_010

CARRIAGENote: 1 The rates are applicable to carriage of material on pacca roads only.

For kacha roads an allowance of 25% extra shall be allowed for 2nd and subsequent mileage (Km) rates. Rateupto 1st mile (1st Km) is however common to both kacha and pacca roads.

Note: 2 For hilly areas 25% above the rates in the plain areas shall be allowed for total mileage (Km) covered.

Note: 3 In case of articles longer than 15 ft. (4.6 m) carried in trucks, the following rates shall be allowed:-

i) Above 15 ft. to 25 ft. (4.6 to 7.6 m) :- Total rates to be paid for 15 ft. to 25 ft. (4.6 to 7.6 m) length will be 1.5 times of the rate given in the Composite Schedule of Rates.

ii) Above 25 ft. (7.6 m) :- The total rate to be paid for above 25 ft. (7.6 m) length will be 2 times of the rate given in th Composite Schedule of Rates.

The length measured shall not be the actual length, but the length of the form of consignment as actuallyreceived.

Note: 4 The term 'mile' (Km) whenever used is to mean statute mile (Km).

Note: 5 The rates include loading and unloading of material from the conveyance and stacking as directed.

Note: 6 The rates for carriage by boat or steamer shall be the same as by any other mechanical means on lan

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

1 Carriage of 100 Cft. (2.83 cu.m) of all materials like stone 16.1aggregate, spawl, kankar lime (unslaked), surkhi, etc. or150 Cft. (4.25 cu.m) of timber, by truck or by any othermeans owned by the contractor.

1st chain (1st 30 m) Chain 60.50 30M 60.502nd chain (2nd 30 m) " 11.15 30M 11.153rd to 10th chain (60 to 300 m) " 6.95 30M 6.951000 to 3000 ft. (300 to 900 m) 1000 ft. 67.80 300 Metre 67.801st Km Km 103.872nd Km Km 49.213rd Km Km 37.674th Km Km 26.245th Km Km 24.306th Km Km 23.887th Km Km 22.218th Km Km 21.959th Km Km 20.5610th Km Km 19.0811th Kms to 200Kms Km 11.77201 Kms to 250 Kms Km 3.25251 Kms & susequent Kms Km 2.00

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

Chap-1 (Carriage) Page 1

Page 3: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

2 Carriage of 5 tons of all material like coal, stone lime 16.1 Cement carried in containers other(unslaked), etc. B.G. Rail fastenings, points and crossing, than bags will be paid according toBridge Girders, pipes, sheets, Rail, M.S. bars, etc. etc. this item. The word "pipes" coverby truck or any other means owned by the contractor. G.I,C.I,R.C.C. and P.C.C.

1st chain (1st 30 m) Chain 60.50 30M 60.502nd chain (2nd 30 m) " 11.15 30M 11.153rd to 10th chain (60 to 300 m) " 6.95 30M 6.951000 to 3000 ft. (300 to 900 m) 1000 Ft. 67.80 300M 67.801st Km Km 103.872nd Km Km 49.213rd Km Km 37.674th Km Km 26.241st mile Mile 167.155th Km Km 24.302nd mile " 41.306th Km Km 23.883rd mile Mile 37.407th Km Km 22.214th mile " 34.208th Km Km 21.955th mile 31.659th Km Km 20.566th mile 29.4010th Km Km 19.081 " 19.6511th Kms to 200Kms Km 11.77201 Kms to 250 Kms Km 3.25251 Kms & susequent Kms Km 2.00

3 Carriage of 100 maunds of fuel wood by truck 16.1or any other means owned by the contractor:

1st chain (1st 30 m) Chain 60.50 30 M 60.502nd chain (2nd 30 m) " 11.15 30 M 11.153rd to 10th chain (60 to 300 m) " 6.95 30 M 6.951000 to 3000 ft. (300 to 900 m) 1000 ft 67.80 300 M 67.801st Km Km 103.872nd Km Km 49.213rd Km Km 37.674th Km Km 26.241st mile Mile 167.155th Km Km 24.302nd mile " 41.306th Km Km 23.883rd mile " 37.407th Km Km 22.21

Chap-1 (Carriage) Page 2

Page 4: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

4th mile " 34.208th Km Km 21.955th mile " 31.659th Km Km 20.566th mile " 29.4010th Km Km 19.087th mile and subsequent miles " 19.6511th & subsequent Kms Km 11.77

4 Carriage of 1000 Nos. bricks 10"x5"x3" (250x125x75 mm) ditto Reduce the rate by 33% in case ofor 1000 Nos. tiles 12"x6"x2" (300x150x50 mm) by truck or carriage of 1000 Nos. tiles sizeany other means owned by the contractor :- 12"x6"x1¼" (300 x 150 x 30 mm)

1st chain (1st 30 m) Chain 60.50 30 M 60.502nd chain (2nd 30 m) " 11.15 30 M 11.153rd to 10th chain (60 to 300 m) " 6.95 30 M 6.951000 to 3000 ft. (300 to 900 m) 1000 Ft 67.80 300 M 67.801st Km Km 103.872nd Km Km 49.213rd Km Km 37.674th Km Km 26.241st mile Mile 167.155th Km Km 24.302nd mile " 41.306th Km Km 23.883rd mile " 37.407th Km Km 22.214th mile " 34.208th Km Km 21.955th mile " 31.659th Km Km 20.566th mile " 29.4010th Km Km 19.087th mile and subsequent miles " 19.6511th & subsequent Kms Km 11.77

5 Carriage of 100 cft. (2.83 cu.m) of all material like stone 16.1 Material trolly to be supplied by theaggregate, spawl, kankar lime(unslaked), surkhi, etc. o Government and maintained and run150 cft. (4.25 cu.m) of timber, by means of material trolly by the contractor.

1st chain (1st 30 m) Chain 60.50 30 M 60.502nd chain to 10th chain (2nd 30 m to 300 m) " 11.15 30 M 11.151000 to 3000 ft. (300 to 900 m) 1000 Ft. 67.80 300 M 67.801st Km Km 85.192nd Km Km 65.053rd Km Km 34.694th Km Km 27.171st mile Mile 137.105th Km Km 23.82

Chap-1 (Carriage) Page 3

Page 5: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

2nd mile 49.556th Km Km 22.893rd mile 42.257th Km Km 19.364th mile 34.208th Km Km 19.145th mile 31.659th Km Km 17.926th mile 29.4010th Km Km 16.617th mile and subsequent miles 19.6511th Kms to 200Kms Km 11.95201 Kms to 250 Kms Km 3.25251 Kms & susequent Kms Km 2.00

6 Carriage of 5 tons of all material like coal, stone lime 16.1 Material trolly to be supplied by the(unslaked), etc. B.G. Rail fastening, points and crossing, Government and maintained and runBridge girders, pipes, sheets, Rail, M.S. bars, etc. etc. by by the contractor.means of material trolly

1st chain (1st 30 m) Chain 60.50 30 M 60.502nd chain (2nd 30 m) " 11.15 30 M 11.151000 to 3000 ft. (300 to 900 m) 0/00 Ft. 67.80 300 M 67.801st Km Km 85.192nd Km Km 65.053rd Km Km 34.694th Km Km 27.17st e e 37. 05th Km Km 23.82d e 9.556th Km Km 22.893rd mile and subsequent miles 42.257th Km Km 19.364th mile 34.208th Km Km 19.145t e 3 .659th Km Km 17.926t e 9. 010th Km Km 16.617t e a d subseque t es 9.6511th Kms to 200Kms Km 11.95201 Kms to 250 Kms Km 3.25251 Kms & susequent Kms Km 2.00

7 Carriage of 100 maunds of fuel wood, by means o ditto Material trolly to be suppliedmaterial trolly. by the Government and

1st chain (1st 30 m) Chain 60.50 30 M 60.50 maintained and run by the2nd chain (2nd 30 m) " 11.15 30 M 11.15 contractor.1000 to 3000 ft. (300 to 900 m) 1000 Ft 67.80 300 M 67.801st Km Km 85.192nd Km Km 65.053rd Km Km 34.694th Km Km 27.171st mile Mile 137.105th Km Km 23.822nd mile " 49.55

Chap-1 (Carriage) Page 4

Page 6: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

6th Km Km 22.893rd mile subsequent miles " 42.257th Km Km 19.364th mile 34.208th Km Km 19.145th mile 31.659th Km Km 17.926th mile 29.4010th Km Km 16.617th mile and subsequent miles 19.6511th & subsequent Kms Km 11.95

8 Carriage of 1000 Nos. tiles 12"x6"x2" (300x150x50 mm), ditto Material trolly to be supplied by theby means of material trolly. Government and maintained and run

1st chain (1st 30 m) Chain 60.50 30 M 60.50 by the contractor.2nd chain (2nd 30 m) " 11.15 30 M 11.151000 to 3000 ft. (300 to 900 m) 0/00 Ft. 67.80 300 M 67.801st Km Km 85.192nd Km Km 65.05 16.13rd Km Km 34.694th Km Km 27.171st mile Mile 137.105th Km Km 23.822nd mile " 49.556th Km Km 22.893rd mile subsequent miles " 42.257th Km Km 19.364th mile 34.208th. Km 19.145th mile 31.659th Km Km 17.926th mile 29.4010th Km Km 16.617th mile and subsequent miles 19.6511th & subsequent Kms Km 11.95

9 Carriage of 1000 No. bricks, 9"x4½"x3" ditto(225x113x75 mm) or 8"x4"x4" (200x100x100mm) (nominal)

1st chain (1st 30 m) Chain 49.57 30 M 49.572nd chain (2nd 30 m) " 9.70 30 M 9.703rd to 10th chain (60 to 300 m) " 5.70 30 M 5.701000 to 3000 ft. (300 to 900 m) 0/00 Ft. 55.51 300 M 55.511st Km Km 85.132nd Km Km 40.233rd Km Km 30.864th Km Km 21.65

Chap-1 (Carriage) Page 5

Page 7: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

1st mile Mile 137.005th Km Km 20.512nd mile " 33.856th Km Km 20.053rd mile " 31.657th Km Km 18.214th mile " 28.058th Km Km 18.005th mile " 25.959th Km Km 16.866th mile " 24.1010th Km Km 15.647th mile and subsequent miles " 16.1011th & subsequent Kms Km 9.56

10 Carriage of 1000 No. tiles 9"x4½"x1½" 16.1(225x113x38 mm).

1st chain (1st 30 m) Chain 29.92 30 M 29.922nd chain (2nd 30 m) " 5.51 30 M 5.51 16.13rd to 10th chain (60 to 300 m) " 3.41 30 M 3.411000 to 3000 ft. (300 to 900 m) 0/00 Ft. 33.53 300 M 33.531st Km Km 51.392nd Km Km 24.353rd Km Km 18.654th Km Km 12.971st mile Mile 82.705th Km Km 11.932nd mile " 20.456th Km Km 11.753rd mile " 18.357th Km Km 11.004th mile " 16.958th Km Km 10.875th mile " 15.659th Km Km 10.176th mile " 14.5510th Km Km 9.477th mile and subsequent miles " 9.7011th & subsequent Kms Km 5.79

11 Carriage of 1 Cwt. (50 Kg) cement in bags ditto

1st chain (1st 30 m) Chain 1.14 30 M 1.142nd chain (2nd 30 m) " 0.14 30 M 0.143rd to 10th chain (60 to 300 m) " 0.07 30 M 0.07

1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 0.67 300 M 0.67

1st Km Km 1.271st mile Mile 2.05

Chap-1 (Carriage) Page 6

Page 8: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

2nd Km Km 0.882nd mile " 0.653rd Km Km 0.393rd mile subsequent miles " 0.354th Km and subsequent kilometers. Km 0.24

12 Carriage of 100 Nos. empty cement bags including 16.1bundling.

1st 1000 (300 m) ft. 0/00 Ft. 16.63 300 M 16.631000 to 3000 (300 to 900 m) ft. " 2.07 300 M 2.07

1st Km Km 3.141st mile Mile 5.052nd Km Km 2.982nd mile to 6th mile Mile 1.953rd Km Km 1.637th mile and subsequent miles " 2.404th Km & subsequent Kms Km 1.43

13 Carriage of 100 (2.83 cu.m) cft. of Sarkanda or pilchi, frash ditto Previous lead of collection notor brushwood, by boat or road :- to be deducted from the next

lead of carriage.

1st chain (1st 30 m) Chain 24.75 30 M 24.752nd chain (2nd 30 m) " 11.15 30 M 11.153rd to 10th chain (60 to 300 m) " 3.41 30 M 3.41

1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 27.85 300 M 27.85

1st Km Km 45.391st mile Mile 73.552nd Km Km 24.352nd mile " 57.753rd Km Km 18.653rd mile " 48.604th Km Km 12.974th mile " 35.955th Km Km 11.935th mile " 30.056th Km Km 11.756th mile 24.107th Km Km 11.007th mile and subsequent miles 16.108th Km Km 10.879th Km Km 10.1710th Km Km 9.4711th Km & subsequent Km 5.79

Chap-1 (Carriage) Page 7

Page 9: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

14 Carriage of light machinery weighing upto 3 tonne Ton Tonne dittoupto 1000 ft. (300 metre) 0/00 ft. 201.53 300 M 201.53Execeeding 1000 to 5000 ft (300 to 1500metre) 1000 ft. 48.83 " 48.83

1st Km Km 102.191st mile Mile 164.452nd Km Km 47.862nd mile " 32.653rd Km Km 32.563rd mile " 31.054th Km Km 21.344th mile " 25.155th Km Km 19.985th mile " 25.756th Km Km 19.206th mile " 19.957th Km Km 16.837th mile and subsequent miles " 15.358th Km Km 16.449th Km Km 15.9910th Km Km 12.6311th Km & susequent Km 9.32

15 Carriage of small consignments weighing upto 5 maunds 16.1 For consignment weighing 5 to 10(job rates) : maunds, rate be increased by 25%;

and for consignments weighing 10Consig- to 20 maunds, rate be increased by

Upto 1000 ft. (300 metre) ment/ 16.37 Consign- 16.37 100%.1000 ft. ment/

Exceeding 1000 to 3000 ft. (300 to 900 1000 ft. 11.22 300 M 11.22metre)

1st Km Consign- 16.001st mile Consign- 25.75 ment/ Km2nd Km ment/Mile 10.002nd mile and subsequent miles " 5.05 "3rd Km & subsequent " 3.34

16 Carriage of consignments job.

i) Cooly load for distance:- Each Each

a) Upto 5 Km Consignment 32.70 Consignment 32.70b) Above 5 to 13 Km " 76.90 " 76.90

Chap-1 (Carriage) Page 8

Page 10: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

ii) Carriage of consignments odd jobs. Each Each a) Donkey load for distance upto 500 feet. Consignment 10.85 Consignment 10.85b) Upto 1000 feet. " 16.45 " 16.45c) Upto ½ Mile/ 0.8 Km " 20.80 " 20.80d) Upto one Mile/ 1.6 Km " 26.00 " 26.00e) Upto three Miles/ 4.8 Km " 45.95 " 45.95f) Exceeding 3 Miles/ 16 km " 82.25 " 82.25

Each Eachiii) Cart load for a distance :- Consign- Consig-

ment nment a) upto 4 Miles/ 6.4 Km " 89.85 " 89.85b) Exceeding 4 Miles(6.4 Km) to10 Miles(16 Km) " 163.55 " 163.55

iv) Camel load for a distance:-

a) upto 4 Miles/ 6.4 Km.) " 66.45 " 66.45b) exceeding 4 to 12 mills (6.4 Km to 19.2 Km) " 100.75 " 100.75

17 Hire charges of:- 1. This item will be allowed withprior concurrence of Superintending

i) truck (10 Ton Capacity) Per 2000.00 Per 2000.00 Engineer.day day 2. The rate includes pay of driver

ii) tractor with trolly " 7616.00 " 1000.00 and cleaner only. The repairs shallbe the responsibility of the owner

iii) tractor without trolly " 7616.00 " 800.00 and the cost of lubrication, fuel,loading and unloading shall be paidby the borrower.

18 Carriage of bitumen, tar or other lubricants, in drums: 16.1

1st Km Per 17.031st mile Per 27.40 Tonne2nd Km Ton " 11.682nd mile " 4.803rd Km & subsequent Kms " " 4.833rd mile 7.75

19 Carriage of Asbestos cement pipes BSS Class 'B" withcomet joint and rubber ring, including loading, unloadingand stacking (rate per 100 Rft. (30 m pipes):-

i) 3" (75 mm) i/d pipes:-1st chain (1st 30 m) Chain 2.40 30 M 2.40

Chap-1 (Carriage) Page 9

Page 11: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

2nd chain (2nd 30 m) " 0.45 30 M 0.453rd to 10th chain (60 to 300 m) " 0.25 30 M 0.251000 to 3000 ft. (300 to 900 m) 0/00 Ft. 2.70 300 M 2.701st Km Km 4.102nd Km Km 1.933rd Km Km 1.471st mile Mile 6.604th Km Km 1.022nd mile " 1.655th Km Km 0.953rd mile " 1.506th Km Km 0.934th mile " 1.357th Km Km 0.855th mile " 1.258th Km Km 0.846th mile " 1.159th Km Km 0.797th mile and subsequent miles " 0.8010th Km Km 0.72

11th Km & Susequent Km 0.70

ii) 4" (100 mm) i/d pipes:-

1st chain (1st 30 m) Chain 3.15 30 M 3.152nd chain (2nd 30 m) " 0.60 30 M 0.603rd to 10th chain (60 to 300 m) " 0.35 30 M 0.35

1000 to 9000 ft. (300 to 900 m) 0/00 Ft. 3.50 300 M 3.50

1st Km Km 5.381st mile Mile 8.652nd Km Km 2.512nd mile " 2.153rd Km Km 1.923rd mile " 1.954th Km Km 1.334th mile " 1.755th Km Km 1.235th mile " 1.656th Km Km 1.206th mile " 1.507th Km Km 1.107th mile and subsequent miles " 1.00

Chap-1 (Carriage) Page 10

Page 12: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

8th Km Km 1.099th Km Km 1.0310th Km Km 0.9411th Km & subsequent Km Km 0.91

iii) 6" (150 mm) i/d pipes:-

1st chain (1st 30 m) Chain 4.70 30 M 4.702nd chain (2nd 30 m) " 0.85 30 M 0.853rd to 10th chain (60 to 300 m) " 0.55 30 M 0.551000 to 9000 ft. (300 to 900 m) 0/00 Ft. 5.25 300 M 5.251st Km Km 8.052nd Km Km 3.803rd Km Km 2.901st mile Mile 12.954th Km Km 2.012nd mile " 3.205th Km Km 1.863rd mile " 2.906th Km Km 1.834th mile " 2.657th Km Km 1.705th mile " 2.458th Km Km 1.686th mile " 2.309th Km Km 1.577th mile and subsequent miles " 1.5510th Km Km 1.4511th Km & subsequent Km Km 1.14

iv) 8" (200 mm) i/d pipes:

1st chain (1st 30 m) Chain 7.95 30 M 7.952nd chain (2nd 30 m) " 1.45 30 M 1.453rd to 10th chain (60 to 300 m) " 0.90 30 M 0.901000 to 3000 ft. (300 to 900 m) 0/00 Ft. 8.90 300 M 8.901st Km Km 13.642nd Km Km 6.533rd Km Km 5.001st mile Mile 21.954th Km Km 3.442nd mile " 5.405th Km Km 3.203rd mile " 4.906th Km Km 3.154th mile " 4.507th Km Km 2.935th mile " 4.158th Km Km 2.78

Chap-1 (Carriage) Page 11

Page 13: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

6th mile " 3.859th Km Km 2.637th mile and subsequent miles " 2.6010th Km Km 2.4211th Km & subsequent Km Km 1.63

v) 10" (250 mm) i/d pipes:-1st chain (1st 30 m) Chain 10.65 30 M 10.652nd chain (2nd 30 m) " 1.95 30 M 1.953rd to 10th chain (60 to 300 m) " 1.20 30 M 1.201000 to 3000 ft. (300 to 900 m) 0/00 Ft. 11.95 300 M 11.951st Km Km 18.332nd Km Km 8.563rd Km Km 6.541st mile Mile 29.504th Km Km 4.522nd mile " 7.305th Km Km 4.173rd mile " 6.606th Km Km 4.104th mile Mile 6.057th Km Km 4.065th mile " 5.608th Km Km 4.016th mile " 5.209th Km Km 3.777th mile and subsequent miles " 3.4510th Km Km 3.5111th Km & subsequent Kms Km 2.14

vi) 12" (300 mm) i/d pipes:1st chain (1st 30 m) Chain 13.90 30 M 13.902nd chain (2nd 30 m) " 2.55 30 M 2.553rd to 10th chain (60 to 300 m) " 1.60 30 M 1.601000 to 3000 ft. (300 to 900 m) 0/00 Ft. 15.55 300 M 15.551st Km Km 23.832nd Km Km 12.133rd Km Km 8.884th Km Km 5.861st mile Mile 38.355th Km Km 5.432nd mile " 9.456th Km Km 5.333rd mile " 8.607th Km Km 4.944th mile " 7.858th Km Km 4.88

Chap-1 (Carriage) Page 12

Page 14: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

5th mile " 7.259th Km Km 4.566th mile " 6.7510th Km Km 4.237th mile and subsequent miles " 4.5011th Km & subsequent Kms Km 2.68

vii) 16" (400 mm) i/d pipes:-1st chain (1st 30 m) Chain 22.75 30 M 22.752nd chain (2nd 30 m) " 4.20 30 M 4.203rd to 10th chain (60 to 300 m) " 2.60 30 M 2.601000 to 3000 ft. (300 to 900 m) 0/00 Ft. 25.50 300 M 25.501st Km Km 39.062nd Km Km 18.753rd Km Km 14.121st mile Mile 62.854th Km Km 9.822nd mile " 15.505th Km Km 9.103rd mile " 14.056th Km Km 8.944th mile " 12.857th Km Km 8.315th mile " 11.908th Km Km 8.226th mile " 11.059th Km Km 7.707th mile and subsequent miles " 7.4010th Km Km 7.1411th Km & subsequent Kms Km 4.43

viii) 18" (450 mm) i/d pipes:-

1st chain (1st 30 m) Chain 29.25 30 M 29.252nd chain (2nd 30 m) " 5.40 30 M 5.403rd to 10th chain (60 to 300 m) " 3.35 30 M 3.351000 to 3000 ft. (300 to 900 m) 0/00 Ft. 32.75 300 M 32.751st Km Km 50.182nd Km Km 23.793rd Km Km 18.211st mile Mile 80.754th Km Km 12.692nd mile " 19.955th Km Km 11.773rd mile " 18.106th Km Km 11.564th mile " 16.50

Chap-1 (Carriage) Page 13

Page 15: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

7th Km Km 10.725th mile " 15.308th Km Km 10.606th mile " 14.209th Km Km 9.957th mile and subsequent miles " 9.5010th Km Km 9.2211th Km & subsequent Kms Km 5.62

ix) 20" (500 mm) i/d pipes:-

1st chain (1st 30 m) Chain 31.05 30 M 31.052nd chain (2nd 30 m) " 5.70 30 M 5.703rd to 10th chain (60 to 300 m) " 3.55 30 M 3.551000 to 3000 ft. (300 to 900 m) 0/00 Ft. 34.75 300 M 34.751st Km Km 53.252nd Km Km 25.233rd Km Km 19.321st mile Mile 85.704th Km Km 13.462nd mile " 21.205th Km Km 12.463rd mile " 19.206th Km Km 12.254th mile " 17.557th Km Km 11.385th mile " 16.258th Km Km 11.256th mile " 15.059th Km Km 10.547th mile and subsequent miles " 10.1010th Km Km 9.7611th Km & subsequent Kms Km 6.13

x) 24" (600 mm) i/d pipes:-

1st chain (1st 30 m) Chain 34.40 30 M 34.402nd chain (2nd 30 m) " 6.35 30 M 6.353rd to 10th chain (60 to 300 m) " 3.95 30 M 3.951000 to 5000 ft. (300 to 1500 m) 0/00 Ft. 38.55 300 M 38.551st Km Km 59.002nd Km Km 27.923rd Km Km 21.351st mile Mile 94.954th Km Km 15.392nd mile " 23.455th Km Km 13.763rd mile " 21.25

Chap-1 (Carriage) Page 14

Page 16: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

6th Km Km 13.524th mile Mile 19.407th Km Km 12.555th mile " 18.008th Km Km 12.416th mile " 16.709th Km Km 11.647th mile and subsequent miles " 11.2010th Km Km 10.7911th Km & subsequent Kms Km 6.60

20 Carriage of PVC pipes B.S.S. Class 'B' including loading,unloading and stacking (Rate per 1000 ft.) (300 metre) :-

i) 3" (75 mm) i/d pipes:-

1st chain (1st 30 m) Chain 4.70 30 M 4.702nd chain (2nd 30 m) " 0.85 30 M 0.853rd to 10th chain (60 to 300 m) " 0.55 30 M 0.551000 to 3000 ft. (300 to 900 m) 0/00 Ft. 5.25 300 M 5.251st Km Km 8.052nd Km Km 3.803rd Km Km 2.911st mile Mile 12.954th Km Km 2.022nd mile " 3.205th Km Km 1.873rd mile " 2.906th Km Km. 1.844th mile " 2.657th Km Km 1.715th mile Mile 2.458th Km Km 1.676th mile " 2.259th Km Km 1.567th mile and subsequent miles " 1.5010th Km Km 1.4311th Km & subsequent Kms Km 1.06

ii) 4" (100 mm) i/d pipes:-

1st chain (1st 30 m) Chain 7.20 30 M 7.202nd chain (2nd 30 m) " 1.35 30 M 1.353rd to 10th chain (60 to 300 m) " 0.85 30 M 0.851000 to 3000 ft. (300 to 900 m) 0/00 Ft. 8.10 300 M 8.101st Km Km 12.402nd Km Km 6.053rd Km Km 4.50

Chap-1 (Carriage) Page 15

Page 17: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

1st mile Mile 19.954th Km Km 3.042nd mile " 4.905th Km Km 2.813rd mile " 4.456th Km Km 2.764th mile " 4.057th Km Km 2.555th mile " 3.758th Km Km 2.526th mile " 3.509th Km Km 2.367th mile and subsequent miles " 2.3510th Km Km 2.1911th Km & subsequent Kms Km 1.77

iii) 5" (125 mm) i/d pipes:-

1st chain (1st 30 m) Chain 9.85 30 M 9.852nd chain (2nd 30 m) " 1.80 " 1.803rd to 10th chain (60 to 300 m) " 1.15 " 1.151000 to 3000 ft. (300 to 900 m) 0/00 Ft. 11.05 300 M 11.051st Km Km 16.902nd Km " 8.153rd Km " 6.261st mile Mile 27.204th Km " 4.402nd mile " 6.705th Km Km. 3.893rd mile " 6.106th Km " 3.824th mile Mile 5.557th Km " 3.545th mile " 5.158th Km 3.506th mile " 4.809th Km 3.287th mile and subsequent miles " 3.2010th Km 3.0511th Km & subsequent Kms 1.91

iv) 6" (150 mm) i/d pipes:

1st chain (1st 30 m) Chain 13.55 30 M 13.552nd chain (2nd 30 m) " 2.50 30 M 2.503rd to 10th chain (60 to 300 m) " 1.55 30 M 1.551000 to 3000 ft. (300 to 300 m) 0/00 Ft. 15.20 300 M 15.201st Km. Km. 23.30

Chap-1 (Carriage) Page 16

Page 18: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

2nd Km Km. 11.043rd Km Km. 8.441st mile Mile 37.50 4th Km Km. 5.882nd mile " 9.255th Km Km. 5.463rd mile " 8.406th Km Km. 5.364th mile " 7.657th Km Km. 4.975th mile " 7.108th Km Km. 4.916th mile " 6.609th Km Km. 4.617th mile and subsequent miles " 4.4010th Km Km. 4.2811th Km & subsequent Kms Km. 2.64

v) 8" (200 mm) i/d pipes:-

1st chain (1st 30 m) Chain 23.80 30 M 23.802nd chain (2nd 30 m) " 4.40 30 M 4.403rd to 10th chain (60 to 300 m) " 2.70 30 M 2.701000 to 3000 ft. (300 to 900 m) 0/00 Ft. 26.65 300 M 26.651st Km Km 40.862nd Km Km 19.383rd Km Km 14.831st mile Mile 65.754th Km Km 10.332nd mile " 16.255th Km Km 9.563rd mile Mile 14.706th Km Km 9.404th mile " 13.457th Km Km 8.745th mile " 12.458th Km Km 8.646th mile " 11.559th Km Km 8.107th mile and subsequent miles " 7.7510th Km Km 7.4811th Km & subsequent Kms Km 4.59

vi) 10" (250 mm) i/d pipes:-

1st chain (1st 30 m) Chain 36.90 30 M 36.902nd chain (2nd 30 m) " 6.80 30 M 6.803rd to 10th chain (60 to 300 m) " 4.20 30 M 4.20

Chap-1 (Carriage) Page 17

Page 19: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

1000 to 3000 ft. (300 to 900 m) 0/00 Ft. 41.35 300 M 41.351st Km Km 63.322nd Km Km 30.013rd Km Km 22.981st mile Mile 101.904th Km Km 16.002nd mile " 25.205th Km Km 14.813rd mile " 22.806th Km Km 14.554th mile " 20.857th Km Km 13.535th mile " 19.308th Km Km 13.386th mile " 17.909th Km Km 12.537th mile and subsequent miles " 12.0010th Km Km 11.6111th Km & subsequent Kms Km 7.23

vii) 12" (300 mm) i/d pipes:-

1st chain (1st 30 m) Chain 51.95 30 M 51.952nd chain (2nd 30 m) " 9.55 30 M 9.553rd to 10th chain (60 to 300 m) " 5.95 30 M 5.951000 to 3000 ft. (300 to 900 m) 0/00 Ft. 58.20 300 M 58.201st Km Km 89.172nd Km Km 42.263rd Km Km 32.341st mile Mile 143.504th Km Km 22.532nd mile Mile 35.455th Km Km 20.863rd mile " 32.106th Km Km 20.504th mile " 29.357th Km Km 19.055th mile " 27.158th Km Km 18.846th mile " 25.209th Km Km 17.637th mile and subsequent miles " 16.9010th Km Km 16.3311th Km & subsequent Kms Km 10.14

viii) 14" (350 mm) i/d pipes:-

1st chain (1st 30 m) Chain 67.60 30 M 67.60

Chap-1 (Carriage) Page 18

Page 20: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

2nd chain (2nd 30 m) " 12.45 30 M 12.453rd to 10th chain (60 to 300 m) " 7.75 30 M 7.751000 to 3000 ft. (300 to 900 m) 0/00 Ft. 75.75 300 M 75.751st Km Km 116.052nd Km Km 54.993rd Km Km 42.091st mile Mile 186.754th Km Km 29.312nd mile " 46.155th Km Km 27.153rd mile " 41.806th Km Km 26.674th mile Mile 38.207th Km Km 24.795th mile " 35.358th Km Km 24.516th mile " 32.859th Km Km 22.957th mile and subsequent miles " 22.0010th Km Km 21.3411th Km & subsequent Kms Km 13.27

21 Carriage of PVC pipes B.S.S. Class 'D' including loading,unloading and stacking (Rates per 1000 ft.):-

i) 2" (50 mm) i/d pipes:-1st chain (1st 30 m) Chain 3.40 30 M 3.402nd chain (2nd 30 m) " 0.65 30 M 0.653rd to 10th chain (60 to 300 m) " 0.40 30 M 0.401000 to 3000 ft. (300 to 900 m) 0/00 Ft. 3.85 300 M 3.851st Km Km 5.872nd Km Km 2.783rd Km Km 2.141st mile Mile 9.454th Km Km 1.482nd mile " 2.355th Km Km 1.363rd mile " 2.106th Km Km 1.344th mile " 1.957th Km Km 1.285th mile " 1.808th Km Km 1.246th mile " 1.659th Km Km 1.167th mile and subsequent miles " 1.10

Chap-1 (Carriage) Page 19

Page 21: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

10Km Km 1.0611th Km & subsequent Kms Km 0.69

ii) 2½" (63 mm) i/d pipes:-

1st chain (1st 30 m) Chain 5.35 30 M 5.352nd chain (2nd 30 m) " 1.00 30 M 1.003rd to 10th chain (60 to 300 m) " 0.60 30 M 0.601000 to 3000 ft. (300 to 900 m) 0/00 Ft. 5.95 300 M 5.951st Km Km 9.132nd Km Km 4.383rd Km Km 3.371st mile Mile 14.704th Km Km 2.362nd mile " 3.655th Km Km 2.193rd mile " 3.306th Km Km 2.154th mile " 3.007th Km Km 1.995th mile " 2.808th Km Km 1.776th mile " 2.609th Km Km 1.767th mile and subsequent miles " 1.7510Km Km 1.6311th Km & subsequent Kms Km 1.07

iii) 3" (75 mm) i/d pipes:-1st chain (1st 30 m) Chain 7.40 30 M 7.402nd chain (2nd 30 m) " 1.35 30 M 1.353rd to 10th chain (60 to 300 m) " 0.85 30 M 0.851000 to 3000 ft. (300 to 900 m) 0/00 Ft. 8.25 300 M 8.251st Km Km 12.682nd Km Km 6.033rd Km Km 4.621st mile Mile 20.404th Km Km 3.222nd mile " 5.055th Km Km 2.983rd mile " 4.556th Km Km 2.924th mile " 4.157th Km Km 2.715th mile Mile 3.858th Km Km 2.686th mile " 3.609th Km Km 2.42

Chap-1 (Carriage) Page 20

Page 22: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

7th mile and subsequent miles " 2.4010th Km Km 2.2511th Km & subsequent Kms Km 1.48

iv) 4" (100 mm) i/d pipes:-

1st chain (1st 30 m) Chain 12.20 30 M 12.202nd chain (2nd 30 m) " 2.25 30 M 2.253rd to 10th chain (60 to 300 m) " 1.40 30 M 1.401000 to 3000 ft. (300 to 900 m) 0/00 Ft. 13.70 300 M 13.701st Km Km 20.972nd Km Km 9.933rd Km Km 7.611st mile Mile 33.754th Km Km 5.302nd mile " 8.355th Km Km 4.903rd mile " 7.556th Km Km 4.814th mile " 6.907th Km Km 4.545th mile " 6.408th Km Km 4.406th mile " 5.959th Km Km 4.127th mile and subsequent miles " 3.9510th Km Km 3.7811th Km & subsequent Kms Km 2.49

v) 5" (125 mm) i/d pipes:-

1st chain (1st 30 m) Chain 18.25 30 M 18.252nd chain (2nd 30 m) " 3.35 30 M 3.353rd to 10th chain (60 to 300 m) " 2.10 30 M 2.101000 to 3000 ft. (300 to 900 m) 0/00 Ft. 20.45 300 M 20.451st Km Km 31.352nd Km Km 14.863rd Km Km 11.361st mile Mile 50.454th Km Km 7.922nd mile " 12.455th Km Km 7.343rd mile " 11.306th Km Km 7.214th mile " 10.307th Km Km 6.695th mile " 9.55

Chap-1 (Carriage) Page 21

Page 23: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

8th Km Km 6.616th mile 8.859th Km Km 6.207th mile and subsequent miles 5.9510th Km Km 5.6511th Km & subsequent Kms Km 3.65

vi) 6" (150 mm) i/d pipes:-

1st chain (1st 30 m) Chain 26.30 30 M 26.302nd chain (2nd 30 m) " 4.85 30 M 4.853rd to 10th chain (60 to 300 m) " 3.00 30 M 3.001000 to 3000 ft. (300 to 900 m) 0/00 Ft. 29.50 300 M 29.501st Km Km 45.142nd Km Km 21.383rd Km Km 16.371st mile Mile 72.654th Km Km 11.402nd mile 17.955th Km Km 10.553rd mile 16.256th Km Km 10.364th mile 14.857th Km Km 9.635th mile 13.758th Km Km 9.526th mile 12.809th Km Km 8.927th mile and subsequent miles 8.5510th Km Km 8.2811th Km & subsequent Kms Km 5.24

22 Hand shunting loaded Railway wagons ortrucks:- a) upto ¼ mile / ¼ Km Each 152.70 Each 95.45b) upto ½ mile / ½ Km No 276.45 No 172.80c) upto ¾ mile / ¾ Km " 373.20 " 233.25d) upto 1 (1.6 Km) mile " 444.10 " 277.55e) 2nd mile and subsequent miles/ Each Each

2nd and subsequent kilometres No/Mile 275.85 No/Km 172.40

23 Hand shunting empty Railway wagons or trucks.

a) upto ¼ mile / ¼ Km Each 88.55 Each 55.35b) upto ½ mile / ½ Km No. 146.75 No. 91.70c) upto ¾ mile / ¾ Km " 193.55 " 120.95d) upto 1 mile / 1 Km " 232.30 " 145.20e) 2nd mile and subsequent miles/ Each Each

2nd and subsequent kilometres No/Mile 135.45 No/Km 84.65

Chap-1 (Carriage) Page 22

Page 24: 26467Sahiwal_1st_010

LOADING, UNLOADING & STACKING1 The rate for loading into and unloading from mobile trucks, trollies and boats, etc. will be the same as for Railway wagons.

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Laoding or unloading into or from Railway wagons, lead 100 Cft. 232.30 cu.m 82.05 within one chain, (30m) shingle, sand, ballast, surkhi, ashes, kankar, brick bats, coal, lime or 1,000 Nos. tiles size12"x6"x2" (300x150x50 mm) or 9"x4½"x1½"(225x113x37mm) properly laid & stacked.

2 Loading or unloading bricks into or from Railway wagonslaid and stacked, lead within one chain:-

a) Bricks 10" (250 mm) size. 1000 Nos. 290.40 1000 Nos. 290.40

b) Bricks 9" (225 mm) or smaller size. ditto 232.30 ditto 232.30

3 Loading or unloading into or from Railway wagons cement 100 Bags 290.40 100 Bags 290.40in bags (from inside or outside the godown) and stackingwithin one chain (30 m)

4 Loading or unloading into or from Railway wagons empty 100 Nos. 27.90 100 Nos. 27.90cement bags (from inside or outside the godown) andstacking.

5 Loading or unloading into or from Railway wagons (from 100 Mds. 174.25 100 Kg 4.65inside or outside the godown) and stacking, white lime in bags.

6 Loading or unloading into or from Railway wagons Per 139.40 Per 137.20Structural Steel, R.S. joists, broad, narrow or meter gauge Tonne Tonnerail and rail fastenings, etc.

7 Loading or unloading 45 gallon (204.57 Litres) drums full Each 17.40 Each 17.40into or from Railway wagons, lead upto one chain.

8 Loading or unloading packages of all sorts, upto one Cwt Each 8.70 Each 8.70 Except cement in jute or(50 Kg). paper bags.

9 Loading or unloading sleepers other than wooden,including stacking lead within one chain:-

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

Chap-2 (Loading/Unloading) Page 23

Page 25: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

a) Broad gauge sleepers 100 Nos. 580.80 100 Nos. 580.80

b) Metre gauge and narrow gauge sleepers. ditto 290.40 ditto 290.40

10 Loading or unloading timber logs or timber for shuttering, Per 72.60 Per 71.45into or from Railway wagons of any gauge, including Ton Tonnestacking lead within one chain (30 m)

11 Loading or unloading bhoosa in Railway wagons lead upto 100 Mds. 696.95 100 Kg 18.65150 ft. (45 m)

12 Loading or unloading timber scrap or wooden plugs, into or Per 116.15 Per 114.35from Railway wagons, and stacking within one chain lead. Ton Tonne

13 Loading or unloading pitching stone or spawl from Railway 100 Cft. 85.95 cu.m 30.35wagons of any gauge (including clearing 5 ft. (1500 mm)away from the rail).

14 Loading or unloading building stone (including clearing 5 ft. 100 Cft. 111.50 cu.m 39.40(1.5 m) away from rails).

15 Unloading oil, bitumen tar, etc.

a) Crude oil (to be pumped from tank wagon into tank). 1000 290.40 100 6.40Gallon litres

b) Crude oil (drained by gravity). 1000 290.40 100 6.40Gallon litres

c) Crude oil materials from railway wagons. 100 Cft. 37.15 cu.m 13.15

d) Fuel oil from tank into empty drums, including Per 103.25 Per 101.60stacking within one chain (30 m). Ton Tonne

e) Petrol (2 gallon tin) 100 Nos. 146.35 100 Nos. 146.35 The rate includes checkingand weighing the tins.

f) Kerosine oil (4 gallon tin) 100 Nos. 290.40 100 Nos. 290.4016 Removing and stacking within one chain

(30 m) lead:

a) Stone, spawl, brick bats, shingle, sand, lime, 100 Cft. 116.15 cu.m 41.05surkhi, ashes, kankar and coat, etc.

Chap-2 (Loading/Unloading) Page 24

Page 26: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

b) Bricks. 1000 Nos. 309.75 1000 Nos. 309.75

c) Broad gauge wooden sleepers. 100 Nos. 185.85 100 Nos. 185.85

d) Metre gauge or narrow gauge wooden sleepers. 100 Nos. 110.65 100 Nos. 110.65

e) Rails girders, pipes, cement etc. Per 51.65 Per 50.80Ton Tonne

f) Bridge and crossing timbers, etc. 100 No. 619.50 100 No. 619.50

17 Loading into wagons girders, rails, permanent way Per 116.15 Per 114.35

material (except wooden sleepers) iron work, M.S. bars, Ton Tonnepipes, etc. including lead one chain (30 M) and stackinginside wagons.

18 Unloading from wagons girders, rails, permanent way Per 66.40 Per 65.35material (except wooden sleepers) iron work, M.S. bars, Ton Tonnepipes, etc. lead upto one chain (30 m) but excludingstacking.

19 Loading into wagons wooden broad gauge sleepers, 100 Nos. 464.65 100 Nos. 464.65including one chain (30 m) lead and stacking,.

20 Unloading wooden broad gauge sleepers from wagons, 100 Nos. 221.25 100 Nos. 221.25including one chain (30 m) lead and stacking.

21 Laoding metre gauge or narrow gauge wooden sleepers, 100 Nos. 232.30 100 Nos. 232.30including one chain (30 m) lead and stacking insidewagons.

22 Unloading metre gauge or narrow gauge wooden sleepers, 100 Nos. 122.25 100 Nos. 122.25including one chain (30 m) lead but excluding stacking.

23 Loading bridge and crossing timbers, including one chain 100 Nos. 929.30 100 Nos. 929.30(30 m) lead and stacking.

24 Unloading bridge and crossing timbers, including one 100 Nos. 464.65 100 Nos. 464.65chain (30 m) lead but excluding stacking.

25 Loading or unloading bitumen, asphalt or tar in drums, into Per 69.70 Per 68.60or from railway wagons, lead upto one chain (30 m). Ton Tonne

Chap-2 (Loading/Unloading) Page 25

Page 27: 26467Sahiwal_1st_010

EARTHWORK (EXCAVATION & EMBANKMENT)1 Special allowances for the hardness, wetness and slush:-

The grant of allowances for hard, very hard, wet and slush will be subject to Superinteding Engineer's approval. Specific instructions regarding grant of suchallowances may be issued by the various Administrative Departments and Statutory Bodies. The earth requiring repeated blows of Kassi to break it and ofwhich dry bulk density is not less than 1.5, will be treated as hard.

2 Deduction for shrinkage from bank measurements:-The following allowances should be provided for material which is not rammed, or equally consolidated:-a) Deduction for shrinkage from the bank measurements when the earthwork is done by manual labour.......... 10%b) Deduction for settlement from the bank measurement when the earthwork is done by machines................... 3 to 6%

Before the work is let out to be done by tractors, scrapers, etc. deduction ranging between 3% to 6% should be agreed to with the contractor

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

1 Earthwork excavation underessed lead upto a single throw 171 to 17.5of Kassi, phaorah or shovel:-

a) In ashes, sand, soft soil or silt clearance. 1000 Cft. 871.20 -- cu.m 30.75 --b) In ordinary soil. 1000 Cft. 1,045.45 -- cu.m 36.95 --

2 Earthwork excavation in ashes, sand and soft soil or silt 1000 Cft. 1,277.75 -- cu.m 45.15 -- ditto

clearance, undressed lead upto 50 ft (15 metre).

3 Bed clearance and dressing slopes of drains to required ditto The rate is applicable where the earthsections including the removal of weeds, roots, etc. of the bed to be removed is of thedisposal of excavated materials within 50 ft. (15 metre) lead. type of ordinary soil. When it is silt ora) Excavated material undressed. 1000 Cft. 1,626.25 -- cu.m 57.45 -- 1 or 2 above, whichever is applicable.b) Excavated material dressed in the specified manner. 1000 Cft. 1,783.05 -- cu.m 63.00 -- the drains of each category.

4 Borrowpit excavation undressed lead upto 100 ft (30 metre).

a) Ordinary soil 1000 Cft. 1,626.25 -- cu.m 57.45 --b) Hard soil 1000 Cft. 1,997.95 -- cu.m 70.55 --

5 Earthowrk in ordinary soil for embankments lead upto 100 *411-1 to The rate includes hire charges of

ft. (30 m), including ploughing and mixing with blade grade 411-13 and machinery, cost of fuel, lubricants, payor disc harrow or other suitable equipment, and 301-1 & of driver and cleaner. The rate alsocompaction by mechanical means at optimum moisture 202-3 includes clearing and grubbingcontent and dressing to designed section, complete in all where necessary.respects:- i) 95% to 100% maximum modified AASHO dry density. 1000 Cft. 1,796.70 2,486.20 cu.m 63.45 87.80ii) 90% maximum modified AASHO dry density. 1000 Cft. 1,796.70 2,394.70 cu.m 63.45 84.60iii) 85% maximum modified AASHO dry density 1000 Cft. 1,796.70 2,303.20 cu.m 63.45 81.35

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

Chap-3 (Earthwork) Page 26

Page 28: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

6 Regular excavation dressed. 1000 Cft. 1,222.20 -- cu.m 43.15 -- *411-2

7 Earthwork excavation in open cutting upto 5'-0" (1.5 m) 17.1 to depth for storm water channels, drains, sullage drains in 17.5open areas, roads, streets, lanes, including under pinning of walls and shoring to protect existing works, shuttering and timbering the trenches, dressed to designed level and dimensions, trimming, removal of surface water from trenches, back filling and surplus excavated material disposed of and dressed within 50 ft. (15 m) lead:- i) ordinary 1000 Cft. 2,084.55 2,141.95 cu.m 73.65 75.65ii) hard 1000 Cft. 2,456.25 2,513.65 cu.m 86.75 88.80 iii) very hard 1000 Cft. 2,851.20 2,908.60 cu.m 100.70 102.75iv) gravel & shingle 1000 Cft. 4,809.00 4,866.45 cu.m 169.85 171.90

8 Earthwork excavation in open cutting 5.01 ft. (1.5 m) to ditto

10.0 ft. (3.0 mm) depth for storm water channels, drains, sullage drains in open areas, roads, streets, lanes, including under pinning of walls and shoring to protect existing works, shuttering and timbering the trenches, dressed to designed level and dimensions, trimming, removal of surface water from trenches, back filling and surplus excavated material disposed of and dressed within 100 ft. (30 m) lead:- i) ordinary 1000 Cft. 2,259.85 2,374.05 cu.m 79.80 83.85ii) hard 1000 Cft. 2,631.55 2,745.75 cu.m 92.95 97.00iii) very hard 1000 Cft. 3,026.50 3,140.70 cu.m 106.90 110.95iv) gravel & shingle 1000 Cft. 5,216.65 5,330.85 cu.m 184.25 188.30

9 Excavation in shingle or gravel formation and rock, not 17.1 to 17.5

requiring blasting, undressed lead upto 100 ft (30 m). i) Dry 1000 Cft. 4,414.10 -- cu.m 155.90 --ii) Wet 1000 Cft. 5,111.05 -- cu.m 180.50 --iii) In flowing water 1000 Cft. 6,504.95 -- cu.m 229.75 --

10 Earthwork excavation in irrigation channels, drains, etc. to

designed section, grades and profiles, excavated material dittodisposed off and dressed within 50 ft. (15 m) lead:-

i) ordinary 1000 Cft. 1,911.35 -- cu.m 67.50 --ii) hard 1000 Cft. 2,283.05 -- cu.m 80.65 --iii) very hard 1000 Cft. 2,678.00 -- cu.m 94.60 --iv) gravel & shingle 1000 Cft. 4,752.00 -- cu.m 167.85 --

Chap-3 (Earthwork) Page 27

Page 29: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

11 Excavation in rock dressed to designed section, grades and profiles, excavated material disposed off within 100 ft. (30 m) 17.1 to 17.5 Tools and plants shall be the liabilityand lift upto 5'-0" (1.5 m). of the contractor.a) Soft rock, slate, shale, schist laterite work, with pick and 1000 Cft. 4,625.30 -- cu.m 163.35 --

crow bar. b) Medium hard rock, requiring occasional blasting. 1000 Cft. 7,286.50 7,862.50 cu.m 257.35 277.70

12 a) Excavation in hard rock requiring blasting and disposal

of excavated material (blasted material) upto 50 ft. (15 17.1 to 17.5 1) Tools and plants required shall bem) lead, (including dressing and levelling to designed the liability of the Contractorsection,e tc. complete).

