PG. 1 Page | 2.3-1 Appendix 2.7 UPC Response on GF Pre-concept Review Submission ISDM Model output Capabilities Sustainability Design Guidelines o Construction Air Quality Management o Construction and Demolition Waste Management o Erosion and Sedimentation Control Plan o Minimum Energy Performance Preliminary Estidama Scorecards (Follow up tasks identified) Estidama Registration Form Response to GF Comments on Draft Report

Upload: brunogiacomelli

Post on 30-Oct-2014

38 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: 2.7 I Sustainability

PG. 1 Page | 2.3-1

Appendix 2.7

• UPC Response on GF Pre-concept

Review Submission

• ISDM Model output Capabilities

• Sustainability Design Guidelines

o Construction Air Quality Management

o Construction and Demolition Waste

Management

o Erosion and Sedimentation Control

Plan

o Minimum Energy Performance

• Preliminary Estidama Scorecards

(Follow up tasks identified)

• Estidama Registration Form

• Response to GF Comments on Draft

Report

Page 2: 2.7 I Sustainability

PG. 1 Page | 2.3-1

UPC Response on GF Pre-concept Review Submission

Page 3: 2.7 I Sustainability

1

Project Details Building or Project Name: Global Foundries

From: Edwin Young

To: Name/ email Terri Va

cc. Name/ email

cc. Name/ email Heidi Brothers

cc. Name/ email Adi Afaneh

Note/ Comment In relation to the recent submission from the design team, we comment as followed in relation to the Estidama section of the documentation

1. In the meeting there was sufficient intent process of sustainable design and construction was being offered and followed

2. We confirm that the Ratings will require to be 2 Pearl as the project is Government led

3. Within the Concept Application th

documentation Planning for Estidama

4. We confirm that it is acceptable to rate the office building separate from the Fab facility, but the energy centre will be include with

5. We recommend that passive measures for peak cooling reduction be focused on before the use

of renewable technologies, but we support the use of solar thermal for hot water generation.

6. We will require a statement of intent in relation within all future applications

7. We would welcome ongoing participation with Global Foundriesduring the concept stage of the design to ensure synergy with the PRS program

------------------- End of Note ------------------------------------------------

Estidama File Note

File Note ID Number: EY

Estidama Project ID Number: Global Foundries- Pre-Concept Comments

Date: 29th

Global Foundries - Pre-Concept Submission

Edwin Young [email protected]

Valiant

Heidi Brothers

Adi Afaneh

In relation to the recent submission from the design team, we comment as followed in relation to the Estidama section of the documentation

In the meeting there was sufficient intent shown by the design team and the client to confirm the process of sustainable design and construction was being offered and followed

We confirm that the Ratings will require to be 2 Pearl as the project is Government led

Within the Concept Application the design team should follow the guidance within the UPC documentation Planning for Estidama (copy attached) communities

We confirm that it is acceptable to rate the office building separate from the Fab facility, but the energy centre will be include within that rating

We recommend that passive measures for peak cooling reduction be focused on before the use , but we support the use of solar thermal for hot water generation.

We will require a statement of intent in relation to site wide construction wastewithin all future applications

ongoing participation with Global Foundries and its design team particularly during the concept stage of the design to ensure synergy with the PRS program

------------------------------------------------

Estidama File Note

File Note ID Number: EY-FN-001

roject ID Number: Global Concept Comments

th August 2010

[email protected]

In relation to the recent submission from the design team, we comment as followed in relation to the

shown by the design team and the client to confirm the

We confirm that the Ratings will require to be 2 Pearl as the project is Government led

e design team should follow the guidance within the UPC

We confirm that it is acceptable to rate the office building separate from the Fab facility, but the

We recommend that passive measures for peak cooling reduction be focused on before the use , but we support the use of solar thermal for hot water generation.

site wide construction waste management

and its design team particularly during the concept stage of the design to ensure synergy with the PRS program

Page 4: 2.7 I Sustainability

PG. 1 Page | 2.3-1

ISDM - Model output capabilities

Page 5: 2.7 I Sustainability

ISDM – Model Output Capabilities

ISDM MODEL

1. ISDM MODEL – SUMMARY DASHBOARD

The ISDM model results are presented in a dashboard arrangement demonstrating a high level

summary of conservation measures applied for both Administration Building and FAB.

Figure 1 – ISDM Model Summary

Page 6: 2.7 I Sustainability

ISDM – Model Output Capabilities

2. CONSERVATION SCENARIOS SUMMARY: ADMINISTRATION BUILDING

The model has the capability to assess up to 5 scenarios compared against the ‘Business as

Usual’ (BAU) case. The Figure below is indicative of the reduction targets that can be applied on

different model scenarios.

Figure 2 – Applied Reduction Factors

3. CONSERVATION MEASURES: ADMINSTRATIVE BUILDING

3.1. WATER

Water Conservation – Example

Various water conservation rates can be applied for each scenario to match Estidama credit

criteria for water reduction. The table below shows an example of reduction target of 15%

applied uniformly for all office water use types.

4

Customer Type Corporate

Officers R&D HR

Lease

Space Auditorium

Fitness

Center Cafeteria

Management

Retails (Warehouse) 15% 15% 15% 15% 15% 15% 15% 15%

Office (Admin) 15% 15% 15% 15% 15% 15% 15% 15%

Institute (Clean Office) 15% 15% 15% 15% 15% 15% 15% 15%

Service (Lab) 15% 15% 15% 15% 15% 15% 15% 15%

WATER USE REDUCTIONS3

SAVE END USE FIXTURES CLOSEApply Uniform

Reduction

Page 7: 2.7 I Sustainability

ISDM – Model Output Capabilities

Water Efficient Fixtures

The table below shows how the reduction target can be achieved by using water efficient

fixtures for various water use types.

3.2. SOLID WASTE

Operational Solid Waste Reduction – example

Various waste reduction rates can be applied for each scenario to match Estidama credit

criteria. The table below shows an example of a reduction target of 15% applied uniformly for all

types of waste generated in the Administration Building.

3.3. ENERGY

Energy Load Reduction - example

Similarly to the water and waste conservation measures, various scenarios can be developed in

line with the Estidama credit requirements. The table below shows an example of an energy

load reduction target of 15% applied.

4

Customer Type Corporate

Officers R&D HR

Lease

Space Auditorium

Fitness

Center Cafeteria

Management

Engineering

& MTS

Maintenance

Technicians

WFTs Supplier

Facility

Customer

Facility

Contingency

Retails (Warehouse) 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15%

Office (Admin) 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15%

Institute (Clean Office) 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15%

Service (Lab) 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15% 15%

MUNICIPAL SOLID WASTE REDUCTIONCLOSE

S3

Apply Uniform

ReductionSAVE SWM MANAGEMENT

Page 8: 2.7 I Sustainability

ISDM – Model Output Capabilities

Page 9: 2.7 I Sustainability

ISDM – Model Output Capabilities

4. CONSERVATION MEASURES – FAB

The following tables are indicative of the various scenarios that can be used when considering

energy and water conservation measures for the FAB Building (2 scenarios are shown). Please

note that ‘1’ indicates measures considered and ‘0’ measures excluded for each scenario.

FAB Conservation Measures - Scenario 1

FAB Conservation Measures - Scenario 2

FAB CONSERVATION MEASURES2

Technology Implemented

Use air handler fan energy to reheat air 1

Dual Temperature Chilled Water Plant Energy Reduction 1

Energy Savings Resulting From reduction of filter coverage from 25 to 20% 1

Use of Premium Efficiency motors (MAU) 1

Use of Premium Efficiency motors (secondary chiller pumps) 1

Variable frequency drives to improve energy / operational efficiency (MAU) 1

Variable frequency drives to improve energy / operational efficiency (secondary chiller pumps) 1

Air side economizer – Energy recovery from general exhaust to pre-cool air intake 1

Power Factor Improvement - include capacitors to improve to 0.95PF 1

Higher thickness of roof insulation for improved thermal resistance 1

Triple glazing 1

Desalination water sourced off site (Additional Cost) 0

Wastewater reclamation (Cooling Towers) 1

MAU Condensate Recover for reuse 1

S1 SAVE CLOSE

FAB CONSERVATION MEASURES3

Technology Implemented

Use air handler fan energy to reheat air 1

Dual Temperature Chilled Water Plant Energy Reduction 1

Energy Savings Resulting From reduction of filter coverage from 25 to 20% 1

Use of Premium Efficiency motors (MAU) 0

Use of Premium Efficiency motors (secondary chiller pumps) 0

Variable frequency drives to improve energy / operational efficiency (MAU) 1

Variable frequency drives to improve energy / operational efficiency (secondary chiller pumps) 1

Air side economizer – Energy recovery from general exhaust to pre-cool air intake 1

Power Factor Improvement - include capacitors to improve to 0.95PF 0

Higher thickness of roof insulation for improved thermal resistance 1

Triple glazing 1

Desalination water sourced off site (Additional Cost) 0

Wastewater reclamation (Cooling Towers) 1

MAU Condensate Recover for reuse 1

S2 SAVE CLOSE

Page 10: 2.7 I Sustainability

PG. 1 Page | 2.3-1

Sustainability Design Guidelines

Page 11: 2.7 I Sustainability

GLOBALFOUNDRIES Construction and Demolition Waste Management – Design Guidelines

1

Construction and Demolition Waste Management

Page 12: 2.7 I Sustainability

GLOBALFOUNDRIES Construction and Demolition Waste Management – Design Guidelines

2

1. SECTION OVERVIEW

This section includes the waste management, disposal and all relevant documentation requirements and procedures to be implemented during construction.

2. DEFINITIONS

Waste – Any substance or object the holder discards, intends to discard or is required to dispose of.

Land-Clearing Debris - Waste materials resulting from land-clearing that include pre-existing development materials and plant matter, but do not include soil.

Reused Waste - Waste materials that are reused at the construction site or sent to a location off-site (e.g. another construction project or product supplier) where they are used in their original form (i.e. without additional processing).

Recycled Waste - Waste materials that are sent off-site to a recycling facility where they are used to displace virgin materials as resource for manufacturing processes that create new products.

Landfill Waste - Waste materials that are sent to a landfill site for disposal

Hazardous Waste - comprise of residues or ash of different activities and operations containing properties of hazardous substances

Centre of Waste Management of Abu Dhabi (CWM) - Agency responsible for controlling and coordinating waste management activities throughout the Emirate. The Centre issues licenses License: Waste Transportation Vehicles and Companies, Temporary Waste Collection and Transportation Permits, Hazardous Waste Transportation Permit, Waste Handling Company Permit, Waste Charges for Trade Licenses of Industrial and Commercial Companies

Waste Service Provider - Companies holding licenses from Abu Dhabi Waste Management Centre for carrying and disposing waste in approved facilities. Registered Providers are posted on CWM website (http://www.cwm.ae/) and updated regularly.

3. REFERENCES

This Document should be revised to incorporate inputs from HSEIA or similar EHS study required for Globalfoundries to obtain an EHS ‘Permit to Establish’ and ‘EHS Permit for Construction’ by the Environment Agency of Abu Dhabi (EAD) and the Higher Corporation for Specialized Economic Zones (ZonesCorp).

The following guidelines shall be followed:

� ESTIDAMA 2010, The Pearl Rating System for Estidama (Building Rating System) – Design and Construction, V.1.0

� Environment Agency of Abu Dhabi, Technical Guidance Document for Construction Environmental Management Plan (CEMP), April 2010

� ZonesCorp Waste Management Requirements

4. OBJECTIVES

A 70 % (weight/volume) waste diversion rate from landfill for construction and demolition waste should be targeted to achieve credits under Estidama Building Rating System. The targeted credits to be obtained under the Estidama are shown on the table below:

Page 13: 2.7 I Sustainability

GLOBALFOUNDRIES Construction and Demolition Waste Management – Design Guidelines

3

Diversion Rate Credit Targeted Total Points Targeted

70% (weight/volume) Estidama

� SM – R2: Basic Construction Waste Management

� SM-13 Credit: Improved

Construction Waste Management

Mandatory Credit + 2 Points (Optional Credit)

5. DESCRIPTION OF WORK

Identify, implement and document measures to achieve the waste management objectives listed above.

Follow a strategy based on the 3R’s hierarchy: Reduce the generation of waste materials at the project site, reuse waste materials at the construction site (when feasible) and Recycle waste materials as a resource for manufacturing new products. Waste Management and Disposal activities shall include but not be limited to:

� Preparing waste management documentation and submittals to summarize all transfers of waste materials from the project site

� Coordinating waste management tasks with subcontractors to ensure timely and orderly progress of the work

� Supervising on-site waste management activities on a daily basis

� Arranging waste segregation facilities within the project site boundaries and consider secondary waste segregation locations to encourage segregation at the source as practicable.

� Arranging waste management service agreements with waste service providers and waste receiving facilities

� Reporting waste management progress to the Consultant

6. ROLES AND RESPONSIBILITIES

6.1. DESIGN CONSULTANT

� Adopt design and procurement methods to minimise use of materials and waste

arisings as Best Practice

� Identify items to be recycled / salvaged and develop a log indicating activity/source

of the generated for each type of waste as well as estimated volume. Consider

materials such as concrete, brick, metal, wood, gypsum, plastic, cardboard etc.

� Identify potential Waste Service Providers to be appointed for each type of waste

and indicate location. Waste Service Providers must be licensed by the Abu Dhabi

Waste Management Center

Page 14: 2.7 I Sustainability

GLOBALFOUNDRIES Construction and Demolition Waste Management – Design Guidelines

4

� Establish targets for diversion from landfill in compliance with Estidama diversion

rate of 70% of total waste generated during construction (weight/volume) or more

(to achieve additional points).

� Develop a Construction and Demolition Waste Management Plan (CDWMP). The

Plan shall include targets estimated and shall incorporate local regulatory

requirements and relevant approved documentation by Regulatory Authorities. The

CDWMP shall be included in the Project Specifications for contractors compliance

� Prepare required documentation for Credit review under Estidama rating system

6.2. CONTRACTOR

� All Contractors are responsible for the appointment of a Waste Management

Contractor approved by Abu Dhabi Waste Management Center (WMC).

� Contractors shall prepare and maintain required documentation prior to

construction commencement and during construction progress.

� All Contractors shall implement the guidelines specified within this document

(Construction Waste Management Plan) to ensure compliance with

EAD/ZonesCorp requirements and to achieve required credits Estidama

certification

� Implementation of the Construction Waste Management Plan (CWMP) may involve

activities performed by Subcontractors and Suppliers. All Main Contractors,

Subcontractors and Suppliers shall be responsible for segregating construction

waste into recyclable components, non-recyclable waste and hazardous wastes.

� Site Supervisors are responsible for coordinating the implementation, and

enforcement of the CWMP, as well as to ensure that the workforce, through

adequate and continuous training, complies with prescribed protocols

� Staff personnel will implement and follow the requirements of the CWMP

� Contractors are responsible of tracking waste being generated, recycled and

disposed off site to through the submission of waste tracking reports as specified

by the client.

6.3. ENGINEER / CLIENT REPRESENTATIVE

� The Engineer / Client Representative will oversee Contractors’ compliance with

DCWMP requirements.

7. CO-ORDINATION MEETINGS

Coordination Meetings should be undertaken between the Design Consultant, the Contractor (subcontractors when required) and the Engineer / Client Representative to review and monitor Waste Management and Disposal requirements. The meeting shall include a review of the following at a minimum:

� Waste Management and Disposal objectives

� Waste Management and Disposal requirements and procedures

� Waste Management and Disposal documentation and submittals

Page 15: 2.7 I Sustainability

GLOBALFOUNDRIES Construction and Demolition Waste Management – Design Guidelines

5

8. SUBMITTALS

� Waste Description and Proposed Receiving Facilities (to include at a minimum)

� Waste Tracking Worksheet (Including receipts, invoices, letters and other documentation)

� Final Waste Diversion Report (Summary of Final results against target and receipts, invoices, letters and other documentation)

Page 16: 2.7 I Sustainability

GLOBALFOUNDRIES Construction Indoor Air Quality Management – Design Guidelines

1

Construction Indoor Air Quality Management

Page 17: 2.7 I Sustainability

GLOBALFOUNDRIES Construction Indoor Air Quality Management – Design Guidelines

2

1. OVERVIEW

Overview of indoor air quality management (including product/material selection) requirements and procedures

2. DEFINITIONS

Pollutant Source – Sources of indoor air pollutants on the construction site. Any construction activity or material that produces odour and/or dust is considered a source of air pollutants (e.g. paints, coats, generators, compressors, cutting tools, vehicles etc.)

Volatile Organic Compounds (VOCs) - Organic chemicals that produce vapors readily at room temperature and normal atmospheric pressure (e.g. gasoline, solvents, etc.)

3. REFERENCES

� Sheet Metal and Air Conditioning Contractors’ National Association (SMACNA). IAQ Guidelines for Occupied Buildings Under Construction, 2007, 2nd Edition

� ASHRAE. ANSI/ASHRAE 52.2-1999: Method of Testing General Ventilation Air-Cleaning Devices for Removal Efficiency by Particle Size.

� BS EN 779 2002 Particulate Air filters for general ventilation – determination of the filtration performance

4. OBJECTIVES

� Meet requirements to achieve Estidama LBi-3: Construction Indoor Air Quality Management and LEED IEQ Credit 3.1 on Construction Indoor Air Quality Management Plan (Construction) and LEED IEQ Credit 3.2 Construction Indoor Air Quality Management Plan (Before Occupancy).

� Meet or exceed the recommended Design Approaches of the Sheet Metal and Air Conditioning Contractors National Association (SMACNA) IAQ Guidelines for Occupied Buildings under Construction, 2007, 2nd Edition

� Protect construction workers and future building occupants from indoor air quality problems resulting from construction activities and building materials.

� Reduce the production and circulation of pollutants during construction.

� Protect equipment and absorptive materials stored and installed on-site from moisture, dust and dirt accumulation during construction.

� Prepare the building for occupancy following construction and prior to occupancy.

5. DESCRIPTION OF WORK

Indoor air quality management activities shall include:

� Preparing indoor air quality management documentation and submittals as detailed herein

� Identifying source of pollution and control measures

� Identifying, implementing and documenting measures to achieve the indoor air quality management objectives

� Supervising on-site indoor air quality management activities on a daily basis

Page 18: 2.7 I Sustainability

GLOBALFOUNDRIES Construction Indoor Air Quality Management – Design Guidelines

3

� Coordinating indoor air quality management tasks with subcontractors to ensure timely and orderly progress of the work

� Conducting indoor air quality management inspections and making necessary repairs

� Maintaining an indoor air quality inspection log to document observations, deficiencies and corrective actions

� Reporting indoor air quality management progress to the Engineer / Client Representative

6. ROLES AND RESPONSIBILITIES

6.1. DESIGN CONSULTANT

� Develop an Indoor Air Quality Management (IAQ) Management Plan to address at a minimum: Source Control during construction, Building Flush Out and Resuming Normal Building Operation upon construction completion as per Estidama requirements

� Prepare IAQ Planning Checklists as per SMACNA IAQ Guidelines (Appendix C)

� Identify and evaluate proposed controls measures as per SMACNA IAQ Guidelines (Appendix C)

� Assess the duration of pre-occupancy flush-out per Estidama requirements

� Prepare documentation for Credit review under Estidama/LEED rating system

6.2. CONTRACTOR

� The Contractor will be responsible in developing and implementing a Construction IAQ Plan compliant with the requirements as stipulated herein.

� The Contractor should designate one person to be responsible for all aspects of Construction Indoor Air Quality coordination (during construction) related to indoor air quality management.

6.3. ENGINEER / CLIENT REPRESENTATIVE

7. THE ENGINEER / CLIENT REPRESENTATIVE WILL OVERSEE CONTRACTOR’S COMPLIANCE WITH THE CONSTRUCTION INDOOR AIR QUALITY PLAN COORDINATION MEETINGS

Coordination Meetings shall be held (Prior to mobilization on-site, the Contractor shall hold a kick-off meeting with the Engineer / Client Representative to review indoor air quality management requirements. This meeting shall include a review of:

� Indoor air quality management objectives

� Indoor air quality management requirements and procedures

� Indoor air quality management documentation and submittals

8. SUBMITTALS

� Detailed Construction Indoor Air Quality Management Plan

Page 19: 2.7 I Sustainability

GLOBALFOUNDRIES Construction Indoor Air Quality Management – Design Guidelines

4

� IAQ Planning Checklists

� Submit IAQ Planning Checklists and evaluations of proposed control measures as per Appendix C of SMACNA IAQ guidelines for occupied building under construction

� IAQ Inspection Checklists

� Develop the IAQ inspection Checklists as per Appendix C of Smacna IAQ Guidelines

� Complete the log on a weekly basis. The log shall commence when the building is enclosed and carry through to building turnover.

� Summary Report

Page 20: 2.7 I Sustainability

GLOBALFOUNDRIES Minimum Energy Performance – Energy Reduction Design Guidelines

1

Minimum Energy Performance – Energy Reduction

Page 21: 2.7 I Sustainability

GLOBALFOUNDRIES Minimum Energy Performance – Energy Reduction Design Guidelines

2

1. SECTION OVERVIEW

This section includes a guide to establish Building Minimum Energy Performance and assist the building design decision making assessing various options to achieve minimum level of energy efficiency.

2. REFERENCES

ASHRAE/IESNA 90.1 – 2007: Energy Standard for Building except Low-Rise Residential Buildings

3. OBJECTIVES

� To establish minimum level of energy efficiency for the building and systems and demonstrate a minimum of 12% performance improvement compared to baseline building performance to comply with RE-R1 Credit: Minimum Energy Performance (Estidama Rating System)

� Achieve reduction in the building energy consumption against the Baseline Building Performance during operation to achieve RE-1 Credit Improved Energy Performance (Estidama Rating System) To obtain additional credits the following energy reduction must be achieved:

Energy Reduction % Estidama Additional Points

12% None (Required Credit)

14% 1

16% 2

18% 3

20% 4

22% - 22.5% 5 (22.5%)

24 – 25 % 6 (25%)

27.5 – 28 % 7 (27.5%)

30 % 8

32 – 32.5% 9 (32.5%)

34 - 35 % 10 (35%)

40 % 11

44 – 45% 12 (45%)

50% 13

55% 14

60% 15

4. DESCRIPTION OF WORK

Page 22: 2.7 I Sustainability

GLOBALFOUNDRIES Minimum Energy Performance – Energy Reduction Design Guidelines

3

� Develop an Energy simulation model to calculate building energy consumption and identify the most cost effective energy efficiency measures. The model should comply with ANSI/ASHRAE/IESNA Standard, 2007.

� Ensure that the proposed design (Building envelop and systems) complies with baseline requirements as per the specified sections ASHRAE/IESNA 90.1 – 2007: Energy Standard for Building except Low-Rise Residential Buildings (Sections 5.4, 6.4, 7.4, 8.4, 9.4, 10.4)

� Compare energy efficiency measure and optimized performance against baseline energy performance

� Develop and submit Energy Model Template and calculations summarizing the model results as per Estidama Design and Construction Submission requirements

5. ROLES AND RESPONSIBILITIES

5.1. DESIGN CONSULTANT

� The Design Consultant is responsible for developing the building envelope and systems design to meet credit requirements

� Develop, in conjunction with the Modeling Consultant, a series of energy conservation measures to be considered for the simulation exercise

� Provide with all energy costs associated with the Energy Performance

� The Design Consultant shall manage the Energy Modeling process to comply with Estidama requirements and referenced standards in coordination with the modeling consultant

� The Design Consultant is responsible of ensuring that the required documentation is maintained and submitted as needed to achieve the required credits under the Estidama rating systems.