2) Reduce the rate by 8% if thei) Grade I 1000 Cft. 4,274.15 4,850.15 cu.m 150.95 171.30 excavated section is not dressed orii) Grade II 1000 Cft. 4,662.25 5,622.25 cu.m 164.65 198.60 levelled to designed section.iii) Grade III 1000 Cft. 5,599.45 6,751.45 cu.m 197.75 238.45iv) Grade IV 1000 Cft. 6,246.25 7,590.25 cu.m 220.60 268.10v) Grade V 1000 Cft. 6,911.50 8,447.50 cu.m 244.10 298.35vi) Grade VI 1000 Cft. 7,442.15 9,170.15 cu.m 262.85 323.90

b) Excavation in hard rock requiring blasting, but blasting

prohibited, and disposal of excavated material within 50 17.1 to 17.5 1) Tools and plants required shall beft. (15 m) lead (including dressing and levelling to the liability of the contractor.designed section, etc. complete):-

2) Reduce the rate by 8% if thei) Grade I 1000 Cft. 8,548.30 9,700.30 cu.m 301.95 342.60 excavated section is not dressed orii) Grade II 1000 Cft. 9,324.50 11,244.50 cu.m 329.35 397.15 levelled to designed section.iii) Grade III 1000 Cft. 11,198.90 13,502.90 cu.m 395.55 476.90iv) Grade IV 1000 Cft. 12,492.50 15,180.50 cu.m 441.25 536.20v) Grade V 1000 Cft. 13,823.05 16,895.05 cu.m 488.25 596.75vi) Grade VI 1000 Cft. 14,884.30 18,340.30 cu.m 525.70 647.80

13 Rehandling of earthwork:

a) Lead upto a single throw of Kassi, phaorah or shovel 1000 Cft. 580.80 -- cu.m 20.50 -- dittob) Upto a lead of 50 ft. (15 m). 1000 Cft. 813.10 -- cu.m 28.70 --

14 Rehandling of gravel work or excavated rock, 1000 Cft. 2,323.20 -- cu.m 82.05 -- 17.1 to 17.5

lead upto 50 ft.( 15 m)

15 Filling, watering and ramming earth under floors:- ditto

i) with surplus earth from foundation, etc. 1000 Cft. 1,214.40 -- cu.m 42.90 --ii) with new earth excavated from outside, 1000 Cft. 2,489.65 -- cu.m 87.95 --

lead upto one chain (30 m).

Chap-3 (Earthwork) Page 28

Page 30: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

16 Extra for every 50 ft. (15 m) additional lead or part thereof :- This rate shall be applicable upto 1000 ft. total distance, including the

i) for earhtwork soft, ordinary, hard and very hard. 1000 Cft. 25.70 -- cu.m 0.90 -- lead covered in the item of earthworkii) for gravel, shingle or rock. 1000 Cft. 29.85 -- cu.m 1.05 --

17 Transportation of earth all types when the total distance, This rate will be paid inaddition to the

including the lead covered in the item of work, is more than rate of earthwork, without deducting1000 ft. (300 m) the lead covered in the item ofa) upto ¼ mile (400 m). 1000 Cft. 938.70 -- cu.m 33.15 -- earthworkb) for every 330 ft. (100 m) additional lead or part thereof,

beyond ¼ mile (400 m) upto one mile. (1.6 Km.) 1000 Cft. 61.05 -- cu.m 2.15 --c) for every ¼ mile (400 m) additional lead or part thereof,

beyond one mile (1.6 Km.) upto 5 mile (8 Km). 1000 Cft. 103.25 -- cu.m 3.65 --d) for every ½ mile (800 m) additional lead

or part thereof, beyond 5 miles (8 Km). 1000 Cft. 85.20 -- cu.m 3.00 --

18 Dressing and levelling of earhtwork to designed section, etc. 17.10 to 17.5complete:- a) Ashes, sand, silt or soft soil. 1000 Cft. 84.90 -- cu.m 3.00 --b) Ordinary or hard soil. 1000 Cft. 170.45 -- cu.m 6.00 --c) Gravel work or soft rock not requiring 1000 Cft. 348.50 -- cu.m 12.30 --

blasting.

19 Dowel dressing. Per 78.75 -- Metre 2.60 -- ditto This rate is in addition to payment forChain dressed earhtwork.

20 a) Dressing slopes of banks or ground surface. 100Sft. 35.50 -- sq.m 3.80 -- ditto To be paid only when exclusively

dressing is done and no earthwork is carried out in embankment or cutting.

b) Dressing of earthwork (done by machinery or otherwise 100Sft. 58.60 -- sq.m 6.30 -- i) The surface area dressed is to beand left undressed) to designed section. taken for measurement.

ii) The item is applicable where the dressing is done by the contractor other than the one who executed the

work.21 Excavation in foundation of building, bridges and other

structures, including dagbelling, dressing, refilling around 17.1 to 17.5structure with excavated earth, watering and rammiing lead upto one chain (30 m) and lift upto 5 ft. (1.5 m) a) in sand, ashes or loose soil 1000 Cft. 2,143.70 -- cu.m 75.70 --b) in ordinary soil. 1000 Cft. 2,518.55 -- cu.m 88.95 --c) in hard soil or soft murum 1000 Cft. 2,822.15 -- cu.m 99.70 --

Chap-3 (Earthwork) Page 29

Page 31: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

22 Cutting hard rock such as granite, ballast, hard lime stone or 1000 Cft. 18,480.00 20,815.05 cu.m 652.70 735.20 17.1 to 17.5 Tools and plants required shall be thesand stone, etc. with chisels and hammers, for small liability of the contractor.foundations.

23 Extra for excavation requiring shoring. 1000 Cft. 316.80 509.00 cu.m 11.20 18.00 17.1 to 17.5 Composite rate includes materials,

i.e. plank, etc.24 Compaction of earthwork (soft, ordinary or hard soil) :- ditto

a) Mixing, moistening earth to optimum moisture content 1000 Cft. 311.40 -- cu.m 11.00 --

in layers for compaction, etc. complete.

b) Compaction by rolling with animal driven roller/hand rammed:

i) soft or sandy soil 1000 Cft. 348.50 -- cu.m 12.30 --

1) The rate does not include hireii) ordinary soil 1000 Cft. 406.55 -- cu.m 14.35 -- charges of the roller.

2) Roller to be 'supplied by iii) hard soil 1000 Cft. 464.65 -- cu.m 16.40 -- Government

iv) admixture of shingle 1000 Cft. 522.70 -- cu.m 18.45 --

c) Ramming earthwork (all types of soil). 1000 Cft. 348.50 -- cu.m 12.30 --

d) Ramming earhtwork behind retaining walls. 1000 Cft. 464.65 -- cu.m 16.40 --

25 Compaction of earthwork with power road roller, including 17.1 (a)

ploughing, mixing, moistening earth to optimum moisture *411-5 and The rate also includes hire charges ofcontent in layers, etc. complete: 202-3 machinery, cost of fuel, lubricant, pay

of driver and cleaner, etc.i) 95% to 100% maximum modified AASHO dry density. 1000 Cft. -- 689.50 cu.m - 24.35

ii) 90% maximum modified AASHO dry density. 1000 Cft. -- 598.00 cu.m - 21.10

iiii) 85% maximum modified AASHO dry density. 1000 Cft. -- 506.50 cu.m - 17.90

26 Extra for wet earthwork. 1000 Cft. 813.10 -- cu.m 28.70 - 17.1 to 17.5 That will support a man's weight.

27 Extra for slush or Daldal including dewatering. 1000 Cft. 1,858.55 -- cu.m 65.65 - 17.1 to 17.5 That will not support a man's weight.

28 Extra for puddling. 1000 Cft. 1,452.00 -- cu.m 51.30 - ditto

29 Earthwork on small rain water drains, along canal banks, 100 Rft. 220.70 -- Metre 7.25 - ditto

roads and plantation drains, dressed, etc. complete

Chap-3 (Earthwork) Page 30

Page 32: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

30 Filling and compacting soil, earth and boulders behind 1000 Cft. 2,090.90 -- cu.m 73.85 -- 17.1 to 17.5

retaining walls (including excavation of soil and lead upto 50 ft.( 15 m).

31 Dag bailing 3" (75 mm) deep. Per mile 1,053.80 -- Per 654.95 -- ditto Dag bailing for layout of borrow pit, to

Km be done by contractors at their own cost.

32 Turfing slopes of banks or lawns with grass sods including 100Sft. 387.20 -- sq.m 41.65 -- dittoploughing, laying, setting and watering (Turf got from within a distance of 5 miles (8 Km.) and maintenance for 15 days).

33 Berm cutting:- 17.1 to 17.5

a) lead upto a single throw of Kassi, phaora or shovel 1000 Cft. 1,045.45 -- cu.m 36.95 --

(without dressing). b) upto 50 ft(15 m)lead (including dressing). 1000 Cft. 1,911.35 -- cu.m 67.50 --

34 Berm trimming both sides of channels:- 17.1 to 17.5

a) upto 3½ ft. (1.06 m) depth. Per Mile 2,798.40 -- Per Km. 1749.00 -- b) exceeding 3½ ft. to 5 ft. (1.06 to 1.5 m) depth. Per Mile 3,951.20 -- Per Km. 2469.50 --c) exceeding 5 ft. to 8 ft. (1.5 to 2.4 m) depth Per Mile 6,124.80 -- Per Km. 3828.00 --

35 Ploughing and levelling borrowpits. ditto Area ploughed to be measured.

i) upto 3 ft. (0.9 m) depth. Per Acre 580.80 -- Per Hect. 1435.20 --ii) above 3 ft. (0.9 m) depth. Per Acre 1,161.60 -- Per Hect. 2870.35 --

36 Making boundary or service roads, including dag-belling, ditto

levelling and dressing:

i) in unploughed land:

a) from 10.0 ft. to 20.0 ft. (3 to 6 m) wide. Per Chain 312.40 -- Metre 10.25 --b) from 20.1 ft. to 40.0 ft. (6.10 to 12 m) wide. Per Chain 431.20 -- Metre 14.15 --

ii) in ploughed land:

a) from 10.0 ft. to 20.0 ft. (3 to 6 m) wide. Per Chain 324.85 -- Metre 10.65 --b) from 20.1 ft. to 40.0 ft. (6.10 to 12 m) wide. Per Chain 443.65 -- Metre 14.55 --

Chap-3 (Earthwork) Page 31

Page 33: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

37 Earthwork by boats, including hire of boats:- 17.1 to 17.5 For ordinary soil.

i) Digging and loading into boats, upto 50 ft. (15 m) lead. 1000 Cft. 1,742.40 -- cu.m 61.55 --ii) Carriage by boats upto 10 chains (300 m). 1000 Cft. 488.20 -- cu.m 17.25 --iii) Extra for every additional one chain (30 m) or part 1000 Cft. 46.45 -- cu.m 1.65 --

thereof beyond 10 chains (300 m). iv) Unloading earth from boats. 1000 Cft. 813.10 -- cu.m 28.70 --

38 Unloading earth from B.G. trucks and clearing 5 ft. (1.5 m) 1000 Cft. 696.95 -- cu.m 24.60 -- 17.1 to 17.5

from rail.

39 Earthwork by tramway, digging and loading in trucks, upto 50 1000 Cft. 1,626.25 -- cu.m 57.45 -- 17.1 to 17.5ft. (15 m) lead.

40 Unloading earth from B.G. trucks and spreading upto 1000 Cft. 1,306.80 -- cu.m 46.15 -- ditto

15 ft. (4.5 m) from rail.

41 Supplying clean and screened river or pit sand within 5 100Cft. 232.65 252.65 cu.m 82.15 89.25 ditto The rate incudes:-chains (150 m). i) removal of top crust of earth

over burden ii) royalty to the government or cost to the private owner.

42 Earthwork excavation in open cutting for sewers and 17.1 to 17.5 The rate does not include back fillingmanholes as shown in drawings including shuttering and **13.1 &13.4 after laying of sewer, which is payabletimbering, dressing to correct section and dimensions separately.according to templates and levels, and removing surface water, in all types of soil except shingle, gravel and rock:-

If the timbering and shuttering is noti) 0 ft. to 7.0 ft. (0 to 2.10 m) depth 1000 Cft. 1,943.80 2,227.60 cu.m 68.65 78.70 actually done at site, the compositeii) 7-01 ft. to 15.0 ft. (2.15 to 4.5 m) depth 1000 Cft. 3,266.20 3,687.25 cu.m 115.35 130.25 rate may be reduced by Rs. 368.20,iii) above 15.0 ft. (4.5 m) depth 1000 Cft. 4,195.50 4,616.50 cu.m 148.20 163.05 579.60 and 579.60 respectively.

43 Earthwork excavation of trenches in open cutting for sewers 17.1 to 17.5 The rate does not include back filling

and manhole chambers, etc. below sub-soil water level to **13.3 & after laying of sewer, which is payablecorrect section and dimensions according to templates and 13.5 separately.levels, including shoring, timbering and shuttering of M.S. sheets on both sides of the trenches:

i) 0 ft. to 4.0 ft. (0 to 1.20 m) depth below SSWL. 1000 Cft. 3,106.40 5,137.75 cu.m 109.70 181.45ii) 4.01 ft. to 8.0 ft. (1.22 to 2.4 m) depth below SSWL. 1000 Cft. 3,883.25 6,513.65 cu.m 137.15 230.05iii) Exceeding 8 ft. (2.4 m) depth below SSWL. 1000 Cft. 5,824.90 8,667.30 cu.m 205.75 306.15

Chap-3 (Earthwork) Page 32

Page 34: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. Unit of Unit of No.

M/ment Labour Composite M/ment Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

44 Excavation of trenches in all kinds of soil, except cutting 1000 Cft. 1,768.80 -- cu.m 62.45 -- 17.1 to 17.5 The rate does not include back fillingrock, for watersupply pipelines upto 5 ft. (1.5 m) depth **8.1 after laying of pipe line, which isfrom ground level, including trimming, dressing sides, payable separately.levelling the beds of trenches to correct grade and cutting pits for joints, etc. complete in all respects.

45 Cutting and removing trees within a distance of 100 ft. (30 m)

a) upto 2½ ft. (760 mm) girth. Each 353.75 -- Each 353.75 b) above 2½ ft. to 6 ft. (760 to 1800 mm) girth. Each 686.40 -- Each 686.40

46 Uprooting stump and removing within 100 ft. (30 m) from 2 ft. Each 435.60 -- Each 435.60

to 6 ft. (600 to 1800 mm) girth.

47 Jungle clearance and removing within 100 ft. (30 m).

a) light 1000 Sft. 58.10 -- sq.m 0.65 --b) thick 1000 Sft. 116.15 -- sq.m 1.25 --

48 Uprooting Sarkanda growth and disposal within 100 ft. (30 m) 100Sft. 27.90 -- sq.m 3.00 --

49 Ploughing 3 times. Per 235.95 -- Per Hect. 583.05 --

Acre

50 Levelling, dressing and making lawns. 100Sft. 116.15 -- sq.m 12.50 --

51 Turfing lawns (excluding cost of turf). 100Sft. 96.80 -- sq.m 10.40 --

52 Earthwork in excavation of drains, irrigation channels through excavator / drag lines in all kind of soil and conditions(dry,wetslush,daldal and under water) including its disposal and prepartion of working pad for operation of machinery.

1000 Cft. -- 1435.00 cu.m -- 50.70

* Specification number correspond to Book of "Specification for Road & Bridge Construction, 1971".** Specification number correspond to Book of "Building & Roads Department Specification Vol. II, 1966 (Public Health Works).

Chap-3 (Earthwork) Page 33

Page 35: 26467Sahiwal_1st_010

DISMANTLING (DEMOLITION)1 Rates for all finished works include the removal of surplus debris, unused material and byproducts.

2 The rates for dismantling roofs or upper storey floor, include the dismantling of all materials, except roosupports such as beams and trusses.

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

Stone Work

1 Dismantling dry stone masonry. 100Cft. 197.45 cu.m 69.75 18.1

2 Dismantling stone masonry in mud mortar. 100Cft. 290.40 cu.m 102.55 ditto

3 Dismantling stone masonry in lime or cement mortar. 100Cft. 696.95 cu.m 246.15 ditto Add extra 13%, 32% and 51% onlabour rates only for 2nd, 3rd, 4thand subsequent floors respectively.

4 a) Dismantling dry stone or spawl pitching. 100Cft. 348.50 cu.m 123.10 ditto

b) Dismantling stone or spawl pitching (mud grouted). 100Cft. 441.40 cu.m 155.90 ditto

5 Dismantling stone or spawl pitching and apron in silted 100Cft. 580.80 cu.m 205.15 dittocondition.

6 Dismantling stone pitching, cement or lime grouted. 100Cft. 929.30 cu.m 328.25 ditto

7 Dismantling stone in crates:

a) wooden crates 100Cft. 464.65 cu.m 164.10

b) wire crates ditto 580.80 ditto 205.15

8 Dismantling stone ware drain including base concrete. 100Cft. 325.25 cu.m 114.90 ditto

Brick Work

9 Dismantling mud/pise walling. 100Cft. 116.15 cu.m 41.00 18.1

10 Dismantling sun dried brick masonry. 100Cft. 290.40 cu.m 102.55 ditto

11 Dismantling dry brick masonry. 100Cft. 197.45 cu.m 69.75 ditto

12 Dismantling brick work in mud mortar. 100Cft. 406.55 cu.m 143.60 18.1 Add extra 13%, 32% and 51% onlabour rates only for 2nd, 3rd, 4th

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

Chap-4 (Dismantling) Page 34

Page 36: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

13 Dismantling brick work in lime or cement mortar. 100Cft. 987.35 cu.m 348.75 ditto and subsequent floors respectivelyagainst item No. 12, 13, 14 & 15.

14 Dismantling cement block masonry. 100Cft. 871.20 cu.m 307.70 ditto

15 Dismantling Dhajji walling. 100Cft. 232.30 cu.m 82.05 ditto

Concrete

16 Dismantling mud concrete. 100Cft. 464.65 cu.m 164.10 ditto

17 Dismantling lime concrete. 100Cft. 638.90 cu.m 225.65 Add extra 13%, 32% and 51% onlabour rates only for 2nd, 3rd, 4th

18 Dismantling lime or cement concrete, under water. 100Cft. 2,439.35 cu.m 861.60 and subsequent floors respectivelyagainst item No. 17, 19 & 20.

19 a) Dismantling cement concrete plain 100Cft. 1,277.75 cu.m 451.30 ditto1:4:8.

b) Dismantling cement concrete plain ditto 2,090.90 ditto 738.501:3:6.

c) Dismantling cement concrete 1:2:4 ditto 2,555.50 ditto 902.60plain.

d) Dismantling cement concrete with brick ditto 696.95 ditto 246.15aggregate.

e) Dismantling D.P.C. of cement concrete ditto 348.50 ditto 123.101½" thick (40 mm) and clearing the site.

20 Dismantling cement concrete reinforced, 100Cft. 4,181.75 cu.m 1477.00 ditto

separating reinforcement from concrete,cleaning and straightening the same.

Roofing

21 Dismantling sirki sarkanda or thatched 100Sft. 139.40 sq.m 15.00 18.1roofing, supported on battens or ballies.

22 a) Dismantling 1st class tile roofing. 100Sft. 348.50 sq.m 37.50 Add extra 13%, 32 and 51% onlabour rate only for 2nd, 3rd, 4th

b) Dismantling 2nd class tile roofing. 100Sft. 290.40 sq.m 31.25 ditto and subsequent floors respectivelyagainst items No. 22, 25, 26 and28.

23 Dismantling from any height, asbestos sheets and ridge 100Sft. 187.45 sq.m 20.15 18.1coping.

Chap-4 (Dismantling) Page 35

Page 37: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

24 a) Dismantling roof of wooden planks and battens, from 100Sft. 160.5 sq.m 17.25 dittoany height.

b) Dismantling wooden ceiling above 20' (6.0 m) height 100Sft. 620.95 sq.m 66.80 dittoin difficult position, including lifting with care andspecial scaffolding along live electric wires and withmachines underneath.

25 Dismantling jack arch roofing, including removal of joists. 100Sft. 464.65 sq.m 50.00 ditto

26 Dismantling R.B. roof complete with mud and plaster, 100Sft. 580.80 sq.m 62.50 dittoincluding separating reinforcement, cleaning andstraightening the same.

27 a) Stripping and stacking slate or tiles from the truss 100Sft. 290.40 sq.m 31.25roofing.

b) Stripping and stacking C.I. sheet roof. ditto 266.55 ditto 28.70

c) Extra for dismantling C.I. sheet roof above 20 ft. (6m) ditto 396.00 ditto 42.60in difficult position, including lifting with specialscaffolding along live electric wire with machineunderneath.

28 Dismantling slates or tiles including battens, purlins and 100Sft. 464.65 sq.m 50.00 18.1planking.

Flooring

29 Dismantling brick or flagged flooring without 100Sft. 197.45 sq.m 21.25 18.1 Add extra 13%, 32% and 51% onconcrete foundation. labour rates only for 2nd, 3rd, 4th

and subsequent floors respectively30 Dismantling plank or wooden block flooring, 100Sft. 290.40 sq.m 31.25 ditto against items No. 29 and 30.

etc.

31 Disjoining R.C.C. pipes inside the trench and dismantling i) The rate does not include theand removing the pipes from the trench and stacking them cost of excavation and refilling ofoutside:- trench, or the demolition of any

masonry or brick work.a) 6" to 12" (150 to 300 mm) diameter Per Lft 9.10 Metre 29.85b) 13" to 24" (325 to 600 mm) diameter Per Lft 13.75 Metre 45.10 ii) Bends, elbows, sluice valves,c) 25" to 36" (625 to 900 mm) diameter ditto 16.20 ditto 53.15 etc. should not be paid for extra ifd) Above 36" (Above 900 mm) diameter ditto 22.90 ditto 75.10 fixed in the length of pipe line that

is being dismantled.

Chap-4 (Dismantling) Page 36

Page 38: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

WOOD WORK32 a) Removing door with chowkat. Per 120.10 Per 120.10 18.1 Add extra 13%, 32% and 51% on

No. No. labour rates only for 2nd, 3rd, 4thb) Removing windows and sky lights with chowkat. ditto 94.50 ditto 94.50 and subsequent floors respectively

against items No. 32, 33, 34, 35 &36.

33 Removing ventilators and wooden sunshade, etc. Per No. 50.70 Per No. 50.70 ditto

34 a) Dismantling wooden beams upto 12' (3.65m) Per No. 72.60 Per No. 72.60 dittolength.

b) Dismantling wooden beams from 12.1' to 23' ditto 116.15 ditto 116.15(3.65 to 7.0 m) length.

35 a) Dismantling wooden partition Jaffry work etc. 100Sft. 143.30 sq.m 15.40 ditto

b) Dismantling wooden trusses. 100Kg 415.75 %Kg 415.75

36 Dismantling wooden palisade fencing. Per Lft. 11.90 Metre 39.05 ditto

Iron work

37 Dismantling iron work of trusses, sheds, water tanks, etc. 100Kg 424.40 %Kg 424.40 18.1 Add extra 13%, 32% and 51% onexcluding cutting of rivets. labour rates only for 2nd, 3rd, 4th

and subsequent floors respectivelyagainst items No. 37 and 38.

38 Dismantling rolled steel beams or iron rails, etc. 100Kg 190.65 %Kg 190.65 ditto

39 Dismantling iron latrine. Per Unit/ 432.95 Per Unit/ 432.95 ditto2 Seats 2 Seats

40 Dismantling tees, bends or sluice valves upto 12" Each per 9.00 Each per 3.60 ditto(300 mm) bore. inch bore cm bore

41 a) Dismantling B.G. water column. Each 3,055.80 Each 3055.80 ditto

b) Dismantling M.G. or N.G. water column. Each 2,046.00 Each 2046.00 ditto

42 Dismantling all type of wire fencing, including rolling wire 100Lft. 197.45 Metre 6.50 18.1into bundles and collecting material.

Chap-4 (Dismantling) Page 37

Page 39: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

Miscellaneous

43 Dismantling wire netting of tennis courts and frame work. 100Sft. 92.95 sq.m 10.00 18.1

44 Dismantling cloth ceiling and supporting timber. 100Sft. 174.25 sq.m 18.75 ditto

45 Dismantling and removing road metalling. 100Cft. 464.65 cu.m 164.10 ditto

46 Dismantling and removing road pavement, etc., including 100Cft. 620.30 cu.m 219.10 dittoscreening and stacking of byproducts upto one chain lead(30 metre).

47 Removing mud plaster from walls. 100Sft. 48.40 sq.m 5.20 ditto Add extra 13%, 32% and 51% onlabour rates only for 2nd, 3rd, 4th

48 Removing cement or lime plaster. 100Sft. 96.80 sq.m 10.40 ditto and subsequent floors against itemNo. 47, 48, 49, & 50 respectively

49 Scraping:- 18.1

a) White wash or colour wash. 100Sft. 58.10 sq.m 6.25

b) Ordinary distemper, oil bound distemper, ditto 174.25 ditto 18.75or paint of wall.

50 Dismantling glazed or encaustic tiles, etc. 100Sft. 675.85 sq.m 72.70 18.1

51 Scraping boulders. 100Cft. 813.10 cu.m 287.20 18.1

52 Cleaning lime or cement mortar of old stones 100Cft. 406.55 cu.m 143.60 18.1to be used in masonry.

Electric Wiring

53 Dismantling light, fan and call bell point Per 18.90 19.15 Per 18.90 19.15including casing and capping/strip open type, point pointand making good damaged surface (buildingportion).

54 Dismantling plug point and making good Per 16.20 16.45 Per 16.20 16.45damaged surface (building portion). point point

55 Dismantling G.I./M.S. conduit/G.I. flexible/PVC pipes orconduit wiring, etc. of all sizes including making gooddamaged surface (building portion):-

i) on surface Per foot 3.45 3.50 P.Mtr 11.30 11.50ii) recessed in wall Per foot 7.25 7.30 P.Mtr 23.80 23.95

Chap-4 (Dismantling) Page 38

Page 40: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

Chap-4 (Dismantling) Page 39

Page 41: 26467Sahiwal_1st_010

Dry Material Required for Dry Material Required for 100 Cft. Wet (Ready) Mortar One Cum Wet (Ready) Mortar

S. No. Ratio of Mortar Cement Lime Cement Lime Sand (50 Kg) Putty Sand (50 Kg.) Putty Cum.

Bag Cft. Cft. Bag. Cum1 2 3 4 5 6 7 81 Cement : Sand

1 : 2 33.48 82 11.83 0.821 : 3 23.11 85 8.16 0.851 : 4 18.37 90 6.49 0.901 : 5 14.70 90 5.19 0.901 : 6 13.61 100 4.81 1.001 : 7 11.68 100 4.12 1.001 : 8 10.21 100 3.61 1.00

2 Cement : Lime : Sand1 : 1 : 6 12.25 15.0 90 4.33 0.15 0.901 : 1 : 7 10.70 13.1 92 3.78 0.13 0.921 : 1 : 8 9.39 11.5 92 3.32 0.12 0.921 : 1 : 9 8.52 10.44 94 3.00 0.10 0.94

1 : 1 : 10 7.67 9.4 94 2.71 0.09 0.941 : 2 : 8 9.19 22.5 90 3.25 0.23 0.901 : 2 : 9 8.16 20.0 90 2.88 0.20 0.90

1 : 2 : 10 7.67 18.8 94 2.71 0.19 0.941 : 2 : 12 6.39 15.66 94 2.26 0.16 0.941 : 3 : 12 6.26 23.0 92 2.21 0.23 0.921 : 3 : 14 5.47 20.1 94 1.93 0.20 0.941 : 3 : 16 4.82 17.7 94 1.70 0.18 0.941 : ¼ : 3 23.11 7.0 85 8.16 0.07 0.85

3 Lime : Sand1 : 2 43 86 0.43 0.861 : 3 31 93 0.31 0.93

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWALMORTAR

Chap-5 (Mortar) Page 39

Page 42: 26467Sahiwal_1st_010

MORTARDry Material Required for 100 Cft. Dry Material Required for

Wet (Ready) Mortar one M3 Wet (Ready) MortarS. Ratio of Mortar Clay Lime Sand Surkhi Cinder Clay Lime Sand Surkhi CinderNo. (Putty) (Putty)

Cft. Cft. Cft. Cft. Cft. M3 M3 M3 M3 M3

1 2 3 4 5 6 7 3 4 5 6 7

4 Mud 135 1.35

5 Lime : Surkhi2 : 3 49.00 - 73.5 - 0.49 - 0.74 -1 : 2 40.75 - 81.5 - 0.41 - 0.82 -1 : 3 30.30 - 91.0 - 0.30 - 0.91 -

6 Lime : Sand : Surkhi1 : 1 : 1 40.50 40.5 40.5 - 0.41 0.41 0.41

7 Lime : Cinder1 : 1 57.0 - 57.0 - 0.57 - - 0.57

Wet material required for 100 Cft. Wet material required for 1M³ (35.32 Cft) masonry (including wastage): masonry ( including wastage) :

1 Brick Masonry :a) Mud Mortar 35.00 Cft 0.35 M3

b) Cement, Sand 25.00 Cft 0.25 M3

c) Cement, Lime (Putty) Sand 25.00 Cft 0.25 M3

d) Lime (Putty) Sand 25.00 Cft 0.25 M3

2 Stone Masonry :a) Random rubble, uncoursed

i) Foundation and Plinth 45.00 Cft 0.45 M3

ii) Superstructure 40.00 Cft 0.40 M3

iii) Coursed 35.00 Cft 0.35 M3

b) Ashlar Block in course or Scabled masonry 30.00 Cft 0.30 M3

c) Ashlar fine masonry 20.00 Cft 0.20 M3

(1) Cement 1 Cft. = 40.8233 KgNotes : (2) Unslaked lime 1.7 Cft. = 37.3242 Kg

(3) Slaked lime 2.5 Cft. = 37.3242 Kg(4) Quick lime 40 Kg Will yield 2.6 Cft. lime putty.

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

Chap-5 (Mortar) Page 40

Page 43: 26467Sahiwal_1st_010

CONCRETENotes 1 Notes (1) Rates for all finished works include the removal of surplus debris, unused material and by products.

2 If concrete mixer or high frequency vibrator, etc. is supplied by the Government, all charges including depreciation will be recovered from the contractor.

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Mud concrete in foundation including watering and ramming, 100Cft 1306.25 2626.25 cu.m 461.35 927.60 The stone ballast, crushed bajri,

using brick or stone ballast 1½" (40 mm) gauge. round shingle from nallah, or brick

ballast may be used according to

2 Dry rammed brick or stone ballast, 1½" to 2"( 40 mm to 50 100Cft 871.20 2059.20 cu.m 307.70 727.30 their comparative cheaper rates in

mm) gauge. various areas of the Province.

3 Cement concrete brick or stone ballast 1½ " to 2" (40 mm to 20.1 -do-

50 mm) gauge, in foundation and plinth:-

(a) Ratio 1: 3: 6 100Cft 1735.80 7150.20 cu.m 613.10 2525.45

(b) Ratio 1: 4: 8 ditto 1735.80 6205.55 " 613.10 2191.80

(c) Ratio 1:5:10 ditto 1735.80 5703.50 " 613.10 2014.50

(d) Ratio 1: 6:12 ditto 1735.80 5316.60 " 613.10 1877.80

(e) Ratio 1: 6: 18 ditto 1735.80 4877.40 " 613.10 1722.70

(f) Ratio 1: 7:20 ditto 1735.80 4695.25 " 613.10 1658.35

4 Extra on item No. 3 above, for sedimentation tank or filter

beds of Public Health Engineering Works: The stone ballast, crushed bajri,

round shingle from nallah, or brick

(a) in bed 100Cft 652.10 - cu.m 230.30 - ballast may be used according to

their comparative cheaper rates in(b) on slope ditto 990.00 - " 349.65 - various areas of the Province.

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

Chap-6 (Concrete) Page 41

Page 44: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

5 Cement concrete plain including placing, 20.1

compacting, finishing and curing

complete (including screening and

washing of stone aggregate):

(a) Ratio 1: 1:2 100Cft 2471.05 15589.45 cu.m 872.80 5506.20

(b) Ratio 1: 1½: 1½ ditto 2471.05 14977.45 " 872.80 5290.05

(c) Ratio 1: 1½: 3 ditto 2471.05 13199.05 " 872.80 4661.90

(d) Ratio 1: 2: 3 ditto 2471.05 12620.65 " 872.80 4457.60

(e) Ratio 1: 3: 3 ditto 2471.05 11272.80 " 872.80 3981.55

(f) Ratio 1: 2: 4 100Cft 2471.05 11932.80 cu.m 872.80 4214.65

(g) Ratio 1: 2: 6 ditto 2471.05 11240.15 " 872.80 3970.00

(h) Ratio 1: 3: 6 ditto 2471.05 10755.85 " 872.80 3798.95

(i) Ratio 1: 4: 8 ditto 2471.05 9936.00 " 872.80 3509.40

6 Providing and laying reinforced cement concrete (including 20.4 1) The rate includes rendering floor

prestressed concrete), using coarse sand and screened surface smooth, and the plastering

graded and washed aggregate, in required shape and design, done for making up all surfaces

including forms, moulds, shuttering, lifting, compacting, after removing centring.

curing, rendering and finishing exposed surface, complete

(but excluding the cost of steel reinforcement, its fabrication 2) Plastering done under soffit of

and placing in position, etc.):- R.C.C. roof slab meant for human

habitation buildings shall be paid

(a) (i) Reinforced cement concrete in roof slab, beams, extra.

columns lintels, girders and other structural members laid in

situ or precast laid in position, or prestressed members cast 3) This item shall not be applicable

in situ, complete in all respects:- to factory made units.

(1) Type A (nominal mix 1:1:2) Per Cft 55.75 224.60 cu.m 1969.10 7932.85 4) Composite rate shall be reduced by

(2) Type B (nominal mix 1: 1½: 3) ditto 55.75 200.90 " 1969.10 7095.80 Rs:5/- P.Cft & Rs:11.50/- P.Cft if chenab (3) (c) Type C (nominal mix 1: 2: 4) ditto 55.75 188.4 " 1969.1 6654.3 sand and local sand respectively is used.

Chap-6 (Concrete) Page 42

Page 45: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

(a)(ii) Reinforced cement concrete in slab of rafts / strip

foundation, base slab of column and retaining walls; etc and

other structural members other than those mentioned in

5(a) (i) above not requiring form work (i.e. horizental

shuttering) complete in all respects:-

(1) Type A (nominal mix 1: 1: 2) Per Cft 33.65 178.05 cu.m 1188.50 6288.75

(2) Type B (nominal mix 1: 1½: 3) ditto 33.65 150.80 " 1188.50 5326.25

(3) Type C (nominal mix 1: 2: 4) ditto 33.65 138.25 " 1188.50 4883.00

(b) Precast reinforced cement concrete and prestressed

reinforced cement concrete in columns, beams, lintels, stair

cases, shelves, etc.

(1) Type A (nominal mix 1: 1: 2) Per Cft 43.05 203.00 cu.m 1520.55 7169.95

(2) Type B (nominal mix 1:1½: 3) ditto 43.05 179.25 " 1520.55 6331.10

(3) Type C (nominal mix 1: 2: 4) ditto 43.05 166.75 " 1520.55 5889.60

(c) Erecting and fixing in position, precast cement concrete

or stone slab in roofs or lintels, etc. lift unto 20 ft., (6m) Per Cft 20.05 28.85 cu.m 708.15 1019.00

including all charges.

(d) Add extra labour for R.C. concrete in Per Cft 8.70 -- cu.m 307.30 -

2nd and subsequent storeys.

7 Providing and casting in situ bored reinforced concrete piles *851-1 Composite rate shall be reduced bywith type C concrete (nominal mix 1: 2: 4 ) , using 10% extra to Rs:5/- P.Cft & Rs:7/- P.Cft if chenab sand cement in dry mix, and course sand, including all labour and 851-10 and local sand respectively is used.material (except the cost of steel reinforcement and itslabour for bending and laying in position, etc. which will bepaid separately, including, screening & washing of shingleand curing:-i) 18 " (450 mm) dia pile Per Rft 621.10 814.75 Metre 2037.20 2672.40ii) 20" (500 mm) dia pile Per Rft 679.00 917.90 Metre 2227.10 3010.70iii) 22" (550 mm) dia pile Per Rft 765.5 1038.4 Metre 2510.85 3405.95iv) 24" (600 mm) dia pile Per Rft 868.60 1213.00 Metre 2849.00 3978.70

Chap-6 (Concrete) Page 43

Page 46: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

8 Fabrication of mild steel reinforcement bar cage for R.C.C. *851-5 The rate includes wastage, overlaps,

bored piles, including cutting, bending, laying in position, etc.

welding and fastening, including cost of binding wire and

labour charges for binding of steel reinforcement (also

includes removal of rust from the bars):-

(a) plain bars Per Cwt. 646.80 3641.50 100 kg 1273.25 7168.30

(b) deformed bars ditto 646.80 4099.55 " 1273.25 8070.00

9 Fabrication of mild steel reinforcement for cement concrete, *851.5 The rate includes wastage, overlaps

including cutting, bending, laying in position, making joints and chairs, etc.

and fastenings, including cost of binding wire and labour

charges for binding of steel reinforcement (also includes

removal of rust from bars):-

(a) plain bars Per Cwt. 178.20 3313.85 100 kg 350.80 6523.35

(b) deformed bars ditto 178.20 3808.85 " 350.80 7497.75

10 Precast cement concrete solid or face blocks (1:2:4), Per Cft 24.80 105.60 cu.m 875.95 3729.80 20.2

including cost of templates.

11 Precast cement concrete hollow blocks (1: 2: 4) , including Per Cft 54.65 108.35 cu.m 1930.25 3826.90 20.2

cost of templates and constructing walls thereof.

12 Providing and fixing ornamental cement jali 2" (50 mm) thick Per Sft 16.90 30.45 sq.m 181.85 327.65 20.1 to

(1: 2: 4), without steel. 20.4

13 Extra labour for laying concrete plain or reinforced:

(a) above 20' (6 m) upto 40'(12 m) height 100Cft 929.30 - cu.m 328.25 -(b) for every additional 10'(3 m) height. 100Cft 580.80 - cu.m 205.15 -

Chap-6 (Concrete) Page 44

Page 47: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

14 Extra labour for work of weirs, rail or road bridges, syphons, and 100Cft 232.30 - cu.m 82.05 -

concreting in superstructure

15 Making reinforced cement concrete spout, including fixing in Each 211.20 326.65 Each 211.20 326.65 20.4

position (2½' x 6" x5") (760 mmx150 mm x 125 mm)

16 Making holes upto 3"(75 mm) dia 18"(450 mm) depth in cement Per hole 506.90 - Each 506.90 - 20.1

concrete or stone masonry walls and repairing.

17 Extra labour for skipping concrete in wells. 100Cft 1443.20 - cu.m 509.75 - 20.1

18 Nicking concrete surface:

(a) Cement concrete surface 100Sft 221.75 - sq.m 23.85 -

(b) Lime concrete surface ditto 73.20 - " 7.90 -

19 Preparing, watering and ramming surface for laying concrete

(for Headworks only):-

(a) Horizontal floor 100Sft 182.25 - sq.m 19.60 -

(b) Glacis and crest ditto 279.85 - " 30.10 -

(c) Inverted filters ditto 84.50 - " 9.10 -

20 Fabrication of high tensile steel prestressing cables for 100 Kg. 2348.15 26708.50 100 Kg. 2348.15 26708.50 *811-1 The rate includes wastage in

prestressed (post tensioned) concrete, including assembling by to cutting and breakage in stressing,drawing the H.T. wire through metal spacer plate, inserting in helix 811-11 etc.core and taping or tying, sheathing in longitudinally welded metalcorrugated sheath, positioning , anchorage with male and femaleset of anchorage cone, forming ducts for transverse cable,stressing cables with jack at both ends as per stressing schedule,maintaining stressing record and supply the same in the approvedproforma to the Engineer-in-charge, making loop at blind end,including all materials required for it, grouting the cable ducts withcement, cutting projected ends and making good recesses, etc.,complete in all respects.

Chap-6 (Concrete) Page 45

Page 48: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

21 Fabrication of High Tensile steel reinforcement for prestressed 100kg 1454.40 25056.00 %kg 1454.40 25056.00 1) The rate includes wastage in

(pretension) concrete work, including inserting wire in moulds, cutting and breakage in stressing,

providing M.S. shear bars, spacers and lift hooks, male and etc.

female anchorage, tie down, struts, stressing cables, maintaining 2) Quantity of H. T. wire will form

stress record and supply the same in approved proforma to the basis of payment.

Engineer-in-charge, cutting wires and projecting ends and making 3) This item shall not be applicable

good recesses, etc., complete in all respects. to factory made units.

22 Lifting, transporting and placing precast prestressed concrete *811-1

B eam, Girder and other members (excluding battens) etc. in to

Position on the bridge to correct alignment and level, etc. 811-11

complete

i) Beam upto 50 ft. (15 m) length 100Cft 1056.75 cu.m 373.25

ii) Beam above 50 ft. (15m) upto 75 ft. (22.5m) length 100Cft 1559.98 cu.m 551.00

iii) Beam above 75ft. (22.5m) upto 100ft. (30m) length 100Cft 1962.45 cu.m 693.15

iv) Beam above 100ft. (30m) upto 150ft.(45m) length 100Cft 2498.15 cu.m 882.35

v) Beam above 150ft. (45m) length 100Cft 2994.35 cu.m 1057.60

23 Providing and laying foam concrete 3 inch (75 mm) thick, Per Sft. 14.60 34.55 sq.m. 157.10 371.75

using cement sand in the ratio of 1:2 and aluminium powder

at the rate of 0.2% of the cement, sand mix,

24 Providing and fixing 6 in(150 mm). wide curved sheet of

required shape fixed on face of the construction joint with G.I.

screw,1.5 in (40 mm) long to cover construction joints

vertically:-

i) aluminium sheet 1/16 in(1.5 mm) thick Per Rft. 10.10 36.65 Metre 33.15 120.20

ii) G.I. sheet, 18 SWG Per Rft. 9.00 64.50 Metre 29.50 211.55

25 Providing and fixing 1/8" (3 mm) thick 3" (75 mm) wide aluminiumstrip on horizontal and vertical expansion joints in walls, columns,

Chap-6 (Concrete) Page 46

Page 49: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

ceilings and floors etc., including cost of clips/screws etc.,

complete in all respects:-

a) On interior surface (without mastic strip) Per Rft. 7.60 34.10 Metre 24.95 111.85

b) On exterior surface (with mastic strip) ditto 7.60 37.00 " 24.95 121.35

26 Providing and fixing 1/16" (1.5 mm) thick copper flashing on Per Sft. 7.15 88.50 Sq.m 76.95 952.25

expansion joints complete in all respects.

27 Providing and fixing 6 in (150 mm). wideG.I. sheet 18SWG. Per Rft. 3.25 55.45 Metre 10.65 181.90

stopper to expansion joint.

28 Providing embeding 10" (250 mm) wide ¼" (6 mm) thick Per Rft. 13.85 55.85 Metre 45.45 183.15

rubber water stopper in expansion joints of R.C.C. roof

slab complete in all respects.

29 Filling expansion joints with bitumen. sand & saw dust in Per Rft Per Metre/

ratio 1:2:2. per inch 1.45 12.80 Per 25 mm 4.75 42.00

width Width

30 Filling expansion joints with bitumen. Per Rft. 23.15 - Metre 75.95 -

31 Laying asphaltic mixture in expansion joints. Per Rft. 20.35 - Metre 66.75 - Material to be paid on actuals.

32 Providing and fixing theremopore (foamed polythene)

sheet in horizontal and vertical expansion joints:

a) 1" (25 mm) thick thermopore sheet Per Sft. 3.40 8.05 Sq.m 36.60 86.60

b) 1½" (40 mm) thick thermopore sheet ditto 3.40 12.15 " 36.60 130.75

33 Providing and laying damp proof course of cement concrete

1:2: 4(using cement, sand and shingle), including bitumencoating :-

Chap-6 (Concrete) Page 47

Page 50: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

(a) with one coat bitumen and one coat polythene sheet

500gauge

i) 1½" thick (40 mm) 100Sft 662.65 2632.30 sq.m 71.30 283.25

ii) 2" thick (50 mm) 100Sft 662.65 2935.80 sq.m 71.30 315.90

iii) 3" thick (75 mm) 100Sft 690.80 3607.60 sq.m 74.35 388.20

(b) with 2 coats of bitumen:

i) 1½" thick (40 mm) 100Sft 662.65 2870.75 sq.m 71.30 308.90

ii) 2" thick (50 mm) 100Sft 662.65 3173.80 sq.m 71.30 341.50

iii) 3" thick (75 mm) 100Sft 690.80 3845.60 sq.m 74.35 413.80

34 Providing and laying damp proof course with cement sand

plaster and bitumen coating:-

(a) with one coat of bitumen and one coat of polythene sheet

500 gauge :-

i) Ratio 1: 4

a) ½" thick (13 mm) 100Sft 620.40 1742.15 sq.m 66.75 187.45

b) ¾" thick (20 mm) 100Sft 620.40 1886.70 sq.m 66.75 203.00

ii) Ratio 1:3

a) ½ " thick (13 mm) 100Sft 620.40 1784.10 sq.m 66.75 191.95

b) ¾ " thick (20mm) 100Sft 620.40 1935.45 sq.m 66.75 208.25

iii) Ratio 1:2

a) ½ " thick (13 mm) 100Sft 620.40 1819.20 sq.m 66.75 195.75

b) ¾ " thick (20 mm) 100Sft 620.40 2018.60 sq.m 66.75 217.20

Chap-6 (Concrete) Page 48

Page 51: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

(b) with 2 coats of bitumen:-

i) Ratio 1: 4

a) ½" thick (13 mm) 100Sft 620.40 1873.20 sq.m 66.75 201.55

b) ¾" thick (20 mm) 100Sft 620.40 2017.95 sq.m 66.75 217.15

ii) Ratio 1:3

a) ½ " thick (13 mm) 100Sft 620.40 1915.85 sq.m 66.75 206.15

b) ¾ " thick (20 mm) 100Sft 620.40 2067.20 sq.m 66.75 222.45

iii) Ratio 1:2

a) ½ " thick (13 mm) 100Sft 620.40 2021.15 sq.m 66.75 217.50

b) ¾ " thick (20 mm) 100Sft 620.40 2244.55 sq.m 66.75 241.50

35 Providing and laying vertical damp proof course with cement

sand plaster and bitumen coating:-

(a) with one coat of bitumen and one coat of polythene sheet

500 gauge:

i) Ratio 1: 4

a) ½" thick (13 mm) 100Sft 620.40 1671.55 sq.m 66.75 179.85

b) ¾" thick (20 mm) 100Sft 620.40 1816.45 sq.m 66.75 195.45

ii) Ratio 1:3

a) ½ " thick (13 mm) 100Sft 620.40 1713.90 sq.m 66.75 184.40

b) ¾ " thick (20 mm) 100Sft 620.40 1865.25 sq.m 66.75 200.70

iii) Ratio 1:2

a) ½ " thick (13 mm) 100Sft 620.40 1819.20 sq.m 66.75 195.75

b) ¾ " thick (20 mm) 100Sft 620.40 2042.60 sq.m 66.75 219.80

Chap-6 (Concrete) Page 49

Page 52: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

(b) with 2 coats of bitumen:-

i) Ratio 1: 4

a) ½" thick (13 mm) 100Sft 620.40 1873.15 sq.m 66.75 201.55

b) ¾" thick (20 mm) 100Sft 620.40 2017.95 sq.m 66.75 217.15

ii) Ratio 1:3

a) ½ " thick (13 mm) 100Sft 620.40 1915.35 sq.m 66.75 206.10

b) ¾ " thick (20 mm) 100Sft 620.40 2066.70 sq.m 66.75 222.40

iii) Ratio 1:2

a) ½ " thick (13 mm) 100Sft 620.40 2020.80 sq.m 66.75 217.45

b) ¾ " thick (20 mm) 100Sft 620.40 2244.05 sq.m 66.75 241.45

36 Grouting concrete between, the grooves of gates, including 100Cft 3062.40 - cu.m. 1081.65 -

shuttering.

37 Chiesel dressing concrete surface on sides of grooves. 100Sft 121.95 - sq.m 13.10 -

38 Laying and ramming dry ballast or kankar. 100Cft 943.80 - cu.m 333.35 -

39 Hoisting and placing in position R.C.C. shelves. per No. 35.50 - per No. 35.50 -

40 Breaking brick ballast, screening and stacking:-

(a) 2"(50 mm) ring 100Cft. 726.00 - cu.m 256.40 -

(b) 1½ "(40 mm) ring ditto 813.10 - " 287.20 -

(c) 1" (25 mm) ring ditto 943.80 - " 333.35 -

(d) Jhama ballast ¾"(20 mm) ring ditto 1089.00 - " 384.65 -

41 Supplying and fixing broken glasses on court yard walls, Per Rft 23.55 53.60 metre 77.25 175.80

including 1:3: 6 cement concrete coping.

Chap-6 (Concrete) Page 50

Page 53: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

42 Crushing stone ballast by machine. 100Cft 726.00 - cu.m. 256.40 - This does not include the charges

for working of crushers, but includes

manual labour for carriageof stone to

crusher within three chains (90 m)

and also stacking the product after

crushing within three chains (90 m).

43 Breaking stone ballast screened and stacked:-

(a) 2" ring (50 mm) 100Cft. 813.10 - cu.m. 287.20 -

(b) 1½ " ring (40 mm) ditto 943.80 - " 333.35 -

(c) 1" ring (25 mm) ditto 1089.00 - " 384.65 -

d) ½ " ring (13 mm) ditto 1452.00 - " 512.85 -

(e)1/8" to ¼" ring (3 mm to 6 mm) ditto 2468.40 - " 871.85 -

44 Screening and stacking stone ballast shingle or bajri, etc. 100Cft. 232.30 - cu.m. 82.05 -

45 Washing ballast, bajri or shingle. 100Cft. 232.30 - cu.m. 82.05 -

46 Erecting and carting sun shades of precast R.C. concrete

upto 5' x 2½' (1.50 m x 0.76 m) Each 148.35 - Each 148.35 -

Specification numbers correspond to book of standard specification of Road and Bridge Construction, "1971"

Chap-6 (Concrete) Page 51

Page 54: 26467Sahiwal_1st_010

BRICK WORK1 Rates for all finsihed works include the removal of surplus debris, unused material and byproducts.2 The rates apply to all sizes of bricks, including the modular bricks of size 8"x4"x4" (200x100x100 mm) nominal.

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Pacca brick work in mud mortar in buildings: 21.1 Masonry of boundary wall to beto considered as masonry other than

i) in foundation and plinth 100Cft. 1392.45 6582.45 cu.m 491.80 2324.90 21.4 building.ii) in ground floor ditto 1846.50 7036.50 ditto 652.20 2485.30

The composite rate is to bereduced by 7% and 14%, if 2nd or3rd class bricks are used.