5.2. MODELING CONSULTANT

� Develop and run simulation model and maintain all required documentation for the purpose of the credit submissions

� The Modeling consultant in conjunction with the Design Consultant shall identify the most cost effective measures to be considered during the modeling exercise.

6. CO-ORDINATION

Coordination Meetings shall be held between the Design and the Modeling Consultant on a regular basis to establish modeling requirements, identify cost effective energy reduction measures, review model results, credit submission requirements etc.

7. SUBMITTALS

The following documentation will be developed and submitted as part of the credit submission as per Estidama requirements:

� Documentation of the all the measures considered that reduce process loads and energy load savings

� Energy Cost Calculations

Page 23: 2.7 I Sustainability

GLOBALFOUNDRIES Minimum Energy Performance – Energy Reduction Design Guidelines

4

� Energy Model Template, calculations and narrative summarizing the model results

8. METHODOLOGY

Methodology of the Energy Model Template should be compliant with Estidama Credit Calculation requirementsand ASHRAE/IESNA 90.1 – 2007

Page 24: 2.7 I Sustainability

GLOBALFOUNDRIES Erosion and Sedimentation Control – Design Guidelines

1

Erosion and Sedimentation Control (ESC)

As mentioned in Section 7.4 ESC measures reflect LEED credit requirements, whereas similar controls compliant with Estidama requirements are expected to be included in the Construction Environmental Management Plan (CEMP). It is understood that the CEMP will be prepared by the appointed Environmental Consultant on behalf of GF. This is expected to fulfill the Estidama Credit IDP – 3 (Construction Environmental Management Plan).

Page 25: 2.7 I Sustainability

GLOBALFOUNDRIES Erosion and Sedimentation Control – Design Guidelines

2

1. REFERENCES

� U.S. Environmental Protection Agency, Office of Water. “Chapter 3: Sediment and Erosion Control” and Chapter 4: Other Controls”. Document No. EPA 832-R-92-005 Storm Water Management for Construction Activities, 1992

� Environment Agency of Abu Dhabi, Technical Guidance Document for Construction Environmental Management Plan (CEMP), April 2010

2. OBJECTIVES

� Prevent the loss of soil from the construction site resulting from storm water runoff, wind erosion, and construction activities.

� Prevent the sedimentation of storm sewers and receiving waters.

� Prevent air pollution caused by dust and particulate matter.

� Meet or exceed the requirements of LEED-NC Version 3.0 Sustainable Sites Prerequisite 1 “Erosion & Sedimentation Control” which specifies compliance with 2003, EPA Construction General Permit (Provisions for Phase I and Phase II of the National Pollutant Discharge Elimination System Programme), or local erosion and sedimentation control standards and codes, whichever is more stringent.

3. DESCRIPTION OF WORK

Develop a detailed Erosion and sedimentation control plan to include activities such as:

� Identifying construction activities potentially causing dust generation, soil erosion and sedimentation as well as applicable mitigation measures

� Develop a Drawing showing erosion and sedimentation control measures as described in this Section

� Installing erosion and sedimentation control products

� Supervising on site erosion and sedimentation control activities on a daily basis

� Coordinating erosion and sedimentation control tasks with subcontractors to ensure timely and orderly progress of the work

� Conducting erosion and sedimentation control inspections and making necessary repairs

� Maintaining an erosion and sedimentation control inspection log to document observations, deficiencies and corrective actions

� Preparing erosion and sedimentation control documentation and submittals as detailed herein

� Reporting erosion and sedimentation control progress to the Consultant

4. ROLES AND RESPONSIBILITIES

Page 26: 2.7 I Sustainability

GLOBALFOUNDRIES Erosion and Sedimentation Control – Design Guidelines

3

4.1. DESIGN CONSULTANT

� Identify Construction Activities with potential soil erosion and sedimentation impacts

� Carry out an analysis of site limitations and constraints such as slope, surface water streams, soil erodability etc.

� Develop an Erosion and Sedimentation Control (ESC) Management Plan to prevent soil erosion and stormwater runoff during construction in compliance with LEED and local regulatory requirements

� Prepare required documentation for Credit review under Estidama/LEED rating system

4.2. CONTRACTOR

� Contractors will be responsible in developing and implementing a project specific ESC Management Plan in compliance with GF requirements

� Each contractor should designate one or more persons (depending on scale and risk of the construction activities) to be responsible for all aspects of LEED coordination (during construction) related to erosion and sedimentation control.

� Each Contractor shall design, document and implement the erosion and sedimentation control measures during construction to meet LEED requirements.

4.3. ENGINEER / CLIENT REPRESENTATIVE

� The Engineer / Client Representative will oversee Contractors’ compliance with the Erosion and Sedimentation Control requirements as stipulated herein

5. COORDINATION MEETINGS

Coordination meetings with the Design Consultant, the Contractor (in conjunction with the Engineer / Client Representative) and subcontractors when required to review erosion and sedimentation control requirements. This meeting shall include a review of:

� Erosion and sedimentation control objectives

� Erosion and sedimentation control requirements and procedures

� Erosion and sedimentation control documentation and submittals

6. SUBMITTALS

Page 27: 2.7 I Sustainability

GLOBALFOUNDRIES Erosion and Sedimentation Control – Design Guidelines

4

� Site Drawing with specifications that detail the specifications of the erosion/sedimentation controls to be followed (The drawing shall also show: project site, the nearest stormwater drain, areas of soil disturbance and areas that will not be disturbed, Materials or equipment storage areas, waste handling areas, stormwater discharge locations, areas where stabilization is likely to occur etc.)

� List of activities likely to generate soil erosion/sedimentation and/or soil/water pollution; List of the specific control measures to be applied with a Brief Description (Best Management Practices ‘BMPs’)

� Inspection and Photograph Checklist

� At the end of construction or prior to removal, whichever comes first Submit the completed checklist

Page 28: 2.7 I Sustainability

PG. 1 Page | 2.3-1

Preliminary Estidama Scorecards

Page 29: 2.7 I Sustainability

Pearl Building Rating System

Credit Section Credit Points Available (Yes)

Credit Points

(Maybe)

Credit Points

IDP - Integrated Development Process 13 10 3

Project Name GF NS - Natural Systems 12 2 0

Project ID Administration Building LB - Livable Buildings 36 21 11

Pearl Rating Stage PW - Precious Water 43 15 19

Date 1/10/2010 RE - Resourceful Energy 44 13 15

SM - Stewarding Materials 28 6 17

IP - Innovating Practice 3 2 1

Project Summary

Project Details

IP - Innovating Practice 3 2 1

Total 69 66

Total Credit Points Pearl Rating

Required credits only 1

60 2

85 3

115 4

140 5

Pearl Rating Levels

Design Pearl Rating 2

Construction Pearl Rating 1

Page 30: 2.7 I Sustainability

Pearl Building Rating System

Project Name GF

Project ID Administration Building

Pearl Rating Stage

Date 1/10/2010

Credit Points Summary

Yes Maybe NoMaster

Plan

Building

DesignConstr. Phase

IDP

IDP-R1 Integrated Development Strategy Required X

Integrated Development Implementation Strategy: to facilitate an effective transition

between project stages and project packages to ensure that the initial vision, objectives and

targets are carried through to completion. Identify Vision, set objectives, targets and KPIs,

Team Chart and Roles etc.)

GF Industry Requirement Report provided by GF

IDP-R2 Tenant Fit-Out Design & Construction Guide Required X X Tenant Fit-Out Design & Construction Guide in order to formally communicate to future

tenants and their design requirements

Not applicable for GF. Requires Clarification

with Estidama

IDP-R3 Basic Commissioning Required X X

Demonstrate that: An independent commissioning agent, reporting to the project owner, is

engaged as part of the project design team throughout the design stages; Commissioning Plan

and Comprehensive commissioning requirements in project specifications and, At the building

completion stage the building has been commissioned by independent commissioning

engineers; The commissioning report has been reviewed and verified prior to building

completion.

Appoint a Commissioning Agent reporting to GF

(Design Stage) / Incorporate commissioning

requirements at building completion stage.

IDP-1 Life Cycle Costing 4 4 X X Use Life Cycle Cost analysis during design

GF to consider appointing a qualified

professional to conduct LCC analysis and update

it through future project stages. CH2M HILL to

include this requirements in RFP

documentation. The LCC proffessional can still

be independent of CH2M and report directly to

GF.

IDP-2 Guest Worker Accommodation 2 2 X X Develop a Guest Worker Accommodation Plan. To be inlcluded in Design Documents

Description Remarks

Integrated Development Process

Yes

Yes

Yes

Project Details

Credit Reference Credit TitleCredit Points

Available

Attainable Design Project Phase

IDP-2 Guest Worker Accommodation 2 2 X X Develop a Guest Worker Accommodation Plan. To be inlcluded in Design Documents

IDP-3 Construction Environmental Management 2 1 1 X X( 1 ) - Develop the CEMP in accordance with Abu Dhabi Environment Agency’s regulations. ( 1

) - Project Lead Contractor is ISO 14001 or EHSMS Certified.Input from Environmental Consultant

IDP-4 Building Envelope Verification 1 1 XDemonstrate that the building envelope meets the design intent and minimizes building

impacts from condensation, water ingress, air infiltration and improper drainage.

Difficult to verify on site (ASHRAE

Guidelines2005, NIBS GL3, BSRIA)

IDP-5 Re-Commissioning 2 2 XDemonstrate that the building performs as designed to protect occupant health and comfort,

as well as providing for ongoing building efficiency.To be determined

IDP-6 Sustainability Awareness 2 2 X( 1 ) - Develop an Occupant Handbook. ( 1 ) - Design an occupant feedback mechanism to give

information on how they impact building performance.To be included in Design requirement

TOTAL 13 10 3 0

NS

NS-R1 Natural Systems Assessment Required XEstablish environmental baseline conditions on site and surroundings to be considered and

assessed at the design stage

Input from ERM / Phase I Assessment and

detailed field surveys to be conducted by

environmental consultantNS-R2 Natural Systems Protection Required X

To protect significant and valuable Natural Systems assets identified in NS-R1 Natural Systems

Assessment.As above

NS-R3Natural Systems Design and Management

StrategyRequired X

To minimize demand for resources, promote soil protection and enhancement and ensure the

long term survival and management of landscaped/habitat areas.Incorporate in Landscape Design

NS-1 Reuse of Land 2 2 X ( 2 ) Demonstrate that at least 75% of the site area has been previously developed.

NS-2 Remediation of Contaminated Land 2 2 X( 2 ) Demonstrate the site is contaminated and an assessment report and remediation strategy

has been prepared.

NS-3 Ecological Enhancement 2 2 X

( 1 ) - 50% of plants to comprise of native and adaptive drought and / or saline tolerant

species including a minimum of 5 different types of species. ( 2 ) - 70% of plants to comprise

native and adaptive drought and / or saline tolerant species including a minimum of 10

different types of species.

Incorporate in Landscape Design

NS-4 Habitat Creation and Restoration 6 6 X

( 4 ) - Prepare a Habitat Creation or Restoration Strategy; and Allocate an on-site or off-site

habitat creation or restoration site of minimum areas as defined above. ( 2 ) - Demonstrate

that through collaboration, off-site ecological corridors have been designed to link similar

habitat types.

TOTAL 12 2 0 10

LBo

LBo-R1 Plan 2030 Required X

Demonstrate that the proposed development is located within an Urban Growth Boundary as

identified by UPC’s adopted Framework Plans. Demonstrate that the proposed development’s

Floor Area Ratio (FAR), dwelling units per hectare (du/ha), building height, building mass,

transportation and open space networks are consistent with the applicable Plan 2030 and/or

Development Code and/or Area Plan.

Obtain Letter from UPC

Required

Demonstrate that, before the start of the design process and site clearance, an urban systems

assessment has been carried out for the project site and at the following scales: Local, Sub-Yes

Natural Systems

Yes

Yes

Yes

Livable Building : Outdoors

Yes

LBo-R2 Urban Systems Assessment Required Xassessment has been carried out for the project site and at the following scales: Local, Sub-

regional, and Regional scale. Identify opportunities and constraints associated with the

development and compile an Urban Systems Assessment Report.

LBo-R3 Outdoor Thermal Comfort Strategy Required X

Shade measures (cover or shade) must be provided in all applicable spaces and achieve a

minimum percent shading. Shade measures include: Exterior Surface Parking with more than

10 spaces (including parking on roof surfaces) 40%, Public Open Spaces (including privately

owned) 60%, Primary Pedestrian Walkways (based on 1.8m width within the through zone)

75%, Secondary Pedestrian Walkways (based on 1.8m width within the through zone) 75%,

Cycle Tracks 50%, Playgrounds 90%

Follow up with Planning Team

LBo-1 Improved Outdoor Thermal Comfort 2 2 x X

Demonstrate that the outdoor thermal comfort strategy has been improved beyond the

minimum established under credit LBo-R3 Outdoor Thermal Comfort Strategy by increasing

the shade measures. (1)50 % (2)55 % - Surface car parking, including parking on roof surfaces

(1)65 % (2)70 % - Public Open Space, including privately owned (1)80 % (2)85 % - Primary

Pedestrian Walkway, based on 1.8m width within the through zone (1)80 % (2)85 % - Secondary

Pedestrian Walkway, based on 1.8m width within the through zone (1)55 % (2)65 % - Cycle

tracks

Follow up with Planning Team

LBo-2 Pearl Rated Communities 1 1 X Demonstrate that the building is located within a Pearl Rated community.

LBo-3 Accessible Community Facilities 1 1 XDemonstrate that the building is located within 350m safe walking distance of any of the five

listed amenities.

LBo-4 Active Urban Environments 1 1 X

Demonstrate that outdoor spaces have been provided and programmed to encourage activity,

including sport and recreation. Develop and implement an Active Urban Environment

Program.

LBo-5 Private Outdoor Space 1 XResidential Only: Provide 90% of units with outdoor amenity space as per the Credit

RequirementsNot Applicable

LBo-6 Public Transport 3 2 1 X

( 2 ) - Demonstrate that the building is within 350m of a tram and/or bus stop with a 15

minute frequency. ( 3 ) - Demonstrate that the building is also within 350m of a metro or

regional rail station.

Confirm with UPC on plans for tram line (North

to GF site)

LBo-7 Bicycle Facilities 2 2 X( 1 ) Meet the Credit Requirements for bicycle parking facilities. ( 1 ) Meet the Additional

Credit Requirements for shower, locker and changing facilities and/or cycle lanes.Confirm with GF on bicycle paths on site

LBo-8 Preferred Car Parking Spaces 1 1 X

6% of parking spaces provided must be identified for the sole use of priority vehicles. The

spaces must be optimally located for building access and half of the spaces must be supplied

with vehicle charging points.

Follow up with Planning Team

LBo-9 Travel Plan 1 1 X

Demonstrate the development of a Travel Plan. The Travel Plan must include: details of the

type of measures proposed to manage the demand for travel by car; targets for reducing car

travel; means of monitoring the effectiveness of the Plan; and remedial measures that will be

implemented in the event that the stated targets are not delivered.

Confirm with GF

LBo-10 Light Pollution Reduction 1 1 X Demonstrate light pollution reduction in compliance with the Credit Requirements Confirm with Technology Lead

14 5 5 3

Yes

Yes

TOTAL

LBi

LBi-R1 Healthy Ventilation Delivery Required X XProtect the quality of air drawn into buildings for ventilation and to ensure minimum delivery

of outdoor fresh air; Develop an Observational Survey of Local Air Quality

Input from Environmental Consultant (Baseline

Air Quality Assessment)

LBi-R2 Smoking Control Required X XDemonstrate appropriate measures are incorporated into the building design to reduce

exposure to tobacco smokeIncorporate in design requirements

LBi-R3 Legionella Prevention Required X X Manage the risk of Legionella in water based building systems. Incorporate in design requirements

LBi-1 Ventilation Quality 3 2 1 X

( 1 ) - CO2 sensors at all return points. ( 1 ) - Demonstrate an increase in

outdoor air ventilation of 15% above the outdoor air ventilation rates. ( 1 ) - Mixed Mode

Operation (not available to retail use type)

Confirm with Technology Lead

LBi-2.1 Material Emissions : Adhesives & Sealants 1 1 X 95% of all adhesives & sealants meet criteria. Confirm with GF on material selection

LBi-2.2 Material Emissions : Paints & Coatings 1 1 X 95% of all surface areas meet criteria Confirm with GF on material selection

LBi-2.3 Material Emissions : Carpet & Hard Flooring 1 1 X 100% of all carpets, carpet cushion, hard flooring and associated finishes comply Confirm with GF on material selection

LBi-2.4 Material Emissions : Ceiling Systems 1 1 X All ceiling systems meet credit criteria Confirm with GF on material selection

LBi-2.5 Material Emissions : Formaldehyde Reduction 2 2 X( 1 ) - All internal construction materials meet formaldehyde class E1 levels. ( 1 ) All internal

construction and furniture meets formaldehyde class E1 levels.Confirm with GF on material selection

LBi-3 Construction Indoor Air Quality Management 2 2 X Develop a construction IAQ plan Include in the specifications

LBi-4 Car Park Air Quality Management 1 1 X

For enclosed cark park. Ensure car parking ventilation design meets the credit requirements.

Where project does not contain any enclosed car parks (75% enclosed) the credit is

automatically awarded

Confirm with Planning Team

LBi-5.1 Thermal Comfort & Controls : Thermal Zoning 1 1 X Compliant thermal zoning strategy and controlsIncorporate in design requirements / Model to

determine cooling demand

LBi-5.2Thermal Comfort & Controls : Occupant

Control2 2 X

( 1 ) - General: 1 control per 2 occupants, General (Mixed Mode) : 50% occupied area, Multi-

Occupant Spaces (Office, Residential, Schools): 1 control per space (more if movable

partitions present). ( 1 ) - General: 1 control per 2 occupants & modulating HVAC systems in

multi-occupant spaces, General (Mixed Mode): 75% of occupied area, Multi-Occupant Spaces

(Office, Residential, Schools): 1 control per space (more if movable partitions present)

Confirm with Technology Lead

LBi-5.3Thermal Comfort & Controls : Thermal

Comfort Modeling2 2 X

( 1 ) - Category C Performance: PMV levels between -0.7 and +0.7 (15% PPD) & 90%

acceptability limits for Mixed Mode (if applicable). ( 1 ) - Category B Performance: PMV levels

between -0.5 and +0.5 (10% PPD) & 90% acceptability limits for Mixed Mode (if applicable).

PMV - Predicted Mean Vote, PDD - Predicted Percentage Dissatisfied

Confirm with Technology Lead

LBi-6 High Frequency Lighting 1 1 XGeneral: All high frequency fluorescent ballasts and occupancy sensors meeting credit

requirements.Incorporate in design requirements

Yes

Livable Building : Indoors

Yes

Yes

Page 31: 2.7 I Sustainability

Pearl Building Rating System

Project Name GF

Project ID Administration Building

Pearl Rating Stage

Date 1/10/2010

Credit Points Summary

Yes Maybe NoMaster

Plan

Building

DesignConstr. Phase

Description Remarks

Project Details

Credit Reference Credit TitleCredit Points

Available

Attainable Design Project Phase

LBi-7 Daylight & Glare 2 2 X

( 1 ) - General : min 250 Lux for 50% of occupied area. Meet requirements for occupancy

sensors relevant to space type. Meet requirements for glare control relevant to space type. (

1 ) - General : min 250 Lux for 75% of occupied area. Meet requirements for occupancy

sensors relevant to space type. Meet requirements for glare control relevant to space type.

Allow Occupancy Sensor. Daylight Design

Software - Include in the design

LBi-8 Views 1 1 X General: 75% of occupied areas have views through vision glazing. Confirm with Architect

LBi-9 Indoor Noise Pollution 1 1 X Demonstrate that internal ambient noise levels do not exceed 50 dB(A) Leq in the area to be

occupied.Confirm with Architect

LBi-10 Safe & Secure Environment 1 1 X Develop & Implement Safety & Security Plan

Incorporate Estidama Requirements to Overall

Security Plan (In line with UPC Security

requirements where applicable)

23 16 6 1

PW

PW-R1 Minimum Interior Water Use Reduction Required x XDemonstrate that the project’s predicted interior potable water consumption will be no

greater than the baseline building water consumption using efficiency measures only.

Use UPC Water Calculator / Input from

Technology Lead

PW-R2 Exterior Water Monitoring Required x X

Demonstrate that easily accessible and clearly labelled water meters are provided and

capable of monitoring the water consumption of, at a minimum, the following exterior water

uses (where present): Heat rejection; External hose bibs; Irrigation systems; Swimming pools;

and Water features.

Incorporate at the design stage

TOTAL

Precious Water

Yes

Yes

and Water features.

PW-1 Improved Interior Water Use Reduction 15 5 5 5 X

Demonstrate using the Building Water Calculator that the proposed building has achieved the

following reduction in potable water consumption compared to the baseline building: ( 1 ) 4%

( 2 ) 8% ( 3 ) 12% ( 4 ) 16% ( 5 ) 20% ( 6 ) 24% ( 7 ) 28% ( 8 ) 32% ( 9 ) 36% ( 10 ) 40% ( 11 )

44% ( 12 ) 48% ( 13 ) 52% ( 14 ) 56% ( 15 ) 60%

Confirm with Technology Lead

PW-2.1 Exterior Water Use Reduction: Landscaping 8 2 4 2 X

( 2-4 ) Demonstrate that the average irrigation requirement for all landscaped areas has been

minimized. ( 1 ) Demonstrate that a water efficient irrigation system has been incorporated

into the landscape design. ( 1 ) Demonstrate that best practices for ongoing system

management and operation have been established. ( 2 ) Demonstrate that 100% of the

exterior irrigation demand can be served using the Exterior Water Allowance, and that a

recycled water mainline loop has been installed where Pearl Building Rating System: Design &

Construction, Version 1.0, April 2010 124 of 223 recycled water is not immediately available.

Confirm with Technology Lead

PW-2.2 Exterior Water Use Reduction: Heat Rejection 8 6 2 X

( 2-5 ) Demonstrate that a percentage of the projects cooling tower/district cooling water

make-up requirements can be served using the Exterior Water Allowance. ( 8 ) Demonstrate

that no water is required for heat rejection.

Confirm with Technology Lead

PW-2.3 Exterior Water Use Reduction: Water Features 4 2 2 X

( 2 ) Demonstrate that the water make-up requirements for all exterior water features can be

served using the Exterior Water Allowance. ( 1 ) Demonstrate that all external swimming

pools are provided with adequate pool blankets. ( 4 ) Demonstrate that there are no exterior

water features or swimming pools.