2 Add extra labour on item No. 1 for brick work in:-

i) first floor 100Cft. 343.20 -- cu.m 121.20 -ii) second floor ditto 797.30 -- ditto 281.60 -iii) third floor ditto 1251.35 -- ditto 442.00 -iv) fourth & subsequent floors ditto 2043.35 -- ditto 721.70 -

3 Pacca brick work in mud mortar other than building:- 21.1 to Same remarks as against21.4 item No. 1 above

i) upto 20 ft. (6.1 m) height 100Cft. 1893.00 7083.00 cu.m 668.60 2501.70ii) extra labour for every 5 ft. (1.5 m) ditto 343.20 -- ditto 121.20 -

additional height, or part thereof.

4 Pacca brick work in foundation and plinth in:- ditto Same remarks as againstitem No. 1 above.

i) Cement, sand mortar:-

Ratio 1:2 100Cft. 1834.90 9477.70 cu.m 648.05 3347.50Ratio 1:3 ditto 1834.90 8912.50 ditto 648.05 3147.90Ratio 1:4 ditto 1834.90 8573.40 ditto 648.05 3028.15Ratio 1:5 ditto 1834.90 8347.30 ditto 648.05 2948.25Ratio 1:6 ditto 1834.90 8177.15 ditto 648.05 2888.15Ratio 1:7 ditto 1834.90 8067.70 ditto 648.05 2849.50Ratio 1:8 ditto 1834.90 7968.55 ditto 648.05 2814.50

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-7(Brickwork) Page 52

Page 55: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

ii) lime, cement sand mortar:- 21.1 The rate of lime mortar alsoincludes grinding of mortar.

Ratio 1:1:6 100Cft. 1834.90 8276.40 cu.m 648.05 2923.25Ratio 1:1:7 ditto 1834.90 8161.45 ditto 648.05 2882.60Ratio 1:1:8 ditto 1834.90 8069.30 ditto 648.05 2850.10Ratio 1:1:9 ditto 1834.90 7991.65 ditto 648.05 2822.65Ratio 1:1:10 ditto 1834.90 7933.50 ditto 648.05 2802.10

iii) lime, sand mortar 1:2 100Cft. 1834.90 7659.80 cu.m 648.05 2705.45 ditto ditto

5 Pacca brick work in ground floor:- ditto i) The composite rate is tobe reduced by 7% and 14%,

i) cement, sand mortar:- if 2nd or 3rd class bricks areused.

Ratio 1:2 100Cft. 2405.15 10047.95 cu.m 849.50 3548.95 ii) Masonry of boundary wallRatio 1:3 ditto 2405.15 9482.75 ditto 849.50 3349.30 to be considered as masonryRatio 1:4 ditto 2405.15 9143.65 ditto 849.50 3229.55 other than building.Ratio 1:5 ditto 2405.15 8917.55 ditto 849.50 3149.70Ratio 1:6 ditto 2405.15 8747.40 ditto 849.50 3089.60Ratio 1:7 ditto 2405.15 8637.95 ditto 849.50 3050.90Ratio 1:8 ditto 2405.15 8537.60 ditto 849.50 3015.50

ii) lime, cement, sand mortar:- The rate of lime mortar alsoincludes grinding of mortar.

Ratio 1:1:6 100Cft. 2405.15 8846.65 cu.m 849.50 3124.65Ratio 1:1:7 ditto 2405.15 8732.80 ditto 849.50 3084.45Ratio 1:1:8 ditto 2405.15 8639.55 ditto 849.50 3051.50Ratio 1:1:9 ditto 2405.15 8561.90 ditto 849.50 3024.05Ratio 1:1:10 ditto 2405.15 8503.90 ditto 849.50 3003.60

iii) lime, sand mortar 1:2 100Cft. 2405.15 8230.00 cu.m 849.50 2906.85 The rate of lime mortar also

includes grinding of mortar.

6 Add extra labour on item No. 5 for brickworkin:-

i) first floor 100Cft. 343.20 -- cu.m 121.20 -ii) second floor ditto 797.30 -- ditto 281.60 -iii) third floor ditto 1251.35 -- ditto 442.00 -iv) fourth & subsequent floors ditto 2043.35 -- ditto 721.70 -

chapter-7(Brickwork) Page 53

Page 56: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

7 Pacca brick work other than building upto 10ft. (3 m) 21.1 i) The composite rate is to beheight. to reduced by 7% and 14%, if 2nd or

21.5 3rd class bricks are used.i) cement, sand mortar:-

ii) Workshops, godowns,, bins,Ratio 1:2 100Cft. 2154.25 9797.05 cu.m 760.90 3460.30 house type godowns, reservoirs,Ratio 1:3 ditto 2154.25 9231.85 ditto 760.90 3260.70 filter beds, storage tanks, wells,Ratio 1:4 ditto 2154.25 8892.70 ditto 760.90 3140.90 screening chambers, collectingRatio 1:5 ditto 2154.25 8666.65 ditto 760.90 3061.05 tanks, manholes etc. are to beRatio 1:6 ditto 2154.25 8496.50 ditto 760.90 3000.95 treated as masonry other thanRatio 1:7 ditto 2154.25 8387.05 ditto 760.90 2962.30 buildings.Ratio 1:8 ditto 2154.25 8287.90 ditto 760.90 2927.30

ii) lime, cement, sand mortar:- The rate of lime mortar alsoincludes grinding of mortar.

Ratio 1:1:6 100Cft. 2154.25 8595.70 cu.m 760.90 3036.00Ratio 1:1:7 ditto 2154.25 8480.75 ditto 760.90 2995.40Ratio 1:1:8 ditto 2154.25 8388.65 ditto 760.90 2962.85Ratio 1:1:9 ditto 2154.25 8310.95 ditto 760.90 2935.45Ratio 1:1:10 ditto 2154.25 8252.85 ditto 760.90 2914.90

iii) lime, sand mortar 1:2 100Cft. 2154.25 7979.10 cu.m 760.90 2818.20 ditto

8 Add extra labour on item No. 7, for every 10ft.(3 m) 100Cft. 343.20 -- cu.m 121.20 -additional height, or part thereof.

9 Extra labour for arch work in brick masonry, including 100Cft. 781.45 -- cu.m 276.00 - 21.5labour for centring and decentring.

10 Extra for pacca brick work in steining of wells or any other 100Cft. 554.40 859.45 cu.m 195.80 303.55 21.1 The composite rate is to becircular masonry. to reduced by 7% and 14%, if 2nd or

21.4 3rd class bricks are used.

11 Extra labour for profile and flared walls. 100Cft. 190.70 -- cu.m 67.35 -

12 Extra labour for pacca brick work in piers and abutment:-

i) from 10ft. to 20ft. (3 m to 6 m) height 100Cft. 169.40 -- cu.m 59.85 -ii) above 20 ft. (6 m) height. 100Cft. 343.20 -- cu.m 121.20 -

13 Extra for face work (half brick thick) using special bricks 100Cft. 4045.00 cu.m 1428.70 This item is to be executed onlyinstead of first class bricks. under the written permission of

Superintending Engineer.

chapter-7(Brickwork) Page 54

Page 57: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-7(Brickwork) Page 55

Page 58: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

14 Reinforced brick work in lintel of openings, laid in 1:3 Per Cft. 60.60 136.90 cu.m 2140.90 4835.30cement mortar, including all labour, material, forms,moulds, lifting & shuttering, etc, (but excluding cost andlabour of steel reinforcement which shall be paid forseparately).

15 Extra for dressing or chamfering bricks for:-

a) special architectural bricks 100 Nos. 1409.55 - % Nos. 1409.55 -b) all other purposes ditto 704.75 - ditto 704.75 -

16 Perforated pacca brick walling half brick thick, in ground 21.1 The composite rate is to befloors:- to reduced by 7% and 14%, if 2nd or

21.4 3rd class bricks are used.i) mud mortar 100 Sft. 922.10 2221.45 Sqm. 99.20 239.05

ii) cement, sand mortar:-

Ratio 1:2 100 Sft. 1204.90 3117.45 sq.m. 129.65 335.45Ratio 1:3 ditto 1204.90 2975.85 ditto 129.65 320.20Ratio 1:4 ditto 1204.90 2891.40 ditto 129.65 311.10Ratio 1:5 ditto 1204.90 2834.85 ditto 129.65 305.05Ratio 1:6 ditto 1204.90 2795.00 ditto 129.65 300.75Ratio 1:7 ditto 1204.90 2764.40 ditto 129.65 297.45Ratio 1:8 ditto 1204.90 2741.70 ditto 129.65 295.00

iii) lime, cement sand mortar The rate of lime mortar alsoincludes grinding of mortar.

Ratio 1:1:6 100Sft. 1204.90 2817.15 sq.m 129.65 303.15Ratio 1:1:7 100Sft. 1204.90 2787.45 sq.m 129.65 299.95Ratio 1:1:8 100Sft. 1204.90 2766.50 sq.m 129.65 297.70Ratio 1:1:9 100Sft. 1204.90 2745.30 sq.m 129.65 295.40Ratio 1:1:10 100Sft. 1204.90 2733.60 sq.m 129.65 294.15

iv) lime, sand mortar 1:2 100Sft. 1204.90 2660.20 sq.m 129.65 286.25 ditto

17 Add extra labour on item No. 16 for pacca brick work in:-

i) first floor 100Sft. 173.80 - sq.m 18.70 -ii) second floor ditto 396.40 - ditto 42.65 -iii) third floor ditto 627.90 - ditto 67.55 -iv) fourth & subsequent floors ditto 989.25 - ditto 106.45 -

chapter-7(Brickwork) Page 56

Page 59: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

18 Perforated pacca brick walling one brick thick, in ground 21.1 The composite rate is to befloor: to reduced by 7% and 14%, if 2nd or

21.4 3rd class bricks are used.i) mud mortar 100Sft. 1274.60 3869.60 sq.m 137.15 416.35

ii) cement, sand mortar:-

Ratio 1:2 100 Sft. 1813.80 5635.20 sq.m 195.15 606.35Ratio 1:3 ditto 1813.80 5352.60 ditto 195.15 575.95Ratio 1:4 ditto 1813.80 5183.05 ditto 195.15 557.70Ratio 1:5 ditto 1813.80 5070.00 ditto 195.15 545.55Ratio 1:6 ditto 1813.80 4990.25 ditto 195.15 536.95Ratio 1:7 ditto 1813.80 4928.75 ditto 195.15 530.35Ratio 1:8 ditto 1813.80 4880.65 ditto 195.15 525.15

iii) lime, cement, sand mortar:- The rate of lime mortar alsoRatio 1:1:6 100Sft. 1813.80 5034.55 sq.m 195.15 541.70 includes grinding of mortarRatio 1:1:7 ditto 1813.80 4975.55 ditto 195.15 535.35Ratio 1:1:8 ditto 1813.80 4931.00 ditto 195.15 530.60Ratio 1:1:9 ditto 1813.80 4892.15 ditto 195.15 526.40Ratio 1:1:10 ditto 1813.80 4863.65 ditto 195.15 523.35

iv) lime, sand mortar 1:2 100Sft. 1813.80 4725.75 sq.m 195.15 508.50 ditto

19 Add extra labour on item No. 18 for perforated pacca brickwork in:-

i) first floor 100Sft. 257.40 -- sq.m 90.90 -ii) second floor ditto 597.95 -- ditto 211.20 -iii) third floor ditto 938.50 -- ditto 331.50 -iv) fourth & subsequent floors ditto 1532.50 -- ditto 541.30 -

20 Fire brick masonry in fireclay mortar:- 21.1to

i) upto 20 ft. (6.10 m) height including all charges. Per Cft. 23.75 483.65 cu.m 839.20 17083.30 21.2

ii) Extra for every 5 ft. (1.5 m) additional height, or part 100Cft. 343.20 -- ditto 121.20 - A&C No.I dated 2.9.1998thereof.

21 First class brick walling laid in 1:3 cement sand mortar,reinforced with 1" (25 mm) wide 18 gauge hoop iron:- 21.19

i) 4½" (113 mm) thick walling with hoop iron, bonding 6" 100Sft. 1053.35 4685.80 sq.m 113.35 504.20(150 mm) apart.

chapter-7(Brickwork) Page 57

Page 60: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

ii) 4½" (113 mm) thick walling with hoop iron, bonding 100Sft. 959.65 4163.30 sq.m 103.25 447.9512" (300 mm) apart.

iii) 3" (75 mm) thick walling with hoop iron, bonding 6" ditto 827.65 3600.55 ditto 89.05 387.40(150 mm) apart.

iv) 3" (75 mm) thick walling with hoop iron, bonding 12" ditto 662.10 2958.75 ditto 71.25 318.35(300 mm) apart.

22 Ghilafi work (1½ brick thick wall) 100Cft. 1855.80 4858.80 cu.m 655.45 1716.15 21.18

23 Dry brick pitching 100Cft. 1135.20 6157.20 cu.m 400.95 2174.70 21.1

24 Sun dried bricks in mud mortar 100Cft. 1536.50 2352.50 cu.m 542.70 830.90 21.16

25 Pise wall (mud walling) 100Cft. 749.75 -- cu.m 264.80 - 21.17

26 Eave brick moulded, weathered and throated with back 21.1 to 21.2brick or drip course cornice, in 1:3 cement mortar:-

i) 3" (75 mm) thick drip course cornice Rft. 12.40 36.45 Metre 40.65 119.55 correction vide A&C No.I dated 2.9.98ii) 4½" (113 mm) thick drip course cornice. ditto 14.10 64.15 ditto 46.25 210.40iii) 4½" (113 mm) thick eave brick with back brick. ditto 9.10 70.70 ditto 29.85 231.90

27 Laying dressed or moulded brick cornices in 1:6 cement 21.1 to 21.2mortar, plastering or painting complete:-

i) 1 brick Rft. 14.10 21.80 Metre 46.25 71.50ii) 2 bricks ditto 20.85 44.40 ditto 68.40 145.65iii) 3 bricks ditto 27.80 68.90 ditto 91.20 226.00iv) 4 bricks ditto 34.95 90.75 ditto 114.65 297.65

28 Cleaning bricks dismantled from kacha pacca masonry 1,000 406.55 -- 1,000 406.55 -Nos Nos

29 Scraping bricks dismantled from pacca masonry 1,000 766.65 -- 1,000 766.65 -Nos Nos

30 Supplying and filling sand under floor; or plugging in wells. 100Cft. 96.80 1296.80 cu.m 34.20 458.05

31 Providing and laying 2" (50 mm) thick and 15" (375 mm) Rft. 52.80 102.50 Metre 173.20 336.20projected tile band, laid in 1:2 cement sand mortar, withhoop iron 1" (25 mm) wide 18 gauge flat iron sheet 9"apart.

chapter-7(Brickwork) Page 58

Page 61: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

32 First class brick tiles clad by laying tiles in stretcher This item is to be executed onlycourse in cement sand mortar reinforced with 18 SWG under the written permission of thehoop iron strips bonding placed at 2.0' (600 mm) apart Superintending Engineer.horizontally, and at 1.0' (300 mm) interval vertically.

i) 1:3 100Sft. 959.65 4888.55 sq.m 103.25 526.00ii) 1:4 ditto 959.65 4752.90 ditto 103.25 511.40

33 Chamfering sides of head regulators and masonry walls to Per Sft. 28.15 -- sq.m 302.90 -increase width.

34 Replacing kallar eaten bricks Each No. 23.30 26.45 Each 23.30 26.45

35 Repairing corners of bridges and other hydraulic masonry Each No. 140.80 196.25 Each 140.80 196.25works

36 Extra labour for drains of bath rooms, etc. Per Lft. 13.85 -- Metre 45.45

37 Maroo corners Each 88.70 -- Each 88.70 Payable in addition to brick workCorner Corner

chapter-7(Brickwork) Page 59

Page 62: 26467Sahiwal_1st_010

STONE MASONRY1 The composite rates do not include the carriage of stone or spawl which will be paid separately by road and/or rail whichever means of

transport is adopted. The supply and carriage to site of work of all other materials is included in the composite rates.

2 The payment of carriage of stone or spawl will be made on the basis of the actual stack measurement (without any reduction factor) of thestone or spawl carried.

3 Where the stone or spawl is issued from stock and the contractor is paid for its carriage and/or labour only; or where the stone or spawl issupplied, carried or handled by the contractor in which no laying is required, the actual stack measurement (without any reduction factor)shall form the basis of the payment of supply or carriage of stone or spawl. The quantity of finished and completed item of work shall formthe basis of laying.

4 Rates for all finished work include the removal of surplus debris, unused material and byproducts.

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Random, rubble masonry (uncoursed), in foundation and 22.10,plinth: 22.11

a) dry masonry 100 Cft. 1980.00 2730.00 cu.m 699.35 964.25b) in mud mortar 100 Cft. 2475.00 3441.00 cu.m 874.15 1215.35c) in lime, sand mortar 1:2 100 Cft. 3814.80 5596.80 cu.m 1347.40 1976.80d) in cement, sand mortar

i) ratio 1:3 100 Cft. 3814.80 7648.20 cu.m 1347.40 2701.35ii) ratio 1:4 100 Cft. 3814.80 7139.50 cu.m 1347.40 2521.65

iii) ratio 1:6 100 Cft. 3814.80 6557.30 cu.m 1347.40 2316.05iv) ratio 1:8 100 Cft. 3814.80 6235.20 cu.m 1347.40 2202.25

2 Coursed rubble masonry hammer dressed, in foundation 22.8and plinth:

a) dry masonry 100 Cft. 2534.40 3284.40 cu.m 895.15 1160.05b) in mud mortar 100 Cft. 3524.40 4490.40 cu.m 1244.80 1586.00c) in lime, sand mortar 1:2 100 Cft. 4303.20 5970.25 cu.m 1519.90 2108.70d) in cement, sand mortar:

i) ratio 1:3 100 Cft. 4303.20 8064.00 cu.m 1519.90 2848.20ii) ratio 1:4 100 Cft. 4303.20 7611.85 cu.m 1519.90 2688.50

iii) ratio 1:6 100 Cft. 4303.20 7093.65 cu.m 1519.90 2505.50iv) ratio 1:8 100 Cft. 4303.20 6809.85 cu.m 1519.90 2405.25

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-8(Stone masonary) Page 59

Page 63: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

3 Random rubble masonry (uncoursed) in 22.10ground floor or 20 ft.(6 m) height, building/otherthan building.

a) dry masonry 100 Cft. 2257.20 3007.20 cu.m 797.25 1062.15b) in mud mortar 100 Cft. 2970.00 3936.00 cu.m 1049.00 1390.20c) in lime, sand mortar 1:2 100 Cft. 4164.60 5946.60 cu.m 1470.95 2100.35d) in cement, sand mortar:

i) ratio 1:3 100 Cft. 4164.60 7998.00 cu.m 1470.95 2824.90ii) ratio 1:4 100 Cft. 4164.60 7489.30 cu.m 1470.95 2645.20

iii) ratio 1:6 100 Cft. 4164.60 6907.10 cu.m 1470.95 2439.60iv) ratio 1:8 100 Cft. 4164.60 6585.00 cu.m 1470.95 2325.80

4 Coursed rubble masonry hammer dressed, in ground floor 22.8or 20 ft. (6 m) height, building/other than building.

a) dry masonry 100 Cft. 2956.80 3706.80 cu.m 1044.35 1309.25b) in mud mortar 100 Cft. 4369.20 5325.60 cu.m 1543.20 1881.00c) in lime, sand mortar 1:2 100 Cft. 4864.20 6531.25 cu.m 1718.05 2306.85d) in cement, sand mortar:

i) ratio 1:3 100 Cft. 4864.20 8625.00 cu.m 1718.05 3046.35ii) ratio 1:4 100 Cft. 4864.20 8172.85 cu.m 1718.05 2886.65

iii) ratio 1:6 100 Cft. 4864.20 7654.65 cu.m 1718.05 2703.60iv) ratio 1:8 100 Cft. 4864.20 7370.85 cu.m 1718.05 2603.40

5 Ashlar block in course or scabbled masonry (including 22.5dressing, etc.,) in ground floor or 20 ft. (6 m) height, &building/other than building. 22.6

a) in lime, sand mortar 1:2 100 Cft. 13332.00 14982.85 cu.m 4708.85 5291.95b) in cement, sand mortar:

i) ratio 1:3 100 Cft. 13332.00 16350.55 cu.m 4708.85 5775.00ii) ratio 1:4 100 Cft. 13332.00 16011.45 cu.m 4708.85 5655.25

iii) ratio 1:6 100 Cft. 13332.00 15627.10 cu.m 4708.85 5519.50

6 Ashlar fine masonry (including dressing, etc.) in ground 22.3floor or 20 ft. 6 m) height, building/other than building. (A) to

(C) &a) in lime, sand mortar 1:2 100 Cft. 25858.80 27477.05 cu.m 9133.35 9704.90 22.4b) in cement, sand mortar:

i) ratio 1:3 100 Cft. 25858.80 28160.90 cu.m 9133.35 9946.45ii) ratio 1:4 100 Cft. 25858.80 27991.10 cu.m 9133.35 9886.45

iii) ratio 1:6 100 Cft. 25858.80 27803.70 cu.m 9133.35 9820.25

chapter-8(Stone masonary) Page 60

Page 64: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

7 Extra labour on items 3, 4, 5 & 6 above for work in:-

i) first floor 100 Cft. 491.05 - cu.m 173.45 -ii) second floor 100 Cft. 1136.25 - cu.m 401.30 -iii) third floor 100 Cft. 1793.10 - cu.m 633.30 -iv) fourth floor 100 Cft. 2897.65 - cu.m 1023.45 -

8 Extra labour on items 3,4,5 & 6 above for every 5 ft.(1.5 m) 100 Cft. 454.10 - cu.m 160.40 -

additional height, other than building, or part thereof.

9 Extra labour for arch work in stone masonry, including 100 Cft. 1423.40 - cu.m 502.75 - 22.12centering and decentring, etc.

10 Extra labour for:- 22.7

a) coping and caps, etc. 100 Cft. 7983.35 - cu.m 2819.70 -b) cornice & string course 100 Rft. 7983.35 - Rm. 261.85 -

11 Dressing stones:- 22.2i) This rate of dressing shall be paid

a) hammer dressed 100 Sft. 2798.40 - sq.m 301.10 only when the supply of undressedb) rough tooled dressed 100 Sft. 5364.50 - sq.m 577.20 stone is made.c) chisel dressed 100 Sft. 6483.85 - sq.m 697.65 ii) In case of masonry, dressing isd) fine dressed 100 Sft. 13918.10 - sq.m 1497.60 already included and this rate shall

not be added thereto.iii) Only dressed surface of stoneshall be measured.

12 Dhajji walling 5"x5" (125 mmx125 mm) thick deodar 100 Sft. 5195.40 9194.45 sq.m 559.05 989.30 22.13framing with stone laid in 1:6 cement sand mortar, and 1:4cement sand plaster on both sides.

13 Providing and fixing stone blocks from 2 Cft. Per Cft. 192.50 215.95 cu.m 6799.10 7627.35(0.6 cu.m) to 6 Cft (0.17 cu.m). eachincluding lift upto 20 ft. (6 m)

14 Providing and fixing stone blocks, under 2 Per Cft. 113.00 139.50 cu.m 3991.15 4927.15Cft. (06 cu.m) each including lift upto 20 ft.(6 m)

chapter-8(Stone masonary) Page 61

Page 65: 26467Sahiwal_1st_010

ROOFING

Rates for all finished works include the removal of surplus debris unused material and byproducts.

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 First class tile roofing, consisting of 4" (100 mm) earth 100Sft. 3303.15 7556.55 sq.m 355.40 813.10 23.1 Add extra 13%, 32% & 51% onand 1" (25 mm) mud plaster with Gobri leeping over ½" (13 labour rates only or 6%, 15% & 23%mm) thick cement plaster 1:6 with 34 lbs. per %Sft or on composite rates for 2nd, 3rd, 4th1.72 Kg/sq.m hot bitumen coating sand blinded, provided & sub- sequent floors, respectively.over 2 layers of tiles 12"x6"x1¼" (300x150x30 mm) laid in1:6 cement mortar with ½" (13 mm) thick sand wichedlayer of 1:6 cement mortar, including 1:2 cement pointingunderside of tiles, complete, including curing, etc.

2 Second class tile roofing consisting of 4" (100 mm) earth 100Sft. 2502.70 5546.75 sq.m 269.30 596.85 23.2 dittoand 1" (25 mm) mud plaster with Gobri leeping over ½" (13mm) thick cement plaster 1:6 with 34 lbs. per %Sft or1.72 Kg/sq.m of hot bitumen coating sand blinded,provided over one layer of 12"x6"x2" (300x150x50 mm)tiles laid in 1:6 cement mortar, including 1:2 cementpointing underneath of tiles complete including curing, etc.

3 Covering mud roof with coal tar, and fine sand. 100Sft. 139.15 699.25 sq.m 14.95 75.25 23.1 to 23.2 ditto

4 Filling spaces in between:-

a) Wooden battens over beams, filled with 100Sft. 237.60 1268.60 sq.m 25.55 136.50 Add extra 13%, 32% & 51% ondeodar wood pieces (spacers). roof area labour rates only or 6%, 15% &

b) RCC battens, filled with CC block 1:3:6. -ditto- 483.10 719.80 52.00 77.45 23% on composite rates for 2nd,c) Spaces filled with bricks. -ditto- 138.15 374.05 14.85 40.25 3rd, 4th & sub- sequent floors,

respectively.

5 Single layer of tiles 9"x4½"x1½" (225x113x40 mm) laid 100Sft. 785.85 3607.75 sq.m 84.55 388.20 23.1 dittoover 4"(100 mm) earth and 1" (25 mm) mud plaster withoutBhoosa, grouted with cement sand 1:3 on top of RCC roofslab, provided with 34 lbs. per %Sft. or 1.72 Kg/Sq.mbitumen coating sand blinded.

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-9(Roofing) Page 62

Page 66: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

6 Jack arch roofing 4½" (113 mm) thick laid in 1:5 cement 23.3 to For steel part and its erection etc.mortar, including an average depth of 4" (100 mm) cement 23.5 items 10 & 14 under Chapter IRONconcrete in haunches and over crown, with 3" (75 mm) WORK be referred.earth and 1" (25 mm) plaster, soffits of arches cementplaster 1:6 and ½" (13 mm) thick. The rate also includes Add extra 13%, 32% & 51% onbitumen coating, centring, laying skew bricks in cement labour rates only or 6%, 15% & 23%mortar (1:3), and encasing exposed flanges of the joints on composite rates for 2nd, 3rd, 4thwith fine cement concrete 1:2:4 using stone aggregate:- & sub- sequent floors, respectively.

a) cement concrete in haunches 1:6:12. 100Sft. 3579.85 11958.05 sq.m 385.20 1286.70b) cement concrete in haunches 1:3:6. ditto 3579.85 12531.45 ditto 385.20 1348.40

7 Jack arch roofing 4½" (113 mm) thick laid in 1:5 cement 23.3 For steel part and its erection etc.mortar, including an average depth of 4" (100 mm) cement to items 10 & 14 under Chapter IRONconcrete in haunches and over crown, with ½" (13 mm) 23.5 WORK be referred.cement plaster 1:6 on top (except earth filling mud plasterand gobri) soffit of arches cement plastered. The rate also Add extra 13%, 32% & 51% onincludes bitumen coating, centring, laying skew bricks in labour rates only or 6%, 15% & 23%cement sand mortar (1:3), and encasing exposed flanges on composite rates for 2nd, 3rd, 4thof the joints with fine cement concrete 1:2:4 using stone & sub- sequent floors, respectively.aggregate:-

a) cement concrete in haunches 1:6:12. 100Sft. 2898.70 11358.30 sq.m 311.90 1222.15b) cement concrete in haunches 1:3:6. ditto 2898.70 11649.55 ditto 311.90 1253.50

8 Extra for vaulted jack arch roofing. 100Sft. 781.45 sq.m 84.10 - ditto

9 Jack arch roofing of shingle and cement concrete 1:3:6, 100Sft. 3603.60 9153.55 sq.m 387.75 984.90 23.3 ditto

4½" (113 mm) thick at crown, with ½" (13 mm) cement toplaster including cost of supplying, erecting and 23.5dismantling centring.

10 Earth filling over roof including watering, ramming with 1" 23.1 Add extra 13%, 32% & 51% on(25 mm) mud plaster finished, with gobri leeping: to labour rates only or 6%, 15% & 23%

23.3 on composite rates for 2nd, 3rd, 4tha) 3" (75 mm) thick earth filling and 1" (25 mm) mud 100Sft. 313.40 560.30 sq.m 33.70 60.30 & sub- sequent floors, respectively.

plaster

b) 4" (100 mm) thick earth filling and 1" (25mm) 100Sft. 409.20 704.10 sq.m 44.05 75.75mud plaster

11 1/8" (3 mm) thick gobri leeping on roofs or floors. 100Sft. 55.95 68.55 sq.m 6.00 7.40 ditto ditto

chapter-9(Roofing) Page 63

Page 67: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

12 Two coats of bitumen laid hot using 34 lbs. per %Sft, or 100Sft. 232.30 1333.75 sq.m 25.00 143.50 23.11.72 Kg per square metre over roof and blinded with sandat one Cft. per %Sft. (0.003 cu.m per sq.m)

13 Providing & Fixing corrugated galvanized iron sheets with G.I. bolts, 23.7 Add extra 13%, 32% & 51% onnuts, limpet and bitumen washers, wind ties, complete in labour rates only or 6%, 15% & 23%all respects without valleys and ridges:- on composite rates for 2nd, 3rd, 4th

& sub- sequent floors, respectively,a) 20 BWG 100Sft. 475.20 11897.60 sq.m 51.15 1280.20 on items 13 to 18.b) 22 BWG 100Sft. 475.20 10244.40 sq.m 51.15 1102.30c) 24 BWG 100Sft. 475.20 8247.15 sq.m 51.15 887.40

14 Khassi parnalas in cement, sand mortar 1:2, 12" (300 Rft. 39.50 50.30 Metre 129.55 165.00 23.10mm) outside width finished smooth with a floating coat ofneat cement.

15 Khuras on roof 2'x2'x6" (600 x 600 x 150 mm) Each 146.80 265.40 Each Each 265.40 23.10

16 Bottom Khuras of brick masonry in cement mortar 1:6, Each 146.80 360.60 Each 146.80 360.60 23.104'x2'x4½" (1200x600x113 mm) over 3" (75 mm) cement concrete 1:4:8.

17 Plain galvanized iron sheets 22 SWG rain water down pipeincluding clamp and fixing in position.

a) 4" (100 mm) diameter down pipe Per Rft. 30.40 118.85 Metre 99.70 389.85b) 5" (125 mm) diameter down pipe Per Rft. 30.40 138.30 Metre 99.70 453.60

18 Plain galvanized iron sheet flashing, 22 gauge. Per Sft. 30.40 96.75 sq.m 327.10 1041.05 23.11

19 Providing and fixing 1/16" (1.5 mm) thick lead flashing over Per Sft. 7.80 69.25 Sq.m 83.95 745.15roof expansion joint complete in all respects.

20 Cast iron rain water downpipe fixed in position, excluding Add extra 13%, 32% & 51% onheads and shoes, but including painting and clamps, etc:- labour rates only or 6%, 15% & 23%

on composite rates for 2nd, 3rd, 4tha) 4" dia (100 mm) cast iron down pipe. Per Rft. 28.15 173.10 Metre 92.35 567.75 & sub- sequent floors, respectively,b) 3" (75 mm) cast iron down pipe. Per Rft. 28.15 148.55 Metre 92.35 487.25 on items 19 to 24

21 Rain water down pipe cast iron head fixed in place, Each 108.10 379.80 Each 108.10 379.80including cost of clamp holdfast and painting.

chapter-9(Roofing) Page 64

Page 68: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

22 Shoes, bends or offsets for cast iron rain water down pipe, Each 32.35 253.25 Each 32.35 253.25including fixing and painting.

23 Plain GI sheet iron spouts fixed in position, including Each 126.70 219.15 Each 126.70 219.15 23.10painting.

24 Laying ½" (13 mm) thick deodar ceiling complete, 100Sft. 2560.80 10622.40 sq.m 275.55 1142.95 26.1including sawing, planing and fixing.

25 Flat sheet roof with galvanized iron plain sheets, includingbattens, rolls, screws, clips etc. (Planking to be paid forseparately):-

a) 22 BWG sheets roofing 100Sft. 1499.50 11487.10 sq.m 161.35 1236.00 23.60b) 24 BWG sheets roofing 100Sft. 1499.50 10174.95 sq.m 161.35 1094.85

26 Asbestos cement corrugated sheet roofing including 100Sft. 1003.20 4572.00 sq.m 107.95 491.95 23.8

necessary overlaps, and GI hook bolts, nuts, screws,washers and bitumen washers, etc. (excluding valleys andridges, etc).

27 Extra labour for erection of GI sheets, flat sheet or 100Sft. 111.05 -- sq.m 11.95 - 23.6asbestos sheet roofing, above 20' (6.10 m) height indifficult position, including lifting with care and specialscaffolding along live electric wires.

28 Fixing asbestos cement sheet ridges and valleys ¼" Per Rft. 12.15 57.60 Metre 39.85 188.95 23.8(6 mm) thick.

29 Plain galvanized iron sheet ridging, including fixture, 23.6timber for ridge roll and ridge sheeting:-

a) 6" (150 mm) lap and 18" (450 mm) Per Rft. 34.05 249.60 Per Metre 111.70 818.70overall, of 22 gauge G.I sheet ridging.

b) 9" (225 mm) lap and 24" (600 mm) Per Rft. 42.75 247.00 Per Metre 140.20 810.15overall, of 24 gauge G.I sheet ridging.

c) 12" (300 mm) lap and 30" (750 mm) Per Rft. 42.75 303.15 Per Metre 140.20 994.35overall, of 22 gauge G.I sheet ridging.

30 Plain 22 gauge G.I sheet gutter semi circular Per Rft. 21.40 125.40 Per Metre 70.20 411.30 23.118" (200 mm) dia meter.

chapter-9(Roofing) Page 65

Page 69: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

31 Making masonry ventilators in cement, sand Each 563.20 810.35 Each 563.20 810.35mortar 1:4

32 Fixing water spouts or parnalas. Each 168.95 -- Each 168.95 - 23.10

33 Making drip course 2"x½" (50x13 mm) under RCC slab edges Per Rft. 6.80 7.45 Metre 22.30 24.45in outer opening, in cement, sand mortar 1:2.

34 Supplying and laying of twin G.I sheet 20 SWG duly Per Sft. 17.00 248.70 sq.m 182.90 2676.00painted with bitumen, with polythene film in between 300gauge, to provide a sliding joint under the bearing of thebeams, including 3" (75 mm) long, 3/8" (10 mm) dia bar toact as holdfast on wall and beam.

35 Providing and laying roof insulation, comprising of singlelayer of tiles 9"x4½"x1½" (225x113x40 mm) grouted withcement sand mortar 1:3 laid over 2" (50 mm) thick earth(including mud plaster) over thermopore sheet, overpolythene sheet 300 gauge over a layer of bitumen,complete in all respects:-

i) Thermopore sheet ½ " (13 mm) thick 100Sft. 1207.80 4152.90 sq.m 129.95 446.85ii) Thermopore sheet ¾ " (20 mm) thick 100Sft. 1207.80 4278.90 sq.m 129.95 460.40iii) Thermopore sheet 1" (25 mm) thick 100Sft. 1210.55 4407.65 sq.m 130.25 474.25

36 Providing and fixing AC rain water down pipe 4" (100 mm) Rft. 7.15 137.10 Metre 23.45 449.70dia, with shoe, T-bend, clamp, etc.

37 Making jharries in existing brick masonry for providing Rate will be increased by 1.5 timerecesses for bearing of RCC roof slab, including repairing for stone masonry or plain; concrete;the damaged face:- and 2 times for reinforced cement

concrete.i) for slabs upto 6" (150 mm) thick Rft. 11.10 12.10 Metre 36.40 39.70ii) for slabs exceeding 6" to 12" (150 to 300 mm) thick. Rft. 18.10 19.90 Metre 59.35 65.25

38 Making recess in existing brick masonry for bearing of Rates will be increased by 1.5 timesbeam, girder, R.S. Joist, etc. including repairing damaged for stone masonry and plainface:- cement concrete and two times

for reinforced cement concrete.i) upto 1.0' (300 mm) height of girder or beam. Each 46.20 49.50 Each 46.20 49.50

ii) for every 6" (150 mm) additional height or part thereof. Each 22.20 23.75 Each 22.20 23.75

chapter-9(Roofing) Page 66

Page 70: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

39 Hoisting RS. Beams and wooden beams and placing in Each 142.55 - Each 142.55 -position.

40 Hoisting and placing in position sahl ballies, over roof. Each 24.15 - Each 24.15 -

41 Hoisting precast R.C.C/prestressed concretebattens and placing in position.

a) 5' to 6' (1.50 to 1.83 m) long Each 20.35 - Each 20.35 -b) 6' to 7' (1.83 to 2.13 m) long Each 28.50 - Each 28.50 -c) 7' to 8' (2.13 to 2.44 m) long Each 35.65 - Each 35.65 -d) 8' to 9' (2.44 to 2.74 m) long Each 47.50 - Each 47.50 -e) above 9' (2.74 m) length Each 57.00 - Each 57.00 -

42 Hoisting and placing in position R.C. trough: Applicable only to roof trough(inverted tees & trough) for height of

a) upto 10' (3 m) in length Each 57.00 - Each 57.00 - 1st storey only.b) 10' to 11' (3 to 3.36 m) in length ditto 71.30 - ditto 71.30 -c) 11' to 12' (3.36 to 3.66 m) in length ditto 95.05 - ditto 95.05 -d) 12' to 13' (3.66 to 3.96 m) in length ditto 109.65 - ditto 109.65 -e) 13' to 14' (3.96 to 4.26 m) in length ditto 118.80 - ditto 118.80 -f) 14' to 15' (4.26 to 4.57 m) in length ditto 129.60 - ditto 129.60 -g) 15' to 16' (4.57 to 4.88 m) in length ditto 142.55 - ditto 142.55 -h) 16' to 17' (4.88 to 5.19 m) in length ditto 158.40 - ditto 158.40 -i) 17' to 18' (5.19 to 5.49 m) in length ditto 203.65 - ditto 203.65 -j) 18' to 19' (5.49 to 5.80 m) in length ditto 219.30 - ditto 219.30 -k) 19' to 20' (5.80 to 6.10 m) in length ditto 237.60 - ditto 237.60 -

43 Hoisting and placing in position R.C. inverted battens:-

i) upto 10' (3.05 m) span Each 42.90 - Each 42.90 -ii) from 10' to 12' (3.05 to 3.66 m) span ditto 95.35 - ditto 95.35 -iii) from 12' to 13' (3.66 to 3.96 m) span ditto 114.40 - ditto 114.40 -iv) from 13' to 14' (3.96 to 4.26 m) span ditto 143.00 - ditto 143.00 -v) from 14' to 15' (4.26 to 4.57 m) span ditto 156.00 - ditto 156.00 -vi) from 15' to 16' (4.57 to 4.88 m) span ditto 171.60 - ditto 171.60 -vii) from 16' to 18' (4.88 to 5.49 m) span ditto 214.50 - ditto 214.50 -viii) from 18' to 20' (5.49 to 6.10 m) span ditto 343.20 - ditto 343.20 -

44 Reinforced cement concrete spout, including fixing in Each 225.30 421.05 Each 225.30 421.05position, with top and bottom Khurras.

chapter-9(Roofing) Page 67

Page 71: 26467Sahiwal_1st_010

FLOORINGRates for all finished works include the removal of surplus debris, unused material and byproducts

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Laying Murum flooring, consisting of 1"(25 mm) layer of 100 Sft. 1293.60 2512.20 sq.m 139.20 270.30fine powdery or flakey variety of Murum, laid over 6"(150mm) good hard layer of Murum spreaded over 9"(225 mm)thick sub-base comprising of hand packed rubble orbroken bricks properly watered and rammed, provided overwell rammed earth.

2 Earth flooring, consisting of 6"(150 mm) thick consolidated 100 Sft. 432.30 672.30 sq.m 46.50 72.35 24.1layer of moistened earth, including ramming.

3 Providing, laying, watering and ramming brick ballast 1½" 100 Cft. 929.30 2309.30 cum. 328.25 815.65to 2"(40 mm to 50 mm) gauge mixed with 25% sand, forfloor foundation, complete in all respects.

4 Mud flooring, consisting of 6"(150 mm) thick consolidated 100 Sft. 792.00 1161.00 sq.m 85.20 124.90 24.2layer of moistened earth and finished off with 1"(25 mm)mud plaster and gobri leeping.

5 Dry brick paving laid flat, sand grouted, including 100 Sft. 465.70 1856.50 sq.m 50.10 199.75 24.12

preparation of bed by watering, ramming and bringing thesame to proper camber, by ½"(13 mm) thick mud plaster

6 Dry brick on edge paving, sand grouted, including 100 Sft. 830.30 2884.10 sq.m 89.35 310.35 24.12preparation of bed by watering, ramming & bringing thesame to proper camber, by ½ "(13 mm) thick mud plaster

7 Grouting 4½"(113 mm) dry brick work with cement mortar 100 Sft. 454.10 716.40 sq.m 48.85 77.10ratio 1: 5

8 Flat brick flooring laid in 1:6 cement mortar, over a bed of 100 Sft. 797.30 2606.15 sq.m 85.80 280.40 24.43/4" (20 mm) thick cement mortar, 1:6.

9 Brick on edge flooring, laid in 1:6 cement mortar, over a 100 Sft. 1,024.30 3,648.15 sq.m 110.20 392.55 24.4bed of ¾" (20 mm) thick cement mortar 1:6.

10 Brick tiles (12"x6"x2") (300x150x50mm) laid in 1:6 100 Sft. 996.60 2,654.75 sq.m 107.25 285.65 dittocement mortar, over a bed of ¾" (20 mm) thick cementmortar 1:6.

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-10(Flooring) Page 68

Page 72: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

11 Brick ties (9"x4½"x1½")(225 mm x 113 mm x 40 mm) laid 100 Sft. 1,135.20 2,955.85 sq.m 122.15 318.05 24.4flat in 1:3 cement mortar, over a bed of 3/4"(20 mm) thickcement mortar 1:6.

12 Cement tiles (8"x8"x¾")(200 x 200 x 20 mm) laid flat in 100 Sft. 686.25 4,179.20 sq.m 73.85 449.70 24.71:2 cement mortar, over 3/4" (20 mm) thick bed of cementmortar 1:2.

13 Cement concrete tiles laid in 1:2 cement mortar, over 24.83/4" (20 mm) thick bed of cement mortar 1:2:-

(a) 12"x12"x1" (300 x 300 x 25 mm) 100 Sft. 686.25 2,804.85 sq.m 73.85 301.80 (b) 9"x9"x¾" (225 x 225 x 20 mm) ditto 686.25 3,751.05 ditto 73.85 403.60 (c) 6"x6"x¾"(150 x 150 x 20 mm) ditto 686.25 5,340.60 ditto 73.85 574.65

14 Coloured cement tiles (8"x8"x¾")(200 x 200 x 20 mm) of 100 Sft. 686.25 4,204.40 sq.m 73.85 452.40 24.7

approved dark shade laid flat in 1:2 cement mortar, over ¾" (20 mm) bedding mortar of 1:2.

15 Providing and laying topping of cement concrete 1:2:4, 24.9 If glass or marble strips are usedincluding surface finishing and dividing in panels:- for panelling, it will be paid extra as

per item No. 41 or 42. (a) 1"(25 mm) thick 100 Sft. 834.25 1,520.65 sq.m 89.75 163.60 (b) 1¼"(30 mm) thick ditto 834.25 1,670.15 ditto 89.75 179.70 (c) 1½"(40 mm) thick ditto 993.95 1,979.40 ditto 106.95 213.00 (d) 1¾"(45 mm) thick ditto 993.95 2,139.00 ditto 106.95 230.15 (e) 2"(50 mm) thick ditto 1,153.70 2,479.90 ditto 124.15 266.85 (f) 2¼"(56 mm) thick ditto 1,182.70 2,653.70 ditto 127.25 285.55 (g) 2½"(62 mm) thick ditto 1,313.40 2,858.60 ditto 141.30 307.60 (h)2¾"(70 mm) thick ditto 1,313.40 3,091.90 ditto 141.30 332.70 (i) 3"(75 mm) thick ditto 1,313.40 3,266.45 ditto 141.30 351.45

16 Providing and laying conglomerate flooring (two coat work) 24.10 If glass or marble strips are used

with top layer of ½"(13mm) thick wearing surface, for panelling, it will be paid extra asconsisting of one part of cement and 2 parts of stone per item No. 41 or 42.chips passing 3/16"(6 mm) sieve, over bottom layer ofcement concrete 1:3:6, including surface finishing anddividing in panels:-

(a) 1½"(40 mm) thick 100 Sft. 1,207.80 2,130.45 sq.m 129.95 229.25 (b) 1¾"(45 mm) thick ditto 1,207.80 2,222.20 ditto 129.95 239.10 (c) 2"(50 mm) thick ditto 1,499.50 2,682.40 ditto 161.35 288.65

chapter-10(Flooring) Page 69

Page 73: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

17 Add extra in cement concrete floor topping, if finished with 100 Sft. 281.60 630.50 sq.m 30.30 67.85pigment and polishing.

18 Extra labour for each storey above ground, for mosaic, 100 Sft 174.25 - sq.m 18.75 - On items 19-25 & 29-34conglomerate, tiles, stone and wooden floor.

19 Flag stone flooring in lime mortar 1:2, over ¾"(20 mm) 24.5bedding mortar, in platforms and floors, etc.

(a) 2"(50 mm) thick 100 Sft. 2,363.35 3,674.70 sq.m 254.30 395.40 (b) 3"(75 mm) thick ditto 2,363.35 3,957.85 ditto 254.30 425.85

20 Asphalt flooring , including preparation of proper base 24.10remelting, setting out, and finishing complete:-

(a) 1"(25 mm) thick topping 100 Sft. 825.00 10,342.60 sq.m 88.75 1112.85 (b) ½"(13 mm) thick topping ditto 652.10 5,513.05 ditto 70.15 593.20 (c) ¼"(6 mm) thick topping ditto 490.25 3,009.70 ditto 52.75 323.85

21 13/8"(35 mm) thick mosaic flooring, consisting of 3/8"(10 If glass or marble strips are usedmm) mosaic topping of one part of cement and marble for panelling, it will be paid extra aspowder in the ratio of 3:1 and two parts of marble chips, per item No. 41 or 42.laid over 1"(25 mm) thick flooring of 1:2:4 cement concreteincluding rubbing and polishing complete :-

(a) using grey cement 100 Sft. 3,222.90 4,801.95 sq.m 346.80 516.70 (b) using white cement ditto 3,222.90 4,973.45 ditto 346.80 535.15

22 1½"(40 mm) thick mosaic flooring, consisting of ½ "(13 If glass or marble strips are used

mm) mosaic topping of one part of cement and marble for panelling, it will be paid extra aspowder in the ratio of 3:1 and two parts of marble chips, per item No. 41 or 42.laid over 1"(25 mm) thick floor of 1:2:4 cement concrete,including rubbing and polishing complete with finishing :-

(a) using grey cement 100 Sft. 3,222.90 4,887.00 sq.m 346.80 525.85 (b) using white cement ditto 3,222.90 5,302.05 ditto 346.80 570.50

23 Providing and laying floor of mosaic marble chips tiles 100 Sft. 1,931.95 5,079.10 sq.m 207.90 546.50 24.81"(25 mm) thick of approved quality and shade, laid inwhite cement and pigment, over ¾"(20 mm) thick beddingof cement sand mortar 1:2, including finishing andpolishing, complete.

chapter-10(Flooring) Page 70

Page 74: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

24 Laying floor of approved white glazed tile ¼" (6 mm) thick 100 Sft. 2,415.60 6,696.80 sq.m 259.90 720.60 24.7in white cement 1:2 over ¾" (20mm) thick cement mortar1:2, complete.

25 Laying floor of approved coloured glazed tiles ¼ "(6 mm) 100 Sft. 2,415.60 6,986.60 sq.m 259.90 751.75 dittothick, laid in white cement and pigment on a bed of ¾"(20 mm) thick cement mortar 1:2.

26 Rubbing and polishing old grit/ mosaic floor, including 100 Sft. 575.50 695.95 sq.m 61.90 74.90 The composite rate will be reducedrepairing voids, uneven surface, complete in all respects. by Rs. 150.00 per % Sft or Rs.13.95 per

Sq. metre respectively, if nopolishing is done.

27 Rubbing and polishing grit floor, including repairing voids, 100 Sft. 610.35 732.40 sq.m 65.65 78.80 The composite rate will be reduceduneven surface, complete in all respects by Rs. 150.00 per % Sft or Rs.13.95 per

Sq. metre respectively, if nopolishing is done.

28 Cleaning and washing mosaic or marble floor with caustic 100 Sft. 115.65 157.35 sq.m 12.45 16.95 24.6soda mixture.

29 Shisham wood boarding or strip flooring 3/4" (20mm) thick 100 Sft. 2,002.00 25,254.95 sq.m 215.40 2717.45 24.13(sawn to required size) tongued and grooved or splayedrebated fixed with brass screws on deodar wood battens1½ "x2"(40 x 50 mm),size placed at 12"(300 mm) centreto centre, including two coats of bitumen laid hot on thebase.

30 Deodar wood boarding or strip flooring 3/4" (20 mm) thick 100 Sft. 2,138.40 24,259.10 sq.m 230.10 2610.30 ditto(sawn to required size) tongued and grooved or splayedrebated fixed with brass screws on deodar wood battens1½"x2"(40 x 50 mm) size , placed at 12"(300 mm) centre,to centre including two coats of bitumen laid hot on thebase.

31 Teak wood boarding or strip flooring ½" (13 mm) "thick 100 Sft. 1,892.00 37,150.30 sq.m 203.60 3997.35 ditto(sawn to required size) to tongued and grooved screwedon deodar wood battens 1½ " x2"(40 x 50 mm) size,placed at 12"(300 mm) centre to centre, including 2 coatsof bitumen laid hot on base.

chapter-10(Flooring) Page 71

Page 75: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

32 Shisham wood block flooring 1"(25 mm) thick cut to 100 Sft. 1,993.20 30,893.45 sq.m 214.45 3324.15 24.13required size, fixed on a layer of asphalt bitumen laid onbase.

33 Teak wood block 1"(25 mm) thick cut to required size, 100 Sft. 1,892.00 67,727.50 sq.m 203.60 7287.50 dittofixed on a layer of asphalt bitumen laid on base.

34 Laying wooden paving of hard wood on edge in coal tar dittoand asphalt:- 100 Sft. sq.m

Per Inch per cm (a) Shisham wood thickness 1,232.00 19,179.45 thickness 132.55 2063.70 (b) Kikar wood ditto 1,232.00 10,082.25 ditto 132.55 1084.85

35 Tile skirting laid in 1:2 cement mortar, over ¾"(20 mm)thick cement mortar, 1:2 including cement washing andfilling joints complete:-

(a) cement tiles 100 Sft. 1,126.40 4,845.30 sq.m 121.20 521.35 (b) mosaic tiles ditto 1,907.40 6,843.50 ditto 205.25 736.35

36 Providing grey cement skirting or dado 3/8"(10 mm) thickincluding rounding of corner and straight ening of top edgeand finishing to smooth surface afterplastering :-

(a) 1:2 cement, sand mortar 100 Sft. 1,536.25 1,851.95 sq.m 165.30 199.25 (b) 1:3 cement, sand mortar ditto 1,536.25 1,763.30 ditto 165.30 189.75 (c) Extra if skirting or dado is finished ditto 72.60 301.10 ditto 7.80 32.40 with pigment of any colour.

37 White glazed tile (6"x6"x¼") (6 mm) thick dado jointed in white 100 Sft. 2,983.20 7,264.40 sq.m 321.00 781.65 24.7cement and laid over 1:2 cement sand mortar 3/4" (20mm)thick, including finishing.

38 Coloured glazed tile dado (6"x6"¼") (6mm) thick in pigment over 1:2 100 Sft. 2,983.20 7,539.20 sq.m 321.00 811.20 dittocement, sand mortar 3/4"(20mm) thick, including finishing.

39 Mosaic dado or skirting with one part of cement andmarble powder in the ratio of 3:1 and two parts of marblechips, laid over ½"(13 mm) thick cement plaster 1:3,including rubbing and polishing, complete with finishing:

(a) using grey cement: i) 3/8"(10 mm) thick 100 Sft. 3,762.00 4,635.50 sq.m 404.80 498.80 ii) ½"(13 mm) thick ditto 3,762.00 5,084.40 ditto 404.80 547.10

chapter-10(Flooring) Page 72

Page 76: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

(b) using white cement :

'i) 3/8"(10 mm) thick 100 Sft. 3,762.00 5,144.20 sq.m 404.80 553.50 ii) ½"(13 mm) thick ditto 3,762.00 5,316.00 ditto 404.80 572.00

40 Rubber flooring, consisting of 12"x12"x1/8" Per Sft. 9.90 66.90 sq.m 106.50 719.85 24.14 The cost of base for rubber flooring(300x300x3mm) rubber tiles, laid on firm foundation. is not included in the rate and is

payable separately.

41 Providing and fixing glass strip 5mm thick and 1½" Per Rft. - 3.95 Metre - 12.95 Labour for fixing already included in(40 mm) wide, for dividing the mosaic flooring into panels. items No. 15, 16, 21and 22 of this

Chapter.

42 Providing and fixing marble strip of any shade for dividingthe mosaic flooring into panels

a) sSize 1½" x 3/8" (40 x 10 mm) Per Rft. - 5.30 Metre - 17.40b) sSize 1½" x ¼" (40 x 6 mm) ditto - 3.70 ditto - 12.15

chapter-10(Flooring) Page 73

Page 77: 26467Sahiwal_1st_010

SURFACE RENDERING1 PLASTERING, POINTING, WHITE WASHING, COLOUR WASHING AND DISTEMPERING, ETC.2 Rates for all finished works include the removal of surplus debris, unused material and byproducts

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Mud plaster on walls (excluding Gobri leeping) upto 20' 25.7(6.00 m) height:-

a) ½" (13 mm) thick 100 Sft. 203.15 267.95 sq.m 21.85 28.85b) 1" (25 mm) thick ditto 279.20 408.80 ditto 30.05 44.00

2 Mud plaster on floor or roof (excluding Gobri leeping):- ditto Add extra 13%, 32% and 51% above

the labour rates only or 6%, 15% &a) ½" (13 mm) thick 100 Sft. 182.70 247.50 sq.m 19.65 26.65 23% on the composite rates for 2nd,

3rd, 4th and subsequenct floors,b) 1" (25 mm) thick ditto 182.70 312.30 ditto 19.65 33.60 respectively.

3 Cement lime plaster 1:7:12 (cement, lime and sand) upto 25.1 to 25.620' (6.00 m) height.

a) ¼" (6 mm) thick 100 Sft. 623.05 707.70 sq.m 67.05 76.15

b) ½" (13 mm) thick ditto 623.05 792.30 ditto 67.05 85.25

4 Cement Neru plaster 1:2 (cement and sand) upto 20' ditto(6.00 m) height:-

a) ¼" (6 mm) thick 100 Sft. 623.05 870.85 sq.m 67.05 93.70b) ½" (13 mm) thick ditto 623.05 1031.70 ditto 67.05 111.00

5 2" (50 mm) stucco cement plaster 1:2:4 (cement, sand 100 Sft. 1442.50 2920.40 sq.m 155.20 314.25 ditto

and shingle) upto 20' (6.00 m) height.

6 Providing and laying machine sprayed plaster ½" (13 mm) dittothick, using cement and chips zero gauge, over theexisting plastered and roughened surface, upto 20' (6.00m) height:-

i) ratio 1:1 100 Sft. 599.40 1511.85 sq.m 64.50 162.70ii) ratio 1:1½ ditto 599.40 1479.70 ditto 64.50 159.20iii) ratio 1:2 ditto 599.40 1461.00 ditto 64.50 157.20

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-11(Surface Rendering) Page 74

Page 78: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

7 Cement plaster 1:2 upto 20' (6.00 m) height:- 25.1to

a) 3/8" (10 mm) thick 100 Sft. 623.05 938.75 sq.m 67.05 101.00 25.6b) ½" (13 mm) thick ditto 623.05 1031.05 ditto 67.05 110.95c) ¾" (20 mm) thick ditto 792.00 1423.40 ditto 85.20 153.15

8 Cement plaster 1:3 upto 20' (6.00 m) height:- ditto

a) 3/8" (10 mm) thick 100 Sft. 623.05 850.05 sq.m 67.05 91.45b) ½" (13 mm) thick ditto 623.05 925.75 ditto 67.05 99.60c) ¾" (20 mm) thick ditto 792.00 1246.05 ditto 85.20 134.10

9 Cement plaster 1:4 upto 20' (6.00 m) height:- ditto

a) 3/8" (10 mm) thick 100 Sft. 623.05 828.65 sq.m 67.05 89.15b) ½" (13 mm) thick ditto 623.05 883.50 ditto 67.05 95.05c) ¾" (20 mm) thick ditto 792.00 1197.25 ditto 85.20 128.80

10 Cement plaster 3/8" (10 mm) thick under soffit of R.C.C. ditto i) This item shall be applicable toroof slabs only, upto 20' height. buildings meant for human

habitation only, such as buildingslike residences, offices,

a) 1:2 100 Sft. 733.90 1109.75 sq.m 78.95 119.40 educational institutions andb) 1:3 ditto 733.90 1020.45 ditto 78.95 109.80 hospitals, etc. It shall not bec) 1:4 ditto 733.90 999.05 ditto 78.95 107.50 admissible on godowns; bins;

agriculture, poultry and animalsheds; cycle stands; garrages; etc.ii) The thickness of the plaster willnot be more than 3/8" (10 mm)thick.

11 Cement plaster 1:5 upto 20' (6.00 mm) height:- 25.1 to 25.6

a) 3/8" (10 mm) thick 100 Sft. 623.05 807.85 sq.m 67.05 86.95b) ½" (13 mm) thick ditto 623.05 849.60 ditto 67.05 91.40c) ¾" (20 mm) thick ditto 792.00 1161.60 ditto 85.20 125.00

12 Cement plaster 1:6 upto 20' (6.00 mm) dittoheight:-a) 3/8" (10 mm) thick 100 Sft. 623.05 778.10 sq.m 67.05 83.70b) ½" (13 mm) thick ditto 623.05 828.75 ditto 67.05 89.15c) ¾" (20 mm) thick ditto 792.00 1102.10 ditto 85.20 118.60

chapter-11(Surface Rendering) Page 75

Page 79: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

13 Applying floating coat of cement 1/32" (0.8 mm) thick. 100 Sft. 413.95 533.00 sq.m 44.55 57.35 25.4 to 25.6

14 Lime pointing flush upto 20' (6.00 m) height including 100 Sft. 454.10 516.00 sq.m 48.85 55.50 25.8raking joints, in lime, sand mortar 1:2.

15 Lime pointing struck joints on walls, upto 20' (6.00 m) 100 Sft. 733.90 795.85 sq.m 78.95 85.65 dittoheight, including raking joints in lime sand mortar 1:2.

16 Cement pointing flush upto 20' (6.00 m) heihgt:- ditto

a) ratio 1:2 100 Sft. 623.05 858.90 sq.m 67.05 92.40b) ratio 1:3 ditto 623.05 807.75 ditto 67.05 86.90

17 Cement pointing 1:2 flush on floor. 100 Sft. 454.10 689.95 sq.m 48.85 74.25 ditto

18 Cement pointing struck joints, on walls, upto20' (6.00 m) hiehgt:-

a) ratio 1:2 100 Sft. 733.90 969.80 sq.m 78.95 104.35b) ratio 1:3 ditto 733.90 918.60 ditto 78.95 98.85

19 Pointing flush on stone work, upto 20' (6.00 m) height. 25.8

a) in lime mortar 1:2 (lime, sand) 100 Sft. 617.75 697.75 sq.m 66.45 75.10b) in cement mortar 1:3 ditto 617.75 802.45 ditto 66.45 86.35c) on stone work raised:-

i) in lime mortar 1:2 100 Sft. 1177.45 1257.40 sq.m 126.70 135.30ii) in cement mortar 1:3 ditto 1177.45 1362.15 ditto 126.70 146.55

20 Raking and washing joints of stone masonry 100 Sft. 285.10 - sq.m 30.70 - ditto

(old work).

21 Raking and washing joints of brick masonry (old work). 100 Sft. 142.55 - sq.m 15.35 - ditto

22 Priming coat of chalk under distemper. 100 Sft. 67.60 73.05 sq.m 7.25 7.85 25.11

23 Distempering:- ditto

a) new surface:-i) one coat 100 Sft. 63.35 137.70 sq.m 6.80 14.80ii) two coats ditto 93.65 190.45 ditto 10.10 20.50iii) three coats ditto 123.90 243.20 ditto 13.35 26.15

chapter-11(Surface Rendering) Page 76

Page 80: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

b) old surface:- i) one coat 100 Sft. 57.75 109.55 sq.m 6.20 11.80ii) two coats ditto 93.65 145.45 ditto 10.10 15.65

24 Colour washing:- 25.10

a) new surface:- i) one coat 100 Sft. 48.15 67.25 sq.m 5.20 7.25ii) two coats ditto 72.25 99.85 ditto 7.75 10.75

b) old surface:-

i) one coat 100 Sft. 48.15 58.80 sq.m 5.20 6.35ii) two coats ditto 72.25 89.55 ditto 7.75 9.65

25 White washing:- 25.9

a) new surface:- i) one coat 100 Sft. 48.15 62.60 sq.m 5.20 6.75ii) two coats ditto 72.25 93.85 ditto 7.75 10.10iii) three coats ditto 93.45 122.25 ditto 10.05 13.15

b) old surface:-

i) one coat 100 Sft. 48.15 59.00 sq.m 5.20 6.35ii) two coats ditto 72.25 90.25 ditto 7.75 9.70

26 Gobri leeping:- 25.7

a) on walls 100 Sft. 80.45 84.05 sq.m 8.65 9.05b) over roofs ditto 67.15 70.75 ditto 7.25 7.60

27 Striking joints of burnt bricks in lime or cement mortar. 100 Sft. 110.90 - sq.m 11.95 - 25.8 Payable with fresh masonry, when

the face of the work is not to be plastered/pointed.

28 Extra for lime, mud or cement plaster and pointing from 100 Sft. 111.30 - sq.m 12.00 -20' (6.00 m) and above for each additional 10' (3.00 m) height or part thereof.

29 Caulking joints of sleeper wall, with sand and coaltar. 100 Sft. 258.70 597.75 sq.m 27.85 64.30

30 Caulking joints of sleepers, withmud and chopped straw. 100 Sft. 258.70 281.50 sq.m 27.85 30.30

31 Extra cost of labour and material for red oxide pigment in 100 Sft. 89.10 181.50 sq.m 9.60 19.55

cement pointing to match with the colour of bricks.

chapter-11(Surface Rendering) Page 77

Page 81: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

32 Providing grooved cement sand plaster 1:3 over existingplastered and roughened surface upto 20' (6.00 m) height.

i) 3/8" (10 mm) thick 100 Sft. 733.90 960.95 sq.m 78.95 103.40ii) ½" (13 mm) thick ditto 733.90 1036.60 ditto 78.95 111.55

33 Providing and fitting expanded metal edge bead for Rft. 4.25 29.70 Metre 13.95 97.40corners, with nails on both sides of edges.

34 Petty repairs to fire place.

i) Single Each 118.25 145.45 Each 118.25 145.45ii) Double Each 236.55 290.85 Each 236.55 290.85

Area above 100 Sft (10.76 sq.m)35 Petty repair to main rooms. Each 237.35 310.65 Each 237.35 310.65

Area upto 100 Sft (10.76 sq.m)36 Petty repair to small rooms. Each 118.65 155.30 Each 118.65 155.30

37 Petty repair to verandah. Each 237.35 295.90 Each 237.35 295.90The height will be taken from the

38 Extra labour for white washing, colour washing, priming coat 100 Sft. 8.05 - sq.m 0.85 - floor, roof or ground uderneath asand distempering, etc. from 20' (6.00 m) height and above, Per Per the case may be on the siderequiring scaffolding, for every additional 10' (3.00m) height coat coat towards which the work is to beor part thereof. done.

chapter-11(Surface Rendering) Page 78

Page 82: 26467Sahiwal_1st_010

WOOD WORK1 No extra rate is to be paid for sawing as the rates are inclusive of these2 Rates for all finished works include the removal of surplus debris, unused material and byproducts.

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Plain wood work sawn, wrought, planed and fixed 26.1inposition, including cost of nails and screws etc.

a) Deodar wood Per Cft. 355.20 2166.00 cu.m 12545.65 76503.10b) Shisham wood ditto 400.40 2211.55 ditto 14142.15 78111.95

2 Plain wood work for regulation karries or needles, etc. 26.1including sawing, planning, wroughting wood and providingand fixing steel parts of karries i.e. end strip and rods, etc.

a) Deodar wood Per Cft. 224.25 2094.60 cu.m 7920.50 73981.25b) Shisham wood ditto 224.25 2094.55 ditto 7920.50 73979.50

3 First class teak wood wrought joinery in doors and 26.1windows, etc. panelled, panelled and glazed or fully toglazed and fixed in position, including chowkat, holdfast, 26.3tower bolt, chocks, rubber stop, cleats/G.I. clamps, &chords with hooks, nails, screws, etc. complete 26.7(excluding sliding bolt and lock):-

i) 2" (50 mm) thick Per Sft. 60.40 1224.25 sq.m 649.90 13172.95ii) 1¾" ( 45 mm) thick ditto 60.40 1140.25 ditto 649.90 12269.10iii) 1½" (40 mm) thick ditto 60.40 1058.20 ditto 649.90 11386.25

4 First class teak wood wrought joinery in wire gauze doors 26.8 i) This also includes the cost ofand windows with frames 22 SWG galvanized iron wire to wood required for extra thickness ofgauze 12x12 meshes to square inch, (5x5 meshes in cm2) 26.10 chowkat.including brass fittings, sash bars, etc. complete:- ii) If 24 SWG wire gauge is used,

the composite rate shall bea) teak wood framing 1¾" (45 mm) thick with wire gauze reduced by Rs.4.70 per sft. and

fixed in position:- Rs.50.60 per sq.m.

i) without springs or spring hinges. Per Sft. 11.10 506.35 sq.m 119.45 5448.35

ii) with springs or spring hinges ditto 11.10 509.90 ditto 119.45 5486.50

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-12(Wood Work) Page 79

Page 83: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

b) teak wood framing 1½" (40 mm) thick, with wiregauze fixed in position:-i) without springs or spring hinges. Per Sft. 11.10 466.35 sq.m 119.45 5017.95ii) with springs or spring hinges. ditto 11.10 470.25 ditto 119.45 5059.90

c) G.I. wire gauze 22 SWG, 12x12 meshes per square Per Sft. 20.00 143.10 sq.m 215.20 1539.75

inch, (5x5 meshes per cm2) fixed to chowkat with ¾"(20 mm) teak wood strips and screws.

d) G.I. wire gauze 22 SWG, 12x12 meshes per square Per Sft. 18.75 479.55 sq.m 201.75 5159.95inch (5x5 meshes per cm2) fixed with ½" (13 mm) stripon separate frame of teak wood 2"x2" (50x50 mm),for windows, etc.

5 P/F expanded metal ½" to ¾" (13 to 20 mm) mesh, 16 Per Sft. 24.35 237.10 sq.m 262.00 2551.20Guage, fixed to chowkat with 1" (25 mm) teak wood coverstrips and screw etc., complete.

6 Providing and fixing expanded metal ½" (13 mm) to ¾" Per Sft. 25.05 358.10 sq.m 269.55 3853.1520 mm), 16 gauge, fixed to chowkat with 1" (25 mm)covermoulding and screws, including teak wood frame 2"x2" (50 mm x 50 mm)

7 First class deodar wood wrought joinery in doors and 26.1 towindows, etc. panelled, or panelled or glazed, or fully 26.3 & 26.7glazed, fixed in position, including chowkat, holdfast, hinges, tower bolts, chocks, rubber stop, cleats/G.I. clamps, handles and chord with hooks, etc. complete (excluding sliding bolt or lock):-

a) 2" thick (50 mm) Per Sft. 60.15 755.75 sq.m 647.20 8131.85b) 1¾" thick (45 mm) ditto 60.15 706.05 ditto 647.20 7597.20c) 1½" thick (40 mm) ditto 60.15 671.50 ditto 647.20 7225.35

8 Deodar wood framed, braced and battened doors and 26.1, 26.2windows, complete with iron fittings and fixed in position, & 26.4including chowkats:-

a) 2¼" (56 mm) thick, with 1¼" (30 mm) Per Sft. 67.25 397.10 sq.m 723.60 4272.80battens and 1" (25 mm) planks.

b) 1¾" (40 mm) thick with 1" (25 mm) ditto 61.60 345.60 ditto 662.80 3718.65battens and ¾" (20 mm) planks.

chapter-12(Wood Work) Page 80

Page 84: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

9 1" (25 mm) thick battneded doors and windows fitted in Per Sft. 78.30 229.65 sq.m 842.50 2471.05position, complete with iron fittings, without chowkats.

10 Deodar battened ledged and braced doors and windows 26.1, 26.22¼" (56 mm) thick (1¼" (30 mm) thick ledge braces and 26.4 to1" (25 mm) thick battens complete with iron fittings, Per Sft. 72.45 389.25 sq.m 779.55 4188.35 26.6chowkats and fixed in position.

11 a) Deodar wood framed with braces and 22 SWG G.I. 26.1, 26.2 If 24 gauge G.I. sheet is used, the

sheet facing, including holdfast, wooden beadings, & 26.4 composite rate will be reduced byhinges, and locking arrangements as directed by the Re.4.70 per Sft. (Rs. Per 50.60

Engineer incharge:- Sq.m) for G.I. facing on one sideand Rs.9.40 per Sft. (Rs.101.20

i) G.I. sheet facing on one side. Per Sft. 31.45 391.90 sq.m 338.40 4216.85 per Sq.m) for G.I. sheet facing onii) G.I. sheet facing on both sides. ditto 34.75 412.15 ditto 373.90 4434.75 both sides.

b) Partal wood framed with braces and 22 SWG G.I.sheet facing, including holdfast, wooden beadings, -ditto-hinges and locking arrangements, as directed by theEngineer-in-charge:-

i) G.I. sheet facing on one side. Per Sft. 31.45 168.80 sq.m 338.40 1816.30ii) G.I. sheet facing on both sides. ditto 34.75 189.05 ditto 373.90 2034.20

12 First class deodar wood wrought joinery work in wire 26.8 to i) This also includes the cost ofgauze doors and windows, with 22 SWG G.I. wire gauze, 26.10 wood required for extra thickness12x12 meshes per square inches (5x5 per cm2) including of chowkat.iron fittings etc. complete:-

ii) If 24 SWG wire gauze is useda) deodar wood framing 1¾" (45 mm) thick with wire the composite rate shall be

gauze fixed in position:- reduced by Rs.4.70 per sft orRs.50.60 per sq.m.

i) without springs or spring hinges. Per Sft. 33.35 325.90 sq.m 358.85 3506.70ii) with springs or spring hinges. ditto 33.35 329.80 ditto 358.85 3548.65

b) deodar wood framing 1½" (40 mm) thick, with wiregauze fixed in position:-i) without springs or spring hinges Per Sft. 33.35 302.80 sq.m 358.85 3258.15ii) with springs or spring hinges ditto 33.35 305.55 ditto 358.85 3287.70

c) G.I. wire gauze 22 SWG, 12x12 meshes per squareinch, (5x5 in cm2) fixed to chowkat, with ¾" Per Sft. 25.05 106.65 sq.m 269.55 1147.55('20 mm) thick deodar wood strip and screws.

chapter-12(Wood Work) Page 81

Page 85: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

d) G.I. wire gauze 22 SWG 12x12 meshes per squareinch, (5x5 meshes in cm2) fixed to chowkat, with ½" Per Sft. 37.55 278.20 sq.m 404.05 2993.45(13 mm) strip on separate frame of deodar wood 2" x2" (50 mm x 50 mm).

13 Making and fixing trellis doors and windows of deodar Per Sft. 55.00 263.80 sq.m 591.80 2838.50 26.1wood, complete. 26.2

14 Providing and fixing mild steel chowkat of doors, windows,C.window, etc. including holdfast, making and threadingholes for hinges, etc. complete:-

a) M.S. angle iron 1½"x 1½"x ¼" (40x40x6 mm) welded Per Sft. 14.45 94.55 sq.m 155.50 1017.35with M.S. flat 2"x ¼" (50 mm x 6 mm)

b) M.S. tee iron 1½"x 1½"x ¼" (40x40x6 mm) welded Per Sft. 14.45 71.80 sq.m 155.50 772.55with M.S. flat 2"x ¼" (50 mm x 6 mm)

15 Providing and fixing M.S. sheet hollow pressed frame ofdoors, windows, C. windows, etc. (chowkat only) of 20SWG welded with M.S. flat 6"x 1¼" x 1/8" (150mmx30mmx3mm) M.S. holdfast 9"x1"x1/8"(225mmx25mmx3mm) welded/screwed 4" (100 mm) longiron hinges, including filling chowkat with cement sandmortar 1:8 and embedding holdfast in cement concrete1:2:4, complete in all respects:

a) single rebate Per Sft. 19.10 95.65 sq.m 205.50 1029.20b) double rebate ditto 22.85 109.75 ditto 245.85 1180.90

16 Extra for providing and fixing iron double spring hinges, Per Sft. 1.85 30.50 sq.m 19.90 328.20 26.2with brass fittings (it shall include brass finger plate, 6" door area door area(150 mm) tower bolt).

17 Providing and fixing brass spring hinges to wire gauzed Each 38.95 158.95 Each 38.95 158.95doors.

18 Providing and fixing sliding bolt to doors:-

i) iron sliding bolt, 10" (250 mm) long Each 37.55 85.55 Each 37.55 85.55ii) iron sliding bolt, 12" (300 mm) long ditto 37.55 121.55 ditto 37.55 121.55iii) brass sliding bolt, 10" (250 mm) long ditto 37.55 127.55 ditto 37.55 127.55iv) brass sliding bolt, 12" (300 mm) long ditto 37.55 289.55 ditto 37.55 289.55

chapter-12(Wood Work) Page 82

Page 86: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

19 Extra for brass fittings to doors and windows, except forhinges, which shall be of iron:-

i) deodar wood panelled or panelled and Per Sft. 1.10 9.95 sq.m 11.85 107.05glazed or fully glazed.

ii) deodar wood wire gauzed shutters. ditto 1.10 7.30 ditto 11.85 78.55

20 Extra for providing and fixing approved quality rim lock Each 118.15 305.35 Each 118.15 305.35adjustable over the style surface.

21 Providing and fixing, approved quality mortice lock. Each 165.00 349.80 Each 165.00 349.80

22 Providing and fixing, expended metal ½" to ¾" (13 mm to20 mm) mesh 16 gauge.

a) fixed to chowkat with 1" (25 mm) thick deodar wood Per Sft. 24.35 166.05 sq.m 262.00 1786.70strip and screws, etc.

b) fixed with 1" (25 mm) cover moulding and screws, ditto 25.05 235.75 ditto 269.55 2536.65including deodar wood frame 2"x2" (50 x 50 mm)

23 a) Providing and fixing deodar wood almirah 9" to 12" For hollow frame shutter with(225 mm to 300 mm) depth, including boxing with Per Sft. 82.30 1081.20 sq.m 885.35 11633.50 commercial ply on one side, theback, shelves, shutter and brass fittings, etc. composite rate shall be reduced bycomplete. Rs.54.00 per Sft;or Rs.580.00

per Sqm and for hollow frameshutter with commercial ply onboth sides, the composite rateshall be reduced by Rs.22.80 perSft. or Rs.245.00 per Sq. metre.

b) Providing and fixing deodar wood almirah 9" to 12"(225 mm to 300 mm)depth with shelves, shutters, Per Sft. 61.15 301.80 sq.m 658.10 3247.35brass fittings, etc., without boxing and back,complete.

24 Providing and fixng class room almirah consiting of 1" (25 Per Sft. 45.25 270.30 Sq.m 486.95 2908.50mm) thick solid flush shutter with deodar wood lipping ¼"(6 mm) thick all around (sterling made) fixed in deodarwood frame 3"x1" (75mm x 25mm) including full hinges C.P. fittings with RCC (1:1½:3) shelves 1½" (40 mm) thickincluding 3 coats of painting.

chapter-12(Wood Work) Page 83

Page 87: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

25 Providing and fixing wooden box type wardrobe 22" (550 If hollow flush door leaves 1" thickmm) deep including ¾" (20 mm) thick boxing and shelves, (25 mm) with commercial plyhanger rods, hard board back drawers, brass fittings, 3 ply) on both sides of deodarlocking arrangements, handles, internal bolts, shoe rods, wood frame and partal woodetc. including three coats of enamel paint:- bracing and deodar wood lipping is

used, the composite rate will bei) Partal wood boxing and deodar wood reduced by Rs.13.00 per Sft. or

shelves and leaves, etc. Per Sft. 92.40 450.10 sq.m 994.20 4843.30 Rs.140.00 per Sq. metre.

ii) Deodar wood boxing, and deodar wood ditto 95.70 517.35 ditto 1029.75 5566.85shelves and leaves, etc.

26 Providing and fixing wardrobe 22" (550 mm) deepconsisting of RCC shelves 1½" (40 mm) thick including ½"thick vinboard boxing and back (one side ply) vinboard Per Sft. 35.55 425.60 Sq.m 382.55 4579.70shutter ¾" (20 mm) thick including deodar wood lipping ¼"(6 mm) on all edges, fixes including deodar wood frame3"x1" (75mm x 25mm) with hanger rod in centre positiondrawers at bottom and openable shutter on upper portionincluding full hinges C.P. fitting and painting 3 coatscomplete.

27 Providing and fixing chowkat for doors, windows and C.windows, including holdfast, etc.

a) Teak wood Per Sft. 17.55 421.30 Sq.m 188.85 4533.00b) Deodar wood ditto 11.10 251.75 ditto 119.70 2708.75c) Shisham wood ditto 13.10 135.10 ditto 141.00 1453.75

28 Making and fixing deodar wood planking in eave boards, 26.1etc. planed on both sides, rebated and fixed including 26.2nails and screws, bolts and brackets:-

a) 1" (25 mm) thick Sft. 20.45 168.95 sq.m 220.15 1817.90b) ¾" (20 mm) thick ditto 20.45 131.80 ditto 220.15 1418.40c) ½" (13 mm) thick ditto 20.45 94.85 ditto 220.15 1020.55

29 Making and fixing deodar wood shelves, including dittobrackets:-

i) 1" (25 mm) thick Sft. 20.45 168.95 sq.m 220.15 1817.90ii) 1½" (40 mm) thick ditto 20.45 243.05 ditto 220.15 2615.20iii) 2" (50 mm) thick ditto 20.45 317.15 ditto 220.15 3412.50

chapter-12(Wood Work) Page 84

Page 88: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

30 a) Making and fixing cleats for doors and windows, Each 24.00 67.80 Each 24.00 67.80 26.1 andincluding hinges and screws. 26.2

b) Making and fixing cleats with brass hooks for roof Each 31.15 53.95 Each 31.15 53.95ventilators.

c) Providing and fixing door stops of 1½" (40 mm) dia Each 3.50 47.00 Each 3.50 47.00rubber block.

d) Providing and fixing G.I. hook with clamps for doors. Each 1.15 6.25 Each 1.15 6.25

31 Hard wood railing of any shape and design, including dittobends and corners, fixed in position, including polishingcomplete as directed.

a) Shisham wood Per Rft. 89.95 211.15 Metre 294.95 692.50b) Teak wood ditto 67.20 558.25 ditto 220.40 1831.00

32 Deodar wood dado or picture rail 3"x1½" (75x40 mm) as Per Rft. 33.60 129.85 Metre 110.20 425.95 26.1per approved design including moulding and fixed in place, 26.2cost of screws, nails, plugs, and painting complete.

33 Sawing wood by hand:-

a) Soft wood (deodar, kail or chir). 100Sft. 389.40 - sq.m 41.90 -b) Hard wood (shisham, kikar, teak or ditto 519.20 - ditto 55.85 -

sahl).

34 Sawing wood by machine:

a) Soft wood 100Sft. 232.28 - sq.m 25.00 -b) Hard wood ditto 349.00 - ditto 37.55 -

35 Making and fixing sun-shade of deodar wood including Per Sft. 28.25 206.80 sq.m 303.95 2225.25 26.1fixing brackets.

36 Making and fixing 1" (25 mm) thick kail or chir wooden dittonotice board with frame. Per Sft. 32.45 88.70 sq.m 349.15 954.40

37 Making deodar punkha pole 10'x6"x6" Each 120.10 4048.90 Each 120.10 4048.90 ditto(3.0 m x 150 mm x 150 mm)

38 Dismantling and refixing eave boards. Per Rft. 8.60 -- Metre 28.15 --

chapter-12(Wood Work) Page 85

Page 89: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

39 Making wooden stair-cases complete 2' to 3' (600 to 900 Per Rft. 127.60 1293.95 Metre 418.55 4244.15 26.1mm) wide frame 1½" (40 mm) thick planks of deodarwood, including hand rails.

40 Providing and fixing partition, including frame work:-

a) Sheets on one side of framework:-

i) Hard board 100Sft. 608.45 7130.80 sq.m 65.45 767.30ii) Ply wood ¼" (6 mm) thick ditto 608.45 8390.80 ditto 65.45 902.85iii) Masonite ditto 608.45 8894.80 ditto 65.45 957.10

b) Sheets on both sides of frame work:-

i) Hard board 100Sft. 730.15 8282.05 sq.m 78.55 891.15ii) Ply wood ¼" (6 mm) thick ditto 730.15 18529.15 ditto 78.55 1993.75iii) Masonite ditto 730.15 11810.05 ditto 78.55 1270.75

41 Providing and fixing ceiling, including frame work:-

i) Hard board 100Sft. 1182.50 6664.45 sq.m 127.25 717.10ii) Chip board ditto 1182.50 8704.45 ditto 127.25 936.60iii) Ply wood ¼" (6 mm) thick ditto 1182.50 8944.45 ditto 127.25 962.40iv) Masonite ditto 1182.50 8584.45 ditto 127.25 923.70

42 Providing and fixing thermopore false ceiling, including In case of acousticwooden frame panelling, cost of M.S. clamps, making Thermopore sheet, theholes in walls and repairing damaged surface, complete in composite rate will beall respects:- increased by Rs.9.00 per Sft.

a) Deodar wood frame panelling:

i) ¾" (20 mm) thick 100Sft. 1352.10 5467.45 sq.m 145.50 588.30ii) 1" (25 mm) thick ditto 1352.10 5549.55 ditto 145.50 597.15

b) Partal wood frame panelling:

i) ¾" (20 mm) thick 100Sft. 1352.10 4447.45 sq.m 145.50 478.55ii) 1" (25 mm) thick ditto 1352.10 4573.45 ditto 145.50 492.10

43 a) Fixing door, including chowkats. Each 211.20 - Each 211.20 -

b) Fixing windows, including chowkats. ditto 105.60 - ditto 105.60 -

chapter-12(Wood Work) Page 86

Page 90: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

44 a) Glazing with panes (16 oz. to 18 oz.,) Per Sft. 12.75 34.90 sq.m 136.95 375.30 26.12including cost of putty

b) Glazing with panes (16 oz. to 18 oz.) Per Sft. 16.65 56.95 sq.m 179.15 612.65using deodar wooden fillets and putty

45 Glazing with panes (24 oz. to 26 oz.), using Per Sft. 24.25 65.40 sq.m 260.75 703.65 26.12putty and deodar wooden fillets

46 a) Cutting to required size and fixing glas Per Sft. 8.90 9.95 sq.m 95.85 106.95panes with putty

b) Cutting to required size and fixing glass panes with Per Sft. 13.80 24.45 sq.m 148.25 262.85wooden fillets and putty

47 Glazing with plate glass 1/4" (6 mm) thick including the coof deodar wood fillets and putty:-

a) Glazing upto 8 sft (0.75 sq.m) Per Sft. 21.00 74.80 sq.m 225.85 804.60

b) Glazing exceeding 8 Sft (0.75 sq.m) but not exceeding 24 sf Per Sft. 21.05 75.00 sq.m 226.30 807.00(2.25 sq.m).

48 Providing and fixing 1½" (40 mm) thick deodar woodpanelled or panelled and glazed, doors and windows, withmild steel chowkat (frame), etc. complete in all respect(excluding sliding bolt or lock) with:

i) M.S. angle iron 1½"x1½"x¼", welded Per Sft. 85.85 397.35 sq.m 923.95 4275.55i) (40 mmx 40 mmx 6mm) with M.S. flat

2"x¼" (50 mm x 6 mm)ii) M.S. tee iron 1½"x1½"x¼", welded Per Sft. 85.85 365.30 sq.m 923.95 3930.55

(40 mmx40 mmx 6mm) with M.S. flat½"x¼" (13 mm x 6 mm)

49 Providing and fixing 1½" (40 mm) thick hollow flush door Teak ply would be used under theand windows with commercial ply (3 ply) on both faces o written permission of thedeodar wood shutter frame 1¼" (30 mm) thick and partal superintending Engineer, and thewood braces at about 3" (75 mm) apart and deodar wood composite rate of using teak plylipping 1½"x3/8" (40 mmx10 mm) fixed with M.S. chowka will be increased by Rs.20.00 per(frame) including chromium plated fittings, etc. complet Sft. ( 216.00 per Sq.m)in all respects (without sliding bolt or lock)

i) M.S. angle iron 1½"x1½"x¼", welded Per Sft. 60.15 355.60 sq.m 647.05 3826.40(40 mmx40 mmx 6mm) with M.S. flat2"x¼" (50 mm x 6 mm)

chapter-12(Wood Work) Page 87

Page 91: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

ii) M.S. tee iron 1½"x1½"x¼", welded Per Sft. 60.15 332.85 sq.m 647.05 3581.50(40 mmx40 mmx 6mm) with M.S. flat½"x¼" (13 mm x 6 mm)

50 Providing and fixing 1½" (40mm) thick solid flush door It C.P. Finger plate and kick plateshutter sterling with commercial ply (5 mm thick) are not provided/fixed theon both sides double pressed and deodar wood lipping Per Sft. 31.80 277.45 sq.m 342.05 2985.55 composite rate will be reduced by1½"x3/8" (40mm x 10mm) around shutter including Rs.15.20 per Sft.chromium plated fitting, iron hinges with aluminium kick Reduce composite rate by Rs.20.00 plate 22 SWG on both sides & finger plate complete in all per. Sq/ft or Rs.215 per sq.meter ifrespect. (Sterling / Oosman Bros / Equivalent ) 3-mm commmercial ply is used

51 Providing and fixing panelled door of M.S. sheet, with Per Sft. 58.00 298.60 sq.m 623.95 3212.85forged door leaves of M.S. sheet 22 SWG fitted in hollowframe chowkat 3"x4½" (75 mmx113 mm) made of M.S.sheet 18 SWG filled with plain cement concrete 1:3:6 etc.complete with all fittings and hammer painting, includingcarriage to site and fixing in position.

52 Providing and laying 24 SWG aluminum kick plate 4" (100 Per Rft. 12.65 20.25 Metre 41.55 66.35mm) high, fixed with screws 4" (100 mm) centre to centre,on bottom rail of flush doors only of commercial ply.

53 Providing and fitting curtain railing to doors and windows, Per Rft. 5.30 90.40 Metre 17.30 296.45comprising of TOSO-elite Japan made superior type ofrailing or equivalent, fixed over 4"x¾" (100mmx20mm)deodar wood strip, including painting.

54 Providing and fixing M.S. flat ½"x1/8" (13mm x 3mm) grill Per Sft. 35.05 131.85 sq.m 377.25 1418.85including ¾" x 1/8" (20 mmx3 mm) M.S. flat frame, inwindows of approved design, including painting threecoats, complete in all respects.

55 Providing and fixing G.I. wire gauze 22 SWG, 12x12 Per Sft. 10.25 40.15 sq.m 110.55 432.00 It 24 SWG wire gauze is used, themeshes per square inch, (5x5 meshes in cm2) fixed to composite rate shall be reduced bysteel window, complete with flat iron patti ½"x 1/8" (13 Rs.4.70 per Sft. or Rs.50.60 per squaremmx3 mm) and machine made screws. metre.

56 Providing and fixing wooden moulding stopper 2½"x5/8"(63 x 16 mm) on door frame fitted with ply of approvedquality complete in all respects.

a) Teak wood moulding Per Sft. 13.20 90.30 sq.m 142.05 971.80b) Deodar wood moulding ditto 13.20 38.25 ditto 142.05 411.55

chapter-12(Wood Work) Page 88

Page 92: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

57 Providing and fixing deodar wood dolly frame having Rate shall be paid as per surface area of1½"x1½" (40 x 40 mm) vertical and horizontal double post dolly frame e-g 0.75' x (3.5' + (2 x 7))with 1½"x1½" (40 x 40 mm) full width of james braces at12" (300 mm) including filling of the spaces in betweenbraces with 1:3:6 PCC fixing ply of approved qualityincluding holdfasts complete in all respects.

a) Teak wood ply Per Sft. 29.95 200.50 sq.m 322.30 2157.50b) With commercial ply ditto 29.95 192.45 ditto 322.30 2070.95

58 Providing and fixing ornamental wooden architrave 3" x (1½" tapered to ¼") all along the door frame complete in allrespect.

a) Teak wood architrave Per Sft. 5.60 56.70 sq.m 60.00 610.35b) Deodar wood architrave ditto 5.60 21.15 ditto 60.00 227.35

59 Providing and fixing Vin board cabinet 3/4" thick with

drawers 3"deep in 'Kitchen including termite proofing and polishing with synthetic enamel as specified, with handles hinges,screws etc., complete in all respects.

i) 1-1/2' deep,without back Per Sft 62.30 372.90 sq.m 670.20 4012.35ii) 1-1/2' deep,with back Per Sft 62.30 414.90 sq.m 670.20 4464.25iii) 2' deep,without back Per Sft 62.30 413.85 sq.m 670.20 4452.95iv) 2' deep,with back Per Sft 62.30 455.85 sq.m 670.20 4904.90

chapter-12(Wood Work) Page 89

Page 93: 26467Sahiwal_1st_010

PAINTING AND VARNISHING1 The rates include charges for scaffolding and other arrangements.

2 The rates for all finished works include the removal of surplus debris, unused material and by products

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 a) Cleaning painted wood work with oil and water. 100 Sft. 58.10 68.95 sq.m 6.25 7.40

b) Oiling woodwork with boiled linseed oil. 100 Sft. 38.70 78.30 sq.m 4.15 8.45 27.7

2 Brushing and scraping blisters of old paints from 100 Sft. 116.15 -- sq.m 12.50 - 27.3woodwork.

3 Scraping, brushing and removing old paint from metal 100 Sft. 464.65 -- sq.m 50.00 - 27.9surface.

4 Painting old surfaces:- 27.127.3 &

a) Painting corrugated surfaces, patent roofing, etc. with 27.9oil paint.

i) first coat 100 Sft. 156.80 316.40 sq.m 16.85 34.05ii) each subsequent coat ditto 118.80 200.40 ditto 12.80 21.55

b) Painting sashes, fanlights, glazed or gauzed doorsand windows:-

i) first coat 100 Sft. 95.05 180.25 sq.m 10.25 19.40ii) each subsequent coat ditto 80.80 150.40 ditto 8.70 16.20

c) Painting doors and windows, any type:

i) first coat 100 Sft. 156.80 320.00 sq.m 16.85 34.45ii) each subsequent coat ditto 118.80 243.00 ditto 12.80 26.15

d) Painting guard bars, gates of iron bars, gratings,railing (including standards, braces etc.) and similaropen work:-i) first coat 100 Sft. 95.05 180.25 sq.m 10.25 19.40ii) each subsequent coat ditto 80.80 150.40 ditto 8.70 16.20

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-13(Painting & Var) Page 90

Page 94: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

e) Painting fillets, framings, skirtings, pipes, gutters andsimilar linear work not exceeding 6" in girth:-

i) first coat 100 Lft. 80.80 166.00 Metre 2.65 5.45ii) each subsequent coat ditto 57.00 126.60 ditto 1.85 4.15

f) Painting small detached articles, not exceeding onesquare foot (Sq.m) of painted surface:-

i) first coat 100 Nos. 247.50 407.10 100 Nos. 247.50 407.10ii) each subsequent coat ditto 222.50 307.70 ditto 222.50 307.70

g) Painting small detached articles, exceeding onesquare foot (Sq.m) but not exceeding three squarefeet (Sq.m) of painted surface:-

i) first coat 100 Nos 565.70 1040.90 100 Nos 565.70 1040.90ii) each subsequent coat ditto 324.35 561.95 ditto 324.35 561.95

5 Painting new surface:- 27.127.2 &

a) Preparing surface and painting corrugated surface, 27.9patent roofing, etc.

i) priming coat. 100 Sft. 246.05 418.85 sq.m 26.50 45.05ii) each subsequent coat of paint. ditto 85.90 284.50 ditto 9.25 30.60

b) Preparing surface and painting sashes, fan light,glazed or gauzed doors and windows etc. any type(including edges):-

i) priming coat. 100 Sft. 103.05 246.75 sq.m 11.10 26.55ii) each subsequent coat of paint. ditto 68.45 181.25 ditto 7.35 19.50

c) Preparing surface and painting of doors and windowsany type (including edges):-

i) priming coat. 100 Sft. 246.05 415.25 sq.m 26.50 44.70ii) each subsequent coat of paint. ditto 85.90 284.50 ditto 9.25 30.60

d) Preparing surface and painting guard bars, gates ofiron bars, gratings, railing (including standards,braces, etc.) and in similar open work:-i) priming coat. 100 Sft. 154.95 258.75 sq.m 16.70 27.85ii) each subsequent coat of paint. ditto 68.45 181.25 ditto 7.35 19.50

chapter-13(Painting & Var) Page 91

Page 95: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

e) Preparing surface and painting of fillets, framing,skirtings, pipes, gutters, and similar linear work notexceeding 6" (150 mm) girth:-

i) priming coat. 100 Lft. 121.20 200.15 Metre 4.00 6.55ii) each subsequent coat of paint. ditto 45.60 138.60 ditto 1.50 4.55

f) Preparing surface and painting of small detachedarticles, not exceeding one sq. ft. (Sq.m) of paintedsurface:-

i) priming coat. 100 Nos. 356.40 851.10 100 Nos. 356.40 851.10ii) each subsequent coat of paint. ditto 176.55 570.15 ditto 176.55 570.15

g) Preparing surface and painting of small detachedarticles, exceeding one Sft. but not exceeding 3 Sft.(Sq.m) of painted surface:-

i) priming coat. 100 Nos. 1029.60 1699.20 100 Nos. 1029.60 1699.20ii) each subsequent coat of paint. ditto 308.00 1013.60 ditto 308.00 1013.60

h) Extra for knotting and stopping to 100 Sft. 16.90 30.95 sq.m 1.80 3.35priming coat on new surface of wood.

6 Applying Khanki Mixture hot to barrage 27.10gates:-

i) first coat 100 Sft. 118.80 294.25 sq.m 12.80 31.65ii) second coat ditto 93.45 206.35 ditto 10.05 22.20

7 French polishing complete:- 27.6

a) on new work 100 Sft. 1252.10 1303.45 sq.m 134.75 140.25b) on old work ditto 648.70 677.00 ditto 69.80 72.85

8 Varnishing wood work, including cleaning and preparingsurface.

a) first coat 100 Sft. 95.05 192.25 sq.m 10.25 20.70b) second coat ditto 35.65 109.45 ditto 3.85 11.80c) third coat ditto 35.65 93.85 ditto 3.85 10.10

chapter-13(Painting & Var) Page 92

Page 96: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

9 Bitumen coating to plastered or cement concrete surface:-

i) 20 lbs. per 100 Sft. (9.07 Kg per Sq.m) 100 Sft. 96.80 750.95 sq.m 10.40 80.80ii) 14 lbs. per 100 Sft. (6.35 Kg per Sq.m) ditto 92.95 426.30 ditto 10.00 45.85iii) 10 lbs. per 100 Sft. (4.54 Kg per Sq.m) ditto 76.65 410.05 ditto 8.25 44.10

10 Writing letters or figures, per letter, per inch (25 mm) Per No. 4.75 5.35 Per No. 4.75 5.35 27.1

height.

11 Writing letters or figures at any surface with reflective paint Per Letter 4.75 5.10 Per Letter 4.75 5.10 27.1of approved quality and colour per letter per inch height. per inch per 25 mm

height height

12 Writing letters of figures on any surface with reflective tape ditto 5.70 6.45 ditto 5.70 6.45 dittoof approved quality and colour per letter per inch (25 mm)height.

13 Coaltar painting: 27.8to

a) first coat, laid hot 100 Sft. 94.10 607.35 sq.m 10.10 65.35 27.11b) second coat, laid hot ditto 57.00 382.15 ditto 6.15 41.10

14 Solignum painting:- 27.8

a) one coat, applied hot 100 Sft. 92.95 115.75 sq.m 10.00 12.45b) two coats, applied hot ditto 140.80 176.90 ditto 15.15 19.05

15 Creosote painting:- ditto

a) one coat, applied hot 100 Sft. 111.50 214.70 sq.m 12.00 23.10b) two coats, applied hot ditto 168.95 341.75 ditto 18.20 36.75

16 Burning off or rubbing down with pumice stone, old paint 100 Sft. 343.20 357.60 sq.m 36.95 38.50 27.3from wood work.

17 Removing with caustic soda, old paint from wood work. 100 Sft. 116.15 123.35 sq.m 12.50 13.25 ditto

18 Painting distance marks for white ground and black Each 23.75 28.20 Each 23.75 28.20 27.1lettering on both sides.

19 Painting two feet wide gauges, reading to 10th of a foot Per Rft. 47.50 56.05 per Metre 155.85 183.80 ditto(metre).

chapter-13(Painting & Var) Page 93

Page 97: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

20 Painting sounding rods and other gauges, reading to 10th Per Lft. 23.75 26.45 per Metre 77.95 86.80 27.1of a foot (metre)

21 Painting leveling staves. Per Lft. 75.70 79.95 per Metre 248.25 262.20

22 a) Painting and lettering mile/Km stones, dittoon both sides:

i) one coat Each 50.90 81.80 Each 50.90 81.80ii) two coats ditto 89.10 137.10 ditto 89.10 137.10

b) Painting and lettering Furlong/½ Km 27.1stones, on both sides:-

i) one coat Each 6.80 10.35 Each 6.80 10.35ii) two coats ditto 11.90 18.20 ditto 11.90 18.20

c) Painting and lettering Sign posts:-

i) one coat Each 57.00 76.80 Each 57.00 76.80ii) two coats ditto 94.10 127.70 ditto 94.10 127.70

23 Removing paint or varnish from wall. 100 Sft. 232.30 - sq.m 25.00 - 27.12

24 Scraping from hydraulic gates:- 27.1

a) Khanki paint 100 Sft. 464.65 - sq.m 50.00 -b) Aluminium paint ditto 464.65 - ditto 50.00 -

25 Painting letters with shade. per letter 7.60 7.60 per letter 7.60 7.60 27.1per inch per 25 mmheight height

26 Scraping rust from old rail or girders. 100 Sft. 348.50 384.50 sq.m 37.50 41.35 27.927.10

27 Chiselling old paint from brick work. 100 Sft. 464.65 488.65 sq.m 50.00 52.60 27.12

28 Cleaning glasses with chalk and spirit, etc. 100 Sft. 387.20 397.20 sq.m 41.65 42.75

29 Cleaning and oiling rafter or rolled steel 100 Sft. 116.15 145.55 sq.m 12.50 15.65 27.9beams.

chapter-13(Painting & Var) Page 94

Page 98: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

30 Cleaning and painting punkha poles, including fixing Each 89.10 96.40 Each 89.10 96.40 27.3hooks.

31 Preparing surface and painting with emulsion paint:- 27.12

a) first coat 100 Sft. 125.45 268.60 sq.m 13.50 28.90b) 2nd and each subsequent coat ditto 96.10 209.20 ditto 10.35 22.50

32 Preparing surface and painting with water proof coloured 27.12cement finish, like duracem, buxcem or other finishes withsimilar specifications, on walls, etc.

a) new surface:

i) 1st coat 100 Sft. 125.45 191.15 sq.m 13.50 20.55ii) 2nd and subsequent coat ditto 96.10 154.10 ditto 10.35 16.60

b) old surface:

i) 1st coat 100 Sft. 125.45 153.70 sq.m 13.50 16.55ii) 2nd and subsequent coat ditto 96.10 123.65 ditto 10.35 13.30

32A Providing and applying weather shield paint of approvedquality on external surface of building including preparation ofsurface, application of primer complete in all respect:

a) new surface:

i) 1st coat %sft 401.30 694.45 sq.m 43.20 74.70ii) 2nd coat %sft 221.75 341.55 sq.m 23.85 36.75

b) old surface: %sft 221.75 341.55 sq.m 23.85 36.75

33 Painting traffic lane 5" (125 mm) wide, with road marking Per Rft. 0.70 1.40 Metre 2.35 4.65enamel.

34 Painting traffic lane 5" (125 mm) wide with reflective Per Rft. 1.10 8.15 Metre 3.65 26.75 AASHTO Rates shall be reduced by Rs.0.50clorinated rubber (CR) paint including glass beads comlpete M248-91 P.Rft or Rs.1.65 P.Mtr. If glass beads in all respect. (2000) are not used.