Confirm with Technology Lead

PW-3 Water Monitoring & Leak Detection 4 4 X

( 2 ) Demonstrate that metering facilities that monitor the water consumption of major

individual interior uses are installed. ( 2 ) Demonstrate that a leak detection system has been

installed.

Include requirements for Leak Detection into

Design requirements

PW-4 Stormwater Management 4 2 2 X

( 1-2 ) Stormwater management system is designed to meet Quantity Control criteria as per

Credit Requirements. ( 1 ) Stormwater management system is designed to meet Quality

Control criteria as per Credit Requirements. ( 1 ) An Operation & Maintenance Plan has been

developed.

Confirm with Technology Lead

TOTAL 43 15 19 9

RE

RE-R1 Minimum Energy Performance Required x X

Develop an energy model for the proposed building(s) using appropriate dynamic simulation

modeling software and calculate the baseline building energy consumption according to the

building performance rating method outlined in Appendix G of ANSI/ASHRAE/IESNA Standard

90.1-2007, using the minimum acceptable standards for building fabric, HVAC, service water

heating, power, lighting and other equipment. Demonstrate a minimum 12% performance

improvement compared to the baseline building performance demonstrated by the energy

simulation model as per the methodology outlined within Appendix G of Standard 90.1-2007.

Include Energy Model in design requirements

RE-R2 Energy Monitoring and Reporting Required x X

Demonstrate that easily accessible and clearly labelled energy sub-meters are provided which

enable a minimum of 90% of the estimated annual energy consumption of each fuel type

(electricity, gas etc) to be monitored as outlined within the Calculations and Methodologies Include in specifications

Yes

Yes

Resourceful Energy

RE-R2 Energy Monitoring and Reporting Required x X(electricity, gas etc) to be monitored as outlined within the Calculations and Methodologies

section.

Include in specifications

RE-R3Ozone Impacts of Refrigerants & Fire

Suppression SystemsRequired x X

Refrigerants - Demonstrate that all refrigerants to be installed within the project site

boundary have an ozone depletion potential (ODP) of zero. Fire Suppression Systems -

Demonstrate that all gaseous fire suppression systems to be installed within the project site

boundary have an ozone depletion potential (ODP) of zero

Include in specifications

RE-1 Improved Energy Performance 15 5 5 5 X

Demonstrate further percentage reductions in the proposed building energy consumption

beyond the baseline building consumption determined in RE-R1. Points are awarded as

follows: ( 1 ) 14% ( 2 ) 16% ( 3 ) 18% ( 4 ) 20% ( 5 ) 22.5% ( 6 ) 25% ( 7 ) 27.5% ( 8 ) 30% ( 9 )

32.5% ( 10 ) 35% ( 11 ) 40% ( 12 ) 45% ( 13 ) 50% ( 14 ) 55% ( 15 ) 60%

The points indicated are based on assumptions

and excpected to be revised once Energy

Simulaition baseline and options are developed

RE-2 Cool Building Strategies 6 3 1 1 X

( 1-5 ) Demonstrate percentage reductions in annual external heat gain attributed to passive

design measures. ( 1 ) 10% ( 2 ) 20% ( 3 ) 30% ( 4 ) 40% ( 5 ) 50% ( 1 ) Demonstrate that

roofing materials with a high Solar Reflectance Index will be used.

Confirm with Technology Lead

RE-3 Energy Efficient Appliances 3 3 X

Demonstrate that all developer purchased and/or leased installed appliances shall be energy

efficient, and that tenant guidelines outlining the benefits of energy efficient appliances will

be produced.

RE-4 Vertical Transportation 3 2 1 X

( 1 ) Demonstrate that easily accessible stairs shall be provided to at least the first three

floors of the building. ( 1 ) Demonstrate that all lifts within the building shall be energy

efficient. ( 1 ) Demonstrate that all escalators within the building shall be energy efficient.

RE-5 Peak Load Reduction 4 4 X

( 2 ) Demonstrate peak electrical load shall be less than 80% above annual average electrical

load. ( 4 ) Demonstrate peak electrical load shall be less than 60% above annual average

electrical load.

Confirm with Technology Lead

RE-6 Renewable Energy 9 3 6 X

Demonstrate that a percentage of the total energy consumption will be supplied by onsite

renewable energy. ( 1 ) 1% ( 2 ) 3% ( 3 ) 5% ( 4 ) 7% ( 5 ) 10% ( 6 ) 13% ( 7 ) 16% ( 8 ) 20% -

( 1 ) Demonstrate that 20% of the project’s non-renewable energy use will be supplied by

offsite renewable energy.

1% Cost of PV to be determined

RE-7Global Warming Impacts of Refrigerants & Fire

Suppression Systems4 2 2 X

( 1 ) Demonstrate that the weighted average of all refrigerants shall have a GWP of 10 or less.

( 1 ) Demonstrate that a permanent refrigerant leak detection system shall be installed. ( 1 )

Demonstrate that an automatic refrigerant pump down system shall be installed. ( 1 )

Demonstrate that 100% of gaseous fire systems shall have a GWP of 1 or less.

Confirm with Technology Lead

TOTAL 44 13 15 15

SM

SM-R1 Hazardous Waste EliminationRequired X X

To eliminate exposure of building occupants to asbestos and minimize toxic effects of

chromated copper arsenate (CCA) treated timber on people and the environment.Include in materials specifications

SM-R2 Basic Construction Waste Management

Required X X

Reduce the long-term environmental impacts associated with construction waste collection,

transport and disposal; Minimum final recycling/salvage rate of 30% of construction and

demolition waste (weight/volume) - excluding hazardous

Incorporate Requirements into Construction

Waste Management Plan prepared by

Environmental Consultant

Yes

Yes

Stewarding Materials

Yes

Yes

SM-R2 Basic Construction Waste Management demolition waste (weight/volume) - excluding hazardous Environmental Consultant

SM-R3 Basic Operational Waste Management

Required X X

Reduce the long-term environmental impacts associated with operational waste collection,

transport and disposal; Proposed option: 40% minimum target of diversion rate

(weight/volume) & Waste segregation in 4 types and waste containers location requirements

Incorporate Requirements into Operational

Waste Management Plan prepared by

Environmental Consultant

SM-1 Non-Polluting Materials

3 2 1 X

( 1 ) Building meets the ‘Zero Ozone Depleting Potential, Low Global Warming Potential

Insulation’ Credit Requirements through design. ( 1 ) Building meets the ‘Chlorine Free

Materials’ Credit Requirements through design. ( 1 ) Building meets the ‘Low Toxicity

Materials’ Credit Requirements through design.

Confirm with Technology Lead

SM-2 Design for Material Reduction1 1 X

General: Building is designed with at least one material reduction initiative. Offices only: At

least two initiatives are required.Confirm with Technology Lead

SM-3 Design for Flexibility & Adaptability

1 1 X

Demonstrate the following: 90% of the building has regular rhythm to exposed facades (by

area); Floor-to-floor heights of at least 3.6 meters; 90% of the windows are evenly distributed

around exposed elevations (by area); 90% of interior, non-structural walls are demountable or

movable (by area); and 90% of pipes, wiring and conduits are not permanently embedded in

building materials (in length).

SM-4 Design for Disassembly

1 1 X

Develop a Building Disassembly Plan highlighting the following: materials intended for

recovery; materials connection requirements; system for marking and identifying recoverable

elements prior to installation; best management practices for disassembly; and the

disassembly sequence. Demonstrate that 50% of the building structural skeleton, 75% of

façade, or 90% of the roof is designed for disassembly (by surface area).

SM-5 Modular Flooring Systems 1 1 X At least 95% (by surface area) of finished floor areas are specified with modular flooring

products.SM-6 Design for Durability 1 1 X Develop a Building Durability Plan.

SM-7 Building Reuse2 2 X

( 1 ) At least 25% of the building structural system, by surface area, will be reused. ( 2 ) At

least 50% of the building structural system, by surface area, will be reused.

SM-8 Material Reuse 1 1 X The cost of specified reused materials equal to at least 3% of the Total Material Cost.

SM-9 Regional Materials2 1 1 X

( 1 ) Cost of regional materials specified equal to 10% of Total Material Cost. ( 2 ) Cost of

regional materials specified equal to 20% of Total Material Cost.Further Research on materials availability

SM-10 Recycled Materials

6 1 5 X

( 1 ) Steel-framed: at least 50% of specified structural steel (by weight) has 25% post-

consumer recycled content or is reused Concrete-framed: at least 80% of specified rebar or

stressing steel has 90% post-consumer recycled content. ( 1 ) Specified concrete mix and

reduction in cement use will achieve an embodied GHG of concrete as per table SM10.1, rows

B1, C1 and D1. ( 2 ) Specified concrete mix and reduction in cement use will achieve an

embodied GHG of concrete as per table SM10.1, rows B2, C2 and D2. ( 1 ) At least 15% of all

specified aggregates to be used for structural or non-structural applications are recycled. ( 2 )

Only recycled aggregate is specified for use as base, sub-base or backfill. ( 1 ) Cost of

specified recycled materials equal to at least 10% of Total Material Costs.

Further Research on materials availability

Yes

Page 32: 2.7 I Sustainability

Pearl Building Rating System

Project Name GF

Project ID Administration Building

Pearl Rating Stage

Date 1/10/2010

Credit Points Summary

Yes Maybe NoMaster

Plan

Building

DesignConstr. Phase

Description Remarks

Project Details

Credit Reference Credit TitleCredit Points

Available

Attainable Design Project Phase

SM-11 Rapidly Renewable Materials

1 1 X

at least 75% (by area) of one or more specified building components are rapidly renewable; at

least 35% (by area) of two or more specified building components are rapidly renewable; or at

least 15% (by area) of four or more specified building components are rapidly renewable.

SM-12 Reused or Certified Timber2 1 1 X

( 1 ) At least 50% (by cost) of the specified timber comply with the Credit Requirements. ( 2 )

At least 70% (by cost) of the specified timber comply with the Credit Requirements.

SM-13 Improved Construction Waste Management

2 1 1 X

( 1 ) Demonstrate CDWMP aims for a minimum of 50% demolition and construction waste (by

weight or volume) to be recycled / salvaged. ( 2 ) Demonstrate CDWMP aims for a minimum of

70% demolition and construction waste (by weight or volume) to be recycled / salvaged.

SM-14 Improved Operational Waste Management

2 1 1 X

( 1 ) General: An Operational Waste Management Plan (OWMP) is developed for a minimum

targeted diversion rate of 60% (by weight or volume. ( 2 ) General: An OWMP is developed for

a minimum targeted diversion rate of 80% (by weight or volume.

SM-15 Organic Waste Management2 2 X

( 1 ) Landscaping waste or food waste collection and/or treatment is proposed onsite. ( 2 )

Food and landscaping waste collection and/or treatment are proposed onsite.

TOTAL 28 6 17 5 0 0 0

IP

IP-1 Innovating Cultural & Regional Practices 1 1Develop a design strategy for incorporating solutions that showcase cultural and regional

practicesMix of Arabic and Islamic features

Develop, document and implement an innovative design and/or construction solution that Occupant Education: Display of Energy

Innovating Practice

IP-2 Innovating Practice 2 1 1

Develop, document and implement an innovative design and/or construction solution that

addresses one or more of the four pillars of Estidama. AND Develop a guideline document that

enables the innovative solution to be repeated.

Occupant Education: Display of Energy

consumption (each floor, kiosk)

TOTAL 3 2 1 0 0 0 0

TOTAL POINTS 180 69 66 43

1 PEARL ALL REQUIRED

2 PEARL 60-84 POINTS

3 PEARL 85 - 114 POINTS

4 PEARL 115 - 139 POINTS

5 PEARL 140 + POINTS

Page 33: 2.7 I Sustainability

Pearl Building Rating System

Credit Section Credit Points AvailableYes

Credit Points

Maybe

Credit Points

Project Name GF IDP - Integrated Development Process 10 3

Project ID FAB NS - Natural Systems 2 0

Pearl Rating Stage LB - Livable Buildings 19 6

Date Oct-10 PW - Precious Water 19 10

RE - Resourceful Energy 10 10

SM - Stewarding Materials 6 15

IP - Innovating Practice 2 1

Total 68 45

Project Details

Pearl Rating Levels Total 68 45

Total Credit Points Pearl Rating

Required credits only 1

60 2

85 3

115 4

140 5

Pearl Rating Levels

Design Pearl Rating 2

Page 34: 2.7 I Sustainability

Pearl Building Rating System

Project Name GF

Project ID FAB

Pearl Rating Stage

Date Oct-10

Credit Points Summary

Yes Maybe NoMaster

Plan

Building

Design

Constr.

Phase

IDP

IDP-R1 Integrated Development Strategy Required X

Integrated Development Implementation Strategy: to facilitate an effective transition

between project stages and project packages to ensure that the initial vision, objectives and

targets are carried through to completion. Identify Vision, set objectives, targets and KPIs,

Team Chart and Roles etc.)

Requires input from GF on Estidama vision,

targets and relative issues. Confirm Project

Boundaries

IDP-R2 Tenant Fit-Out Design & Construction Guide Required X X Tenant Fit-Out Design & Construction Guide in order to formally communicate to future

tenants and their design requirements

Not applicable for GF. Requires Clarification

with Estidama

IDP-R3 Basic Commissioning Required X X

Demonstrate that: An independent commissioning agent, reporting to the project owner, is

engaged as part of the project design team throughout the design stages; Commissioning Plan

and Comprehensive commissioning requirements in project specifications and, At the building

completion stage the building has been commissioned by independent commissioning

engineers; The commissioning report has been reviewed and verified prior to building

completion.

Appoint a Commissioning Agent reporting to GF

(Design Stage) / Incorporate commissioning

requirements at building completion stage.

IDP-1 Life Cycle Costing 4 4 X X Use Life Cycle Cost analysis during design

GF to consider appointing a qualified

professional to conduct LCC analysis and update

it through future project stages. CH2M HILL to

include this requirements in RFP

documentation.

IDP-2 Guest Worker Accommodation 2 2 X X Develop a Guest Worker Accommodation Plan. To be inlcluded in Design Documents

IDP-3 Construction Environmental Management 2 1 1 X X( 1 ) - Develop the CEMP in accordance with Abu Dhabi Environment Agency’s regulations. ( 1

) - Project Lead Contractor is ISO 14001 or EHSMS Certified.Input from Environmental Consultant

Project Details

Credit Reference Credit TitleCredit Points

Available

Attainable Design Project Phase

Description Remarks

Integrated Development Process

Yes

Yes

Yes

) - Project Lead Contractor is ISO 14001 or EHSMS Certified.

IDP-4 Building Envelope Verification 1 1 XDemonstrate that the building envelope meets the design intent and minimizes building

impacts from condensation, water ingress, air infiltration and improper drainage.Difficult to verify on site.

IDP-5 Re-Commissioning 2 2 XDemonstrate that the building performs as designed to protect occupant health and comfort,

as well as providing for ongoing building efficiency.To be determined

IDP-6 Sustainability Awareness 2 2 X( 1 ) - Develop an Occupant Handbook. ( 1 ) - Design an occupant feedback mechanism to give

information on how they impact building performance.To be included in Design requirement

TOTAL 13 10 3 0

NS

NS-R1 Natural Systems Assessment Required XEstablish environmental baseline conditions on site and surroundings to be considered and

assessed at the design stage

Input from ERM / Phase I Assessment and

detailed field surveys to be conducted by

environmental consultantNS-R2 Natural Systems Protection Required X

To protect significant and valuable Natural Systems assets identified in NS-R1 Natural Systems

Assessment.As above

NS-R3Natural Systems Design and Management

StrategyRequired X

To minimize demand for resources, promote soil protection and enhancement and ensure the

long term survival and management of landscaped/habitat areas.Incorporate in Landscape Design

NS-1 Reuse of Land 2 2 X ( 2 ) Demonstrate that at least 75% of the site area has been previously developed.

NS-2 Remediation of Contaminated Land 2 2 X( 2 ) Demonstrate the site is contaminated and an assessment report and remediation strategy

has been prepared.

NS-3 Ecological Enhancement 2 2 X

( 1 ) - 50% of plants to comprise of native and adaptive drought and / or saline tolerant

species including a minimum of 5 different types of species. ( 2 ) - 70% of plants to comprise

native and adaptive drought and / or saline tolerant species including a minimum of 10

different types of species.

Incorporate in Landscape Design

NS-4 Habitat Creation and Restoration 6 6 X

( 4 ) - Prepare a Habitat Creation or Restoration Strategy; and Allocate an on-site or off-site

habitat creation or restoration site of minimum areas as defined above. ( 2 ) - Demonstrate

that through collaboration, off-site ecological corridors have been designed to link similar

habitat types.

TOTAL 12 2 0 10

LBo

LBo-R1 Plan 2030 Required X

Demonstrate that the proposed development is located within an Urban Growth Boundary as

identified by UPC’s adopted Framework Plans. Demonstrate that the proposed development’s

Floor Area Ratio (FAR), dwelling units per hectare (du/ha), building height, building mass,

transportation and open space networks are consistent with the applicable Plan 2030 and/or

Development Code and/or Area Plan.

Obtain Letter from UPC

LBo-R2 Urban Systems Assessment Required X

Demonstrate that, before the start of the design process and site clearance, an urban systems

assessment has been carried out for the project site and at the following scales: Local, Sub-

regional, and Regional scale. Identify opportunities and constraints associated with the

development and compile an Urban Systems Assessment Report.

Natural Systems

Yes

Yes

Yes

Livable Building : Outdoors

Yes

Yes

development and compile an Urban Systems Assessment Report.

LBo-R3 Outdoor Thermal Comfort Strategy Required X

Shade measures (cover or shade) must be provided in all applicable spaces and achieve a

minimum percent shading. Shade measures include: Exterior Surface Parking with more than

10 spaces (including parking on roof surfaces) 40%, Public Open Spaces (including privately

owned) 60%, Primary Pedestrian Walkways (based on 1.8m width within the through zone)

75%, Secondary Pedestrian Walkways (based on 1.8m width within the through zone) 75%,

Cycle Tracks 50%, Playgrounds 90%

Follow up with Planning Team

LBo-1 Improved Outdoor Thermal Comfort 2 2 x X

Demonstrate that the outdoor thermal comfort strategy has been improved beyond the

minimum established under credit LBo-R3 Outdoor Thermal Comfort Strategy by increasing

the shade measures. (1)50 % (2)55 % - Surface car parking, including parking on roof surfaces

(1)65 % (2)70 % - Public Open Space, including privately owned (1)80 % (2)85 % - Primary

Pedestrian Walkway, based on 1.8m width within the through zone (1)80 % (2)85 % - Secondary

Pedestrian Walkway, based on 1.8m width within the through zone (1)55 % (2)65 % - Cycle

tracks

Follow up with Planning Team

LBo-2 Pearl Rated Communities 1 1 X Demonstrate that the building is located within a Pearl Rated community.

LBo-3 Accessible Community Facilities 1 1 XDemonstrate that the building is located within 350m safe walking distance of any of the five

listed amenities.

LBo-4 Active Urban Environments 1 1 X

Demonstrate that outdoor spaces have been provided and programmed to encourage activity,

including sport and recreation. Develop and implement an Active Urban Environment

Program.

LBo-5 Private Outdoor Space 1 XResidential Only: Provide 90% of units with outdoor amenity space as per the Credit

RequirementsNot Applicable

LBo-6 Public Transport 3 2 1 X

( 2 ) - Demonstrate that the building is within 350m of a tram and/or bus stop with a 15

minute frequency. ( 3 ) - Demonstrate that the building is also within 350m of a metro or

regional rail station.

Confirm with UPC on plans for tram line (North

to GF site)

LBo-7 Bicycle Facilities 2 2 X( 1 ) Meet the Credit Requirements for bicycle parking facilities. ( 1 ) Meet the Additional

Credit Requirements for shower, locker and changing facilities and/or cycle lanes.Confirm with GF on bicycle paths on site

LBo-8 Preferred Car Parking Spaces 1 1 X

6% of parking spaces provided must be identified for the sole use of priority vehicles. The

spaces must be optimally located for building access and half of the spaces must be supplied

with vehicle charging points.

Follow up with Planning Team

LBo-9 Travel Plan 1 1 X

Demonstrate the development of a Travel Plan. The Travel Plan must include: details of the

type of measures proposed to manage the demand for travel by car; targets for reducing car

travel; means of monitoring the effectiveness of the Plan; and remedial measures that will be

implemented in the event that the stated targets are not delivered.

Confirm with GF

LBo-10 Light Pollution Reduction 1 1 X Demonstrate light pollution reduction in compliance with the Credit Requirements Confirm with Technology Lead

14 5 5 3

LBi

Yes

TOTAL

Livable Building : IndoorsLBi

LBi-R1 Healthy Ventilation Delivery Required X XProtect the quality of air drawn into buildings for ventilation and to ensure minimum delivery

of outdoor fresh air; Develop an Observational Survey of Local Air Quality

Input from Environmental Consultant (Baseline

Air Quality Assessment)

LBi-R2 Smoking Control Required X XDemonstrate appropriate measures are incorporated into the building design to reduce

exposure to tobacco smokeIncorporate in design requirements

LBi-R3 Legionella Prevention Required X X Manage the risk of Legionella in water based building systems. Incorporate in design requirements

LBi-1 Ventilation Quality 3 2 1 X

( 1 ) - CO2 sensors at all return points. ( 1 ) - Demonstrate an increase in

outdoor air ventilation of 15% above the outdoor air ventilation rates. ( 1 ) - Mixed Mode

Operation (not available to retail use type)

Achieve 15% above outdoor ventilation rates for

the Clean Room

LBi-2.1 Material Emissions : Adhesives & Sealants 1 1 X 95% of all adhesives & sealants meet criteria. Confirm with GF on material selection

LBi-2.2 Material Emissions : Paints & Coatings 1 1 X 95% of all surface areas meet criteria Confirm with GF on material selection

LBi-2.3 Material Emissions : Carpet & Hard Flooring 1 1 X 100% of all carpets, carpet cushion, hard flooring and associated finishes comply Confirm with GF on material selection

LBi-2.4 Material Emissions : Ceiling Systems 1 1 X All ceiling systems meet credit criteria Confirm with GF on material selection

LBi-2.5 Material Emissions : Formaldehyde Reduction 2 2 X( 1 ) - All internal construction materials meet formaldehyde class E1 levels. ( 1 ) All internal

construction and furniture meets formaldehyde class E1 levels.Confirm with GF on material selection

LBi-3 Construction Indoor Air Quality Management 2 2 X Develop a construction IAQ plan Include in the specifications

LBi-4 Car Park Air Quality Management 1 1 X

For enclosed cark park. Ensure car parking ventilation design meets the credit requirements.