35 Repainting of ceiling fan (all sizes and types), including Per Job 30.15 60.75 Job 30.15 60.75painting of blades, canopy, suspension rod and regulator,with suitable enamel paint.

chapter-13(Painting & Var) Page 95

Page 99: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

36 Repainting of iron poles with cross arms, with bitumen or Per Job 70.40 179.00 Job 70.40 179.00 other approved paint.

37 Repainting of pipes and specials of G.I., M.S. or conduit,etc., fixed for on surface electric wiring, with approvedpaint:

i) upto 40 mm (1½") dia Per Rft. 0.65 2.10 Metre 2.10 5.60ii) above 40 mm (1½") to 50 mm (2") dia ditto 1.30 3.10 ditto 4.20 10.15iii) above 50 mm (2") to 100 mm (4") dia ditto 2.15 4.85 ditto 7.05 15.95

38 Repainting main switches and branch distribution boards Per Job 13.95 57.85 Job 13.95 57.85of all sizes and types, with approved paint (complete set).

39 Extra labour for painting, varnishing, etc. from 20' (6.10 m) 100 Sft. 37.15 - sq.m 4.00 - The height will be taken from theheight and above, for every additional 10' (3.05 m) height, per coat floor, roof or ground underneath, asor part thereof, requiring scaffolding. the case may be on the side

towards which the work is to bedone.

chapter-13(Painting & Var) Page 96

Page 100: 26467Sahiwal_1st_010

LINING OF CANALS1 Rates for all finished works include the removal of surplus debris, unused material and byproducts2 The rates also include curing for specified period wherever necessary.3 Nominal dimension of tile or brick shall be taken for the purpose of measurement and payment

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Formation, dressing and preparing sub-grade:- 28.1 to 28.3

a) in bed 100Sft. 273.00 - sq.m 29.35 -b) on slope ditto 374.90 - ditto 40.35 -

2 Stabilized layer of cement, sand ratio 1:30, 2" (50 mm) 100Sft. 686.40 1051.20 sq.m 73.85 113.10 dittothick on slope.

3 Cement plaster ½" (13 mm) thick ratio 1:10. ditto

a) in bed 100Sft. 494.85 646.45 sq.m 53.25 69.55b) on slope ditto 628.30 779.90 ditto 67.60 83.90

4 Cement plaster 3/8" (10 mm) thick ratio 1:3. ditto

a) in bed 100Sft. 494.85 733.15 sq.m 53.25 78.90b) on slope ditto 628.30 866.65 ditto 67.60 93.25

5 Cement plaster 1½" (40 mm) thick ratio 1:6. ditto

a) in bed 100Sft. 628.30 1233.00 sq.m 67.60 132.65b) on slope ditto 797.30 1401.95 ditto 85.80 150.85

6 Tile lining 12"x6"x2" (300x 150x50 mm) in 1:6 cement, 28.2 to 28.3 The rates are only for laying tilessand mortar:- over 1/8" (3 mm) thick layer of 1:6

mortar. Items 1 to 5 above area) in bed 100Cft. 3055.80 11443.95 cu.m 1079.30 4042.00 payable separately.b) on slope ditto 3484.80 11872.95 ditto 1230.85 4193.50

7 Tile lining 12"x6"x2" (300x150x50 mm) in 28.2 to 28.3 The rates are only for laying tiles1:3 cement, sand mortar:- over 1/8" (3 mm) thick layer of 1:3

mortar. Items 1 to 5 above area) in bed 100Cft. 3055.80 12167.40 cu.m 1079.30 4297.55 payable separately.

b) on slope ditto 3484.80 12596.40 ditto 1230.85 4449.05

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-14(Lining of canal) Page 99

Page 101: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

8 Brick lining 9"x4½"x3" (225x113x75 mm) in 1:6 cement, 28.2 The rates are only for laying brickssand mortar:- over 1/8" (3 mm) thick layer of 1:6

mortar. Items 1 to 5 above area) in bed 100Cft. 3055.80 9409.95 cu.m 1079.30 3323.60 payable separately.b) on slope ditto 3484.80 9838.95 ditto 1230.85 3475.10

9 Brick lining 9"x4½"x3" (225x113x75 mm), in 1:3 cement, ditto The rates are only for layingsand mortar:- bricks over 1/8" (3 mm) thick

layer of 1:3 mortar. Items 1 toa) in bed 100Cft. 3055.80 10133.40 cu.m 1079.30 3579.10 5 above are payableb) on slope ditto 3484.80 10562.40 ditto 1230.85 3730.65 separately.

10 Cement concrete lining, using washed screened and 20.1, 28.1graded stone aggregate:- & 28.3

a) in bed:-

i) ratio 1:2:4 100Cft. 2471.05 11932.80 cu.m 872.75 4214.65ii) ratio 1:3:6 ditto 2471.05 10755.85 ditto 872.75 3798.95iii) ratio 1:4:8 ditto 2471.05 9936.00 ditto 872.75 3509.40

b) on slope:-

i) ratio 1:2:4 100Cft. 2871.00 12332.75 cu.m 1014.05 4355.95 ii) ratio 1:3:6 ditto 2871.00 11155.80 ditto 1014.05 3940.25iii) ratio 1:4:8 ditto 2871.00 10335.95 ditto 1014.05 3650.65

chapter-14(Lining of canal) Page 100

Page 102: 26467Sahiwal_1st_010

SHEET PILINGRates for all finished works include the removal of surplus debris, unused material and by produc

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Cutting Ransome and Larson piles. Per 84.50 - Per 84.50 - 29.1-cut cut 29.3

2 Cutting universal piles. Per cut 125.05 - Per cut 125.05 - ditto

3 Driving steel piles, 25' to 30'. (7.5 to 9.0 m) 100Sft. 1676.40 - sq.m 180.40 - ditto 1) The rate includes laying andremoving of track and also carriageof piles to machine, averagedistance of 3 chains (90 metre).

2) The rates are for the tacklegangs only supplied by thecontractor, Mechanical staffon-machines will be supplied byGovernment.

3) T-piles and adjustable junctionpiles will be counted as two piles.

4 Driving steel piles,more than 15' (4.6 m) and less than 25' 100Sft. 1605.10 - sq.m 172.70 - ditto ditto(7.5 m).

5 Driving steel piles, 15' (4.5 m) and under. 100Sft. 1177.45 - sq.m 126.70 - ditto ditto

6 Dolleying piles. Each 103.50 - Each 103.50 - ditto Upto 5' (1.5 m) dolleying.

7 Drilling holes in piles by hand. Each 11.60 - Each 11.60 - ditto

8 Raising and lowering machine. Per Ft. 1575.20 - Metre 5166.65 - ditto

9 Turning Machine, 90o . Per 2302.10 - Per 2302.10 - 29.1 toJob Job 29.3

10 Turning Machine, 135o . Per 2872.30 - Per 2872.30 - dittoJob Job

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-15(Sheet piling) Page 101

Page 103: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

11 Turning Machine, 180o . Per 3907.20 - Per 3907.20 - 29.1 toJob Job 29.3

12 Travelling machine (light). Per 4612.10 - 30 M. 4612.10 - dittoChain

13 Loading and unloading piles. Ton 85.95 - Tonne 84.60 - ditto To be done by hand carts orramps, including cost of ropes.

14 Dismantling piling machine. Each 10128.80 - Each 10128.80 - ditto

15 Erecting piling machine. Each 11687.10 - Each 11687.10 - ditto

16 Carriage of piling machine under different conditions. per 1869.10 - 30 M 1869.10 - dittochain

chapter-15(Sheet piling) Page 102

Page 104: 26467Sahiwal_1st_010

PROTECTION & DIVERSION WORKS1 Rates for all finished works include the removal of surplus debris, unused material and byproducts2 The composite rates of the items in which stone, boulders, shingle spawl are used do not contain the carriage

of the these stone materials, which will be paid separately by road, and/or rail, whichever means of transport isadopted. The supply and carriage to site of work of all other material required in the item, is included in thecomposite rates.

3 The carriage of stone or spawl will be paid on the basis of actual stack measurement (without any reductionfactor) of the stone, boulders, shingle or spawl carried.

4 Where stone, boulder or spawl is issued from stock and contractor is paid for its carriage and/or labour only; or where such stone product is supplied, carried or handled by the contractor in which no laying is required,the actual stack measurement (without any reduction factor) shall from the basis of payment of supply orcarriage of the stone, boulder or spawl, etc. The quantity of finished and completed item of work shall form thebasis of laying.

5 In case of the items in which the rates include carriage of stakes, bushing, Pilchi, sarkanda or farash, etc. withinone mile (1.6 Km.)

i) the cost of the carriage within one mile (one Km) shall not be deducted from the carriage charges to follow thereafterfrom the point of supply.

ii) if the site of work happens to be within one mile (one Km.) of the source of supply, the materials will be collectedand measured at site of work and no extra carriage would be admissible in such cases.

iii) where the site of the work is situated at more than one mile (one Km.) distance from the source of supply, the pointof supply will be fixed carefully by the Engineer-in-charge in such a way that the carriage charges wouldbe arrived at, most economically. Extra carriage will be admissible from the place of supply of thematerial which will be considered its starting point. The demarcation of the place of supply will bepre-determined before calling the tenders.

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Cutting pilchi frash or sarkanda inlcuidng carriage within 100Cft. 441.40 cu.m 155.90one mile.

2 Weaving matresses. 100Cft. 836.35 cu.m 295.35

3 a) Supplying and filling jute bags 1.25 (o.o35 cum) Cft., Per 13.05 25.45 Per Baq 13.05 25.45 The rate does not include supply ofcapacity, with sand or earth, sewing and stacking, in Bag sand or earth for filling bags, whichdry. will be paid extra.

b) Supply and filling jute bags 1.25 (0.35 ccum) Cft. ditto 20.35 32.70 Per Baq 20.35 32.7 -ditto-capacity, with sand or earth, sewing and laying inposition, under water.

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-16(Protec & Div) Page 101

Page 105: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

4 a) Supplying and filling jute bags 4 to 5 cft Per 31.25 78.05 Per 31.25 78.05 The rate does not include supply of(0.11 to 0.14 cum) capacity, with sand or earth, Bag Bag sand or earth for filling bags, whichsewing and stacking, in dry. will be paid extra.

b) Supply and filling new jute bags 4 to 5 cft (0.11 to ditto 44.70 91.50 ditto 44.70 91.5 -ditto-0.14 cu.m) capacity, with sand or earth, sewing andlaying in position, under water.

5 Carriage of jute bags 1.25 Cft. (0.035 cu m) capacity, filledwith sand or earth:-

a) 1st chain (30 m) 100 Nos 116.15 % Nos 116.15

b) 2nd to 4th chain (30 m to 120 m) Per chain 41.80 Per 30 m 41.80per 100 Per 100 Nos/

Nos

c) 5th and subsequent chains ditto 16.25 ditto 16.25(150 m and subsequent every 30 m)

6 Carriage of new jute bags 4 to 5 Cft.(0.11 to 0.14 cu.m) capacity, filled with sand or earth:-

a) 1st chain (Ist 30 metre) 100 Nos 464.65 % Nos 464.65

b) 2nd to 4th chain (60 m to 120 m) per chain 162.60 Per 30 m 162.60per 100Nos per %Nos

c) 5th and subsequent chains (150 m and ditto 62.75 ditto 62.75subsequent every 30 m)

7 Rolling matresses to river edge and floating,after unroling:-

a) area of matress upto 2,000 Sft. 100Sft. 261.35 sq.m 28.10( 186 sq.m)

chapter-16(Protec & Div) Page 102

Page 106: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

b) area of matress 2,000 to 2,500 Sft. 100Sft. 435.60 sq.m 46.85

(186 sq.m to 232 sq.m)

c) area of matress over 2,500 Sft. ditto 508.20 ditto 54.70(232 sq.m)

8 Sewing empty cement bags in sheets. 100 Nos 406.55 434.55 % Nos 406.55 434.55

9 Making compact round pilchi, frash or sarkanda round 100Cft. 566.30 638.50 cu.m 200.00 225.55 Measured in the shape of compactbundles of specified size for the work. round bundles and of size specified

for the work, before filling at site.

10 Launching the above and placing in position. 100Cft. 278.80 cu.m 98.45

11 Supply within 5 chains (150 m):-

a) Boulders 9" (225 mm) and above 100Cft. 841.00 cu.m 297.00

b) Over size shingle 3" to 9"(75 to 225 mm) ditto 562.20 ditto 198.55

c) Mixed graded shingle ditto 666.75 ditto 235.45

12 Supplying Munj or Patha Trungers 6" (150 mm) mesh to hold Each 36.30 67.70 Each 36.30 67.73 Cft. (0.085 cu.m)

13 Providing and weaving G.I. wire netting for wire crates, withG.I. wire of approved size (including siding and partition tomake crate):-

a) 6" (150 mm) mesh

i) 15 SWG wire 100Sft. 498.95 757.70 sq.m 53.70 81.55ii) 10 SWG wire ditto 534.60 1374.60 ditto 57.50 147.90iii) 8 SWG wire ditto 534.60 1851.70 ditto 57.50 199.25

b) 4" (100 mm) mesh

i) 15 SWG wire 100Sft. 641.50 1030.45 sq.m 69.05 110.9ii) 10 SWG wire ditto 712.80 1970.30 ditto 76.70 212.00iii) 8 SWG wire ditto 712.80 2684.30 ditto 76.70 288.85

14 Providing and laying shingle on top of bund, including 100Cft. 290.40 580.80 cu.m 102.55 205.15handling of materials within three chains.

chapter-16(Protec & Div) Page 103

Page 107: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

15 Supply and dumping at site, without boat, includinghandling of materials within three chains (90 m)

a) stone or boulder 100Cft. 508.20 904.20 cu.m 179.45 319.3 The rate includes supply of brickb) shingle or spawl ditto 508.20 798.60 ditto 179.45 282.05 bats to site of work.c) brick bats ditto 392.05 1184.05 ditto 138.45 418.20

16 Supply and dumping by boat, including loading into boat The rate includes supply of brickwithin three chains (90 m) lead, and hire charges of boat and bats to site of work.boatman.

a) stone or boulder 100Cft. 1201.20 1597.20 cu.m 424.25 564.15b) shingle or spawl ditto 1201.20 1491.60 ditto 424.25 526.85c) brick bats ditto 1085.05 1877.05 ditto 383.25 662.95

17 Providing and filling brick bats in crates 100Cft. 733.90 1525.90 cu.m 259.20 538.95 The rate includes supply of brick(excluding cost of crates). bats to site of work.

18 Supplying and filling bricks in crates and hand packing 100Cft. 879.10 6459.10 cu.m 310.50 2281.35 The rate includes supply of bricks(excluding cost of crates). to site of work.

19 Supply and filling in wire crates, including sewing crates(excluding cost of crates):-

i) stone or boulder 100Cft. 995.30 1391.30 cu.m 351.55 491.40ii) shingle or spawl ditto 995.30 1285.70 ditto 351.55 454.10

20 Extra for anchoring boat, for dumping by boats or tipping 100Cft. 102.20 - cu.m 36.10 -crates.

21 Extra for tipping crates (in addition to anchoring boats). 100Cft. 511.10 - cu.m 180.50 -

22 Pilchi reventment, including carriage upto one mile 100Sft. 290.40 690.40 sq.m 31.25 74.3 30.1(1.6 km.)

23 Surface protection with pilchi matresses, carriage upto 100Sft. 726.00 766.00 sq.m 78.10 82.40 dittoone mile (1.6 Km).

24 Pilchi, sarkanda or frash pitching on slopes, including The cost of placing earth betweensupply of pilchi, sarkanda or frash within one mile, (1.6 km) 100Sft. 1847.60 2778.55 sq.m 198.80 298.95 rolls shall be paid separately, asalso supply and driving of pegs 1½' (460 mm) long earthwork.sharpened at one end and, tying with wire or Munj Ban(excluding cost of placing earth between rolls).

chapter-16(Protec & Div) Page 104

Page 108: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

25 Constructing Groynes upto 5' (1.5 m) height, with single 100Sft. 593.35 654.85 sq.m 63.85 70.45 Measurement to be made of therow of wooden vertical stakes 7" to 12" (175 to 300 mm) area of elevation on one face only.dia, 1' (300 mm) apart, average lead one mile (1.6 km.)

26 Construction Groynes upto 10' (3.0 m) height, with double 100Sft. 1008.50 1081.85 sq.m 108.50 116.4row of wooden vertical stakes 7" to 12" (175 to 300 mm)dia, 2' (600 mm) apart, average lead one mile (1.6 Km).

27 Providing and laying stone pitching/filling, dry hand 100Cft. 646.80 1319.10 cu.m 228.45 465.9packed, as filling behind retaining walls or in pitching andaprons.

28 Providing and laying stone pitching with hammer dressed 100Cft. 2118.60 2716.20 cu.m 748.30 959.35stones on surface, laid in courses.

29 Providing and laying stone pitching, for top layer only:-

a) one slope 100Cft. 1702.80 2300.40 cu.m 601.45 812.5b) on level ditto 1557.60 2155.20 ditto 550.15 761.2

30 Providing and laying stone or spawl filling:-

a) on level 100Cft. 429.00 693.00 cu.m 151.50 244.75

b) on slope ditto 556.50 820.50 ditto 196.55 289.8

31 Providing and laying stone pitching, hand packed, withsurface levelled off to the correct section and voids filled in1:8 cement, sand mortar, in floors of bridges along banksand in appons etc.

i) top layer on slope 100Cft. 2338.50 4056.45 cu.m 825.95 1432.75ii) top layer on level ditto 2193.30 3911.25 ditto 774.70 1381.45iii) stone pitching/filling on slope or on level ditto 1236.05 3028.65 ditto 436.55 1069.75

(other than top layer).

32 Grouting stone pitching or apron, etc. in:-

a) cement, sand mortar 1:3 100Sft. 738.95 2792.15 sq.m 79.50 300.45b) cement, sand mortar 1:8 ditto 640.20 1760.50 ditto 68.90 189.45

33 Sand grouting in stone apron, with high 100Sft. 256.10 856.10 sq.m 27.55 92.10pressure hose.

chapter-16(Protec & Div) Page 105

Page 109: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

34 Grouting stone filling or pitching, with bajri. 100Cft. 363.00 1083.00 cu.m 128.20 382.5

35 Removing stone and repitching hand packed, on slopes or 100Cft. 1559.70 - cu.m 550.90 -level after making good damaged slope/portion.

36 Collecting and stacking boulders from nullah beds or loose 100Cft. 464.65 - cu.m 164.10 -shale, or from any other site, within 3 chains (90 m) lead.

37 Levelling and dressing stone filling under blocks and 100Cft. 429.00 1149.00 cu.m 151.50 405.85grouting with shingle.

38 Grouting jharies between blocks with bajri. 100Cft. 429.00 909.00 cu.m 151.50 321.05

39 Breaking stone into spawls and stacking 100Cft. 348.50 - cu.m 123.10 -

Canal and Roads

40 Fixing floating spurs, with material from canal plantationwithin one mile (1.6 Km) lead:-

a) upto 2.0' (600 mm) F.S. depth Each 12.50 - Each 12.50 -

b) above 2.0' to 3.0' (600 to 900 mm) F.S. depth ditto 14.05 - ditto 14.05 -

c) above 3.0' to 4.0' F.S. (900 mm to 1200mm) depth Each 18.75 - ditto 18.75 -

d) above 4.0' (1200 mm) F.S. depth ditto 46.85 - ditto 46.85 -

41 Staking and bushing from canal plantation, royalty to bepaid to Forest Department or cost to private owner, if andwhen required:-

a) i) Cutting and supply unsharpened pegs 3.5' (1.07 100 Nos 580.80 608.80 % Nos 580.80 608.80m) long, 3" to 6" (75 to 150 mm) dia, within one mile(1.6 Km) lead.

ii) Sharpening one end of 3.5' (1.07 m) long pegs, 3" 100 Nos 285.10 - 100 Nos 285.10 -to 6" (75 to 150 mm) dia.

iii) Driving pegs 3.5' (1.07 m) long, 3" to 6" (75 to 150 100 Nos 399.15 - 100 Nos 399.15 -mm) dia (driven 1.0' (300 mm) below the available bedor ground (average).

chapter-16(Protec & Div) Page 106

Page 110: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

iv) Tying pegs with Munj, Patha ban (one line, Per Chain 29.05 50.90 Per 30 29.05 50.90incuding tying around the pegs). of One Metre

Row of one row

v) Cutting and supplying brush wood from canal ditto 530.10 680.50 ditto 530.10 680.50plantation or private owners, lead within one mile(1.6 Km) and wattling between stakes and intertwining(thickness of wattled brushwood 1.0' (300 mm)average).

b) i) Cutting and supplying unsharpened pegs 4.0' 100 Nos 79.65 111.50 100 Nos 79.65 111.50(1.20 m) long, 3" to 6" (75 to 150 mm) dia, from canalplantation, lead within one mile (1.6 Km).

ii) Sharpening one end of 4' (1.20 M) long pegs, 3" 100 Nos 285.10 - 100 Nos 285.10 -to 6" (75 to 150 mm) dia.

iii) Driving pegs 4' (1.20 m) long, 3" to 6" (75 to 150 100 Nos 454.70 - 100 Nos 454.70 -mm) dia (driven 1.0' (300 mm) below the available bedor ground (average).

iv) Tying pegs with Munj, Patha ban (one line, Per 29.05 Per 29.05 incuding tying around the pegs). Chain of 30 M of

one row one row

v) Cutting and supplying brush wood from canal ditto 1082.40 ditto 1082.40 plantation or private source, lead within one mile(1.6 Km). and wattling between stakes and intertwining(thickness of wattled brushwood 1.0' (300 mm)average).

c) i) Cutting and supplying unsharpened pegs 5.0' (1.5 100 Nos 99.65 139.50 100 Nos 99.65 139.50m) long, 3" to 6" (75 to 150 mm) dia, from canalplantation, lead within one mile (1.6 Km).

ii) Sharpening one end of 5' (1.5 m) long pegs, 3" to 100 Nos 302.00 - 100 Nos 302.00 -6" (75 to 150 mm) dia.

iii) Driving pegs 5' (1.5 m) long, 3" to 6" (75 to 150 100 Nos 517.45 - 100 Nos 517.45 -mm) dia (driven 1.5' (450 mm) below the available bedor ground (average).

chapter-16(Protec & Div) Page 107

Page 111: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

iv) Tying pegs with Munj, Patha ban (one line, Per 29.05 50.90 Per 29.05 50.90incuding tying around the pegs). Chain of 30 M

one row of one row

v) Cutting and supplying brush wood from canal Per chain 534.60 745.00 Per 30 M 534.60 745.00plantation or private source, lead within one mile of one row of one row(1.6 Km) and wattling between stakes and intertwining(thickness of wattled brushwood 1.0' (300 mm)average).

d) i) Cutting and supplying unsharpened 100 Nos 1161.60 1209.45 100 Nos 1161.60 1209.45pegs 6.0' (1.8 m) long, 3" to 6" (75 to150 mm) dia, from canal plantation, leadwithin one mile (1.6 Km).

ii) Sharpening one end of 6' (1.8 m) long pegs, 3" to 100 Nos 359.05 - 100 Nos 359.05 -6" (75 to 150 mm) dia.

iii) Driving pegs 6' (1.8 m) long, 3" to 6" (75 to 150 100 Nos 620.95 - 100 Nos 620.95 -mm) dia (driven 1.75' (530 mm) below the availablebed or ground (average).

iv) Tying pegs with Munj, Patha ban (one line, Per Per Chainincuding tying around the pegs). Chain of 29.05 50.90 of one row 29.05 50.90

one row

v) Cutting and supplying brush wood from canal ditto 1227.60 1483.10 ditto 1227.60 1483.10plantation or private source, lead within one mile(1.6 Km) and wattling between stakes and intertwining(thickness of wattled brushwood 1.0' (300 mm)average).

e) i) Cutting and supplying unsharpened pegs 6'-1" to 100 Nos 871.20 970.40 100 Nos 871.20 970.408.0' long (1.85 to 2.45 m), 4" to 8" (100 to 200 mm)dia, from canal plantation, lead within one mile (1.6 Km).

ii) Sharpening one end of 6'-1" to 8.0' (1.85 to 2.45m) 100 Nos 456.20 - 100 Nos 456.20 -long pegs, 4" to 8" (100 to 200 mm) dia.

chapter-16(Protec & Div) Page 108

Page 112: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

iii) Driving pegs 6'-1" to 8.0' (1.85 to 2.45 m) long, 3" 100 Nos 684.30 - 100 Nos 684.30 -to 6" (75 to 150 mm) dia driven 2' (600 mm) belowthe available bed or ground (average).

iv) Tying pegs with Munj, Patha ban (one line, Per chain 29.05 41.15 Per 30 M 29.05 41.15incuding tying around the pegs). of one row of one row

v) Cutting and supplying brush wood from canal Per 1405.80 1706.40 Per 30 M 1405.80 1706.40plantation or private source, lead within one mile Chain of of one row(1.6 Km) and wattling between stakes and intertwining one row(thickness of wattled brushwood 1.0' (300 mm)average).

42 Staking with Bamboo from market and bushing from canalplantation or private source (royalty of brushwood to bepaid to Forest Department or cost to private owner, if andwhen required):-

a) i) Supplying Bamboos 8'-1" to 10.0' (2.46 to 3.05 m) 100 Nos 6600.00 - 100 Nos 6600.00 -long, 2½" to 5" (63 m to 125 mm) dia.

ii) Sharpening one end of 8'-1" to 10.0' (2.46 to 30.5 100 Nos 399.15 - 100 Nos 399.15 -m) long Bomboos, 2½" to 5" (63 to 125 mm) dia.

iii) Driving Bamboos 8'-1" to 10.0' (2.46 to 3.05 m) 100 Nos 750.30 - 100 Nos 750.30 -long 2½" to 5" (63 to 125 mm) dia, driven 2.5' (750mm) below the available bed or ground (average).

iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per Per 30 MMunj, Patha Ban, two lines, including tying around Chain of 43.55 77.85 of one 43.55 77.85the Bamboos. one row Row

v) Cutting and supplying brushwood from canal ditto 1729.20 2119.60 ditto 1729.20 2119.60plantation or private source, lead within one mile(1.6 Km), and wattling between stakes andintertwining (thickness of wattled brushwood 1.0' (300 mm) average).

b) i) Supplying Bamboos 10'-1" to 12.0' (3.07 to 3.66 100 Nos - 10200.00 100 Nos - 10200m) long, 2½" to 5" (63 to 125 mm) dia.

ii) Sharpening one end of 10'-1" to 12.0' 100 Nos 456.20 - 100 Nos 456.20 -(3.07 to 3.66 m) long Bamboos, 2½" to5" (63 to 125 mm) dia.

chapter-16(Protec & Div) Page 109

Page 113: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

iii) Driving Bamboos 10'-1" to 12.0' (3.07 to 3.66 m) 100 Nos 813.65 - 100 Nos 813.65 -long 2½" to 5" (63 to 125 mm) dia, driven 2.75' (840 mm) below the available bed or ground (average).

iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per chain Per 30 MS.W.G. No. 10 wire, two lines, including tying around of one 145.20 755.90 of one Row 145.20 755.90the Bamboos and third tie around the top end only. row

v) Cutting and supplying brushwood from canal ditto 2108.70 2604.70 ditto 2108.70 2604.70plantation or private source, lead within one mile(1.6 Km) and wattling between stakes and intertwining(thickness of wattled brushwood 1.0' ( 300 mm)average).

c) i) Supplying Bamboos 12'-1" to 14.0' (3.68 to 4.27 100 Nos - 10800.00 100 Nos - 10800.00m) long, 2½" to 5" (63 to 125 mm) dia.

ii) Sharpening one end of 12'-1" to 14.0' (3.68 to 4.27 100 Nos 513.20 - 100 Nos 513.20 -m) long Bamboos, 2½" to 5" (63 to 125 mm) dia.

iii) Driving Bamboos 12'-1" to 14.0' (3.68 to 4.27 m) 100 Nos 931.40 - 100 Nos 931.40 -long 2½" to 5" dia, driven 3.5' (1.07 mm) below theavailable bed or ground (average).

iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per chain Per 30 MS.W.G. No. 10 wire, two lines, including tying around of one row 145.20 755.90 of one row 145.20 755.90the Bamboos and third tie around the top end only.

v) Cutting and supplying brushwood from canal ditto 2488.20 3059.40 ditto 2488.20 3059.40plantation or private source, lead within one mile(1.6 Km) and wattling between stakes and intertwining(thickness of wattled brushwood 1.0' (300 mm)average).

d) i) Supplying Bamboos 14'-1" to 16.0' (4.30 to 4.90 m) 100 Nos - 12000.00 100 Nos - 12000.00long, 2½" to 5" (63 to 125 mm) dia.

ii) Sharpening one end of 14'-1" to 16.0' (4.30 to 100 Nos 570.25 - 100 Nos 570.25 -4.90 m) long Bamboos, 2½" to 5" (63 to 125 mm) dia.

iii) Driving Bamboos 14'-1" to 16.0' long (4.30 to 4.90m) 100 Nos 1034.90 - 100 Nos 1034.90 -2½" to 5" (63 to 125 mm) dia, driven 4' (1.20 m)below the available bed or ground (average).

chapter-16(Protec & Div) Page 110

Page 114: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per Chain Per 30 MS.W.G. No. 10 wire, two lines, including tying around of one 145.20 755.90 of one 145.20 755.90the Bamboos and third tie around the top end only. Row Row

v) Cutting and supplying brushwood from canal ditto 2869.70 3531.00 ditto 2869.70 3531.00plantation or private source, lead within one mile(1.6 Km) and wattling between stakes and intertwining(thickness of wattled brushwood 1.0' (300 mm)average).

e) i) Supplying Bamboos 16'-1" to 20' (4.9 to 6.10 m) 100 Nos - 12600.00 100 Nos - 12600.00long, 2½" to 5" (63 to 125 mm) dia.

ii) Sharpening one end of 16'-1" to 20' (4.9 to 100 Nos 684.30 - 100 Nos 684.30 -6.10 m) long Bamboos, 2½" to 5" (63 to 125 mm) dia.

iii) Driving Bamboos 16'-1" to 20' long (4.9 to 6.10 m) 100 Nos 1241.85 - 100 Nos 1241.85 -2½" to 5" (63 to 125 mm) dia, driven 4' (1.20 m)below the available bed or ground (average).

iv) Tying Bamboos 2½" to 5" (63 to 125 mm) dia with Per Chain Per 30 MS.W.G. No. 10 wire, two lines, including tying around of one 145.20 755.90 of one 145.20 755.90the Bamboos and third tie around the top end only. row row

v) Cutting and supplying brushwood from canal ditto 3603.60 4445.20 ditto 3603.60 4445.20plantation or private source, lead within one mile (1.6 Km) and wattling between stakes and intertwining(thickness of wattled brushwood 1.0' (300 mm) average).

43 Cutting and supplying brushwood from canal plantation or 100Cft. 145.20 205.20 cu.m 51.30 72.50 Royalty to be paid to the Forestfrom any other source, within one mile (1.6 Km). Department or cost to the private

owner, if and when required.

44 Filling brush wood only, thoroughly packed. 100Cft. 116.15 - cu.m 41.05 - Measured in compacted andpacked shape before filling.

45 Covering road 10' to 12' (3.00 to 3.65 m) wide, with 3" Per 278.80 - Per 278.80 -(75 mm) sarkanda or jungle upto one chain lead (30 m). Chain 30 M

46 a) Gachi pitching 1' (300 mm) thick. 100Sft. 1510.10 - Sq.m 162.50 -b) Gachi pitching done with silt clearance 100Sft. 1277.75 - Sq.m 137.50 -

and berm dressing.

chapter-16(Protec & Div) Page 111

Page 115: 26467Sahiwal_1st_010

OUTLETSRates for all finished works include the removal of surplus debris, unused material and byproduc

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Earthwork for outlets, excavation refilling, ramming and 17.1 Includes consolidation of earth afterpuddling:- to refilling.

17.5a) channels, discharge upto 50 cusecs. Job 484.00 - Job 484.00 -

b) channels, discharge from 51 to 100 cusecs. Job 638.90 - Job 638.90 -

c) channels, discharge from 101 to 200 cusecs. Job 968.00 - Job 968.00 -

d) channels, discharge from 201 to 350 cusecs. Job 1306.80 - Job 1306.80 -

e) channels, discharge over 350 cusecs. Job 1936.00 - Job 1936.00 -

2 Dismantling outlets:- 18.1 These rates are for totaldismantlement and removal

a) old types, such as K.G.O's orifices, etc. Each 484.00 - Each 484.00 - of material. The rates do notinclude earth work for which

b) A.P.M. or O.F., "H" upto 2.0 ft. (600 mm) ditto 726.00 - ditto 726.00 - rates are given in item 1,above.

c) A.P.M. or O.F., "H" from 2.1 ft. to 3.0'. ditto 968.00 - ditto 968.00 -(630 mm to 900 mm)

d) A.P.M. or O.F., "H" above 3.0'. ditto 1210.00 - ditto 1210.00 -(900 mm)

e) Tail cluster bifurcation ditto 726.00 - ditto 726.00 -

f) Tail cluster trifurcation ditto 968.00 - ditto 968.00 -

g) Tail cluster quardification ditto 1210.00 - ditto 1210.00 -

3 Making temporary A.P.M. bricks block and fixing at site. Each 278.80 439.60 Each 278.80 439.60 21.1 & 21.2

4 Dismantling walls, taking out temporary Job 564.95 - Job 564.95 - 18.1, 21.1A.P.M. brick block, fixing iron block and & 21.2rebuilding dismantled walls

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-17(Outlet) Page 112

Page 116: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

5 Dismantling walls and fitting iron block of O.F. outlet. Each 564.95 - Each 564.95 - 18.1, 21.1

& 21.2

6 Constructing, watching and removing bund for outlet built 17.1in running water:- to

17.2a) upto 3.0' (0.300 m) depth Each 1161.60 - Each 1161.60 -b) above 3.0' (0.300 m) depth ditto 1568.15 - ditto 1568.15 -

7 Adjusting "B" of tail cluster by dismantling and rebuilding Each 293.05 517.90 Each 293.05 517.90 18.1, 21.1throat walls. & 21.2

8 Adjusting "Y" of an A.P.M. outlet, including dismantling Each 567.60 926.40 Each 567.60 926.40 ditto

and rebuilding.

9 Extra labour in fixing A.P.M. and O.F. outlet blocks, 21.1 & 21.2 Rates to be Rs. 4.00 less in caseincluding dressing of bricks:- of O.F. outlets, where there is no

O.F. iron block.a) for channel depth of 5.0'. (1.5 m) Each 675.85 747.35 Each 675.85 747.35b) for channel depth of 4.0'. (1.2 m) ditto 506.90 578.45 ditto 506.90 578.45c) for channel depth of 3.0'. (900 mm) ditto 405.50 477.00 ditto 405.50 477.00d) for channel depth of 2.0'. (600 mm) ditto 337.90 394.55 ditto 337.90 394.55e) for channel depth of less than 2.0'. (600 mm) ditto 270.35 312.10 ditto 270.35 312.10

10 Repairing damaged reducing collar of Hume pipe outlets. Each 278.80 407.20 Each 278.80 407.20

11 Laying iron pipes for outlets. Per Lft. 13.50 - Metre 44.35 - 21.1, 21.2& 17.1 to

17.5

12 Water allowance for constructing outlets or culverts, when Each 236.20 Each 236.20 At the discretion of thecanal water is not flowing. to to Engineer-in-charge depending upon

484.00 484.00 the distance and source of supply.

13 Hoisting and placing R.C. slab or stone in position on Each 199.75 - Each 199.75 -outlets or W.C. culverts.

14 Fixing pipe outlet, including back filling of earth and 17.1 to 17.5puddling:- & 21.1 to

21.2a) portion under bank. Rft. 47.95 52.75 Metre 157.35 173 b) portion under road, beyond bank. ditto 21.90 26.70 ditto 71.90 87.55

chapter-17(Outlet) Page 113

Page 117: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

15 Removing pipe outlet, refilling earth and puddling. 17.1to

a) portion under bank. Rft. 38.70 - Metre 127.05 - 17.5b) portion under road, beyond bank. ditto 14.50 - ditto 47.65 -

16 Changing pipe outlets by removing one pipe and replacinit at the same site with another pipe complete with eartand puddling.

a) portion under bank. Rft. 55.80 60.55 Metre 183.05 198.7b) portion under road, beyond bank ditto 27.90 32.65 ditto 91.50 107.15

chapter-17(Outlet) Page 114

Page 118: 26467Sahiwal_1st_010

ROAD & ROAD STRUCTURE

1 Specification No. correspond to Book of "Standard Specification for Road and Bridge Construction 1971".2 Rates for all finished works include the removal of surplus debris, unused material and byproducts.3 The rates include the provision and maintenance of field test laboratory, pay of laboratory staff, cost of material for testing, etc.

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

Sub-base & base construction

1 Providing and laying sub-base course of brick on edge 100Cft. 1806.05 7278.05 cu.m 637.90 2570.60 521-1 The nominal thickness of bricks shall4½" (113 mm) thick, including compaction to required to be taken for the purpose ofcamber and grade. 521-6 measurement and payment.

2 Providing and laying sub-base course of brick aggregate, 100Cft. 1489.80 2326.80 cu.m 526.20 821.85 501-1 To be used only when brickincluding compaction of sub-base course material to to aggregate is cheaper than stonerequired depth, camber, grade & density. 501-6 aggregate.

3 a) Providing and laying sub-base course of stone product dittoof approved quality and grade, including placing, mixing,spreading and compaction of sub-base material torequired depth, camber, grade to achieve 100%maximum modified AASHO dry density, includingcarriage of all material to site of work except gravel and.aggregate.

i) Pit run or bed run gravel. 100Cft. 1489.80 1921.80 cu.m 526.20 678.80ii) Crushed stone aggregate. 100Cft. 1489.80 2029.80 cu.m 526.20 716.95

(b) Subsequent carriage of gravel and crushed stone 100Cft. of 1) The carriage of the whole distanceaggregate consoli- to the site of work shall be

dated calculated on the basis of the ratessub-base of the actual means of transport

used in carriage, i.e. road and/or rail,as the case may be.

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-18(R & Road Struc) Page 115

Page 119: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

2) It shall be payable from thenearest approved quarry.

4 a) Providing and laying base course of crushed stone 100Cft. 1668.00 3216.00 cu.m 589.15 1135.90 501-1aggregate of approved quality and grade, and supply and tospreading of stone screening, including placing, mixing, 501-6spreading and compaction of base course material torequired depth, camber and grade to achieve 100%maximum modified AASHO dry density, includingcarriage of all materials to site of work except gravel and.aggregate.

b) Subsequent carriage of crushed stone aggregate. 100Cft. of 1) The carriage for the wholeconsole- distance to the site of work shall bedated calculated on the basis of the ratesbase of the actual means of transport

used in carriage, i.e. road and/orrail, as the case may be.

2) It shall be payable from thenearest approved quarry.

5 Providing and laying road edging of 3" (75 mm) wide and Per Rft. 4.55 15.25 Metre 14.95 50.10 552-1 to9" (225 mm) deep brick on end, complete in all respects. 552-5

Bituminous Work & Resurfacing

6 Providing and laying bituminous priming coat, using 10 100Sft. 58.10 699.60 sq.m 6.25 75.30 601-1 tolbs. kerosene oil and 10 lbs. binder per 100 Sft. or 0.5 Kg 601-6kerosene and 0.5 Kg binder per square metre.

3) The quantity of pit run or bed run graveland crushed stone aggregate for payment ofcarriage shall be taken as per actual loosevolume but not more than 120 Cft.

3) The quantity of crushed stone aggregatefor payment of carriage shall be taken asper actual loose volume but not more than122 Cft.

chapter-18(R & Road Struc) Page 116

Page 120: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

7 Providing and laying bituminous tack coat, using 10 lbs. of 100Sft. 58.10 368.55 sq.m 6.25 39.65 611-1 tobitumen per 100 Sft (0.49 Kg of bitumen per sq.m.) 611-5

8 a) Providing surface treatment to roads, including supply 612-1 to

of bitumen and bajri/crushed stone aggregate of 612-6approved quality, including cleaning of road surface,heating and spraying bitumen, spreading bajri and rollingwith road roller (including its operation cost, fuel andhire charges, etc.) etc. complete including carriage of allmaterials to site of work except bajjri/crushed stone aggregate.

1) 1st coat:-

i) 40 lbs. bitumen, and 5.5 Cft. bajri of nominal size 1" (25 100Sft. 68.70 1525.55 Sq.m 7.40 164.15mm) per 100 sq. feet or 1.96 Kg bitumen and 0.017cu.metre bajri per square metre..

ii) 35 lbs. bitumen, and 4.0 Cft. bajri of nominal size ¾" 100Sft. 68.70 1334.45 Sq.m 7.40 143.60(20 mm) per %Sft. or 1.72 Kg bitumen and 0.013 cu.metrebajri per sq.metre.

2) 2nd coat:-

i) 25 lbs. bitumen, and 2.75 Cft. bajri of nominal size ½" 100Sft. 52.85 955.60 Sq.m 5.70 102.80(13 mm) per %sft or 1.23 Kg bitumen and 0.008 cu. metre bajri persq.metre.

ii) 18 lbs. bitumen, and 2.0 Cft. bajri of nominal size 3/8" 100Sft. 52.85 703.15 Sq.m 5.70 75.65(10 mm) per %Sft. or 0.89 Kg bitumen and 0.006 cu.metrebajri per sq. metre.

3) 3rd coat:-

14 lbs. bitumen, and 1.5 Cft. bajri of nominal size ¼" (6 100Sft. 36.15 541.00 sq.m 3.90 58.20mm) per %sft or 0.69 Kg bitumen and 0.005 cubic metre bajjri per sq.metre.

chapter-18(R & Road Struc) Page 117

Page 121: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

b) Subsequent carriage of crushed stone aggregate/bajri, 100Cft. cu.m 1) The carriage for the wholedistance to the site of work shall becalculated on the basis of the ratesof the actual means of transportused in carriage, i.e. road and/or rail,as the case may be.

2) It shal be payable from thenearest approved quarry.

9 a) Resurfacing of road, including supply of bitumen and 612-1bajri/crushed stone aggregate of approved quality, toincluding cleaning of road surface, heating and spraying 612-6of bitumen, and spreading bajri/crushed stoneaggregate and rolling with road roller (including itsoperation cost, fuel and hire charges, etc.) complete,including carriage of all materials to site of work.

i) 22 lbs. bitumen, and 2.5 Cft. bajri of nominal size ½" 100Sft. 45.80 841.05 sq.m 4.95 90.50(13 mm) per %Sft. or 1.07 Kg bitumen and bajjri 0.007 cu.mper sq.m.

ii) 20 lbs. bitumen, and 2.0 Cft. bajri of nominal size 3/8" 100Sft. 45.80 764.75 sq.m 4.95 82.30(10 mm) per % Sft. or 0.79 Kg bitumen and 0.006cu.metre bajri per sq.metre.

b) Subsequent carriage of crushed stone aggregate/bajri. 100Cft. cu.m Same remarks as againstitem 8(b) above.

10 Providing and laying plant premixed bituminous carpet, per inch per 25mm 641-1 toincluding compaction and finishing to required camber, grade thickness thickness 642-6and density. per 100Sft. per Sq.m (i) 3% Bitumen -do- 764.80 2336.50 -do- 82.35 251.50(ii) 3.5% Bitumen -do- 764.80 2526.75 -do- 82.35 272.00(iii) 4% Bitumen -do- 764.80 2717.00 -do- 82.35 292.45(iv) 4.5% Bitumen -do- 764.80 2907.30 -do- 82.35 312.95(v) 5% Bitumen -do- 764.80 3097.40 -do- 82.35 333.40(vi) 5.5% Bitumen -do- 764.80 3287.80 -do- 82.35 353.90(vii) 6% Bitumen -do- 764.80 3478.05 -do- 82.35 374.40

chapter-18(R & Road Struc) Page 118

Page 122: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

11 Scarifying old road surface including removal of debris within 100Sft. 96.80 - Sq.m 10.40 -1 chain (30 m).

Incidental Construction

12 Providing R.C.C. railing on bridges, as per standard drawing. Per Rft. 57.60 730.55 Metre 189.00 2396.75 901-1 The rate includes cost of steel, itsto fabrication, laying in position and

901-4 fastening, including cost of bindingwire and removal of rust from thebars, etc.

13 Providing and fixing G.I. pipe railing, as per Per Rft. of 41.75 478.60 Metre 136.90 1570.25 dittostandard drawing. 3 rows of

Pipes

14 Providing and fixing steel bearings of standard quality and Each Set - 2184.00 Each set - 2184.00 911-1 totype at site of work. of one of one 911-6

end end

15 Providing and fixing rubber bearing pad at site Per - 15.60 cu.cm - 0.95 dittoof work. Cu. Inch

16 Providing and laying expansion joint of neoprine strip 4"x¼" Per Rft. 35.65 128.30 Metre 116.95 420.90 921-1 to(100 mmx 6 mm) and plastic bitumen. 921-4

17 Providing and fixing rain water outlet of A.C. pipe. Each 17.80 194.40 Each 17.80 194.40 931-1 to933-4

18 Providing and erection at site of work:- 941-1 to The rate is for complete item of941-5 work according to Standard design

i) R.C.C. mile/Km. stone Each 1099.35 2646.00 Each 1099.35 2646.00 including cement concreteii) R.C.C. furlong/½ Km. stone Each 53.15 217.00 Each 53.15 217.00 foundation block and paintingiii) R.C.C. boundary pillar. Each 98.40 338.15 Each 98.40 338.15 letters etc.iv) Sign post of M.S. plate 1/8" thick (3 mm)

a) Mandatory. Each 362.90 3461.00 Each 362.90 3461.00b) Warning/Direction/Informatory. Each 351.50 3222.10 Each 351.50 3222.10

19 Providing and laying dry brick pavement/soling in streets or 100Cft. 1279.75 6751.75 cu.m 452.00 2384.70 The nominal thickness of bricks (2-11/16")roads, etc. sand grounted, laid in proper camber, including shall be taken for the purpose ofpreparation, watering, compaction of bed to proper camber, measurement and payment.and sand cushion. ( 9" x 4-3/8"x 2-11/16")

chapter-18(R & Road Struc) Page 119

Page 123: 26467Sahiwal_1st_010

PLUMBING, SANITARY INSTALLATION & GAS FITTINGS1 Rates for all finished works include the removal of surplus debris, unused material & by products.2 The material used shall conform to Schedule of Rates, Vol. I, Part I, (Specifications for Materials of

Construction, 1964, and the work will be executed according to Buildings & Roads Department Specifications,Vol II, 1966 (Public Health Works).

3 The rates include cutting and making good of the surface of walls, roof, floor, etc. where necessary.

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Providing and fitting glazed earthen ware water closetEuropean type, excluding seat and cover:-

i) white Each 194.70 1,861.55 Each 194.70 1,861.55 ii) coloured Each 194.70 1,365.95 Each 194.70 1,365.95

2 Providing and fixing, double seat and cover only.

i) bakelite Each 2.20 362.20 Each 2.20 362.20 ii) plastic Each 2.20 230.20 Each 2.20 230.20

3 Providing and fitting glazed earthen ware water closet,squatter type (Orisa pattern), combined with foot rest.

i) white Each 141.90 1,048.80 Each 141.90 1,048.80 ii) coloured Each 141.90 1,192.80 Each 141.90 1,192.80

4 Providing and fitting white glazed earthen ware water closet, Each 141.90 1,795.50 Each 141.90 1,795.50 squartter type, with separate foot rest.

5 Providing and fitting water closet, squatter type of terrazzo Each 141.90 448.80 Each 141.90 448.80 concrete.

6 Providing and fitting glazed earthen ware wash hand basin56x40 cm (22"x16") including bracket set, waste pipe andwaste coupling, etc.i) white, with pedestal Each 178.20 2,157.00 Each 178.20 2,157.00 ii) coloured, with pedestal Each 178.20 2,303.40 Each 178.20 2,303.40 iii) white, without pedestal Each 160.05 1,454.85 Each 160.05 1,454.85 iv) coloured, without pedestal Each 160.05 1,512.45 Each 160.05 1,512.45

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-19(PSI & GF) Page 120

Page 124: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

7 Providing and fixing stainless steel sink with drain board, size Each 160.05 4,009.30 Each 160.05 4,009.30 120x60 cm (48"x24") including bracket set, waste pipe andwaste coupling.

8 Providing and fitting terrazzo concrete sink 60x45 cm (24"x18") Each 160.05 958.55 Each 160.05 958.55 with drain board of mosaic, including bracket set, waste pipeand waste coupling.