Where project does not contain any enclosed car parks (75% enclosed) the credit is

automatically awarded

Confirm with Planning Team

LBi-5.1 Thermal Comfort & Controls : Thermal Zoning 1 1 X Compliant thermal zoning strategy and controlsIncorporate in design requirements / Model to

determine cooling demand

LBi-5.2Thermal Comfort & Controls : Occupant

Control2 2 X

( 1 ) - General: 1 control per 2 occupants, General (Mixed Mode) : 50% occupied area, Multi-

Occupant Spaces (Office, Residential, Schools): 1 control per space (more if movable

partitions present). ( 1 ) - General: 1 control per 2 occupants & modulating HVAC systems in

multi-occupant spaces, General (Mixed Mode): 75% of occupied area, Multi-Occupant Spaces

(Office, Residential, Schools): 1 control per space (more if movable partitions present)

Confirm with Technology Lead

LBi-5.3Thermal Comfort & Controls : Thermal

Comfort Modeling2 2 X

( 1 ) - Category C Performance: PMV levels between -0.7 and +0.7 (15% PPD) & 90%

acceptability limits for Mixed Mode (if applicable). ( 1 ) - Category B Performance: PMV levels

between -0.5 and +0.5 (10% PPD) & 90% acceptability limits for Mixed Mode (if applicable).

PMV - Predicted Mean Vote, PDD - Predicted Percentage Dissatisfied

Confirm with Technology Lead

LBi-6 High Frequency Lighting 1 1 XGeneral: All high frequency fluorescent ballasts and occupancy sensors meeting credit

requirements.Incorporate in design requirements

LBi-7 Daylight & Glare 2 2 X

( 1 ) - General : min 250 Lux for 50% of occupied area. Meet requirements for occupancy

sensors relevant to space type. Meet requirements for glare control relevant to space type. (

1 ) - General : min 250 Lux for 75% of occupied area. Meet requirements for occupancy

sensors relevant to space type. Meet requirements for glare control relevant to space type.

Allow Occupancy Sensor. Daylight Design

Software - Include in the design

LBi-8 Views 1 1 X General: 75% of occupied areas have views through vision glazing. Confirm with Architect

Livable Building : Indoors

Yes

Yes

Yes

LBi-8 Views 1 1 X General: 75% of occupied areas have views through vision glazing. Confirm with Architect

Page 35: 2.7 I Sustainability

LBi-9 Indoor Noise Pollution 1 1 X Demonstrate that internal ambient noise levels do not exceed 50 dB(A) Leq in the area to be

occupied.Confirm with Architect

LBi-10 Safe & Secure Environment 1 1 X Develop & Implement Safety & Security PlanIncorporate Estidama Requirements to Overall

Security Plan

23 14 1 8

PW

PW-R1 Minimum Interior Water Use Reduction Required x XDemonstrate that the project’s predicted interior potable water consumption will be no

greater than the baseline building water consumption using efficiency measures only.

Use UPC Water Calculator / Input from

Technology Lead

PW-R2 Exterior Water Monitoring Required x X

Demonstrate that easily accessible and clearly labelled water meters are provided and

capable of monitoring the water consumption of, at a minimum, the following exterior water

uses (where present): Heat rejection; External hose bibs; Irrigation systems; Swimming pools;

and Water features.

Incorporate at the design stage

PW-1 Improved Interior Water Use Reduction 15 5 10 X

Demonstrate using the Building Water Calculator that the proposed building has achieved the

following reduction in potable water consumption compared to the baseline building: ( 1 ) 4%

( 2 ) 8% ( 3 ) 12% ( 4 ) 16% ( 5 ) 20% ( 6 ) 24% ( 7 ) 28% ( 8 ) 32% ( 9 ) 36% ( 10 ) 40% ( 11 )

44% ( 12 ) 48% ( 13 ) 52% ( 14 ) 56% ( 15 ) 60%

Confirm with Technology Lead

PW-2.1 Exterior Water Use Reduction: Landscaping 8 4 2 2 X

( 2-4 ) Demonstrate that the average irrigation requirement for all landscaped areas has been

minimized. ( 1 ) Demonstrate that a water efficient irrigation system has been incorporated

into the landscape design. ( 1 ) Demonstrate that best practices for ongoing system

management and operation have been established. ( 2 ) Demonstrate that 100% of the

exterior irrigation demand can be served using the Exterior Water Allowance, and that a

recycled water mainline loop has been installed where Pearl Building Rating System: Design &

Construction, Version 1.0, April 2010 124 of 223 recycled water is not immediately available.

Confirm with Technology Lead

PW-2.2 Exterior Water Use Reduction: Heat Rejection 8 6 2 X

( 2-5 ) Demonstrate that a percentage of the projects cooling tower/district cooling water

make-up requirements can be served using the Exterior Water Allowance. ( 8 ) Demonstrate

that no water is required for heat rejection.

Confirm with Technology Lead

PW-2.3 Exterior Water Use Reduction: Water Features 4 4 X

( 2 ) Demonstrate that the water make-up requirements for all exterior water features can be

served using the Exterior Water Allowance. ( 1 ) Demonstrate that all external swimming

pools are provided with adequate pool blankets. ( 4 ) Demonstrate that there are no exterior

water features or swimming pools.

Confirm with Technology Lead

PW-3 Water Monitoring & Leak Detection 4 4 X

( 2 ) Demonstrate that metering facilities that monitor the water consumption of major

individual interior uses are installed. ( 2 ) Demonstrate that a leak detection system has been

installed.

Include requirements for Leak Detection into

Design requirements

PW-4 Stormwater Management 4 2 2 X

( 1-2 ) Stormwater management system is designed to meet Quantity Control criteria as per

Credit Requirements. ( 1 ) Stormwater management system is designed to meet Quality

Control criteria as per Credit Requirements. ( 1 ) An Operation & Maintenance Plan has been

developed.

Confirm with Technology Lead

TOTAL

Precious Water

Yes

Yes

TOTAL 43 19 10 14

RE

RE-R1 Minimum Energy Performance Required x X

Develop an energy model for the proposed building(s) using appropriate dynamic simulation

modeling software and calculate the baseline building energy consumption according to the

building performance rating method outlined in Appendix G of ANSI/ASHRAE/IESNA Standard

90.1-2007, using the minimum acceptable standards for building fabric, HVAC, service water

heating, power, lighting and other equipment. Demonstrate a minimum 12% performance

improvement compared to the baseline building performance demonstrated by the energy

simulation model as per the methodology outlined within Appendix G of Standard 90.1-2007.

Include Energy Model in design requirements

RE-R2 Energy Monitoring and Reporting Required x X

Demonstrate that easily accessible and clearly labelled energy sub-meters are provided which

enable a minimum of 90% of the estimated annual energy consumption of each fuel type

(electricity, gas etc) to be monitored as outlined within the Calculations and Methodologies

section.

Include in specifications

RE-R3Ozone Impacts of Refrigerants & Fire

Suppression SystemsRequired x X

Refrigerants - Demonstrate that all refrigerants to be installed within the project site

boundary have an ozone depletion potential (ODP) of zero. Fire Suppression Systems -

Demonstrate that all gaseous fire suppression systems to be installed within the project site

boundary have an ozone depletion potential (ODP) of zero

Include in specifications

RE-1 Improved Energy Performance 15 5 10 X

Demonstrate further percentage reductions in the proposed building energy consumption

beyond the baseline building consumption determined in RE-R1. Points are awarded as

follows: ( 1 ) 14% ( 2 ) 16% ( 3 ) 18% ( 4 ) 20% ( 5 ) 22.5% ( 6 ) 25% ( 7 ) 27.5% ( 8 ) 30% ( 9 )

32.5% ( 10 ) 35% ( 11 ) 40% ( 12 ) 45% ( 13 ) 50% ( 14 ) 55% ( 15 ) 60%

The points indicated are based on assumptions

and excpected to be revised once Energy

Simulaition baseline and options are developed

RE-2 Cool Building Strategies 6 3 1 1 X

( 1-5 ) Demonstrate percentage reductions in annual external heat gain attributed to passive

design measures. ( 1 ) 10% ( 2 ) 20% ( 3 ) 30% ( 4 ) 40% ( 5 ) 50% ( 1 ) Demonstrate that

roofing materials with a high Solar Reflectance Index will be used.

Confirm with Technology Lead

RE-3 Energy Efficient Appliances 3 3 X

Demonstrate that all developer purchased and/or leased installed appliances shall be energy

efficient, and that tenant guidelines outlining the benefits of energy efficient appliances will

be produced.

RE-4 Vertical Transportation 3 2 1 X

( 1 ) Demonstrate that easily accessible stairs shall be provided to at least the first three

floors of the building. ( 1 ) Demonstrate that all lifts within the building shall be energy

efficient. ( 1 ) Demonstrate that all escalators within the building shall be energy efficient.

RE-5 Peak Load Reduction 4 4 X

( 2 ) Demonstrate peak electrical load shall be less than 80% above annual average electrical

load. ( 4 ) Demonstrate peak electrical load shall be less than 60% above annual average

electrical load.

Confirm with Technology Lead

RE-6 Renewable Energy 9 3 6 X

Demonstrate that a percentage of the total energy consumption will be supplied by onsite

renewable energy. ( 1 ) 1% ( 2 ) 3% ( 3 ) 5% ( 4 ) 7% ( 5 ) 10% ( 6 ) 13% ( 7 ) 16% ( 8 ) 20% -

( 1 ) Demonstrate that 20% of the project’s non-renewable energy use will be supplied by

offsite renewable energy.

1% Cost of PV

Resourceful Energy

Yes

Yes

Yes

offsite renewable energy.

RE-7Global Warming Impacts of Refrigerants & Fire

Suppression Systems4 2 2 X

( 1 ) Demonstrate that the weighted average of all refrigerants shall have a GWP of 10 or less.

( 1 ) Demonstrate that a permanent refrigerant leak detection system shall be installed. ( 1 )

Demonstrate that an automatic refrigerant pump down system shall be installed. ( 1 )

Demonstrate that 100% of gaseous fire systems shall have a GWP of 1 or less.

Confirm with Technology Lead

TOTAL 44 10 10 23

SM

SM-R1 Hazardous Waste EliminationRequired X X

To eliminate exposure of building occupants to asbestos and minimize toxic effects of

chromated copper arsenate (CCA) treated timber on people and the environment.Include in materials specifications

SM-R2 Basic Construction Waste Management

Required X X

Reduce the long-term environmental impacts associated with construction waste collection,

transport and disposal; Minimum final recycling/salvage rate of 30% of construction and

demolition waste (weight/volume) - excluding hazardous

Incorporate Requirements into Construction

Waste Management Plan prepared by

Environmental Consultant

SM-R3 Basic Operational Waste Management

Required X X

Reduce the long-term environmental impacts associated with operational waste collection,

transport and disposal; Proposed option: 40% minimum target of diversion rate

(weight/volume) & Waste segregation in 4 types and waste containers location requirements

Incorporate Requirements into Operational

Waste Management Plan prepared by

Environmental Consultant

SM-1 Non-Polluting Materials

3 2 1 X

( 1 ) Building meets the ‘Zero Ozone Depleting Potential, Low Global Warming Potential

Insulation’ Credit Requirements through design. ( 1 ) Building meets the ‘Chlorine Free

Materials’ Credit Requirements through design. ( 1 ) Building meets the ‘Low Toxicity

Materials’ Credit Requirements through design.

Confirm with Technology Lead

SM-2 Design for Material Reduction1 1 X

General: Building is designed with at least one material reduction initiative. Offices only: At

least two initiatives are required.Confirm with Technology Lead

SM-3 Design for Flexibility & Adaptability

1 1 X

Demonstrate the following: 90% of the building has regular rhythm to exposed facades (by

area); Floor-to-floor heights of at least 3.6 meters; 90% of the windows are evenly distributed

around exposed elevations (by area); 90% of interior, non-structural walls are demountable or

movable (by area); and 90% of pipes, wiring and conduits are not permanently embedded in

building materials (in length).

SM-4 Design for Disassembly

1 1 X

Develop a Building Disassembly Plan highlighting the following: materials intended for

recovery; materials connection requirements; system for marking and identifying recoverable

elements prior to installation; best management practices for disassembly; and the

disassembly sequence. Demonstrate that 50% of the building structural skeleton, 75% of

façade, or 90% of the roof is designed for disassembly (by surface area).

SM-5 Modular Flooring Systems 1 1 X At least 95% (by surface area) of finished floor areas are specified with modular flooring

products.SM-6 Design for Durability 1 1 X Develop a Building Durability Plan.

SM-7 Building Reuse2 2 X

( 1 ) At least 25% of the building structural system, by surface area, will be reused. ( 2 ) At

least 50% of the building structural system, by surface area, will be reused.

Yes

Stewarding Materials

Yes

Yes

SM-7 Building Reuse least 50% of the building structural system, by surface area, will be reused.

SM-8 Material Reuse 1 1 X The cost of specified reused materials equal to at least 3% of the Total Material Cost.

SM-9 Regional Materials2 1 1 X

( 1 ) Cost of regional materials specified equal to 10% of Total Material Cost. ( 2 ) Cost of

regional materials specified equal to 20% of Total Material Cost.Further Research on materials availability

SM-10 Recycled Materials

6 1 5 X

( 1 ) Steel-framed: at least 50% of specified structural steel (by weight) has 25% post-

consumer recycled content or is reused Concrete-framed: at least 80% of specified rebar or

stressing steel has 90% post-consumer recycled content. ( 1 ) Specified concrete mix and

reduction in cement use will achieve an embodied GHG of concrete as per table SM10.1, rows

B1, C1 and D1. ( 2 ) Specified concrete mix and reduction in cement use will achieve an

embodied GHG of concrete as per table SM10.1, rows B2, C2 and D2. ( 1 ) At least 15% of all

specified aggregates to be used for structural or non-structural applications are recycled. ( 2 )

Only recycled aggregate is specified for use as base, sub-base or backfill. ( 1 ) Cost of

specified recycled materials equal to at least 10% of Total Material Costs.

Further Research on materials availability

SM-11 Rapidly Renewable Materials

1 1 X

at least 75% (by area) of one or more specified building components are rapidly renewable; at

least 35% (by area) of two or more specified building components are rapidly renewable; or at

least 15% (by area) of four or more specified building components are rapidly renewable.

SM-12 Reused or Certified Timber2 2 X

( 1 ) At least 50% (by cost) of the specified timber comply with the Credit Requirements. ( 2 )

At least 70% (by cost) of the specified timber comply with the Credit Requirements.

SM-13 Improved Construction Waste Management

2 1 1 X

( 1 ) Demonstrate CDWMP aims for a minimum of 50% demolition and construction waste (by

weight or volume) to be recycled / salvaged. ( 2 ) Demonstrate CDWMP aims for a minimum of

70% demolition and construction waste (by weight or volume) to be recycled / salvaged.

SM-14 Improved Operational Waste Management

2 1 1 X

( 1 ) General: An Operational Waste Management Plan (OWMP) is developed for a minimum

targeted diversion rate of 60% (by weight or volume. ( 2 ) General: An OWMP is developed for

a minimum targeted diversion rate of 80% (by weight or volume.

SM-15 Organic Waste Management2 2 X

( 1 ) Landscaping waste or food waste collection and/or treatment is proposed onsite. ( 2 )

Food and landscaping waste collection and/or treatment are proposed onsite.

TOTAL 28 6 15 7 0 0 0

IP

IP-1 Innovating Cultural & Regional Practices 1 1Develop a design strategy for incorporating solutions that showcase cultural and regional

practicesMix of Arabic and Islamic features

IP-2 Innovating Practice 2 1 1

Develop, document and implement an innovative design and/or construction solution that

addresses one or more of the four pillars of Estidama. AND Develop a guideline document that

enables the innovative solution to be repeated.

Occupant Education: Display of Energy

consumption (each floor, kiosk)

TOTAL 3 2 1 0 0 0 0

Innovating Practice

Page 36: 2.7 I Sustainability

TOTAL POINTS 180 68 45 65

1 PEARL ALL REQUIRED

2 PEARL 60-84 POINTS

3 PEARL 85 - 114 POINTS

4 PEARL 115 - 139 POINTS

5 PEARL 140 + POINTS

Page 37: 2.7 I Sustainability

PG. 1 Page | 2.3-1

Estidama Registration Form

Page 38: 2.7 I Sustainability

Pearl Building Rating System Registration Form

Project Name

Project Location (street name, region, emirate)

Current Project Stage

Total Site Area (m2)

Gross Floor Area (m2) - Office

Gross Floor Area (m2) - Multi-Unit Residential

Gross Floor Area (m2) - Retail

Gross Floor Area (m2) - School

Gross Floor Area (m2) - All Other Occupancy Types

Gross Floor Area (m2)

Site Context (Urban,Suburban,Rural)

Current Site Condition

Within Urban Growth Boundary?

Estimated number of permanent residents

Estimated Date of Completion (dd/mm/yyyy)

Is the Project Government Funded?

What Pearl Level is the project targeting?

Is the Project Confidential ?

Emailed affection plan to UPC with this form ?

Project Description (include list of all 'other space types' in the project)

Name (individual / organisation)

Authorized contact name

City

Country

Type of organization

Prefered contact method

Phone number

Fax number

Email address

Office / Unit number

Office building name

Office street name and number

City

Country

P.O. Box

Name

Accreditation

Phone number

Fax number

Email address

Project Information

Owner or Owners Representative Information

PQP / Sustainability Consultant Information

Postal Address :

Email address

Company Address

Emailed proof of sustainability consultant accreditation with this form?

Emailed owners consent for project registration with this form?

For any queries related to project registration [email protected]

Estidama Project ID

(will be issued by UPC upon return of this information)

Page 39: 2.7 I Sustainability

PG. 1 Page | 2.3-1

Response to GF Comments on Draft Report

Page 40: 2.7 I Sustainability

GF – Milestone 10 (Design Guidelines): Response to Comments

Section GF Comments CH2M HILL Response

General

There should be a section to describe the purpose of this document.

This document is a section of the overall CH2M HILL submittal (as per CH2M HILL Scope of Work). A small introductory paragraph is added.

Analysis of Building Rating Systems

It should also be noted that LEED is the only system currently at use in the SC industry.

Text added

Perhaps it should be noted here what the frequency is for certifications under each system specific to the SC industry.

LEED is the only building certification systems used for FAB application. GF FAB AD 01 will be the first facility following Estidama Building Rating System.

This comment is not needed Phrase deleted

Please modify - delete However Word deleted Project Boundary for certification

a To clarify, while the CUB building technically wasn't included in certification for Fab8, the systems in the CUB were included. They must be, because these systems are required as part of the energy model.

Text modified as follows: ‘ Separate project boundaries were established for the Administration and FAB Building, with the utility systems (CUB building) included in the energy model calculations for the FAB’

To clarify, we would certainly expect CUB to be covered under Estidama. We don't want UPC to think otherwise.

Noted : Text changed accordingly

ISDM

Is this fair? Is the average building in AD not already above and beyond "business as usual"?

For the purpose of this document, only Estidama will be looked at, hence Abu Dhabi BAU building performance is more applicable.

How is this baseline meant to relate to that required under LEED and/or Estidama?

The Baseline for the FAB application will need to be developed and agreed with UPC when pursuing Estidama certification.

Model is suitable for high level comparison of scenarios

Text amended

Section 7 Technical Design Guidelines

Why was this particular set of indicators chosen?

This was agreed with GF and is part of CH2M HILL – Milestone 10 Deliverables requirements. These specific guidelines cover key sustainability aspects particularly when pursuing LEED certification as initially targeted.

The final version of the document examines applicability with Estidama requirements consistent with client’s direction as of 17th of October 2010. Hence, the ‘Erosion and Sedimentation

Page 41: 2.7 I Sustainability

GF – Milestone 10 (Design Guidelines): Response to Comments

Control’ section is not considered applicable to Estidama rating system and is only kept in the Appendix section.

This was in ERM Permitting scope, although we have not approved development of that deliverable.

Typically, for EHS permitting purposes waste management focuses on waste handling and disposal, whereas sustainability guidelines would focus in achieving the required percentage of waste diversion from landfill to obtain the relevant Estidama credits.

Text added to reflect permitting/compliance requirements under the sections:

7.1.1

‘Demonstrate Compliance with local regulation with respect to Construction and Demolition Waste Management’ 7.4.1.

‘Ensure full compliance with the Local Regulatory Framework as reflected within GF’s Construction Environmental Management Plan’

Section 7.1 - Construction and Demolition Waste Management

As noted, 30% is minimum required under Estidama so design target should aim higher. At least to the 50% that earns "Improved" level (and LEED credit). 75% should probably be used, it allows all credit points to be earned and recent projects (GF and others) have demonstrated that 90% and greater is feasible.

Text modified to reflect this: A 70% diversion from landfill is targeted as a minimum, in line with Estidama Credit requirements.

Section 7.2 - Construction Indoor Air Quality Management

Need to ensure the project benefits from Fab8 experience with SAIC/NYSERDA energy modeling

Sharing Lessons Learnt with the Abu Dhabi Team would be beneficial.

Section 7.4 - Erosion and Sedimentation

Do we have any indication of comparability of AD construction requirements vs. the EPA regs cited here?

This section was initially prepared in line with LEED credit rating requirements. Following client’s direction as of 17th of October 2010 to include in our deliverable only Estidama

Page 42: 2.7 I Sustainability

GF – Milestone 10 (Design Guidelines): Response to Comments

Control (ESC) Management Plan

requirements, the Erosion and Sedimentation Control Management section is not considered relevant to the Estidama rating system. Comparing to LEED, under Estidama, there is no individual credit on Erosion and Sedimentation Control Management. Relevant control measures fulfilling Estidama requirements (Credit: IDP – 3) are expected to be addressed under the Construction Environmental Management Plan in line with EAD ‘CEMP - Technical Guidelines Document’ (April 2010). It is understood that the GF CEMP will be prepared by ERM. No further comparison is required at this stage. The ESC section is kept in the Appendix section for reference only.

Section 8.1 - Preliminary Scorecards Purpose

‘Identify potential opportunities that can be refined via ROI analysis in Design phase’

Text added

Figure 7-2

Figure 7.2 and meant to cover the Fab/CUB? Typo corrected

Section 10 – Supply Chain Strategy

Missing

Figure is not shown on pdf format / Figure added

Is this referring to embodied carbon? Yes, text amended.

Appendix 1 How is this being planned relative to concept submittal? It would be advantageous to proactively reach out to the UPC Estidama team to review our approach

During the preparation of Concept Review Submission, CH2M HILL team met with UPC to clarify various issues, including Estidama.

Appendix 3 What is the purpose of this item? The contractor is responsible for ensuring they implement the Air Quality Plan. This applies to the other sections as well. What is the purpose of this comment? Ultimately, the contractor is responsible for ensuring that the

Text amended: The Engineer / Client Representative will be responsible for overseeing Contractor’s compliance.

Page 43: 2.7 I Sustainability

GF – Milestone 10 (Design Guidelines): Response to Comments

required reporting occurs. This applies to the other sections as well.

Appendix 3 What "lessons learned" can we note from Fab8 experience?

Sharing Lessons Learnt with the Abu Dhabi Team would be beneficial.

Appendix 3 - ESC

Is there a citation available detailing local requirements?

Added: Environment Agency of Abu Dhabi, Technical Guidance Document for Construction Environmental Management Plan (CEMP), April 2010

Appendix 3 - Minimum Energy performance Page: 60

What other references should we be citing, there must be a host of them.

ASHRAE is referenced by Estidama.

change "and/or" to "and" (in next bullet as well) As mentioned earlier, as per client’s request (17/10/10), the final CH2M HILL deliverable will only assess Estidama requirements. Text has been amended accordingly.

Scorecards All GF comments have been incorporated into the scorecards. Total score has been revised accordingly.