9 Providing and fixing glazed earthen ware sink, includingbracket set, waste pipe and waste coupling:-

i) 60x45 cm (24"x18") Each 160.05 1,432.75 Each 160.05 1,432.75 ii) 37.5x45 cm (15"x18") Each 160.05 1,252.75 Each 160.05 1,252.75

10 Providing and fixing glazed earthen ware flat back urinal. Each 105.60 769.20 Each 105.60 769.20

11 Providing and fitting glazed earthen ware low down flushingcistern 13,63 litres (3 gallons) capacity, including bracketset, copper connection, etc.

i) white Each 160.05 1,110.70 Each 160.05 1,110.70 ii) coloured Each 160.05 1,191.10 Each 160.05 1,191.10

12 Providing and fitting plastic made low down flushing cistern1363 litre (3 gallons) capacity, including bracket set, copperconnection, etc. complete.

i) white Each 160.05 966.70 Each 160.05 966.70 If rubber connection is used, theii) coloured Each 160.05 966.70 Each 160.05 966.70 composite rate will be reduced by

Rs. 12.50

13 Providing and fixing white enameled cast iron low down flushing Each 160.05 1,102.95 Each 160.05 1,102.95 cistern 13.63 litres (3 gallons) capacity, including bracketset, copper connection, etc.

14 Providing and fixing cast iron high level flushing cisternincluding cost of bracket set, copper connection, etc.

i) 13.63 litres (3 gallons) capacity Each 170.60 2,181.55 Each 170.60 2,181.55 ii) 4.55 litres (1 gallon) capacity Each 170.60 1,401.55 Each 170.60 1,401.55

15 Providing and fixing, chromium plated soap dish. Each 10.55 168.95 Each 10.55 168.95

chapter-19(PSI & GF) Page 121

Page 125: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

16 Providing and fitting, glazed earthen ware soap dish.

i) white Each 10.55 432.95 Each 10.55 432.95 ii) coloured Each 10.55 216.95 Each 10.55 216.95

17 Providing and fixing, chromium plated toilet paper holder. Each 14.10 291.40 Each 14.10 291.40

18 Providing and fixing, chromium plated towel rail:-

i) 60 cm (24") long, and 2 cm (¾") dia. Each 14.10 317.70 Each 14.10 317.70 ii) 50 cm (20") long, and 1.5 cm (½") dia. Each 14.10 287.70 Each 14.10 287.70

19 Providing and fixing looking glass 55x40 cm (22"x16") size, Each 26.40 343.20 Each 26.40 343.20 and 5 mm thick, first quality.

20 Providing and fixing glass shelf 60x13 cm (24"x5"), with5mm thick glass:-

i) with chromium plated brackets and railing. Each 31.95 309.25 Each 31.95 309.25 ii) glass shelf only, without chromium plated brackets Each 21.10 63.10 Each 21.10 63.10

and railing.

21 Providing and fitting glazed earthen ware shelf 60x13 cm (24"x5"), with chromium plated bracket and railing:-

i) White Each 31.95 639.25 Each 31.95 639.25 ii) Coloured Each 31.95 699.25 Each 31.95 699.25

22 Providing and fitting:-

i) plastic soap dish Each 10.55 146.80 Each 10.55 146.80 ii) plastic toilet paper holder Each 14.10 155.80 Each 14.10 155.80 iii) plastic towel rail Each 14.10 215.80 Each 14.10 215.80 iv) plastic shelf 60x13 cm (24"x5") with bracket and railing. Each 14.10 369.50 Each 14.10 369.50

23 Providing and fixing chromium plated pillar-cock, heavy:-

i) 2 cm (¾") Each 14.10 494.10 Each 14.10 494.10 ii) 1.5 cm (½") Each 14.10 651.30 Each 14.10 651.30

24 Providing and fixing chromium plated stop cock, heavy:-

i) 2 cm (¾") Each 14.10 278.10 Each 14.10 278.10 ii) 1.5 cm (½") Each 14.10 173.70 Each 14.10 173.70

chapter-19(PSI & GF) Page 122

Page 126: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

25 Providing and fixing underground stop cock 13 mm (½"), Each 20.00 439.35 Each 20.00 439.35 with chromium plated cover.

26 Providing and fixing chromium plated bib cock:-i) 2 cm (¾") Each 14.10 368.10 Each 14.10 368.10 ii) 1.5 cm (½") Each 14.10 299.70 Each 14.10 299.70

27 Providing and fixing chromium plated tee stop cock Each 14.10 426.90 Each 14.10 426.90 15mm (½").

28 Providing and fixing chromium plated shower rose:-

i) 1.5x10 cm (½"x4") Each 14.10 312.90 Each 14.10 312.90 ii) 2x15 cm (¾"x6") Each 14.10 374.10 Each 14.10 374.10

29 Providing and fixing, chromium plated mixing valve, for wash Each 17.60 1,449.20 Each 17.60 1,449.20 hand basin, sink or shower.

30 Providing and fixing gun metal peet/gate valve (screwed):- For brass peet/gate valve (screwed),the composite rates of items (i) to (v)

i) 30 mm (1¼") dia Each 21.10 405.10 Each 21.10 405.10 will be reduced by Rs. 66, 77, 95, 107ii) 40 mm(1½") dia Each 21.10 561.10 Each 21.10 561.10 and 120 respectively.iii) 50 mm(2") dia Each 21.10 765.10 Each 21.10 765.10 iv) 65 mm(2½") dia Each 21.10 1,209.10 Each 21.10 1,209.10 v) 80 mm(3") dia Each 21.10 1,791.10 Each 21.10 1,791.10

31 Providing and fitting, chromium plated or brass oxidised,swan neck cock 15 mm (½") dia.

i) single way Each 14.10 350.10 Each 14.10 350.10 ii) two way Each 21.10 603.10 Each 21.10 603.10 iii) three way Each 28.15 730.15 Each 28.15 730.15

32 Providing and fixing, union brass cock.

i) 13 mm (½") dia Each 14.10 68.10 Each 14.10 68.10 ii) 20 mm (¾") dia Each 14.10 206.10 Each 14.10 206.10

33 Providing and fixing, floor trap of cast iron, including concrete

chamber all round, and C.I. grating:-

i) 10x5 cm (4"x2") Each 42.25 340.50 Each 42.25 340.50 ii) 10x7.5 cm (4"x3") Each 42.25 328.50 Each 42.25 328.50

chapter-19(PSI & GF) Page 123

Page 127: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

34 Providing and fitting "P" trap:-

i) 10 cm (4") of cast iron. Each 35.20 403.85 Each 35.20 403.85 ii) 10 cm (4") glazed. Each 35.20 103.85 Each 35.20 103.85

35 Providing and fitting 10 cm (4") gully trap, including cement Each 52.80 478.45 Each 52.80 478.45

concrete, cost of PVC grating 15x15 cm (6"x6") andmasonry chamber 30x30 cm (12"x12").

36 Providing and fitting, cast iron soil pipe with:-

i) lead caulked, yarn joint:-

a) 10 cm (4") i/d Per foot 15.30 184.95 Metre 50.15 606.55 b) 5 cm (2") i/d Per foot 6.10 92.60 Metre 20.05 303.70

ii) cement caulked joint:-

a) 10 cm (4") i/d Per foot 3.75 120.75 Metre 12.40 396.05 b) 5 cm (2") i/d Per foot 1.50 82.50 Metre 4.95 270.60

37 Providing and fitting, A.C. soil pipe with cement caulkedjoint, including all specials:-

i) 60 (2¼)" mm i/d Per foot 3.00 24.80 Metre 9.90 81.30 ii) 80 (3") mm i/d Per foot 3.35 61.35 Metre 11.00 201.20 iii) 100 (4") mm i/d Per foot 3.75 95.85 Metre 12.40 314.45 iv) 150 (6") mm i/d Per foot 5.05 120.20 Metre 16.50 394.15

38 Providing and fitting cast iron specials, such as tee bend, In case of plug type, the compositecollar, cross, etc. plain type:- rate shall be increased by Rs.2 per kg.

i) lead caulked joint Kg 12.85 131.80 Kg 12.85 131.80 ii) cement caulked joint Kg 7.90 98.70 Kg 7.90 98.70

39 Supply and fitting of cast iron manhole coverwith frame, etc. complete.

i) 30 cm (12") dia Each 21.10 165.10 Each 21.10 165.10 ii) 45 cm (18") dia Each 21.10 771.10 Each 21.10 771.10 iii) 60 cm (24") dia Each 33.00 1,245.00 Each 33.00 1,245.00

40 Providing and fitting R.C.C. pipe 10 cm (4") dia, including Per foot 7.65 31.65 Metre 25.10 103.80 laying and jointing in trenches.

chapter-19(PSI & GF) Page 124

Page 128: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

41 Providing and fitting chromium plated or oxidised, gas cock 6'mm (¼"):-

i) single way Each 14.10 179.70 Each 14.10 179.70 ii) two way Each 21.10 273.10 Each 21.10 273.10 iii) three way Each 28.15 466.15 Each 28.15 466.15

42 Providing and fitting nipple or bush, 6 mm to Each 10.55 22.55 Each 10.55 22.55 10 mm (¼" to 3/8") i/d.

43 Providing and fixing, brass gas cock:-

a) 15 mm (½") dia Each 2.20 74.20 Each 2.20 74.20 b) 20 mm (¾") dia Each 80.00 92.20 Each 80.00 92.20

44 Providing and fixing brass stop cock/bib cock:-

a) 15 mm (½") dia Each 3.50 79.10 Each 3.50 79.10 b) 20 mm (¾") dia Each 3.50 111.50 Each 3.50 111.50

45 Hoisting and placing in position, precast R.C. latrine seats. Each 186.45 - Each 186.45 -

Replacement

1 Providing and fixing, chromium plated waste coupling:-

i) 3 cm (1¼") Each 21.10 117.10 Each 21.10 117.10 ii) 4 cm (1½") Each 21.10 123.10 Each 21.10 123.10

2 Providing and fixing rubber plug with chain:-

i) 3 cm (1¼") Each 0.85 45.25 Each 0.85 45.25 ii) 4 cm (1½") Each 0.85 42.85 Each 0.85 42.85

3 Providing and fixing, waste pipe of PVC:-

i) 3 cm (1¼") Each 10.55 40.55 Each 10.55 40.55 ii) 4 cm (1½") Each 10.55 52.55 Each 10.55 52.55

4 Providing and fixing, flushing bend of PVC.

i) 3 cm (1¼") Each 9.40 39.40 Each 9.40 39.40 ii) 4 cm (1½") Each 9.40 51.40 Each 9.40 51.40

chapter-19(PSI & GF) Page 125

Page 129: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

5 Providing and fixing chromium plated bottle trap with wastepipe, etc. complete:-

i) 3 cm (1¼") i/d Each 21.10 531.10 Each 21.10 531.10 ii) 4 cm (1½") Each 21.10 621.10 Each 21.10 621.10

6 Providing and fixing, angle iron brackets for:-

i) wash hand basin and cistern Each 21.10 133.90 Each 21.10 133.90 ii) sinks Each 21.10 145.90 Each 21.10 145.90

7 Providing and fixing 1.5 cm (½") dia connection, includingcheck nuts, etc.:-

i) plastic rubber connection Each 8.45 50.45 Each 8.45 50.45 ii) copper connection Each 8.45 80.45 Each 8.45 80.45

8 Providing and fixing brass ball float valve:-

i) 1.5 cm (½") dia Each 17.60 197.60 Each 17.60 197.60 ii) 2.0 cm (¾") dia Each 17.60 257.60 Each 17.60 257.60 iii) 2.5 cm (1") dia Each 17.60 317.60 Each 17.60 317.60 iv) 3 cm (1¼") dia Each 17.60 341.60 Each 17.60 341.60 v) 4.0 cm (1½") dia Each 17.60 485.60 Each 17.60 485.60 vi) 5 cm (2") dia Each 17.60 557.60 Each 17.60 557.60

chapter-19(PSI & GF) Page 126

Page 130: 26467Sahiwal_1st_010

SURFACE DRAINAGE1. Specification No. correspond to Book of Specification (B & R Department ) Vol. 11, 1966 (public Health Works).

2. Rates for all finished works include the removal of surplus debris, unused material and by produc

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Tega formed of pacca bricks on end, laid in and over 17.1cement sand mortar projecting to a height of not morethan 6" (150 mm) top of drain along the property sidewhere required, laid to lines, grades, slopes and shapeaccording to the Engineer's drawing:-

a) 3" thick (75 mm)

i) ratio 1:3 100Rft 587.55 1,878.85 Metre 19.25 61.65 ii) ratio 1:5 ditto 587.55 1,793.20 ditto 19.25 58.80

B) 4½" thick (113 mm)

i) ratio 1:3 100Rft 880.30 2,737.15 ditto 28.85 89.80 ii) ratio 1:5 ditto 880.30 2,603.30 ditto 28.85 85.40

2 Pacca flat brick 3" (75 mm ) thick, laid in reimbursement, 17.1in cement, sand mortar, on sides of drains and in otherworks where required. All joints to be completely filledand struck flush:-

a) ratio 1:3 100Sft. 868.65 2,684.25 Sqm. 93.45 288.85 b) ratio 1:5 ditto 868.65 2,543.25 ditto 93.45 273.65 c) ratio 1:6 ditto 868.65 2,503.40 ditto 93.45 269.35

3 Pacca brick on edge, laid in reimbursement, in cement, 17.1sand mortar, on sides of drains and on other works whererequired. All joints to be completely filled and struckflush:-

a) ratio 1:3 100Sft. 1,246.10 3,986.15 Sqm. 134.10 428.90 b) ratio 1:5 ditto 1,246.10 3,759.50 ditto 134.10 404.50 c) ratio 1:6 ditto 1,246.10 3,703.30 ditto 134.10 398.50

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-20(Surface Drainage) Page 127

Page 131: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

4 Pacca flat brick, Herring bond pitching in cement, sand 17.2mortar, laid to lines, grades, shapes and slopes as perEngineer's drawing:-

a) ratio 1:3 100Sft. 797.30 2,612.90 Sqm. 85.80 281.15 b) ratio 1:5 ditto 797.30 2,471.90 ditto 85.80 265.95 c) ratio 1:6 ditto 797.30 2,432.00 ditto 85.80 261.70

5 Pacca brick on edge, Herring bond pitching in cement, 17.2sand mortar, laid to lines, grades, shapes and slopes asper Engineer's drawing:-

a) ratio 1:3 100Sft. 1,210.20 3,950.25 Sqm. 130.20 425.05 b) ratio 1:5 ditto 1,210.20 3,723.60 ditto 130.20 400.65 c) ratio 1:6 ditto 1,210.20 3,667.40 ditto 130.20 394.60

6 Constructing Punjab Standard Drains. of cement concrete1:2 ½ :5, with cement concrete bedding ratio 1:6:12, 17.1complete, laid to lines, grades, slopes and shapes,rendering exposed surface of concrete with 1:1 cement,sand mortar, ¼" (6 mm) thick, as per Engineer's drawing(excluding excavation):-

a) Type I Per Rft 19.20 55.90 Metre 63.00 183.30 b) Type II ditto 38.40 100.20 ditto 126.00 328.65 c) Type III ditto 48.05 128.10 ditto 157.65 420.10 d) Type IV ditto 57.20 152.35 ditto 187.70 499.75 e) Type V ditto 75.05 207.75 ditto 246.10 681.45 f) Type VI ditto 86.20 237.70 ditto 282.75 779.60 g) Type VII ditto 95.55 261.25 ditto 313.40 856.90 h) Type VIII ditto 106.70 293.55 ditto 350.05 962.90 i) Type IX ditto 141.30 418.10 ditto 463.45 1,371.40 j) Type X ditto 155.25 458.05 ditto 509.25 1,502.45 k) Type XI ditto 173.70 509.45 ditto 569.80 1,671.00 l) Type XII ditto 185.20 539.70 ditto 607.45 1,770.20

7 Laying R.C.C hume pipes in position, including jointing:-a) 6" to 12" (150 mm to 300 mm ) dia Per Lft. 34.30 36.10 Metre 112.55 118.40 b) 12" to 24" (300 mm to 600 mm) dia ditto 51.75 55.30 ditto 169.70 181.35 c) 24" to 36" (600 mm to 900 mm) dia ditto 68.65 74.00 ditto 225.15 242.75

chapter-20(Surface Drainage) Page 128

Page 132: 26467Sahiwal_1st_010

SEWERAGE1 Specification No. correspond to Book of Specification of B&R Department Vol. II, 1966 (Public Health Works).2 Rate for all finished works include the removal of surplus debris, unused material and byproducts

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Providing and laying R.C.C. pipe, moulded with cement Chapter - 8concrete 1:1½:3, with spigot socket or collar joint, etc.including cost of reinforcement, conforming to B.S. 5911:Part I: 1981, Class "L" including carriage of pipe fromfactory to site of work, lowering in trenches to correctalignment and grade, jointing, cutting pipes wherenecessary, finishing and testing, etc., complete.

i) 100 mm (4") i/d Rft. 9.20 61.65 Metre 30.20 202.20ii) 150 mm (6") i/d Rft. 11.20 99.05 Metre 36.75 324.90iii) 225 mm (9:) i/d Rft. 21.65 177.90 Metre 71.00 583.50

2 Providing and laying non-reinforced concrete pipe, dittomoulded with cement concrete 1:1½:3, conforming toASTM Specification C-14-73, Class 2, including carriageof pipe from factory to site of work, lowering in trenches tocorrect alignment and grade, jointing, cutting pipe wherenecessary, finishing and testing, etc. complete.i) 100 mm (4") i/d Rft. 6.90 30.10 Metre 22.65 98.75ii) 150 mm (6") i/d Rft. 8.40 43.80 Metre 27.55 143.65iii) 200 mm (8") i/d Rft. 13.45 59.85 Metre 44.10 196.30iv) 225 mm (9:) i/d wall thickness 1 inch (25 mm) Rft. 14.65 77.05 Metre 48.05 252.70v) 250 mm (10") i/d Rft. 15.00 85.95 Metre 49.20 281.90

3 Providing and laying R.C.C. pipe sewers, moulded with dittocement concrete 1:1½:3 conforming to ASTMSpecification C-76-79, Class II. Wall B, including carriageof pipe from factory to site of work, lowering in trenches tocorrect alignment and grade, jointing with rubber ring,cutting pipes where necessary, testing, etc., complete.

i) 310 mm (12") i/d Rft. 22.75 275.00 Metre 74.60 902.00ii) 380 mm (15") i/d Rft. 28.65 336.60 Metre 93.95 1104.05iii) 460 mm (18") i/d Rft. 34.65 352.55 Metre 113.65 1156.35iv) 530 mm (21":) i/d Rft. 43.45 442.20 Metre 142.50 1450.40v) 610 mm (24") i/d Rft. 50.30 542.05 Metre 165.00 1777.90vi) 690 mm (27") i/d Rft. 72.55 856.00 Metre 237.95 2807.70vii) 760 mm (30") i/d Rft. 86.95 900.35 Metre 285.20 2953.15viii) 840 mm (33") i/d Rft. 108.00 1051.80 Metre 354.25 3449.90

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-21(Sewerage) Page 129

Page 133: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

ix) 910 mm (36") i/d Rft. 132.90 1413.75 Metre 435.90 4637.10x) 1070 mm (42") i/d Rft. 173.00 1710.00 Metre 567.45 5608.80xi) 1220 mm (48") i/d Rft. 320.10 2310.15 Metre 1049.95 7577.30xii 1370 mm (54") i/d Rft. 437.25 2937.15 Metre 1434.20 9633.85xiii) 1520 mm (60") i/d Rft. 564.35 3812.65 Metre 1851.05 12505.50xiv) 1680 mm (66") i/d Rft. 869.95 5124.05 Metre 2853.45 16806.90xv) 1830 mm (72") i/d Rft. 1073.35 5975.70 Metre 3520.60 19600.30

4 Providing and laying R.C.C. pipe sewers, moulded with Chapter-8cement concrete 1:1½:3 conforming to ASTM SpecificationC-76-79, Class III, Wall B, including carriage of pipes fromfactory to site of work, lowering in trenches to correctalignment and grade, jointing with rubber ring, cutting pipeswhere necessary, testing, etc. complete:-

i) 310 mm (12") i/d Rft. 22.75 320.85 Metre 74.60 1052.40ii) 380 mm (15") i/d Rft. 28.65 395.10 Metre 93.90 1295.95iii) 460 mm (18") i/d Rft. 34.65 469.50 Metre 113.55 1539.95iv) 530 mm (21":) i/d Rft. 43.45 558.95 Metre 142.50 1833.35v) 610 mm (24") i/d Rft. 50.30 670.95 Metre 164.95 2200.70vi) 690 mm (27") i/d Rft. 72.55 920.70 Metre 237.90 3019.90vii) 760 mm (30") i/d Rft. 86.95 1113.65 Metre 285.15 3652.75viii) 840 mm (33") i/d Rft. 108.00 1237.35 Metre 354.15 4058.50ix) 910 mm (36") i/d Rft. 132.90 1675.85 Metre 435.95 5496.80x) 1070 mm (42") i/d Rft. 173.00 1975.15 Metre 567.40 6478.50xi) 1220 mm (48") i/d Rft. 324.35 2397.95 Metre 1063.90 7865.30xii 1370 mm (54") i/d Rft. 443.15 3204.35 Metre 1453.60 10510.25xiii) 1520 mm (60") i/d Rft. 571.80 4143.00 Metre 1875.40 13589.05xiv) 1680 mm (66") i/d Rft. 881.85 5446.65 Metre 2892.45 17865.00xv) 1830 mm (72") i/d Rft. 1088.20 6401.80 Metre 3569.20 20997.90

5 Providing and laying R.C.C. pipe sewers, moulded with Chapter - 8cement concrete 1:1½:3 conforming to ASTMSpecification C-76-79, Class IV, Wall B, including carriageof pipes from factory to site of work, lowering in trenchesto correct alignment and grade, jointing with rubber ring,cutting pipes where necessary, testing, etc. complete:-

i) 310 mm (12") i/d Rft. 22.75 326.95 Metre 74.60 1072.40ii) 380 mm (15") i/d Rft. 28.65 401.25 Metre 93.90 1316.00iii) 460 mm (18") i/d Rft. 34.65 475.65 Metre 113.55 1560.05iv) 530 mm (21":) i/d Rft. 43.45 614.05 Metre 142.50 2014.05v) 610 mm (24") i/d Rft. 50.30 879.00 Metre 164.95 2883.15vi) 690 mm (27") i/d Rft. 72.55 1165.50 Metre 237.90 3822.80vii) 760 mm (30") i/d Rft. 86.95 1358.40 Metre 285.15 4455.70viii) 840 mm (33") i/d Rft. 108.00 1698.80 Metre 354.15 5572.10ix) 910 mm (36") i/d Rft. 132.90 2043.05 Metre 435.95 6701.30

chapter-21(Sewerage) Page 130

Page 134: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

x) 1070 mm (42") i/d Rft. 173.00 2464.75 Metre 567.40 8084.35xi) 1220 mm (48") i/d Rft. 324.35 2997.60 Metre 1063.65 9832.25xii) 1370 mm (54") i/d Rft. 443.15 3877.60 Metre 1453.80 12718.50xiii) 1520 mm (60") i/d Rft. 571.80 4999.80 Metre 1875.40 16399.25xiv) 1680 mm (66") i/d Rft. 881.85 6670.65 Metre 2892.45 21879.65xv) 1830 mm (72") i/d Rft. 1088.20 7368.75 Metre 3569.20 24169.45

6 Lowering of sub-soil water table, by installation of tubewells 1) This rate shall be payable, inalong sewer line and pumping out water, for excavation in addition to the item of excavationopen cutting below sub-soil water level, concreting, curing, below SSWL for sewers andlaying and jointing pipes, filling haunches, etc. till the manholes under Chapter,completion of sewer line, including disposal of pumped out EARTHWORKwater:- 2) The grant of these rates shall be

Rft of Metre of subject to Superintending Engineer's1) 0-1 ft. (0 to 310 mm) below SSWL laid sewer - 147.00 laid sewer - 482.10 approval.2) 0-2 ft. (0 to 610 mm) below SSWL ditto - 288.90 ditto - 947.603) 0-3 ft. (0 to 910 mm) below SSWL ditto - 488.75 ditto - 1603.10 3) The rate includes cost of4) 0-4 ft. (0 to 1220 mm) below SSWL ditto - 703.55 ditto - 2307.60 providing pumps, POL and all5) 0-5 ft. (0 to 1520 mm) below SSWL ditto - 973.45 ditto - 3192.90 operation charges at the site6) 0-6 ft. (0 to 1830 mm) below SSWL ditto - 1205.70 ditto - 3954.65 of work, etc.7) 0-7 ft. (0 to 2170 mm) below SSWL ditto - 1439.80 ditto - 4722.608) 0-8 ft. (0 to 2480 mm) below SSWL ditto - 1653.75 ditto - 5424.259) 0-9 ft. (0 to 2790 mm) below SSWL ditto - 1828.10 ditto - 5996.1010) 0-10 ft. (0 to 3100 mm) below SSWL ditto - 2103.35 ditto - 6899.0511) 0-11 ft. (0 to 3410 mm) below SSWL ditto - 2336.10 ditto - 7662.3512) 0-12 ft. (0 to 3720 mm) below SSWL ditto - 2587.30 ditto - 8486.30

7 Constructing gully grating chamber, 12"x12", ( 300x300 16.2 Pipe connection to be paidmm) complete in all respects: separately.

a) with C.I. gully trap, weighing 81 lbs. (36.75 Kg.) frame Each 395.25 1458.20 Each 395.25 1458.20hinged safety type.

b) concrete Gully trap. ditto 395.25 1498.20 ditto 395.25 1498.20

8 Constructing standard gully grating chamber, 3'x2½' Each 1204.25 4667.35 Each 1204.25 4667.35 ditto Pipe connection to be paid(900x750 mm), with chinaware trap as per PHED Drawing separately.STD/PD No. 3 of 1977, complete in all respects.

9 Extra for making and finishing benching floor work in 100Sft. 544.65 791.65 Sq.m 58.60 85.20 14.4manhole chamber, with 1/8" (3 mm) thick cement finish

10 Restoration of brick pavement on edge, over laid service 100Sft. 746.60 1598.00 Sq.m 80.35 171.95 13.1line, with 2" (50 mm) sand cushion under soling

chapter-21(Sewerage) Page 131

Page 135: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

11 Restoration of flat brick pavement sand grouted, over 2" 100Sft. 454.10 1089.75 Sq.m 48.85 117.25 13.1(50 mm) thick dry sand cushion, under soling on laidservice line.

12 Restoration of metalled road, on laid service line, including 13.1compaction:-

a) Carpetted road, with 2" (50 mm) carpet and 10" (250 100Sft. 1939.35 6343.05 Sq.m 208.65 682.50mm) depth of stone metal for sub-base and base

b) Carpeted road, with 1½" (38 mm) carpet and 6" (150 100Sft. 1396.05 4681.85 Sq.m 150.20 503.75mm) depth of stone metal, for sub-base and base

c) Black Topped Road with two coats of surfacing & 10" 100Sft. 535.40 2722.55 Sq.m 57.60 292.95(250 mm) depth of stone metal, for sub base & base

13 Providing and fixing 1¼"x1¼"x3/16" (31x31x5 mm) angle 14.7iron step, in manhole chambers, including carriage and Each 61.25 164.90 Each 61.25 164.90setting the same in work to correct lines and levels.

14 Fixing manhole frame and cover in R.C.C. slab including Per 141.40 - Per 141.40 - dittocarriage to site. set set

15 Providing and fixing 3" (75 mm) thick R.C.C. manhole Per 91.00 2364.30 Per 91.00 2364.30 dittocover, 22" (550 mm) dia, with tee shaped C.I. frame of 20" set set(500 mm) clear i/d (frame weighing 37.324 Kg. or onemaund) as per Standard Drawing STD/PD No. 5, of 1977,complete in all respects.

15-A Providing and fixing 6" thick R.C.C. manhole Per 171.35 3236.05 Per 171.35 3236.05cover with tee shaped C.I. frame of 22" I/d (frame set setweighing 37.324 Kg. or one maund as per StandardDrawing STD/PD No. 6, of 1977, complete in all respect.

16 Providing and fixing, 6" (150 mm) thick R.C.C. manhole Per 154.80 1688.05 Per 154.80 1688.05 dittocover for 22" as per standard drawing STD/PD No. 6 of set set1977, complete in all respects.

17 Providing and fixing, 6" (150 mm) thick R.C.C. manhole Per 134.65 2662.40 Per 134.65 2662.40 dittocover with 3"x3"x¼" (75x75x6mm) angle iron frame, 22" set set(550 mm) i/d as per standard drawing STD/PD No. 7 of1977, complete in all respects.

18 Desilting of disposal work collecting tank, including 100Cft. 331.90 386.15 cum 117.20 136.40 16.2removal of sludge within 3 chains (90 metre).

chapter-21(Sewerage) Page 132

Page 136: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

19 Providing and installing, C.I. ventilating shaft painted with 14.6bituminous paint with foundation bolts, as per PHEDStandard Drawing STD/PD No. 4 of 1977, complete in allrespects (except concrete foundation block):-

a) 6" (150 mm) i/d shaft

i) 18 ft. (5.5 metre) long Per Cwt 94.90 2126.45 %kg 186.75 4185.90ii) 24 ft. (7.30 metre) long ditto 105.40 2142.60 ditto 207.50 4217.70iii) 30 ft. (9.15 metre) long ditto 113.85 2149.70 ditto 224.10 4231.65iv) 36 ft. (11 metre) long ditto 119.15 2155.25 ditto 234.50 4242.65

b) 9" (225 mm) i/d shaft

i) 18 ft. (5.5 metre) long Per Cwt 83.95 2111.80 %kg 165.25 4157.05ii) 24 ft. (7.30 metre) long ditto 90.45 2117.80 ditto 178.10 4168.90iii) 30 ft. (9.15 metre) long ditto 96.85 2124.65 ditto 190.70 4182.40iv) 36 ft. (11 metre) long ditto 116.60 2144.20 ditto 229.55 4220.90

c) 12" (300 mm) i/d shaft

i) 18 ft. (5.5 metre) long Per Cwt 74.45 2103.40 %kg 146.50 4140.55ii) 24 ft. (7.30 metre) long ditto 95.70 2122.00 ditto 188.40 4177.15iii) 30 ft. (9.15 metre) long ditto 111.65 2137.30 ditto 219.80 4207.25

20 Silt clearing 10' (3.00 m) dia wells, andremoval of slush outside the compound:-

a) upto 10' (3.00 m) depth of slush Per well 2864.40 - Per well 2864.40 -b) beyond 10' (3.00 m) depth of slush Per well 5596.80 - Per well 5596.80 -

chapter-21(Sewerage) Page 133

Page 137: 26467Sahiwal_1st_010

SINKING OF WELLS1 Rates for all finished works include the removal of surplus debris, unused material and byproducts.2 Well curbs to be laid at spring level or as deep as possible.

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Excavation of well in dry upto 20'(6 metre) below groundlevel, and disposal of soil within one chain (30 metre)

a) in ordinary soil or sand :- 1000 Cft. cu.m

i) from 0' to 5' (o to 1.5 m) depth ditto 1726.15 - ditto 60.95 -ii) from 5.1' to 10' (1.5 to 3.0 metre) depth ditto 1802.80 - ditto 63.70 -iii) from 10.1' to 15' (3.0 to 4.5 metre) depth ditto 2028.15 - ditto 71.65 -iv) from 15.1' to 20' (4.5 metre to 6.0 metre) depth ditto 2327.85 - ditto 82.20 -

b) in hard soil

i) from 0' to 5'(0 to 1.5 metre) depth 1000 Cft. 2102.50 - cu.m 74.25 -ii) from 5.1' to 10'(1.5 to 3.0 metre) depth ditto 2197.75 - ditto 77.60 -iii) from 10.1' to 15'(3.0 to 4.5 metre) depth ditto 2402.20 - ditto 84.85 -iv) from 15.1' to 20'(4.5 to 6.0 metre) depth ditto 2701.90 - ditto 95.45 -

c) in hard strata, such as shingle, gravel, etc.

i) from 0' to 5'(0 to 1.5 metre) depth 1000 Cft. 4534.90 - cu.m 160.15 -ii) from 5.1' to 10'(1.5 to 3.0 metre) depth ditto 4697.50 - ditto 165.90 -iii) from 10.1' to 15'(3.0 to 4.5 metre) depth ditto 4897.30 - ditto 172.95 -iv) from 15.1' to 20'(4.5 to 6.0 metre ) depth ditto 5257.40 - ditto 185.70 -

2 Dry sinking of well, including loading, and removingexcavated material within one chain (30 m):-

a) in ordinary soil :-

i) from 10' to 15'(3.0 to 4.5 m) depth 1000 Cft. 9292.80 - cu.m 328.20ii) from 15.1' to 20'(4.5 to 6.0 m) depth ditto 11616.00 - ditto 410.30iii) from 20.1' to 25'(6.0 to 7.5 m) depth ditto 13939.20 - ditto 492.35iv) from 25.1' to 30'(7.5 to 9.0 m) depth ditto 16262.40 - ditto 574.40v) from 30.1' to 35'(9.0 to 10.5 m) depth ditto 18585.60 - ditto 656.45vi) from 35.1' to 40'(10.5 to 12.0 m) depth ditto 20908.80 - ditto 738.50vii) from 40.1'to 45'(12.0 to 13.5 m) depth ditto 23232.00 - ditto 820.55viii) from 45'(13.5 Sm) to any depth ditto 25555.20 - ditto 902.60

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-22(Sinking of Wells) Page 134

Page 138: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

b) in hard soil :-

i) from 10' to 15'(3.0 to 4.5 m) depth 1000 Cft. 12777.60 - cu.m 451.30 -ii) from 15.1' to 20'(4.5 to 6.0 m) depth ditto 15100.80 - ditto 533.35 -iii) from 20.1' to 25'(6.0 to 7.5 m) depth ditto 17424.00 - ditto 615.40 -iv) from 25.1' to 30'(7.5 to 9.0 m) depth ditto 19747.20 - ditto 697.45 -v) from 30.1' to 35'(9.0 to 10.5 m) depth ditto 22070.40 - ditto 779.55 -vi) from 35.1' to 40'(10.5 to 12.0 m) depth ditto 24393.60 - ditto 861.60 -vii) from 40.1' to 45'(12.0 to 13.5 m) depth ditto 26716.80 - ditto 943.65 -viii) from 45'(13.5 m) to any depth ditto 29040.00 - ditto 1025.70 -

c) in hard strata, such as shingle, gravel, etc.

i) from 10' to 15'(3.0 to 4.5 m) depth 1000 Cft. 17424.00 - cu.m 615.40 -ii) from 15.1' to 20'(4.5 to 6.0 m) depth ditto 19747.20 - ditto 697.45 -iii) from 20.1' to 25'(6.0 to 7.5 m) depth ditto 22070.40 - ditto 779.55 -iv) from 25.1' to 30'(7.5 to 9.0 m) depth ditto 22360.80 - ditto 789.80 -v) from 30.1' to 35'(9.0 to 10.5 m) depth ditto 26716.80 - ditto 943.65 -vi) from 35.1' to 40'(10.5 to 12.0 m) depth ditto 29040.00 - ditto 1025.70 -vii)from 40.1' to 45'(12.0 to 13.5 m) depth ditto 31363.20 - ditto 1107.75 -viii) from 45'-1" (13.5 m) to any depth ditto 33686.40 - ditto 1189.80 -

3 Wet sinking of well in ordinary soil (value of C upto 5), for *841-1 The outer dimensions of the curbdepths below spring level, including charges of machinery, to shall form basis of payment.shoring, kentledge and removal of excavated spoil within 841-9one chain (30 m):-

i) from o' to 10'(0 to 3.0 m) depth 1000 Cft. 15218.80 - cu.m 537.55 -ii) above 10' to 20'(3.0 to 6.0 m) depth ditto 32340.00 - ditto 1142.25 -iii) above 20' to 30'(6.0 to 9.0 m) depth ditto 39803.10 - ditto 1405.85 -iv) above 30' to 40'(9.0 to 12.0 m) depth ditto 51744.00 - ditto 1827.60 -v) above 40' to 50'(12.0 to 15.0 m) depth ditto 57493.35 - ditto 2030.65 -vi) above 50' to 60'(15.0 to 18.0 m) depth ditto 64680.00 - ditto 2284.50 -vii) above 60' to 70'(18.0 to 21.0 m) depth ditto 66338.45 - ditto 2343.10 -viii) above 70' to 80'(21.0 to 24.0 m) depth ditto 68084.20 - ditto 2404.75 -ix) above 80'(24.0 m) to any depth ditto 73920.00 - ditto 2610.85 -

chapter-22(Sinking of Wells) Page 135

Page 139: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

4 Wet sinking of well in cohesive soil (value of Cmore than *841-1 The outer dimensions of the curb5), for depths below spring level, including charges of to shall form basis of payment.machinery shoring, kentledge and removal of excavated 841-9spoil within one chain (30 m):-

i) from o' to 10'(0 to 3.0 m) depth 1000 Cft. - 25577.35 cu.m - 903.40ii) above 10' to 20'(3.0 to 6.0 m) depth ditto - 31971.70 ditto - 1129.25iii) above 20' to 30'(6.0 to 9.0 m) depth ditto - 38366.00 ditto - 1355.10iv) above 30' to 40'(9.0 to 12.0 m) depth ditto - 51154.70 ditto - 1806.80v) above 40' to 50'(12.0 to 15.0 m) depth ditto - 59024.65 ditto - 2084.75vi) above 50' to 60'(15.0 to 18.0 m) depth ditto - 63943.35 ditto - 2258.50vii) above 60' to 70'(18.0 to 21.0 m) depth ditto - 69756.40 ditto - 2463.80viii) above 70' to 80'(21.0 to 24.0 m) depth ditto - 72388.70 ditto - 2556.75ix) above 80'(24.0 m) to any depth ditto - 76732.05 ditto - 2710.20

5 Wet sinking of well in shingle, or gravel, etc, for depths *841-1 The outer dimensions of the curbbelow spring level, including charges of machinery, to shall form basis of payment.shoring, kentledge and removal of excavated spoil within 841-9one chain (30 m) :-i) from o' to 10'(0 to 3.0 m) depth 1000 Cft. - 34878.20 cu.m - 1231.90ii) above 10' to 20'(3.0 to 6.0 m) depth ditto - 42628.90 ditto - 1505.65iii) above 20' to 30'(6.0 to 9.0 m) depth ditto - 51154.70 ditto - 1806.80iv) above 30' to 40'(9.0 to 12.0 m) depth ditto - 69756.40 ditto - 2463.80v) above 40' to 50'(12.0 to 15.0 m) depth ditto - 76732.05 ditto - 2710.20vi) above 50' to 60'(15.0 to 18.0 m) depth ditto - 85257.80 ditto - 3011.30vii) above 60' to 70'(18.0 to 21.0 m) depth ditto - 89223.30 ditto - 3151.35viii) above 70' to 80'(21.0 to 24.0 m) depth ditto - 91347.65 ditto - 3226.40ix) above 80'(24.0 m) to any depth ditto - 100963.20 ditto - 3566.00

6 Making and fixing in position, kiker wood well curb. Per Cft. 453.05 1524.80 cu.m 16001.75 53856.25

7 Laying well curb in position only. Each 168.95 - Each 168.95 -

8 Providing, making and laying R.C.C. well curb in position, *841-1 1) If concrete mixer is supplied byusing coarse sand, including all kinds of form, moulds, to Government, all charges includingcuring, shuttering, rendering and finishing the exposed 841-9 depreciation will be recovered fromsurface, (including screening and washing of aggregate :- the contractor.

2) The rate does not include cost ofa) Ratio 1:1½:3 Per Cft. 105.05 239.30 cu.m 3711.15 8451.70 steel reinforcement and its labour forb) ratio 1:2:4 ditto 105.05 226.90 ditto 3711.15 8014.65 bending, which is payable, separately.

chapter-22(Sinking of Wells) Page 136

Page 140: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

9 Providing and fixing structural steel for cutting 100Kg 323.40 6997.90 100Kg 323.40 6997.90 841-1 toedge. 841-9

10 Making and removing false masonry on well. 100Cft. 3179.45 8279.10 cu.m 1123.00 2924.20 21.1 to The rate includes dismantling of false21.5 & 18.1 masonry, scraping bricks obtained

from dismantling and credit ofbyproducts.

* Specification No. correspond to Book of "Standard Specification for Road and Bridge Construction, 1971".

chapter-22(Sinking of Wells) Page 137

Page 141: 26467Sahiwal_1st_010

TUBEWELL AND WATER SUPPLY1 Specification No. correspond to Book of "Specification for B&R Department, 1966, Vol. II (Public Health Works)".2 Rates for all finished works include the removal of surplus debris, unused material and byproduc

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Boring for tubewell in all types of soil except shingle and Chap. 2rock, from ground level to 100 ft. (30 m) depth, includingsinking and withdrawing of casing pipe, complete:-

a) 3" (75 mm) i/d Per Rft. 31.00 Per Metre 101.65b) 4" (100 mm) i/d of bore 43.25 of bore 141.85c) 5" (125 mm) i/d ditto 77.70 ditto 254.95d) 6" (150 mm) i/d ditto 118.40 ditto 388.30e) 8" (200 mm) i/d ditto 156.10 ditto 512.05f) 10" (250 mm) i/d ditto 195.25 ditto 640.40g) 12" (300 mm) i/d ditto 213.20 ditto 699.35h) 15" (375 mm) i/d ditto 312.75 ditto 1025.85i) 18" (450 mm) i/d ditto 333.15 ditto 1092.75

2 Boring for tubewell in all types of soil except shingle, dittogravel & rock, from a depth of 100.1 ft. to 200 ft.(30 to 60 m) below ground level, including sinking andwithdrawing of casing pipe, complete:-

a) 5" (125 mm) i/d Per Rft. 131.95 Per Metre 432.75b) 6" (150 mm) i/d of bore 184.95 of bore 606.65c) 8" (200 mm) i/d ditto 210.70 ditto 691.10d) 10" (250 mm) i/d ditto 238.95 ditto 783.80e) 12" (300 mm) i/d ditto 264.75 ditto 868.35f) 15" (375 mm) i/d ditto 366.80 ditto 1203.05g) 18" (450 mm) i/d ditto 387.20 ditto 1270.00

3 Boring for tubewell in all types of soil except shingle, dittogravel & rock, from a depth of 200.1 ft. to 300 ft. (60to 90 m) below ground level, including sinking andwithdrawing of casing pipe, complete:-a) 5" (125 mm) i/d Per Rft. 183.75 Per Metre 602.70b) 6" (150 mm) i/d of bore 236.75 of bore 776.60c) 8" (200 mm) i/d ditto 265.30 ditto 870.15d) 10" (250 mm) i/d ditto 296.45 ditto 972.40e) 12" (300 mm) i/d ditto 315.05 ditto 1033.30

f) 15" (375 mm) i/d ditto 402.80 ditto 1321.20g) 18" (450 mm) i/d ditto 424.40 ditto 1392.05

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-23(Tubewell) Page 138

Page 142: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

4 Boring for tubewell in all types of soil except shingle, Chap. 2gravel & rock, from a depth of 300.1 ft. to 400 ft.(90 to 120 m) below ground level, including sinking andwithdrawing of casing pipe, complete:-

a) 8" (200 mm) i/d Rft of bore 319.90 Per Metre 1049.20b) 10" (250 mm) i/d ditto 353.95 of bore 1160.95c) 12" (300 mm) i/d ditto 374.95 ditto 1229.75d) 15" (375 mm) i/d ditto 491.65 ditto 1612.60e) 18" (450 mm) i/d ditto 495.85 ditto 1626.35

5 Direct Rotary/Reverse Rotary drilling of bore for tubewells, dittoin all types of soil except shingle, gravel and rock:-

a) from ground level to 250 ft. (75 m) below ground level:-

Per Rft. Per Metrei) 15" to 18" (375 to 450 mm) i/d of bore 307.60 of bore 1008.90 Upto 2 cusec dischargeii) 20" to 26" (500 to 650 mm) i/d ditto 442.35 ditto 1450.95 Above 2 cusec discharge

b) exceeding 250 ft. (75 m) depth below ground level:-

Rft Per Metrei) 15" to 18" (375 to 450 mm) i/d of bore 307.60 of bore 1008.90 Upto 2 cusec dischargeii) 20" to 26" (500 to 650 mm) i/d ditto 442.35 ditto 1450.95 Above 2 cusec discharge

6 Boring for tubewell in shingle, gravel and rock, including ditto Location and depth of shingle,sinking and withdrawing of casing pipe:- gravel or rock is to be determined

from the bore log.a) from ground level to 200 ft. (60 m) below ground level:-

Per Rft. Per Metre

i) 12" to 18" (300 to 450 mm) i/d of bore 693.70 of bore 2275.40 Upto 2 cusec dischargeii) 20" to 26" (500 to 650 mm) i/d ditto 938.20 ditto 3077.35 Above 2 cusec discharge

b) exceeding 200 ft. (60 m) depth belowground level:-

i) 12" to 18" (300 to 450 mm) i/d ditto 693.70 ditto 2275.40 Upto 2 cusec dischargeii) 20" to 26" (500 to 650 mm) i/d ditto 938.20 ditto 3077.35 Above 2 cusec discharge

7 Providing strong substantially built box of deodar wood Job for 419.40 6487.80 Job for 419.40 6487.80 ditto4'x2½'x9" (1200x750x225 mm), with compartments, lock compl- compl-and locking arrangement, for preserving samples of strata ete bore ete borefrom bore hole.

chapter-23(Tubewell) Page 139

Page 143: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

8 Furnishing sample of water from bore hole. Per Set 108.00 156.00 Per Set 108.00 156.00 Chap. 2

of 2 of 2bottles bottles

9 Providing and installing, brass strainer in tubewell bore ditto Cost/labour of jointing both ends ishole, including sockets, special sockets, studs, etc. included in the rate.complete:-

a) 2" i/d, 5/32" (50 mm i/d 4 mm) thick Per Rft. 14.35 635.95 Per Metre 47.05 2085.90b) 3" i/d, 5/32" (75 mm i/d 4 mm) thick Per Rft. 14.35 959.35 Per Metre 47.05 3146.65c) 4" i/d, 3/16" (100 mm i/d 5 mm) thick Per Rft. 18.95 1173.95 Per Metre 62.10 3850.50d) 5" i/d, 3/16" (125 mm i/d 5 mm) thick Per Rft. 21.40 1386.40 Per Metre 70.10 4547.30e) 6" i/d, 3/16" (150 mm i/d 5 mm) thick Per Rft. 24.10 1494.10 Per Metre 79.10 4900.70f) 7" i/d, 3/16" (175 mm i/d 5 mm) thick Per Rft. 28.10 1760.60 Per Metre 92.15 5774.75g) 8" i/d, 3/16" (200 mm i/d 5 mm) thick Per Rft. 34.65 2239.65 Per Metre 113.70 7346.10h) 9" i/d, 3/16" (225 mm i/d 5 mm) thick Per Rft. 34.65 2292.15 Per Metre 113.70 7518.30i) 10" i/d, 3/16" (250 mm i/d 5 mm) thick Per Rft. 38.95 2348.95 Per Metre 127.70 7704.50j) 10" i/d, ¼" (250 mm i/d 6 mm) thick Per Rft. 38.95 2978.95 Per Metre 127.70 9770.90k) 12" i/d, ¼" (300 mm i/d 6 mm) thick Per Rft. 40.15 3400.15 Per Metre 131.65 11152.45l) 15" i/d, ¼" (375 mm i/d 6 mm) thick Per Rft. 45.80 4245.80 Per Metre 150.30 13926.30m) 18" i/d, ¼" (450 mm i/d 6 mm) thick Per Rft. 45.80 4755.05 Per Metre 150.30 15596.65n) 20" i/d, ¼" (500 mm i/d 6 mm) thick Per Rft. 53.80 5240.80 Per Metre 176.40 17189.75o) 22" i/d, ¼" (550 mm i/d 6 mm) thick Per Rft. 55.00 6061.00 Per Metre 180.35 19880.05

10 Providing and installing M.S. Bail plug in tubewell bore In the case of increase or decreasehole: in the length of Bail plug, the rates

will be increased or decreased asa) 2" i/d, 1.5 ft. (50 mm i/d 450 mm) long. Each 60.45 418.25 Each 60.45 418.25 per rates given in serial No. 14 ofb) 3" i/d, 1.5 ft. (75 mm i/d 450 mm) long. Each 60.45 570.75 Each 60.45 570.75 this chapter for the respectivec) 4" i/d, 2 ft. (100 mm i/d 600 mm) long. Each 100.90 1157.45 Each 100.90 1157.45 diameter.d) 5" i/d, 2 ft. (125 mm i/d 600 mm) long. Each 100.90 1480.15 Each 100.90 1480.15e) 6" i/d, 2 ft. (150 mm i/d 600 mm) long. Each 136.85 1871.55 Each 136.85 1871.55f) 7" i/d, 2 ft. (175 mm i/d 600 mm) long. Each 136.85 2170.25 Each 136.85 2170.25g) 8" i/d, 2 ft. (200 mm i/d 600 mm) long Each 167.90 2404.35 Each 167.90 2404.35h) 9" i/d, 2 ft. (225 mm i/d 600 mm) long Each 167.90 2681.10 Each 167.90 2681.10i) 10" i/d, 2 ft. (250 mm i/d 600 mm) long Each 167.90 3489.70 Each 167.90 3489.70j) 12" i/d, 2 ft. (300 mm i/d 600 mm) long Each 201.50 4198.25 Each 201.50 4198.25k) 15" i/d, 2 ft. (375 mm i/d 600 mm) long Each 201.50 5193.55 Each 201.50 5193.55l) 18" i/d, 2 ft. (450 mm i/d 600 mm) long Each 243.10 5903.90 Each 243.10 5903.90m) 20" i/d, 2 ft. (500 mm i/d 600 mm) long Each 264.00 6581.90 Each 264.00 6581.90n) 22" i/d, 2 ft. (550 mm i/d 600 mm) long Each 264.00 7247.15 Each 264.00 7247.15

chapter-23(Tubewell) Page 140

Page 144: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

11 Providing and installing, P.V.C. strainer B.S.S. Class 'B', Chap. 2in tubewell bore hole, including sockets and solvents, etc.complete:-

a) 3" i/d (75 mm) Per Rft. 12.20 99.60 Per Metre 39.95 326.65b) 4" i/d (100 mm) Per Rft. 14.00 146.05 Per Metre 45.95 479.10c) 5" i/d (125 mm) Per Rft. 15.05 202.75 Per Metre 49.45 665.00d) 6" i/d (150 mm) Per Rft. 18.10 267.75 Per Metre 59.35 878.20e) 8" i/d (200 mm) Per Rft. 23.90 646.45 Per Metre 78.40 2120.40f) 10" i/d (250 mm) Per Rft. 24.60 967.05 Per Metre 80.70 3171.90g) 12" i/d (300 mm) Per Rft. 24.60 1291.55 Per Metre 80.70 4236.25

12 Providing and installing P.V.C. strainer B.S.S. Class `D' ,in tubewell bore hole, including sockets and solvent, etc.complete:-

a) 1¼" i/d (30 mm) Per Rft. 7.80 41.00 Per Metre 25.60 134.5b) 1½" i/d (40 mm) Per Rft. 8.15 48.15 Per Metre 26.75 158c) 2" i/d (50 mm) Per Rft. 8.30 73.75 Per Metre 27.25 241.9d) 3" i/d (75 mm) Per Rft. 12.20 154.45 Per Metre 40.00 506.65e) 4" i/d (100 mm) Per Rft. 14.10 246.50 Per Metre 46.25 808.6f) 5" i/d (125 mm) Per Rft. 15.40 361.20 Per Metre 50.50 1184.7g) 6" i/d (150 mm) Per Rft. 32.85 520.55 Per Metre 107.75 1707.35

13 Providing and installing P.V.C. Bail/End plug, in tubewellbore hole:-

i) B.S.S. Class `B'

a) 3" i/d (75 mm) Each 7.65 55.65 Each 7.65 55.65b) 4" i/d (100 mm) Each 8.75 74.75 Each 8.75 74.75c) 5" i/d (125 mm) Each 9.75 112.95 Each 9.75 112.95d) 6" i/d (150 mm) Each 12.10 162.10 Each 12.10 162.10e) 8" i/d (200 mm) Each 14.90 314.90 Each 14.90 314.90f) 10" i/d (250 mm) Each 15.75 442.95 Each 15.75 442.95g) 12" i/d (300 mm) Each 18.00 594.00 Each 18.00 594.00h) 14" i/d (350 mm) Each 18.00 625.20 Each 18.00 625.20

ii) B.S.S. Class `D'

a) 1¼" i/d (30 mm) Each 4.90 28.90 Each 4.90 28.90b) 1½" i/d (40 mm) Each 5.30 41.30 Each 5.30 41.30c) 2" i/d (50 mm) Each 5.55 59.55 Each 5.55 59.55d) 3" i/d (75 mm) Each 7.60 79.60 Each 7.60 79.60

chapter-23(Tubewell) Page 141

Page 145: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

e) 4" i/d (100 mm) Each 8.75 104.75 Each 8.75 104.75f) 5" i/d (125 mm) Each 9.75 147.75 Each 9.75 147.75g) 6" i/d (150 mm) Each 12.1 192.1 Each 12.1 192.1

14 Providing and installing M.S. blind pipe socketed/welded Chap.joint, M.S. reducer (where necessary), in tubewell bore 2hole, including jointing/welding with strainer, etc.complete:-

a) 2" i/d, 1/8" (50 mm i/d 3 mm) thick Per Rft. 39.20 183.95 Per Metre 128.60 603.30b) 3" i/d, 1/8" (75 mm i/d 3 mm) thick Per Rft. 39.20 248.10 Per Metre 128.60 813.75c) 4" i/d, 1/8" (100 mm i/d 3 mm) thick Per Rft. 49.05 325.35 Per Metre 160.90 1067.10d) 5" i/d, 3/16" (125 mm i/d 5 mm) thick Per Rft. 49.05 599.60 Per Metre 160.90 1966.75e) 6" i/d, 3/16" (150 mm i/d 5 mm) thick Per Rft. 69.95 720.80 Per Metre 229.45 2364.30f) 7" i/d, 3/16" (175 mm i/d 5 mm) thick Per Rft. 69.95 829.30 Per Metre 229.45 2720.10g) 8" i/d, 3/16" (200 mm i/d 5 mm) thick Per Rft. 81.65 1089.05 Per Metre 267.80 3572.15h) 9" i/d, 3/16" (225 mm i/d 5 mm) thick Per Rft. 81.65 1215.00 Per Metre 267.80 3985.20i) 10" i/d, ¼" (250 mm i/d 6 mm) thick Per Rft. 81.65 1578.35 Per Metre 267.80 5176.95j) 12" i/d, ¼" (300 mm i/d 6 mm) thick Per Rft. 98.00 1894.05 Per Metre 321.45 6212.40k) 15" i/d, ¼" (375 mm i/d 6 mm) thick Per Rft. 98.00 2343.05 Per Metre 321.45 7685.15l) 18" i/d, ¼" (450 mm i/d 6 mm) thick Per Rft. 118.75 2711.00 Per Metre 389.50 8892.15m) 20" i/d, ¼" (500 mm i/d 6 mm) thick Per Rft. 128.65 3008.95 Per Metre 421.95 9869.35n) 22" i/d, ¼" (550 mm i/d 6 mm) thick Per Rft. 128.65 3297.00 Per Metre 421.95 10814.10

15 Providing and installing P.V.C. blind pipe, B.S.S. Class ditto`B', in tubewell bore hole, including sockets and solventsand jointing with strainer, etc. complete.

a) 3" i/d (75 mm) Per Rft. 15.25 97.60 Per Metre 49.95 320.15b) 4" i/d (100 mm) Per Rft. 17.35 142.00 Per Metre 57.00 465.70c) 5" i/d (125 mm) Per Rft. 18.45 195.85 Per Metre 60.50 642.40d) 6" i/d (150 mm) Per Rft. 22.95 263.70 Per Metre 73.75 863.45e) 8" i/d (200 mm) Per Rft. 29.20 417.85 Per Metre 95.85 1370.50f) 10" i/d (250 mm) Per Rft. 30.90 628.60 Per Metre 101.30 2061.75g) 12" i/d (300 mm) Per Rft. 36.50 777.85 Per Metre 119.75 2551.30h) 14" i/d (350 mm) Per Rft. 34.10 1183.70 Per Metre 111.90 3882.60

16 Providing and installing P.V.C. blind pipe, B.S.S. Class`D', in tubewell bore hole, including sockets and solventsand jointing with strainer, etc. complete.

a) 1¼" i/d (30 mm) Per Rft. 9.20 39.50 Per Metre 30.15 129.60b) 1½" i/d (40 mm) Per Rft. 9.55 47.55 Per Metre 31.25 155.95c) 2" i/d (50 mm) Per Rft. 10.15 69.90 Per Metre 33.25 229.30d) 3" i/d (75 mm) Per Rft. 13.45 145.45 Per Metre 44.15 477.10

chapter-23(Tubewell) Page 142

Page 146: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

e) 4" i/d (100 mm) Per Rft. 17.50 238.20 Per Metre 57.45 781.35f) 5" i/d (125 mm) Per Rft. 18.80 348.25 Per Metre 61.60 1142.25g) 6" i/d (150 mm) Per Rft. 22.95 498.15 Per Metre 75.30 1633.95

17 Testing and developing of tubewell of size 6" (150 mm)i/d and above continuously.

i) upto 1.5 cs. discharge Per 691.65 Per 691.65Hour Hour

ii) above 1.5 cs. discharge ditto 832.30 ditto 832.30

18 Shrouding with graded pea gravel 3/8" to 1/8" (10 to 3 Per Cft. 14.70 68.85 cu.m 519.20 2431.75 The rate includes wastage, etc.mm), around tubewell in bore hole.

19 Laying cutting, jointing, testing and disinfecting cast iron Chap. 1) Pipes to be supplied bypipe line in trenches, with spigot and socket caulked lead 2 Government.joints, including cost of materials, such as lead, yarn, etc. 2) Providing and installing specialscomplete in all respects:- and valves is not included in the

rate, which is payable separately.

a) 3" (75 mm) i/d Per Rft. 32.65 Per Metre 107.15b) 4" (100 mm) i/d Per Rft. 40.75 Per Metre 133.65c) 5" (125 mm) i/d Per Rft. 50.70 Per Metre 166.25d) 6" (150 mm) i/d Per Rft. 60.50 Per Metre 198.45e) 8" (200 mm) i/d Per Rft. 75.15 Per Metre 246.55f) 10" (250 mm) i/d Per Rft. 111.15 Per Metre 364.60g) 12" (300 mm) i/d Per Rft. 130.15 Per Metre 426.80h) 15" (375 mm) i/d Per Rft. 169.20 Per Metre 554.95i) 18" (450 mm) i/d Per Rft. 225.30 Per Metre 739.05

20 Laying, cutting, jointing, testing and disinfecting cast iron ditto 1) Pipes to be supplied bypipe line in trenches, with flanged and flanged joints, Government.complete in all respects:- 2) Providing and installing specials

and valves is not included in thea) 3" (75 mm) i/d Per Rft. 14.15 Per Metre 46.35 rate, which is payable separately.b) 4" (100 mm) i/d Per Rft. 15.75 Per Metre 51.65c) 5" (125 mm) i/d Per Rft. 24.55 Per Metre 80.50d) 6" (150 mm) i/d Per Rft. 26.85 Per Metre 88.05e) 8" (200 mm) i/d Per Rft. 31.60 Per Metre 103.60f) 10" (250 mm) i/d Per Rft. 44.90 Per Metre 147.25g) 12" (300 mm) i/d Per Rft. 52.20 Per Metre 171.15h) 15" (375 mm) i/d Per Rft. 71.20 Per Metre 233.35i) 18" (450 mm) i/d Per Rft. 87.60 Per Metre 287.35

chapter-23(Tubewell) Page 143

Page 147: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

21 Laying, cutting, jointing, testing and disinfecting cast iron Chap. 2 1) Pipes to be supplied bypipe line in trenches with Tyton joints, complete in all Government.respects:- 2) Providing and installing specials

and valves is not included in thea) 3" (75 mm) i/d Per Rft. 7.10 Per Metre 23.35 rate, which is payable separately.b) 4" (100 mm) i/d Per Rft. 8.30 Per Metre 27.20c) 5" (125 mm) i/d Per Rft. 10.60 Per Metre 34.80d) 6" (150 mm) i/d Per Rft. 12.05 Per Metre 39.45e) 8" (200 mm) i/d Per Rft. 16.25 Per Metre 53.35f) 10" (250 mm) i/d Per Rft. 20.65 Per Metre 67.70g) 12" (300 mm) i/d Per Rft. 24.80 Per Metre 81.35h) 15" (375 mm) i/d Per Rft. 38.75 Per Metre 127.05i) 18" (450 mm) i/d Per Rft. 46.50 Per Metre 152.45

22 Providing, laying, cutting, jointing, testing and disinfecting Chap. Cost of sockets, tees, elbows,G.I. pipeline in trenches, with socket joints, using G.I. 2 bends, valves, crosses, unions andpipes of B.S.S. 1387-1967 complete in all respects, with plugs, etc. is included in the rates.specials and valves.

i) Light Quality

a) ½" i/d (15 mm) 2mm thick Per Rft. 3.90 39.90 Per Metre 12.80 130.90b) ¾" i/d (20 mm) 2.35mm thick Per Rft. 4.35 55.90 Per Metre 14.30 183.30c) 1" i/d (25 mm) 2.65mm thick Per Rft. 5.15 77.30 Per Metre 16.85 253.50d) 1¼" i/d (32 mm) 2.65mm thick Per Rft. 5.25 97.55 Per Metre 17.20 319.95e) 1½" i/d (40 mm) 2.9mm thick Per Rft. 5.35 122.15 Per Metre 17.60 400.60f) 2" i/d (50 mm) 2.9mm thick Per Rft. 6.05 152.95 Per Metre 19.90 501.75g) 2"½ i/d (65 mm) 3.25mm thick Per Rft. 6.45 207.80 Per Metre 21.10 681.55h) 3" i/d (75 mm) 3.25mm thick Per Rft. 7.40 243.60 Per Metre 24.30 799.00i) 4" i/d (100 mm) 3.65mm thick Per Rft. 8.25 337.05 Per Metre 27.10 1105.55 ii) Medium Quality

a) ½" i/d (15 mm) 2.65mm thick Per Rft. 3.90 48.30 Per Metre 12.80 158.40b) ¾" i/d (20 mm) 2.65mm thick Per Rft. 4.35 61.10 Per Metre 14.30 200.50c) 1" i/d (25 mm) 3.25mm thick Per Rft. 5.15 90.00 Per Metre 16.85 295.15d) 1¼" i/d (32 mm) 3.25mm thick Per Rft. 5.25 114.15 Per Metre 17.20 374.50e) 1½" i/d (40 mm) 3.25mm thick Per Rft. 5.40 130.45 Per Metre 17.80 427.90f) 2" i/d (50 mm) 3.65mm thick Per Rft. 6.05 178.15 Per Metre 19.90 584.40g) 2"½ i/d (65 mm) 3.65mm thick Per Rft. 6.45 222.65 Per Metre 21.10 730.25h) 3" i/d (75 mm) 4.05mm thick Per Rft. 7.40 286.00 Per Metre 24.30 938.10i) 4" i/d (100 mm) 4.5mm thick Per Rft. 8.25 403.25 Per Metre 27.10 1322.60j) 5" i/d (150 mm) 4.85mm thick Per Rft. 9.50 547.45 Per Metre 31.20 1795.65k) 6" i/d (200 mm) 4.85mm thick Per Rft. 9.80 645.20 Per Metre 32.20 2116.30

ii. For internal G.I piping (1"dia, 3/4"dia & 1/2"dia) Bath room(s)/

Levorotary of rate (composite) shall be reduced by 8% and specials mentioned

above may be paid at the rates placed onWebsite as per actual quantity used.

i. Cost of sockets, tees, elbow, bends, valves, crosses, unions and plugs etc isincluded in the rates except for internal G.I piping (1"dia, 3/4"dia & 1/2"dia)

for Bath rooms/ Levorotary.

chapter-23(Tubewell) Page 144

Page 148: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

iii) Heavy Quality

a) ½" i/d (15 mm) 3.25mm thick Per Rft. 3.90 52.10 Per Metre 12.85 170.85b) ¾" i/d (20 mm) 3.25mm thick Per Rft. 4.35 67.55 Per Metre 14.30 221.55c) 1" i/d (25 mm) 4.05mm thick Per Rft. 5.15 103.10 Per Metre 16.85 338.2d) 1¼" i/d (32 mm) 4.05mm thick Per Rft. 5.25 131.60 Per Metre 17.20 431.7e) 1½" i/d (40 mm) 4.05mm thick Per Rft. 5.40 155.10 Per Metre 17.80 508.7f) 2" i/d (50 mm) 4.5mm thick Per Rft. 6.05 208.70 Per Metre 19.90 684.6g) 2"½ i/d (65 mm) 4.5mm thick Per Rft. 6.45 265.25 Per Metre 21.10 870h) 3" i/d (75 mm) 4.85mm thick Per Rft. 7.40 337.40 Per Metre 24.30 1106.6i) 4" i/d (100 mm) 5.4mm thick Per Rft. 8.25 478.00 Per Metre 27.10 1567.85j) 5" i/d (125 mm) 5.4mm thick Per Rft. 9.50 598.80 Per Metre 31.20 1964.1k) 6" i/d (150 mm) 5.4mm thick Per Rft. 9.80 709.75 Per Metre 32.20 2327.95

23 Providing, laying, cutting, jointing, testing and disinfectingAsbestos cement/Fibre Cement pipe line in trenches, with PS 428 & Providing and installing specialscomet joint and rubber ring, complete in all respects:- ISO 160 and valves is not included in the

rate, which is payable separately.B Class WOrking Pressure

a) 3" i/d (75 mm) Per Rft. 6.50 102.30 Per Metre 21.30 335.60b) 4" i/d (100 mm) Per Rft. 6.90 133.25 Per Metre 22.65 437.10c) 6" i/d (150 mm) Per Rft. 9.45 219.00 Per Metre 31.05 718.35d) 8" i/d (200 mm) Per Rft. 13.05 375.25 Per Metre 42.80 1230.90e) 10" i/d (250 mm) Per Rft. 17.00 552.95 Per Metre 55.75 1813.65f) 12" i/d (300 mm) Per Rft. 21.65 745.00 Per Metre 70.95 2443.55g) 14" i/d (350 mm) Per Rft. 25.15 968.55 Per Metre 82.45 3176.90h) 16" i/d (400 mm) Per Rft. 28.45 1231.95 Per Metre 93.30 4040.75i) 18" i/d (450 mm) Per Rft. 33.60 1452.95 Per Metre 110.15 4765.70j) 20" i/d (500 mm) Per Rft. 39.55 1743.15 Per Metre 129.65 5717.50k) 24" i/d (600 mm) Per Rft. 47.75 2401.90 Per Metre 156.55 7878.30

24 C Class Working Pressure PS 428 &a) 3" i/d (75 mm) Per Rft. 6.50 102.30 Per Metre 21.30 335.60 ISO 160b) 4" i/d (100 mm) Per Rft. 6.90 138.55 Per Metre 22.65 454.35c) 6" i/d (150 mm) Per Rft. 9.45 255.85 Per Metre 31.05 839.15d) 8" i/d (200 mm) Per Rft. 13.05 401.60 Per Metre 42.80 1317.20e) 10" i/d (250 mm) Per Rft. 17.00 609.80 Per Metre 55.75 2000.10f) 12" i/d (300 mm) Per Rft. 21.65 859.75 Per Metre 70.95 2819.90g) 14" i/d (350 mm) Per Rft. 25.15 1313.85 Per Metre 82.45 4309.35h) 16" i/d (400 mm) Per Rft. 28.45 1684.55 Per Metre 93.30 5525.40i) 18" i/d (450 mm) Per Rft. 33.60 2030.85 Per Metre 110.15 6661.20j) 20" i/d (500 mm) Per Rft. 39.55 2423.15 Per Metre 129.65 7947.90k) 24" i/d (600 mm) Per Rft. 48.40 3437.35 Per Metre 158.80 11274.50

chapter-23(Tubewell) Page 145

Page 149: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

25 D Class Working Pressure PS 428 &a) 3" i/d (75 mm) Per Rft. 6.50 102.30 Per Metre 21.30 335.60 ISO 160b) 4" i/d (100 mm) Per Rft. 6.90 157.45 Per Metre 22.65 516.50c) 6" i/d (150 mm) Per Rft. 9.45 310.60 Per Metre 31.05 1018.70d) 8" i/d (200 mm) Per Rft. 13.05 547.90 Per Metre 42.80 1797.10e) 10" i/d (250 mm) Per Rft. 17.00 864.50 Per Metre 55.75 2835.65f) 12" i/d (300 mm) Per Rft. 21.65 1256.55 Per Metre 70.95 4121.55g) 14" i/d (350 mm) Per Rft. 25.15 1859.10 Per Metre 82.45 6097.85h) 16" i/d (400 mm) Per Rft. 28.45 2411.95 Per Metre 93.30 7911.20i) 18" i/d (450 mm) Per Rft. 33.60 2850.85 Per Metre 110.15 9350.80j) 20" i/d (500 mm) Per Rft. 39.55 3484.20 Per Metre 129.65 11428.20k) 24" i/d (600 mm)

26 Providing, laying, cutting, jointing, testing and disinfecting Chap Providing and installing specialsP.V.C. pipe line of B.S.S. with `B' Class working pressure 2 and valves is not included in thepipe, in trenches, complete in all respects:- rate, which is payable separately.

a) 3" i/d (75 mm) Per Rft. 2.35 86.35 Per Metre 7.75 283.30 b) 4" i/d (100 mm) Per Rft. 2.95 130.05 Per Metre 9.65 426.50 c) 5" i/d (125 mm) Per Rft. 3.60 184.60 Per Metre 11.90 605.40 d) 6" i/d (150 mm) Per Rft. 3.95 249.50 Per Metre 12.90 818.40e) 8" i/d (200 mm) Per Rft. 5.55 401.90 Per Metre 18.15 1318.30f) 10" i/d (250 mm) Per Rft. 7.10 616.75 Per Metre 23.35 2023.00h) 12" i/d (300 mm) Per Rft. 8.80 764.90 Per Metre 28.80 2508.90g) 14" i/d (350 mm) Per Rft. 11.10 1183.70 Per Metre 36.40 3882.50

27 Providing, laying, cutting, jointing, testing and disinfecting ditto Providing and installing specialspipe line in trenches with P.V.C. pipes of B.S.S. with `D' and valves is not included in theClass working pressure complete in all respects:- rate, which is payable separately.a) 2" i/d (50 mm) Per Rft. 1.95 62.95 Per Metre 6.45 206.40 b) 3" i/d (75 mm) Per Rft. 2.35 137.00 Per Metre 7.75 449.35 c) 4" i/d (100 mm) Per Rft. 2.95 228.05 Per Metre 9.65 748.00 d) 5" i/d (125 mm) Per Rft. 3.60 339.70 Per Metre 11.90 1114.15 e) 6" i/d (150 mm) Per Rft. 3.95 488.65 Per Metre 12.90 1602.70

28 Providing and fixing cast iron special of B.S.S. Class `B' 9.1 i) Labour rates include the cost of(such as bend, tee cross collar, reducer, tail piece, jointing material & labour.flanged spigot, cap, flanged socket, taper, angle branch,plug etc.) for cast iron pipe line , complete:- ii) The internal dia of the pipe, from

which the branch is taken out wila) C.I.S.S. Specials, with spigot. and be considered the internal dia for

socket joint:- the purpose of payments ofi) 3" to 6" (75 to 150 mm) i/d Per Kg. 14.10 92.05 Per Kg 14.10 92.05 specials.ii) 8" to 12" (200 to 300 mm) i/d Per Kg. 7.85 85.80 Per Kg 7.85 85.80iii) 15" to 18" (375 to 450 mm) i/d Per Kg. 4.55 82.50 Per Kg 4.55 82.50

chapter-23(Tubewell) Page 146

Page 150: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

b) C.I. flanged specials, with flanged andflanged joints:-

i) 3" to 6" (75 to 150 mm) i/d Per Kg 6.50 84.45 Per Kg 6.50 84.45ii) 8" to 12" (200 to 300 mm) i/d Per Kg 2.25 80.20 Per Kg 2.25 80.20iii) 15" to 18" (375 to 450 mm) i/d Per Kg 2.85 80.20 Per Kg 2.85 80.20

c) C.I. Specials, with tyton joints:-

i) 3" to 6" (75 to 150 mm) i/d Per Kg 6.65 84.60 Per Kg 6.65 84.60ii) 8" to 12" (200 to 300 mm) i/d Per Kg 6.65 84.60 Per Kg 6.65 84.60iii) 15" to 18" (375 to 450 mm) i/d Per Kg 6.65 84.60 Per Kg 6.65 84.60

29 Providing and fixing cast iron specials of B.S.S. Class 'B' 9.1 1) Labour rates include the cost of(such as bend, tee, cross collar, reducer, tail piece, jointing material and labour.flanged socket, flanged spigot, cap, taper, angle branch,plug, etc) for Asbestos cement pipe line, with comet joint 2) The internal dia of the pipe, fromand rubber ring, complete. which the branch is taken out, willi) 3" to 6" (75 to 150 mm) i/d Per Kg 10.40 88.35 Per Kg 10.40 88.35 be considered the internal dia forii) 8" to 18" (200 to 450 mm) i/d Per Kg 5.50 83.45 Per Kg 5.50 83.45 the purpose of payment.iii) 20" to 24" (500 to 600 mm) i/d Per Kg 4.40 82.35 Per Kg 4.40 82.35

30 Providing and fixing sluice valve of B.S.S. quality and 9.1 Labour rates include cost of jointingweight, Class `B', for cast iron pipe line, and Asbestos material and labour.cement pipe line (including cost of jointing material):-a) 3" i/d (75 mm) Each 385.95 4585.95 Each 385.95 4585.95b) 4" i/d (100 mm) Each 420.00 5220.00 Each 420.00 5220.00c) 5" i/d (125 mm) Each 756.05 6756.05 Each 756.05 6756.05d) 6" i/d (150 mm) Each 806.00 8006.00 Each 806.00 8006.00e) 8" i/d (200 mm) Each 941.10 14141.10 Each 941.10 14141.10f) 10" i/d (250 mm) Each 1525.50 18325.50 Each 1525.50 18325.50g) 12" i/d (300 mm) Each 1714.30 23314.30 Each 1714.30 23314.30h) 16" i/d (400 mm) Each 2273.70 44273.70 Each 2273.70 44273.70i) 18" i/d (450 mm) Each 2616.90 86616.90 Each 2616.90 86616.90

31 Providing and fixing, sluice valve of B.S.S. quality and Labour rates include cost of jointingweight, for Asbestos cement pipe line, with comet joint 9.1 material and labour.and rubber ring, complete (including cost of jointingmaterials):-a) 3" i/d (75 mm) Each 322.30 4522.30 Each 322.30 4522.30b) 4" i/d (100 mm) Each 399.60 5199.60 Each 399.60 5199.60c) 6" i/d (150 mm) Each 509.70 7709.70 Each 509.70 7709.70d) 8" i/d (200 mm) Each 853.40 14053.40 Each 853.40 14053.40e) 10" i/d (250 mm) Each 1084.50 17884.50 Each 1084.50 17884.50

chapter-23(Tubewell) Page 147

Page 151: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

f) 12" i/d (300 mm) Each 1247.60 22847.60 Each 1247.60 22847.60g) 16" i/d (400 mm) Each 1481.30 43481.30 Each 1481.30 43481.30h) 18" i/d (450 mm) Each 1796.90 85796.90 Each 1796.90 85796.90

32 Providing and fixing, fire hydrants B.S.S. quality and Each 49.00 1969.00 Each 49.00 1969.00 9.1 1) Labour rates include cost ofweight of 2½" (65 mm) dia (including cost of jointing jointing material and labour.material).

2) Connecting pipes and specials,if used, will be paid extra.

33 Providing and fixing, air valve 2½ (65mm) dia of B.S.S. dittoquality and weight (complete with jointing material).

a) single Each 99.05 1899.05 Each 99.05 1899.05

b) double Each 99.05 3099.05 Each 99.05 3099.05

34 Providing and fitting C.I. flanges on pipes, includingturning, threading, facing and fitting, etc. complete in all dittorespects:-

a) 3" to 6" (75 to 150 mm) i/d Per Kg 17.30 50.75 Per Kg 17.30 50.75

b) 8" to 12" (200 to 300 mm) i/d Per Kg 11.05 44.50 Per Kg 11.05 44.50

c) 15" to 18" (375 to 450 mm) i/d Per Kg 9.25 42.70 Per Kg 9.25 42.70

35 Cutting C.I. pipe, and welding spigot or socket, flanged ortyton end, after finishing ends of pipes:

Per Inch Per cm i/d a) 3" to 6" (75 to 150 mm) i/d i/d of pipe 35.70 of pipe 14.30b) 8" to 12" (200 to 300 mm) i/d ditto 43.35 ditto 17.35c) 15" to 18" (375 to 450 mm) i/d ditto 40.30 ditto 16.10

36 Providing, laying, cutting, jointing, testing and disinfecting Cost of sockets, tees, elbows,G.I. pipe line in trenches, with flanged joints, using G.I. bends, valves, crosses, unions andpipe of B.S.S. 1387-1967 complete in all respects, plugs, etc. is included in the rates.including specials and valves:-

i) G.I. flanged joints (Heavy Quality)

a) 1½" i/d (40 mm) Per Rft. 8.40 236.20 Per Metre 27.55 774.75b) 2" i/d (50 mm) Per Rft. 8.40 328.40 Per Metre 27.55 1077.20c) 2½" i/d (65 mm) Per Rft. 8.85 418.35 Per Metre 29.00 1372.20d) 3" i/d (75 mm) Per Rft. 8.90 544.55 Per Metre 29.25 1786.10

chapter-23(Tubewell) Page 148

Page 152: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

e) 4" i/d (100 mm) Per Rft. 10.55 771.30 Per Metre 34.65 2529.80f) 6" i/d (150 mm) Per Rft. 12.15 950.50 Per Metre 39.90 3117.70g) 8" i/d (200 mm) Per Rft. 12.20 1126.85 Per Metre 40.05 3696.00

ii) C.I. flanged joints (Medium Quality)

a) 1½" i/d (40 mm) Per Rft. 9.65 170.90 Per Metre 31.55 560.45b) 2" i/d (50 mm) Per Rft. 8.95 230.75 Per Metre 29.40 756.90c) 2½" i/d (65 mm) Per Rft. 10.05 288.75 Per Metre 32.95 947.05d) 3" i/d (75 mm) Per Rft. 10.15 369.20 Per Metre 33.20 1211.00e) 4" i/d (100 mm) Per Rft. 11.85 537.40 Per Metre 38.95 1762.60f) 6" i/d (150 mm) Per Rft. 13.55 729.60 Per Metre 44.50 2393.05g) 8" i/d (200 mm) Per Rft. 13.65 859.75 Per Metre 44.80 2819.90

37 Providing and installing P.V.C. bends, of B.S.S.

i) Class `B' working pressure:-a) 3" i/d (75 mm) Each 60.45 173.25 Each 60.45 173.25b) 4" i/d (100 mm) Each 72.00 313.20 Each 72.00 313.20c) 5" i/d (125 mm) Each 90.00 559.20 Each 90.00 559.20d) 6" i/d (150 mm) Each 93.70 786.10 Each 93.70 786.10

ii) Class `D' working pressure:-a) 1¼" i/d (30 mm) Each 36.85 66.85 Each 36.85 66.85b) 1½" i/d (40 mm) Each 40.75 73.15 Each 40.75 73.15c) 2" i/d (50 mm) Each 45.20 108.80 Each 45.20 108.80d) 3" i/d (75 mm) Each 60.45 228.45 Each 60.45 228.45e) 4" i/d (100 mm) Each 72.00 466.80 Each 72.00 466.80f) 5" i/d (125 mm) Each 90.00 1002.00 Each 90.00 1002.00g) 6" i/d (150 mm) Each 93.70 1374.10 Each 93.70 1374.10

38 Providing and installing P.V.C. tees, of B.S.S.

i) Class `B' working pressure:-

a) 3" i/d (80 mm) Each 90.70 507.10 Each 90.70 507.10b) 4" i/d (100 mm) Each 109.70 953.30 Each 109.70 953.30c) 5" i/d (125 mm) Each 132.45 1820.85 Each 132.45 1820.85d) 6" i/d (150 mm) Each 140.50 1880.50 Each 140.50 1880.50

ii) Class `D' working pressure:-

a) 1¼" i/d (30 mm) Each 56.70 171.90 Each 56.70 171.90b) 1½" i/d (40 mm) Each 61.40 203.00 Each 61.40 203.00c) 2" i/d (50 mm) Each 67.35 255.75 Each 67.35 255.75

chapter-23(Tubewell) Page 149

Page 153: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

d) 3" i/d (75 mm) Each 90.70 507.10 Each 90.70 507.10e) 4" i/d (100 mm) Each 109.70 953.30 Each 109.70 953.30f) 5" i/d (125 mm) Each 132.45 1820.85 Each 132.45 1820.85g) 6" i/d (150 mm) Each 140.50 1880.50 Each 140.50 1880.50

39 Providing and installing P.V.C. sockets, B.S.S.

i) Class `B' working pressure:-

a) 3" i/d (75 mm) Each 46.70 121.10 Each 46.70 121.10b) 4" i/d (100 mm) Each 58.20 191.40 Each 58.20 191.40c) 5" i/d (125 mm) Each 72.75 252.75 Each 72.75 252.75d) 6" i/d (150 mm) Each 76.45 329.65 Each 76.45 329.65e) 8" i/d (200 mm) Each 111.80 697.40 Each 111.80 697.40f) 10" i/d (250 mm) Each 134.00 1718.00 Each 134.00 1718.00g) 12" i/d (300 mm) Each 154.45 3828.85 Each 154.45 3828.85h) 14" i/d (350 mm) Each 175.60 3055.60 Each 175.60 3055.60

ii) Class `D' working pressure:-a) 1¼" i/d (30 mm) Each 25.35 45.75 Each 25.35 45.75b) 1½" i/d (40 mm) Each 29.25 56.85 Each 29.25 56.85c) 2" i/d (50 mm) Each 33.70 78.10 Each 33.70 78.10d) 3" i/d (75 mm) Each 46.70 189.50 Each 46.70 189.50e) 4" i/d (100 mm) Each 58.20 322.20 Each 58.20 322.20f) 5" i/d (125 mm) Each 72.75 552.75 Each 72.75 552.75g) 6" i/d (150 mm) Each 76.45 916.45 Each 76.45 916.45

40 Providing and installing P.V.C. Tapered core, B.S.S.

i) Class `B' working pressure:-

a) 3" i/d (75 mm) Each 60.45 96.45 Each 60.45 96.45b) 4" i/d (100 mm) Each 72.00 120.00 Each 72.00 120.00c) 5" i/d (125 mm) Each 90.00 150.00 Each 90.00 150.00d) 6" i/d (150 mm) Each 93.70 165.70 Each 93.70 165.70e) 8" i/d (200 mm) Each 134.75 254.75 Each 134.75 254.75f) 10" i/d (250 mm) Each 156.95 312.95 Each 156.95 312.95g) 12" i/d (300 mm) Each 182.00 374.00 Each 182.00 374.00h) 14" i/d (350 mm) Each 203.15 443.15 Each 203.15 443.15

ii) Class `D' working pressure:-a) 1¼" i/d (30 mm) Each 36.85 54.85 Each 36.85 54.85b) 1½" i/d (40 mm) Each 40.75 64.75 Each 40.75 64.75c) 2" i/d (50 mm) Each 45.20 75.20 Each 45.20 75.20

chapter-23(Tubewell) Page 150

Page 154: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

41 Making connection for new watersupply lines with the The rate includes the component ofrunning main, including excavation of trench and refilling, bailing out water from the trenchcomplete, but excluding cost of pipe and specials, etc. and cutting of existing pipe line.

Diameter of running main:Per Per

i) upto 6" i/d (150 mm) Connection 686.40 Connection 686.40ii) upto 8" i/d (200 mm) ditto 860.65 ditto 860.65iii) upto 10" i/d (250 mm) ction 1227.60 ction 1227.60iv) upto 12" i/d (300 mm) ditto 1663.20 ditto 1663.20v) upto 16" i/d (400 mm) ditto 2051.95 ditto 2051.95vi) upto 20" i/d (500 mm) ditto 2640.00 ditto 2640.00vii) upto 24" i/d (600 mm) ditto 3181.20 ditto 3181.20

chapter-23(Tubewell) Page 151

Page 155: 26467Sahiwal_1st_010

ELECTRIC INSTALLATIONRates for all finished works include the removal of surplus debris, unused material and byproducts.

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Supply and erection of G.I. pipes for wiring purposes, includingpull boxes, inspection boxes, bends, tees, etc. complete withall specials.

a) on surface, including clamps, etc. 38.4

i) 15 mm i/d Per Rft. 9.50 42.35 Per Metre 31.15 139.00 ii) 20 mm i/d Per Rft. 9.50 53.25 Per Metre 31.15 174.65 iii) 25 mm i/d Per Rft. 9.50 69.60 Per Metre 31.15 228.30 iv) 32 mm i/d Per Rft. 11.65 87.70 Per Metre 38.30 287.70 v) 40 mm i/d Per Rft. 11.65 107.25 Per Metre 38.30 351.80 vi) 50 mm i/d Per Rft. 13.90 133.85 Per Metre 45.55 439.00 vii) 80 mm i/d Per Rft. 17.70 210.05 Per Metre 58.00 689.05

b) recessed in walls, including hooks, cutting jharries andrepairing surface: 38.3

i) 15 mm i/d Per Rft. 13.85 45.75 Per Metre 45.40 150.00 ii) 20 mm i/d Per Rft. 13.85 57.60 Per Metre 45.40 188.90 iii) 25 mm i/d Per Rft. 14.40 74.75 Per Metre 47.30 245.25 iv) 32 mm i/d Per Rft. 14.40 90.90 Per Metre 47.30 298.15 v) 40 mm i/d Per Rft. 15.75 111.50 Per Metre 51.60 365.70 vi) 50 mm i/d Per Rft. 21.65 141.70 Per Metre 70.95 464.75 vii) 80 mm i/d Per Rft. 34.60 227.95 Per Metre 113.50 747.65

2 Supply and erection of M.S. conduit pipes for wiring, including 38.4 & 38.6pull boxes, inspection boxes, bends, tees, etc. complete with all specials.

a) on surface, including clamps, etc.

i) 16 mm i/d Per Rft. 6.60 23.85 Per Metre 21.65 78.25 ii) 20 mm i/d Per Rft. 6.60 28.65 Per Metre 21.65 94.00 iii) 25 mm i/d Per Rft. 6.60 34.80 Per Metre 21.65 114.15 iv) 32 mm i/d Per Rft. 6.60 38.20 Per Metre 21.65 125.30 v) 40 mm i/d Per Rft. 7.40 49.35 Per Metre 24.35 161.80 vi) 50 mm i/d Per Rft. 9.15 60.55 Per Metre 29.95 198.60

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-24(Electric Installation) Page 152

Page 156: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

b) recessed in walls, including cutting jharries, cost of 38.3 &hooks and repairing surface etc. 38.7

i) 16 mm i/d Per Rft. 12.35 31.05 Per Metre 40.55 101.90 ii) 20 mm i/d Per Rft. 12.35 35.60 Per Metre 40.55 116.75 iii) 25 mm i/d Per Rft. 13.85 42.85 Per Metre 45.40 140.50 iv) 32 mm i/d Per Rft. 14.40 47.20 Per Metre 47.30 154.85 v) 40 mm i/d Per Rft. 15.05 57.25 Per Metre 49.35 187.75 vi) 50 mm i/d Per Rft. 15.75 69.15 Per Metre 51.60 226.85

3 Supply and erection of PVC pipe for wiring recessed in walls, 38.3 &including inspection boxes, pull boxes, hooks, cutting jharries, 38.5and repairing surface, etc., complete with all specials.

i) 12 mm i/d Per Rft. 11.15 19.60 Per Metre 36.60 64.30 ii) 20 mm i/d Per Rft. 11.55 22.50 Per Metre 37.85 73.85 iii) 25 mm i/d Per Rft. 12.80 27.20 Per Metre 42.05 89.20 iv) 32 mm i/d Per Rft. 13.85 33.75 Per Metre 45.40 110.70 v) 40 mm i/d Per Rft. 14.40 40.50 Per Metre 47.30 132.80 vi) 50 mm i/d Per Rft. 15.05 50.75 Per Metre 49.35 166.40

4 Supply and erection of PVC pipe for wiring on surfaceincluding clamps inspection boxes, pull boxes, bends, tees, repairing surface, etc., complete with all specials:-

i) 12 mm i/d Per Rft. 2.95 11.10 Per Metre 9.75 36.35 ii) 20 mm i/d Per Rft. 2.95 13.50 Per Metre 9.75 44.30 iii) 25 mm i/d Per Rft. 2.95 17.65 Per Metre 9.75 57.90 iv) 32 mm i/d Per Rft. 3.40 24.05 Per Metre 11.15 78.80 v) 40 mm i/d Per Rft. 3.40 31.10 Per Metre 11.15 101.95 vi) 50 mm i/d Per Rft. 4.10 44.60 Per Metre 13.45 146.30

5 Supply and erection of G.I. flexible pipe for wiring, including 38.4welding of sockets, nipples and check nuts, etc. complete:-

i) 12 mm i/d Per Rft. 7.80 34.15 Per Metre 25.60 112.00 ii) 20 mm i/d Per Rft. 8.30 42.70 Per Metre 27.30 140.10 iii) 25 mm i/d Per Rft. 8.60 56.90 Per Metre 28.25 186.65 iv) 32 mm i/d Per Rft. 10.40 75.50 Per Metre 34.10 247.70 v) 40 mm i/d Per Rft. 11.35 93.30 Per Metre 37.20 306.00 vi) 50 mm i/d Per Rft. 12.50 128.45 Per Metre 40.95 421.35 vii) 80 mm i/d Per Rft. 16.65 284.45 Per Metre 54.55 932.95

chapter-24(Electric Installation) Page 153

Page 157: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

6 Supply and erection PVC pipe for recessed wiring (main and 38.2 &sub-main) purpose, including bends, specials, etc. in floor, 38.3wall or trenches:-

i) 50 mm i/d Per Rft. 15.05 52.20 Per Metre 49.35 171.20 ii) 80 mm i/d Per Rft. 17.30 67.30 Per Metre 56.75 220.80 iii) 100 mm i/d Per Rft. 17.30 88.95 Per Metre 56.75 291.75

7 Supply and erection of PVC pipe for surface wiring (main andsub-main) including clamps, inspection boxes, pull boxesbends etc., complete with all specials:-

i) 50 mm i/d Per Rft. 4.10 40.95 Per Metre 13.45 134.35 ii) 80 mm i/d Per Rft. 5.95 68.30 Per Metre 19.45 224.05 iii) 100 mm i/d Per Rft. 6.80 85.55 Per Metre 22.25 280.60

8 Supply and erection of wooden strip batten for wiring Per Rft. 1.20 2.85 Per Metre 3.90 9.40 38.8 Additional width required to

purposes, including clips, insulation cleats, etc. accommodate wires will be providedby erection of additional strips.

9 Supply and erection of Sahl wood casing and capping for Per Rft. 1.20 10.50 Per Metre 3.90 34.35 38.8wiring purposes, including insulation cleats, screws, etc. complete.

10 Supply and erection of single core PVC insulated copper 38.1conductor cables, in prelaid PVC pipe/M.S. conduit/G.Ipipe/wooden strip batten/wooden casing an capping/G.I.wire/trenches (rate for cables only):-

a) 250/440 volts, PVC insulated:

i) 3/0.74 mm (3/0.029") Per Rft. 2.35 6.15 Per Metre 7.80 20.15 ii) 3/0.91 mm (3/0.036") Per Rft. 2.35 8.05 Per Metre 7.80 26.35 iii) 7/0.74 mm (7/0.029") Per Rft. 2.35 10.65 Per Metre 7.80 35.00 iv) 7/0.91 mm (7/0.036") Per Rft. 2.65 15.45 Per Metre 8.65 50.70 v) 7/1.12 mm (7/0.044") Per Rft. 2.95 21.45 Per Metre 9.75 70.30 vi) 7/1.63 mm (7/0.064") Per Rft. 3.65 42.10 Per Metre 12.00 138.05 vii) 19/1.32 mm (19/0.052") Per Rft. 8.35 66.55 Per Metre 27.35 218.30 viii) 19/1.63 mm (19/0.064") Per Rft. 9.75 89.60 Per Metre 31.90 293.85

chapter-24(Electric Installation) Page 154

Page 158: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

b) 250/440 volts, PVC insulated cotton braided andcompounded cables:-

i) 3/0.74 mm (3/0.029") Per Rft. 2.65 6.40 Per Metre 8.65 21.00 ii) 3/0.91 mm (3/0.036") Per Rft. 2.65 8.30 Per Metre 8.65 27.20 iii) 7/0.74 mm (7/0.029") Per Rft. 2.65 10.95 Per Metre 8.65 35.85 iv) 7/0.91 mm (7/0.036") Per Rft. 2.80 15.60 Per Metre 9.15 51.20 v) 7/1.12 mm (7/0.044") Per Rft. 3.10 21.60 Per Metre 10.25 70.80 vi) 7/1.63 mm (7/0.064") Per Rft. 3.60 42.05 Per Metre 11.80 137.85

11 Supply and erection of single core PVC insulated, PVCsheathed copper conductor, 250/440 volts grade cable(BSS-2004), in prelaid PVC pipes/M.S. conduit/G.I.pipe/wooden strip batten/wooden casing andcapping/trenches, etc. (rate for cable only):-

i) 3/0.74 mm (3/0.029") Per Rft. 2.35 6.90 Per Metre 7.80 22.60 ii) 3/0.91 mm (3/0.036") Per Rft. 2.35 9.15 Per Metre 7.80 30.05 iii) 7/0.74 mm (7/0.029") Per Rft. 2.35 11.40 Per Metre 7.80 37.45 iv) 7/0.91 mm (7/0.036") Per Rft. 2.65 16.60 Per Metre 8.65 54.40 v) 7/1.12 mm (7/0.044") Per Rft. 2.95 22.95 Per Metre 9.75 75.25 vi) 7/1.63 mm (7/0.064") Per Rft. 3.65 44.35 Per Metre 12.00 145.45

12 Supply and erection of single core PVC insulated, PVCsheathed copper conductor, 660/1100 volts grade cable, in 38.1 toprelaid G.I. pipe/M.S. conduits/PVC pipe/G.I. wire/trenches, 38.7etc (rate for cable only):-

i) 7/1.63 mm (7/0.064") Per Rft. 3.60 45.40 Per Metre 11.80 148.90 ii) 19/1.32 mm (19/0.052") Per Rft. 3.95 59.55 Per Metre 13.00 195.35 iii) 19/1.63 mm (19/0.064") Per Rft. 4.30 81.20 Per Metre 14.15 266.30 iv) 19/2.11 mm (19/0.083") Per Rft. 4.75 153.25 Per Metre 15.60 502.75 v) 37//1.83 mm (37/0.072") Per Rft. 8.20 211.95 Per Metre 26.85 695.15 vi) 37/2.11 mm (37/0.083") Per Rft. 9.90 265.90 Per Metre 32.45 872.10 vii) 37/2.62 mm (37/0.103") Per Rft. 13.95 405.05 Per Metre 45.80 1,328.55

13 Supply and erection of copper conductor cables for service dittoconnection, in prelaid pipe/G.I. wire/trenches, etc. (rate forcable only):-

a) PVC insulated, PVC sheathed twin core, 250/440 volts.

i) 3/0.74 mm (3/0.029") Per Rft. 2.65 11.30 Per Metre 8.65 37.10 ii) 3/0.91 mm (3/0.036") Per Rft. 2.65 15.85 Per Metre 8.65 51.90 iii) 7/0.74 mm (7/0.029") Per Rft. 2.65 21.10 Per Metre 8.65 69.20

chapter-24(Electric Installation) Page 155

Page 159: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

iv) 7/0.91 mm (7/0.036") Per Rft. 2.80 30.30 Per Metre 9.15 99.40 v) 7/1.12 mm (7/0.044") Per Rft. 3.10 42.70 Per Metre 10.25 140.05 vi) 7/1.63 mm (7/0.064") Per Rft. 3.60 84.60 Per Metre 11.80 277.40

b) PVC insulated, PVC sheathed 3 core,660/1100 volt cable:-

i) 3/0.74 mm (3/0.029") Per Rft. 2.80 16.75 Per Metre 9.15 54.90 ii) 3/0.91 mm (3/0.036") Per Rft. 2.80 23.50 Per Metre 9.15 77.15 iii) 7/0.74 mm (7/0.029") Per Rft. 2.80 31.80 Per Metre 9.15 104.35 iv) 7/0.91 mm (7/0.036") Per Rft. 3.10 46.40 Per Metre 10.25 152.25 v) 7/1.12 mm (7/0.044") Per Rft. 3.30 65.25 Per Metre 10.80 214.00 vi) 7/1.63 mm (7/0.064") Per Rft. 3.75 131.00 Per Metre 12.35 429.75

c) PVC insulated, PVC sheathed 4 core,660/1100 volt non armoured cable:-

i) 3/0.74 mm (3/0.029") Per Rft. 2.95 21.80 Per Metre 9.75 71.55 ii) 3/0.91 mm (3/0.036") Per Rft. 2.95 29.70 Per Metre 9.75 97.50 iii) 7/0.74 mm (7/0.029") Per Rft. 3.10 40.45 Per Metre 10.25 132.65 iv) 7/0.91 mm (7/0.036") Per Rft. 3.10 59.10 Per Metre 10.25 193.85 v) 7/1.12 mm (7/0.044") Per Rft. 3.30 84.30 Per Metre 10.80 276.45 vi) 7/1.63 mm (7/0.064") Per Rft. 3.75 170.20 Per Metre 12.35 558.25 vii) 19/1.32 mm (19/0.052") Per Rft. 5.30 227.70 Per Metre 17.30 746.80

d) PVC insulated, PVC sheathed 4 core 660/1100 volt grade cable, Cost of trenches where necessaryarmoured with G.I. wire 16 SWG. is included in the rates.i) 19/1.32 mm (19/0.052") Per Rft. 5.30 271.70 Per Metre 17.30 891.25 ii) 19/1.63 mm (19/0.064") Per Rft. 5.65 360.15 Per Metre 18.55 1,181.35 iii) 19/1.83 mm (19/0.072") Per Rft. 5.95 488.80 Per Metre 19.45 1,603.35 iv) 19/2.11 mm (19/0.083") Per Rft. 6.40 678.15 Per Metre 21.05 2,224.25 v) 37//1.83 mm (37/0.072") Per Rft. 6.60 919.75 Per Metre 21.65 3,016.75 vi) 37/2.11 mm (37/0.083") Per Rft. 7.90 1,165.50 Per Metre 25.95 3,822.80 vii) 37/2.36 mm (37/0.093") Per Rft. 9.50 1,414.85 Per Metre 31.15 4,640.75 viii) 37/2.62 mm (37/0.103") Per Rft. 11.85 1,756.80 Per Metre 38.95 5,762.35

14 Supply and erection of M.S. sheet box of 16 SWG, 10 cm (4") 38.1deep, with 4.75 mm thick (3/16") bakelite sheet top, for torecessed wiring, including making holes for regulators, 38.7switches, plugs, etc.

i) 10 x 10 cm (4"x4") Each 38.95 88.15 Each 38.95 88.15 ii) 17.5 x 10 cm (7"x4") Each 48.70 123.50 Each 48.70 123.50 iii) 22.5 x 10 cm (9"x4") Each 64.90 153.40 Each 64.90 153.40

chapter-24(Electric Installation) Page 156

Page 160: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

iv) 20 x 25 cm (8"x10") Each 77.90 234.40 Each 77.90 234.40 v) 25 x 30 cm (10"x12") Each 97.35 317.20 Each 97.35 317.20 vi) 30 x 35 cm (12"x14") Each 129.80 417.45 Each 129.80 417.45

15 Supply and erection of round block of Sahl wood, 10x4 cm Each 11.15 20.75 Each 11.15 20.75 38.1(4"x1½") thick.

16 Supply and erection of teak wood board, 4.5 cm (1¾") thick. 38.1

i) 17.5 x 10 cm (7"x4") Each 15.60 67.20 Each 15.60 67.20 ii) 22.5 x 10 cm (9"x4") Each 15.60 79.20 Each 15.60 79.20 iii) 20 x 25 cm (8"x10") Each 17.30 92.90 Each 17.30 92.90 iv) 25 x 30 cm (10"x12") Each 19.45 125.05 Each 19.45 125.05 v) 30 x 35 cm (12"x14") Each 22.25 175.85 Each 22.25 175.85

17 Supply and erection of Sahl wood board, 4.5 cm (1¾") thick.

i) 17.5 x 10 cm (7"x4") Each 15.60 46.80 Each 15.60 46.80 ii) 22.5 x 10 cm (9"x4") Each 15.60 63.60 Each 15.60 63.60 iii) 20 x 25 cm (8"x10") Each 17.30 78.50 Each 17.30 78.50 iv) 25 x 30 cm (10"x12") Each 19.45 95.05 Each 19.45 95.05 v) 30 x 35 cm (12"x14") Each 22.25 111.05 Each 22.25 111.05

18 Supply and erection of iron/aluminum clad, 500 volts main 38.1 When the base frame is alreadyswitches with kitkat fuses, on angle iron board with 3 mm installed, the labour and composite(1/8") thick M.S. sheet covering, including bonding to earth rates will be reduced as follows:- For with necessary flexible pipe and thimbles, etc. 15 to 35 Amps. by Rs. 21.20 and Rs.

145.50. For 60 to 65 Amps. by Rs.a) double pole: 38.80 and Rs. 252.60. For 100 Amps.

by Rs. 38.80 and Rs. 350.80.i) 15/20 Amp. Each 259.60 1,056.10 Each 259.60 1,056.10 ii) 30/35 Amp. Each 259.60 1,320.10 Each 259.60 1,320.10 iii) 60/65 Amp. Each 389.40 1,767.90 Each 389.40 1,767.90 iv) 100 Amp. Each 389.40 2,279.10 Each 389.40 2,279.10

b) triple pole:i) 15/20 Amp. Each 389.40 1,487.10 Each 389.40 1,487.10 ii) 30/35 Amp. Each 259.60 1,734.10 Each 259.60 1,734.10

c) triple pole with neutral link:

i) 30/35 Amp. Each 259.60 1,854.10 Each 259.60 1,854.10 ii) 60/65 Amp. Each 389.40 2,359.45 Each 389.40 2,359.45 iii) 100 Amp. Each 499.90 2,973.90 Each 499.90 2,973.90

chapter-24(Electric Installation) Page 157

Page 161: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

19 Supply and erection of iron/aluminum clad, 500 volts main When the base frame is alreadyswitches with triple pole and neutral link and HRC fuses, on 38.1 installed, the labour & compositeangle iron board with 3 mm (1/8") thick M.S. sheet covering, rates will be reduced as follows:-including bonding to earth with necessary flexible pipe andthimbles. i) For 60/65 Amp. by Rs. 21.20 and

Rs. 145.50.60/65 Amp Each 389.40 2,434.20 Each 389.40 2,434.20 ii) For 100 to 300 Amp. by Rs. 21.20100 Amp Each 499.90 3,493.90 Each 499.90 3,493.90 and Rs. 350.80150 Amp Each 499.90 4,933.90 Each 499.90 4,933.90 iii) For 400 to 500 Amp. by Rs. 42.20200 Amp Each 1,135.20 7,779.60 Each 1,135.20 7,779.60 and Rs. 526.20300 Amp Each 1,135.20 9,032.40 Each 1,135.20 9,032.40 400 Amp Each 1,597.20 12,102.60 Each 1,597.20 12,102.60 500 Amp Each 1,702.80 15,443.10 Each 1,702.80 15,443.10

20 Supply and erection of iron/aluminum clad, branch ditto When the base frame is alreadydistribution board, 250 volt, on angle iron frame of suitable installed the labour and compositesize with 3 mm (1/8") M.S. sheet covering: rates will be reduced by Rs. 19.50 &

Rs. 152.20 respectively.i) 2 way, 15 Amp per way Each 129.80 450.20 Each 129.80 450.20 ii) 3 way, 15 Amp per way Each 129.80 450.20 Each 129.80 450.20 iii) 4 way, 15 Amp per way Each 129.80 516.20 Each 129.80 516.20 iv) 5 way, 15 Amp per way Each 129.80 570.20 Each 129.80 570.20 v) 6 way, 15 Amp per way Each 129.80 612.20 Each 129.80 612.20 vi) 7 way, 15 Amp per way Each 129.80 660.20 Each 129.80 660.20 vii) 8 way, 15 Amp per way Each 129.80 708.20 Each 129.80 708.20 viii) 9 way, 15 Amp per way Each 129.80 756.20 Each 129.80 756.20 ix) 10 way, 15 Amp per way Each 129.80 828.20 Each 129.80 828.20 x) 11 way, 15 Amp per way Each 129.80 876.20 Each 129.80 876.20 xi) 12 way, 15 Amp per way Each 129.80 930.20 Each 129.80 930.20 xii) 2 way, 30 Amp per way Each 194.70 515.10 Each 194.70 515.10 xiii) 3 way, 30 Amp per way Each 194.70 521.10 Each 194.70 521.10 xiv) 4 way, 30 Amp per way Each 194.70 575.10 Each 194.70 575.10 xv) 5 way, 30 Amp per way Each 194.70 635.10 Each 194.70 635.10 xvi) 6 way, 30 Amp per way Each 194.70 677.10 Each 194.70 677.10 xvii) 7 way, 30 Amp per way Each 194.70 737.10 Each 194.70 737.10 xviii)8 way, 30 Amp per way Each 194.70 785.10 Each 194.70 785.10 xix) 9 way, 30 Amp per way Each 194.70 833.10 Each 194.70 833.10 xx) 10 way, 30 Amp per way Each 194.70 905.10 Each 194.70 905.10

chapter-24(Electric Installation) Page 158

Page 162: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

21 Supply and erection of bus bars, for 500 volts 3 phase A.C. When the base frame is alreadysupply with four copper bars, including glazed porcelain 38.1 installed the labour and compositebridges, on angle iron board, fixed with rag bolts and M.S. rates will be reduced by Rs. 21.20 andsheet box 1.5 mm thick, etc. complete:- Rs. 145.50 respectively.

i) 60 Amp. with 4 copper bars Each 462.00 2,270.90 Each 462.00 2,270.90 size 1½"x1/8" (40 x 3 mm)

ii) 100 Amp. with 4 copper bars Each 462.00 2,270.90 Each 462.00 2,270.90 size 1½"x1/8" (40 x 3 mm)

iii) 200 Amp with 4 copper bars Each 712.80 2,641.70 Each 712.80 2,641.70 size 2"x1/8" (50x 3 mm)

iv) 300 Amp with 4 copper bars Each 884.40 2,813.30 Each 884.40 2,813.30 size 2"x3/16" (50x 5 mm)

v) 500 Amp with 4 copper Each 567.60 3,007.50 Each 567.60 3,007.50 size 2"x1/4" (50x 6 mm)

22 i) Supply and erection of plain pendent lamp holder, Each 8.80 80.80 Each 8.80 80.80 38.1complete with bakelite lamp holder and flexible twin wire23/0.0076" upto 2 metre length (without bulb and shade).

ii) Extra for additional length of flexible wire, beyond Per Rft. -- 1.65 Per Metre -- 5.45 2 metres.

23 Supply and erection of counter weight pedent with porcelain Each 17.60 192.80 Each 17.60 192.80 38.1

counter weight, and fitting on bakelite lamp holder, withflexible twin wire 23/0.0076" complete (without bulb andshade).

24 Supply and erection of stiff pedent with brass/metal pipe 6.3 Each 23.75 272.15 Each 23.75 272.15 dittocm (2.5") long, and 15 mm (½") dia brass oxidised or painted,along with brass lamp holder with VIR/PVC cable 3/0.74 mm(3/0.029").

25 Supply and erection of 22.5 cm (9") long swan neck plain Each 24.60 63.00 Each 24.60 63.00 dittobrass/steel brass oxidised bracket lamp holder, complete.

26 Supply and erection of wall type/pole type bracket, with double Each 33.95 323.15 Each 33.95 323.15 dittocover water tight reflector, flexible wire and brass bolder.

27 Supply and erection of bakelite button holder shade, large Each 5.70 33.30 Each 5.70 33.30 dittosize.

28 Supply and erection of call bell 220/250 volts, fixed on teak Each 23.75 187.10 Each 23.75 187.10 38.1wood board 17.5x10 cm (7"x4").

chapter-24(Electric Installation) Page 159

Page 163: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

29 Supply and erection of bell push or bed switch, with 5 metres Each 5.30 170.90 Each 5.30 170.90 38.1twin flexible wire 23/0.0076".

30 Supply and erection of ceiling rose, bakelite. Each 8.80 19.30 Each 8.80 19.30 ditto

31 Supply and erection of switches 5 Amp.

i) open type Each 8.45 20.15 Each 8.45 20.15 dittoii) piano type Each 8.45 20.15 Each 8.45 20.15 iii) ring type, recessed Each 8.45 15.65 Each 8.45 15.65 iv) plate type, recessed Each 8.45 40.55 Each 8.45 40.55 v) double control, open type Each 11.25 29.25 Each 11.25 29.25 vi) double control, ring type recessed Each 11.25 30.45 Each 11.25 30.45 vii) double control, piano type Each 11.25 26.85 Each 11.25 26.85

32 Supply and erection of switches 10/15 Amp. ditto

i) open type Each 8.45 31.25 Each 8.45 31.25 ii) recessed type Each 8.45 39.65 Each 8.45 39.65

33 Supply and erection of wall socket with 3 pin 5 Amp, shoe. Each 8.45 61.25 Each 8.45 61.25 ditto

34 Supply and erection of 3 pin. 5 Amp wall socket. Each 8.45 45.65 Each 8.45 45.65 ditto

35 Supply and erection of 3 pin, 10/15 Amp. wall socket. ditto

i) open type Each 8.45 39.65 Each 8.45 39.65 ii) recessed type Each 8.45 75.65 Each 8.45 75.65

36 Supply and erection of 3 pin switch and plug combined, dittorecessed type.

i) 5 Amp Each 8.45 58.85 Each 8.45 58.85 ii) 10/15 Amp Each 8.45 83.45 Each 8.45 83.45

37 Supply and erection of 3 pin 10/15 Amp. wall socket with shoe, Each 8.45 118.85 Each 8.45 118.85 dittoopen type.

38 Supply and erection of cut out, bakelite. ditto

i) open type Each 4.70 23.90 Each 4.70 23.90 ii) recessed type Each 4.70 29.90 Each 4.70 29.90

chapter-24(Electric Installation) Page 160

Page 164: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

39 Supply and erection of button holder. 38.1

i) bakelite large size Each 5.30 20.90 Each 5.30 20.90 ii) brass Each 5.30 20.90 Each 5.30 20.90

40 Supply and erection of brass bracket with holder. Each 7.05 22.65 Each 7.05 22.65 ditto

41 Supply and erection of bell push open/recessed type Each 4.70 15.50 Each 4.70 15.50 ditto(without flexible wire).

42 Supply and erection of kitkat, 500 volt: ditto

i) 15/20 Amp Each 8.25 33.45 Each 8.25 33.45 ii) 30/35 Amp Each 9.00 34.20 Each 9.00 34.20 iii) 60/65 Amp Each 13.75 53.95 Each 13.75 53.95 iv) 100 Amp Each 15.45 89.25 Each 15.45 89.25 v) 200 Amp Each 17.70 129.90 Each 17.70 129.90 vi) 300 Amp Each 17.70 277.50 Each 17.70 277.50 vii) 400 Amp Each 22.70 347.30 Each 22.70 347.30 viii) 500 Amp Each 22.70 496.70 Each 22.70 496.70

43 Supply and erection of tube light, including rod, choke, starter 38.1with frame, flexible wire, including connection from ceilingrose, etc., complete.

i) double rod (80 watts) with two chokes and 2 starters. Per set 141.90 936.30 Per set 141.90 936.30

ii) single rod (40 watts) with one choke and one starter. ditto 113.50 469.90 ditto 113.50 469.90

iii) round tube, 32 watt, with one choke and one starter, Each 113.50 532.30 Each 113.50 532.30 without cover.

iv) round tube, 32 watt with one chock and one starter, with ditto 94.60 633.40 ditto 94.60 633.40 cover.

44 Providing and fixing M.S. iron box for housing main switches, dittomade of 1.5 mm (1/16") thick M.S. sheet, with lockingarrangement, including painting:-i) 60x35x15 cm (24"x14"x6") Each 297.00 1,880.80 Each 297.00 1,880.80 ii) 95x40x20 cm (38"x16"x8") Each 431.20 2,326.30 Each 431.20 2,326.30 iii) 105x52.5x22.5 cm (42"x21"x9") Each 656.30 3,205.70 Each 656.30 3,205.70 iv) 135x70x27.5 cm (54"x28"x11") Each 726.00 4,752.40 Each 726.00 4,752.40

chapter-24(Electric Installation) Page 161

Page 165: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

45 Supply and erection of girder clamp hook, 16 mm (5/8") with Each 18.90 124.50 Each 18.90 124.50 38.1M.S. plate 25x6 mm (1"x¼"), with bolts and nuts for hanging &ceiling fans. 38.10

46 Supply and erection of girder strut, of M.S. tee section Each 23.75 552.15 Each 23.75 552.15 ditto40x40x6 mm (1½"1½"x ¼"), complete with clamp, bolts andnuts, etc., including fixing with cement concrete 1:3:6.

47 Supply and erection of roof suspension hook, 16 mm (5/8") Each 25.45 1,150.65 Each 25.45 1,150.65 38.1dia rod with 75x40x3 mm (3"x1½"x1/8") M.S. steel channel, with clamp, bolts and nuts, etc., including fixing with cementconcrete 1:3:6.

48 Supply and erection of roof suspension hook of M.S plate Each 33.95 442.55 Each 33.95 442.55 75x40x12.7mm (3"x1½"x½") with 16 mm (5/8") hook completewith bolts, nuts and fixing with cement concrete 1:3:6

49 Supply and erection of 3/8" (10 mm) dia M.S. bar fan hook, Each 10.85 25.25 Each 10.85 25.25 dittoplaced at the time of casting of slab.

50 Erection of circular L.T. pole in cement concrete 1:3:6 one Each 286.10 1,590.25 Each 286.10 1,590.25 38.12metre below ground level (excluding the cost of pole),including cement concrete collar (1:2:4) excavation offoundation, and finishing surface.

51 Supply and erection of bracket of M.S. channel 75x40x6 mm (3"x1½"x¼") section:-i) 0.60 metre (2') long for 2 lines. Each 75.45 506.65 Each 75.45 506.65 ii) 1.200 metre (4') long for 4 lines. Each 88.00 995.85 Each 88.00 995.85

52 Supply and erection of anchor rod Henley type for pole, Per Rft. 4.35 15.95 Per Metre 14.35 52.25 38.14including necessary clamps and 7/12" stay wire, strainingscrews, etc., erected in cement concrete 1:3:6 and collar ofcement concrete.

53 Supply and erection of stay for house service pipe, erected Per Rft. 6.80 25.00 Per Metre 22.25 82.00 dittowith straining screws and 7/14" stay wire, complete.

54 Supply and erection of house service pipe Henley (G.I. pipe Per Rft. 28.85 179.50 Per Metre 94.60 588.70 water quality) or pole type, 50 mm (2") dia, erected to instalinsulated overhead line,include shackle insulator for holdinginsulated wire and straining devices for bearer wire and otheraccessories etc., complete.

chapter-24(Electric Installation) Page 162

Page 166: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

55 Supply and erection of house service pipe 50 mm (2") dia G.I. Per Rft. 25.50 175.00 Per Metre 83.60 574.00 pipe Henley or pole type for bare copper wire overhead line,including shackle insulator, straining devices and otheraccessories etc.

56 Supply and erection of lightning arrestor horn type, complete. Each 142.55 2,062.55 Each 142.55 2,062.55

57 Supply and erection of shackle insulator, medium size. Each 19.90 169.90 Each 19.90 169.90 38.12

58 Supply and erection of pin insulator, green medium size. Each 19.90 61.90 Each 19.90 61.90 ditto

59 Supply and erection of bare copper conductor wire No. 2 to Per Kg 10.35 949.15 Per Kg 10.35 949.15 38.1No. 10 SWG, including binding wire No. 16 SWG.

60 Supply and erection of G.I. wire of all sizes, including binding Per Kg 10.35 97.15 Per Kg 10.35 97.15 dittowire No. 16 SWG for support of rubber wire or earthing wire,pole to pole etc.

61 Wiring overhead line in 2 single core, PVC/weather proof 38.12cable, on G.I. wire No. 8 SWG bearer wire and in house service pipe, including connection through joint box.

i) 3/0.74 mm (3/0.029") Per Rft. 2.40 7.65 Per Metre 7.90 25.05 ii) 7/0.74 mm (7/0.029") ditto 2.40 13.20 ditto 7.90 43.30 iii) 7/0.91 mm (7/0.036") ditto 2.40 17.80 ditto 7.90 58.35 iv) 7/1.12 mm (7/0.044") ditto 2.40 23.25 ditto 7.90 76.35

62 Supply and erection of all aluminum stranded hard drawn bare Per Rft. 4.95 16.65 Per Metre 16.25 54.65 38.1conductor, of size 7/3.099 mm (7/0.122").

63 Supply and erection of street light pole bracket 30 mm (1¼") Each 118.80 657.55 Each 118.80 657.55 G.I. pipe 2 metre long, complete with 2 No. pole clamp.

64 Supply and erection of pole mounted street light, holders, shade and glass, etc., for fitting 125/250 watts mercury vapourlamp (excluding cost of lamps):

i) G.E.C. design Each 237.60 2,481.60 Each 237.60 2,481.60 ii) Philips design ditto 237.60 2,907.60 ditto 237.60 2,907.60

65 Supply and fitting of mercury vapour lamp, complete with

choke set.i) 125 watt lamp Each 94.60 934.60 Each 94.60 934.60 ii) 250 watt lamp ditto 113.50 1,733.50 ditto 113.50 1,733.50

chapter-24(Electric Installation) Page 163

Page 167: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

66 Manufacture and erection of angle iron lattice steel structure Each 4,141.10 14,757.95 Each 4,141.10 14,757.95 38.13 The composite rate will be reducedpole (36.0') 10,923 mm long 9348 mm (30.5') above ground or increased by Rs. 36.50 for eachlevel) 355 mm (14") square at base and 204 mm (8") square at (100 mm) of reduction or addition intop for electric distribution line, using 1¼"x1¼"x3/16" (30x30x5 the height of the pole above groundmm) angle iron legs and ¾"x¾"1/8" (20x20x3 mm) angle iron level.bracing 420 mm (17") long fixed between legs on all the foursides in diagonal position, and 1¾"x1¾"x3/16"(45x45x5 mm)angle iron on top and 4 bands of M.S. flat iron 2"x¼" (50x6 mm)305 mm (12") centre to centre, as per standard drawingincluding silver painting of pole 3 coats, excavation and refillingof foundation cement concrete 1:2:4. 6'-0"x1'-8"x1'-8"(1807x500x500 mm) for foundation, etc, complete in allrespects.

67 Manufacture and erection of galvanized angle iron lattice steel Each 3,846.90 22,250.75 Each 3,846.90 22,250.75 38.13 The composite rate will be reducedstructure pole 37 ft. (11.25 m) long 30 ft. (9 m) above ground or increased by Rs. 237.00 for eachlevel), 34" square (850 mm) at base, 13.75" (35 mm) square at foot (300 mm) of reduction ortop, for electric distribution line, using 2"x2"x5/32" addition in the height of the pole(50x50x4mm) high tensile steel angle iron legs, and 1-3/8"x above ground level.1-3/8"x1/8" (35x35x3 mm) M.S. angle iron bracings fixedbetween legs on all the four sides in diagonal position as perstandard drawing including silver painting of pole, excavationand refilling of foundation, one ft. (300 mm) thick cementconcrete 1:3:6 foundation of outer size 8'x3½'x3½'(2400x1050x1050 mm), etc. complete in all respects.

68 Earthing of iron clad/aluminum switches, etc. with G.I. wire No. Job 501.60 2,467.70 Job 501.60 2,467.70 8 SWG in G.I. pipe 15 mm (½") dia, recessed or on surface ofwall and floor, complete with 1.5 metre long G.I. pipe, 50 mm(2") dia with reducing socket 4 to 5 metre below ground level,and 2 metre away from building plinth.

69 Earthing of Metallic cases, etc. with G.I. wire No. 8 SWG, in 38.1115 mm (½") dia G.I. pipe, best quality:-i) on surface, including clamps, etc. Per Rft. 5.45 38.20 Per Metre 17.80 125.25 ii) recessed in wall, including hooks, ditto 12.25 45.75 ditto 40.15 150.05

jharries and making good surface.

70 Bonding to earth with wire on surface, including cost of wire, dittoclamps, thimbles, etc.

a) G.I. wire:i) 8 SWG Per Rft. 2.60 7.35 Per Metre 8.45 24.10 ii) 16 SWG ditto 2.60 3.85 ditto 8.45 12.70

chapter-24(Electric Installation) Page 164

Page 168: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

b) Copper wire:

i) 16 SWG Per Rft. 2.60 9.00 Per Metre 8.45 29.60 ii) 20 SWG ditto 2.60 4.90 ditto 8.45 16.15

71 Erection only, of lightning conductor of copper tape, including Per Rft. 8.70 12.15 Per Metre 28.50 39.80 38.11 Rate includes all materials requiredsupply of copper staple and copper nails and cement, sand in erection (excluding copper tapemortar. lightning conductor).

72 Supply and erection of 600x600x3 mm (2'x2'x1/8") copper Each 334.40 3,557.10 Each 334.40 3,557.10 dittoplate, including revitting to copper tape and placing in mixtureof salt and charcoal, etc.

73 Supply and erection of copper tape, including copper staple copper nails, cement, sand, etc.

i) tape 40x3 mm (1½"x1/8") Per Rft. 12.25 106.80 Per Metre 40.15 350.35 ii) tape 50x3 mm (2"x1/8") ditto 12.25 125.10 ditto 40.15 410.35

74 Supply and erection of 25 mm (1") dia and one metre long Job 237.60 2,127.60 Job 237.60 2,127.60 lightning conductor copper rod with 5 spikes on ball and base,etc. complete.

75 Supply and erection of electric energy meter, including meter 38.1testing fee, etc.

a) single phase:

i) 1x10 Amp, 250 volts Each 105.60 1,869.60 Each 105.60 1,869.60 ii) 1x30 Amp, 250 volts ditto 105.60 1,869.60 ditto 105.60 1,869.60

b) three phase, 4 wires:

i) 3x15 Amp, 400 volts Each 211.20 5,329.20 Each 211.20 5,329.20 ii) 3x50 Amp, 400 volts ditto 283.80 5,401.80 ditto 283.80 5,401.80 iii) 3x80 Amp, 400 volts ditto 283.80 5,401.80 ditto 283.80 5,401.80

76 Rewinding of A.C. ceiling fan, capacitor type, including cost of The credit of out turn of dismantledwire, leatheride paper cotton tape, soldering, etc. material has been accounted for in

the rate.i) 1200 mm (48") sweep, 275-300 RPM. Each 194.70 854.70 Each 194.70 854.70 ii) 1400 mm (56") sweep, 250-275 RPM. ditto 212.85 1,066.15 ditto 212.85 1,066.15

chapter-24(Electric Installation) Page 165

Page 169: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

77 Rewinding of A.C. exhaust fan, including cost of wire, The credit of out turn of dismantledleatheride paper, cotton tape, soldering, etc. material has been accounted for in

the rate.i) 375 mm (15") sweep, and 1300-1500 RPM Each 140.80 653.90 Each 140.80 653.90 ii) 450 mm (18") sweep, and 1300-1500 RPM ditto 140.80 743.55 ditto 140.80 743.55

78 Rewinding of pedestal fan 600 mm (24") sweep, and 900-950 Each 168.95 865.80 Each 168.95 865.80 The credit of out turn of dismantledRPM, including wire, leatheride paper, cotton, tape, etc. material has been accounted for in

the rate.79 Supply and fitting of regulator knob with shaft Each 26.40 86.40 Each 26.40 86.40 38.1

and plate of electric fan regulator.

80 Supply and fitting of capacitor 2.2 uF, for ceiling fans. Each 21.10 45.10 Each 21.10 45.10 ditto

81 Supply and fitting of ball bearing of size Each 26.40 134.40 Each 26.40 134.40 ditto6201, 6202 or 6203 for ceiling fans.

82 Rewinding regulator of ceiling fan 48"/56" (1200/1400 mm) Each 52.80 187.90 Each 52.80 187.90 The credit out turn of dismantledsweep, to control 3/4 speeds. material has been accounted for in

the rate.83 Erection of ceiling fan alongwith regulator (all sizes), including Each 94.45 118.45 Each 94.45 118.45

carriage from local Railway Station/Store to site of work,electric wire/cable for suspension rod and board connection,and cutting, threading on the rod, where necessary.

chapter-24(Electric Installation) Page 166

Page 170: 26467Sahiwal_1st_010

IRON WORKThe Rates for all finished works include the removal of surplus debris, unused material and byproduct

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

Railway Track, etc.

1 Laying, linking and packing tramway line. 100Lft. 784.45 Metre 25.75

2 Dismantling tramway track. 100Lft. 258.35 Metre 8.45

3 Laying, linking of B.G. track, including packing, 100Lft. 2046.00 Metre 67.10straightening and leveling.

4 Linking points and crossings, complete with fastenings. Each 1953.60 Each 1953.60

5 Bending or strainghtening B.G. rail with Jim Each 229.70 Each 229.70Crow. Point Point

6 Fixing street lamp posts. Each 246.85 Each 246.85

7 Binding ends of sleepers and timber of all sizes and kinds, 100 Nos 2382.60 100 Nos 2382.60including spreading and restacking.

8 Opening stacks of sleepers and timber of all kinds and 100 Nos 294.80 100 Nos 294.80sizes, including spreading for inspection and restackingwithin one chain lead.

IRON WORK

9 Small iron work, such as gusset plates, knees, bends, Per Cwt 1359.60 4897.55 100 Kg 2676.40 9640.90stirrups, straps, rings, etc. including cutting, drilling,riveting, handling, assembling and fixing; but excludingerection in position.

10 Fabrication of heavy steel work, with angle, tees, flat iron Per Cwt 472.55 3837.40 100 Kg 930.25 7553.90round iron and sheet iron for making trusses, girders,tanks, etc., including cutting, drilling, revitting, handling,assembling and fixing, but excluding erection in position.

11 Erection and fitting in position iron trusses, staging of Per Cwt 143.75 100 Kg 282.95water tanks, etc.

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-25(Iron work) Page 167

Page 171: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

12 Fixing corrugated iron sheet, including revitting, etc. 100 Sft. 570.25 sq.m 61.35

13 Erecting corrugated iron sheet tanks, upto 20' Per Cwt 252.90 100 Kg 497.80(6 m) height.

14 Erecting rolled steel beams or old rails, in roofs, etc., Per Cwt 147.40 100 Kg 290.15erection and fixing in position.

15 Erecting rolled steel beams or rails, erection for posts etc. Per Cwt 72.40 100 Kg 142.50(other than in roofs).

16 Making bolts and nuts of iron rods. Per Cwt 1069.20 5476.40 100 Kg 2104.70 10780.35

17 Cutting rails, rolled steel joists and beams, with hacksaw:-

a) upto 6" size (150 mm) Per Cut 97.00 Per Cut 97.00b) above 6" size (150 mm) Per Cut 143.60 Per Cut 143.60

18 Cutting rails or rolled steel beams of size below 6" Per 46.20 Per Cwt 46.20(150 mm), with jim. Cut Cut

19 Bending rolled steel beams or rails. Per 53.45 255.00 Per 53.45 255.00Bend Bend

20 Drilling holes, in plates upto ½" (13 mm) thick, per inch Per 19.00 Per 19.00dia, (25mm) or part thereof. Hole Hole

21 Extra for drilling holes in plates over ½" (13 mm) thick, per Per 10.40 Per 10.40inch dia, (25 mm) or part thereof. Hole Hole

22 Rivetting 1/8" dia (3 mm). 100 Nos 297.00 100 Nos 297.00

23 Cutting out Rivets, all sizes. 100 Nos 808.50 100 Nos 808.50

24 Fitting and erection of gutters of sheet iron. Per Lft. 33.15 Metre 108.80

25 Cutting and fixing iron bars, for barred windows. Per bar 19.40 Per bar 19.40

26 Cutting G.I. sheets. Each 9.95 Each 9.95Cut Cut

27 Notching web or foot of rail posts, for housing rail beams Per 237.60 372.00 Per 237.60 372.00Notch Notch

chapter-25(Iron work) Page 168

Page 172: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

28 Hoop iron netted trellis work fixed with nails Per Sft. 12.95 sq.m 139.20

29 Fixing zinc iron or G.I. sheet on table tops Per Sft. 8.40 sq.m 90.25

30 Making and fixing steel grated doors, complete wit Per Sft. 82.05 451.85 sq.m 882.65 4862.05locking arrangement, angle iron frame 2"x2"x3/8(50x50x10 mm) and ¾" (20 mm) square bars 4" (100 mm)centre to centre.

31 Making and fixing steel grated door with 1/16" thic Per Sft. 85.80 568.55 sq.m 923.20 6117.55(1.5mm) sheeting, including angle iron frame 2"x2"x3/8(50x50x10 mm) and ¾" (20 mm) square bars 4" (100 mm)centre to centre, with locking arrangement

32 Making and fixing grating in opening, including fixing Per Sft. 33.15 221.60 sq.m 356.85 2384.45site with flat iron 2"x3/8" (50x10 mm) and ¾" (19 mm)square bars, at 4" (100 mm) centre to centre.

33 Providing and fixing stair railing (all types and designs) o Per Rft. 192.65 537.70 Metre 632.10 1764.15 The composite rate shall behard wood, including bends and corners, screwed to reduced or increased by Rs. 31.905/8"x5/8" (16x16 mm) M.S. square bars 2.75 ft. (838 mm) for each foot of reduction orhigh, at 5.5 inch (137 mm) inch centre to centre, fixed in addition in the height of the squaresteps of stairs, M.S. flat 1"x1/8" (25x3 mm) welded to bars.bars, painting/polishing 3 coats, etc. complete

34 Providing/fixing stair railing consisting of M.S. Box sectio Per Rft. 98.30 365.05 Metre 322.40 1197.60size 1-1/2"x3" of 16 SWG welded with M.S. flat 1"x1/8"continuously and welded over M.S. square bars 5/8"x5/8"punched in M.S. flat 2 ¾' high @ 5½" c/c fixed in steps ofstair I/C painting 3 coats complete

35 Providing and fixing terrace railing of 2" (50 mm) i/ Per Rft. 71.05 388.60 Metre 233.10 1274.93 -do-conduit pipe 16 SWG, welded with 5/8"x5/8" (16x16 mm)square bar 2.75 ft. (838 mm) high fixed at 5" (125 mm)centre to centre, in reinforced cement concrete slab withsuitable arrangement, complete in all respects, as pedesign and drawing

36 Providing and fixing collapsible gate made of 2"x2"x"¼ Per Sft. 125.40 434.95 sq.m 1349.40 4680.30(50x50x6 mm) tee iron at top and bottom, channel ironverticals ¾"x¼"x¼"x1/8" (20x6x6x3 mm) at 3" (75 mm) to5" (125 mm) centre to centre (approximate) and flat ironcrosses 3"x3/16" (75x5 mm), and best quality rollers abottom of 3" (75 mm) diameter including holdfastshandles 12" (300 mm) long of ¾"x¼"x¼"x1/8" (20x6x6x3mm) channel iron, locking arrangement inside andoutside, painting 3 coats of black Japan enameledcomplete in working order

chapter-25(Iron work) Page 169

Page 173: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

37 Providing and fixing 24 SWG G.I. sheet rolling shutter, Per Sft. 30.00 176.70 sq.m 322.55 1901.35consisting of steel frame of M.S. channel 2"x1¼"x1/8"(50x30x3 mm), angle iron 1½"x1½"x1/8" (40x40x3 mm),M.S. plate 1'x1'x1/8" (300x300x3 mm), G.I. pipe 1½" (37mm) dia, springs 2' (600 mm) centre to centre, rollers, 24SWG G.I. covering 1 ft. x 1 ft. (300x300 mm), handles,holdfast, and painting three coats, complete in allrespects.

38 Providing and fixing M.S. angle iron 1½"x1½"x¼" Per Rft. 14.90 91.20 Metre 48.90 299.15(40x40x6 mm) edge protector nozing of steps of stairs,having holdfast or 3/8" (10 mm) dia M.S. bars 8" (200 mm)long welded at 2' (600 mm) centre to centre andembedded in cement concrete on steps, complete in allrespects.

39 Providing and fixing stair railing of 2½" (63 mm) i/d G.I. Per Rft. 84.55 440.85 Metre 277.35 1446.40 The composite rate shall bepipe, welded with 5/8"x5/8" (16x16 mm) square M.S. bars reduced or increased by Rs. 31.902'-9" (838 mm) high, fixed in each step, complete in all for each foot of reduction orrespects, including painting, polishing three coats. addition in the height of the square

bars.40 Providing and fixing G.I. wire gauze 24 SWG, 12x12 Per Sft. 14.10 41.30 sq.m 151.50 444.35

meshes per square inch, fixed to steel windows or doors,etc., complete in all respects.

41 Providing and fixing steel windows with openable glazedpanels, using beam section for frame 1½"x1"x5/8"x1/8" For fixed pannels, the composite(40x25x16x3 mm), Z-section for leaves ¾"x1"x¾"x1/8" rate will be reduced by Rs.30.00(20x25x20x3 mm), T-section sashes 1"x1"x1/8" (25x25x3 per Sft. or Rs. 305.00 per Sq. mm), glass panes, wooden screed for glazing embedded metre.over a thin layer of putty duly screwed with leaves, brassfittings, holdfast, duly painted, complete in all respects,including all cost of material and labour, etc. as perapproved design and as directed by theEngineer-in-charge:-

a) without wire gauze:

i) glass pane 2 mm thick Per Sft. 36.75 192.60 sq.m 395.30 2072.35ii) glass pane 2.5 mm thick ditto 36.75 195.00 ditto 395.30 2098.15iii) glass pane 3 mm thick ditto 36.75 199.80 ditto 395.30 2149.80iv) glass pane 4 mm thick ditto 36.75 202.20 ditto 395.30 2175.65v) glass pane 5 mm thick ditto 36.75 204.60 ditto 395.30 2201.45

chapter-25(Iron work) Page 170

Page 174: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

b) fixed with wire gauze, 22 SWG

i) glass pane 2 mm thick Per Sft. 49.05 231.85 sq.m 527.65 2494.60ii) glass pane 2.5 mm thick ditto 49.05 234.25 ditto 527.65 2520.40iii) glass pane 3 mm thick ditto 49.05 239.05 ditto 527.65 2572.05iv) glass pane 4 mm thick ditto 49.05 241.45 ditto 527.65 2597.90v) glass pane 5 mm thick ditto 49.05 243.85 ditto 527.65 2623.70

42 Providing and fixing steel windows using M.S. sheet (16SWG) moulded tubular pipe 1½"x1½" (40x40mm) forframe and 1¼"x1¼" (30x30mm) for leaves including M.S.square bars ¼"x¼" (6x6 mm) welded around each panelof frame, 5 mm thick glass panes fixed with double M.S.square tubular pipe 3/8"x3/8" (10x10mm) (22 SWG)beading with U' shaped rubber lining, brass fitting,holdfast, including painting three coats complete in allrespects.a) For openable panels fixed with wire Per Sft. 39.75 226.80 Sq.m 427.60 2440.60

gauze 24 SWG, 12x12 mesh and glasspanes ¼" (6 mm) thick.

b) For fixed panels without wire gauze. ditto 38.70 126.80 ditto 416.25 1364.20

43 Providing and fixing windows consisting of M.S. box Per Sft. 37.00 274.10 Sq.m 397.85 2949.20section frame 2"x1½" (50x40mm), leaves frame 1-½"x1"(40x25mm) box section frame for glazing 3/8"x3/8"(10x10mm) using 16 SWG sheet 'U' shaped rubbersupported with 1"x1/8" (25x3mm) M.S. flat for fixing 3/16"(5 mm) thick glass panes M.S. box section ½"x½"(13x13mm) of 16 SWG for fixing 24 SWG wire gauze onouter side by means of ¾"x1/8" (20x3mm) M.S. flat andscrews I/C all C.P. fitting and painting 3 coats complete inall respect.

44 Providing and fixing windows consisting of M.S. box Per Sft. 45.55 326.05 Per Sft. 490.25 3508.45section frame 2"x1½", (50x40mm) leaves frame 1½"x1"(40x25mm) box section frame for glazing 3/8"x3/8"(10x10mm) using 16 SWG sheet 'U' shaped rubbersupported with 1"x1/8" (25x3mm) M.S. flat for fixing 3/16"(5 mm) thick glass panes M.S. box section ½"x½"(13x13mm) of 16 SWG for fixing 24 SWG wire gauze onouter side by means of ¾"x1/8" (20x3mm) M.S. flat andscrews including grill of M.S. flat ½"x1/8" (13x3mm) or¼"x¼" (6x6mm) square bar with independent frame of½"x½" (13x13mm) box section of 16 SWG i/c all C.P.fitting and painting 3 coats complete in all respect.

chapter-25(Iron work) Page 171

Page 175: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

45 Flapping G.I. pipes for bath room drains. Each 267.30 300.90 Each 267.30 300.90

46 Supply and fixing iron grating for fire place. Per Sft. 69.95 165.95 sq.m 752.75 1785.75

47 Fixing copper flashing, including cutting of sheets, Per Lft. 23.75 Metre 77.95grooving and rivetting.

48 Providing and fixing angle iron railing, using 2½"x2½"x3/8" Per Rft. 35.60 510.55 Metre 116.80 1675.05(63x63x10 mm) angle iron post 4½" (113 mm) long, 5' to6' (1500 to 1800 mm) apart, with 2½"x2½"x3/8" (63x63x10mm) angle iron top rail, and two rows of M.S. flat 2½"x¼"(63x6 mm) including fixing to side of Bridge/structure withU.bolt 1½' (450 mm) long ¾" (20 mm) dia, painting posts,etc. complete in all respects.

49 Providing and fixing barbed wire fencing on compound 100Rft. 862.15 6475.85 Metre 28.30 212.45wall, consisting of 1½"x1½"x3/16" (40x40x5 mm), angleiron post 3¼ ft. (990 mm) long, 5 to 6 ft. (1500 to 1800mm) centre to centre, embedded in cement concrete1:4:8, base of size 9"x9"x12" (225x225x300 mm), andthree rows of barbed wire, painting posts, etc. complete inall respects.

50 Providing and fixing barbed wire fencing on compound 100Rft. 1442.60 8279.10 Metre 47.35 271.60wall, consisting of 1½"x1½"x3/16" (40x40x5mm) angleiron post 3' (900 mm) long, 4' (1200 mm) apart embeddedin cement concrete 1:4:8 base of size 6"x6"x9"(150x150x225 mm) and 4 rows of barbed wire, includingbinding wire, painting posts, etc. complete in all respects.

51 Providing and fixing all types of partly fixed and partly (1) Increase rate by Rs. 30.00 per openable glazed anodised bronze colour aluminium Sft or Rs.322.80 per Sq-metre ifdoors, using delux section of M/s Al-Cop or Pakistan sections thickness is 2 mm.Cables, having chowkat frame of size 40 x 100 mm (1½" x (2) Reduce rate by Rs.20.00 per Sft4") and leaf frame of 60x40mm (2½"x1½") wide sections or Rs.215.20 per Sq-metre ifincluding the cost of ¼" (5 mm) thick imported tinted sections are of dull aluminimumglass with aluminium triangular gola and rubber gasket to Per Sft 46.85 385.30 sq. m 504.10 4145.85 shade.support the glass and leaf edging, using approved (3) Reduce rate by Rs.20.00 perstandard fittings, locks, 3" (75 mm) wide long handles Sft or Rs.215.20 per Sq-metre ifetc., and hardware any required as approved by the local glass is used.engineer in-charge.

chapter-25(Iron work) Page 172

Page 176: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

52 Providing and fitting all types of glazed aluminium Per Sft 67.50 286.35 sq. m 726.30 3081.15 (1) Reduce rate by Rs.20.00 per Sftwindows of anodised bronze colour partly fixed and partly or Rs.215.20 per Sq-metre ifsliding using delux sections of M/s Al-Cop or Pakistan section thickness is 1.2 mm.Cables having frame size of 100 x 20 mm (4"x¾") andleaf frame sections of 50 x 20 mm (2"x¾"), all of 1.6mm (2) Reduce rate by Rs.20.00 per Sftthickness including 5 mm thick imported tinted glass with or Rs.215.20 per Sq-metre ifrubber gasket using approved standard latches, hardware sections are of dull aluminiumetc., as approved by the Engineer in-charge. shade.

(3) Reduce rate by Rs.20.00 per Sftor Rs.215.20 per sq-metre if localglass is used.

chapter-25(Iron work) Page 173

Page 177: 26467Sahiwal_1st_010

MISCELLANEOUSRates for all finished works include the removal of surplus debris, unused material and byproduc

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

1 Notice board made of cement, sand mortar 1:3. Per Sft. 35.30 40.50 Per 379.95 435.70 The board is to be of cementsq.m plaster ½" (13 mm) thick, with 2"

(50 mm) wide and 1" (25 mm) thick beading.

2 Fixing handles to iron hammers. Each 44.00 - Each 44.00 -

3 Providing and fixing barbed wire fencing, with 4 horizontal 100Lft. 3,101.15 16,068.65 L.m. 101.75 527.20 Vertical bars in straining andand 2 number cross wires fixed with posts of R.C.C., 1:2:4 stiffening posts to be 4 No. each by(straining posts 7'x9"x9" (2.13 mx225x225 mm) at 100' ½" (13 mm) dia and for(30 m) centre to centre, stiffening posts 7'x6"x6" (2.13 intermediate posts to be 4 No. ofmx150x150 mm) at 50 ft. (15 m) interval and intermediate 3/8" (10 mm) dia Stirrups for allpost 7'x5"x5" (2.13 mx125x125 mm) at 8 ft.(2.4 m) centre posts to be ¼" (6 mm) dia. at 12"to centre), including cost of steel, its fabrication and (300 mm) centre to centre.placing of steel reinforcement, eye bolts, washers, etc.complete.

Surveying

4 Supplying Bamboo Jhandies 10' to 12' (3.00 to 3.65 m) with Each 24.80 117.20 Each 24.80 117.20 iron shoes, and flags 15" (375mm) square.

5 Supplying wooden pegs for levelling, 1½" (40 mm) dia, 6" 100Nos. 70.40 86.00 100Nos. 70.40 86.00 (150mm) long.

6 Supplying wooden pegs for alignment, 2" to 3" dia (50 to 100Nos. 168.95 348.95 100Nos. 168.95 348.95 75 mm), 9" (225 mm) long.

7 Fixing enamalled iron gauges flush with masonry, including Per Lft. 42.25 49.45 Per 138.60 162.20 cost of hooks. L.M.

8 Placing boundary pillars in position, including digging pits. Each 28.15 - Each 28.15 -

9 Fixing main line type distance mark in position, including Each 113.50 231.90 Each 113.50 231.90 Composite rate does not includemaking 1:3:6 cement concrete base block, size cost of iron distance marks.14"x10"x15" (350x250x375 mm).

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

chapter-26( Misc) Page 174

Page 178: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

Hand Pumps & Pressure Pipes

10 Cutting pipes, upto 2" (50 mm) dia. Per cut 23.75 - Per cut 23.75 -

11 Cutting pipe, above 2" (50 mm) dia. Per cut 44.10 - Per cut 44.10 -

12 Threading pipe ends, 1½" (40 mm) to 4" (100 mm) dia. Each 30.80 - Each 30.80 - End End

13 Assembling 1½" (40 mm) dia pressure pipe. 100Lft. 99.00 - Per Metre 3.25 -

14 Boring and fixing 1½" (40 mm) dia pressure pipe:

a) in ordinary soil Per Lft. 34.30 - Per Metre 112.60 - b) in clay Per Lft. 67.00 - Per Metre 219.80 - c) in shingle Per Lft. 99.66 - Per Metre 326.95 -

15 Repairs to hand pump, pulling out and refitting. Per Lft. 15.85 - Per Metre 51.95 -

16 Fixing hand pump (Machine only) Each 84.50 - Each 84.50 -

Rest House Furniture & Fuel, etc.

17 Washing Niwar of bed. Per bed 217.80 237.95 Per bed 217.80 237.95

18 Washing Durries. 100Sft. 290.40 338.40 sq.m 31.25 36.45

19 Recaning chairs:

i) office chairs, single caning seat only. Each 147.85 178.45 Each 147.85 178.45 ii) office chairs, double canning seat only. Each 190.10 233.30 Each 190.10 233.30 iii) office chairs, single caning back only. Each 105.60 107.55 Each 105.60 107.55 iv) office chairs, double caning back only. Each 168.95 185.50 Each 168.95 185.50 v) easy chairs, single caning seat only. Each 105.60 146.65 Each 105.60 146.65 vi) easy chairs, double caning seat only. Each 295.70 356.90 Each 295.70 356.90 vii) easy chairs, single caning only, back and seat in one Each 422.40 674.40 Each 422.40 674.40

piece.viii) easy chairs, double caning back & seat in one piece Each 633.60 1,245.60 Each 633.60 1,245.60

or couches with caned area about 16 Sft (1.5 Sqm).

20 Making and fixing Hat pegs ordinary. Each 76.05 354.65 Each 76.05 354.65

21 Weaving charpoy. Each 231.65 - Each 231.65 -

chapter-26( Misc) Page 175

Page 179: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

22 Sweeping chimney Each 48.40 49.60 Each 48.40 49.60

23 Picture railing, including making, fixing and painting Per Lft. 21.75 62.50 Per LM 71.35 205.05

24 Cutting fuel wood, from plantation 100Kg 64.80 - 100Kg 64.80 -

25 Splitting fuel wood 100Kg 135.75 - 100Kg 135.75 -

26 Burning charcoal, including loading, unloading and 100Kg of 231.30 - 100Kg of 231.30 - repairing kilns. Char- Char-

coal coal

27 Filling cement bags with coal and sewing (including cos 100Cft. 595.30 598.20 cu.m 210.25 211.30 of strings).

28 Supplying manure. Cart 72.60 192.60 Cart 72.60 192.60 Capacity of cart, 20 Cft. (0.57Load Load cu.m).

29 Washing punkha frills. Each 71.30 - Each 71.30 -

30 Washing:-

a) table cloth Each 17.80 - Each 17.80 - b) napkins, dusters, etc Each 11.90 - Each 11.90 -

31 Hoisting and placing sleepers for centring, includin Each 28.70 - Each 28.70 - carriage within one chain No. No.

32 Dismantling sleepers from centring, including stackin Each 29.85 - Each 29.85 - within one chain No. No.

33 Dredging Sumps. Per 1,089.00 - Per 1,089.00 - Not less than five gangmen to beShift Shift employed for each shift to ensur

effective dredging

34 Fixing `U' bolt in masonry or concrete, including levellin Each 105.60 - Each 105.60 - and tying for fixing angle iron post

35 Bailing out water:-

a) by hand 1000 Cft. 871.20 - cu.m 30.75 - Rate includes cost of providingb) by pump 1000 Cft. 111.40 215.20 ditto 3.95 7.60 pump, POL and operation charges

etc.

36 Drilling holes in R.C. Trough Per Nos. 59.40 - Per Nos. 59.40 -

chapter-26( Misc) Page 176

Page 180: 26467Sahiwal_1st_010

Sr. Description Rate (British System) Rate (Metric System) Spec. RemarksNo. No.

Unit Labour Composite Unit Labour Composite

MRS, 1ST QUARTER OF 2010 (January to March) DISTRICT SAHIWAL

37 Supplying and laying polythene sheet over D.P.C. unde The rate includes overlapsfloors and on roofs, etc

i) 300 gauge (.003" thick) Per Sft. 0.55 1.65 sq.m 5.75 17.80 ii) 500 gauge (.005" thick) Per Sft. 1.05 2.00 sq.m 11.50 21.60

38 Laying 2" (50 mm) thick sand and bitumen carpet, on top 100Sft. 682.50 4,316.25 sq.m 73.45 464.45 of foundation of oil tank.

39 Cutting hole 4"x6" (100x150 mm) in stone masonry or Per 120.70 - Per 120.70 - Same rate to be paid for other typebrick wall with chisel, repairing masonry and removing Hole Hole of masonry and R.C.C. work.debris within one chain lead.

40 Making 1½"x1½" (40x40 mm) groove in wall of stone or Per 105.60 - Per 105.60 - brick masonry in cement for fixing planks upto 9" (225 Plank Plankmm) deep.

41 Drilling holes in stone or brick masonry upto 2" (50 mm) Per hole 29.05 Per hole 11.60 dia, per inch (25 mm) depth. per inch per c.m

depth depth

42 Spraying anti-termite liquid mixed with water in the ratio of 100Sft. of 42.25 173.00 sq.m of 4.55 18.60 1:40. each each

spray spray

43 Providing and fixing barbed wire fencing, with 4 horizontaland two cross wires, with R.C.C. 1:2:4 posts, 5.5'x6"x9"(1.68mx150mmx225 mm) at 8 ft. (2.45 m) centre tocentre, reinforced with 4 No. 3/8" (10 mm) dia vertical barsand 1/8" (3 mm) dia stirrups 12" (300 mm) centre tocentre, complete in all respects.

i) without cement concrete base. 100Rft. 3,612.80 15,846.05 Per Metre 118.50 519.75 ii) in cement concrete 1:4:8 base of size 12"x12"x21" 100Rft. 3,958.15 17,080.70 Per Metre 129.85 560.25

(300x300x525 mm).